CN103397741A - Construction method for steel reinforced concrete beam - Google Patents

Construction method for steel reinforced concrete beam Download PDF

Info

Publication number
CN103397741A
CN103397741A CN2013103438812A CN201310343881A CN103397741A CN 103397741 A CN103397741 A CN 103397741A CN 2013103438812 A CN2013103438812 A CN 2013103438812A CN 201310343881 A CN201310343881 A CN 201310343881A CN 103397741 A CN103397741 A CN 103397741A
Authority
CN
China
Prior art keywords
steel pipe
concrete
strength non
filling material
high strength
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013103438812A
Other languages
Chinese (zh)
Inventor
叶长青
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2013103438812A priority Critical patent/CN103397741A/en
Publication of CN103397741A publication Critical patent/CN103397741A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a construction method for a steel reinforced concrete beam, and is characterized in that a part below 1/3 of the beam bottom is made of a high-strength non-shrinkage grouting material, a part above 2/3 of the beam bottom is made of concrete, and the particle size of stones in the concrete is controlled within 15 mm. A construction order of the beam comprises firstly, pouring the high-strength non-shrinkage grouting material, half an hour later, starting to pour the concrete, and before the high-strength non-shrinkage grouting material is initially set, finishing pouring of the upper concrete. The initial setting time of the high-strength non-shrinkage grouting material is controlled to be 6-8 h, and the pouring of the high-strength non-shrinkage grouting material of the beam is completed in 2-3 h; the slump degree of the high-strength non-shrinkage grouting material is 300-350 mm; a template at one side of the beam is provided with 8 inspection holes as vent holes with the diameter of 16 mm, and the hole elevations are at positions of 200 mm above the beam bottom.

Description

The steel reinforced concrete beam construction method
Technical field
The present invention relates to a kind of girder with rolled steel section en cased in concrete, particularly a kind of steel reinforced concrete beam construction method.
Background technology
In the steel reinforced concrete beam structure construction, section steel beam and reinforced concrete post beam steel mutually intert and arrange, particularly in the close concrete steel bone of large span, beam column shaped steel cross section is large and reinforcement placement is more, between reinforcing bar and reinforcing bar, between steel pier and reinforcing bar, space is all less, the intensive complexity of bean column node, take very difficulty of conventional concreting method construction, and construction quality also is difficult to guarantee.In addition, the girder steel two ends are reinforced concrete column, and in reinforced concrete column column cap and steel frame beam, the reinforcing bar gap is little, can't carry out pervibration, adopt the ordinary concrete compactness not reach code requirement, bring great difficulty for this position concrete pouring construction.
Summary of the invention
Technical problem to be solved by this invention is to provide the steel reinforced concrete beam construction method that a kind of construction quality is good, cost is low.
At the bottom of central sill of the present invention, High Strength Non-shrinking Filling Material is adopted at 1/3 following position, and at the bottom of beam, 2/3 adopts concrete with upper part, and in concrete, cobble-stone diameter is controlled to be in 15mm.
The beam sequence of construction is: first builds High Strength Non-shrinking Filling Material, starts concreting after 3h, and top concreting is not complete before initial set at High Strength Non-shrinking Filling Material.The job practices of tradition concreting is first to build High Strength Non-shrinking Filling Material, build again upper surface concrete after intensity reaches 30MPa, although construction quality easily guarantee, waits for too long, the bi-material contact surface easily produces crack, to structural bearing capacity, brings impact.And the present invention can effectively avoid the generation of constuction joint at High Strength Non-shrinking Filling Material concreting before initial set not.The High Strength Non-shrinking Filling Material initial setting time is controlled to be 6~8h, and the deck-molding strength contraction-free grouting concrete is cast in 2~3h and completes.
The High Strength Non-shrinking Filling Material slump is too small easily causes leakiness between shaped steel and steel bar stress, and the High Strength Non-shrinking Filling Material slump is crossed conference affects intensity,, according to a large amount of practices, determines that the High Strength Non-shrinking Filling Material slump is 300~350mm.
High Strength Non-shrinking Filling Material adopts forced mixer to stir, and mixing time, greater than 3min, is finished using in the slurry 1h that stirs into continuously, and slurry out should carry out grouting procedure immediately from mixer, and middle holding time must not surpass 5min.
Consider that the High Strength Non-shrinking Filling Material heat of hydration is larger, template adopts the thick composite board of 15mm, is conducive to the High Strength Non-shrinking Filling Material insulation effect, and the steel frame beam cross section is large, and the concrete load is large, and specialized purpose-build is adopted in the reinforcing of beam forms.Because the compactness of High Strength Non-shrinking Filling Material is difficult for checking, double as steam vent therefore at beam one side template, the inspection eye that 8 diameters are 16mm is set, the hole absolute altitude is the position of above 200mm at the bottom of beam.
girder with rolled steel section en cased in concrete formwork erection structure comprises wooden form, rough ground, the steel pipe hoop, split bolt, reinforced bar support, the steel pipe bottom bracing, the steel pipe diagonal brace, height adjusting part, wooden form thickness is 15mm, the wooden form outside arranges rough ground, rough ground thickness is 20~25mm, the rough ground outside arranges the steel pipe hoop, below beam sill template, rough ground is set, the steel pipe bottom bracing is set below rough ground, the steel pipe diagonal brace is linked to be integral body with steel pipe bottom bracing and steel pipe hoop, the steel pipe bar slope is 60 °~70 °, below the steel pipe bottom bracing, height adjusting part is set, the offside wooden form connects by split bolt, the split bolt diameter is 14~16mm, offside depth of beam 1/3 is to arrange reinforced bar support between the wooden form of upper part, the reinforced bar support diameter is 16~18mm, the reinforced bar support setting space is for to arrange 1 every 300~350mm.
Build to other end column cap from newel post's head while building, will check when building whether High Strength Non-shrinking Filling Material arrives position, inspection eye place, confirm the rear enclosed steam vent.
, due to High Strength Non-shrinking Filling Material easy segregation under high vibration,, therefore should avoid the vibrating spear direct tamping when High Strength Non-shrinking Filling Material vibrates, adopt at the bottom of beam and beam side tapping template is carried out jolt ramming.
The method of vibrating simultaneously inside and outside adopting during concrete vibrating is carried out.Outside by the little vibrating spear vibration additional steel pipe of diameter less than 30mm, band moving platen surface vibration, discharge the bubble in reinforcing bar and reinforcing bar, takes simultaneously artificial tapping template; When the concrete of pervibration top, the excellent degree of depth under strict control, vibrating spear mustn't be inserted into High Strength Non-shrinking Filling Material and vibrate, and prevents that High Strength Non-shrinking Filling Material is subject to judder and emanates.
After beam concreting final set, cover 1 layer of plastic sheeting and 2 layers of straw screen or mat and be incubated by water conservation, simultaneously bury the temperature temperature measurer after reinforcing bar binding underground in reinforcing bar, at the bottom of detecting beam respectively, in, upper 3 temperature, carry out maintenance according to the actual temperature difference.The steel frame beam concrete curing time is no less than 14d.
Construction quality of the present invention is better guaranteed, while saving construction cost, reduction of erection time.
Description of drawings
Fig. 1 girder with rolled steel section en cased in concrete formwork erection organigram.
Reference numeral: 1, wooden form, 2, rough ground, 3, the steel pipe hoop, 4, split bolt, 5, reinforced bar support, 6, the steel pipe bottom bracing, 7, the steel pipe diagonal brace, 8, height adjusting part.
Specific embodiment 1
Below in conjunction with accompanying drawing, the present embodiment is described in detail.
Certain engineering adopts girder with rolled steel section en cased in concrete, and beam section height is 1500mm, and width is 800mm, and span is 12m, the shaped steel span 12m in beam, and cross section is I shape, reinforcing bar master muscle diameter is 28mm.
At the bottom of beam, High Strength Non-shrinking Filling Material is adopted at 1/3 following position, and at the bottom of beam, 2/3 adopts concrete with upper part, and in concrete, cobble-stone diameter is controlled to be in 15mm.
The beam sequence of construction is: first builds High Strength Non-shrinking Filling Material, starts concreting after 3h, and top concreting is not complete before initial set at High Strength Non-shrinking Filling Material.The High Strength Non-shrinking Filling Material initial setting time is controlled to be 6~8h, and the deck-molding strength contraction-free grouting concrete is cast in 2~3h and completes.
The High Strength Non-shrinking Filling Material slump is 300~350mm.High Strength Non-shrinking Filling Material adopts forced mixer to stir, and mixing time, greater than 3min, is finished using in the slurry 1h that stirs into continuously, and slurry out should carry out grouting procedure immediately from mixer, and middle holding time must not surpass 5min.
Template adopts the thick composite board of 15mm.At beam one side template, the inspection eye that 8 diameters are 16mm is set and doubles as steam vent, the hole absolute altitude is the position of above 200mm at the bottom of beam.
Fig. 1 is girder with rolled steel section en cased in concrete formwork erection organigram.the present embodiment Shaped Steel concrete beam mould board installs structure and comprises wooden form 1, rough ground 2, steel pipe hoop 3, split bolt 4, reinforced bar support 5, steel pipe bottom bracing 6, steel pipe diagonal brace 7, height adjusting part 8, wooden form 1 thickness is 15mm, wooden form 1 outside arranges rough ground 2, rough ground 2 thickness are 22mm, rough ground 2 outsides arrange steel pipe hoop 3, below beam sill template 1, rough ground 2 is set, steel pipe bottom bracing 6 is set below rough ground 2, steel pipe diagonal brace 7 is linked to be integral body with steel pipe bottom bracing 6 and steel pipe hoop 3, steel pipe diagonal brace 7 gradients are 65 °, height adjusting part 8 is set below steel pipe bottom bracing 7, offside wooden form 1 connects by split bolt 4, split bolt 4 diameters are 16mm, offside depth of beam 1/3 is to arrange reinforced bar support 5 between upper part wooden form 1, reinforced bar support 5 diameters are 18mm, the reinforced bar support setting space is for to arrange 1 every 320mm.
For ease of exhaust in beam, build to other end column cap from newel post's head while building, to check when building whether High Strength Non-shrinking Filling Material arrives position, inspection eye place, confirm the rear enclosed steam vent.
Should avoid the vibrating spear direct tamping when High Strength Non-shrinking Filling Material vibrates, adopt at the bottom of beam and beam side tapping template is carried out jolt ramming.
The method of vibrating simultaneously inside and outside adopting during concrete vibrating is carried out.Outside by the little vibrating spear vibration additional steel pipe of diameter less than 30mm, band moving platen surface vibration, discharge the bubble in reinforcing bar and reinforcing bar, takes simultaneously artificial tapping template; When the concrete of pervibration top, the excellent degree of depth under strict control, vibrating spear mustn't be inserted into High Strength Non-shrinking Filling Material and vibrate, and prevents that High Strength Non-shrinking Filling Material is subject to judder and emanates.
After beam concreting final set, cover 1 layer of plastic sheeting and 2 layers of straw screen or mat and be incubated by water conservation, simultaneously bury the temperature temperature measurer after reinforcing bar binding underground in reinforcing bar, at the bottom of detecting beam respectively, in, upper 3 temperature, carry out maintenance according to the actual temperature difference.The steel frame beam concrete curing time is no less than 14d.
In the present embodiment, the form removable back rest is not found mass defect, and quality is better guaranteed, has saved simultaneously great amount of cost, has shortened the duration.

Claims (2)

1. steel reinforced concrete beam construction method, it is characterized in that beam at the bottom of 1/3 following position adopt High Strength Non-shrinking Filling Material, at the bottom of beam, 2/3 adopts concrete with upper part, in concrete, cobble-stone diameter is controlled to be in 15mm; The beam sequence of construction is: first builds High Strength Non-shrinking Filling Material, starts concreting after 3h, and top concreting is not complete before initial set at High Strength Non-shrinking Filling Material; The High Strength Non-shrinking Filling Material initial setting time is controlled to be 6~8h, and the deck-molding strength contraction-free grouting concrete is cast in 2~3h and completes; The High Strength Non-shrinking Filling Material slump is 300~350mm; High Strength Non-shrinking Filling Material adopts forced mixer to stir, and mixing time, greater than 3min, is finished using in the slurry 1h that stirs into continuously, and slurry out should carry out grouting procedure immediately from mixer, and middle holding time must not surpass 5min; The girder with rolled steel section en cased in concrete formwork erection adopts specialized purpose-build, and template adopts the thick composite board of 15mm; At beam one side template, the inspection eye that 8 diameters are 16mm is set and doubles as steam vent, the hole absolute altitude is the position of above 200mm at the bottom of beam.
2. steel reinforced concrete beam construction method according to claim 1, it is characterized in that girder with rolled steel section en cased in concrete formwork erection structure comprises wooden form, rough ground, the steel pipe hoop, split bolt, reinforced bar support, the steel pipe bottom bracing, the steel pipe diagonal brace, height adjusting part, wooden form thickness is 15mm, the wooden form outside arranges rough ground, rough ground thickness is 20~25mm, the rough ground outside arranges the steel pipe hoop, below beam sill template, rough ground is set, the steel pipe bottom bracing is set below rough ground, the steel pipe diagonal brace is linked to be integral body with steel pipe bottom bracing and steel pipe hoop, the steel pipe bar slope is 60 °~70 °, below the steel pipe bottom bracing, height adjusting part is set, the offside wooden form connects by split bolt, the split bolt diameter is 14~16mm, offside depth of beam 1/3 is to arrange reinforced bar support between the wooden form of upper part, the reinforced bar support diameter is 16~18mm, the reinforced bar support setting space is for to arrange 1 every 300~350mm.
CN2013103438812A 2013-08-03 2013-08-03 Construction method for steel reinforced concrete beam Pending CN103397741A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013103438812A CN103397741A (en) 2013-08-03 2013-08-03 Construction method for steel reinforced concrete beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013103438812A CN103397741A (en) 2013-08-03 2013-08-03 Construction method for steel reinforced concrete beam

Publications (1)

Publication Number Publication Date
CN103397741A true CN103397741A (en) 2013-11-20

Family

ID=49561436

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013103438812A Pending CN103397741A (en) 2013-08-03 2013-08-03 Construction method for steel reinforced concrete beam

Country Status (1)

Country Link
CN (1) CN103397741A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105350441A (en) * 2015-11-30 2016-02-24 广东工业大学 Concrete combined box beam internally provided with tie bar steel and box column
CN110700490A (en) * 2019-10-30 2020-01-17 武汉市盘龙明达建筑有限公司 Transfer floor large-span steel reinforced concrete beam and construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006169826A (en) * 2004-12-16 2006-06-29 Kajima Corp Steel-concrete composite beam and its construction method
CN201180313Y (en) * 2008-03-14 2009-01-14 中建三局建设工程股份有限公司 Large-span dense-reinforcement steel beam pouring structure
CN101775903A (en) * 2010-01-22 2010-07-14 北京首钢建设集团有限公司 Construction method for pouring after settlement of reinforced concrete continuous beam with cohesive pre-stress
KR20100111883A (en) * 2009-04-08 2010-10-18 (주)대우건설 Method for constructing beam reinforced concrete in delay joint sections by using coupler
CN102182309A (en) * 2011-03-22 2011-09-14 中国十九冶集团有限公司 Construction method of steel reinforced concrete beam of large metallurgical industry factory building

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006169826A (en) * 2004-12-16 2006-06-29 Kajima Corp Steel-concrete composite beam and its construction method
CN201180313Y (en) * 2008-03-14 2009-01-14 中建三局建设工程股份有限公司 Large-span dense-reinforcement steel beam pouring structure
KR20100111883A (en) * 2009-04-08 2010-10-18 (주)대우건설 Method for constructing beam reinforced concrete in delay joint sections by using coupler
CN101775903A (en) * 2010-01-22 2010-07-14 北京首钢建设集团有限公司 Construction method for pouring after settlement of reinforced concrete continuous beam with cohesive pre-stress
CN102182309A (en) * 2011-03-22 2011-09-14 中国十九冶集团有限公司 Construction method of steel reinforced concrete beam of large metallurgical industry factory building

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
陈明留: "大跨密筋钢骨梁灌浆料与混凝土浇筑结合施工技术", 《施工技术》, no. 7, 30 July 2005 (2005-07-30), pages 3 - 1 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105350441A (en) * 2015-11-30 2016-02-24 广东工业大学 Concrete combined box beam internally provided with tie bar steel and box column
CN110700490A (en) * 2019-10-30 2020-01-17 武汉市盘龙明达建筑有限公司 Transfer floor large-span steel reinforced concrete beam and construction method
CN110700490B (en) * 2019-10-30 2021-07-13 武汉市盘龙明达建筑有限公司 Transfer floor large-span steel reinforced concrete beam and construction method

Similar Documents

Publication Publication Date Title
CN108678258A (en) Large-span hemispherical reinforced concrete dome structure and construction method thereof
CN106088326B (en) Assembling frame rod structure based on 3D printing
CN106437142A (en) Construction method and double-layer formwork structure for cast-in-situ slope roof
CN107724680A (en) A kind of high-storey building frame structure beam-column node construction method
CN101818570B (en) Method for constructing girder structure conversion layer of high-rise building
CN105064555A (en) Structural wallboard for superimposed decorative layer and insulating layer and construction method
CN105839850A (en) Basement reverse-construction scape post-casting pre-stressed construction method
CN103015717A (en) Construction process for coating faced concrete outside ultrahigh steel tube column after floor is closed
CN106836463A (en) The constructing device and construction method of cushion cap and ground girder construction
CN209482591U (en) Prefabricated molds shell structure column construction structure
CN107143065A (en) Prefabricated load bearing concrete wall panel combining structure and construction method
CN206267422U (en) A kind of assembly concrete superposed column
CN103046465B (en) Reinforcing construction method for foam core die precast hollow plate beam
CN101487293A (en) Concrete pouring method for beam-column joints with different strength grades
CN101984189A (en) Construction method of large steel concrete composite multi-terrace slope skewback
CN101302783A (en) Building cast-in-situ roof
CN104631680B (en) A kind of construction method of thin-walled square chest superstructure
CN200999409Y (en) Prefabricated thin-plate cast-in-situs super-positioned hollow core floor slab
CN103397741A (en) Construction method for steel reinforced concrete beam
CN206245730U (en) A kind of cast-in-place pitched roof double template structure
CN107859061A (en) A kind of construction method of box culvert primary concreting
CN205476487U (en) Dismantled cyclic utilization device of centre form come -up is packed to control light block
CN206529881U (en) The constructing device of cushion cap and ground girder construction
CN103397778A (en) Method for constructing high-rise commercial and residential building structure transfer floor
CN206956978U (en) Prefabricated load bearing concrete wall panel combining structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20131120