KR200447023Y1 - Base block for installing sidewalk boundary stone - Google Patents

Base block for installing sidewalk boundary stone Download PDF

Info

Publication number
KR200447023Y1
KR200447023Y1 KR20090006343U KR20090006343U KR200447023Y1 KR 200447023 Y1 KR200447023 Y1 KR 200447023Y1 KR 20090006343 U KR20090006343 U KR 20090006343U KR 20090006343 U KR20090006343 U KR 20090006343U KR 200447023 Y1 KR200447023 Y1 KR 200447023Y1
Authority
KR
South Korea
Prior art keywords
boundary stone
foundation block
sidewalk
block
boundary
Prior art date
Application number
KR20090006343U
Other languages
Korean (ko)
Inventor
김영
Original Assignee
김영
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김영 filed Critical 김영
Priority to KR20090006343U priority Critical patent/KR200447023Y1/en
Application granted granted Critical
Publication of KR200447023Y1 publication Critical patent/KR200447023Y1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/22Gutters; Kerbs ; Surface drainage of streets, roads or like traffic areas
    • E01C11/221Kerbs or like edging members, e.g. flush kerbs, shoulder retaining means ; Joint members, connecting or load-transfer means specially for kerbs
    • E01C11/222Raised kerbs, e.g. for sidewalks ; Integrated or portable means for facilitating ascent or descent
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/16Reinforcements
    • E01C11/18Reinforcements for cement concrete pavings
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C2201/00Paving elements
    • E01C2201/16Elements joined together
    • E01C2201/167Elements joined together by reinforcement or mesh

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

본 고안 보차도 경계석 설치용 기초 블록은 보도와 차도의 경계부분에 설치되는 경계석을 설치하기 위한 기초 블록으로서, 보도측에 근접한 상면의 일측에 일정 두께로 상향 돌출되어 기초 블록의 길이 방향을 따라 형성되고 상면 중앙 부위에 안착되는 경계석의 대응 측면을 지지하는 경계석 지지부; 상기 경계석과 차도 사이의 측구측에 근접한 상면의 다른 일측에 상향 돌출된 복수의 돌출편들이 배열되어 측구의 현장 타설시 상기 기초 블록의 상면에 타설되는 콘크리트와 기초 블록의 부착력을 보강하기 위한 보강부를 포함한다. 이에 의하면, 경계석을 신속하게 설치할 수 있으며, 경계석의 설치시 경계석의 이탈 없이 견고하게 안착시킬 수 있으며, 경계석의 설치 및 측구 시공의 연속 작업이 가능하고, 도로 시공시 시공 기간 단축 및 노무비를 절감할 수 있는 등의 이점이 있다.The base block for installing the curbside boundary stone of the present invention is a foundation block for installing a boundary stone installed at the boundary between the sidewalk and the roadway, protrudes upward at a predetermined thickness on one side of the upper surface close to the sidewalk, and is formed along the longitudinal direction of the foundation block and the upper surface. A boundary stone support for supporting a corresponding side of the boundary stone seated at the central portion; A plurality of protrusions protruding upwardly are arranged on the other side of the upper surface adjacent to the side opening side between the boundary stone and the roadway, so that the reinforcing portion for reinforcing the adhesive force between the concrete and the foundation block placed on the upper surface of the foundation block during the site casting of the side opening. Include. According to this, the boundary stone can be installed quickly, and when the boundary stone is installed, it can be firmly settled without detachment of the boundary stone, and it is possible to install the boundary stone and the continuous construction of the side gate, and to shorten the construction period and reduce labor costs during road construction. And so on.

경계석, 기초 블록, 경계석 지지부, 돌출편, 보강부 Boundary stone, foundation block, boundary stone support, protrusion, reinforcement

Description

보차도 경계석 설치용 기초 블록{BASIS BLOCK FOR BOUNDARY STONE INSTALLATION OF SIDEWALK AND ROADWAY}Basic block for footpath boundary stone installation {BASIS BLOCK FOR BOUNDARY STONE INSTALLATION OF SIDEWALK AND ROADWAY}

본 고안은 보차도 경계석 설치용 기초 블록에 관한 것으로, 더욱 상세하게는 보도 및 차도를 형성하는 도로 시공시 보차도 경계석을 신속하게 설치할 수 있는 보차도 경계석 설치용 기초 블록에 관한 것이다.The present invention relates to a foundation block for installing a sidewalk road curbstone, and more particularly, to a foundation block for a sidewalk road boundary stone installation that can quickly install a sidewalk road boundary stone when a road construction forms a sidewalk and a roadway.

일반적으로 보도 및 차도를 포함하는 도로를 건설할 때, 경계석과 측구를 별도의 공정으로 설치한 후 보도 및 차도를 형성한다.In general, when constructing a road including sidewalks and driveways, the curbstones and sideways are installed in a separate process and then the sidewalks and driveways are formed.

더욱 상세하게는 종래에 도로를 건설할 때, 먼저 보도 및 차도의 경계를 위한 경계석을 설치하기 위하여 경계석 설치 부위의 지반에 콘크리트를 타설하고, 콘크리트가 굳어지면 경계석을 설치하였다.More specifically, when constructing a road in the prior art, in order to install a boundary stone for the boundary of the sidewalk and the roadway, first, concrete is placed on the ground of the boundary stone installation site, and when the concrete is hardened, the boundary stone is installed.

이때, 작업자는 경계석 설치를 위한 콘크리트의 타설 후 굳어지는 시간까지 장시간 대기하고, 콘크리트가 굳어지면 경계석을 설치하였다.At this time, the worker waits for a long time until the time to harden after the concrete is installed for the installation of the boundary stone, and installed the boundary stone when the concrete is hardened.

경계석의 설치 후에는 경계석에서 보도측으로 콘크리트를 타설하여 경계석을 고정한 다음, 경계석에서 차도측으로 다시 콘크리트를 타설하여 측구를 형성하였다.After the installation of the boundary stone, concrete was cast from the boundary stone to the sidewalk to fix the boundary stone, and then concrete was cast from the boundary stone to the side of the roadway to form a side opening.

측구가 형성된 후에는 보도측에 보도블록을 나열하여 보도를 형성하고, 측구의 옆으로는 아스팔트를 깔면서 차도를 형성하여 도로 시공을 완료하였다.After the side opening was formed, sidewalk blocks were arranged on the side of the sidewalk to form a sidewalk, and the sideways of the side were laid with asphalt to form a roadway to complete the construction of the road.

이러한 종래의 도로 시공 과정에서는 상기 설명과 같이 경계석을 설치하기 위하여 경계석 설치 부위에 콘크리트를 타설한 후 콘크리트가 굳어지기까지 작업자가 장시간 기다려야 하므로 경계석의 설치가 신속하게 이루어질 수 없었다. 이에 따라 도로 시공 기간은 길어질 수 밖에 없었으며, 노무비가 증가하는 문제가 있었다.In this conventional road construction process, since the worker has to wait for a long time until concrete is solidified after placing concrete at the boundary stone installation site to install the boundary stone as described above, the installation of the boundary stone could not be made quickly. Accordingly, the road construction period was inevitably long, and there was a problem that labor costs increased.

또한 경계석의 설치가 신속하게 이루어질 수 없게 되므로 도로 시공 현장에서 측구 시공, 보도 및 차도의 형성 작업이 연속적으로 이루어질 수 없었다.In addition, since the installation of the boundary stone can not be made quickly, the construction work of the sideways construction, sidewalks and roadways could not be performed continuously at the road construction site.

따라서 본 고안이 해결하고자 하는 과제는 경계석을 신속하게 설치하여 측구 시공의 연속 작업이 가능하도록 하고, 도로 시공 기간 단축 및 노무비를 절감할 수 있도록 한 보차도 경계석 설치용 기초 블록을 제공하는데 있다.Therefore, the problem to be solved by the present invention is to provide a foundation block for the installation of a boundary road boundary stone to install the boundary stone quickly to enable the continuous work of the side construction, and to reduce the road construction period and labor costs.

상술한 과제를 해결하기 위한 본 고안의 한 실시예에 따른 보차도 경계석 설치용 기초 블록은 보도와 차도의 경계부분에 설치되는 경계석을 설치하기 위한 기초 블록으로서, 보도측에 근접한 상면의 일측에 일정 두께로 상향 돌출되어 기초 블록의 길이 방향을 따라 형성되고 상면 중앙 부위에 안착되는 경계석의 대응 측면을 지지하는 경계석 지지부; 상기 경계석과 차도 사이의 측구측에 근접한 상면의 다른 일측에 상향 돌출된 복수의 돌출편들이 배열되어 측구의 현장 타설시 상기 기초 블록의 상면에 타설되는 콘크리트와 기초 블록의 부착력을 보강하기 위한 보강부를 포함한다.The base block for installing a sidewalk road boundary stone according to an embodiment of the present invention for solving the above problems is a base block for installing a boundary stone installed at the boundary between the sidewalk and the roadway, and has a predetermined thickness on one side of the upper surface close to the sidewalk. A boundary stone support portion protruding upward to support a corresponding side surface of the boundary stone formed along the longitudinal direction of the foundation block and seated on the central portion of the upper surface; A plurality of protrusions protruding upwardly are arranged on the other side of the upper surface adjacent to the side opening side between the boundary stone and the roadway, so that the reinforcing portion for reinforcing the adhesive force between the concrete and the foundation block placed on the upper surface of the foundation block during the site casting of the side opening. Include.

상기 돌출편들은 상호 교차하여 바둑판식으로 배열될 수 있다.The protruding pieces may be tiled to cross each other.

상기 돌출편들은 단면 형상이 반원형, 직사각형, ㄱ자형, T자형 중 어느 하나의 형상으로 형성될 수 있다.The protruding pieces may have a cross-sectional shape in the shape of any one of a semicircle, a rectangle, an L-shape, and a T-shape.

상기 기초 블록의 상기 보강부측 측면에 설치되는 적어도 하나의 균열 방지 부재를 더 포함할 수 있다.The base block may further include at least one crack preventing member installed on the side of the reinforcing portion side.

상기 균열 방지 부재는 ㄷ자 형상으로 형성될 수 있다.The crack preventing member may be formed in a U shape.

상술한 과제를 해결하기 위한 본 고안의 다른 실시예에 따른 보차도 경계석 설치용 기초 블록은 상기 경계석이 안착되는 상기 기초 블록의 상면 중앙 부위에 매설되어 상기 기초 블록의 상면에 다수의 요철을 형성시키는 경계석 밀림 방지 부재를 더 포함한다.The boundary block installation foundation block according to another embodiment of the present invention for solving the above problems is embedded in the central portion of the upper surface of the foundation block on which the boundary stone is seated to form a plurality of irregularities on the upper surface of the foundation block It further comprises a prevention member.

상기 경계석 밀림 방지 부재는 판상의 베이스, 그리고 상기 베이스 상면에 등간격 배열되어 상단이 상기 기초 블록의 상면에 노측되는 다수의 요철편들로 구성될 수 있다.The boundary stone rolling prevention member may be formed of a plate-shaped base and a plurality of uneven pieces which are arranged at equal intervals on an upper surface of the base, and whose upper end is a roadside on the upper surface of the foundation block.

상기 요철편들은 원뿔, 삼각뿔 중 어느 하나의 형상으로 형성될 수 있다.The uneven pieces may be formed in any one of a cone, a triangular pyramid.

본 고안에 따른 보차도 경계석 설치용 기초 블록에 의하면, 경계석을 신속하게 설치할 수 있으며, 경계석의 설치시 경계석의 이탈 없이 견고하게 안착시킬 수 있으며, 경계석의 설치 및 측구 시공의 연속 작업이 가능하고, 도로 시공시 시공 기간 단축 및 노무비를 절감할 수 있는 등의 효과가 있다.According to the basic block for the installation of the boundary road according to the present invention, the boundary stone can be installed quickly, and when the boundary stone is installed, it can be firmly seated without detachment of the boundary stone, and the continuous work of the boundary stone installation and side construction can be performed, and the road construction It can shorten the construction period and reduce labor costs.

기타 실시예의 구체적인 사항들은 상세한 설명 및 도면들에 포함되어 있다.Specific details of other embodiments are included in the detailed description and drawings.

본 고안의 이점 및 특징, 그리고 그것들을 달성하는 방법은 첨부되는 도면과 함께 상세하게 후술되어 있는 실시예를 참조하면 명확해질 것이다.Advantages and features of the present invention, and methods for achieving them will be apparent with reference to the embodiments described below in detail in conjunction with the accompanying drawings.

그러나 본 고안은 이하에서 개시되는 실시예에 한정되는 것이 아니라 서로 다른 다양한 형태로 구현될 것이며, 단지 본 실시예는 본 고안의 개시가 완전하도록 하며, 본 고안이 속하는 기술분야에서 통상의 지식을 가진 자에게 고안의 범주 를 완전하게 알려주기 위해 제공되는 것이며, 본 고안은 청구항의 범주에 의해 정의될 뿐이다.However, the present invention is not limited to the embodiments disclosed below, but will be implemented in various different forms, only this embodiment is to make the disclosure of the present invention is complete, and having ordinary skill in the art It is provided to inform the full disclosure of the scope of the invention, and the invention is defined only by the scope of the claims.

이하, 첨부된 도면을 참조로 하여 본 고안의 한 실시예에 따른 보차도 경계석 설치용 기초 블록에 대하여 상세히 설명한다.Hereinafter, with reference to the accompanying drawings will be described in detail with respect to the foundation block for installing the sidewalk road boundary stone according to an embodiment of the present invention.

도 1은 본 고안의 한 실시예에 따른 보차도 경계석 설치용 기초 블록의 외관을 나타낸 사시도이고, 도 2는 본 고안의 한 실시예에 따른 보차도 경계석 설치용 기초 블록에 의해 경계석이 설치된 상태를 나타낸 부분 확대 단면도이다.1 is a perspective view showing the appearance of the foundation block for the installation of a sidewalk according to an embodiment of the present invention, Figure 2 is a partially enlarged cross-sectional view showing a state in which the boundary stone is installed by the foundation block for installing a boundary road according to an embodiment of the present invention. to be.

본 고안의 한 실시예에 따른 보차도 경계석 설치용 기초 블록은 보도(3)와 차도(4)의 경계부분에 설치되는 경계석(5)을 설치하기 위한 것으로, 기초 블록(10)의 경계석(5)이 안착되는 상면의 중앙 부위 양측에는 도 1과 같이 경계석 지지부(11)와 보강부(12)가 형성되어 있다.The foundation block for installing a sidewalk road boundary stone according to an embodiment of the present invention is for installing a boundary stone 5 installed at the boundary of the sidewalk 3 and the roadway 4, and the boundary stone 5 of the foundation block 10 is provided. On both sides of the central portion of the upper surface to be seated, the boundary stone support 11 and the reinforcement 12 are formed as shown in FIG. 1.

경계석 지지부(11)는 기초 블록(10) 상면의 일측, 즉 보도(3)에 근접한 일측에 상측으로 돌출되어 형성되고, 기초 블록(10) 상면 중앙 부위에 경계석(5)이 안착될 때 경계석(5)의 대응되는 측면을 지지한다.The boundary stone support part 11 is formed to protrude upward on one side of the upper surface of the foundation block 10, that is, on one side close to the sidewalk 3, and when the boundary stone 5 is seated on the center portion of the upper surface of the foundation block 10, the boundary stone ( Support the corresponding side of 5).

이러한 경계석 지지부(11)는 경계석(5)이 기초 블록(10) 상면에 안착될 때 경계석(5)이 측면 방향으로 밀려나는 것을 방지할 수 있으며, 50㎝의 두께 및 높이를 가지도록 형성될 수 있고, 50㎝ 이하 또는 이상의 높이 및 두께를 갖도록 형성될 수도 있다.The boundary stone support 11 may prevent the boundary stone 5 from being pushed laterally when the boundary stone 5 is seated on the upper surface of the foundation block 10, and may be formed to have a thickness and a height of 50 cm. It may be formed to have a height and thickness of 50 cm or less or more.

보강부(12)는 기초 블록(10)의 다른 일측, 즉 경계석 지지부(11)와 대향되고 경계석(5)과 차도(4) 사이의 측구(2) 측에 근접한 일측에 형성되고, 상향 돌출된 복수의 돌출편(12a)들이 배열되어 있다.The reinforcement part 12 is formed on one side of the foundation block 10 opposite to the other side, that is, the boundary stone support 11, and close to the side opening 2 side between the boundary stone 5 and the roadway 4, and protrudes upward. A plurality of protruding pieces 12a are arranged.

그리고 돌출편(12a)들은 도 1과 같이 상호 수평, 수직으로 교차하여 바둑판식으로 배열될 수 있으며, 상호 사선으로 교차하여 벌집 형상으로 형성될 수도 있다.In addition, the protruding pieces 12a may be tiled to cross each other horizontally and vertically as shown in FIG. 1, and may be formed in a honeycomb shape by crossing each other diagonally.

또한 돌출편(12a)들의 단면 형상은 직사각형으로 형성될 수 있으며, 반원형, ㄱ자형, T자형 중 어느 하나의 형상으로 형성될 수도 있다.In addition, the cross-sectional shape of the protruding pieces 12a may be formed in a rectangular shape, and may be formed in any one of a semi-circular shape, a L shape, and a T shape.

이러한 보강부(12)는 기초 블록(10) 상면에 도 2와 같이 경계석(5)을 안착시킨 후 측구(2) 시공을 위해 콘크리트를 타설할 때 콘크리트와 기초 블록(10)의 부착력을 증대시킬 수 있다.This reinforcement 12 is to increase the adhesion between the concrete and the foundation block 10 when placing the concrete for the construction of the side opening (2) after seating the boundary stone 5 on the upper surface of the foundation block 10 as shown in FIG. Can be.

한편, 기초 블록(10)의 보강부(12)측 측면에는 복수의 균열 방지 부재(13)가 구비된다. On the other hand, the crack prevention member 13 is provided in the side surface of the reinforcement part 12 side of the foundation block 10. As shown in FIG.

균열 방지 부재(13)는 ㄷ자 형상으로 구비되어 기초 블록(10)의 운반시 손잡이로 사용될 수 있고, 측구(2) 시공을 위한 콘크리트 타설시 콘크리트 내에 매설되어 기초 블록(10)과 콘크리트의 결착력을 증대시키거나, 콘크리트 타설 후 콘크리트의 균열을 방지할 수 있다.The crack preventing member 13 may be provided as a U-shape and used as a handle when transporting the foundation block 10. The crack preventing member 13 may be embedded in the concrete during the concrete pouring for the construction of the side opening 2, thereby improving the binding force between the foundation block 10 and the concrete. It can increase or prevent cracking of concrete after concrete pouring.

이하에서는 본 고안의 한 실시예에 따른 보차도 경계석 설치용 기초 블록을 이용하여 경계석의 설치 및 차도와 보도를 형성시키는 과정을 설명한다.Hereinafter, the process of installing the boundary stone and forming the roadway and the sidewalk using the foundation block for installing the sidewalk road boundary stone according to an embodiment of the present invention.

먼저, 차도(4)와 보도 블록이 깔리는 보도(3) 사이의 지반(1)위에 기초 블록(10)을 설치하고, 경계석(5)을 기초 블록(10)의 중앙 부위에 안치시킨다.First, the foundation block 10 is provided on the ground 1 between the driveway 4 and the sidewalk 3 on which the sidewalk block is laid, and the boundary stone 5 is placed in the central portion of the foundation block 10.

이때, 경계석(5)의 일측면을 기초 블록(10)의 경계석 지지부(11)에 밀착시키 면서 기초 블록(10)의 중앙 부위에 안착시킨다.At this time, one side of the boundary stone (5) is seated on the central portion of the foundation block 10 while in close contact with the boundary stone support (11) of the foundation block (10).

도 2와 같이 경계석(5)을 안착시킨 후 즉시, 기초 블록(10)의 보강부(12)측으로 측구(2) 시공을 위한 콘크리트를 타설한다.Immediately after seating the boundary stone 5 as shown in Figure 2, the concrete for the construction of the side opening (2) to the reinforcement portion 12 side of the foundation block 10 is poured.

이때, 타설되는 콘크리트는 기초 블록(10)의 보강부(12) 상면까지 타설되며, 보강부(12) 상면에 타설되는 콘크리트는 보강부(12)의 돌출편(12a)들에 의해 분할 형성된 각 공간에 타설됨에 따라 기초 블록(10)과 콘크리트, 즉 기초 블록(10)과 측구(2)의 부착력이 증대된다.In this case, the concrete to be poured is poured up to the upper surface of the reinforcement part 12 of the foundation block 10, and the concrete poured on the upper surface of the reinforcement part 12 is divided by the protrusion pieces 12a of the reinforcement part 12. As it is poured into the space, the adhesion between the foundation block 10 and the concrete, that is, the foundation block 10 and the side opening 2 increases.

그리고 측구(2) 시공을 위한 콘크리트가 타설되면 기초 블록(10)의 보강부(12)측에 설치된 균열 방지 부재(13)는 타설된 콘크리트 내에 매설되며, 이에 따라 콘크리트의 타설 후 균열 방지 부재(13)에 의해 콘크리트, 즉 측구(2)의 균열이 방지된다.When the concrete for construction of the side opening 2 is poured, the crack preventing member 13 installed on the reinforcement part 12 side of the foundation block 10 is embedded in the poured concrete, and thus, after the concrete is poured, the crack preventing member ( 13) prevents cracking of the concrete, that is, the side opening 2.

이와 같이 기초 블록(10)을 이용하여 경계석(5)의 설치 및 측구(2)의 시공이 완료된 후, 기초 블록(10)의 경계석 지지부(11)측으로는 지반(1) 위에 보도 블록을 배열하여 보도(3)를 형성한다.After the installation of the boundary stone 5 and the construction of the side opening 2 are completed using the foundation block 10, the sidewalk blocks are arranged on the ground 1 toward the boundary stone support 11 side of the foundation block 10. The walkway 3 is formed.

그리고 시공된 측구(2)의 옆으로는 아스팔트를 깔면서 차도(4)를 형성한다.And the sideways of the constructed side opening (2) while laying the asphalt to form a roadway (4).

상술한 바와 같이 본 고안의 한 실시예에 따른 기초 블록(10)을 이용하여 경계석(5)을 설치하면, 종래에 경계석을 설치하기 위한 목적으로 타설되는 콘크리트 타설용 거푸집을 지반 내에 매설하여 콘크리트 타설 후 콘크리트가 굳어지는 시간까지 장시간 대기하여 경계석을 설치하여야 하는 번거러움이 해소된다.As described above, when the boundary stone 5 is installed by using the foundation block 10 according to the embodiment of the present invention, the concrete is placed by embedding the formwork for concrete placing in the ground which is conventionally placed for the purpose of installing the boundary stone. After that, waiting for a long time until the concrete is hardened eliminates the trouble of installing boundary stones.

이에 따라, 기초 블록(10)을 이용하여 경계석(5)을 현장에서 즉시 설치할 수 있으며, 경계석(5)의 설치 후 측구(2)를 즉시 시공하는 연속적인 작업이 가능하여 보도(3) 및 차도(4)를 형성하는 도로 시공이 신속하게 완료될 수 있다.Accordingly, by using the foundation block 10, the boundary stone (5) can be immediately installed in the field, and after the installation of the boundary stone (5), it is possible to continuously work to construct the side opening (2), so that the sidewalk (3) and the roadway The road construction forming (4) can be completed quickly.

또한, 경계석(5) 설치를 위한 콘크리트 타설 작업이 생략되므로 콘크리트 타설 후 경계석의 설치가 가능한 시점까지 대기하는 작업자의 대기 시간이 생략되어 도로 시공 기간을 현저히 단축 시킬 수 있고, 도로 시공 기간이 단축됨에 따라 노무비가 절감될 수 있다.In addition, since the concrete placing work for the installation of the boundary stone 5 is omitted, the waiting time of the worker waiting for the installation of the boundary stone after the concrete placement is omitted, thereby significantly shortening the road construction period and shortening the road construction period. As a result, labor costs can be reduced.

이하에서는 본 고안의 다른 실시예에 따른 보차도 경계석 설치용 기초 블록을 도 3을 참조하여 본 고안의 한 실시예에 따른 보차도 경계석 설치용 기초 블록과의 차이점을 중심으로 설명한다. 도 3은 본 고안의 다른 실시예에 따른 보차도 경계석 설치용 기초 블록을 나타낸 사시도이다. Hereinafter, with reference to FIG. 3, the base block for installing the sidewalk road boundary stone according to another embodiment of the present invention will be described based on the difference from the base block for installing the sidewalk road boundary stone according to an embodiment of the present invention. Figure 3 is a perspective view showing the foundation block for installing the sidewalk road boundary stone according to another embodiment of the present invention.

본 고안의 다른 실시예에 따른 보차도 경계석 설치용 기초 블록(20)은 도 3에 도시된 바와 같이 경계석이 안착되는 기초 블록(20)의 상면 중앙 부위에 매설되어 기초 블록(20)의 상면에 다수의 요철을 형성시키는 경계석 밀림 방지 부재(14)를 더 포함하는 것을 제외하고는 본 고안의 한 실시예에 따른 보차도 경계석 설치용 기초 블록(10)과 동일하다.Pavement road boundary stone installation foundation block 20 according to another embodiment of the present invention is buried in the central portion of the upper surface of the foundation block 20, the boundary stone is seated as shown in Figure 3 a plurality of the upper surface of the foundation block 20 It is the same as the foundation block 10 for installing the sidewalk road boundary stone according to an embodiment of the present invention, except that it further includes a boundary stone rolling prevention member 14 for forming the unevenness.

경계석 밀림 방지 부재(14)는 판상의 베이스(14a)가 구비되고, 베이스(14a) 상면에는 등간격 배열되어 상단이 기초 블록(10)의 상면에 노출되는 다수의 요철편(14b)들이 일체로 구비되어 있다.The boundary stone rolling prevention member 14 is provided with a plate-shaped base 14a, and a plurality of concave-convex pieces 14b whose upper ends are exposed on the upper surface of the foundation block 10 are integrally arranged on the upper surface of the base 14a. It is provided.

그리고 다수의 요철편(14b)들은 도 3과 같이 원뿔 형상으로 형성될 수 있으며, 삼각뿔 형상으로 형성될 수도 있다.The plurality of uneven pieces 14b may be formed in a conical shape as shown in FIG. 3, or may be formed in a triangular pyramid shape.

이러한 경계석 밀림 방지 부재(14)는 기초 블록(10)의 상면 중앙 부위에 매설되어 기초 블록(10)이 전방 또는 후방으로 밀리는 것을 방지한다.The boundary stone rolling prevention member 14 is embedded in the central portion of the upper surface of the foundation block 10 to prevent the foundation block 10 from being pushed forward or backward.

즉, 기초 블록(10)의 상면 중앙 부위에 경계석(5)이 안착되면 경계석(5)의 저면에 경계석 밀림 방지 부재(14)의 요철편(14b)들 상단이 박히면서 경계석(5)이 전방 또는 후방으로 밀려나지 않을 수 있다.That is, when the boundary stone 5 is seated at the center of the upper surface of the foundation block 10, the upper end of the uneven pieces 14b of the boundary stone rolling prevention member 14 is stuck on the bottom surface of the boundary stone 5, and the boundary stone 5 is moved forward. Or it may not be pushed backwards.

따라서, 본 고안의 다른 실시예에 따른 보차도 경계석 설치용 기초 블록(10)은 경계석(5)의 안착시 기초 블록(10)의 상면에서 경계석의 이탈을 더욱 방지할 수 있다.Therefore, the foundation block 10 for installing the sidewalk road boundary stone according to another embodiment of the present invention may further prevent departure of the boundary stone from the upper surface of the foundation block 10 when the boundary stone 5 is seated.

도 1은 본 고안의 한 실시예에 따른 보차도 경계석 설치용 기초 블록의 외관을 나타낸 사시도.1 is a perspective view showing the appearance of the foundation block for installing a sidewalk boundary stone in accordance with an embodiment of the present invention.

도 2는 본 고안의 한 실시예에 따른 보차도 경계석 설치용 기초 블록에 의해 경계석이 설치된 상태를 나타낸 부분 확대 단면도.Figure 2 is a partially enlarged cross-sectional view showing a state in which the boundary stone is installed by the foundation block for installing the sidewalk boundary stone in accordance with an embodiment of the present invention.

도 3은 본 고안의 다른 실시예에 따른 보차도 경계석 설치용 기초 블록의 외관을 나타낸 사시도.Figure 3 is a perspective view showing the appearance of the foundation block for installing the sidewalk boundary stone in accordance with another embodiment of the present invention.

* 도면의 주요 부분에 대한 부호의 설명 *Explanation of symbols on the main parts of the drawings

1 : 지반 2 : 측구1: ground 2: side mouth

3 : 보도 4 : 차도3: sidewalk 4: driveway

5 : 경계석 10 : 기초 블록5: boundary stone 10: foundation block

11 : 경계석 지지부 12 : 보강부11: boundary stone support 12: reinforcement

12a : 돌출편 13 : 균열 방지 부재12a: protrusion 13: crack preventing member

14 : 경계석 밀림 방지 부재 14a : 베이스14: boundary stone rolling prevention member 14a: base

14b : 요철편14b: irregularities

Claims (8)

보도와 차도의 경계부분에 설치되는 경계석을 설치하기 위한 기초 블록으로서, 보도측에 근접한 상면의 일측에 일정 두께로 상향 돌출되어 기초 블록의 길이 방향을 따라 형성되고 상면 중앙 부위에 안착되는 경계석의 대응 측면을 지지하는 경계석 지지부; 상기 경계석과 차도 사이의 측구측에 근접한 상면의 다른 일측에 상향 돌출된 복수의 돌출편들이 배열되어 측구의 현장 타설시 상기 기초 블록의 상면에 타설되는 콘크리트와 기초 블록의 부착력을 보강하기 위한 보강부를 포함하는 보차도 경계석 설치용 기초 블록에 있어서,As a foundation block for installing a boundary stone installed at the boundary between the sidewalk and the roadway, the boundary stone is formed along the longitudinal direction of the foundation block and protrudes upward at a predetermined thickness on one side of the upper surface proximate to the sidewalk and is seated at the central portion of the upper surface. A boundary stone support supporting a side; A plurality of protrusions protruding upwardly are arranged on the other side of the upper surface adjacent to the side opening side between the boundary stone and the roadway, so that the reinforcing portion for reinforcing the adhesive force between the concrete and the foundation block placed on the upper surface of the foundation block during the site casting of the side opening. In the base block for the sidewalk road boundary stone setting to include, 상기 경계석이 안착되는 상기 기초 블록의 상면 중앙 부위에 매설되어 상기 기초 블록의 상면에 다수의 요철을 형성시키는 경계석 밀림 방지 부재를 더 포함하며,Further comprising a boundary stone rolling prevention member buried in the central portion of the upper surface of the foundation block on which the boundary stone is seated to form a plurality of irregularities on the upper surface of the foundation block, 상기 경계석 밀림 방지 부재는 The boundary stone rolling prevention member 판상의 베이스, 그리고The base of the plate, and 상기 베이스 상면에 등간격 배열되어 상단이 상기 기초 블록의 상면에 노출되고 원뿔, 삼각뿔 중 어느 하나의 형상으로 형성되는 다수의 요철편들로 구성되는 보차도 경계석 설치용 기초 블록.The base block is installed on the base surface at regular intervals, the upper end is exposed to the upper surface of the foundation block, the foundation block for the road block installation consisting of a plurality of concave-convex pieces formed in any one of a cone, a triangular pyramid. 제1항에서,In claim 1, 상기 돌출편들은 상호 교차하여 바둑판식 배열되는 보차도 경계석 설치용 기초 블록.The protruding pieces are the base block for installing the sidewalk road boundary stone tiled to cross each other. 제2항에서,In claim 2, 상기 돌출편들은 단면 형상이 반원형, 직사각형, ㄱ자형, T자형 중 어느 하나의 형상으로 형성되는 보차도 경계석 설치용 기초 블록.The protruding pieces have a cross-sectional shape semi-circular, rectangular, angled, T-shaped foundation block for the installation of the boundary road boundary stone is formed in any one shape. 제3항에서,In claim 3, 상기 기초 블록의 상기 보강부측 측면에 설치되는 적어도 하나의 균열 방지 부재를 더 포함하는 보차도 경계석 설치용 기초 블록.The foundation block for guard road boundary stone installation further including at least one crack prevention member provided in the side surface of the said reinforcement part side of the said foundation block. 제4항에서,In claim 4, 상기 균열 방지 부재는 ㄷ자 형상으로 형성되는 보차도 경계석 설치용 기초 블록.The crack preventing member is a foundation block for installing a sidewalk road boundary stone is formed in a U-shape. 삭제delete 삭제delete 삭제delete
KR20090006343U 2009-05-26 2009-05-26 Base block for installing sidewalk boundary stone KR200447023Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR20090006343U KR200447023Y1 (en) 2009-05-26 2009-05-26 Base block for installing sidewalk boundary stone

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR20090006343U KR200447023Y1 (en) 2009-05-26 2009-05-26 Base block for installing sidewalk boundary stone

Publications (1)

Publication Number Publication Date
KR200447023Y1 true KR200447023Y1 (en) 2009-12-22

Family

ID=46086456

Family Applications (1)

Application Number Title Priority Date Filing Date
KR20090006343U KR200447023Y1 (en) 2009-05-26 2009-05-26 Base block for installing sidewalk boundary stone

Country Status (1)

Country Link
KR (1) KR200447023Y1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105735084A (en) * 2016-03-14 2016-07-06 中国建筑第八工程局有限公司 Road side stone construction method and structure
KR101815890B1 (en) * 2017-06-28 2018-01-19 와이엠아이 주식회사 The bollard
CN111119003A (en) * 2019-12-26 2020-05-08 中铁二十三局集团第一工程有限公司 Cast-in-place curb construction method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01120504U (en) * 1988-02-05 1989-08-15
JPH032004U (en) * 1989-05-20 1991-01-10
KR100531397B1 (en) * 2005-09-01 2005-11-28 주식회사 서영엔지니어링 L-shaped slope of assembly for road

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01120504U (en) * 1988-02-05 1989-08-15
JPH032004U (en) * 1989-05-20 1991-01-10
KR100531397B1 (en) * 2005-09-01 2005-11-28 주식회사 서영엔지니어링 L-shaped slope of assembly for road

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105735084A (en) * 2016-03-14 2016-07-06 中国建筑第八工程局有限公司 Road side stone construction method and structure
KR101815890B1 (en) * 2017-06-28 2018-01-19 와이엠아이 주식회사 The bollard
CN111119003A (en) * 2019-12-26 2020-05-08 中铁二十三局集团第一工程有限公司 Cast-in-place curb construction method

Similar Documents

Publication Publication Date Title
US20050066623A1 (en) Efficiently installable and durable embedment tile for producing tactilely-detectable surfaces
US6939078B1 (en) Tactile detectable warning ramps for pedestrian pathways
WO2014138981A1 (en) A modular concrete unit, a concrete assembly, and a method of installation thereof
KR200447023Y1 (en) Base block for installing sidewalk boundary stone
US7950276B1 (en) System and method of forming vehicle test road by joining pre-fabricated pavement modules
CN107237232B (en) high-durability cement concrete pavement expansion joint structure and construction method thereof
US6688805B1 (en) Pre-cast curbside access ramp and methods of making and installing the same
KR20110132880A (en) Boundary stone for public works, landscaping, road and concrete leveling construction apparatus enabling simultaneously installation of boundary stone support, and boundary stone for public works, landscaping, road and concrete leveling construction method enabling simultaneously installation of boundary stone support
US20080145144A1 (en) Precast Curb System and Method of Installation thereof
CN112281568A (en) Prefabricated ultrahigh-performance concrete light pavement structure and construction method thereof
KR20210048232A (en) Pavement block reinforcement method using asphalt pavement
US20100098489A1 (en) Preformed screed system
KR100613845B1 (en) Surface reinforcement for pavement
KR101050205B1 (en) Apparatus and method for constructing concrete structure with boundary stone, boundary stone support of public works, landscaping, road
KR20030057840A (en) Method for dry constructing road boundary stones and road boundary stone supporting device
RU2403334C1 (en) Method and design of motor road erection with hard surface
JP5318257B1 (en) CONCRETE EXTENDED WAY COMPOSITION AND METHOD FOR CONSTRUCTING A VEHICLE WITH AN EXTENDED WAY
KR200456737Y1 (en) A supporter of a road boundary stone
RU2357037C2 (en) Method and structure of automobile road erection with hard surface
KR100598771B1 (en) Sink prevent structure of pavement block for road
CN216006476U (en) A apron of mating formation and curb structure for solving inspection shaft and curb conflict
KR100924022B1 (en) Construction housing development using Footway-block of Installation method
AU2011250774A1 (en) Prefabricated formwork element
JPH0786246B2 (en) Drainage channel for concrete paved road that can be repaired and repair method
KR100580614B1 (en) Asphalt sinking prevention apparatus of smooth ground's road

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
REGI Registration of establishment
LAPS Lapse due to unpaid annual fee