KR100662811B1 - Non-synthetic complex steel pipe columm having tie ends for filling a steel soncrete and construction method thereof - Google Patents

Non-synthetic complex steel pipe columm having tie ends for filling a steel soncrete and construction method thereof Download PDF

Info

Publication number
KR100662811B1
KR100662811B1 KR1020060090059A KR20060090059A KR100662811B1 KR 100662811 B1 KR100662811 B1 KR 100662811B1 KR 1020060090059 A KR1020060090059 A KR 1020060090059A KR 20060090059 A KR20060090059 A KR 20060090059A KR 100662811 B1 KR100662811 B1 KR 100662811B1
Authority
KR
South Korea
Prior art keywords
steel pipe
composite
concrete
pillar
cable
Prior art date
Application number
KR1020060090059A
Other languages
Korean (ko)
Inventor
노윤근
정상욱
Original Assignee
우경건설 주식회사
정상욱
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 우경건설 주식회사, 정상욱 filed Critical 우경건설 주식회사
Priority to KR1020060090059A priority Critical patent/KR100662811B1/en
Application granted granted Critical
Publication of KR100662811B1 publication Critical patent/KR100662811B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D11/00Suspension or cable-stayed bridges
    • E01D11/04Cable-stayed bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/14Towers; Anchors ; Connection of cables to bridge parts; Saddle supports
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/268Composite concrete-metal

Abstract

A construction method for a non-synthetic complex steel pipe column having tied ends for filling ferroconcrete is provided to reduce flexure of a column constructed thereby. A construction method for a non-synthetic complex steel pipe column(20) having tied ends for filling ferroconcrete(25) comprises the steps of mounting a base(11) for a cable-stayed bridge pylon column(10), laying a connection plate(13) on an upper part of the base, and laying an anchor bolt in the base, welding a reinforcing cover plate(23) into upper and lower ends(21,22), mounting a shear connector in a steel pipe, mounting a plurality of anchor brackets(14) at regular intervals to a vertical part between the reinforcing cover plate and the connection plate, fixing the connection plate mounted to a lower part of the steel pipe to another connection plate mounted on the base by a connection bolt(17), inserting a reinforcing rod column assembly in the steel pipe and mounting the non-synthetic complex steel pipe column by casting non-shrinkage concrete in the steel pipe, and mounting the non-synthetic complex steel pipe column by inserting a cable(16) and fixing the cable by a fixation device(15).

Description

양단이 결합된 철근콘크리트속채움 비합성복합강관기둥의 시공방법.{Non-synthetic complex steel pipe columm having tie ends for filling a steel soncrete and construction method thereof}Non-synthetic complex steel pipe columm having tie ends for filling a steel soncrete and construction method

도 1은 본 발명의 비합성복합강관기둥을 사장교파이론기둥으로 사용하여 사장교의 사장재를 설치한 것을 보여주는 도면.BRIEF DESCRIPTION OF THE DRAWINGS The figure which shows the installation of the cable-bearing material of a cable-stayed bridge using the non-composite composite steel pipe pillar of this invention as a cable-stayed bridge pylon.

도 2는 본 발명의 비합성복합강관기둥을 상세히 보여주는 도면.Figure 2 is a view showing in detail the non-composite composite steel pipe pillar of the present invention.

도 3은 본 발명의 비합성복합강관기둥의 상단부와 하단부에 설치된 전단연결재를 보여주는 도면.Figure 3 is a view showing a shear connector installed on the upper end and the lower end of the non-composite composite steel pipe pillar of the present invention.

도 4는 본 발명의 비합성복합강관기둥내에 철근을 조립하여 철근기둥조립체를 설치한 것을 보여주는 도면.4 is a view showing that the reinforcing bar pillar assembly by assembling the reinforcing bars in the non-composite composite steel pipe pillar of the present invention.

<도면의 주요 부분에 대한 부호의 설명> <Explanation of symbols for the main parts of the drawings>

10 ; 사장교파이론기둥 11 ; 기초10; Pillar pylon pillar 11; Foundation

12 ; 앵커볼트 13 ; 연결플레이트12; Anchor bolt 13; Connecting plate

14 ; 앵커브라켓 15 ; 정착구14; Anchor bracket 15; Anchorage

16 ; 사장재 17 ; 연결볼트16; Boss material 17; Connecting bolt

20 ; 비합성복합강관기둥 21 ; 상단부20; Noncomposite composite steel pipe columns 21; Upper part

22 ; 하단부 23 ; 보강커버플레이트22; Bottom 23; Reinforcement Cover Plate

24 ; 강관 25 ; 무수축철근콘크리트24; Steel pipe 25; Non-contraction Reinforced Concrete

26 ; 전단연결재 27 ; 강관내부26; Shear connector 27; Inside steel pipe

28 ; 링형돌출부28; Ring protrusion

30 ; 철근기둥조립체 31 ; 띠철근30; Reinforcing column assembly 31; Steel bars

32 ; 수직철근 32; Vertical rebar

본 발명은 사장교의 사장재가 설치되는 주탑인 사장교파이론기둥을 강관과 강관내에 설치되는 철근기둥조립체가 강관의 양단부에서 전단연결재에 의하여 강결연결되어 합성되도록 하고, 그 이외에는 연결되지 않은 비합성으로 시공한 비합성복합강관기둥의 시공방법에 관한 것으로서, The present invention is a steel pipe and the reinforcement column assembly is installed in the steel pipe and the steel pipe and the steel column is installed in the steel pipe is a non-synthetic non-synthetic construction that is not connected to the other end of the steel pipe and the reinforcing column assembly is installed in the pipe As for the construction method of non-composite composite steel pipe pillar,

주탑인 사장교파이론 기둥을 설치하기 위하여 기초를 설치하고, 기초 상부에 연결플레이트를 매설하면서 연결플레이트와 연결된 앵커볼트를 기초내에 매설하고, 상하단부에 일정한 높이의 보강커버플레이트가 각각 용접설치되고, 상기 보강커버플레이트가 설치된 강관내부에 일정한 간격을 두고 전단연결재를 설치하고, 강관 하단부의 일정한 높이로 설치된 보강커버플레이트와 강관의 하부에 설치된 연결플레이트와의 직각부에 일정한 간격을 두고 앵커브라켓을 다수개 설치한 강관의 하부에 설치된 연결플레이트를 상기 기초 위에 설치된 연결플레이트와 밀착고정되도록 연결볼트로 고정설치하고, 수직철근과 일정한 간격을 두고 설치된 띠철근으로 조립 된 철근기둥조립체를 강관 내부에 삽입설치하고, 강관내부를 무수축콘크리트로 충전타설하여 비합성복합강관기둥을 설치한 다음, 상기 강관기둥의 상단부에 일정한 간격을 두고 다수개 형성된 관통홈을 따라 사장교의 거더에 연결된 사장재를 상비관통시킨 다음 정착구로 정착하여 사장교의 주탑인 사장교파이론기둥의 설치를 완료하는 것이다.The foundation is installed in order to install the cable-stayed bridge pylon pillar, and the anchor bolt connected to the connection plate is embedded in the base while the connection plate is embedded in the upper part, and the reinforcement cover plate of the constant height is welded and installed at the upper and lower ends, respectively. Shear connector is installed at regular intervals inside the steel pipe where the reinforcement cover plate is installed, and a plurality of anchor brackets are installed at regular intervals between the reinforcement cover plate installed at a constant height of the lower part of the steel pipe and the connection plate installed at the lower part of the steel pipe. The connection plate installed on the lower part of the installed steel pipe is fixed to the connection bolt so as to be tightly fixed to the connection plate installed on the foundation, and the reinforcing column assembly assembled from the band bars installed at regular intervals from the vertical reinforcing bar is inserted into the steel pipe. And filling steel pipe with non-concrete concrete The non-composite composite steel pipe pillar was installed, and the pipe material connected to the girder of the cable-stayed bridge was always penetrated along a plurality of through grooves formed at regular intervals at the upper end of the steel pipe pillar. To complete the installation of the column.

상기 비합성복합강관기둥은 강관의 상하단부의 일정높이에 보강커버플레이트를 설치하고, 상기 보강커버플레이트가 설치된 강관내부에 일정한 간격을 두고 전단연결재를 설치하고, 강관내부에 수직철근과 띠철근으로 조립된 철근기둥조립체를 삽입한 다음, 강관내부를 무수축콘크리트로 타설충전하여 무수축철근콘크리트가 설치되도록 하여 강관내에 설치된 무수축철근콘크리트와 강관을 일정한 범위에 걸쳐 설치된 강관 상하단부의 강관내부에 설치된 전단연결재에 의하여 결합, 합성시키고, 그 이외의 부분인 강관의 중앙부에서는 강관과 무수축철근콘크리트와 결합시키지 않은 비합성상태로 시공한 것이다.The non-composite composite steel pipe column is provided with a reinforcement cover plate at a predetermined height of the upper and lower ends of the steel pipe, a shear connection member is installed at regular intervals inside the steel pipe in which the reinforcement cover plate is installed, and the vertical reinforcing bars and the band reinforcing bar inside the steel pipe. After inserting the assembled reinforcement column assembly, the inside of the steel pipe is filled with non-contraction concrete so that the non-contraction reinforcement concrete is installed so that the non-contraction reinforcement concrete and the steel pipe installed in the steel pipe are installed in the steel pipe at the upper and lower ends of the steel pipe. It is bonded and synthesized by the installed shear connector, and the other part is constructed in a non-synthetic state in which the steel pipe and the non-reinforced concrete are not bonded.

본 발명의 목적은 강관의 상하단부 내부에 전단연결재를 설치하여 강관내부에 삽입된 철근기둥조립체에 타설된 무수축콘크리트에 의하여 형성된 무수축철근콘크리트의 상하단부와 강관이 상호연결된 합성으로 하고, 강관의 중앙부는 연결이 안된 비합성상태로 시공한 비합성복합강관기둥을 압축부재인 사장교파이론기둥으로 사용하여 교량구조역학적인 면에서 효율성이 있으면서 시공성이 향상되어 이로인하여 공사비가 절감되는 비합성복합강관기둥의 시공방법을 제공하는데 있다.An object of the present invention is to install a shear connector in the upper and lower ends of the steel pipe to be a composite of the upper and lower ends and the steel pipe of the non-contracted reinforced concrete formed by the non-concrete concrete placed in the reinforcement pillar assembly inserted into the steel pipe, the steel pipe The non-composite composite steel pipe pillar, which is constructed in an unsynthesized state, is used as a cable-stayed cable-pylon pillar, which is a compression member, so that the construction efficiency is improved in terms of bridge structural dynamics, thereby reducing construction costs. It is to provide a method of constructing a column.

일반적으로 사장교의 주탑인 사장교파이론기둥은 정확히 수직을 유지하면서 기둥의 직진성이 요구되는 시공이 매우 정밀하게 진행되어야 하는 기둥인 것이다. In general, the cable-stayed pylon pillar, which is the main tower of the cable-stayed bridge, is a column whose construction requires very precise construction while maintaining the verticality.

상기와 같이 시공의 정밀성이 요구되는 사장교파이론기둥을 강관의 내부에 속채움콘크리트로 타설한 강관기둥을 사용하는 것이 시공성 및 경제적으로 효율성이 있으나, 강관과 콘크리트를 상호연결되는 합성으로 하기 위하여는 강관내부 전체면에 걸쳐 전단연결재를 설치하여야 하나 강관내부 전체에 걸쳐 돌출된 내부연결재의 설치가 매우 곤란한 관계로 인하여 제작이 매우 번거로운 점, 특히 소규모의 사장교파이론기둥인 경우에는 전혀 시공이 불가능한 점이 문제점으로 대두되어 왔다.As mentioned above, although the use of a steel pipe pillar in which a cable-stayed pylon column is required to be placed inside the steel pipe is required for construction accuracy, it is efficient in construction and economical, but in order to make the composite of the steel pipe and concrete interconnected Shear connector should be installed over the entire inner surface, but it is very cumbersome to manufacture because of the very difficult installation of the inner connector that protrudes throughout the inside of the steel pipe, especially in the case of small cable-stayed pylon pillars. It has been emerging.

본 발명은 상기와 같은 문제점을 개선하기 위하여 제안된 발명으로서, 본 발명은 번거로운 강관 내부 전체면에 걸쳐 설치되는 전단연결재의 설치를 생략하고, 강관의 양단부에서만 강관과 철근콘크리트기둥이 상호 연결되도록 하고, 강관의 중앙부에서는 상호 연결되지 않은 비합성의 상태로 하여 하중이 작용될때 강관과 강관내부에 설치된 무수축철근콘크리트가 각각 분담하여 저항하도록 하는 비합성복합강관기둥시공방법의 제공에 있다. The present invention has been proposed in order to improve the above problems, the present invention omits the installation of the shear connecting material is installed over the entire inner surface of the cumbersome steel pipe, so that the steel pipe and reinforced concrete pillars only interconnected at both ends of the steel pipe In the center of the steel pipe, there is provided a method of constructing a non-composite composite steel pipe column in which the non-composite reinforced concrete installed inside the steel pipe and the non-composite reinforced concrete are respectively shared and resisted when the load is applied to the non-synthetic state.

또한, 휨부재인 경우에는 각각의 부재가 상호 연결된 합성부재로 제작시공되어야 작용하는 하중의 휨모멘트에 저항할 수 있어 구조역학적으로 문제가 발생되지 않으나, 본 발명과 같이 기둥부재는 수직의 힘인 압축력에 주로 저항하는 부재로서, 상기 휨부재와 달리 부재상호간에 연결되지 않은 비합성상태의 부재를 이용하여도 구조역학적으로 전혀 문제가 되지 않은 즉, 외력에 대하여 비합성상태에서 각 각의 부재의 재료의 특성에 따라 일체적으로 작용하게되어 구조적인 취약점이 전혀발생하지 않는 점을 이용하여 사장교파이론기둥에 비합성복합강관기둥을 사용하도록 하는 시공방법을 제공하기 위함이다.In addition, in the case of the bending member, each member must be constructed with interconnected composite members to resist the bending moment of the load to be applied, so structural problems do not occur, but the column member is a compressive force that is a vertical force as in the present invention. It is a member that mainly resists, and unlike the bending member, even if a member of a non-synthetic state is not connected between members, there is no structural problem at all, that is, the material of each member in a non-synthetic state against external force. It is to provide a construction method that uses non-composite composite steel pipe pillars for cable-stayed pylon pillars by taking advantage of the fact that structural weakness does not occur at all.

본 발명은 사장교의 사장재(16)가 설치되는 주탑인 사장교파이론기둥(10)에 비합성복합강관기둥(20)을 사용하기 위하여 시공방법은 다음과 같다. The present invention is a construction method to use the non-composite composite steel pipe pillar 20 to the cable-stayed bridge pylon pillar 10, which is the main tower on which the cable-bearing material 16 is installed.

주탑인 사장교파이론기둥(10)을 설치하기 위하여 기초(11)를 설치하고, 기초 상부에 연결플레이트(13)를 매설하면서 연결플레이트와 연결된 앵커볼트(12)를 기초(11)내에 매설하고, 상하단부(21,22)에 일정한 높이의 보강커버플레이트(23)가 각각 용접설치되고, 상기 보강커버플레이트(23)가 설치된 강관내부(27)에 일정한 간격을 두고 전단연결재(26)를 설치하고, 강관 하단부(22)의 일정한 높이로 설치된 보강커버플레이트(23)와 강관(24)의 하부에 설치된 연결플레이트(13)와의 직각부에 일정한 간격을 두고 앵커브라켓(14)을 다수개 설치한 강관(24)의 하부에 설치된 연결플레이트(13)를 상기 기초(11) 위에 설치된 연결플레이트(13)와 밀착고정되도록 연결볼트(17)로 고정설치하고, 수직철근(32)과 일정한 간격을 두고 설치된 띠철근(31)으로 조립된 철근기둥조립체(30)를 강관(24) 내부에 삽입설치하고, 강관(24)내부를 무수축콘크리트로 충전타설하여 무수축철근콘크리트(25)가 설치된 비합성복합강관기둥(20)을 설치한 다음, 상기 비합성복합강관기둥(20)의 상부에 일정한 간격을 두고 다수개 형성된 관통홈(미도시)을 따라 사장교의 거더에 연결된 사장재(16)를 삽입관통시킨 다음 정착구(15)로 정착하여 사장교의 주탑인 사장교파이론 기둥(10)의 설치를 완료하는 것에 특징이 있다.In order to install the cable-stayed bridge pylon pillar 10, which is the main tower, the foundation 11 is installed, and the anchor bolt 12 connected to the connection plate is embedded in the foundation 11 while the connection plate 13 is embedded in the upper portion of the foundation. Reinforcement cover plates 23 of constant height are welded to the lower ends 21 and 22, respectively, and the shear connection members 26 are installed at regular intervals in the steel pipe inner portion 27 where the reinforcement cover plates 23 are installed. Steel pipes having a plurality of anchor brackets 14 installed at regular intervals at right angles with the reinforcing cover plate 23 installed at a constant height of the lower portion of the steel pipe 22 and the connecting plate 13 installed at the lower portion of the steel pipe 24 ( The connection plate 13 installed at the lower part of the 24 is fixed to the connection bolt 17 so as to be fixed in close contact with the connection plate 13 installed on the base 11, and the strip is installed at regular intervals with the vertical reinforcement 32 Reinforcing bar pillar assembly (30) assembled from reinforcing bars (31) The non-composite composite steel pipe pillar (20) provided with non-concrete reinforced concrete (25) was installed by inserting and installing the steel pipe (24) and filling the steel pipe (24) with non-concrete concrete. Insert the penetrating material (16) connected to the girder of the cable-stayed bridge along a plurality of through grooves (not shown) formed at regular intervals on the top of the pillar 20, and then settled into the anchorage (15), the cable-stayed bridge pylon, the main tower of the cable-stayed bridge There is a feature in completing the installation of the pillar 10.

상기 비합성복합강관기둥(20)은 강관(24)의 상하단부(21,22)의 일정높이에 보강커버플레이트(23)를 설치하고, 상기 보강커버플레이트(23)가 설치된 강관내부(27)에 일정한 간격을 두고 전단연결재(26)를 설치하고, 강관(24) 내부에 수직철근(32)과 띠철근(31)으로 조립된 철근기둥조립체(30)를 삽입한 다음, 강관(24) 내부를 무수축콘크리트로 타설충전하여 무수축철근콘크리트(25)가 설치되도록 하여 강관(24)내에 설치된 무수축철근콘크리트(25)와 강관(24)을 일정한 범위에 걸쳐 설치된 강관 상하단부(21,22)의 강관내부(27)에 설치된 전단연결재(26)에 의하여 결합, 합성시키고, 그 이외의 부분인 강관(24)의 중앙부에서는 강관(24)과 무수축철근콘크리트(25)와 결합시키지 않은 비합성상태로 시공한 것이다.The non-composite composite steel pipe pillar 20 has a reinforcement cover plate 23 installed at a predetermined height of the upper and lower ends 21 and 22 of the steel pipe 24, and the steel pipe inner portion 27 in which the reinforcement cover plate 23 is installed. Shear connector (26) is installed at regular intervals, and the reinforcing column assembly (30) assembled with the vertical reinforcing bars (32) and the band reinforcing bars (31) is inserted into the steel pipe (24), and then inside the steel pipe (24). Is poured into non-contraction concrete so that the non-contraction reinforcement concrete (25) is installed so that the non-contraction reinforcement concrete (25) and the steel pipe (24) installed in the steel pipe (24) over a predetermined range (21, 22) Non-bonded and synthesized by the shear connection member 26 installed in the inner steel pipe 27 of the (), the central portion of the steel pipe 24 that is other than the steel pipe 24 and the non-concrete reinforced concrete 25 It was constructed in a synthetic state.

결과적으로 사장교파이론기둥은 기둥에 축력작용시 강관과 강관내에 설치된 무수축철근콘크리트가 별개로 각각 작용하여 상기 작용하는 축력에 저항하되 한 기둥구조체내에서 복합적으로 작용거동하도록 한 것이다.As a result, the cable-stayed pylon column is designed to resist the axial force acting separately by the steel pipe and the non-concrete reinforced concrete installed in the steel pipe, respectively, when acting on the pillar.

이하, 본 발명의 구성 및 작용을 첨부된 도면에 의하여 상세히 설명하면 다음과 같다.Hereinafter, the configuration and operation of the present invention will be described in detail by the accompanying drawings.

도 1은 본 발명의 비합성복합강관기둥을 사장교의 주탑인 사장교파이론기둥으로 사용하여 사장교의 사장재를 설치한 것을 보여주는 도면으로서, 주탑인 사장교파이론기둥(10)을 설치하기 위하여 기초(11)를 설치하고, 기초 상부에 연결플레이트(13)를 매설하면서 연결플레이트와 연결된 앵커볼트(12)를 기초(11)내에 매설하고, 상하단부(21,22)에 일정한 높이의 보강커버플레이트(23)가 각각 용접설치되 고, 상기 보강커버플레이트(23)가 설치된 강관내부(27)에 일정한 간격을 두고 전단연결재(26)를 설치하고, 강관 하단부(21,22)의 일정한 높이로 설치된 보강커버플레이트(23)와 강관(24)의 하부에 설치된 연결플레이트(13)와의 직각부에 일정한 간격을 두고 앵커브라켓(14)을 다수개 설치한 일정 높이의 강관(24)의 하부에 설치된 연결플레이트(13)를 상기 기초(11) 위에 설치된 연결플레이트(13)와 밀착고정되도록 연결볼트(17)로 고정설치하고, 수직철근(32)과 일정한 간격을 두고 설치된 띠철근(31)으로 조립된 철근기둥조립체(30)를 강관(24) 내부에 삽입설치하고, 강관(24)내부를 무수축콘크리트로 충전타설하여 무수축철근콘크리(25)가 설치된 비합성복합강관기둥(20)을 설치한 다음, 상기 강관(24) 기둥의 상부에 일정한 간격을 두고 다수개 형성된 관통홈(미도시)을 따라 사장교의 거더에 연결된 사장재(16)를 삽입관통시킨 다음 정착구(15)로 정착하여 사장교의 주탑인 비합성복합강관기둥(20)을 설치하여 사장재의 설치가 완료되는 것이다.Figure 1 is a view showing the installation of the cable-stayed cable-stayed bridge using the non-composite composite steel pipe pillar of the present invention as the cable-stayed bridge pylon pillar, the foundation (11) to install the cable-stayed bridge pylon pillar 10 And install the anchor plate 12 connected to the connecting plate in the base 11 while embedding the connecting plate 13 on the upper portion of the foundation, and the reinforcement cover plate 23 having a constant height at the upper and lower ends 21 and 22. Are welded to each other, the reinforcement cover plate is installed at a constant height of the steel pipe lower ends (21, 22) and the shear connection member 26 is installed at regular intervals in the steel pipe inner portion 27, the reinforcement cover plate 23 is installed. Connection plate 13 installed in the lower portion of the steel pipe 24 of a predetermined height in which a plurality of anchor brackets 14 are installed at regular intervals at right angles to the connection plate 13 installed on the lower portion of the steel pipe 24 and (23). Above the base 11 Steel pipe 24 is fixed to the connection plate (13) is installed and fixed to the connection bolt (17) to be fixed, and the reinforcing column assembly (30) assembled with a band reinforcement (31) installed at regular intervals with the vertical reinforcement (32) Inserted and installed inside, and filling the inside of the steel pipe (24) with non-concrete concrete to install a non-composite composite steel pipe column (20) in which the non-concrete reinforced concrete (25) is installed, and then on the top of the steel pipe (24) pillar Insert the through-fill material (16) connected to the girder of the cable-stayed bridge along a plurality of through grooves (not shown) at regular intervals, and then settled to the anchorage (15) to form a non-composite composite steel pipe pillar (20), which is the main tower of the cable-stayed bridge. After installation, the installation of the presidential material is completed.

도 2는 본 발명의 비합성복합강관기둥을 상세히 보여주는 도면으로서, 강관(24)의 상하단부(21,22)의 일정높이에 보강커버플레이트(23)를 설치하고, 상기 보강커버플레이트(23)가 설치된 강관내부(27)에 일정한 간격을 두고 전단연결재(26)를 설치하고, 강관(24) 내부에 수직철근(32)과 띠철근(31)으로 조립된 철근기둥조립체(30)를 삽입한 다음, 강관(24) 내부를 무수축콘크리트로 타설충전하여 무수축철근콘크리트(25)가 설치되도록 하여 강관(24) 내에 설치된 무수축철근콘크리트(25)와 강관(24)을 일정한 범위에 걸쳐 설치된 강관 상하단부(21,22)의 강관 내부(27)에 설치된 전단연결재(26)에 의하여 결합, 합성시키고, 그 이외의 부분인 강관의 중앙부에서는 강관(24)과 무수축철근콘크리트(25)와 결합시키지 않은 비합성상태인 것이다.2 is a view showing the non-composite composite steel pipe pillar of the present invention in detail, the reinforcement cover plate 23 is installed at a predetermined height of the upper and lower ends 21 and 22 of the steel pipe 24, and the reinforcement cover plate 23 is shown. Shear connector 26 is installed at regular intervals in the inner steel pipe 27 is installed, and the reinforcing column assembly 30 assembled with the vertical reinforcing bar 32 and the band reinforcing bar 31 is inserted into the steel pipe 24. Next, the steel pipe 24 is poured into non-concrete concrete so that the non-concrete reinforced concrete 25 is installed so that the non-concrete reinforced concrete 25 and the steel pipe 24 installed in the steel pipe 24 are installed over a predetermined range. The steel pipes 24 and the non-reinforced concrete 25 and the steel pipes 24 and the non-reinforced concrete 25 are joined and synthesized by the shear connecting members 26 installed in the steel pipes 27 in the upper and lower ends 21 and 22 of the steel pipes. It is a nonsynthetic state that is not bound.

상기 강관(24)내에 삽입된 철근기둥조립체(30)에 충전된 것이 무수축콘크리트인 것은 충전되고 난 다음 양생과정에서 콘크리트가 수축되어 강관(24) 내에 동공이 발생되거나 철근기둥조립체(30)와 강관(24) 간의 공극이 발생되는 것을 방지하여 무수축콘크리트를 타설하여 강관(24) 내에서 철근기둥조립체(30)가 타설된 무수축콘트리트에 의하여 밀실하게 강관(24) 내에 빈틈없이 타설양생되도록 하여 작용하는 외력에 대하여 각각의 부재의 특성을 100%발휘하여 당초 계획된 지지하중을 발휘할 수 있도록 하기 위함이다.Filled in the reinforcement pillar assembly 30 inserted into the steel pipe 24 is the non-contraction concrete is filled and then the concrete shrinks in the curing process to generate a pupil in the steel pipe 24 or the reinforcement pillar assembly 30 and By preventing the generation of voids between the steel pipes 24, the non-concrete concrete is poured so that the reinforcement pillar assembly 30 in the steel pipe 24 is tightly poured in the steel pipe 24 tightly by the non-contraction concrete in which the steel pillars 24 are poured. This is to exert 100% of each member's characteristics against external force acting in order to exert the originally planned support load.

또한, 강관의 상하단부(21,22)의 일정한 높이에 걸쳐 보강커버플레이트(23)를 설치하여 강관의 상하단부(21,22)를 보강하도록 하고, 상기 보강커버플레이트(23)의 면적에 해당하는 강재내부(27)면에 일정한 간격을 두고 전단연결재(26)인 링형돌출부(28)를 설치하여 강관내부에 설치된 무수축철근콘크리트(25)와 상호 연결하도록 하는 것은, 본 발명과 같이 사장교파이론기둥(10)은 기둥부재로서 수직의 힘인 압축력에 주로 저항하는 부재로서, 휨부재와 달리 부재상호간에 연결되지 않은 비합성상태의 부재를 이용하여도 구조역학적으로 전혀 문제가 되지 않은 즉, 외력에 대하여 비합성상태에서 각각의 부재의 재료의 특성에 따라 일체적으로 작용하게되어 구조적인 취약점이 전혀발생하지 않으나, 강관기둥이 압축력에 보다 강하게 효과적으로 저항하기 위하여 강관의 상하단부에 보강커버플레이트(23)로 강성을 보강하도록 하면서 강관내부(27)에는 전단연결재(26)로 무수축철근콘크리트(25)와 상 호 연결되도록 한 것이다. In addition, by installing a reinforcement cover plate 23 over a certain height of the upper and lower ends 21 and 22 of the steel pipe to reinforce the upper and lower ends 21 and 22 of the steel pipe, corresponding to the area of the reinforcing cover plate 23. To provide a ring-shaped protrusion 28, which is a shear connector 26, at regular intervals on the inner surface of the steel 27 to be interconnected with the non-concrete reinforced concrete 25 installed in the steel pipe, the cable-stayed pylon as in the present invention. The pillar 10 is a pillar member that mainly resists a compressive force, which is a vertical force. Unlike the bending member, the pillar 10 has no structural problems at all, even when using non-synthetic members that are not connected to each other. In the case of non-synthetic state, it works integrally according to the characteristics of the material of each member, so that no structural weakness occurs, but the steel pipe pillars can effectively resist the compressive force more effectively. It is one such as to reinforce the rigidity by the reinforcing cover plate 23 on the lower end of the steel tube inside the steel pipe 27 is connected with mutual non-contraction RC 25 to the shear connector (26).

도 3은 본 발명의 비합성복합강관기둥의 상단부와 하단부에 설치된 전단연결재를 보여주는 도면으로서, 강관의 상하단부(21,22)의 일정한 높이에 걸쳐 보강커버플레이트(23)를 설치한 면적에 해당하는 강재내부(27)면에 일정한 간격을 두고 전단연결재(26)인 링형돌출부(28)를 다수개 설치한 것이다.Figure 3 is a view showing the shear connection material installed in the upper end and the lower end of the non-composite composite steel pipe pillar of the present invention, corresponding to the area where the reinforcement cover plate 23 is installed over a certain height of the upper and lower ends (21, 22) To install a plurality of ring-shaped projections 28, which are the shear connection member 26 at regular intervals on the steel inner surface 27.

상기와 같이 강관내부(27)면에 전단연결재(26)를 설치하여 강관내부에 설치된 무수축철근콘크리트(25)와 상호 연결하도록 한 것은, 강관기둥이 압축력에 보다 강하게 효과적으로 저항하기 위하여 강관의 상하단부에 보강커버플레이트(23)로 강성을 보강하도록 하면서 강관내부(27)에는 전단연결재(26)로 무수축철근콘크리트(25)와 상호 연결되도록 한 것이다.As described above, the shear connection member 26 is installed on the inner surface of the steel pipe so as to interconnect with the non-concrete reinforced concrete 25 installed in the steel pipe, so that the steel pipe pillar can effectively resist the compressive force more effectively. Reinforcing the rigidity with the reinforcing cover plate 23 at the lower end is to be connected to the non-reinforced concrete 25 as a shear connector 26 in the steel pipe inner 27.

상기 전단연결재는 강관내부에 일정한 간격을 두고 강관내부면을 감싸는 링형돌출부이다.The shear connector is a ring-shaped protrusion that surrounds the inner surface of the steel pipe at regular intervals inside the steel pipe.

도 4는 본 발명의 비합성복합강관기둥내에 철근을 조립하여 철근기둥조립체를 설치한 것을 보여주는 도면으로서, 강관내부에 삽입설치될 수 있도록 일정한 간격을 두고 수직으로 원형상의 수직철근(32)을 배치하고, 상기 수직철근(32)을 상하로 일정한 간격마다 연결한 띠철근(31)을 설치하여 조립된 철근기둥조립체(30)인 것이다.Figure 4 is a view showing the reinforcement column assembly is installed by assembling the reinforcing bars in the non-composite composite steel pipe pillar of the present invention, vertically arranged vertical vertical bars 32 at regular intervals to be inserted into the steel pipe In addition, the vertical reinforcing bar 32 is a reinforcing column assembly 30 assembled by installing a band reinforcing bar 31 connected at regular intervals up and down.

본 발명은 강관의 상하단부 내부에 전단연결재를 설치하여 강관내부에 삽입된 철근기둥조립체에 타설된 무수축콘크리트에 의하여 형성된 무수축철근콘크리트 의 상하단부와 강관이 상호연결된 합성으로 하고, 강관의 중앙부는 연결이 안된 비합성상태로 시공한 비합성복합강관기둥을 압축부재인 사장교파이론기둥으로 사용하여 교량구조역학적인 면에서 효율성이 있으면서 시공성이 향상되어 이로인하여 공사비가 절감되는 비합성복합강관기둥시공방법인 것이다.The present invention is a composite of the upper and lower ends of the non-shrink reinforced concrete formed by the non-shrink concrete is formed by the non-shrink concrete placed in the reinforcing column assembly inserted into the steel pipe by installing a shear connector in the upper and lower ends of the steel pipe, the center portion of the steel pipe The non-composite composite steel pipe pillar, which is constructed in an unconnected non-synthetic state, is used as a cable-stayed cable pylon pillar, which is a compression member, and has an efficient construction in terms of bridge structural dynamics. It is a way.

Claims (5)

사장교의 주탑인 사장교파이론기둥(10)을 설치하기 위하여 기초(11)를 설치하고, 기초 상부에 연결플레이트(13)를 매설하면서 연결플레이트와 연결된 앵커볼트(12)를 기초(11)내에 매설하고, In order to install the cable-stayed bridge pylon pillar 10, which is the main tower of the cable-stayed bridge, the foundation 11 is installed, and the anchor bolt 12 connected to the connection plate is embedded in the foundation 11, while the connection plate 13 is buried in the upper part of the foundation. , 상하단부(21,22)에 일정한 높이의 보강커버플레이트(23)가 각각 용접설치되고, Reinforcement cover plates 23 of constant height are welded to upper and lower ends 21 and 22, respectively. 상기 보강커버플레이트(23)가 설치된 강관내부(27)에 일정한 간격을 두고 전단연결재(26)를 설치하고, The reinforcing cover plate 23 is provided with a shear connecting member 26 at regular intervals in the inner steel pipe 27 is installed, 강관 하단부(21,22)의 일정한 높이로 설치된 보강커버플레이트(23)와 강관(24)의 하부에 설치된 연결플레이트(13)와의 직각부에 일정한 간격을 두고 앵커브라켓(14)을 다수개 설치한 일정 높이의 강관(24)과,A plurality of anchor brackets 14 are provided at regular intervals at a right angle between the reinforcing cover plate 23 installed at a constant height of the lower ends of the steel pipes 21 and 22 and the connecting plate 13 installed at the lower part of the steel pipe 24. Steel pipe 24 of constant height, 상기 강관의 하부에 설치된 연결플레이트(13)를 상기 기초(11) 위에 설치된 연결플레이트(13)와 밀착고정되도록 연결볼트(17)로 고정설치하고, The connection plate 13 installed in the lower portion of the steel pipe fixed to the connection bolt 17 to be fixed in close contact with the connection plate 13 installed on the base 11, 상기 강관(24) 내부에 철근기둥조립체를 삽입설치하고, 강관(24)내부를 무수축콘크리트로 충전타설하여 무수축철근콘크리(25)가 설치된 비합성복합강관기둥(20)을 설치한 다음, Insert and install the reinforcing column assembly inside the steel pipe 24, and filling the steel pipe 24 inside the non-contraction concrete to install a non-composite composite steel pipe column (20) in which the non-contraction reinforcing concrete (25) is installed, 상기 강관(24) 기둥의 상부에 일정한 간격을 두고 다수개 형성된 관통홈(미도시)을 따라 사장교의 거더에 연결된 사장재(16)를 삽입관통시킨 다음 정착구(15)로 정착하여 사장교의 주탑인 비합성복합강관기둥(20)을 설치하는 것에 특징이 있 는 양단이 결합된 철근콘크리트속채움 비합성복합강관기둥의 시공방법.Insert the through-fill material 16 connected to the girder of the cable-stayed bridge along a plurality of through grooves (not shown) formed at a predetermined interval on the upper portion of the steel pipe 24, and then settled into the anchorage 15 to be the main tower of the cable-stayed bridge A method of constructing a non-composite composite steel tube pillar, in which both ends are combined with reinforced concrete, characterized in that the non-composite composite steel tube pillar (20) is installed. 제 1항에 있어서,The method of claim 1, 상기 비합성복합강관기둥은 강관(24)의 상하단부(21,22)의 일정높이에 보강커버플레이트(23)를 설치하고, 상기 보강커버플레이트(23)가 설치된 강관내부(27)에 일정한 간격을 두고 전단연결재(26)를 설치하고, 강관(24) 내부에 수직철근(32)과 띠철근(31)으로 조립된 철근기둥조립체(30)를 삽입한 다음, 강관(24) 내부를 무수축콘크리트로 타설충전하여 무수축철근콘크리트(25)가 설치되도록 한 것에 특징이 있는 양단이 결합된 철근콘크리트속채움 비합성복합강관기둥의 시공방법.The non-composite composite steel pipe column is provided with a reinforcement cover plate 23 at a predetermined height of the upper and lower ends 21 and 22 of the steel pipe 24, and a predetermined interval in the steel pipe inner portion 27 where the reinforcement cover plate 23 is installed. Then, the shear connector 26 is installed, and the reinforcing column assembly 30 assembled with the vertical reinforcing bars 32 and the band reinforcing bars 31 is inserted into the steel pipe 24, and then the inside of the steel pipe 24 is unshrunk. A method of constructing a non-composite composite steel pipe pillar, in which both ends are combined, characterized in that the non-concrete reinforced concrete (25) is installed by filling with concrete. 제 1항 또는 제 2항에 있어서The method according to claim 1 or 2 상기 비합성복합강관기둥은 강관(24)내에 설치된 무수축철근콘크리트(25)와 강관 상하단부의 내부의 일정한 범위에 걸쳐 설치된 전단연결재(26)에 의하여 강관과 무수축철근콘크리트와 결합합성되고, 그 이외의 강관 중앙부에서는 강관(24)과 무수축철근콘크리트(25)가 결합되지 않은 비합성상태인 것에 특징이 있는 양단이 결합된 철근콘크리트속채움 비합성복합강관기둥의 시공방법.The non-composite composite steel pipe pillar is combined with the steel pipe and the non-reinforced concrete by the non-reinforced reinforced concrete 25 installed in the steel pipe 24 and the shear connection member 26 provided over a predetermined range inside the upper and lower ends of the steel pipe, Construction method of the non-composite composite steel pipe pillars in which both ends are combined in a non-synthetic state in which the steel pipe 24 and the non-contracted reinforced concrete 25 are not bonded at the other center of the steel pipe. 제 1항 또는 제 2항에 있어서,The method according to claim 1 or 2, 상기 보강커버플레이트가 설치된 범위에 해당하는 강관내부에 전단연결재를 설치하고, 그 이외의 강관내부에는 전단연결재를 설치하지 않은 것에 특징이 있는 양단이 결합된 철근콘크리트속채움 비합성복합강관기둥의 시공방법.The construction of the reinforced concrete inner composite non-composite composite steel pipe column, which is coupled to both ends, characterized in that the shear connector is installed in the steel pipe corresponding to the range where the reinforcement cover plate is installed, and the shear connector is not installed in the other steel pipe. Way. 제 1항 또는 제 2항에 있어서,The method according to claim 1 or 2, 상기 전단연결재는 강관내부에 일정한 간격을 두고 강관내부면을 감싸는 링형돌출부인 것에 특징이 있는 양단이 결합된 철근콘크리트속채움 비합성복합강관기둥의 시공방법.The shear connector is a method of constructing a composite composite steel tube pillar reinforced reinforced concrete both ends are characterized in that the ring-shaped protrusions surrounding the inner surface of the steel pipe at regular intervals inside the steel pipe.
KR1020060090059A 2006-09-18 2006-09-18 Non-synthetic complex steel pipe columm having tie ends for filling a steel soncrete and construction method thereof KR100662811B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020060090059A KR100662811B1 (en) 2006-09-18 2006-09-18 Non-synthetic complex steel pipe columm having tie ends for filling a steel soncrete and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020060090059A KR100662811B1 (en) 2006-09-18 2006-09-18 Non-synthetic complex steel pipe columm having tie ends for filling a steel soncrete and construction method thereof

Publications (1)

Publication Number Publication Date
KR100662811B1 true KR100662811B1 (en) 2006-12-29

Family

ID=37815869

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020060090059A KR100662811B1 (en) 2006-09-18 2006-09-18 Non-synthetic complex steel pipe columm having tie ends for filling a steel soncrete and construction method thereof

Country Status (1)

Country Link
KR (1) KR100662811B1 (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100962514B1 (en) * 2009-11-06 2010-06-14 (주)범건축종합건축사사무소 Concrete column unit and producing apparatus and producing method for the same
KR101127923B1 (en) * 2009-07-01 2012-03-21 주식회사 포스코건설 Pylon of cable-stayed bridge having composite combination structure and construction method thereof
KR101131829B1 (en) 2009-02-26 2012-03-30 엘아이지건설 주식회사 base plate and RCreinforce concrete construction method
CN103790115A (en) * 2014-02-20 2014-05-14 中铁十局集团第三建设有限公司 Assistive device for installing cable-stayed bridge steel tower combination section
CN104818675A (en) * 2015-02-13 2015-08-05 中交路桥华南工程有限公司 Assembling method of rebar segments
KR101730006B1 (en) * 2015-06-25 2017-04-25 황문삼 Concrete strut
CN107253026A (en) * 2017-06-23 2017-10-17 江苏中铁山桥重工有限公司 A kind of multidirectional four anchor heads overall steel anchor beam preparation method
CN108018780A (en) * 2017-12-15 2018-05-11 中交二航局第四工程有限公司 A kind of steel tower column design and construction method of bolting and welding
CN108797350A (en) * 2018-06-01 2018-11-13 广州市第二市政工程有限公司 Stiff skeleton device and its construction method inside and outside a kind of king-post
KR20180131672A (en) * 2017-05-30 2018-12-11 주식회사 포스코 Concrete filled steel tube column and steel tube column structure
CN111021234A (en) * 2019-12-18 2020-04-17 重庆大学 Self-resetting circular steel tube restrained reinforced concrete pier externally-wrapped column base node
CN111622083A (en) * 2020-05-21 2020-09-04 大连理工大学 Device and method for solidifying steel box girder and concrete bridge pier

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101131829B1 (en) 2009-02-26 2012-03-30 엘아이지건설 주식회사 base plate and RCreinforce concrete construction method
KR101127923B1 (en) * 2009-07-01 2012-03-21 주식회사 포스코건설 Pylon of cable-stayed bridge having composite combination structure and construction method thereof
KR100962514B1 (en) * 2009-11-06 2010-06-14 (주)범건축종합건축사사무소 Concrete column unit and producing apparatus and producing method for the same
CN103790115A (en) * 2014-02-20 2014-05-14 中铁十局集团第三建设有限公司 Assistive device for installing cable-stayed bridge steel tower combination section
CN103790115B (en) * 2014-02-20 2015-12-09 中铁十局集团第三建设有限公司 Cable stayed bridge head tower adapter section installation accessory
CN104818675A (en) * 2015-02-13 2015-08-05 中交路桥华南工程有限公司 Assembling method of rebar segments
KR101730006B1 (en) * 2015-06-25 2017-04-25 황문삼 Concrete strut
KR102020441B1 (en) * 2017-05-30 2019-09-11 주식회사 포스코 Concrete filled steel tube column and steel tube column structure
KR20180131672A (en) * 2017-05-30 2018-12-11 주식회사 포스코 Concrete filled steel tube column and steel tube column structure
CN107253026B (en) * 2017-06-23 2019-03-19 江苏中铁山桥重工有限公司 A kind of multidirectional four anchor heads overall steel anchor beam production method
CN107253026A (en) * 2017-06-23 2017-10-17 江苏中铁山桥重工有限公司 A kind of multidirectional four anchor heads overall steel anchor beam preparation method
CN108018780A (en) * 2017-12-15 2018-05-11 中交二航局第四工程有限公司 A kind of steel tower column design and construction method of bolting and welding
CN108018780B (en) * 2017-12-15 2019-04-16 中交二航局第四工程有限公司 A kind of steel tower column design and construction method of bolting and welding
CN108797350A (en) * 2018-06-01 2018-11-13 广州市第二市政工程有限公司 Stiff skeleton device and its construction method inside and outside a kind of king-post
CN111021234A (en) * 2019-12-18 2020-04-17 重庆大学 Self-resetting circular steel tube restrained reinforced concrete pier externally-wrapped column base node
CN111622083A (en) * 2020-05-21 2020-09-04 大连理工大学 Device and method for solidifying steel box girder and concrete bridge pier

Similar Documents

Publication Publication Date Title
KR100662811B1 (en) Non-synthetic complex steel pipe columm having tie ends for filling a steel soncrete and construction method thereof
KR100713692B1 (en) A prestresed connection set bridge post using unit filled concrete with internally confined hollow and a method for construction
CN110541354B (en) Single-section prefabricated anti-seismic pier and construction method thereof
KR101339946B1 (en) Precast bridge post
KR20110103000A (en) Precast bridge joint structure with composite hollow concrete filled tube and a construction method for the same
KR101170922B1 (en) The rahmen bridge construction technique for which tendon and the connection support stand was used
KR100854224B1 (en) Precast half depth cantilever deck and constructing method of such bridge deck
KR101478131B1 (en) Construction Method of Precast Pier
KR100862005B1 (en) Manufacturing method of segmental internally confined hollow concrete filled tube
KR101183785B1 (en) Fixing structure for column to footing and column-footing connecting structure using the same
KR101086646B1 (en) Prestress concrete composite girder with prestress non-introducing portion provided at both ends, manufacturing method thereof, and built-up type slab bridge construction method using the same
KR100653283B1 (en) Method for connecting reinforced concrete structures
JP2010261270A (en) Composite structure and method for constructing composite structure building
KR101472027B1 (en) Method of building concrete structure using attachment plates adjoining ends of concrete beam with walls of abutments
KR101157607B1 (en) Prestressed steel composite girder with prestressed non-introducing portions provided at both ends of lower flange casing concrete, manufacturing method thereof, and Rahmen structure and construction method thereof
JP7194531B2 (en) Seismic isolation upper foundation structure and manufacturing method thereof, footing structure, and seismic isolation foundation construction method
CN114045750B (en) Construction method of high pier column tie beam
JP7144341B2 (en) Concrete floor slab joint structure and concrete floor slab joint method
KR101357637B1 (en) Horizontal shear connector for precast concrete bridge pier
KR100599768B1 (en) Hollow type Composite Pier Structure using Precast Concrete Form and Constructing Method therefor
KR20080000243A (en) Reinforced soil pier and the bridge construction method therewith
JP2006169837A (en) Column-beam joint structure of reinforced concrete construction
KR200435076Y1 (en) Complex pile commected integral steel pile to prestressed concrete composite pile
KR100541162B1 (en) Composite Beam Stiffened with Prestressed Concrete Panel Having Embedded Lower Flange and Constructing Method thereof
KR101131630B1 (en) Prestressed concrete panel with prestress non-introducing portions provided in both slope ends, manufacturing method thereof, precasted Rahmen and construction method thereof using the same

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20121204

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20131210

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20141203

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20151202

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20161102

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20181101

Year of fee payment: 13