KR20060008453A - Bridge construction work method - Google Patents

Bridge construction work method Download PDF

Info

Publication number
KR20060008453A
KR20060008453A KR1020040056191A KR20040056191A KR20060008453A KR 20060008453 A KR20060008453 A KR 20060008453A KR 1020040056191 A KR1020040056191 A KR 1020040056191A KR 20040056191 A KR20040056191 A KR 20040056191A KR 20060008453 A KR20060008453 A KR 20060008453A
Authority
KR
South Korea
Prior art keywords
forming
ceiling
assembly
side wall
box
Prior art date
Application number
KR1020040056191A
Other languages
Korean (ko)
Inventor
김근택
Original Assignee
김근택
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김근택 filed Critical 김근택
Priority to KR1020040056191A priority Critical patent/KR20060008453A/en
Publication of KR20060008453A publication Critical patent/KR20060008453A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/04Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

본 발명은 첫 번째 경간뿐만 아니라, 첫 번째 경간에서 콘크리트를 타설할 때 두 번째 경간에 해당되는 교각에 지지수단을 매개로 받침수단과 하면 형성판을 먼저 가설한 상태에서 작업자의 작업 공간을 충분히 확보한 후에 측벽부 형성 철근 조립체와 바닥부 형성 철근 조립체를 설치한 다음 외부 거푸집을 상기 받침수단상에 설치한 후에 콘크리트를 타설함으로써, 작업 영역이 충분히 확보된 상태에서 작업자가 시공 작업을 수행할 수 있으며, 이로 인해 시공 시간을 대폭 단축시킬 수 있도록 한 교량 시공방법을 제공하는 것을 목적으로 한다.The present invention, as well as the first span, when the concrete is placed in the first span, the working means of the worker is sufficiently secured in the state in which the supporting means and the lower plate forming plate is installed first through the support means in the piers corresponding to the second span. After installing the sidewall forming reinforcing bar assembly and the bottom forming reinforcing bar assembly and then installing the external formwork on the supporting means and placing concrete, the worker can perform the construction work with sufficient working area. Therefore, it aims to provide a bridge construction method that can significantly shorten the construction time.

상기와 같은 목적을 달성하기 위한 본 발명은, 일정한 간격을 두고 다수개 설치된 교각위에 천정부와 바닥부와 양측벽부 및 중앙에 중공부가 구비된 박스형 거더를 시공하는 교량의 시공방법에 있어서, 상기 교각들중 첫 번째 경간에 해당되는 교각 사이에 소정 높이의 지지수단을 매개로 하여 받침수단을 설치하는 제1 단계와; 상기 받침수단을 상면에 상기 박스형 거더를 구성하는 바닥부의 하면의 하면을 형성하기 위한 하면 형성판을 설치하는 제2 단계와; 상기 하면 형성판위에 박스형 거더를 구성하는 양측벽부 및 바닥부를 형성하기 위한 측벽부 형성 철근 조립체와 바닥부 형성 철근 조립체를 설치하는 제3 단계와; 상기 양측벽부의 외면과 이에 인접한 상기 천정부의 외면을 형성하기 위한 외면 형성판이 구비된 외부 거푸집을 상기 받침수단상에 설치하여 상기 외면 형성판과 상기 하면 형성판이 서로 접촉시키는 제4 단계와; 상기 박스형 거더를 구성하는 중공부의 내면을 형성하기 위해 상 기 측벽부 형성 철근 조립체와 바닥부 형성 철근 조립체와 천정부 형성 철근 조립체 각각의 내면을 지지하도록 내부 거푸집을 설치하는 제5 단계와; 상기 측벽부 형성 철근 조립체의 상부에 상기 박스형 거더를 구성하는 천정부를 형성하기 위한 천정부 형성 철근 조립체를 연결 설치하는 제6 단계와; 상기 측벽부 형성 철근 조립체와 바닥부 형성 철근 조립체 및 상기 천정부 형성 철근 조립체에 콘크리트를 타설하는 제7 단계와; 상기 제7 단계를 진행함과 동시에 상기 교각들중 두 번째 경간에 해당되는 교각에 상기 제1,제2,제3,제4,제5,제6, 제7 단계를 반복적으로 진행하여 경간 전체에 한 경간씩 순서적으로 시공하는 것을 특징으로 한다.The present invention for achieving the above object, in the construction method of the bridge for constructing a box-shaped girders provided with a ceiling and a bottom portion, both side wall portion and a hollow portion in the center on a plurality of bridges installed at regular intervals, the bridges A first step of installing the support means through the support means having a predetermined height between the piers corresponding to the first span of the bridge; A second step of installing a lower surface forming plate for forming a lower surface of a lower surface of a bottom part of the box-shaped girder on the upper surface of the supporting means; A third step of installing a sidewall forming reinforcing bar assembly and a bottom forming bar forming bar assembly for forming both side wall portions and a bottom portion constituting a box-shaped girder on the bottom forming plate; A fourth step of installing an external formwork having an outer surface forming plate for forming an outer surface of the ceiling and the adjacent side wall portions on the supporting means to contact the outer surface forming plate and the lower surface forming plate with each other; A fifth step of installing an inner formwork to support the inner surfaces of each of the side wall forming reinforcing bar assembly and the bottom forming reinforcing bar assembly and the ceiling forming reinforcing bar assembly to form an inner surface of the hollow part constituting the box girder; A sixth step of connecting and installing a ceiling forming reinforcing bar assembly for forming a ceiling constituting the box-shaped girder on top of the side wall forming bar reinforcing bar assembly; A seventh step of placing concrete on the sidewall forming rebar assembly and the bottom forming rebar assembly and the ceiling forming rebar assembly; At the same time, the first, second, third, fourth, fifth, sixth, and seventh steps are repeatedly performed on the bridge corresponding to the second span of the bridges. It is characterized in that the construction in order one by one span.

교량, 거더, 타설, Bridges, girders, pours,

Description

교량 시공방법{bridge construction work method}Bridge construction work method

도 1은 종래 기술에 의한 교량 시공방법의 흐름도.1 is a flow chart of a bridge construction method according to the prior art.

도 2는 본 발명에 의한 교량 시공방법의 흐름도.2 is a flow chart of the bridge construction method according to the present invention.

도 3 내지 도 10은 본 발명의 시공 방법에 따른 도면화하여 순서적으로 나타낸 도면.3 to 10 are drawings according to the construction method of the present invention in order shown.

도 11 및 도 12는 본 발명의 시공 방법에 의해 완성된 박스형 거더의 단면도.11 and 12 are cross-sectional views of the box girders completed by the construction method of the present invention.

<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for the main parts of the drawings>

200,210 : 교각200,210: piers

300 : 중앙 벤트 구조물300: center vent structure

310,320 : 사이드 벤트 구조물310,320: Side Vent Structure

330 : 하면 형성판330: lower surface forming plate

400 : 받침수단400: support means

510 : 외부 거푸집510: external formwork

600 : 측벽부 형성 철근 조립체600: side wall forming rebar assembly

610 : 바닥부 형성 철근 조립체610: bottom forming rebar assembly

620 : 천정부 형성 철근 조립체620: ceiling forming rebar assembly

630 : 내부 거푸집630: internal formwork

본 발명은 교량 시공방법에 관한 것으로, 더욱 상세하게는 첫 번째 경간 뿐만 아니라, 첫 번째 경간에서 콘크리트를 타설할 때 두 번째 경간에 해당되는 교각에 지지수단을 매개로 받침수단과 하면 형성판을 먼저 가설한 상태에서 작업자의 작업 공간을 충분히 확보한 후에 측벽부 형성 철근 조립체와 바닥부 형성 철근 조립체를 설치한 다음 외부 거푸집을 상기 받침수단상에 설치한 후에 콘크리트를 타설함으로써, 작업 영역이 충분히 확보된 상태에서 작업자가 시공 작업을 수행할 수 있으며, 이로 인해 시공 시간을 대폭 단축시킬 수 있도록 한 교량 시공방법에 관한 것이다.The present invention relates to a bridge construction method, and more particularly, when the concrete is laid in the first span as well as the first span, the supporting means and the lower plate forming plate first through the support means in the piers corresponding to the second span. After securing sufficient working space of the worker in the hypothetical state, the side wall forming rebar assembly and the bottom forming reinforcing assembly are installed, and the external formwork is installed on the supporting means, and then concrete is poured to secure the working area. The construction can be performed by the operator in the state, and this relates to a bridge construction method that can significantly shorten the construction time.

일반적으로, 교량의 시공 방법으로 MSS 공법, ILM 공법, FCM 공법, PSM 공법, FSM 공법등이 있는데, 이중에서 FSM(Full Staging Method;동바리 공법) 공법은 상기 MSS 공법, ILM 공법, FCM 공법, PSM 공법에 밀려 그 사용예가 줄어들고 있으나, 사용 장비의 비용이 저렴하고 비교적 간편한 장점이 있기 때문에, 지금도 평탄한 지형에 적당한 높이의 짧은 교량을 가설할 경우에는 보편적으로 많이 이용되고 있다.In general, bridge construction methods include MSS method, ILM method, FCM method, PSM method, FSM method, among which FSM (Full Staging Method) method is the MSS method, ILM method, FCM method, PSM method Due to the push of the construction method is decreasing, but because of the low cost and relatively easy advantage of the equipment used, it is still widely used when constructing a short bridge of a suitable height on the flat terrain.

상기 FSM(Full Staging Method;동바리 공법) 공법을 이용한 교량 방법은 콘크리트를 타설하는 경간 전체에 걸쳐 동바리를 설치하여 타설된 콘크리트가 소정의 강도에 도달할 때까지 콘크리트의 자중 및 거푸집, 작업대등의 중량을 일반적으로 동바리가 지지하는 방식으로, 경간 전체에 걸쳐 작업대, 거푸집 및 동바리를 설치하고, 콘트리트를 타설/양생한 후 프리스트레싱 작업을 하여 교량을 건설하는 공법이다.Bridge method using the FSM (Full Staging Method) method is to install the copper bar throughout the span of the concrete, the weight of the concrete weight, formwork, work table, etc. until the concrete reaches a predetermined strength It is a method of constructing bridges by prestressing after installing / working concrete, placing workbench, formwork and clubs throughout the span, and supporting them.

상기와 같은 FSM(Full Staging Method;동바리 공법) 공법을 이용한 교량중 교각위에 시공되는 거더중 천정부와 바닥부와 양측벽부 및 중앙에 중공부가 구비된 박형 거더 타입을 최근에 들어 시공을 많이 하고 있다.In recent years, many girders are installed on the pier of the bridge using the Full Staging Method (FSM) method as described above.

상기와 같은 거더 타입의 시공 방법은 교각들중 첫 번째 경간에 해당되는 교각 사이에 동바리 등의 지지수단을 이용하여 받침수단을 가설한 후, 이 받침수단의 상면에 박스형 거더를 구성하는 바닥부 하면을 형성하기 위한 하면 형성판을 설치한다(1)(제1 단계)In the construction method of the girder type as described above, after installing the supporting means using a supporting means such as a club between the bridges corresponding to the first span of the bridges, the bottom of the bottom constituting the box-shaped girders on the upper surface of the supporting means (1) (First Step)

다음으로, 상기 하면 형성판의 상면 양측에 한쌍의 외부 거푸집을 가설한다(2)(제2 단계) Next, a pair of external formwork is installed on both sides of the upper surface of the lower surface forming plate (2) (second step)

이후, 상기 하면 형성판의 상면에 박스형 거더의 측벽부 형성용 철근 조립체, 바닥부 형성용 철근 조립체와, 천정부 형성용 철근 조립체를 연결 설치한다.(3)(제3단계)Then, the reinforcing bar assembly for forming the side wall portion of the box-shaped girder, the reinforcing bar assembly for forming the bottom portion, and the reinforcing bar assembly for forming the ceiling are installed on the upper surface of the bottom forming plate.

계속하여 박스형 거더를 구성하는 중공부의 내면을 형성하기 위해 상기 측벽부 형성 철근 조립체와 바닥부 형성 철근 조립체와 천정부 형성 철근 조립체 각각의 내면을 지지하도록 내부 거푸집을 설치한다(4)(제4 단계)Subsequently, an internal formwork is installed to support the inner surfaces of each of the side wall forming reinforcing bar assembly, the bottom forming reinforcing bar assembly, and the ceiling forming reinforcing bar assembly to form the inner surface of the hollow part constituting the box-shaped girders (step 4).

다음으로, 상기 측벽부 형성 철근 조립체와 바닥부 형성 철근 조립체 및 상 기 천정부 형성 철근 조립체에 콘크리트를 타설한다.(5)(제5 단계)Next, concrete is poured into the sidewall forming rebar assembly, the bottom forming rebar assembly, and the ceiling forming rebar assembly. (5) (Step 5)

다음으로, 상기 교각들중 두 번째 경간에 해당되는 교각에 상기 제1,제2,제3,제4, 제5 단계를 반복하여 실시하여 경간 전체에 한 경간씩 순서적으로 시공한다.Next, the first, second, third, fourth, and fifth steps are repeatedly performed on the piers corresponding to the second span of the piers, and the construction is sequentially performed one by one over the entire span.

그러나, 상기와 같은 종래 FSM(Full Staging Method;동바리 공법) 공법은 다음과 같은 문제점이 있었다.However, the conventional Full Staging Method (FSM) method as described above has the following problems.

첫째, 종래 기술은 제1,제2,제3,제4 단계를 진행하여 한 경간에 걸쳐 박스형 거더를 완성한 후, 다음 경간에 걸쳐 상기 제1,2,3,4,5 단계를 반복하여 시공하기 때문에 시공 시간이 많이 걸려 공기를 단축시킬 수 없는 문제점이 있다.First, in the prior art, the first, second, third, and fourth steps are completed to complete the box girders over one span, and then the first, second, third, fourth, and fifth steps are repeated for the next span. Therefore, there is a problem in that it takes a lot of construction time to shorten the air.

둘째, 종래 기술은 상기 제1 단계를 진행한 다음, 제2 단계를 진행한 다음, 제3 단계를 진행하는 과정에서 상기 제1 단계에서 시공된 외부 거푸집에 의해 작업 공간이 축소되기 때문에 제2 단계인 하면 형성판과, 제3 단계인 측벽부 형성 철근 조립체와 바닥부 형성 철근 조립체 및 상기 천정부 형성 철근 조립체의 설치시 기 설치된 외부 거푸집 사이의 좁은 작업 공간에 작업자가 작업하기에 불편한 점이 있었으며, 이로 인해 시공 시간이 오히려 많이 걸리는 문제점이 있었다.Second, in the prior art, since the work space is reduced by the external formwork constructed in the first step, the second step is performed after the first step, the second step, and the third step. There was an inconvenience for a worker to work in a narrow work space between the lower surface forming plate, the third side wall forming reinforcing bar assembly and the bottom forming reinforcing bar assembly, and the external formwork installed during the installation of the ceiling forming reinforcing bar assembly. Due to the rather long construction time there was a problem.

본 발명은 상기와 같은 문제점을 해결하기 위해 창출된 것으로, 첫 번째 경간 뿐만 아니라, 첫 번째 경간에서 콘크리트를 타설할 때 두 번째 경간에 해당되는 교각에 지지수단을 매개로 받침수단과 하면 형성판을 먼저 가설한 상태에서 작업자의 작업 공간을 충분히 확보한 후에 측벽부 형성 철근 조립체와 바닥부 형성 철근 조립체를 설치한 다음 외부 거푸집을 상기 받침수단상에 설치한 후에 콘크리트를 타설함으로써, 작업 영역이 충분히 확보된 상태에서 작업자가 시공 작업을 수행할 수 있으며, 이로 인해 시공 시간을 대폭 단축시킬 수 있도록 한 교량 시공방법을 제공하는 것을 목적으로 한다.The present invention was created to solve the above problems, as well as the first span, when placing concrete in the first span when the support means in the piers corresponding to the second span through the support means and the lower plate forming plate First, secure enough working space for the worker in the state of installation, then install the sidewall forming reinforcing bar assembly and the bottom forming reinforcing bar assembly, and then install the external formwork on the supporting means, and then cast concrete to secure the working area. It is an object of the present invention to provide a bridge construction method that can allow a worker to perform a construction work in this state, thereby significantly reducing construction time.

상기와 같은 목적을 달성하기 위한 본 발명은, 일정한 간격을 두고 다수개 설치된 교각위에 천정부와 바닥부와 양측벽부 및 중앙에 중공부가 구비된 박스형 거더를 시공하는 교량의 시공방법에 있어서, 상기 교각들중 첫 번째 경간에 해당되는 교각 사이에 소정 높이의 지지수단을 매개로 하여 받침수단을 설치하는 제1 단계와; 상기 받침수단을 상면에 상기 박스형 거더를 구성하는 바닥부의 하면의 하면을 형성하기 위한 하면 형성판을 설치하는 제2 단계와; 상기 하면 형성판위에 박스형 거더를 구성하는 양측벽부 및 바닥부를 형성하기 위한 측벽부 형성 철근 조립체와 바닥부 형성 철근 조립체를 설치하는 제3 단계와; 상기 양측벽부의 외면과 이에 인접한 상기 천정부의 외면을 형성하기 위한 외면 형성판이 구비된 외부 거푸집을 상기 받침수단상에 설치하여 상기 외면 형성판과 상기 하면 형성판이 서로 접촉시키는 제4 단계와; 상기 박스형 거더를 구성하는 중공부의 내면을 형성하기 위해 상기 측벽부 형성 철근 조립체와 바닥부 형성 철근 조립체와 천정부 형성 철근 조립체 각각의 내면을 지지하도록 내부 거푸집을 설치하는 제5 단계와; 상기 측벽부 형성 철근 조립체의 상부에 상기 박스형 거더를 구성하는 천정부를 형성하기 위한 천정부 형성 철근 조립체를 연결 설치하는 제6 단계와; 상기 측벽부 형성 철근 조립 체와 바닥부 형성 철근 조립체 및 상기 천정부 형성 철근 조립체에 콘크리트를 타설하는 제7 단계와; 상기 제7 단계를 진행함과 동시에 상기 교각들중 두번째 경간에 해당되는 교각에 상기 제1,제2,제3,제4,제5,제6,제7 단계를 반복적으로 진행하여 경간 전체에 한 경간씩 순서적으로 시공하는 것을 특징으로 한다.The present invention for achieving the above object, in the construction method of the bridge for constructing a box-shaped girders provided with a ceiling and a bottom portion, both side wall portion and a hollow portion in the center on a plurality of bridges installed at regular intervals, the bridges A first step of installing the support means through the support means having a predetermined height between the piers corresponding to the first span of the bridge; A second step of installing a lower surface forming plate for forming a lower surface of a lower surface of a bottom part of the box-shaped girder on the upper surface of the supporting means; A third step of installing a sidewall forming reinforcing bar assembly and a bottom forming bar forming bar assembly for forming both side wall portions and a bottom portion constituting a box-shaped girder on the bottom forming plate; A fourth step of installing an external formwork having an outer surface forming plate for forming an outer surface of the ceiling and the adjacent side wall portions on the supporting means to contact the outer surface forming plate and the lower surface forming plate with each other; A fifth step of installing an internal formwork to support the inner surfaces of each of the side wall forming reinforcing bar assembly, the bottom forming reinforcing bar assembly and the ceiling forming reinforcing bar assembly to form an inner surface of the hollow part constituting the box-shaped girders; A sixth step of connecting and installing a ceiling forming reinforcing bar assembly for forming a ceiling constituting the box-shaped girder on top of the side wall forming bar reinforcing bar assembly; A seventh step of placing concrete on the sidewall forming rebar assembly, the bottom forming rebar assembly, and the ceiling forming rebar assembly; At the same time, the first, second, third, fourth, fifth, sixth, and seventh steps are repeatedly performed on the bridge corresponding to the second span of the bridges. It is characterized by constructing one by one sequentially.

이하, 본 발명에 의한 교량의 시공방법의 바람직한 실시예를 첨부된 도면을 참조하여 상세하게 설명하면 다음과 같다.Hereinafter, a preferred embodiment of the bridge construction method according to the present invention will be described in detail with reference to the accompanying drawings.

도 2는 본 발명에 의한 교량 시공방법의 흐름도이고, 도 3 내지 도 10은 본 발명의 시공 방법에 따른 도면화하여 순서적으로 나타낸 도면이며, 도 11 및 도 12는 본 발명의 시공 방법에 의해 완성된 박스형 거더의 단면도이다.2 is a flow chart of the bridge construction method according to the present invention, Figures 3 to 10 are drawings according to the construction method of the present invention shown in sequence, Figures 11 and 12 by the construction method of the present invention Sectional view of the finished box girders.

본 발명은 일정한 간격을 두고 다수개 설치된 설치된 교각(200)(210)위에 천정부(110)와 바닥부(120)와 양측벽부(130) 및 중앙에 중공부(140)가 구비된 박스형 거더(100)를 시공하는 교량의 시공방법에 있어서, FSM 공법을 적용하여 콘크리트를 현장에서 타설하여 시공하는 공법이다.The present invention is a box-shaped girders 100 provided with a ceiling portion 110 and a bottom portion 120 and both side wall portion 130 and a hollow portion 140 in the center on a plurality of installed piers (200, 210) at regular intervals. In the construction method of the bridge to construct), it is a construction method by placing concrete on the site by applying the FSM method.

본 발명의 시공 방법을 본 발명의 도면을 참조하여 좀더 상세하게 설명하면 다음과 같다.Referring to the construction method of the present invention in more detail with reference to the drawings as follows.

먼저, 상기 교각(200)(210)들중 첫 번째 경간에 해당되는 교각 사이에 소정 높이의 지지수단(310)(320)을 매개로 하여 받침수단(400)을 설치하는 제1 단계를 진행한다.(10)First, the first step of installing the support means 400 through the support means 310, 320 of a predetermined height between the piers corresponding to the first span of the piers 200, 210 proceeds. (10)

여기서, 상기 받침수단(400)은 중앙 벤트 구조물(300)과, 사이드 벤트 구조물(310)(320)을 포함하여 이루어진다.(도 3참조)Here, the support means 400 comprises a central vent structure 300, side vent structure 310, 320 (see Fig. 3).

상기 제1 단계를 진행하고 나서, 상기 받침수단(400)을 상면에 상기 박스형 거더(100)를 구성하는 바닥부(120)의 하면(120a)의 하면을 형성하기 위한 하면 형성판(330)을 설치하는 제2 단계를 진행한다.(20)(도 4참조)After the first step, the bottom forming plate 330 for forming a bottom surface of the bottom surface 120a of the bottom portion 120 constituting the box-shaped girders 100 on the top surface of the support means 400 Proceed with the second step of installation (20) (see Fig. 4).

상기 제3 단계를 진행하고 나서, 상기 하면 형성판(330)위에 박스형 거더(100)를 구성하는 양측벽부(130) 및 바닥부(120)를 형성하기 위한 측벽부 형성 철근 조립체(600)와 바닥부 형성 철근 조립체(610)를 설치하는 제3 단계를 진행한다.(30)(도 4참조,도 5참조)After proceeding to the third step, the side wall portion forming reinforcing bar assembly 600 and the bottom to form both side wall portion 130 and the bottom portion 120 constituting the box-shaped girders 100 on the bottom forming plate 330 Proceed to the third step of installing the secondary forming rebar assembly 610. (30, see Fig. 4, see Fig. 5).

상기 제3 단계를 진행하고 나서, 상기 양측벽부(130)의 외면과 이에 인접한 상기 천정부(110)의 외면을 형성하기 위한 외면 형성판(511)이 구비된 외부 거푸집(510)을 상기 하면 형성판(330)상에 설치하여 상기 외면 형성판(511)과 상기 하면 형성판(330)이 서로 접촉시키는 제4 단계를 진행한다.(40)(도 7참조)After the third step, the outer form plate 510 is provided with an outer form forming plate 511 for forming the outer surface of the side wall portion 130 and the outer surface of the ceiling portion 110 adjacent thereto. On the 330, a fourth step of contacting the outer surface forming plate 511 and the lower surface forming plate 330 with each other is performed. (40) (see FIG. 7).

여기서, 상기 외부 거푸집(510)의 설치 방법은 도 7에 도시된 바와 같이, 받침수단(400)의 상부에 레일(512)을 설치하고, 이 레일(512)을 따라 슬라이딩 이동하도록 외부 거푸집(510)에 로울러(513)를 설치하여 상기 외부 거푸집(510)을 밀게 되면 로울러(513)가 레일(512)을 따라 이동되도록 한 것이다.Here, the installation method of the external formwork 510, as shown in Figure 7, the rail 512 is installed on the upper portion of the support means 400, the external formwork 510 to slide along the rail 512 When the roller 513 is installed to push the external formwork 510, the roller 513 is moved along the rail 512.

한편, 상기 외부 거푸집(510)을 슬라이딩 이동시키는 방법 이외에도 크레인장비를 이용하여 별도로 설치할 수 있음은 물론이다.On the other hand, in addition to the method of sliding the external formwork 510 can be installed separately using a crane equipment, of course.

상기 제5 단계를 진행하고 나서, 상기 박스형 거더(100)를 구성하는 중공부(140)의 내면을 형성하기 위해 상기 측벽부 형성 철근 조립체(600)와 바닥부 형성 철근 조립체(610)와 천정부 형성 철근 조립체(620) 각각의 내면을 지지하도록 내부 거푸집(630)을 설치하는 제5 단계를 진행한다.(50)(도 9참조)After the fifth step, the sidewall forming rebar assembly 600 and the bottom forming rebar assembly 610 and the ceiling are formed to form the inner surface of the hollow part 140 constituting the box-shaped girder 100. The fifth step of installing the inner formwork 630 to support the inner surface of each of the rebar assembly 620 is carried out (50) (see Fig. 9).

상기 제5 단계를 진행하고 나서, 상기 측벽부 형성 철근 조립체(600)의 상부에 상기 박스형 거더(100)를 구성하는 천정부(110)를 형성하기 위한 천정부 형성 철근 조립체(620)를 연결 설치하는 제6 단계를 진행한다.(60)(도 10 참조)After the fifth step, the ceiling forming reinforcing bar assembly 620 for forming the ceiling portion 110 constituting the box-shaped girders 100 to the upper portion of the side wall forming reinforcing bar assembly 600 is installed Proceed to step 6 (60) (see FIG. 10).

상기 제6 단계를 진행하고 나서, 상기 측벽부 형성 철근 조립체(600)와 바닥부 형성 철근 조립체(610) 및 상기 천정부 형성 철근 조립체(620)에 콘크리트를 타설하는 제7 단계를 진행한다.(70)After the sixth step, the seventh step of pouring concrete into the sidewall forming rebar assembly 600, the bottom forming rebar assembly 610, and the ceiling forming rebar assembly 620 is performed. )

다음으로, 상기 제7 단계를 진행함과 동시에 상기 교각들중 두 번째 경간에 해당되는 교각에 상기 제1,제2,제3,제4,제5,제6, 제7 단계를 반복적으로 진행하여 경간 전체에 한 경간씩 순서적으로 시공하는 것이다.Subsequently, the first, second, third, fourth, fifth, sixth, and seventh steps are repeatedly performed in the pier corresponding to the second span of the pier at the same time as the seventh step. Thus, the construction is done one by one span over the span.

여기서, 본 발명은 상기 제3 단계에서 상기 측벽부 형성 철근 조립체(600)는 측부에 사이드 지지대(601)에 의해 지지되도록 설치하며,(도 4참조) 상기 측벽부 형성 철근 조립체(600)는 상부에 상부 지지대(602)에 의해 지지되도록 설치하며,(도 6참조) 상기 제4 단계에서 상기 외부 거푸집(510)의 설치전에 상기 사이드 지지대(601)를 제거하는 공정을 더 추가하여 실시한다.(도 7참조)Here, in the third step, the side wall forming rebar assembly 600 is installed in the third step so as to be supported by the side support 601 on the side (see FIG. 4), and the side wall forming reinforcing assembly 600 is upper part. It is installed so as to be supported by the upper support 602 (see Fig. 6), and in the fourth step, a step of removing the side support 601 before the installation of the external formwork 510 is further performed. See Figure 7)

여기서, 상기 사이드 지지대(601)를 설치하는 이유는 도 4 및 도 5에 도시된 바와 같이, 임시적으로 측벽부 형성 철근 조립체(600)를 지지하지 위함이다.Here, the reason for installing the side support 601 is to temporarily support the side wall forming rebar assembly 600, as shown in Figures 4 and 5.

그리고, 상기 외부 거푸집(510)은 상기 사이드 지지대(601)가 설치된 지점에 설치되어야 하기 때문에 이를 제거해야 하는데, 상기 사이드 지지대(601)를 제거하기 위해서는 도 6에 도시된 바와 같이, 측벽부 형성 철근 조립체(600)의 상부에 다 수개의 상부 지지대(602)를 연결하여 임시적으로 연결하여 측벽부 형성 철근 조립체(600)의 와해를 방지한다.In addition, the external formwork 510 should be removed because the side support 601 should be installed at the point where the side support 601 is installed. In order to remove the side support 601, as shown in FIG. A plurality of upper supports 602 are temporarily connected to the top of the assembly 600 to prevent breakage of the sidewall forming rebar assembly 600.

상기와 같이 상부 지지대(602)를 연결하고 나서, 사이드 지지대(601)를 제거한다.After connecting the upper support 602 as described above, the side support 601 is removed.

다음으로, 제거된 사이드 지지대(601)의 공간에 외부 거푸집(510)을 설치하는 것이다. Next, the outer formwork 510 is installed in the space of the removed side support 601.

한편, 본 발명은 상기 제4 단계를 진행한 후, 측벽부 형성 철근 조립체(600)와 바닥부 형성 철근 조립체(610)내에 다수개의 쉬스관(700)을 내장 설치하고, 상기 쉬스관(700)의 내부에 강선(710)을 삽입하는 단계를 더 포함할 수 도 있음은 물론이다.(도 5참조)On the other hand, according to the present invention, after the fourth step, a plurality of sheath pipes 700 are installed in the side wall forming rebar assembly 600 and the bottom forming rebar assembly 610, and the sheath pipe 700 is installed. Of course, it may further include the step of inserting the steel wire 710 in the (see Fig. 5).

그리고, 본 발명의 단계중 상기 콘크리트 타설 단계를 두가지 방법으로 실시할 수 있는데, 그 중 하나는 상기 측벽부 형성 철근 조립체(600)와 바닥부 형성 철근 조립체(610)내에 콘크리트를 타설하여 박스형 거더(100)를 구성하는 바닥부(120)와 양측벽부(130)를 동시에 형성하는 1회 타설단계와; 상기 단계를 진행한 후, 상기 콘크리트가 굳은 다음, 천정부 형성 철근 조립체(620)내에 콘크리트를 타설하여 상기 박스형 거더(100)를 구성하는 천정부(110)를 형성하는 2회 타설단계로 이루어진다.In addition, the concrete placing step of the step of the present invention can be carried out in two ways, one of which is to cast concrete in the sidewall forming reinforcing assembly 600 and the bottom forming reinforcing assembly 610 to box-shaped girders ( A one-time pouring step of simultaneously forming the bottom portion 120 and both side wall portions 130 constituting the 100; After the above step, the concrete is hardened, and then the concrete is placed in the ceiling forming reinforcing bar assembly 620 consists of two casting steps to form the ceiling (110) constituting the box-shaped girders (100).

상기와 같이 실시함으로, 도 12에 도시된 바와 같이, 박스형 거더(100)를 구성하는 바닥부(120)와 양측벽부(130)는 일체형의 단면이 되고, 천정부(110)는 별도의 단면을 가지게 된다.By performing as described above, as shown in Figure 12, the bottom portion 120 and the side wall portion 130 constituting the box-shaped girder 100 is an integral cross section, the ceiling portion 110 to have a separate cross section do.

한편, 콘트리트 타설 방법중 나머지 하나는 상기 측벽부 형성 철근 조립체(600)와 바닥부 형성 철근 조립체(610)와 천정부 형성 철근 조립체(620)내에 콘크리트를 1회 타설하여 박스형 거더(100)를 구성하는 천정부(110)와 바닥부(120)와 양측벽부(130) 및 중앙에 중공부(140)를 동시에 형성하는 것이다.On the other hand, the other one of the concrete placing method is to cast the concrete in the sidewall forming rebar assembly 600, the bottom forming rebar assembly 610 and the ceiling forming rebar assembly 620 once to form a box-shaped girders (100) The ceiling portion 110 and the bottom portion 120 and both side wall portion 130 and the hollow portion 140 is formed at the same time.

상기와 같이 실시함으로, 도 11에 도시된 바와 같이, 박스형 거더(100)를 구성하는 바닥부(120)와 양측벽부(130) 및 천정부(110)는 하나의 단면을 갖는 일체형으로 형성되는 것이다.By performing as described above, as shown in Figure 11, the bottom portion 120 and the side wall portion 130 and the ceiling portion 110 constituting the box-shaped girders 100 is formed integrally having a single cross-section.

이상 살펴본 바와 같이, 본 발명에 의한 교량 시공방법은, 첫 번째 경간뿐만 아니라, 첫 번째 경간에서 콘크리트를 타설할 때 두 번째 경간에 해당되는 교각에 지지수단을 매개로 받침수단과 하면 형성판을 먼저 가설한 상태에서 작업자의 작업 공간을 충분히 확보한 후에 측벽부 형성 철근 조립체와 바닥부 형성 철근 조립체를 설치한 다음 외부 거푸집을 상기 받침수단상에 설치한 후에 콘크리트를 타설함으로써, 작업 영역이 충분히 확보된 상태에서 작업자가 시공 작업을 수행할 수 있으며, 이로 인해 시공 시간을 대폭 단축시킬 수 있게 된다.

As described above, in the bridge construction method according to the present invention, when placing concrete in the first span as well as the first span, the supporting means and the lower plate forming plate first through the support means in the piers corresponding to the second span. After securing sufficient working space of the worker in the hypothetical state, the side wall forming rebar assembly and the bottom forming reinforcing assembly are installed, and the external formwork is installed on the supporting means, and then concrete is poured to secure the working area. In the state, the operator can perform the construction work, which can greatly reduce the construction time.

Claims (5)

일정한 간격을 두고 다수개 설치된 교각(200)(210)위에 천정부(110)와 바닥부(120)와 양측벽부(130) 및 중앙에 중공부(140)가 구비된 박스형 거더(100)를 시공하는 교량의 시공방법에 있어서,Constructing a box-shaped girders 100 provided with a ceiling part 110, a bottom part 120, both side wall parts 130, and a hollow part 140 in the center on a plurality of bridges 200 and 210 installed at regular intervals. In the construction method of the bridge, 상기 교각(200)(210)들중 첫 번째 경간에 해당되는 교각 사이에 소정 높이의 지지수단(310)(320)을 매개로 하여 받침수단(400)을 설치하는 제1 단계와;A first step of installing the support means (400) through the support means (310, 320) of a predetermined height between the bridges corresponding to the first span of the bridges (200, 210); 상기 받침수단(400)을 상면에 상기 박스형 거더(100)를 구성하는 바닥부(120)의 하면(120a)의 하면을 형성하기 위한 하면 형성판(330)을 설치하는 제2 단계와;A second step of installing a lower surface forming plate (330) for forming a lower surface of the lower surface (120a) of the bottom portion (120) constituting the box-shaped girder (100) on the upper surface of the supporting means (400); 상기 하면 형성판(330)위에 박스형 거더(100)를 구성하는 양측벽부(130) 및 바닥부(120)를 형성하기 위한 측벽부 형성 철근 조립체(600)와 바닥부 형성 철근 조립체(610)를 설치하는 제3 단계와;The side wall forming rebar assembly 600 and the bottom forming rebar assembly 610 for forming both side wall portions 130 and the bottom portion 120 constituting the box-shaped girder 100 are installed on the bottom forming plate 330. Performing a third step; 상기 양측벽부(130)의 외면과 이에 인접한 상기 천정부(110)의 외면을 형성하기 위한 외면 형성판(511)이 구비된 외부 거푸집(510)을 상기 받침수단(400)상에 설치하여 상기 외면 형성판(511)과 상기 하면 형성판(330)이 서로 접촉시키는 제4 단계와;The outer surface is formed by installing an outer formwork 510 having an outer surface forming plate 511 for forming an outer surface of the both side wall portions 130 and an outer surface of the ceiling 110 adjacent thereto on the support means 400. A fourth step of bringing the plate 511 and the lower surface forming plate 330 into contact with each other; 상기 박스형 거더(100)를 구성하는 중공부(140)의 내면을 형성하기 위해 상기 측벽부 형성 철근 조립체(600)와 바닥부 형성 철근 조립체(610)와 천정부 형성 철근 조립체(620) 각각의 내면을 지지하도록 내부 거푸집(630)을 설치하는 제5 단 계와;In order to form an inner surface of the hollow part 140 constituting the box-shaped girder 100, an inner surface of each of the sidewall forming rebar assembly 600, the bottom forming rebar assembly 610, and the ceiling forming rebar assembly 620 is formed. A fifth step of installing the inner formwork 630 to support it; 상기 측벽부 형성 철근 조립체(600)의 상부에 상기 박스형 거더(100)를 구성하는 천정부(110)를 형성하기 위한 천정부 형성 철근 조립체(620)를 연결 설치하는 제6 단계와;A sixth step of connecting and installing the ceiling forming reinforcing bar assembly (620) for forming the ceiling part (110) constituting the box-shaped girder (100) on the sidewall forming bar (600); 상기 측벽부 형성 철근 조립체(600)와 바닥부 형성 철근 조립체(610) 및 상기 천정부 형성 철근 조립체(620)에 콘크리트를 타설하는 제7 단계와;A seventh step of placing concrete in the sidewall forming rebar assembly (600), the bottom forming rebar assembly (610), and the ceiling forming rebar assembly (620); 상기 제7 단계를 진행함과 동시에 상기 교각들중 두 번째 경간에 해당되는 교각에 상기 제1,제2,제3,제4,제5,제6,제7 단계를 반복적으로 진행하여 경간 전체에 한 경간씩 순서적으로 시공하는 것을 특징으로 하는 교량 시공방법.At the same time, the first, second, third, fourth, fifth, sixth, and seventh steps are repeatedly performed on the bridge corresponding to the second span of the bridges. Bridge construction method characterized in that the construction in order one by one span. 제 1 항에 있어서,The method of claim 1, 상기 제4 단계를 진행한 후, 측벽부 형성 철근 조립체(600)와 바닥부 형성 철근 조립체(610)내에 다수개의 쉬스관(700)을 내장 설치하고, 상기 쉬스관(700)의 내부에 강선(710)을 삽입하는 단계를 더 포함하는 것을 특징으로 하는 교량 시공방법.After the fourth step, a plurality of sheath pipes 700 are built-in in the side wall forming rebar assembly 600 and the bottom forming rebar assembly 610, and a steel wire is formed inside the sheath pipe 700. Bridge construction method further comprises the step of inserting (710). 제 1 항에 있어서,The method of claim 1, 상기 콘크리트 타설 단계는,The concrete pouring step, 상기 측벽부 형성 철근 조립체(600)와 바닥부 형성 철근 조립체(610)내에 콘크리트를 타설하여 박스형 거더(100)를 구성하는 바닥부(120)와 양측벽부(130)를 동시에 형성하는 1회 타설단계와;Placing concrete in the sidewall forming rebar assembly 600 and the bottom forming rebar assembly 610 to form the bottom 120 and both side wall 130 at the same time to form a box-shaped girder 100 at the same time Wow; 상기 단계를 진행한 후, 상기 콘크리트가 굳은 다음, 천정부 형성 철근 조립체(620)내에 콘크리트를 타설하여 상기 박스형 거더(100)를 구성하는 천정부(110)를 형성하는 2회 타설단계로 이루어진 것을 특징으로 하는 교량 시공방법.After the above step, the concrete is solidified, and then cast the concrete in the ceiling-formed reinforcing bar assembly 620 to form a two-stage casting step to form the ceiling (110) constituting the box-shaped girders (100) Bridge construction method. 제 1 항에 있어서,The method of claim 1, 상기 콘트리트 타설 단계는,The concrete pouring step, 상기 측벽부 형성 철근 조립체(600)와 바닥부 형성 철근 조립체(610)와 천정부 형성 철근 조립체(620)내에 콘크리트를 1회 타설하여 박스형 거더(100)를 구성하는 천정부(110)와 바닥부(120)와 양측벽부(130) 및 중앙에 중공부(140)를 동시에 형성하는 것을 특징으로 하는 교량 시공방법.The ceiling part 110 and the bottom part 120 which form the box-type girder 100 by pouring concrete once in the side wall forming reinforcing assembly 600, the bottom forming reinforcing bar assembly 610, and the ceiling forming reinforcing bar assembly 620. ) And both side wall portion 130 and the bridge construction method, characterized in that to form the hollow portion 140 at the same time. 제 1 항에 있어서,The method of claim 1, 상기 제3 단계에서 상기 측벽부 형성 철근 조립체(600)는 측부에 사이드 지지대(601)에 의해 지지되도록 설치하며,In the third step, the side wall forming rebar assembly 600 is installed to be supported by the side support 601 on the side, 상기 측벽부 형성 철근 조립체(600)는 상부에 상부 지지대(602)에 의해 지지되도록 설치하며, The side wall portion forming reinforcing assembly 600 is installed to be supported by the upper support 602 on the top, 상기 제4 단계에서 상기 외부 거푸집(510)의 설치전에 상기 사이드 지지대(501)를 제거하는 것을 특징으로 하는 교량 시공방법.Bridge construction method, characterized in that to remove the side support (501) before the installation of the external formwork (510) in the fourth step.
KR1020040056191A 2004-07-20 2004-07-20 Bridge construction work method KR20060008453A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020040056191A KR20060008453A (en) 2004-07-20 2004-07-20 Bridge construction work method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020040056191A KR20060008453A (en) 2004-07-20 2004-07-20 Bridge construction work method

Publications (1)

Publication Number Publication Date
KR20060008453A true KR20060008453A (en) 2006-01-27

Family

ID=37119479

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020040056191A KR20060008453A (en) 2004-07-20 2004-07-20 Bridge construction work method

Country Status (1)

Country Link
KR (1) KR20060008453A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101011417B1 (en) * 2010-09-10 2011-01-28 (주)아크메엔지니어링 System Formwork for FSM
CN103352427A (en) * 2013-07-04 2013-10-16 中铁十三局集团电务工程有限公司 Cast-in-place box beam lateral die sliding construction device and method
CN104372890A (en) * 2014-11-07 2015-02-25 成龙建设集团有限公司 Construction method of bare concrete prefabricated box beam with complicated structure
CN104499434A (en) * 2014-12-16 2015-04-08 中铁大桥局集团有限公司 Movable formwork for casting of wide-body box girder and construction method
CN114182616A (en) * 2021-12-27 2022-03-15 任江利 Box girder template for road and bridge building
CN116874314A (en) * 2023-07-11 2023-10-13 重庆工程职业技术学院 Large-volume pier column hydration heat control device

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101011417B1 (en) * 2010-09-10 2011-01-28 (주)아크메엔지니어링 System Formwork for FSM
CN103352427A (en) * 2013-07-04 2013-10-16 中铁十三局集团电务工程有限公司 Cast-in-place box beam lateral die sliding construction device and method
CN104372890A (en) * 2014-11-07 2015-02-25 成龙建设集团有限公司 Construction method of bare concrete prefabricated box beam with complicated structure
CN104499434A (en) * 2014-12-16 2015-04-08 中铁大桥局集团有限公司 Movable formwork for casting of wide-body box girder and construction method
CN114182616A (en) * 2021-12-27 2022-03-15 任江利 Box girder template for road and bridge building
CN114182616B (en) * 2021-12-27 2023-09-05 任江利 Box girder template for road bridge construction
CN116874314A (en) * 2023-07-11 2023-10-13 重庆工程职业技术学院 Large-volume pier column hydration heat control device
CN116874314B (en) * 2023-07-11 2024-03-19 重庆工程职业技术学院 Large-volume pier column hydration heat control device

Similar Documents

Publication Publication Date Title
KR100667921B1 (en) Construction method of pylon using precast concrete beam
JP4569878B2 (en) Bridge girder construction method
CN104109999A (en) Construction method for bridge tower transverse beams
CN210067002U (en) Support-free assembled frame structure system
KR20110115349A (en) Pier cap installation structure using precast concrete shell and construction method thereof
CN110821022A (en) Full-prefabricated high-strength PC floor in steel construction that can install fast
KR101127130B1 (en) A precast type pre-stress box girder bridge excution method
KR20060008453A (en) Bridge construction work method
CN108316150B (en) Construction system and construction method for main tower and steel anchor beam of cable-stayed bridge
JP6889010B2 (en) Bridge construction method
CN111441576A (en) Method and structure for pouring concrete beam post-cast strip by adopting inflatable template
CN110847239A (en) Assembled large reinforced concrete prefabricated inspection well and construction method thereof
CN115573597A (en) Fully-assembled concrete canopy and construction method thereof
CN210421625U (en) Cast-in-place combination beam structure of assembled
CN112359965A (en) Precast concrete assembled structure with rib mold structure and construction method thereof
JP7134133B2 (en) Bridge railing construction method
JP4425500B2 (en) How to install arch ribs
JP4071981B2 (en) Construction method of large section box culvert
JP5714337B2 (en) Railway viaduct pillar replacement method
CN112281635A (en) Novel track full-assembly type integrated industrialization system
KR20100045740A (en) Support assembly for precast half depth cantilever deck, constructing method of such cantilever deck, bridge using such assembly and constructing method for such bridge
JP2004084322A (en) Method of constructing concrete pier
CN214061940U (en) Precast concrete assembled structure with rib mold structure
KR102149661B1 (en) Method for constructing overground transfer layer of building using precast concrete
CN219450404U (en) Thin-wall hollow pier top prestress steel strand construction positioning framework

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
AMND Amendment
E601 Decision to refuse application
J201 Request for trial against refusal decision
AMND Amendment
E801 Decision on dismissal of amendment
B601 Maintenance of original decision after re-examination before a trial
J301 Trial decision

Free format text: TRIAL DECISION FOR APPEAL AGAINST DECISION TO DECLINE REFUSAL REQUESTED 20070209

Effective date: 20070827