KR20100111883A - Method for constructing beam reinforced concrete in delay joint sections by using coupler - Google Patents

Method for constructing beam reinforced concrete in delay joint sections by using coupler Download PDF

Info

Publication number
KR20100111883A
KR20100111883A KR1020090030336A KR20090030336A KR20100111883A KR 20100111883 A KR20100111883 A KR 20100111883A KR 1020090030336 A KR1020090030336 A KR 1020090030336A KR 20090030336 A KR20090030336 A KR 20090030336A KR 20100111883 A KR20100111883 A KR 20100111883A
Authority
KR
South Korea
Prior art keywords
coupler
prosthesis
slab
delay
post
Prior art date
Application number
KR1020090030336A
Other languages
Korean (ko)
Other versions
KR101062718B1 (en
Inventor
오보환
박형철
천성철
이명호
Original Assignee
(주)대우건설
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)대우건설 filed Critical (주)대우건설
Priority to KR1020090030336A priority Critical patent/KR101062718B1/en
Publication of KR20100111883A publication Critical patent/KR20100111883A/en
Application granted granted Critical
Publication of KR101062718B1 publication Critical patent/KR101062718B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/41Connecting devices specially adapted for embedding in concrete or masonry
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/16Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
    • E04C5/162Connectors or means for connecting parts for reinforcements
    • E04C5/163Connectors or means for connecting parts for reinforcements the reinforcements running in one single direction
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Reinforcement Elements For Buildings (AREA)

Abstract

PURPOSE: A construction method for a beam steel bar in a delay joint section using a coupler is provided to prevent cracking in a beam due to the dry shrinkage of concrete, since the coupler is re-coupled before filling concrete in a delay joint section. CONSTITUTION: A construction method for a beam steel bar in a delay joint section using a coupler comprises following steps. A mold is installed. A pre-concrete placing slab and a pre-concrete placing beam are formed by the placing of concrete after a slab steel bar and a first beam steel bar are arranged. The mold is installed on the side of the pre-concrete placing slab and the pre-concrete placing beam. A slab steel bar and a second slab steel bar are arranged, a first beam steel bar(110) and a second steel bar(120) are connected by a coupler(130), and then concrete is poured for the formation of the post-concrete placing slab and the post-concrete placing beam.

Description

커플러를 이용한 딜레이 조인트 구간의 보철근 시공방법{METHOD FOR CONSTRUCTING BEAM REINFORCED CONCRETE IN DELAY JOINT SECTIONS BY USING COUPLER}METHODS FOR CONSTRUCTING BEAM REINFORCED CONCRETE IN DELAY JOINT SECTIONS BY USING COUPLER}

본 발명은 커플러를 이용한 딜레이 조인트 구간의 보철근 시공방법에 관한 것으로서, 상세하게는 선타설된 슬래브의 보철근에 커플러를 이용하여 후타설될 슬래브의 보철근을 체결한 후 콘크리트를 타설한 다음 후타설된 슬래브의 양생전에 커플러를 풀어주고, 딜레이 조인트 구간에 콘크리트를 충진 전에 다시 커플러를 재체결하도록 하는 커플러를 이용한 딜레이 조인트 구간의 보철근 시공방법에 관한 것이다.The present invention relates to a method of constructing a prosthesis of a delay joint section using a coupler, and in detail, after fastening the prosthesis of the slab to be post-installed using a coupler to the prosthesis of the pre-slabed slab The present invention relates to a method of reinforcing reinforcement of a delay joint section using a coupler to release the coupler before curing the poured slab and to refit the coupler again before filling concrete in the delay joint section.

일반적으로 리모델링 공사시 신구 슬래브의 접합시 부등처짐에 의한 응력완화를 위해 딜레이 조인트(Delay Joint)를 이용하여 시공하는 사례가 증가하고 있다.In general, there is an increasing number of constructions using delay joints to relieve stress due to inequality when joining new and old slabs during remodeling.

또한 주동통합형 지하주차장의 슬래브 시공은 편의상 거푸집이나 메탈라스를 이용하여 시공 줄눈(Construction Joint)으로 끊어치기를 주로 하지만 주동부와 구속력 등에 의한 슬래브 후타설 구간의 건조수축을 후타설 슬래브 구간에서 흡수해 야 하기 때문에 균열이 발생할 가능성이 높고, 관통균열로 이어져 누수의 위험성도 높기 때문에 이에 대한 대안으로 딜레이 조인트(Delay Joint)를 이용하여 시공하는 사례가 증가하고 있다.In addition, the slab construction of the main integrated underground parking lot is usually cut into construction joints using formwork or metal laths, but it absorbs the dry shrinkage of the slab post-installation section by the main part and binding force from the post-casting slab section. Since the cracks are more likely to occur, and through cracking leads to a higher risk of leakage, there is an increasing number of applications using a delay joint as an alternative.

딜레이 조인트를 이용할 경우 슬래브와 보 철근 절단 여부가 가장 중요한 요소인 데, 통상 슬래브 철근은 모두 절단하고, 보철근은 절단여부에 따라 시공성에 미치는 영향이 매우 커서 가능한 보철근을 절단하지 않으려고 한다.When using a delay joint, the most important factor is whether the slab and the reinforcing bar are cut. In general, all slab reinforcing bars are cut, and the prosthetic bar has a great effect on workability depending on whether or not to cut the prosthetic bar.

그러나, 보철근을 절단하지 않는 경우 콘크리트 건조수축에 의해 보에 균열이 발생하는 문제점이 있고, 콘크리트 건조수축에 의해 보철근의 응력이 증가되는 문제점이 있다.However, when the prosthetic reinforcement is not cut, there is a problem in that the crack is generated in the beam by the concrete dry shrinkage, and there is a problem in that the stress of the reinforcement is increased by the concrete dry shrinkage.

본 발명은 상기와 같은 문제점을 해결하기 위한 것으로, 선타설된 슬래브의 보철근에 커플러를 이용하여 후타설될 슬래브의 보철근을 체결한 후 콘크리트를 타설한 다음 후타설된 슬래브의 양생전에 커플러를 풀어줌으로써 응력 발생을 방지하고, 딜레이 조인트 구간에 콘크리트를 충진 전에 다시 커플러를 재체결하여 콘크리트 건조수축에 의해 보에 균열이 발생하는 것을 방지하도록 하는 커플러를 이용한 딜레이 조인트 구간의 보철근 시공방법을 제공하는데 그 목적이 있다.The present invention is to solve the problems as described above, after coupling the prosthetic reinforcement of the slab to be post-installed using a coupler to the prosthetic reinforcement of the pre-installed slab after placing the concrete coupler before curing of the post-installed slab Provides a method of prosthetic reinforcement for delay joint sections using a coupler to prevent stress from occurring and to re-join the coupler before filling concrete in the delay joint section to prevent cracks in the beam due to concrete shrinkage Its purpose is to.

상기와 같은 목적을 달성하기 위한 본 발명의 특징은,Features of the present invention for achieving the above object,

거푸집을 설치하고, 슬래브 철근과 제 1보철근을 배근한 후 콘크리트를 타설 하여 선타설 슬래브 및 선타설 보를 형성하는 선타설 공정과; 상기 선타설 슬래브 및 선타설 보로부터 일정 거리 이격시킨 딜레이 조인트 구간을 제외한 상기 선타설 슬래브 및 선타설 보의 측면에 거푸집을 설치하고, 슬래브 철근과 제 2보철근을 배근하되, 상기 제 1보철근과 상기 제 2보철근을 커플러를 이용하여 이음한 후 콘크리트를 타설하여 후타설 슬래브 및 후타설 보를 형성하는 후타설 공정과; 상기 제 1보철근과 상기 제 2보철근간의 응력 발생을 방지하도록 상기 후타설 보의 완전 양생전에 상기 커플러의 체결을 해제하는 보철근 이음 해제 공정; 및 일정 기간이 지나 상기 커플러를 재체결한 다음 곧바로 상기 딜레이 조인트 구간에 콘크리트를 충진하여 선타설 슬래브와 후타설 슬래브 및 선타설 보와 후타설 보를 연결하는 딜레이 조인트 충진 공정으로 이루어지는 것을 특징으로 한다.A preliminary placing process of installing the formwork, reinforcing the slab reinforcing bars and the first reinforcing bars, and then placing concrete to form the precast slab and the precast beam; Forming the formwork on the side of the first placing slab and the first placing beams, except the delay joint section spaced from the first placing slab and the first placing beams, and reinforce the slab reinforcement and the second reinforcing bar, the first reinforcing bar A post-installation process of forming a post-pouring slab and a post-pouring beam by jointing the second reinforcing bar with a coupler and then pouring concrete; A prosthetic joint release step of releasing the coupling of the coupler before full curing of the post-pouring beam to prevent stress between the first and second prosthesis; And a delay joint filling process of connecting concrete to the delay joint section immediately after fastening the coupler after a predetermined period of time and connecting the pre-pouring slab and the post-pouring slab and the pre-pouring beam and the post-pouring beam.

여기에서, 상기 커플러는 나사 이음 방식 또는 편체 이음 방식이다.Here, the coupler is a screw joint type or a single joint type.

여기에서 또한, 상기 제 1보철근 및 상기 제 2보철근은 상기 나사 이음 방식 커플러가 나사 결합되도록 일끝단에 나사 가공부가 형성된다.Here, the first prosthesis and the second prosthesis is a threaded portion is formed at one end so that the screwed coupler is screwed.

여기에서 또, 상기 나사 이음 방식 커플러는 커플러 재체결시 딜레이 조인트 구간이 넓은 경우 체결의 용이성을 위하여 양단에 나사 가공부이 형성된 연결 보철근과, 2개의 커플러를 이용하여 상기 제 1보철근과 제 2보철근을 체결한다.Here, the screw joint type coupler is a connecting prosthesis having threaded portions formed at both ends for ease of fastening when the delay joint section is wide when the coupler is re-fastened, and the first prosthesis and the second coupler using two couplers. Tighten the prosthesis.

여기에서 또, 상기 제 1보철근 또는 제 2보철근의 나사 가공부는 상기 제 2보철근 또는 제 1보철근의 나사 가공부의 길이보다 더 길게 형성되어 상기 나사 이음 방식 커플러의 체결을 해제시 상기 커플러가 상기 제 1보철근 또는 제 2보철근측으로 완전히 이동되도록 한다.Here, the thread processing portion of the first prosthesis or the second prosthesis is formed longer than the length of the thread processing portion of the second prosthesis or the first prosthesis, the coupler when releasing the screw joint type coupler To completely move toward the first or second prosthesis.

여기에서 또, 상기 제 1보철근 및 상기 제 2보철근은 접촉에 의한 응력 전달을 방지하도록 상기 커플러에 의해 체결시 그 끝단이 상호 이격되는 길이를 갖는다.Here, the first prosthesis and the second prosthesis have a length at which the ends are spaced apart from each other when fastened by the coupler to prevent stress transmission by contact.

여기에서 또, 상기 제 1보철근 또는 제 2보철근의 유격에 의한 균열을 방지하도록 상기 나사 이음 방식 커플러를 압입하는 잠금너트를 더 구비한다.Here, the lock nut for pressing the screw joint type coupler is further provided to prevent cracking due to the play of the first or second prosthetic reinforcement.

여기에서 또, 상기 보철근 이음 해제 공정은 상기 나사 이음 방식 커플러의 체결을 해제한 후 상기 제 1보철근 및 상기 제 2보철근의 나사 가공부를 보양한다.Here, the prosthetic reinforcement joint release step to release the screw coupling portion of the first prosthetic reinforcement and the second prosthetic reinforcement after releasing the coupling.

상기와 같이 구성되는 본 발명인 커플러를 이용한 딜레이 조인트 구간의 보철근 시공방법에 따르면, 선타설된 슬래브의 보철근에 커플러를 이용하여 후타설될 슬래브의 보철근을 체결한 후 콘크리트를 타설한 다음 후타설된 슬래브의 양생전에 커플러를 풀어줌으로써 응력 발생을 방지하고, 딜레이 조인트 구간에 콘크리트를 충진 전에 다시 커플러를 재체결하여 콘크리트 건조수축에 의해 보에 균열이 발생하는 것을 방지할 수 있는 이점이 있다.According to the method of construction of the prosthetic reinforcement of the delay joint section using the present invention coupler configured as described above, after fastening the reinforcement of the slab to be post-installed using the coupler to the reinforcement of the pre-placed slab after pouring concrete The stress is prevented by releasing the coupler before curing of the poured slab, and the coupler is re-fastened again before the concrete is filled in the delay joint section to prevent cracks in the beam due to the shrinkage of the concrete.

이하, 본 발명에 따른 커플러를 이용한 딜레이 조인트 구간의 보철근 시공방법을 첨부된 도면을 참조하여 상세하게 설명하면 다음과 같다.Hereinafter, with reference to the accompanying drawings a method of constructing a prosthesis of the delay joint section using a coupler according to the present invention will be described in detail.

하기에서 본 발명을 설명함에 있어, 관련된 공지 기능 또는 구성에 대한 구체적인 설명이 본 발명의 요지를 불필요하게 흐릴 수 있다고 판단되는 경우에는 그 상세한 설명은 생략할 것이다. 그리고 후술되는 용어들은 본 발명에서의 기능을 고 려하여 정의된 용어들로서 이는 사용자, 운용자의 의도 또는 관례 등에 따라 달라질 수 있다. 그러므로 그 정의는 본 명세서 전반에 걸친 내용을 토대로 내려져야 할 것이다.In the following description of the present invention, if it is determined that a detailed description of a related known function or configuration may unnecessarily obscure the subject matter of the present invention, the detailed description thereof will be omitted. Terms to be described later are terms defined in consideration of functions in the present invention, and may vary according to intentions or customs of users and operators. Therefore, the definition should be based on the contents throughout this specification.

도 1은 본 발명에 따른 커플러를 이용한 딜레이 조인트 구간의 보철근 시공방법에 적용된 커플러와 보철근의 구성을 나타낸 사시도이고, 도 2는 도 1의 단면도이며, 도 3 내지 도 6은 본 발명의 다른 실시예에 따른 커플러를 이용한 딜레이 조인트 구간의 보철근 시공방법에 적용된 커플러와 보철근의 구성을 나타낸 사시도이고, 도 7 내지 도 10은 본 발명에 따른 본 발명에 따른 커플러를 이용한 딜레이 조인트 구간의 보철근 시공방법을 설명하기 위한 공정도이다.1 is a perspective view showing a configuration of a coupler and a prosthesis applied to a method of constructing a prosthetic reinforcement of a delay joint section using a coupler according to the present invention, FIG. 2 is a cross-sectional view of FIG. 1, and FIGS. 7 is a perspective view illustrating a configuration of a coupler and a prosthesis applied to a prosthesis construction method of a delay joint section using a coupler according to an embodiment, and FIGS. 7 to 10 are beams of a delay joint section using a coupler according to the present invention. It is a process chart to explain the method of constructing rebar.

도 1 내지 도 10을 참조하면, 본 발명에 따른 커플러를 이용한 딜레이 조인트 구간의 보철근 시공방법은 거푸집(미도시)을 설치하고, 선타설 슬래브 철근(101)과 제 1보철근(110)을 배근한 후 콘크리트를 타설하여 선타설 슬래브(102) 및 선타설 보(103)를 형성하는 선타설 공정(S100)과; 선타설 슬래브(102) 및 선타설 보(103)로부터 일정 거리 이격시킨 딜레이 조인트 구간(DJ)을 제외한 선타설 슬래브(102) 및 선타설 보(103)의 측면에 거푸집(미도시)을 설치하고, 후타설 슬래브 철근(104)과 제 2보철근(120)을 배근하되, 제 1보철근(110)과 제 2보철근(120)을 커플러(130)를 이용하여 이음한 후 콘크리트를 타설하여 후타설 슬래브(105) 및 후타설 보(106)를 형성하는 후타설 공정(S110)과; 제 1보철근(110)과 제 2보철근(120)간의 응력 발생을 방지하도록 후타설 보(106)의 완전 양생전에 커플러(130)의 체결을 해제하는 보철근 이음 해제 공정(S120); 및 일정 기간이 지나 후타설 슬 래브(105) 및 후타설 보(106)의 건조수축이 완료되면 커플러(130)를 재체결한 다음 곧바로 딜레이 조인트 구간(DJ)에 콘크리트를 충진하여 선타설 슬래브(102)와 후타설 슬래브(105) 및 선타설 보(103)와 후타설 보(106)를 연결하는 딜레이 조인트 충진 공정(S130)으로 이루어진다.1 to 10, in the method of constructing the prosthetic reinforcement of the delay joint section using the coupler according to the present invention, a formwork (not shown) is installed, and the first placing slab reinforcement 101 and the first prosthetic reinforcement 110 are installed. After placing the concrete to place the pre-pouring slab 102 and the pre-pouring beam 103 to form a pre-pouring slab (S100); Formwork (not shown) is installed on the sides of the pre-stacking slab 102 and the pre-casting beam 103, except for the delay joint section DJ spaced a predetermined distance from the pre-stacking slab 102 and the pre-casting beam 103. Reinforce the post-installation slab reinforcement 104 and the second prosthesis 120, but after the first prosthesis 110 and the second prosthesis 120 are joined using the coupler 130, the concrete is poured. A post pour process (S110) for forming a post pour slab 105 and a post pour beam 106; Prosthetic bar joint release step (S120) of releasing the coupling of the coupler 130 before the complete curing of the post-pouring beam 106 to prevent the stress between the first reinforcement 110 and the second reinforcement (120); And when the drying contraction of the post-pouring slab 105 and the post-pouring beam 106 is completed after a predetermined period of time, the coupler 130 is re-fastened and the concrete is filled in the delay joint section (DJ). 102 is a delay joint filling process (S130) for connecting the post-pouring slab 105 and the pre-pouring beam 103 and the post-pouring beam 106.

한편, 본 발명에 따른 본 발명에 따른 커플러를 이용한 딜레이 조인트 구간의 보철근 시공방법을 도면을 참조하여 각 공정별로 보다 자세하게 설명하면 다음과 같다.On the other hand, the method of prosthetic reinforcement of the delay joint section using the coupler according to the present invention according to the present invention with reference to the drawings in more detail for each process as follows.

《선타설 공정 : S100》`` Pasting process: S100 ''

먼저, 리모델링시 신구 슬래브의 접합 및 주동통합형 지하 주차장의 슬래브와 같이 딜레이 조인트를 이용하여 슬래브를 시공하는 경우 일정 구획을 나누어 선타설 구간과 후타설 구간으로 나누고, 선타설 구간과 후타설 구간 사이에 딜레이 조인트 구간을 형성한다.First, when remodeling, when constructing slabs using delay joints, such as joining of old and new slabs and slabs of main integrated underground parking lot, divide the certain sections into pre-pouring and post-pouring sections, and between the pre-pouring section and the post-pouring section. Form a delay joint section.

즉, 선타설 슬래브와 선타설 보를 시공하기 위하여 거푸집을 설치하고, 해당 구간에 선타설 슬래브 철근(101)과 제 1보철근(110)을 배근한 후 콘크리트를 타설하여 선타설 슬래브(102) 및 선타설 보(103)를 형성한다.That is, formwork is installed in order to construct the first placing slab and the first placing beam, and after placing the first placing slab reinforcement 101 and the first reinforcing bar 110 in the corresponding section, the concrete is poured by placing the first placing slab 102 and A first place beam 103 is formed.

이때, 딜레이 조인트 구간(DJ)으로 선타설 슬래브 철근(101)과 제 1보철근(110)이 노출되고, 제 1보철근(110)의 끝단, 즉 딜레이 조인트 구간(DJ)으로 노출되는 부분의 끝단에는 나사 가공부(111)가 형성된다.At this time, the pre-slab slab 101 and the first prosthetic reinforcement 110 are exposed to the delay joint section DJ, and the end of the first prosthetic reinforcement 110, that is, the portion exposed to the delay joint section DJ. At the end, a thread processing part 111 is formed.

《후타설 공정 : S110》`` Foot casting process: S110 ''

선타설 슬래브(102) 및 선타설 보(103)의 양생이 완료되면, 후타설 슬래 브(105)와 후타설 보(106)를 시공하기 위하여 거푸집을 설치하고, 해당 구간에 후타설 슬래브 철근(104)과 제 2보철근(120)을 배근한다.When curing of the pre-stacking slab 102 and the pre-pouring beam 103 is completed, formwork is installed to construct the post-pouring slab 105 and the post-pouring beam 106, and the post-pouring slab reinforcing bar ( 104) and the second prosthesis 120 is reinforced.

이때, 딜레이 조인트 구간(DJ)으로 후타설 슬래브 철근(104)과 제 2보철근(120)이 노출되고, 제 2보철근(120)의 끝단, 즉 딜레이 조인트 구간(DJ)으로 노출되는 부분의 끝단에는 나사 가공부(121)가 형성된다.At this time, the post-installation slab reinforcement 104 and the second prosthesis 120 are exposed to the delay joint section DJ, and the end of the second prosthesis 120, that is, the portion exposed to the delay joint section DJ. At the end is formed a screw machining portion 121.

또한, 제 1보철근(110) 및 제 2보철근(120)은 접촉에 의한 응력 전달을 방지하도록 커플러(130)에 의해 체결시 그 끝단 서로 이격되는 길이(L1)를 갖는 것이 바람직하고, 제 2보철근(120)의 나사 가공부(121)의 길이(L2)는 제 1보철근(110)의 나사 가공부(111)의 길이(L1)보다 더 길게 형성되어 커플러(130)의 체결 및 체결 해제시 커플러가 제 2보철근(120) 측으로 완전히 이동되도록 한다. 이와 반대로 제 1보철근(110)의 나사 가공부(111)의 길이(L1)를 제 2보철근(120)의 나사 가공부(121)의 길이(L2)보다 더 길게 형성할 수도 있다.In addition, the first prosthesis 110 and the second prosthesis 120 has a length (L1) that is spaced apart from each other at the ends thereof when fastened by the coupler 130 to prevent stress transfer by contact, The length L2 of the thread machining portion 121 of the second prosthesis 120 is formed longer than the length L1 of the thread machining portion 111 of the first prosthesis 110 so as to fasten the coupler 130. When the coupling is released, the coupler is completely moved to the second prosthesis 120 side. On the contrary, the length L1 of the thread processing part 111 of the first prosthesis 110 may be longer than the length L2 of the thread processing part 121 of the second prosthesis 120.

배근이 완료되면, 제 1보철근(110)의 나사 가공부(111)와 제 2보철근(120)의 나사 가공부(121)를 커플러(130)를 통해 상호 체결한다.When the reinforcement is completed, the thread processing unit 111 of the first prosthesis 110 and the thread processing unit 121 of the second prosthesis 120 are fastened to each other through the coupler 130.

이와 동시에, 제 1보철근과 제 2보철근을 이음시 딜레이 조인트 구간(DJ)으로 노출된 선타설 슬래브 철근(101)과 후타설 슬래브 철근(104)을 겹침 이음할 수도 있다.At the same time, when the first prosthesis and the second prosthesis are jointed, the first placing slab reinforcement 101 and the post placing slab reinforcing bar 104 exposed to the delay joint section DJ may be overlapped.

이때, 커플러 재체결시 딜레이 조인트 구간(DJ)이 넓은 경우 체결의 용이성을 위하여 도 3에 도시된 바와 같이 양단에 나사 가공부(141)이 형성된 연결 보철근(140)을 이용하여 2개의 커플러(130)를 이용하여 제 1보철근(110)과 제 2보철 근(120)을 체결할 수도 있다. At this time, when the coupler is re-joined, when the delay joint section (DJ) is wide, two couplers (using the connecting prosthesis 140 formed with thread processing parts 141 at both ends as shown in FIG. 3 for ease of fastening) 130 may be used to fasten the first prosthesis 110 and the second prosthesis 120.

그리고, 제 2보철근(120)의 나사 가공부(141)에는 도 4에 도시된 바와 같이 제 1보철근(110)과 제 2보철근(120)의 유격에 의한 균열을 방지하도록 커플러(130)를 압입하는 잠금너트(131)를 더 구비할 수도 있고, 잠금너트(131)는 제 1보철근(110) 또는 제 2보철근(120)중 길이가 더 긴측에 형성되는 것이 바람직하다.In addition, the screw processing unit 141 of the second prosthesis 120, as shown in FIG. 4, the coupler 130 to prevent cracking due to the play between the first prosthesis 110 and the second prosthesis 120. The lock nut 131 may be further provided, and the lock nut 131 may be formed on the longer side of the first prosthesis 110 or the second prosthesis 120.

또한, 커플러(130)를 도 5 및 도 6에 도시된 바와 같이 나사 이음 방식이 아닌 편체 이음 방식 커플러(즉, 보철근에 나사 가공부를 미형성하고, 편체를 이용하여 연결하는 방식)를 사용할 수도 있다.In addition, the coupler 130 may be a knitted joint coupler (ie, a method of not forming a threaded portion on the prosthesis and connecting by using a knitted body) instead of a screwed joint as shown in FIGS. 5 and 6. have.

그런 다음, 제 1보철근(110)과 제 2보철근(120)의 이음이 완료되면 콘크리트를 타설하여 후타설 슬래브(105) 및 후타설 보(106)를 형성한다.Then, when the joint of the first prosthesis 110 and the second prosthesis 120 is completed, the concrete is poured to form the post-pouring slab 105 and the post-pouring beam 106.

《보철근 이음 해제 공정 : S120》《Prosthetic Rebar Joint Release Process: S120》

그리고, 제 1보철근(110)과 제 2보철근(120)간의 응력 발생을 방지하도록 후타설 보(106)의 완전 양생전(콘크리트를 타설후 약 12시간이 경과 후)에 커플러(130)를 회전시켜 커플러(130)를 제 2보철근(120)측으로 완전 이동시켜 제 1보철근(110)과 제 2보철근(120)의 이음을 해제한다. 이때, 커플러를 제 2보철근(120)측으로 이동시킨 다음 제 1보철근(110)의 나사 가공부(111)와 제 2보철근(120)의 나사 가공부(121)에 이물질이 부착되거나 녹의 발생을 방지하도록 테이프나 천 또는 캡을 이용하여 제 1보철근(110)의 나사 가공부(111)와 제 2보철근(120)의 나사 가공부(121)를 보양한다. Then, the coupler 130 at the time of complete curing (after about 12 hours after the concrete is cast) of the post-pouring beam 106 to prevent the stress between the first and second reinforcing bars 110 and 120. Rotating the coupler 130 is completely moved to the second prosthesis 120 side to release the joint of the first prosthesis 110 and the second prosthesis 120. At this time, the coupler is moved to the second prosthesis 120 side, and then foreign matter is attached or rusted to the thread processing unit 111 of the first prosthesis 110 and the screw processing unit 121 of the second prosthesis 120. In order to prevent the occurrence of the tape, a cloth or a cap is used to provide the threaded portion 111 of the first prosthesis 110 and the threaded portion 121 of the second prosthesis 120.

《딜레이 조인트 충진 공정 : S130》《Delay Joint Filling Process: S130》

그런 다음, 일정 기간(약 4~6주)이 지나면 커플러(130)를 이용하여 제 1보철근(110)과 제 2보철근(120)을 재이음한 다음 곧바로 딜레이 조인트 구간(DJ)에 콘크리트를 충진하여 선타설 슬래브(102)와 후타설 슬래브(105) 및 선타설 보(103)와 후타설 보(106)를 연결하여 시공을 완료한다.Then, after a certain period of time (approximately 4-6 weeks), the coupler 130 is used to rejoin the first and second prosthetics 110 and the second prosthesis 120, and then the concrete is placed in the delay joint section DJ. The filling is completed by connecting the pre-pouring slab 102 and the post-pouring slab 105 and the pre-pouring beam 103 and the post-pouring beam 106 to complete the construction.

본 발명은 다양하게 변형될 수 있고 여러 가지 형태를 취할 수 있으며 상기 발명의 상세한 설명에서는 그에 따른 특별한 실시 예에 대해서만 기술하였다. 하지만 본 발명은 상세한 설명에서 언급되는 특별한 형태로 한정되는 것이 아닌 것으로 이해되어야 하며, 오히려 첨부된 청구범위에 의해 정의되는 본 발명의 정신과 범위 내에 있는 모든 변형물과 균등물 및 대체물을 포함하는 것으로 이해되어야 한다.As those skilled in the art would realize, the described embodiments may be modified in various ways, all without departing from the spirit or scope of the present invention. It is to be understood, however, that the present invention is not limited to the specific forms referred to in the description, but rather includes all modifications, equivalents, and substitutions within the spirit and scope of the invention as defined by the appended claims. Should be.

도 1은 본 발명에 따른 본 발명에 따른 커플러를 이용한 딜레이 조인트 구간의 보철근 시공방법에 적용된 커플러와 보철근의 구성을 나타낸 사시도,1 is a perspective view showing a configuration of a coupler and a prosthesis applied to a method of constructing a prosthesis of a delay joint section using a coupler according to the present invention;

도 2는 도 1의 단면도,2 is a cross-sectional view of FIG.

도 3 내지 도 6은 본 발명의 다른 실시예에 따른 커플러를 이용한 딜레이 조인트 구간의 보철근 시공방법에 적용된 커플러와 보철근의 구성을 나타낸 도면,3 to 6 is a view showing the configuration of the coupler and the prosthesis applied to the prosthetic construction method of the delay joint section using a coupler according to another embodiment of the present invention,

도 7 내지 도 10은 본 발명에 따른 본 발명에 따른 커플러를 이용한 딜레이 조인트 구간의 보철근 시공방법을 설명하기 위한 공정도.7 to 10 is a process chart for explaining the prosthesis construction method of the delay joint section using a coupler according to the present invention.

<도면의 주요 부분에 관한 부호의 설명><Explanation of symbols on main parts of the drawings>

101 : 선타설 슬래브 철근 102 : 선타설 슬래브101: reinforcement slab reinforcement 102: reinforcement slab

103 : 선타설 보 104 : 후타설 슬래브 철근103: Strut casting 104: Reinforced slab rebar

105 : 후타설 슬래브 106 : 후타설 보105: post-installation slab 106: post-installation beam

110, 120 : 제 1, 2보철근 111, 121 : 나사 가공부110, 120: 1st, 2nd reinforcing bar 111, 121: thread processing part

130 : 커플러 131 : 잠금너트130: coupler 131: lock nut

Claims (8)

거푸집을 설치하고, 슬래브 철근과 제 1보철근을 배근한 후 콘크리트를 타설하여 선타설 슬래브 및 선타설 보를 형성하는 선타설 공정과;A preliminary casting process of installing the formwork, reinforcing the slab reinforcing bars and the first reinforcing bars, and then placing concrete to form the precast slab and the precast beam; 상기 선타설 슬래브 및 선타설 보로부터 일정 거리 이격시킨 딜레이 조인트 구간을 제외한 상기 선타설 슬래브 및 선타설 보의 측면에 거푸집을 설치하고, 슬래브 철근과 제 2보철근을 배근하되, 상기 제 1보철근과 상기 제 2보철근을 커플러를 이용하여 이음한 후 콘크리트를 타설하여 후타설 슬래브 및 후타설 보를 형성하는 후타설 공정과;Forming the formwork on the side of the first placing slab and the first placing beams, except the delay joint section spaced from the first placing slab and the first placing beams, and reinforce the slab reinforcement and the second reinforcing bar, the first reinforcing bar A post-installation process of forming a post-pouring slab and a post-pouring beam by jointing the second reinforcing bar with a coupler and then pouring concrete; 상기 제 1보철근과 상기 제 2보철근간의 응력 발생을 방지하도록 상기 후타설 보의 완전 양생전에 상기 커플러의 체결을 해제하는 보철근 이음 해제 공정; 및A prosthetic joint release step of releasing the coupling of the coupler before full curing of the post-pouring beam to prevent stress between the first and second prosthesis; And 일정 기간이 지나 상기 커플러를 재체결한 다음 곧바로 상기 딜레이 조인트 구간에 콘크리트를 충진하여 선타설 슬래브와 후타설 슬래브 및 선타설 보와 후타설 보를 연결하는 딜레이 조인트 충진 공정으로 이루어지는 것을 특징으로 하는 커플러를 이용한 딜레이 조인트 구간의 보철근 시공방법.A coupler comprising a delay joint filling process for connecting a pre-slab slab, a post-slab slab, a pre-pour beam and a post-pour beam by filling concrete in the delay joint section immediately after reconnecting the coupler after a certain period of time. Construction method of prosthetic reinforcement of used delay joint section. 제 1 항에 있어서,The method of claim 1, 상기 커플러는,The coupler is, 나사 이음 방식 또는 편체 이음 방식인 것을 특징으로 하는 커플러를 이용한 딜레이 조인트 구간의 보철근 시공방법.Prosthetic reinforcement method of the delay joint section using a coupler, characterized in that the screw joint method or a knitted joint method. 제 2 항에 있어서,The method of claim 2, 상기 제 1보철근 및 상기 제 2보철근은,The first prosthesis and the second prosthesis, 상기 나사 이음 방식 커플러가 나사 결합되도록 일끝단에 나사 가공부가 형성되는 것을 특징으로 하는 커플러를 이용한 딜레이 조인트 구간의 보철근 시공방법.Prosthesis construction method of the delay joint section using a coupler, characterized in that the screw processing portion is formed at one end so that the screw joint coupler is screwed. 제 3 항에 있어서,The method of claim 3, wherein 상기 나사 이음 방식 커플러는,The screw joint type coupler, 커플러 재체결시 딜레이 조인트 구간이 넓은 경우 체결의 용이성을 위하여 양단에 나사 가공부이 형성된 연결 보철근과, 2개의 커플러를 이용하여 상기 제 1보철근과 제 2보철근을 체결하는 것을 특징으로 하는 커플러를 이용한 딜레이 조인트 구간의 보철근 시공방법.Coupler for connecting the first and second prosthetic reinforcement by using two couplers and a connecting prosthesis having a threaded portion formed at both ends for ease of fastening when the delay joint section is wide when the coupler is refastened. Prosthesis construction method of delay joint section using 제 2 항에 있어서,The method of claim 2, 상기 제 1보철근 또는 제 2보철근의 나사 가공부는,Thread processing part of the first or second reinforcing bar, 상기 제 2보철근 또는 제 1보철근의 나사 가공부의 길이보다 더 길게 형성되어 상기 나사 이음 방식 커플러의 체결을 해제시 상기 커플러가 상기 제 1보철근 또는 제 2보철근측으로 완전히 이동되도록 하는 것을 특징으로 하는 커플러를 이용한 딜레이 조인트 구간의 보철근 시공방법.It is formed longer than the length of the thread processing portion of the second prosthesis or the first prosthesis, so that the coupler is completely moved to the first prosthesis or the second prosthesis side when releasing the fastening of the screw joint coupler Prosthesis construction method of delay joint section using a coupler. 제 5 항에 있어서,The method of claim 5, 상기 제 1보철근 또는 제 2보철근의 나사 가공부에는,In the thread processing part of the first or second reinforcement, 상기 제 1보철근 또는 제 2보철근의 유격에 의한 균열을 방지하도록 상기 나사 이음 방식 커플러를 압입하는 잠금너트를 더 구비하는 것을 특징으로 하는 커플러를 이용한 딜레이 조인트 구간의 보철근 시공방법.And a lock nut for press-fitting the screw-coupled coupler to prevent cracking by the play of the first or second prosthetic reinforcing bars. 제 1 항에 있어서,The method of claim 1, 상기 제 1보철근 및 상기 제 2보철근은,The first prosthesis and the second prosthesis, 접촉에 의한 응력 전달을 방지하도록 상기 커플러에 의해 체결시 그 끝단이 상호 이격되는 길이를 갖는 것을 특징으로 하는 커플러를 이용한 딜레이 조인트 구간의 보철근 시공방법.Prosthesis construction method of the delay joint section using a coupler, characterized in that the end has a length that is spaced apart from each other when fastened by the coupler to prevent stress transfer by contact. 제 3 항에 있어서,The method of claim 3, wherein 상기 보철근 이음 해제 공정은,The prosthetic reinforcement joint release process, 상기 나사 이음 방식 커플러의 체결을 해제한 후 상기 제 1보철근 및 상기 제 2보철근의 나사 가공부를 보양하는 것을 특징으로 하는 커플러를 이용한 딜레이 조인트 구간의 보철근 시공방법.Prosthesis reinforcement method of the delay joint section using a coupler characterized in that to maintain the threaded portion of the first prosthesis and the second prosthesis after releasing the fastening of the screw joint type coupler.
KR1020090030336A 2009-04-08 2009-04-08 Construction method of prosthetic bar in delay joint section using coupler KR101062718B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020090030336A KR101062718B1 (en) 2009-04-08 2009-04-08 Construction method of prosthetic bar in delay joint section using coupler

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020090030336A KR101062718B1 (en) 2009-04-08 2009-04-08 Construction method of prosthetic bar in delay joint section using coupler

Publications (2)

Publication Number Publication Date
KR20100111883A true KR20100111883A (en) 2010-10-18
KR101062718B1 KR101062718B1 (en) 2011-09-06

Family

ID=43131987

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020090030336A KR101062718B1 (en) 2009-04-08 2009-04-08 Construction method of prosthetic bar in delay joint section using coupler

Country Status (1)

Country Link
KR (1) KR101062718B1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103397741A (en) * 2013-08-03 2013-11-20 叶长青 Construction method for steel reinforced concrete beam
CN104295006A (en) * 2014-10-17 2015-01-21 四川省建筑科学研究院 Spring extrusion type steel bar connecting component and construction method thereof
CN104405041A (en) * 2014-11-21 2015-03-11 大元建业集团股份有限公司 Assembly type prefabricated floor slab connecting piece for steel structure building and mounting method thereof
CN104963454A (en) * 2015-07-07 2015-10-07 山东万斯达建筑科技股份有限公司 Cage type steel bar connector with cone and construction method thereof
CN115679812A (en) * 2022-11-03 2023-02-03 中铁大桥勘测设计院集团有限公司 Main tower vertical steel bar sectional type reinforcing structure and construction method thereof

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104963511B (en) * 2015-06-12 2017-04-05 中国建筑第八工程局有限公司 The maintenance process of outer wall of basement
CN106245851A (en) * 2016-08-01 2016-12-21 福州市第三建筑工程公司 Steel reinforcement abutting joints structure and docking calculation thereof and application in a kind of reinforced concrete
KR102333870B1 (en) 2020-04-08 2021-12-01 롯데건설 주식회사 Reinforcing device for preventing shrinkage crack of apartment underground parking lot delay joint and construction method thereof

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103397741A (en) * 2013-08-03 2013-11-20 叶长青 Construction method for steel reinforced concrete beam
CN104295006A (en) * 2014-10-17 2015-01-21 四川省建筑科学研究院 Spring extrusion type steel bar connecting component and construction method thereof
CN104405041A (en) * 2014-11-21 2015-03-11 大元建业集团股份有限公司 Assembly type prefabricated floor slab connecting piece for steel structure building and mounting method thereof
CN104963454A (en) * 2015-07-07 2015-10-07 山东万斯达建筑科技股份有限公司 Cage type steel bar connector with cone and construction method thereof
CN104963454B (en) * 2015-07-07 2017-06-16 山东万斯达建筑科技股份有限公司 A kind of cage reinforcing bar connector with cone cylinder and its construction method
CN115679812A (en) * 2022-11-03 2023-02-03 中铁大桥勘测设计院集团有限公司 Main tower vertical steel bar sectional type reinforcing structure and construction method thereof

Also Published As

Publication number Publication date
KR101062718B1 (en) 2011-09-06

Similar Documents

Publication Publication Date Title
KR101062718B1 (en) Construction method of prosthetic bar in delay joint section using coupler
US8806820B2 (en) Segments for building spliced prestressed concrete girder and method of manufacturing the segments
JP7430155B2 (en) Method for constructing a connection structure between precast structural members and time-cured materials
KR101491952B1 (en) Twin-leaf Arch System and Fabrication Method for thereof
KR101080836B1 (en) Buit-in steel plate with shear key for rebar splice
KR100836079B1 (en) Structure of precast half slab-girder unit and method constructing the slab of a bridge with it
KR20120054705A (en) Connecting details and connecting method of uhpc precast slab using steel bar in tapered recess
CN105888078A (en) U-shaped building embedded part and construction method of anchoring component of U-shaped building embedded part
KR100704055B1 (en) continuous steel bridge having precast concrete slab and construction method thereof
WO2014189031A1 (en) Storage tank construction method
KR100710984B1 (en) Flat plate concrete structure having openings reinforced by opening formative assembly
KR20140058076A (en) Construction method for connecting new and old concrete
JP3925837B2 (en) How to build a joint
JP2014015753A (en) Structure and method for joining girder and floor slab together
JP6721940B2 (en) Widening structure of existing PC floor slab
JP7120897B2 (en) Joining method of precast members
KR102071148B1 (en) I-type Prestressed Concrete Girder, Rahmen Bridge using thereof and Construction method for thereof
JP2002061296A (en) Structure of joint and construction method therefor
CN106760190A (en) Concrete simply supported beam and preparation method based on carbon fiber mesh composite board
KR101026949B1 (en) Segment of precast concrete girder
JP6839622B2 (en) Concrete slab joining structure, concrete slab joining method and concrete slab manufacturing method
JP2018119333A (en) Precast concrete block joint structure and precast concrete block joint structure body
CN205776796U (en) A kind of U-shaped building built-in part
KR101440436B1 (en) Method for constructing of Prestressed Concrete Composite Girder which combined tension applied type
KR100966943B1 (en) Reinforcement Structure of External Tendon Anchorage Part with Fiber Sheet and Construction Method Thereof

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
LAPS Lapse due to unpaid annual fee