KR102375439B1 - Pc slab structure using horizontal connecting reinforcement - Google Patents

Pc slab structure using horizontal connecting reinforcement Download PDF

Info

Publication number
KR102375439B1
KR102375439B1 KR1020200170690A KR20200170690A KR102375439B1 KR 102375439 B1 KR102375439 B1 KR 102375439B1 KR 1020200170690 A KR1020200170690 A KR 1020200170690A KR 20200170690 A KR20200170690 A KR 20200170690A KR 102375439 B1 KR102375439 B1 KR 102375439B1
Authority
KR
South Korea
Prior art keywords
slab
joint
bent
members
reinforcing bar
Prior art date
Application number
KR1020200170690A
Other languages
Korean (ko)
Inventor
박용선
Original Assignee
한국콘크리트산업 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 한국콘크리트산업 주식회사 filed Critical 한국콘크리트산업 주식회사
Application granted granted Critical
Publication of KR102375439B1 publication Critical patent/KR102375439B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/02Load-carrying floor structures formed substantially of prefabricated units
    • E04B5/04Load-carrying floor structures formed substantially of prefabricated units with beams or slabs of concrete or other stone-like material, e.g. asbestos cement
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/01Reinforcing elements of metal, e.g. with non-structural coatings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/16Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups

Abstract

The present invention provides a PC slab structure using horizontal joint rebar, which enables bent rebar to be pre-installed in continuously installed joint units of a PC slab to minimize installation of the additional rebar on a site, distributes vertical load applied to an upper surface unit of the PC slab to have structural stability and reduce a construction period, and has a firm joint structure of the PC slabs.

Description

수평이음철근을 이용한 PC슬래브 구조물{PC SLAB STRUCTURE USING HORIZONTAL CONNECTING REINFORCEMENT}PC slab structure using horizontal joint reinforcement {PC SLAB STRUCTURE USING HORIZONTAL CONNECTING REINFORCEMENT}

본 발명은 수평이음철근을 이용한 PC슬래브 구조물에 관한 것으로, 상호 인접한 PC슬래브를 수평이음철근을 사용하여 연결함으로써 견고한 결합구조를 만드는 수평이음철근을 이용한 PC슬래브 구조물에 관한 것이다.The present invention relates to a PC slab structure using horizontal jointed reinforcing bars, and to a PC slab structure using horizontal jointed reinforcing bars that creates a solid joint structure by connecting adjacent PC slabs using horizontal jointed reinforcing bars.

콘크리트 슬래브를 시공하는 방식에는, 거푸집을 설치하여 현장에서 직접 콘크리트를 타설하는 현장시공법과, 공장에서 제작된 PC(precast concrete)부재를 현장에서 조립하여 설치하는 PC공법으로 구분할 수 있다. 현장시공법은 많은 현장작업량에 따라 많은 인력과 공기(工期)가 소요되므로, 최근에는 부재의 표준화, 공정의 간소화, 노동 생산성 등을 꾀할 수 있는 PC공법이 주목받고 있는 상황이다.The method of constructing a concrete slab can be divided into an on-site construction method in which concrete is poured directly on the site by installing a formwork, and a PC construction method in which a PC (precast concrete) member manufactured in a factory is assembled and installed on-site. Since the on-site construction method requires a lot of manpower and time depending on the amount of on-site work, the PC construction method that can achieve standardization of members, simplification of processes, and labor productivity, etc. is attracting attention in recent years.

PC공법에는 다양한 형태의 PC부재들이 개발되어 사용되고 있으며, 그러한 PC부재 중의 하나가 하프PC슬래브이다. 하프PC슬래브는 양중무게를 고려하여 소요 슬래브 두께의 절반 정도의 두께로 미리 공장에서 제작한 부재인데, 통상적으로 하부철근 다수개를 병렬 배치한 후 상하현재와 래티스재가 조립된 트러스조립철근 다수개를 병렬 배치하여 하부철근 위에 교차하게 접합한 상태에서 콘크리트를 부어 하부철근이 콘크리트에 매입되도록 하는 한편 트러스조립철근 상부가 콘크리트에서 돌출되도록 제작한다. 이와 같은 하프PC슬래브는 시공위치에 양중 설치한 후에 나머지 콘크리트를 현장에서 타설하여 슬래브 구조체로 완성된다.In the PC method, various types of PC members have been developed and used, and one of such PC members is a half PC slab. Half PC slab is a member manufactured at the factory in advance with a thickness of about half the thickness of the required slab in consideration of the lifting weight. Usually, a plurality of lower rebars are placed in parallel, and then a plurality of truss assembly reinforcing bars with upper and lower chords and lattice materials are assembled. By placing them in parallel, pour concrete in the state that they are cross-joined on the lower reinforcing bars so that the lower reinforcing bars are embedded in the concrete, while the upper part of the truss assembly reinforcing bars protrude from the concrete. Such a half PC slab is completed as a slab structure by pouring the remaining concrete at the site after lifting it at the construction site.

한편, 하프PC슬래브의 운반과 양중 등 전반적인 사정을 고려할 때 하프PC슬래브는 그 폭이 제한되기 마련이며, 이러한 하프PC슬래브를 이용하여 슬래브 공사를 수행한다면 하나의 스팬 내에 여러 개의 하프PC슬래브를 맞대어 설치해야만 하는 경우가 있을 수밖에 없다. 이 경우 하프PC슬래브 상호 간 맞댄 이음부는 전단 내지 휨 등 구조적으로 취약하므로 이에 대한 고려가 필요한데, 전단성능은 하프PC슬래브 위에 상부철근(전단철근으로 역할함)을 배근하는 것으로, 휨성능은 하프PC슬래브에 근접하게 보강부재를 설치하는 것으로 확보할 수 있다.On the other hand, considering the overall circumstances such as transportation and lifting of half PC slabs, the width of half PC slabs is bound to be limited. There are times when you just have to install it. In this case, the butt joint between the half PC slabs is structurally weak, such as shearing or bending, so it is necessary to consider this. It can be secured by installing a reinforcing member close to the slab.

종래의 하프PC슬래브 이음구조로서, 보강부재로 통상적인 철근을 채택하여 이를 하프PC슬래브의 맞댄이음부에 설치함으로써 맞댄이음부의 휨성능을 보강한 예가 있다. 이러한 예에서 보강부재(철근)는 이음방향으로 배근되며, 다만 충분한 휨성능을 확보하기 위해서는 보강부재(철근)의 충분한 설치길이(충분한 정착력 확보를 위한 설치길이)가 필요하다.As a conventional half-PC slab joint structure, there is an example in which the bending performance of the butt joint is reinforced by adopting a conventional rebar as a reinforcing member and installing it at the butt joint of the half PC slab. In this example, the reinforcing member (reinforcing bar) is reinforced in the joint direction, but in order to secure sufficient bending performance, a sufficient installation length (installation length to secure sufficient anchoring force) of the reinforcing member (reinforcing bar) is required.

그런데, 보강부재(철근)을 충분한 설치 길이로 설치하는 것은 그리 쉽지 않다. 왜냐하면 보강부재(철근)와 하프PC슬래브의 트러스조립철근 사이에 간섭이 일어나기 때문이다. 다시 말해, 보강부재(철근)는 하프PC슬래브의 트러스조립철근과 교차하게 배근되는데, 이 경우 보강부재(철근)가 트러스조립철근의 래티스근에 걸리기 때문에 보강부재(철근)을 배근하기 위해서는 간섭부위의 래티스근을 일일이 절단해야 하는 번거로운 현장작업을 수행해야 하는 바, 보강부재(철근)의 설치길이가 길수록 그 현장작업량은 많아질 수밖에 없는 것이다.However, it is not so easy to install the reinforcing member (reinforcing bar) with a sufficient installation length. This is because interference occurs between the reinforcing member (reinforcing bar) and the truss assembly rebar of the half PC slab. In other words, the reinforcing member (reinforcing bar) is reinforced to cross the truss assembly reinforcing bar of the half PC slab. It is necessary to perform cumbersome field work in which the lattice reinforcing bars are cut one by one.

특히나 슬래브 경량화를 위해 하프PC슬래브에 중공재를 설치할 수도 있는데, 이 경우에는 보강부재(철근)가 중공재와도 간섭이 일어나게 된다. 이러한 간섭문제는 간섭위치의 중공재를 제거하는 방법으로 해결할 수밖에 없으나, 중공재를 제거하면 그만큼 콘크리트 타설량을 증대시켜야 하기 때문에 슬래브 경량화 효과는 그 만큼 떨어진다.In particular, a hollow material may be installed in the half PC slab to reduce the weight of the slab. In this case, the reinforcing member (reinforcing bar) also interferes with the hollow material. This interference problem cannot but be solved by removing the hollow material at the interference location, but if the hollow material is removed, the amount of concrete pouring must be increased by that much, so the slab weight reduction effect is lowered by that much.

이러한 하프PC슬래브 이음구조는 대부분 일반적인 PC슬래브 이음구조에 적용될 수 있으며, 슬래브의 사전 제작과 설치 과정에서 동일한 문제를 일으크게 된다. 더욱이 PC슬래브들을 맞대응되게 배치한 상태에서, 그 이음부를 대상으로 철근을 추가로 배근하고 현장콘크리트를 타설하며, 별도의 방수작업을 추가로 진행하여 PC슬래브를 일체로 결합시킨다. 이때는 별도의 방수작업을 추가적을 실시함에 따라 시공비용 및 공기가 증가하게 되며, 시공자에 따라 시공품질이 불규칙적으로 이루어짐에 따라 균일한 품질의 시공을 확보하기 어려웠다.Most of these half PC slab joint structures can be applied to general PC slab joint structures, and the same problem occurs during the pre-production and installation of slabs. Furthermore, in the state where the PC slabs are arranged to face each other, reinforcing bars are additionally reinforced at the joint, pouring on-site concrete, and additionally performing a separate waterproofing operation to unite the PC slabs. In this case, as additional waterproofing work is carried out, the construction cost and construction period increase. As the construction quality is irregular depending on the contractor, it was difficult to secure a uniform quality of construction.

이에 따라 연속되어 설치되는 PC슬래브 구조물을 대상으로 각 이음부의 접합강도를 향상시키며, 공기를 단축시킬 수 있는 이음 구조가 요구되고 있다.Accordingly, there is a demand for a joint structure capable of improving the joint strength of each joint and shortening the air period for a PC slab structure that is continuously installed.

한국등록특허출원 제10-0423126호 (2004.03.04.)Korean Patent Application No. 10-0423126 (2004.03.04.) 한국등록특허출원 제10-1899442호 (2018.09.11.)Korean Patent Application No. 10-1899442 (2018.09.11.) 공개특허공보 제10-2010-0013548호 (2010.02.10)Laid-Open Patent Publication No. 10-2010-0013548 (2010.02.10)

본 발명은 상기의 문제점을 해결하기 위하여 창안된 것으로서, 연속 설치되는 PC슬래브의 이음부에 미리 굴절된 수평이음철근을 구성함으로써 현장에서 별도의 철근설치를 최소화하며, PC슬래브의 상면부에 작용하는 수직 하중을 분산시켜 구조적 안정성 및 공기를 단축시킬 수 있으며, PC슬래브들의 이음구조를 견고하게 만드는 수평이음철근을 이용한 PC슬래브 구조물을 제공함을 그 목적으로 한다.The present invention was devised to solve the above problems, and by configuring pre-refracted horizontal joint reinforcing bars at the joints of consecutively installed PC slabs, it minimizes the installation of separate reinforcing bars in the field, and acts on the upper surface of the PC slab. The purpose of this is to provide a PC slab structure using horizontal joint reinforcing bars that can reduce structural stability and time by distributing vertical load, and make the joint structure of PC slabs strong.

본 발명에 따른 수평이음철근을 이용한 PC슬래브 구조물은, 수평방향으로 서로 연속 설치되는 PC슬래브를 일체화시키는 수평이음철근을 이용한 PC슬래브 구조물에 있어서, 중앙부분을 기준으로 일측부에 소정의 두께를 갖는 제1 파트와, 타측부에 상기 제1 파트보다 더 두꺼운 두께를 형성하는 제2 파트가 마련된 슬래브 부재; 일측 부분이 상기 슬래브 부재의 내부에 매립되어 타측 부분이 상기 슬래브 부재의 측면부로부터 소정의 길이만큼 돌출 형성되며, 상기 슬래브 부재에 간격을 두고 배치되는 슬라브 이음철근; 및 하측단부가 상기 슬래브 부재에 매립되고, 상측단부가 슬래브 부재의 상면부로부터 소정의 길이만큼 돌출 형성되는 복수개의 트러스거더를 포함하며,The PC slab structure using horizontal jointed reinforcing bars according to the present invention is a PC slab structure using horizontal jointed reinforcing bars that integrates PC slabs continuously installed with each other in the horizontal direction. a slab member provided with a first part and a second part having a thickness greater than that of the first part on the other side thereof; a slab joint reinforcing bar in which one side is embedded in the slab member so that the other side protrudes by a predetermined length from the side of the slab member, the slab reinforcing bars are disposed at intervals in the slab member; and a plurality of truss girders having a lower end embedded in the slab member and an upper end protruding from the upper surface of the slab member by a predetermined length,

상기 슬라브 이음철근은, 상기 슬래브 부재와 맞닿도록 시공 구조물에 설치되며 제1 파트와 제2 파트가 마련된 다른 슬래브 부재의 제2 파트 상으로 연장 배치되되, 상기 슬래브 부재와 다른 슬래브 부재 사이의 타설 콘크리트에 매설되는 절곡 이음부를 구비함을 특징으로 한다.The slab joint reinforcing bar is installed in the construction structure so as to come into contact with the slab member, and is disposed to extend over the second part of the other slab member provided with the first part and the second part, Concrete poured between the slab member and the other slab member It is characterized in that it is provided with a bent joint to be buried in the.

상기 슬라브 이음철근은, 상기 슬래브 부재의 내부에 매립되는 기초 매립부; 및 상기 기초 매립부보다 더 상측에 위치하여 상기 절곡 이음부에 구비되는 단차 이음부를 포함하며, 상기 기초 매립부, 절곡 이음부, 및 단차 이음부는 상기 기초 매립부와 단차 이음부가 단차를 두고 상기 절곡 이음부에 의해 연결된 S자 형상을 이루며, 상기 절곡 이음부는 제2 파트의 측면으로부터 돌출되어 인접한 다른 슬래브 부재의 제1 파트의 상측단부에 위치하되, 상기 다른 슬래브 부재의 제1 파트의 상면부로부터 이격됨이 적절하다.The slab joint reinforcing bar includes: a foundation buried part embedded in the interior of the slab member; and a stepped joint provided at the bent joint by being positioned higher than the foundation buried part, wherein the foundation buried part, the bent joint, and the stepped joint are bent with the foundation buried part and the stepped joint having a step difference. It forms an S-shape connected by a joint, and the bent joint protrudes from the side surface of the second part and is located at the upper end of the first part of another adjacent slab member, from the upper surface of the first part of the other slab member. It is appropriate to be separated.

상기 단차 이음부는 스프링 형상을 포함할 수 있다.The stepped joint may include a spring shape.

본 발명은 상기 단차 이음부와 절곡 이음부를 연결하는 커플링 너트를 더 포함할 수 있다.The present invention may further include a coupling nut connecting the stepped joint and the bent joint.

상기 단차 이음부는 수평 파형 형상을 갖도록 절곡될 수 있다.The step joint may be bent to have a horizontal wave shape.

본 발명은 상기 절곡 이음부와 단차 이음부를 연결하며, 상기 다른 슬래브 부재의 제2 파트에 접촉되도록 만곡 받침부재를 더 포함할 수 있다.The present invention may further include a curved support member that connects the bent joint and the stepped joint, and is in contact with the second part of the other slab member.

본 발명은 연속 설치되는 PC슬래브의 이음부에 미리 굴절된 수평이음철근을 구성함으로써 현장에서 별도의 철근설치를 최소화하며, PC슬래브의 상면부에 작용하는 수직 하중을 분산시켜 구조적 안정성 및 공기를 단축시킬 수 있으며, PC슬래브들의 이음구조를 견고하게 만드는 장점이 있는 수평이음철근을 이용한 PC슬래브 구조물을 제공할 수 있다.The present invention minimizes the installation of separate reinforcing bars in the field by configuring pre-refracted horizontal joint reinforcing bars at the joints of continuously installed PC slabs, and by distributing the vertical load acting on the upper surface of the PC slabs, structural stability and shortening of air It is possible to provide a PC slab structure using horizontal joint reinforcement, which has the advantage of making the joint structure of PC slabs strong.

도 1은 본 발명의 실시 예에 따른 수평이음철근을 이용한 PC슬래브 구조물의 슬래브 부재에 대한 평면도.
도 2는 도 1의 슬라브 이음철근이 슬래브 부재들에 배치된 개략적 정면도.
도 3은 도 1의 A-A 단면도.
도 4는 도 1의 B-B 단면도.
도 5는 도 3의 일부 확대 상세도.
도 6은 도 4의 일부 확대 상세도.
도 7은 다른 실시예에 따른 슬라브 이음철근이 슬래브 부재들에 배치된 개략적 정면도.
도 8은 또 다른 실시예에 따른 슬라브 이음철근이 슬래브 부재들에 배치된 개략적 정면도.
도 9는 또 다른 실시예에 따른 슬라브 이음철근이 슬래브 부재들에 배치된 개략적 정면도.
도 10은 또 다른 실시예에 따른 슬라브 이음철근이 슬래브 부재들에 배치된 개략적 정면도.
1 is a plan view of a slab member of a PC slab structure using horizontal joint reinforcement according to an embodiment of the present invention.
Figure 2 is a schematic front view of the slab joint reinforcement of Figure 1 is arranged on the slab members.
3 is a cross-sectional view taken along line AA of FIG. 1 ;
Fig. 4 is a cross-sectional view taken along line BB of Fig. 1;
5 is a partially enlarged detail view of FIG. 3 ;
6 is a partially enlarged detailed view of FIG.
7 is a schematic front view of a slab joint reinforcing bar arranged on slab members according to another embodiment.
Figure 8 is a schematic front view of a slab joint reinforcing bar is disposed on the slab members according to another embodiment.
Figure 9 is a schematic front view of the slab joint reinforcement is disposed on the slab members according to another embodiment.
10 is a schematic front view of a slab joint reinforcing bar disposed on slab members according to another embodiment.

이하, 본 발명이 속하는 선호적인 실시예를 참고로 하여 더욱 상세하게 설명한다.Hereinafter, it will be described in more detail with reference to preferred embodiments to which the present invention pertains.

도 1 내지 도 6을 참조하면, 본 발명의 실시 예에 따른 수평이음철근을 이용한 PC슬래브 구조물은, 슬래브 부재(100, 101), 슬라브 이음철근(110), 트러스거더(120), 결합철근(130), 및 보강철근(140)과 함께 미리 블록화된 콘크리트를 포함한다.1 to 6, the PC slab structure using horizontal joint reinforcement according to an embodiment of the present invention, slab members 100, 101, slab joint reinforcement 110, truss girder 120, combined reinforcement ( 130), and pre-blocked concrete with reinforcing bars 140.

슬래브 부재(100, 101)는 중앙부분을 기준으로 제1 파트(105)와 제2 파트(106)로 구분된다. 제1 파트(105)는 소정의 두께로 형성되고 제2 파트(106)는 제1 파트(105)보다 더 두꺼운 두께로 형성된다. 제1 파트(105)와 제2 파트(106) 사이에는 소정의 경사면이 형성된다.The slab members 100 and 101 are divided into a first part 105 and a second part 106 based on a central portion. The first part 105 is formed to have a predetermined thickness, and the second part 106 is formed to have a greater thickness than the first part 105 . A predetermined inclined surface is formed between the first part 105 and the second part 106 .

슬라브 이음철근(110)는 일측 단부가 슬래브 부재(100, 101)의 내부에 매립되고, 타측 단부가 슬래브 부재(100, 101)의 일측면으로부터 소정의 길이만큼 돌출 형성된 것이다.The slab joint reinforcement 110 has one end embedded in the slab member 100 and 101, and the other end protrudes from one side of the slab member 100 and 101 by a predetermined length.

이러한 슬라브 이음철근(110)는 수평방향으로 형성되며, 슬래브 부재(100, 101)의 내부에 매립되는 기초 매립부(111)와 슬래브 부재(100, 101)의 외부로 돌출되는 절곡 이음부(112)로 구성된다. 기초 매립부(111)는 절곡 이음부(112)보다 더 하부에 위치하며, 슬라브 이음철근(110)는 누운 S자 형상처럼 절곡 형성된 구조를 갖는다.The slab joint reinforcing bar 110 is formed in the horizontal direction, and the foundation buried part 111 embedded in the slab member 100 and 101 and the bent joint 112 protruding to the outside of the slab member 100 and 101 are formed. ) is composed of The foundation buried part 111 is located further below the bent joint 112, and the slab joint reinforcing bar 110 has a bent structure like an S-shaped lying down.

절곡 이음부(112)는 슬래브 부재(100)의 제2 파트(106) 측면으로부터 돌출되는데, 인접되어 설치되는 다른 슬래브 부재(101)의 제1 파트(105)의 상측단부에 위치한다. 즉 절곡 이음부(112)는 콘크리트 타설에 따른 결합구조를 위해서 제1 파트(105)의 상측면으로부터 소정의 거리만큼 이격되어 배치된다.The bent joint 112 protrudes from the side surface of the second part 106 of the slab member 100 and is located at the upper end of the first part 105 of the other slab member 101 that is installed adjacently. That is, the bent joint 112 is disposed to be spaced apart by a predetermined distance from the upper surface of the first part 105 for a bonding structure according to the concrete pouring.

트러스거더(120)는 복수개로 구성되어 역 V자 형상으로 형성되며 하측단부는 슬래브 부재(100, 101)에 매립되고, 상측단부는 슬래브 부재(100, 101)의 상측면으로부터 소정의 길이만큼 돌출 형성된다. 이러한 트러스거더(120)의 상단부는 모두 동일한 수평선상을 형성하도록 위치된다.The truss girder 120 is composed of a plurality and is formed in an inverted V-shape, the lower ends are embedded in the slab members 100 and 101 , and the upper ends protrude from the upper surfaces of the slab members 100 and 101 by a predetermined length. is formed The upper ends of the truss girder 120 are all positioned to form the same horizontal plane.

슬래브 부재(100, 101)에는 결합철근(130)이 추가로 구성된다.The slab members 100 and 101 are further configured with a coupling reinforcing bar 130 .

결합철근(130)은 ㄷ자 형상으로 절곡 형성되며 하부는 슬래브 부재(100, 101)의 내부에 매립되고, 상부는 슬래브 부재(100, 101)의 상면으로부터 소정의 길이만큼 돌출 형성된다.The coupling reinforcing bar 130 is bent in a U-shape, the lower part is embedded in the inside of the slab members 100 and 101, and the upper part is formed to protrude from the upper surface of the slab member 100 and 101 by a predetermined length.

이러한 결합철근(130)은 서로 인접하여 연속 설치되는 PC슬래브 구조물의 상측면에 현장타설 콘크리트가 타설되는 경우, 내구성을 향상시켜 PC슬래브 구조물의 구조적 안정성 및 수명을 향상시킬 수 있는 장점을 제공한다.When the cast-in-place concrete is poured on the upper side of the PC slab structure continuously installed adjacent to each other, the combined reinforcing bars 130 provide the advantage of improving the durability and improving the structural stability and lifespan of the PC slab structure.

한편, 슬래브 부재(100, 101)의 내부에는 슬라브 이음철근(110)의 매립부에 접하는 보강철근(140)이 구성된다.On the other hand, inside the slab members 100 and 101, the reinforcing bar 140 in contact with the buried portion of the slab joint reinforcing bar 110 is configured.

이러한 보강철근(140)은 기초 매립부(111)에 배근되며, 슬래브 부재(100, 101)의 내부에 매립된 상태로 구성된다. 슬래브 부재(100, 101)의 내부에 매립된 트러스거더(120)의 하측단부는 보강철근(140)의 상면에 인접하도록 구성된다.These reinforcing reinforcing bars 140 are reinforced in the foundation buried part 111 , and are configured to be embedded in the slab members 100 and 101 . The lower end of the truss girder 120 embedded in the interior of the slab members 100 and 101 is configured to be adjacent to the upper surface of the reinforcing bar 140 .

이러한 PC슬래브 구조물은, 슬래브 부재(100)의 일측으로부터 돌출되는 슬라브 이음철근(110)의 절곡 이음부(112)가 인접한 슬래브 부재(101)의 제1 파트(105) 상측면에 위치하도록 설치된다.This PC slab structure is installed so that the bent joint 112 of the slab joint reinforcing bar 110 protruding from one side of the slab member 100 is located on the upper surface of the first part 105 of the adjacent slab member 101. .

절곡 이음부(112)는 제1 파트(105)의 상측면으로부터 소정의 간격만큼 이격되도록 위치되며, 슬래브 부재(100, 101)가 연결 설치되면 트러스거더(120)의 상측면에 제1 보강철근(141)을 배근한다. 이때 제1 보강철근(141)은 결합철근(130)의 내측과 외측에 간격을 두고 배치되며, 제1 보강철근(141)과 수직으로 이격되어 제2 보강철근(142)이 배근된다.The bent joint 112 is positioned to be spaced apart from the upper surface of the first part 105 by a predetermined distance, and when the slab members 100 and 101 are connected and installed, the first reinforcing bar is located on the upper surface of the truss girder 120 . (141) is deployed. At this time, the first reinforcing rebar 141 is disposed at intervals on the inside and outside of the coupling reinforcing bar 130 , and vertically spaced apart from the first reinforcing bar 141 so that the second reinforcing bar 142 is reinforced.

한편, 서로 인접하여 설치되는 슬래브 부재(100, 101)들 사이의 이음부를 완전히 밀폐하기 위하여 별도의 방수작업을 추가로 실시한다.On the other hand, in order to completely seal the joint between the slab members 100 and 101 installed adjacent to each other, a separate waterproofing operation is additionally performed.

상기와 같이 제1 보강철근(141)과 제2 보강철근(142)의 배근이 완료되면, 슬래브 부재(100, 101)의 상측면에 구성된 슬라브 이음철근(110), 트러스거더(120) 및 결합철근(130)이 내부에 완전히 매립되도록 소정의 두께를 형성하는 현장타설 콘크리트를 타설하여 시공을 완료하게 된다.When the reinforcement of the first reinforcing bar 141 and the second reinforcing bar 142 is completed as described above, the slab joint reinforcing bar 110, the truss girder 120 and the combination formed on the upper surface of the slab members 100 and 101 Construction is completed by pouring cast-in-place concrete to form a predetermined thickness so that the reinforcing bar 130 is completely embedded therein.

상기의 슬라브 이음철근(110)의 다른 실시예들에 대해서 더욱 상세하게 설명하면 다음과 같다.The other embodiments of the slab joint reinforcing bar 110 will be described in more detail as follows.

도 7을 참조하면, 다른 실시예에 따른 슬라브 이음철근(110)도, 슬래브 부재(100, 101)들이 맞닿아 연결되도록 시공 구조물에 설치되며 제1 파트(105)와 제2 파트(106)가 마련된 다른 슬래브 부재(101)의 제2 파트(106) 상으로 연장 배치되며, 슬래브 부재(100)와 다른 슬래브 부재(101) 사이의 타설 콘크리트에 매설되는 절곡 이음부(112)를 구비한 것이다.7, the slab joint reinforcing bar 110 according to another embodiment is also installed in the construction structure so that the slab members 100 and 101 are abutted and connected, and the first part 105 and the second part 106 are It is provided with a bent joint 112 that is disposed to extend on the second part 106 of the other slab member 101 and is embedded in the concrete poured between the slab member 100 and the other slab member 101 .

이러한 슬라브 이음철근(110)는, 슬래브 부재(100, 101)의 내부에 매립되는 기초 매립부(111), 및 기초 매립부(111)보다 더 상측에 위치하여 절곡 이음부(112)에 구비되는 단차 이음부(115)를 포함한다. 기초 매립부(111), 절곡 이음부(112), 및 단차 이음부(115)는 기초 매립부(111)와 단차 이음부(115)가 단차를 두고 절곡 이음부(112)에 의해 연결된 S자 구조을 이루게 된다.The slab joint reinforcement 110 is located higher than the foundation buried part 111 buried in the interior of the slab members 100 and 101, and the foundation buried part 111, and is provided in the bent joint 112. It includes a stepped joint 115 . The foundation buried part 111 , the bent joint 112 , and the stepped joint 115 have an S shape in which the foundation buried part 111 and the stepped joint 115 are connected by the bent joint 112 with a step difference. structure will be achieved.

절곡 이음부(112)는 제2 파트(106)의 측면으로부터 돌출되어 인접한 다른 슬래브 부재(101)의 제1 파트(105)의 상측단부에 위치하며, 다른 슬래브 부재(101)의 제1 파트(105)의 상면부로부터 이격됨이 적절하다.The bent joint 112 protrudes from the side surface of the second part 106 and is located at the upper end of the first part 105 of the adjacent other slab member 101, and the first part ( 105), it is appropriate to be spaced apart from the upper surface.

한편, 이러한 단차 이음부(115)는 스프링 부재(151)를 구비함으로써 다른 슬래브 부재(101) 상에 설치되어 타설 콘크리트의 양생에 의해 고정되면, 슬래브 부재(100, 101)들을 상호 견고하게 연결하며, 다른 슬래브 부재(101) 상에 충격이나 진공에 의해 이탈되지 않는 고정구조를 제공한다. 단차 이음부(115)의 스프링 형상은 슬라브 이음철근(110)가 3차원 절곡 가공기에 의해 가공됨으로써 형성될 수 있다.On the other hand, when this step joint 115 is provided on another slab member 101 by having a spring member 151 and fixed by curing of the poured concrete, the slab members 100 and 101 are firmly connected to each other and , to provide a fixing structure that is not separated by impact or vacuum on the other slab member 101 . The spring shape of the stepped joint 115 may be formed by processing the slab joint reinforcing bar 110 by a three-dimensional bending machine.

다른 실시예에는 단차 이음부(115)와 절곡 이음부(112)를 연결하는 커플링 너트(155)가 더 포함될 수 있다. 즉 스프링 형상의 단차 이음부(115)는 절곡 이음부(112)와 별도로 스프링 형상으로 제작된 후 커플링 너트(155)에 의해 절곡 이음부(112)에 결합될 수 있다.In another embodiment, a coupling nut 155 connecting the stepped joint 115 and the bent joint 112 may be further included. That is, the spring-shaped stepped joint 115 may be manufactured in a spring shape separately from the bent joint 112 and then coupled to the bent joint 112 by the coupling nut 155 .

이러한 단차 이음부(115)의 결합은 슬래브 부재(100, 101)들의 시공 구조물에 설치 전에 이루어지거나 시공과 함께 진행될 수 있다. 스프링 형상의 단차 이음부(115)는 슬래브 부재(100, 101)의 측면부에서 돌출되는 절곡 이음부(112)들에 모두 배치되지 않고 교대로 또는 2개씩 건너서 배치될 수 있다.The coupling of the stepped joint 115 may be performed prior to installation in the construction structure of the slab members 100 and 101 or may proceed along with the construction. The spring-shaped stepped joint 115 may not be disposed on all of the bent joint 112 protruding from the side portions of the slab members 100 and 101, but may be alternately or alternately disposed two by two.

도 8을 참조하면, 또 다른 실시예에 따른 단차 이음부(115)는 수평 파형 형상을 갖도록 절곡될 수 있다. 이러한 단차 이음부(115)는 정현파 형상의 수평 파형부재(156)를 갖는 것으로서, 다른 슬래브 부재(101)의 제1 파트(105) 상에서 수평 파형 형상으로 배치된다. 이에 따라 타설 콘크리트의 양생 후에 견고하게 고정시키는 파형 구조가 콘크리트에 만들어진다.Referring to FIG. 8 , the stepped joint 115 according to another exemplary embodiment may be bent to have a horizontal wave shape. The stepped joint 115 has a horizontal wavy member 156 having a sinusoidal wave shape, and is disposed on the first part 105 of the other slab member 101 in a horizontal wave shape. Accordingly, a corrugated structure that is firmly fixed after curing of the poured concrete is made in the concrete.

도 9를 참조하면, 또 다른 실시 예에 따른 단차 이음부(115)는 절곡 이음부(112)와 단차 이음부(115)를 연결하며, 다른 슬래브 부재(101)의 제2 파트(106)에 접촉되도록 만곡 받침부재(157)를 더 포함할 수 있다.Referring to FIG. 9 , the stepped joint 115 according to another embodiment connects the bent joint 112 and the stepped joint 115 to the second part 106 of the other slab member 101 . It may further include a curved support member 157 to be in contact.

만곡 받침부재(157)는 다른 슬래브 부재(101)의 제1 파트(105) 상에 접촉되어 단차 이음부(115)의 설치와 콘크리트타설 과정에서 처짐을 방지하는 것으로서, 반원형에 가까운 형상을 가질 수 있다.The curved support member 157 is in contact with the first part 105 of the other slab member 101 to prevent sagging during the installation of the step joint 115 and the concrete pouring process, and may have a shape close to a semicircle. there is.

도 10을 참조하면, 또 다른 실시예에는, 단차 이음부(115)가 삽입되는 거치 홀(161)들이 마련되며, 다른 슬래브 부재(101)의 제1 파트(105) 상에 배치되는 받침판(160)이 더 포함될 수 있다.Referring to FIG. 10 , in another embodiment, mounting holes 161 into which the stepped joint 115 is inserted are provided, and a support plate 160 disposed on the first part 105 of the other slab member 101 . ) may be further included.

이러한 받침판(160)은 강화 플라스틱 구조로서, 다른 슬래브 부재(101)의 제1 파트(105) 상에 미리 설치될 수 있다. 이에 따라 슬래브 부재(100, 101)에 설치된 단차 이음부(115)가 받침판(160)에 삽입되어 설치될 수 있으며, 콘트리트 타설 후에 단차 이음부(115)는 받침판(160)과 함께 다른 슬래브 부재(101)에 견고하게 연결된다.The support plate 160 is a reinforced plastic structure and may be pre-installed on the first part 105 of the other slab member 101 . Accordingly, the stepped joint 115 installed on the slab members 100 and 101 may be inserted into the support plate 160 to be installed, and the stepped joint 115 after pouring concrete is formed with the support plate 160 together with other slab members ( 101) is firmly connected.

상기와 같은 본 실시예들은 연속 설치되는 PC슬래브의 이음부에 미리 설치되는 굴절된 철근을 구성함으로써 현장에서 별도의 철근설치를 최소화하며, PC슬래브의 상면부에 작용하는 수직 하중을 분산시켜 구조적 안정성 및 공기를 단축시킬 수 있으며, PC슬래브들의 이음구조를 견고하게 만드는 장점이 있다.The present embodiments as described above minimize the installation of separate reinforcing bars in the field by configuring the refracted rebars installed in advance at the joints of the continuously installed PC slabs, and distribute the vertical load acting on the upper surface of the PC slabs for structural stability And air can be shortened, and there is an advantage of making the joint structure of the PC slabs strong.

한편 본 명세서에 개시된 기술에 관한 설명은 단지 구조적 내지 기능적 설명을 위한 실시예에 불과하므로, 개시된 기술의 권리범위는 본문에 설명된 실시예에 의하여 제한되는 것으로 해석되어서는 아니 된다. 즉, 실시예는 다양한 변경이 가능하고 여러 가지 형태를 가질 수 있으므로 개시된 기술의 권리범위는 기술적 사상을 실현할 수 있는 균등물들을 포함하는 것으로 이해되어야 한다. 또한, 개시된 기술에서 제시된 목적 또는 효과는 특정 실시예가 이를 전부 포함하여야 한다거나 그러한 효과만을 포함하여야 한다는 의미는 아니므로, 개시된 기술의 권리범위는 이에 의하여 제한되는 것으로 이해되어서는 아니 될 것이다.On the other hand, since the description of the technology disclosed in this specification is merely an embodiment for structural or functional description, the scope of the disclosed technology should not be construed as being limited by the embodiment described in the text. That is, since the embodiment may have various changes and may have various forms, it should be understood that the scope of the disclosed technology includes equivalents capable of realizing the technical idea. In addition, since the object or effect presented in the disclosed technology does not mean that a specific embodiment should include all of them or only such effects, it should not be understood that the scope of the disclosed technology is limited thereby.

단수의 표현은 문맥상 명백하게 다르게 뜻하지 않는 한 복수의 표현을 포함하는 것으로 이해되어야 하고, "포함하다"또는 "가지다" 등의 용어는 설시된 특징, 숫자, 단계, 동작, 구성요소, 부분품 또는 이들을 조합한 것이 존재함을 지정하려는 것이며, 하나 또는 그 이상의 다른 특징이나 숫자, 단계, 동작, 구성요소, 부분품 또는 이들을 조합한 것들의 존재 또는 부가 가능성을 미리 배제하지 않는 것으로 이해되어야 한다.The singular expression is to be understood to include the plural expression unless the context clearly dictates otherwise, and terms such as "comprises" or "have" refer to the specified feature, number, step, action, component, part or these It is intended to indicate that a combination exists, and it should be understood that it does not preclude the possibility of the existence or addition of one or more other features or numbers, steps, operations, components, parts, or combinations thereof.

상기에서는 본 발명의 바람직한 실시예를 참조하여 설명하였지만, 해당 기술 분야의 숙련된 당업자는 하기의 특허 청구의 범위에 기재된 본 발명의 사상 및 영역으로부터 벗어나지 않는 범위 내에서 본 발명을 다양하게 수정 및 변경시킬 수 있음을 이행할 수 있을 것이다.Although the above has been described with reference to preferred embodiments of the present invention, those skilled in the art can variously modify and change the present invention within the scope without departing from the spirit and scope of the present invention as set forth in the claims below. You can do what you can do.

100, 101: 슬래브 부재
105: 제1 파트 106: 제2 파트
110: 슬라브 이음철근
111: 기초 매립부 112: 절곡 이음부
115: 단차 이음부
120: 트러스거더
130: 결합철근
140: 보강철근
141: 제1 보강철근 142: 제2 보강철근
151: 스프링 부재 155: 커플링 너트
156: 수평 파형부재 157: 만곡 받침부재
160: 받침판 161: 거치 홀
100, 101: slab member
105: first part 106: second part
110: slab joint reinforcement
111: foundation buried part 112: bent joint
115: step joint
120: truss girder
130: bonding reinforcing bar
140: rebar
141: first rebar 142: second rebar
151: spring member 155: coupling nut
156: horizontal corrugated member 157: curved support member
160: base plate 161: mounting hole

Claims (6)

중앙부분을 기준으로 일측부는 소정의 두께로 형성되는 제1 파트(105)와, 타측부에는 제1 파트(105)보다 더 두꺼운 두께로 형성되는 제2 파트(106)로 구성되며, 제1 파트(105)와 제2 파트(106) 사이에는 소정의 경사면이 형성되는 슬래브 부재(100, 101);
일측단부에 구성되어 슬래브 부재(100, 101)의 내부에 매립되는 기초 매립부(111)와, 타측단부에 구성되어 슬래브 부재(100, 101)의 일측면으로부터 소정의 길이만큼 돌출 형성되는 절곡 이음부(112)와, 절곡 이음부(112)에 구비되는 단차 이음부(115)로 구성되며, 기초 매립부(111)는 단차 이음부(115) 보다 더 하부에 위치되어 절곡 이음부(112)에 의해 연결된 S자 형상으로 절곡되는 형상으로 형성되는 슬라브 이음철근(110);
복수개로 구성되며 역 V자 형상으로 형성되고, 하측단부는 슬래브 부재(100, 101)에 매립되고, 상측단부는 슬래브 부재(100, 101)의 상측면으로부터 소정의 길이만큼 돌출 형성되되, 상단부가 동일한 수평선상에 위치되는 트러스거더(120);
ㄷ자 형상으로 절곡 형성되어 하부는 슬래브 부재(100, 101)의 내부에 매립되고, 상부는 슬래브 부재(100, 101)의 상면으로부터 소정의 길이만큼 돌출 형성되는 결합철근(130); 및
기초 매립부(111)에 배근되어 슬래브 부재(100, 101)의 내부에 매립되고, 트러스거더(120) 하측단부에 상면이 인접하는 보강철근(140);을 포함하며,
단차 이음부(115)의 끝단에는 스프링 형상의 스프링 부재(151)와, 절곡 이음부(112)와 단차 이음부(115)를 연결하는 커플링 너트(155)가 더 포함되며,
상기 절곡 이음부(112)는
슬래브 부재(100)의 제2 파트(106) 측면으로부터 돌출되되, 인접설치되는 다른 슬래브 부재(101)의 제1 파트(105)의 상측면으로부터 소정의 거리만큼 이격 배치되며,
슬래브 부재(100, 101)가 연결 설치되면 트러스거더(120)의 상측면에 제1 보강철근(141)이 배근되되, 제1 보강철근(141)은 결합철근(130)의 내측과 외측에 간격을 두고 배치되며, 제1 보강철근(141)과 수직으로 이격되는 제2 보강철근(142)이 배근되는 것을 특징으로 하는 수평이음철근을 이용한 PC슬래브 구조물.
Based on the central portion, the first part 105 is formed with a predetermined thickness on one side, and the second part 106 is formed with a thicker thickness than the first part 105 on the other side, and the first part slab members 100 and 101 in which a predetermined inclined surface is formed between the 105 and the second part 106;
A foundation buried part 111 configured at one end and buried in the interior of the slab members 100 and 101, and a bent joint configured at the other end and formed to protrude from one side of the slab member 100, 101 by a predetermined length It is composed of a part 112 and a stepped joint 115 provided in the bent joint 112, and the foundation buried part 111 is located further lower than the stepped joint 115, so that the bent joint 112 is formed. Slab joint reinforcing bars 110 formed in a shape that is bent into an S-shape connected by;
It consists of a plurality and is formed in an inverted V-shape, the lower ends are embedded in the slab members 100 and 101, and the upper ends are formed to protrude by a predetermined length from the upper surfaces of the slab members 100 and 101, and the upper end is Truss girder 120 positioned on the same horizontal line;
A coupling reinforcing bar 130 that is bent in a U-shape, the lower part is embedded in the interior of the slab member (100, 101), and the upper part is formed to protrude by a predetermined length from the upper surface of the slab member (100, 101); and
Reinforced in the foundation buried part 111, embedded in the interior of the slab member 100, 101, the truss girder 120, the upper surface adjacent to the lower end of the reinforcing bar 140; includes;
The end of the stepped joint 115 further includes a spring-shaped spring member 151 and a coupling nut 155 for connecting the bent joint 112 and the stepped joint 115,
The bent joint 112 is
It protrudes from the side of the second part 106 of the slab member 100, and is spaced apart by a predetermined distance from the upper surface of the first part 105 of the other slab member 101 that is adjacently installed,
When the slab members 100 and 101 are connected and installed, the first reinforcing bar 141 is reinforced on the upper surface of the truss girder 120 , and the first reinforcing bar 141 is spaced on the inside and outside of the coupling reinforcing bar 130 . PC slab structure using horizontal joint reinforcing bars, characterized in that the second reinforcing bars 142 spaced apart from the first reinforcing bars 141 are vertically disposed.
제 1 항에 있어서,
상기 단차 이음부(115)는
정현파 형상의 수평 파형부재(156)로 구성되며, 연속 설치되는 슬래브 부재(100, 101) 중 인접하는 슬래브 부재(101)의 제1 파트(105) 상에서 수평 파형 형상으로 배치되는 것을 특징으로 하는 수평이음철근을 이용한 PC슬래브 구조물.
The method of claim 1,
The step joint 115 is
It is composed of a sine wave-shaped horizontal corrugated member 156, and is disposed in a horizontal corrugated shape on the first part 105 of the adjacent slab member 101 among the slab members 100 and 101 continuously installed. PC slab structure using jointed reinforcing bars.
제 1 항에 있어서,
상기 단차 이음부(115)는
절곡 이음부(112)와 단차 이음부(115)를 연결하며, 연속 설치되는 슬래브 부재(100, 101) 중 인접하는 슬래브 부재(101)의 제2 파트(106)에 접촉되는 만곡 받침부재(157)를 더 포함하는 것을 특징으로 하는 수평이음철근을 이용한 PC슬래브 구조물.
The method of claim 1,
The step joint 115 is
The curved support member 157 connects the bent joint 112 and the stepped joint 115 and contacts the second part 106 of the adjacent slab member 101 among the slab members 100 and 101 that are continuously installed. ) PC slab structure using horizontal joint reinforcement, characterized in that it further comprises.
제 3 항에 있어서,
상기 만곡 받침부재(157)는
연속 설치되는 슬래브 부재(100, 101) 중 인접하는 슬래브 부재(101)의 제1 파트(105) 상에 접촉되어 단차 이음부(115)의 설치와 콘크리트 타설 과정에서의 처짐을 방지하는 것을 특징으로 하는 수평이음철근을 이용한 PC슬래브 구조물.
4. The method of claim 3,
The curved support member 157 is
It is in contact with the first part 105 of the adjacent slab member 101 among the slab members 100 and 101 that are continuously installed to prevent sagging during the installation of the step joint 115 and the concrete pouring process. PC slab structure using horizontal jointed reinforcing bars.
제 1 항에 있어서,
상기 단차이음부(115)가 삽입되는 거치홀(161)이 형성되며, 연속 설치되는 슬래브 부재(100, 101) 중 인접하는 슬래브 부재(101)의 제1 파트(105) 상에 배치되어 단차 이음부(115)를 지지하는 받침판(160)을 더 포함하는 것을 특징으로 하는 수평이음철근을 이용한 PC슬래브 구조물.
The method of claim 1,
A mounting hole 161 into which the stepped joint 115 is inserted is formed, and is disposed on the first part 105 of the adjacent slab member 101 among the continuously installed slab members 100 and 101 to provide a stepped joint. PC slab structure using horizontal joint reinforcement, characterized in that it further comprises a support plate 160 for supporting the part 115.
삭제delete
KR1020200170690A 2020-09-17 2020-12-08 Pc slab structure using horizontal connecting reinforcement KR102375439B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR20200119904 2020-09-17
KR1020200119904 2020-09-17

Publications (1)

Publication Number Publication Date
KR102375439B1 true KR102375439B1 (en) 2022-03-18

Family

ID=80936669

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020200170690A KR102375439B1 (en) 2020-09-17 2020-12-08 Pc slab structure using horizontal connecting reinforcement

Country Status (1)

Country Link
KR (1) KR102375439B1 (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11107529A (en) * 1997-10-02 1999-04-20 Katayuki Sendai Binding method for post-placing concrete and post-placing concrete binder
JP2001132149A (en) * 1999-11-09 2001-05-15 Nippon Kaiser Kk Precast concrete floorboard for viaduct, viaduct and construction method
KR100423126B1 (en) 2002-02-04 2004-03-16 유승룡 T-shape PC slab
KR20100013548A (en) 2008-07-31 2010-02-10 삼성중공업 주식회사 Joint of half pc slab
KR20170067584A (en) * 2015-12-08 2017-06-16 이진희 Reinforced Steel Half Slab
KR101899442B1 (en) 2018-02-05 2018-09-17 정도건설산업 (주) PC slab with inclined end plate

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11107529A (en) * 1997-10-02 1999-04-20 Katayuki Sendai Binding method for post-placing concrete and post-placing concrete binder
JP2001132149A (en) * 1999-11-09 2001-05-15 Nippon Kaiser Kk Precast concrete floorboard for viaduct, viaduct and construction method
KR100423126B1 (en) 2002-02-04 2004-03-16 유승룡 T-shape PC slab
KR20100013548A (en) 2008-07-31 2010-02-10 삼성중공업 주식회사 Joint of half pc slab
KR20170067584A (en) * 2015-12-08 2017-06-16 이진희 Reinforced Steel Half Slab
KR101899442B1 (en) 2018-02-05 2018-09-17 정도건설산업 (주) PC slab with inclined end plate

Similar Documents

Publication Publication Date Title
KR101693256B1 (en) Construction method of prefabricated psc bridge
KR102155646B1 (en) FRP Reinforcement PC Deck, Formwork for it and Manufacturing Method of FRP Reinforcement PC Deck using same
KR20100013548A (en) Joint of half pc slab
JP6491034B2 (en) Concrete floor slab
KR200394787Y1 (en) continuous structure system type precast prestressed concrete single slab girder bridge connecting and supporting the same bridge with one point supporting structure or strongly coupled integrated structure
KR102375439B1 (en) Pc slab structure using horizontal connecting reinforcement
KR100938876B1 (en) Stay-in-place precast concrete panel
JP4073746B2 (en) Construction method of corrugated steel web bridge
JP6066981B2 (en) Connection structure in bridges using reinforced concrete slabs and connection method in existing bridges using reinforced concrete slabs
KR20050079301A (en) Precast concrete slab panel with lateral load resistancy and slab structure using the same
JP2004197388A (en) Flat slab structure
KR20040007956A (en) Hybrid Type Composite Deck having Deck Plate and I Beam, and Constructing Method thereof
KR102327700B1 (en) Girder structure and construction method for continuity of supporting portion of girder using the same
KR102155645B1 (en) Formwork for the PC Deck that can be placed at the Exact Position, the Manufacturing Method of the PC Deck using the same and the PC Deck
KR102140407B1 (en) Mamanufacturing method of PSC girder using end form steel plate
KR102393088B1 (en) Half Depth Concrete Deck Panel With Precast Rib And Construction Method Using Therof
KR101752285B1 (en) Hybrid beam with wide PSC lower flange and enlarged section upper flange and structure frame using the same
JPH09221706A (en) Floor slab for road surface and layout method thereof
KR101304335B1 (en) Precast concrete slab having variable horizontal shear connecting member, and method for the same
CN111485490A (en) Wide prefabricated bridge deck and construction method thereof
JPH0913486A (en) Concrete structure body
KR100730018B1 (en) Prestressed steel-concrete composite and method for constructing the same
JPH10227010A (en) Steel form with main reinforcement for bridge floor panel and bridge floor panel construction method using it
KR102021119B1 (en) Channel type pc slab with opening and construction method thereof
KR20010095899A (en) Composition of precast concrete wall and precast concrete column for outdoor to sustain external force

Legal Events

Date Code Title Description
GRNT Written decision to grant