KR20100065450A - Construction method using environmental affinity type bank - Google Patents

Construction method using environmental affinity type bank Download PDF

Info

Publication number
KR20100065450A
KR20100065450A KR1020080123783A KR20080123783A KR20100065450A KR 20100065450 A KR20100065450 A KR 20100065450A KR 1020080123783 A KR1020080123783 A KR 1020080123783A KR 20080123783 A KR20080123783 A KR 20080123783A KR 20100065450 A KR20100065450 A KR 20100065450A
Authority
KR
South Korea
Prior art keywords
block
eye
space
blocks
aggregate
Prior art date
Application number
KR1020080123783A
Other languages
Korean (ko)
Other versions
KR101160882B1 (en
Inventor
이화
Original Assignee
이화
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 이화 filed Critical 이화
Priority to KR1020080123783A priority Critical patent/KR101160882B1/en
Publication of KR20100065450A publication Critical patent/KR20100065450A/en
Application granted granted Critical
Publication of KR101160882B1 publication Critical patent/KR101160882B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • E02B3/14Preformed blocks or slabs for forming essentially continuous surfaces; Arrangements thereof
    • AHUMAN NECESSITIES
    • A01AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
    • A01GHORTICULTURE; CULTIVATION OF VEGETABLES, FLOWERS, RICE, FRUIT, VINES, HOPS OR SEAWEED; FORESTRY; WATERING
    • A01G2/00Vegetative propagation
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/40Miscellaneous comprising stabilising elements

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental Sciences (AREA)
  • Paleontology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Developmental Biology & Embryology (AREA)
  • Botany (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Revetment (AREA)

Abstract

PURPOSE: A slope construction method using environmentally friendly revetment blocks is provided to safely protect a slope from a flood and secure enough space for inhabitation of fishers and vegetation. CONSTITUTION: A slope construction method using environmentally friendly revetment blocks is as follows. The floor side of a slope is excavated into a depth and cement concrete is placed to form foundation ground(30). Second revetment blocks(10,20) are installed at certain intervals in the foundation ground. Two to five first revetment blocks are successively installed between the second revetment blocks. A second pipe(24) functioning as a space for fish is connected to the end of a first pipe(23) installed in the second revetment block. Aggregate(50) is filled inside the first and second revetment blocks and an intervening space between the revetment blocks and a slope. Other first revetment blocks are stacked like stairs on the top of the first and second revetment blocks. Aggregate is filled up inside the first revetment blocks stacked on the top of the first and second revetment blocks and an intervening space between the first revetment blocks and the slope. A vegetative revetment block(60) is installed on the rest exposed side of the slope.

Description

환경친화형 호안블록을 이용한 법면 시공방법{Construction method using environmental affinity type bank}Construction method using environmental affinity type bank

본 발명은 수로, 하천, 강 등의 제방이나 방조제 또는 배수로(이하 "법면"이라 통칭함)에 설치되어 홍수 등으로부터 수로, 하천, 강 등의 법면을 보호하고, 어류의 서식과 식물이 식생 될 수 있는 충분한 공간이 확보되어 생태계를 보존하며, 오염된 상기 수로, 하천, 강등을 흐르는 물을 정화하여 수질을 향상시킬 수 있도록 한 환경친화형 호안블록을 이용한 법면 시공방법에 관한 것이다.The present invention is installed in a dike or embankment of a water channel, a river, a river or the like (hereinafter referred to as "law") to protect the water surface, a river, a river, and the like from floods, and to inhabit fish habitat and plants. The present invention relates to a legal construction method using an environmentally friendly shore revetment block which can secure sufficient space to preserve an ecosystem and improve water quality by purifying the water flowing through the contaminated waterways, rivers, and rivers.

최근 하천 제방이나 수로 유실을 방지하고 기상 이변으로 인한 홍수피해를 줄이고자 하천 개발공사가 활발히 진행되고 있으며, 정비되는 하천의 시공방식은 자연 생태계의 보존 및 주변 환경과 조화를 이루도록 녹지를 조성시켜 시공되고 있는 추세이다.Recently, river development works have been actively conducted to prevent the loss of river banks and waterways and to reduce flood damage due to extreme weather.The streams are being constructed by creating green areas in harmony with the preservation of natural ecosystems and the surrounding environment. It is becoming a trend.

일반적으로, 하천의 제방이나 방조제 또는 배수로에는 지반의 침식 및 침하를 방지하고 수로의 유실을 막는 방법으로 다양한 형태의 호안블록이나 돌망태 및 옹벽, 그리고 자연석 등을 이용하여 시공하고 있다.In general, river banks are constructed using various types of revetment blocks, gabions and retaining walls, and natural stones in order to prevent erosion and settlement of the ground and to prevent the loss of waterways.

그러나 상기 종래 돌망태, 옹벽은 주변의 환경과 조화를 이루지 못할 뿐만 아니라 하천 생태계의 단절을 초래한다는 문제점이 있고, 자연석의 경우 시공이 어렵고 시공조건이 까다롭다는 문제점이 있어서, 최근에는 생태계의 보존 및 하천의 주변 환경과 조화를 이루는 환경 친화적인 호안블록이 선호되고 있다.However, the conventional gabions and retaining walls not only do not harmonize with the surrounding environment, but also cause problems in the stream ecosystem, and in the case of natural stones, construction is difficult and the construction conditions are difficult. Environmentally friendly shore banks in harmony with the river's surroundings are preferred.

특히, 호안블록은 도로변, 제방, 하천변, 해안 변 및 각종 법면을 정비하고 그 법면의 토사유출 및 붕괴를 방지하기 위해 설치되는 것으로 상기와 같은 호안블록은 강화목적 이외에 잔디나 화초 등이 자랄 수 있는 식생환경을 형성하여 생태계 복원에 일조함으로써 자연친화적 환경조성을 가능토록 하기 위한 용도로서 사용된다.In particular, the raft block is installed to maintain roadsides, embankments, riversides, coastal sides, and various slopes and to prevent the outflow and collapse of the slopes. It is used as a way to make nature friendly environment by forming vegetation environment and contributing to the restoration of ecosystem.

최근 들어 많이 시공되고 있는 콘크리트 재질의 호안블록은 인접하는 호안블록을 상호 끼워 맞춤하도록 호안블록의 몸체에 결합부를 형성시켜 그 결합부에 의해 호안블록을 결속하는 방법으로 시공하거나 별도의 결속용 부재를 이용하여 강제로 체결하는 방법이 있다.In recent years, a lot of concrete revetment block is formed by forming a coupling part in the body of the relieving block to fit the adjacent relieving block to each other by binding the relieving block by the coupling part or a separate binding member. There is a method of forcibly tightening by using.

상기와 같은 종래 호안블록들은 그 재질이 콘크리트임으로 식생환경을 조성하기 위한 구조가 부재하였고, 오히려 지중에서 자라던 기반식물의 성장을 가로막는 등의 환경파괴 기능을 하고 있어 최근에는 콘크리트 재질의 호안블록 사용을 제안하고 있는 추세이다. As the conventional revetment blocks as described above have a structure for creating a vegetation environment because the material is concrete, rather than using a revetment block made of concrete in recent years, it has a destructive function such as preventing the growth of the plant grown in the ground. The trend is to propose.

또한 상기 콘크리트재질의 호안블록을 이용하여 도로변, 제방, 하천변, 해안 변 및 각종 법면을 시공한 후 그 시공된 블록의 일부가 훼손되게 되면 우천시 상기 훼손된 부분의 지면으로 빗물이 스며들게 되고 그 스며들은 빗물의 배수가 상기 시공된 콘크리트재질의 호안블록으로 인해 지연되어 지반이 약화됨으로 그에 따른 상기 도로변, 제방, 하천변, 해안 변 및 각종 법면이 유실되는 문제점이 있었다.In addition, after constructing roadsides, embankments, riversides, coastal edges, and various legal surfaces using the revetment blocks of the concrete material, if some of the constructed blocks are damaged, rainwater penetrates into the ground of the damaged parts during rainy weather and the permeated rainwater. Due to the delay of the drainage of the constructed concrete material is delayed due to the weakening of the ground, there was a problem that the road side, embankment, river side, coastal side and various slopes are lost.

상기와 같은 호안블록의 문제점을 해결하기 위하여 제공된 등록실용신안공보 제0337316호(2003.13.17, 고안의 명칭: 생태계 어초블록)에서는 사각형상의 판체로 전면은 길이방향을 따라 상측에서 하측으로 법면을 형성하고, 양측 일 측은 체결 홈이 타 측은 체결돌기가 형성되며, 상면에는 피라미드형상의 돌출부가 각각 대응하게 일체로 형성되어 상기 돌출부의 각 면에 어류들이 이동할 수 있는 이동통로가 형성되고, 바닥면에는 가장자리를 따라 하천 바닥면에 고정할 수 있는 복수 개의 고정 돌기와 돌출부의 이동통로와 통공될 수 있도록 공간부가 형성되게 하여 여류의 서식과 식물이 식생 할 수 있게 하여 오염된 하천수의 정화와 더불어 자연생태계를 보존 할 수 있도록 하고 있다.Registered Utility Model Publication No. 037316 (2003.13.17, Designated Name: Ecosystem Echo Block) provided to solve the problems of the above-mentioned retreat block has a square plate, and the front face is formed from the upper side to the lower side along the longitudinal direction. On both sides, one side of the fastening groove is formed on the other side of the fastening protrusion, the upper surface of the pyramid-like protrusions are formed integrally correspondingly to each side of the protrusions to form a moving passage through which the fish can move, the bottom surface A plurality of fixing protrusions that can be fixed to the bottom of the river along the edge and a moving passage of the protrusions are formed so that the space is formed so that the habitat and vegetation of the breeze can be planted, thereby purifying the contaminated river water and the natural ecosystem. I can save it.

그러나 상기 등록실용신안공보 제0337316호의 호안블록은 형상이 복잡하고 둘레의 길이가 일정치 않아 설치작업이 까다로울 뿐만 아니라 설치될 수 있는 환경이 제한적이며, 제작이 어렵다는 단점이 있어 원가의 상승과 더불어 설치비용의 증가를 가져오는 단점이 있다.However, the registration block of the Utility Model Publication No. 0337316 has a complicated shape and irregular circumference, which makes installation work difficult and the environment that can be installed is limited and difficult to manufacture. The disadvantage is the increase in cost.

또한 상기 호안블록은 단시간 내에 대량생산이 불가능할 뿐만 아니라 여러 번의 공정을 통해 제조됨에 따라 인건비의 상승과 작업효율의 저하를 가져오는 단점이 있으며, 더욱이 상기의 블록은 숙련된 기술자에 의해 제작이 가능함에 따라 그 생산수령이 적을 뿐만 아니라 제품의 비용이 증가하게 되는 문제점이 있다.In addition, the revetment block is not only impossible to mass production in a short time, but also has a disadvantage in that the labor cost and the work efficiency is lowered because it is manufactured through a number of processes, moreover, the block can be manufactured by a skilled technician Therefore, there is a problem that the production receipt is not only small, but also the cost of the product increases.

본 발명은 상기와 같은 문제점을 감안하여 이를 해소하고자 발명한 것으로서, 그 목적은 홍수 등으로부터 수로, 하천, 강 등의 법면을 안전하고 견고하게 보호 하고, 어류의 서식과 식물이 식생될 수 있는 충분한 공간을 확보하여 생태계를 보존하며, 오염된 상기 수로, 하천, 강등을 흐르는 물을 정화하여 수질을 향상시킬 수 있도록 한 환경친화형 호안블록을 이용한 법면 시공방법을 제공함에 있다.The present invention has been invented to solve this problem in view of the above problems, the object is to securely and firmly protect the surface of waterways, rivers, rivers, etc. from floods, etc., sufficient to allow the habitat and plants of fish The present invention provides a method for constructing a surface using an environmentally friendly shore revetment block to secure a space to preserve an ecosystem and to improve water quality by purifying the water flowing through the contaminated waterways, rivers, and rivers.

상기 목적을 달성하기 위한 본 발명의 기술적 수단은 4방에 목재기둥(11a)이 세워지고 그 목재기둥에 목재횡대(11b)를 등 간격으로 설치하여 4방 측면(11)을 형성한 제1호안블록(10)을 마련하는 단계; 4방에 목재기둥(21a)이 세워지고 그 목재기둥에 목재횡대(21b)를 등 간격으로 설치하여 4방 측면(21)을 형성하고 선택된 일 측에는 어소기능을 하는 제1파이프(23)를 설치하여 된 제2호안블록(20)을 마련하는 단계; 상기 제1 및 제2호안블록(10,20)을 법면(40)의 바닥면(41)에 설치하기 위하여 법면의 바닥면을 일정깊이로 파고 이에 시멘트콘크리트를 타설하여 기초지반(30)을 조성하는 단계; 상기 기초지반에 제2호안블록(10,20)을 일정간격을 유지하도록 설치하고 상기 제2호안블록의 일정간격 사이에 제1호안블록(10)을 2-5개 연이어 설치하는 단계; 상기 일정간격을 유지하도록 설치된 제2호안블록(20)에 설치 된 제1파이프(23)의 끝단에 어소기능을 하는 제2파이프(24)를 상호 연결 설치하는 단계; 상기 제1 및 제2호안블록(10,20)의 내부 공간부(12,22)와 제1 및 제2호안블록과 법면의 사이 공간에 골재(50)를 채우는 단계; 상기 바닥면(41)에 설치된 제1 및 제2호안블록(10,20)의 상부에 제1호안블록(10)을 계단형태가 되도록 적층하여 고정시키는 단계: 상기 제1 및 제2호안블록(10,20)의 상부에 적층된 제1호안블록(10)의 공간부(12)와 상기 적층된 제1호안블록(10)과 법면(40)의 사이 공간에 골재(50)를 채우는 단계; 상기 적층된 제1호안블록(10)과 법면(40)의 사이 공간에 골재(50)를 채우고 발생하는 나머지 외부로 노출된 법면(40)에 통상의 판형 식생 호안블록(60)을 설치하는 단계를 포함하는 구성으로 이루어진다.Technical means of the present invention for achieving the above object is the first proposal to form a four-sided side 11 by installing a wooden pillar (11a) in four rooms and a wooden cross (11b) at equal intervals in the wooden pillar Preparing a block 10; Wooden pillars 21a are erected in four rooms, and wooden crossbars 21b are installed on the wooden pillars at equal intervals to form four-sided sides 21, and a selected first pipe 23 is installed on the selected side. Providing a second draft block 20; In order to install the first and second eye blocks 10 and 20 on the bottom surface 41 of the law surface 40, the bottom surface of the law surface is dug to a certain depth and cement concrete is poured thereon to form the foundation ground 30. Making; Installing second second eye blocks 10 and 20 on the foundation ground so as to maintain a predetermined interval, and sequentially installing two fifth eye blocks 10 and 10 between the second one eye blocks; Interconnecting and installing a second pipe (24) which functions as an associative function at the end of the first pipe (23) installed in the second arc block (20) installed to maintain the predetermined interval; Filling the aggregate (50) in the space between the internal spaces (12, 22) of the first and second eye block (10, 20) and the first and second eye block and the normal surface; Stacking and fixing the first relief block 10 to a step shape on top of the first and second relief blocks 10 and 20 installed on the bottom surface 41: the first and second relief blocks ( Filling the aggregate 50 into the space 12 of the first bank block 10 stacked on top of the 10 and 20 and the space between the stack of the first bank block 10 and the surface 40; Filling the aggregate 50 in the space between the stacked first first eye block 10 and the law surface 40 and installing a conventional plate-like vegetation relief eye block 60 on the remaining outer surface 40 generated It consists of a configuration comprising a.

이상과 같은 본 발명은 환경친화형 목재 호안블록 이용하여 본 발명의 방법에 의해 법면을 시공함으로써, 홍수 등으로 인하여 수로, 하천, 강 등에 강한 수입의 물이 진행하여도 법면 및 지면의 침식과 유실을 방지할 수 있음은 물론, 어류가 은신 및 휴식을 취할 수 있는 어소 공간 및 식물이 식생할 수 있는 식물 식생공간이 충분히 확보됨으로써 생태계보존과 녹지 환경을 조성할 수 있으며, 상기 수로, 하천, 강등을 흐르는 오염된 물을 정화할 수 있어 수질을 향상시킬 수 있는 효과가 있다.The present invention as described above by using the environmentally friendly wood revetment block by the method of the present invention, the erosion and loss of the surface and ground even if the water of strong imports such as waterways, rivers, rivers due to flooding, etc. proceeds It is possible to prevent, as well as to secure a habitat for the fish to hide and rest and the vegetation space where plants can be planted to create an ecosystem and green environment, the waterways, rivers, relegation It can purify the contaminated water flowing through it has the effect of improving the water quality.

본 발명의 환경친화형 목재 호안블록을 이용한 법면 시공방법은 4방에 목재기둥(11a)이 세워지고 그 목재기둥에 목재횡대(11b)를 등 간격으로 설치하여 4방 측면(11)을 형성한 제1호안블록(10)을 마련하는 단계; 4방에 목재기둥(21a)이 세워지고 그 목재기둥에 목재횡대(21b)를 등 간격으로 설치하여 4방 측면(21)을 형성하고 선택된 일 측에는 어소기능을 하는 제1파이프(23)를 설치하여 된 제2호안블록(20)을 마련하는 단계; 상기 제1 및 제2호안블록(10,20)을 법면(40)의 바닥면(41)에 설치하기 위하여 법면의 바닥면을 일정깊이로 파고 이에 시멘트콘크리트를 타설하여 기초지반(30)을 조성하는 단계; 상기 기초지반에 제2호안블록(10,20)을 일정간격을 유지하도록 설치하고 상기 제2호안블록의 일정간격 사이에 제1호안블록(10)을 2-5개 연이어 설치하는 단계; 상기 일정간격을 유지하도록 설치된 제2호안블록(20)에 설치된 제1파이프(23)의 끝단에 어소기능을 하는 제2파이프(24)를 상호 연결 설치하는 단계; 상기 제1 및 제2호안블록(10,20)의 내부 공간부(12,22)와 제1 및 제2호안블록과 법면의 사이 공간에 골재(50)를 채우는 단계; 상기 바닥면(41)에 설치된 제1 및 제2호안블록(10,20)의 상부에 제1호안블록(10)을 계단형태가 되도록 적층하여 고정시키는 단계: 상기 제1 및 제2호안블록(10,20)의 상부에 적층된 제1호안블록(10)의 공간부(12)와 상기 적층된 제1호안블록(10)과 법면(40)의 사이 공간에 골재(50)를 채우는 단계; 상기 적층된 제1호안블록(10)과 법면(40)의 사이 공간에 골재(50)를 채우고 발생하는 나머지 외부로 노출된 법면(40)에 통상의 판형 식생 호안블록(60)을 설치하는 단계를 포함하는 구성을 요지로 한다.In the construction method of the front surface using the eco-friendly timber revetment block of the present invention, the wooden pillars 11a are erected in four rooms, and the wooden cross bars 11b are installed on the wooden pillars at equal intervals to form four side surfaces 11. Preparing a first block 10; Wooden pillars 21a are erected in four rooms, and wooden crossbars 21b are installed on the wooden pillars at equal intervals to form four-sided sides 21, and a selected first pipe 23 is installed on the selected side. Providing a second draft block 20; In order to install the first and second eye blocks 10 and 20 on the bottom surface 41 of the law surface 40, the bottom surface of the law surface is dug to a certain depth and cement concrete is poured thereon to form the foundation ground 30. Making; Installing second second eye blocks 10 and 20 on the foundation ground so as to maintain a predetermined interval, and sequentially installing two fifth eye blocks 10 and 10 between the second one eye blocks; Interconnecting and installing a second pipe (24) which functions as an associative function at the end of the first pipe (23) installed in the second arc block (20) installed to maintain the predetermined interval; Filling the aggregate (50) in the space between the internal spaces (12, 22) of the first and second eye block (10, 20) and the first and second eye block and the normal surface; Stacking and fixing the first relief block 10 to a step shape on top of the first and second relief blocks 10 and 20 installed on the bottom surface 41: the first and second relief blocks ( Filling the aggregate 50 into the space 12 of the first bank block 10 stacked on top of the 10 and 20 and the space between the stack of the first bank block 10 and the surface 40; Filling the aggregate 50 in the space between the stacked first first eye block 10 and the law surface 40 and installing a conventional plate-like vegetation relief eye block 60 on the remaining outer surface 40 generated The configuration including the gist.

상기와 같은 요지를 갖는 본 발명에서 제1호안블록(10)의 구체적인 구성은 도1에 나타낸 바와 같이 4방에 목재기둥(11a)이 세워지고, 상기 각 목재기둥(11a)의 외부 측면에는 목재횡대(11b)가 등 간격으로 적어도 3개 이상 설치되어 목재횡대(11b)와 목재횡대(11b) 사이에 공간이 형성되는 4방 측면(11)이 형성되며, 상부 및 하부는 오픈되고 내부에는 공간부(12)가 형성되는 것으로 이루어진다.In the present invention having the above-described gist, the specific configuration of the first block 10 is a wooden pillar 11a is erected in four rooms, as shown in Figure 1, the wood on the outer side of each wooden pillar 11a At least three cross bars 11b are installed at equal intervals to form four sides 11 forming a space between the wood cross bars 11b and the wood cross bars 11b. The part 12 consists of being formed.

그리고 상기 본 발명에 따른 제2호안블록(20)의 구체적인 구성은 도2에 나타낸 바와 같이 4방에 목재기둥(21a)이 세워지고, 상기 각 목재기둥(21a)의 외부 측면에는 목재횡대(21b)가 등 간격으로 적어도 3개 이상 설치되어 목재횡대(21b)와 목재횡대(21b) 사이에 공간이 형성되는 4방 측면(21)이 형성되며, 상부 및 하부는 오픈되고 내부에는 공간부(22)가 형성되며, 그 공간부(22)를 형성하는 4방 측면(21) 중 하천을 향하는 전면과 법면(40)을 향하는 후면의 선택된 부분에는 상기 공간부(22)를 가로지르며 어소공간을 마련하는 제1파이프(23)를 설치하는 것으로 이루어진다.In addition, as shown in FIG. 2, the second pillar block 20 according to the present invention has a wooden pillar 21a erected in four rooms, and a wooden crossbar 21b on an outer side surface of each of the wooden pillars 21a. ) Is installed at least three or more at equal intervals to form a four-sided side 21 in which a space is formed between the wood crossbar 21b and the wood crossbar 21b. ) Is formed, and selected portions of the front side facing the stream and the rear side facing the normal surface 40 of the four side surfaces 21 forming the space portion 22 are provided with an associative space across the space portion 22. It consists of installing the 1st pipe 23 to make.

상기와 같은 본 발명의 제1 및 제2호안블록(10,20)의 각 구성에 대한 기능을 상세하게 설명하면 다음과 같다.The function of each component of the first and second eye blocks 10 and 20 of the present invention as described above will be described in detail as follows.

상기 목재기둥(11a,21a)에 설치되는 목재횡대(11b,21b)의 배열은, 상호 마주보는 일측 양 측면에 상호 동일한 높이로 설치되고, 상호 마주보는 타측 양 측면은 상기 일측 양 측면에 설치된 목재횡대(11b,21b)의 각 단부에 얹쳐지도록 설치된다.Arrangement of the wood rails (11b, 21b) installed in the wooden columns (11a, 21a), is installed at the same height on both sides of the opposite sides, the opposite sides of each other are installed on both sides of the wood It is provided so that it may be mounted to each edge part of the cross bars 11b and 21b.

상기에서 기둥(11a,21a)과 횡대(11b,21b)를 목재로 하는 이유는 환경 친화적으로 하기 위해서이고, 또 상기 4방 측면(11,21)을 형성하는 목재횡대(11b,21b)와 목재횡대(11b,21b) 사이에 공간을 형성하는 이유는 어소공간을 확보함은 물론, 외 부로 노출된 법면(40)으로 스며들은 수분의 배수를 원활하게 하기 위함이다. The reason why the columns 11a and 21a and the crossbars 11b and 21b are made of wood is to be environmentally friendly, and the wood crossbars 11b and 21b and the wood forming the four sides 11 and 21 are made of wood. The reason why the space is formed between the transverses (11b, 21b) is to ensure the drainage space, as well as to facilitate the drainage of moisture permeated into the external surface 40 exposed.

또 상기 중공부(12,22)에는 골재(50) 및 괴상의 물정화제(51)가 채워지는데 그 이유는 제1 및 제2호안블록(10,20)에 중량을 부여하여 안정성을 확보함과 동시에 흐르는 물을 정화(자정작용에 도움을 주고)하고, 또 수로, 하천, 강 등을 흐르는 수압이 법면(40)과 직접 접촉되어 충격을 줌으로서 발생하는 침식, 침하, 유실을 방지하는 수압을 완충하기 위해서이다.In addition, the hollow parts 12 and 22 are filled with aggregate 50 and the bulk water purifying agent 51, because the first and second eye blocks 10 and 20 are weighted to secure stability. At the same time, the water flow is purified (to help with the self-cleaning), and the water pressure flowing through the waterways, rivers, rivers, etc. is directly contacted with the surface 40 to shock and prevent erosion, settlement, and loss generated by the impact. To buffer.

상기 괴상의 물정화제(51)는 숯 덩어리 또는 세라믹 덩어리로서 그들의 물 정화 효능은 이미 널리 알려진 것으로 그에 대한 구체적인 설명은 생략한다. 또 수로, 하천, 강 등을 흐르는 물은 제1 및 제2호안블록(10,20)에 채워진 골재와 부딪치면서 대기 중의 산소 용존 율을 높여 물의 정화작용에 도움을 준다.The bulk water purification agent 51 is a charcoal or a ceramic mass, and their water purification efficacy is well known, and a detailed description thereof will be omitted. In addition, the water flowing through the channel, rivers, rivers, etc. collide with the aggregates filled in the first and second eye blocks (10, 20) to increase the oxygen dissolved rate in the air to help the purification of the water.

상기 골재(50)와 골재(50)의 사이 또는 골재(50)와 괴상의 물정화제(51) 사이는 어류의 은신 및 휴식을 할 수 있는 공간이 되는 것이며, 그와 아울러 식물이 식생 될 수 있는 공간이 되는 것이다. 한편 상기 골재(50)와 골재(50)의 사이 또는 골재(50)와 괴상의 물정화제(51) 사이에는 주위의 흙이 비산되어 들어가거나 인위적으로 사람이 흙을 채워주기 때문에 식물의 식생이 가능하다.Between the aggregate 50 and the aggregate 50 or between the aggregate 50 and the bulk water purifying agent 51 is a space for hiding and resting the fish, and at the same time the plant can be planted It becomes a space. On the other hand, between the aggregate 50 and the aggregate 50 or between the aggregate 50 and the bulk water purifying agent 51, the surrounding soil is scattered or artificially fills the soil, so the vegetation of the plant is possible. Do.

그리고 상기 목재기둥(11a,21a)과 목재횡대(11b,21b)의 형태는 원기둥형 또는 3각 이상의 각형기둥 중 어느 것을 선택하여 사용해도 무방하며, 상기 제1 및 제2호안블록(10,20)을 형상은 정4면 또는 직4면체로 형성시키는데 그 이유는 수로, 하천, 강 등의 법면(40) 바닥면(41)에 일렬로 설치하기 용이하게 하기 위함이다.And the shape of the wooden columns (11a, 21a) and the wooden cross (11b, 21b) may be selected from any one of a cylindrical or triangular prisms or more, and the first and second eye block (10, 20) ) Is formed into a tetrahedron or a tetrahedron, for the purpose of facilitating installation in a line 41 on the bottom surface 41 of a normal surface 40 such as a channel, a river or a river.

또 상기 제1 및 제2호안블록(10,20)에서 일 측의 목재기둥(11a,21a)이 위치 하는 부분의 목재횡대(11,b21b) 단부는 상기 해당 목재기둥(11a,21a)으로부터 외부로 일정길이 연장 형성되게 설치하는데, 그 이유는 인접하는 호안블록과의 상호 연결 설치를 용이하게 하기 위함이고, 상기 인접하는 호안블록과의 상호 연결 설치를 용이하게 하는 방법은 상기 연장 형성된 부분이 인접한 호안블록의 4방 측면(11,21)에 형성되는 공간에 끼워져 결합된다.In addition, the ends of the timber cross (11, b21b) of the portion in which the first side and the second column (10, 20) wooden pillars (11a, 21a) is located from the corresponding wooden columns (11a, 21a) In order to facilitate the installation of the interconnection with the neighboring raft block, the method for facilitating the installation of the interconnection with the neighboring raft block is adjacent It is fitted in the space formed on the four sides 11 and 21 of the revetment block.

상기 제2호안블록(20)에 설치되는 어소공간이 되는 제1파이프(23)의 입구는 하천을 흐르는 물의 진행방향을 향하도록 설치하거나 또는 상기 제1파이프(23)의 입구가 물의 진행 방향을 향하도록 절곡시켜 형성시키는데 그 이유는 제1파이프(15) 내부로 흙이나 모래 및 기타 이물질이 들어가는 것을 방지하기 위함이다.The inlet of the first pipe 23, which is an ergonomic space installed in the second bank block 20, is installed so as to face the traveling direction of the water flowing through the stream, or the inlet of the first pipe 23 is directed to the water traveling direction. It is formed to be bent toward the reason for preventing the entry of dirt, sand and other foreign matter into the first pipe (15).

상기와 같은 기능을 하는 제1 및 제2호안블록(10,20)을 이용하여 해당 법면(수로, 하천, 강 등의 법면)을 시공하고자 할 때에는 도3 및 도4에 나타낸 바와 같이 법면(40)의 하부 바닥면(41)을 일정깊이로 파고 그 판 자리에 시멘트콘크리트를 타설하여 기초지반(30)을 조성한다. If you want to construct the corresponding surface (surfaces of waterways, rivers, rivers, etc.) using the first and second draft eye blocks (10,20) having the above functions, the surface (40) as shown in Figures 3 and 4 Dig the bottom surface 41 of the bottom to a certain depth and cast a cement concrete in the plate place to form a foundation ground (30).

이때 상기 기초지반(30)의 조성 두께는 40-70cm하는데 그 이유는 바닥면으로 흐르는 수압에 의해 흙의 침식, 침하, 유실되는 것을 방지하여 제1 및 제2호안블록(10,20)을 안전하게 지지하기 위해서이다. 그리고 상기 기초지반(30)에 제1 및 제2호안블록(10,20)을 고정하는 방법은 앵커볼트 또는 그이외의 지지부재를 이용하여 고정하면 된다.At this time, the composition thickness of the foundation ground 30 is 40-70cm because of the erosion, settlement and loss of the soil by the water pressure flowing to the bottom surface to secure the first and second bills (10, 20) safely To support it. And the method of fixing the first and second eye block 10, 20 to the base ground 30 may be fixed using an anchor bolt or other supporting members.

상기 기초지반(30)은 법면(40)을 따라 그 법면(40)의 하단 바닥면(41)에 형성되는 것이고, 상기 기초지반(30)에 제1 및 제2호안블록(10,20)을 배열하는 순서 는 제2호안블록(20)을 상기 기초지반(30)을 따라 일정간격을 유지하도록 설치하고, 그 일정간격 유지하도록 설치된 제2호안블록(20)의 사이사이에는 제1호안블록(10)을 2-5개 연이어 설치한다.The base ground 30 is formed on the bottom bottom surface 41 of the normal surface 40 along the normal surface 40, and the first and second draft eye blocks (10, 20) to the basic ground 30 The order of arranging is to install the second bank block 20 to maintain a predetermined interval along the foundation ground 30, and between the second bank block 20 installed to maintain the predetermined interval between the first bank block ( 10) are installed 2-5 consecutively.

그 후 상기 제2호안블록(20)에 설치된 어소기능을 하는 제1파이프(23)의 후단은 제2파이프(24)를 상호 연결 설치함으로써, 어소 공간(고기의 휴식 및 놀이 공간)을 더욱 많이 형성시켜 주는 것이다.After that, the rear end of the first pipe 23 serving as an associate function installed in the second arc block 20 is connected to the second pipe 24 so as to further increase the associate space (meat rest and play space). It is to form.

상기와 같이 어소공간을 형성하는 파이프의 연결 작업이 완료되면 상기 제1 및 제2호안블록(10,20)의 내부 공간부(12,22)와 제1 및 제2호안블록과 법면(40)의 사이 공간에 골재(50)를 채워 하천을 흐르는 물의 수압이 법면(40)에 직접 접촉되지 않고 상기 골재(50)와 부딪치면서 완충되어 법면(40)을 보호하도록 하는 것이다.When the connection work of the pipes forming the associal space is completed as described above, the inner space portions 12 and 22 of the first and second arc eye blocks 10 and 20, and the first and second arc eye blocks and the surface 40 are formed. Filling the aggregate 50 in the space between the water pressure of the water flowing in the stream is not directly in contact with the surface (40) bumps against the aggregate 50 to protect the surface (40).

또한 상기 제2호안블록(20)에 설치된 제1파이프(23) 및 그 제1파이프(23)의 후단을 상호 연결하는 제2파이프(24)에는 하천을 흐르는 물이 유입되어 고기들에게 안락한 어소공간을 제공하게 됨은 물론, 하절기에 햇빛을 피할 수 있음과 동시에 더위를 피할 수 있는 공간이 되는 것이다.In addition, the first pipe 23 and the second pipe 24 connecting the rear end of the first pipe 23 installed in the second bank block 20, the water flowing through the river flows in the comfort of fish Not only will it provide space, but it will also be able to avoid sunlight in summer and avoid heat.

상기 지초지반(30)에 설치된 제1 및 제2호안블록(10,20)의 상부에 제1호안블록(10)을 계단형태가 되도록 적층하여 고정시킨다. 그 이유는 하절기 장마 및 기타 우천으로 인하여 하천을 흐르는 물의 양이 많을 때에 법면(40)을 보호하도록 하기 위함이다.The first bank block 10 is laminated and fixed to a stepped shape on top of the first and second bank block 10 and 20 installed on the ground foundation 30. The reason is to protect the surface 40 when the amount of water flowing through the river due to the rainy season and other rainy season.

상기 제1 및 제2호안블록(10,20)의 상부에 제1호안블록(10)을 계단형태가 되 도록 적층하는 이유는 상기 적층되는 제1호안블록(10)의 안전성을 확보함은 물론, 법면(40)의 자연미를 살리기 위해서이다.The reason for stacking the first bank block 10 on the upper part of the first and second bank block 10, 20 to have a step shape is to ensure the safety of the stacked first bank block 10 as well. , To save the natural beauty of the law (40).

상기와 같이하여 제1 및 제2호안블록(10,20)의 상부에 제1호안블록(10)이 적층되면 그 적층된 제1호안블록(10)의 공간부(12)와 상기 적층된 제1호안블록(10)과 법면(40)의 사이 공간에 골재(50)를 채우는데 그 이유는 상술한 바와 같이 법면(40)을 수압으로부터 보호하기 위함이다.As described above, when the first bank block 10 is stacked on the first and second bank block 10 and 20, the space part 12 of the stacked first bank block 10 and the stacking agent are stacked. The aggregate 50 is filled in the space between the first eye block 10 and the surface 40 in order to protect the surface 40 from water pressure as described above.

그리고 상기 제1 및 제2호안블록(10,20)의 상부에 적층되는 호안블록을 제1 및 제2파이프(23,24)가 설치되지 않은 제1호안블록(10)으로 하는 이유는 하천을 흐르는 물의 양이 평상시에는 상기 상부의 제1호안블록(10)까지 도달하지 않기 때문에 어소공간이 필요 없기 때문이다.In addition, the reason why the first bank block 10, which is not provided with the first and second pipes 23 and 24, is the first bank block 10 which is stacked on top of the first and second bank block 10 and 20. This is because the amount of flowing water does not reach the first first eye block 10 in the upper part, and therefore, there is no need for an associative space.

한편 상기 적층된 제1호안블록(10)과 법면(40)의 사이 공간에도 골재(50)를 채우고 발생하는 나머지 외부로 노출된 법면(40)에는 통상의 판형 식생 호안블록(60)을 설치하여 법면(40)을 보호함은 물론, 그 호안블록(60)에서 식물이 자랄 수 있도록 하여 녹지의 제방을 형성한다.On the other hand, by filling the aggregate 50 in the space between the stacked first first eye block 10 and the normal surface 40, the conventional plate-shaped vegetation revetment block 60 is installed on the remaining external surface 40 generated As well as protecting the surface 40, the plant can grow in the lake block 60 to form a bank of greenery.

상술한 바와 같은 본 발명은 제1 및 제2호안블록에 어소공간이 충분히 확보됨으로써 하천의 생태계를 보존하고, 식물이 식생할 될 수 있어 녹지를 조성할 수 있으며, 골재 및 물정화제에 의해 흐르는 물을 정화할 수어 수질을 향상시키고, 수압을 동반한 물이 법면에 직접 부딪치지 않고 골재에 부딪쳐 완충시킴으로써 법면을 보호하고, 제1 및 제2호안블록을 목재로 함으로서 자연 친화감을 주는 장점이 있다.In the present invention as described above, by securing enough fishery space in the first and second lake block, the ecosystem of the river can be preserved, and the plants can be vegetated to create greenery, and the water flowing by aggregate and water purification agent Purify the water quality of the fish, protect the water surface by hitting the aggregate with water pressure does not directly hit the surface of the water surface, and has a natural affinity by using the first and second block of wood as a wood.

도 1은 본 발명에 따른 제1 실시예의 목재 호안블록 사시도,1 is a perspective view of a wooden revetment block according to a first embodiment of the present invention;

도 2는 본 발명에 따른 제2 실시예의 목재 호안블록 사시도,2 is a perspective view of a wooden revetment block according to a second embodiment of the present invention;

도 3은 본 발명에 따른 제1 및 제2 실시예의 목재 호안블록을 이용하여 시공한 법면의 측면도,Figure 3 is a side view of the construction surface using the wooden revetment block of the first and second embodiments according to the present invention,

도4는 본 발명에 따른 제1 및 제2 실시예의 목재 호안블록을 이용하여 시공한 법면의 정면도. Figure 4 is a front view of the surface of the construction using the wooden relief block of the first and second embodiments according to the present invention.

*도면의 주요부분에 대한 부호 설명*Description of the Related Art [0002]

10,20 : 제1 및 제2호안블록 11,21 : 측면10,20: 1st and 2nd proposal block 11,21: side

11a,21a : 목재기둥 11b,21b : 목재횡대11a, 21a: Wooden post 11b, 21b: Wood crossbar

12,22 : 공간부 23 : 제1파이프12,22: space part 23: first pipe

24 : 제2파이프 30 : 기초지반24: 2nd pipe 30: Foundation ground

40 : 법면 41 : 바닥면40: surface 41: the bottom surface

50 : 공재 51 : 정화제50: common material 51: purifier

60 : 판형호안블록60: plate-shaped shore block

Claims (4)

4방에 목재기둥(11a)이 세워지고 그 목재기둥에 목재횡대(11b)를 등 간격으로 설치하여 4방 측면(11)을 형성한 제1호안블록(10)을 마련하는 단계;A first pillar block (10) is formed in the four pillars (11a) is erected in the four pillars and the four sides (11) formed by equipping the wood pillars (11b) at equal intervals; 4방에 목재기둥(21a)이 세워지고 그 목재기둥에 목재횡대(21b)를 등 간격으로 설치하여 4방 측면(21)을 형성하고 선택된 일 측에는 어소기능을 하는 제1파이프(23)를 설치하여 된 제2호안블록(20)을 마련하는 단계;Wooden pillars 21a are erected in four rooms, and wooden crossbars 21b are installed on the wooden pillars at equal intervals to form four-sided sides 21, and a selected first pipe 23 is installed on the selected side. Providing a second draft block 20; 상기 제1 및 제2호안블록(10,20)을 법면(40)의 바닥면(41)에 설치하기 위하여 법면의 바닥면을 일정깊이로 파고 이에 시멘트콘크리트를 타설하여 기초지반(30)을 조성하는 단계;In order to install the first and second eye blocks 10 and 20 on the bottom surface 41 of the law surface 40, the bottom surface of the law surface is dug to a certain depth and cement concrete is poured thereon to form the foundation ground 30. Making; 상기 기초지반에 제2호안블록(10,20)을 일정간격을 유지하도록 설치하고 상기 제2호안블록의 일정간격 사이에 제1호안블록(10)을 2-5개 연이어 설치하는 단계;Installing second second eye blocks 10 and 20 on the foundation ground so as to maintain a predetermined interval, and sequentially installing two fifth eye blocks 10 and 10 between the second one eye blocks; 상기 일정간격을 유지하도록 설치된 제2호안블록(20)에 설치된 제1파이프(23)의 끝단에 어소기능을 하는 제2파이프(24)를 상호 연결 설치하는 단계;Interconnecting and installing a second pipe (24) which functions as an associative function at the end of the first pipe (23) installed in the second arc block (20) installed to maintain the predetermined interval; 상기 제1 및 제2호안블록(10,20)의 내부 공간부(12,22)와 제1 및 제2호안블록과 법면의 사이 공간에 골재(50)를 채우는 단계;Filling the aggregate (50) in the space between the internal spaces (12, 22) of the first and second eye block (10, 20) and the first and second eye block and the normal surface; 상기 바닥면(41)에 설치된 제1 및 제2호안블록(10,20)의 상부에 제1호안블록(10)을 계단형태가 되도록 적층하여 고정시키는 단계:Stacking and fixing the first relief block 10 in a stepped shape on top of the first and second relief blocks 10 and 20 installed on the bottom surface 41: 상기 제1 및 제2호안블록(10,20)의 상부에 적층된 제1호안블록(10)의 공간 부(12)와 상기 적층된 제1호안블록(10)과 법면(40)의 사이 공간에 골재(50)를 채우는 단계;The space portion 12 of the first bank block 10 stacked above the first and second bank block 10 and 20 and the space between the stacked first bank block 10 and the surface 40. Filling the aggregate 50 into the; 상기 적층된 제1호안블록(10)과 법면(40)의 사이 공간에 골재(50)를 채우고 발생하는 나머지 외부로 노출된 법면(40)에 통상의 판형 식생 호안블록(60)을 설치하는 단계를 포함하는 구성을 특징으로 하는 환경친화형 목재 호안블록을 이용한 법면 시공방법.Filling the aggregate 50 in the space between the stacked first first eye block 10 and the law surface 40 and installing a conventional plate-like vegetation relief eye block 60 on the remaining outer surface 40 generated Method of construction of the surface using environmentally friendly wood coastal block characterized in that the configuration comprising a. 제1항에 있어서, 상기 제1파이프의 입구는 하천을 흐르는 물의 진행방향을 향하도록 된 것을 특징으로 하는 환경친화형 목재 호안블록을 이용한 법면 시공방법.The method according to claim 1, wherein the inlet of the first pipe is directed toward the traveling direction of the water flowing through the stream. 제1항에 있어서, 상기 제1 및 제2파이프 중 어느 하나 또는 둘 모두는 주름 관임을 특징으로 하는 환경친화형 목재 호안블록을 이용한 법면 시공방법.The method of claim 1, wherein one or both of the first and second pipes are corrugated pipes. 제1항에 있어서, 상기 제1 및 제2호안블록의 내부 공간부 채워지는 골재에는 물을 정화할 수 있는 물정화제인 숯, 세라믹 중 어느 하나가 일정량 채워짐을 특징으로 하는 환경친화형 목재 호안블록을 이용한 법면 시공방법. The method of claim 1, wherein the aggregate is filled in the interior space of the first and second revetment block environmentally friendly wood revetment block, characterized in that any amount of water or charcoal, which is a water purifier to purify water is filled in a certain amount. Surface construction method using.
KR1020080123783A 2008-12-08 2008-12-08 Construction method using environmental affinity type bank KR101160882B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020080123783A KR101160882B1 (en) 2008-12-08 2008-12-08 Construction method using environmental affinity type bank

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020080123783A KR101160882B1 (en) 2008-12-08 2008-12-08 Construction method using environmental affinity type bank

Publications (2)

Publication Number Publication Date
KR20100065450A true KR20100065450A (en) 2010-06-17
KR101160882B1 KR101160882B1 (en) 2012-06-28

Family

ID=42364707

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020080123783A KR101160882B1 (en) 2008-12-08 2008-12-08 Construction method using environmental affinity type bank

Country Status (1)

Country Link
KR (1) KR101160882B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101043361B1 (en) * 2010-09-03 2011-06-21 주식회사 도화엔지니어링 A vegetation mesh bag and constructing method of ecological gabion used it
KR102152973B1 (en) * 2020-03-05 2020-09-07 고연우 Structure of Installation for Preventing Overflow

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105714736A (en) * 2016-02-18 2016-06-29 朱方明 Novel ecological ditch and building method thereof
KR20190056004A (en) 2017-11-16 2019-05-24 경희대학교 산학협력단 Revetment structure for water purification
KR102138839B1 (en) 2019-12-04 2020-07-28 박서진 Cast-in-place concrete blocks using large scales and revetment methods using them

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3205290B2 (en) * 1997-10-28 2001-09-04 東王技研株式会社 Revetment lining
KR200195533Y1 (en) 2000-04-20 2000-09-01 주식회사한림에코텍 Framework for protecting banks from flood water
KR200268853Y1 (en) 2001-12-10 2002-03-18 주식회사 우일 이알에스 Bank protection vegetation zone at the low-water channel of river
KR200311988Y1 (en) 2003-01-09 2003-05-09 장시성 a

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101043361B1 (en) * 2010-09-03 2011-06-21 주식회사 도화엔지니어링 A vegetation mesh bag and constructing method of ecological gabion used it
KR102152973B1 (en) * 2020-03-05 2020-09-07 고연우 Structure of Installation for Preventing Overflow

Also Published As

Publication number Publication date
KR101160882B1 (en) 2012-06-28

Similar Documents

Publication Publication Date Title
KR101160882B1 (en) Construction method using environmental affinity type bank
CN101387107A (en) Ecological riverbank with pile type wave-protection structure
KR200433035Y1 (en) Frame structure for ecological restoration
KR100891738B1 (en) The crib block for a vegetation and shore protection which has a fishway facilities
KR100671791B1 (en) Block in revetment to preserve river environment
KR20120005503U (en) Scour Protection Block
CN201228353Y (en) Ecological riverbank with pile type wave-protection structure
KR200408078Y1 (en) Connection type revetment block for vegetation
KR200303587Y1 (en) Embankment block
KR200356111Y1 (en) Embankment block
KR200262788Y1 (en) Inter locking multi-function block for river conservation work
KR100478156B1 (en) Embankment block set
KR100478158B1 (en) Embankment block
KR101684340B1 (en) Scour protection system for shore and its installation methods
JP2500358B2 (en) Seawall block and seawall structure
KR100919614B1 (en) The crib block for a vegetation and shore protection which has a fishway facilities
KR200250172Y1 (en) Embankment block set
KR200438261Y1 (en) Fish breeding ground block
KR101166215B1 (en) Retaining wall type prevention frame forming tree
KR20090000362U (en) Embankment block
KR100645316B1 (en) Tree planting structure of levee used concrete block
JP2000080624A (en) Execution method for revetment wall
KR200289866Y1 (en) Embankment block
KR200290673Y1 (en) Protection block of retaining wall structure
KR200217682Y1 (en) Block for protecting banks for use in a curvature portion of river

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20150601

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20160527

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20170612

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20180702

Year of fee payment: 7