KR20060003474A KR1020040052368A KR20040052368A KR20060003474A KR 20060003474 A KR20060003474 A KR 20060003474A KR 1020040052368 A KR1020040052368 A KR 1020040052368A KR 20040052368 A KR20040052368 A KR 20040052368A KR 20060003474 A KR20060003474 A KR 20060003474A
Authority
KR
South Korea
Prior art keywords
drilling
workbench
tunnel
ceiling
outer support
Prior art date
Application number
KR1020040052368A
Other languages
Korean (ko)
Inventor
박준형
Original Assignee
한국서부발전 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 한국서부발전 주식회사 filed Critical 한국서부발전 주식회사
Priority to KR1020040052368A priority Critical patent/KR20060003474A/en
Publication of KR20060003474A publication Critical patent/KR20060003474A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/40Devices or apparatus specially adapted for handling or placing units of linings or supporting units for tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F13/00Transport specially adapted to underground conditions
    • E21F13/006Equipment transport systems
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66FHOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
    • B66F11/00Lifting devices specially adapted for particular uses not otherwise provided for
    • B66F11/04Lifting devices specially adapted for particular uses not otherwise provided for for movable platforms or cabins, e.g. on vehicles, permitting workmen to place themselves in any desired position for carrying out required operations

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Mechanical Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Earth Drilling (AREA)

Abstract

본 발명은 수평 터널 내부의 천장부 천공작업 수행시 천공각도 별로 작업의 용이성을 위해 천공장비의 높낮이가 조절되고 작업대의 흔들림 방지와 바닥면의 급구배에 대해 보다 안정되게 보유 유지되는 터널내 천장부 천공장비 작업대에 관한 것으로, 외각 지지 프레임(1)과 이동용 바퀴(2)및 천공 시추기 작업 받침대(3)를 갖춘 터널 내 천장부 천공장비 작업대에 있어서, 상기 외각 지지 프레임(1)의 하부에는 가이드 롤러(4)와 스톱퍼(5)에 의해 이동이 규제된 대차(6)가 설치되고, 이 외각 지지 프레임(1)의 상부 프레임(1a)에는 호이스트 크레인(7)에 의해 천공 시추에 작업 받침대(3)가 현수 설치되며, 이 상부 프레임(1a)의 양측으로 가변되는 지지용 실린더(8) 들이 장착되어 이루어진 구조로 되어 있다.The present invention is to control the height of the drilling equipment for ease of operation for each drilling angle when performing the ceiling drilling work inside the horizontal tunnel, the ceiling drilling equipment workbench in the tunnel that is more stably held against the shake of the workbench and the bottom gradient In the perforated ceiling drilling rig workbench having an outer support frame (1), a moving wheel (2) and a drilling rig pedestal (3), the lower part of the outer support frame (1) has a guide roller (4). And a trolley 6 whose movement is restricted by the stopper 5 is installed, and a work pedestal 3 is suspended from the upper frame 1a of the outer support frame 1 by a hoist crane 7 for drilling. It is provided and has a structure in which the support cylinders 8 which are variable to both sides of this upper frame 1a are mounted.

Description

터널내 천장부 천공장비 작업대{Boring machine work deck of crown in tunnel}Boring machine work deck of crown in tunnel}

도 1은 본 발명에 따른 터널 내 천장부 천공장비 작업대를 나타낸 정면도이고, 1 is a front view showing a ceiling drilling rig workbench in accordance with the present invention,

도 2는 도 1의 측면도 이다.2 is a side view of FIG. 1.

- 도면의 주요 부분에 대한 부호의 설명--Explanation of symbols for the main parts of the drawing

1 : 외각 지지 프레임, 2 : 이동용 바퀴,1: outer support frame, 2: wheel for movement,

3 : 작업 받침대, 4 : 가이드 롤러,3: work base, 4: guide roller,

5 : 스톱퍼, 6 : 대차,5: stopper, 6: bogie,

7 : 호이스트 크레인, 8 : 지지용 실린더,7 hoist crane, 8 support cylinder,

9 : 유압 실린더, 10 : 고정용 지그,9: hydraulic cylinder, 10: jig for fixing,

11 : 사다리, 12 : 고정 작업대.11: ladder, 12: stationary worktable.

본 발명은 수평 터널 내부의 천장부 천공 작업 수행시 천공각도 별로 작업의 용이성을 위해 천공장비의 높낮이가 조절되고 작업대의 흔들림 방지 와 바닥면의 급구배에 대해 보다 안정되게 보유 유지되는 터널 내 천장부 천공장비 작업대에 관한 것이다.The present invention is to adjust the height of the drilling equipment for ease of operation for each drilling angle when performing the ceiling drilling work inside the horizontal tunnel, the ceiling drilling equipment workbench in the tunnel that is more stably held against the shaking of the workbench and the bottom gradient It is about.

통상 터널은 그 용도에 따라 철도, 도로와 같은 교통용 터널과, 수력발전· 관개 등을 위한 수로용 터널, 상·하수도, 전선로 등의 관로용 터널 및, 이 밖의 지하 발전소, 변전소, 석유 저장용 공동 등도 포함되는데, 이중 수력발전·관개 등을 위한 수로용 터널의 굴착단면은 지압에 견딜 수 없는 말굽형으로 되어 있으면서 콘크리트 등으로 피복하여 소정의 내공단면을 갖는 복공 작업으로 마무리 하도록 되어 있다. Normally, tunnels are used for transportation tunnels such as railroads and roads, tunnels for waterways for hydroelectric power generation and irrigation, pipelines for water and sewage and wire lines, and other underground power plants, substations and oil storage. For example, the excavation section of the waterway tunnel for hydroelectric power generation, irrigation, etc. is made of horseshoe type that cannot withstand acupressure, but is covered with concrete and finished with a perforation work having a predetermined internal air cross section.

이와 같이 굴착된 터널의 복공 작업시 천장부는 도 1과 같이 천공장비를 이용하여 보링 구멍(101) 들을 천공한 다음, 비럭처리 작업과 콘크리트 타설 작업이 이루어지게 되어 있다.As a result of the perforated work of the excavated tunnel, the ceiling unit drills the boring holes 101 by using the drilling equipment as shown in FIG. 1, and then the rubbing treatment and the concrete pouring work are performed.

한편, 종래 터널 천장부의 천공 작업시 이용되는 천공장비의 작업대는 천공 작업시 차량 교행이 불가능하여 긴 터널 내에서 작업자들의 진출입에 상당한 애로점이 있었으며, 콘크리트 타설과 같은 타공정 과의 병행작업도 불가능하여 자연히 건설공기가 지연되는 문제점이 있었다.On the other hand, the workbench of the drilling equipment used in the drilling work of the conventional tunnel ceiling has a considerable difficulty in the entry and exit of workers in the long tunnel because it is impossible to cross the vehicle during the drilling work, and the parallel work with other processes such as concrete casting is also impossible. Naturally, there was a problem that construction air is delayed.

또한, 천공장비를 보유 지지하는 작업대가 구배진 터널 바닥면에서 불안정 작업상태 위치를 유지 하에 따라 작업대의 안정된 작업위치 확보에 많은 시간을 소요하게 되는 단점도 있었다.In addition, as the workbench holding the drilling equipment maintains the unstable work position at the bottom of the gradient tunnel, it takes a long time to secure a stable work position of the workbench.

이에 본 발명은 상기와 같은 종래 문제점을 해결하기 위해 발명된 것으로, 천공 시추장비의 높낮이 조절이 가능하면서 타공정 과의 병행작업이 이루어지며, 작업대의 하부굴 차량 교행을 위한 공간확보와 작업대의 안정성도 향상되는 터널내 천장부 천공장비 작업대를 제공함에 그 목적이 있다.Therefore, the present invention was invented to solve the above conventional problems, while being able to adjust the height of the drilling rig, and make parallel work with other processes, to secure the space and the stability of the workbench for working on the lower berth of the workbench. The object of the present invention is to provide a workbench in the tunnel ceiling drilling equipment is improved.

상기와 같은 목적을 달성하기 위한 본 발명은 외각 지지 프레임과 이동용 바퀴 및 천공 시추기 작업 받침대를 갖춘 터널내 천장부 천공장비 작업대에 있어서, 상기 외각 지지 프레임의 하부에는 가이드 롤러 와 스톱퍼에 의해 이동이 규제되는 대차가 설치되고, 이 외각 지지 프레임의 상부 프레임에는 호이스트 크레임에 현수된 천공 시추기 작업 받침대가 설치되며, 이 상부 프레임의 양측으로 가변되는 지지용 실린더들이 장착되어 이루어진 구조로 되어 있다.In order to achieve the above object, the present invention provides a perforated ceiling drilling rig workbench with an outer support frame, a movable wheel and a drilling rig pedestal, the lower portion of the outer support frame being restricted by a guide roller and a stopper. The trolley is installed, and the upper frame of the outer support frame is provided with a perforated drilling work pedestal suspended from the hoist frame, and has a structure in which support cylinders that are variable to both sides of the upper frame are mounted.

이하, 본 발명을 첨부된 예시도면에 의거 상세히 설명한다.Hereinafter, the present invention will be described in detail with reference to the accompanying drawings.

도 1은 본 발명에 따른 터널내 천장부 천공장비 작업대의 정면도이고, 도 2는 도 1의 측면도이다.1 is a front view of the ceiling drilling rig workbench in accordance with the present invention, Figure 2 is a side view of FIG.

본 발명은 도면에 도시된 바와 같이 터널(100)내 천장부에 보링 구멍(101) 들을 천공하는 천공장비를 싣는 작업대로서, 외각 지지 프레임(1)과 이동용 바퀴(2) 및 천공 시추기 작업 받침대(3)를 갖춘 터널내 천장부 천공장비 작업대에 있어서, 상기 외각 지지 프레임(1)의 하부에는 가이드 롤러(4)와 스톱퍼(5)에 의해 이동이 규제된 대차(6)가 설치되고, 이 외각 지지 프레임(1)의 상부 프레임(1a)에는 호이스트 크레인(7)에 의해 천공 시추에 작업 받침대(3)가 현수 설치되며, 이 상부 프레임(1a)의 양측으로 가변되는 지지용 실린더(8)들이 장착되어 이루어진 구조로 되어 있다.The present invention is a workbench for mounting the drilling equipment for drilling boring holes 101 in the ceiling in the tunnel 100, as shown in the drawings, the outer support frame 1 and the moving wheels 2 and drilling drilling work pedestal (3) In the perforated ceiling drilling rig workbench having a), a trolley 6 whose movement is restricted by a guide roller 4 and a stopper 5 is installed below the outer support frame 1, and the outer support frame is installed. On the upper frame 1a of (1), a work pedestal 3 is suspended from a drilling rig by a hoist crane 7, and supporting cylinders 8 that are variable to both sides of the upper frame 1a are mounted. It is made of structure.

그리고 상기 외각 지지 프레임(1)의 하부 프레임(1b)에는 유압 실린더(9)에 의해 그 위치가 가변되어 고정되는 고정용 지그(10) 들이 설치되어 있으며, 상기 상·하부 프레임(1a, 1b) 사이에는 사다리(11)를 갖춘 고정 작업대(12)가 장착되어 있다.The lower frame 1b of the outer shell supporting frame 1 is provided with fixing jig 10 fixed in a fixed position thereof by the hydraulic cylinder 9, and the upper and lower frames 1a and 1b. A fixed work bench 12 having a ladder 11 is mounted therebetween.

그리고 도면 중 미설명 부호 (13)은 운전 판넬부이다.In the drawings, reference numeral 13 denotes an operation panel.

이러한 구조를 갖는 본 발명은 터널(100) 내부의 바닥면에서 자유롭게 이동 또는 고정 지지되면서 터널(100)의 천장부에 보링 구멍(101)을 공지의 천공 시추기로 시공할 수 있다.According to the present invention having such a structure, the boring hole 101 may be installed in the ceiling of the tunnel 100 by a well-known drilling rig while being freely moved or fixedly supported on the bottom surface of the tunnel 100.

즉 천공 시추기를 작업 받침대(3)에 싣고서 천장부의 천공작업 위치에 작업대가 도달하게 되면, 먼저 유압 실린더(9)를 이용하여 고정용 지그(8)를 터널(100) 바닥면에 고정 위치시키게 되는데, 이때 이 터널(100) 바닥면이 구배진 상태에서도 도 2와 같이 고정용 지그(10)는 견고하게 바닥면에 위치 고정된다.That is, when the worktable reaches the drilling work position of the ceiling by mounting the drilling drilling machine on the work stand 3, first, the fixing jig 8 is fixed to the bottom surface of the tunnel 100 using the hydraulic cylinder 9. In this case, the fixing jig 10 is firmly fixed to the bottom surface as shown in FIG.

그런 다음 상부 프레임(1a)의 호이스트 크레인(7)을 하강시킨 후, 작업받침대(3)에 공지의 천공 시추기를 적재한 후 다시 승강 시키어 정확한 천공작업 위치에서 터널(100) 천장부의 천공 보링 작업을 수행할 수 있도록 되어 있다.Then, after lowering the hoist crane (7) of the upper frame (1a), the well-drilling drilling machine is loaded on the work support (3), and then lifted again to drill the boring boring work in the ceiling of the tunnel 100 at the correct drilling work position. It can be done.

한편, 도 1과 같이 상기 외각 지지 프레임(1)의 하부 쪽에 설치된 대차(6)를 이용하여 천공작업 중이라도 차량의 교행이 확보된 외각 지지 프레임(1)의 하부공간을 통해 이루어지게 하며, 이 대차(6)는 유압에 의해 가이드 롤러(4)와 스톱퍼(5) 들에 의해 그 이동이 규제되어진다.On the other hand, as shown in Figure 1 by using the trolley (6) installed on the lower side of the outer support frame (1) to make the through the lower space of the outer support frame (1) secured the intersection of the vehicle even during the drilling operation, The movement of 6 is regulated by the guide roller 4 and the stoppers 5 by hydraulic pressure.

상기와 같이 본 발명에 따른 터널내 천장부 천공장비 작업대는 다음과 같은 잇점들을 갖추게 된다.As described above, the workbench in the ceiling ceiling drilling apparatus according to the present invention has the following advantages.

① 작업대 하부 차량 교행을 위한 하부 단면 확보.① Secure the lower section for vehicle traffic under the workbench.

② 바닥면 급구배로 인한 시추작업의 불편함을 개선하기 위해 하부에 높이 조정이 가능.② Height adjustment is possible in the lower part to improve the inconvenience of drilling work due to the bottom grade gradient.

③ 천장부 경사각 시추시 작업대의 흔들림 방지를 위해 작업대 상단부 지지.③ Support the upper part of the workbench to prevent shaking of the workbench when drilling the inclined angle of the ceiling part.

④ 천공장비 발판의 안정성 확보.④ Secure the stability of drilling equipment scaffolding.

⑤ 천공 각도별로 작업을 용이하게 하기 위해 천공장비 높이 조절이 가능.⑤ Height adjustment of drilling equipment is possible to facilitate the work by drilling angle.

⑥ 작업 받침대 상·하 이동시 안정성 확보.⑥ Securing stability when moving work base up and down.

Claims (2)

외각 지지 프레임(1)과 이동용 바퀴(2)및 천공 시추시 작업 받침대(3)를 갖춘 터널내 천장부 천공장비 작업대에 있어서, In a perforated ceiling drilling rig workbench with an outer support frame (1), a moving wheel (2) and a work stand (3) for drilling drilling, 상기 외각 지지 프레임(1)의 하부에는 가이드 롤러(4)와 스톱퍼(5)에 의해 이동이 규제된 대차(6)가 설치되고, 이 외각 지지 프레임(1)의 상부 프레임(1a)에는 호이스트 크레인(7)에 의해 천공 시추에 작업 받침대(3)가 현수 설치되며, 이 상부 프레임(1a)의 양측으로 가변 되는 지지용 실린더(8) 들이 장착되어 이루어진 것을 특징으로 하는 터널내 천장부 천공장비 작업대.The trolley | bogie 6 by which the movement was regulated by the guide roller 4 and the stopper 5 is installed in the lower part of the outer support frame 1, and the hoist crane is attached to the upper frame 1a of this outer support frame 1; (7) The work pedestal (3) is suspended in the drilling drilling, the ceiling in the tunnel drilling equipment workbench, characterized in that the support cylinders (8) which are variable to both sides of the upper frame (1a) is mounted. 제 1 항에 있어서, 상기 외각 지지 프레임(1)의 하부 프레임(1b)에는 유압 실린더(9)에 의해 그 위치가 가변 되어 고정되는 고정용 지그(10) 들이 설치되어 이루어진 것을 특징으로 하는 터널내 천장부 천공장비 작업대.The inside of the tunnel according to claim 1, wherein the lower frame 1b of the outer support frame 1 is provided with fixing jigs 10 fixed in position by a hydraulic cylinder 9 and fixed thereto. Ceiling drilling rig workbench.
KR1020040052368A 2004-07-06 2004-07-06 Boring machine work deck of crown in tunnel KR20060003474A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020040052368A KR20060003474A (en) 2004-07-06 2004-07-06 Boring machine work deck of crown in tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020040052368A KR20060003474A (en) 2004-07-06 2004-07-06 Boring machine work deck of crown in tunnel

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR20-2004-0026105U Division KR200372292Y1 (en) 2004-09-10 2004-09-10 Boring machine work deck of crown in tunnel

Publications (1)

Publication Number Publication Date
KR20060003474A true KR20060003474A (en) 2006-01-11

Family

ID=37105910

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020040052368A KR20060003474A (en) 2004-07-06 2004-07-06 Boring machine work deck of crown in tunnel

Country Status (1)

Country Link
KR (1) KR20060003474A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103512465A (en) * 2012-06-19 2014-01-15 中铁十九局集团第一工程有限公司 Multifunctional section detecting trolley for tunnel
KR102109969B1 (en) * 2019-06-25 2020-05-12 주식회사 동해종합기술공사 A work bogie for tunnel work

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103512465A (en) * 2012-06-19 2014-01-15 中铁十九局集团第一工程有限公司 Multifunctional section detecting trolley for tunnel
KR102109969B1 (en) * 2019-06-25 2020-05-12 주식회사 동해종합기술공사 A work bogie for tunnel work

Similar Documents

Publication Publication Date Title
CN203403418U (en) Steel casing double-layer guide frame structure
CN103669351A (en) Full-stroke hole-leading hydraulic static pile driver
CN105464117A (en) Rotary-type overwater piling guide frame and piling process for overwater pile group foundations
CN201738321U (en) Multifunctional pile machine
CN108839758A (en) A kind of offshore engineering ship borne type platform prospecting equipment draw off gear and folding and unfolding method
WO2012062968A1 (en) Scaffolding attachment arrangement
CN101936009B (en) Deepwater single-wall steel overhead bin cofferdam and construction method thereof
CN106088120B (en) A kind of cofferdam decentralization construction method
JP2016199929A (en) Bridge construction method and column body and guide means used in the same
CN203654196U (en) Guide apparatus for large and multifunctional over-water construction platform
KR200372292Y1 (en) Boring machine work deck of crown in tunnel
KR20060003474A (en) Boring machine work deck of crown in tunnel
CN105604061B (en) A kind of surface unit and its construction method entering rock installation for steel-pipe pile in water
CN201908578U (en) Hydraulic drill frame for drilling holes on anti-impact walls
CN208715418U (en) A kind of offshore engineering ship borne type platform prospecting equipment draw off gear
JP2006348595A (en) Pier undersurface concrete automatic chipping apparatus
KR100592929B1 (en) Workbench on the side wall of tunnel
CN116356801A (en) Ground continuous wall stay column dismantling mode
KR200369333Y1 (en) Boring machine work deck of side wall in tunnel
CN106050125B (en) A kind of portable all-hydraulic engineering investigation drilling machine
CN214944030U (en) Locking and fixing device suitable for bridge pile foundation percussion drill
JPH07217392A (en) Working apparatus for tunnel construction
JP4844934B2 (en) Drilling leader vertical adjustment mechanism
CN209908502U (en) Frame type shaft self-climbing template
CN207700189U (en) A kind of pile-grafting machine with monitoring function

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E601 Decision to refuse application