KR20110009882A - Tailor-made manufacturing method for furniture-style buildings and traditional korean-style structure - Google Patents
Tailor-made manufacturing method for furniture-style buildings and traditional korean-style structure Download PDFInfo
- Publication number
- KR20110009882A KR20110009882A KR1020090067319A KR20090067319A KR20110009882A KR 20110009882 A KR20110009882 A KR 20110009882A KR 1020090067319 A KR1020090067319 A KR 1020090067319A KR 20090067319 A KR20090067319 A KR 20090067319A KR 20110009882 A KR20110009882 A KR 20110009882A
- Authority
- KR
- South Korea
- Prior art keywords
- wall
- pillar
- foundation
- furniture
- groove
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/26—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of wood
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/343—Structures characterised by movable, separable, or collapsible parts, e.g. for transport
- E04B1/34315—Structures characterised by movable, separable, or collapsible parts, e.g. for transport characterised by separable parts
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/56—Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
- E04B2/70—Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members with elongated members of wood
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B7/00—Roofs; Roof construction with regard to insulation
- E04B7/02—Roofs; Roof construction with regard to insulation with plane sloping surfaces, e.g. saddle roofs
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C3/00—Structural elongated elements designed for load-supporting
- E04C3/02—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
- E04C3/12—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of wood, e.g. with reinforcements, with tensioning members
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/26—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of wood
- E04B1/2604—Connections specially adapted therefor
- E04B2001/262—Connection node with interlocking of specially shaped wooden members, e.g. puzzle type connection
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/26—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of wood
- E04B1/2604—Connections specially adapted therefor
- E04B2001/268—Connection to foundations
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Life Sciences & Earth Sciences (AREA)
- Wood Science & Technology (AREA)
- Joining Of Building Structures In Genera (AREA)
Abstract
Description
본 발명은 건축물 건축공법 중 건식공법에 분류되는 목조주택 건축으로써,가구식 건축물을 공업화하여 조립식으로 건축하고자 하는 것으로, 건축 구조부품들을 규격화하고 조립식 구조를 갖추어 공사시에 소요되는 기간의 단축과, 작업을 원할하면서 기술 인력의 수요를 줄이면서도 정확하게 건축할 수 있도록 하는 전통한옥에 대한 조립식 건축방법 및 그 한옥의 구조와 공업화 건축에 관한것이다The present invention is to build a wooden house, which is classified in the dry construction method of the building construction method, to industrialize the furniture-type buildings to build prefabricated, shortening the time required for construction by standardizing the building structural parts and equipping the prefabricated structure, It is about the prefabricated building method for traditional hanok and the structure and industrialized construction of traditional hanok that wants to work and can reduce the demand of technical personnel and build accurately.
한국의 전통 한옥을 축조하는 방법으로는 먼저 건축하고자 하는 터를 조성하고, 그 터에 건축하고자 하는 건물의 위치를 선정하여 지반을 소금, 숯, 회를 넣고 다진 후 기둥을 세울 자리에 자연석주춧돌을 세우고, 그 주춧돌 위에 가랑이질을 하여 기둥을 수직하게 세우고, 기둥위에서 대들보와 중간보를 가로 세로방향으로 교차시키는 상태로 골조를 설치하여 공간을 형성하는 구조이며, 상기 공간구조에서 주춧돌과 기둥사이의 공간에 마루 및 온돌 구비하는 방바닥을 형성하며, 기둥과 기둥 그리고 중간보 사이의 공간을 수수깡 혹은 싸리로 엮은 벽 양쪽에 맞벽을 치거나, 흙벽돌 또는 창문 문틀 소재로 막아 벽을 형성하여 방을 형성하거나 마루 등을 구획하는 구조이고, 대들보와 중간보 위에는 서까래를 설치하여 기와를 사용하는 지붕을 형성하는 구조로 이루어져 있다.In order to build a traditional Korean hanok, first construct a site to be built, select the location of the building to be built on the ground, add salt, charcoal, and ash to the ground, and then place natural stone headstone in the place where the column will be built. It is a structure that forms a space by setting up the pillars vertically by arranging the pillars vertically on the headstones and crossing the girders and the intermediate beams horizontally and vertically on the pillars, and forming a space between the headstones and the pillars in the space structure. Forms a floor with floors and ondols, and the walls between pillars, columns, and intermediate beams are lined with both cans or shrouds, or walls are formed by blocking walls of mud bricks or window frames. It is a structure that partitions the floor, etc., and forms a roof using tile to install rafters on girders and intermediate beams. It consists of a structure.
이러한 전통한옥을 건축할 때에는 반드시 건축자재와 공정을 책임지고 해결하는 대목수가 필요하였고, 선정된 목수는 재료를 구매하여 현장에서 용도에 맞게 가공하는 방식으로 구조물을 설치하는 관계로 한옥이 완성되기까지는 장기간의 공사기간이 소요되는 문제점이 있었다.When building such a traditional hanok, a large carpenter must be responsible for and resolve the building materials and processes.The selected carpenter purchases materials and installs the structure in such a way that they can be processed according to their purpose until the hanok is completed. There was a problem that it takes a long period of construction.
또한, 현재의 주변상황에서 전통한옥을 건축하기 위하여 고급인력인 목수를 구하기는 매우 어려워 작업진행이 용이하지 못하고, 개별 동은 가능하나 단지건축 및 대량생산, 대량시공은 불가능하다. 건축재료를 현장에서 직접 부재의 형태에 따라 가공하여 사용하므로 정밀도와 취급성이 매우 낮아지는 문제점이 있었다. 즉, 건축재료가 규격화 되지 못하여 현장에서 재료를 현장의 규격에 맞도록 가공하므로 시간과 작업공수가 증가되고, 당연히 정밀성이 떨어지는 것이다. 이는, 현대 산업에 기본이 되는 대량생산과 시공이 불가능하다.In addition, it is very difficult to obtain high-quality carpenters to build traditional hanok in the present surrounding situation, so it is not easy to proceed with work, and individual buildings are possible, but only construction, mass production, and mass construction are impossible. Since the building materials are processed and used according to the shape of the members directly in the field, there is a problem in that precision and handling are very low. In other words, the building material is not standardized, so the material is processed to meet the site's specifications, increasing time and labor, and of course, lacking precision. This is impossible to mass production and construction that is the basis for the modern industry.
특히, 건축구조적인 부분에서는 벽체와 기둥이 단순 맞댄 구조 상태를 유지하므로 건축 후 이완현상이 발생하고, 이로 인해 단열 기능이 없어진다. 지붕의 구조상 흙의 무게와 기와의 무게등 무거운 하중이 대들보와 중간보 및 기둥으로 집중되는 현상이 있어 각 부재에 변형이 많이 발생하여 구조적으로 안전성이 떨어지는 문제점이 있었다. 또한, 자연 목재에 제한된 구조 내력에 의해 구성코자 하는 평면의 크기, 건물의 높이 구축에 한계가 현대식 평면과 공간 창출에 문제가 많다.In particular, in the structural structure, the wall and the column maintain a simple butt structural state, so that a relaxation phenomenon occurs after the construction, and thus the insulation function is lost. Due to the structure of the roof, heavy loads such as soil weight and roof tile weight are concentrated on girders, intermediate beams, and columns. In addition, there is a problem in creating a modern plane and a space that is limited to the size of the plane and the height of the building to be constructed by limited structural strength in natural wood.
벽체 단열문제와 창호의 긴밀성에 기본 구조상 문제가 있으며, 또한 기둥이 나 대들보 및 중간보와 같은 건축부재는 생목재 자체로만 사용하는 관계로 목재에 도장을 바로 할 수 없으며 건축 후 비틀리거나 갈라지는 현상과 처짐현상을 배제할 수가 없고, 기둥과 기둥사이에 형성하는 벽체는 신축에 의해 이완되고, 기둥과 흙벽돌이 각각의 구조물로 존재하게 되어 장막벽화 되므로써, 총체적으로 구조적 안정성이 결여되는 문제점이 있었다.There is a basic structural problem in the insulation of walls and the tightness of windows. Also, building members such as columns, girders, and intermediate beams are used only as raw wood. The deflection phenomenon cannot be excluded, and the walls formed between the pillars and the pillars are relaxed by stretching and contraction, and since the pillars and the soil bricks exist as respective structures, there is a problem of lacking overall structural stability.
본 발명은 건축물 건축공법 중 건식 공법에 분류되는 가구식 목조주택 건축공법 중 한옥 건축 공법으로, 소요되는 건축부재를 모듈화 하여 고급 기술인력 없이도 가구식 목조주택 건물 및 한옥을 안정된 구조로 설계, 대량생산, 현장조립 건축할 수 있으며, 건축 후에도 비틀림이나 이완되는 구조적결함이 발생하지 않도록 함을 목적으로 한다.The present invention is a hanok construction method of the furniture wooden house building construction method that is classified in the dry construction method of the building construction method, by designing the mass of building wooden house building and hanok in a stable structure without the need for advanced technical personnel by modularizing the building member required It aims to ensure that no structural defects such as torsion or relaxation occur after construction.
본 발명은 모든부재가 건조된 목재로 일체 집성처리되어 공학목재 및 공학 부재를 사용하므로서, 부재의 균열, 변형, 무거운 하중으로 처짐에 대한 문제점 해결을 목적으로 한다 .The present invention aims to solve the problem of sagging due to cracking, deformation and heavy loads of members, since all members are integrally integrated with dried wood and use engineering wood and engineering members.
본 발명은 수직재인 기둥과 벽체가 상호 결합되는 요철상태로 연결하여 구조물에서 공간틈새가 발생하지 않게 함과 동시에 수평재 또한, 요철로 상하 연결시켜 강성을 보강하여 지붕의 하중을 벽체를 내력 벽화하여, 전체에 고르게 분산시켜 구조물의 안정성을 향상되게 함을 목적으로 한다.The present invention connects the column and the wall as a vertical material in the uneven state coupled to each other to prevent space gaps in the structure and at the same time, the horizontal material, also connected to the top and bottom to reinforce the rigidity by strengthening the strength of the roof wall load wall murals, It aims to improve the stability of the structure by distributing it evenly throughout.
본 발명의 목적은 지면에 지반을 강화하여, 바닥 기초면을 형성하여 상기 기초 바닥면에 건축하고자하는 면적을 설정하여 면적의 테두리 옹벽에 토대목을 설치 고정하면서 기초 면과 토대목 사이에 방습, 방수용 완충부재를 적층시키는 완충재 및 토대목 고정단계, 토대목 상부에 설비배관 설치단계(전기,통신,TV)와 상기 토대목 모서리 위치에 보강재가 내장된 벽체 연결구와 몰딩(MOLDING)연결구가 있는 제기둥을 설치 고정하는 기둥설치단계와, 창방과 설비 유도홈이 내장된 하인방이 벽체의 상하단에 조립되며 신축 기능의 단열재가 내장되고 미장이 완료되고, 개구부가 부착되 있는 벽 각각의 외벽체를 제1기둥 측면홈과 몰딩(MOLDING)홈에 조립하고, 제1기둥의 상단으로 창방 연결홈이 있는 보아지와 +자 연결홈과 +자 돌기가 있는 주두를 조립 설치하는 외벽체설치단계와,상기 제1기둥에 조립고정된 외벽 부재의 타측단에 보강재가 내장된 벽체 연결구와 몰딩 연결구가 있는 제2기둥을 벽체의 돌출부와 조립하여 설비 배관이 완료된 토대목에 조립하고, 제2기둥의 상단에는 보아지와 주두를 조립한 뒤, 외벽체의 상단과 제1기둥과 제2기둥의 주두사이에 장혀를 설치 조립하는 외벽고정단계와, 상기 외벽고정단계에서 장혀와 창방을 설치조립하기 전에 제2기둥에 대하여 소정의 간격을 두고 한옥의 내실측으로 이어진 토대목에 보강재가 내장된 제3기둥을 세우고 제3기둥과 제2기둥사이에 창방이 설치된 내벽부재를 조립 설치하고, +자 연결홈과 +자 연결돌기가 있는 주두가 설치된 제2기둥상단과 제3기둥의 상단을 보강재가 내장된 대들보 하부에 장여 설치 후, 연결하는 내부공간 형성단계와,설비배관 홈이 있는 대들보 상단에 동자주를 구조 연결 홈에 연결하고 상부에 동자주, 주두 설치 후 중량을 설치하여 중앙에 판대공을 중량 상단 연결홈에 설치하여 지붕틀을 구조를 구축 단계 후, 장여와 대들보 마구리 상면에 처마도리를 설치하고 지붕틀 구조부재를 설치하여 지붕틀구조 고정단계와, 상기 지붕틀 구조부재의 상부에는 서까래와 판넬이 일체화 된 서까래 지붕판넬 부재를 올려 고정하고, 부연과 부연개판이 고정된 부연판을 서까래판넬 부재 위에 올려 고정하는 지붕판 설치단계를 순차적으로 행하는 방법을 제공함에 의하여 달성된다.The purpose of the present invention is to strengthen the ground on the ground, to form a ground foundation surface to set the area to be built on the foundation floor surface, while setting the foundation wood to the retaining wall of the area moisture-proof between the foundation surface and the foundation wood, Step of fixing buffer material and foundation wood for laminating waterproof buffer member, installation of facility piping on base wood (electric, communication, TV) and wall connector with built-in reinforcement at the corner of base wood and molding (MOLDING) connector The pillar installation step of installing and fixing the pillars, and the lintels with built-in windows and equipment guide grooves are assembled at the upper and lower ends of the walls, and the outer walls of each wall with the opening of the elastic function, the plastering completed, and the opening are attached to the first pillar. Assemble to side groove and molding groove, and install and install bore with window connecting groove and + head connecting groove and + head projection to the top of first pillar. Assembling the wall installation step, and the second column having a wall connector and a molding connector with a reinforcing material is built in the other end of the outer wall member fixed to the first pillar assembled with the protrusions of the wall and assembled to the foundation of the installation pipe, At the upper end of the second pillar, after assembling the bore and the ovule, an outer wall fixing step of installing and assembling a tongue between the upper end of the outer wall body and the head of the first and second pillars, and assembling the tongue and the window at the outer wall fixing step Before setting up, place a third pillar with reinforcement on the foundation that extends to the interior of Hanok at a predetermined interval with respect to the second pillar, and assemble and install the inner wall member with a window installed between the third pillar and the second pillar. After the installation of the upper end of the second column and the upper end of the third pillar with the girder connecting groove and the + girder connecting projection is installed in the lower part of the girder with a built-in reinforcement, and forming the internal space for connecting, Connect the copper column to the structure connecting groove on the top of the girder, and install the weight after installing the copper column on the upper part, and then install the weight and install the plate in the center at the upper connecting groove in the middle to build the truss structure. Install the eaves on the roof frame structure member to install the truss structure fixing step, and the top of the truss structural member to raise the rafters roof panel member is integrated with the rafters and panel, and the secondary board is fixed and the secondary board is fixed It is achieved by providing a method of sequentially performing a roof plate installation step of mounting on a rafter panel member.
또한, 본 발명은 건축하고자 하는 대지에 지반 강화공사를 하여 표면을 수평하게 하며 소정의 간격으로 고정용 철물을 매설한 기초면과, 상기 고정용 철물이 돌출된 기초면에 건축하고자하는 면적을 설정하여 그 면적의 테두리에 완충부재를 두고, 이에 상면으로 끼움턱이 돌출된 토대목과, 기둥의 수직면에 구조연결 및 벽체 몰딩이 설치되는 오목한 홈을 갖고 상기 토대목의 모서리 위치에 설치하는 제1기둥과, 상기 제1기둥의 수직면의 오목한 주먹장, 또는 산지 반주먹장 홈으로 삽입되는 골조와, 토대목의 반주먹장 끼움턱에 설치 결합되는 주먹장 또는 산지용 주먹장 오목한 홈을 하인방의 저면으로 구비한 판넬형상의 외벽판과, 상기 토대목의 반주먹장 끼움턱과 외벽판의 몰딩목이 삽입되는 주먹장 및 반주먹장 홈이 저면과 양측 수직면에 구비하여서 된 제2기둥과, 상기 제1기둥과 제2기둥 사이에 위치하는 외벽체의 상단 보아지의 연결돌기를 가진 창방에 조립되는 장여와, 상기 외벽체 부재와 제2기둥 및 제1기둥 그리고 장혀를 설치한 토대목위에 반복적으로 설치하여 벽체면이 설비 배관이 완료된 토대목 전체에 형성하는 벽체구조와, 상기 제1,제2기둥의 상단에 구비된 홈으로 조립하는 창방이 끼워지는 보아지와 +자 연결홈과 +자 연결돌기가 있는 주두, 상기 외벽체에서 한옥의 내실측으로 이어진 토대목의 반주 먹장 끼움턱에 결합되는 끼움홈이 상하단에 구비되고, 제2기둥의 측면홈에 결합되는 골조를 구비하여서된 내벽부재와, 상기 한옥의 내실측으로 이어진 토대목에 수직하게 설치되는 제3기둥, 상기 실외측의 제2기둥과 실내측의 기둥사이를 연결하는 보강재가 삽입된 대들보, 중량 및 도리에 의해 지붕구조를 완성하고, 일식판넬로 일체화 제작된 서까래 지붕판과 부연판넬, 덧지붕판 그리고, 목기연판넬등에 의해 지붕마감 구조가 달성된다.In addition, the present invention is to set the area to be built on the ground to the ground to be built on the ground to be built, the surface to be horizontal and the fixing surface at the predetermined intervals, and the base surface protruding the fixing hardware And a buffer member at the edge of the area, the foundation having a projection protruding from the upper surface thereof, and a first recess installed at a corner position of the foundation with concave grooves in which structural connections and wall moldings are installed on vertical surfaces of the pillars. A panel having a pillar, a concave fist hole in a vertical plane of the first pillar, or a frame inserted into a hillside pitch hole groove, and a fist field or mountain hole hole recessed groove that is installed and coupled to a basin hole fitting jaw of a foundation tree as a bottom of a linch. An outer wall plate having a shape, and a fist pad and an accommodating groove into which the base wall fitting jaw of the foundation tree and the molding tree of the outer wall board are inserted are provided at the bottom and both vertical surfaces. An extension which is assembled in a window having a second pillar and a connecting protrusion of an upper bore of the outer wall located between the first and second pillars, the outer wall member, the second pillar, the first pillar and the tongue + -Shaped connection with a bore fitted with a wall structure that is repeatedly installed on one foundation tree to form a wall structure on the entire foundation tree in which facility piping is completed, and a window that is assembled with grooves provided at the upper ends of the first and second pillars. A groove with a groove and a + -shaped connecting protrusion, and a fitting groove coupled to the accommodating fitting jaw of the foundation tree extending from the outer wall to the inner chamber side of the hanok is provided at the upper and lower ends, and having a frame coupled to the side groove of the second pillar. Girders, weight and a girder inserted between the inner wall member and a third pillar vertically installed on a foundation tree leading to the inner chamber side of the hanok, and a reinforcement connecting the second pillar on the outdoor side and the pillar on the indoor side. The roof structure is completed by a purlin, and the roof finishing structure is achieved by rafters roof panels, side panels, laminate roof boards, and wood board panels.
이상에서와 같이 본 발명은 건축 공법 중 건식공법으로서 목조 가구식 건축물과 한옥 건축 시 각 구조물들의 외면과 형상이 상호 형합되는 구조를 갖추므로서, 건축 후 수직하중에 대한 하중분산이 일체식 집성구조인 기둥과 벽체를 통해 구조물 전체에서 이루어지게 하여 안전성이 향상되고, 건축구조물을 공장에서 부품화 하여 현장에서 조립하는 구성에 의하여 부재의 손실을 줄이고, 조립공정으로인한 고급인력의 수요를 감소하고, 작업의 간편함으로 시공기간이 현저하게 단축되는 이점이 있다.As described above, the present invention has a structure in which the outer surface and the shape of each structure in the construction of a wooden furniture structure and a hanok are mutually matched as a dry construction method among the construction methods, so that the load distribution for vertical load after construction is integrated. Safety is improved by making the entire structure through the pillars and walls, reducing the loss of members by the construction of the building parts in the factory and assembling them on site, and reducing the demand for high-quality manpower due to the assembly process, The simplicity of work has the advantage that the construction period is significantly shortened.
이하 본 발명에 대한 바람직한 실시예를 첨부도면과 함께 상세히 설명한다.Hereinafter, preferred embodiments of the present invention will be described in detail with the accompanying drawings.
본 발명의 실시예에서 설명하는 가구식 목조 공법과 전통한옥은 여러 형태와 여러 구조가 있으므로 도면에 표현된 구성을 한정 하지 않는다.Furniture wooden method and the traditional hanok described in the embodiment of the present invention is not limited to the configuration shown in the drawings because there are many forms and structures.
도 1은 본 발명에 대한 건축공정도이고, 도 2는 본 발명에 대한 조립전 상태의 분해도이다.1 is a building process diagram for the present invention, Figure 2 is an exploded view of the pre-assembly state for the present invention.
본 발명에 따른 건축 건축 공법 중 건식공법의 목조 건축으로서 가구식 건축방식 및 전통한옥의 조립시공은 건축하고자 하는 터를 선정하여 바닥에 지반을 강화하여 바닥 표면이 평평해지도록 하여 기초면을 형성하는 기초단계를 행한다. 이 때, 강화방법은 강회, 황토, 소금, 숯과 기 개발된 KGSC공법으로 강화한다. 상기 기초단계에서 건물의 하중과, 토지의 경도를 계산해서 가구식 건축물 및 전통한옥의 축조후 바닥이 갈라지거나, 내려앉지 않도록 하기 위해 지반 강화시, 철근골조 및 보강재를 삽입하는 것이 바람직하다. 상기 기초면을 형성할 때 반주먹장 연결장부 형태의 끼움턱이 있는 토대목을 고정하기 위한 고정 철물을 일정간격으로 설치하고 기둥부는 주춧돌 위에 설치한다. (1공정)Among the building construction methods according to the present invention, the wooden construction of the dry construction method, the furniture construction method and the assembly construction of the traditional hanok to select the ground to be built to strengthen the ground on the floor to form a base surface by making the floor surface flat Perform the basic steps. At this time, the strengthening method is reinforced with lime, loess, salt, charcoal and the KGSC method developed. In the foundation step, it is preferable to insert the reinforcing bar and reinforcement when reinforcing the ground in order to prevent the floor from splitting or falling after the construction of furniture buildings and traditional hanok by calculating the load of the building and the hardness of the land. When forming the base surface, install a fixed hardware for fixing the foundation timber with the fitting of the accommodating mating connector type at regular intervals and the pillar portion is installed on the headstone. (1 step)
상기 기초와 주춧돌 윗면에 건축하고자하는 위치를 설정하여 면적의 테두리에 토대목을 설치 고정하면서 기초 면과 토대목 사이에 방습, 방수용 완충부재를 적층시키는 패드설치 (2공정)Install the pad on the edge of the area by setting the position to be built on the foundation and the top of the headstone, and install the pad to laminate the damping and waterproof buffer member between the foundation and the foundation.
상기 토대목 상단에 전기설비 설치단계 (3공정)Electrical equipment installation step on the top of the foundation (3 steps)
상기 토대목의 기둥 위치에 보강재가 내장된 기둥에 연결구 및 주먹장 연결구, 그리고 벽체 몰딩 연결구가 만들어진 제1 기둥을 설치 고정하는 기둥설치단계와, (4공정)A pillar installation step of installing and fixing a first column made of a connector and a fist connector, and a wall molding connector at a pillar having a reinforcement in the pillar position of the foundation, and (4 step)
창방과 하인방이 상 하단에 조립되며 장력이 상존하는 이중 열반사와 단열재로 만들어진 외벽체를 제1 기둥 측면에 조립하고, 제1기둥의 상단으로 창방의 주먹장 끼움홈을 가진 보아지와 주두를 조립 설치하는 외벽설치단계와, (5공정)Outer wall is assembled to the upper and lower sides of the upper and lower chambers, and the outer wall made of double heat reflection and heat insulator with constant tension on the side of the first column, and the outer wall for assembling and installing the bore and the head of the window with the fist hole of the window as the top of the first pillar. Installation step, (5 step)
상기 제1기둥에 조립 고정된 외벽부재의 타측단에 보강재가 내장된 주먹장 연결구 및 연결구 그리고, 벽체 몰딩연결구가 있는 제2기둥을 조립하여 반주먹장의 연결 장부가 있는 설비시설이 설치된 토대목에 조립하고, 제2기둥의 상단에는 창방 연결홈을 가진 보아지와 +자 연결돌기가 있는 주두를 조립한 뒤, 외벽체의 상단과 제1기둥과 제2기둥의 주두사이에 장여를 설치 조립하는 외벽체를 반복 고정한다Assemble on the other end of the outer wall member fixed and assembled to the first pillar assembling the fist connector and the connector with the reinforcement material, and the second column with the wall molding connector to assemble on the foundation installed with the installation facility of the connection ledger of the accompaniment After assembling the bore with the window connecting groove and the head of the + -shaped connecting projection at the upper end of the second pillar, the outer wall body is repeatedly fixed to the upper wall of the outer wall and the barrier between the first and second pillars. do
상기 외벽고정단계에서 장여와 창방을 설치조립하기 전에 제2기둥에 대하여 소정의 간격을 두고 한옥의 내실측으로 이어진 토대목에 보강재가 내장된 제3기둥을 세우고 제3기둥과 제2기둥사이에 주먹장 및 연결 돌출부가 내장 된 내벽부재를 조립 설치하고, +자 연결고리가 내장된 주두가 설치된 제2기둥상단과 제3기둥의 상단을 창방 장여 설치후 보강재가 내장된 상하부에 부재 안장홈과 설비홈이 만들어진 대들보로 연결하여 내부공간 형성단계와,In the fixing step of the outer wall, before installing and assembling the donor and the window, the third pillar with the reinforcement is erected in the foundation tree which extends to the inner chamber side of the hanok at a predetermined interval with respect to the second pillar, and between the third pillar and the second pillar. Assemble and install the inner wall member with built-in fist and connecting protrusions, and install the upper end of the second column and the third column where the pod with the + -shaped link ring is installed. The internal space forming step by connecting the grooves made girders,
상기 외벽설치단계와 외벽고정단계 및 내부공간형성단계를 반복적으로 수행하여 벽체 구조를 형성한다, (6공정)The outer wall installation step, the outer wall fixing step and the inner space forming step are repeatedly performed to form a wall structure (step 6).
상기 외벽체 형성단계 후 장여와 대들보 상면 설비홈 및 동자주 받침홈에 동자주 받침을 끼운 동자주를 대들보 상부 연결홈에 고정하고 상부에 중량을 설치하고 중량의 판대공 연결홈에 판대공을 설치하고 처마도리, 중도리, 종도리, 중장여, 종장여가 계단적로 설치된 지붕틀부재를 설치하여서 되는 지붕구조 형성단계와, (7공정)After the outer wall formation step, secure the copper column with the copper column base on the upper and the girders of the upper and the girders, install the weight on the upper girder and install the weight on the upper part, Roof structure forming step by installing roof frame member with stairway, middle way, Jongdori, middle long woman and long long woman (step 7)
상기 서까래막이 연결홈, 회벽막이 연결홈 기능이 있는 처마도리 상부에 서까래가 고정되는 안장 자리홈이 있는 울림산방을 추녀마루와 함께 안장하고 사래가 같이 설치고,지붕틀부재의 상부에는 일체화 된 서까래 판넬부재를 올려 고정하고, 서까래판위에는 부연판넬을 올려 지붕판 설치하는 단계. (8공정)The rafters connecting grooves, circuit wall connecting grooves, the saddle seating grooves where the rafters are fixed to the upper part of the eaves with the function of saddle together with the saddle and the saddle and installed together, the rafter panel member integrated on the roof frame member Step up and fix the roof panels on the rafters to lift the side panels. (8 steps)
팔짝지붕 구조시 지붕판 위에 지방을 설치하고 판넬화 제작된 일체식 목기연판을 고정되 있는 박공판넬 위에 설치하고 경량 박공벽을 설치하고 설치 시, 목기연, 부연, 서까래, 추녀마루 사태의 마구리는 방부도료 처리나 금속판넬로 씌워 보강하는 박공구조 설치 단계로 이루어지는 가구식 건축물의 조립식 한옥 건축공법.(9공정)In case of roof structure, install fat on roof board, install panelized wooden board on fixed gable panel, and install lightweight gable wall. Prefabricated Hanok construction method of furniture building consisting of preservative paint treatment or gable structure installation step reinforced with metal panel. (9 steps)
이러한 방법으로 건축되는 가구식 목조건축물 및 전통한옥의 구조는 건축하고자 하는 터를 설정하여 터 전체를 지반강화 작업을 하여 표면 전체를 평평하게 형성하는 기초면(1)과, 상기 기초면(1)위에 완충 및 차단 역할하는 차단판넬 건축하고자 하는 면적의 둘레에 설치고정하는 토대목부재(2)와, 상기 토대목부재(2)의 상면에 수직하게 설치하는 기둥 및 수평하게 설치하는 벽체로 된 외벽부재(4)와, 상기 외벽부재위에 설치하는 창방부재(5), 장여재(8 ), 대들보재(14), 주두재(13), 보아지재(7), 동자주재(16), 중량재(19),지붕틀부재와, 처마도리재(9), 중도리재(18), 종도리재 (23), 마루도리재(24), 추녀마루재(25) 및 이를 보강하는 장여재(23-1) 그리고, 상기 지붕틀부재의 상부에 설치하는 서까래 판넬부재(11)와, 상기 서까래부재(11)위에 설치하는 부연판넬 부재(12), 목기연 판넬부재(26), 박공판넬부재(27) 및 기와 지붕판부재(14)로 이루어진다.The structure of furniture wooden building and traditional hanok that is constructed in this way is based on the foundation to be built and ground strengthening of the entire ground to form the entire surface to form a flat surface, the foundation surface (1) Block panel acting as a buffer and blocking on the base member (2) is fixed to the periphery of the area to be built, a column vertically installed on the upper surface of the
상기 외벽부재(4)에 의해 형성되는 내부공간의 바닥에 형성되는 온돌판넬층 또는 마루부재(27), 단열층 부재와, 상기 내부공간을 수직하게 분할하는 내벽부재(4)로 구분된다.It is divided into an ondol panel layer or
상기의 가구식 목조건물 건축과 전통 한옥구성 중 기초면(1)은 건축하고자 하는 면적보다 큰 면적으로 형성하고, 소정의 간격으로 고정용 철물(1-1)의 조임부가 노출되게 매립한다.The base surface (1) of the above-described furniture wooden building construction and traditional hanok configuration is formed with a larger area than the area to be built, and is buried to expose the fasteners of the fixing hardware (1-1) at predetermined intervals.
상기 가구식 목조건물 건축과 전통한옥의 설치면적의 테두리에 설치하는 토대목(2)은 상면의 중앙부가 요철형상으로 돌출되는 반주먹장 형태를 가진 끼움턱(2-1) 및 상부에는 설비배관 안장부(2-2), 그리고 각각의 기둥이 설치 위치에 기둥 연결홈(3-4 )을 형성한다.The foundation wood (2) is installed on the border of the furniture wooden building construction and the installation area of the traditional hanok has a fitting pit (2-1) and the upper part of the fitting pipe protruding into the uneven shape in the center of the upper surface The dove 2-2 and each column form a column connecting groove 3-4 at the installation position.
상기 토대목(2)위에 수직하게 설치되는 기둥은 토대목의 모서리에 위치하는 제1기둥(3-1)과 제2기둥(3-2)과 제3기둥(3-3)은 측면에 외벽체와의 조립을 위한 주먹장 또는, 반주먹장 연결홈(3-4)과 벽체 마감면을 감추는 몰딩홈이 형성되고, 하면에는 토대목(2)의 끼움턱(2-1), 상면에는 보아지(7)와 결합을 위한 끼움홈이 형성된다. 민도리 구조시에는 상부에 장여홈과 대들보 그리고, 처마도리가 동시에 연결되는 홈을 가지며 주먹장 연결홈 형태를 가진다.The pillars installed vertically on the foundation wood (2) is the first pillar (3-1) and the second pillar (3-2) and the third pillar (3-3) located at the corner of the foundation wood, the outer wall body on the side A fist hole for assembling or a fist-feeding connection groove (3-4) and a molding groove to hide the wall finishing surface is formed, the fitting jaw (2-1) of the base wood (2) on the lower surface, the bore (7) ) And a fitting groove is formed for coupling. In the Mindori structure, the grooves, girders, and eaves are simultaneously connected to the upper portion and have a form of a fist connection.
상기 제1기둥(3)과 제2기둥(3-2)에 조립되는 외벽체(4)는 하단에 토대목에 연결부에 고정되는 주먹장 연결홈을 가진 하인방(32)을 두고 그 위에 격자살을 다수개 설치하는 상태에서 격자살 사이에 합판을 설치한다.The
상기 판재(4-1)는 표면에 방수지, 후면에 열반사지를 접착제로 압착시킨 상태로 형성하고, 판재과 판재 사이에 형성되는 공간으로 황토코팅 식물성 섬유단열재(4), 숯 코팅 식물섬유 단열재, 진공단열재 통상의 구조단열재(4-2)를 충진하고 테두리를 디자인목(4-3)으로 고정하되 디자인목(4-3)은 벽체의 저면을 제외한 상 면, 양측면에서 기둥의 디자인홈(3-1)과 조립될 수 있는 높이로 형성한다. 이때, 스위치 선로 및 전기배관 선로(4-4)를 시공하고 통상적으로 외부에는 라스처리 후 방수회벽, 화방벽(4-5)을 미장하고, 내부에는 라스처리 후 황토 미장(4-6)을 하여 완성한다.The plate (4-1) is formed in a state in which the waterproof paper on the surface, the heat reflection paper on the back with the adhesive, the space formed between the plate and the plate ocher coated vegetable fiber insulation (4), charcoal coated plant fiber insulation, vacuum Insulation Material The structural insulation material (4-2) is filled and the edge is fixed with the design wood (4-3), but the design wood (4-3) is the design groove of the column on the upper surface and both sides except the bottom of the wall (3- To form a height that can be assembled with 1). At this time, construct the switch line and the electric pipe line (4-4), and usually plastering the waterproofing wall and the fire wall (4-5) after lath treatment on the outside, and the ocher plastering (4-6) after lath treatment on the inside To complete.
처마도리(9)에는 서까래부재(11)를 설치할 때 고정하기 위한 가이드홈(9-3)을 형성하여 설치되는 서까래 부재(11)의 고정판(10)이 걸림과 동시에 실내의 전기배선공사를 위한 안내홈(9-3) 역할을 하게 한다. 또한, 내부에 회반죽(9-4)처리하여 공기유통을 단절하고, 도리 연결부에는 고정목(9-5)을 설치, 구조 연결부 보강의 기능을 한다.The fixing
이 때, 벽체 하부에는 하인방(32)과 벽체골조(41) 및 판재와 동시에 고정시켜 일체식 제작으로 내력 벽체로서의 골격과 강도를 유지하며, 하부에있는 하인방(32)에 반주먹장 연결홈은 토대목에 수직으로 하강, 내부로 수평이동 시켜 좌우에 있는 기둥의 조끼대에 의해 이동 고정된다. 상부에는 창방(5)이 일체식으로 제작, 하부에 있는 하인방과 일체식으로 제작되기도 하고, 분리 제작 할때는 주먹장으로 제작, 좌우로 밀어 넣어 조립 후, 기둥에 조립하여 맞춘다.At this time, the lower part of the wall is fixed at the same time with the
또한, 창방(5) 상부에 장여(8)구조는 2층 구조시와 외부에 비 또는 물에 노출시는 창방(5)과 장여(8)를 일체식으로 하여, 외부로 부터의 누수를 방지할 수 있고, 항상, 수평판넬 또는 수평부재는 아래는 돌출 상부홈으로 연결 방법을 택하고, 수직재는 꺽음턱을 두어 외부 누수로부터 차단하는 구조와 부재의 신축으로부터 외부 공기위층을 차단하는 구조를 가진다.In addition, in the upper part of the
또한, 창방(5)은 내부에 설비구(5-1)를 가져, 토대목(2), 벽체중심(4) 설비구(4-4)를 통해 올리는 연결을 창방(5-1) 내부에 두어 처마도리(9)와 함께 2중으로 설치되어, 대들보(15)로 연결, 동자주(16)를 통해 중량(19)으로, 중량(19)에서 판대공(20)으로, 판대공(20)에서 중도리(18)로 연결 배선되며, 마루도리(24)와 함께 배관 연결홈을 형성하는 구조를 가진다.In addition, the
상기 구조위에 서까래 판넬부재(11)는 건축하고자 하는 가구식 목조건물과 한옥의 크기로 미리 형성하는 구성이며, 상기 서까래 모서리부분에 한옥의 미를 나타내기 위한 부연판넬(12)을 설치한다. 이러한 서까래 판넬(11) 및 부연판넬(12)의 덧지붕판(14)으로 기와 경사면을 잡고, 부재(11)의 덧지붕판 부재(14)를 얹어 고정한다.The
지붕판넬(11)은 상,하면 특히 하부는 불연판넬로 제작하고 중앙부 단열재는 판넬구조적 강도가 강한 우레탄판넬을 발포하여 제작한다.The
지붕구조가 팔짝지붕의 경우 처마도리(18) 상부에 추녀마루와 울림산방을 걸고, 상부에 산자서까래 판넬을 설치, 지붕판을 형성한다.In the case of the roof structure of the roof of the roof hang the ugyeo maru and the Ullimsanbang on the top of eaves (18), install a panel of mountain rafters on the top to form a roof plate.
또한, 완성된 지붕판 상부에 지방으로 고정하고 박공부 판넬 구조를 완성 후 집성 가공된 박공판넬을 설치 후 상부에 기 제작된 목기연 판넬을 상부에 얹어 고정시키는 구조를 가지며, 마루도리를 곡선재로 사용하거나 마루 울림산방을 곡선각에 맞추어서 설치한다.In addition, it is fixed to the upper part of the roof plate with fat and completed the structure of the gable panel after installing the aggregated gable panel has a structure that is fixed on the top by mounting the woodworking panel made in the upper part, curved floor material Either use it or install Maru Ullimsanbang at a curved angle.
이상에서와 같은 본 발명의 가구식 목조 건축물과 전통한옥의 건축방법과 가구식 목조 건축물과 한옥의 구조는 상호 결합되는 구조와 기둥과 벽체의 일체식 결 합구조와 강성결방법에 의한 합성 구조로 되어 있어 구조적 안정을 주고, 단순 공정 제작에 의한 공학부재 가공으로 고도의 숙련에 의하지 않고서도 정밀하게 단순공정으로 제작하여 대량생산하여 공급하여 시공할 수 있고 , 시공 후, 함수율 15%이하로 건조시킨 목재로 제작하므로 변형이 적어 틈새 및 비틀림과 휨이 발생하지 않는다.The construction method of the furniture wooden building and the traditional hanok of the present invention and the structure of the furniture wooden building and the hanok of the present invention as described above are combined with each other, and the composite structure by the integral joining structure of the pillar and the wall and the rigidity forming method. It gives structural stability, and it can be manufactured and supplied by mass production by supplying it by simple process precisely without high skill by processing the engineering member by simple process production, and after drying, it is dried under 15% water content. Because it is made of wood, there is little deformation and no gaps, twists and warpages occur.
또한 본 발명의 가구식 목조 건축물과 한옥구조는 구조물을 부품화 하므로 생산과 취급 및 운반이 편리하다.In addition, the furniture wooden structure and hanok structure of the present invention is convenient to produce, handle and transport because the parts are structured.
[실시예1]Example 1
본 발명은 단층 구조외에 이층이상의 구조를 갖은 가구식 내화 목구조 건축물과 내화 목구조 한옥으로 건축할 수 있다.The present invention can be constructed of a furniture fireproof wood structure building and a fireproof wood structure hanok having a structure of two or more layers in addition to the single-layer structure.
이층이상의 건축방법으로는 지면에 콘크리트로 시공하여서 기초 바닥면을 형성하는 기초단계와(1),In the construction method of two or more floors, the foundation step of forming the foundation floor surface by constructing concrete on the ground (1),
상기 기초 바닥면에 건축하고자 하는 면적을 설정하여 면적의 테두리에 토대목(2)을 설치 고정하면서 기초면과 토대목사이에 방습,방수용 완충부재를 적층시키는 단계와, 벽체부(4)의 하면에 주먹장홈과 연결 구조를 갖고, 축선에 기둥(3)을 설치 할 수 있는 턱구조, 설비 배관을 할 수 있는 주먹장구조를 가진 토대목(2)을 설치하는 단계와By setting the area to be built on the bottom surface of the foundation to install and fix the base wood (2) on the border of the area between the base surface and the base wood, the step of stacking the damping, waterproof buffer member, and on the lower surface of the wall portion (4) Installing a foundation (2) having a connection structure with a fist hole, a jaw structure for installing a pillar (3) on an axis, and a fist structure for a plumbing facility;
상기 토대목(2)의 모서리 위치에 보강재가 내장된 제 1기둥(3)을 설치고정하는 기둥설치단계와,A pillar installation step of fixing and fixing the
창방(5)과 하인방(32)이 상하단에 구비된 단열재가 내장된 각각의 외벽부재 를 제1기둥 측면에 조립하고, 제1기둥의 상단으로 보아지(7)와 보강재가 내장된 보(15)를 조립 설치하는 외벽설치단계와,Assembling each of the outer wall members with the heat insulating material provided with upper and lower ends of the
상기 제1기둥(3)에 조립고정된 외벽부재의 타측단에 보강재가 내장된 제2기둥(3-1)을 조립하여 토대목(2)에 조립고정하고, 제2기둥(3-1)의 상단에는 보아지(7)와 보(15)를 조립한 뒤, 외벽부재의 상단과 제1기둥과 제2기둥사이를 장혀(7)로 조립고정하는 외벽고정단계와,Assembling a second column (3-1) with a reinforcing material in the other end of the outer wall member is fixed to the first pillar (3), assembled and fixed to the foundation wood (2), the second pillar (3-1) On the upper end of the bore (7) and the beam (15), the outer wall fixing step of assembling and fixing the upper end of the outer wall member and between the first pillar and the second pillar (7),
상기 외벽고정단계에서 장여(8)를 설치조립하기 전에 제2기둥에 대하여 소정의 간격을 두고 한옥의 내실측으로 이어진 토대목(2)에 보강재가 내장된 제3기둥(3-2)을 세우고 제3기둥과 제2기둥사이의 내벽부재를 조립 설치하고, 보아지(7)가 설치된 제2기둥상단과 제3기둥의 상단을 보강재가 내장된 보로 연결하여 내부공간 형성단계와,Before installing and assembling the Jangyeo (8) in the outer wall fixing step, the third pillar (3-2) with the reinforcement is built in the foundation wood (2) leading to the inner chamber side of the hanok at a predetermined interval with respect to the second pillar, An inner space forming step of assembling and installing the inner wall member between the third pillar and the second pillar, and connecting the upper end of the second pillar with the
상기 외벽설치단계와 외벽고정단계 및 내부공간형성단계를 반복적으로 수행 이행하여 1층 외벽체를 형성하는 단계와,Repeatedly performing the outer wall installation step, the outer wall fixing step and the inner space forming step to form a one-layer outer wall body;
상기 외벽체 형성단계로 인해 구분된 실내의 기초면 위에 상부 구조 받기 위한 마루판 구조(27)위에 단열판넬과 상부에 난방판넬을 시공하는 온돌판넬 설치단계와,An ondol panel installation step of constructing a heat insulation panel and a heating panel on the
상기 외벽체 형성 후 장여의 상부에 보강재가 삽입된 층보(28)를 설치 조립하여서 되는 2층 골조단계와,After forming the outer wall and the two-layer skeleton step of installing and assembling the
상기 층보(28)의 내측에 소정의 두께로 되고 보강재가 내장된 스틸데크 (steel deck)바닥판넬 부재(27)를 고정볼트에 의해 설치하여 판을 설치하는 바닥형 성단계와,A floor-forming step of installing a plate by installing a steel deck
상기 층보(28)와 바닥판(27)의 상면에는 상기 1층 외벽체(4) 형성단계를 동일하게 반복하여 2층 외벽체를 형성하는 이층외벽체단계와,The two-layer outer wall step of forming a two-layer outer wall body by repeating the same step of forming the first-layer
2층 외벽체의 각각의 기둥(3)과 외벽부재(4) 상부에는 소로와 보아지가 조립된 장혀, 그리고 보아지(7)와 주두(13)가 조립된 보(15)를 조립 설치하는 이층외벽고정단계와,On each
상기 이층외벽 고정단계로 형성되는 내부공간의 스틸데크 (steel deck) 바닥판(27)에 단열판넬과 황토 축열판 위에 난방판넬을 시공하는 온돌판넬 설치단계와,An ondol panel installation step of constructing a heating panel on the heat insulation panel and the ocher heat storage plate on the steel
상기 장혀(9-1)와 보(15)의 상부에는 처마도리(9)가 계단적로 설치된 지붕틀부재를 설치하여서 되는 지붕틀고정단계와,(11)A roof frame fixing step of installing a roof frame member in which the eaves (9) are installed stepwise on the upper part of the tongue (9-1) and the beam (15);
상기 지붕틀부재의 상부에는 일체화된 서까래판넬부재를 올려 고정하고, 서까래판(11) 위에는 부연판넬(12)을 올려 고정하고, 기와지붕판(14)을 상기 서까래부판넬부재 위(11)에 올려 고정하는 지붕설치단계를 순차적으로 이행하는 건축방법이다.The upper part of the roof frame member is fixed by raising the integrated rafter panel member, and the upper part of the
이러한 2층이상의 가구식 내화 목구조건물과 한옥구조는 제1기둥(3), 제2기둥(3-1), 제3기둥(3-2)은 1층구조 가구식 목조 건축물과 한옥에서의 길이보다 긴 길이로 형성하고, 외벽체(4)상부의 창방(5)에 조립되는 장여(8) 위에 이층의 스틸데크 (steel deck) 마루판넬 부재(27)를 조립하기 위한 걸림턱이 구비된 보강재가 내장되 층보(28)를 조립하는 구조가 추가된다.These two-storey furniture fireproof wooden furniture and hanok structure is the first pillar (3), the second pillar (3-1), and the third pillar (3-2) is a one-story furniture wooden structure and hanok Reinforcement formed of a length longer than the length, and provided with a latching jaw for assembling a two-level steel deck
상기 층보(28)의 걸림턱에 조립되는 스틸데크 (steel deck) 마루부재(27)에 는 온돌판넬이 설치될 수 있고, 마루판넬이 설치될 수도 있다.The steel
그리고, 상기 보강재가 삽입된 층보(28)에는 2층의 벽체(4)를 설치하기 위한 하인방(3) 또는 외벽체 하부에 하인방이 일체되게 설치되며, 상기 층보(28)와 하인방(3) 은 직접 연결되는 결합되는 구조이다.In addition, the
이러한 층보(28)에 설치되는 2층 외벽체(4)의 상단 창방(5)과 기둥(3)의 상단에는 1층 가구식 목조건축물과 한옥 구조에 설치되는 소로, 보아지,장혀 및 처마도리등이 순차적으로 설치되고, 서까래 부재판넬(11)과, 기둥지붕판넬 부재(14)가 설치되는 구조이다.In the upper window (5) and the top of the pillar (3) of the two-story outer wall (4) is installed in the
도1은 본 발명의 건축공정도.1 is a building process of the present invention.
도2는 본 발명의 구조물에 대한 분해도.Figure 2 is an exploded view of the structure of the present invention.
도3은 본 발명의 1층구조에 대한 기둥조립순서도.Figure 3 is a column assembly sequence diagram for a one-layer structure of the present invention.
도4는 본 발명의 1층구조에 대한 기둥조립완성도.Figure 4 is a column assembly completion of the one-layer structure of the present invention.
도5는 본 발명의 1층구조에 대한 벽체조립순서도.5 is a wall assembly sequence diagram for a one-layer structure of the present invention.
도6은 본 발명의 1층구조에 대한 벽체조립완성도.6 is a wall assembly completion of the one-layer structure of the present invention.
도7은 본 발명의 2층구조에 대한 기둥조립순서도.7 is a column assembly sequence diagram for a two-layer structure of the present invention.
도8은 본 발명의 2층구조에 대한 기둥조립완성도.8 is a column assembly completion of the two-layer structure of the present invention.
도9는 본 발명의 2층구조에 대한 벽체조립순서도.9 is a wall assembly sequence diagram for a two-layer structure of the present invention.
도10은 본 발명의 2층구조에 대한 벽체조립완성도.10 is a wall assembly completion of the two-layer structure of the present invention.
도11은 본 발명의 2층 통재주 조립 순서도11 is a flow chart of assembling two layers of the present invention
도12는 본 발명의 2층 통재주 조립 완성도Figure 12 is a two-layer cylindrical column assembly complete view of the present invention
도13은 본 발명의 통재주 난간 조립 순서도Figure 13 is a flow chart assembly flow chart of the present invention
도14는 본 발명의 통재주 난간 조립 완성도Figure 14 is a complete rail handrail assembly completeness of the present invention
도15는 본 발명의 분리주 난간 조립 순서도Figure 15 is a flow chart of the separation railing assembly of the present invention
도16은 본 발명의 분리주 난간 조립 완성도Figure 16 is a complete assembly of separation railing of the present invention
도17은 본 발명의 벽 부분 난간조립 상세도17 is a detailed view of assembling the wall portion railing of the present invention
도18은 본 발명의 벽 부분 난간조립 완성도Figure 18 is a wall partial railing assembly completeness of the present invention
도19의 본 발명은 지붕 상부구조 구성도19 is a block diagram of a roof superstructure
도20의 본 발명은 박공부 구성도20 is a gable portion configuration of the present invention
도21의 본 발명은 벽체 조립 순서도21 is a wall assembly flow chart of the present invention.
도22의 본 발명은 벽체 조립 완성도22 is a wall assembly complete view of the present invention
Claims (12)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020090067319A KR101213504B1 (en) | 2009-07-23 | 2009-07-23 | Tailor-Made Type Korean House Manufacturing Method for Furniture-style Buildings and Tailor-Made Type Korean House Structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020090067319A KR101213504B1 (en) | 2009-07-23 | 2009-07-23 | Tailor-Made Type Korean House Manufacturing Method for Furniture-style Buildings and Tailor-Made Type Korean House Structure |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020120078614A Division KR101292748B1 (en) | 2012-07-19 | 2012-07-19 | Tailor-Made Manufacturing Method for Furniture-style Buildings and Traditional Korean-style Structure |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20110009882A true KR20110009882A (en) | 2011-01-31 |
KR101213504B1 KR101213504B1 (en) | 2012-12-24 |
Family
ID=43615434
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020090067319A KR101213504B1 (en) | 2009-07-23 | 2009-07-23 | Tailor-Made Type Korean House Manufacturing Method for Furniture-style Buildings and Tailor-Made Type Korean House Structure |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR101213504B1 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101101788B1 (en) * | 2011-09-08 | 2012-01-05 | 한국건설기술연구원 | The prefabcated hanok |
KR101402959B1 (en) * | 2012-09-12 | 2014-06-02 | 이규인 | Modern Hanok Using Light-weight wooden structure |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20170018587A (en) | 2015-08-10 | 2017-02-20 | (주)영승조경랜드 | Column capital of prefabrication Type Pavilion |
KR200481105Y1 (en) | 2015-11-23 | 2016-08-16 | 주식회사 황토와문화 | the roof structure of movable house |
KR102063860B1 (en) * | 2018-01-11 | 2020-01-08 | 진경애 | The tiled roof structure of korean style house and construction method thereof |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100890342B1 (en) | 2008-12-31 | 2009-03-25 | 안중각 | A post-and-lintel construction to do re-modeling of a general wood building to a traditional building and an execution method of the post-and-lintel construction |
-
2009
- 2009-07-23 KR KR1020090067319A patent/KR101213504B1/en active IP Right Grant
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101101788B1 (en) * | 2011-09-08 | 2012-01-05 | 한국건설기술연구원 | The prefabcated hanok |
KR101402959B1 (en) * | 2012-09-12 | 2014-06-02 | 이규인 | Modern Hanok Using Light-weight wooden structure |
Also Published As
Publication number | Publication date |
---|---|
KR101213504B1 (en) | 2012-12-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US9115504B2 (en) | System for modular building construction | |
JP5643205B2 (en) | Unit building system | |
US20160160515A1 (en) | System for modular building construction | |
US6588161B2 (en) | Laminated construction elements and method for constructing an earthquake-resistant building | |
US20160040443A1 (en) | Modular Building System | |
US20090165399A1 (en) | Prefabricated reinforced-concrete single-family dwelling and method for erecting said dwelling | |
US20130305629A1 (en) | Modular Building System | |
CN105178629A (en) | Jointed wood structure house | |
KR101213504B1 (en) | Tailor-Made Type Korean House Manufacturing Method for Furniture-style Buildings and Tailor-Made Type Korean House Structure | |
CN104060853A (en) | Lightweight steel structure modularized residential building | |
WO2019227174A1 (en) | Connection system | |
US20220049488A1 (en) | Systems and methods for constructing a multi-storey building | |
KR101292748B1 (en) | Tailor-Made Manufacturing Method for Furniture-style Buildings and Traditional Korean-style Structure | |
Öztank | An investigation of traditional Turkish wooden houses | |
KR20020037002A (en) | Assembly Korean-style house construction method and that Korean-style house structure of furniture building | |
KR102089751B1 (en) | Assembly type wall and floor structure of ocher room | |
GB2480994A (en) | Timber I-beams and panels in attic roof structures | |
JP2552051B2 (en) | Panel and frame pre-cut panel fitting construction method | |
AU2014265071B2 (en) | A building and methods of constructing the building | |
GB2200383A (en) | Engineered housing | |
JP2688877B2 (en) | Wooden construction method | |
RU119373U1 (en) | BUILDING CONSTRUCTION FROM MULTILAYER PANELS | |
Chen et al. | Design and construction of a two-story modern bamboo house | |
RU200790U1 (en) | Overlap | |
RU127772U1 (en) | WOODEN FOR MAKING WOODEN HOUSES, BUILDINGS, CONSTRUCTIONS AND BUILDING FROM WOODEN |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
E902 | Notification of reason for refusal | ||
A107 | Divisional application of patent | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20151209 Year of fee payment: 4 |
|
FPAY | Annual fee payment |
Payment date: 20161209 Year of fee payment: 5 |
|
FPAY | Annual fee payment |
Payment date: 20180604 Year of fee payment: 6 |
|
FPAY | Annual fee payment |
Payment date: 20190131 Year of fee payment: 7 |
|
FPAY | Annual fee payment |
Payment date: 20200224 Year of fee payment: 8 |
|
R401 | Registration of restoration |