KR20060005466A - Method of drain construction for basement - Google Patents

Method of drain construction for basement Download PDF

Info

Publication number
KR20060005466A
KR20060005466A KR1020040054265A KR20040054265A KR20060005466A KR 20060005466 A KR20060005466 A KR 20060005466A KR 1020040054265 A KR1020040054265 A KR 1020040054265A KR 20040054265 A KR20040054265 A KR 20040054265A KR 20060005466 A KR20060005466 A KR 20060005466A
Authority
KR
South Korea
Prior art keywords
drainage
pipe
concrete
groundwater
basement floor
Prior art date
Application number
KR1020040054265A
Other languages
Korean (ko)
Other versions
KR100655384B1 (en
Inventor
엄기형
Original Assignee
엄기형
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 엄기형 filed Critical 엄기형
Priority to KR1020040054265A priority Critical patent/KR100655384B1/en
Publication of KR20060005466A publication Critical patent/KR20060005466A/en
Application granted granted Critical
Publication of KR100655384B1 publication Critical patent/KR100655384B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/10Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure
    • E02D31/12Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure against upward hydraulic pressure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0006Plastics
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0085Geotextiles

Abstract

본 발명은 지하층 바닥에 배수로를 형성하는 배수시공 방법에 있어서, 지층에 굴토를 행하여 집수정 및 굴토마감면을 형성하는 굴토단계; 상기 굴토마감면 상에 버림콘크리트를 타설하는 단계; 상기 버림콘크리트에 지하수 유도 홀을 형성하는 단계 ; 상기 버림콘크리트 상에 등간격으로 배치된 배수판을 주배수부재에 연결하고, 상기 주배수부재의 일단을 상기 집수정에 연결하여 배수로를 형성하는 단계; 상기 버림콘크리트와 상기 시스템 배수로 상에 비닐을 설치하는 단계; 및 상기 비닐 상에 지하층 바닥을 형성하기 위하여 구체콘크리트를 타설하는 단계를 포함하여 이루어지는 것을 특징으로 하는 지하층 바닥 배수시공 방법이다.The present invention provides a drainage method for forming a drainage path in a basement floor, comprising: a gulto step of forming a water collecting well and a gulto finish surface by performing gulting on a stratum; Casting the discarded concrete onto the gulting finish surface; Forming a groundwater guide hole in the discarded concrete; Connecting drain plates disposed at equal intervals on the discarded concrete to a main drain member, and connecting one end of the main drain member to the sump to form a drainage path; Installing vinyl on the discarded concrete and the system drain; And pouring concrete concrete to form the basement floor on the vinyl.

배수판, 배수관, 다발관, 배수시스템, 지하수, 수위조절관, 집수정Drain board, drain pipe, bundle pipe, drainage system, groundwater, water level control pipe, sump

Description

지하층 바닥 배수시공 방법{METHOD OF DRAIN CONSTRUCTION FOR BASEMENT}Basement floor drainage construction method {METHOD OF DRAIN CONSTRUCTION FOR BASEMENT}

도 1a는 본 발명의 제1실시예에 의한 지하층 바닥 배수시공 방법을 설명하기 위한 배수로의 평면도,Figure 1a is a plan view of the drainage for explaining the underground floor drainage construction method according to a first embodiment of the present invention,

도 1b는 본 발명의 제1실시예에 의한 배수로 형성시 주배수부재와 배수판이 연결되어 매설된 상태를 도시한 A-A선 단면도,1B is a cross-sectional view taken along line A-A showing a state in which a main drain member and a drain plate are embedded in a drainage path according to the first embodiment of the present invention;

도 2a는 본 발명의 제2실시예에 의한 지하층 바닥 배수시공 방법을 설명하기 위한 배수로의 평면도,Figure 2a is a plan view of the drainage for explaining the underground floor drainage construction method according to a second embodiment of the present invention,

도 2b는 본 발명의 제2실시예에 의한 배수로 형성시 시스템 배수로의 주배수부재가 버림콘크리트와 굴토마감면상을 지나 집수정에 연결되어 매설된 상태를 도시한 B-B선 단면도,2B is a cross-sectional view taken along line B-B showing a state in which the main drainage member of the system drainage drainage is connected to the water collecting well through the discarded concrete and the gulting dead face when forming the drainage drainage according to the second embodiment of the present invention;

도 3은 본 발명의 제3실시예에 의한 지하층 바닥 배수시공 방법을 설명하기 위한 배수로의 단면도,Figure 3 is a cross-sectional view of the drainage for explaining the underground floor drainage construction method according to a third embodiment of the present invention,

도 4는 본 발명의 제4실시예에 의한 지하층 바닥 배수시공 방법을 설명하기 위한 배수로의 단면도,Figure 4 is a cross-sectional view of the drainage for explaining the underground floor drainage construction method according to a fourth embodiment of the present invention,

도 5는 본 발명의 제5실시예에 의한 지하층 바닥 배수시공 방법을 설명하기 위한 배수로의 단면도,Figure 5 is a cross-sectional view of the drainage for explaining the underground floor drainage construction method according to a fifth embodiment of the present invention,

도 6은 본 발명의 제6실시예에 의한 지하층 바닥 배수시공 방법을 설명하기 위한 배수로의 단면도,Figure 6 is a cross-sectional view of the drainage for explaining the underground floor drainage construction method according to a sixth embodiment of the present invention,

도 7은 본 발명의 제7실시예에 의한 지하층 바닥 배수시공 방법을 설명하기 위한 배수로의 단면도,Figure 7 is a cross-sectional view of the drainage for explaining the underground floor drainage construction method according to a seventh embodiment of the present invention,

도 8은 본 발명의 제8실시예에 의한 지하층 바닥 배수시공 방법을 설명하기 위한 배수로의 단면도,8 is a cross-sectional view of a drainage path for explaining the underground floor drainage construction method according to an eighth embodiment of the present invention;

도 9는 본 발명의 제9실시예에 의한 지하층 바닥 배수시공 방법을 설명하기 위한 배수로의 단면도,9 is a cross-sectional view of a drainage path for explaining the underground floor drainage construction method according to the ninth embodiment of the present invention;

도 10은 본 발명의 제10실시예에 의한 지하층 바닥 배수시공 방법을 설명하기 위한 배수로의 단면도, 10 is a cross-sectional view of the drainage passage for explaining the underground floor drainage construction method according to a tenth embodiment of the present invention;

도 11은 본 발명의 제11실시예에 의한 지하층 바닥 배수시공 방법을 설명하기 위한 배수로의 평면도이다.11 is a plan view of a drainage passage for explaining a method for constructing a basement floor drain according to an eleventh embodiment of the present invention.

*도면의 주요부분에 대한 부호의 설명** Description of the symbols for the main parts of the drawings *

1 : 주배수부재 2: 배수판1: main drainage member 2: drainage plate

3 : 다발관 4 : 부배수부재3: bundle tube 4: secondary drainage member

5, 5a, 5b : 집수정 6 : 커넥터5, 5a, 5b: sump 6: connector

7 : 토목섬유 10 : 굴토마감면7: geotextile 10: oyster finish cotton

20 : 비닐 30 : 버림콘크리트20: vinyl 30: discarded concrete

40 : 구체콘크리트 50 : 지하수 유도 홀40: concrete concrete 50: groundwater guide hole

60 : 철근 70 : 자갈층60: rebar 70: gravel layer

80, 80a, 80b : 집수관 100, 100a : 트렌치80, 80a, 80b: collection pipe 100, 100a: trench

200 : 거푸집 300 : 수위조절관200: formwork 300: water level control pipe

400 : 공기구멍 500 : 플랜지400: air hole 500: flange

600 : 건물 외벽 700 : 맨홀600: outer wall of the building 700: manhole

800 : 보조배수부재 900 : 연결관800: auxiliary drain member 900: connector

A : 높이A: height

본 발명은 건축물의 하부로부터 침투하는 지하수를 집수정으로 유도하여 배수시키기 위한 지하층 바닥 배수시공 방법에 관한 것으로, 특히 버림콘크리트상에 배수판(드래인보드) 또는 다발관을 연결하여 배수로를 형성함에 있어서 토사의 유입을 차단하면서 지하수가 원활히 배수되도록 주배수부재 또는 부배수부재를 집수정에 직접 연결하는 방법으로 배수로를 형성하는 지하층 바닥 배수시공 방법에 관한 것이다.The present invention relates to an underground floor drainage construction method for inducing and draining groundwater penetrating from the lower part of a building to a water collecting well, and in particular, in forming a drainage path by connecting a drain board (drainboard) or a bundle pipe on a cast concrete. It relates to a basement floor drainage construction method for forming a drainage path by directly connecting the main drainage member or the secondary drainage member to the sump well so that the groundwater is smoothly drained while blocking the inflow of soil.

일반적으로 대형 건물 또는 건축물을 신축하게 되면 지하구조물의 시공이 필수로 수반되고, 이를 시공할 때 깊은 굴착이 이루어지므로 지하층의 바닥면에는 건축물의 사하중(자중)이 가해지며, 그와 동시에 상기 바닥면에는 지하수에 의한 상향수압(uplift pressure)이 작용하게 되는데, 이 때 사하중보다 상향수압이 크게 작용하는 경우 상기 건축물이 부상하게 되어 건축물의 바닥면, 벽체 등에 변형이 발생될 수 있다.In general, when a large building or a building is newly constructed, the construction of the underground structure is essential, and deep excavation is performed when the construction is performed. Therefore, the dead weight (self-weight) of the building is applied to the floor of the basement, and at the same time the floor There is an uplift pressure due to groundwater (uplift pressure) acts, at this time, if the upstream pressure is greater than the dead weight, the building rises may cause deformation, such as the floor, walls of the building.

따라서, 상기 지하층의 바닥면에 작용하는 상향수압을 감소시켜 주고, 상기 지하층의 바닥면으로부터 침투되는 지하수를 배수 처리하기 위한 적절한 배수시공이 요구되고 있다.Therefore, there is a need for an appropriate drainage construction to reduce the upward water pressure acting on the bottom surface of the basement layer and to drain the groundwater penetrating from the bottom surface of the basement layer.

상기 지하층의 바닥면에 작용하는 상향수압을 감소시켜 주기 위한 일반적인 시공 방법으로는 지하 구조물의 하부 암반층에 앵커(anchor)를 정착시켜 사하중과 영구앵커(permanent anchor)에 의하여 상향수압에 저항하도록 하는 앵커공법과 굴토마감면의 바닥면 상에 배수로를 형성하여 집수정으로 지속적인 배수를 실시하여 지하수의 수위를 떨어뜨려 지하층의 바닥면에 작용하는 상향수압을 억제시키는 배수공법이 주로 적용되고 있다.As a general construction method for reducing the upward pressure acting on the bottom surface of the basement layer anchors anchored in the lower rock layer of the underground structure to resist upward hydraulic pressure by dead weight and permanent anchor (permanent anchor) The drainage method is mainly applied to form a drainage path on the bottom surface of the gulto finish surface and to continuously drain the water well to reduce the water level of the groundwater to suppress the upward water pressure acting on the bottom surface of the basement layer.

먼저, 상기 앵커공법은 암반층까지 천공하고, 천공부분에 스트랜드를 삽입한 후 요구되는 하중 이상으로 인장하여 정착시키는 공정에 의하여 시공되므로 각 공정에 대한 공사비가 고가이고, 시공후 상기 천공부분에 방수하자가 많이 발생되는데 이에 대한 보수가 어려우며, 상기 앵커를 정착시키는데 고도의 기술과 다수의 공정이 요구되어 시공기간도 지하층의 바닥면에 배수로를 형성하는 배수공법보다 적어도 1개월 이상 지연되며, 상기 앵커공법에 요구되는 기술적인 문제인 인장력 손실, 방청, 유지보수 등을 해결할 수 있는 국내 전문 시공업체가 희소하여 시공에 부담이 되고 있다. 또한, 상기 앵커의 인장력 손실을 보완하기 위하여 재인장 시스템을 구성할 경우에는 공사비가 시공시보다 2~3배 이상 소요되는 문제점이 있다.First, the anchoring method is perforated to the rock layer, and after inserting the strand in the perforated portion is constructed by the process of tensioning and fixing more than the required load, the construction cost for each process is expensive, and after construction, let waterproof to the perforated portion There are a lot of occurrence is difficult to repair this, and a high technology and a number of processes are required to anchor the anchor construction period is also delayed at least one month or more than the drainage method of forming a drainage on the bottom of the basement layer, the anchor method There are few domestic construction companies that can solve the technical problems required for tension loss, rust prevention, and maintenance. In addition, when constructing a re-tensioning system to compensate for the loss of tensile strength of the anchor, there is a problem that the construction cost takes two to three times or more than when construction.

한편, 상기 배수공법의 경우 건축물의 지하층을 이루고 있는 구체콘크리트의 하부에 배수로를 형성하기 위한 수단으로 배수판 또는 다발관이 널리 이용되고 있 는데 상기 배수로는 내방수용으로 지하층으로부터 침투되는 지하수를 유도하여 집수정으로 처리하기 위하여 굴토마감면과 버림콘크리트 사이에 상기 배수판 또는 상기 다발관을 상호 교차시켜 설치하며, 집수정에 인접한 배수로의 단부를 집수정에 연결한 후 구체콘크리트를 타설하는 공정에 의하여 시공된다.On the other hand, in the drainage method, a drainage plate or a bundle pipe is widely used as a means for forming a drainage path under the concrete concrete forming the basement floor of a building, and the drainage path induces groundwater penetrating from the basement floor for water resistance. It is installed by intersecting the drainage plate or the bundle tube between the gulto finish surface and the discarded concrete to be treated by fertilization, and connecting the end of the drainage channel adjacent to the sump to the sump, and then pouring concrete concrete. .

그러나 종래의 지하층 바닥 배수시공 방법은 배수로의 역할을 하는 다발관이 굴토를 행한 트렌치에 매설되고, 상기 다발관의 외주면에 인접하도록 배수판이 설치된 후 상기 트렌치를 자갈로 채우고 버림콘크리트 및 구체콘크리트의 타설이 이루어지기 때문에 상기 트렌치 형성에 따른 시공기간이 길어지며, 상기 다발관의 내부에는 S형 플라스틱 바가 다발진 상태로 토목섬유에 의하여 감싸져 있기 때문에 지하수가 유입되기 위하여는 높은 수압이 필요했다. 또한, 상기 배수판으로 유도된 지하수는 상기 다발관의 외주면에 감싸진 토목섬유에 의하여 여과되어 상기 다발관으로 유입되는데 상기 지하수가 토사와 함께 유입되는 경우에는 상기 토목섬유에 눈막힘 현상이 발생되어 지하수의 집수기능을 상실하여 다발관에 의한 집수 또는 배수기능을 수행할 수 없게 되어 결과적으로 상기 건축물의 지하층에 상향수압이 가해져 지하수가 상기 지하층의 바닥면으로 침투될 수 있다.However, in the conventional underground floor drainage method, a bundle pipe acting as a drainage channel is buried in a trench, and a drain plate is installed to be adjacent to the outer circumferential surface of the bundle pipe, filling the trench with gravel, and casting concrete and concrete concrete. Because of this, the construction period according to the trench formation is long, and because the S-type plastic bar is wrapped in the fiber state in the bundle state by the geosynthetic fiber, high water pressure was required to flow the groundwater. In addition, the groundwater induced by the drainage plate is filtered by the geosynthetic fibers wrapped on the outer circumferential surface of the bundle pipe and is introduced into the bundle pipe. When the groundwater is introduced together with the soil, a clogging phenomenon occurs in the geotextile and the groundwater. The water collection function of the can not be carried out by the multi-chamber collection or drainage function as a result of the upward pressure is applied to the basement floor of the building, groundwater can penetrate the bottom surface of the basement floor.

상기한 바와 같이 상기 다발관과 상기 배수판이 직접 연결되지 못하여 발생되는 문제점을 해결하기 위하여 본원 출원인에 의하여 고안되어 기 출원된 실용신안등록 제314875호의 배수처리 구조물용 커넥터는 원통 또는 사각관 등의 소켓형태로 형성되어, 다발관 또는 배수판이 상호 연결되도록 적어도 두 개 이상의 연결구가 형성된 커넥터이며, 상기 커넥터는 상부케이스와 하부케이스가 분리 또는 조립 되어 이루어지고, 상기 상부케이스 또는 상기 하부케이스에는 삽입홈 및 삽입돌기가 적어도 한개 이상 형성되어 있으며, 상기 배수처리 구조물용 커넥터에 결합되어 집수정에 연결되는 다발관은 그 측면으로 배수판이 확실하게 연결되어 배수로가 형성되기 때문에 종래와 같이 트렌치를 형성하지 않고도 배수시공이 가능하였다.As described above, the connector for the wastewater treatment structure of Utility Model Registration No. 314875, which is designed and applied by the applicant of the present application in order to solve the problem caused by not being directly connected to the bundle pipe and the drain plate, is a socket such as a cylinder or a square tube. Is formed in the form, the connector is formed with at least two connectors for interconnecting the bundle tube or the drain plate, the connector is made of the upper case and the lower case is separated or assembled, the upper case or the lower case with an insertion groove and At least one insertion protrusion is formed, and the bundle pipe connected to the drainage structure connector and connected to the sump is securely connected to the drainage plate to form a drainage path, so that drainage is formed without forming a trench as in the prior art. Construction was possible.

그러나, 상기한 배수처리 구조물용 커넥터를 이용한 배수시공 방법은 배수판에 의하여 흡수된 지하수가 집수정에 연결된 다발관을 통해서만 집수되도록 되어 있기 때문에 강수량의 증가로 인하여 지하수의 발생량이 증가할 경우 이를 상기 다발관만으로는 원활하게 처리해 줄 수 없게 되어 결국 지하층 바닥면에 상향수압이 가해져 구조물이 변형되거나 지하수가 침투될 수 있다. 따라서, 이러한 문제를 해결하기 위해서는 상기 배수판으로 유도되는 지하수를 적절하게 분산시켜 집수 또는 배수할 수 있도록 배수로가 형성되어야 하며, 상기 지하수가 분산 집수될 때 집수정에 연결되는 배수로의 흐름 저항을 최소화하면서 원활한 배수가 이루어질 수 있는 배수로를 형성하는 것이 필요하다.However, in the drainage construction method using the connector for the drainage structure, the groundwater absorbed by the drainage plate is collected only through the bundle pipe connected to the sump. The pipes alone cannot be processed smoothly, and eventually upward pressure is applied to the bottom of the basement, which can deform the structure or penetrate the groundwater. Therefore, in order to solve this problem, a drainage path must be formed to properly collect and drain the groundwater guided to the drainage plate, while minimizing the flow resistance of the drainage path connected to the sump when the groundwater is dispersed and collected. It is necessary to form a drainage path through which smooth drainage can be made.

이러한 문제점을 해결하는 방법으로 본원 출원인에 의해 기출원(출원번호 제10-2004-00038330호)된 발명이 있다. In order to solve this problem, there is an invention filed by the present applicant (Application No. 10-2004-00038330).

상기 발명의 내용을 살펴보면, 지하층 바닥에 대하여 배수로를 시공할 때 평평한 굴토마감면에 대하여 별도의 트렌치를 굴토하지 않고, 지하수와 함께 유입된 토사에 의하여 다발관의 외주면에 감싸진 토목섬유의 눈막힘 현상이 발생되지 않도록 하기 위하여 집수정에 연결되는 배수관과 배수판 또는 다발관을 커넥터와 같은 연결수단으로 직접 연결하여 배수로를 형성하는 지하층 바닥 배수시공 방법을 제공 하고, 다량의 지하수가 유입되었을 때 이를 적절하게 분산 집수할 수 있도록 다발관 또는 배수판의 측방에 다수의 배수관을 연결하여 이를 통하여 배수시킬 수 있도록 배수로를 형성하며, 상기 다수의 배수관을 통합하여 집수정으로 원활하게 배수가 이루어지도록 집수관을 연결하여 배수로를 형성하는 지하층 바닥 배수시공 방법을 제공하는 것이었다.Looking at the contents of the present invention, when constructing the drainage passages for the basement floor, do not dig a separate trench for the flat gulto finish surface, clogging of geotextiles wrapped on the outer circumferential surface of the bundle by earth and sand introduced with groundwater In order to prevent the phenomenon from occurring, it provides a basement floor drainage construction method that forms a drainage path by directly connecting a drain pipe and a drain plate or a bundle pipe connected to a sump with a connector such as a connector. A plurality of drain pipes are connected to the side of the bundle pipe or the drain board so that the water can be drained through the drain pipes, and the water pipes can be connected to the water collecting wells by integrating the plurality of water pipes. To provide a basement floor drainage construction method to form a drainage path Respectively.

그러나 상기 발명은 건축물 시공중에 버림콘크리트를 타설한 후 상압수압에 대한 지하수 배수 보강시공이 요청될 경우 버림콘크리트를 다시 제거한 후 상기 시스템 배수로를 시공해야 하기 때문에 예상외의 공사기간이나 비용이 발생할 수 있는 문제점과 버림 콘크리트 타설후 갑작스런 배수시스템 시공요구에 적절하게 대응할 수 없는 문제점이 있었다.However, the present invention, if the groundwater drainage reinforcement construction for the atmospheric pressure after the casting concrete is placed during the construction of the building, it is necessary to remove the discarded concrete and then construct the drainage system, which may cause unexpected construction periods and costs. There was a problem in that it was not possible to adequately respond to sudden drainage system construction requirements after casting abandoned concrete.

또한 종래의 배수 시스템은 시스템 배수로의 지하 깊이와 같은 깊이에 있는 집수정으로 집수관을 통해 직접 지하수를 유도하기 때문에 결국 지면에서 부터 집수정과 시스템 배수로와의 연결되는 깊이까지의 압력이 작용하는 지하수를 처리할 수 밖에 없는 문제점이 있었다.In addition, the conventional drainage system induces groundwater directly through the collecting pipe to the sump at the same depth as the underground depth of the system drainage, so that the groundwater where the pressure from the ground to the depth between the sump and the system drainage acts. There was a problem that can only be processed.

본 발명은 상기와 같은 문제점을 해결하기 위하여 창안한 것으로서, 본 발명의 목적은 지하층 바닥에 시스템 배수로를 시공할 때 버림콘크리트 위에 시스템 배수로를 시공함으로써 평평한 기초위에 배수로를 시공할 수 있는 지하층 바닥 배수시공 방법을 제공하는 것이다.The present invention has been made to solve the above problems, an object of the present invention is to construct a basement floor drainage construction that can be constructed on a flat foundation by constructing a system drainage on the discarded concrete when the system drainage to the basement floor To provide a way.

또한, 버림콘크리트를 타설한 후에 상기 시스템 배수로를 시공할 수 있으므 로, 버림콘크리트를 시공한 후에 발생한 지하수 배수 시스템 시공 요구조건에 적절히 대응할 수 있는 방법을 제공하는 지하층 바닥 배수시공 방법을 제공하는 것이다.In addition, since the system drainage can be constructed after the casting of the discarded concrete, it is to provide a basement floor drainage construction method that provides a method that can adequately respond to the groundwater drainage system construction requirements generated after the construction of the discarded concrete.

또한, 종래에는 직접 집수정과 연결되던 주배수부재에 뒤집힌 U자 형상의 수위조절관을 연결하여 집수정으로 배수함으로써 배수량이 많은 지역에서도 효과적으로 지하수를 처리할 수 있는 지하층 바닥 배수시공 방법을 제공하는 것이다. In addition, by connecting the U-shaped water level control tube inverted to the main drain member directly connected to the conventional sump well to drain to the sump to provide a basement floor drainage construction method that can effectively treat the groundwater even in a large drainage area. will be.

이와 같은 본 발명의 목적은, 지층에 굴토를 행하여 굴토마감면 및 집수정을 형성하는 굴토단계;An object of the present invention as described above, the gulto step to form a gulto finish surface and a water collecting well by performing gulto the strata;

상기 굴토마감면상에 버림콘크리트를 타설하는 단계; Casting the discarded concrete onto the gulting finish surface;

상기 타설된 버림콘크리트상에 일방향에 대하여 등간격으로 소정의 내경을 갖는 지하수 유도 홀을 형성하는 단계;Forming a groundwater induction hole having a predetermined inner diameter at equal intervals in one direction on the cast concrete;

상기 타설된 버림콘크리트상에 등간격으로 배치된 배수판을 주배수부재에 연결하고, 상기 주배수부재의 일단을 상기 집수정내에 연장하여 시스템 배수로를 형성하는 단계; 상기 버림콘크리트와 상기 시스템 배수로 상에 비닐을 설치하는 단계; 상기 비닐상에 지하층 바닥을 형성하기 위하여 구체콘크리트를 타설하는 단계를 포함하여 이루어지는 것을 특징으로 하는 지하층 바닥 배수시공 방법에 의해 달성된다.Connecting drain plates disposed at equal intervals on the poured concrete to a main drain member, and extending one end of the main drain member into the sump to form a system drain; Installing vinyl on the discarded concrete and the system drain; It is achieved by the basement floor drainage method comprising the step of pouring concrete concrete to form a basement floor on the vinyl.

또한, 상기 지하수 유도홀을 형성하는 단계에 있어서, 상기 버림콘크리트 타설시 PVC관이나 파이프를 일방향 등간격으로 매설하여 상기 지하수 유도홀을 형성 하는 것을 특징으로 하는 지하층 바닥 배수시공 방법에 의해 달성된다.In the forming of the groundwater induction hole, the groundwater induction hole is formed by embedding the PVC pipe or pipe at equal intervals in one direction at the time of casting the concrete.

또한, 상기 지하수 유도홀을 형성하는 단계에 있어서, 상기 버림콘크리트 타설시 PVC관이나 파이프를 일방향 등간격으로 매설하여 상기 지하수 유도홀을 형성하는 것을 특징으로 하는 지하층 바닥 배수시공 방법에 의해 달성된다.In addition, in the step of forming the groundwater induction hole, when the discarded concrete is placed by the underground pipe bottom drainage method characterized in that the groundwater induction hole is formed by embedding the PVC pipe or pipe at equal intervals in one direction.

또한, 상기 지하수 유도홀을 형성하는 단계에 있어서,상기 버림콘크리트 타설시 나무도막을 일방향 등간격으로 매설 후 상기 버림콘크리트가 굳으면 상기 나무도막을 빼내어 상기 지하수 유도홀을 형성하는 것을 특징으로 하는 지하층 바닥 배수시공 방법에 의해 달성된다.In addition, in the step of forming the groundwater induction hole, the underground layer when the discarded concrete is laid in one direction at equal intervals, and if the discarded concrete is hardened, the ground layer is characterized in that the groundwater induction hole is formed by removing the wood coating. It is achieved by floor drainage method.

또한, 버림콘크리트와 버림콘크리트가 미타설된 굴토마감면이 상존하는 넓은 시공현장에 있어서, 상기 시스템 배수로가 버림콘크리트상과 상기 버림콘크리트가 타설되지 않은 굴토마감면상에 설치되고 상기 시스템 배수로의 주배수부재 및 부재부수재가 집수정내로 연결되는 것을 특징으로 하는 지하층 바닥 배수시공 방법에 의해 달성된다.In addition, in a large construction site where the discarded concrete and the discarded oyster finish surface in which the discarded concrete is not present, the system drainage channel is installed on the discarded concrete and the discarded concrete poured surface and the main drainage of the system drainage channel. It is achieved by the basement floor drainage method, characterized in that the member and the member accessory is connected into the sump.

또한, 상기 주배수부재가 뒤집힌 U자 모양의 수위조절관의 일측에 연결되고, 수위조절관의 타측은 집수정내에 연결되는 것을 특징으로 하는 지하층 바닥 배수시공 방법에 의해 달성된다.In addition, the main drainage member is connected to one side of the inverted U-shaped water level control pipe, the other side of the water level control pipe is achieved by the basement floor drainage construction method characterized in that connected to the sump.

상기 수위조절관이 PVC, 강 및 스테인레스 중 어느 하나의 재료로 이루어진 관인 것을 특징으로 하는 지하층 바닥 배수시공 방법 의해 달성된다.The level control pipe is achieved by the underground floor drainage method, characterized in that the pipe made of any one material of PVC, steel and stainless steel.

또한, 상기 수위조절관의 굽은 부위 상단에 공기 구멍이 형성된 것을 특징으로 하는 지하층 바닥 배수시공 방법 의해 달성된다.In addition, it is achieved by the basement floor drainage method characterized in that the air hole is formed on the top of the bent portion of the water level control pipe.

또한, 상기 버림콘크리트상의 주배수부재가 미리 굴토된 트렌치내의 자갈층에 매입되고, 상기 트렌치내의 집수관의 일단이 집수정에 연결되는 것을 특징으로 하는 지하층 바닥 배수시공 방법 의해 달성된다.In addition, the main drainage member on the discarded concrete is buried in a gravel layer in a trench previously excavated, and one end of the collecting pipe in the trench is achieved by the basement floor drainage method, characterized in that connected to the sump.

또한, 상기 버림콘크리트상의 주배수부재는 미리 굴토된 트렌치내의 집수관에 연결되고, 집수관의 일단은 집수정의 내측으로 연장되어 형성되는 것을 특징으로 하는 지하층 바닥 배수시공 방법 의해 달성된다.In addition, the main drain member on the discarded concrete is connected to a collecting pipe in a trench that has been previously pitted, and one end of the collecting pipe is formed by an underground floor drainage method, characterized in that it is formed to extend to the inside of the collecting well.

또한, 상기 트렌치와 집수정이 건물 외부에 있는 것을 특징으로 하는 지하층 바닥 배수시공 방법 의해 달성된다.In addition, the trench and the sump is achieved by the basement floor drainage method, characterized in that the outside of the building.

또한, 상기 주배수부재와 부배수부재의 일단이 건물 외부의 맨홀에 연결되어 상기 맨홀이 집수정의 역할을 하는 것을 특징으로 하는 지하층 바닥 배수시공 방법 의해 달성된다.In addition, one end of the main drainage member and the secondary drainage member is connected to the manhole outside the building is achieved by the basement floor drainage construction method characterized in that the manhole serves as a water collecting well.

또한, 상기 주배수부재와 부배수부재의 일단이 건물 외부의 집수관에 연결되고 상기 집수관의 일면에 연결관이 연결되고, 그 연결관이 연장되어 건물 외부의 집수정내로 연결되는 것을 특징으로 하는 지하층 바닥 배수시공 방법에 의해 달성된다.In addition, one end of the main drainage member and the sub-drainage member is connected to a water collecting pipe outside the building, and a connection pipe is connected to one surface of the water collecting pipe, and the connection pipe is extended to be connected to the water collecting well outside the building. It is achieved by the basement floor drainage method.

또한, 상기 집수관의 일면에 연결관이 연결되고, 그 연결관이 연장되어 건물 외부의 맨홀에 연결되어, 상기 맨홀이 상기 집수정의 역할을 하는 것을 특징으로 하는 지하층 바닥 배수시공 방법에 의해 달성된다.In addition, a connecting pipe is connected to one surface of the water collecting pipe, and the connecting pipe is extended and connected to a manhole outside the building, and the manhole serves to achieve the water collecting well. do.

또한, 시스템 배수로의 커넥터에서 직접 연결되어 나온 보조배수관이 상기 집수관에 연결되는 것을 특징으로 하는 지하층 바닥 배수시공 방법에 의해 달성된 다.In addition, it is achieved by the basement floor drainage method characterized in that the auxiliary drain pipe connected directly from the connector of the system drainage passage is connected to the collecting pipe.

이하, 본 발명에 의한 실시예를 첨부한 도면을 참조하여 더욱 상세하게 설명하면 다음과 같다.Hereinafter, an embodiment according to the present invention will be described in more detail with reference to the accompanying drawings.

도 1a는 본 발명의 제1실시예에 의한 지하층 바닥 배수시공 방법을 설명하기 위한 배수로의 평면도이며, 도 1b는 본 발명의 제1실시예에 의한 배수로 형성시 주배수부재와 배수판이 연결되어 매설된 상태를 도시한 A-A선 단면도이다.Figure 1a is a plan view of the drainage for explaining the underground floor drainage construction method according to a first embodiment of the present invention, Figure 1b is the main drainage member and the drain plate is embedded when the drainage is formed according to the first embodiment of the present invention It is the AA line cross section which shows the state.

도 1b에는 지층을 소정의 깊이 즉, 건축물의 지하층 깊이 만큼 굴토한 후 정지작업에 의하여 형성된 굴토마감면(10)과 그 위에 타설된 소정의 내경을 갖는 일방향의 등간격으로 지하수 유도 홀(50)이 내부에 형성된 버림콘크리트(30), 그리고 상기 버림콘크리트 상에 지하층 바닥 배수로가 설치된 상태가 도시되어 있다.In FIG. 1B, the groundwater induction hole 50 is disposed at equal intervals in one direction having a gulto finish surface 10 formed by a stop operation after excavating the ground floor to a predetermined depth, that is, the basement floor depth of the building, and a predetermined inner diameter placed thereon. The discarded concrete 30 formed therein, and a state in which the basement floor drainage channel is installed on the discarded concrete.

상기 지하수 유도 홀(50)은 버림콘크리트 타설 후 드릴이나 착안기로 구멍을 뚫어 형성되거나, PVC관을 상기 버림콘크리트 타설시 매설하는 방법 또는 나무도막을 매설한 상태에서 버림콘크리트를 타설한 후 버림콘크리트가 굳으면 나무도막을 제거하는 방법등에 의해 형성될 수 있다.  The groundwater induction hole 50 is formed by drilling or drilling with a drill or an eye drill after casting concrete, or by laying a concrete pipe in the state of laying a PVC pipe or laying a concrete film after casting concrete. If hardened, it may be formed by a method of removing the wood coating.

본 출원인에 의해 기출원된 출원번호 제10-2004-00038330호에 기재된 것처럼, 상기 배수로는 배수판(2), 다발관(혹는 유공관이나 중공관)으로 이루어진 주배수부재(1), 및 다발관(혹은 유공관이나 중공관 및 호스)으로 이루어진 부배수부재(4)가 커넥터(6)에 의하여 상호 연결됨으로써 형성되어 있으며, 상기 주배수부재(1)와 상기 부배수부재(4)가 각각 집수정(5)에 연결되어 있다.As described in Korean Patent Application No. 10-2004-00038330 filed by the applicant, the drainage passage includes a drain plate 2, a main drainage member 1 consisting of a bundle pipe (or a hollow pipe or a hollow pipe), and a bundle pipe ( Alternatively, the sub-drainage member 4 formed of a perforated pipe, a hollow pipe, and a hose) is formed by being connected to each other by the connector 6, and the main drainage member 1 and the sub-drainage member 4 each have a collecting well ( 5) is connected.

건축물의 지하층 하부로부터 분출되는 지하수를 배수시킴과 동시에 상기 지 하층 바닥에 작용하는 상향수압을 효과적으로 감소시켜 주기 위한 구성으로, 상기 배수판(2)은 버림콘크리트(30)내의 지하수 유도 홀(50) 전체에 대하여 상기 지하수 유도홀(50) 위에 등간격으로 설치되어 있고, 상기 배수판(2)으로 유도되는 지하수 중에 포함된 토사가 유입되는 것을 차단하기 위하여 상기 배수판(2)의 외주면에 토목섬유(부직포)(7)가 감싸져 있다.In order to effectively drain the groundwater discharged from the basement floor of the building and at the same time to effectively reduce the up-water pressure acting on the ground floor, the drain plate 2 is the groundwater induction hole 50 in the discarded concrete 30 as a whole Geosynthetic fibers (non-woven fabric) is installed on the ground water induction hole 50 at equal intervals, and on the outer circumferential surface of the drain plate 2 to block the inflow of soil contained in the groundwater guided to the drain plate 2. (7) is wrapped.

상기 주배수부재(1)는 상기 배수판(2)으로 유도된 지하수를 집수한 후 이를 집수정(5)으로 배수시키기 위하여 상기 버림콘크리트 상에 상기 주배수부재(1)의 일측 또는 양측방향으로 연장된 상기 배수판(2)과 직각방향으로 설치되고, 도 1b에 도시된 바와 같이 커넥터(6)에 의하여 상기 주배수부재(1)의 양측방향으로 각각 상기 배수판(2)이 연결되어 있으며, 상기 주배수부재(1)의 일단은 집수정(5)에 연결되어 있다. 여기서, 상기 주배수부재(1)는 상기 지하수가 집수정(5)으로 원활하게 흐를 수 있도록 S형 단면을 갖는 플라스틱 바(plastic bar)가 다발져 형성된 다발관이나 유공관 또는 중공관으로 형성되며, 상기 주배수부재(1) 역시 외주면이 토목섬유(7)에 의하여 감싸져 있다.The main drainage member 1 extends in one or both directions of the main drainage member 1 on the discarded concrete in order to collect groundwater induced by the drainage plate 2 and then drain it to the sump 5. The drainage plate 2 is installed at right angles to the drainage plate 2, and as shown in FIG. 1B, the drainage plate 2 is connected to both sides of the main drainage member 1 by the connector 6, respectively. One end of the drain member 1 is connected to the sump 5. Here, the main drainage member (1) is formed of a bundle tube, a perforated tube or a hollow tube formed by bundles of plastic bars having an S-shaped cross section so that the groundwater flows smoothly into the sump (5), The main drain member 1 is also surrounded by the geotextile (7) outer peripheral surface.

부배수부재(4)는 강수량의 증가로 인해 다량의 지하수가 유입될 경우 상기 주배수부재(1)에 집중되는 지하수를 분산시켜 집수하기 위하여 상기 주배수부재(1)의 일측 또는 양측으로 연장된 상기 배수판(2)과 직각방향으로 연결 설치되고, 상기 부배수부재(4)의 일단은 집수정(5) 내로 연장되도록 설치되어 있으며, 상기 부배수부재(4) 역시 외주면이 토목섬유(9)에 의하여 감싸져 있다.The secondary drainage member 4 extends to one side or both sides of the main drainage member 1 to disperse and collect groundwater concentrated in the main drainage member 1 when a large amount of groundwater flows due to an increase in precipitation. It is connected to the drainage plate (2) at right angles and installed, one end of the sub-drain member (4) is installed to extend into the sump (5), the sub-drain member (4) also has an outer peripheral surface of the geotextile (9) Is wrapped.

상기한 구성요소들을 상호 연결하여 도 1a와 같이 배수로를 형성하고 이를 도 1b에 도시된 바와 같이 지하층 바닥에 매설하는 배수시공 방법을 설명하면 다음과 같다.The drainage construction method of interconnecting the above components to form a drainage channel as shown in FIG. 1A and embedding them in the basement floor as shown in FIG. 1B is as follows.

먼저, 건축물의 지하층에 배수로를 형성하기 위하여 지층에 굴토를 행하고, 상기 굴토된 지층에 대하여 굴토면이 수평을 이루도록 정지작업을 행하여 굴토마감면(10)을 형성하며, 상기 굴토마감면(10)의 임의의 위치에 굴토를 행하여 집수정(5)을 형성하는 순서에 의거 굴토단계가 수행된다. 상기 굴토마감면(10) 형성시 필요에 따라 소량의 자갈 또는 잡석을 포설하여 수평 정지작업을 실시하는 것도 가능하다.First, in order to form a drainage path in the basement floor of the building, the ground layer is excavated, and a stop operation is performed so that the ground surface becomes horizontal with respect to the excavated ground layer to form the gulto finish surface 10, and the gulto finish surface (10) The gulting step is performed based on the order of forming the water collecting well 5 by gulting at any position of. It is also possible to perform a horizontal stop operation by laying a small amount of gravel or rubble as necessary when forming the gulto finish surface (10).

상기 굴토마감면(10)을 형성한 후 버림콘크리트(30)를 타설하게 되는데, 상기 버림콘크리트에는 굴토마감면 내의 지하수가 유도될 수 있도록 소정의 내경을 갖는 지하수 유도 홀(50)이 일방향에 대하여는 등간격으로 형성되어야 하고, 종방향으로는 하기 배수판(2)이 상기 지하수 유도홀(50)위에 위치하도록 넓은 등간격으로 두어 형성된다. 상기 지하수 유도 홀(50)은 버림콘크리트(30) 타설 후 드릴이나 착안기로 구멍을 뚫어 형성하거나, PVC관을 상기 버림콘크리트 타설시 매설하는 방법 또는 나무도막을 매설한 상태에서 버림콘크리트(30)를 타설한 후 버림콘크리트(30)가 굳으면 나무도막을 제거하는 방법등에 의해 형성될 수 있다.After forming the gulto finish surface 10 is cast concrete 30, the ground concrete induction hole 50 having a predetermined inner diameter to guide the groundwater in the gulto finish surface is in one direction It should be formed at equal intervals, and in the longitudinal direction, the drain plate 2 is formed at a wide equal interval so as to be located on the groundwater induction hole 50. The groundwater induction hole 50 is formed by drilling or drilling with a drill or an eye drill after casting the discarded concrete 30, or embedding a PVC pipe when the discarded concrete is laid or when the discarded concrete 30 is buried. After casting, the discarded concrete 30 may be formed by a method of removing the wood coating.

상기한 바와 같이 지하수 유도홀(50)이 형성된 버림콘크리트(30) 타설이 끝나면, 도 1a에 도시된 바와 같이 상기 배수판(2)을 가로방향으로 상기 지하수 유도 홀(50)상에 배치시킨다.After the casting of the discarded concrete 30 having the groundwater induction hole 50 formed as described above, the drainage plate 2 is disposed on the groundwater induction hole 50 in the horizontal direction as shown in FIG. 1A.

상기 배수판(2)에 직각방향으로 연결되어 집수정(5)으로 배수를 행하기 위한 주배수부재(1)가 커넥터(6)에 의하여 배수판(2)과 연결되는데 이때, 상기 주배수부재(1)는 상기 커넥터(6)에 연결되어 상기 집수정(5)까지 연장되도록 각각의 상기 배수판(2)이 배치된 간격과 동일한 길이로 절단되어 연결된다. 여기서, 상기 배수판(2)과 상기 주배수부재(1)는 지하수에 포함된 토사를 걸러주기 위하여 그 외주면에 토목섬유(7)가 감싸진 상태로 상기 커넥터(6)에 의해 상호 연결되며, 상기 커넥터(6)에 의해 연결된 상기 배수판(2)과 상기 주배수부재(1)가 보다 견고하게 연결되도록 연결부위에 테이프를 감아서 연결을 행하는 것도 가능하다.The main drainage member 1 connected to the drainage plate 2 at right angles to drain water to the sump 5 is connected to the drainage plate 2 by the connector 6. ) Is cut and connected to the connector 6 to the same length as each of the drainage plate 2 is disposed so as to extend to the sump (5). Here, the drain plate (2) and the main drain member (1) are interconnected by the connector (6) in a state in which the geotextile (7) is wrapped in its outer peripheral surface to filter the soil contained in the groundwater, It is also possible to connect by winding a tape around the connecting portion so that the drainage plate 2 and the main drainage member 1 connected by the connector 6 are connected more firmly.

아울러, 상기 배수로 형성시 상기 배수판(2)으로 흡수된 다량의 지하수를 여러 경유를 통하여 집수하기 위하여 부배수부재(4)가 상기 배수판(2)에 연결되는데 이 경우에도 상기 주배수부재(1)의 경우과 같이 상기 배수판(2)에 직각방향으로 커넥터(6)에 의하여 상기 배수판(2)과 부배수부재(4)가 연결된다. 이때 상기 부배수부재(4) 역시 외주면에 토목섬유(7)가 감싸진 상태로 상기 배수판(2)과 연결된다.In addition, the secondary drainage member (4) is connected to the drainage plate (2) in order to collect a large amount of groundwater absorbed by the drainage plate (2) when forming the drainage passage through a number of diesel, even in this case the main drainage member (1) As in the case, the drainage plate 2 and the sub-drainage member 4 are connected by the connector 6 in a direction perpendicular to the drainage plate 2. At this time, the secondary drainage member 4 is also connected to the drainage plate 2 in a state in which the civil fiber 7 is wrapped on an outer circumferential surface thereof.

상기 배수판(2)이 연결된 상기 주배수부재(1)와 상기 부배수부재(4)는 지하수가 배수되기 위한 배수로를 형성하기 위하여 집수정(5)을 향하도록 설치되어 있으며, 그 일단이 집수정(5)의 내로 연장되어 있다.The main drain member 1 and the secondary drain member 4 to which the drain plate 2 is connected are provided to face the sump well 5 to form a drainage path for draining the groundwater. It extends into the inside of (5).

상기한 방법에 의하여 시스템 배수로 형성단계가 완료되면 상기 시스템 배수로와, 시스템 배수로가 설치되지 않은 상기 버림콘크리트(30) 상에 지하수에 대한 방수층을 형성하기 위하여 비닐(20)을 설치하는 단계를 수행한다.When the system drainage forming step is completed by the above-described method, a step of installing the vinyl 20 to form a waterproof layer for groundwater on the discarded concrete 30 on which the system drainage and the system drainage are not installed is performed. .

상기 시스템 배수로와 버림콘크리트(30) 상에 비닐(20)이 설치되면 건축물의 지하층 바닥을 형성하기 위하여 구체콘크리트(40)를 타설하는 콘크리트 타설단계에 의하여 지하층에 배수로를 형성하는 배수시공이 이루어진다.When the vinyl 20 is installed on the system drainage channel and the discarded concrete 30, a drainage construction is formed to form a drainage path in the basement floor by a concrete pouring step of placing concrete concrete 40 to form a basement floor of a building.

도 2a는 본 발명의 제2실시예에 의한 지하층 바닥 배수시공 방법을 설명하기 위한 배수로의 평면도이며, 도 2b는 본 발명의 제2실시예에 의한 배수로 형성시 주배수부재가 버림콘크리트(30)를 관통하고, 그 후 굴토마감면(10)을 지나 집수정에 연결된 상태를 도시한 B-B선 단면도이다.Figure 2a is a plan view of the drainage for explaining the basement floor drainage construction method according to a second embodiment of the present invention, Figure 2b is the main drainage member when the drainage is formed according to the second embodiment of the present invention 30 A cross-sectional view taken along line BB showing a state that penetrates through and then passes through the gulting finish surface 10 to be connected to the sump.

도 2a에는 지층을 소정의 깊이 즉, 건축물의 지하 깊이 만큼 굴토한 굴토마감면(10)에 타설되어 건축물의 기초부를 형성하는 버림콘크리트(30)상에 시스템 배수로가 설치되고, 주배수부재(1) 및 부재수부재(4)가 버림콘크리트(30)가 타설된 현장에서 연결되어 굴토마감면(10)위의 시스템 배수로와 연결되고, 굴토마감면(10)상의 주배수부재(1)가 연장되어 집수정(5)에 연결된 상태가 도시되어 있다.In FIG. 2A, the system drainage path is installed on the discarded concrete 30 which is formed on the gulting dead surface 10 which has excavated the strata to a predetermined depth, that is, the underground depth of the building, and forms the foundation of the building. ) And the water-receiving member 4 are connected at the site where the discarded concrete 30 is poured and connected to the system drainage channel on the gulting finish surface 10, and the main drainage member 1 on the gulting finish surface 10 extends. Is shown connected to the sump (5).

시공현장이 넓은 경우, 버림콘크리트(30)가 미리 타설된 부분과 버림콘크리트(30)가 미타설된 굴토마감면(10)이 상존하는 현장이 존재한다. 상기와 같은 시공현장에서 배수시스템을 설치해야할 경우 제2실시예를 적용할 수 있다.When the construction site is wide, there is a site where the discarded concrete 30 is pre-poured and the abandoned concrete surface 10 where the discarded concrete 30 is not poured. When the drainage system is to be installed at the construction site as described above, the second embodiment may be applied.

상기 제1실시예에서 기술한 구성요소들을 상호 연결하여 도 2a와 같이 배수로를 형성하고 이를 도 2b에 도시된 바와 같이 지하층 바닥에 매설하는 배수시공 방법을 설명하면 다음과 같다.The drainage construction method of interconnecting the components described in the first embodiment to form a drainage channel as shown in FIG. 2A and embedding it in the basement floor as shown in FIG. 2B is as follows.

우선 미리 타설된 버림콘크리트(30)에 소정의 직경을 갖는 지하수 유도 홀(50)이 굴토마감면(10)의 깊이까지 드릴이나 착안기에 의해 형성된다.First, a groundwater induction hole 50 having a predetermined diameter is formed in a precast concrete 30 by a drill or an eye drill to the depth of the gulting finish surface 10.

상기 지하수 유도 홀(50)위에 배수판(2)을 깔고 제1실시예와 동일한 방법으로 시스템 배수로가 버림콘크리트(30)와 굴토마감면(10) 위에 설치되고 주배수로 (1)는 집수정(5) 내에 위치하도록 형성된다. The drainage plate (2) is laid on the groundwater induction hole (50), and the system drainage path is installed on the discarded concrete (30) and the gulting finish surface (10) in the same manner as the first embodiment, and the main drainage (1) is a sump (5). It is formed to be located within).

집수정이 상기 버림콘크리트(30)와 인접하여 있으면 상기 버림콘크리트(30)상의 시스템 배수로에서 연장되어 나온 주배수부재가 집수정으로 연결된다.If the sump is adjacent to the discard concrete 30, the main drain member extending from the system drain on the discard concrete 30 is connected to the sump.

상기한 방법에 의하여 배수로 형성단계가 완료되면 상기 시스템 배수로와, 배수로가 설치되지 않은 상기 버림콘크리트(30)와, 상기 굴토마감면(10)에 지하수에 대한 방수층을 형성하기 위하여 비닐(20)을 설치하는 단계를 수행한다.When the drainage channel forming step is completed by the above method, the vinyl 20 is formed in order to form a waterproof layer for groundwater on the system drainage channel, the discarded concrete 30 having no drainage path, and the gulting finish surface 10. Follow the steps to install.

상기 비닐(20)설치 단계가 끝나면, 시스템 배수로가 설치된 굴토마감면 위에 미리 타설된 버림콘크리트(30)의 두께만큼 버림콘크리트(30)가 타설된다.When the vinyl 20 installation step is completed, the discarded concrete 30 is poured as much as the thickness of the discarded concrete 30 which is pre-poured on the gulting finish surface on which the system drainage path is installed.

이 후 건축물의 지하층 바닥을 형성하기 위하여 구체콘크리트(40)를 타설하는 콘크리트 타설단계에 의하여 지하층에 배수로를 형성하는 배수시공이 이루어진다.Thereafter, a drainage construction is performed in which a drainage path is formed in the basement floor by a concrete pouring step of placing concrete concrete 40 to form a basement floor of a building.

도 3은 본 발명의 제3실시예에 의한 지하층 바닥 배수시공 방법을 설명하기 위한 배수로의 단면도이다. Figure 3 is a cross-sectional view of the drainage for explaining the underground floor drainage construction method according to a third embodiment of the present invention.

도 3에는 주배수부재(1)는 굴토마감면(10) 상에 설치하고 배수판(2)은 버림콘크리트(30) 상에 설치하여 시스템 배수로를 구성한 상태가 도시되어 있다.In FIG. 3, the main drainage member 1 is installed on the gulting finish surface 10 and the drainage plate 2 is installed on the discarded concrete 30 to form a system drainage path.

제3실시예는 철근(60)과 버림콘크리트(30)사이의 공간이 협소하여 주 배수로가 버림콘크리트 상에 바로 설치될 수 없을 때 시공하는 방법이다.The third embodiment is a construction method when the space between the reinforcement 60 and the discarded concrete 30 is narrow so that the main drainage channel cannot be installed directly on the discarded concrete.

도 3을 참조하여 본 발명의 제3실시예에 의한 지하층 바닥 배수시공 방법을 설명하면, 지층을 굴토하여 집수정(5) 및 굴토마감면(10)을 형성한 후 다발관(3)으로 이루어진 주배수부재(1)를 상기 굴토마감면(10) 상에 설치하고 상기 주배수부재 (1)의 일단을 집수정(5)내에 위치하도록 연장하여 형성한다.Referring to Figure 3 describes the method for draining underground floors according to the third embodiment of the present invention, after forming the water collecting well (5) and the gulting finish surface 10 by excavating the ground layer consisting of a bundle pipe (3) The main drainage member 1 is installed on the gulting finish surface 10 and extends so that one end of the main drainage member 1 is located in the collecting well 5.

상기 설치된 주배수부재(1)의 주위에는 상기 굴토마감면(10) 상으로부터 주배수부재와 배수판(2)이 연결될 연결부위 높이 전까지 콘크리트를 타설하고, 제1실시예와 마찬가지로 버림콘크리트(30) 내에 지하수 유도홀(50)이 형성한다. The concrete is poured around the installed main drainage member 1 until the height of the connection portion to which the main drainage member and the drainage plate 2 are to be connected from the gulting finish surface 10, and throwing concrete 30 as in the first embodiment. Groundwater induction hole 50 is formed within.

버림콘크리트(30)가 굳은 후 등간격으로 형성된 상기 지하수 유도홀(50)위에 배수판(2)을 설치하고 주배수부재(1)와 배수판(2)을 상호 연결한다. 이 때 주배수부재(1)와 배수판(2) 모두 외면이 토목용 부직포(7)로 감싸져있다. After the discarded concrete 30 is hardened, the drainage plate 2 is installed on the groundwater induction hole 50 formed at equal intervals, and the main drainage member 1 and the drainage plate 2 are interconnected. At this time, the outer surface of both the main drain member (1) and the drain plate (2) is wrapped with a civil engineering nonwoven fabric (7).

상기한 방법에 의하여 배수로 형성단계가 완료되면 상기 시스템 배수로와, 시스템 배수로가 설치되지 않은 상기 버림콘크리트(30)상에 지하수에 대한 방수층을 형성하기 위하여 비닐(20)을 설치하는 단계를 수행한다.When the drainage channel forming step is completed by the above-described method, a step of installing the vinyl 20 to form a waterproof layer for groundwater on the discarded concrete 30 on which the system drainage channel and the system drainage channel are not installed is performed.

상기 배수로와 버림콘크리트(30)상에 비닐(20)이 설치되면 건축물의 지하층 바닥을 형성하기 위하여 구체콘크리트(40)를 타설하는 콘크리트 타설단계에 의하여 지하층 배수로를 형성하는 배수시공이 이루어진다.When the vinyl 20 is installed on the drainage channel and the discarded concrete 30, a drainage construction is performed to form the basement drainage channel by the concrete pouring step of placing the concrete concrete 40 to form the basement floor of the building.

도 4는 본 발명의 제4실시예에 의한 지하층 바닥 배수시공 방법을 설명하기 위한 배수로의 단면도이다. Figure 4 is a cross-sectional view of the drainage for explaining the underground floor drainage construction method according to a fourth embodiment of the present invention.

도 4에는 제1실시예에서 기술한 배수구조에서 주배수부재(1)가 집수정(5)으로 직접 연결되지 않고, 굴토작업에 의해 형성된 트렌치(100)내의 자갈층(70)에 상기 주배수부재(1)의 일단이 매입되어 있는 상태가 도시되어 있다. In FIG. 4, in the drainage structure described in the first embodiment, the main drainage member 1 is not directly connected to the sump 5, and the main drainage member 70 in the gravel layer 70 in the trench 100 formed by the excavation work. The state in which one end of (1) is embedded is shown.

도 4를 참조하여 본 발명의 제4실시예에 의한 지하층 바닥 배수시공 방법을 설명하면, 제1실시예와 같은 방법으로 지층을 굴토하여 형성된 집수정(5) 및 굴토 마감면(10)이 형성되고, 상기 굴토마감면위에 지하수 유도홀(50)이 형성된 버림콘크리트가 타설된다. 이 후 배수판(2) 및 다발관으로 이루어진 주배수부재(1)가 커넥터에 의하여 상호 연결되어 지하수 유도 홀(50)이 형성된 상기 버림콘크리트(30)상에 시스템 배수로가 형성된다.Referring to Figure 4 describes the basement floor drainage method according to a fourth embodiment of the present invention, the water collecting well 5 and the gulto finish surface 10 formed by excavating the ground layer in the same manner as the first embodiment is formed And, the discarded concrete on which the groundwater induction hole 50 is formed on the gulting finish surface is poured. Thereafter, the drainage plate 2 and the main drainage member 1 consisting of a bundle pipe are interconnected by a connector to form a system drainage path on the discarded concrete 30 in which the groundwater induction hole 50 is formed.

상기 시스템 배수로가 형성된 후, 굴토작업에 의해 형성된 트렌치(100) 내에 집수관(80)이 매설되고 상기 집수관(80)의 일단은 집수정(5)내로 연장하여 형성된다. 집수관 매설 단계가 끝나면, 시스템 배수로의 주배수부재(1)의 일단을 상기 트렌치내에 연장시켜 주배수부재(1)를 통해 흐르는 지하수가 트렌치(100)로 고이도록 한다. 이 후 상기 트렌치(100)내의 집수관(80)과 주배수부재(1)의 일단은 자갈로 메워져 시스템 배수로가 트렌치(100)에 연결된다.After the system drainage path is formed, a collecting pipe 80 is embedded in the trench 100 formed by the excavation work, and one end of the collecting pipe 80 extends into the collecting well 5. At the end of the collecting pipe embedding step, one end of the main drain member 1 of the system drainage channel is extended in the trench so that the groundwater flowing through the main drain member 1 accumulates in the trench 100. Thereafter, one end of the collecting pipe 80 and the main drain member 1 in the trench 100 is filled with gravel so that the system drainage path is connected to the trench 100.

상기 주배수부재(1)를 통해, 지하수는 트렌치(100) 내의 자갈층(70)에 고이게 되고 상기 자갈층(70)에 고인 지하수는 집수관(80)으로 스며들어 상기 집수관(80)을 통해 흘러 집수정(5)내로 지하수가 배수된다. Through the main drainage member (1), groundwater accumulates in the gravel layer (70) in the trench 100, and groundwater accumulated in the gravel layer (70) soaks into the collecting pipe (80) and flows through the collecting pipe (80). Groundwater is drained into the sump 5.

상기한 방법에 의하여 배수로 형성단계가 완료되면 상기 배수로와, 배수로가 설치되지 않은 상기 버림콘크리트(30)상에 지하수에 대한 방수층을 형성하기 위하여 비닐(20)을 설치하는 단계를 수행한다.When the drainage channel forming step is completed by the above method, the step of installing the vinyl 20 to form a waterproof layer for groundwater on the drainage and the discarded concrete 30 is not installed.

상기 배수로와 버림콘크리트(30)상에 비닐(20)이 설치되면 건축물의 지하층 바닥을 형성하기 위하여 구체콘크리트(40)를 타설하는 콘크리트 타설단계에 의하여 지하층 배수로를 형성하는 배수시공이 이루어진다.When the vinyl 20 is installed on the drainage channel and the discarded concrete 30, a drainage construction is performed to form the basement drainage channel by the concrete pouring step of placing the concrete concrete 40 to form the basement floor of the building.

도 5는 본 발명의 제5실시예에 의한 지하층 바닥 배수시공 방법을 설명하기 위한 배수로의 단면도이다. Figure 5 is a cross-sectional view of the drainage for explaining the underground floor drainage construction method according to a fifth embodiment of the present invention.

도 5에는 주배수부재(1)가 굴토작업에 의해 형성된 트렌치(100)내의 집수관(80)에 연결되어 있는 상태가 도시되어 있다. 5 shows a state in which the main drainage member 1 is connected to the collection pipe 80 in the trench 100 formed by the excavation work.

도 5를 참조하여 본 발명의 제5실시예에 의한 지하층 바닥 배수시공 방법을 설명하면, 제1실시예와 같은 방법으로 지층을 굴토하여 집수정(5) 및 굴토마감면(10)을 형성한 후 상기 굴토마감면(10)위에 버림콘크리트(30)를 타설하고 지하수 유도홀(50)을 형성한다. 상기 버림콘크리트(30)가 굳으면 다발관으로 이루어진 주배수부재(1)와 배수판(2)을 커넥터에 의하여 상호 연결하여 지하수 유도 홀(50)이 형성된 버림콘크리트(30)상에 시스템 배수로를 형성한다.Referring to FIG. 5, the method for draining underground floors according to the fifth embodiment of the present invention is to excavate the ground layers in the same manner as in the first embodiment to form the water collecting well 5 and the gulting finish surface 10. After the cast concrete 30 is poured on the gulto finish surface 10 to form a groundwater guide hole (50). When the discarded concrete 30 is hardened, a system drainage path is formed on the discarded concrete 30 having the groundwater induction hole 50 formed by interconnecting the main drainage member 1 and the drainage plate 2 formed of a bundle tube by a connector. do.

상기 시스템 배수로 형성단계가 끝나면 미리 굴토된 트렌치(100)내에 집수관(80)을 매설하고, 상기 집수관(80)의 일단을 굴토에 의해 형성된 상기 집수정(5) 내로 연결한다. 주배수부재(1)를 통하여 집수된 지하수를 집수정(5)으로 배수시켜 주기 위하여 상기 주배수부재(1)의 일단을 굴토된 트렌치(100)내의 상기 집수관(80)에 연결하고 트렌치를 자갈로 메우는 작업을 하여 지하수 배수로를 완성한다.When the system drainage channel forming step is completed, the water collecting pipe 80 is embedded in the trench 100 previously excavated, and one end of the water collecting pipe 80 is connected into the water collecting well 5 formed by the excavation. In order to drain the groundwater collected through the main drainage member 1 to the sump 5, one end of the main drainage member 1 is connected to the water collecting pipe 80 in the excavated trench 100 and the trench The gravel filling works to complete the groundwater drainage.

주배수부재(1)를 통해 지하수는 트렌치(100) 내의 집수관(80)으로 흐르고 상기 집수관(80)의 일단은 집수정(5)에 연결되어 상기 집수관(80)을 통해 흐르는 물은 집수정(5)으로 유도된다.Through the main drain member (1), groundwater flows into the collecting pipe (80) in the trench 100, and one end of the collecting pipe (80) is connected to the collecting well (5) so that the water flowing through the collecting pipe (80) Guided to the sump (5).

상기한 방법에 의하여 배수로 형성단계가 완료되면 상기 배수로와, 배수로가 설치되지 않은 상기 버림콘크리트(30)상에 지하수에 대한 방수층을 형성하기 위하여 비닐(20)을 설치하는 단계를 수행한다.When the drainage channel forming step is completed by the above method, the step of installing the vinyl 20 to form a waterproof layer for groundwater on the drainage and the discarded concrete 30 is not installed.

상기 배수로와 버림콘크리트(30)상에 비닐(20)이 설치되면 건축물의 지하층 바닥을 형성하기 위하여 구체콘크리트(40)를 타설하는 콘크리트 타설단계에 의하여 지하층 배수로를 형성하는 배수시공이 이루어진다.When the vinyl 20 is installed on the drainage channel and the discarded concrete 30, a drainage construction is performed to form the basement drainage channel by the concrete pouring step of placing the concrete concrete 40 to form the basement floor of the building.

도 6은 본 발명의 제6실시예에 의한 지하층 바닥 배수시공 방법을 설명하기 위한 배수로의 평면도이다.Figure 6 is a plan view of the drainage for explaining the underground floor drainage construction method according to a sixth embodiment of the present invention.

도 6은 상기한 제1, 제2실시예에서 집수정내로 연장되어 형성된 주배수부재(1)의 일단과 뒤집힌 U자 모양의 수위 조절관(300)의 일단을 플랜지(500)로 연결하여 집수정(5)으로 지하수를 유도한 상태가 도시되어 있다.6 is connected to one end of the main drainage member 1 formed in the first and second embodiments by extending into the sump well and one end of the inverted U-shaped water level control pipe 300 by the flange 500. The state of inducing groundwater with the crystal (5) is shown.

제6실시예는 소정의 높이(A)를 갖는 뒤집힌 U자 모양의 수위 조절관(300)을 통해 지하수가 집수정(5)으로 유도되기 때문에 주배수부재(1)와 수위조절관(300) 최상부와의 높이(A)차이 만큼에 해당되는 수압차를 이겨내는 배수압인 경우에만 배수될 수 있도록 하여 배수량이 많은 지역에서 효과적으로 지하수를 배수할 수 있다.The sixth embodiment is the main drainage member (1) and the water level control pipe (300) because the groundwater is guided to the sump (5) through the inverted U-shaped water level control pipe 300 having a predetermined height (A) It is possible to drain the groundwater effectively in an area with a large amount of drainage by allowing drainage only when the drainage pressure overcomes the hydraulic pressure difference corresponding to the difference in height (A) with the top.

도 6을 참조하여 본 발명의 수위 조절관(300)을 갖는 지하층 배수시공 방법을 설명하면, 지층을 굴토하여 집수정(5) 및 굴토마감면(10)을 형성하고, 지하수 유도홀(50)이 형성된 버림콘크리트(30)를 형성한 후 주배수부재(1), 상기 배수판(2) 및 다발관으로 이루어진 부배수부재(4)를 커넥터(6)로 상호 연결하여 시스템 배수로를 형성하는 방법은 도1a에서 설명한 본 발명의 제 1 실시예에 의한 방법과 동일하게 실시된다.Referring to FIG. 6, the method for draining underground floors having the water level control pipe 300 according to the present invention is to excavate the ground layers to form the water collecting well 5 and the gulting dead surface 10, and the groundwater induction hole 50. After forming the cast concrete 30 is formed a method for forming a system drainage by interconnecting the sub-drainage member (4) consisting of the main drainage member (1), the drainage plate (2) and the bundle pipe with a connector (6) It is implemented in the same manner as the method according to the first embodiment of the present invention described with reference to FIG.

이후 상기 주배수부재(1)를 통하여 집수된 지하수를 집수정(5)으로 배수시켜 주기 위하여 시스템 배수로에서 연장되어 집수정(5) 내부에 형성된 주배수부재(1)의 일단에 뒤집힌 U자 모양의 수위조절관(300)의 일단을 플랜지(또는 나사 체결 방법)로 연결한다.Then, the U-shaped inverted at one end of the main drain member (1) formed in the sump (5) extending from the system drainage in order to drain the groundwater collected through the main drain member (1) to the sump (5) One end of the water level control pipe 300 is connected to the flange (or screw fastening method).

아울러 상기 집수정(5)내부에 형성된 상기 주배수부재(1)의 일단을 플랜지(500)로 상기 집수정(5) 내에 미리 고정시켜 놓은 후, 수위조절관(300)이 필요할 시 추후에 상기 수위조절관(300)을 연결할 수 있도록 구성할 수 있다.In addition, after fixing one end of the main drain member 1 formed in the sump (5) in the sump (5) in advance with a flange 500, the water level control pipe (300) if necessary later It can be configured to connect the water level control pipe (300).

종래의 수위조절관에서는 일단 수위조절관(300)의 높이(A)차이 만큼의 수압차를 이겨내는 배수압으로 상기 수위조절관을 통해 지하수가 배수되다가 상기 수압차를 이겨내지 못할 정도로 배수압이 낮아진 경우에도 계속 배수된다. 그러나 본원 발명에서는 상기 수위조절관(300)의 위로 올라갔다가 꺾여져 내려오는 최상단 부위에 공기구멍(400)을 형성하여 수위조절관(300)의 높이(A)차이 만큼의 수압차를 이겨내는 배수압인 경우에만 배수되도록 하여 배수량이 많은 지역에서 한꺼번에 많은 양이 배수되는 것을 방지할 수 있다.In the conventional water level control pipe, the groundwater is drained through the water level control pipe with a drain pressure that overcomes the water pressure difference as much as the difference of the height (A) of the water level control pipe 300, so that the water pressure is low enough to overcome the water pressure difference. Even if it continues to drain. However, in the present invention, by forming an air hole 400 in the uppermost portion of the water level control pipe 300 to go up and down, the water drainage to overcome the water pressure difference as much as the height (A) difference of the water level control pipe 300 It can be drained only in the case of pressure, to prevent the drainage of large quantities at once in areas with large drainage.

상기 수위조절관(300)은 PVC관이나 Steel관 혹은 스테인레스관을 사용하여 형성할 수 있다. 상기 뒤집힌 U자 모양의 수위조절관(300)의 높이(A)는 건물의 자중이나 토질의 배수능력과 지하수의 양에 따라 조절될 수 있고 배수관을 통해 흐르는 지하수는 상기 수위조절관(300)을 따라 상승을 한 후 다시 하강하여 집수정(5)으로 유도되는데, 수두의 높이에 따른 수압차로 수위조절관(300)의 가장 높은 부위 이상에 있는 지하수만 처리하게 되어 지하수 처리량의 부담을 덜 수 있다. The water level control pipe 300 may be formed using a PVC pipe, steel pipe or stainless steel pipe. The height (A) of the inverted U-shaped water level control pipe 300 can be adjusted according to the weight of the building or the drainage capacity of the building and the amount of groundwater, and the groundwater flowing through the drain pipe is the water level control pipe (300). Ascending and descending again leads to the sump (5), the pressure difference depending on the height of the head can be treated only groundwater above the highest portion of the water level control pipe 300 can reduce the burden of groundwater throughput. .

상기한 방법에 의하여 배수로 형성단계가 완료되면 상기 배수로와 배수로가 설치되지 않은 상기 버림콘크리트(30)상에 지하수에 대한 방수층을 형성하기 위하여 비닐(20)을 설치하는 단계를 수행한다.When the drainage channel forming step is completed by the above method, the step of installing the vinyl 20 to form a waterproof layer for groundwater on the discarded concrete 30 on which the drainage channel and the drainage path are not installed is performed.

상기 배수로와 버림콘크리트(30)상에 비닐(20)이 설치되면 건축물의 지하층 바닥을 형성하기 위하여 구체콘크리트(40)를 타설하는 콘크리트 타설단계에 의하여 지하층 배수로를 형성하는 배수시공이 이루어진다.When the vinyl 20 is installed on the drainage channel and the discarded concrete 30, a drainage construction is performed to form the basement drainage channel by the concrete pouring step of placing the concrete concrete 40 to form the basement floor of the building.

상기한 실시예들과 더불어 건물외부에 집수관을 설치하여 지하수를 건물외부의 집수관으로 유도하거나 건물 외부의 맨홀로 유도하는 시공이 이루어질 수 있다. 이하 지하수를 건물 외부로 유도하는 시공방법을 자세히 설명하면 다음과 같다.In addition to the embodiments described above, a water pipe may be installed outside the building to guide groundwater to the water pipe outside the building or to guide the manhole outside the building. Hereinafter, the construction method for inducing groundwater to the outside of the building in detail.

도 7은 본 발명의 제7실시예에 의한 지하층 바닥 배수시공 방법을 설명하기 위한 단면도이다.Figure 7 is a cross-sectional view for explaining the underground floor drainage construction method according to a seventh embodiment of the present invention.

도 7에는 시스템 배수로의 주배수부재가 건물외벽밖으로 연장되어 건물외벽밖에 있는 집수관에 연결되고, 집수관에서 연결되어 나온 연결관이 외부 집수정내부로 연결된 상태가 도시되어 있다.FIG. 7 illustrates a state in which the main drainage member of the system drainage channel extends out of the building exterior wall to be connected to a collection pipe outside the building exterior wall, and the connection pipe connected from the collection pipe is connected to the interior of the external collection well.

도 7을 참조하여 본 발명의 제7실시예에 의한 지하층 바닥 배수시공 방법을 설명하면, 지층을 굴토하여 외부 집수정 및 굴토마감면을 형성한 후 버림콘코리트를 타설하며 지하수 유도 홀(50)을 형성하고, 다발관으로 이루어진 주배수부재(1), 상기 배수판(2), 및 다발관으로 이루어진 부배수부재(4)를 커넥터(8)에 의하여 상호 연결하여 시스템 배수로를 형성하는 방법은 도1a에서 설명한 본 발명의 제1 실시예에 의한 방법과 동일하게 실시된다.Referring to FIG. 7, the method for draining underground floors according to the seventh embodiment of the present invention is described below. After excavating the ground layer to form an external water collecting well and the gulting dead surface, casting concrete is poured and groundwater induction hole 50 is formed. And a main drainage member (1) consisting of a bundle pipe, the drainage plate (2), and a secondary drainage member (4) consisting of a bundle pipe are interconnected by a connector (8) to form a system drainage path. It is implemented in the same manner as the method according to the first embodiment of the present invention described in 1a.

이후 도 7에서 도시한 바와 같이, 상기 주배수부재(1)의 일단이 연장되어 건 물 외부에 건물 외벽(600)과 평행하게 설치된 외부집수관(80a)에 커넥터로 연결된다. 상기 집수정(80a)의 일면에서 연결된 연결관(900)은 외부 집수정(5a) 내로 연장되어 형성되어 집수관(80a)에 집수돤 지하수를 집수정으로 유도하여 지하층에 배수로를 형성하는 배수시공이 이루어진다. Thereafter, as shown in FIG. 7, one end of the main drainage member 1 extends and is connected to the outer collection pipe 80a installed in parallel with the building exterior wall 600 outside the building. The connecting pipe 900 connected from one surface of the sump well (80a) is formed to extend into the outer sump (5a) drainage construction to guide the catchment 에 groundwater to the sump to the sump pipe (80a) to form a drainage in the basement layer This is done.

도 8은 본 발명의 제8실시예에 의한 지하층 바닥 배수시공 방법을 설명하기 위한 단면도이다.8 is a cross-sectional view for explaining the underground floor drainage construction method according to the eighth embodiment of the present invention.

도 8은 외부 집수관에서 연장된 연결관(900)이 외부 맨홀(700)에 연결된 상태가 도시되어 있다.8 shows a state in which the connecting tube 900 extending from the outer collecting pipe is connected to the outer manhole 700.

도 8을 참조하여 본 발명의 제8실시예에 의한 지하층 바닥 배수시공 방법을 설명하면, 지층을 굴토하여 굴토마감면을 형성한 후 버림콘코리트를 타설하며 지하수 유도 홀(50)을 형성하고, 다발관으로 이루어진 주배수부재(1), 상기 배수판(2), 및 다발관으로 이루어진 부배수부재(4)를 커넥터(8)에 의하여 상호 연결하여 시스템 배수로를 형성하는 방법은 도1a에서 설명한 본 발명의 제1 실시예에 의한 방법과 동일하게 실시된다.Referring to FIG. 8, the method for draining underground floors according to an eighth embodiment of the present invention is to excavate a ground layer to form a gulting finish surface, and then cast discard concrete to form a groundwater induction hole 50. A method of forming a system drainage path by connecting the main drainage member 1 consisting of the bundle pipe, the drainage plate 2, and the subdrainage drainage member 4 consisting of the bundle pipe by the connector 8 is described with reference to FIG. 1A. It is carried out similarly to the method according to the first embodiment of the invention.

이후 도 8에서 도시한 바와 같이, 상기 주배수부재(1)의 일단이 연장되어 건물 외부에 건물 외벽(600)과 평행하게 설치된 외부집수관(80a)에 커넥터로 연결된다. 상기 집수관(80a)의 일면에서 연결된 연결관(900)은 외부 맨홀(700) 내로 형성되어 집수관(80a)에 집수돤 지하수를 맨홀(700)로 유도하여 지하층에 배수로를 형성하는 배수시공이 이루어진다. Thereafter, as shown in FIG. 8, one end of the main drainage member 1 extends and is connected to the outer collection pipe 80a installed in parallel with the building exterior wall 600 outside the building. The connecting pipe 900 connected from one surface of the collecting pipe 80a is formed into the outer manhole 700 to drain the groundwater into the collecting hole 80a to the manhole 700 to form a drainage path in the basement floor. Is done.

상기 외부집수관(80a)에서 연결된 연결관(900)이 맨홀(700)에 연결될 시, 상 기 연결관(900)이 집수관(80a)으로부터 곧게 연장되어 맨홀과 연결되거나, 지형을 고려하여 소정의 높이 만큼 상기 연결관(900)을 꺾어 올린 후 상기 연결관(900)을 연장하여 맨홀에 연결될 수 있다.When the connecting pipe 900 connected from the outer collecting pipe 80a is connected to the manhole 700, the connecting pipe 900 extends straight from the collecting pipe 80a to be connected to the manhole or predetermined in consideration of the terrain. After elevating the connecting tube 900 by the height of the connecting tube 900 may be connected to the manhole.

도 9은 본 발명의 제9실시예에 의한 지하층 바닥 배수시공 방법을 설명하기 위한 단면도이다.9 is a cross-sectional view for explaining the underground floor drainage construction method according to the ninth embodiment of the present invention.

도 9는 건물 외벽(600) 주위에 지층을 굴토하여 형성된 트렌치(100a)내의 집수관(80b)에 건물 내부의 시스템 배수로에서 연장된 주배수부재(1)이 연결되고 상기 집수관(80b)의 일면에 연결된 연결관(900)이 외부 집수정(5b)내로 형성된 상태가 도시되어 있다.9 is connected to the water collecting pipe 80b in the trench 100a formed by excavating a stratum around the outer wall 600 of the building, and the main drainage member 1 extending from the system drainage channel inside the building is connected to the water collecting pipe 80b. A state in which a connecting tube 900 connected to one surface is formed into an outer sump 5b is illustrated.

도 9을 참조하여 본 발명의 제8실시예에 의한 지하층 바닥 배수시공 방법을 설명하면, 지층을 굴토하여 외부 집수정 및 굴토마감면을 형성한 후 버림콘코리트를 타설하며 지하수 유도 홀(50)을 형성하고, 다발관으로 이루어진 주배수부재(1), 상기 배수판(2), 및 다발관으로 이루어진 부배수부재(4)를 커넥터(8)에 의하여 상호 연결하여 건물 내부 지하 바닥에 시스템 배수로를 형성하는 방법은 도1a에서 설명한 본 발명의 제1실시예에 의한 방법과 동일하게 실시된다.Referring to FIG. 9, the method for draining underground floors according to the eighth embodiment of the present invention is to excavate a ground layer to form an external water collecting well and a gulting dead surface, and then cast down concrete and ground water induction hole 50. And a main drain member (1) consisting of a bundle pipe, the drain plate (2), and a sub drainage member (4) consisting of a bundle tube are connected to each other by a connector (8) to form a system drainage passage on the basement floor of the building. The forming method is performed in the same manner as the method according to the first embodiment of the present invention described with reference to Fig. 1A.

이 후 건물 외벽 주위의 굴토마감면(10)을 굴토하여 트렌치(100a)를 형성하고 상기 트렌치(100a)내에 집수관(80b)을 매설한다. 상기 집수관(80b) 매설 작업이 끝나면 상기 시스템 배수로에서 연장된 주배부수재(1)의 일단이 상기 집수관(80b)에 연결된다. 상기 트렌치(100a)내의 집수관(80b)의 일면에는 연결관(900)이 연결되고, 상기 연결관(900)의 일단은 연장되어 외부 집수정(5) 내로 연결되어 지 하층 바닥 배수시공이 이루어진다.Thereafter, the trench 100a around the outer wall of the building is excavated to form a trench 100a, and a water collecting pipe 80b is embedded in the trench 100a. When the collecting pipe 80b is finished, one end of the main drainage material 1 extending from the system drainage passage is connected to the collecting pipe 80b. A connecting pipe 900 is connected to one surface of the collecting pipe 80b in the trench 100a, and one end of the connecting pipe 900 is extended to be connected to the external water collecting well 5 so that the ground floor drainage construction is performed. .

도 10은 본 발명의 제10실시예에 의한 지하층 바닥 배수시공 방법을 설명하기 위한 단면도이다.10 is a cross-sectional view for explaining the underground floor drainage construction method according to the tenth embodiment of the present invention.

도 10은 트렌치(100a)내의 집수관(80b)에서 연결된 연결관(900)이 외부 맨홀(700)로 연결된 상태가 도시되어 있다.FIG. 10 shows a state in which the connecting pipe 900 connected to the water collecting pipe 80b in the trench 100a is connected to the outer manhole 700.

도 10을 참조하여 본 발명의 제8실시예에 의한 지하층 바닥 배수시공 방법을 설명하면, 지층을 굴토하여 굴토마감면을 형성한 후 버림콘코리트를 타설하며 지하수 유도 홀(50)을 형성하고, 다발관으로 이루어진 주배수부재(1), 상기 배수판(2), 및 다발관으로 이루어진 부배수부재(4)를 커넥터(6)에 의하여 상호 연결하여 건물 내부 지하 바닥에 시스템 배수로를 형성하는 방법은 도1a에서 설명한 본 발명의 제1 실시예에 의한 방법과 동일하게 실시된다.Referring to FIG. 10, the method for draining underground floors according to an eighth embodiment of the present invention is described below. After the ground layer is excavated, the ground surface is formed, and the groundwater induction hole 50 is formed. The method for forming a system drainage path on the basement floor of a building by interconnecting the main drainage member (1) consisting of a bundle pipe, the drainage plate (2), and the secondary drainage member (4) consisting of a bundle pipe by a connector (6) It is implemented in the same manner as the method according to the first embodiment of the present invention described in FIG.

이 후 건물 외벽 주위의 굴토마감면을 굴토하여 트렌치(100a)를 형성하고 상기 트렌치(100a)내에 집수관(80b)을 매설한다. 상기 집수관(80b) 매설 작업이 끝나면 상기 시스템 배수로에서 연장된 주배부수재(1)의 일단이 상기 집수관(80b)에 연결된다. 상기 트렌치(100a)내의 집수관(80b)의 일면에는 연결관(900)이 연결되고, 상기 연결관(900)의 일단은 연장되어 외부 맨홀(700)로 연결되어 지하층 바닥 배수시공이 이루어진다.After that, the trench 100a is formed by excavating the gulting dead surface around the outer wall of the building, and the water collecting pipe 80b is embedded in the trench 100a. When the collecting pipe 80b is finished, one end of the main drainage material 1 extending from the system drainage passage is connected to the collecting pipe 80b. A connection pipe 900 is connected to one surface of the collecting pipe 80b in the trench 100a, and one end of the connection pipe 900 is extended to be connected to an external manhole 700 to perform a basement floor drainage construction.

도 11은 본 발명의 제11실시예에 의한 지하층 바닥 배수시공 방법을 설명하기 위한 단면도이다.11 is a cross-sectional view for explaining the underground floor drainage construction method according to the eleventh embodiment of the present invention.

도 11은 배수판(2)과 주배수부재(1) 및 부배수부재(4)를 연결한 커넥터(8)상 단에 직통배수관(800)이 직접 외부 집수관(80c)에 연결된 상태를 나타낸 평면도이다.11 is a plan view showing a state in which a direct drain pipe 800 is directly connected to an external collection pipe 80c at an upper end of a connector 8 connecting the drainage plate 2, the main drain member 1, and the sub drain member 4; to be.

도 11을 참조하여 본 발명의 제8실시예에 의한 지하층 바닥 배수시공 방법을 설명하면, 지층을 굴토하여 굴토마감면을 형성한 후 버림콘코리트를 타설하며 지하수 유도 홀(50)을 형성하고, 다발관으로 이루어진 주배수부재(1), 상기 배수판(2), 및 다발관으로 이루어진 부배수부재(4)를 커넥터(6)에 의하여 상호 연결하여 건물 내부 지하 바닥에 시스템 배수로를 형성하는 방법은 도1a에서 설명한 본 발명의 제1 실시예에 의한 방법과 동일하게 실시된다.Referring to FIG. 11, the method for draining underground floors according to an eighth embodiment of the present invention will be described below. After the ground layer is excavated to form a gulting finish surface, casting concrete is formed to form a groundwater induction hole 50. The method for forming a system drainage path on the basement floor of a building by interconnecting the main drainage member (1) consisting of a bundle pipe, the drainage plate (2), and the secondary drainage member (4) consisting of a bundle pipe by a connector (6) It is implemented in the same manner as the method according to the first embodiment of the present invention described in FIG.

이 후 주배수부재 및 부배수부재의 끝단이 연결될 방향으로 건물 외벽과 평행하게 건물 외벽바깥쪽에 집수관(80c)을 설치하고 주배수부재(1) 및 부배수부재(4)의 일단을 건물 외부의 상기 집수관(80c)에 연결하고, 배수판(2)과 주배수부재(1) 및 부배부수재(4)에 집수된 지하수가 많을시 집수관(80c)으로 원활히 지하수를 유도하기 위해, 상기 커넥터(6) 상단에 직통배수관(800)의 일단을 연결하고, 상기 직통배수관(800)의 타단을 외부 집수관(80c)에 직접 연결한다. 이후 상기 집수관(80c)의 일면에 연결관의 일단을 연결하고, 상기 연결관의 타단은 연장되어 외부 집수정 또는 맨홀내부로 연결되어 지하층에 배수로를 형성하는 배수시공이 이루어진다.Thereafter, a water collecting pipe 80c is installed outside the building outer wall parallel to the building outer wall in the direction in which the ends of the main drainage member and the subdrainage member are connected, and one end of the main drainage member 1 and the subdrainage member 4 is placed outside the building. Connected to the collecting pipe (80c) of, and when there is a lot of groundwater collected in the drainage plate (2) and the main drain member (1) and the secondary drainage material (4), in order to guide the groundwater smoothly to the collecting pipe (80c), One end of the straight through pipe 800 is connected to the upper end of the connector 6, and the other end of the straight through pipe 800 is directly connected to the outer collecting pipe 80c. Thereafter, one end of the connection pipe is connected to one surface of the collecting pipe 80c, and the other end of the connection pipe is extended to be connected to an external water collecting well or a manhole to form a drainage pipe in the basement layer.

상기 직통배수관(800)은 외부 집수관(80c)이 없는 시공현장에서 직접 외부 집수정이나 외부 맨홀에 연결될 수도 있다.The direct drain pipe 800 may be directly connected to an external water collecting well or an external manhole at a construction site without the external water collecting pipe 80c.

상술한 바와 같이 본 발명은 지하층 바닥에 대하여 배수로를 시공함에 있어서, 버림콘크리트 상에 배수 시스템을 시공하기 때문에 종래의 굴토마감면에 시공하는 것보다 평평한 기초위에 시공할 수 있어서 배수 시스템의 변형을 막을 수 있다.  As described above, in the present invention, since the drainage system is constructed on the basement floor, the drainage system is constructed on the discarded concrete, so that the construction can be applied on a flat foundation rather than the conventional gulting surface, thereby preventing deformation of the drainage system. Can be.

또한 버림콘크리트 상에 배수 시스템을 시공하기 때문에 버림콘크리트를 타설한 후에라도 상향수압의 처리 요구에 적절히 대응하여 공사기간이나 시공 비용을 줄일 수 있다.In addition, since the drainage system is constructed on the discarded concrete, it is possible to reduce the construction period or the construction cost by appropriately responding to the demand of the upstream hydraulic pressure even after the discarded concrete is poured.

또한 구체콘크리트는 종래의 굴토마감면과는 달리 지하수를 흡수하는 양이 적으므로, 방수 비닐과 더불어 2중의 방수 효과를 제공한다.In addition, concrete concrete has a small amount of absorbing groundwater, unlike conventional gulto finish surface, provides a double waterproof effect in addition to the waterproof vinyl.

또한 주배수부재에 공기 구멍을 갖는 뒤집힌 U자 모양의 수위조절관을 연결함으로써, 배수량이 많은 지역에서 상기 뒤집힌 U자 모양의 수위조절관의 최 상단 높이 위에 있는 지반의 수위만을 처리하여, 배수해야 할 지하수의 양을 적게 할 수 있다.In addition, by connecting an inverted U-shaped water level control tube having air holes to the main drainage member, it is necessary to process only the ground level above the highest level of the inverted U-shaped water level control tube in a large drainage area. Less groundwater to do

Claims (20)

지하층 바닥에 배수로를 형성하는 배수시공 방법에 있어서,In the drainage method of forming a drainage path in the basement floor, 지층에 굴토를 행하여 굴토마감면(10) 및 집수정(5)을 형성하는 굴토단계;A gulto step of forming gulto finish surface 10 and the water collecting well (5) by performing gulting on the strata; 상기 굴토마감면(10)상에 버림콘크리트(30)를 타설하는 단계; Casting the discarded concrete 30 on the gulting finish surface 10; 상기 타설된 버림콘크리트(30)상에 일방향에 대하여 등간격으로 소정의 내경을 갖는 지하수 유도 홀(50)을 형성하는 단계;Forming a groundwater guide hole (50) having a predetermined inner diameter at equal intervals in one direction on the poured concrete (30); 상기 타설된 버림콘크리트(30)상에 등간격으로 배치된 배수판(2)을 주배수부재(1)에 연결하고, 상기 주배수부재(1)의 일단을 상기 집수정(5)내에 연장하여 시스템 배수로를 형성하는 단계;The drainage plate 2 disposed at equal intervals on the cast concrete 30 is connected to the main drainage member 1, and one end of the main drainage member 1 extends in the sump 5. Forming a drainage path; 상기 버림콘크리트(30)와 상기 시스템 배수로 상에 비닐(20)을 설치하는 단계;Installing vinyl (20) on the discarded concrete (30) and the system drain; 상기 비닐(20)상에 지하층 바닥을 형성하기 위하여 구체콘크리트(40)를 타설하는 단계;Pouring concrete concrete (40) to form a basement floor on the vinyl (20); 를 포함하여 이루어지는 것을 특징으로 하는 지하층 바닥 배수시공 방법.Basement floor drainage construction method comprising a. 제1항에 있어서, The method of claim 1, 상기 지하수 유도홀(50)을 형성하는 단계에 있어서, 상기 버림콘크리트 타설 후 상기 콘크리트가 굳으면 드릴이나 착안기로 일방향 등간격으로 구멍을 뚫어서 상기 지하수 유도홀(50)을 형성하는 것을 특징으로 하는 지하층 바닥 배수시공 방 법In the step of forming the groundwater induction hole 50, if the concrete is solidified after the cast concrete is cast underground hole, characterized in that to form a groundwater induction hole 50 by drilling holes in one direction at equal intervals with a drill or an eyepiece Floor drainage method 제1항에 있어서,The method of claim 1, 상기 지하수 유도홀(50)을 형성하는 단계에 있어서, 상기 버림콘크리트 타설시 PVC관이나 파이프를 일방향 등간격으로 매설하여 상기 지하수 유도홀(50)을 형성하는 것을 특징으로 하는 지하층 바닥 배수시공 방법.In the step of forming the groundwater induction hole 50, the groundwater floor drainage method, characterized in that the groundwater induction hole 50 is formed by embedding the PVC pipe or pipe at equal intervals in one direction at the time of casting the concrete. 제1항에 있어서,The method of claim 1, 상기 지하수 유도홀(50)을 형성하는 단계에 있어서,상기 버림콘크리트 타설시 나무도막을 일방향 등간격으로 매설 후 상기 버림콘크리트가 굳으면 상기 나무도막을 빼내어 상기 지하수 유도홀(50)을 형성하는 것을 특징으로 하는 지하층 바닥 배수시공 방법.In the step of forming the groundwater induction hole 50, when the discarded concrete is laid at the same interval in one direction, when the discarded concrete is hardened to remove the wood coating to form the groundwater induction hole (50) Basement floor drainage construction method characterized in that. 제1항에 있어서,The method of claim 1, 버림콘크리트(30)와 버림콘크리트가 미타설된 굴토마감면(10)이 상존하는 넓은 시공현장에 있어, 상기 시스템 배수로가 버림콘크리트(30)를 관통하고, 그 후 상기 굴토마감면(10)상을 지나 집수정(5)으로 연결되는 것을 특징으로 하는 지하층 바닥 배수시공 방법.In a large construction site where the discarded concrete 30 and the discarded concrete pitted surface of the discarded concrete remain, the system drainage penetrates the discarded concrete 30, and then on the pitted soiled surface 10 Basement floor drainage construction method characterized in that connected to the sump (5). 제1항에 있어서,The method of claim 1, 버림콘크리트가 미타설된 굴토마감면(10)과 버림콘크리트(30)이 상존하는 넓은 시공현장에 있어, 상기 시스템 배수로가 굴토마감면(10)을 관통하고, 그 후 상기 버림콘크리트(30)상을 지나 집수정(5)으로 연결되는 것을 특징으로 하는 지하층 바닥 배수시공 방법.In the large construction site where the discarded concrete with the discarded oyster finish surface 10 and the discarded concrete 30 remain, the system drainage penetrates the pitted finish surface 10, and then on the discarded concrete 30 Basement floor drainage construction method characterized in that connected to the sump (5). 제1항, 제5항 및 제6항 중 어느 한 항에 있어서, The method according to any one of claims 1, 5 and 6, 상기 주배수부재(1)가 뒤집힌 U자 모양의 수위조절관(300)의 일측에 연결되고, 수위조절관(300)의 타측은 집수정(5)내에 연결되는 것을 특징으로 하는 지하층 바닥 배수시공 방법.The main drain member 1 is connected to one side of the inverted U-shaped water level control pipe 300, and the other side of the water level control pipe 300 is connected to the basement floor drainage construction, characterized in that Way. 제7항에 있어서,The method of claim 7, wherein 상기 수위조절관(300)이 PVC, 강 및 스테인레스 중 어느 하나의 재료로 이루어진 관인 것을 특징으로 하는 지하층 바닥 배수시공 방법.The water level control pipe 300 is a basement floor drainage construction method, characterized in that the pipe made of any one material of PVC, steel and stainless steel. 제7항에 있어서,The method of claim 7, wherein 상기 수위조절관(300)의 굽은 부위 상단에 공기 구멍이 형성된 것을 특징으로 하는 지하층 바닥 배수시공 방법.Basement floor drainage construction method characterized in that the air hole is formed on the top of the bent portion of the water level control pipe (300). 제1항에 있어서,The method of claim 1, 상기 버림콘크리트(30)상의 주배수부재(1)가 미리 굴토된 트렌치(100)내의 자갈층(70)에 매입되고, 상기 트렌치(100)내의 집수관(80)의 일단이 집수정(5)에 연결되는 것을 특징으로 하는 지하층 바닥 배수시공 방법.The main drainage member 1 on the discarded concrete 30 is embedded in the gravel layer 70 in the trench 100 that has been previously excavated, and one end of the collecting pipe 80 in the trench 100 is connected to the collecting well 5. Basement floor drainage construction method characterized in that connected. 제1항에 있어서,The method of claim 1, 상기 버림콘크리트(30)상의 주배수부재(1)는 미리 굴토된 트렌치(100)내의 집수관(80)에 연결되고, 집수관(80)의 일단은 집수정(5)의 내측으로 연장되어 형성되는 것을 특징으로 하는 지하층 바닥 배수시공 방법.The main drainage member 1 on the discarded concrete 30 is connected to the water collecting pipe 80 in the trench 100 which has been previously excavated, and one end of the water collecting pipe 80 extends into the water collecting well 5. Basement floor drainage construction method, characterized in that. 제9항 또는 제10항에 있어서,The method of claim 9 or 10, 상기 트렌치(100a)와 집수정(5b)이 건물 외부에 설치된 것을 특징으로 하는 지하층 바닥 배수시공 방법.Basement floor drainage method, characterized in that the trench (100a) and the sump (5b) is installed outside the building. 제1항에 있어서,The method of claim 1, 상기 주배수부재(1)와 부배수부재(2)의 일단이 건물 외부의 맨홀(700)에 연결되는 것을 특징으로 하는 지하층 바닥 배수시공 방법.Basement floor drainage construction method, characterized in that one end of the main drainage member (1) and the secondary drainage member (2) is connected to the manhole (700) outside the building. 제1항에 있어서,The method of claim 1, 상기 주배수부재(1)와 부배수부재(4)의 일단이 건물 외부의 집수관(80a)에 연결되고 상기 집수관(80a)이 건물 외부의 집수정(5a)내로 연결되는 것을 특징으로 하는 지하층 바닥 배수시공 방법.One end of the main drainage member 1 and the sub-drainage member 4 is connected to a water collecting pipe 80a outside the building, and the water collecting pipe 80a is connected into a water collecting well 5a outside the building. Basement floor drainage method. 제1항에 있어서,The method of claim 1, 상기 주배수부재(1)와 부배수부재(4)의 일단이 건물 외부의 집수관(80a)에 연결되고 상기 집수관(80a)이 건물 외부의 맨홀(700)내로 연결되는 것을 특징으로 하는 지하층 바닥 배수시공 방법.Basement floor, characterized in that one end of the main drain member (1) and the sub-drain member (4) is connected to the water collecting pipe (80a) outside the building and the water collecting pipe (80a) is connected to the manhole 700 outside the building Floor drainage method. 제14항 또는 15항에 있어서,The method according to claim 14 or 15, 시스템 배수로의 주배수부재(1)와 배수판(2)을 연결하는 커넥터에서 직접 연결되어 나온 직통배수관(800)이 상기 외부 집수관(80c)에 연결되는 것을 특징으로 하는 지하층 바닥 배수시공 방법.Underground floor drainage construction method characterized in that the direct drainage pipe (800) directly connected from the connector connecting the main drainage member (1) and the drain plate (2) of the system drainage is connected to the outer collection pipe (80c). 제14항 또는 15항에 있어서,The method according to claim 14 or 15, 시스템 배수로의 주배수부재(1)와 배수판(2)을 연결하는 커넥터에서 직접 연결되어 나온 직통배수관(800)이 건물외부에 굴토에 의해 형성된 집수정에 연결되는 것을 특징으로 하는 지하층 바닥 배수시공 방법.Underground floor drainage construction method characterized in that the direct drainage pipe (800) directly connected from the connector connecting the main drain member (1) and the drain plate (2) of the system drainage is connected to the sump formed by the excavation outside the building . 제14항 또는 15항에 있어서,The method according to claim 14 or 15, 시스템 배수로의 주배수부재(1)와 배수판(2)을 연결하는 커넥터에서 직접 연결되어 나온 직통배수관(800)이 건물외부에 인접한 맨홀에 연결되는 것을 특징으로 하는 지하층 바닥 배수시공 방법.Basement floor drainage construction method characterized in that the direct drainage pipe (800) directly connected from the connector connecting the main drain member (1) and the drain plate (2) of the system drainage is connected to the manhole adjacent to the outside of the building. 제1항에 있어서,The method of claim 1, 상기 주배수부재(1)는 다발관, 유공관 및 중공관 중 어느 하나로 이루어진 것을 특징으로 하는 지하층 바닥 배수시공 방법.The main drainage member (1) is a basement floor drainage construction method, characterized in that made of any one of a bundle pipe, a perforated pipe and a hollow pipe. 제1항에 있어서,The method of claim 1, 상기 부배수부재(1)는 다발관, 유공관 및 중공관 중 어느 하나로 이루어진 것을 특징으로 하는 지하층 바닥 배수시공 방법.The sub-drainage member (1) is a basement floor drainage construction method, characterized in that made of any one of a bundle tube, a perforated tube and a hollow tube.
KR1020040054265A 2004-07-13 2004-07-13 Method of drain construction for basement KR100655384B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020040054265A KR100655384B1 (en) 2004-07-13 2004-07-13 Method of drain construction for basement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020040054265A KR100655384B1 (en) 2004-07-13 2004-07-13 Method of drain construction for basement

Publications (2)

Publication Number Publication Date
KR20060005466A true KR20060005466A (en) 2006-01-18
KR100655384B1 KR100655384B1 (en) 2006-12-08

Family

ID=37117416

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020040054265A KR100655384B1 (en) 2004-07-13 2004-07-13 Method of drain construction for basement

Country Status (1)

Country Link
KR (1) KR100655384B1 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104404985A (en) * 2014-10-08 2015-03-11 中国十七冶集团有限公司 Construction method for basement floor post-cast strip waterproofing structure
CN106988341A (en) * 2017-05-11 2017-07-28 广东首汇蓝天工程科技有限公司 Multifunctional shield piping lane integrates well
CN108930263A (en) * 2018-09-04 2018-12-04 商丘工学院 A kind of basement process structure based on level of ground water
CN109457736A (en) * 2018-11-16 2019-03-12 中铁二十三局集团有限公司 One kind being used for underground engineering side wall and bottom plate water seepage treatment method
CN110847247A (en) * 2019-11-14 2020-02-28 中国二十冶集团有限公司 Waterproof operation construction method on multi-anti-floating anchor rod node basement bottom plate
CN114892724A (en) * 2022-04-25 2022-08-12 河南五建第二建筑安装有限公司 Anti pressure reduction system that floats of basement

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106759364B (en) * 2016-11-28 2018-09-04 中冶建工集团有限公司 Deep basal pit bottom plate step-by-step construction method
KR102012134B1 (en) * 2018-09-04 2019-08-19 박태환 Salt farm floor structure and method for constructing salt farm floor

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104404985A (en) * 2014-10-08 2015-03-11 中国十七冶集团有限公司 Construction method for basement floor post-cast strip waterproofing structure
CN106988341A (en) * 2017-05-11 2017-07-28 广东首汇蓝天工程科技有限公司 Multifunctional shield piping lane integrates well
CN108930263A (en) * 2018-09-04 2018-12-04 商丘工学院 A kind of basement process structure based on level of ground water
CN109457736A (en) * 2018-11-16 2019-03-12 中铁二十三局集团有限公司 One kind being used for underground engineering side wall and bottom plate water seepage treatment method
CN110847247A (en) * 2019-11-14 2020-02-28 中国二十冶集团有限公司 Waterproof operation construction method on multi-anti-floating anchor rod node basement bottom plate
CN114892724A (en) * 2022-04-25 2022-08-12 河南五建第二建筑安装有限公司 Anti pressure reduction system that floats of basement

Also Published As

Publication number Publication date
KR100655384B1 (en) 2006-12-08

Similar Documents

Publication Publication Date Title
CN110847199A (en) Construction method for drainage of underground water of deep foundation pit
KR100655384B1 (en) Method of drain construction for basement
KR100789976B1 (en) The soft ground improvement method with drain board having consecutive drainage space
CN110952574A (en) Method for treating landslide deformation body
KR100665984B1 (en) The construction method of basement self drainage
KR101024787B1 (en) Tunnel abutment precast block structure and drainage structure of new concept and method constructing abutment used by them
KR100926694B1 (en) Groundwater collection and drainage system of the substructure under the underground structure
KR100748607B1 (en) The construction method of basement drainage having double drainage canals and the system
KR100655383B1 (en) Method of drain construction for basement
KR100326868B1 (en) Drain Board and Drainage method using the same
CN214363925U (en) Cut water seepage ditch system
KR200434601Y1 (en) Drain Board System Of Basement Floor Construction
KR200433390Y1 (en) The construction system of basement drainage having double drainage canals
KR20020035216A (en) Structure method for drainageway of weak stratum and the conduct pipe thereof
KR200408863Y1 (en) The construction system of basement drainage having double drainage canals
KR20020033686A (en) Drainage System using Hexa-Tube Connector
KR100665985B1 (en) The construction method of basement self drainage
KR200431569Y1 (en) Hole Drain Board
KR100666102B1 (en) Vertical type basement drainage system
KR100383656B1 (en) Drainage construction method for concrete bottom of the underground floor
KR200314875Y1 (en) Connector for apparatus draining
KR20020013168A (en) A drainage construction method of ground floor
KR100561716B1 (en) A drain at slope
KR100656413B1 (en) The construction method of basement drainage having double drainage canals and the system
KR102110297B1 (en) Retaining wall and Retaining wall construction method

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
LAPS Lapse due to unpaid annual fee