KR101131969B1 - Continuous Construction Method for Composite Bridge using Prestressed I-Type Girder - Google Patents

Continuous Construction Method for Composite Bridge using Prestressed I-Type Girder Download PDF

Info

Publication number
KR101131969B1
KR101131969B1 KR1020080025780A KR20080025780A KR101131969B1 KR 101131969 B1 KR101131969 B1 KR 101131969B1 KR 1020080025780 A KR1020080025780 A KR 1020080025780A KR 20080025780 A KR20080025780 A KR 20080025780A KR 101131969 B1 KR101131969 B1 KR 101131969B1
Authority
KR
South Korea
Prior art keywords
girder
span
pier
girders
center
Prior art date
Application number
KR1020080025780A
Other languages
Korean (ko)
Other versions
KR20090100537A (en
Inventor
함영남
Original Assignee
함영남
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 함영남 filed Critical 함영남
Priority to KR1020080025780A priority Critical patent/KR101131969B1/en
Publication of KR20090100537A publication Critical patent/KR20090100537A/en
Application granted granted Critical
Publication of KR101131969B1 publication Critical patent/KR101131969B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/02Bridges characterised by the cross-section of their bearing spanning structure of the I-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/14Towers; Anchors ; Connection of cables to bridge parts; Saddle supports
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/28Concrete reinforced prestressed

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

본 발명은 피에스씨(PSC) I형 거더를 이용한 합성형 교량에서 다경간을 연속적으로 시공할 수 있는 공법에 관한 것으로서, 다수의 피에스씨 I형 거더를 제작하되, 1차 텐던(40)이 중앙을 관통하도록 각 단부에 다수의 정착구(30)를 설치하고, 거더 단부에서 단면이 확대되는 부분을 이용하여 2차 텐던(60)의 설치공간을 확보하면서 1차 텐던(40)의 좌우로 편기정착되도록 하기 위해 각 단부의 양측면에 2차 텐던(60)이 정착되는 돌출부(50)를 각각 형성함과 동시에, 2차 텐던(60)의 배치방향에 따라 측경간 거더(10)와 중앙경간 거더(20)로 구분하여 제작한 후, 상기 각 거더(10,20)의 1차 텐던(40)을 포스트텐셔닝(Post-Tensioning)시키는 제1 단계(S1); 상기 피에스씨 I형 거더(10,20)들을 현장으로 운반한 후 크레인을 이용하여 교대(1)와 교각(2) 사이에는 측경간 거더(10)를 거치하고 교각(2)들 사이에는 중앙경간 거더(20)를 거치하는 제2 단계(S2); 길이방향으로 연속해서 설치되는 상기 피에스씨 I형 거더들을 관통하여 상기 2차 텐던(60)을 삽입하면서 일단의 교대(1) 위에 일단이 배치되는 측경간 거더(10)의 일측 단부에 형성된 돌출부(50)로부터 상기 측경간 거더(10)의 내부를 관통하여 교각(2) 위에 배치되는 상기 측경간 거더(10)의 타측 단부와 함께 동일한 상기 교각(2) 위에 배치되는 중앙경간 거더(20)의 일측 단부를 관통하여 상기 중앙경간 거더(20)의 일측 단부에 형성된 돌출부(50)에 정착되도록 하며, 상기 교각(2) 위에 배치되는 상기 측경간 거더(10)의 타측 단부에 형성된 돌출부(50)로부터는 같은 교각(2) 위에 배치되는 상기 중앙경간 거더(20)의 내부를 관통하여 타 교각(2) 위에 배치되는 중앙경간 거더(20)의 일측 단부에 형성된 돌출부(50)에 정착시키는 과정을 반복하여 복수의 중앙경간 거더(20)들을 결속시키고, 타단의 중앙경간 거더(20)의 타측 단부에 형성된 돌출부(50)로부터는 타단의 교대(1) 위에 일측 단부가 배치되는 측경간 거더(10)의 타측 단부에 형성된 돌출부(50)에 정착되도록 하여, 측경간 및 중앙경간 거더(10,20)들을 구조적으로 상호 결속시키는 제3 단계(S3); 단순교 상태에서 상기 PSC I형 거더들을 횡방향으로 연결하는 가로보 및 종방향으로 연결하는 중간연결부를 설치하고 하단부에 소핏 플레이트(70)를 연결하며 현장에서 바닥판 슬래브 콘크리트를 타설 및 양생하여 연속합성구조를 형성한 후, 가받침대를 제거하고 영구받침대를 설치하는 제4 단계(S4); 및 상기 2차 텐던(50)을 각 경간 별로 프리스트레싱(Prestressing)하여 정착시키는 제5 단계(S5); 를 포함하므로, 구조물 전체에 프리스트레싱에 의한 압축력을 도입시켜 경간장을 증가시키고 상부바닥판 균열문제를 해결할 수 있으며, 3경간 이상의 다경간 연속화구조물을 적용함에 의해 주행성 향상, 시공성 향상 및 시공비와 유지보수비를 절감시키며 교량의 내구성을 증가시킬 수 있다.The present invention relates to a method for continuously constructing multiple spans in a composite bridge using PSC type I girders, wherein a plurality of PS type I girders are manufactured, but the first tendon 40 is centered. Installing a plurality of anchorages 30 at each end to penetrate the through, and secure the installation space of the secondary tendon 60 by using a portion that the cross section is enlarged at the end of the girder while fixing the knitting side to the left and right of the primary tendon 40 In order to ensure that the projections 50 are fixed to the secondary tendon 60 on both sides of each end, and at the same time, the side span girders 10 and the center span girders 20 according to the arrangement direction of the secondary tendon 60 A first step (S1) of post-tensioning the primary tendons (40) of the respective girders (10, 20); After carrying the PS-type I girder (10, 20) to the site, using a crane mounted between the side bridge girder (10) between the shift (1) and the pier (2) and the center span girder between the bridges (2) A second step S2 of passing through 20; A protrusion 50 formed at one end of the side span girder 10, one end of which is disposed on one end of the shift 1 while inserting the secondary tendon 60 through the PSC type I girders continuously installed in the longitudinal direction. One end of the center span girder 20 disposed on the same pier (2) with the other end of the side span girder (10) is disposed on the pier (2) passing through the inside of the side span girder (10) from It penetrates and is fixed to the protrusion 50 formed at one end of the center span girder 20, and the same pier from the protrusion 50 formed at the other end of the side span girder 10 disposed on the pier 2. (2) a plurality of repetitive processes of penetrating the inside of the center span girder 20 disposed on the protrusion 50 formed at one end of the center span girder 20 disposed on the other piers 2 Center span girder (20) From the protrusion 50 formed at the other end of the center span girder 20 at the other end to the protrusion 50 formed at the other end of the side span girder 10 on which one end is disposed on the alternate end 1 of the other end. A third step (S3) of structurally binding side and center span girders 10 and 20 to be fixed; In the simple bridge state, install the intermediate connecting portion connecting the horizontal beam and the longitudinal direction connecting the PSC I type girders in the transverse direction, connect the Sofit plate 70 to the bottom, and the bottom plate slab concrete in the field to continually synthesize After forming the structure, the fourth step (S4) of removing the temporary support and installing a permanent support; And a fifth step (S5) of fixing the secondary tendons 50 by prestressing the respective spans. Since it includes a compressive force by prestressing the entire structure to increase the span length and solve the problem of the top plate cracks, by applying a multi-span continuous structure of more than three spans to improve the runability, construction properties and construction costs and maintenance costs It can reduce and increase the durability of the bridge.

PSC I형 거더, 합성형 교량, 측경간, 중앙경간, 연속화 공법, 2차 텐던 PSC type I girder, composite bridge, side span, center span, sequencing method, secondary tendon

Description

피에스씨(PSC) I형 거더를 이용한 합성형 교량의 다경간 연속화 공법{Continuous Construction Method for Composite Bridge using Prestressed I-Type Girder}Continuous Construction Method for Composite Bridge using Prestressed I-Type Girder}

본 발명은 피에스씨 I형 거더를 이용한 합성형 교량에서 다경간을 연속적으로 시공할 수 있는 공법에 관한 것으로서, 더욱 상세하게는 측경간 거더와 중앙경간 거더를 구분하여 제작하고 2차 텐던으로 상호 교차 및 결속시켜 구조물 전체에 프리스트레싱에 의한 압축력이 도입되도록 함으로써 경간장을 증가시키고 시공비와 유지보수비를 절감시키며 교량의 내구성을 증가시킬 수 있는 피에스씨 I형 거더를 이용한 합성형 교량의 다경간 연속화 공법에 관한 것이다.The present invention relates to a method for continuously constructing a multi-span in a composite bridge using PS-type I girder, and more specifically, to separate the side-span girders and the center-span girders, and to cross each other with a secondary tendon The present invention relates to a multi-span sequencing method for composite bridges using PS-type I girders, which can increase span length, reduce construction cost and maintenance cost, and increase bridge durability by introducing prestressing compressive force to the entire structure. .

피에스씨(PSC : Prestressed Concrete) I형 거더를 이용하여 건설된 교량은 자중이 무겁고 위치에 따라 하중의 차이가 심하므로 텐던(tendon)을 이용하여 조절하는 방법을 사용한다.Prestressed Concrete (PSC) Bridges constructed using Type I girders are heavily weighted and have a large load difference depending on their location.

일반적으로, PSC I형 거더의 연속화 방법은 설치된 교대 및 교각에 PSC I형 거더를 거치하고 거치된 거더 사이의 연결부와 바닥판 슬래브를 동시에 타설하여 연속화하는 방법을 사용하였으나, 상기 방법은 시공의 편의성은 있지만 변화되는 하중의 반복에 의해 연결부에 균열이 발생하여 내구성이 떨어지는 문제점이 있다.In general, the method of continuity of the PSC type I girder uses a method of mounting the PSC type I girder on the installed shifts and piers, and continually placing the connection part and the bottom plate slab between the mounted girders. Although there is a problem in that the cracks occur in the connection portion by the repetition of the changing load, durability is inferior.

이를 해결하기 위하여 2차 텐던을 부가하는 방법이 시도되고 있으며, 이러한 공법으로서 대한민국 특허등록번호 제10-0724739호에는 "긴장력 조절이 가능한 정착구를 이용한 피에스씨 거더교량의 시공방법"이 개시되어 있는데, 상기 특허의 기공방법은 연속 설치된 거더가 연결되는 단부에 돌출부를 형성하여 2차 텐던을 종방향으로 관통시키도록 하고 있으며, 연속 설치된 거더들을 2차 텐던으로 한꺼번에 관통시켜 긴장시키고 보수 등이 필요할 때 긴장력을 완화시킬 수 있도록 구성하고 있다.In order to solve this problem, a method of adding a secondary tendon has been attempted, and as such a method, Korean Patent Registration No. 10-0724739 discloses a "method of constructing a PS-C girder bridge using a fixing device capable of adjusting tension force". The pore method of the patent is to form a protrusion at the end connected to the continuously installed girders to penetrate the secondary tendon in the longitudinal direction, and through the continuously installed girders through the secondary tendon all at once to tension and repair when necessary To mitigate this problem.

그러나, 다경간의 교량을 가설할 때 하나의 연속된 2차 텐던으로 전체 거더들에 대해 긴장력을 부가하게 되면 구조물 전체에 가해지는 압축력이 약해질 수 밖에 없어 3경간 이상의 구조물에는 2차텐던의 프리스트레스 손실량 증가로 인해 적용하기 어려우며, 특히 보수 등을 위해 긴장력을 완화시킬 경우 상부 바닥판과 연결부에 균열이 발생하여 교량의 내구성이 떨어지는 문제점이 있다.However, when constructing multi-span bridges, if the tension force is applied to the entire girder with one continuous secondary tendon, the compressive force applied to the entire structure will be weakened. It is difficult to apply due to the increase, especially when the tension is relieved for repair, there is a problem that the cracks occur in the upper bottom plate and the connection to the durability of the bridge falls.

따라서, 상기와 같은 문제점을 해결하기 위한 본 발명의 기술적 과제는 구조물 전체에 프리스트레싱에 의한 압축력이 도입시켜 경간장을 증가시키고 시공비와 유지보수비를 절감시키며 교량의 내구성을 증가시킬 수 있는 피에스씨(PSC) I형 거더를 이용한 합성형 교량의 다경간 연속화 공법을 제공하는 것이다.Therefore, the technical problem of the present invention for solving the above problems is the PSC (PSC) that can increase the span, reduce the construction cost and maintenance costs by increasing the compression length by the prestressing to the whole structure It is to provide a multi-span continuous method for a composite bridge using an I-girder.

상기의 기술적 과제를 해결하기 위하여 본 발명은,The present invention to solve the above technical problem,

1차 텐던이 중앙을 관통하도록 양 단부에는 다수의 정착구를 설치하며, 단면이 확대되는 부분을 이용하여 2차 텐던의 설치공간을 확보하고, 상기 1차 텐던의 좌우로 편기정착되도록 하기 위해 양 단부에 인접하는 양측면에는 2차 텐던이 정착되는 돌출부를 각각 형성되도록 하며, 상기 돌출부의 형성방향에 따라 양 단부측 상기 돌출부가 일단부측으로만 향하도록 형성되는 측경간 거더와 양 단부측 상기 돌출부가 각 단부에 인접하는 단부측으로만 향하도록 형성되는 중앙경간 거더로 구분하여 제작한 후, 상기 각 거더의 1차 텐던을 양 단부의 정착구에 의해 포스트텐셔닝(Post-Tensioning)시키는 제1 단계; Both ends are provided with a plurality of anchorages at both ends so that the primary tendons penetrate the center, and both ends are secured to secure the installation space of the secondary tendons by using a portion having an enlarged cross section, and both sides are fixed to the left and right sides of the primary tendons. Both side surfaces adjacent to each other are formed with projections on which secondary tendons are fixed, and both end side girders and side end girders are formed so as to face only one end side in accordance with a direction in which the protrusions are formed. A first step of dividing the girder into center span girders formed only toward the end sides adjacent to the first girder, and then post-tensioning the primary tendons of the respective girders by fixing units at both ends;

상기 피에스씨 I형 거더들을 현장으로 운반한 후 크레인을 이용하여 교대와 교각 사이에는 측경간 거더를 거치하고 교각들 사이에는 중앙경간 거더를 거치하는 제2 단계; A second step of carrying the PS I type girders to a site and using a crane to mount side-girder girders between shifts and piers and to mount center-girder girders between piers;

상기 교대와 교각 간으로 배치되는 상기 측경간 거더의 교대측 단부에 형성된 돌출부로부터는 상기 측경간 거더의 내부와 상기 교각 위에 배치되는 상기 측경간 거더의 교각측 단부를 관통하여 상기 교각에 동시에 배치되는 중앙경간 거더의 상기 교각측 단부를 통해 상기 교각에 인접하는 일측 단부에 형성된 돌출부간으로 2차 텐던이 정착되도록 하고, 상기 측경간 거더의 상기 교각측 단부에 형성된 돌출부로부터는 상기 교각측 단부와 같은 교각에 배치되는 상기 중앙경간 거더의 양단부를 관통하여 상기 중앙경간 거더에 인접하는 타 중앙경간 거더 또는 다른 측경간 거더의 상기 중앙경간 거더와 동일한 교각에 배치되는 단부측 돌출부으로 다른 2차 텐던이 정착되도록 하며, 상기 중앙경간 거더의 다른 중앙경간 거더 또는 다른 측경간 거더와 동일한 교각에 배치되는 단부측 돌출부는 인접하는 단부와 이와 동일한 교각에 배치되는 상기 다른 중앙경간 거더 또는 다른 측경간 거더의 일측 단부를 관통하여 타측 단부에 형성된 돌출부에 또 다른 2차 텐던을 정착시키는 과정을 반복하여, 측경간 및 중앙경간 거더들을 구조적으로 상호 결속시키는 제3 단계; A center span girder, which is disposed at the pier at the same time through the pier side end of the lateral girder and the lateral girder disposed on the pier from the protrusion formed at the alternating side end of the lateral girder disposed between the alternating and the pier. The secondary tendon is settled between the protrusions formed at one end portion adjacent to the pier via the pier side end portion of, and from the protrusions formed at the pier side end portion of the side span girder, the second tendon is disposed at the same pier as the pier side end portion. The second secondary tendon is fixed to an end side protrusion which is disposed at the same pier as other center span girders or other side span girders adjacent to the center span girders or through the ends of the center span girders, and the center span girders of the other side span girders. With other center span girders or other side span girders of span girders An end side protrusion disposed in one pier penetrates one end of the other center span girder or another side span girder disposed in the same pier as the adjacent end, and sets another secondary tendon to a protrusion formed at the other end. Repeatedly, a third step of structurally binding side span and center span girders;

단순교 상태에서 상기 PSC I형 거더들을 횡방향으로 연결하는 가로보 및 종방향으로 연결하는 중간연결부를 설치하고 그 하단부에 소핏 플레이트를 연결하여 현장에서 바닥판 슬래브 콘크리트를 타설 및 양생하여 연속합성구조를 형성한 후, 가받침대를 제거하고 영구받침대를 설치하는 제4 단계; 및In the simple bridge state, the intermediate beam connecting the horizontal beams and the longitudinal connecting the PSC I-girders in the lateral direction is installed, and the bottom plate slab concrete is poured and cured in the field by connecting the sofit plate at the bottom to form a continuous composite structure. After forming, the fourth step of removing the temporary stand and install the permanent stand; And

상기 2차 텐던을 각 경간 별로 프리스트레싱(Prestressing)하여 정착시키는 제5 단계; 를 포함하는 피에스씨 I형 거더를 이용한 합성형 교량의 다경간 연속화 공법을 제공한다.A fifth step of prestressing and fixing the secondary tendons for each span; Provides a multi-span continuous method of the composite bridge using PS C type girder comprising a.

삭제delete

삭제delete

상기에서 설명한 바와 같은 본 발명의 피에스씨 I형 거더를 이용한 합성형 교량의 다경간 연속화 공법에 의하면, 연속가능한 경간장이 증가되어 신축이음장치의 설치개소 수가 대폭 감소되고 3경간 이상의 다경간 연속화 구조물을 적용함에 의해 차량의 주행성 향상 및 유지보수비용의 절감효과를 얻을 수 있으며, 거더의 구조적 연속화 및 연속적으로 설치되는 텐던의 프리스트레스 손실 최소화로 교량건설에 사용되는 콘크리트, 철근, 프리스트레싱 강재 등 건설재료의 양을 종래 공법에 비해 대폭 절감시킬 수 있다.According to the multi-span sequencing method of the composite bridge using the PS-type I girder of the present invention as described above, the continuous span length is increased, the number of installation points of the expansion joint device is greatly reduced, By applying it, it is possible to improve the driving performance of the vehicle and reduce the maintenance cost, and the amount of construction materials such as concrete, reinforcing steel and prestressing steel used in bridge construction by structural continuity of girder and minimizing prestress loss of tendon installed continuously. Can be significantly reduced compared to the conventional method.

또한, 상부슬래브와 피에스씨 I형 거더가 구조적으로 합성된 상태에서 연속적으로 텐던을 긴장시킴으로써 구조물 전체에 대해 프리스트레싱에 의한 압축력을 도입할 수 있으며, 연속되는 텐던이 중간연결부에서 교차되도록 하여 양호한 압축력을 구조물에 전달할 수 있어서 연속 합성형 교량에서 흔히 발생되는 중간연결부 부근의 상부슬래브에 균열이 발생하는 문제점을 제거할 수 있어 교량의 내구성을 대폭 증대시킬 수 있다.In addition, by compressing the tendons continuously in the state where the upper slab and the PS-type I girder are structurally synthesized, prestressing force can be introduced to the entire structure, and successive tendons are intersected at the intermediate connection to provide good compressive force. It can be delivered to the structure to eliminate the problem of cracking in the upper slab near the intermediate connection that is commonly encountered in continuous composite bridge can significantly increase the durability of the bridge.

이하에서 첨부된 예시도면에 의거하여 본 발명의 일 실시예에 의한 피에스씨(PSC) I형 거더를 이용한 합성형 교량의 다경간 연속화 공법을 상세히 설명한다.Hereinafter, a multi-span continuous method of a composite bridge using a PSC type I girder according to an embodiment of the present invention will be described in detail with reference to the accompanying drawings.

도 5는 본 발명의 일 실시예에 의한 다경간 연속화 공법을 각 단계별로 도시한 정면측 투영도이고, 도 8은 본 발명의 일 실시예에 의한 다경간 연속화 공법의 플로우차트이다.5 is a front side projection view illustrating each step of the multi-span continuous method according to an embodiment of the present invention, and FIG. 8 is a flowchart of the multi-span continuous method according to an embodiment of the present invention.

도 5와 도 8을 참조하면, 본 발명의 일 실시예에 의한 피에스씨 I형 거더를 이용한 합성형 교량의 다경간 연속화 공법은, 피에스씨 I형 거더를 측경간(10)과 중앙경간(20)으로 구분하여 제작하고 1차 텐던(40)을 포스트텐셔닝(Post-tensioning)하는 제1 단계(S1)와, 상기 피에스씨 I형 거더(10,20)들을 인양하여 교대(1)와 교각(2)에 거치하는 제2 단계(S2)와, 상기 거치된 거더(10,20)에 2차 텐던(60)을 삽입하는 제3 단계(S3)와, 중간연결부와 가로보를 설치하고 상부슬래브 콘크리트를 타설하여 양생하는 제4 단계(S4)와, 각 경간 별로 2차 텐던(60)을 긴장시켜 정착시키는 제5 단계(S5)를 포함한다.5 and 8, the multi-span sequencing method of the composite bridge using the PS-type I girder according to an embodiment of the present invention, the PS-type I girder is a side span 10 and the center span 20 The first step (S1) to produce and post-tensioning the primary tendon 40, and to lift the PS I-type girder (10, 20) and shift (1) and piers ( 2) the second step (S2) to be mounted on, the third step (S3) for inserting the secondary tendon 60 into the mounted girders (10, 20), and the intermediate slab and cross beams to install the upper slab concrete A fourth step (S4) of pouring and curing, and a fifth step (S5) of tensioning and fixing the secondary tendon 60 for each span.

상기 각 단계에 대하여 도면을 참조하여 더욱 자세하게 설명한다.Each step will be described in more detail with reference to the drawings.

도 5a는 피에스씨 I형 거더를 제작하는 제1 단계를 도시하고 있다. 도 5a와 도 8에서 알 수 있는 바와 같이, 상기 제1 단계(S1)는 교량의 상부를 구성하는 다수의 피에스씨 I형 거더를 제작하는 단계로서, 공장이나 교량가설현장에 인접한 제작장에서 측경간 거더(10)와 중앙경간 거더(20)로 구분하여 제작한다.FIG. 5A shows a first step of manufacturing the PS I type girder. As can be seen in Figures 5a and 8, the first step (S1) is a step of manufacturing a plurality of PS I-girder constituting the upper portion of the bridge, the side span at the production site adjacent to the factory or bridge construction site Produced by separating the girder 10 and the center span girder 20.

상기 피에스씨 I형 거더(10,20)는 각 단부에 다수의 정착구(30)를 설치하여 1차 텐던(40)이 중앙을 관통하여 양 단부에서 정착되도록 하고, 2차 텐던(60)의 설치공간을 확보하기 위해 각 단부의 상부를 블록아웃하고 2차 텐던(60)을 1차 텐던(40)의 좌우로 편기시키기 위해 각 측면에 돌출부(50)를 형성한다. 이때, 2차 텐던(60)이 거더 내에서 배치되는 방향에 따라 측경간 거더(10)와 중앙경간 거더(20)로 구분하여 제작한다.The CS-type I girder (10, 20) is provided with a plurality of fixing holes 30 at each end so that the primary tendon 40 is fixed at both ends through the center, the installation of the secondary tendon 60 Blocks are formed at the top of each end to secure space, and protrusions 50 are formed at each side to bias the secondary tendons 60 to the left and right of the primary tendons 40. At this time, according to the direction in which the secondary tendon 60 is disposed in the girder is produced by dividing the side span girders 10 and the center span girders 20.

도 1과 도 2는 본 발명의 일 실시예에 의한 측경간 거더(10)와 중앙경간 거 더(20)의 사시도이고, 도 3과 도 4는 본 발명의 일 실시예에 의한 측경간 거더(10)와 중앙경간 거더(20)의 정면 및 평면측 투영도이다.1 and 2 are perspective views of the side span girders 10 and the center span girders 20 according to an embodiment of the present invention, Figures 3 and 4 are side span girders 10 according to an embodiment of the present invention And front and planar side projection views of the center span girders 20.

도면을 참조하면, 상기 측경간 거더(10)는 교대(1)와 교각(2)을 연결하기 위한 거더로서, 일측 단부의 양측면에 각각 돌출부(50)를 형성하고, 2차 텐던(60)이 상기 각 돌출부(50)로부터 중앙부분 내부를 통해 타측 단부까지 종방향으로 관통할 수 있도록 쉬스관을 삽입한다. 또한, 타측 단부의 양측면에 각각 돌출부(50)를 형성하고, 2차 텐던(60)이 중앙부분을 거치지 않고 상기 돌출부(50)로부터 인접한 위치의 상기 타측 단부까지 종방향으로 관통할 수 있도록 쉬스관을 삽입한다.Referring to the drawings, the side-girder 10 is a girder for connecting the alternating portion 1 and the pier 2, each forming a protrusion 50 on both sides of one end, the secondary tendon 60 is the The sheath tube is inserted to penetrate longitudinally from each protrusion 50 to the other end portion through the inside of the central portion. Further, sheath pipes are formed on both sides of the other end, respectively, and the sheath pipe can penetrate in the longitudinal direction from the protrusion 50 to the other end of the adjacent position without passing through the center portion of the secondary tendon 60. Insert

그리고, 상기 중앙경간 거더(20)는 교각(2)과 교각(2)을 연결하는 거더로서, 거더(20) 양측 단부의 양측면에는 각각 돌출부(50)를 형성하고, 2차 텐던(60)이 중앙부분을 거치지 않고 상기 돌출부(50)로부터 인접한 위치의 각 단부까지 길이방향으로 관통할 수 있도록 쉬스관을 삽입한다.The center span girder 20 is a girder connecting the pier 2 and the pier 2 to form protrusions 50 on both sides of both ends of the girder 20, and the secondary tendons 60 are formed. The sheath tube is inserted to penetrate in the longitudinal direction from the protrusion 50 to each end of the adjacent position without passing through the central portion.

다음으로, 상기 거더 내에 설치된 1차 텐던(40)을 포스트텐셔닝(Post-tensioning) 방법으로 긴장시켜 양단부에 설치된 정착구(30)로 고정시킨다.Next, the primary tendon 40 installed in the girder is tensioned by a post-tensioning method, and fixed to the fixing unit 30 installed at both ends.

도 5b는 피에스씨 I형 거더를 교대(1)와 교각(2)에 거치하는 제2 단계를 도시하고 있다.FIG. 5B shows a second step of mounting the PS I-girder to the shift 1 and the pier 2.

도면에서 알 수 있는 바와 같이, 상기 제2 단계(S2)는 제작된 상기 거더를 인양하여 거치시키는 단계로서, 상기 피에스씨 I형 거더(10,20)들을 현장으로 운반한 후 크레인을 이용하여 교대(1)와 교각(2)의 상단에 설치한 가받침대 위에 거치시킨다. 이때, 교대(1)와 교각(2) 사이에는 측경간 거더(10)를 거치하고 교각(2)들 사이에는 중앙경간 거더(20)를 거치한다.As can be seen in the drawing, the second step (S2) is a step of lifting and mounting the manufactured girder, the PS I-type girders (10, 20) are transported to the site and alternately using a crane Mount it on the support base installed on the upper part of (1) and pier (2). At this time, the side span girder 10 is mounted between the shift 1 and the pier 2 and the center span girder 20 is mounted between the bridges 2.

도 5c는 거치된 피에스씨 I형 거더에 길이방향으로 2차 텐던(60)을 삽입하는 제3 단계를 도시하고 있는데, 상기 제3 단계(S3)는 도면에서 알 수 있는 바와 같이 거치된 거더(10,20)들에 2차 텐던(60)을 삽입하는 단계로서, 3경간인 경우 측경간(10) 거더와 중앙경간 거더(20)를 상호 결속되게 연결하고, 4경간 이상인 경우 상기와 같이 함과 함께 중앙에 연속되는 중앙경간 거더(20)들도 상호 결속되게 연결한다.Figure 5c shows a third step of inserting the secondary tendon 60 in the longitudinal direction to the mounted CS C-girder, the third step (S3) is a mounted girder (as can be seen in the figure) Inserting the secondary tendon (60) in the 10,20), in the case of three spans, the side span (10) girder and the center span girders (20) are connected to each other, and if more than four spans as described above The center span girders 20 that are continuous in the center together are also connected to each other.

도 6은 본 발명의 일 실시예에 의해 교대(1) 위에 배치된 측경간 거더(10)의 단부에 1차 및 2차 텐던(40,60)이 삽입설치된 상태를 보여주는 투영도이고, 도 7은 본 발명의 일 실시예에 의해 교각(2) 위에 배치된 중앙연결부에 1차 및 2차 텐던(40,60)이 삽입설치된 상태를 보여주는 투영도이다.FIG. 6 is a projection view showing a state in which primary and secondary tendons 40 and 60 are inserted and installed at ends of side span girders 10 disposed on shifts 1 according to an embodiment of the present invention, and FIG. According to one embodiment of the invention is a projection view showing a state in which the primary and secondary tendon (40, 60) is inserted into the central connection portion disposed on the pier (2).

도 6과 도 7을 참조하여 설명하면, 길이방향으로 연속하여 설치된 측경간 거더(10)와 중앙경간 거더(20)를 관통하여 2차 텐던(60)을 삽입하되, 교대(1) 위에 배치된 측경간 거더(10)의 일측 단부에 형성한 돌출부(50)로부터 측경간 거더(10)의 내부를 관통하여 교각(2) 상에 연속배치되는 중앙경간 거더(20)의 일측 단부에 형성한 돌출부(50)에 있는 정착구(30)로 정착시킨다.Referring to FIGS. 6 and 7, a secondary tendon 60 is inserted through the side span girders 10 and the center span girders 20 continuously installed in the longitudinal direction, and the side spans are disposed on the shift 1. A protrusion 50 formed at one end of the center span girder 20 continuously penetrating the inside of the side span girder 10 from the protrusion 50 formed at one end of the girder 10 and disposed on the piers 2. Settle to the anchorage 30 in the.

그리고, 도면에서와 같이 3경간인 경우 교각(2) 위에 일측 단부가 배치되는 측경간 거더(10)의 일측 단부에 형성한 돌출부(50)에서부터 그와 연속하여 배치되어 있는 중앙경간 거더(20)의 내부를 관통하여 타 교각(2) 위에 일측 단부가 배치되는 측경간 거더(10)의 일측 단부에 형성한 돌출부(30)에 있는 정착구(30)에 정착시킨다.
또한 중앙경간 거더(20)의 타측 단부에 형성한 돌출부(30)로부터는 2차 텐던(20)이 중앙경간 거더(20)를 기준으로 타단에 형성되는 측경간 거더(10)의 타 교대(1) 위에 배치되는 타측 단부에 형성한 돌출부(50)에 정착시킨다. 이때, 4경간 이상인 경우에는 중앙경간 거더(20)들 사이에도 상기와 마찬가지로 결속시킨다.
And, in the case of three spans, as shown in the figure, from the protrusion 50 formed at one end of the side span girder 10 on which one end is disposed on the pier 2, the center span girder 20 continuously disposed thereon. It penetrates inside and is fixed to the fixing unit 30 in the protrusion part 30 formed in one end part of the side span girder 10 in which one end part is arrange | positioned on the other piers 2.
In addition, from the protrusion 30 formed at the other end of the center span girder 20, the second tendon 20 is alternately formed of the side span girder 10 formed at the other end with respect to the center span girder 20. It is fixed to the protrusion part 50 formed in the other end part arrange | positioned above. At this time, in the case of more than four spans, the center span girders 20 are also bonded as described above.

전체 거더(10,20)들에 대해 상기와 같은 과정을 시행함으로써 측경간과 중앙경간 거더(10,20)들을 2차 텐던(60)에 의해 구조적으로 상호 결속시킨다.By performing the above process for the entire girder (10, 20), the side span and the center span girders (10, 20) are structurally bound by the secondary tendon (60).

또한, 도면에서 알 수 있는 바와 같이, 연속적으로 삽입되는 2차 텐던(20)은 각 거더(10,20)들의 중앙부와 단부 사이에서 좌우 및 상하로 관통하도록 배치되어 있고 중간연결부에서 상호 교차되고 있어서, 교량에 대해 구조적으로 양호한 압축력을 전달할 수 있어 연속 합성형 교량에서 흔히 발생되는 중간연결부 부근의 상부슬래브에 균열이 발생하는 문제점을 제거할 수 있으므로 교량의 내구성을 대폭 증대시킬 수 있다.In addition, as can be seen in the figure, the secondary tendons 20 inserted continuously are arranged to penetrate left and right and up and down between the center and the ends of the girders 10 and 20 and cross each other at the intermediate connection part. As a result, it is possible to transmit structurally good compressive force to the bridge, thereby eliminating the problem of cracking in the upper slab near the intermediate joint, which is often found in continuous composite bridges, thereby significantly increasing the durability of the bridge.

도 5d는 중간연결부와 가로보를 설치하고 상부슬래브의 콘크리트를 타설하는 제4 단계를 도시하고 있다. 즉, 상기 제4 단계(S4)는 각종 부재를 설치하고 콘크리트를 타설하여 합성교량을 형성하는 단계로서, 중간연결부, 가로보, 소핏 플레이트 등을 설치한 다음, 상부슬래브(80)를 형성하기 위해 콘크리트를 타설하여 양생한다.Figure 5d shows a fourth step of installing the intermediate connection and cross beams and placing the concrete of the upper slab. That is, the fourth step (S4) is a step of forming a composite bridge by installing a variety of members and placing concrete, after installing the intermediate connecting portion, cross beam, sofit plate, etc., to form the upper slab 80 Heal by pouring.

즉, 피에스씨 I형 거더(10,20)들이 교대(1)와 교각(2) 사이에 거치된 단순교 상태에서 교량의 폭을 확보하기 위해 상기 거더들이 횡방향으로 2 이상 거치되어 있는 경우 상기 각 거더(10,20)들을 횡방향으로 연결하기 위한 가로보를 설치하고, 교각(2) 위에 거치된 거더(10,20)들을 길이방향으로 연결하기 위하여 중간연결부를 설치하며, 그 하단부에는 소핏 플레이트(70)를 연결한다. 그리고, 교량의 바닥판을 이루는 상부슬래브(80)를 형성하기 위하여 콘크리트를 타설하고 양생하여 상기 거더(10,20)들을 기반으로 하는 연속합성구조의 교량을 형성한 후 가받침대를 제거하고 영구받침대를 설치한다.That is, when the girder is mounted in two or more in the transverse direction to secure the width of the bridge in a simple bridge state in which the CS-type I girder (10,20) is mounted between the shift (1) and the bridge (2) A horizontal beam is installed to connect each girder 10 and 20 in the lateral direction, and an intermediate connection part is installed to connect the girders 10 and 20 mounted on the pier 2 in the longitudinal direction. Connect 70. Then, in order to form the upper slab 80 constituting the bottom plate of the bridge, the concrete is poured and cured to form a bridge of a continuous composite structure based on the girder 10, 20, and then remove the backrest and permanent support Install it.

도 5e는 2차 텐던(60)을 경간장별로 긴장시키는 제5 단계를 도시하고 있다.5E illustrates a fifth step of tensioning the secondary tendon 60 by span length.

도 5e에 도시된 바와 같이, 상기 제5 단계(S5)는 2차 텐던(60)을 긴장시키는 단계로서, 상기 거더(10,20)들을 연속하여 결속시키면서 관통하고 있는 2차 텐던(60)들을 각 경간 별로 프리스트레싱(Prestressing)하여 각 정착구(30)에 고정시켜 교량에 가해지는 사하중과 활하중을 상쇄시키기 위한 긴장력을 부여한다.As shown in FIG. 5E, the fifth step S5 is a step of tensioning the secondary tendons 60, through which the secondary tendons 60 penetrating while continuously binding the girders 10 and 20. Prestressing for each span (Prestressing) is fixed to each anchorage 30 to give a tension force to offset the dead and live loads applied to the bridge.

이와 같은 단계를 거치면 본 발명의 다경간 연속화 공법에 의해 합성단면을 가지며 구조적으로 결속된 피에스씨 I형 거더 합성형 교량을 완성하게 된다.Through such a step, the PS-type I girder composite bridge having a composite section and structurally bound by the multi-span continuous method of the present invention is completed.

도 1은 본 발명의 일 실시예에 의한 측경간 거더의 사시도이다.1 is a perspective view of a side span girder according to an embodiment of the present invention.

도 2는 본 발명의 일 실시예에 의한 중앙경간 거더의 사시도이다.2 is a perspective view of a center span girder according to an embodiment of the present invention.

도 3은 본 발명의 일 실시예에 의한 측경간 거더의 정면측 및 평면측 투영도이다.3 is a front side and a planar side projection view of the side span girders according to an embodiment of the present invention.

도 4는 본 발명의 일 실시예에 의한 중앙경간 거더의 정면측 및 평면측 투영도이다.4 is a front side and a planar side projection view of a center span girder according to an embodiment of the present invention.

도 5는 본 발명의 일 실시예에 의한 피에스씨 I형 거더를 이용한 합성형 교량의 다경간 연속화 공법을 각 단계별로 도시한 정면측 투영도로서, 도 5a는 피에스씨 I형 거더를 제작하는 제1 단계를 도시하고 있고, 도 5b는 피에스씨 I형 거더를 교대와 교각에 거치하는 제2 단계를 도시하고 있고, 도 5c는 거치된 피에스씨 I형 거더에 2차 텐던을 종방향으로 삽입하는 제3 단계를 도시하고 있고, 도 5d는 중간연결부와 가로보를 설치하고 상부슬래브의 콘크리트를 타설하는 제4 단계를 도시하고 있으며, 도 5e는 2차 텐던을 경간장별로 긴장시키는 제5 단계를 도시하고 있다.FIG. 5 is a front side projection view illustrating each step of the multi-span sequencing method of a composite bridge using PS I-girder according to an embodiment of the present invention, and FIG. 5A illustrates a first process of manufacturing a PS I-girder. FIG. 5B shows a second step of mounting the PS-I girder to the alternating and piers, and FIG. 5C shows a second step of longitudinally inserting the secondary tendon into the mounted CS-I girder. FIG. 5D shows the fourth step of installing the intermediate connection and the cross beam and placing the concrete of the upper slab, and FIG. 5E shows the fifth step of tensioning the secondary tendon by span length. .

도 6은 본 발명의 일 실시예에 의해 교대위에 설치된 측경간부의 단부에 1차 및 2차 텐던이 삽입설치된 상태를 보여주는 투영도이다.6 is a projection view showing a state in which the primary and secondary tendon is inserted into the end portion of the side span portion provided on the shift by an embodiment of the present invention.

도 7은 본 발명의 일 실시예에 의해 교각위에 설치된 연결지점부에 1차 및 2차 텐던이 삽입설치된 상태를 보여주는 투영도이다.7 is a projection view showing a state in which the primary and secondary tendon is inserted into the connection point portion installed on the piers according to an embodiment of the present invention.

도 8은 본 발명의 일 실시예에 의한 피에스씨 I형 거더를 이용한 합성형 교 량의 다경간 연속화 공법의 플로우차트이다.8 is a flowchart of a multi-span sequencing method of a composite bridge using PS I-girder according to an embodiment of the present invention.

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

1:교대 2:교각1: Shift 2: Pier

10:측경간 거더 20:중앙경간 거더 10: side span girder 20: middle span girder

30:정착구 40:1차 텐던 30: anchorage 40: 1 primary tendon

50:돌출부 60:2차 텐던 50: protrusion 60: the second tendon

70:소핏 플레이트 80:상부슬래브 70: Sofitt plate 80: Upper slab

Claims (2)

1차 텐던(40)이 중앙을 관통하도록 양 단부에는 다수의 정착구(30)를 설치하며, 단면이 확대되는 부분을 이용하여 2차 텐던(60)의 설치공간을 확보하고, 상기 1차 텐던(40)의 좌우로 편기정착되도록 하기 위해 양 단부에 인접하는 양측면에는 2차 텐던(60)이 정착되는 돌출부(50)를 각각 형성되도록 하며, 상기 돌출부(50)의 형성방향에 따라 양 단부측 상기 돌출부(50)가 일단부측으로만 향하도록 형성되는 측경간 거더(10)와 양 단부측 상기 돌출부(50)가 각 단부에 인접하는 단부측으로만 향하도록 형성되는 중앙경간 거더(20)로 구분하여 제작한 후, 상기 각 거더(10,20)의 1차 텐던(40)을 양 단부의 정착구(30)에 의해 포스트텐셔닝(Post-Tensioning)시키는 제1 단계(S1); A plurality of anchorages 30 are installed at both ends so that the primary tendons 40 penetrate the center, and an installation space of the secondary tendons 60 is secured by using a portion having an enlarged cross section, and the primary tendons ( In order to fix the knitting side to the left and right sides of the 40), both sides adjacent to both ends are formed with protrusions 50 on which the secondary tendons 60 are fixed, respectively, according to the forming direction of the protrusions 50. Produced by dividing the side span girder 10 is formed so that the protrusion 50 is directed only to one end side and the center span girder 20 is formed so that both ends side the protrusion 50 is directed only to the end side adjacent to each end Then, the first step (S1) of post-tensioning the primary tendon (40) of each girder (10, 20) by the fixing unit 30 at both ends; 상기 피에스씨 I형 거더(10,20)들을 현장으로 운반한 후 크레인을 이용하여 교대(1)와 교각(2) 사이에는 양 단부의 상기 돌출부(50)가 공히 상기 교각(2)을 향하도록 하여 측경간 거더(10)를 거치하고, 교각(2)들 사이에는 중앙경간 거더(20)를 거치하는 제2 단계(S2); After carrying the PS I type girders 10 and 20 to the site, between the shift 1 and the pier 2 using a crane so that the protrusions 50 at both ends face the pier 2. A second step (S2) of mounting side span girders (10) and a center span girder (20) between the piers (2); 상기 교대(1)와 교각(2) 간으로 배치되는 상기 측경간 거더(10)의 교대(1)측 단부에 형성된 돌출부(50)로부터는 상기 측경간 거더(10)의 내부와 상기 교각(2) 위에 배치되는 상기 측경간 거더(10)의 교각(2)측 단부를 관통하여 상기 교각(2)에 동시에 배치되는 중앙경간 거더(20)의 상기 교각(2)측 단부를 통해 상기 교각(2)에 인접하는 일측 단부에 형성된 돌출부(50)간으로 2차 텐던(60)이 정착되도록 하고, 상기 측경간 거더(10)의 상기 교각(2)측 단부에 형성된 돌출부(50)로부터는 상기 교각(2)측 단부와 같은 교각(2)에 배치되는 상기 중앙경간 거더(20)의 양단부를 관통하여 상기 중앙경간 거더(20)에 인접하는 타 중앙경간 거더(2) 또는 다른 측경간 거더(10)의 상기 중앙경간 거더(20)와 동일한 교각(2)에 배치되는 단부측 돌출부(50)으로 다른 2차 텐던(60)이 정착되도록 하며, 상기 중앙경간 거더(20)의 다른 중앙경간 거더(20) 또는 다른 측경간 거더(10)와 동일한 교각(2)에 배치되는 단부측 돌출부(50)는 인접하는 단부와 이와 동일한 교각(2)에 배치되는 상기 다른 중앙경간 거더(20) 또는 다른 측경간 거더(10)의 일측 단부를 관통하여 타측 단부에 형성된 돌출부(50)에 또 다른 2차 텐던(60)을 정착시키는 과정을 반복하여, 측경간 및 중앙경간 거더(10,20)들을 구조적으로 상호 결속시키는 제3 단계(S3);From the projection 50 formed at the end of the alternating side 1 of the side girder 10 arranged between the alternating member 1 and the pier 2, on the inside of the side girder 10 and on the pier 2. Adjacent to the pier 2 through the pier (2) side end of the center span girder 20, which is disposed at the same time in the pier 2 through the pier (2) side end of the side span girder 10 is disposed The secondary tendon 60 is fixed between the protrusions 50 formed at one end of the side, and from the protrusion 50 formed at the end of the pier 2 side of the side span girder 10, the pier 2 side. The center span of another center span girder 2 or another side span girder 10 adjacent to the center span girder 20 through both ends of the center span girder 20 disposed in the pier 2 such as an end. The other secondary tendon 60 is fixed to the end side protrusion 50 disposed in the same pier 2 as the girder 20. The end side protrusion 50 disposed in the same pier 2 as another center span girder 20 or another side span girder 10 of the center span girder 20 has an adjacent end and the same pier 2. Repeat the process of fixing another secondary tendon 60 to the protrusion 50 formed at the other end through the other end of the other center span girder 20 or the other side span girder 10 is arranged, the side span and A third step S3 of structurally binding the center span girders 10 and 20; 단순교 상태에서 상기 PSC I형 거더들을 횡방향으로 연결하는 가로보 및 종방향으로 연결하는 중간연결부를 설치하고 하단부에 소핏 플레이트(70)를 연결하며 현장에서 바닥판 슬래브 콘크리트를 타설 및 양생하여 연속합성구조를 형성한 후, 가받침대를 제거하고 영구받침대를 설치하는 제4 단계(S4); 및In the simple bridge state, install the intermediate connecting portion connecting the horizontal beam and the longitudinal direction connecting the PSC I type girders in the transverse direction, connect the Sofit plate 70 to the bottom, and the bottom plate slab concrete in the field to continually synthesize After forming the structure, the fourth step (S4) of removing the temporary support and installing a permanent support; And 상기 2차 텐던(50)을 각 경간 별로 프리스트레싱(Prestressing)하여 정착시키는 제5 단계(S5); 를 포함하는 피에스씨 I형 거더를 이용한 합성형 교량의 다경간 연속화 공법.A fifth step (S5) of prestressing and fixing the secondary tendon (50) for each span; Multi-span sequencing method of the composite bridge using PS C-type girder comprising a. 삭제delete
KR1020080025780A 2008-03-20 2008-03-20 Continuous Construction Method for Composite Bridge using Prestressed I-Type Girder KR101131969B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020080025780A KR101131969B1 (en) 2008-03-20 2008-03-20 Continuous Construction Method for Composite Bridge using Prestressed I-Type Girder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020080025780A KR101131969B1 (en) 2008-03-20 2008-03-20 Continuous Construction Method for Composite Bridge using Prestressed I-Type Girder

Publications (2)

Publication Number Publication Date
KR20090100537A KR20090100537A (en) 2009-09-24
KR101131969B1 true KR101131969B1 (en) 2012-03-29

Family

ID=41358699

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020080025780A KR101131969B1 (en) 2008-03-20 2008-03-20 Continuous Construction Method for Composite Bridge using Prestressed I-Type Girder

Country Status (1)

Country Link
KR (1) KR101131969B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102321582B1 (en) 2021-03-10 2021-11-05 (주)한맥기술 PSC I-type girder capable of adjusting transverse displacement using the tension member of the upper flange
KR102335963B1 (en) 2021-03-10 2021-12-07 (주)한맥기술 PS girder with improved structural performance by modifying the tension member arrangement structure of the lower flange
KR102509254B1 (en) 2022-10-27 2023-03-14 (주)한맥기술 A method of measuring the displacement information of a girder capable of calculating the rotational displacement information of a PSC type I girder and a bridge construction method using the same
KR20230123201A (en) 2022-02-16 2023-08-23 (주)한맥기술 Multi-span PS girder and construction method of multi-span PS girder

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101134290B1 (en) * 2011-03-08 2012-04-13 (주)삼현피에프 Method of constructing prestressed concrete box girder bridge
KR102551807B1 (en) * 2021-05-11 2023-07-05 주식회사 후레씨네코리아 Construction method of post-tensioned PC beam system

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200394787Y1 (en) * 2005-04-29 2005-09-07 홍석희 continuous structure system type precast prestressed concrete single slab girder bridge connecting and supporting the same bridge with one point supporting structure or strongly coupled integrated structure
KR100566653B1 (en) * 2005-09-09 2006-03-31 우경건설 주식회사 The middle point part continuous structure and the continuous method of prestressed concrete girder bridge

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200394787Y1 (en) * 2005-04-29 2005-09-07 홍석희 continuous structure system type precast prestressed concrete single slab girder bridge connecting and supporting the same bridge with one point supporting structure or strongly coupled integrated structure
KR100566653B1 (en) * 2005-09-09 2006-03-31 우경건설 주식회사 The middle point part continuous structure and the continuous method of prestressed concrete girder bridge

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102321582B1 (en) 2021-03-10 2021-11-05 (주)한맥기술 PSC I-type girder capable of adjusting transverse displacement using the tension member of the upper flange
KR102335963B1 (en) 2021-03-10 2021-12-07 (주)한맥기술 PS girder with improved structural performance by modifying the tension member arrangement structure of the lower flange
KR20230123201A (en) 2022-02-16 2023-08-23 (주)한맥기술 Multi-span PS girder and construction method of multi-span PS girder
KR102509254B1 (en) 2022-10-27 2023-03-14 (주)한맥기술 A method of measuring the displacement information of a girder capable of calculating the rotational displacement information of a PSC type I girder and a bridge construction method using the same

Also Published As

Publication number Publication date
KR20090100537A (en) 2009-09-24

Similar Documents

Publication Publication Date Title
KR101131969B1 (en) Continuous Construction Method for Composite Bridge using Prestressed I-Type Girder
KR100991869B1 (en) Single and continuous prestressed concrete girder bridge and the construction method
KR100349864B1 (en) The Structural Continuity Method for Prestreseed Concrete Bridge of Composite I-Beam
KR101223699B1 (en) Prestressed steel girder and it&#39;s manufacture and construction method which used pretensioning steel plate
KR100988074B1 (en) Girder bridge connected to abutment and the construction method thereof
KR100982974B1 (en) Method for manufacturing multi-span continuous re-prestressed preflex composite bridge
CN110924287A (en) Semi-fabricated large-span combined box girder and construction method thereof
KR20100025162A (en) Precast psc t-type girder bridge and its construction method
KR101242842B1 (en) Construction method for corrugated steel plate web-psc composite beam
KR100398021B1 (en) Prestressed concrete slab reinforced by various section girder and construction method of simple and continuous supported slab bridge using the same
KR100720996B1 (en) Continuous bridge construction method using precast slab
KR100823448B1 (en) The improved seismic resistant continuation structure of prestressed concrete composite beam bridge and method thereof
KR20090122608A (en) Prestressed concrete composite girder
KR101060566B1 (en) Continuous method of multi-span PS beam using plate type tension material
KR100785634B1 (en) Continuation structure of prestressed concrete composite beam bridge and method thereof
KR20130107870A (en) Psc girder segment with connecting anchor block, psc girder and modular psc girder bridge construction method using the same
KR200342287Y1 (en) A structure of prestressed preflex steel composite beam prestressed by each construction steps
KR20130090709A (en) Construction method for corrugated steel plate web-psc composite beam
KR100712622B1 (en) Continuous Preflex Girder Structure Using Prestress in Parent Section Using Expanded Concrete and Its Construction Method
KR100724739B1 (en) Construction method of PSC Girder bridge using Retensionable and Detensionable anchorage with unbonded tendon
KR100989153B1 (en) Psc girder connection structure with strength connector detail for substitution of rebar placement in deck and bridge construction method using the same
KR20040102470A (en) Continuous multi-span bridge using bridge girder units and construction method thereof
KR20060017949A (en) Field-fabricated prestressing steel-composed girder and construction method of continuous bridge using the girder
KR100720997B1 (en) Continuous bridge construction method using concrete slab
KR102033052B1 (en) Method for constructing truss bridge support with infilled tube using src girder

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E902 Notification of reason for refusal
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20160212

Year of fee payment: 5

LAPS Lapse due to unpaid annual fee