KR200394787Y1 - continuous structure system type precast prestressed concrete single slab girder bridge connecting and supporting the same bridge with one point supporting structure or strongly coupled integrated structure - Google Patents
continuous structure system type precast prestressed concrete single slab girder bridge connecting and supporting the same bridge with one point supporting structure or strongly coupled integrated structure Download PDFInfo
- Publication number
- KR200394787Y1 KR200394787Y1 KR20-2005-0012097U KR20050012097U KR200394787Y1 KR 200394787 Y1 KR200394787 Y1 KR 200394787Y1 KR 20050012097 U KR20050012097 U KR 20050012097U KR 200394787 Y1 KR200394787 Y1 KR 200394787Y1
- Authority
- KR
- South Korea
- Prior art keywords
- girder
- bridge
- single slab
- precast psc
- slab
- Prior art date
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2/00—Bridges characterised by the cross-section of their bearing spanning structure
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/20—Concrete, stone or stone-like material
- E01D2101/24—Concrete
- E01D2101/26—Concrete reinforced
- E01D2101/28—Concrete reinforced prestressed
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
본 고안은 바닥판슬래브를 거더의 상부플랜지와 일체로 하여 복부와 하부플랜지로 구성된 거더를 제작장에서 1차강선을 긴장정착한 프리캐스트 PSC단일슬래브거더를 제작하고, 상기 프리캐스트 PSC단일 슬래브거더를 교대 및 교각사이에 연이어서 거치하면서, 연이어서 설치된 상기 거더를 교량부속품을 거더코너앵글과 강결연결하고, 철근을 활동방지용 시스템으로 강결접합하면서 거더사이 구간을 고강도 콘크리트를 현장타설하여 연결한 다음, 2차연속강선을 바닥판 슬래브플랜지상에 균등배치하여 긴장 및 정착하여 상호 연속구조계로 구축한 다음, 교대 및 교각에서 연속화된 상기 거더를 1점지지구조로 하거나, 상기 거더와 거더 및 거더와 교각 또는 교대를 강결일체구조로 설치하여 강결일체구조의 경계조건을 갖는 연속다가구 프리캐스트 PSC단일 슬래브거더교를 구축하는 방법과, 상기 프리캐스트 PSC 단일슬래브거더를 정형화된 프리캐스트로 제작하기 위하여, 상기 거더를 제작하기 위한 거푸집은 단면변화위치, 사각변화위치, 곡률변화위치등에 적용할 수 있는 힌지시스템과 탈착식클램프를 도입하고, 상기 거푸집을 지지하는 지지대에 연결된 잭으로 지지 및 표고변화에 따른 위치조정이 가능토록하여, 어느 단면에도 적용할 수 있는 전용성과 성역성이 뛰어난 표준화된 거푸집을 제작하는 방법에 관한 것이다. The present invention manufactures a precast PSC single slab girder with tension plated primary steel wire at the workshop by combining the bottom plate slab with the upper flange of the girder and the abdomen and the lower flange, and the precast PSC single slab girder After connecting between the bridges and bridges, the bridges are connected to the girder corner angles and the steel parts are connected to the girder corner angles. The secondary continuous steel is evenly placed on the slab flange and tensioned and settled to form a mutually continuous structure system, and then the girders continued in alternating and piers as one-point supporting structures, or the girders, girders and girders and Continuous multi-family precast PSC with boundary condition of steel integral structure by installing pier or alternating steel structure In order to construct one slab girder bridge and to manufacture the precast PSC single slab girder as a standardized precast, the formwork for manufacturing the girder can be applied to a cross-sectional change position, a square change position, and a curvature change position. The hinge system and the removable clamp are introduced, and the jacks connected to the support for supporting the formwork allow the position to be adjusted according to the change of the support and the elevation. It is about how to.
Description
본 고안은 바닥판슬래브를 거더의 상부플랜지와 일체로 하여 복부와 하부플랜지로 구성된 거더를 제작장에서 1차강선을 긴장정착한 프리캐스트 PSC단일슬래브거더를 제작하고, 상기 프리캐스트 PSC단일 슬래브거더를 교대 및 교각사이에 연이어서 거치하면서, 연이어서 설치된 상기 거더를 교량부속품을 거더코너앵글과 강결연결하고, 철근을 활동방지용 시스템으로 강결접합하면서 거더사이 구간을 고강도콘크리트를 현장타설하여 연결한 다음, 2차연속강선을 바닥판 슬래브플랜지상에 균등배치하여 긴장 및 정착하여 상호 연속구조계로 구축한 다음, 교대 및 교각에서 연속화된 상기 거더를 1점지지구조로 하거나, 상기 거더와 거더 및 거더와 교각 또는 교대를 강결일체구조로 설치하여 강결일체구조의 경계조건을 갖는 연속다가구 프리캐스트 PSC단일 슬래브거더교를 구축하는 방법과, 상기 프리캐스트 PSC 단일슬래브거더를 정형화된 프리캐스트로 제작하기 위하여, 상기 거더를 제작하기 위한 거푸집은 단면변화위치, 사각변화위치, 곡률변화위치등에 적용할 수 있는 힌지시스템과 탈착식클램프를 도입하고, 상기 거푸집을 지지하는 지지대에 연결된 잭으로 지지 및 표고변화에 따른 위치조정이 가능토록하여, 어느 단면에도 적용할 수 있는 전용성과 성역성이 뛰어난 표준화된 거푸집을 제작하는 방법에 관한 것이다. The present invention manufactures a precast PSC single slab girder with tension plated primary steel wire at the workshop by combining the bottom plate slab with the upper flange of the girder and the abdomen and the lower flange, and the precast PSC single slab girder After connecting the bridge between the alternating bridge and the bridge, the bridge parts are connected with the girder corner angle and the steel parts are connected with the girder corner angle. The secondary continuous steel is evenly placed on the slab flange and tensioned and settled to form a mutually continuous structure system, and then the girders continued in alternating and piers as one-point supporting structures, or the girders, girders and girders and Continuous multi-family precast PSC with boundary condition of steel integral structure by installing pier or alternating steel structure In order to construct one slab girder bridge and to manufacture the precast PSC single slab girder as a standardized precast, the formwork for manufacturing the girder can be applied to a cross-sectional change position, a square change position, and a curvature change position. The hinge system and the removable clamp are introduced, and the jacks connected to the support for supporting the formwork allow the position to be adjusted according to the change of the support and the elevation. It is about how to.
본 고안의 목적은 표준화된 거푸집으로 프리캐스트PSC단일슬래브거더의 제작전용성을 높이고, 상기 슬래브거더연결이 상호 일관성을 유지하면서 설계에서 요구하는 품질을 갖고자 하는 교량의 단면 및 위치와 표고를 컴퓨터에 사전에 입력된 교량설치프로그램에 입력하여 각각의 교량위치에 따른 단면3차원좌표를 계산하여 이를 제작장의 거푸집설치시스템에 연결하여 자동으로 제어하여 프리캐스트 PSC단일 슬래브거더를 제작하되, 즉 바닥판 슬래브와 거더의 상부플랜지를 일체화하도록 하여 거더를 제작한 후에 이를 교대 및 교각에 연속화된 일체구조로 하여 1점지지구조의 연속구조로 지지하던지 또는 상기 거더와 거더 및 거더와 교대 또는 교각을 강결일체화한 연속다가구 프리캐스트 PSC단일슬래브거더교를 설치하도록 하여 거더를 현장상황에 맞는 단면으로 제작하도록 하는 정형화된 거푸집을 이용하여 컴퓨터로 자동으로 제어가 되도록 하여 제작하도록 하는 일괄제작방법을 적용하여 교량설치에 따른 거더를 제작 및 설치비용을 절감할 수 있는 교량설치방법을 제공하는데 있다. The purpose of the present invention is to standardize the formwork of precast PSC single slab girder, and to make the cross section, location and elevation of the bridge to have the quality required by the design while maintaining the coherence of the slab girder connection. The precast PSC single slab girder is manufactured by inputting into the bridge installation program input in advance and calculating the cross-sectional 3D coordinates according to each bridge location and automatically controlling it by connecting to the formwork installation system of the manufacturing site. After making the girder by integrating the upper flange of the girder and supporting it with a continuous structure of one-point supporting structure by making it a continuous structure of alternating and piers or rigidly integrating the girder, girder and girders with alternating or piers Continuous multi-family precast PSC single slab girder bridge It provides a bridge installation method that can reduce the cost of manufacturing and installing the girder according to the bridge installation by applying the batch production method that can be controlled by the computer automatically by using the standard formwork to produce the correct cross section. have.
종래에는 도 1과 도 2에서 보는바와 같이 PS 강선(11)에 긴장력을 도입하여 제작한 PSC 빔(12)을 교대(13) 및 교각(14)에 단순구조계로 설치한 후에 그 상부에 철근 콘크리트로 된 바닥판을 현장타설하여 합성형교로 구성하며 교각의 지점부상의 신축이음을 줄여 주행성을 좋게하기 위하여 상기 위치 빔 상부의 지점부바닥판에 보강철근(18)을 추가 설치한 후에 바닥판 콘크리트(17)를 타설하여 지점부바닥판을 연결형으로 하는 것을 특징으로 한 PSC 합성형교(10)를 설치한 것으로서, In the related art, as shown in FIGS. 1 and 2, the PSC beam 12 manufactured by introducing a tension force into the PS steel wire 11 is installed on the alternating 13 and the piers 14 in a simple structure system, and then reinforced concrete is formed thereon. In order to improve the driving performance by reducing the expansion joints on the point of the pier, the bottom plate made of composite girder bridge is installed on the bottom plate, and then the reinforcing bar 18 is added to the bottom plate of the point beam. PSC composite girder bridge (10) characterized in that the point bottom plate is connected by placing (17),
상기 교각상 지점부의 빔과 빔의 상부에 지점부바닥판보강철근(18)을 이용하여 바닥판 콘크리트(17)를 타설한 것은 빔과빔을 일체화 연속화한 것이 아니고 단순히 바닥판만 연결된 구조로 하거나 빔과 빔을 연결한 연결형 구조인 것이며, 이로인하여 도 1에서보는바와 같이 지점부인 교각(15)에 2개의 받침(16)을 설치하여 빔의 각각을 지지하도록 한 단순보구조계로 설치한 후에 그 상부에 철근 콘크리트 바닥판(19)을 현장타설하고, 상기 거더(12)와 바닥판(17)은 전단연결재로 연결하여 합성형 구조로 하고, 교각 지점부의 바닥판은 단순히 철근만 보강하여 바닥판만 연결되므로서 실질적인 연속교가 아닌 단순구조교량으로서 실질적으로 연속교로 설치된 교량에서 발생되는 휨모멘트의 크기를 감소 또는 재분배효과가 없어 경제적인 면과 보다 안전적인 교량을 구축하기가 곤란하고, 지점부 바닥판에는 인장균열제어가 곤란한 문제가 있으며, Placing the bottom plate concrete 17 using the point bottom plate reinforcing bar 18 on the beam portion of the pier point and the beam is not a continuous integration of the beam and the beam, but simply connected to the bottom plate. It is a connection type structure connecting the beam and the beam, and as a result, as shown in FIG. 1, after the two beams 16 are installed in the bridge piers 15 as point parts, the beams are installed in a simple beam structure system to support each of the beams. Reinforce the concrete floor plate 19 in the upper part, and the girder 12 and the bottom plate 17 is connected to the shear connection material to the composite structure, the bottom plate of the pier point is simply reinforced only the bottom plate As it is a simple structural bridge rather than a continuous bridge, it is economical and safer because it does not reduce or redistribute the amount of bending moment generated in a bridge that is installed as a continuous bridge. It is difficult to construct the amount, and there is a problem that the tension crack control is difficult in the branch bottom plate,
또한, 도 2는 도 1의 교량구조의 합성형교 단면과 설치방법과 단면을 지지하는 구조계가 근본적인 변화가 없이 동일한 방법이며, 단순히 교량상의 지점부 바닥판의 인장균열을 다소 제어하기 위해 PSC빔내에 2차강선(22)을 설치하여 합성후 사하중과 활하중을 부담토록하였으나, 도 1의 구조계 변화없이 단순히 빔의 상부만 연결되므로서 그 지점부의 철근콘크리트바닥판이 최대인장력을 발휘하게됨에따라 PSC 빔내의 2차강선배치로는 상기 도 1에서 언급한 인장균열이 피할 수 없음에 따라 도 1과 같이 지점부보강철근(18)을 보강하므로 도 1의 종래방식의 문제점을 대부분 내포하고 있으며, 합성형 단면의 빔(12)은 전문업체에서 제작하고, 슬래브바닥판(17)은 다른 시공회사가 현장시공하는 이중적 구조로는 완전한 합성단면 구성이 어렵고, 실제 현장조사결과를 보면 서로간의 품질차이로 인한 여러 문제점이 있는 것뿐만아니라 한 교각내에 서로 다른 두 빔의 지지를 각각 한 상태에서 2차 강선을 현장긴장으로 상호 두 빔을 연결하다보니 2차강선의 긴장력에 의해 두 빔을 지지하는 탄성받침(16)이 전단변형을 일으킬 염려가 있는바 구조계 변화를 하는 구조안전성 및 내구성에 문제점이 있다. In addition, Figure 2 is the same method of the composite bridge cross section and the installation method of the bridge structure of Figure 1 and the structural system supporting the cross section without the fundamental change, and simply in the PSC beam to control somewhat the tensile crack of the bottom plate of the point on the bridge The secondary steel wire 22 was installed to bear the dead load and the live load after the synthesis, but since the upper part of the beam was simply connected without changing the structural system of FIG. 1, the reinforced concrete floor plate at the point exhibited the maximum tensile strength in the PSC beam. As the secondary steel wire arrangement, the tensile cracks mentioned in FIG. 1 cannot be avoided, thereby reinforcing the branch reinforcing bars 18 as shown in FIG. 1, and most of the problems of the conventional method of FIG. The beam 12 is manufactured by a specialized company, and the slab bottom plate 17 is a double structure that is installed by another construction company, and thus, it is difficult to construct a complete composite cross section. The results show that there are various problems due to the quality difference between each other, as well as the support of two different beams in a pier, each connecting two beams with on-site tension, which is why As a result, the elastic support 16 supporting the two beams may cause shear deformation, and thus there is a problem in structural safety and durability of changing the structural system.
본 고안은 상기와 같은 종래기술의 문제점인 합성형 단면별 시공주체가 서로 상이함에따른 품질저하에 의한 내하율 및 내구성 저하, 지점부 인장측인 바닥슬래브 인장균열 발생, 2차강선긴장시 2점지지에 따른 받침의 전단변형, 단순구조계로서 모멘트재분배 현상이 없어 복부고 상승, 비경제적인 단면 및 내하율 저하를 해결하기 위하여 개발된 것으로서, The design of the present invention is a problem of the above-described problems of the conventional composite type cross-section of the construction according to the quality deterioration due to the deterioration of the load ratio and durability, the tensile cracking of the bottom slab on the tensile side of the point, two points when the secondary wire tension Shear deformation and simple structure of the bearing according to the support, developed to solve the abdominal height rise, uneconomical cross-section, and load-bearing rate reduction because there is no moment redistribution phenomenon.
프리캐스트PSC 거더와 현장타설 철근콘크리트슬래브합성단면을 단일화 PSC슬래브거더로 프리캐스트화 하여 프리캐스트 PSC단일 슬래브거더구조로 제작하는 기술과, 상기 제작된 프리캐스트 PSC단일슬래브거더를 현장의 교대 및 교각상에 거치하고, 1점받침지지로 교체하면서 거더끼리 강결하거나, 교각 및 교대와 거더를 서로 완전고정강결 일체화하여 완전한 연속다가구구조로 형성하여 부정정 차수가 높은 구조계로 형성하여 붕괴경로가 많아 연성이 많은 구조계로 형성하여 보다 안정적이고 단일공장제작된 고품질화와 경제성이 확보된 교량을 시공하는 방법을 제공하는 것과, Precast PSC girder and cast-in-place reinforced concrete slab composite sections are precast into a single PSC slab girder to fabricate a precast PSC single slab girder structure, and the precast PSC single slab girder fabricated on the site alternately and pier Mounted on the floor and replaced with one-point support, the girders are stiffened, or the bridges and shifts and girders are completely fixed together, forming a complete continuous multi-structure structure. To provide a way to construct more stable and single factory-made high-quality and economical bridges formed by this many structural systems,
상기 프리캐스트 PSC단일슬래브거더 구조를 보다 전용성이 넓게 성역화를 도모하기 위하여 어느 경간의 단면, 평면선형, 사선, 종단선형에도 적용되도록 3헌치단면, 상기 단면변화와 평면선형 변화위치에 유연하게 적용할 수 있는 힌지시스템이 도입된 표준화거푸집이 되도록 하여 전용성, 경제성이 확보된 교량을 시공하는 방법을 제공하는데 있다. The precast PSC single slab girder structure can be flexibly applied to the three-hundred section, the cross-sectional change, and the planar linear change position to be applied to any cross section, planar linear, oblique, and longitudinal linear in order to achieve more diversification. It is to provide a method for constructing bridges with dedicated and economical efficiency by making standard formwork with a hinge system.
본 고안은 바닥판슬래브를 거더의 상부플랜지와 일체로 하여 복부와 하부플랜지로 구성된 거더를 제작장에서 1차강선이 긴장정착된 상태인 프리캐스트 PSC 단일슬래브거더로 제작하고, 상기 제작된 프리캐스트 PSC단일슬래브거더를 교대 및 교각사이에 연이어서 거치하고, 연이어서 거치된 상기 프리캐스트 PSC 단일슬래브거더를 교량부속품을 거더코너앵글과 강결연결하고, 철근을 호라동방지용 시스템을 이용하여 강결접합하면서 거더사이 구간을 고강도현장타설 콘크리트로 연결한 다음, 2차연속강선을 바닥판 슬래브플랜지상에 균등배치하여 긴장 및 정착하여, 상호 연속구조계로 구축한 다음, 교대 및 교각에서 상기 거더를 1점지지구조로 하거나 상기 거더와 교대 및 교각을 강결일체구조로서 경계조건을 갖는 연속다가구 프리캐스트 PSC단일 슬래브거더교를 구축하는 방법과, The present invention is made of a precast PSC single slab girder in which the primary steel wire is tension-fixed in the workshop by combining the bottom plate slab with the upper flange of the girder and the abdomen and the lower flange. The PSC single slab girder is mounted successively between shifts and piers, and the precast PSC single slab girder is connected to the girder corner angle with the bridge parts, and the steel bars are rigidly joined using the anti-braking system. The sections between the girders are connected with high-strength cast concrete, and the secondary continuous steel is evenly placed on the slab flange and tensioned and settled, constructed in a mutually continuous structure system, and supporting one point of the girder at the shift and piers. Continuous multi- furniture precast PSC single slab having boundary condition as structure How to build a girder and the bracket,
상기 프리캐스트 PSC단일슬래브거더를 정형화하여 프리캐스트로 제작하기 위한 거푸집은 단면변화위치, 사각변화위치, 곡률변화위치등의 단면변화에 맞도록 조정이 가능한 힌지가 설치된 3헌치단면으로 형성된 힌지시스템과 착탈식 클램프를 도입하고, 상기 거푸집을 지지하고 있는 지지대에 연결된 잭을 이용하여 지지 및 표고 위치조정이 가능하도록 하여 단면변화와 평면선형변화에 유연하게 적용할 수 있도록 전용성, 경제성 및 성역성이 뛰어난 표준화된 거푸집을 이용하여 PSC단일슬래브거더를 제작하는 것과 상기 슬래브거더의 상호연결이 일관성 유지와 설계에서 요구하는 품질이나 균등성을 갖고자, 상기 슬래브거더의 상호관련 위치에 대한 3차원좌표를 컴퓨터를 이용한 프로그램에 의해 자동계산하고, 이를 현장에서 자동제어하는 시스템으로 정밀하게 PSC단일슬래브거더를 제작하여 교량을 시공하는 방법을 제공하는데 특징이 있다. Forming the precast PSC single slab girder to form the precast form the hinge system formed of a three-hundred section with a hinge that can be adjusted to match the cross-sectional change, such as the cross-sectional change position, square change position, curvature change position and the like; Standardization with high dedication, economics and sanctuary for introducing flexible clamp and flexible support for cross-sectional change and planar linear change by enabling support and elevation adjustment using jacks connected to the support supporting the formwork. In order to fabricate the PSC single slab girder using the built-in formwork and to maintain the consistency and quality or uniformity required for the design of the slab girder, the three-dimensional coordinates of the interrelated positions of the slab girder are computerized. System that automatically calculates by program and automatically controls it on site To precisely produce a PSC girder single slab is characterized as to provide a method for construction of a bridge.
이하, 본 고안의 구성 및 작용을 첨부된 도면에 의하여 상세히 설명하면 다음과 같다. Hereinafter, with reference to the accompanying drawings the configuration and operation of the present invention in detail as follows.
도 3은 본 고안의 연속다가구 프리캐스트 PSC 단일슬래브거더교의 1점받침으로 교체 및 지지하여 완전연속교를 설치하는 것을 보여주는 도면으로서, 1차 강선(51)에 프리스트레스를 도입하여 프리캐스트 PSC단일슬래브거더(40)를 공장에서 제작한 다음, 상기 거더(40)를 지점부인 교각 및 교대의 임시받침에 위에 설치하고, 상기 지점부의 거더(40)와 거더(40)사이 연결부에서 거더코너앵글을 솔플레이트(98)로 강절용접하여 연결하고, 영구받침(97)으로 교체하면서 상기 임시받침(21)을 제거하여 1점지지연속구조(54)로 한 다음, 거더(40)와 거더(40)사이의 철근을 연결부철근슬립클립루프장치(80)로 연결하고 무수축고강도콘크리트(71)를 타설한 다음, 2차 지점부 PS강선(52)을 삽입하여 긴장력을 도입한 후에, 정착(53)하여 거더와 거더연결을 완전일체연속한 거더연결부(70)를 구축하도록 하여 상기 지점부인 교각(14)위에 1점지지구조(54)로 지지하고, 거더를 완전일체화되게 연결한 완전연속교를 설치하도록 한 실질적인 연속다가구 프리캐스트 PSC단일슬래브거더교(30)를 설치한 것이다. 3 is a view showing the installation of a complete continuous bridge by replacing and supporting the one-point support of the continuous multi- furniture precast PSC single slab girder bridge of the present invention, the prestress is introduced to the primary steel wire 51 by a precast PSC single slab After the girder 40 is manufactured in the factory, the girder 40 is installed on the temporary support of the pier and the shift, which is the branch portion, and the girder corner angle is brushed at the connection portion between the girder 40 and the girder 40 of the branch portion. The steel plate 98 is welded and connected, and the temporary support 21 is removed while replacing it with a permanent support 97 to form a one-point continuous structure 54, and then between the girder 40 and the girder 40. After connecting the reinforcing bar of the rebar slip clip loop device 80 and pouring the non-contraction high-strength concrete 71, and then insert the secondary point PS steel wire 52 to introduce the tension force, then settled (53) Girder kite with complete girder connection Substantial continuous multi- furniture precast PSC single slab girder bridge, which is constructed to support the one-piece support structure 54 on the pier 14, which is the point portion, and to install the complete continuity bridge that connects the girder to be integrated. (30) was installed.
또한, 상기 교량(30)의 부재력에 대한 내하율을 추가확보할 필요가 있을 경우에는 별도의 3차연속 및 유지관리강선(55)을 설치하여 긴장 및 정착하도록 한다. In addition, when it is necessary to further secure the load-bearing rate for the member force of the bridge 30 to install a separate third continuous and maintenance steel wire (55) to tension and settle.
도 4는 본 고안의 연속다가구 프리캐스트 PSC단일슬래브거더교의 다른 실시예로서 지점부를 강결연결한 것을 보여주는 도면으로서, 1차 강선(51)에 프리스트레스를 도입하여 프리캐스트 PSC단일 슬래브거더(40)를 제작한 다음, 상기 거더(40)를 교각(14)의 브라켓(93) 및 교대(13)에 설치하고, 교각에 연이어서 설치된 거더와거더를 상호 연결하면서 교각과도 연결을 위하여 상기 거더의 코너앵글(78)과 하부받침덮개강판(92)을 강절용접하고, 거더철근(73, 79)과 교각 축방향철근(94)들을 연결부철근슬립그립루프장치(80)로 연결하면서 무수축고강도콘크리트(71)를 타설한 다음, 2차 지점부PS강선(52)을 삽입하여 긴장력을 도입한 후에 정착(53)하여 교각과 거더, 거더와 거더의 연결을 완전강결일체화한 교각강결연결연속다가구구조(90)로 한 연속교를 설치한 것이다. 4 is a view showing the rigid connection of the point portion as another embodiment of the continuous multi- furniture precast PSC single slab girder bridge of the present invention, the pre-cast PSC single slab girder 40 by introducing a prestress to the primary steel wire 51 After the fabrication, the girder 40 is installed on the bracket 93 and the shift 13 of the pier 14, and the girder and the girder installed in succession to the pier are interconnected with the pier for connection with the pier. Steel angle welding of the angle 78 and the lower support cover plate 92, and connecting the girder reinforcement (73, 79) and pier axial reinforcement (94) to the connection reinforcing bar slip grip loop device (80) without shrinkage high strength concrete ( 71) and then the secondary point PS steel wire (52) is inserted to introduce the tension force, and then settled (53) to fully connect the pier and the girder, and the connection between the girder and the girder. 90) installed a continuous bridge.
또한, 상기 교량(30)의 부재력에 대한 내하율을 추가확보할 필요가 있을 경우에는 별도의 3차연속 및 유지관리강선(55)을 설치하여 긴장 및 정착하도록 한다. In addition, when it is necessary to further secure the load-bearing rate for the member force of the bridge 30 to install a separate third continuous and maintenance steel wire (55) to tension and settle.
상기와 같이 거더와 거더를 상호 연결한 거더연결부(70)를 설치하고, 상기 거더연결부(70)와 교각(14)을 일체로 강결연결한 연속교는 부정정차수가 많아 교량에서 발생되는 모멘트의 크기를 감소시키는 경제적이면서 단면력이 강한 교량을 설치할 수 있는 장점이 있다. As described above, the girder connecting portion 70 is installed to interconnect the girder and the girder, and the continuous bridge in which the girder connecting portion 70 and the pier 14 are integrally rigidly connected has a large magnitude of moments generated in the bridge. There is an advantage to install an economical and strong cross-section bridge to reduce the.
도 5는 본 고안의 연속다가구 프리캐스트 PSC 단일슬래브거더교의 또 다른 실시예로서 거더의 일측지점부와 교대의 파라페트부를 강결연결한 것을 보여주는 도면으로서, 1차 강선(51)에 프리스트레스를 도입하여 프리캐스트 PSC 단일슬래브거더(40)를 제작한 다음, 상기 거더(40)를 교대의 브라켓(93)에 연결설치한 후에, 교대의 브라켓에 연결설치된 거더의 일측단부와 파라페트부(19)연결은 상기 거더(40)의 코너앵글(78)과 하부받침덮개강판(92)을 강결용접하고, 거더철근(73,79)과 교대 축방향철근(94)들을 연결부 철근슬립클립루프장치(80)로 연결하고, 무수축고강도콘크리트(71)를 타설한 다음, 2차지점부PS강선(52)을 삽입하여 긴장력을 도입한 후에 정착(53)하여 교대와 거더의 연결을 완전강결연결한 교대강결연결연속다가구구조(100)의 연속다가구 프리캐스트 PSC단일슬래브거더교(30)를 설치한 것이다. FIG. 5 is a view showing the rigid connection of one side point portion and an alternate parapet portion of a girder as another embodiment of the continuous multi-family precast PSC single slab girder bridge according to the present invention, by introducing prestress into the primary steel wire 51. After the precast PSC single slab girder 40 is manufactured, the girder 40 is connected to the alternating bracket 93, and then one side end of the girder connected to the alternating bracket and the parapet section 19 are connected. Reinforced welding the corner angle 78 and the lower support cover steel plate 92 of the girder 40, connecting the girder reinforcement (73, 79) and the alternating axial reinforcement (94) rebar slip clip loop device 80 Alternately solidified the connection between the alternating and girder by inserting the secondary point PS steel wire (52), and then introducing the tension force and then inserting the tension force (53). Continuous Multi-Furniture Precast of Connection Continuous Multi-Furniture Structure 100 PSC single slab girder bridge 30 is installed.
상기와 같이 거더(40)와 교대(13)의 파라페트부(19)와 상호 강결연결하도록 한 연속교는 부정정차수가 많아 교량에서 발생되는 모멘트의 크기를 감소시키는 경제적이면서 단면력이 강한 교량을 설치할 수 있는 장점이 있다. As described above, the continuous bridge that is rigidly connected to the parapet portion 19 of the girder 40 and the shift 13 has an indefinite number of irregular orders to install an economical and cross-sectional strong bridge that reduces the magnitude of moment generated in the bridge. There are advantages to it.
도 6(a)는 본 고안의 도 3, 4, 5의 중앙부 단면A-A를 보여주는 도면으로서, 상기 단면은 하부플랜지(62)와 복부(61) 및 3헌치단면의 상부플랜지 슬래브(57)로 구성되도록 한 것이다. Figure 6 (a) is a view showing a central cross section AA of Figures 3, 4, 5 of the present invention, the cross section is composed of a lower flange 62, the abdomen 61 and the upper flange slab 57 of the three haunch cross section. It was made possible.
특히 상부플랜지 슬래브의 하부단면형상은 3부분에서 단면이 변화되도록 하는 3헌치형태(59)로서 복부연결된 헌치는 고정으로 하고, 나머지 2개의 헌치로 선형변화에 따른 3차원좌표변화를 수용토록하여 어떠한 선형, 표고 및 사각에 따른 단면의 변화에도 적용할 수 있도록 하기 위함이며, 중앙부 단면의 PS 강선(51,55)이 하부플랜지에 집중되도록 한 것이다. In particular, the lower cross-sectional shape of the upper flange slab is a three-hundred form (59) that allows the cross-section to be changed in three parts, and the abdominal connected haunches are fixed, and the remaining two haunches allow three-dimensional coordinate changes due to the linear change. In order to be applicable to the change of the cross section according to the linear, elevation and square, the PS steel wire (51, 55) of the central section is to be concentrated on the lower flange.
도 6(b)는 본 고안의 도 3, 4, 5의 지점부 단면 B-B를 보여주는 도면으로서, 상기 단면은 상기 도 6(a)와 동일하나, 가로보(60)가 추가배치되는 것에서 차이가 있으며, 상기 단면에서의 2차지점부 PS강선(52,55)은 상부플랜지슬래브내에 균등배치한다. Figure 6 (b) is a view showing a cross-section BB of the point portion of Figures 3, 4, 5 of the present invention, the cross section is the same as Figure 6 (a), but there is a difference in that the cross beam 60 is additionally arranged The secondary point PS steel wires 52 and 55 in the cross section are equally arranged in the upper flange slab.
도 7은 본 고안의 프리캐스트 PSC단일슬래브거더를 교축방향으로 연이어서 설치하여 형성된 상기 거더와의 상부슬래브를 강결연결한 슬래브강결연결부(50)를 보여주는 도면이다. FIG. 7 is a view showing a slab hardening connection part 50 for tightly connecting an upper slab with the girder formed by successively installing a precast PSC single slab girder in the axial direction.
도 8은 도 7의 슬래브강결연결부를 상세히 보여주는 도면으로서, 교축직각방향으로 연이어서 설치된 거더(40)와 거더(40)의 상부플랜지슬래브의 상하부에서 연장설치된 인장 및 압축철근(73, 79)을 슬립클립루프철근(74)으로 상호 완전강결연결하고, 그 사이에 접합용보강철근(76)으로 수평구속하고, 상기 접합용보강철근(76)과 상기 인장 및 압축철근(79, 73)의 활동을 확실하게 구속하기 위하여, 상기 철근들(73,79,76)을 다수개의 슬립클립트러스철근(72)으로 상호 연결설치하도록 한 연결부철근슬립클립루프장치(80)를 설치한 후에, 양측에 설치된 슬래브의 양측단부 하부에 "??"자형의 코너앵글(78)을 설치하면서 코너앵글(78)의 일측부에는 단부절곡철근(75)을 거더내부에 각각 구속설치하고, 코너앵글(78)의 타측부에는 아연도강판을 인접하여 설치된 또 다른 코너앵글(78)에 얹혀져 강결하여 설치하여 인장철근겸용 및 거푸집(77)으로 이용한 다음, 상기 거더의 슬래브와 슬래브사이에 고강도 무수축콘크리트(71)를 타설하여 슬래브강결연결부(50)를 형성하도록 한다. FIG. 8 is a detailed view of the slab hardening connection of FIG. 7, wherein the girder 40 and the extension and compression reinforcing bars 73 and 79 extending from the upper and lower portions of the upper flange slab of the girder 40 are installed successively in the axial direction. And fully clipped to each other with a slip clip loop reinforcing bar 74, and horizontally bound with reinforcing reinforcing bars 76 in between, and of the reinforcing bar 76 for joining and the tension and compression reinforcing bars (79, 73) In order to reliably restrain the activity, after installing the connecting rebar slip clip loop device 80 for interconnecting the reinforcing bars 73, 79, and 76 with a plurality of slip clip truss bars 72, While installing a corner angle 78 having a “??” shape at both sides of the lower end of the installed slab, one side of the corner angle 78 is restrained and installed with the end bending bars 75 inside the girder, respectively, and the corner angle 78 Another nose installed adjacent to the galvanized steel sheet on the other side of the It is mounted on the angle 78 and is firmly installed to use as a tensile reinforcing bar and formwork 77, and then cast a high-strength non-concrete concrete 71 between the slab and the slab of the girder to form the slab steel connection portion 50. do.
도 9는 도 3의 1점받침지지연속구조와 거더연결부를 상세히 보여주는 도면으로서, 교각(14) 위에 연이어서 설치된 거더(40)와 거더(40)를 임시받침대에 거치한 다음, 상기 임시받침대 위에 설치된 거더(40)의 양측단부 하부에 코너앵글(78)을 설치하면서 코너앵글(78)의 일측부에는 단부절곡철근(75)을 거더(50)내부에 각각 설치하고, 코너앵글(78)의 하부에는 전단스터드볼트(96)가 부착된 솔(Sole)플레이트(99)를 용접(96)하고, 그 하부에는 영구받침(97)을 설치하면서 상기 임시받침대를 제거하여 상기 영구받침이 교각(14)에 설치되도록 하여 1점받침지지연속구조 (54)로 한 다음, 슬래브거더내의 인장 및 압축철근(79,73)을 거더사이의 연결부에서 서로 강결연결되도록 슬립을 방지하기 위하여 상기 철근의 단부를 슬립클립루프철근(74)으로 서로 중첩시켜 연결하고, 그 사이에 접합부보강철근(76)으로 인장 및 압축철근(73,79)을 수평구속하고, 보다 완전한 강결연결구조로 하기 위하여 상기 철근들(73,76,79)을 슬립클립트러스철근(72)으로 구속하여 연결부철근슬립클립루프장치(80)를 만든 다음 고강도 무수축콘크리트를 타설하여 지점부연결부 및 1점받침지지연속구조가 되도록 설치한다. 9 is a view showing in detail the one-point support continuous structure and the girder connection of Figure 3, the girder 40 and the girder 40 installed in succession on the pier 14 mounted on the temporary support, and then on the temporary support While installing corner angles 78 under both side ends of the installed girders 40, one end portion of the corner angles 78 is provided with end bending bars 75 inside the girders 50, respectively, and the corners of the corners 78 A sole 96 is attached to the lower portion of the sole plate 99 to which a shear stud bolt 96 is attached, and a lower portion of the lower portion is removed by installing the permanent portion 97. And the one-point supporting continuous structure (54), and then the ends of the reinforcing bars to prevent slipping so that the tension and compression bars (79, 73) in the slab girder are rigidly connected to each other at the connection between the girder. Slip clip loop reinforcing bars 74 are connected to each other, The reinforcing bars 73, 76, and 79 are slip clip truss 72 in order to horizontally constrain the tension and compression reinforcing bars 73 and 79 with the joint reinforcing bar 76 and to form a more complete connection structure. Constrained to make the reinforcing bar slip clip loop device 80, and then to install a high-strength non-concrete concrete so that the point connection and one point support continuous structure.
도 10은 본 고안의 연속다가구 프리캐스트 PSC단일슬래브거더의 거더 연결부와 지점부를 강결연결하는 교각강결연결연속다가구구조를 보여주는 도면으로서, 도 4의 거더(40)와 거더(40)를 일체화 연속시키는 거더연결부(70)와 상기 거더연결부(70)와 교각(14)을 상호 강결연결시키는 교각강결연결연속다가구구조(90)를 상세히 보여주는 것이다. 10 is a view showing a piercing steel connection continuous multi- furniture structure for rigidly connecting the girder connection portion and the branch portion of the continuous multi- furniture precast PSC single slab girder of the present invention, the girder 40 and the girder 40 of FIG. The girder connecting portion 70 and the girder connecting portion 70 and the pier 14 is shown in detail the pier steel connection continuous multi- furniture structure 90 to the rigid connection.
상기 거더연결부(70)는 교각(14)의 브라켓(93) 위에 거더(40)와 거더(40)가 서로 연이어서 설치된 사이에 상기 거더의 상하부플랜지에서 배근된 인장 및 압축철근(73,79)을 상호 연결설치하고, 상기 인장 및 압축철근(73,79)의 사이에 도 9와 동일한 연결부철근클립루프장치(80)를 상하로 설치한 다음 축방향철근(94)을 거더가 연이어서 설치된 사이의 공간에 걸쳐서 폭방향으로 절곡배근하되, 상기 절곡된 철근부분이 상기 인장철근(79)의 연결부철근슬립클립루프장치(80) 사이를 통과하도록 하고, 압축철근(73)이 횡단하는 거더와 교각이 접하는 부분에 전단연결스터드(95)로 활동을 억제시키고, 각 거더상에 배근된 수평전단철근(91)을 서로 중첩연결하면서 상기 거더의 양측단부 하부에 제작된 코너앵글(78)에는 상기 코너앵글(78)의 일측에서 거더(40)의 단부내로 단부절곡철근(75)을 설치한 다음, 상기 교각(14)의 상부이면서 상기 코너앵글(78)은 기 설치된 하부받침덮개강판(92)에 강결용접하여 일체화하도록 하고, 상기 거더연결부(70)에 고강도무수축콘크리트(71)를 타설하여 거더연결부(70)와 지점부연결부(90)에 의하여 거더(40)와 지점부인 교각(14)이 일체화 강결연결되도록 한 교각강결연결연속다가구구조(90)인 것이다. The girder connection portion 70 is a tensile and compressive reinforcement (73, 79) reinforcement in the upper and lower flanges of the girder between the girder 40 and the girder 40 are installed in succession on the bracket 93 of the piers (14) Between the tension and compression reinforcement (73,79) between the installation of the reinforcing bar reinforcing clip loop device 80 as shown in Figure 9 up and down, and then the axial reinforcement 94 is installed in succession It is bent in the width direction over the space of the, the bent portion of the reinforcing bar is passed between the connecting reinforcing bar slip clip loop device 80 of the tensile reinforcement (79), the compression reinforcement (73) transverse girder and pier The corner is restrained by the shear connection stud 95 at the contact portion, and the horizontal shear bars 91 arranged on each girder overlap each other, while the corner angle 78 formed at the lower end of both sides of the girder has the corner. Into the end of the girder 40 at one side of the angle 78 After installing the bending reinforcing bar 75, the corner angle 78 while the upper portion of the pier 14 is welded to the lower support cover steel plate 92 is installed to be integrally welded, high strength to the girder connecting portion 70 By piercing non-concrete concrete 71, the girder 40 and the pier 14 by the girder connecting portion 70 and the branch connecting portion 90 are integrally rigidly connected to the bridge piercing connection continuous multi- furniture structure (90) will be.
도 11은 본 고안의 연속다가구 프리캐스트 PSC단일슬래브거더와 일측지점부인 교대의 파라페트부(19)를 강결연결한 교대강결연결연속다가구구조를 보여주는 도면으로서, 도 5의 거더(50)와 교대(13)의 파라페트부(19)를 상호 강결연결시키는 교대강결연속다가구 구조부(100)를 상세히 보여주는 것이다. FIG. 11 is a view illustrating an alternate steel fastening connection continuous multi-furniture structure in which a continuous multi-furniture precast PSC single slab girder and an alternate parapet part 19 which is one side point part are rigidly connected according to the present invention, and alternate with the girder 50 of FIG. 5. (13) shows the details of the alternating steel-coupling continuous multi- furniture structure 100 for rigidly connecting the parapet portion 19 of (13).
상기 교대연결부(100)는 교대(13)의 파라페트부(19)와 거더(40)의 일측단부를 일체화 강결연결시키기 위하여 설치한 것을 보여주는 것이다. The alternating connection part 100 shows that the parapet part 19 and the one end of the girder 40 of the alternator 13 are integrally and rigidly connected to each other.
프리캐스트 PSC단일슬래브거더(40)를 교대 브라켓(93)에 거치한 후에 거더(40)의 일측 단부의 하면의 단부절곡철근(75)이 부착된 코너앵글(78)과 상기 브라켓(93)상에 부착된 하부받침덮개강판(92)과 용접, 강결한 후에, 거더에 연장배근된 인장 및 압축철근(73,79)과 교대의 축방향철근(91)은 도 9와 동일한 매카니즘으로 연결부철근슬립클립루프장치(80)를 설치한 다음, 수평전단철근(91)을 축방향철근(94)에 연결시키고, 파라페트부의 중앙에는 전단연결스터드(95)을 배치한 다음, 고강도 무수축콘크리트(71)을 타설하고, 교대와 거더를 일체강결연결토록한 교대강결연결연속다가구구조(100)를 설치하는 것이다. After mounting the precast PSC single slab girder 40 to the shift bracket 93, the corner angle 78 to which the end bending bar 75 of the lower surface of one end of the girder 40 is attached and on the bracket 93 is mounted. After welding and stiffening with the lower support cover steel plate 92 attached thereto, the tensile and compressive rebars 73,79 and alternating axial rebars 91 extending to the girder are connected to the rebar with the same mechanism as shown in FIG. After the clip loop device 80 is installed, the horizontal shear reinforcement 91 is connected to the axial reinforcement 94, the shear connection stud 95 is disposed at the center of the parapet section, and the high strength non-contraction concrete 71 is provided. ) And to install the alternating steel connection continuous multi-furniture structure (100) to allow the integral steel gilt connection with the shift.
도 12는 본 고안의 프리캐스트 PSC단일슬래브거더의 단부에 정착장치를 설치하기 위하여 홈부가 형성된 것을 보여주는 도면으로서, 거더(40)의 단부에 쐐기형의 홈부(58)를 형성하고 상기 홈부(58)내에 정착장치(53)를 설치하여 강선이 정착고정되도록 하면서 단부에 형성된 홈부가 전단키역할을 하면서 타 콘크리트타설시 부착능력향상과 활동방지를 하기 위하여 일체화가 보다 강하게 이루어지도록 하기 위함이다. 12 is a view showing that a groove is formed in order to install a fixing device at the end of the precast PSC single slab girder of the present invention, wherein the groove 58 is formed at the end of the girder 40 and the groove 58 is formed. In order to install the fixing device 53 in the) to secure the fixing of the steel wire while the groove portion formed at the end serves as a shear key, so that the integration is made stronger in order to improve the adhesion capacity and prevent the activity during other concrete placing.
도 13(a)(b)는 본 고안의 연속다가구 프리캐스트 PSC단일슬래브거더교의 지점부연결부(70)에 배치되는 2차지점부연속강선(52)과 상기 강선을 슬래브하면에 설치된 슬래브하면정착블럭(85)에 연결설치한 것을 보여주는 도면으로서, Figure 13 (a) (b) is the secondary point portion continuous steel wire 52 and the slab surface is disposed on the lower surface of the slab disposed on the point connection portion 70 of the continuous multi- furniture precast PSC single slab girder bridge of the present invention As a figure showing the connection to the block 85,
도 (a)는 2차지점부연속강선(52)이 상부플랜지 슬래브(57)를 통과하고, 슬래브하면에 직접설치되는 슬래브하면정착블럭(85)과 정착장치(53)를 설치하여 상기 강선을 연결정착한 것이며, (A) shows that the secondary wire portion continuous steel wire 52 passes through the upper flange slab 57, and the slab bottom fixing block 85 and the fixing device 53 are installed directly on the lower surface of the slab to install the steel wire. The connection is established,
도 (b)는 도 13(a)의 단면 A와 단면 B를 보여주는 것으로서, 단면 A는 슬래브하면정착블럭이 횡단면상에 설치된 위치와 상기 블록에 설치된 정착장치를 보여주고, 단면 B는 지점부 구간에서 상부플랜지의 슬래브내에 설치된 PS강선을 이용하는 것을 보여주고 있다. (B) shows the cross-section A and cross-section B of Fig. 13 (a), the cross-section A shows the position where the fixing block is installed on the cross section when the slab and the fixing device installed in the block, cross-section B is the point section Shows the use of PS steel wires installed in the slab of the upper flange.
도 14(a)(b)는 본 고안의 프리캐스트 PSC단일슬래브거더의 저항단면력을 증대시키기 위하여 지점부의 하부플랜지의 폭을 증가시키거나, 복부높이를 증가시킨 변단면의 프리캐스트 PSC단일슬래브거더를 보여주는 도면으로서, 지점부에는 발생모멘트 특성상 상연슬래브, 즉 인장응력이 부담하는 지역으로 위치하여 상부슬래브에 지점부연속강선이 배치되는바, 이에 의한 편심모멘트를 크게하기 위하여 단면의 증립축이 하부플랜지로 이동시킬 경우도 있을 수 있다. 이 경우를 위하여 하부플랜지 단면은 변단면이 되도록 도 (a)와 같이 당초하부플랜지의 폭(41)에서 양측으로 일정길이 연장시킨 증가된 하부플랜지폭(42)만큼 키워서 전체 단면중 지점부 구간의 하부플랜지폭이 증가되도록 하거나 또는 도 (b)와 같이 당초 거더의 복부높이(43)에서 일정한 길이만큼 증가된 복부높이(44)를 증가시켜 전체단면중 지점부 구간의 복부높이를 증가시키도록 단면을 증가시켜 거더의 저항단면력을 증강시키도록 한 것이다. Figure 14 (a) (b) is the precast PSC single slab girder of the edge of the cross section to increase the width of the lower flange of the point portion, or to increase the abdominal height in order to increase the resistance cross-sectional force of the precast PSC single slab girder of the present invention As shown in the drawing, in the point part, the continuous slab is located in the area of load-bearing slab due to the characteristics of the generated moment, that is, the point continuous steel wire is disposed on the upper slab, so that the enlarged axis of the cross section is lowered to increase the eccentric moment. There may be cases where it is moved to the flange. For this case, the lower flange cross-section is increased by an increased lower flange width 42 extending a certain length from the width 41 of the lower lower flange as shown in FIG. Cross section to increase the abdominal height of the point section of the overall section by increasing the lower flange width or by increasing the abdominal height 44, which is increased by a certain length from the abdominal height 43 of the original girder as shown in FIG. It is to increase the resistance cross section of the girder.
도 15는 본 고안의 연속다가구 프리캐스트 PSC단일슬래브거더교를 제작할 때 교량의 선형, 편구배, 표고에 따라 변화되는 단면에 대해 거푸집이 전용되도록 일정 높이는 고정거푸집으로 정형화하고, 단면변화구간은 단면조정힌지거푸집으로 각각 설치하여 프리캐스트 PSC단일슬래브거더를 제작한 것을 보여주는 도면으로서, 교량은 평면선형, 종단선형, 편구배 및 사각방향에 따라 단면변화를 일으키는데, 이 변화하는 단면을 제작하기 위한 거푸집(110)은 전용성과 표준화가 되어야만 경제성을 확보하는바, 이를 위해서 상기 거푸집을 슬래브거더고정거푸집(120)과 단면조정힌지거푸집(115)으로 구성하도록 하고, 상기 슬래브거더고정거푸집(120)은 하부플랜지거푸집(129), 복부거푸집(128) 및 상부플랜지슬래브(57)의 하면거푸집(122) 중 복부와 연결된 일부구간으로 구성하여 각 경간마다 표준단면으로 하여 전용횟수를 대폭늘려 경제성을 확보하도록 하고, 상기에서 언급한 단면변화를 수용하고 전용성을 높이기 위해 상부플랜지하면거푸집(122)의 나머지 구간을 2개의 힌지(123)와 잭(126)이 부착된 지지대(124)를 설치하여, 단면변화에 대해서 잭(126)의 스트로크를 조정하고, 그 조정된 결과에 따라 상하로 자유롭게 2개의 힌지(123)에 의하여 변형되도록 구성된 단면조정힌지거푸집(115)으로 하며, 상기 상부플랜지하면거푸집(122)의 양측단부에 바닥판 및 상부플랜지측면거푸집(129)을 설치한 후에 프리캐스트 PSC단일슬래브거더(40)를 형성하기 위하여 콘크리트를 타설하여 형성하도록 한다. Figure 15 is to form a fixed height to form a dedicated die for the cross-section changed according to the linear, single-gradient, elevation of the bridge when manufacturing a continuous multi- furniture precast PSC single slab girder bridge of the present invention, the cross-sectional change section is adjusted The figure shows the fabrication of precast PSC single slab girder by installing each hinge formwork, and the bridge causes cross-sectional change along the plane, longitudinal, single-gradient and quadrangle directions. 110) to ensure the economics only to be dedicated and standardized, for this purpose, the formwork to be composed of the slab girder fixed formwork 120 and the cross-section hinge hinge formwork 115, the slab girder fixed formwork 120 is the lower flange Some spheres connected to the abdomen of the formwork 129, the lower formwork 122 of the abdominal formwork 128 and the upper flange slab (57) In order to secure economic feasibility by greatly increasing the number of times by using a standard section for each span, and to accommodate the above-mentioned cross-sectional change and increase the degree of availability, the remaining sections of the formwork 122 are hinged by two hinges 123. ) And the support 124 to which the jack 126 is attached to adjust the stroke of the jack 126 for the cross-sectional change, and to be deformed by the two hinges 123 freely up and down according to the adjusted result. In order to form the precast PSC single slab girder 40 after the bottom plate and the upper flange side formwork 129 are installed at both ends of the upper flange 122 when the upper flange is configured. It is to be formed by pouring concrete.
도 16은 본 고안의 연속다가구 프리캐스트 PSC단일슬래브거더교의 제작을 거푸집에 의하여 상기 도 15의 교축방향으로 설치하는 것과 교축방향으로 설치된 세그먼트마다 일정한 간격으로 힌지로 연결하여 단면변화의 조정이 용이하게 설치한 것을 보여주는 도면으로서, 거더(40)를 형성하는 상하부플랜지 상하부면과 복부면에 접하게 상부플랜지 하면거푸집(122), 하부플랜지외측거푸집(127)과 복부거푸집(128)을 설치하고, 상부플랜지 하부면에 설치되는 상부플랜지하면거푸집(122)에는 다수개의 힌지(123)를 설치하여 상부플랜지의 하부면의 변화에 따라 거푸집이 변화되도록 하기 위하여 힌지(123)를 절점으로 이용하여 상기 상부플랜지하면거푸집(122)을 설치하고, 상기 상부플랜지하면거푸집(122)의 하부면과 하부플랜지 상부면에 설치된 하부플랜지외측거푸집(127)의 상부에 잭(126)이 부착된 지지대(124)를 다수개 설치하면서 상기 상부플랜지하면거푸집(122)의 다양한 위치변동을 상기 잭(126)이 작동하므로서 지지대(124)가 상하로 이동하여 상기 상부플랜지하면거푸집(122)을 지지하도록 하면서, 상기 상부플랜지하면거푸집(122)의 일측단부에 바닥판 및 상부플랜지 측면거푸집(129)을 설치한 후에 바닥판 및 상부플랜지(121)를 형성하는 도 15의 교축방향의 종단면도를 나타내는 것과 교축방향에 따라 단면변화에 의한 조정이 용이하도록 고정 및 단면조정힌지거푸집(110)의 수직방향으로 세그먼트마다 일정한 간격을 두고 힌지를 설치하여 교축방향단변변화에도 자유롭게 조정셋팅하여 콘크리트를 타설하여 형성하도록 한다. Figure 16 is to install the continuous multi- furniture precast PSC single slab girder bridge of the present invention by the formwork in the axial direction of Figure 15 by connecting the hinges at regular intervals for each segment installed in the axial direction to easily adjust the cross-sectional change As an illustration showing the installation, the upper and lower flanges forming the girder 40 and the upper flange in contact with the ventral surface, the bottom flange 122, the lower flange outer form 127 and the abdomen form 128 are installed, the upper flange If the upper flange to be installed on the lower surface die 122 to install a plurality of hinges 123 to use the hinge 123 as a node to change the form according to the change of the lower surface of the upper flange when the upper flange When the form 122 is installed and the upper flange, the lower flange outer side installed on the lower surface and the lower flange upper surface of the form 122 If the upper flange while installing a plurality of support 124 with the jack 126 attached to the upper portion of the house 127, the support 124 is moved up and down as the jack 126 operates various position variations of the die 122 While moving to the upper flange to support the die 122, while the upper flange, the bottom plate and the upper flange 121 after installing the bottom plate and the upper flange side die 129 at one end of the die 122 Fig. 15 shows a longitudinal cross-sectional view of the axial direction and forms a hinge at regular intervals for each segment in the vertical direction of the fixed and cross-sectional adjustment hinge dies 110 to facilitate adjustment by cross-sectional change along the axial direction. Freely adjust and set the change of direction short side to form concrete.
도 17은 도 15와 도 16의 바닥판 및 상부플랜지측면거푸집을 상세히 보여주는 도면으로서, 상부플랜지 슬래브하부면에 접하게 상부플랜지 하면거푸집(122)을 설치하고, 상부플랜지 슬래브하부면에 설치되는 상부플랜지하면거푸집(122)에는 다수개의 힌지(123)를 설치하여 프리캐스트 PSC단일슬래브거더의 단면변화에 따라 거푸집이 변화되도록 하기 위하여 힌지를 절점으로 이용하여 상기 상부플랜지하면거푸집(122)을 설치하고, 상기 거푸집(122)의 단면조정이 가능하도록 잭이 부착된 지지대(124)로 지지하는 것이며, 상기 상부플랜지하면거푸집(122)의 양측단부에 설치되는 바닥판 및 상부플랜지 측면거푸집(129)에 구멍(131)을 형성하여 상부플랜지에서 연장형성되는 철근을 관통삽입할 수 있도록 하고, 상기 바닥판 및 상부플랜지측면거푸집(129)의 내측면에 요철형 부직포(130)를 설치한 다음 바닥판 및 상부플랜지(121)를 형성하기 위하여 콘크리트를 타설하여 상부플랜지단부에 요철부가 형성되도록 하여 추후에 거더의 슬래브와 거더의 슬래브를 연결할때 전단키를 형성하여 상기 형성된 요철부에 의하여 보다강하게 연결되도록 하기 위함이다. 17 is a view showing in detail the bottom plate and the upper flange side die of Figures 15 and 16, the upper flange to form a lower surface 122 in contact with the lower flange of the upper flange, the upper flange installed on the lower surface of the upper slab In order to form a plurality of hinges 123 on the lower surface die 122 so that the formwork changes according to the cross-sectional change of the precast PSC single slab girder, the upper flange is installed by using the hinge as a node, It is supported by the support 124 attached to the jack to enable the cross-section adjustment of the formwork 122, the upper flange is a hole in the bottom plate and the upper flange side formwork 129 is installed on both side ends of the formwork 122 131 is formed so as to penetrate the reinforcing bar extending from the upper flange, the inner side of the bottom plate and the upper flange side formwork 129 After installing the iron type nonwoven fabric 130, and then to form the bottom plate and the upper flange 121 to form an uneven portion in the upper flange end to form a shear key when connecting the slab of the girder and the slab of the girder later This is to be connected more strongly by the formed concave-convex portion.
도 18(a)(b)는 본 고안의 연속다가구 프리캐스트 PSC단일슬래브거더교가 사각에 설치되는 경우, 상기 교량의 제작을 위하여 설치되는 거푸집의 직선형과 사각별표준거푸집설치형상을 각각 보여주는 도면으로서, 도 (a)는 사각에 배치된 프리캐스트 PSC단일슬래브거더의 제작을 위하여 직선형 표준거푸집(140)의 교축직각방향(142)과 교축방향(141)으로 구성된 표준화된 고정형 거푸집으로 제작하고, 상기 거더의 단부는 사각에 따라 각각의 위치마다 단면이 변화하게 되므로, 상기 변화되는 단부단면을 제작하기 위하여 상하변(151,153)과 빗변(152)으로 구성된 사다리꼴형태의 사각별표준거푸집(150)을 제작한 것이다. Figure 18 (a) (b) is a view showing the straight form of the formwork installed for the fabrication of the bridge and the standard formwork for each square, when the continuous multi- furniture precast PSC single slab girder bridge of the present invention is installed in a square; , (A) is made of a standard fixed formwork consisting of the axial direction perpendicular 142 and the axial direction 141 of the straight standard formwork 140 for the production of precast PSC single slab girder arranged in a square, the Since the end of the girder is changed in cross-section at each position according to the square, to produce a trapezoidal quadrangular standard formwork 150 consisting of upper and lower sides (151,153) and hypotenuse 152 to produce the changed end cross-section. It is.
도 (b)는 상기 사각별표준거푸집(150)과 직선형표준거푸집(140)을 거더(40)를 제작하기 위하여 설치할 때 상기 사각별표준거푸집과 직선형표준거푸집을 착탈식클램프(143)로 상호연결하여 설치하도록 한 것이다. (B) is the rectangular standard formwork 150 and the linear standard formwork 140, when installed to manufacture the girder 40, the rectangular standard formwork and the linear standard formwork by interconnecting with a removable clamp 143 It was installed.
도 19는 본 고안의 연속다가구 프리캐스트 PSC단일슬래브거더교의 직선 및 곡선부 및 사각의 프리캐스트 PSC단일슬래브거더를 제작하고, 상기 거더를 일체로 연결하기 위하여 변화하는 단면의 각 지점의 표고 및 좌표를 각 거더별 상호연결될 위치에 해당하는 코드를 각각 부여하여 사전에 입력된 교량설치프로그램에 상기 각각의 코드를 입력하여 상기 교량 각각의 위치에 설치되는 거푸집의 위치 및 표고를 산출하여 이를 거푸집에 적용하여 거더를 제작하는 것을 보여주는 도면이다. 19 is a straight and curved portion of the continuous multi- furniture precast PSC single slab girder bridge and square precast PSC single slab girder of the present invention, and the elevation and coordinates of each point of the cross section to change in order to connect the girder integrally The code is given to each of the girder corresponding to the position to be interconnected by inputting the respective codes to the bridge installation program previously input to calculate the position and elevation of the formwork installed in each position of the bridge and apply it to the formwork This is a drawing showing the making of girder.
상기 도 15내지 도 18의 방법의 고정 및 단면조정힌지거푸집(110)과 직선형 및 사각별 표준거푸집(140, 150)을 이용하여 거더(40)를 제작하여 도 3내지 도 5의 연속다가구 프리캐스트 PSC단일슬래브거더교(30)를 설치할 때 직선부 및 곡선부의 상호연결된 각각의 위치별로 부여된 각각의 코드에 해당하는 표고 및 위치좌표(180)등의 3차원제원을 컴퓨터(150)에 미리 입력된 교량설치프로그램에 의해 계산하고, 그 결과를 현장에서 측량(170)으로 정밀하게 셋팅되도록 상기 위치조정거푸집(110)에 설치된 잭(126)을 제어하는 유압잭(미도시)에 연결하여 각각의 위치에 해당하는 높이등에 맞도록 잭을 가동시켜 거푸집을 설치하도록 하기 위한 것이다. The continuous multi- furniture precast of FIGS. 3 to 5 is manufactured by manufacturing the girder 40 using the fixed and cross-section hinge dies 110 and the linear and rectangular standard dies 140 and 150 of the method of FIGS. 15 to 18. When the PSC single slab girder bridge 30 is installed, a three-dimensional specification such as elevation and position coordinates 180 corresponding to each code given to each interconnected position of the straight and curved portions is input to the computer 150 in advance. Calculated by the bridge installation program, the result is connected to a hydraulic jack (not shown) to control the jack 126 installed in the positioning die 110 to be precisely set to the surveying 170 in the field at each position It is intended to install the formwork by operating the jack to the corresponding height.
본 고안은 종래의 빔을 프리스트레스된 고강도 콘크리트로 제작장에서 제작하고, 그 위에 현장타설콘크리트슬래브를 타설하여 합성형교를 설치하므로서, 제작상 차이에 의한 일체단면의 신뢰성부족, 각 공종별 시공업체상이에 의한 품질 및 내구성 저하와 공기증가등의 문제점을 대폭개선하기 위하여 상기 빔과 슬래브를 단일 PSC슬래브거더로 제작하여 품질과 균질성, 공기단축, 전단연결재등 재료감소로 인한 경제적이고 내구성있는 구조를 갖을 수 있으며, 종래에는 단순보로 설치함에 따른 신축이음증가로 주행성 결여등을 극복하기 위하여 지점부 바닥판을 교축방향으로 철근보강으로 연결하든지, 상기 방법을 겸용하면서 거더를 2차강선으로 연결하였으나 실질적인 연속교가 아니고 연결형으로 전부재력을 부담하지 못해 지점부 바닥판에 인장균열발생과 복부고 상승등에 의한 경제적인 단면추구 곤란과 복부교 증가로 현장적용성이 결여되는 부분등을 개선하기 위하여 교대와 교각의 지지연결을 1점받침으로 지지하거나 거더와 상기 구조를 강결시키고 2차연속강선을 상기 단일 PSC 슬래브거더의 슬래브상에 균등하게 연속긴장배치하므로서 단일연속다가구 교량으로 구축하여 모멘트 재분배 효과에 의한 보다 높은 경제적인 단면과 부정정차수가 높아져 붕괴경로가 많아 연성이 높은 구조계로 형성하여 안전성이 아주 높은 구조를 확보하며, 상기 거더연결부 및 거더와 교대, 교각 연결부의 일체성과 연속성을 높이기 위하여 2차연속강선을 단일거더의 슬래브에 균등배치할뿐만 아니라 거더를 임시지지하는 곳에 고정된 브라켓강판과 거더의 코너앵글을 강절용접하고, 직각의 인장철근을 활동방지를 위하여 연결부보다 높여 안정성이 높은 구조를 확보하도록 하고, 상기 PSC 단일슬래브거더의 단면을 제작하기 위한 거푸집의 전용성을 높이기 위하여 일정단면을 고정거푸집으로 하고 단면이 변화하는 부분에는 거푸집에 힌지와 잭이부착된 지지대로 연결하여 잭스트로크 조정으로 상하연동이 자유롭게 하면서 직선형 구간과 사각 구간별로 표준화하여 거푸집의 전용성을 높여 보다 효율적이면서 경제적이되도록 하고, 상기 PSC 단일 슬래브거더의 연결성의 선형유지가 이루어지도록 각 거더의 상호 위치별로 코드를 부여 위치좌표, 표고등의 3차원 단면을 컴퓨터의 프로그램으로 처리하여 현장측량에 적용하므로서 아주 높은 연결선형이 유지되는 교량을 제작하고 시공하는 방법인 것이다. The present invention is to manufacture the conventional beam in the workshop made of pre-stressed high-strength concrete, and to install a composite bridge by placing a cast-in-place concrete slab thereon, the lack of reliability of the integrated cross-section due to the manufacturing differences, the construction companies for each type of construction In order to drastically improve the problems such as deterioration of quality and durability and increase of air, the beam and slab are manufactured as a single PSC slab girder, which can have an economical and durable structure due to quality and homogeneity, air shortening, and shear connection materials. In the related art, in order to overcome the lack of driving due to the increase in expansion joints due to the installation of a simple beam, the bottom plate of the branch part is connected with reinforcement in the axial direction, or the girder is connected with the secondary steel wire while using the above method. It is not a bridge but is a connection type. In order to improve the economical cross-section difficulty caused by heat generation and abdominal height rise and the lack of field applicability due to the increase of abdominal bridge, the support connection of the shift and piers is supported by one point support or the girders and the above structure are strengthened. The secondary continuous steel is evenly placed on the slab of the single PSC slab girder and constructed as a single continuous multi-furniture bridge, so that the higher economic cross-section due to the moment redistribution effect and the irregularity order are higher, resulting in more collapse paths. In order to secure the structure with very high safety, and to improve the integrity and continuity of the girder connection part and the girder alternating and pier connection parts, the secondary continuous steel wire is not only equally arranged on the slab of the single girder, but also temporarily supporting the girder. Weld-weld the corner angle of fixed bracket steel plate and girder, and apply right angled reinforcing bar In order to prevent the structure to be higher than the connection to ensure a high stability, in order to increase the formability of the formwork for producing the cross section of the PSC single slab girder fixed section to form a fixed die and hinges and jacks on the form change section Connected with the attached support, freeing up and down interlocking by adjusting jack stroke, standardizing by linear section and rectangular section to increase formability, making it more efficient and economical, and maintaining linearity of connection of the PSC single slab girder. It is a method of manufacturing and constructing bridges that maintain very high connection linearity by applying codes to each position of each girder and applying them to site surveys by processing three-dimensional sections such as position coordinates and elevations using computer programs.
도 1은 종래기술인 프리캐스트 PSC빔과 현장타설철근콘크리트 바닥판으로 구성된 합성단면을 지점부에는 2점지지구조로 지지하고 지점바닥판은 철근으로 연결한 단순 PSC 합성형교를 연결한 것을 보여주는 도면. 1 is a view showing a composite cross-section consisting of a precast PSC beam and a cast-in-place concrete bottom plate of the prior art connected to a simple PSC composite bridge connected to the point portion by a two-point supporting structure and the point bottom plate connected by reinforcing bars.
도 2는 또 다른 종래기술로서 프리캐스트 PSC빔과 현장타설철근콘크리트 바닥판으로 구성된 합성단면으로 하고, 지점부에는 2점지지구조로 지지하고 지점부의 거더를 PSC 강선으로 연결하고 지점부와 바닥판은 철근으로 연결한 단순 IPC 합성형교를 연결형으로 보여주는 도면. Figure 2 is a conventional cross-sectional view consisting of a precast PSC beam and cast-in-place reinforced concrete floor plate, and supported by a two-point support structure to the point portion, connecting the girders of the branch portion with a PSC steel wire, and the branch portion and the bottom plate Is a drawing showing a simple IPC composite bridge connected by reinforcing bars.
도 3은 본 고안의 연속다가구 프리캐스트 PSC단일슬래브거더교를 1점받침으로 지지하고, 2차연속강선이 지점슬래브를 연속긴장하여 연속교로 설치된 것을 보여주는 도면. 3 is a view showing that the continuous multi- furniture precast PSC single slab girder bridge of the present invention is supported by one point support, and the secondary continuous steel is installed as a continuous bridge by continuously tensioning the point slab.
도 4는 본 고안의 연속다가구 프리캐스트 PSC 단일슬래브거더교의 다른 실시예로서 지점부를 강결연결한 연속교를 보여주는 도면. 4 is a view showing a continuous bridge rigidly connected to a branch as another embodiment of the continuous multi- furniture precast PSC single slab girder bridge of the present invention.
도 5는 본 고안의 연속다가구 프리캐스트 PSC 단일슬래브거더교의 또 다른 실시예로서 일측 지점부인 거더와 벽체부를 강결연결한 것을 보여주는 도면. 5 is a view showing the rigid connection between the girder and the wall portion of one point as another embodiment of the continuous multi- furniture precast PSC single slab girder bridge of the present invention.
도 6a는 본 고안의 도3, 4, 5의 중앙부 단면과 PS강선배치를 나타낸 단면을 보여주는 도면. Figure 6a is a view showing a cross-section showing the central section and PS steel wire arrangement of Figures 3, 4, 5 of the present invention.
도 6b는 본 고안의 도3, 4, 5의 지점부 단면과 PS 강선배치를 나타낸 단면 B-B를 보여주는 도면. Figure 6b is a view showing a cross-section B-B showing the point cross section and PS steel wire arrangement of Figures 3, 4, 5 of the present invention.
도 7은 본 고안의 프리캐스트 PSC단일슬래브거더의 횡방향배치와 그의 연결부를 보여주는 도면. Figure 7 is a view showing the transverse arrangement of the precast PSC single slab girder of the present invention and its connections.
도 8은 본 고안의 프리캐스트 PSC단일슬래브거더를 횡방향으로 서로 연결하는 슬래브연결부를 보여주는 도면. 8 is a view showing a slab connection for connecting the precast PSC single slab girder of the present invention in the transverse direction.
도 9는 본 고안의 연속다가구 프리캐스트 PSC 단일슬래브거더교의 거더연결부와 받침으로 설치된 1점지지구를 보여주는 도면. 9 is a view showing a one-point support installed by the girder connection portion and the support of the continuous multi- furniture precast PSC single slab girder bridge of the present invention.
도 10은 본 고안의 프리캐스트 PSC 단일슬래브거더의 거더연결부와 교각을 강결연결한 교각강결연결연속다가구구조를 보여주는 도면. 10 is a view showing the pier steel fastening connection continuous multi- furniture structure of the girder connection and the pier of the precast PSC single slab girder of the present invention.
도 11은 본 고안의 프리캐스트 PSC 단일슬래브거더의 거더연결부와 교대의 파라페트부를 강결연결한 교대강결연결연속다가구구조를 보여주는 도면. 11 is a view showing an alternating steel fastening connection continuous multi- furniture structure of the precast PSC single slab girder of the present invention and the rigid connection of the girder connection portion and the alternate parapet portion.
도 12는 본 고안의 프리캐스트 PSC 단일슬래브거더의 단부에 정착장치를 이용하여 홈부를 형성하여 전단키를 보여주는 도면. 12 is a view showing a shear key by forming a groove portion using a fixing device at the end of the precast PSC single slab girder of the present invention.
도 13(a)는 본 고안의 연속다가구 프리캐스트 PSC 단일 슬래브거더교의 지점부에 배치된 2차지점부연속강선과 이를 슬래브하면에 정착한 것을 보여주는 도면. Figure 13 (a) is a view showing that the secondary point portion continuous steel wire disposed on the point portion of the continuous multi- furniture precast PSC single slab girder bridge of the present invention and fixed to the bottom surface of the slab.
도 13(b)는 본 고안의 도 13(a)의 단면 A와 단면B를 보여주는 도면. Figure 13 (b) is a view showing a cross section A and cross section B of Figure 13 (a) of the present invention.
도 14(a)(b)는 본 고안의 프리캐스트 PSC단일슬래브거더의 단면력을 증대시키기 위하여 하부플랜지의 폭을 증가시키거나 복부높이를 증가시킨 변단면을 보여주는 도면. Figure 14 (a) (b) is a view showing a cross-sectional side to increase the width of the lower flange or to increase the abdominal height in order to increase the cross-sectional force of the precast PSC single slab girder of the present invention.
도 15는 본 고안의 연속다가구 프리캐스트 PSC단일슬래브거더교를 제작할 때 교량의 평면 및 종단선형이 곡선에 따른 단면변화가 용이하고 표준화된 고정단면이 되도록 위치조정이 용이한 고정과 힌지거푸집을 보여주는 도면. 15 is a view showing the fastening and hinge formwork easy to adjust the position so that the cross-section of the bridge is easy to change the cross section according to the curve and the standardized fixed section when manufacturing the continuous multi- furniture precast PSC single slab girder bridge of the present invention .
도 16은 도 15의 거푸집 종단면도를 보여주고, 곡선부분에 설치되는 프리캐스트 PSC단일슬래브거더를 제작할 때 위치조정거푸집을 설치한 것을 보여주는 도면. Figure 16 shows the formwork longitudinal cross-sectional view of Figure 15, showing the installation of the positioning dies when manufacturing the precast PSC single slab girder installed in the curved portion.
도 17은 도 15, 도 16의 슬래브바닥판 단면변화에 조정이 용이하도록 힌지가 설치된 거푸집과 바닥판 측면의 거푸집을 상세히 보여주는 도면. 17 is a view showing in detail the formwork of the hinge and the formwork is installed in the hinge hinge so that the slab bottom plate cross-sectional changes of Figure 15, Figure 16 in detail.
도 18(a)는 본 고안의 연속다가구 프리캐스트 PSC단일슬래브거더교가 사각으로 설치되는 경우 직선 및 사각부분 및 표준형 거푸집을 보여주는 도면. Figure 18 (a) is a view showing a straight and square parts and standard formwork when the continuous multi- furniture precast PSC single slab girder bridge of the present invention is installed in a square.
도 18(b)는 도 18(a)의 직선표준형거푸집과 사각별표준거푸집을 서로연결 및 해체가 용이하도록 착탈식클램프가 설치된 것을 보여주는 도면. Figure 18 (b) is a view showing that the removable clamp is installed to facilitate the connection and disassembly of the linear standard formwork and the square standard formwork of Figure 18 (a) with each other.
도 19는 본 고안의 연속다가구 프리캐스트 PSC단일슬래브거더교의 직선 및 곡선부의 프리캐스트 PSC단일슬래브거더를 제작하기 위하여, 각 지점의 표고 및 좌표를 사전에 컴퓨터에 입력된 교량설치프로그램에 입력 및 계산하여 교량 각각의 위치에 설치되는 거푸집의 위치 및 표고를 산출하여 이를 제작장의 거푸집에 연결하여 상기 거푸집을 자동제어하여 프리캐스트 PSC 단일슬래브거더를 정밀제작하는 것을 보여주는 도면. Figure 19 is to input and calculate the elevation and coordinates of each point in the bridge installation program that is input to the computer in advance in order to fabricate the precast PSC single slab girder of the straight and curved portion of the continuous multi- furniture precast PSC single slab girder bridge of the present invention Drawing to calculate the position and elevation of the formwork is installed at each position of the bridge by connecting it to the formwork of the production site to show that the precision control of the precast PSC single slab girder by automatically controlling the formwork.
<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>
10 ; PSC 합성형교 11 ; PS 강선 10; PSC composite bridge 11; PS liner
12 ; 프리캐스트 PSC빔 13 ; 교대 12; Precast PSC beam 13; rotation
14 ; 교각 15 ; 지점부 14; Pier 15; Branch office
16 ; 받침 17 ; 현장타설철근콘크리트바닥판 16; Base 17; Cast-in-place reinforced concrete floor plate
18 ; 지점부 바닥판 보강철근 19 ; 파라페트부 18; Branch bottom plate reinforcement 19; Parapet
20 ; IPC 합성형교 21 ; 임시받침 20; IPC composite bridge 21; Provisional
22 ; 빔연속PS 강선 23 ; 전단연결재 22; Beam continuous PS steel wire 23; Shear connector
30 ; 연속다가구 프리캐스트 PSC 단일슬래브거더교 30; Continuous Multi-Furniture Precast PSC Single Slab Girder Bridge
40 ; 프리캐스트 PSC단일슬래브거더 40; Precast PSC Single Slab Girder
41 ; 당초하부플랜지폭 41; Lower Flange Width
42 ; 증가된 하부플랜지폭 43 ; 당초복부높이 42; Increased lower flange width 43; Initial abdominal height
44 ; 증가된 복부높이 44; Increased abdominal height
50 ; 슬래브강결연결부 51 ; 1차PS강선 50; Slab tight connection 51; Primary PS Steel Wire
52 ; 2차지점부연속강선 53 ; 정착장치 52; Secondary point continuous steel 53; Fuser
54 ; 1점받침지지연속구조 55 ; 3차연속 및 유지관리강선 54; Single point supporting continuous structure 55; 3rd continuous and maintenance steel wire
56 ; 받침 57 ; 상부플랜지슬래브 56; Base 57; Upper Flange Slab
58 ; 홈전단키 59 ; 3헌치슬래브하부단면 58; Home shear key 59; 3 Haunches slab bottom section
60 ; 가로보 61 ; 복부 60; Crossbeam 61; stomach
62 ; 하부플랜지 62; Lower Flange
70 ; 거더연결부 71 ; 고강도 무수축콘크리트 70; Girder connection 71; High strength non-contraction concrete
72 ; 슬립클립트러스철근 73 ; 압축철근 72; Slip clip truss rebar 73; Compressed rebar
74 ; 슬립클립루프철근 75 ; 단부절곡철근 74; Slip clip loop rebar 75; Bending Rebar
76 ; 접합용보강철근 77 ; 거푸집겸용강판 76; Reinforcing bars for joining 77; Formwork Steel Sheet
78 ; 코너앵글 79 ; 인장철근 78; Corner angle 79; Tensile rebar
80 ; 연결부철근슬립클립루프장치 85 ; 슬래브하면정착블럭 80; Connecting rebar slip clip loop device 85; Slab settle block
90 ; 교각강결연결연속다가구구조 91 ; 수평전단철근 90; Bridge steel connection continuous multi-furniture structure 91; Horizontal shear bar
92 ; 하부받침덮개강판 93 ; 브라켓 92; Lower support cover steel 93; Brackets
94 ; 축방향철근 95 ; 전단연결스터드 94; Axial reinforcement 95; Shear Connection Stud
96 ; 전단스터드볼트 97 ; 영구받침 96; Shear stud bolt 97; Permanent bearing
98 ; 용접 99 ; 솔플레이트 98; Welding 99; Sol Plate
100 ; 교대강결연결연속다가구구조 100; Alternating Steel Connection Continuous Multi Furniture Structure
110 ; 고정 및 단면조정힌지거푸집 115 ; 단면조정힌지거푸집 110; Fixed and sectioned hinge dies 115; Sectional Adjustable Hinge Formwork
120 ; 슬래브거더고정거푸집 120; Slab girder fixed dies
122 ; 상부슬래브플랜지 하면 거푸집 123 ; 단면조정힌지 122; Upper slab flange formwork 123; Section Adjustable Hinge
124 ; 지지대 124; support fixture
126 ; 잭 127 ; 하부플랜지외측거푸집 126; Jack 127; Lower Flange Outside Formwork
128 ; 복부거푸집 128; Abdominal form
129 ; 바닥판 및 상부플랜지 측면거푸집 129; Bottom plate and upper flange side formwork
130 ; 요철형부직포 131 ; 철근홀 130; Uneven type nonwoven fabric 131; Rebar
132 ; 앵글 132; angle
140 ; 직선형표준거푸집 141 ; 교축방향 140; Straight standard formwork 141; Axial direction
142 ; 교축직각방향 143 ; 탈착식클램프 142; Axial direction 143; Removable Clamp
150 ; 사각별표준거푸집 151 ; 단변 150; Rectangular formwork 151; Short side
152 ; 빗면 153 ; 장변 152; Slope 153; Long side
160 ; 거푸집설치후 제작된 프리캐스트 PSC단일슬래브거더 160; Precast PSC single slab girder manufactured after formwork installation
170 ; 현장측량 180 ; 각 위치별 표고 및 좌표 170; Field survey 180; Elevation and Coordinates for Each Location
190 ; 컴퓨터 및 프로그램 190; Computers and programs
Claims (11)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR20-2005-0012097U KR200394787Y1 (en) | 2005-04-29 | 2005-04-29 | continuous structure system type precast prestressed concrete single slab girder bridge connecting and supporting the same bridge with one point supporting structure or strongly coupled integrated structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR20-2005-0012097U KR200394787Y1 (en) | 2005-04-29 | 2005-04-29 | continuous structure system type precast prestressed concrete single slab girder bridge connecting and supporting the same bridge with one point supporting structure or strongly coupled integrated structure |
Related Parent Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020050036163A Division KR100722501B1 (en) | 2005-04-29 | 2005-04-29 | continuous structure system type precast prestressed concrete single slab girder bridge connecting and supporting the same bridge with one point supporting structure or strongly coupled integrated structure |
Publications (1)
Publication Number | Publication Date |
---|---|
KR200394787Y1 true KR200394787Y1 (en) | 2005-09-07 |
Family
ID=43695944
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR20-2005-0012097U KR200394787Y1 (en) | 2005-04-29 | 2005-04-29 | continuous structure system type precast prestressed concrete single slab girder bridge connecting and supporting the same bridge with one point supporting structure or strongly coupled integrated structure |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR200394787Y1 (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100963488B1 (en) | 2009-07-29 | 2010-06-17 | 노윤근 | Negative moment floor slab prestress introduction method for which precast concrete pc wire anchorage block and this were used |
KR101083036B1 (en) * | 2007-06-08 | 2011-11-16 | 삼성물산 주식회사 | Construction method for girder of bridge |
KR101131969B1 (en) * | 2008-03-20 | 2012-03-29 | 함영남 | Continuous Construction Method for Composite Bridge using Prestressed I-Type Girder |
KR101240477B1 (en) | 2010-03-26 | 2013-03-11 | 홍석희 | Continuous bridge using multiple stage displacement and taper member PSC slab girder connected by member rigid connection portions and method for constructing the same |
CN109881574A (en) * | 2019-04-18 | 2019-06-14 | 上海市城市建设设计研究总院(集团)有限公司 | Using the prefabricated bent cap in π type cross section and its method for prefabricating of external prestressing steels |
CN112982149A (en) * | 2021-04-13 | 2021-06-18 | 四川省交通建设集团股份有限公司 | Device for preventing template deformation of extrusion prestressed pier body and design method thereof |
KR102553230B1 (en) | 2023-01-09 | 2023-07-10 | 이형훈 | Precast earthquake-resistant hollow slab and the connection method therefor |
-
2005
- 2005-04-29 KR KR20-2005-0012097U patent/KR200394787Y1/en not_active IP Right Cessation
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101083036B1 (en) * | 2007-06-08 | 2011-11-16 | 삼성물산 주식회사 | Construction method for girder of bridge |
KR101131969B1 (en) * | 2008-03-20 | 2012-03-29 | 함영남 | Continuous Construction Method for Composite Bridge using Prestressed I-Type Girder |
KR100963488B1 (en) | 2009-07-29 | 2010-06-17 | 노윤근 | Negative moment floor slab prestress introduction method for which precast concrete pc wire anchorage block and this were used |
KR101240477B1 (en) | 2010-03-26 | 2013-03-11 | 홍석희 | Continuous bridge using multiple stage displacement and taper member PSC slab girder connected by member rigid connection portions and method for constructing the same |
CN109881574A (en) * | 2019-04-18 | 2019-06-14 | 上海市城市建设设计研究总院(集团)有限公司 | Using the prefabricated bent cap in π type cross section and its method for prefabricating of external prestressing steels |
CN109881574B (en) * | 2019-04-18 | 2024-04-09 | 上海市城市建设设计研究总院(集团)有限公司 | Pi-shaped cross section prefabricated bent cap adopting external prestressed tendons and prefabricating method thereof |
CN112982149A (en) * | 2021-04-13 | 2021-06-18 | 四川省交通建设集团股份有限公司 | Device for preventing template deformation of extrusion prestressed pier body and design method thereof |
KR102553230B1 (en) | 2023-01-09 | 2023-07-10 | 이형훈 | Precast earthquake-resistant hollow slab and the connection method therefor |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100722501B1 (en) | continuous structure system type precast prestressed concrete single slab girder bridge connecting and supporting the same bridge with one point supporting structure or strongly coupled integrated structure | |
KR100926140B1 (en) | Structure for using precast members and construction method thereof | |
KR200394787Y1 (en) | continuous structure system type precast prestressed concrete single slab girder bridge connecting and supporting the same bridge with one point supporting structure or strongly coupled integrated structure | |
KR20010078870A (en) | Development and construction methods of the prestressed composite truss beams | |
US3577504A (en) | Method of manufacturing a girder with a web of reinforced and/or prestressed concrete | |
JP5620344B2 (en) | Construction method of pier | |
KR101693256B1 (en) | Construction method of prefabricated psc bridge | |
KR102206783B1 (en) | Temporary Fixing System for Prestressed Concrete Spliced Girder Bridge and Construction method using thereof | |
CN210636656U (en) | Steel bar truss floor bearing plate and prefabricated superposed beam mounting structure | |
CN208918133U (en) | A kind of assembly concrete beam connection structure | |
CN108316150B (en) | Construction system and construction method for main tower and steel anchor beam of cable-stayed bridge | |
JP2006009449A (en) | Truss panel girder and precast truss panel | |
KR101527752B1 (en) | Construction method of prestressed composite girder bridge | |
KR101631096B1 (en) | Multiple composite girder for bridge | |
KR100522298B1 (en) | Improved prestressed steel reinforced concrete beam and bridge construction method using the same beam | |
KR101212259B1 (en) | Composite slab using corrugated plate and making method therewith | |
KR100583671B1 (en) | Prestressed concrete beam manufactured by installing steel anchorage devices to various positions and reinforcing member to the upper and lower flanges, and construction method of bridge using the concrete beam | |
KR102033052B1 (en) | Method for constructing truss bridge support with infilled tube using src girder | |
KR20080111973A (en) | Prestressed steel composite beam and a manufacturing method thereof | |
KR101311207B1 (en) | Column of steel framed reinforced precast concrete structure, manufacturing methods for the same, and construction methods for the same | |
JP2004197388A (en) | Flat slab structure | |
KR100899713B1 (en) | Bridge structure of steel composite girder using precast arch-deck, and constructing method thereof | |
EP1416101A1 (en) | Composite beam | |
KR102327700B1 (en) | Girder structure and construction method for continuity of supporting portion of girder using the same | |
KR101752285B1 (en) | Hybrid beam with wide PSC lower flange and enlarged section upper flange and structure frame using the same |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
U107 | Dual application of utility model | ||
REGI | Registration of establishment | ||
T201 | Request for technology evaluation of utility model | ||
T701 | Written decision to grant on technology evaluation | ||
G701 | Publication of correction | ||
EXTG | Extinguishment |