KR100924022B1 - Construction housing development using Footway-block of Installation method - Google Patents

Construction housing development using Footway-block of Installation method Download PDF

Info

Publication number
KR100924022B1
KR100924022B1 KR1020080117669A KR20080117669A KR100924022B1 KR 100924022 B1 KR100924022 B1 KR 100924022B1 KR 1020080117669 A KR1020080117669 A KR 1020080117669A KR 20080117669 A KR20080117669 A KR 20080117669A KR 100924022 B1 KR100924022 B1 KR 100924022B1
Authority
KR
South Korea
Prior art keywords
binding
block
sand
sidewalk block
sidewalk
Prior art date
Application number
KR1020080117669A
Other languages
Korean (ko)
Inventor
오정준
Original Assignee
오정준
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 오정준 filed Critical 오정준
Priority to KR1020080117669A priority Critical patent/KR100924022B1/en
Application granted granted Critical
Publication of KR100924022B1 publication Critical patent/KR100924022B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C15/00Pavings specially adapted for footpaths, sidewalks or cycle tracks
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C2201/00Paving elements
    • E01C2201/14Puzzle-like connections
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Abstract

PURPOSE: A bonding type sidewalk block installation method is provided to prevent the bottom from subsiding in raining and maintain the bottom uniformly by preventing sidewalk blocks from being pushed in the weak soil foundation or the slope region. CONSTITUTION: A bonding type sidewalk block installation method comprises following steps. A boundary stone(10) is installed on the earth and sand. A sand layer is made by piling up sand between the boundary stones and making the sand flat. A bottom reinforcement net(20) is installed on the sand layer to prevent the bottom from subsiding. A plurality of binding sidewalk blocks(30) are installed on a bottom reinforcing mesh at constant intervals. An anchor block(40) is inserted into an anchor block hole of the binding sidewalk blocks to fix the binding sidewalk blocks on the bottom.

Description

건축단지용 결속식 보도블록 설치방법{Construction housing development using Footway-block of Installation method}Construction housing development using footway-block of installation method

본 발명은 건축단지용 결속식 보도블록 설치방법에 관한 것으로서, 더욱 상세하게는 보도와 차도의 경계부분에 경계석을 설치하고, 상기 경계석 내측으로 모래를 쌓아 편평하게 작업한 뒤, 바닥 보강망을 깔아주며, 상기 바닥 보강망 위에 결속 보도블록을 깔고, 상기 결속 보도블록의 중앙부에 앙카블록을 설치함으로써, 연약지반이나 비탈지역에서도 보도블록이 밀리지 않아 바닥이 균일하고, 비가 많이 오는 우기시에도 바닥이 침하되는 것을 방지하고, 상기 앙카블록의 칼라무늬가 화려하여 미관상 뛰어난 건축단지용 결속식 보도블록 설치방법에 관한 것이다.The present invention relates to a method of installing a pedestrian-type sidewalk block for a building complex, and more particularly, install a boundary stone at a boundary between a sidewalk and a driveway, stack sand into the boundary stone, and then lay a floor reinforcement network. By laying a binding sidewalk block on the bottom reinforcement network, and by installing an anchor block in the center of the binding sidewalk block, even in soft ground or slope area, the sidewalk block is not pushed down, so that the floor is uniform, even during rainy rainy seasons. The present invention relates to a method of installing a binding sidewalk block for a building complex, which prevents the settlement and is excellent in aesthetic appearance because the collar pattern of the anchor block is gorgeous.

종래의 보도 블럭은 일반적으로 지반 위에 토사가 적층되어 있고, 토사 위에는 다짐된 지면 층이 형성된다. 다짐된 지면 위에 경계석을 설치하고, 그 내부에 모래를 쌓아 편평하게 모래층을 만든 다음 그 위에 보도블록의 수평을 맞추어 깔게 된다.Conventional sidewalk blocks are generally stacked with soil on the ground, with a ground layer formed on the soil. A boundary stone is installed on the plowed ground, sand is piled up inside it to form a flat layer of sand, and the sidewalk block is leveled on it.

하지만 이러한 보도블록의 경우 소나기가 내리거나 많은 물이 보도블록 위로 쏟아질 경우 보도블록 밑의 모래가 흩어져 부등침하가 일어난다.However, in the case of such a sidewalk block, when showers fall or when a lot of water is poured onto the sidewalk block, sand beneath the sidewalk block is scattered, causing uneven settlement.

일단 부등침하가 일어난 보도블록은 사이 틈이 계속 벌어져 부등침하 현상이 더욱 심화되어 보도블록을 새로 깔아야 하는 문제가 발생한다.Once the sidewalk block has been inevitably settled, the gap between the gaps continued to deepen, causing further problems.

이러한 점을 보완하기 위한 보도블록은 상판과 하판을 상호 지그재그로 포개어 놓은 상태를 갖추어 상,하판이 서로 포개어지지 않는 상판의 연장부와 하판의 받침턱이 각각 서로 다른 보도블록 본체와 포개어 지그재그로 연결되므로 보도블록 상호 간에 수평이 지속적으로 유지되고 조립시 맨 가장자리에 위치하는 보도블록 본체의 연장부나 받침턱은 이를 절단하여 주므로서 부분절단으로 마무리를 미끄럽게 하여 줄 수 있도록 하였으며, 측면에는 배수용 홈통을 상,하판에 연결형성시켜 놓아 빗물이나 눈 녹은 물이 다른 데로 흘러가지 않고 밑으로 흘러 스며들게 한다.The sidewalk block to complement this point has a state in which the upper and lower plates are stacked in a zigzag pattern, and the upper and lower plates are not overlapped with each other, and the supporting bases of the upper and lower plates are stacked in a zigzag with different sidewalk block bodies. Therefore, the level of the sidewalk block is continuously maintained horizontally, and the extension or the supporting jaw of the sidewalk block body located at the far edge at the time of assembly is cut so that the finish can be made slippery by partial cutting. The upper and lower plates are connected to each other so that rainwater or snow melted water does not flow to the other place but soaks down.

이렇듯, 상기 보도블록은 단판형태로 이루어져 있으며 이를 상호연결하기 위하여는 네모서리를 서로 맞추어 모래판위에 지그재그 또는 나란히 배열하여 설치사용함은 일반적인 사용방법이나, 이렇게 사용할 경우 바닥이 고르지 않거나 배수로 인하여 밑면에 침하현상이 생겼을 때에는 보도블록이 상호 수평을 유지하지 못하는 것이 일반적이다.As such, the sidewalk block is formed in a single plate shape, and in order to interconnect them, the four corners are aligned with each other and zigzag or arranged side by side on a sand plate, which is a common use method, but in this case, the bottom is uneven or sinks due to drainage. When this occurs, it is common for the sidewalk blocks to not be horizontal to each other.

그리고 단층으로 이루어진 보도블록의 경우에는 바닥면이 고르지 못할 때 밑받침을 각각 받쳐놓은 상태에서 상호연결하게 되므로 숙련된 시공자의 시공작업에도 설치조립된 보도블록의 수평상태가 고르지 못하였다.In the case of the single-sided sidewalk block, when the bottom surface is uneven, the bottom blocks are interconnected in the state of supporting each underlay, so even in the construction work of an experienced contractor, the horizontal state of the sidewalk block installed and assembled is not even.

이와 같이 보도블록 설치작업은 그 설치공법이 전근대적인 방법이어서 보도블록을 고르고 정확하게 설치 및 시공할 수 없을 뿐만 아니라 시공공기가 많이 소 요되어 실사용에 많은 어려움이 있었다.As such, the installation process of the sidewalk block is a premodern method, so it is not possible to select and install the sidewalk block correctly and to install it correctly.

특히, 상기의 보도블록에 사용되는 모래나 자갈 등은 타지에서 공급되는 것이며 풍족하게 밑바닥에 펼쳐줄 수 없어 그 위에 깔게 되는 보도블록은 단기간의 사용으로도 파손되거나 또는 수평상태를 유지하지 못하는 경우가 허다하여 잦은 보수공사로 예산을 낭비하는 점도 있었다.In particular, the sand or gravel used in the sidewalk block is supplied from other places and can not be spread abundantly on the bottom, so the sidewalk block laid on it may be damaged or not maintained even in a short period of time. There was also a waste of budget due to frequent repair work.

이와 같이 보도블록이 침하 되어 보도가 균일하지 못하게 되면, 보행자가 보도블록에 걸려 넘어져 안전사고가 발생하는 등 많은 문제를 유발한다.When the sidewalk block is settled as described above and the sidewalk is not uniform, pedestrians trip over the sidewalk block and cause a lot of problems such as a safety accident.

그리고 일단 부등침하 되어 보도블록이 파손되면 그 부분만 교체하여서 되는 것이 아니라 다시 전체 보행자도로가 새로운 보도블록으로 교체되어야 한다.And once the sidewalk block is damaged due to inequality, the entire pedestrian road must be replaced with a new sidewalk block, not just the part.

따라서, 본 발명은 상기 종래의 문제점을 해소하기 위해 안출된 것으로서,Accordingly, the present invention has been made to solve the above conventional problems,

보도와 차도의 경계부분에 경계석을 설치하고, 상기 경계석 내측으로 모래를 쌓아 편평하게 작업한 뒤, 바닥 보강망을 깔아주며, 상기 바닥 보강망 위에 결속 보도블록을 깔고, 상기 결속 보도블록의 중앙부에 앙카블록을 설치함으로써, 연약지반이나 비탈지역에서도 보도블록이 밀리지 않아 바닥이 균일하고, 비가 많이 오는 우기시에도 바닥이 침하되는 것을 방지하는 건축단지용 결속식 보도블록 설치방법을 제공하는데 목적이 있다.A boundary stone is installed at the boundary of the sidewalk and the driveway, sand is piled up inside the boundary stone, and the floor reinforcement net is laid. By installing anchor blocks, it is aimed to provide a method of installing a combined sidewalk block for a construction complex that prevents the floor from sinking even in rainy or rainy season because the sidewalk block is not pushed even in soft ground or sloped areas. .

또한, 본 발명은 앙카블록의 칼라무늬가 화려하여 미관상 뛰어난 건축단지용 결속식 보도블록 설치방법을 제공하는데 또 다른 목적이 있다.In addition, the present invention has a further object to provide a method of installing a binding sidewalk block for building complexes because the color pattern of the anchor block is gorgeous.

상기 목적을 달성하고자, 본 발명은 건축단지에 설치되되, 지반 위에 토사를 적층시켜 다져주고, 상기 다져진 토사 위에 모래를 쌓아 편평하게 모래층을 만든 다음 그 위에 결속식 보도블록을 설치하는 방법에 있어서,In order to achieve the above object, the present invention is installed in the building complex, stacking the earth and sand on the ground, the sand piled on the ground to make a flat sand layer, and then in the method of installing a binding sidewalk block thereon,

상기 모래를 쌓기 전에 다져진 토사 위에 설치하되, 보도와 차도의 경계부분에 설치하여 보도블록을 설치하고자 하는 부위를 구획하도록 경계석을 설치하는 단계(S100);A step of installing a boundary stone so as to install on the grounded sand before stacking the sand, and install a boundary stone on a boundary between the sidewalk and the driveway to partition a portion to which the sidewalk block is to be installed;

상기 경계석 설치단계(S100) 후, 모래를 쌓아 편평하게 다진 모래층 위에 바 닥을 보강하여 침하현상을 방지하도록 그물망 형태로 형성된 바닥 보강망을 설치하는 단계(S200);After the boundary stone installation step (S100), the step of installing a floor reinforcing net formed in the form of a net to prevent the sinking phenomenon by reinforcing the floor on the sand chopped flat sand layer (S200);

상기 바닥 보강망 설치단계(S200) 후, 바닥 보강망 위에 다수개의 결속 보도블록을 간격에 맞춰 설치하는 단계(S300);After the floor reinforcement net installation step (S200), the step of installing a plurality of binding walkway blocks on the floor reinforcement at intervals (S300);

상기 결속 보도블록 설치단계(S300) 후, 결속 보도블록을 바닥에 고정하기 위해 다수개의 결속 보도블록의 중앙부에 각각 앙카블록을 설치하는 단계(S400);를 포함한 단계로 보도블록을 설치되는 것을 특징으로 하는 건축단지용 결속식 보도블록 설치방법에 관한 것이다.After the binding sidewalk block installation step (S300), in order to fix the binding sidewalk block on the floor step of installing each anchor block in the center of the plurality of binding sidewalk block (S400); The present invention relates to a method of installing a sidewalk block for a building complex.

이상에서 살펴 본 바와 같이, 본 발명의 건축단지용 결속식 보도블록 설치방법은 보도와 차도의 경계부분에 경계석을 설치하고, 상기 경계석 내측으로 모래를 쌓아 편평하게 작업한 뒤, 바닥 보강망을 깔아주며, 상기 바닥 보강망 위에 결속 보도블록을 깔고, 상기 결속 보도블록의 중앙부에 앙카블록을 설치함으로써, 연약지반이나 비탈지역에서도 보도블록이 밀리지 않아 바닥이 균일하고, 비가 많이 오는 우기시에도 바닥이 침하되는 것을 방지하는 효과가 있다.As described above, in the method of installing the binding type sidewalk block for the construction complex of the present invention, the boundary stone is installed at the boundary between the sidewalk and the driveway, and the sand is piled up inside the boundary stone to work flat, and then the floor reinforcement network is laid. By laying a binding sidewalk block on the bottom reinforcement network, and by installing an anchor block in the center of the binding sidewalk block, even in soft ground or slope area, the sidewalk block is not pushed down, so that the floor is uniform, even during rainy rainy seasons. It is effective to prevent settlement.

또한, 본 발명은 앙카블록의 칼라무늬가 화려하여 미관상 뛰어난 효과가 있다.In addition, the present invention has an excellent effect of aesthetic appearance because the collar pattern of the anchor block is gorgeous.

본 발명은 상기의 목적을 달성하기 위해 아래와 같은 특징을 갖는다.The present invention has the following features to achieve the above object.

본 발명은 건축단지에 설치되되, 지반 위에 토사를 적층시켜 다져주고, 상기 다져진 토사 위에 모래를 쌓아 편평하게 모래층을 만든 다음 그 위에 결속식 보도블록을 설치하는 방법에 있어서,The present invention is installed in the building complex, stacking the earth and sand on the ground, and compacted, stacked sand on the ground to make a flat sand layer in the method of installing a binding sidewalk block thereon,

상기 모래를 쌓기 전에 다져진 토사 위에 설치하되, 보도와 차도의 경계부분에 설치하여 보도블록을 설치하고자 하는 부위를 구획하도록 경계석을 설치하는 단계(S100);A step of installing a boundary stone so as to install on the grounded sand before stacking the sand, and install a boundary stone on a boundary between the sidewalk and the driveway to partition a portion to which the sidewalk block is to be installed;

상기 경계석 설치단계(S100) 후, 모래를 쌓아 편평하게 다진 모래층 위에 바닥을 보강하여 침하현상을 방지하도록 그물망 형태로 형성된 바닥 보강망을 설치하는 단계(S200);After the boundary stone installation step (S100), the step of installing a floor reinforcing net formed in the form of a net to prevent the sinking phenomenon by reinforcing the floor on the sand layer stacked flat sand (S200);

상기 바닥 보강망 설치단계(S200) 후, 바닥 보강망 위에 다수개의 결속 보도블록을 간격에 맞춰 설치하는 단계(S300);After the floor reinforcement net installation step (S200), the step of installing a plurality of binding walkway blocks on the floor reinforcement at intervals (S300);

상기 결속 보도블록 설치단계(S300) 후, 결속 보도블록을 바닥에 고정하기 위해 다수개의 결속 보도블록의 중앙부에 각각 앙카블록을 설치하는 단계(S400);를 포함한 단계로 보도블록을 설치되는 것을 특징으로 한다.After the binding sidewalk block installation step (S300), in order to fix the binding sidewalk block on the floor step of installing each anchor block in the center of the plurality of binding sidewalk block (S400); It is done.

이와 같은 특징을 갖는 본 발명은 그에 따른 바람직한 실시예를 통해 더욱 명확히 설명될 수 있을 것이다.The present invention having such a feature will be more clearly described through the preferred embodiment accordingly.

이하 첨부된 도면을 참조로 본 발명의 바람직한 실시예를 상세히 설명하도록 한다. 이에 앞서, 본 명세서 및 청구범위에 사용된 용어나 단어는 통상적이거나 사 전적인 의미로 한정해서 해석되어서는 아니되며, 발명자는 그 자신의 발명을 가장 최선의 방법으로 설명하기 위해 용어의 개념을 적절하게 정의할 수 있다는 원칙에 입각하여 본 발명의 기술적 사상에 부합하는 의미와 개념으로 해석되어야만 한다.Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings. Prior to this, the terms or words used in this specification and claims should not be construed as being limited to the ordinary or dictionary meanings, and the inventors should properly explain the concept of terms in order to best explain their own invention. Based on the principle that can be defined, it should be interpreted as meaning and concept corresponding to the technical idea of the present invention.

따라서, 본 명세서에 기재된 실시예와 도면에 도시된 구성은 본 발명의 가장 바람직한 일실시예에 불과할 뿐이고 본 발명의 기술적 사상을 모두 대변하는 것은 아니므로, 본 출원시점에 있어서 이들을 대체할 수 있는 다양한 균등물과 변형예들이 있을 수 있음을 이해하여야 한다.Therefore, the embodiments described in the specification and the drawings shown in the drawings are only one of the most preferred embodiments of the present invention and do not represent all of the technical idea of the present invention, various modifications that can be replaced at the time of the present application It should be understood that there may be equivalents and variations.

도 1은 본 발명의 일실시예에 따른 건축단지용 결속식 보도블록 설치구성을 나타낸 개략도이고, 도 2는 도 1의 A-A부분을 나타낸 단면도이고, 도 3은 본 발명의 일실시예에 따른 결속 보도블록을 나타낸 사시도이고, 도 4는 본 발명의 일실시예에 따른 앙카블록을 나타낸 사시도이고, 도 5는 본 발명의 일실시예에 따른 바닥 보강망을 나타낸 사시도이고, 도 6은 본 발명의 일실시예에 따른 건축단지용 결속식 보도블록 설치방법을 나타낸 순서도이다.1 is a schematic view showing the installation of the binding type sidewalk block for a building complex according to an embodiment of the present invention, Figure 2 is a cross-sectional view showing a portion AA of Figure 1, Figure 3 is a binding according to an embodiment of the present invention Figure 4 is a perspective view showing a block, Figure 4 is a perspective view showing an anchor block according to an embodiment of the present invention, Figure 5 is a perspective view showing a floor reinforcement net according to an embodiment of the present invention, Figure 6 is a view of the present invention 1 is a flowchart illustrating a method of installing a binding sidewalk block for a building complex according to an embodiment.

도 1과 도 2 및 도 6에 도시한 바와 같이, 본 발명의 건축단지용 결속식 보도블록 설치방법은 건축단지(아파트단지 등) 내외에 보도블록(30)을 설치하는 방법으로 우선, 보도블록(30)을 설치하고자 하는 지반 위에 토사를 적층시켜 다져주고, 상기 다져진 토사 위에 모래(50)를 쌓은 뒤, 상기 모래(50)를 편평하게 작업하여 일정두께의 모래층을 만들어 준다.As shown in Figures 1 and 2 and 6, the method of installing the combined sidewalk block for the building complex of the present invention is a method of installing the sidewalk block 30 inside and outside the building complex (apartment complex, etc.). The sand is laminated on the ground on which the 30 is to be installed and chopped, and the sand 50 is piled on the chopped soil, and the sand 50 is worked flat to form a sand layer having a predetermined thickness.

이때, 상기 모래(50)를 토사 위에 쌓기 전에 보도와 차도의 경계부분 또는 보도블록(30)을 설치하고자 하는 부위를 구획하기 위해 다져진 토사 위에 경계 석(10)을 먼저 설치한다.(S100) 그런 다음, 상기 경계석(10)과 경계석(10) 사이에 모래(50)를 쌓고 편평하게 작업하여 모래층을 만드는 것이다.At this time, before the sand 50 is stacked on the soil, the boundary stone 10 is first installed on the grounded soil to divide the boundary portion between the sidewalk and the roadway or the portion to which the sidewalk block 30 is to be installed. Next, the sand 50 is stacked between the boundary stone 10 and the boundary stone 10 to form a sand layer.

여기서, 상기 경계석(10)은 직사각형의 콘크리트로 제작된 것으로 일반적으로 사용되는 경계석과 유사한 것으로 별도의 구조, 형태 기술은 하지 않는다.Here, the boundary stone 10 is made of rectangular concrete and similar to the boundary stone generally used, and does not have a separate structure and form description.

그리고, 상기 경계석(10)을 설치한 다음, 모래(50)를 쌓아 편평하게 다진 모래층 위에 비와 눈이 많이 올 때나 비탈길 또는 연악한 지반에 보도블록(30)을 설치시, 바닥이 침하하는 현상을 방지하도록 바닥 보강망(20)을 설치(깐다)한다.(S200)Then, after installing the boundary stone (10), when the rain and snow a lot on the sand crushed flat sand layer 50 or when installing the sidewalk block 30 on the slope or soft ground, the bottom sinks phenomenon Install the floor reinforcement net (20) to prevent (S200).

여기서, 상기 바닥 보강망(20)은 도 5에 도시한 바와 같이, 그물망 형태로 형성되어 바닥이 유실되거나 움푹 파일 때도 상부에 설치되는 결속 보도블록(30)이 이격되지 않는 재질(금속제 또는 특수 플라스틱 등)로 형성되고, 상기 바닥 보강망(20)에 형성된 다수개의 홀의 크기는 설치위치 등에 따라 다양하게 설계변경 가능하다.Here, the bottom reinforcement net 20 is formed in the form of a net, as shown in Figure 5, the material is not separated from the binding sidewalk block 30 is installed on the top even when the floor is lost or recessed (metal or special plastic Etc.), and the size of the plurality of holes formed in the bottom reinforcement net 20 can be variously changed according to the installation position.

그런 다음, 상기 바닥 보강망(20) 위에 다수개의 결속 보도블록(30)을 간격에 맞춰 설치한다.(S300) 이때, 상기 결속 보도블록(30)을 경계석(10)과 경계석(10) 사이에 설치하는데, 상기 결속 보도블록(30)의 형태에 따라 경계석(10) 사이를 촘촘히 메우지 못할 때는 현장 또는 제작시 결속 보도블록(30)의 형태를 변경할 수 있다.Then, a plurality of binding walkway blocks 30 are installed at intervals on the floor reinforcement net 20 (S300). At this time, the binding walkway block 30 is disposed between the boundary stone 10 and the boundary stone 10. In the installation, when it is not possible to closely fill the boundary stones 10 according to the shape of the binding sidewalk block 30 can change the shape of the binding sidewalk block 30 in the field or manufacturing.

여기서, 상기 결속 보도블록(30)은 경계석(10)과 경계석(10) 사이의 바닥 보강망(20) 위에 설치하는데, 도 3에 도시한 바와 같이, 결속 보도블록(30) 간의 결 속력을 높이기 위해 외주연에 원주방향으로 다수개의 결속부(31)가 형성된다. 이때, 상기 결속부(31)는 삼각형, 사각형, 오각형 등 다각형으로 형성되어 상기 결속 보도블록(30)이 상호 결합시 결속력을 높여준다.Here, the binding sidewalk block 30 is installed on the bottom reinforcing net 20 between the boundary stone 10 and the boundary stone 10, as shown in Figure 3, to increase the binding force between the binding sidewalk block 30 To the outer periphery, a plurality of binding portions 31 are formed in the circumferential direction. At this time, the binding unit 31 is formed of a polygon, such as a triangle, a square, a pentagon, thereby increasing the binding force when the binding sidewalk block 30 is mutually coupled.

또한, 상기 결속 보도블록(30)은 결속부(31)와 결속부(31) 사이에 결속홈(32)이 형성되어 다른 결속 보도블록(30)의 결속부(31)가 결합되고, 상기 결속 보도블록(30)의 중앙부에는 앙카블록(40)이 삽입 설치되도록 원형의 앙카블록홀(33)이 형성된다.In addition, the binding walkway block 30 has a binding groove 32 is formed between the binding portion 31 and the binding portion 31 is coupled to the binding portion 31 of the other binding sidewalk block 30, the binding A circular anchor block hole 33 is formed in the center portion of the sidewalk block 30 so that the anchor block 40 is inserted.

마지막으로, 상기 결속 보도블록(30)을 설치한 다음, 상기 결속 보도블록(30)을 바닥에 고정하기 위해 다수개의 결속 보도블록(30)의 앙카블록홀(33)에 앙카블록(40)을 각각 삽입 설치한다.(S400)Finally, the anchoring block 40 is installed in the anchor block hole 33 of the plurality of binding sidewalk blocks 30 in order to fix the combined sidewalk block 30 to the floor. Insert each install. (S400)

이때, 상기 앙카블록(40)은 도 4에 도시한 바와 같이, 원통형(상기 결속 보도블록의 앙카블록홀(33) 형태에 맞춰 형성됨)으로 형성되어 외주연에 다수개의 돌기(41)가 형성되고, 상기 앙카블록(40)의 하단면에는 바닥에 박혀 고정되도록 끝단부가 뽀족한 앙카(42)가 일체형으로 돌출 형성된다.At this time, the anchor block 40 is formed in a cylindrical shape (formed to match the shape of the anchor block hole 33 of the binding sidewalk block), as shown in Figure 4 is formed a plurality of projections 41 on the outer periphery In addition, the lower end of the anchor block 40 is formed to be integrally projected by the anchor 42 having a sharp end end so as to be fixed to the bottom.

그리고 상기 앙카블록(40)의 상부면은 도보블록의 아픔다운 미관을 위하여 다양한 형태의 칼라무늬(43)가 형성되고, 상기 칼라무늬(43)는 직접 앙카블록(40)의 상부면에 새겨넣거나 색지 등을 별도로 붙여서 표현할 수 있다.And the upper surface of the anchor block 40 is formed with various types of collar pattern 43 for the painful aesthetics of the walking block, the collar pattern 43 is directly engraved on the upper surface of the anchor block 40 or Colored paper etc. can be attached separately.

도 1은 본 발명의 일실시예에 따른 건축단지용 결속식 보도블록 설치구성을 나타낸 개략도이고, 1 is a schematic diagram showing the installation structure of the binding sidewalk block for a building complex according to an embodiment of the present invention,

도 2는 도 1의 A-A부분을 나타낸 단면도이고, 2 is a cross-sectional view showing part A-A of FIG. 1,

도 3은 본 발명의 일실시예에 따른 결속 보도블록을 나타낸 사시도이고, 3 is a perspective view showing a binding sidewalk block according to an embodiment of the present invention,

도 4는 본 발명의 일실시예에 따른 앙카블록을 나타낸 사시도이고, 4 is a perspective view showing an anchor block according to an embodiment of the present invention,

도 5는 본 발명의 일실시예에 따른 바닥 보강망을 나타낸 사시도이고, 5 is a perspective view showing a floor reinforcement net according to an embodiment of the present invention,

도 6은 본 발명의 일실시예에 따른 건축단지용 결속식 보도블록 설치방법을 나타낸 순서도이다.Figure 6 is a flow chart illustrating a method of installing a binding sidewalk block for a building complex according to an embodiment of the present invention.

<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for the main parts of the drawings>

10 : 경계석 20 : 바닥 보강막10: boundary stone 20: floor reinforcement film

30 : 결속 보도블록 31 : 결속부30: binding sidewalk block 31: binding unit

32 : 결속홈 33 : 앙카블록홀32: Binding Home 33: Anchor Block Hall

40 : 앙카블록 41 : 돌기40: anchor block 41: projection

42 : 앙카 43 : 칼라무늬42: anchor 43: color pattern

50 : 모래50: sand

Claims (3)

건축단지에 설치되되, 지반 위에 토사를 적층시켜 다져주고, 상기 다져진 토사 위에 모래(50)를 쌓아 편평하게 모래층을 만든 다음 그 위에 결속식 보도블록(30)을 설치하는 방법에 있어서,In the method of installing in the building complex, stacking the earth and sand on the ground and crushed, stacked sand (50) on the chopped earth and sand to make a flat layer of sand and then install the binding sidewalk block 30 thereon, 상기 모래(50)를 쌓기 전에 다져진 토사 위에 설치하되, 보도와 차도의 경계부분에 설치하거나 보도블록(30)을 설치하고자 하는 부위를 구획하도록 경계석(10)을 설치하는 단계(S100);Installing the sand 50 before stacking the sand, but installing the boundary stone 10 so as to partition the area to be installed on the boundary of the sidewalk and the roadway or to install the sidewalk block 30 (S100); 상기 경계석(10) 설치단계(S100) 후, 모래(50)를 쌓아 편평하게 다진 모래층 위에 바닥을 보강하여 침하현상을 방지하도록 그물망 형태로 형성된 바닥 보강망(20)을 설치하는 단계(S200);After the boundary stone 10 installation step (S100), the step of installing the bottom reinforcing net 20 formed in the form of a net to prevent the settlement by reinforcing the floor on the sand crushed flat sand layer (S200); 상기 바닥 보강망(20) 설치단계(S200) 후, 바닥 보강망(20) 위에 다수개의 결속 보도블록(30)을 간격에 맞춰 설치하는 단계(S300);After the installation step (S200) of the bottom reinforcing net 20, the step of installing a plurality of binding walkway blocks 30 on the bottom reinforcing net 20 at intervals (S300); 상기 결속 보도블록(30) 설치단계(S300) 후, 결속 보도블록(30)을 바닥에 고정하기 위해 다수개의 결속 보도블록(30)의 중앙부에 각각 원통형으로 형성되어 외주연에 다수개의 돌기(41)가 형성되고 하단면에 바닥에 박히도록 끝단부가 뽀족한 앙카(42)가 일체형으로 돌출 형성되며 상부면에 도보블록의 아픔다운 미관을 위하여 다양한 형태의 칼라무늬(43)가 형성되는 앙카블록(40)을 설치하는 단계(S400);After the binding sidewalk block 30 installation step (S300), in order to fix the binding sidewalk block 30 to the floor, each of the plurality of protrusions 41 are formed in a central portion in the center of the binding sidewalk block 30 to the outer periphery 41. Anchors block (42) is formed and protruded integrally to the bottom end so that the bottom end is stuck to the floor, and the collar pattern (43) of various shapes is formed on the upper surface for painful aesthetics of the walking block ( 40) installing the step (S400); 를 포함한 단계로 보도블록(30)을 설치되는 것을 특징으로 하는 건축단지용 결속식 보도블록 설치방법.Method of installation of the combined sidewalk block for the building complex, characterized in that the sidewalk block 30 is installed in a step including. 제 1항에 있어서,The method of claim 1, 상기 결속 보도블록(30)을 설치하는 단계(S300)에서,In the step (S300) of installing the binding sidewalk block 30, 상기 결속 보도블록(30)은 설치시 상호 간의 결속력을 높이기 위해 외주연의 원주방향으로 다각형으로 형성된 결속부(31)가 다수개 형성되고, 상기 결속부(31)와 결속부(31) 사이에 결속홈(32)이 형성되어 다른 결속 보도블록(30)의 결속부(31)가 결합되며, 상기 결속 보도블록(30)의 중앙부에는 앙카블록(40)이 삽입 설치되도록 원형의 앙카블록홀(33)이 형성되는 것을 특징으로 하는 건축단지용 결속식 보도블록 설치방법.The binding sidewalk block 30 has a plurality of binding portions 31 formed in a polygonal shape in the circumferential direction of the outer circumference in order to increase the mutual binding force during installation, and is formed between the binding portion 31 and the binding portion 31. A binding groove 32 is formed so that the binding portion 31 of the other binding sidewalk block 30 is coupled, and a circular anchor block hole is inserted into the central portion of the binding sidewalk block 30 to install the anchor block 40 ( 33) is a method of installing a binding type sidewalk block for a building complex. 삭제delete
KR1020080117669A 2008-11-25 2008-11-25 Construction housing development using Footway-block of Installation method KR100924022B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020080117669A KR100924022B1 (en) 2008-11-25 2008-11-25 Construction housing development using Footway-block of Installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020080117669A KR100924022B1 (en) 2008-11-25 2008-11-25 Construction housing development using Footway-block of Installation method

Publications (1)

Publication Number Publication Date
KR100924022B1 true KR100924022B1 (en) 2009-11-02

Family

ID=41560970

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020080117669A KR100924022B1 (en) 2008-11-25 2008-11-25 Construction housing development using Footway-block of Installation method

Country Status (1)

Country Link
KR (1) KR100924022B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101185816B1 (en) 2010-04-05 2012-09-27 대한민국 Wood paving block

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000257009A (en) 1999-03-10 2000-09-19 Interlocking Block Hoso Gijutsu Kyokai Pavement concrete block
JP2004027690A (en) 2002-06-27 2004-01-29 Minoru Matsuoka Paving structure and paving method
KR20080006264A (en) * 2006-07-12 2008-01-16 김흥섭 Construction method of the sidewalk block

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000257009A (en) 1999-03-10 2000-09-19 Interlocking Block Hoso Gijutsu Kyokai Pavement concrete block
JP2004027690A (en) 2002-06-27 2004-01-29 Minoru Matsuoka Paving structure and paving method
KR20080006264A (en) * 2006-07-12 2008-01-16 김흥섭 Construction method of the sidewalk block

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101185816B1 (en) 2010-04-05 2012-09-27 대한민국 Wood paving block

Similar Documents

Publication Publication Date Title
KR101619285B1 (en) Sidewalk block with multi-function
EP2268866B1 (en) Drainage system, apparatus, and method
KR100757453B1 (en) Connection. the apartment complex in, which and uses this with the separable draining board an installation is facilitated road, the construction method
KR100924022B1 (en) Construction housing development using Footway-block of Installation method
KR100930419B1 (en) Sidewalk block supporting device and construction method of the same
KR101167981B1 (en) Construction method for protecting device of shade tree by the road side
CN214573096U (en) Pavement paving structure with high water permeability
CN108570904B (en) Sidewalk structure and construction method thereof
KR20110121374A (en) Water permeability way road pave method
KR100475329B1 (en) L type roadside drain having boundary stone and construction method thereof
KR100833688B1 (en) The road structure with subsidence preventing block, and construction method of road
KR200437489Y1 (en) Boundary block installation outlet of a roadway and sidewalk
KR102051860B1 (en) Drainage trench for pavement
KR100598771B1 (en) Sink prevent structure of pavement block for road
CN107829347B (en) Sidewalk structure for urban natural turf and construction method thereof
KR100989448B1 (en) Holder of permeant block for paving pedestrian-vehicle passage and paving method of pedestrian-vehicle passage using this
KR100876140B1 (en) Base block for eco-friendly footpath pavement and construction method thereof
CN210886800U (en) Novel antiskid structure of municipal administration pavement
CN217678437U (en) Ground surface drainage structure
CN213682391U (en) Precast concrete guiding gutter system in landscape engineering
KR100989978B1 (en) Rainwater cover for digging construction
CN220685680U (en) Assembled concrete pavement structure
CN216919886U (en) Curb with folded edge convenient to install
CN110258246B (en) Pedestrian road structure and construction method thereof
KR102563746B1 (en) Prefabricated support plate for sidewalk block and prevention of weeds growth

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
N231 Notification of change of applicant
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
N231 Notification of change of applicant
LAPS Lapse due to unpaid annual fee