KR20100117309A - Prestress concrete composite girder with prestress non-introducing portion provided at both ends, manufacturing method thereof, and built-up type slab bridge construction method using the same - Google Patents

Prestress concrete composite girder with prestress non-introducing portion provided at both ends, manufacturing method thereof, and built-up type slab bridge construction method using the same Download PDF

Info

Publication number
KR20100117309A
KR20100117309A KR1020090035985A KR20090035985A KR20100117309A KR 20100117309 A KR20100117309 A KR 20100117309A KR 1020090035985 A KR1020090035985 A KR 1020090035985A KR 20090035985 A KR20090035985 A KR 20090035985A KR 20100117309 A KR20100117309 A KR 20100117309A
Authority
KR
South Korea
Prior art keywords
girder
prestressed
steel wire
steel
concrete
Prior art date
Application number
KR1020090035985A
Other languages
Korean (ko)
Other versions
KR101086646B1 (en
Inventor
김회준
김창래
Original Assignee
(주)에스앤씨산업
주식회사 젬콘
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)에스앤씨산업, 주식회사 젬콘 filed Critical (주)에스앤씨산업
Priority to KR1020090035985A priority Critical patent/KR101086646B1/en
Publication of KR20100117309A publication Critical patent/KR20100117309A/en
Application granted granted Critical
Publication of KR101086646B1 publication Critical patent/KR101086646B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/28Concrete reinforced prestressed
    • E01D2101/285Composite prestressed concrete-metal

Abstract

PURPOSE: A prestress concrete composite girder with prestress non-introduction parts, a manufacturing method thereof, and a construction method of a prefabricated slab bridge using the same are provided to reduce installation costs by minimally reducing a concrete placing work. CONSTITUTION: A prestress concrete composite girder is composed of steel wires(11), prestress non-introduction parts(25), and concrete. The steel wires are installed on the front surface at uniform intervals. The prestress non-introduction parts are formed in both ends of the girder using the steel wires. The concrete is placed and is hardened so that exposed steel wires(12) and exposed reinforcing bars(14) can be installed in both ends of the girder.

Description

양단부에 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더와 이의 제작방법 및 이를 이용한 조립식슬래브교 시공방법{Prestress concrete composite girder with prestress non-introducing portion provided at both ends, manufacturing method thereof, and built-up type slab bridge construction method using the same}Prestress concrete composite girder with prestress non-introducing portion provided at both ends, manufacturing method according to both ends, and built-up type slab bridge construction method using the same}

본 발명은 해안에 일정한 크기의 부두를 설치하기 위하여 잔교를 설치하거나 또는 하천을 복개하기 위하여 복개교량의 설치에 적용하기 위한 것이다. The present invention is to be applied to the installation of the bridge bridge to install the remnant bridge or to cover the river to install a pier of a constant size on the coast.

즉, 지반에 격자형으로 다수개 설치된 강관파일 상부에 하부지지대를 설치하고, 상기 하부지지대위에 프리스트레스트콘크리트합성거더를 거치하고, 상기 강관파일에 설치된 수직철근과 상기 프리스트레스트콘크리트합성거더의 단부에 돌출설치된 돌출강선 및 노출철근을 루프철근으로 상호 결합하고, 이들을 방사철근으로 결합한 거더연결부와, 상기 프리스트레스트콘크리트합성거더에 양단에 프리스트레스미도입부가 설치된 프리캐스트콘크리트판넬을 설치하고, 콘크리트로 상기 거더연결부와 프리스트레스트콘크리트합성거더위에 타설하여 슬래브를 설치한 조립식슬래브교 시공방법에 관한 것이다.That is, a lower support is installed on the upper part of the steel pipe piles, which are installed in a lattice form on the ground, and a prestressed concrete composite girder is mounted on the lower support, and the vertical reinforcement installed on the steel pipe pile and the ends of the prestressed concrete composite girder. The girder connection portion which mutually combines the protruding steel wire and the exposed steel reinforcement with the loop reinforcement and combines them with the radial reinforcing bar, and the prestressed concrete panel on which the prestressed non-introduction part is installed at both ends of the prestressed concrete composite girder, and the girder with concrete The present invention relates to a method of constructing a prefabricated slab bridge in which a slab is installed by placing it on a joint and a prestressed concrete composite girder.

또한, 상기 프리스트레스트콘크리트합성거더 및 프리캐스트콘크리트판넬은 프리스트레스를 양단부를 제외한 부분에만 선택적으로 도입하도록 하는 거더제작대를 이용하여 제작한 것으로서, 양단부에는 프리스트레스가 도입되지 않도록하면서, 그 이외의 부분에는 프리스트레스가 도입되도록 하고, 양단부에는 일정길이 연장된 노출강선 또는 노출강선 및 노출철근을 설치하도록 한 것이다.In addition, the prestressed concrete girder and the precast concrete panel is manufactured by using a girder fabrication table to selectively introduce the prestress only to the portion except the both ends, while preventing the prestress to be introduced at both ends, Prestress is introduced, and both ends are provided with exposed steel wire or exposed steel wire and exposed steel bars extending a certain length.

종래에는 하천 또는 바닷가에 교량을 설치하기 위하여, 가물막이를 설치하고, 가물막이가 설치된 내부의 지반을 굴착하여 기초부를 형성하기 위한 철근 배근 및 콘크리트를 타설하여 기초부를 설치한 다음, 그 위에 교량의 교각을 설치하고, 그 위에 교좌장치를 설치하고 그 위에 거더를 설치하여 교량을 설치하는 과정을 거치므로서, 공사기간이 과다하게 소요되면서, 이로인하여 공사비 또한 과다하게 소요되는 문제점이 상존하여 왔다.Conventionally, in order to install a bridge in a river or a beach, a clamshell is installed, reinforcement and concrete are laid to form a foundation by excavating the internal ground where the clamshell is installed, and then a foundation is installed thereon. As the bridge is installed, the bridge device is installed thereon, and the girder is installed thereon, and the bridge is installed. As a result, the construction period is excessively consumed.

본 발명은 상기와 같은 문제점을 개선하면서 보다 효율적으로 공사기간을 감축시키면서 공사비를 절감할 수 있는 경제성과 효율성이 있는 교량시공방법을 제공하기 위하여 제안된 발명이다. The present invention has been proposed to provide a bridge construction method having economical efficiency and efficiency that can reduce the construction cost while reducing the construction period more efficiently while improving the above problems.

하상의 연약지반상에 바로 교량의 교각으로 활용할 수 있도록 설치된 다수개의 강관파일 상단에 하부지지대를 설치하고, 상기 강관파일 내부의 일정깊이에 설치된 내부받침판까지 수직철근을 다수개 설치하고, 상기 하부지지대에 프리스트레스트콘크리트합성거더를 거치하고, 상기 프리스트레스트콘크리트합성거더의 양단에 노출된 노출강선 및 노출철근을 상기 수직철근과 결속하고, 이들을 루프철근으로 상호 연결하면서, 상기 루프철근에 방사상으로 설치된 방사철근을 설치한 거더연결부를 설치하고, 상기 프리스트레스트콘크리트합성거더에 양단부에 프리스트레스미도입부를 설치한 프리캐스트콘크리트판넬을 마루바닥깔듯이 설치하고, 상기 거더연결부와 상기 프리캐스트콘크리트판넬 위에 콘크리트를 타설경화하여 슬래브를 형성하여 설치한 조립식슬래브교를 시공하는 것이다.The lower support is installed on the upper part of the plurality of steel pipe piles installed to be utilized as a bridge pier on the soft ground of the lower floor, and the plurality of vertical reinforcing bars are installed to the inner support plate installed at a predetermined depth inside the steel pipe pile, and the lower support Radiating installed on the roof reinforcement, mounted on the prestressed concrete girder, the exposed steel wire and exposed reinforcement exposed to both ends of the prestressed concrete composite girder and the vertical reinforcement, and interconnected with the loop reinforcement, Install the girder connection part with reinforcing bar, and install the precast concrete panel with the prestress non-introduction part on both ends of the prestressed concrete girder like flooring, and cast concrete on the girder connection part and the precast concrete panel. Hardening to form slabs To build a prefabricated slab bridge.

사전에 공장제작된 하부지지대위에 양단부에 프리스트레스미도입부가 설치된 프리캐스트콘크리트판넬과 프리스트레스트콘크리트합성거더를 지반에 격자형으로 다수개 설치된 강관파일위에 조립식으로 설치하여 교량을 설치하도록 한 것으로서, 최대한으로 콘크리트작업을 축소하면서, 사전에 공장제작된 자재를 간단히 조립설치하여 공사기간 및 인건비를 절감하는 경제적이면서 공사효율을 향상시키는 시공 방법을 제공하는데 있다.The precast concrete panel and prestressed concrete girder with prestressed non-introduced parts at both ends on the factory-supported lower support base are prefabricated on the steel pipe piles installed in a lattice form on the ground. It is to provide a construction method that improves the construction efficiency and economics by reducing the construction work and labor costs by simply assembling and installing the prefabricated materials while reducing the concrete work.

본 발명은 하상인 연약지반상에 바로 교량의 교각으로 활용할 수 있는 다수개의 강관파일을 지반내에 격자로 다수개 타입 또는 관입설치한 다음, 강관파일 상부에 하부지지대를 설치하고, 상기 하부지지대 위에 프리스트레스트콘크리트합성거더를 다양한 방향으로 설치하고, 상기 프리스트레스트콘크리트합성거더의 양단부에 노출된 노출강선 및 노출철근과 강관파일내에 설치된 수직철근을 루프철근으로 상호 결속하면서 상기 루프철근에 방사상으로 설치된 방사철근을 연결한 거더연결부를 설치하고, 상기 하부지지대 위에 거치된 프리스트레스트콘크리트합성거더 위에 양단부에 프리스트레스미도입부가 설치된 프리캐스트콘크리트판넬을 설치한 후에, 거더연결부와 상기 프리캐스트콘크리트판넬 위에 콘크리트를 타설경화시켜 슬래브를 설치한 조립식슬래브교량을 설치하는 것이다.The present invention installs a plurality of steel pipe piles can be used as a bridge pier directly on the lower bed of the river bed in a grid or a plurality of types, and then install a lower support on top of the steel pipe pile, the frist on the lower support Radial reinforcement radially installed on the roof reinforcement while the rest concrete girder is installed in various directions, and the exposed steel wire and the exposed reinforcement exposed to both ends of the prestressed concrete girder and the vertical reinforcement installed in the steel pipe pile are mutually bound by the loop reinforcement. After installing the girder connection portion connecting the pre-cast concrete panel installed on both ends of the pre-stressed concrete composite girder mounted on the lower support, and then pour hardening concrete on the girder connection portion and the precast concrete panel Install the slab To install a prefabricated slab bridges.

본 발명은 하상인 연약지반상에 바로 교량의 교각으로 활용할 수 있는 다수개의 강관파일을 지반내에 격자로 다수개 타입 또는 관입설치한 다음, 강관파일 상부에 하부지지대를 설치하고, 상기 하부지지대 위에 프리스트레스트콘크리트합성거더를 다양한 방향으로 설치하고, 상기 프리스트레스트콘크리트합성거더의 양단부에 노출된 노출강선 및 노출철근과 강관파일내에 설치된 수직철근을 루프철근으로 상호 결속하면서 상기 루프철근에 방사상으로 설치된 방사철근을 연결한 거더연결부를 설치하고, 상기 하부지지대 위에 거치된 프리스트레스트콘크리트합성거더 위에, 양단부에 프리스트레스미도입부가 설치된 프리캐스트콘크리트판넬을 설치한 후에, 거더연결부와 상기 프리캐스트콘크리트판넬 위에 콘크리트를 타설경화시켜 슬래브를 설치한 조립식슬래브교량을 설치하는 것이다.The present invention installs a plurality of steel pipe piles can be used as a bridge pier directly on the lower bed of the river bed in a grid or a plurality of types, and then install a lower support on top of the steel pipe pile, the frist on the lower support Radial reinforcement radially installed on the roof reinforcement while the rest concrete girder is installed in various directions, and the exposed steel wire and the exposed reinforcement exposed to both ends of the prestressed concrete girder and the vertical reinforcement installed in the steel pipe pile are mutually bound by the loop reinforcement. After installing the girder connection portion connected to the prestressed concrete girder mounted on the lower support, precast concrete panels with prestressed non-introduced portions are installed at both ends, and then cast concrete on the girder connection and the precast concrete panel. To harden the slab To install a prefabricated slab bridges.

상기 거더의 양단부에 프리스트레스가 도입되지 않은 부분을 이용하여 거더연결부와 콘크리트타설파일연결부를 상호 연결하여 일체화한 지점연결부에 작용하는 부모멘트에 의하여 발생된 압축력이 상기 거더의 프리스트레스 미도입부에 의하여 감소되도록 한 것이다.The compressive force generated by the parent acting on the girder joint and the concrete placing pile joint by connecting the girder connecting portion and the concrete placing pile connecting part by using the portions where no prestress is introduced at both ends of the girder is reduced by the prestress unintroducing portion of the girder. It is.

또한, 공장에서 사전에 제작된, 프리스트레스를 선별적으로 도입한 프리스트레스트콘크리트합성거더와 프리캐스트콘크리트판넬, 강관파일, 하부지지대등을 단순히 조립설치하고, 콘크리트타설작업을 최소한으로 줄여 교량을 설치하는 기간을 단축하면서 설치비용을 절감하도록 하는 효율적이면서 경제성이 뛰어난 교량설치방법인 것이다.In addition, the prestressed concrete girder, precast concrete panel, steel pipe pile, lower supporter, etc., which are prefabricated in the factory, are pre-fabricated, and the bridge is installed with minimal concrete placing work. It is an efficient and economical bridge installation method to reduce the installation cost while reducing the period.

본 발명의 구성 및 작용을 첨부된 도면에 의하여 상세히 설명하면 다음과 같다.The configuration and operation of the present invention will be described in detail with reference to the accompanying drawings.

도 1은 본 발명의 프리스트레스트콘크리트합성거더를 보여주는 도면이며, 도 2(a)(b)(c)(d)는 본 발명의 프리스트레스트콘크리트합성거더를 거더제작대를 이용하여 제작하는 과정을 보여주는 도면이며, 도 3은 도 2의 거더제작대의 단부지압강판을 보여주는 도면이며, 도 4는 도 2의 거더제작대의 가동지압강판을 보여주는 도면이며, 도 5는 도 2의 거더제작대의 강선체결지압강판을 보여주는 도면이며, 도 6(a)(b)는 도 2의 거더제작대의 강선체결지압강판에 강선이 체결된 상태를 상세히 보여주는 도면이며, 도 7은 본 발명의 프리스트레스트콘크리트합성거더를 이용하여 조립식슬래브교를 설치한 것을 보여주는 도면이며, 도 8은 도 7의 단면을 보여주는 단면도이며, 도 9(a)(b)는 본 발명의 조립식슬래브교의 강판파일의 상단에 걸쳐지도록 설치하고, 그 위에 설치되는 거더를 지지하도록 하는 하부지지대를 상세히 보여주는 도면이며, 도 10은 본 발명 조립식슬래브교의 기둥인 강관파일의 상부에 일정범위에 걸쳐 설치된 콘크리트타설파일연결부와 그 내부에 전단연결재가 설치된 것를 보여주는 도면이며, 도 11은 본 발명의 조립식슬래브교를 설치하기 위하여 강관파일의 상부에 설치된 하부지지대 위에 거치된 거더의 노출강선 및 노출철근과 상기 강관파일내에 설치된 철근을 루프철근으로 상호 연결하는 거더연결부를 측면에서 단면으로 보여주는 도면이며, 도 12는 도 11의 평면을 보여주는 도면이며, 도 13은 본 발명의 거더제작대를 이용하여 양단부에 프리스트레스미도입부가 설치되도록 하여 양단부에 노출강선이 배치된 프리캐스트콘크리트판넬을 상세히 보여주는 도면이며, 도 14는 본 발명의 프리캐스트콘크리트판넬를 프리스트레스콘크리트합성거더와의 사이에 마루깔듯이 설치한 것을 보여주는 도면이다.1 is a view showing a prestressed concrete composite girder of the present invention, Figure 2 (a) (b) (c) (d) is a process for producing a prestressed concrete composite girder of the present invention using a girder production stage Figure 3 is a view showing the end pressure steel plate of the girder production table of Figure 2, Figure 4 is a view showing a movable acupressure steel sheet of the girder production table of Figure 2, Figure 5 is a wire fastening pressure of the girder production table of Figure 2 Figure 6 (a) (b) is a view showing the state in which the steel wire is fastened to the steel wire fastening pressure steel plate of the girder manufacturing table of Figure 2 in detail, Figure 7 using the prestressed concrete composite girder of the present invention 8 is a cross-sectional view showing a cross section of FIG. 7, and FIGS. 9A and 9B are installed to span the upper end of the steel plate pile of the prefabricated slab bridge of the present invention. above Figure 10 is a view showing in detail the lower support to support the girder to be installed, Figure 10 is a view showing that the concrete pour pile connection portion installed over a certain range on the upper portion of the steel pipe pile which is a pillar of the prefabricated slab bridge of the present invention and the shear connection material installed therein 11 is a girder connection portion interconnecting the exposed steel wire and exposed steel of the girder mounted on the lower support installed on the upper portion of the steel pipe pile and the reinforcing steel installed in the steel pipe pile with a loop reinforcement to install the prefabricated slab bridge of the present invention. FIG. 12 is a cross-sectional view of the side surface, and FIG. 12 is a view showing the plane of FIG. 11, and FIG. 13 is a precast non-stressed portion installed at both ends by using a girder manufacturing stand of the present invention so that exposed steel wires are disposed at both ends. Detailed view showing a concrete panel, Figure 14 is a free of the present invention A diagram illustrating that a floor rug, as arranged between the cast concrete and prestressed concrete pannelreul composite girder.

본 발명은 해안에 일정한 크기의 부두를 설치하기 위하여 잔교를 설치하거나 또는 하천을 복개하기 위한 복개교량의 설치시 적용하기 위한 것으로서, 프리스트레스를 선별적으로 도입하도록 설치된 거더제작대(30)를 이용하여 제작한 프리스트레스트콘크리트합성거더(10)를 이용하여 기둥으로 설치된 강관파일(81) 위에 거치하고, 상기 강관파일(81) 위에 거치된 프리스트레스트콘크리트합성거더(10)들과 강 관파일(81) 내에 설치된 철근(101, 102, 103)을 상호 연결한 지점연결부(120)를 설치하고, 상기 거더제작대(30)를 이용하여 양단의 일정부분에 프리스트레스가 도입되지 않은 부분(25)을 설치하여 제작한 프리캐스트콘크리트판넬(121)을 상기 프리스트레스트콘크리트합성거더(10) 위에 마루깔듯이 설치하고, 그 위에 슬래브철근을 배근하고, 상기 지점연결부(120)와 프리캐스트콘크리트판넬(121) 위에 콘크리트를 타설하여 설치한 조립식슬래브교량(80)에 관한 것이다.The present invention is to be applied at the time of installing the remnant bridge to install a pier of a certain size on the shore or the installation of the open bridge to cover the river, by using the girder manufacturing platform 30 installed to selectively introduce the prestress The prestressed concrete composite girders (10) and the steel pipe piles (81) mounted on the steel pipe pile (81) installed as a column using the prepared prestressed concrete composite girder (10) Install the point connecting portion 120 interconnecting the reinforcing bars (101, 102, 103) installed in the inside, and by using the girder fabrication table 30 to install a portion 25, the pre-stress is not introduced into a predetermined portion of both ends The fabricated precast concrete panel 121 is installed on the prestressed concrete composite girder 10 as a floor, and the slab reinforcement is disposed thereon, and the point connection part ( 120) and the prefabricated slab bridge (80) installed by placing concrete on the precast concrete panel (121).

즉, 지반(31)에 격자식으로 다수개 설치된 강관파일(81)의 상단에 하부지지부(90)가 거치되도록 하고, 상기 강관파일(81) 내의 하부에 내부받침판(83)을 내부면과 밀착되게 설치한 콘크리트타설파일연결부(110)를 설치하고, 상기 콘크리트타설파일연결부(110)의 강관파일(81)내에 다수개 수직철근(101)을 설치하고, 상기 하부지지대(90) 위에 프리스트레스콘크리트합성거더(10)를 네방향 또는 세방향 또는 두방향으로 각각 설치하고, 상기 다양한 방향에 설치된 프리스트레스트콘크리트합성거더(10)의 양단에 노출된 노출강선(12) 및 노출철근(14)과 수직철근(101)을 루프철근(102)으로 결속하면서 상기 루프철근(102)에 방사상으로 방사철근(103)을 설치한 거더연결부(100)를 포함한 지점연결부(120)를 설치하고, 상기 프리스트레스트콘크리트합성거더(10) 위에 양단에 프리스트레스미도입부(25)를 설치한 프리캐스트콘크리트판넬(121)을 마루깔듯이 밀착하여 설치한 다음, 상기 지점연결부(120)와 프리캐스트콘크리트판넬(121) 위에 콘크리트를 타설경화시켜 슬래브를 설치한 조립식슬래브교량(80)이다.That is, the lower support portion 90 is mounted on the upper end of the steel pipe pile 81 installed in a plurality of lattice type on the ground 31, the inner support plate 83 in close contact with the inner surface in the lower portion of the steel pipe pile 81. The concrete placing pile connecting portion 110 is installed to be installed, a plurality of vertical reinforcement 101 is installed in the steel pipe pile 81 of the concrete placing pile connecting portion 110, and the prestressed concrete composite on the lower support 90 The girders 10 are installed in four directions, three directions, or two directions, respectively, and exposed steel wires 12 and exposed steel bars 14 and vertical reinforcing bars exposed at both ends of the prestressed concrete composite girder 10 installed in the various directions. While binding the 101 to the loop reinforcement 102, and install the point connection portion 120 including the girder connecting portion 100 in which the radial reinforcement 103 is radially installed on the loop reinforcement 102, the prestressed concrete composite It is free at both ends on girder (10) The precast concrete panel 121 with the tresmi introduction part 25 is installed in close contact with the floor, and the concrete is poured on the point connection part 120 and the precast concrete panel 121 to install the slab. It is a prefabricated slab bridge (80).

먼저 본 발명의 교량에 사용되는 거더(10)에 관하여 설명하면 다음과 같다.First, the girder 10 used in the bridge of the present invention will be described.

상기 프리스트레스트콘크리트합성거더(10)는 거더의 전단면에 일정한 간격을 두고 설치된 강선(11)을 설치하고, 상기 강선을 이용하여 거더 양단의 일정부분에는 프리스트레스가 도입되지 않은 프리스트레스미도입부(25)를, 그 이외의 부분에는 프리스트레스가 도입된 프리스트레스도입부(20)를 설치하고, 상기 양단에는 일정길이 노출된 노출강선(12)과 노출철근(14)이 설치되도록 콘크리트를 타설하여 제작한 것이 도 1의 거더로서, 일명 SPC거더로 명명된다.The prestressed concrete composite girder 10 is provided with a steel wire (11) provided at regular intervals on the front end surface of the girder, pre-stressed non-introduction portion 25 is not introduced into the predetermined portion of both ends of the girder using the steel wire To the other parts, the prestress is introduced to the pre-stress introduction portion 20 is introduced, and both ends of the concrete to install the exposed steel wire 12 and the exposed reinforcing bars (14) to a certain length is manufactured As girder of, it is named as SPC girder.

상기 거더의 상부에 다수개의 전단연결재를 설치하여 추후에 타설되는 슬래브콘크리트와 일체화되도록 한다. By installing a plurality of shear connector on the top of the girder to be integrated with the slab concrete that is later poured.

상기와 같이 H형강재등의 강재를 사용하지 않고, 강선(11)만으로 거더의 전단면에 일정한 간격을 두고 골고루 배치하고, 상기 골고루 배치된 강선에 프리스트레스인 긴장력을 도입할 때, 거더 양단의 일정부분에는 프리스트레스가 도입되지 않도록 하고, 그 외의 전부분에는 프리스트레스가 도입되도록 하면서 양단부에는 강선을 일정길이 노출되도록 제작하기 위하여 도 2 내지 도 6과 같은 거더제작대(30)를 이용하여 제작하게 된다.As described above, without using steel such as H-shaped steel, evenly arranged at regular intervals on the shear surface of the girder with only the steel wire 11, and when the prestressed tension force is introduced into the evenly arranged steel wire, In order to prevent the pre-stress is introduced into the part, and the other part is introduced to the pre-stress, the girder manufacturing table 30 as shown in FIGS.

또한, 본 발명의 거더제작대를 이용하여 거더를 제작할 때, 강선(11)을 상기와 같은 방법으로 배치한 다양한 형태, 즉 일반적으로 사용하고 있는 형태의 거더뿐만아니라 거더가 사용되는 장소의 특징을 살릴 수 있는 특정한 형태의 거더를 제작할 수 있으며, 동시에 상기 거더제작대를 이용하여 거더의 부위별로 선택적으로 긴장력의 크기를 조절하여 도입하던지 또는 특정의 위치에만 선택적으로 긴장력을 도입할 수 있으며, 다수개 배치된 강선에 각기 다른 크기의 긴장력을 차별적으로 도입할 수 있도록 한 것이다.In addition, when manufacturing the girder by using the girder manufacturing table of the present invention, the girder of various forms in which the steel wire 11 is arranged in the above manner, that is, the form in which the girder is generally used, as well as the characteristics of the girder is used. It is possible to produce a specific type of girders that can be saved, and at the same time, by using the girder manufacturing platform, the tension can be selectively adjusted for each part of the girder, or the tension can be selectively introduced only at a specific position. Differently sized tensions can be introduced differentially into the placed steel wires.

상기 거더제작대(30)를 이용하여 거더(10)를 제작하는 과정을 도 2를 참고로 하여 상세히 설명하면,The process of manufacturing the girder 10 using the girder production table 30 will be described in detail with reference to FIG. 2.

지반(31) 위에 일정한 간격을 두고 지지대(40)를 마주보게 설치하고, 상기 지지대(40)의 수직지지부(41)에 관통공(43)을 다수개 설치하면서 상기 관통공(43)내에 관(44)을 도 (a)와 같이 설치한다.The support base 40 is installed to face the ground 31 at regular intervals, and a plurality of through holes 43 are installed in the vertical support part 41 of the support 40 while the pipes in the through holes 43 44) is installed as shown in FIG.

상기 과정이 완료되면, 상기 수직지지부(41)의 양면에 관통공(51)이 다수개 형성된 단부지압강판(50)을 설치하고,When the process is completed, install the end pressure-bearing steel plate 50 is formed with a plurality of through holes 51 on both sides of the vertical support portion 41,

상기 수직지지부(41)의 외측에 다수개의 관통공(61)이 형성된 가동지압강판(60)을 설치하고,A movable acupressure steel plate 60 having a plurality of through holes 61 formed outside the vertical support part 41 is provided.

상기 수직지지부(41)의 내측에 다수개의 관통공(71)과 강선체결공(72)이 동시에 형성된 강선체결지압강판(70)을 설치하고,On the inner side of the vertical support portion 41 is provided with a steel wire fastening pressure steel plate 70 in which a plurality of through holes 71 and steel wire fastening holes 72 are formed at the same time,

상기 수직지지부(41)에 형성된 관통공(43)을 관통하여 내외면에 각각 설치된 가동지압강판(60)과 강선체결지압강판(70)의 관통공(61,71)을 관통하여 강봉(32)으로 상호연결하여 너트(36)로 각각 고정설치한 도 (b)를 설치한다.Steel bars 32 through the through holes 43 formed in the vertical support portion 41 and through the through-holes 61 and 71 of the movable pressure-bearing steel plate 60 and the steel wire fastening pressure-steel plate 70 respectively installed on the inner and outer surfaces thereof. To install Figures (b) fixed to each of the nuts (36).

이어서, 도 (c)와 같이, 상기 강선체결지압강판(70)에 형성된 다수개의 강선체결공(72)에 강선(11)의 단부가 체결되도록 한다.Subsequently, as shown in (c), the ends of the steel wire 11 is fastened to a plurality of steel wire fastening holes 72 formed in the steel wire fastening pressure steel plate 70.

상기 과정이 완료되면, 상기 수직지지부(41)와 가동지압강판(60)과의 사이에 유압잭(34)을 설치한 거더제작대(30)를 설치하고,When the process is completed, the girder manufacturing table 30 is installed between the vertical support portion 41 and the movable acupressure steel sheet 60, the hydraulic jack 34 is installed,

상기 설치된 강선에 거더의 양단부에서 일정거리까지 응고시간지연접착수지 재를 도포한 응고시간지연접착수지재도포부(21)를 형성하고,Forming a solidification time delay adhesive resin coating portion 21 coated with the solidification time delay adhesive resin material to a predetermined distance from both ends of the girder on the installed steel wire,

상기 유압잭(34)에 스트로크를 발생시켜 가동지압강판(60)을 외측으로 밀면 강봉(32)에 의하여 상호 연결된 강선체결지압강판(70)이 지지대(40)쪽으로 이동하게되어, 상기 강선체결지압강판(70)의 강선체결공(72)에 체결연결된 강선(21)도 당겨지게되어 강선에 긴장력이 도입되도록 하면서 체결너트(35)로 강봉(32)과 수직지지대의 외측면에 매입된 단부지압강판(50)을 체결고정하고,When the movable jack steel plate 60 is pushed outward by generating a stroke in the hydraulic jack 34, the steel wire fastening pressure steel plate 70 interconnected by the steel bar 32 moves toward the support 40, and the steel wire fastening pressure steel sheet The steel wire 21 fastened and connected to the steel wire fastening hole 72 of the 70 is also pulled so that the tension force is introduced into the steel wire while the end pressure plate is embedded in the outer surface of the steel rod 32 and the vertical support with the fastening nut 35. Fasten and secure the (50),

상기 양측에 설치된 지지대(40)와의 사이에 설치된 긴장력이 도입된 상태의 다수개의 강선(11)을 포함하면서 다수개의 거더를 제작할 수 있는 콘크리트를 타설양생하고,Placing concrete to manufacture a plurality of girders, including a plurality of steel wires 11 in a state where a tension force installed between the support 40 installed on both sides is introduced,

상기 콘크리트의 양생이 완료된 후에 거더와 거더 사이에 설치된 강선(11)을 절단하되, 노출강선(12)이 설치되도록 하고, 동시에 거더를 형성하도록 배근된 철근을 거더의 양단부에 일정길이 노출되도록 노출철근(14)을 설치하고,After the curing of the concrete is completed, the steel wire 11 installed between the girder and the girder is cut, so that the exposed steel wire 12 is installed, and at the same time, the reinforcing bars are exposed to both ends of the girder to form a girder. Install 14,

상기 강선체결지압강판(70)에 설치된 강선체결공(72)에 체결된 강선(11)을 이탈시키는 도 (d)의 과정을 거쳐, 원하는 부분에만 선별적으로 프리스트레스가 도입된 도 1의 프리스트레스트콘크리트합성거더(10)를 다수개 동시에 제작한 것이다.The prestress of FIG. 1 in which prestress is selectively introduced only to a desired portion through the process of FIG. D, which deviates from the steel wire 11 fastened to the steel fastening hole 72 installed in the steel wire fastening pressure plate 70. The concrete composite girder 10 will be manufactured at the same time.

상기와 같이 거더(10)의 원하는 부분에만 프리스트레스가 도입되도록 하기 위하여 에폭시와 같은 응고시간지연접착수지재를 강선의 표면에 일정한 두께로 도포표면이 거칠게 도포하는 이유는 상기 거더(10)의 양단에서 거더내의 일정길이에 걸쳐 프리스트레스가 도입되지 않도록 하기 위하여 상기 강선의 일정범위에 걸쳐 응고시간지연접착수지재를 도포한 다음, 상기 접착수지재가 경화되기 전에 강선(11)을 긴장한 상태에서, 강선(11)을 포함하는 콘크리트를 타설경화시키고, 강선을 강선체결공(72)으로부터 이탈시켜 릴리스하면, 응고시간지연접착수지재가 도포된 강선에는 콘크리트가 접착되지 않아 강선에 도입된 프리스트레스가 도입되지 않는 반면에, 상기 응고시간지연접착수지재가 도포되지 않은 중앙부의 강선은 콘크리트와 접착되어 강선에 도입된 프리스트레스가 콘크리트에 전달되어 프리스트레스가 도입되도록 한 것이다.The reason why the coating surface is roughly coated on the surface of the steel wire with a coagulation time delay adhesive resin material such as epoxy so that prestress is introduced only to a desired portion of the girder 10 as described above is at both ends of the girder 10. In order to prevent the prestress from being introduced over a certain length in the girder, a solidification time delay adhesive resin material is applied over a certain range of the steel wire, and then the steel wire 11 is tensioned before the adhesive resin material is cured. When the concrete containing the pour and the steel wire is released by releasing the steel wire from the steel fastening hole 72, the concrete is not bonded to the steel wire to which the solidification time delay adhesive resin material is applied, so that the prestress introduced into the steel wire is not introduced. The steel wire in the center of the solidification time delay adhesive resin is not applied to the steel wire The introduced prestress is transferred to the concrete so that the prestress is introduced.

한편, 상기 강선에 도포된 응고시간지연접착수지재의 경화시간을 24 ~ 36시간이 경과된 후에 경화가 진행되도록 한 것이므로 콘크리트가 타설되어 경화되고, 콘크리트에 프리스트레스가 도입된 후에, 강선에 도포된 응고시간지연접착수지재가 경화되어 콘크리트와 일체화되어 프리스트레스가 도입되지 않도록 한 것이며, 강선에 도포된 표면을 거칠게 일정두께로 한 것은 상기 일정시간 경과되어 접착수지재가 경화되어 콘크리트와 일체화될때 표면의 거친면에 의하여 접착력이 강화되어 일체거동하도록 하기 위한 것이다.On the other hand, since the curing time of the coagulation time delayed adhesive resin applied to the steel wire is to proceed after 24 to 36 hours, the concrete is poured and cured, after the prestress is introduced into the concrete, the solidification applied to the steel wire The time-delay adhesive resin is hardened and integrated with concrete so that prestress is not introduced. The surface coated on the steel wire is roughened to a certain thickness when the adhesive resin is hardened and integrated with concrete. By the adhesive force is to strengthen the integral behavior.

상기 강선(11)을 릴리스하여 응고시간지연접착수지재가 경화되기 전에 겔상태로 일정한 시간동안 있도록 하여 강선을 릴리스하여 강선이 줄어들때에도 상기 강선외부에 도포된 겔상태에 응력이 전달되지 않도록 하기 위함인 것이다. To release the steel wire 11 so that the solidification time delay adhesive resin material is in a gel state for a certain period of time before being cured to release the steel wire so that stress is not transmitted to the gel state applied to the outside of the steel wire even when the steel wire is reduced. will be.

결국 시간차에 의하여 프리스트레스를 원하는 부분인 정모멘트가 작용하는 거더의 중앙에 도입되도록 하면서 양단부에도 접착수지재가 일정시간이 경과후 경화되어 콘크리트와 접착되어 일체거동하도록 한 것이다.As a result, the adhesive resin material is cured after a certain period of time to be integrated into the concrete at both ends of the girder while the positive moment, which is a desired part of the prestress, is caused by the time difference.

상기 응고시간지연접착수지재인 에폭시등이 도포된 도포부(21)는 거더길이(L)의 0.1L ~ 0.25L의 범위에 걸쳐 설치한 것이다.The coating unit 21 coated with epoxy, which is the solidification time delay adhesive resin material, is installed over the range of 0.1L to 0.25L of the girder length L.

상기와 같이 응고시간지연접착수지재를 도포하여 프리스트레스를 도입하지 않은 부분을 거더의 양단에 설치하도록 한 것은 향후에 설명되는 본 발명의 조립식슬래브교(80) 시공시 기둥인 강관파일(81)위에 거치된 하부지지대(90) 위에서 다양한 방향으로 프리스트레스트콘크리트합성거더(10)를 거치하면서 상기 거더(10)의 양단에 노출된 노출강선(12) 및 노출철근(14)과, 강관파일(81)에 설치된 수직철근(101)을 루프철근(102)으로 상호 결합하고, 상기 루프철근(102)에 방사형으로 설치된 방사철근(103)을 결속한 후에 콘크리트를 타설경화시켜 설치한 거더연결부(100)와, 강관파일(81)의 콘크리트타설파일연결부(110)가 일체화연결된 지점연결부(120)가 일체거동하므로서 상기 강관단면력이 상기 거더연결부의 전단연결력과 같아 지도록 한다.As described above, the application of the coagulation time delay adhesive resin material to install the portion without introducing prestress on both ends of the girder is on the steel pipe pile 81 which is a pillar when constructing the prefabricated slab bridge 80 of the present invention. The exposed steel wire 12 and the exposed reinforcing bars 14 and steel pipe piles 81 exposed to both ends of the girder 10 while passing the prestressed concrete composite girder 10 in various directions on the mounted lower support 90. The girder connection portion 100 and the vertical reinforcement 101 installed in the roof reinforcement 102 and mutually coupled, and after binding the radial reinforcement 103 installed radially to the roof reinforcement 102 and pour hardening concrete As the concrete connection pile connection part 110 of the steel pipe pile 81 is integrally connected to the point connection part 120, the steel pipe section force is equal to the shear connection force of the girder connection part.

또한, 상기 지점연결부(120)에 발생된 부모멘트에 의하여 부재에는 압축응력이 발생되어 상기 거더의 프리스트레스미도입부(25)에 전달될때, 상기 거더(10)의 양단에는 프리스트레스가 도입되지 않으므로 그만큼 지점연결부에 발생되는 압축응력이 감소되도록 하여, 결국 기존교량의 지점연결부에서 발생되는 압축응력의 크기보다 획기적으로 감소시키도록 하여 연결부의 파괴등을 방지하여 교량의 지점연결부의 안정성이 보다 크게 확보될 수 있도록 한 것이다.In addition, when the compressive stress is generated in the member due to the parent moment generated in the point connecting portion 120 is transmitted to the pre-stress non-introduction portion 25 of the girder, the pre-stress is not introduced to both ends of the girder 10, so the point By reducing the compressive stress generated in the connection part, and eventually reducing the magnitude of the compressive stress generated in the point connection part of the existing bridge to prevent the breakage of the connection portion, the stability of the point connection portion of the bridge can be secured more It would be.

상기 방법에 의하여 제작된 거더는 전단면에 걸쳐 일정한 간격을 두고 골고루 설치된 다수개의 강선에 의하여 전단면이 프리스트레스가 도입된 상태이므로 거더의 전단면이 유효한 단면인 반면에,The girder produced by the above method is a shear cross-section of the girder because the shear surface is a state in which the pre-stress is introduced by a plurality of steel wires evenly spaced at regular intervals across the shear surface,

기존의 콘크리트거더는 상부의 압축부만 유효한 단면이 되므로, 활용성면에서 기존 거더의 활용범위 보다, 본 발명 거더의 활용범위를 보다 광범위하게 사용할 수 있으며, 거더의 크기를 줄일 수 있는 장점이 있다.Existing concrete girders are effective cross-section only the upper compression section, in terms of usability than the range of the existing girder, can be used more widely the scope of the present invention girder, there is an advantage to reduce the size of the girder.

또한, 상기 거더의 단부에 프리스트레스미도입부(25)와 거더연결부(100)와 콘크리트타설파일연결부(110)를 상호 연결한 지점연결부(120)에서 발생되는 모멘트와 전단력을 감소시켜 지점연결부(120)가 파괴되는 것을 방지하므로서 교량의 내하력을 증강시키도록 한 것이다.In addition, the point connection portion 120 by reducing the moment and shear force generated in the point connection portion 120 interconnecting the pre-stressed non-introduction portion 25, the girder connection portion 100 and the concrete placing pile connection portion 110 at the end of the girder It is to increase the load capacity of the bridge while preventing the breakage.

상기 거더제작대(30)의 각각의 구성을 도면에 의하여 설명하면 다음과 같다.Referring to the drawings, each configuration of the girder production stage 30 is as follows.

상기 지지대(40)는 철근콘크리트로 수직지지부(41)와 수평지지부(42)의 ㄴ자형으로 설치하되, 수평지지부(42)를 지반(31)내에 매입설치하되, 상기 수평지지부(42)가 내측으로 설치되도록 한 것이 도 (a)이다.The support 40 is installed in the shape of the vertical support portion 41 and the horizontal support portion 42 of the reinforced concrete, the horizontal support portion 42 is embedded in the ground 31, the horizontal support portion 42 is installed inside It is shown in Figure (a) to be installed.

상기 수평지지부(42)를 내측으로 일정길이로 설치하면, 수평지지부(42)의 측면에서 유압잭(34)에 의하여 발생되는 스트로크에 의하여 수직지지부(41)가 내측으로 전도되려는 힘을 상기 스트로크힘의 작용방향과 반대방향으로 일정길이 설치되는 수평지지부(42)의 지지력에 의한 힘보다 작게 하여 지지대(40)가 안전하게 지지되어 거더를 제작할 수 있도록 한 것이다.When the horizontal support portion 42 is installed to a predetermined length inwardly, the force that the vertical support portion 41 is to be transferred inwards by the stroke generated by the hydraulic jack 34 on the side of the horizontal support portion 42 is applied to the inner side of the stroke force. The support 40 is safely supported by a force less than the force of the horizontal support 42 which is installed at a predetermined length in the direction opposite to the direction of action, so that the girder can be manufactured.

상기 수직지지부(41)에는 다수개의 관통공(43)이 형성되고, 상기 관통공(43)내에는 관(44)을 삽입한 것이다.A plurality of through holes 43 are formed in the vertical support part 41, and the tube 44 is inserted into the through holes 43.

상기 관통공(43)내에 관(44)을 삽입한 이유는 관(44)내에 향후에 설치되는 강봉(32)이 유압잭(34)에 의하여 관(44)내에서 이동할 때 관통공(43)내에서 원활하 게 이동할 수 있도록 안내관의 역할을 하도록 하기 위함이다.The reason why the pipe 44 is inserted into the through hole 43 is that the steel bar 32 which is installed in the pipe 44 in the future is moved in the pipe 44 by the hydraulic jack 34. This is to act as a guide to move smoothly in.

도 (b)는 수직지지부(41)의 내외면에 도 3의 단부지압강판(50)이 매입된 상태를 보여주는 것이다.FIG. (B) shows a state in which the end pressure bearing steel plate 50 of FIG. 3 is embedded in the inner and outer surfaces of the vertical support part 41.

상기 단부지압강판(50)은 직각사각형의 강판으로 다수개의 관통공(51)이 형성된 것이다.The end pressure-bearing steel sheet 50 is a rectangular steel sheet formed with a plurality of through holes 51.

상기 관통공(51)은 수직지지부(41)의 관통구(43)에 일치되게 설치되는 것이다.The through hole 51 is installed to coincide with the through hole 43 of the vertical support part 41.

상기와 같이 단부지압강판(50)의 관통공(51)과 수직지지부(41)의 관통공(43)을 일치시켜 설치하고, 양단부에 나사산(33)이 형성된 강봉(32)을 관통설치한다.As described above, the through hole 51 of the end pressure-bearing steel plate 50 and the through hole 43 of the vertical support part 41 are coincident with each other, and the steel rods 32 formed with the thread 33 are provided at both ends.

상기 단부지압강판(50)을 수직지지부(41)의 내외면에 매입설치하는 이유는 유압잭의 스트로크에 의하여 강선에 긴장력이 도입될때 수직지지부의 단면을 보강하기 위하여 설치하는 것이다. The reason why the end pressure bearing steel plate 50 is embedded in the inner and outer surfaces of the vertical support part 41 is to reinforce the cross section of the vertical support part when a tension force is introduced into the steel wire by the stroke of the hydraulic jack.

또한, 수직지지부(41)의 외측에서 일정거리 떨어져 설치되는 것으로서, 도 4의 직사각형의 강판으로 다수개의 관통공(61)이 설치된 가동지압강판(60)이다. In addition, it is provided a predetermined distance away from the outside of the vertical support portion 41, a rectangular steel sheet of Figure 4 is a movable acupressure steel sheet 60 provided with a plurality of through-holes 61.

상기 관통공(61)은 상기 단부지압강판(50)의 관통공(51)과 수직지지부(41)의 관통공(43)이 하나의 강봉(32)으로 상호 관통 체결되도록 하기 위한 것이다.The through hole 61 is for allowing the through hole 51 of the end pressure-bearing steel plate 50 and the through hole 43 of the vertical support part 41 to be penetrated through each other by one steel bar 32.

상기 가동지압강판(60)은 향후 유압잭(34)에 의하여 뒤쪽으로 이동하여야 하므로 유압잭의 스트로크 힘을 전부 받아야 하므로 강판의 강성이 높아야 한다.Since the movable acupressure steel sheet 60 should be moved backward by the hydraulic jack 34 in the future, the hydraulic jack should receive all of the stroke force, so the rigidity of the steel sheet should be high.

도 5의 강선체결지압강판(40)은 수직지지부(41)의 내측에서 일정거리 간격을 두고 설치되는 것으로서, 직사각형의 강판에 다수개의 관통공(71)과 강선체결공(72)이 동시에 형성된 것이다.The steel fastening bearing steel plate 40 of FIG. 5 is installed at a predetermined distance from the inside of the vertical support part 41, and a plurality of through holes 71 and the steel wire fastening holes 72 are simultaneously formed in a rectangular steel plate. .

상기 관통공(71)은 수직지지부(41)의 관통공(43)과 상기 수직지지부의 내외면에 매입된 단부지압강판(50)의 관통공(51)과 가동지압강판(60)의 관통공(61)을 모두 관통하여 강봉을 설치하기 위한 것이다.The through hole 71 is a through hole 43 of the vertical support part 41 and a through hole 51 of the end pressure bearing steel plate 50 embedded in the inner and outer surfaces of the vertical support part, and a through hole of the movable pressure steel plate 60. It is for installing a steel bar through all 61.

상기 강봉(32)이 관통공(61,71)에 삽입된 상기 가동지압강판(60)과 강선체결지압강판(70)과 강봉(32)을 너트(36)에 의하여 각각 체결고정한다. The steel bar 32 is fastened and fastened to the movable acupressure steel plate 60, the steel wire fastening pressure steel plate 70, and the steel bar 32 inserted into the through holes 61 and 71 by nuts 36.

상기와 같이 관통공(61,71)에 삽입된 각각의 강판(60,70)을 너트(36)로 고정체결하여야 유압잭(34)에 의하여 가동지압강판(60)이 외측으로 밀리면 강선체결지압강판(70)도 동시에 상기 가동지압강판이 이동한 동일한 양만큼 이동하도록 하기 위함이다. As described above, each steel plate 60 and 70 inserted into the through holes 61 and 71 must be fastened by a nut 36. When the movable pressure steel plate 60 is pushed outward by the hydraulic jack 34, the steel wire fastening pressure plate At the same time as 70, the movable acupressure steel sheet is moved by the same amount moved.

도 6의 (a)는 상기 강선체결공(72)을 상세히 보여주면서 동시에 강선(11)의 단부가 체결고정된 것을 보여주는 도면이다.6 (a) shows the wire fastening hole 72 in detail and at the same time shows that the end of the steel wire 11 is fastened and fastened.

상기 강선체결공(72)은 열쇠구멍의 형상으로, 상부는 원형구멍(73)이 형성되고 이와 접하여 하부에는 상기 원형구멍(73)보다 폭은 작으나 길이는 길게 형성된 수직구멍(74)이 형성된 것이다. The steel wire fastening hole 72 is in the shape of a key hole, the upper portion is formed with a circular hole 73 is in contact with the lower portion is formed with a vertical hole 74 formed in a smaller width than the circular hole 73 but longer in length. .

상기와 같이 형성된 강선체결구멍(72)에 도 (b)와 같이 강선(11)의 단부를 강선의 직경보다 크게 설치한 확대두부(24)를 상기 원형구멍(73)내에 밀어넣은 다음, 상기 원형구멍(73)의 하부에 연접하여 설치된 수직구멍(74)으로 밀어내리면 도 (a)와 같이 수직구멍(74)에 강선의 확대두부(24)가 걸쳐져 체결되는 것이다.The enlarged head 24 having the end portion of the steel wire 11 larger than the diameter of the steel wire is pushed into the circular hole 73 in the steel wire fastening hole 72 formed as described above, as shown in FIG. When pushed down to the vertical hole 74 in contact with the lower portion of the hole 73, the enlarged head 24 of the steel wire is fastened to the vertical hole 74 as shown in (a).

상기와 같이 체결된 강선(11)을 해체할때에는 반대로 수직구멍(74)에 체결된 강선(11)을 위로 올리면 수직구멍(74)보다 직경이 넓은 원형구멍(73)으로 강선의 확대두부(24)가 올라오면서 원형구멍(73)을 통하여 외부로 빠지게 되는 것이다.When dismantling the steel wire 11 fastened as described above, on the contrary, when the steel wire 11 fastened to the vertical hole 74 is lifted up, the enlarged head 24 of the steel wire is formed into a circular hole 73 having a diameter larger than that of the vertical hole 74. As you come up is to fall out through the circular hole (73).

이렇게 강선(11)의 단부를 강선체결지압강판(70)의 강선체결공(72)에 설치하고 강선을 체결하도록 한 것은 수직지지부(41)와 가동지압강판(60)과의 사이에 설치된 유압잭(34)에 스트로크를 발생시키면 가동지압강판(60)이 외측으로 밀리면서 강봉(32)에 의하여 일체 연결된 강선체결지압강판(70)이 수직지지부(41) 쪽으로 움직이게된다. In this way, the end of the steel wire 11 is installed in the steel wire fastening hole 72 of the steel wire fastening pressure plate (70) to fasten the steel wire is a hydraulic jack (between the vertical support portion 41 and the movable pressure steel plate 60) When the stroke is generated at 34, the movable acupressure steel plate 60 is pushed outward so that the steel wire fastening pressure steel plate 70 which is integrally connected by the steel bar 32 is moved toward the vertical support part 41.

이때 상기 강선체결지압강판(70)에 형성된 강선체결공(72)에 체결된 강선(11)도 동시에 수직지지부(41) 쪽으로 이동하면 강선(11)에 긴장력이 도입되게되는 것이다.At this time, when the wire 11 fastened to the wire fastening hole 72 formed in the wire fastening pressure plate 70 also moves toward the vertical support portion 41, the tension force is introduced into the steel wire 11.

상기와 같이 강선(11)에 긴장력이 도입된 상태에서 원하는 부분에만 프리스트레스를 도입하도록 응고시간지연접착수지재를 도포한 다음, 콘크리트를 타설양생하여 거더의 제작이 완료된 후에, 제작이 완료된 거더를 이동하기 위하여 상기 강선체결지압강판(70)에 체결된 강선(11)을 별도의 해체장비 없이 망치로 수직구멍(74)에 거치된 강선(11)을 위로 쳐 올리기만 하면 원형구멍(73)으로 이동된 강선의 확대두부(24)가 원형구멍(73)을 통하여 외부로 간단히 이탈하도록 한 것이다.After applying the coagulation time delay adhesive resin material to introduce the pre-stress only to the desired portion in the state where the tension force is introduced to the steel wire 11 as described above, after casting the concrete to finish the manufacture of the girder, the girder is completed to move In order to move the steel wire 11 fastened to the steel wire fastening pressure plate 70 by lifting the steel wire 11 mounted on the vertical hole 74 with a hammer without a separate dismantling equipment, it moves to the circular hole 73. Expanded head 24 of the steel wire is to be easily separated to the outside through the circular hole (73).

즉, 강선(11)의 체결과 해체를 용이하게 하기 위하여 강선체결공(72)을 열쇠구멍과 같이 설치한 것이다.That is, in order to facilitate the fastening and dismantling of the steel wire 11, the steel wire fastening hole 72 is provided as a key hole.

상기 지반(31)에 설치되는 지지대(40)가 유압잭(34)의 스트로크에 저항하면서 안전 하게 거더를 제작할 수 있도록 하기 위한 지지대(40)의 설치조건중에서 전도되지 않고 안전하게 지지될 수 있도록 P x H1〈W x L1가 되어야 한다.P x H1 so that the support (40) installed on the ground (31) can be safely supported without falling in the installation conditions of the support (40) to safely manufacture the girder while resisting the stroke of the hydraulic jack (34). <W x L1.

즉, 지지대(40)의 수평지지부(42)를 내측으로 일정길이설치하면, 수직지지부(41)의 외측면의 일정높이(H1)에서 유압잭(14)에 의하여 발생되는 스트로크힘(P)에 의하여 수직지지부(41)가 내측으로 전도되려는 힘에 대항하여 상기 스트로크힘의 작용방향과 반대방향으로 일정길이 내측으로 설치되는 수평지지부(42)의 자체 중량(W)이 작용하는 거리(L1)에 의한 힘보다 작게 하여 지지대(40)가 안전하게 지지되어 거더를 제작할 수 있도록 한 것이다.That is, when the horizontal support portion 42 of the support 40 is provided with a predetermined length inward, the stroke force P generated by the hydraulic jack 14 at a predetermined height H1 of the outer surface of the vertical support portion 41. By the distance (L1) the self-weight (W) of the horizontal support portion 42, which is installed in a predetermined length in the opposite direction to the direction of action of the stroke force against the force that the vertical support portion 41 is to be conducted inwardly Less than the force is to support the support (40) is to make the girder securely.

또한, 상기 지반(31)에 설치되는 지지대(40)가 유압잭(34)의 스트로크에 저항하면서 안전하게 거더를 제작할 수 있도록 하기 위한 지지대(40)의 설치조건중에서 지지대가 활동, 즉 미끄러지지 않도록 하기 위하여 P〈W x μ+C 가 되어야 한다.In addition, in order to prevent the support from being active, that is, slipping, in the installation conditions of the support 40 to allow the support 40 installed on the ground 31 to safely manufacture the girder while resisting the stroke of the hydraulic jack 34. It should be <W x μ + C.

즉, 상기 지지대(40)는 스트로크힘(P)보다 수평지지부(42)의 자체중량(W)과 저면마찰계수(μ)를 곱한 값에 수동토압(C)을 더한 힘이 더 크도록 하여 활동 즉, 지지대(40)가 미끄러지지 않도록 하여야 한다.That is, the support 40 acts to increase the force by adding the manual earth pressure (C) to the value multiplied by the self-weight (W) of the horizontal support portion 42 and the bottom friction coefficient (μ) than the stroke force (P). That is, the support 40 should not slip.

또한, 상기 지반(31)에 설치되는 지지대(40)가 유압잭(34)의 스트로크에 저항하면서 안전하게 거더를 제작할 수 있도록 하기 위한 지지대(40)의 설치조건중에서 지지대(40)의 수직지지부(41)와 수평지지부(42)가 만나는 부분의 단면파괴를 방지하여야 하므로 이를 위하여는 P x h2 /Z〈fa 가 되어야 한다.In addition, the vertical support portion 41 of the support 40 in the installation conditions of the support 40 to enable the support 40 to be installed on the ground 31 to safely manufacture the girder while resisting the stroke of the hydraulic jack 34. And cross-sectional destruction of the portion where the horizontal support portion 42 meets, for this purpose should be P x h2 / Z <fa.

즉, 수평지지부(42)와 수직지지부(41)가 만나는 부분의 단면파괴를 방지하기 위하여 콘크리트허용응력(fa)보다 스트로크힘(P)과 수직지지부 작용거리(h2)를 곱한 값을 수직지지부(41)의 단면계수(Z)로 나눈 값의 크기가 작아야 단면이 파괴되지 않아 안전하게 유지될 수 있는 것이다.That is, in order to prevent cross-sectional destruction of the portion where the horizontal support portion 42 and the vertical support portion 41 meet, the value of the vertical support portion (multiplied by the stroke force P and the vertical support portion working distance h2 than the concrete allowable stress fa). The smaller the value of the value divided by the cross section coefficient (Z) of 41), the cross section is not destroyed so that it can be safely maintained.

결국 상기 지지대(40) 안전조건은 지지대(40)가 전도되지 않고, 활동이 되지 않으며, 동시에 단면파괴가 되지 않도록 설치되어야 하는 것이다. As a result, the safety condition of the support 40 is that the support 40 is not to be inverted, is inactive, and at the same time, it is to be installed so as not to be damaged in section.

또한, 상기 유압잭(34)에 발생된 스트로크에 의하여 강선(11)에 도입된 긴장력이 유지될 수 있도록 체결너트(35)로 강봉(32)과 수직지지대(41)의 외측면에 매입된 단부지압강판(50)을 체결하여 고정시키도록 한다.In addition, end pressure buried in the outer surface of the steel bar 32 and the vertical support 41 by the fastening nut 35 so that the tension force introduced into the steel wire 11 can be maintained by the stroke generated in the hydraulic jack 34. The steel plate 50 is fastened to be fixed.

상기와 같은 거더제작대(30)를 이용하여, 거더(10)의 전단면에 일정한 간격을 두고 설치된 강선(11)을 이용하여 긴장력을 도입할 때, 상기 거더 양측단의 일정부분에는 프리스트레스가 도입되지 않도록 하고, 그 외의 부분에는 프리스트레스가 도입되도록 하면서, 양측단부에 일정길이의 강선(11)을 거더의 단부 외부로 노출시킨 프리스트레스트콘크리트합성거더(10)를 제작한다.When the tension force is introduced by using the steel wire 11 provided at regular intervals on the front end face of the girder 10 using the girder manufacturing table 30 as described above, prestress is introduced to a predetermined portion of both ends of the girder. The prestressed concrete composite girder 10 is formed by exposing the steel wire 11 having a predetermined length to the outside of the end of the girder while the prestress is introduced into the other portion.

또한, 상기 거더제작대(30)를 이용하여 상기와 같은 동일한 방법에 의하여 양단의 일정부분에는 프리스트레스미도입부(25)를, 중앙 부분에는 프리스트레스도입부(20)를 각각 설치하고 양단에는 노출강선(12)을 설치한 프리캐스트콘크리트판넬(121)을 제작한다.In addition, by using the girder production table 30 by the same method as described above, a predetermined portion of both ends of the pre-stressed non-introduction portion 25, the central portion of the pre-stressed introduction portion 20 is provided, respectively, and both ends of the exposed steel wire 12 Manufacture the precast concrete panel 121 is installed.

또한, 상기 프리스트레스트콘크리트합성거더(10)와 프리캐스트콘크리트판넬(121)의 상부면에 다수개의 전단연결재(84)를 다수개 설치하여 추후에 타설되는 슬래브콘크리트와 접착력이 강화되어 일체거동하도록 한 것 이다.In addition, by installing a plurality of shear connecting members 84 on the upper surface of the prestressed concrete composite girder 10 and the precast concrete panel 121, the slab concrete and the adhesive force is later reinforced to strengthen the integral behavior will be.

상기 제작된 프리스트레스트콘크리트합성거더(10)와 프리캐스트콘크리트판넬(121)을 이용하여 조립식슬래브교(80)를 시공하는 방법을 도 7 내지 14를 참고로 하여 설명하면 다음과 같다.The method of constructing the prefabricated slab bridge 80 using the prepared prestressed concrete composite girder 10 and the precast concrete panel 121 will be described with reference to FIGS. 7 to 14 as follows.

일정한 면적의 하상 또는 해저의 지반(31)내에 강관파일(81)을 일정한 간격을 두고 격자로 다수개 설치한다.A plurality of steel pipe piles 81 are provided in a lattice at regular intervals in the bed 31 of the lower bed or the seabed of a predetermined area.

상기 설치된 강관파일(81)의 상부가 하부지지대(90)의 중앙에 형성된 관통공(92)의 하부에 형성된 단턱(93)의 턱에 강관파일의 상단이 거치되도록 설치한다.The upper portion of the steel pipe pile 81 is installed so that the upper end of the steel pipe pile is mounted on the jaw of the stepped jaw 93 formed in the lower portion of the through-hole 92 formed in the center of the lower support (90).

상기 강관파일(81) 내측 일정길이 떨어진 부분에 내부받침판(83)을 설치하되, 상기 내부받침판이 설치된 내면에 다수개의 전단연결재(84)가 설치된 콘크리트타설파일연결부(110)를 설정한다.The inner support plate 83 is installed on a portion of the steel pipe pile 81 at a predetermined length away from the inside of the steel pipe pile 81, and the concrete placing pile connection unit 110 is provided with a plurality of shear connecting members 84 installed on the inner surface of the steel support pile 81.

상기 강관파일 내부의 내부받침판이 설치된 부분인 콘크리트타설파일연결부(110)에 수직철근(101)을 다수개 설치하면서 상기 강관파일(81)의 외부로 노출되도록 한다.While installing a plurality of vertical reinforcement 101 in the concrete placing pile connecting portion 110, which is an internal support plate installed inside the steel pipe pile to be exposed to the outside of the steel pipe pile (81).

상기 하부지지대(90)의 상부에 2개방향 이상으로 설치된 프리스트레스트콘크리트합성거더(10)의 노출강선(12) 및 노출철근(14)과, 상기 콘크리트타설파일연결부(110)에 매입되어 강관파일(81) 상부로 노출설치된 수직철근(101)을 원형의 루프철근(102)로 상호 결속하면서, 상기 루프철근(102)에 방사상으로 방사철근(103)으로 결속한 거더연결부(100)와 상기 콘크리트타설파일연결부(110)를 포함하는 지점 연결부(120)를 설치한다.The steel pipe pile is embedded in the exposed steel wire 12 and the exposed reinforcing bar 14 of the prestressed concrete composite girder 10 installed in two or more directions on the lower support 90 and the concrete placing pile connecting part 110. (81) The girder connecting portion 100 and the concrete, which are bound to the reinforcing bars (103) radially bound to the reinforcing bars (103) radially bound to the reinforcing bars (102) while mutually binding the vertical reinforcement (101) installed at the top. The point connection unit 120 including the pour file connection unit 110 is installed.

상기 프리스트레스트콘크리트합성거더(10)의 상부에 양단에 프리스트레스미도입부(25)가 설치된 프리캐스트콘크리트판넬(121)을 마루깔듯이 다수개 밀착설치하고, 상기 프리캐스트콘크리트판넬(121)의 상부와 상기 지점연결부(120)에 콘크리트를 타설경화시켜 슬래브(82)를 설치하여 조립식슬래브교(80)를 설치한 것이 도 7과 도 8이다.The prestressed concrete composite girders 10 are installed in close contact with a plurality of precast concrete panels 121 on which both ends of the prestressed non-introduction portion 25 are installed, and the upper part of the precast concrete panels 121 and 7 and 8 install the prefabricated slab bridge 80 by installing the slab 82 by pour hardening concrete to the point connection part 120.

이하에서 상세하게 설치방법과 구성을 설명하면 다음과 같다.Hereinafter, the installation method and configuration in detail.

일정한 면적의 하상 또는 해저의 지반(31)내에 강관파일(81)을 일정한 간격을 두고 격자로 다수개 설치된 상기 강관파일(81)의 상부가 도 9의 하부지지대(90)의 관통구(92)의 하부에 형성된 단턱(93)에 거치되도록 한다.A through hole 92 of the lower support 90 of FIG. 9 is provided with an upper portion of the steel pipe pile 81 provided with a plurality of steel pipe piles 81 in a lattice at regular intervals in the ground or on the sea bed 31 of the sea bed. To be mounted on the stepped 93 formed at the bottom of the.

다음에는, 상기 강관파일(81) 내부의 일정길이 하부까지 다수개의 전단연결재(84)를 설치하면서 내부받침판(83)을 강관파일 내부면에 접하게 설치하여 콘크리트타설파일연결부(110)가 도 10과 같이 설치되도록 한다. Next, while installing a plurality of shear connection member 84 to a predetermined length lower portion inside the steel pipe pile 81, the inner support plate 83 is installed in contact with the inner surface of the steel pipe pile concrete casting pile connecting portion 110 is shown in FIG. To be installed together.

상기 콘크리트타설파일연결부(110)내에 수직철근(101)을 설치하면서 강관파일의 상부 외부로 노출되도록 설치한다.While installing the vertical reinforcement 101 in the concrete placing pile connecting portion 110 is installed to be exposed to the outside of the upper portion of the steel pipe pile.

상기 수직철근(101)과 거더(10)의 단부에 노출된 노출강선(12)과 노출철근을 원형의 루프철근(102)으로 상호결속하면서 상기 루프철근(102)에 방사형으로 다수개 일정한 간격으로 방사철근(103)을 결속하여 거더연결부(100)를 설치하여, 상기 콘크리트타설파일연결부(110)와 거더연결부(100)를 포함하는 지점연결부(120)를 도 11 및 도 12와 같이 설치한다.The exposed steel wire 12 exposed to the ends of the vertical reinforcement 101 and the girder 10 and the exposed reinforcement with a circular loop reinforcement 102 are radially connected to the loop reinforcement 102 at regular intervals. By binding the radial reinforcement 103 to install the girder connecting portion 100, the point connection portion 120 including the concrete placing pile connecting portion 110 and the girder connecting portion 100 is installed as shown in FIGS.

상기 하부지지대(90) 위에 2방향이상으로 설치된 프리스트레스트콘크리트합성거더(10) 위에 양단에 프리스트레스가 도입되지 않은 부분(25)을 설치하여 제작한 프리캐스트콘크리트판넬(121)이 걸쳐지도록 설치하면서 마루를 깔듯이 상호 밀착시켜 설치하고 그 위에 슬래브(82)를 형성하는 철근을 배치하고, 상기 지점연결부(120)와 프리캐스트콘크리트판넬(121) 위에 콘크리트를 타설경화시켜 슬래브(82) 및 지점연결부(120)를 형성하도록 한 조립식슬래브교(80)를 도 7 및 도 8과 같이 설치한 것이다.On the lower support 90, the floor is installed so that the precast concrete panel 121, which is manufactured by installing the portions 25 on which the prestress is not introduced, is formed at both ends on the prestressed concrete girder 10 installed in at least two directions. To install close to each other and lay the reinforcing bar to form the slab 82 thereon, and to pour the concrete on the point connection portion 120 and the precast concrete panel 121, the slab 82 and the point connection portion ( The prefabricated slab bridge 80 to form 120 is installed as shown in Figs.

도 13과 같이 양단에는 프리스트레스미도입부를, 정모멘트가 발생되는 중앙에는 프리스트레스도입부(20)를 각각 설치한 상기 프리캐스트콘크리트판넬(121)의 상부에 전단연결재(84)를 다수개 설치하여 추후에 타설되는 슬래브콘크리트(82)와 일체화되도록 한다.As shown in FIG. 13, a plurality of shear connecting members 84 are installed on the precast concrete panels 121 each having pre-stress non-introduction portions at both ends and pre-stress introduction portions 20 at the center where positive moments are generated. It is to be integrated with the slab concrete 82 is poured.

또한, 상기 프리캐스트콘크리트판넬(121)의 양단에 일정길이 노출된 노출강선(12)은 상기 거더에 걸쳐져 설치될때 반대방향에 인접하여 설치된 다른 프리캐스트콘크리트판넬(121)의 노출강선(12)과 추후에 타설되는 슬래브콘크리트(82)와 상호일체 결합되어 일체거동하도록 한 것이다.In addition, the exposed steel wire 12 exposed to a predetermined length on both ends of the precast concrete panel 121 and the exposed steel wire 12 of the other precast concrete panel 121 installed adjacent to the opposite direction when installed over the girder The slab concrete 82 to be poured later is integrally coupled with each other to be integrated.

상기 프리캐스트콘크리트판넬(121)은 전체적으로 마루판과 같이 직사각형의 형상을 갖도록 하되, 전단면에 일정한 간격을 두고 설치된 강선(11)과, 상기 강선을 이용하여 양단의 일정부분에 설정된 프리스트레스미도입부(25)와, 그 이외부분에는 프리스트레스도입부(20)를 설치한 것으로서, 양단부에는 노출강선(12)이 설치되도록 콘크리트로 도 13과 같이 제작한 것이다. The precast concrete panel 121 is to have a rectangular shape as a whole floorboard, the steel wire 11 is provided at a predetermined interval on the front end surface, and the pre-stressed non-introduction portion 25 is set at both ends using the steel wire ), And the other portion is provided with a pre-stress introduction portion 20, and both ends are made of concrete as shown in Figure 13 so that the exposed steel wire 12 is installed.

상기와 같이 프리스트레스트콘크리트합성거더(10)의 설치와 이를 이용하여 프리캐스트콘크리트판넬을 설치하도록 한 것은 슬래브(82)를 설치하기 위하여 콘크리트작업시 수반되는 동바리 및 거푸집의 설치를 생략하기 위함인 것이다.The installation of the prestressed concrete composite girder 10 and the precast concrete panel installation using the same are to omit the installation of copper bars and formwork accompanying concrete work for installing the slab 82 as described above. .

도 7에서보는바와 같이 중앙에 설치되는 강관파일(81) 위에 설치되는 프리스트레스트콘크리트합성거더(10)는 하부지지대(90) 위에서 네방향으로 마주보게 설치하지만, 외곽에 설치되는 경우, 상기 거더(10)가 3개 또는 2개가 설치되면서 설치각도도 다양하게 설치되도록 한 것이다.As shown in FIG. 7, the prestressed concrete composite girder 10 installed on the steel pipe pile 81 installed at the center is installed to face in four directions on the lower support 90, but when installed outside, the girder ( 10) 3 or 2 are installed so that the installation angles are variously installed.

상기 하부지지대(90)는 도 9(a)(b)와 같이 철근콘크리트의 정육면체 또는 직육면체등 다양한 형태의 몸체(91)를 갖고, 상기 몸체의 중앙에 관통공(92)을 형성하되, 상기 관통공(92)의 하부에 단턱(93)의 턱이 형성된 것이다.The lower support 90 has a body 91 of various forms, such as a cube or a cuboid of reinforced concrete, as shown in Figure 9 (a) (b), forming a through hole 92 in the center of the body, the through The jaw of the step 93 is formed at the bottom of the ball 92.

상기 관통공(92) 내면에 다수개의 전단연결재를 설치하여 추후에 타설되는 슬래브콘크리트(82)와의 부착력을 향상시키도록 한다.By installing a plurality of shear connection material on the inner surface of the through hole 92 to improve the adhesion to the slab concrete 82 is to be poured later.

상기 단턱(93)의 턱에 강관파일(81)의 상단부가 도 11과 같이 거치되도록 한 것이다.The upper end of the steel pipe pile 81 to the jaw of the step 93 is to be mounted as shown in FIG.

상기 강관파일(81) 내측 일정길이 떨어진 부분에 내부받침판(83)을 설치하되, 상기 강관파일(81)의 상단에서 내부받침판(83)이 설치된 내면에는 다수개의 전단연결재(84)가 설치된 콘크리트타설파일연결부(110)를 설정하고, 상기 내부받침판(83)까지 도 11과 같이 수직철근을 설치하고, 향후에 슬래브의 설치를 위한 콘크리트타설시 동시에 콘크리트를 타설하도록 한 것이다.The inner support plate 83 is installed on a portion of the steel pipe pile 81 in a predetermined distance away from the inner surface of the steel pipe pile 81, the concrete bearing is installed on the inner surface of the inner support plate 83 is installed a plurality of shear connecting members 84 The pile connection part 110 is set, and the inner support plate 83 is installed with vertical reinforcement as shown in FIG. 11, and the concrete is poured at the same time when concrete is laid for future installation of the slab.

상기 콘크리트타설파일연결부(110)와 거더연결부(100)를 일체연결한 지점연 결부(120)를 설치한 이유는 연결부(110, 100)가 일체거동할 수 있도록 타설된 콘크리트를 매개체로 하여 일체화되어 연속구조를 이루도록 한 것이다.The reason for installing the point connection part 120 in which the concrete placing pile connection part 110 and the girder connection part 100 are integrally connected is integrated through the concrete that is placed so that the connection parts 110 and 100 can be integrated. It is to achieve a continuous structure.

상기 일체화된 연속구조의 지점연결부(120)의 일정범위에는 부모멘트로 인한 압축력이 작용하는 압축부가 발생되므로, 상기 연결부에 연결된 상기 프리스트레스트콘크리트합성거더의 양단부에 프리스트레스가 도입되지 않은 부분을 설치하여 상기 일체화된 지점연결부에서 발생된 압축력을 상쇄시켜 전체적으로 지점연결부에서 발생되는 부모멘트의 크기를 감소시키기 위한 것이다.Since a compression part acts as a compressive force due to a parent in a predetermined range of the pointed connection part 120 of the integrated continuous structure, a portion where prestress is not introduced is provided at both ends of the prestressed concrete composite girder connected to the connection part. To cancel the compressive force generated in the integrated point connection to reduce the size of the parent generated in the point connection as a whole.

또한, 도 14와 같이, 상기 거더(10)와 거더(10) 위에 설치되는 프리캐스트콘크리트판넬(121)의 양단부에도 프리스트레스가 도입되지 않은 부분을 설치하여 상기 거더(10)와 프리캐스트콘크리트판넬(121)이 상호연결된 부분에서 발생된 압축력을 상쇄하도록 하여 부모멘트의 크기를 감소시키기 위한 것이다.In addition, as shown in Figure 14, the girder 10 and the precast concrete panel (installed on both ends of the precast concrete panel 121 installed on the girder 10 and the pre-stress is not introduced) 121) to reduce the size of the parent by offsetting the compressive forces generated in the interconnected portions.

상기 콘크리트타설파일연결부(110)의 설치이유는 강관파일단면력과 전단연결재(84)에 의한 전단연결력이 같도록 하면서 채움연결매개체인 콘크리트와의 전단연결재에 의하여 일체화 거동하면서 발생되는 응력이 전달되도록 하기 위함이다.The reason for the installation of the concrete placing pile connection part 110 is to ensure that the stress generated while the integration operation is performed by the shear connecting material with the concrete, which is the filling connecting medium, while the shear connection force by the steel pipe pile cross section force and the shear connecting material 84 are the same. To do this.

상기 콘크리트타설파일연결부(110)는 상기 강관파일 내부에 전단연결재(84)가 충분히 설치될 수 있는 범위로 하되, 바람직한 범위는 강관파일(81)의 상부에서 하부로 0.5 ~ 1M에 설치한 것이다.The concrete pouring pile connecting portion 110 is a range in which the shear connector 84 is sufficiently installed in the steel pipe pile, but the preferred range is installed at 0.5 ~ 1M from the top of the steel pipe pile 81 to the bottom.

도 10은 강관파일(11) 내면에 전단연결재(84)와 내부받침판(83)이 설치된 것을 보여주는 도면이다. 10 is a view showing that the shear connector 84 and the inner support plate 83 is installed on the inner surface of the steel pipe pile (11).

도 12는 도 11의 연결상태를 평면에서 보여주는 도면이다.12 is a plan view illustrating the connection state of FIG. 11.

또한, 상기 거더의 양단에 노출된 철근의 단부를 절곡하여 위에 설치된 철근의 절곡방향은 하부로 향하게 하고, 하부에 설치된 철근의 절곡방향은 상부로 향하게 설치하면서 상기 절곡된 부분은 수직철근 및 노출강선과 루프철근과 결속하여 연결부가 보다 강하게 일체연결되도록 하기 위한 것이다.In addition, bending the end of the rebar exposed on both ends of the girder bending direction of the reinforcing bar installed on the lower side, while the bending direction of the reinforcing bar installed on the lower side is installed toward the top while the bent portion is vertical bar and exposed steel wire It is to bind with the reinforcement and the loop reinforcing to connect the connection more strongly.

참고적으로 본 발명의 거더(10)와 프리캐스트콘크리트판넬(121)을 제작하기 위하여 골조를 이루도록 철근을 배근하도록 한 것은 당업자는 아주관용적으로 실시하여 당연히 설치하는 것이므로 이것에 대한 상세한 설명을 생략한 것과, 전단연결재의 설치 이유도 당업자가 너무나 잘 알 고 있는 기술이므로 상세한 설명을 생략하였음을 밝혀두고자 합니다.For reference, in order to reinforce the reinforcing bar to form a frame to fabricate the girder 10 and the precast concrete panel 121 of the present invention, those skilled in the art are quite tolerant to install it naturally, and thus a detailed description thereof will be omitted. In addition, the reason for the installation of the shear connector is also well known to those skilled in the art, so it will be clear that the detailed description is omitted.

도 1은 본 발명의 프리스트레스트콘크리트합성거더를 보여주는 도면.1 is a view showing a prestressed concrete composite girder of the present invention.

도 2(a)(b)(c)(d)는 본 발명의 프리스트레스트콘크리트합성거더를 거더제작대를 이용하여 제작하는 과정을 보여주는 도면.Figure 2 (a) (b) (c) (d) is a view showing a process of manufacturing the prestressed concrete composite girder of the present invention using a girder production stage.

도 3은 도 2의 거더제작대의 단부지압강판을 보여주는 도면.Figure 3 is a view showing the end pressure plate of the girder manufacturing table of Figure 2;

도 4는 도 2의 거더제작대의 가동지압강판을 보여주는 도면. Figure 4 is a view showing a movable chiropractor of the girder manufacturing table of FIG.

도 5는 도 2의 거더제작대의 강선체결지압강판을 보여주는 도면.Figure 5 is a view showing a steel wire fastening pressure plate of the girder production of Figure 2;

도 6(a)(b)는 도 2의 거더제작대의 강선체결지압강판에 강선이 체결된 상태를 상세히 보여주는 도면.Figure 6 (a) (b) is a view showing in detail the state in which the steel wire is fastened to the steel wire fastening pressure steel plate of the girder production of Figure 2;

도 7은 본 발명의 프리스트레스트콘크리트합성거더를 이용하여 조립식슬래브교를 설치한 것을 보여주는 도면.7 is a view showing the installation of prefabricated slab bridge using the prestressed concrete composite girder of the present invention.

도 8은 도 7의 단면을 보여주는 단면도.8 is a cross-sectional view showing a cross section of FIG.

도 9(a)(b)는 본 발명의 조립식슬래브교의 강판파일의 상단에 걸쳐지도록 설치하고, 그 위에 설치되는 거더를 지지하도록 하는 하부지지대를 상세히 보여주는 도면.Figure 9 (a) (b) is installed to span the upper end of the steel plate pile of the prefabricated slab bridge of the present invention, a view showing in detail the lower support to support the girder installed thereon.

도 10은 본 발명 조립식슬래브교의 기둥인 강관파일의 상부에 일정범위에 걸쳐 설치된 콘크리트타설파일연결부와 그 내부에 전단연결재가 설치된 것를 보여주는 도면.10 is a view showing that the concrete placing pile connecting portion installed over a certain range on the upper portion of the steel pipe pile which is a pillar of the prefabricated slab bridge of the present invention and the shear connecting material is installed therein.

도 11은 본 발명의 조립식슬래브교를 설치하기 위하여 강관파일의 상부에 설치된 하부지지대 위에 거치된 거더의 노출강선 및 노출철근과 상기 강관파일내에 설치된 철근을 루프철근으로 상호 연결하는 거더연결부를 측면에서 단면으로 보여주는 도면.Figure 11 is a girder connecting portion for interconnecting the exposed steel wire and exposed reinforcement of the girder mounted on the lower support installed on the upper portion of the steel pipe pile and the reinforcing steel installed in the steel pipe pile with a loop reinforcement to install the prefabricated slab bridge of the present invention from the side Drawing shown in cross section.

도 12는 도 11의 평면을 보여주는 도면.12 shows the plane of FIG. 11;

도 13은 본 발명의 거더제작대를 이용하여 양단부에 프리스트레스미도입부가 설치되도록 하여 양단부에 노출강선이 배치된 프리캐스트콘크리트판넬을 상세히 보여주는 도면.Figure 13 is a view showing in detail the precast concrete panel with the exposed steel wires at both ends so that the pre-stress non-introduction portion is installed at both ends by using the girder manufacturing table of the present invention.

도 14는 본 발명의 프리캐스트콘크리트판넬를 프리스트레스콘크리트합성거더와의 사이에 마루깔듯이 설치한 것을 보여주는 도면.14 is a view showing that the precast concrete panel of the present invention is installed between the prestressed concrete composite girder floor.

<도면의 주요 부분에 대한 부호의 설명>              <Explanation of symbols for the main parts of the drawings>

10 : 프리스트레스트콘크리트합성거더 11 : 강선10: prestressed concrete composite girder 11: steel wire

12 ; 노출강선 13 : 콘크리트 12; Exposed steel wire 13: concrete

20 : 프리스트레스도입부 14 ; 노출철근20: prestress introduction part 14; Exposed rebar

21 : 응고시간지연접착수지재도포부 24 : 확대두부21: coagulation time delay adhesive resin coating part 24: enlarged tofu

25 ; 프리스트레스미도입부25; Prestressed non-introduction

30 : 거더제작대 31 ; 지반30: girder production 31; Ground

32 ; 강봉 33 ; 나사산32; Rod 33; Thread

34 ; 유압잭 35 ; 체결너트34; Hydraulic jack 35; Tightening Nut

36 ; 너트36; nut

40 ; 지지대 41 ; 수직지지부40; Support 41; Vertical support

42 : 수평지지부 43 : 관통공42: horizontal support 43: through hole

44 : 관44: tube

50 : 단부지압강판 51 : 관통공50: end pressure steel plate 51: through hole

60 : 가동지압강판 61 : 관통공60: movable acupressure steel sheet 61: through hole

70 : 강선체결지압강판 71 : 관통공70: steel wire fastening pressure plate 71: through hole

72 : 강선체결공 73 ; 원형구멍72: steel fastening 73; Circular hole

74 ; 수직구멍74; Vertical hole

80 : 조립식슬래브교 81 ; 강관파일80: prefabricated slab bridge 81; Steel pipe

82 ; 슬래브 83 ; 내부받침판82; Slab 83; Inner support plate

84 ; 전단연결재 85 ; 파일내부84; Shear connector 85; Inside file

90 ; 하부지지대 91 ; 몸체90; Lower support 91; Body

92 ; 관통공 93 ; 단턱92; Through hole 93; Step

100 ; 거더연결부 101 ; 수직철근100; Girder connection 101; Vertical rebar

102 ; 루프철근 103 ; 방사철근102; Roof reinforcement 103; Rebar

110 ; 콘크리트타설파일연결부 120 ; 지점연결부110; Concrete placing pile connection 120; Branch connection

121 ; 프리캐스트콘크리트판넬121; Precast Concrete Panel

Claims (29)

전단면에 일정한 간격을 두고 설치된 강선(11)과, 상기 강선을 이용하여 거더 양단의 일정부분에 설정된 프리스트레스미도입부(25)와, 그 이외의 부분에 설정된 프리스트레스도입부(20)와, 상기 거더의 양단에는 일정길이 노출된 노출강선(12)과 노출철근(14)이 설치되도록 타설경화된 콘크리트로 이루어진 것에 특징이 있는 양단부에 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더. The steel wire 11 provided at regular intervals on the front end surface, the prestressed non-introduction portion 25 set at a predetermined portion of both ends of the girder by using the steel wire, the prestressed introduction portion 20 set at the other portion, and the girder Prestressed concrete girder with prestressed non-introduced portions installed at both ends, characterized in that the exposed steel wire 12 and the exposed reinforcing bars 14 are made of pour hardened concrete at both ends. 전체적으로 마루판과 같이 직사각형의 형상을 갖도록 하되, 전단면에 일정한 간격을 두고 설치된 강선(11)과, 상기 강선을 이용하여 양단의 일정부분에 설정된 프리스트레스미도입부(25)와, 그 이외부분에는 프리스트레스도입부(20)를 설치한 것으로서, 양단부에는 노출강선(12)이 설치되도록 콘크리트로 제작한 프리캐스트콘크리트판넬(121)인 것에 특징이 있는 양단부에 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더.The steel wire 11 is formed to have a rectangular shape as a whole, but is provided at regular intervals on the shear surface, and the prestressed non-introduction part 25 set at a predetermined portion of both ends by using the steel wire, and the prestressed introduction part at other parts thereof. The prestressed concrete girder having the prestressed non-introduced portions installed at both ends, which is characterized in that the precast concrete panel 121 made of concrete so that the exposed steel wire 12 is installed at both ends. 제 1항 또는 제 2항에 있어서,The method according to claim 1 or 2, 상기 프리스트레스미도입부(25)의 범위는 거더 또는 판넬길이(L)의 0.1 ~ 0.25인 것에 특징이 있는 양단부에 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더.The prestressed concrete composite girders provided with the prestressed non-introduced portions at both ends characterized in that the range of the prestressed non-introduced portion 25 is 0.1 to 0.25 of the girder or the panel length (L). 제 1항 또는 제2항에 있어서,3. The method according to claim 1 or 2, 상기 프리스트레스미도입부(25)의 강선(11)에 응고시간지연접착수지재를 표면이 거칠게 소정의 두께로 도포한 것에 특징이 있는 양단부에 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더.A prestressed concrete composite girder provided with prestressed non-introduced portions at both ends characterized in that the surface of the prestressed non-introduced portion 25 is coated with a coarse time delay adhesive resin material with a predetermined thickness. 제 1항 또는 제 2항에 있어서,The method according to claim 1 or 2, 상기 프리스트레스트콘크리트합성거더(10) 또는 프리캐스트콘크리트판넬(121)의 상부면에 다수개의 전단연결재(84)가 설치된 것에 특징이 있는 양단부에 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더.A prestressed concrete composite girder having a prestressed non-introduced portion at both ends characterized in that a plurality of shear connecting members 84 are installed on an upper surface of the prestressed concrete composite girder 10 or a precast concrete panel 121. 지반(31) 위에 일정한 간격을 두고 지지대(40)를 마주보게 설치하고, 상기 지지대(40)의 수직지지부(41)에 관통공(43)을 다수개 설치하면서 상기 관통공(43)내에 관(44)을 설치하고,The support base 40 is installed to face the ground 31 at regular intervals, and a plurality of through holes 43 are installed in the vertical support part 41 of the support 40 while the pipes in the through holes 43 44) install it, 상기 수직지지부(41)의 양면에 관통공(51)이 다수개 형성된 단부지압강판(50)을 설치하고,Install the end pressure-bearing steel plate 50 is formed with a plurality of through holes 51 on both sides of the vertical support portion 41, 상기 수직지지부(41)의 외측에 다수개의 관통공(61)이 형성된 가동지압강판(60)을 설치하고,A movable acupressure steel plate 60 having a plurality of through holes 61 formed outside the vertical support part 41 is provided. 상기 수직지지부(41)의 내측에 다수개의 관통공(71)과 강선체결공(72)이 동시에 형성된 강선체결지압강판(70)을 설치하고,On the inner side of the vertical support portion 41 is provided with a steel wire fastening pressure steel plate 70 in which a plurality of through holes 71 and steel wire fastening holes 72 are formed at the same time, 상기 수직지지부(41)에 형성된 관통공(43)을 관통하여 내외면에 각각 설치된 가동지압강판(60)과 강선체결지압강판(70)의 관통공(61,71)을 관통하여 강봉(32)으로 상호연결하여 너트(36)로 각각 고정설치하고, Steel bars 32 through the through holes 43 formed in the vertical support portion 41 and through the through-holes 61 and 71 of the movable pressure-bearing steel plate 60 and the steel wire fastening pressure-steel plate 70 respectively installed on the inner and outer surfaces thereof. Fixed with nuts 36, 상기 강선체결지압강판(70)에 형성된 다수개의 강선체결공(72)에 강선(11)의 단부가 체결되도록 하고,The ends of the steel wire 11 is fastened to a plurality of steel wire fastening holes 72 formed in the steel wire fastening pressure plate 70, 상기 수직지지부(41)와 가동지압강판(60)과의 사이에 유압잭(34)을 설치한 거더제작대(30)를 설치하고,A girder production table 30 having a hydraulic jack 34 is installed between the vertical support portion 41 and the movable acupressure steel sheet 60, 상기 설치된 강선에 거더의 양단부에서 일정거리까지 응고시간지연접착수지재를 일정두께로 표면을 거칠게 도포한 도포부(21)를 형성하고,In the steel wire provided is formed a coating portion 21, the surface of which the coagulation time delay adhesive resin material is roughly coated to a certain thickness from both ends of the girder to a predetermined distance, 상기 유압잭(34)에 스트로크를 발생시켜 가동지압강판(60)을 외측으로 밀면 강봉(32)에 의하여 상호 연결된 강선체결지압강판(70)이 지지대(40)쪽으로 이동하게되어, 상기 강선체결지압강판(70)의 강선체결공(72)에 체결연결된 강선(11)도 당겨지게되어 강선에 긴장력이 도입되도록 하면서 체결너트(35)로 강봉(32)과 수직지지대의 외측면에 매입된 단부지압강판(50)을 체결고정하고,When the movable jack steel plate 60 is pushed outward by generating a stroke in the hydraulic jack 34, the steel wire fastening pressure steel plate 70 interconnected by the steel bar 32 moves toward the support 40, and the steel wire fastening pressure steel sheet The steel wire 11 fastened and connected to the steel fastening hole 72 of the 70 is also pulled so that tension force is introduced into the steel wire while the end pressure plate is embedded in the outer surface of the steel rod 32 and the vertical support with the fastening nut 35. Fasten and secure the (50), 상기 양측에 설치된 지지대(40)와의 사이에 설치된 긴장력이 도입된 상태의 다수개의 강선(11)을 포함하면서 다수개의 거더를 제작할 수 있는 콘크리트를 타설양생하고,Placing concrete to manufacture a plurality of girders, including a plurality of steel wires 11 in a state where a tension force installed between the support 40 installed on both sides is introduced, 상기 콘크리트의 양생이 완료된 후에 거더와 거더 사이에 설치된 강선(11)을 절단하면서, 노출강선(12)이 설치되도록 하고, 동시에 거더를 형성하도록 배근된 철근의 양단부가 상기 거더의 양단부에 노출되도록 노출철근(14)을 설치하고, 상기 강선체결지압강판(70)에 설치된 강선체결공(72)에 체결된 강선(21)을 이탈시키는 과정을 거쳐 제작하는 것에 특징이 있는 양단부에 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더의 제작방법. After the curing of the concrete is completed, the steel wire 11 installed between the girder and the girder is cut, so that the exposed steel wire 12 is installed, and at the same time, both ends of the reinforcing bars exposed to form the girder are exposed to both ends of the girder. Install the reinforcing bars 14 and pre-stressed non-introducing parts are installed at both ends characterized by the process of leaving the steel wire 21 fastened to the steel fastening hole 72 installed in the steel wire fastening pressure plate (70). How to make a prestressed concrete composite girder. 제 6항에 있어서,The method of claim 6, 상기 거더제작대(30)를 이용하여 양단에 프리스트레스미도입부(25)를, 그 이외의 부분에는 프리스트레스도입부(20)를 설치한 프리캐스트콘크리트판넬(121)을 제작한 것에 특징이 있는 양단부에 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더의 제작방법. Pre-stressed at both ends, characterized in that the pre-cast concrete panel 121 having the pre-stress non-introduction portion 25 at both ends and the pre-stress introduction portion 20 is provided at the other end using the girder production table 30. Manufacturing method of prestressed concrete composite girder with no inlet. 제 6항 또는 제 7항에 있어서,The method according to claim 6 or 7, 상기 응고시간지연접착수지재도포부(21)의 범위는 거더 또는 판넬길이(L)의 0.1 ~ 0.25이며, 상기 응고시간지연접착수지재의 경화시작 시간은 24 ~ 36시간이 경과된 후인 것에 특징이 있는 양단부에 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더의 제작방법. The solidification time delay adhesive resin coating portion 21 is in the range of 0.1 ~ 0.25 of the girder or panel length (L), the curing start time of the solidification time delay adhesive resin material is characterized in that after 24 to 36 hours have elapsed Manufacturing method of prestressed concrete composite girder with prestressed non-introduced parts at both ends. 제 6항 또는 제 7항에 있어서,The method according to claim 6 or 7, 상기 지지대(40)는 철근콘크리트로 수직지지부(41)와 수평지지부(42)의 ㄴ자형으로 설치하되, 수평지지부(42)를 지반(31)내에 매입설치하되, 상기 수평지지부(42)가 내측으로 설치되도록 한 것에 특징이 있는 양단부에 프리스트레스미도입 부를 설치한 프리스트레스트콘크리트합성거더의 제작방법.The support 40 is installed in the shape of the vertical support portion 41 and the horizontal support portion 42 of the reinforced concrete, the horizontal support portion 42 is embedded in the ground 31, the horizontal support portion 42 is installed inside Method of manufacturing a prestressed concrete composite girder having prestressed non-introduced portions at both ends characterized by being installed by 제 6항 또는 제 7항에 있어서,The method according to claim 6 or 7, 상기 수직지지부(41)에는 다수개의 관통공(43)이 형성되고, 상기 관통공(43)내에는 관(44)을 삽입한 것에 특징이 있는 양단부에 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더의 제작방법.A plurality of through holes 43 are formed in the vertical support portion 41, and prestressed concrete girder having prestressed non-introduced portions provided at both ends, wherein the pipe 44 is inserted into the through holes 43. How to make. 제 6항 또는 제 7항에 있어서,The method according to claim 6 or 7, 상기 단부지압강판(50)은 수직지지부(41)의 내외면에 매입되어 설치되는 것으로서, 직각사각형의 강판으로 다수개의 관통공(51)이 형성된 것에 특징이 있는 양단부에 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더의 제작방법.The end pressure-bearing steel plate 50 is embedded and installed on the inner and outer surfaces of the vertical support portion 41, the pre-stress non-introduction portion is installed on both ends characterized in that a plurality of through holes 51 formed of a rectangular steel sheet Manufacturing method of rest concrete composite girder. 제 6항 또는 제 7항에 있어서,The method according to claim 6 or 7, 상기 가동지압강판(60)은 수직지지부(41)의 외측면에서 일정거리 떨어져 설치되는 것으로서, 직사각형의 강판으로 다수개의 관통공(61)이 설치된 것에 특징이 있는 양단부에 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더의 제작방법.The movable acupressure steel sheet 60 is installed a predetermined distance away from the outer surface of the vertical support portion 41, the pre-stressed non-stressed portion is provided on both ends characterized in that a plurality of through holes 61 are installed in a rectangular steel sheet Manufacturing method of rest concrete composite girder. 제 6항 또는 제 7항에 있어서,The method according to claim 6 or 7, 상기 강선체결지압강판(70)은 수직지지부(41)의 내측면에서 일정거리 간격을 두고 설치되는 것으로서, 직사각형의 강판에 다수개의 관통공(71)과 강선체결공(72)이 동시에 형성된 것에 특징이 있는 양단부에 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더의 제작방법.The wire fastening pressure steel plate 70 is installed at a predetermined distance from the inner surface of the vertical support portion 41, characterized in that a plurality of through holes 71 and the steel wire fastening holes 72 are formed at the same time in a rectangular steel sheet Method of manufacturing prestressed concrete composite girder with prestressed non-introduced portions at both ends. 제 6항 또는 제 7항에 있어서,The method according to claim 6 or 7, 상기 강선체결공(72)은 열쇠구멍의 형태로서, 상부는 원형구멍(73)이 형성되고 이와 접하여 하부에는 상기 원형구멍(73)보다 폭은 작으나 수직구멍(74)의 길이는 길게 형성된 것에 특징이 있는 양단부에 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더의 제작방법.The steel wire fastening hole 72 is in the form of a key hole, the upper portion is formed with a circular hole 73 is in contact with the lower portion is smaller than the circular hole 73, but the length of the vertical hole 74 is characterized in that formed long Method of manufacturing prestressed concrete composite girder with prestressed non-introduced portions at both ends. 제 6항 또는 제 7항에 있어서,The method according to claim 6 or 7, 상기 강선체결공(72)에 체결된 강선(11)의 단부는 강선의 직경보다 크게 설치된 확대두부(24)가 형성된 것에 특징이 있는 양단부에 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더의 제작방법.The end of the steel wire 11 fastened to the wire fastening hole 72 is a prestressed concrete composite girder manufacturing method of the pre-stressed non-introduction portion is installed at both ends characterized in that the enlarged head 24 is formed larger than the diameter of the steel wire . 제 6항 또는 제 7항에 있어서,The method according to claim 6 or 7, 상기 지지대(40)가 안정성이 있게 지반(31)에 설치되는 조건은 P x H1〈W x L1 인 것에 특징이 있는 양단부에 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더의 제작방법.The prestressed concrete composite girder manufacturing method is provided with a prestressed non-introduction portion at both ends characterized in that the support (40) is stably installed on the ground (31) is P x H1 <W x L1. 제 6항 또는 제 7항에 있어서,The method according to claim 6 or 7, 상기 지지대가 안정성이 있게 지반에 설치되는 조건은 P x h1〈W x L1 인 것에 특징이 있는 양단부에 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더의 제작방법.The prestressed concrete composite girder manufacturing method is provided with a prestressed non-introduction portion at both ends characterized in that the support is stably installed on the ground is P x h1 &lt; W x L1. 제 6항 또는 제 7항에 있어서,The method according to claim 6 or 7, 상기 지지대가 안정성이 있게 지반에 설치되는 조건은 P〈W x μ+C인 것에 특징이 있는 양단부에 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더의 제작방법. The prestressed concrete composite girder manufacturing method is provided with a prestressed non-introduced portion at both ends characterized in that the support is stably installed on the ground is P <W x μ + C. 제 6항 또는 제 7항에 있어서,The method according to claim 6 or 7, 상기 지지대가 안정성이 있게 지반에 설치되는 조건은 P x h2 /Z〈fa인 것에 특징이 있는 양단부에 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더의 제작방법.The prestressed concrete composite girder manufacturing method is provided with a prestressed non-introduction portion at both ends characterized in that the support is stably installed on the ground is P x h2 / Z <fa. 제 6항 또는 제 7항에 있어서,The method according to claim 6 or 7, 상기 지지대가 안정성이 있게 지반에 설치되는 조건은 지지대의 전도 및 활동 및 단면파괴를 모두 만족할 수 있도록 설치되어야 하는 것에 특징이 있는 양단부에 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더의 제작방법.The prestressed concrete composite girder manufacturing method of the prestressed non-introduced portion is installed at both ends, characterized in that the support is installed on the ground stably to satisfy both the conduction and the activity of the support and cross-sectional destruction. 제 6항 또는 제 7항에 있어서,The method according to claim 6 or 7, 상기 강선체결공(72)에 강선을 체결하는 방법은 강선체결공(72)의 원형구멍(73)내에 강선(11)의 단부에 설치된 확대두부(24)를 밀어넣은 다음, 상기 원형구멍(73)의 하부에 연접하여 설치된 수직구멍(74)으로 밀어내려 체결하는 것에 특징이 있는 양단부에 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더의 제작방법.The method for fastening the steel wire to the steel fastening hole 72 is to push the expansion head 24 provided at the end of the steel wire 11 in the circular hole 73 of the steel fastening hole 72, and then the circular hole 73 A method of manufacturing a prestressed concrete composite girder, in which a prestressed non-introduced portion is provided at both ends characterized by being pushed down into a vertical hole 74 connected to a lower portion of the bottom). 제 6항 또는 제 7항에 있어서,The method according to claim 6 or 7, 상기 강선(11)을 강선체결구멍(72)으로부터 이탈시키는 방법은 상기 강선체결공(72)의 수직구멍(74)에 체결된 강선(11)을 위로 올리면 수직구멍(74)보다 직경이 넓은 원형구멍(73)으로 강선의 확대두부(24)가 올라오면서 원형구멍(73)을 통하여 외부로 빠지게 되도록 한 것에 특징이 있는 양단부에 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더의 제작방법.The method of detaching the steel wire 11 from the steel wire fastening hole 72 is to raise the steel wire 11 fastened to the vertical hole 74 of the steel wire fastening hole 72 upwards and have a larger diameter than the vertical hole 74. A method of manufacturing prestressed concrete composite girders provided with prestressed non-introduced portions at both ends characterized in that the expansion head (24) of the steel wire is raised to the hole (73) so as to fall out through the circular hole (73). 일정한 면적의 하상 또는 해저의 지반(31)내에 강관파일(81)을 일정한 간격을 두고 격자로 다수개 설치하고,A plurality of steel pipe piles 81 are installed in a lattice at regular intervals in the bed 31 or on the bottom 31 of the sea floor, 상기 설치된 강관파일(81)의 상부가 하부지지대(90)의 중앙에 형성된 관통공(92)의 하부에 형성된 단턱(93)의 턱에 강관파일의 상단이 거치되도록 설치하고,The upper portion of the steel pipe pile 81 is installed so that the upper end of the steel pipe pile is mounted on the jaw of the stepped jaw 93 formed in the lower portion of the through hole 92 formed in the center of the lower support 90, 상기 강관파일(81) 내측 일정길이 떨어진 부분에 내부받침판(83)을 설치하 되, 상기 내부받침판이 설치된 내면까지 다수개의 전단연결재(84)가 설치된 콘크리트타설파일연결부(110)를 설정하고,The inner support plate (83) is installed on a portion of the steel pipe pile (81) in a predetermined distance away from the inner support plate, and the concrete placing pile connecting portion (110) is installed, and a plurality of shear connecting members (84) are installed to the inner surface on which the inner support plate is installed. 상기 강관파일 내부의 내부받침판이 설치된 부분인 콘크리트파일연결부(110)에 수직철근(101)을 다수개 설치하면서 상기 강관파일(81)의 외부로 노출되도록 하고,While installing a plurality of vertical reinforcing bars 101 in the concrete pile connection portion 110, which is an internal support plate installed inside the steel pipe pile to be exposed to the outside of the steel pipe pile 81, 상기 하부지지대(90)의 상부에 2개방향 이상으로 설치된 프리스트레스트콘크리트합성거더(10)의 노출강선(12) 및 노출철근과, 상기 콘크리트타설파일연결부(110)에 매입되어 강관파일(81) 상부로 노출설치된 수직철근(101)을 원형의 루프철근(102)로 상호 결속하면서, 상기 루프철근(102)에 방사상으로 방사철근(103)으로 결속한 거더연결부(100)를 포함한 지점연결부(120)를 설치하고,Steel pipe pile 81 is embedded in the exposed steel wire 12 and the exposed steel reinforcement of the prestressed concrete composite girder 10 installed in two or more directions on the lower support 90, and the concrete placing pile connecting portion 110 Point connection portion 120 including a girder connection portion 100 which is bound to the reinforcing bars (103) radially bound with the reinforcing bars (103) while binding the vertical reinforcement 101 is installed to the upper roof reinforcement (102). ), 상기 프리스트레스트콘크리트합성거더(10)의 상부에 양단에 프리스트레스미도입부(25)를 설치한 프리캐스트콘크리트판넬(121)을 마루깔듯이 다수개 밀착설치하고, 상기 프리캐스트콘크리트판넬의 상부와 상기 지점연결부(120)에 콘크리트를 타설경화시켜 슬래브(82)를 설치하여 조립식슬래브교(80)를 설치한 것에 특징이 있는 양단부에 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더를 이용한 조립식슬래브교 시공방법.A plurality of precast concrete panels 121 having prestressed non-introduced portions 25 are installed on both ends of the prestressed concrete girder 10, and the upper part of the precast concrete panel and the point Prefabricated slab bridge construction method using prestressed concrete composite girders with prestressed non-introduced portions installed at both ends characterized by placing the slab 82 by installing concrete in the connection part 120 and installing the prefabricated slab bridge 80. . 제 23항에 있어서,24. The method of claim 23, 상기 하부지지대(90)는 철근콘크리트의 정육면체 또는 직육면체와 같은 다양한 형태의 몸체(91)를 갖고, 상기 몸체의 중앙에 관통공(92)을 형성하되, 상기 관 통공(92)의 내부면에 다수개의 전단연결재를 설치하고, 상기 관통공의 하부에 단턱(93)이 형성된 것에 특징이 있는 양단부에 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더를 이용한 조립식슬래브교 시공방법.The lower support 90 has a body 91 of various forms, such as a cube or a cube of reinforced concrete, and forms a through hole 92 in the center of the body, but a plurality of inner surfaces of the through hole 92. A prefabricated slab bridge construction method using prestressed concrete composite girders provided with two shear connection members and prestressed non-introduced portions are provided at both ends, characterized by a stepped portion 93 formed below the through hole. 제 23항에 있어서,24. The method of claim 23, 상기 콘크리트타설파일연결부(110)의 범위는 0.5 ~ 1.0M인 것에 특징이 있는 양단부에 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더를 이용한 조립식슬래브교 시공방법.Prefabricated slab bridge construction method using the pre-stressed concrete composite girders provided with the pre-stressed non-introduction portion on both ends characterized in that the range of the concrete placing pile connection portion 110 is 0.5 ~ 1.0M. 제 23항에 있어서,24. The method of claim 23, 상기 콘크리트타설파일연결부(110)와 거더연결부(100)를 설치한 이유는 연결부(110, 100)가 일체거동할 수 있도록 타설된 콘크리트를 매개체로 일체연결한 연결부에서 발생되는 부모멘트에 의하여 발생되는 압축력이 거더연결부에 의하여 결합된 거더의 양단부에 프리스트레스가 도입되지 않은 부분에 전달되어 압축력이 상쇄되도록 한 것에 특징이 있는 양단부에 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더를 이용한 조립식슬래브교 시공방법. The concrete installation pile connection part 110 and the girder connection part 100 is installed due to the parent generated from the connection part integrally connected to the cast concrete so that the connection parts 110 and 100 can be integrated. Construction method of prefabricated slab bridge using prestressed concrete composite girders with prestressed non-introduced parts installed at both ends characterized by the fact that the compressive force is transmitted to the part where prestress is not introduced at both ends of the girder joined by the girder connecting part . 제 23항에 있어서,24. The method of claim 23, 상기 프리스트레스트콘크리트합성거더(10)는 전단면에 일정한 간격을 두고 설치된 강선(11)과, 상기 강선을 이용하여 거더 양단의 일정부분에 설정된 프리스 트레스미도입부(25)와, 그 이외의 부분에 설정된 프리스트레스도입부(20)와, 상기 거더의 양단에는 일정길이 노출된 노출강선(12)과 노출철근(14)이 설치되도록 타설경화된 콘크리트로 이루어진 것에 특징이 있는 양단부에 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더를 이용한 조립식슬래브교 시공방법. The prestressed concrete composite girder 10 is provided with a steel wire 11 provided at regular intervals on the shear surface, a prestressed non-introducing portion 25 set at a predetermined portion of both ends of the girder by using the steel wire, and other portions thereof. Prestress non-introduction portion is installed at both ends characterized in that the pre-stress introduction portion 20 and the end of the girder is made of concrete pour hardened so that the exposed steel wire 12 and the exposed reinforcing bars 14 are installed at a predetermined length Construction method of prefabricated slab bridge using rest concrete composite girder. 제 23항에 있어서,24. The method of claim 23, 상기 프리캐스트콘크리트판넬(121)은 전체적으로 마루판과 같이 직사각형의 형상을 갖도록 하되, 전단면에 일정한 간격을 두고 설치된 강선(11)과, 상기 강선을 이용하여 양단의 일정부분에 설정된 프리스트레스미도입부(25)와, 그 이외부분에는 프리스트레스도입부(20)를 설치한 것으로서, 양단부에는 노출강선(12)이 설치되도록 콘크리트로 제작한 프리캐스트콘크리트판넬(121)인 것에 특징이 있는 양단부에 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더를 이용한 조립식슬래브교 시공방법.The precast concrete panel 121 is to have a rectangular shape as a whole floorboard, the steel wire 11 is provided at a predetermined interval on the front end surface, and the pre-stressed non-introduction portion 25 is set at both ends using the steel wire ) And other prestressed introduction portions 20, and prestressed non-introduced portions are installed at both ends, which are precast concrete panels 121 made of concrete so that exposed steel wires 12 are installed at both ends. Construction method of prefabricated slab bridge using prestressed concrete composite girder. 제 23항에 있어서,24. The method of claim 23, 상기 프리스트레스트콘크리트합성거더(10)와 프리캐스트콘크리트판넬(121)의 상부면에 다수개의 전단연결재(84)가 설치된 것에 특징이 있는 양단부에 프리스트레스미도입부를 설치한 프리스트레스트콘크리트합성거더를 이용한 조립식슬래브교 시공방법. Prestressed concrete composite girders using prestressed concrete composite girders provided with prestressed non-introduced portions at both ends characterized in that a plurality of shear connecting members 84 are installed on the upper surface of the prestressed concrete composite girder 10 and the precast concrete panel 121 Slab construction method.
KR1020090035985A 2009-04-24 2009-04-24 Prestress concrete composite girder with prestress non-introducing portion provided at both ends, manufacturing method thereof, and built-up type slab bridge construction method using the same KR101086646B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020090035985A KR101086646B1 (en) 2009-04-24 2009-04-24 Prestress concrete composite girder with prestress non-introducing portion provided at both ends, manufacturing method thereof, and built-up type slab bridge construction method using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020090035985A KR101086646B1 (en) 2009-04-24 2009-04-24 Prestress concrete composite girder with prestress non-introducing portion provided at both ends, manufacturing method thereof, and built-up type slab bridge construction method using the same

Publications (2)

Publication Number Publication Date
KR20100117309A true KR20100117309A (en) 2010-11-03
KR101086646B1 KR101086646B1 (en) 2011-11-24

Family

ID=43403954

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020090035985A KR101086646B1 (en) 2009-04-24 2009-04-24 Prestress concrete composite girder with prestress non-introducing portion provided at both ends, manufacturing method thereof, and built-up type slab bridge construction method using the same

Country Status (1)

Country Link
KR (1) KR101086646B1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101297127B1 (en) * 2011-07-07 2013-08-14 주식회사 장헌산업 Landing pier structure construction method
KR20150046680A (en) * 2013-10-22 2015-04-30 주식회사 대산시빌테크날러지 Prestressing method using non-composite parts of tendon and concrete structure therewith
KR101532004B1 (en) * 2012-06-21 2015-07-06 주식회사 알트이엔씨 Precast structure for pier of harbors and constructing method using it
CN109624038A (en) * 2019-01-24 2019-04-16 江苏新高新型建材有限公司 A kind of pretensioning prestressed concrete tensioning equipment and working method
KR20200134191A (en) * 2018-10-18 2020-12-01 주식회사 지랜드피씨 Precast structure for expanding road

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101939132B1 (en) 2018-04-16 2019-01-16 한녹희 Girder, modular rahmen structure and construction method thereof

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101297127B1 (en) * 2011-07-07 2013-08-14 주식회사 장헌산업 Landing pier structure construction method
KR101532004B1 (en) * 2012-06-21 2015-07-06 주식회사 알트이엔씨 Precast structure for pier of harbors and constructing method using it
KR20150046680A (en) * 2013-10-22 2015-04-30 주식회사 대산시빌테크날러지 Prestressing method using non-composite parts of tendon and concrete structure therewith
KR20200134191A (en) * 2018-10-18 2020-12-01 주식회사 지랜드피씨 Precast structure for expanding road
CN109624038A (en) * 2019-01-24 2019-04-16 江苏新高新型建材有限公司 A kind of pretensioning prestressed concrete tensioning equipment and working method
CN109624038B (en) * 2019-01-24 2024-03-08 滨海新高构件有限公司 Pretensioned prestressed concrete tensioning equipment and working method

Also Published As

Publication number Publication date
KR101086646B1 (en) 2011-11-24

Similar Documents

Publication Publication Date Title
JP5373979B2 (en) Construction Method of Steel Composite Girder Bridge {ConstructionMethod SteelCompositeGirderBridge}
KR100713692B1 (en) A prestresed connection set bridge post using unit filled concrete with internally confined hollow and a method for construction
KR100662811B1 (en) Non-synthetic complex steel pipe columm having tie ends for filling a steel soncrete and construction method thereof
KR101086646B1 (en) Prestress concrete composite girder with prestress non-introducing portion provided at both ends, manufacturing method thereof, and built-up type slab bridge construction method using the same
KR101170922B1 (en) The rahmen bridge construction technique for which tendon and the connection support stand was used
KR100854224B1 (en) Precast half depth cantilever deck and constructing method of such bridge deck
KR20100099495A (en) Central connecting apparatus engaged with lattice type steel pipe pile and construction method of assembling slab bridge using the same
JP2005097946A (en) Construction method of bridge pier
KR101086643B1 (en) Prestressed concrete girder with plural steel wires disposed at shear surface of tension port
KR101084993B1 (en) Prestress steel composite panel with prestress non-introducing portions provided at both ends and manufacturing method thereof
KR100894650B1 (en) Rahmen bridge with preflexion load and manufacturing method the same
KR101157607B1 (en) Prestressed steel composite girder with prestressed non-introducing portions provided at both ends of lower flange casing concrete, manufacturing method thereof, and Rahmen structure and construction method thereof
KR101170077B1 (en) Prestress concrete composite with prestress non-introducing portion selectively installed at upper and lower portions to which compression force is applied, manufacturing method thereof, slab structure and construction method using the same
KR20090101416A (en) Small scaled bridge for bicycle and walking which is assembled and installed in jobsite after manufacturing all main structures at factory and method of constructing thereof
KR101036177B1 (en) Method for constructing building using PRC integrating method
KR20080111973A (en) Prestressed steel composite beam and a manufacturing method thereof
KR200422840Y1 (en) Fabrication-type slab bridge constructed by supporting H-girder to connection member inserted on matrix pile column
KR101131631B1 (en) Assembling bridge construction method using Prestressed concrete girder with plural steel wires disposed at shear surface of tension port
KR100860592B1 (en) Temporary system for vertical structure using precast concreat block
JP6817589B1 (en) How to build pile support structure
KR101151773B1 (en) Prestress steel composite girder with prestress non-introducing portions respectively provided at both ends thereof and manufacturing method thereof
KR101131629B1 (en) Manufacturing method of Prestressed concrete girder with plural steel wires disposed at shear surface of tension port
KR20120030206A (en) A precast concrete deck and construction method for slab structure by using it
KR101131630B1 (en) Prestressed concrete panel with prestress non-introducing portions provided in both slope ends, manufacturing method thereof, precasted Rahmen and construction method thereof using the same
KR101127804B1 (en) Prestressed concrete panel with prestress non-introducing portions provided in both slope ends, manufacturing method

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20141112

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20151109

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20161104

Year of fee payment: 6