KR20100013548A - Joint of half pc slab - Google Patents

Joint of half pc slab Download PDF

Info

Publication number
KR20100013548A
KR20100013548A KR1020080075123A KR20080075123A KR20100013548A KR 20100013548 A KR20100013548 A KR 20100013548A KR 1020080075123 A KR1020080075123 A KR 1020080075123A KR 20080075123 A KR20080075123 A KR 20080075123A KR 20100013548 A KR20100013548 A KR 20100013548A
Authority
KR
South Korea
Prior art keywords
slab
slabs
reinforcing bar
concrete
reinforcing
Prior art date
Application number
KR1020080075123A
Other languages
Korean (ko)
Inventor
이기장
이강건
황현식
Original Assignee
삼성중공업 주식회사
이한승
김승훈
강인석
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 삼성중공업 주식회사, 이한승, 김승훈, 강인석 filed Critical 삼성중공업 주식회사
Priority to KR1020080075123A priority Critical patent/KR20100013548A/en
Publication of KR20100013548A publication Critical patent/KR20100013548A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/383Connection of concrete parts using adhesive materials, e.g. mortar or glue
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/61Connections for building structures in general of slab-shaped building elements with each other
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/17Floor structures partly formed in situ
    • E04B5/18Floor structures partly formed in situ with stiffening ribs or other beam-like formations wholly cast between filling members
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/32Floor structures wholly cast in situ with or without form units or reinforcements
    • E04B5/326Floor structures wholly cast in situ with or without form units or reinforcements with hollow filling elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/32Floor structures wholly cast in situ with or without form units or reinforcements
    • E04B5/36Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor
    • E04B5/38Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor with slab-shaped form units acting simultaneously as reinforcement; Form slabs with reinforcements extending laterally outside the element
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/01Reinforcing elements of metal, e.g. with non-structural coatings
    • E04C5/06Reinforcing elements of metal, e.g. with non-structural coatings of high bending resistance, i.e. of essentially three-dimensional extent, e.g. lattice girders
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/01Reinforcing elements of metal, e.g. with non-structural coatings
    • E04C5/06Reinforcing elements of metal, e.g. with non-structural coatings of high bending resistance, i.e. of essentially three-dimensional extent, e.g. lattice girders
    • E04C5/0604Prismatic or cylindrical reinforcement cages composed of longitudinal bars and open or closed stirrup rods

Abstract

PURPOSE: A joint structure of a half PC slab is provided to secure enough bending performance of the joint and enable application to a hollow slab. CONSTITUTION: A joint structure of a half PC slab comprises first and second half PC slabs(100,200), reinforcement members(310), and topping concrete. The first and second half PC slabs are abutted against each other in a slab construction position. The reinforcing members are installed at the junction of the first and second half PC slabs. The topping concrete is placed above the first and second half PC slabs to bury the reinforcing members.

Description

하프PC슬래브의 이음구조{Joint of half PC slab}Joint structure of half PC slab {Joint of half PC slab}

본 발명은 하나의 스팬 내에 설치되는 복수개의 하프PC슬래브 상호 간 이음구조에 관한 것으로, 더욱 상세하게는 보강부재의 설치길이를 줄여 시공성을 확보하면서도 이음부의 휨성능을 충분히 만족시킬 수 있는 하프PC슬래브의 이음구조에 관한 것이다.The present invention relates to a joint structure between a plurality of half PC slabs installed in one span, and more particularly, a half PC slab that satisfies the bending performance of the joint part while securing construction properties by reducing the installation length of the reinforcing member. It is about the joint structure of.

콘크리트 슬래브를 시공하는 방식에는 거푸집을 설치하여 현장에서 직접 콘크리트를 타설하는 현장시공법과, 공장에서 제작된 PC(precast concrete)부재를 현장에서 조립하여 설치하는 PC공법으로 구분할 수 있다. 현장시공법은 많은 현장작업량에 따라 많은 인력과 공기(工期)가 소요되므로, 최근에는 부재의 표준화, 공정의 간소화, 노동 생산성 등을 꾀할 수 있는 PC공법이 주목받고 있는 상황이다.The method of constructing the concrete slab can be divided into the field construction method of placing concrete directly at the site by installing formwork, and the PC method of assembling and installing precast concrete (PC) members manufactured at the factory. Since the site construction method requires a lot of manpower and air according to the amount of work on site, the PC method that can achieve the standardization of members, the process simplification, labor productivity, etc. has been attracting attention recently.

PC공법에는 다양한 형태의 PC부재들이 개발되어 사용되고 있으며, 그러한 PC부재 중의 하나가 하프PC슬래브이다. 하프PC슬래브는 양중무게를 고려하여 소요 슬래브 두께의 절반 정도의 두께로 미리 공장에서 제작한 부재인데, 통상적으로 하 부철근 다수개를 병렬 배치한 후 상·하현재와 래티스재가 조립된 트러스조립철근 다수개를 병렬 배치하여 하부철근 위에 교차하게 접합한 상태에서 콘크리트를 부어 하부철근이 콘크리트에 매입되도록 하는 한편 트러스조립철근 상부가 콘크리트에서 돌출되도록 제작한다. 이와 같은 하프PC슬래브는 시공위치에 양중 설치한 후에 나머지 콘크리트를 현장에서 타설하여 슬래브 구조체로 완성된다.Various types of PC members have been developed and used in the PC method, and one of such PC members is a half PC slab. The half PC slab is a factory manufactured member that is about half the thickness of the required slab in consideration of the weight of the weight.Truss-assembled reinforcing bars, in which upper and lower chords and lattice materials are assembled after placing several lower rebars in parallel Plural concrete is placed in parallel and placed on the bottom of the rebar to pour the concrete so that the bottom of the rebar is embedded in the concrete, while the top of the truss assembly reinforcement is manufactured to protrude from the concrete. Such a half PC slab is installed in the construction position in both places, and then the remaining concrete is poured on site to complete the slab structure.

한편, 하프PC슬래브의 운반과 양중 등 전반적인 사정을 고려할 때 하프PC슬래브는 그 폭이 제한되기 마련이며, 이러한 하프PC슬래브를 이용하여 슬래브 공사를 수행한다면 하나의 스팬 내에 여러 개의 하프PC슬래브를 맞대어 설치해야만 하는 경우가 있을 수밖에 없다. 이 경우 하프PC슬래브 상호 간 맞댄이음부는 전단 내지 휨 등 구조적으로 취약하므로 이에 대한 고려가 필요한데, 전단성능은 하프PC슬래브 위에 상부철근(전단철근으로 역할함)을 배근하는 것으로, 휨성능은 하프PC슬래브에 근접하게 보강부재를 설치하는 것으로 확보할 수 있다.On the other hand, considering the overall circumstances such as transportation and lifting of the half PC slab, the width of the half PC slab is limited, and if the slab construction is carried out using such a half PC slab, several half PC slabs may be faced in one span. There must be a case to install. In this case, butt joints between the half PC slabs are structurally fragile such as shearing or bending, so consideration is required. Shearing performance is to reinforce the upper reinforcing bar (same as shear bar) on the half PC slab. This can be ensured by providing a reinforcing member close to the PC slab.

도 1 및 도 2는 종래의 하프PC슬래브 이음구조로서, 보강부재로 통상적인 철근을 채택하여 이를 하프PC슬래브의 맞댄이음부에 설치함으로써 맞댄이음부의 휨성능을 보강한 예를 보여준다. 도시하고 있는 바와 같이 보강부재(철근)는 이음방향으로 배근되며, 다만 충분한 휨성능을 확보하기 위해서는 보강부재(철근)의 충분한 설치길이(충분한 정착력 확보를 위한 설치길이)가 필요하다. 그런데, 보강부재(철근)을 충분한 설치길이로 설치하는 것은 그리 쉽지 않다. 왜냐하면 보강부재(철근)와 하프PC슬래브의 트러스조립철근 사이에 간섭이 일어나기 때문이다. 다시 말 해, 보강부재(철근)는 하프PC슬래브의 트러스조립철근과 교차하게 배근되는데, 이 경우 보강부재(철근)가 트러스조립철근의 래티스근에 걸리기 때문에 보강부재(철근)을 배근하기 위해서는 간섭부위의 래티스근을 일일이 절단해야 하는 번거로운 현장작업을 수행해야 하는 바, 보강부재(철근)의 설치길이가 길수록 그 현장작업량은 많아질 수밖에 없는 것이다.1 and 2 show a conventional half PC slab joint structure, which adopts a conventional reinforcing bar as a reinforcing member and installs it in the butt joint of the half PC slab to reinforce the bending performance of the butt joint. As shown, the reinforcing member (rebar) is reinforced in the joint direction, but in order to secure sufficient bending performance, sufficient installation length of the reinforcing member (rebar) (installation length for securing sufficient fixing force) is required. By the way, it is not so easy to install the reinforcing member (rebar) with sufficient installation length. This is because interference occurs between the reinforcing member (bar) and the truss assembly bar of the half PC slab. In other words, the reinforcing member (rebar) is reinforced to cross the truss reinforcing bar of the half PC slab. In this case, the reinforcing member (rebar) is caught by the lattice reinforcing bar of the truss reinforcing bar. The cumbersome field work to cut the lattice muscles of the site must be performed one by one, the longer the installation length of the reinforcing member (reinforcing bar) will have to increase the amount of field work.

특히나 슬래브 경량화를 위해 하프PC슬래브에 중공재를 설치할 수 있는데, 이 경우에는 보강부재(철근)가 중공재와도 간섭이 일어나게 된다. 이러한 간섭문제는 도 2와 같이 간섭위치의 중공재를 제거하는 방법으로 해결할 수밖에 없으나, 중공재를 제거하면 그만큼 콘크리트 타설량을 증대시켜야 하기 때문에 슬래브 경량화 효과는 그만큼 떨어진다.In particular, a hollow material may be installed in the half PC slab to reduce the weight of the slab. In this case, the reinforcing member (rebar) will also interfere with the hollow material. This interference problem can not only be solved by the method of removing the hollow material at the interference position as shown in FIG. 2, but when the hollow material is removed, the slab lightweighting effect is inferior to that of the concrete.

본 발명은 상기한 종래의 문제를 개선하고자 발명된 것으로서, 하나의 스팬 내에 설치되는 복수개의 하프PC슬래브 상호 간 이음구조로 보강부재의 설치길이를 줄이면서도 이음부의 휨성능을 충분히 만족시킬 수 있으며 특히 중공슬래브에 유용하게 적용할 수 있는 하프PC슬래브의 이음구조를 제공하는데 기술적 과제가 있다.The present invention has been invented to improve the above-described conventional problems, and it is possible to sufficiently satisfy the bending performance of the joint part while reducing the installation length of the reinforcing member with a plurality of half PC slab mutual joint structures installed in one span. There is a technical problem to provide a joint structure of a half PC slab that can be usefully applied to the hollow slab.

상기한 기술적 과제를 해결하기 위해 본 발명은 다음과 같은 구성의 하프PC 슬래브의 이음구조를 제안한다.In order to solve the above technical problem, the present invention proposes a joint structure of a half PC slab having the following configuration.

본 발명에 따른 하프PC슬래브의 이음구조는, 하나의 스팬 내에 설치되는 복수개의 하프PC슬래브 상호 간 이음구조로서, 제1하부철근 다수개가 병렬 배치되고 상·하현재와 래티스재가 조립된 제1트러스조립철근 다수개가 병렬로 제1하부철근 위에 교차하게 배치되어 접합된 상태에서 상기 제1하부철근이 콘크리트에 매입되는 한편 상기 제1트러스조립철근 상부가 콘크리트를 돌출하도록 제작되며, 슬래브 시공위치에 설치되는 제1하프PC슬래브; 제2하부철근과 제2트러스조립철근을 포함하여 상기 제1하프PC슬래브와 동일한 구조로 제작되며, 상기 제2하부철근이 상기 제1하프PC슬래브의 제1하부철근과 동일한 방향으로 배치되도록 상기 제1하프PC슬래브에 맞대어 설치되는 제2하프PC슬래브; 상기 제1,2하프PC슬래브의 맞댄이음부 위로 설치되는 보강부재; 및, 상기 제1,2하프PC슬래브 위로 상기 보강부재가 매입되도록 타설되는 토핑콘크리트;를 포함하여 구성되되,The joint structure of the half PC slab according to the present invention is a joint structure of a plurality of half PC slabs provided in one span, the first truss having a plurality of first lower rebars arranged in parallel and assembled with upper and lower chords and lattice materials. The first lower reinforcing bar is embedded in the concrete while a plurality of reinforcing bars are arranged in parallel on the first lower reinforcing bar, and the upper part of the first truss reinforcing bar protrudes from the concrete and is installed at a slab construction position. The first half PC slab; Including the second lower reinforcing bar and the second truss assembly reinforcing bar is made of the same structure as the first half PC slab, so that the second lower reinforcing bar is arranged in the same direction as the first lower reinforcing bar of the first half PC slab A second half PC slab installed against the first half PC slab; Reinforcing members installed on the butt joints of the first and second half PC slabs; And a topping concrete which is poured so that the reinforcing member is embedded over the first and second half PC slabs.

상기 보강부재가, 철근 양단이 상향하여 갈고리로 절곡된 것으로 다수개가 상기 제1,2하프PC슬래브의 제1,2하부철근과 동일한 방향으로 서로 평행하게 설치되는 갈고리철근이거나, 철근 양단에 플레이트가 접합된 것으로 다수개가 상기 제1,2하프PC슬래브의 제1,2하부철근과 동일한 방향으로 서로 평행하게 설치되는 I형헤드조립철근이거나, 다수개의 철근이 격자로 조립된 격자조립철근임을 특징으로 한다.The reinforcing member is a reinforcing bar, both ends of the reinforcing hook is bent into a hook reinforcement is installed in parallel with each other in the same direction as the first and second lower reinforcement of the first and second half PC slab, A plurality of I-shaped head assembly reinforcing bars are installed in parallel with each other in the same direction as the first and second lower reinforcing bars of the first and second half PC slab, or a plurality of reinforcing lattice assembly reinforcing lattice do.

본 발명에 따른 다른 하프PC슬래브의 이음구조는, 하나의 스팬 내에 설치되는 복수개의 하프PC슬래브 상호 간 이음구조로서, 제1하부철근 다수개가 병렬 배치 되고 상·하현재와 래티스재가 조립된 제1트러스조립철근 다수개가 병렬로 제1하부철근 위에 교차하게 배치되어 접합된 상태에서 상기 제1하부철근이 콘크리트에 매입되는 한편 상기 제1트러스조립철근 상부가 콘크리트를 돌출하도록 제작되며, 슬래브 시공위치에 설치되는 제1하프PC슬래브; 제2하부철근과 제2트러스조립철근을 포함하여 상기 제1하프PC슬래브와 동일한 구조로 제작되며, 상기 제2하부철근이 상기 제1하프PC슬래브의 제1하부철근과 동일한 방향으로 배치되도록 상기 제1하프PC슬래브에 맞대어 설치되는 제2하프PC슬래브; 상기 제1,2하프PC슬래브의 맞댄이음부 위로 설치되는 보강부재; 및, 상기 제1,2하프PC슬래브 위로 상기 보강부재가 매입되도록 타설되는 토핑콘크리트;를 포함하여 구성되되,The joint structure of another half PC slab according to the present invention is a joint structure of a plurality of half PC slabs provided in one span, and a plurality of first lower reinforcing bars are arranged in parallel, and the first and the lower chords and the lattice material are assembled. A plurality of truss prefabricated rebars are arranged so that the first bottom reinforcement is embedded in the concrete while the first truss reinforcement bars are protruded from the concrete in a state in which the truss reinforcing bars are arranged to be intersected and intersected on the first lower reinforcing bars in parallel. A first half PC slab installed; Including the second lower reinforcing bar and the second truss assembly reinforcing bar is made of the same structure as the first half PC slab, so that the second lower reinforcing bar is arranged in the same direction as the first lower reinforcing bar of the first half PC slab A second half PC slab installed against the first half PC slab; Reinforcing members installed on the butt joints of the first and second half PC slabs; And a topping concrete which is poured so that the reinforcing member is embedded over the first and second half PC slabs.

상기 제1,2하프PC슬래브 각각은 맞댄이음부에 위치한 제1,2하부철근 단부가 상향하여 수직 절곡되어 콘크리트를 돌출하도록 제작된 것이며, 상기 보강부재는 판면에 2개 이상의 통공이 형성된 것으로 다수개가 각각 상기 제1,2하프PC슬래브에서 돌출하는 제1,2하부철근에 동시에 끼워져 연결플레이트이며, 상기 연결플레이트에 끼워진 제1,2하프PC슬래브의 제1,2하부철근은 연결플레이트 위에서 절곡되어 연결플레이트에 구속되는 것을 특징으로 한다.Each of the first and second half PC slabs is manufactured to protrude concrete by vertically bending the first and second lower reinforcing bar ends located at the butt joint, and the reinforcing member has two or more through holes formed on the plate surface. The dogs are respectively connected to the first and second lower reinforcing bars projecting from the first and second half PC slabs, respectively, and the first and second lower reinforcing bars of the first and second half PC slabs fitted to the connecting plates are bent over the connecting plates. And is constrained to the connection plate.

본 발명에 따르면 다음과 같은 효과를 기대할 수 있다.According to the present invention, the following effects can be expected.

첫째, 보강부재의 설치길이를 줄이면서도 충분한 휨성능을 확보할 수 있기 때문에 보강부재와 하프PC슬래브에 고정 설치된 철근과의 간섭문제를 최소화하면서 슬래브공사를 수행할 수 있다. 따라서, 종래 간섭문제를 해결하기 위해 부수적으로 따르던 작업을 생략하거나 줄일 수 있어 전반적으로 슬래브공사의 시공성을 향상시킬 수 있다.First, the slab construction can be performed while minimizing the interference problem between the reinforcing member and the rebar fixed to the half PC slab because the sufficient bending performance can be secured while reducing the installation length of the reinforcing member. Therefore, it is possible to omit or reduce the incidental work to solve the conventional interference problem, it is possible to improve the overall construction of the slab construction.

둘째, 중공재가 설치된 하프PC슬래브를 이용하는 경우에도 중공재를 제거하지 않아도 되기 때문에 슬래브 경량화를 그대로 유지하면서 슬래브공사를 수행할 수 있다.Second, even when using a half-PC slab installed with a hollow material, it is not necessary to remove the hollow material, so that the slab construction can be performed while maintaining the slab weight.

이하, 첨부한 도면 및 바람직한 실시예에 따라 본 발명을 상세히 설명한다.Hereinafter, the present invention will be described in detail with reference to the accompanying drawings and preferred embodiments.

도 3 내지 도 9는 본 발명에 따른 하프PC슬래브의 이음구조에 대한 다양한 실시예를 보여준다. 본 발명에 따른 하프PC슬래브의 이음구조는, 하나의 스팬 내에 설치되는 복수개의 하프PC슬래브 상호 간 이음구조로서, 서로 맞대어 설치되는 제1,2하프PC슬래브(100, 200)와 제1,2하프PC슬래브의 맞댄이음부에 설치되는 보강부재(310, 320, 330, 340) 및 제1,2하프PC슬래브 위로 보강부재가 매입되도록 타설되는 토핑콘크리트를 기본적인 구성으로 한다. 본 발명에서는 상기 보강부재(310, 320, 330, 340)의 형태와 제1,2하프PC슬래브(100, 200) 상호간의 맞댄이음부의 형성방법에 따라 다양한 실시예로 구분하여 제안하고 있다.3 to 9 show various embodiments of the joint structure of the half PC slab according to the present invention. The joint structure of the half PC slab according to the present invention is a mutual joint structure of a plurality of half PC slabs provided in one span, and the first and second half PC slabs 100 and 200 and the first and second half PC slabs are installed to face each other. Reinforcing members (310, 320, 330, 340) provided on the butt joint portion of the half PC slab and the topping concrete is placed so that the reinforcing member is embedded over the first and second half PC slab as a basic configuration. In the present invention, the reinforcing member 310, 320, 330, 340 and the first and second half PC slab (100, 200) according to the formation method of the butt joint between each other are divided into various embodiments are proposed.

본 발명에서 제1,2하프PC슬래브(100, 200)는 종래의 하프PC슬래브와 마찬가지로 제작되어 준비된다. 다시 말해, 제1하프PC슬래브(100)는 제1하부철근(110) 다수개가 병렬 배치되고 상·하현재와 래티스재가 조립된 제1트러스조립철근(120) 다수개가 병렬로 제1하부철근(110) 위에 교차하게 배치되어 접합된 상태에서, 상기 제1하부철근(110)이 콘크리트에 매입되는 한편 상기 제1트러스조립철근(120) 상부가 콘크리트를 돌출하도록 제작된 것이다. 물론, 제2하프PC슬래브(200)는 제2하부철근(210)과 제2트러스조립철근(220)을 포함하여 제1하프PC슬래브(100)와 동일한 구조로 제작된 것이다. 상기 제1,2하프PC슬래브(100, 200)에서 제1,2트러스조립철근(120, 220)은 1본의 상현재와 1본의 하현재로 구성된 평면트러스조립철근은 물론 1본의 상현재와 2본의 하현재로 구성된 입체트러스조립철근도 포함하며, 다만 본 발명에서는 실시예를 통해 입체트러스조립철근을 채택하고 있다.In the present invention, the first and second half PC slabs 100 and 200 are manufactured and prepared as in the conventional half PC slab. In other words, in the first half PC slab 100, a plurality of first truss assembly reinforcing rods 120 in which a plurality of first lower reinforcing bars 110 are arranged in parallel and upper and lower chords and a lattice material are assembled in parallel with the first lower reinforcing bars ( In a state in which the joints are arranged to cross each other, the first lower reinforcement 110 is embedded in concrete while the upper portion of the first truss assembly reinforcement 120 protrudes from the concrete. Of course, the second half PC slab 200 is manufactured in the same structure as the first half PC slab 100 including the second lower reinforcement 210 and the second truss assembly reinforcement 220. In the first and second half PC slab (100, 200), the first and second truss assembly reinforcement (120, 220) is a flat truss reinforcing bar consisting of one top chord and one bottom chord, as well as one image Also included is a three-dimensional truss assembly reinforcing bar consisting of the present and two lower chords, but the present invention adopts a three-dimensional truss assembly reinforcing bar through the embodiment.

특히, 슬래브의 경량화를 위해서 슬래브 내부에 중공재(경량성 부재)를 매입시켜 중공슬래브로 완성할 수 있는데, 이러한 중공슬래브를 위해서라면 상기 제1,2하프PC슬래브(100, 200) 각각은 각각의 제1,2트러스조립철근(120, 220) 사이에 중공재(130, 230)를 배치하여 중공재(130, 230)가 콘크리트를 돌출하도록 제작함이 바람직하다. 이때 중공재(130, 230)는 막대형 중공재는 물론 단위블록형 중공재를 채택할 수 있으며, 다만 본 발명에서는 실시예를 통해 단위블록형(직육면체형) 중공재를 채택하고 있다.Particularly, in order to reduce the weight of the slab, a hollow material (lightweight member) may be embedded in the slab and completed as a hollow slab. For the hollow slab, each of the first and second half PC slabs 100 and 200 may be respectively. It is preferable to arrange the hollow material (130, 230) between the first and second truss assembly reinforcing bars (120, 220) of the hollow material (130, 230) to protrude concrete. At this time, the hollow material (130, 230) can be adopted in the unit block-type hollow material as well as the rod-shaped hollow material, but in the present invention, the unit block type (cuboid-shaped) hollow material is adopted through the embodiment.

상기와 같이 제작된 제1,2하프PC슬래브(100, 200)는 슬래브 시공위치에 서로 맞대어 설치되며, 그 맞댄이음부 위로 보강부재(310, 320, 330, 340)를 설치한 후 동시에 토핑콘크리트를 타설하면 보강부재가 토핑콘크리트에 구속되어 휨성능을 발휘하게 된다. 이때 상기 제1,2하프PC슬래브(100, 200)가 단부 모서리가 모따기되 도록 제작된 것이라면 상기 제,2하프PC슬래브(100, 200)는 맞댄이음부에 모따기홈(G1)을 형성시키면서 설치되는데, 이러한 모따기홈(G1)에는 토핑콘크리트가 충진되어 맞댄이음부에서의 휨성능은 증대된다.The first and second half PC slabs 100 and 200 manufactured as described above are installed to face each other at the slab construction position, and at the same time after installing the reinforcing members 310, 320, 330 and 340 on the butt joints, When scooping up, the reinforcing member is constrained to the topping concrete to exhibit the bending performance. In this case, if the first and second half PC slabs 100 and 200 are manufactured so that the end edges are chamfered, the first and second half PC slabs 100 and 200 are installed while forming a chamfer groove G1 in the butt joint portion. The chamfering groove (G1) is filled with topping concrete, the bending performance at the butt joint is increased.

도 3 내지 도 6은 맞댄이음부에 설치하는 보강부재로 갈고리철근(310)을 채택한 예를 보여준다. 도 3 내지 도 6의 이음구조는, 철근 양단을 상향하여 갈고리로 절곡시킨 갈고리철근(310)을 준비하고, 갈고리철근(310) 다수개를 제1,2하프PC슬래브의 제1,2하부철근(110, 210)과 동일한 방향으로 서로 평행하게 설치한 후, 토핑콘크리트를 타설함으로써 완성된다. 이와 같이 완성된 이음구조에서는 갈고리철근(310)과 토핑콘크리트의 구속력으로 휨성능을 발휘하게 된다. 특히, 갈고리철근(310)을 제1,2하프PC슬래브의 제1,2하부철근(110, 210)과 동일라인에 위치하도록 설치하는 것이 바람직한데 이는 제1,2하프PC슬래브의 제1,2하부철근(110, 210)과 갈고리철근(310)과의 연속성 확보를 통해 휨성능을 증대시키기 위함이며, 나아가 갈고리철근(310)을 제1,2하프PC슬래브의 제1,2트러스조립철근(120, 220)에 결속시키거나 걸리도록 설치한다면 갈고리철근(310)의 구속력이 증대되어 더욱 강력하게 휨저항할 것이다.3 to 6 show an example in which the hook reinforcement 310 is adopted as a reinforcing member installed in the butt joint portion. The joint structure of FIGS. 3 to 6 prepares hook reinforcing bars 310, which are bent by hooks with the upper ends of the reinforcing bars, and the first and second lower reinforcing bars of the first and second half PC slabs. After installation in parallel with each other in the same direction as (110, 210), it is completed by pouring topping concrete. In the completed joint structure as described above, the bending performance is exhibited by the restraint force of the hook reinforcement 310 and the topping concrete. In particular, the hook reinforcement 310 is preferably installed on the same line as the first and second lower reinforcing bars 110 and 210 of the first and second half PC slabs. It is to increase the bending performance by securing the continuity between the lower reinforcement (110, 210) and the hook reinforcement 310, and further, the first and second truss assembly reinforcement of the first and second half PC slab If the binding to the (120, 220) or installed to hang will increase the restraint of the hook reinforcement 310 will be more powerful bending resistance.

도 3이 갈고리철근(310)을 채택한 경우의 가장 기본적인 예라면, 도 4 내지 도 6은 맞댄이음부의 휨성능을 더욱 보강한 예이다. 도 4는 제1,2하프PC슬래브(100, 200)로 맞댄이음부에 위치한 제1,2하부철근(110, 210)의 단부가 상향하여 갈고리로 절곡된 채 콘크리트를 돌출하도록 제작된 것을 채택한 예로서, 제1,2하부 철근(110, 210)의 갈고리를 토핑콘크리트에 매입되도록 함으로써 휨보강하고 있다. 도 5는 제1,2하프PC슬래브(100, 200)로 단부가 얇은 두께의 낮은턱으로 형성되도록 제작된 것을 채택한 예로서, 이와 같은 제1,2하프PC슬래브(100, 200)를 설치하면 맞댄이음부에 낮은턱홈(G2)이 형성되는데 갈고리철근(310)을 상기 낮은턱홈(G2)에 위치하도록 설치하여 갈고리철근(310)의 설치위치를 아래로 내린 상태에서 토핑콘크리트에 매입되도록 함으로써 휨보강하고 있다. 도 6은 도 4와 도 5의 방법을 함께 적용하여 휨보강한 예이다. 3 is the most basic example in the case of adopting the hook reinforcement 310, Figures 4 to 6 is an example to further strengthen the bending performance of the butt joint. FIG. 4 adopts the first and second lower reinforcing bars 110 and 210 positioned at the butt joints of the first and second half PC slabs 100 and 200 to protrude concrete while being bent upwardly by hooks. For example, flexural reinforcement is performed by allowing the hooks of the first and second lower reinforcing bars 110 and 210 to be embedded in the topping concrete. FIG. 5 is an example in which the first and second half PC slabs 100 and 200 are manufactured so that their ends are formed with a low thickness of the lower jaw, and the first and second half PC slabs 100 and 200 are installed. The lower jaw groove G2 is formed in the butt joint, and the hook reinforcement 310 is installed in the lower jaw groove G2 so as to be buried in the topping concrete while the installation position of the hook reinforcement 310 is lowered. Reinforcing 6 is an example of flexural reinforcement by applying the method of FIGS. 4 and 5 together.

도 7은 맞댄이음부에 설치하는 보강부재로 I형헤드조립철근(320)을 채택한 예를 보여준다. 도 7의 이음구조는, 철근 양단에 플레이트를 접합한 I형헤드조립철근(320)을 준비하고, I형헤드조립철근(320) 다수개를 제1,2하프PC슬래브의 제1,2하부철근(110, 210)과 동일한 방향으로 서로 평행하게 설치한 후, 토핑콘크리트를 타설함으로써 완성된다. 7 shows an example in which an I-type head assembly reinforcing bar 320 is adopted as a reinforcing member installed in the butt joint portion. In the joint structure of FIG. 7, the I-type head assembly reinforcing bars 320 are prepared by joining plates to both ends of the reinforcing bars, and a plurality of I-type head assembly reinforcing bars 320 are disposed in the first and second lower parts of the first and second half PC slabs. After installing in parallel with each other in the same direction as the reinforcing bars (110, 210), it is completed by pouring the topping concrete.

도 8은 맞댄이음부에 설치하는 보강부재로 격자조립철근(330)을 채택한 예를 보여준다. 도 8의 이음구조는 다수개의 철근을 격자로 조립한 격자조립철근(330)을 준비하고, 이 격자조립철근(330)을 맞댄이음부에 설치한 후, 토핑콘크리트를 타설함으로써 완성된다. 다만, 격자조립철근(330)을 용이하게 설치하기 위해서는 제1,2하프PC슬래브의 제1,2트러스조립철근(120, 220)에서 격자조립철근(330)과의 간섭부위를 적절하게 미리 절단하도록 한다(격자조립철근을 설치하기 위해 절단작업을 수행하지만 종래 절단작업보다는 작업개소가 적음).8 shows an example in which the grid assembly reinforcing bar 330 is adopted as a reinforcing member installed in the butt joint. The joint structure of FIG. 8 is completed by preparing a lattice-assembled reinforcing bar 330 in which a plurality of reinforcing bars are assembled into a lattice, and installing the lattice reinforcing bar 330 in a joint part, and then pouring topping concrete. However, in order to easily install the lattice assembly reinforcing bar 330, the first and second truss assembly reinforcing bars 120 and 220 of the first and second half PC slabs are appropriately cut in advance with the lattice assembly reinforcing bar 330. (Cutting work is performed to install grid reinforcing bar, but less work place than conventional cutting work).

도 7 및 도 8과 같은 이음구조는 I형헤드조립철근(320)과 격자조립철근(330)이 앞서 살펴본 갈고리철근(310)과 마찬가지로 토핑콘크리트에 구속되어 휨성능을 발휘한다. I형헤드조립철근(320)과 격자조립철근(330)을 채택하는 경우에도 갈고리철근(310)을 채택하는 경우와 동일한 방식으로 휨성능을 더욱 증대시킬 수 있다.As shown in FIGS. 7 and 8, the I-type head assembly reinforcement 320 and the lattice assembly reinforcement 330 are constrained to the topping concrete similar to the hook reinforcement 310 described above to exhibit bending performance. Even when the type I head assembly reinforcing bar 320 and the grid assembly reinforcing bar 330 are adopted, flexural performance may be further increased in the same manner as when the hook reinforcing bar 310 is adopted.

도 9는 맞댄이음부에 설치하는 보강부재로 연결플레이트(340)를 채택한 예를 보여준다. 도 9의 이음구조는 판면에 2개 이상의 통공을 형성시킨 연결플레이트(340)를 준비하고, 다수개의 연결플레이트(340) 각각을 제1,2하프PC슬래브(100, 200)의 단부에서 상향하여 수직으로 돌출한 제1,2하부철근(110, 210)에 동시에 끼워 설치한 다음, 제1,2하부철근(110, 210)을 연결플레이트(340) 위에서 절곡하여 연결플레이트(340)에 구속시킨 후, 토핑콘크리트를 타설함으로써 완성된다. 도 9와 같은 이음구조에서도 휨성능 증대를 위해 앞서 살펴본 바와 같은 방식을 그대로 적용할 수 있다. 9 shows an example in which the connecting plate 340 is adopted as a reinforcing member installed in the butt joint portion. In the joint structure of FIG. 9, a connection plate 340 having two or more through holes formed on a plate surface is prepared, and each of the plurality of connection plates 340 is upward from the ends of the first and second half PC slabs 100 and 200. The first and second lower reinforcing bars (110, 210) protruding at the same time and installed, and then, the first and second lower reinforcing bars (110, 210) are bent on the connecting plate 340 to restrain the connecting plate (340) Then, it is completed by pouring the topping concrete. In the joint structure shown in FIG. 9, the same method as described above may be applied as it is to increase bending performance.

이상에서 본 발명은 실시예를 참조하여 상세히 설명되었으며, 다만 본 발명이 속하는 기술 분야에서 통상의 지식을 가진 자라면 상기에서 설명된 기술적 사상을 벗어나지 않는 범위 내에서 여러가지 치환, 부가 및 변형이 가능할 것임은 당연하며, 이와 같은 변형된 실시 형태들 역시 특허청구범위에 의하여 정하여지는 본 발명의 보호 범위에 속하는 것으로 이해되어야 할 것이다.The present invention has been described in detail above with reference to the embodiments, but those skilled in the art to which the present invention pertains will be capable of various substitutions, additions and modifications within the scope without departing from the technical spirit described above. It is to be understood that such modified embodiments also fall within the protection scope of the invention as defined by the claims.

도 1 및 도 2는 종래의 하프PC슬래브의 이음구조를 보여준다.1 and 2 show the joint structure of a conventional half PC slab.

도 3 내지 도 9는 본 발명에 따른 하프PC슬래브의 이음구조를 보여준다.3 to 9 show the joint structure of the half PC slab according to the present invention.

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

100: 제1하프PC슬래브100: first half PC slab

200: 제2하프PC슬래브200: second half PC slab

310: 갈고리철근310: hook rebar

320: I형헤드조립철근320: Type I head assembly rebar

330: 격자조립철근330: grid assembled rebar

340: 연결플레이트340: connecting plate

G1: 모따기홈G1: Chamfer groove

G2: 낮은턱홈G2: Lower Jaw Groove

Claims (8)

하나의 스팬 내에 설치되는 복수개의 하프PC슬래브 상호 간 이음구조로서,As a joint structure of a plurality of half PC slabs installed in one span, 제1하부철근(110) 다수개가 병렬 배치되고 상·하현재와 래티스재가 조립된 제1트러스조립철근(120) 다수개가 병렬로 제1하부철근(110) 위에 교차하게 배치되어 접합된 상태에서 상기 제1하부철근(110)이 콘크리트에 매입되는 한편 상기 제1트러스조립철근(120) 상부가 콘크리트를 돌출하도록 제작된 것으로, 슬래브 시공위치에 설치되는 제1하프PC슬래브(100);A plurality of first lower reinforcing bars 110 are arranged in parallel, and the plurality of first truss assembly reinforcing bars 120, in which the upper and lower chords and the lattice material are assembled, are arranged in parallel on the first lower reinforcing bars 110 and joined to each other. A first half PC slab 100 having a first lower reinforcing bar 110 embedded in concrete while the first truss assembly reinforcing bar 120 is formed to protrude concrete, and installed at a slab construction position; 제2하부철근(210)과 제2트러스조립철근(220)을 포함하여 상기 제1하프PC슬래브(100)와 동일한 구조로 제작된 것으로, 상기 제2하부철근(210)이 상기 제1하프PC슬래브의 제1하부철근(110)과 동일한 방향으로 배치되도록 상기 제1하프PC슬래브(100)에 맞대어 설치되는 제2하프PC슬래브(200);Including the second lower reinforcing bar 210 and the second truss assembly reinforcing bar 220, the same structure as the first half PC slab 100, the second lower reinforcement 210 is the first half PC A second half PC slab 200 which is installed against the first half PC slab 100 so as to be disposed in the same direction as the first lower reinforcing bar 110 of the slab; 상기 제1,2하프PC슬래브(100, 200)의 맞댄이음부 위로 설치되는 보강부재;Reinforcing members installed on the butt joints of the first and second half PC slabs (100, 200); 상기 제1,2하프PC슬래브(100, 200) 위로 상기 보강부재가 매입되도록 타설되는 토핑콘크리트;를 포함하여 구성되되,It is configured to include; topping concrete is poured so that the reinforcing member is embedded over the first and second half PC slab (100, 200), 상기 보강부재는, 철근 양단이 상향하여 갈고리로 절곡된 것으로 다수개가 상기 제1,2하프PC슬래브의 제1,2하부철근(110, 210)과 동일한 방향으로 서로 평행하게 설치되는 갈고리철근(310)임을 특징으로 하는 하프PC슬래브의 이음구조The reinforcing member, both ends of the reinforcing bar is bent into hooks, a plurality of hooks rebar 310 are installed in parallel with each other in the same direction as the first and second lower reinforcement (110, 210) of the first and second half PC slab Joint structure of half PC slab 하나의 스팬 내에 설치되는 복수개의 하프PC슬래브 상호 간 이음구조로서,As a joint structure of a plurality of half PC slabs installed in one span, 제1하부철근(110) 다수개가 병렬 배치되고 상·하현재와 래티스재가 조립된 제1트러스조립철근(120) 다수개가 병렬로 제1하부철근(110) 위에 교차하게 배치되어 접합된 상태에서 상기 제1하부철근(110)이 콘크리트에 매입되는 한편 상기 제1트러스조립철근(120) 상부가 콘크리트를 돌출하도록 제작된 것으로, 슬래브 시공위치에 설치되는 제1하프PC슬래브(100);A plurality of first lower reinforcing bars 110 are arranged in parallel, and the plurality of first truss assembly reinforcing bars 120, in which the upper and lower chords and the lattice material are assembled, are arranged in parallel on the first lower reinforcing bars 110 and joined to each other. A first half PC slab 100 having a first lower reinforcing bar 110 embedded in concrete while the first truss assembly reinforcing bar 120 is formed to protrude concrete, and installed at a slab construction position; 제2하부철근(210)과 제2트러스조립철근(220)을 포함하여 상기 제1하프PC슬래브(100)와 동일한 구조로 제작된 것으로, 상기 제2하부철근(210)이 상기 제1하프PC슬래브의 제1하부철근(110)과 동일한 방향으로 배치되도록 상기 제1하프PC슬래브(100)에 맞대어 설치되는 제2하프PC슬래브(200);Including the second lower reinforcing bar 210 and the second truss assembly reinforcing bar 220, the same structure as the first half PC slab 100, the second lower reinforcement 210 is the first half PC A second half PC slab 200 which is installed against the first half PC slab 100 so as to be disposed in the same direction as the first lower reinforcing bar 110 of the slab; 상기 제1,2하프PC슬래브(100, 200)의 맞댄이음부 위로 설치되는 보강부재;Reinforcing members installed on the butt joints of the first and second half PC slabs (100, 200); 상기 제1,2하프PC슬래브(100, 200) 위로 상기 보강부재가 매입되도록 타설되는 토핑콘크리트;를 포함하여 구성되되,It is configured to include; topping concrete is poured so that the reinforcing member is embedded over the first and second half PC slab (100, 200), 상기 보강부재는, 철근 양단에 플레이트가 접합된 것으로 다수개가 상기 제1,2하프PC슬래브의 제1,2하부철근(110, 210)과 동일한 방향으로 서로 평행하게 설치되는 I형헤드조립철근(320)임을 특징으로 하는 하프PC슬래브의 이음구조.The reinforcing member, the plate is joined to both ends of the reinforcing bar is a plurality of I-shaped head assembly reinforcing bars are installed in parallel with each other in the same direction as the first and second lower reinforcement (110, 210) of the first and second half PC slab ( The joint structure of half PC slab, characterized in that 320). 하나의 스팬 내에 설치되는 복수개의 하프PC슬래브 상호 간 이음구조로서,As a joint structure of a plurality of half PC slabs installed in one span, 제1하부철근(110) 다수개가 병렬 배치되고 상·하현재와 래티스재가 조립된 제1트러스조립철근(120) 다수개가 병렬로 제1하부철근(110) 위에 교차하게 배치되어 접합된 상태에서 상기 제1하부철근(110)이 콘크리트에 매입되는 한편 상기 제1트러스조립철근(120) 상부가 콘크리트를 돌출하도록 제작된 것으로, 슬래브 시공위치에 설치되는 제1하프PC슬래브(100);A plurality of first lower reinforcing bars 110 are arranged in parallel, and the plurality of first truss assembly reinforcing bars 120, in which the upper and lower chords and the lattice material are assembled, are arranged in parallel on the first lower reinforcing bars 110 and joined to each other. A first half PC slab 100 having a first lower reinforcing bar 110 embedded in concrete while the first truss assembly reinforcing bar 120 is formed to protrude concrete, and installed at a slab construction position; 제2하부철근(210)과 제2트러스조립철근(220)을 포함하여 상기 제1하프PC슬래브(100)와 동일한 구조로 제작된 것으로, 상기 제2하부철근(210)이 상기 제1하프PC슬래브의 제1하부철근(110)과 동일한 방향으로 배치되도록 상기 제1하프PC슬래브(100)에 맞대어 설치되는 제2하프PC슬래브(200);Including the second lower reinforcing bar 210 and the second truss assembly reinforcing bar 220, the same structure as the first half PC slab 100, the second lower reinforcement 210 is the first half PC A second half PC slab 200 which is installed against the first half PC slab 100 so as to be disposed in the same direction as the first lower reinforcing bar 110 of the slab; 상기 제1,2하프PC슬래브(100, 200)의 맞댄이음부 위로 설치되는 보강부재;Reinforcing members installed on the butt joints of the first and second half PC slabs (100, 200); 상기 제1,2하프PC슬래브(100, 200) 위로 상기 보강부재가 매입되도록 타설되는 토핑콘크리트;를 포함하여 구성되되,It is configured to include; topping concrete is poured so that the reinforcing member is embedded over the first and second half PC slab (100, 200), 상기 보강부재는, 다수개의 철근이 격자로 조립된 격자조립철근(330)임을 특징으로 하는 하프PC슬래브의 이음구조.The reinforcing member is a joint structure of a half-PC slab, characterized in that the plurality of reinforcing bars are assembled into a lattice assembled grid. 하나의 스팬 내에 설치되는 복수개의 하프PC슬래브 상호 간 이음구조로서,As a joint structure of a plurality of half PC slabs installed in one span, 제1하부철근(110) 다수개가 병렬 배치되고 상·하현재와 래티스재가 조립된 제1트러스조립철근(120) 다수개가 병렬로 제1하부철근(110) 위에 교차하게 배치되어 접합된 상태에서 상기 제1하부철근(110)이 콘크리트에 매입되는 한편 상기 제1트러스조립철근(120) 상부가 콘크리트를 돌출하도록 제작된 것으로, 슬래브 시공위 치에 설치되는 제1하프PC슬래브(100);A plurality of first lower reinforcing bars 110 are arranged in parallel, and the plurality of first truss assembly reinforcing bars 120, in which the upper and lower chords and the lattice material are assembled, are arranged in parallel on the first lower reinforcing bars 110 and joined to each other. A first half reinforcing bar (110) is embedded in concrete while the first truss assembly reinforcing bar (120) is manufactured to protrude concrete, the first half PC slab (100) installed at a slab construction location; 제2하부철근(210)과 제2트러스조립철근(220)을 포함하여 상기 제1하프PC슬래브(100)와 동일한 구조로 제작된 것으로, 상기 제2하부철근(210)이 상기 제1하프PC슬래브의 제1하부철근(110)과 동일한 방향으로 배치되도록 상기 제1하프PC슬래브(100)에 맞대어 설치되는 제2하프PC슬래브(200);Including the second lower reinforcing bar 210 and the second truss assembly reinforcing bar 220, the same structure as the first half PC slab 100, the second lower reinforcement 210 is the first half PC A second half PC slab 200 which is installed against the first half PC slab 100 so as to be disposed in the same direction as the first lower reinforcing bar 110 of the slab; 상기 제1,2하프PC슬래브(100, 200)의 맞댄이음부 위로 설치되는 보강부재;Reinforcing members installed on the butt joints of the first and second half PC slabs (100, 200); 상기 제1,2하프PC슬래브(100, 200) 위로 상기 보강부재가 매입되도록 타설되는 토핑콘크리트;를 포함하여 구성되되,It is configured to include; topping concrete is poured so that the reinforcing member is embedded over the first and second half PC slab (100, 200), 상기 제1,2하프PC슬래브(100, 200) 각각은 맞댄이음부에 위치한 제1,2하부철근(110, 210) 단부가 상향하여 수직 절곡되어 콘크리트를 돌출하도록 제작된 것이며,Each of the first and second half PC slabs 100 and 200 is manufactured to protrude concrete by vertically bending end portions of the first and second lower reinforcing bars 110 and 210 positioned at the butt joints. 상기 보강부재는, 판면에 2개 이상의 통공이 형성된 것으로 다수개가 각각 상기 제1,2하프PC슬래브(100, 200)에서 돌출하는 제1,2하부철근(110, 210)에 동시에 끼워져 설치되는 연결플레이트(340)이며,The reinforcing member has two or more holes formed on the plate surface, and a plurality of reinforcing members are inserted into the first and second lower reinforcing bars 110 and 210 protruding from the first and second half PC slabs 100 and 200, respectively. Plate 340, 상기 연결플레이트(340)에 끼워진 제1,2하프PC슬래브의 제1,2하부철근(110, 210)은 연결플레이트(340) 위에서 절곡된 채 토핑콘크리트에 매입되는 것을 특징으로 하는 하프PC슬래브의 이음구조.The first and second lower reinforcing bars 110 and 210 of the first and second half PC slabs fitted to the connecting plate 340 are embedded in the topping concrete while being bent on the connecting plate 340. Joint structure. 제1항 내지 제3항 중 어느 한 항에서, The method according to any one of claims 1 to 3, 상기 제1,2하프PC슬래브(100, 200) 각각은 맞댄이음부에 위치한 각각의 제1,2하부철근(110, 210) 단부가 상향하여 갈고리로 절곡된 채 콘크리트를 돌출하도록 제작된 것이며,Each of the first and second half PC slabs 100 and 200 is manufactured to protrude concrete while the ends of each of the first and second lower reinforcing bars 110 and 210 positioned at the butt joint are bent upwardly by hooks. 상기 제1,2하프PC슬래브의 제1,2하부철근 단부 갈고리는 토핑콘크리트에 매입되는 것을 특징으로 하는 하프PC슬래브의 이음구조.A joint structure of a half PC slab, characterized in that the first and second lower reinforcing bar end hooks of the first and second half PC slabs are embedded in the topping concrete. 제1항 내지 제4항 중 어느 한 항에서,The method according to any one of claims 1 to 4, 상기 제1,2하프PC슬래브(100, 200) 각각은 각각의 제1,2트러스조립철근(120, 220) 사이에 중공재(130, 230)가 배치되어 중공재(130, 230) 상부가 콘크리트를 돌출하도록 제작된 것이며,Each of the first and second half PC slabs 100 and 200 has hollow members 130 and 230 disposed between the first and second truss assembly reinforcing bars 120 and 220 so that an upper portion of the hollow members 130 and 230 is provided. Designed to extrude concrete, 상기 제1,2하프PC슬래브의 중공재(130, 230) 상부는 토핑콘크리트에 매입되는 것을 특징으로 하는 하프PC슬래브의 이음구조.Joint structure of the half PC slab, characterized in that the upper portion of the hollow material (130, 230) of the first and second half PC slab is embedded in the topping concrete. 제1항 내지 제4항 중 어느 한 항에서,The method according to any one of claims 1 to 4, 상기 제1,2하프PC슬래브(100, 200) 각각은 단부 모서리가 모따기되도록 제작된 것이어서 상기 제1,2하프PC슬래브(100, 200)의 맞댄이음부에 모따기홈(G1)이 형성시키면서 설치되며,Each of the first and second half PC slabs 100 and 200 is manufactured so that the end edges are chamfered so that the chamfering grooves G1 are formed at the butt joints of the first and second half PC slabs 100 and 200. , 상기 토핑콘크리트는 상기 제1,2하프PC슬래브(100, 200)의 맞댄이음부의 모 따기홈(G1)에 충진되는 것을 특징으로 하는 하프PC슬래브의 이음구조.The topping concrete is a joint structure of a half PC slab, characterized in that the filling groove (G1) in the chamfered portion of the butt joint of the first and second half PC slab (100, 200). 제1항 내지 제4항 중 어느 한 항에서,The method according to any one of claims 1 to 4, 상기 제1,2하프PC슬래브(100, 200) 각각은 단부가 얇은 두께의 낮은턱으로 형성되도록 제작된 것이어서 상기 제1,2하프PC슬래브(100, 200)의 맞댄이음부에 낮은턱홈(G2)이 형성되도록 설치되며,Each of the first and second half PC slabs 100 and 200 has an end portion formed to have a low thickness of the lower jaw, so that the lower jaw groove G2 is provided at the butt joint of the first and second half PC slabs 100 and 200. ) Is formed to form, 상기 보강부재는 상기 낮은턱홈(G2)에 위치하도록 설치되는 것을 특징으로 하는 하프PC슬래브의 이음구조.The reinforcing member is a joint structure of the half PC slab, characterized in that installed in the lower jaw groove (G2).
KR1020080075123A 2008-07-31 2008-07-31 Joint of half pc slab KR20100013548A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020080075123A KR20100013548A (en) 2008-07-31 2008-07-31 Joint of half pc slab

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020080075123A KR20100013548A (en) 2008-07-31 2008-07-31 Joint of half pc slab

Publications (1)

Publication Number Publication Date
KR20100013548A true KR20100013548A (en) 2010-02-10

Family

ID=42087529

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020080075123A KR20100013548A (en) 2008-07-31 2008-07-31 Joint of half pc slab

Country Status (1)

Country Link
KR (1) KR20100013548A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101152270B1 (en) * 2012-02-02 2012-06-19 정원이엔씨(주) Precast concrete slab system for building which have long span and require high design load and construction method using this system
KR101402620B1 (en) * 2013-12-11 2014-06-13 박정환 Construction method of slab type rahmen birdge using Half-PC slab for slab bridge
CN104314217A (en) * 2013-07-26 2015-01-28 王本淼 Novel steel-concrete combined cast-in-situ hollow floor
CN104314216A (en) * 2013-07-26 2015-01-28 王本淼 Cast-in-situ hollow floor with pores formed by reticular box-shaped component
CN104314214A (en) * 2013-07-26 2015-01-28 王本淼 Cast-in-situ hollow floor with pores formed by combined reticular box-shaped component
CN105569245A (en) * 2016-01-01 2016-05-11 郭朋中 Construction method for in-situ concrete hollow floor
KR101627820B1 (en) * 2015-12-23 2016-06-07 주식회사 아이에스중공업 Steel horizontal assembly for forming a hollow slab
CN105839823A (en) * 2016-03-24 2016-08-10 中国十七冶集团有限公司 Truss type dense-rib hollow superposed floor
KR102074792B1 (en) * 2019-02-15 2020-02-07 (주)연우피씨엔지니어링 Pc slab panel which is improved joint performance
KR102375439B1 (en) 2020-09-17 2022-03-18 한국콘크리트산업 주식회사 Pc slab structure using horizontal connecting reinforcement

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101152270B1 (en) * 2012-02-02 2012-06-19 정원이엔씨(주) Precast concrete slab system for building which have long span and require high design load and construction method using this system
CN104314217A (en) * 2013-07-26 2015-01-28 王本淼 Novel steel-concrete combined cast-in-situ hollow floor
CN104314216A (en) * 2013-07-26 2015-01-28 王本淼 Cast-in-situ hollow floor with pores formed by reticular box-shaped component
CN104314214A (en) * 2013-07-26 2015-01-28 王本淼 Cast-in-situ hollow floor with pores formed by combined reticular box-shaped component
KR101402620B1 (en) * 2013-12-11 2014-06-13 박정환 Construction method of slab type rahmen birdge using Half-PC slab for slab bridge
KR101627820B1 (en) * 2015-12-23 2016-06-07 주식회사 아이에스중공업 Steel horizontal assembly for forming a hollow slab
CN105569245A (en) * 2016-01-01 2016-05-11 郭朋中 Construction method for in-situ concrete hollow floor
CN105569245B (en) * 2016-01-01 2018-11-27 郭朋中 A kind of construction method of cast-in-place concrete hollow building roof
CN105839823A (en) * 2016-03-24 2016-08-10 中国十七冶集团有限公司 Truss type dense-rib hollow superposed floor
CN105839823B (en) * 2016-03-24 2018-06-29 中国十七冶集团有限公司 A kind of hollow superposed floor of close rib of truss-like
KR102074792B1 (en) * 2019-02-15 2020-02-07 (주)연우피씨엔지니어링 Pc slab panel which is improved joint performance
KR102375439B1 (en) 2020-09-17 2022-03-18 한국콘크리트산업 주식회사 Pc slab structure using horizontal connecting reinforcement

Similar Documents

Publication Publication Date Title
KR20100013548A (en) Joint of half pc slab
JP6108595B2 (en) Ribbed precast concrete plate and method of placing concrete floor slab and beam using it
KR101260863B1 (en) Rhamen bridge having prestressed concrete girder of arch-shaped and construction method thereof
CN108951418B (en) Hinge joint structure of prefabricated hollow slab beam and construction method thereof
KR101229263B1 (en) Slab-type box girder with a vertical connecting structure made by precast concrete and method constructing the bridge thereof
JP5973206B2 (en) Wall construction method
KR101024991B1 (en) Hollowness slab type-deck plate structure and contruction method thereof
JP5143666B2 (en) PC bridge erection method
KR100938876B1 (en) Stay-in-place precast concrete panel
JP4073746B2 (en) Construction method of corrugated steel web bridge
KR101994089B1 (en) Precast Concrete Slab With Pullout-Shear Resistance Elements Of Mesh Rib And Manufacturing Method Thereof
JP5271635B2 (en) Joint member, joint structure of concrete material, and concrete member
JP2008144459A (en) Slab form and method of constructing composite floor slab
KR101196343B1 (en) Concrete arch-slab bridge of stone facing
KR101028372B1 (en) Construction for connection of the truss assembled deck plates
KR20050075777A (en) Precast transfer girder and method for constructing a structure by using of it
KR101839520B1 (en) Reinforced Steel Half Slab
JP2006233577A (en) Form for constructing slope frame and method for constructing slope frame
KR20120124129A (en) Non-supporting rc top down construction method using hybrid formwork beam
KR101304335B1 (en) Precast concrete slab having variable horizontal shear connecting member, and method for the same
KR101888001B1 (en) Superstructure of Girder Bridge, and Constructing Method thereof
KR101206991B1 (en) Structural Connection Methods for Half Precast Panels
JP6555623B2 (en) Concrete structure and construction method thereof
WO2014073506A1 (en) Construction method for concrete members
KR20220048104A (en) Libbed half PC hollow slab with truss girder

Legal Events

Date Code Title Description
A201 Request for examination
N231 Notification of change of applicant
E902 Notification of reason for refusal
E601 Decision to refuse application