CN108018780A - A kind of steel tower column design and construction method of bolting and welding - Google Patents

A kind of steel tower column design and construction method of bolting and welding Download PDF

Info

Publication number
CN108018780A
CN108018780A CN201711346711.4A CN201711346711A CN108018780A CN 108018780 A CN108018780 A CN 108018780A CN 201711346711 A CN201711346711 A CN 201711346711A CN 108018780 A CN108018780 A CN 108018780A
Authority
CN
China
Prior art keywords
segment
connecting structure
strength bolt
bolt connecting
welding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711346711.4A
Other languages
Chinese (zh)
Other versions
CN108018780B (en
Inventor
李有为
张鸿
唐启
尤田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Second Harbor Engineering Co
CCCC SHEC Fourth Engineering Co Ltd
CCCC Highway Long Bridge Construction National Engineering Research Center Co Ltd
Original Assignee
CCCC Second Harbor Engineering Co
CCCC SHEC Fourth Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Second Harbor Engineering Co, CCCC SHEC Fourth Engineering Co Ltd filed Critical CCCC Second Harbor Engineering Co
Priority to CN201711346711.4A priority Critical patent/CN108018780B/en
Publication of CN108018780A publication Critical patent/CN108018780A/en
Application granted granted Critical
Publication of CN108018780B publication Critical patent/CN108018780B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/14Towers; Anchors ; Connection of cables to bridge parts; Saddle supports
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/02Structures made of specified materials
    • E04H12/08Structures made of specified materials of metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/34Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
    • E04H12/342Arrangements for stacking tower sections on top of each other
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/30Metal

Abstract

The invention discloses a kind of steel tower column design and construction method of bolting and welding, belong to science of bridge building or other structural steelwork fields, between steel tower column segment and segment, first pass through a small amount of high-strength bolt connecting structure connection, to undertake the dead weight of two to three segment head tower segments thereon, in this way, certain segment is after installation is complete, without waiting for the segment and the indirect seam welding in next segment, you can carry out segment installation.After in certain segment, installation is complete, first pass through high-strength bolt connecting structure to be connected with next segment, thereafter, while a segment on continuing lifting, and then the Partial seams welding in addition to high-strength bolt connecting structure between the segment and next segment is carried out, until its welding finishes.After seam welds beyond high-strength bolt connecting structure, high-strength bolt connecting structure is removed, and the area joints are welded, so completes the welding of tunneling boring weld seam.The present invention not only has extremely low project cost and maintenance difficulties, but also has high construction efficiency.

Description

A kind of steel tower column design and construction method of bolting and welding
Technical field
The invention belongs to science of bridge building or other structural steelwork fields, in particular to a kind of steel tower column design and construction side Method.
Background technology
Steel tower column is widely used in science of bridge building, and because steel tower column height is high, construction weight is big, and generally use " is divided at present Segment factory manufacture, segmented assembly at the scene connect height " design and construction method.When segmented scene connects high, generally there is two Kind connection method, a kind of method that method is welded to connect between segment, another method are connected between segment using high-strength bolt Method.
For being welded to connect, because the girth welding cycle is grown, and steel construction segment lifting assembled speed is relatively fast, to steel King-post installation period, which is formed, to be restricted, and if certain steel tower column segment under normal circumstances is after installation is complete, generally requires to wait 4-5 days or very To the longer time, the segment and next segment (note are treated:Next segment refers in following segment) after the completion of seam welds, Fang Nengjin The upper segment of row (note:A upper segment refers in segment above) installation, head tower weld during tower crane be in idle state, by welding Control critical circuits are connect, so as to restrict installation speed.
For high-strength bolt connection, installation progress is very fast for it is welded to connect relatively, the duration is restricted small.But because complete Section is all connected using high-strength bolt, and high-strength bolt connecting structure input amount is huge, increases cost, and increase later maintenance is difficult Degree, and harmful effect is caused to steel tower column appearance.And if wait tunneling boring high-strength bolt is all applied after twisting, then install one Segment, will also restrict the duration to a certain extent.
The content of the invention
It is an object of the invention to:It is proposed a kind of head tower column construction method of bolting and welding, both made with extremely low engineering Valency and maintenance difficulties, and there is high construction efficiency.
The object of the invention is realized by following technical proposals:
A kind of steel tower column design and construction method of bolting and welding, it is characterised in that comprise the following steps successively, wherein n is just Integer:
Step 1:The (n+1)th segment is lifted, and is connected by part high-strength bolt connecting structure with the n-th segment, high-strength bolt The dosage of connecting structure need to only meet the dead weight for undertaking two to three segment head tower segments thereon;
Step 2:The n-th+2 segment is lifted, and is connected by part high-strength bolt connecting structure with the (n+1)th segment, high-strength spiral shell The dosage of bolt connecting structure need to only meet the dead weight for undertaking two to three segment head tower segments thereon;Meanwhile carry out the n-th segment with Except high-strength bolt connecting structure is with the girth welding of exterior domain between (n+1)th segment;
This stage, the gravity load of the (n+1)th segment and the n-th+2 segment are undertaken by high-strength bolt connecting structure, welded The n-th segment and the (n+1)th intersegmental weld seam do not undertake upper load;
Step 3:Continue the n-th+3 segment of lifting, and be connected by part high-strength bolt connecting structure with the n-th+2 segment, it is high The dosage of strength bolt connecting structure need to only meet the dead weight for undertaking two to three segment head tower segments thereon;Meanwhile carry out (n+1)th Except high-strength bolt connecting structure is with the girth welding of exterior domain between segment and the n-th+2 segment, this in stage the n-th segment with the (n+1)th section The intersegmental weld seam in addition to high-strength bolt connecting structure finishes welding, alternatively, removing high-strength spiral shell between the n-th segment and the (n+1)th segment Weld seam beyond bolt connecting structure can be completed before the n-th+3 segment lifting;
This stage, the (n+1)th segment, the n-th+2 segment, the gravity load of the n-th+3 segment are undertaken by high-strength bolt connecting structure, The n-th segment welded does not undertake top lotus with the (n+1)th intersegmental weld seam, the (n+1)th segment and the n-th+2 intersegmental weld seam Carry;
Step 4:Continue the n-th+4 segment of lifting, and be connected by part high-strength bolt connecting structure with the n-th+3 segment, it is high The dosage of strength bolt connecting structure need to only meet the dead weight for undertaking two to three segment head tower segments thereon;Meanwhile carry out n-th+2 Except high-strength bolt connecting structure is with the girth welding of exterior domain between segment and the n-th+3 segment, this, the (n+1)th segment was with n-th+2 in stage Weld seam between segment in addition to high-strength bolt connecting structure finishes welding, alternatively, except height between the (n+1)th segment and the n-th+2 segment Weld seam beyond strength bolt connecting structure can be completed before the n-th+4 segment lifting;
In this stage, the n-th segment and the intersegmental high-strength bolt connecting structure of n+1 are removed, seam crossing above segment weight Amount, which is transferred to, has welded the weld seam of completion and has undertaken;After high-strength bolt connecting structure is removed, the area joints welding is carried out, until should All welding finishes seam at the merogenesis of segment;
Step 5:According to abovementioned steps, similarly promote, carry out the connection construction of other head tower segments.
Alternatively, when high-strength bolt connecting structure releases between certain segment, solder joint length reaches entirely between the segment Section length is 80% or even more than 90%.
In the method for the present invention, between steel tower column segment and segment, a small amount of high-strength bolt connecting structure connection is first passed through, to undertake The dead weight of two to three segment head tower segments thereon, without whole high-strength bolt connecting structure of constructing, in this way, certain segment is pacified After the completion of dress, without waiting for the segment and the indirect seam welding in next segment, you can carry out segment installation.Installed in certain segment After the completion of, first pass through high-strength bolt connecting structure and be connected with next segment, thereafter, while a segment on continuing lifting, tightly Then the Partial seams welding in addition to high-strength bolt connecting structure between the segment and next segment is carried out, until its welding finishes. After seam welds beyond high-strength bolt connecting structure, high-strength bolt connecting structure is removed, and the area joints are welded, So complete the welding of tunneling boring weld seam.In the case of general progress, when certain segment tunneling boring weld seam welding finishes, it newly pacifies above Fill segment and save left and right in 2-3, therefore, when actual design is constructed, consider that high-strength bolt connecting structure undertakes the head tower dead weight of 2-3 segments .Moreover, when high-strength bolt connecting structure releases, solder joint length reaches tunneling boring length 80% or even 90% More than, and seam crossing stress level is very low at this time, there is no at high-strength bolt connecting structure with other first welding regions because Weld it is asynchronous and caused by stress state difference condition, do not influence structural stress state.
The foregoing main solution of the present invention and further alternatives thereof can be freely combined to form multiple schemes, be this The scheme that invention can be used and is claimed;And the present invention, between (each non conflicting selection) selection and between other selections It can also be freely combined.Those skilled in the art can understand have after the present invention program is understood according to the prior art and common knowledge Multiple combinations, are the claimed technical solution of the present invention, do not do exhaustion herein.
Beneficial effects of the present invention:Not only there is extremely low project cost and maintenance difficulties, but also there is high construction efficiency.
Brief description of the drawings
Fig. 1 is the head tower segment horizontal layout schematic diagram of the embodiment of the present invention;
Fig. 2 is the head tower segment facade arrangement schematic diagram of the embodiment of the present invention;
Fig. 3 is the Construction State schematic diagram of the step 1 of the embodiment of the present invention;
Fig. 4 is the Construction State schematic diagram of the step 2 of the embodiment of the present invention;
Fig. 5 is the Construction State schematic diagram of the step 3 of the embodiment of the present invention;
Fig. 6 is the Construction State schematic diagram of the step 4 of the embodiment of the present invention;
Fig. 7 is the Construction State schematic diagram of the step 5 of the embodiment of the present invention;
Wherein 1 it is head tower segment, 2 be high-strength bolt connecting structure, 3 be segment merogenesis line, 4 be girth welding, 5 is former high Seam welds at strength bolt connecting structure.
Embodiment
Following non-limiting examples are used to illustrate the present invention.
Referring to figs. 1 to shown in 6, a kind of steel tower column design and construction method of bolting and welding, comprises the following steps (this hair successively Bright middle n is positive integer, when the connection from the 1st head tower segment and the 2nd head tower segment uses the method for the present invention, n 1, according to this Analogize.The high-strength bolt, refers to what is manufactured with high strength steel, or needs to impose the bolt of larger pretightning force, belongs to a kind of Standard component.Under normal circumstances, the plain bolt for the load ratio same specification that high-strength bolt can be born is big.Usually by regulation bolt Performance rate more than 8.8 grades person, be known as high-strength bolt):
Step 1, with reference to shown in figure 3:The (n+1)th segment is lifted, and passes through part high-strength bolt connecting structure 2 and the n-th segment Connection, the dosage of high-strength bolt connecting structure 2 need to only meet the dead weight for undertaking two to three segment head tower segments 1 thereon, and nothing The high-strength bolt connecting structure 2 that need to construct whole;
Step 2, with reference to shown in figure 4:The n-th+2 segment is lifted, and is saved by part high-strength bolt connecting structure 2 and (n+1)th Section connection, the dosage of high-strength bolt connecting structure 2 need to only meet the dead weight for undertaking two to three segment head tower segments 1 thereon, and Without whole high-strength bolt connecting structure 2 of constructing;Meanwhile carry out between the n-th segment and the (n+1)th segment except high-strength bolt connection structure 2 are made with the girth welding 4 of exterior domain;
This stage, the gravity load of the (n+1)th segment and the n-th+2 segment are undertaken by high-strength bolt connecting structure 2, welded The n-th segment and the (n+1)th intersegmental weld seam do not undertake upper load;
Step 3, with reference to shown in figure 5:Continue the n-th+3 segment of lifting, and by part high-strength bolt connecting structure 2 and n-th+ 2 segments connect, and the dosage of high-strength bolt connecting structure 2 need to only meet the dead weight for undertaking two to three segment head tower segments 1 thereon, Without whole high-strength bolt connecting structure 2 of constructing;Meanwhile carry out between the (n+1)th segment and the n-th+2 segment except high-strength bolt connects Construction 2 is connect with the girth welding 4 of exterior domain, this in stage the n-th segment and the (n+1)th segment between in addition to high-strength bolt connecting structure Weld seam finishes welding, alternatively, the weld seam between the n-th segment and the (n+1)th segment in addition to high-strength bolt connecting structure is in the n-th+3 section It can be completed before section lifting;
This stage, the (n+1)th segment, the n-th+2 segment, the gravity load of the n-th+3 segment are held by high-strength bolt connecting structure 2 Load, the n-th segment welded do not undertake with the (n+1)th intersegmental weld seam, the (n+1)th segment and the n-th+2 intersegmental weld seam Portion's load;
Step 4, with reference to shown in figure 6:Continue the n-th+4 segment of lifting, and by part high-strength bolt connecting structure 2 and n-th+ 3 segments connect, and the dosage of high-strength bolt connecting structure 2 need to only meet the dead weight for undertaking two to three segment head tower segments 1 thereon, Without whole high-strength bolt connecting structure 2 of constructing;Meanwhile carry out between the n-th+2 segment and the n-th+3 segment except high-strength bolt connects Construction 2 is connect with the girth welding 4 of exterior domain, this in stage the (n+1)th segment and the n-th+2 segment between in addition to high-strength bolt connecting structure Weld seam welding is finished, alternatively, the weld seam between the (n+1)th segment and the n-th+2 segment in addition to high-strength bolt connecting structure is n-th It can be completed before+4 segment liftings;
In this stage, the n-th segment and the intersegmental high-strength bolt connecting structure 2 of n+1 are removed, seam crossing above segment weight Amount, which is transferred to, has welded the weld seam of completion and has undertaken;When high-strength bolt connecting structure 2 releases between the segment, weld and connect between the segment Stitch length and reach tunneling boring length more than 90%.After high-strength bolt connecting structure 2 is removed, the area joints welding is carried out, until All welding finishes seam at the segment merogenesis;
Step 5, with reference to shown in figure 7:According to abovementioned steps, similarly promote, carry out the connection construction of other head tower segments.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention All any modification, equivalent and improvement made within refreshing and principle etc., should all be included in the protection scope of the present invention.

Claims (3)

1. a kind of steel tower column design and construction method of bolting and welding, it is characterised in that comprise the following steps successively, wherein n is just whole Number:
Step 1:The (n+1)th segment is lifted, and is connected by part high-strength bolt connecting structure with the n-th segment, high-strength bolt connection The dosage of construction need to only meet the dead weight for undertaking two to three segment head tower segments thereon;
Step 2:The n-th+2 segment is lifted, and is connected by part high-strength bolt connecting structure with the (n+1)th segment, high-strength bolt connects Connect the dead weight that the dosage of construction need to only meet to undertake two to three segment head tower segments thereon;Meanwhile carry out the n-th segment with n-th+ Except high-strength bolt connecting structure is with the girth welding of exterior domain between 1 segment;
This stage, the gravity load of the (n+1)th segment and the n-th+2 segment are undertaken by high-strength bolt connecting structure, n-th welded Segment does not undertake upper load with the (n+1)th intersegmental weld seam;
Step 3:Continue the n-th+3 segment of lifting, and be connected by part high-strength bolt connecting structure with the n-th+2 segment, high-strength spiral shell The dosage of bolt connecting structure need to only meet the dead weight for undertaking two to three segment head tower segments thereon;Meanwhile carry out the (n+1)th segment Except high-strength bolt connecting structure is with the girth welding of exterior domain between the n-th+2 segment, this in stage the n-th segment and the (n+1)th segment between Weld seam in addition to high-strength bolt connecting structure finishes welding, alternatively, except high-strength bolt connects between the n-th segment and the (n+1)th segment Connecing the weld seam beyond construction can complete before the n-th+3 segment lifting;
This stage, the (n+1)th segment, the n-th+2 segment, the gravity load of the n-th+3 segment are undertaken by high-strength bolt connecting structure, N-th segment of welding does not undertake upper load with the (n+1)th intersegmental weld seam, the (n+1)th segment and the n-th+2 intersegmental weld seam;
Step 4:Continue the n-th+4 segment of lifting, and be connected by part high-strength bolt connecting structure with the n-th+3 segment, high-strength spiral shell The dosage of bolt connecting structure need to only meet the dead weight for undertaking two to three segment head tower segments thereon;Meanwhile carry out the n-th+2 segment Except high-strength bolt connecting structure is with the girth welding of exterior domain between the n-th+3 segment, this in stage the (n+1)th segment with the n-th+2 segment Between weld seam in addition to high-strength bolt connecting structure welding is finished, alternatively, removing high-strength spiral shell between the (n+1)th segment and the n-th+2 segment Weld seam beyond bolt connecting structure can be completed before the n-th+4 segment lifting;
In this stage, the n-th segment and the intersegmental high-strength bolt connecting structure of n+1 are removed, which turns Move to and welded the weld seam of completion and undertake;After high-strength bolt connecting structure is removed, the area joints welding is carried out, until the segment All welding finishes seam at merogenesis;
Step 5:According to abovementioned steps, similarly promote, carry out the connection construction of other head tower segments.
2. the steel tower column design and construction method of bolting and welding as claimed in claim 1, it is characterised in that:It is high-strength between certain segment When bolt connection structure releases, solder joint length reaches tunneling boring length more than 80% between the segment.
3. the steel tower column design and construction method of bolting and welding as claimed in claim 2, it is characterised in that:It is high-strength between certain segment When bolt connection structure releases, solder joint length reaches tunneling boring length more than 90% between the segment.
CN201711346711.4A 2017-12-15 2017-12-15 A kind of steel tower column design and construction method of bolting and welding Active CN108018780B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711346711.4A CN108018780B (en) 2017-12-15 2017-12-15 A kind of steel tower column design and construction method of bolting and welding

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711346711.4A CN108018780B (en) 2017-12-15 2017-12-15 A kind of steel tower column design and construction method of bolting and welding

Publications (2)

Publication Number Publication Date
CN108018780A true CN108018780A (en) 2018-05-11
CN108018780B CN108018780B (en) 2019-04-16

Family

ID=62073733

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711346711.4A Active CN108018780B (en) 2017-12-15 2017-12-15 A kind of steel tower column design and construction method of bolting and welding

Country Status (1)

Country Link
CN (1) CN108018780B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110904857A (en) * 2019-12-30 2020-03-24 中国铁建投资集团有限公司 Temporary buckling tower installation method for self-anchored suspension bridge construction
CN112692521A (en) * 2020-12-23 2021-04-23 吉林建筑大学 Fine processing method for connecting node based on assembly type steel structure
CN114033234A (en) * 2021-12-14 2022-02-11 安徽省路港工程有限责任公司 Novel main tower crown structure and sectional installation method thereof

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100662811B1 (en) * 2006-09-18 2006-12-29 우경건설 주식회사 Non-synthetic complex steel pipe columm having tie ends for filling a steel soncrete and construction method thereof
CN102261043A (en) * 2011-07-08 2011-11-30 中铁大桥局股份有限公司 Assembled steel pipe upright post system
CN105735112A (en) * 2016-04-14 2016-07-06 北京工业大学 Bolt connection-based rapid assembling precast rectangular concrete filled steel tube bridge pier

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100662811B1 (en) * 2006-09-18 2006-12-29 우경건설 주식회사 Non-synthetic complex steel pipe columm having tie ends for filling a steel soncrete and construction method thereof
CN102261043A (en) * 2011-07-08 2011-11-30 中铁大桥局股份有限公司 Assembled steel pipe upright post system
CN105735112A (en) * 2016-04-14 2016-07-06 北京工业大学 Bolt connection-based rapid assembling precast rectangular concrete filled steel tube bridge pier

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110904857A (en) * 2019-12-30 2020-03-24 中国铁建投资集团有限公司 Temporary buckling tower installation method for self-anchored suspension bridge construction
CN112692521A (en) * 2020-12-23 2021-04-23 吉林建筑大学 Fine processing method for connecting node based on assembly type steel structure
CN114033234A (en) * 2021-12-14 2022-02-11 安徽省路港工程有限责任公司 Novel main tower crown structure and sectional installation method thereof

Also Published As

Publication number Publication date
CN108018780B (en) 2019-04-16

Similar Documents

Publication Publication Date Title
CN103132506B (en) Bored pile double-deck Reinforced Hoop reinforcing cage processing and fabricating method
CN108018780B (en) A kind of steel tower column design and construction method of bolting and welding
CN102674136A (en) Lifting method for large-scale tower equipment
CN108005267A (en) A kind of yi word pattern assembled stem steel plate shear force wall and its assembling constructing method
CN106930436A (en) A kind of reinforced concrete shear wall of built-in prestress steel diagonal brace
CN107529575A (en) Universal steel concrete supporting component
CN207436371U (en) A kind of constructing structure of super-span girder with rolled steel section en cased in concrete
CN203856082U (en) Large-pulling-force integrated support joint suitable for large-cantilever pipe truss structure
CN206625366U (en) A kind of more rod members of steel construction, which cross, welds steel node
CN204850148U (en) Shear force wall with continuous zigzag lacing wire structure
CN107654057A (en) Fix self-locking type steel pipe scaffold
CN108086481A (en) A kind of metro depot upper cover Estate Development Self-resetting integral structure and method
CN107965056A (en) A kind of improved profile steel concrete column beam connecting node and its improved method
CN205875401U (en) Close frame structure of multilayer of urceolus in connecting
CN207998929U (en) A kind of concrete filled steel tube and shaped steel girder connection
CN204163280U (en) A kind of crossbeam
CN207761069U (en) Profile steel concrete column and reinforced beam connection structure
CN207331961U (en) A kind of bolt connection node for single-layer lattice shell
CN206016058U (en) A kind of shaped steel or normal concrete beams exist the discrepancy in elevation larger when continuous beam
CN205444694U (en) Multiple arrangement of reinforcement reinforced concrete column of high restraint
CN206873620U (en) A kind of more bar crossover nodes of light steel truss structure structure
CN104234316A (en) Steel-tube square reinforced concrete member and preparation method thereof
CN104234320A (en) Cellular connection steel plate-three-limb circular concrete filled steel tube composite column
CN205296589U (en) Steelframe for building and shear force wall
CN204174834U (en) Cellular junction plate-three limb round steel tubing string

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20210902

Address after: 241060 R & D Center (buildings 4 and 5), No. 17-8 Fumin Road, Jiujiang Economic Development Zone, Jiujiang District, Wuhu City, Anhui Province

Patentee after: CCCC SHEC FOURTH ENGINEERING Co.,Ltd.

Patentee after: The Second Harbor Engineering Co.

Patentee after: CCCC HIGHWAY BRIDGES NATIONAL ENGINEERING RESEARCH CENTER Co.,Ltd.

Address before: 241009 Building 1, West Side of Innovation Road, Jiujiang Economic Development Zone, Wuhu City, Anhui Province

Patentee before: CCCC SHEC FOURTH ENGINEERING Co.,Ltd.

Patentee before: The Second Harbor Engineering Co.

TR01 Transfer of patent right