KR20040073415A - Extracting casing after lower part curing type cast-in-place pile method - Google Patents

Extracting casing after lower part curing type cast-in-place pile method Download PDF

Info

Publication number
KR20040073415A
KR20040073415A KR1020040053097A KR20040053097A KR20040073415A KR 20040073415 A KR20040073415 A KR 20040073415A KR 1020040053097 A KR1020040053097 A KR 1020040053097A KR 20040053097 A KR20040053097 A KR 20040053097A KR 20040073415 A KR20040073415 A KR 20040073415A
Authority
KR
South Korea
Prior art keywords
casing
pile
curing
support
reinforcing material
Prior art date
Application number
KR1020040053097A
Other languages
Korean (ko)
Other versions
KR100657176B1 (en
Inventor
한동덕
Original Assignee
동명특수건설 주식회사
한동덕
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Family has litigation
First worldwide family litigation filed litigation Critical https://patents.darts-ip.com/?family=37360584&utm_source=google_patent&utm_medium=platform_link&utm_campaign=public_patent_search&patent=KR20040073415(A) "Global patent litigation dataset” by Darts-ip is licensed under a Creative Commons Attribution 4.0 International License.
Application filed by 동명특수건설 주식회사, 한동덕 filed Critical 동명특수건설 주식회사
Priority to KR1020040053097A priority Critical patent/KR100657176B1/en
Publication of KR20040073415A publication Critical patent/KR20040073415A/en
Application granted granted Critical
Publication of KR100657176B1 publication Critical patent/KR100657176B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/385Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with removal of the outer mould-pipes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

PURPOSE: A casing drawing-type cast-in place pile method after concrete curing of a front end is provided to secure safety of the pile foundation and the whole structure by precisely constructing a cast-in place pile regardless of conditions of the ground. CONSTITUTION: A casing drawing-type cast-in place pile method after concrete curing of a front end comprises steps for forming an excavating hole in a sediment layer(11) by intruding a casing(30) and excavating the sediment contained in the casing with a sediment excavator(S10); pulling out the sediment excavator with leaving the casing to keep a borehole after completing the excavation to a planned penetration(S20); forming the front end of the pile by pouring concrete(33) into the casing and drawing the casing at the predetermined distance to closely contact the lower end of the casing and the surface of the concrete(S41); preventing the settlement of the casing by mounting a casing support(50) on the casing exposed to the ground, putting a stiffener(31) in the casing after mounting a stiffener support(40) to the upper end of the casing, and fixing the upper end of the stiffener to the upper end of the casing through the stiffener support(S42); curing the front end of the pile with fixing the casing and the stiffener by the casing and stiffener supports(S43); and dismantling the stiffener and casing supports after completing the curing of the front end and forming a pile body by pulling out the casing, injecting a filler(34) in the casing, and filling the excavating hole(S51).

Description

선단부 양생후 케이싱 인발식 현장타설 말뚝공법{EXTRACTING CASING AFTER LOWER PART CURING TYPE CAST-IN-PLACE PILE METHOD}Casing drawing-in-place pile pile method after curing of the tip part {EXTRACTING CASING AFTER LOWER PART CURING TYPE CAST-IN-PLACE PILE METHOD}

본 발명은 철골이나 철근 등의 보강재가 매입(埋入)된 현장타설 말뚝을 시공함에 있어서, 일단 말뚝의 선단부에 콘크리트를 타설한 후 보강재 및 케이싱을 지표면에 고정한 상태로 양생하고, 양생이 완료되면 말뚝의 나머지 부분을 구성하여, 말뚝의 양생 중에 보강재의 위치가 변경되는 것을 방지함으로써, 현장타설 말뚝의 정밀한 시공이 가능하도록 한 것이다.In the present invention, when constructing a field-placed pile in which reinforcement materials such as steel frame or reinforcing steel are embedded, once the concrete is poured at the tip of the pile, the reinforcement and the casing are fixed to the ground, and curing is completed. By constructing the rest of the pile, by preventing the position of the reinforcing material is changed during the curing of the pile, it is possible to precise construction of the cast-in-place pile.

현장타설 말뚝은 기성(旣成)말뚝과 대비되는 말뚝기초의 일종으로서, 미리 천공된 굴착공 내부로 콘크리트를 타설한 후 양생하여 구성하게 되며, 기성말뚝과는 달리 지반에 타입(打入)하는 공정이 불필요하므로, 항타(杭打)과정에서 유발되는 소음이나 진동을 방지할 수 있는 장점이 있다.The cast-in-place pile is a kind of pile foundation in contrast to the ready-made pile, and it is composed by pouring concrete into the pre-drilled excavation hole and curing it. Since the process is unnecessary, there is an advantage that can prevent the noise or vibration caused during the driving process.

일반적으로 말뚝기초는 선단지지력과 주면(柱面)마찰력에 의하여 말뚝 상부 구조물의 하중이나 지하수로 인한 지중구조물의 부압(浮壓)에 저항하게 되므로, 암반층 이상의 굴착심도를 확보하거나, 암반층이 지나치게 깊은 경우 소정길이 이상의 근입장(根入長)을 확보하여야 한다.In general, pile foundations are resistant to negative pressure of underground structures due to the load of the upper pile structure or groundwater due to the tip bearing and main surface frictional forces, thus securing the excavation depth beyond the rock layer or the rock layer being too deep. In this case, it is necessary to secure near-term entry length.

도 1은 토사층(11)과 암반층(12)으로 구성된 전형적인 지반에 현장타설 말뚝을 시공하는 과정을 나타낸 것으로, 게이싱(30)을 관입시키며 토사굴착장비(21)로 케이싱(30) 내부의 토사를 굴착하여 토사층(11)에 굴착공을 형성하는 토사층굴착단계(S10), 암반층(12) 까지 굴착이 완료되면 공벽이 유지되도록 케이싱(30)은 남겨둔 채 토사굴착장비(21)를 인발하는 굴착장비인발단계(S20), 케이싱(30) 내에 암반굴착비트(22)를 투입하여 암반층(12)을 굴착하는 암반층굴착단계(S30), 암반층(12)에 형성된 굴착공에 철골이나 철근 등의 보강재(31)를 삽입하는 보강재투입단계(S40), 케이싱(30)을 인발하면서 트레미관(32)을 통하여 케이싱(30) 내부로 콘크리트(33)를 타설하는 콘크리트타설단계(50) 및 타설된 콘크리트(33)를 양생하여 말뚝을 완성하는 양생단계(S60)로 이루어진다.FIG. 1 shows a process of constructing a cast-in-place pile in a typical ground composed of a soil layer 11 and a rock layer 12, injecting the gasket 30, and the earth and sand inside the casing 30 with the earth excavation equipment 21. As shown in FIG. Excavation to excavate the earth and sand layer excavation step (S10) to form an excavation hole in the soil layer (11), rock excavation to the rock layer (12) is completed excavation to pull out the earth excavation equipment 21 while leaving the casing 30 so that the empty wall is maintained Equipment drawing step (S20), the rock bed excavation bit 22 into the casing 30 to excavate the rock bed layer 12 rock bed layer excavation step (S30), reinforcing materials such as steel or steel in the excavation hole formed in the rock bed layer 12 Reinforcement input step (S40) for inserting the 31, the concrete pouring step (50) and poured concrete to cast the concrete (33) into the casing (30) through the tremis tube (32) while drawing the casing (30) Curing (33) consists of a curing step (S60) to complete the pile.

경우에 따라서는 암반층(12)을 굴착하지 않고, 케이싱(30) 내에 철골을 거치한 후 항타하여 암반층(12)에 보강재(31)인 철골을 타입하는 방법을 사용할 수 도 있으며, 이렇듯 암반층(12)의 심도가 깊지 않아서 시공중 말뚝의 선단부 고정이 용이한 경우, 즉 보강재(31)를 케이싱(30) 내로 투입함에 있어서 보강재(31)의 하단이 암반층(12)으로 인하여 용이하게 고정되는 경우에는 이후 현장타설 말뚝의 본체를 구성하기 위한 콘크리트(33)의 타설 및 양생과정 중에 보강재(31)의 변위가 미미하므로 높은 정도(精度)의 시공이 가능하게 된다.In some cases, without drilling the rock layer 12, the steel frame is mounted in the casing 30, and then driven to drive the steel frame, which is a reinforcing material 31 to the rock layer 12, as described above. In the case that the depth of the stiffener is not easy to fix the tip of the pile during construction, that is, when the bottom of the stiffener 31 is easily fixed due to the rock layer 12 when the stiffener 31 is introduced into the casing 30. Since the displacement of the reinforcing material 31 during the casting and curing process of the concrete 33 for constituting the body of the cast-in-place pile is minimal, construction of high precision is possible.

그러나 도 2에서와 같이, 토사층(11)으로만 구성된 지반에 현장타설 말뚝을 시공하는 경우에는 콘크리트(33)의 타설 및 양생과정 중 보강재(31)의 위치나 각도가 변경될 가능성이 매우 크며, 따라서 정밀한 시공이 어려울 뿐 아니라, 지지력 확보를 위하여 안전계수를 높히게 되므로 과다설계 및 과다시공이 이루어지게 되어공사비가 증액되는 심각한 문제점이 있었다.However, as shown in Figure 2, when the construction site on the ground consisting of only the soil layer (11) when the pile is placed and the position or angle of the reinforcement 31 is very likely to change during the curing and curing of the concrete 33, Therefore, not only the precise construction is difficult, but also the safety factor is increased to secure the bearing capacity, so there is a serious problem that the construction cost is increased due to the overdesign and the overconstruction.

특히, 토사층(11)과 암반층(12)을 막론하고 말뚝 선단부에 지지력 확보를 위한 확대부를 형성하는 경우, 콘크리트(33) 타설 및 양생과정 중의 보강재(31) 변위 발생가능성이 더욱 증가되어, 기초 뿐 아니라 지상 구조물의 안전을 심각하게 위협하는 문제점이 있었다.Particularly, in the case of forming an enlarged portion for securing bearing capacity at the pile tip regardless of the soil layer 11 and the rock layer 12, the possibility of displacement of the reinforcement 31 during the casting and curing process of the concrete 33 is further increased. But there was a serious threat to the safety of the ground structure.

본 발명은 전술한 문제점을 감안하여 창안한 것으로, 보강재가 매입되는 현장타설 말뚝을 시공함에 있어서, 일단 케이싱을 소폭 인발하면서 말뚝의 선단부를 타설한 후 보강재 및 케이싱을 지표면에 고정한 상태로 양생하고, 양생이 완료되면 굴착공을 콘크리트, 모래 또는 쇄석등의 충전체로 충전함으로써 말뚝의 나머지 부분을 구성하여, 말뚝의 양생 중에 보강재의 위치가 변경되는 것을 방지한 것이다.The present invention has been devised in view of the above-described problems, in constructing a site-placement pile into which the reinforcement is embedded, curing the reinforcement and the casing in a state where the reinforcement and the casing are fixed to the ground surface after placing the tip of the pile while drawing the casing slightly. When curing is completed, the excavation hole is filled with a filler such as concrete, sand, or crushed stone to form the remainder of the pile, thereby preventing the position of the reinforcement during the curing of the pile.

소폭 인발된 케이싱의 상부에는 케이싱의 자중을 지면에 분산 재하할 수 있도록 구성된 케이싱지지대를 설치하여 양생 중 케이싱의 침하를 방지하고, 케이싱의 상단에는 케이싱 내부에 투입된 철골이나 철근 등의 보강재를 고정하는 보강재지지대를 설치함으로써 양생 중에 보강재의 변위가 발생하지 않도록 하였다.The upper part of the casing which is narrowly drawn is installed with a casing support configured to disperse the weight of the casing on the ground to prevent settlement of the casing during curing, and the upper part of the casing secures reinforcing materials such as steel or steel reinforced into the casing. The reinforcement support was installed to prevent displacement of the reinforcement during curing.

도 1은 일반적인 지반조건에서의 종래 현장타설 말뚝공법 설명도1 is an explanatory diagram of a conventional cast-in-place pile method in general ground conditions

도 2는 토사층에서의 종래 현장타설 말뚝공법 설명도2 is an explanatory diagram of a conventional cast-in-place pile method in the soil layer

도 3은 본 발명의 일 실시예 설명도Figure 3 is an illustration of an embodiment of the present invention

도 4는 본 발명의 일 실시예에 있어서 양생 중인 말뚝의 두부 상세도Figure 4 is a detailed view of the head of the curing pile in an embodiment of the present invention

도 5는 본 발명의 일 실시예에 있어서 시공중인 말뚝의 분해 사시도5 is an exploded perspective view of a pile under construction in an embodiment of the present invention;

도 6은 본 발명에 있어서 양생 중인 말뚝 선단부의 상세도Figure 6 is a detailed view of the pile tip being cured in the present invention

도 7은 본 발명의 보강재 투입상태도.Figure 7 is a state of reinforcement input of the present invention.

<도면의 주요부분에 대한 부호설명><Code Description of Main Parts of Drawing>

11 : 토사층11: soil layer

12 : 암반층12: rock bed

21 : 토사굴착장비21: Earth excavation equipment

22 : 암반굴착비트22: rock drilling bit

30 : 케이싱(Casing)30: Casing

31 : 보강재31: reinforcement

32 : 트레미관(Tremie pipe)32: Tremie pipe

33 : 콘크리트33: concrete

34 : 충전체34: charging body

40 : 보강재지지대40: reinforcement support

41 : 프레임41: frame

42 : 고정판42: fixed plate

43 : 고정나사43: set screw

50 : 케이싱지지대50: casing support

51 : 평판플랜지51: flat flange

52 : 밀착부52: close contact

53 : 체결나사53: Tightening Screw

S10 : 토사층굴착단계S10: earth excavation stage

S20 : 굴착장비인발단계S20: Excavation Equipment Drawing Step

S30 : 암반층굴착단계S30: rock bed excavation stage

S40 : 보강재투입단계S40: Reinforcement input step

S41 : 선단부타설단계S41: Tip placement step

S42 : 보강재정치(定置)단계S42: reinforcement finance stage

S43 : 선단부양생단계S43: Tip curing stage

S50 : 콘크리트타설단계S50: Concrete pouring step

S51 : 본체충전단계S51: main body charging step

S60 : 양생단계S60: Curing Stage

본 발명의 상세한 구성을 첨부된 도면을 통하여 설명하면 다음과 같다.The detailed configuration of the present invention through the accompanying drawings as follows.

도 3에서와 같이, 우선 게이싱(30)을 관입시키며 토사굴착장비(21)로케이싱(30) 내부의 토사를 굴착하여 토사층(11)에 굴착공을 형성하고, 계획심도까지 굴착이 완료되면 공벽이 유지되도록 케이싱(30)은 남겨둔 채 토사굴착장비(21)를 인발하게 되는데, 여기까지의 공정은 앞서 도 2를 통하여 설명한 바 있는 종래의 공법과 동일하다.As shown in FIG. 3, first, inject the gasket 30 and excavate the earth and sand inside the casing 30 by forming the excavation hole in the earth and sand layer 11, and when the excavation is completed to the planned depth. The excavation equipment 21 is drawn out while the casing 30 is left to maintain the empty wall. The process up to this point is the same as the conventional method described above with reference to FIG. 2.

굴착공의 형성이 완료되면, 케이싱(30)을 서서히 인발하면서 케이싱(30) 내부에 콘크리트(33)를 타설하여 말뚝의 선단부를 구성하는데, 이때 케이싱(30)의 인발속도와 콘크리트(33)의 타설속도 및 양을 조절하여 케이싱(30)의 하단이 타설된 콘크리트(33)의 상부 표면에 인접하도록 한다.When the formation of the excavation hole is completed, while drawing the casing 30 slowly, the concrete 33 is poured into the casing 30 to form the tip of the pile, wherein the drawing speed of the casing 30 and the concrete 33 Adjusting the pouring speed and the amount so that the lower end of the casing 30 is adjacent to the upper surface of the poured concrete (33).

이렇듯 말뚝 선단부 형성을 위한 콘크리트(33) 타설시, 케이싱(30)의 하단이 타설된 콘크리트(33)와 완전히 이격되거나 콘크리트(33) 내로 관입되지 않고, 인접하도록 유지하는 이유는 공벽(孔壁)을 유지함과 동시에, 추후 양생과정에서 케이싱(30)에 콘크리트(33)가 부착되지 않도록 하기 위해서 이다.As such, when pouring concrete 33 to form the tip of the pile, the lower end of the casing 30 is not completely spaced from the poured concrete 33 or penetrated into the concrete 33, and the reason for keeping the adjacent wall is a hollow wall (孔 壁). At the same time to maintain the, so that the concrete 33 is not attached to the casing 30 in the later curing process.

특히, 말뚝 선단부타설이 완료된 후 양생과정에 있어서, 케이싱(30)의 하단이 콘크리트(33)에 매입될 경우, 케이싱(30)이 인발되지 않거나, 양생된 말뚝 선단부가 케이싱(30)과 함께 인발될 수도 있으므로 각별히 주의해야 되며, 실제 시공에 있어서는 이러한 현상을 방지하기 위하여 도 6에서와 같이, 콘크리트(33)와 케이싱(30)이 약간 이격되도록 시공하는 것이 바람직하다.In particular, in the curing process after the pile tip portion is completed, when the lower end of the casing 30 is embedded in the concrete 33, the casing 30 is not drawn, or the cured pile tip portion is drawn together with the casing 30 In particular, in order to prevent this phenomenon, it is preferable to construct the concrete 33 and the casing 30 so as to be slightly spaced apart from each other.

말뚝 선단부 구성을 위한 콘크리트(33) 타설이 완료되면, 지면위로 노출된 케이싱(30)의 상부에 케이싱지지대(50)를 설치하여 케이싱(30)이 침하되지 않도록 하고, 케이싱(30)의 상단에는 보강재지지대(40)를 설치한 후, 도 7에서와 같이, 보강재지지대(40)를 통하여 정확한 위치와 자세를 유지하면서 보강재(31)를 케이싱(30) 내부에 투입하게 된다.When the pouring of concrete 33 for the pile tip configuration is completed, the casing support 50 is installed on the upper portion of the casing 30 exposed on the ground so that the casing 30 does not settle and the upper end of the casing 30 After the reinforcement support 40 is installed, as shown in FIG. 7, the reinforcement 31 is introduced into the casing 30 while maintaining the correct position and posture through the reinforcement support 40.

케이싱지지대(50)는 말뚝 선단부 콘크리트(33)의 양생과정 중에 케이싱(30)이 침하되는 것을 방지하기 위한 것으로서, 지면 위로 노출된 케이싱(30)의 상부에 고정되어 케이싱(30)의 자중을 지면에 분산할 수 있도록 구성되며, 그 실시예가 도 4 및 도 5에 도시되어 있다.The casing support 50 is for preventing the casing 30 from sinking during the curing process of the pile tip concrete 33. The casing support 50 is fixed to the upper portion of the casing 30 exposed to the ground to ground the weight of the casing 30. And an embodiment thereof are shown in FIGS. 4 and 5.

도시된 실시예의 케이싱지지대(50)는 일면이 케이싱(30)의 외주면과 일치하도록 형성된 밀착부(52) 및 상부면은 밀착부(52) 하단에 접합되고 저면은 지면에 접하는 판상(板狀)의 평판플랜지(51)로 구성되며, 한쌍의 케이싱지지대(50)가 대칭을 이루면서 케이싱(30)에 밀착 체결되어 고정되는 구조로서, 신속한 체결 및 해체가 가능하도록 체결나사(53)가 구성되어 있다.The casing support 50 of the illustrated embodiment has a contact portion 52 and an upper surface formed such that one surface thereof coincides with the outer circumferential surface of the casing 30, and a bottom surface is joined to the lower portion of the contact portion 52 and the bottom surface thereof is in contact with the ground. Consists of a flat flange 51, the pair of casing support 50 is symmetrical to the casing 30 is fastened tightly fixed, fastening screw 53 is configured to enable fast fastening and disassembly. .

보강재지지대(40)는 도 4 및 도 5에 그 실시예가 도시되어 있으며, 말뚝 선단부 콘크리트(33)의 양생 중 철골이나 철근 등의 보강재(31) 상단을 케이싱(30)의 상단에 고정함으로써, 보강재(31)의 위치나 각도가 변하지 않도록 하는 역할과 함께, 전술한 바와 같이 보강재(31)를 케이싱(30) 내부에 투입함에 있어서, 투입경로를 안내함으로써 투입된 보강재(31)가 기 타설된 콘크리트(33)에 정확한 위치와 자세로 관입될 수 있도록 하는 역할 또한 수행하게 된다.4 and 5, the embodiment is shown in the reinforcement support 40, by fixing the upper end of the reinforcing material 31, such as steel frame or reinforcing steel during the curing of the pile tip concrete 33 to the upper end of the casing 30, In addition to the role that the position or angle of the 31 is not changed, as described above, when the reinforcing material 31 is introduced into the casing 30, the reinforcing material 31 introduced by guiding the feeding path is poured into concrete. 33, it will also play a role in intruding into the correct position and posture.

도시된 실시예의 보강재지지대(40)는 고정나사(43)에 의하여 케이싱(30) 상단에 고정되는 장방형의 프레임(41)과 프레임(41)에 설치된 한쌍의 평행한 고정판(42) 등으로 구성되고, 투입되는 보강재(31)의 치수에 따라 양측 고정판(42)간의 간격을 조절할 수 있도록 구성되며, 콘크리트(33) 타설시 부분 인발된 케이싱(30)의 상단부를 절단한 후 설치하게 된다.The reinforcing material support 40 of the illustrated embodiment is composed of a rectangular frame 41 fixed to the upper casing 30 by a fixing screw 43 and a pair of parallel fixing plates 42 installed on the frame 41 and the like. , It is configured to adjust the interval between the two fixing plates 42 according to the dimensions of the reinforcing material 31 is inserted, it is installed after cutting the upper end of the partially drawn casing (30) when the concrete 33 is placed.

이렇듯 보강재(31)를 고정한 상태에서 선단부의 양생이 완료되면 보강재지지대(40) 및 케이싱지지대(50)를 해체하고 케이싱(30)을 인발하면서 케이싱(30) 내부에 콘크리트(33)나 모래, 쇄석 등의 충전체(34)를 주입하여 굴착공을 충전(充塡)함으로써 현장타설 말뚝의 본체를 구성하게 된다.As such, when curing of the tip portion is completed in the state of fixing the reinforcing material 31, the reinforcing material support 40 and the casing support 50 are dismantled and the casing 30 is pulled out while the concrete 33, sand, and crushed stone are inside the casing 30. The main body of the cast-in-place pile is formed by filling the excavation hole by injecting the filler 34 such as the back.

도 3에 도시된 실시예는 충전체(34)로서 콘크리트(33)가 적용된 것으로서, 타설된 콘크리트(33)는 소정 기간의 양생과정을 통하여 말뚝으로 완성되게 되며, 이후 두부(頭部)정리 등의 후처리 공정을 거치게 된다.3 shows that the concrete 33 is applied as the filler body 34, and the poured concrete 33 is completed with a pile through a curing period of a predetermined period, and then, tofu, etc. After the post-treatment process.

결국 본 발명의 기술요지는 보강재(31)가 매입된 현장타설 말뚝의 시공방법에 있어서, 게이싱(30)을 관입시키며 토사굴착장비(21)로 케이싱(30) 내부의 토사를 굴착하여 토사층(11)에 굴착공을 형성하는 토사층굴착단계(S10)와, 계획심도까지 굴착이 완료되면 공벽이 유지되도록 케이싱(30)은 남겨둔 채 토사굴착장비(21)를 인발하는 굴착장비인발단계(S20)와, 케이싱(30) 내부로 콘크리트(33)를 소정량 타설하여 말뚝의 선단부를 구성하되 케이싱(30)의 하단과 타설된 콘크리트(33)의 표면이 인접하도록 케이싱(30)을 소정거리 인발하는 선단부타설단계(S41)와, 지면위로 노출된 케이싱(30)의 상부에 케이싱지지대(50)를 설치하여 케이싱(30)이 침하되지 않도록 하고, 케이싱(30)의 상단에는 보강재지지대(40)를 설치한 후, 보강재(31)를 케이싱 내부에 투입하고 보강재지지대(40)를 통하여 보강재(31)의 상단을 케이싱(30)의 상단에 고정하는 보강재정치(定置)단계(S42)와,케이싱지지대(50)와 보강재지지대(40)를 통하여 케이싱(30) 및 보강재(31)를 고정한 상태에서 말뚝의 선단부를 양생하는 선단부양생단계(S43)와, 선단부의 양생이 완료되면 보강재지지대(40) 및 케이싱지지대(50)를 해체하고 케이싱(30)을 인발하면서 케이싱(30) 내부에 충전체(34)를 주입하여 굴착공을 충전함으로써 말뚝 본체를 구성하는 본체충전단계(S51)가 포함됨을 특징으로 하는 선단부 양생후 케이싱 인발식 현장타설 말뚝공법으로서, 상기 케이싱지지대(50)는 일면이 케이싱(30)의 외주면과 일치하도록 형성된 한쌍의 밀착부(52)와, 상부면은 각각의 밀착부(52) 하단에 접합되고 저면은 지면에 접하는 판상(板狀)의 평판플랜지(51)와, 각각의 밀착부(52) 간에 체결되는 다수의 체결나사(53)로 구성됨을 특징으로 하는 선단부 양생후 케이싱 인발식 현장타설 말뚝공법이다.As a result, the technical gist of the present invention, in the construction method of the site-placed pile in which the reinforcement 31 is embedded, penetrates the casing 30 and excavates the earth and sand inside the casing 30 with the earth excavation equipment 21. 11) the excavation layer (S10) to form an excavation hole, and excavation equipment drawing step (S20) to pull out the excavation excavation equipment 21 while leaving the casing 30 so that the empty wall is maintained when excavation is completed to the planned depth And to cast the predetermined amount of concrete 33 into the casing (30) to form the tip of the pile, but to draw the casing (30) a predetermined distance so that the lower end of the casing (30) and the surface of the cast concrete 33 is adjacent to the casing (30) Install the casing support 50 on the tip portion placing step (S41) and the upper portion of the casing 30 exposed on the ground, so that the casing 30 does not settle, and the reinforcing material support 40 on the upper end of the casing 30 After installation, the reinforcing material 31 is put into the casing and the reinforcing material is supported. Reinforcing step (S42) for fixing the upper end of the reinforcing material 31 to the upper end of the casing 30 through the (40), the casing 30 and through the casing support 50 and the reinforcing material support (40) The tip curing step (S43) for curing the tip of the pile in a state in which the reinforcing material 31 is fixed, and when the curing of the tip is completed, the reinforcing member support 40 and the casing support 50 are dismantled and the casing 30 is drawn out. (30) Injecting the filling body 34 to fill the excavation hole by filling the excavation hole, the body filling step (S51) comprising the casing pull-out casing pull-out method after curing the front end portion, characterized in that the casing support 50 is a pair of close contact portion 52 formed so that one surface coincides with the outer circumferential surface of the casing 30, the upper surface is joined to the lower end of each contact portion 52, the bottom surface of the plate-like (하는) in contact with the ground It is fastened between the flat plate flange 51 and each contact portion 52 A plurality of front end after curing, characterized by consisting of a fastening screw (53) is a casing drawn expression Drilled method.

본 발명을 통하여 현장타설 말뚝의 정밀도를 향상시킴으로써, 기초를 비롯한 구조물 전체의 안전을 확보하는 효과를 얻을 수 있으며, 특히 지반조건에 관계없이 정밀한 시공이 가능하게 되어, 안전율 확보를 위한 과다설계 및 시공관행을 개선함으로써 공사비를 절감하는 효과 또한 얻을 수 있다.By improving the precision of the cast-in-place pile through the present invention, it is possible to obtain the effect of ensuring the safety of the entire structure, including the foundation, and in particular, it is possible to precise construction regardless of the ground conditions, overdesign and construction for securing the safety factor Improving practices can also reduce the cost of construction.

Claims (2)

보강재(31)가 매입된 현장타설 말뚝의 시공방법에 있어서,In the construction method of the cast-in-place pile in which the reinforcing material 31 is embedded, 게이싱(30)을 관입시키며 토사굴착장비(21)로 케이싱(30) 내부의 토사를 굴착하여 토사층(11)에 굴착공을 형성하는 토사층굴착단계(S10)와;A soil layer excavation step (S10) of injecting the gasket 30 to excavate the soil inside the casing 30 with the soil excavation equipment 21 to form an excavation hole in the soil layer 11; 계획심도까지 굴착이 완료되면 공벽이 유지되도록 케이싱(30)은 남겨둔 채 토사굴착장비(21)를 인발하는 굴착장비인발단계(S20)와;Excavation equipment drawing step (S20) for drawing the earth excavation equipment 21 while leaving the casing 30 to maintain the empty wall when the excavation is completed by the planned depth; 케이싱(30) 내부로 콘크리트(33)를 소정량 타설하여 말뚝의 선단부를 구성하되 케이싱(30)의 하단과 타설된 콘크리트(33)의 표면이 인접하도록 케이싱(30)을 소정거리 인발하는 선단부타설단계(S41)와;A predetermined amount of concrete 33 is poured into the casing 30 to form a tip end of the pile, but a tip end casting for drawing the casing 30 a predetermined distance so that the bottom of the casing 30 and the surface of the poured concrete 33 are adjacent to each other. Step S41; 지면위로 노출된 케이싱(30)의 상부에 케이싱지지대(50)를 설치하여 케이싱(30)이 침하되지 않도록 하고, 케이싱(30)의 상단에는 보강재지지대(40)를 설치한 후, 보강재(31)를 케이싱 내부에 투입하고 보강재지지대(40)를 통하여 보강재(31)의 상단을 케이싱(30)의 상단에 고정하는 보강재정치(定置)단계(S42)와;The casing support 50 is installed on the upper part of the casing 30 exposed on the ground so that the casing 30 does not settle, and the reinforcing material support 40 is installed on the upper end of the casing 30, and then the reinforcing material 31 is provided. A reinforcing step (S42) for putting the inside of the casing and fixing the upper end of the reinforcing material 31 to the upper end of the casing 30 through the reinforcing material support 40; 케이싱지지대(50)와 보강재지지대(40)를 통하여 케이싱(30) 및 보강재(31)를 고정한 상태에서 말뚝의 선단부를 양생하는 선단부양생단계(S43)와;A tip curing step (S43) for curing the tip of the pile in a state where the casing 30 and the reinforcing material 31 are fixed through the casing support 50 and the reinforcing material support 40; 선단부의 양생이 완료되면 보강재지지대(40) 및 케이싱지지대(50)를 해체하고 케이싱(30)을 인발하면서 케이싱(30) 내부에 충전체(34)를 주입하여 굴착공을 충전함으로써 말뚝 본체를 구성하는 본체충전단계(S51)가 포함됨을 특징으로 하는 선단부 양생후 케이싱 인발식 현장타설 말뚝공법.When curing of the front end is completed, the pile body is formed by dismantling the reinforcing material support 40 and the casing support 50, and filling the excavation hole by injecting the filling body 34 into the casing 30 while drawing the casing 30. Casing-pulling on-site casting method after the end portion curing, characterized in that the main body charging step (S51) is included. 제1항에 있어서, 케이싱지지대(50)는 일면이 케이싱(30)의 외주면과 일치하도록 형성된 한쌍의 밀착부(52)와;According to claim 1, the casing support (50) and a pair of close contact portion 52 formed so that one surface and the outer peripheral surface of the casing (30); 상부면은 각각의 밀착부(52) 하단에 접합되고 저면은 지면에 접하는 판상(板狀)의 평판플랜지(51)와;An upper surface is joined to the lower end of each contact portion 52, and a lower surface of the plate-like flat flange 51 is in contact with the ground; 각각의 밀착부(52) 간에 체결되는 다수의 체결나사(53)로 구성됨을 특징으로 하는 선단부 양생후 케이싱 인발식 현장타설 말뚝공법.Casing pull-in-place pile method after the end portion curing, characterized in that it consists of a plurality of fastening screws 53 fastened between each of the close contact portion (52).
KR1020040053097A 2004-07-08 2004-07-08 Extracting casing after lower part curing type cast-in-place pile method KR100657176B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020040053097A KR100657176B1 (en) 2004-07-08 2004-07-08 Extracting casing after lower part curing type cast-in-place pile method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020040053097A KR100657176B1 (en) 2004-07-08 2004-07-08 Extracting casing after lower part curing type cast-in-place pile method

Publications (2)

Publication Number Publication Date
KR20040073415A true KR20040073415A (en) 2004-08-19
KR100657176B1 KR100657176B1 (en) 2006-12-13

Family

ID=37360584

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020040053097A KR100657176B1 (en) 2004-07-08 2004-07-08 Extracting casing after lower part curing type cast-in-place pile method

Country Status (1)

Country Link
KR (1) KR100657176B1 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100710575B1 (en) * 2006-09-05 2007-04-24 주식회사 도화종합기술공사 Boiling prevention type piling method
KR100762991B1 (en) * 2006-08-08 2007-10-02 지에스이앤씨(주) Precast piling method injected with high-strength mortar
KR100900941B1 (en) * 2008-09-12 2009-06-08 금오전력 주식회사 Method for installing fixed light-concentrating apparatus
KR101105853B1 (en) * 2011-04-04 2012-01-13 이승수 Constructing method of cast-in-place concrete pile using mold case
CN111042121A (en) * 2019-12-20 2020-04-21 深圳市蛇口招商港湾工程有限公司 Construction method of bored backfill end pile foundation
KR102267676B1 (en) * 2020-10-23 2021-06-21 남궁부학 A method of construction for temporary retaining wall and sheating work cup using its method
KR102325548B1 (en) 2021-04-01 2021-11-11 남궁부학 Sheating work cup using method of construction for temporary retaining wall

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100783786B1 (en) 2006-05-18 2007-12-10 주식회사 포스코건설 Pre-bored Disconnected Pile Method
KR101071958B1 (en) * 2008-10-20 2011-10-12 이동희 underground excuvation pile construction method using percussion rotary drill
KR100938407B1 (en) * 2009-07-01 2010-01-25 주식회사 성우지오텍 About the cavity where the underground water flows the cavity charging method which is environmental-friendly
KR100970440B1 (en) * 2009-12-03 2010-07-15 대한기초엔지니어링 주식회사 Beam penetrating after lower part casting type cast-in-place pile method
US9816246B2 (en) 2010-01-19 2017-11-14 University Of Washington Through Its Center For Commercialization Pile with sound abatement for vibratory installations
US9617702B2 (en) 2010-01-19 2017-04-11 University Of Washington Through Its Center For Commercialization Pile with sound abatement
US8622658B2 (en) 2010-01-19 2014-01-07 University Of Washington Through Its Center For Commercialization Pile to minimize noise transmission and method of pile driving
KR101059921B1 (en) 2010-04-29 2011-08-26 (주)한미글로벌건축사사무소 Steel column pile construction method using the roller
EP2776636B1 (en) 2011-11-03 2016-12-21 University of Washington through its Center for Commercialization Pile with low noise generation during driving
KR101375155B1 (en) * 2012-03-30 2014-03-17 주식회사 영신 Construction Method of Reinforced Bar Insert Type in-situ Concrete Pile

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5248208A (en) * 1975-10-13 1977-04-16 Takenaka Komuten Co Posttcenter correcting apparatus
JPS5248207A (en) * 1975-10-13 1977-04-16 Takenaka Komuten Co Method of inserting post into pit
JPH0321705A (en) * 1989-06-16 1991-01-30 Hiroshi Sano Strut support mechanism for underground laying of street light base
JPH0626204A (en) * 1992-02-21 1994-02-01 Shimizu Corp Frame for erecting kitchen god post and kitchen god post erecting method using it
JP3631552B2 (en) * 1996-01-26 2005-03-23 株式会社竹中工務店 Upper centering device for guide pipe for construction of true pillar
KR100532024B1 (en) * 2003-10-27 2005-11-29 한동덕 Column supporter installed at the top of casing

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100762991B1 (en) * 2006-08-08 2007-10-02 지에스이앤씨(주) Precast piling method injected with high-strength mortar
KR100710575B1 (en) * 2006-09-05 2007-04-24 주식회사 도화종합기술공사 Boiling prevention type piling method
KR100900941B1 (en) * 2008-09-12 2009-06-08 금오전력 주식회사 Method for installing fixed light-concentrating apparatus
KR101105853B1 (en) * 2011-04-04 2012-01-13 이승수 Constructing method of cast-in-place concrete pile using mold case
CN111042121A (en) * 2019-12-20 2020-04-21 深圳市蛇口招商港湾工程有限公司 Construction method of bored backfill end pile foundation
KR102267676B1 (en) * 2020-10-23 2021-06-21 남궁부학 A method of construction for temporary retaining wall and sheating work cup using its method
KR102325548B1 (en) 2021-04-01 2021-11-11 남궁부학 Sheating work cup using method of construction for temporary retaining wall

Also Published As

Publication number Publication date
KR100657176B1 (en) 2006-12-13

Similar Documents

Publication Publication Date Title
KR100657176B1 (en) Extracting casing after lower part curing type cast-in-place pile method
KR20100068597A (en) A shoring method using arch plate pile and h-pile
KR100415809B1 (en) precast pile for braced wall and the method using the same
KR100970440B1 (en) Beam penetrating after lower part casting type cast-in-place pile method
KR101662072B1 (en) Temporary retaining wall using underground wall and connector and the construction method therefor
KR101065017B1 (en) A shoring method using arch plate pile and H-Pile
JP4925267B2 (en) Independent foundation and its construction method
KR101021915B1 (en) A method for constructing cut-off temporary structure for sheathing work
KR101045625B1 (en) Construction method of retaining wall using cast-in-place pile
JP3752560B2 (en) Basic structure for constructing a new building in an existing basement and its construction method
JP4811176B2 (en) Construction method of ready-made piles
JP3448629B2 (en) Seismic retrofitting method for existing structure foundation
KR200362565Y1 (en) Earth Retaining Wall Structure Using Precast Concrete Pile and Construction Method Thereof
JP4485006B2 (en) Construction method for underground structures
KR101375155B1 (en) Construction Method of Reinforced Bar Insert Type in-situ Concrete Pile
KR101021913B1 (en) A method for constructing cut-off temporary structure for sheathing work
KR100793510B1 (en) Tension soil nail and construction method of underground wall using the same
KR20130073336A (en) Pile structure and construction methods
KR100549088B1 (en) Method for isolated footing type under-Reamed pile and the isolated footing type under-Reamed thereof
KR20100123576A (en) Method for carrying out improved pile
JP2008075336A (en) Construction method for precast pile
US11613864B2 (en) Secant concrete shoring using helical piles for depth
KR100997229B1 (en) The slope protection structure and it&#39;s construction method for which multi grouting pipe and front wall panel were used
KR102146926B1 (en) Constructing method of micropile
KR200375610Y1 (en) Cast in place concrete pile using vibro magnetic shovel hammer

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
N231 Notification of change of applicant
E701 Decision to grant or registration of patent right
N231 Notification of change of applicant
GRNT Written decision to grant
J206 Request for trial to confirm the scope of a patent right
J121 Written withdrawal of request for trial
J204 Invalidation trial for patent
J301 Trial decision

Free format text: TRIAL DECISION FOR INVALIDATION REQUESTED 20081107

Effective date: 20090818

Free format text: TRIAL NUMBER: 2008100003373; TRIAL DECISION FOR INVALIDATION REQUESTED 20081107

Effective date: 20090818

J2X1 Appeal (before the patent court)

Free format text: INVALIDATION

Free format text: TRIAL NUMBER: 2009200006564; INVALIDATION

J204 Invalidation trial for patent
J302 Written judgement (patent court)

Free format text: JUDGMENT (PATENT COURT) FOR INVALIDATION REQUESTED 20090908

Effective date: 20121018

Free format text: TRIAL NUMBER: 2009200006564; JUDGMENT (PATENT COURT) FOR INVALIDATION REQUESTED 20090908

Effective date: 20121018

J2X2 Appeal (before the supreme court)

Free format text: APPEAL BEFORE THE SUPREME COURT FOR INVALIDATION

Free format text: TRIAL NUMBER: 2010300002575; APPEAL BEFORE THE SUPREME COURT FOR INVALIDATION

J301 Trial decision

Free format text: TRIAL DECISION FOR INVALIDATION REQUESTED 20100615

Effective date: 20110721

Free format text: TRIAL NUMBER: 2010100001548; TRIAL DECISION FOR INVALIDATION REQUESTED 20100615

Effective date: 20110721

J2X1 Appeal (before the patent court)

Free format text: INVALIDATION

Free format text: TRIAL NUMBER: 2011200007942; INVALIDATION

EXTG Extinguishment
J302 Written judgement (patent court)

Free format text: JUDGMENT (PATENT COURT) FOR INVALIDATION REQUESTED 20110817

Effective date: 20120615

Free format text: TRIAL NUMBER: 2011200007942; JUDGMENT (PATENT COURT) FOR INVALIDATION REQUESTED 20110817

Effective date: 20120615

J121 Written withdrawal of request for trial
J123 Written withdrawal of action (supreme court)