KR200390445Y1 - Auto-syncronized supporting system controlling to recover and offset displacement and repulsive force occurred according to working load - Google Patents

Auto-syncronized supporting system controlling to recover and offset displacement and repulsive force occurred according to working load Download PDF

Info

Publication number
KR200390445Y1
KR200390445Y1 KR20-2005-0010855U KR20050010855U KR200390445Y1 KR 200390445 Y1 KR200390445 Y1 KR 200390445Y1 KR 20050010855 U KR20050010855 U KR 20050010855U KR 200390445 Y1 KR200390445 Y1 KR 200390445Y1
Authority
KR
South Korea
Prior art keywords
load
displacement
vertical
girder
jack
Prior art date
Application number
KR20-2005-0010855U
Other languages
Korean (ko)
Inventor
홍석희
Original Assignee
홍석희
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 홍석희 filed Critical 홍석희
Priority to KR20-2005-0010855U priority Critical patent/KR200390445Y1/en
Application granted granted Critical
Publication of KR200390445Y1 publication Critical patent/KR200390445Y1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2220/00Temporary installations or constructions
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them

Abstract

본 고안은 지하구조물을 설치하기 위하여 굴착공사를 할때 토사가 붕괴되는 것을 방지하기 위하여 흙막이 구조의 수직벽과 띠장지지에 활용하여 토압이나 수압에 의하여 발생되는 변위와 하중을 설계관리치의 변위와 하중과의 관계를 연동하여 변위량과 하중을 복귀 및 상쇄시키면서 토압이나 수압을 지지하도록 하고, 현장계측치와 설계관리치를 피드백하여 허용치를 벗어날 염려가 있는 경우 재차 유압잭의 스트로크를 자동연동시켜 회복 및 상쇄하거나 또는 철근 콘크리트타설과 철근조립을 위해 설치되는 거푸집의 하부에 설치지지되어 콘크리트타설 및 철근조립중량으로 발생되는 변위량과 하중을 설계관리치의 캡버량과 하중관계에 연동되어 변위량과 하중을 직접 회복 및 상쇄하면서 또한 현장계측지와 설계관리치를 피드백하여 허용치를 벗어날 염려가 있는 경우 재차 유압잭을 삽입하여 스트로크를 자동연동시켜 회복 및 상쇄하면서 콘크리트 구조물을 지지하도록 하기 위한 흙막이벽 및 구조물지지동바리용 싱크로나이즈지지시스템에 관한 것이다.        In order to prevent the earth and sand from collapsing during the excavation work for the installation of underground structures, the present design utilizes the displacement and load generated by earth pressure or water pressure to support the vertical wall and band support of the earthquake structure. To support the earth pressure or hydraulic pressure while restoring and canceling the displacement and load by interlocking the relationship, and feedback the site measurement value and the design control value to recover and offset the hydraulic jack by automatically linking the stroke of the hydraulic jack again. Supported under the formwork installed for reinforcing concrete and reinforcing steel reinforcement, the displacement and load generated by concrete placing and reinforcing steel reinforcement are linked to the capber amount and load relationship of the design management value to directly recover and offset the displacement and load. Also, feedback the field measurement site and design management value If the eonal concerned will again for the stroke by inserting yuapjaek the retaining wall and the support structure supporting the system for synchronizing to Shore for supporting a concrete structure with recovery and offset automatically by interlocking.

Description

작용하중에 따라 발생되는 변위와 반력을 직접회복 및 상쇄하도록 제어하는 자동싱크로나이즈지지시스템{Auto-syncronized supporting system controlling to recover and offset displacement and repulsive force occurred according to working load}Auto-syncronized supporting system controlling to recover and offset displacement and repulsive force occurred according to working load}

본 고안은 지하구조물을 설치하기 위하여 굴착공사를 할때 토사가 붕괴되는 것을 방지하기 위하여 설치되는 흙막이 구조의 수직벽과 띠장지지에 활용하여 토압이나 수압에 의하여 발생되는 변위와 하중을 설계관리치의 변위와 하중과의 관계를 연동하여 변위량과 하중을 직접복귀 및 상쇄시키면서 토압이나 수압을 지지하도록 하거나 또는 철근콘크리트 타설과 철근조립을 위해 설치되는 거푸집의 하부에 설치지지되어 콘크리트를 타설 및 철근조립 중량으로 발생되는 변위량과 하중을 설계관리치의 캠버량과 하중관계에 연동되어 직접변위량과 하중을 회복 및 상쇄하면서 콘크리트 구조물을 지지하도록 하기 위한 흙막이구조 및 구조물지지동바리용 싱크로나이즈지지시스템에 관한 것이다.        The present design utilizes the displacement and load generated by earth pressure or water pressure by using the vertical wall and band support of the earthquake structure that is installed to prevent the earth and sand from collapsing during the excavation work to install the underground structure. In order to support the earth pressure or hydraulic pressure by directly restoring and canceling the displacement and load by linking the relationship between and the load, or to be installed under the formwork installed for reinforcement concrete casting and reinforcing steel reinforcement, The present invention relates to an earth retaining structure and a synchronizer support system for supporting structural structures, in which a displacement and load generated are linked to a camber amount and a load relationship of a design management value while supporting and restoring a direct displacement amount and load.

일반적으로 흙막이구조는 토사굴착면에 연하여 일정한 간격으로 수직파일을 설치하고 토사를 수직으로 굴착하면서 발생되는 토압이나 변위를 지지하기 위하여 상기 수직파일 내측에 일정한 간격을 두고 횡으로 띠장과 직각버팀대를 설치하는데 있어, 그 직각버팀대 대신에 경사(레이커)버팀대를 설치하는 경우에 상기 수직파일의 상부에 설치된 띠장에 레이커거더의 상부와 접하게 설치하면서 일정한 각도를 유지하도록 경사지게 설치하고, 상기 레이커거더의 하부는 터파기선의 굴착면에 기초를 설치한 후에 그 위에 설치하여 수직파일을 직접지지하도록 한다.       In general, the earth block structure is connected to the earth excavation surface to install vertical piles at regular intervals, and to support the earth pressure or displacement generated by excavating the soil vertically, and to support the earth pressure or displacement at a predetermined interval inside the vertical piles and the girdle and the right angle brace In the installation, in the case of installing the inclined (raker) brace instead of the right angle brace, it is installed inclined so as to maintain a constant angle in contact with the upper portion of the raker girder in a band installed on the upper portion of the vertical pile, and the lower portion of the raker girder After the foundation is installed on the excavation surface of the trench, it is installed on it so as to directly support the vertical pile.

상기 설명은 레이커거더를 흙막이 수직파일을 지지하기 위하여 설치되는 기존의 방법을 설명하는 것으로 기존의 레이커거더를 이용한 흙막이 수직파일지지는 1단만 지지할 수 있어, 레이커버팀대거더시스템의 공기단축, 작업공간최대확보 및 공사비대폭절감등의 대단히 높은 효과적인 측면에 비해 그 적용성에는 한계가 있었다.       The above description describes the existing method of installing the raker girder to support the vertical pile of the soil barrier. The vertical pile support of the soil barrier using the existing raker girder can support only one stage. The applicability was limited compared to the very high effective aspects such as maximum security and reduction of construction cost.

이를 극복하기 위하여 상기 시스템을 개발하였다. 상기 시스템은 거더상에 단계별 굴착에 따라 설치되는 수직벽의 횡 띠장 위치와 직각 방향과 일치되는 위치에 수직재를 설치하고 그 수직재의 끝단부에 하중변위연동 및 고정장치를 설치하고, 그 장치에 접하여 인장케이블을 설치하고, 그 인장케이블은 레이커거더의 양단부에 설치되는 고정장치에 정착한다.       The system was developed to overcome this. The system installs a vertical member at a position coincident with the lateral band position of the vertical wall installed by the stepwise excavation on the girder, and installs a load displacement linkage and fixing device at the end of the vertical member, The tension cable is installed, and the tension cable is fixed to fixing devices provided at both ends of the raker girder.

상기 수직재는 토압과 변위의 크기에 따라 그 길이를 변화하는데 그에 연하여 설치되는 인장케이블의 형상은 모멘트 분포도와 유사하게 되는 것을 특징으로 하는 싱크로나이즈 레이커거더 시스템이다.       The vertical member changes its length according to the earth pressure and the magnitude of the displacement, and the shape of the tension cable installed in connection with the vertical member is similar to that of the moment distribution diagram.

흙막이 수직파일을 중심으로 아이슬랜드 공법으로 절취한 후 1단계굴착 한 뒤에 설치한 1단 횡띠장과 상기 중앙부를 절취한 최종 굴착면에 설치되는 기초상에 상기 싱크로나이즈레이커거더지지시스템을 설치지지고정한 다음, 2단계 굴착하여 설치된 2단띠장과 상기 시스템의 1단의 수직재 위치와 일치하여 스크류잭이 부착된 하중전달버팀대를 직접 설치고정한 다음, 상기 1단의 수직재 끝단부에 설치된 하중변위 연동 및 고정장치에 유압잭을 삽입하고, 그 스트로크를 작용하중의 변위 및 하중크기에 따라 설계관리치 및 상기 거더 및 수직재에 부착된 변위계와 하중계의 계측결과를 비교하면서 연동시켜 직접복귀 및 상쇄하도록 하고, 그 스트로크를 연동시킬 때 그에 접하여 설치된 인장케이블은 잭의 반력대 역할을 하면서 인장력이 작용하도록 설치 및 지지하는 싱크로나이즈레이커거더지지시스템이다.       After the first step is excavated after cutting by Icelandic method around the vertical pile of earthen board, the synchronizer raker girder support system is installed and fixed on the foundation installed on the final excavation surface after cutting the central part. In accordance with the two-stage excavation installed in the two-stage excavation and the position of the vertical material of the first stage of the system, directly install and fix the load-carrying brace with the screw jack, and then to the load displacement interlocking and fixing device installed at the end of the vertical Insert the hydraulic jack and interlock the strokes by directly comparing the design management values and the measurement results of the displacement gauges attached to the girders and vertical members with the load gauges according to the displacements and load sizes of the working loads. The tension cable installed adjacent to it acts as a reaction zone for the jack, And a supporting synchronized raker girder support system.

이를 흙막이레이커거더 3단, 4단등으로 여러차례를 굴착하면서 상기 시스템을 반복적으로 설치 및 연동시켜 흙막이벽을 지지하도록 한다.        This excavation several times in the three-stage, four-stage, etc. of the earthquake raker girder to repeatedly install and interlock the system to support the earth walls.

흙막이벽으로 사용하는 경우로서 다른 실시예는 토사굴착면에 연하여 일정한 간격으로 수직파일을 설치하고 토사를 수직으로 굴착하면서 상기 수직파일 내측에 일정한 간격을 두고 횡으로 띠장거더를 설치한 후에 상기 띠장거더의 상당히 폭을 크게한 양단부에는 스크류잭이 부착된 수평버팀대를 설치하여 싱크로나이즈띠장거더지지시스템을 고정하도록 한 후에 상기 띠장거더시스템의 양측단부에 고정장치를 설치하고, 일정한 간격을 두고 수직재를 설치하되 상기 수직재의 길이를 중앙부는 길게하면서, 양측에 설치되는 수직재의 길이를 점차 작게한 수직재를 설치하면서 상기 수직재의 끝단부에 하중변위연동 및 고정장치를 설치한 후에 상기 띠장거더의 양측에 설치된 고정장치에 인장케이블을 정착하면서 상기 인장케이블이 상기 수직재의 하부에 설치된 하중변위연동 및 고정장치에 접하게 설치하여 포물선형의 인장케이블이 설치되도록 하여 외부토압 및 변위크기에따라 하중변위연동 및 고정장치에 유압잭을 삽입하고, 그 잭의 스트로크를 설계관리치 및 실제현장계측치와의 피드백에 따라 연동시켜 흙막이벽의 토압이나 수압을 직접 상쇄 및 회복하도록 하여 수평버팀대를 대폭삭제하는 싱크로나이즈띠장거더지지시스템이다.       Another embodiment is to use the earthen wall as a vertical pile at regular intervals in connection with the earth excavation surface and excavation of the soil vertically while installing the girders horizontally at regular intervals inside the vertical piles The horizontal braces with screw jacks are installed on both ends of the girder to make them significantly wider to fix the synchronizer girders supporting system, and then the fixing devices are installed at both ends of the girders girder system, and the vertical members are installed at regular intervals. While the length of the vertical member is extended to the center portion, while the vertical member is gradually reduced in the length of the vertical member installed on both sides while the load displacement interlocking and fixing device is installed at the end of the vertical member fixed to the both sides of the band girders While the tension cable is fixed to the device, the tension cable is Install the hydraulic jack into the load displacement linkage and fixing device according to the external earth pressure and displacement size by installing it in contact with the load displacement linkage and fixing device installed in the part. It is a synchronizer girders supporting system that significantly cancels horizontal braces by directly canceling and recovering earth pressure and water pressure of the earth wall by interlocking with feedback from actual field measurements.

또 다른 적용 실시예로서 콘크리트구조물을 설치하기 위한 거푸집의 하부에 설치되어 콘크리트를 타설 및 철근중량으로 발생되는 변위량과 하중을 설계관리치의 캠버량과 하중관계에 연동되어 변위량과 하중을 직접회복 상쇄하면서 콘크리트 구조물을 지지하도록 설치한 구조물지지동바리인 것으로서, 교량의 경우를 예로들어 설명하면, 교각사이의 지반 상에 기초를 설치하고, 그 위에 가설벤트를 설치하고, 상기 가설벤트위에 종거더를 설치한 후에 상기 종거더 위에 일정한 간격을 두고 횡으로 횡빔을 설치한 후에 그 위에 구체콘크리트슬래브를 형성하기 위한 거푸집을 설치하고,       As another application example, the displacement amount and load generated by placing concrete under the formwork for placing concrete structures and reinforcing steel are directly linked to the camber amount and load relationship of the design management value and directly offset the displacement amount and load. As a structural support bar installed to support a concrete structure, the bridge case is described as an example. A foundation is installed on the ground between the bridges, a temporary vent is installed thereon, and a vertical girder is installed on the temporary vent. After the horizontal beam is installed laterally at regular intervals on the vertical girder, formwork for forming concrete concrete slab is installed thereon,

상기 종거더의 하부에 일정한 간격을 두고 수직재를 설치하되, 상기 수직재의 길이를 중앙부는 길게하면서, 양측에 설치되는 수직재의 길이를 점차 작게한 수직재를 설치하고, 상기 수직재의 하부에 하중변위연동 및 고정장치를 설치하도록 한 후에 상기 종거더의 양측에 설치된 고정장치에 인장케이블을 정착하면서 상기 인장케이블이 상기 수직재의 하부에 설치된 하중변위연동 및 고정장치에 접하게 설치하여 포물선형의 인장케이블이 설치되도록 한 후에 상기 레이커거더시스템이나 띠장시스템과 동일한 매카니즘으로 작용하중과 변위를 직접 상쇄 및 회복시키면서 콘크리트를 타설하여 구조물을 설치하도록 하기 위한 싱크로나이즈동바리지지시스템이다.       A vertical member is installed at regular intervals at a lower portion of the vertical girder, and the vertical member is installed at both sides while the length of the vertical member is increased, and the vertical member is gradually reduced in length. After the fixing device is installed, the tension cable is fixed to the fixing devices installed on both sides of the vertical girder, and the tension cable is installed in contact with the load displacement linkage and the fixing device installed at the lower part of the vertical member so that the parabolic tension cable is installed. Afterwards, it is a synchronized movement blockage system for installing concrete by directly placing and reconstructing the working load and displacement by the same mechanism as that of the raker girder system or the strip system.

상기와 같이 싱크로나이즈지지시스템의 레이커거더, 띠장거더 및 동바리 종거더에 직각으로 설치된 수직재의 끝단부에 부착된 하중변위연동 및 고정장치에 유압잭을 삽입하고, 그 장치 끝에 연하여 설치된 인장케이블을 반력대로 이용하여 설계에서 요구되는 변위량과 응력을 도입한 상태의 지지시스템을 설계위치에 설치하면, 이들의 상기 거더상에는 외부하중에 의해 변위와 응력이 작용되고, 이는 상기 제작시에 도입된 설계관리치의 변위와 응력에 의해 직접상쇄하는 매카니즘을 갖도록 하는 것이며, 또한 상기 거더상에는 변위계와 하중계를 설치하여 실제발생변위와 하중의 계측값을 컴퓨터에 연결시켜 설계관리치와 피드백하여 허용치를 벗어날 염려가 있을 경우는 회로적으로 서로 상호연결된 유압실린더를 작동하여 유압잭의 스트로크를 연동시켜 설계관리치내로 조절하도록 직접변위량을 회복하거나 하중을 상쇄하도록 하여 토압등의 외부하중을 지지하도록 하는 흙막이벽의 레이커 거더나 띠장거더 또는 구체콘크리트구조물을 지지하는 동바리에 사용하는 싱크로나이즈지지시스템인 것이다.       Insert the hydraulic jack into the load displacement linkage and fixing device attached to the end of the vertical member installed at right angles to the raker girder, band girders, and vertical girder of the synchronizer support system as described above. When the support system is installed at the design position in which the displacement amount and stress required for the design are introduced at the design position, the displacement and the stress are acted on the girder by the external load, which is the displacement of the design management value introduced at the time of manufacture. And a mechanism that cancels directly by the stress and the girder is provided with a displacement gauge and a load gauge to connect the measured values of the actual displacement and load to the computer and feed back to the design management value, if there is a risk of deviation from the allowable value. Operate the hydraulic cylinders that are interconnected to each other to reduce the stroke of the hydraulic jack. It is a synchronizer support system used for a raker girder, bandage girder, or copper bar that supports concrete concrete structure to support external load such as earth pressure by restoring direct displacement or offsetting load to adjust it to design control value. will be.

본 고안의 목적은 싱크로나이즈지지시스템의 레이커거더, 띠장거더 및 동바리 종거더에 직각으로 설치된 수직재의 끝단부에 부착된 하중변위연동 및 고정장치에 유압잭을 삽입하고, 그 장치 끝에 연하여 설치된 인장케이블을 반력대로 이용하여, 설계에서 요구되는 변위량과 하중을 미리 도입하고, 케이블에는 기존의 압축프리스트레스힘이 도입되는 방법 대신에 인장력이 도입된 시스템을 설계위치에 설치하면, 이 상기 거더상에는 외부하중이 작용하게되며 외부하중에 의한 변위와 하중은 기제작시에 설계에서 요구되어 도입한 캠버와 하중에 의해 직접 회복 및 상쇄하는 매카니즘을 갖는 것이며, 또한 상기 거더상에는 변위계와 하중계의 센서를 부착하여 컴퓨터에 연결시켜 실제계측값과 설계관리치를 피드백하여 허용치를 벗어나거나 또는 벗어날 염려가 있을 경우는 회로적으로 서로 상호 연결된 유압실린더를 작동하여 유압잭의 스트로크를 연동시켜 설계관리치내로 조절하도록 변위량을 직접회복하거나 하중을 직접 상쇄하도록하여 토압등의 외부하중을 지지하도록 하는 흙막이벽의 레이커거더나 띠장거더 또는 구체구조물을 지지하는 동바리 공법에 적용하는 싱크로나이즈지지시스템을 설치하는 방법을 제공하기 위함이다.       The purpose of the present invention is to insert a hydraulic jack into the load displacement interlocking and fixing device attached to the end of the vertical member installed at right angles to the raker girder, band girders and the vertical girder of the synchronizer support system, By using the reaction force, the displacement and load required in the design are introduced in advance, and a system in which the tension force is introduced in the design position instead of the conventional compression prestressing force is introduced into the cable, and the external load acts on the girder. Displacement and load due to external load have a mechanism that directly recovers and cancels by the camber and load introduced and required in the design at the time of manufacture.In addition, a sensor of displacement gauge and load gauge is attached on the girder and connected to the computer. Feed back actual measurements and design control values to In case of fear, it is possible to operate hydraulic cylinders that are interconnected to each other in circuit, so that the stroke of hydraulic jacks can be interlocked to adjust within the design management value. It is to provide a method of installing a synchronizer support system applied to a wall raker girder, a strip girder, or a copper cladding method for supporting concrete structures.

종래기술로는 도1과 같이 토사를 수직으로 굴착한 수직벽에 작용하는 토압을 경사지게 설치된 레이커스트러트(11)를 1단으로 설치하여 토압을 지지하도록 한 것으로서, 구조 안전상 1단의 띠장(13)에만 설치하여 지지할 수 밖에 없어 굴착깊이가 극히 제한적이며, 그 적용 굴착 깊이가 깊거나 또는 변위가 크게 발생할 경우 상기 레이커스트러트(11)외에도 추가로 수평버팀대와 중간 파일을 더 설치하여야 하므로 공기증가의 문제와 이로인하여 추가적으로 강재를 설치하여야 하므로 공사비의 증가 및 보조강재를 사용하므로서 여유공간이 협소해지게되어 장비 작업공간의 제약등의 문제점이 상존하고 있다.        In the prior art, as shown in Fig. 1 to support the earth pressure by installing a raker strut 11 inclined to the earth pressure acting on the vertical wall excavated soil vertically in one stage, the first stage belt 13 for structural safety Excavation depth is extremely limited because it can only be installed and supported. If the excavation depth is deep or the displacement is large, the horizontal brace and the intermediate pile must be installed in addition to the raker strut 11 so that the air can be increased. Due to the problems and the need to install additional steel materials, the increase in construction cost and the use of auxiliary steel has become a narrow space, there is a problem such as constraints of the equipment work space.

종래의 굴착공사용 흙막이벽 공사에 보편적으로 많이 사용되는 기술은 도 2와 같이 수직파일(15)의 설치와 이를 지지하기 위하여 횡으로 일정한 간격으로 설치되는 띠장(13)과, 상기 띠장(13)에 2 ~ 4m 간격으로 수평으로 설치되는 버팀대(20)와 이들 버팀대(20)를 지지하도록 중간 파일(19)을 설치하고 가설구조계 안전을 확보하기 위하여 브레이싱(18)을 설치하고, 상기 띠장(13)과 버팀대(20) 사이에 스크류잭(12)을 설치하여 토압을 지지하도록 하는 흙막이벽(10)을 설치한 것이다.       Conventionally used in conventional excavating earth wall construction technology is the installation of the vertical pile 15 as shown in Figure 2 and the belt strip 13 is installed at regular intervals laterally to support it, and the strip sheet 13 Install the intermediate pile 19 so as to support the brace 20 horizontally installed at 2 to 4m intervals and these braces 20, and install the bracing 18 to ensure the safety of the temporary structural system, the belt length 13 And a jack jack 12 is installed between the brace 20 to install the earth wall 10 to support the earth pressure.

상기의 방법으로 설치되는 흙막이벽(10)은 상기 도1에서 언급한바와 같은 문제점인 조밀한 강재배치로 인한 경제성 저하와 장비작업공간의 협소로 인한 공기증가와 토압의 작용에 의한 띠장(13)에 발생되는 변위를 제어할 수 없어 토류벽 주변의 배면 침하등에 의한 민원야기와 흙막이벽(10)의 수직벽이 상호 마주보고있지 않으면 적용이 곤란한 문제가 있다.       The barrier wall 10 installed by the above method has a bandage 13 due to the action of increasing air pressure and earth pressure due to the economical deterioration due to the dense steel arrangement, which is the problem mentioned in FIG. It is difficult to control the displacement generated in the case that the civil petition due to the subsidence of the earth wall and the vertical wall of the retaining wall 10 do not face each other.

상기와 같은 문제점을 다소 해소하기 위하여 도3과 같이 버팀대(20)와 버팀대(20)의 간격을 다소확장하도록 하는 경우에는 상기 도 2와 같이 띠장(13)과 버팀대(20)를 설치하되 버팀대(20)와 버팀대(20) 사이의 띠장(13)에 별도의 보강띠장(23)을 붙이고, 상기 보강띠장(23)의 양단부에 한쌍으로 설치된 정착장치(21)에 PS강선(22)을 배치한 다음 상기 PS 강선(22)을 긴장 정착하므로서 압축의 프리스트레스힘이 작용하도록 하여 이로인하여 발생되는 편심모멘트로 외력의 모멘트를 상쇄하는 방법이다.        In order to somewhat expand the gap between the brace 20 and the brace 20 as shown in Figure 3 in order to solve the problem as described above, as shown in Figure 2 to install the band 13 and the brace 20, but the brace ( Attaching a separate reinforcing band length 23 to the band length 13 between the 20 and the brace 20, and the PS steel wire 22 to the fixing device 21 installed in pairs at both ends of the reinforcing band length 23 Next, the PS steel wire 22 is tensioned and fixed, so that the prestressing force of compression acts to offset the moment of external force by the eccentric moment generated thereby.

상기 PS강선(22) 정착위치에서 급격한 모멘트 반전이 이루어져 상기 위치에는 응력집중의 원인이 있고 그 편심모멘트로 인하여 띠장(13)에 발생되는 균등응력 직선분포가 외력에 의하여 발생되는 모멘트의 포물선형 상태와 불일치 함에 따라 띠장(13)에 발생되는 응력상태를 적절히 못하고 변위를 복귀시키지 못하며, 또한 굴착공사의 특징인 각 굴착단계별로 굴착하면서 발생되는 응력과 변위가 단계별로 변화하는데 반해 고정된 편심모멘트에 의해 적절하게 대응하지 못하여 적용성의 한계가 있을뿐만아니라 상기 수직벽의 변위를 적절하게 제어를 할 수 없어 수직벽의 주변배면에 토사의 침하 문제등이 야기되는 문제점이 있다.        The moment of reversal of moment in the PS steel wire 22 anchoring position causes a stress concentration in the position, and the uniform stress linear distribution generated in the strip 13 due to the eccentric moment causes the parabolic state of the moment generated by the external force. Due to the mismatch between the stress state and the displacement generated during the excavation at each excavation stage, which is characteristic of the excavation work, the stress state generated in the strip 13 is not appropriately restored and the displacement is changed step by step. There is a problem in that it does not properly correspond to the limit of the applicability, and the displacement of the vertical wall can not be properly controlled, causing settlement problems of earth and sand on the peripheral surface of the vertical wall.

상기 도3의 방법을 개선한 것이 도4의 기술로서 띠장(13)에 설치된 버팀대(20)의 간격을 보다 넓히기 위하여 보강띠장(23)에 편심이 크게 발생되도록 보강 띠장(23)에 일정한 간격을 두고 간격재(24)를 설치하고, 상기 보강띠장(23)의 양단부에 설치된 정착장치(21)에 PS 강선(22)을 정착하면서 간격재(24)의 하단에 PS 강선(22)이 접하도록 설치한 후에 상기 PS 강선(22)의 양단에서 인장력을 가한 후에 정착장치(21)에 긴장정착하여 PS 강선(22)에 압축력이 도입되고, 그 압축력이 편심모멘트를 발생하도록 하여 외력에 의해 발생하는 모멘트와 상쇄하는 방법으로서,        The improvement of the method of FIG. 3 is to improve the method of FIG. 4 to increase the spacing of the brace 20 installed in the belt 13, so that the eccentricity is generated in the reinforcing belt 23 so that a large distance is generated. The spacer 24 is installed, and the PS steel wire 22 is in contact with the lower end of the spacer 24 while fixing the PS steel wire 22 to the fixing device 21 installed at both ends of the reinforcing strip length 23. After installation, the tensile force is applied to both ends of the PS steel wire 22, and then it is tension-fixed to the fixing device 21, and a compressive force is introduced into the PS steel wire 22, and the compressive force is generated by an external force by generating an eccentric moment. As a way to offset the moment,

상기 방법의 경우 장경간의 띠장(13) 설치시 외력 모멘트가 상당히 증가하므로 이를 상쇄하기 위해서는 편심모멘트를 크게 발생하여야 함에 따라 상기 보강띠장(23)에 도입되는 프리스트레스힘도 또한 크게하여야 하고, PS강선(22)량 또한 과다하게 사용하여야 하고, 이에따라 사용되는 정착장치(21) 또한 과대하게 소요되며, 별도의 보강띠장(23)을 중첩배치하여야 하므로서 과도하게 사용하는 강재양과 과도한 인장력이 요구되므로 비경제적인 요소와 설치되는 장치의 과대한 중량으로 인하여 현장설치 작업의 효율성 저하와 상기 장치를 제작설치하여 고정됨에따라 프리스트레스의 조절이 안되므로 굴착공사의 특징인 단계별 터파기 및 되메우기에 의하여 발생되는 하중변화에 적절히 대응할 수 없어 그 적용성에 한계가 있으며, 기발생된 수직벽의 변위를 복귀시키지 못하므로 수직벽의 배면 침하를 제어할 수 없는등으로 인하여 민원의 소지가 있는 문제점이 있고, 과도한 편심모멘트 발생을 위해 간격재 길이가 커져 상대적으로 굴착공사 범위가 커져야 하는 문제점이 있다.        In the case of the method, since the external force moment increases considerably when installing the strip length 13 between the long spans, the eccentric moment must be generated largely to offset the prestress force introduced into the reinforcing strip length 23, and the PS steel wire ( 22) The amount is also excessively used, and the fixing device 21 used accordingly is excessively required, and the additional reinforcing band length 23 is required to be superimposed so that an excessive amount of steel and excessive tensile force are required, which is an uneconomical factor. Due to the excessive weight of the installed device, the efficiency of the field installation work is reduced and the prestress cannot be adjusted as the device is manufactured and installed. Therefore, it is appropriate to cope with the load change caused by the stepping and backfilling, which is the characteristic of the excavation work. There is a limit to its applicability, and the displacement of the generated vertical wall There is a problem of civil complaints due to the inability to control the back settlement of the vertical wall, there is a problem in that the excavation work should be relatively large because the length of the spacer is increased to generate excessive eccentric moment.

또한 기존의 슬래브 콘크리트 타설시 슬래브의 하중을 지지할 수 있도록 하는 구조물지지동바리는 도5와 도6에서 설명하는바와 같이 구체슬래브콘크리트(31)의 하부 전체를 강관 지주(33)로 지지하는 구조물전체지지동바리 방식(30)과 가설벤트(39)를 설치하고, 그 위에 종거더(35)와 횡빔(36)을 설치하여 지지하도록 하는 가설벤트(39)에 의한 구조물지지동바리(30) 방식이 있는데, 상기 두가지 모두 지지하도록 하는 강재의 사용량이 많아지며 지지하고자 하는 하부공간에 강관지주(33) 및 가설벤트(39)가 설치되므로 하부공간을 활용할 수 없어 교량건설시 교통우회도로를 별도로 만들거나 일시적으로 도로를 폐쇄함에 따른 공사비의 추가소요와 민원야기등의 문제점이 있으며, 하천교량의 경우 하천통수단면을 축소하게되므로 원활하게 하천수가 통수될 수 없는 수리학적인 문제가 발생될 수 있으므로 우기시에는 공사를 중지하여야 하는 문제점들이 상존하여 왔다.        In addition, the structure supporting movement bar for supporting the load of the slab in the existing slab concrete casting, as described in Figures 5 and 6, the entire structure for supporting the entire lower part of the concrete slab concrete 31 with the steel pipe support (33) There is a support structure of the structure 30 by means of a temporary vent (39) to install and support the support shaft method (30) and the temporary vent (39), the vertical girders (35) and side beams (36) installed thereon. The amount of steel used to support both of the above is increased, and the steel pipe holder 33 and the temporary vent 39 are installed in the lower space to be supported, so the lower space cannot be utilized, so the traffic bypass road can be separately created or temporarily constructed during the bridge construction. As a result, there are problems such as additional cost of construction and civil complaints due to the closure of roads. It has to be a hydraulics problem occurs lingering issues that have to be there to stop the construction during the rainy season.

본 고안은 상기와 같은 문제점을 개선하기 위하여 제안된 것으로서, 흙막이벽 및 구조물지지동바리에 적용된 레이커거더, 띠장거더 또는 종거더에 외부하중 즉 토압, 수압, 타설중량에 의하여 내부하중과 변위가 발생되면, 상기 띠장거더, 레이커거더 및 종거더에 직각으로 설치된 수직재의 종단부에 부착된 하중변위연동 및 고정장치에 유압잭을 삽입하고, 그 장치길이에 접하여 설치된 인장케이블을 반력대로 이용하여 설계에서 요구되는 변위량과 하중을 잭의 스트로크 연동에 의하여 도입되고, 케이블에는 인장력이 도입된 싱크로나이즈지지시스템을 설치위치에 부착하면, 상기 외부하중에 의한 변위를 회복시킴과 동시에 하중을 상쇄하는 매카니즘을 갖는 것이며, 또한, 상기 종거더상에는 변위계와 하중계의 센서를 부착하여 실측계측값을 컴퓨터에 연결시켜 설계관리치를 피드백하여 허용한계를 벗어나거나 또는 벗어난 경우가 있을 경우 회로적으로 상호 연결된 유압잭을 작동시켜 유압잭의 스트로크를 연동시켜 설계관리치내로 변위 및 하중을 관리하도록 하여 상기 띠장거더 및 종거더에 작용하는 변위 및 하중을 상쇄시키면서 다시 원상태로 복귀시키도록 변위회복량만큼 상향으로 작용하도록 하여 토압을 지지하도록 하거나 또는 구체콘크리트구조물을 지지하도록 하는 시스템을 설치하는 방법에 관한 것으로서,        The present invention is proposed to improve the problems as described above, if the internal load and displacement caused by the external load, that is, earth pressure, hydraulic pressure, pour weight on the raker girder, band girders or longitudinal girders applied to the wall and the structure support bar The hydraulic jack is inserted into the load displacement interlocking and fixing device attached to the end of the vertical member installed at right angles to the strip girders, the raker girder and the vertical girder, and the tension cable installed in contact with the device length is used as a reaction force. When the displacement amount and load are introduced by the jack's stroke linkage, and the cable is equipped with a synchronized support system in which a tension force is introduced at the installation position, it has a mechanism to recover the displacement due to the external load and at the same time cancel the load. On the vertical girder, a displacement gauge and a sensor of a load gauge are attached to calculate the measured measurement value. To the design management value by connecting to the control system, and when there is a deviation or deviation from the allowable limit, by operating the hydraulically interconnected hydraulic jacks to interlock the strokes of the hydraulic jacks to manage displacement and load within the design management values. A method of installing a system for supporting earth pressure or supporting a concrete concrete structure by acting upward by a displacement recovery amount to cancel the displacement and load acting on the longitudinal girder and returning it to its original state.

상기의 시스템을 이용하여 공사를 시공하면 다단계의 굴착단계를 실행 할 수 있도록 적용깊이를 대폭 증가할 수 있고, 버팀대수를 대폭절감하여 아이슬랜드공법을 적용할 수 있으며, 장비 공간 활용을 극대화하여 공기단축과 자재절감을 통한 공사비의 절감으로 인한 경제성 제고와 띠장과 버팀대로 지지하던 종래의 방식을 보다 효율적으로 적용할 수 있도록 하므로서 강재사용을 최소화하여 경제성을 높이고, 작업 공간을 확보하여 공기를 단축할 수 있도록 하고, 단계별 굴착이나 되메우기에 따른 하중 변화에 피드백하고 콘트롤하면서 하중변화에 따른 변위에 적절하게 대응 할 수 있도록 하는 하중변위연동 및 고정장치의 스트로크를 자동연동도입하여 공사의 성역화를 도모하여 공사의 안정성을 높일 수 있으며, 기 발생된 변위도 부분적으로 복귀시켜 주변배면 침하를 억제 및 회복할 수 있도록 유도하여 도심공사에서 발생할 수 있는 민원야기등을 사전에 차단할 수 있는 경제적이면서 안전성과 효율성을 증가시켰으며, 종래의 방법을 보다 효율적으로 적용할 수 있는 매우 적용성이 넓은 시스템의 시공방법을 제공하는데 있다.       By constructing the construction using the above system, the application depth can be greatly increased to execute the multi-stage excavation stage, and the Icelandic method can be applied by greatly reducing the number of braces, and the equipment space is maximized to shorten the air. It can improve the economic efficiency by reducing construction cost by reducing the cost of materials and materials, and can apply the conventional method supported by the belt and brace more efficiently, thereby minimizing the use of steel materials, increasing the economic efficiency, and reducing the air by securing the working space. It is designed to feed the displacement of the load displacement linkage and the fixing device to feed back and control the load change due to the excavation or backfilling step by step, and to automatically adjust the stroke of the construction. Stability can be increased, and the previously generated displacement is partially restored. In order to prevent and recover the settlement of the surrounding rear surface, it is economical, safety and efficiency that can block civil complaints that may occur in urban construction in advance, and it is very effective to apply conventional methods more efficiently. It is to provide a construction method of a wide range of applicability.

본 고안은 흙막이벽으로 사용할 경우, 토사굴착면에 연하여 일정한 간격으로 수직파일(15)을 설치하고 토사를 수직으로 굴착하면서 발생되는 토압이나 변위를 지지하기 위하여 상기 수직파일(15) 내측에 일정한 간격을 두고 횡으로 띠장(13)과 수평버팀대를 설치하는데 있어, 그 수평버팀대 대신 레이커(경사)버팀대(45)로 설치하는 경우에는 상기 수직파일(15)의 상부에 설치된 띠장(13)에 레이커거더(45)의 상부와 접하게 설치하면서 일정한 각도를 유지하도록 경사지게 설치하고, 상기 레이커거더(45)의 하부는 최종터파기선(16)의 굴착면에 기초(17)를 설치한 후에, 그 위에 설치하도록 하고,       The present invention, when used as a retaining wall, is installed in the vertical pile 15 in order to support the earth pressure or displacement caused by installing the vertical pile 15 at regular intervals in connection with the earth excavation surface and excavating the soil vertically In installing the band 13 and the horizontal brace horizontally at intervals, in the case of installing the raker (tilt) brace 45 instead of the horizontal brace, the raker on the band 13 installed on the upper portion of the vertical pile 15 It is installed to be inclined to maintain a constant angle while being installed in contact with the upper portion of the girder 45, the lower portion of the raker girder 45 is installed on the excavation surface of the final breaker line 16, and then installed thereon Let's do it,

상기 레이커거더(45)상에는 단계별 굴착에 따라 설치되는 수직벽(15)의 횡띠장(13) 위치와 직각방향과 일치되는 위치에 수직재(44)를 설치하고, 수직재(44)의 끝단부에 하중변위연동 및 고정장치(60)를 설치하고, 그 장치(60)에 접하여 인장케이블(43)을 설치하고, 그 인장케이블(43)은 레이커거더(45)의 양단부의 고정장치(42)에 정착한다.       On the raker girder 45, a vertical member 44 is installed at a position coincident with the horizontal direction 13 position of the vertical wall 15, which is installed according to the stepwise excavation, and the load is applied to the end of the vertical member 44. Displacement interlocking and fixing device 60 is provided, and the tension cable 43 is installed in contact with the device 60, and the tension cable 43 is fixed to the fixing device 42 at both ends of the raker girder 45. do.

상기 수직재(44)는 토압과 변위의 크기에 따라 그 길이를 변화하는데, 그에 접하여 설치되는 인장케이블(43)의 형상은 모멘트분포도와 유사하게 되어 외력모멘트에 비례하게되므로 소수부재의 사용과 변위스트로크 조절량이 적게되므로 보다 경제적이면서 안전적이고, 효율적인 구조계를 갖는 것을 특징으로 하는 싱크로나이즈지지시스템(40)이다.       The vertical member 44 changes its length according to the earth pressure and the magnitude of the displacement, and the shape of the tension cable 43 which is installed in contact with the vertical member is similar to the moment distribution and is proportional to the external force. The synchronization support system 40 is characterized by having a structure that is more economical, safer and more efficient because of less adjustment.

흙막이 수직파일(15)을 중심으로 아이슬랜드 공법으로 중앙부를 절취한 후 1단계 굴착한뒤 설치한 1단 횡띠장(13)과 상기 중앙부절취된 최종굴착면(16)에 설치된 기초(17)에 상기 싱크로나이즈지지시스템(40)을 설치고정한 다음, 2단계 굴착(59)하여 설치된 2단띠장(13)과 상기 시스템(40)의 1단수직재(44)위치와 일치하여 스크류잭(12)이 부착된 하중전달버팀대(40)를 직각으로 설치고정한 다음, 상기 1단의 수직재(44) 끝단부에 설치된 하중변위 연동 및 고정장치(60)에 유압잭(64)을 삽입하고, 그 스트로크를 상기 변위 및 하중을 설계관리치와 상기 거더(45) 및 수직재(44)에 부착된 변위계(54)와 하중계(53)의 계측결과를 비교하면서 연동시켜 직접 변위와 하중이 복귀 및 상쇄하도록 하고, 그 스트로크를 연동시킬 때 그에 접하여 설치된 인장케이블(43)은 잭(64)의 반력대 역할을 하면서 인장력이 작용하도록 설치 및 지지하는 싱크로나이즈레이커거더지지시스템이다.       After cutting the central part by the Icelandic method around the vertical pile 15, the first stage transverse length 13 and the foundation 17 installed on the central excavated final excavation surface 16 were installed after the first step excavation. After the installation of the synchronizer support system 40 is fixed, the two-stage excavation 59 is installed and the screw jack 12 is attached in accordance with the position of the first stage 44 of the system 40. After the load transmission brace 40 is installed and fixed at right angles, the hydraulic jack 64 is inserted into the load displacement interlocking and fixing device 60 installed at the end of the vertical member 44 of the first stage, and the stroke is transferred to the displacement and load. Comparing the measured values of the design management value and the measurement results of the displacement gauge 54 and the load gauge 53 attached to the girder 45 and the vertical member 44 so that the displacement and load can be directly returned and canceled, and the stroke is interlocked. When the tension cable 43 is installed in contact with the reaction force of the jack (64) A synchronizing raker girder support system for installing and supporting a tensile force to act as a role.

상기 굴착이 3, 4단계등으로 시행하면서 상기 시스템을 반복적으로 설치 및 연동시켜 흙막이벽을 지지하도록 한다.        The excavation is carried out in three or four stages, such that the system is repeatedly installed and interlocked to support the retaining wall.

또 다른 흙막이벽의 실시예는, 토사굴착면에 연하여 일정한 간격으로 수직파일(15)을 설치하고 토사를 수직으로 굴착하면서 상기 수직파일(15) 내측에 일정한 간격을 두고 횡으로 띠장거더(46)를 설치한 후에 상기 띠장거더(46)의 상당히 넓은 간격을 둔 양단부에 스크류잭(12)이 부착된 수평버팀대(20)를 설치하여 띠장거더(46)를 지지하도록 한 후에 상기 띠장거더(46)의 양측단부에 고정장치(42)를 설치하고, 일정한 간격을 두고 수직재(44)를 설치하되 상기 수직재(44)의 길이를 중앙부는 길게하면서, 양측에 설치되는 수직재(44)의 길이를 점차 작게한 수직재(44)를 설치하면서 상기 수직재(44)의 일측단부에 하중변위연동 및 고정장치(60)를 설치한 후에 상기 띠장거더(46)의 양측에 설치된 고정장치(42)에 인장케이블(43)을 고정시킨 후 상기 인장케이블(43)이 상기 수직재(44)의 하부에 설치된 하중변위연동 및 고정장치(60)에 접하게 설치하여 포물선형의 인장케이블(43)이 설치되도록 하여 변위크기에따라 하중변위연동 및 고정장치와 유압잭을 삽입설치하고, 그 잭(64)의 스트로크를 설계관리치와 실제현장계측치 결과를 피드백하여 연동시켜 흙막이벽의 토압을 지지하도록 하여 수평버팀대를 대폭삭감하도록 하는 싱크로나이즈띠장거더지지시스템(40)이다.       Another embodiment of the retaining wall, the vertical pile 15 is installed at regular intervals in connection with the earth excavation surface, and the excavation of the earth and sand vertically while the vertical pile (15) inside the horizontal girders (46) ) And then install the horizontal brace 20 with the screw jack 12 attached to both ends of the girder girder 46 to allow the girder girder 46 to be supported. The fixing device 42 is installed at both ends of the side), and the vertical member 44 is installed at regular intervals, while the length of the vertical member 44 is increased in the center portion, and the length of the vertical member 44 installed on both sides is gradually increased. While installing the small vertical member 44, the load displacement interlocking and fixing device 60 is installed at one end of the vertical member 44, and then a tension cable (for the fixing device 42 provided on both sides of the band girder 46). 43) after the tension cable 43 is fixed It is installed in contact with the load displacement interlocking and fixing device 60 installed in the lower portion of the woven fabric 44 so that the parabolic tension cable 43 is installed so that the load displacement interlocking and fixing device and the hydraulic jack are installed according to the displacement size. The stroke of the jack 64 is fed back to the design management value and the actual field measurement result so as to support the earth pressure of the retaining wall so as to greatly reduce the horizontal brace girder gird support system 40.

또 다른 적용 실시예로서, 콘크리트 구조물의 설치시 구조물을 지지할 수 있도록 구조물지지동바리(30)에 적용하도록 한 것으로서, 콘크리트구조물을 설치하기 위한 거푸집(32)의 하부에 설치되어 콘크리트를 타설하면서 발생되는 변위량과 하중을 설계관리치의 캠버량과 하중관계에 연동되어 변위량과 하중을 회복 및 상쇄하면서 콘크리트 구조물을 지지하도록 설치한 구조물지지동바리인 것으로서, 교량의 경우를 예로들어 설명하면, 교각(37)사이의 지반 상에 기초(38)를 설치하고, 그 위에 가설벤트(39)를 설치하고, 상기 가설벤트(39)위에 종거더(35)를 설치한 후에 상기 종거더(35) 위에 일정한 간격을 두고 횡으로 횡빔(36)을 설치한 후에 그 위에 구체콘크리트슬래브(34)를 형성하기 위한 거푸집(32)을 설치하고,       As another application embodiment, which is to be applied to the structure support bar (30) to support the structure when installing the concrete structure, it is generated while placing the concrete installed in the lower part of the formwork 32 for installing the concrete structure It is a structure supporting bar installed to support concrete structure while restoring and offsetting displacement amount and load by linking displacement amount and load to the camber amount and load relationship of the design management value. After installing the foundation 38 on the ground between the installation of the temporary vent 39 thereon, and the vertical girders 35 on the temporary vents 39 after a certain interval on the vertical girders 35 After the horizontal beam 36 is installed laterally, formwork 32 for forming the concrete concrete slab 34 is installed thereon.

상기 종거더(35)의 하부에 일정한 간격을 두고 수직재(44)를 설치하되, 상기 수직재(44)의 길이를 중앙부는 길게하면서, 양측에 설치되는 수직재(44)의 길이를 점차 작게한 수직재(44)를 설치하고, 상기 수직재(44)의 하부에 하중변위연동 및 고정장치(60)를 설치하도록 한 후에 상기 종거더(35)의 양측에 설치된 고정장치(42)에 인장케이블(43)을 정착하면서 상기 인장케이블(43)이 상기 수직재(44)의 하부에 설치된 하중변위연동 및 고정장치(60)에 접하게 설치하여 포물선형의 인장케이블(43)이 설치되도록 한 후에 콘크리트를 타설시 발생하는 하중과 변위를 상쇄 및 회복시키거나 실제계측치와 피드백을 통해 설계관리치에 벗어날 염려가 있을 경우 재차 잭을 삽입하고 상기 잭의 스트로크 조절을 컴퓨터와 최종적으로 연동하여 직접제어하면서 구조물을 설치하도록 하기 위한 싱크로나이즈동바리지지시스템(40)이다.       Vertical member 44 is installed at a lower portion of the vertical girder at regular intervals, while the length of the vertical member 44 is increased in the center, while the vertical member 44 is gradually reduced in length. 44), load displacement interlocking and fixing device 60 to be installed in the lower portion of the vertical member 44, and then tension cable 43 to the fixing device 42 installed on both sides of the longitudinal girder (35). While fixing, the tension cable 43 is installed in contact with the load displacement interlocking and fixing device 60 installed in the lower portion of the vertical member 44 so that the parabolic tension cable 43 is installed, and then occurs when concrete is poured. If there is a risk of offsetting and restoring the load and displacement, or the deviation from the design management value through actual measurement and feedback, insert the jack again and install the structure while directly controlling the stroke adjustment of the jack with the computer. A synchronizing Shore support system 40 for recording.

상기와 같은 싱크로나이즈지지시스템(40)의 레이커거더(45), 따장거더(46) 및 종거더(54)에 직각으로 설치된 수직재(44)의 끝단부에 부착된 하중변위연동 및 고정장치(60)에 유압잭(64)을 삽입하고, 그 장치(60) 끝에 접하여 설치된 인장케이블(43)을 반력대로 이용하여 설계에서 요구되는 변위량과 하중을 도입한 상태의 시스템(40)을 설계위치에 설치하고, 이를 상기 거더(45,46,54)상에 작용하는 외부하중에 의한 변위회복(55)과 하중을 상쇄하는 매카니즘을 갖는 것이며, 또한 상기 거더상에는 변위계(54)와 하중계(58)을 설치하여 컴퓨터(48)에 연결시켜 설계관리치를 피드백(49)하여 허용치를 벗어나거나 또는 벗어날 염려가 있을 경우 상호 연동된 유압실린더(50)를 작동하여 유압호스(51)를 통해 전달되어 유압잭(64)의 스트로크를 연동(56)시켜 설계관리치내로 직접조절하도록 변위량을 회복(55)하거나 하중을 상쇄(57)하도록 하여 토압등의 외부하중을 지지하도록 하는 흙막이벽의 레이커거더나 띠장거더 또는 구체콘크리트구조물을 지지하고 동바리에 사용하도록 하는 싱크로나이즈지지시스템(40)에 특징이 있다.        Load displacement interlocking and fixing device 60 attached to the end of the vertical member 44 installed at right angles to the raker girder 45, the column girder 46, and the longitudinal girder 54 of the synchronizer support system 40 as described above. Insert the hydraulic jack (64) into the system, and use the tension cable (43) installed in contact with the end of the device (60) as a reaction force, and install the system (40) in the state where the displacement amount and load required in the design were introduced. It has a mechanism for canceling the load and the displacement recovery 55 caused by the external load acting on the girders (45, 46, 54), and on the girder by installing a displacement meter 54 and a load meter 58 When connected to the (48) and the design management value (49) feedback or if there is a risk of deviation or deviation, the hydraulic cylinder 50 is interlocked to operate through the hydraulic hose 51 is delivered to the stroke of the hydraulic jack (64) Interlock (56) directly into the design management value Synchronized support system for supporting and using raker girder, strip girders, or concrete concrete structures on the wall of walls to support external loads such as earth pressure by restoring displacement (55) or offsetting loads (57). 40).

이하, 본 고안의 구성 및 작용을 첨부된 도면에 의하여 상세히 설명하면 다음과 같다.       Hereinafter, with reference to the accompanying drawings the configuration and operation of the present invention in detail as follows.

도7은 본 고안의 싱크로나이즈지지시스템이 수직파일을 지지하도록 설치된 레이커거더에 설치되어 토압을 지지하도록 흙막이벽을 설치한 것을 보여주는 도면으로서, 토사굴착면에 연하여 일정한 간격으로 수직파일(15)을 설치하고 토사를 수직으로 굴착하면서 발생되는 토압이나 변위를 지지하기 위하여 상기 수직파일(15) 내측에 일정한 간격을 두고 횡으로 띠장(13)을 설치하고, 상기 수직파일(15)의 상부에 설치된 띠장(13)에 레이커거더(45)의 상부와 접하게 설치하면서 일정한 각도를 유지하도록 하여 레이커거더(45)를 경사지게 설치하고, 상기 레이커거더(45)의 하부는 최종 터파기선(16)의 굴착면에 기초(17)를 설치한 후에, 그 위에 설치하도록 하고,       FIG. 7 is a view showing that the synchronizer support system of the present invention is installed on a raker girder installed to support a vertical pile and installs a retaining wall to support earth pressure. The vertical pile 15 is connected to a soil excavation surface at regular intervals. To install and support the earth pressure or displacement generated by excavating the soil vertically to install a strip 13 horizontally at regular intervals inside the vertical pile (15), the strip is installed on top of the vertical pile (15) The raker girder 45 is installed to be inclined while being installed in contact with the upper portion of the raker girder 45 so as to maintain a constant angle, and the lower portion of the raker girder 45 is disposed on the excavation surface of the final trench line 16. After installing the foundation 17, let it be installed there,

상기 레이커거더(45)상에 단계별 굴착에 따라 설치되는 수직파일(15)에 횡으로 설치된 띠장(13)과 직각되는 위치에 수직재(44)를 설치하고, 수직재(44)의 끝단부에 하중변위연동 및       On the raker girder 45, a vertical member 44 is installed at a position perpendicular to the band long 13 installed horizontally on the vertical pile 15 installed by the stepwise excavation, and the load displacement is applied to the end of the vertical member 44. Interlock and

고정장치(60)를 설치하고, 상기 장치(60)에 접하여 인장케이블(43)을 설치하되 레이커거더(45)의 양단부에 설치된 고정장치(42)에 정착한다.The fixing device 60 is installed, and the tension cable 43 is installed in contact with the device 60 and fixed to the fixing device 42 installed at both ends of the raker girder 45.

상기 수직재(44)는 토압과 변위의 크기에 따라 그 길이를 다양하게 변화시켜 설치하는데, 상기 다양한 길이로 설치된 수직재(44)에 접하여 설치된 인장케이블(43)의 설치형상은 모멘트크기와 비례하여 설치하므로 외부하중과 변위를 보다 효율적으로 상쇄 및 회복매카니즘을 갖도록 설치한 싱크로나이즈지지시스템(40)이다.      The vertical member 44 is installed varying the length in accordance with the earth pressure and the size of the displacement, the installation shape of the tension cable 43 installed in contact with the vertical member 44 installed in the various length is installed in proportion to the moment size Therefore, the synchronization support system 40 is installed to have a more effective offset and recovery mechanism of the external load and displacement.

흙막이 수직파일(15)을 중심으로 아이슬랜드 공법으로 중앙부를 절취한 후 1단계 굴착한뒤 설치한 1단 횡띠장(13)과 상기 중앙부절취된 최종굴착면인 터파기선(16)에 설치된 기초(17)에 상기 싱크로나이즈지지시스템(40)을 설치고정한 다음, 2단계로 굴착하여 2단계굴착선(59)을 형성한 다음 설치된 2단띠장(13)과 상기 시스템(40)의 1단 수직재(44)위치와 일치하여 스크류잭(12)이 부착된 하중전달버팀대(41)를 직각으로 설치고정한 다음, 상기 1단의 수직재(44) 끝단부에 설치된 하중변위연동 및 고정장치(60)에 유압잭(64)을 삽입하고, 그 스트로크를 상기 변위 및 하중의 설계관리치와 상기 거더(45) 및 수직재(44)에 부착된 변위계(54)와 하중계(53)의 계측결과를 컴퓨터에 연결시켜 피드백을 통하여 비교하면서 최종적으로 상호연결된 유압잭의 유압실린더를 작동시켜 그 스트로크 크기를 연동시켜 복귀 및 상쇄하도록 하고, 그 스트로크를 연동시킬 때 그에 접하여 설치된 인장케이블(43)을 잭(64)의 반력대 역할을 하면서 상기 케이블에는 인장력이 도입되어 거더에 작용하는 외부하중과 변위를 상쇄 및 회복이 직접 작용하도록 설치 및 지지하는 싱크로나이즈지지시스템이다.      The foundation (17) installed on the first stage horizontal strip (13) and the trench (16), which is the final excavated surface of the central section, are cut after the first stage is excavated and cut in the center part of the soil pile vertical pile (15). And fix the synchronizer support system 40 to the second stage, and excavate in two stages to form a two-stage excavation line 59, and then install the two-stage belt length 13 and the first stage vertical member 44 of the system 40. In accordance with the position, and fixed to the load transmission brace 41 with the screw jack 12 attached to the right angle, the hydraulic jack (64) to the load displacement interlocking and fixing device (60) installed at the end of the vertical member 44 of the first stage. ), And the strokes are connected to the computer by connecting the design management values of the displacements and loads and the measurement results of the displacement gauges 54 and the load gauges 53 attached to the girder 45 and the vertical member 44 to a computer. By comparing the hydraulic cylinders of the hydraulic jacks When the stroke is interlocked, the stroke size is returned and canceled, and when the stroke is interlocked, the tension cable 43, which is in contact with the stroke, serves as a reaction zone for the jack 64, and the cable is introduced with a tensile force to act on the girder. It is a synchronized support system that installs and supports over displacement and displacement directly.

상기 굴착이 3, 4단계등으로 반복시행하면서 상기 시스템을 반복적으로 설치 및 연동시켜 흙막이벽을 지지하도록 한다.       The excavation is repeatedly carried out in three, four, and the like to repeatedly install and interlock the system to support the retaining wall.

도8은 본 고안의 싱크로나이즈지지시스템을 띠장거더에 설치하여 토압을 지지하도록 흙막이벽을 설치한 것을 보여주는 도면으로서, 토사굴착면에 연하여 일정한 간격으로 수직파일(15)을 설치하고 토사를 수직으로 굴착하면서 상기 수직파일(15) 내측에 일정한 간격을 두고 횡으로 띠장거더(46)를 설치한 후에 상기 띠장거더(46)의 상당히 넓은 간격의 양단부에 스크류잭(12)이 부착된 수평버팀대(20)를 설치하여 띠장거더(46)를 지지하도록 한 후에 상기 띠장거더(46)의 양측단부에 고정장치(42)를 설치하고, 일정한 간격을 두고 수직재(44)를 설치하되 상기 수직재(44)의 길이를 중앙부는 길게하면서, 양측에 설치되는 수직재(44)의 길이를 점차 작게한 수직재(44)를 설치하면서 상기 수직재(44)의 일측단부에 하중변위연동 및 고정장치(60)를 설치한 후에 상기 띠장거더(46)의 양측에 설치된 고정장치(42)에 인장케이블(43)을 정착하면서 상기 인장케이블(43)이 상기 수직재(44)의 하부에 설치된 하중변위연동 및 고정장치(60)에 접하게 설치하여 포물선형의 인장케이블(43)이 설치되도록 하여 하중 및 변위크기에따라 하중변위연동 및 고정장치에 유압잭을 삽입설치하고, 상기 잭(64)의 스트로크를 설계관리치와 실제현장계측치 결과를 피드백하여 연동시켜 흙막이벽의 토압을 지지하도록 하여 수평버팀대를 대폭삭감하도록 하는 싱크로나이즈지지시스템(40)이다.       8 is a view showing the installation of the earthen wall to support the earth pressure by installing the synchronizer support system of the present invention to the band girders, the vertical pile 15 is installed at regular intervals in connection with the earth excavation surface and the soil is vertically The horizontal brace 20 is provided with screw jacks 12 attached to both ends of the girder girders 46 at a wider interval after the installation of the girders 46 laterally at regular intervals inside the vertical pile 15 while being excavated. ) To support the strip girders 46, and then, the fixing devices 42 are installed at both ends of the strip girders 46, and the vertical members 44 are installed at regular intervals. After installing the load displacement interlocking and fixing device 60 at one end of the vertical member 44 while installing the vertical member 44 gradually decreasing the length of the vertical member 44 installed on both sides while lengthening the central portion. The girdle The tension cable 43 is installed in contact with the load displacement interlocking and fixing device 60 installed in the lower portion of the vertical member 44 while fixing the tension cable 43 in the fixing device 42 provided on both sides of the girder 46. The parabolic tension cable 43 is installed so that the hydraulic jack is inserted into the load displacement linkage and fixing device according to the load and displacement size, and the stroke of the jack 64 is fed back to the design management value and the actual field measurement result. By interlocking to support the earth pressure of the retaining wall is a synchronized support system 40 to greatly reduce the horizontal brace.

도9는 본 고안의 싱크로나이즈지지시스템을 이용하여 흙막이벽의 레이커거더나 띠장거더 및 동바리용 종거더에 발생되는 하중과 변위를 직접제어하는 과정을 보여주는 도면으로서, 상기 도 7과 8, 10에서와 같이 싱크로나이즈지지시스템(40)의 레이커거더(45), 띠장거더(46) 및 종거더(54)에 직각으로 설치된 수직재(44)의 끝단부에 부착된 하중변위연동 및 고정장치(60)에 유압잭(64)을 삽입하고, 그 장치(60) 끝에 접하여 설치된 인장케이블(43)을 반력대로 이용하고 인장케이블에는 인장력(47)이 도입되어 설계에서 요구되는 변위량과 하중을 도입한 상태의 시스템(40)을 설계위치에 설치하고, 이를 상기 거더(45,46,54)상에 작용하는 외부하중에 의한 변위와 하중을 직접변위회복(55)과 하중을 상쇄하는 매카니즘을 갖는 것이며, 또한 상기 거더상에는 변위계(54)와 하중계(58)을 설치하여 컴퓨터(48)에 연결시켜 설계관리치를 피드백(49)하여 허용치를 벗어나거나 또는 벗어날 염려가 있을 경우 상호 연동된 유압실린더(50)를 작동하여 유압호스(51)를 통해 전달되어 유압잭(64)의 스트로크를 연동(56)시켜 설계관리치내로 직접조절하도록 변위량을 회복(55)하거나 하중을 상쇄(57)하도록 하여 토압등의 외부하중을 지지하도록 하는 흙막이벽의 레이커거더나 띠장거더 또는 구체콘크리트구조물을 지지하고 동바리에 사용하도록 하는 싱크로나이즈지지시스템(40)이다.        9 is a view showing a process of directly controlling the load and displacement generated in the raker girder, belt girders, and vertical girders of the earthen wall using the synchronizer support system of the present invention, as shown in FIGS. The hydraulic jack is connected to the load displacement interlocking and fixing device 60 attached to the end of the vertical member 44 installed at right angles to the raker girder 45, the band girder 46, and the longitudinal girder 54 of the synchronizer support system 40. Insert (64), use the tension cable (43) installed in contact with the end of the device (60) as a reaction force, and the tension cable (47) is introduced into the tension cable to introduce the displacement amount and load required in the design (40). ) Is installed in the design position, and has a mechanism for canceling the displacement and the load caused by the external load acting on the girders 45, 46, 54 and the direct displacement recovery 55 and the load. With displacement meter 54 When the relay 58 is installed and connected to the computer 48 to feed back the design management value 49 to operate the hydraulic cylinder 50 interlocked with each other when there is a risk of deviation or deviation from the allowance, the hydraulic hose 51 is operated. Raker girder of the earthquake wall which is transmitted to interlock 56 of hydraulic jack 64 to recover displacement 55 to adjust directly into design management value or offset load 57 to support external load such as earth pressure. (2) A synchronizer support system (40) for supporting girders or concrete concrete structures and for use in clubs.

도10은 본 고안의 싱크로나이즈지지시스템이 구체슬래브의 하부의 거푸집을 지지하는데 설치되어 구체슬래브에 의해 발생되는 하중과 변위를 제어하는 과정을 보여주는 도면으로서, 콘크리트 구조물의 설치시 작용하는 하중과 변위를 지지할 수 있도록 구조물지지동바리(30)에 적용하도록 한 것으로서, 콘크리트구조물을 설치하기 위한 거푸집(32)의 하부에 설치되어 콘크리트를 타설하면서 발생되는 변위량과 하중을 설계관리치의 캠버량과 하중관계에 연동되어 변위량과 하중을 회복 및 상쇄하면서 콘크리트 구조물을 지지하도록 설치한 구조물지지동바리인 것으로서, 교량의 경우를 예로들어 설명하면, 교각(37)사이의 지반 상에 기초(38)를 설치하고, 그 위에 가설벤트(39)를 설치하고, 상기 가설벤트(39)위에 종거더(35)를 설치한 후에 상기 종거더(35) 위에 일정한 간격을 두고 횡으로 횡빔(36)을 설치한 후에 그 위에 구체슬래브를 형성하기 위한 거푸집(32)을 설치하고,       10 is a view showing a process in which the synchronizer support system of the present invention is installed to support the formwork in the lower part of the concrete slab to control the load and displacement generated by the concrete slab. It is to be applied to the structure support bar (30) so that it can be supported, it is installed in the lower part of the formwork 32 for installing the concrete structure, the displacement amount and load generated while placing concrete to the camber amount and load relationship of the design management value It is a structure support bar which is interlocked and installed to support a concrete structure while restoring and canceling displacement and load. For example, in the case of a bridge, a base 38 is installed on the ground between the piers 37. After installing the temporary vent 39, the vertical girder 35 is installed on the temporary vent 39, the vertical girder 35 At regular intervals to install the mold 32, for forming a concrete slab thereon after installing a hoengbim 36 in the transverse and,

상기 종거더(35)의 하부에 일정한 간격을 두고 수직재(44)를 설치하되, 상기 수직재(44)의 길이를 중앙부는 길게하면서, 양측에 설치되는 수직재(44)의 길이를 점차 작게한 수직재(44)를 설치하고, 상기 수직재(44)의 하부에 하중변위연동 및 고정장치(60)를 설치하도록 한 후에 상기 종거더(35)의 양측에 설치된 고정장치(42)에 인장케이블(43)을 정착하면서 상기 인장케이블(43)이 상기 수직재(44)의 하부에 설치된 하중변위연동 및 고정장치(60)에 접하게 설치하여 포물선형의 인장케이블(43)이 설치되도록 한 후에 상기 도에서 서술된 회복 및 상쇄 매카니즘에 의해 조절하면서 콘크리트를 타설하여 구조물을 설치하도록 하기 위한 싱크로나이즈지지시스템(40)이다.      Vertical member 44 is installed at a lower portion of the vertical girder at regular intervals, while the length of the vertical member 44 is increased in the center, while the vertical member 44 is gradually reduced in length. 44), load displacement interlocking and fixing device 60 to be installed in the lower portion of the vertical member 44, and then tension cable 43 to the fixing device 42 installed on both sides of the longitudinal girder (35). After fixing, the tension cable 43 is installed in contact with the load displacement interlocking and fixing device 60 installed below the vertical member 44 so that the parabolic tension cable 43 is installed. And a synchronizer support system 40 for installing concrete by pouring concrete while adjusting by an offset mechanism.

도11은 본 고안의 싱크로나이즈지지시스템의 수직재의 하부에 설치되는 하중변위연동 및 고정장치에 인장케이블이 설치된 상태를 보여주는 도면으로서, 레이커거더(45) 및 띠장거더(46) 또는 종거더(35)의 하부에 각각의 길이로 일정한 간격을 두고 설치된 수직재(44)의 하부에 하중변위연동 및 고정장치(60)를 설치하고, 상기 장치(60)와 접하여 인장케이블(43)을 설치하도록 하여 설계관리치내로 잭의 스트로크를 연동(56)시키면 상기 인장케이블에 인장력이 발생하면서 반력대 역할을 하여 상기 수직재에 회복변위(55)와 상기 수직재(44) 내부에 내부반력(57)이 발생되어 이러한 내부반력과 회복변위량이 띠장거더(46) 또는 종거더(35)에 전달되어 일정량의 변위가 발생된 상기 띠장거더 또는 종거더의 변위를 일정량의 변위회복량만큼 상쇄시켜 띠장거더 또는 종거더와 토압이 평형을 이루도록 하여 전체적으로 안정성을 유지하도록 한 것이다.        11 is a view showing a state in which the tension cable is installed in the load displacement interlocking and fixing device installed in the lower portion of the vertical member of the synchronizer support system of the present invention, the raker girder 45 and the strip girders 46 or longitudinal girder 35 Designed by installing the load displacement interlocking and fixing device (60) in the lower portion of the vertical member 44 installed at regular intervals at each length in the lower portion of the, and the tension cable (43) in contact with the device (60) Interlocking 56 of the jack's stroke into the tooth acts as a reaction zone while generating tension in the tension cable, thereby causing a recovery displacement 55 in the vertical member and an internal reaction 57 in the vertical member 44. The reaction force and recovery displacement are transmitted to the girders girder 46 or the longitudinal girders 35 to offset the displacements of the girders or longitudinal girders where a certain amount of displacement is generated by a certain amount of displacement recovery amount. By the girder and the soil pressure will be allowed to equilibrate to a whole remains stable.

도12는 본 고안의 싱크로나이즈지지시스템의 하중변위연동 및 고정장치를 보여주는 도면으로서, 수직재의 하부에 견고하게 하중변위연동 및 고정장치(60)를 고정연결시키기 위하여 스티프너(61)와 잭하부지지판(62)을 연결시키고, 상기 수직재(44)에 스티프너(61)를 연결고정시키도록 하고, 상기 잭하부지지판(62)의 하부에 잭(64)을 설치할 수 있는 공간을 확보하기 위하여 일정한 간격을 두고 잭상부지지판(65)을 설치하되, 상기 잭 상하부지지판(62,65)의 모서리부를 고장력볼트(63)와 스프링와샤너트(67)로 상호 연결하고, 상기 잭상부지지판(65)의 하부에 인장케이블(43)을 안내할 수 있는 인장케이블가이드판(66)을 양측에 설치하면서 상기 인장케이블가이드판(66)의 사이에 인장케이블(43)을 설치할 때 인장케이블을 밀착접촉되도록 중앙부가 볼록하게 곡률면이 되도록 상기 잭상부지지판(65)을 설치하여 잭(64)을 삽입 및 배제할 수 있으며 설계관리치 만큼 변위스트로크(56)을 작동시킨 후 고장력볼트(63)와 스프링와샤너트(67)로 고정하므로서 하중변위연동 및 고정장치를 설치하는 것이다.       12 is a view showing load displacement interlocking and fixing device of the synchronizer support system of the present invention, in which the stiffener 61 and the lower jack support plate (for fixing the load displacement interlocking and fixing device 60 firmly to the lower part of the vertical member) 62) to connect and fix the stiffener 61 to the vertical member 44, and at regular intervals to secure a space for installing the jack 64 in the lower portion of the lower jack support plate 62 The upper jack support plate 65 is installed, and the edges of the upper and lower support plates 62 and 65 are interconnected with the high tension bolt 63 and the spring and the nut 67, and the lower upper support plate 65 is tensioned. When the tension cable 43 is installed between the tension cable guide plate 66 while the tension cable guide plate 66 capable of guiding the cable 43 is installed, the center portion is convex so as to be in close contact with the tension cable. The curvature plane The jack upper support plate 65 may be installed so that the jack 64 can be inserted and removed, and the displacement stroke 56 is operated as much as the design management value, and then fixed by the high tension bolt 63 and the spring and the shoulder nut 67. It is to install load displacement interlock and fixing device.

도13은 본 고안의 하중변위연동 및 고정장치의 잭하부지지판의 유압잭을 고정하는 방법을 보여주는 도면으로서, 잭 상하부지지판(62,65)을 고장력볼트(63)로 설치하여 유압잭설치공간을 조성한 다음, 유압잭을 중앙에 삽입한 다음 잭의 양측으로 설치된 스티프너(61) 중앙에 볼트와 스프링와샤너트(63,67)을 조여 고정시키도록 하는 것이다.       Figure 13 is a view showing a method of fixing the hydraulic jack of the jack lower support plate of the load displacement interlocking and fixing device of the present invention, the jack upper and lower support plates (62, 65) by installing a high-tension bolt 63 to create a hydraulic jack installation space , Insert the hydraulic jack in the center and then tighten the bolt and the spring and the nut (63, 67) in the center of the stiffener (61) installed on both sides of the jack to be fixed.

도14는 본 고안의 하중변위연동 및 고정장치의 잭하부지지판을 보여주는 도면으로서, 도 12에서 이미 설명한바와 같이 잭 상, 하부지지판(62,65)을 고장력볼트(63)로 상호 연결하여 수직재(44)에 연결설치한 다음 상기 잭하부지지판(65)의 하부에 인장케이블(43)을 안내할 수 있는 인장케이블가이드판(66)을 양측에 설치하면서 양측에 설치된 상기 인장케이블가이드판(66)의 사이에 인장케이블(43)을 설치할 때 인장케이블을 보다 강하게 밀착접촉되도록 중앙부가 볼록한 곡률면이 되도록 상기 잭하부지지판(65)을 설치한다.       14 is a view showing the lower jack support plate of the load displacement interlocking and fixing device of the present invention, as described above in Figure 12, the jack upper, lower support plates 62, 65 are interconnected with a high-tensile bolt 63 to the vertical material ( 44 and the tension cable guide plate 66 installed at both sides while installing the tension cable guide plate 66 capable of guiding the tension cable 43 at the lower portion of the lower jack support plate 65. When the tension cable 43 is installed between the jack lower support plate 65 is installed so that the center surface is convex curvature so that the tension cable more tightly contact.

도15는 도14의 단면 A-A를 보여주는 도면으로서, 잭하부지지판(65)의 하부에 인장케이블(43)을 안내할 수 있도록 강판으로 개복박스형태로 부착설치한 다음 상기 박스내에 인장케이블을 설치하도록 한다.        Figure 15 is a view showing a cross-sectional AA of Figure 14, to be installed in the form of a open box with a steel plate so as to guide the tension cable 43 to the lower portion of the lower jack support plate 65 to install the tension cable in the box do.

도16은 본 고안의 싱크로나이즈지지시스템의 띠장을 설치하기 위하여 편기된 수직파일에 하중분산쐐기받침판을 설치하여 띠장이 수평으로 설치되게 한 것을 보여주는 도면으로서, 토사굴착면이 일직선이 아닌 경우에는 토사굴착면을 따라 설치되는 수직파일(15)이 일정한 각도로 편기되어 설치되어 있으므로 상기 편기된 수직파일의 측면에 일정한 간격을 두고 상기 수직파일의 길이방향으로 설치되는 띠장(13,46)은 향후에 설치되는 수직재(44)가 반드시 띠장(13,46)에 직각으로 설치되어야 상기 수직재의 하부에 설치된 하중변위연동 및 고정장치(60)의 변위연동 조절에 의해 외부하중에 의한 변위와 하중을 관리하게되므로 일정한 각도로 편기된 상기 수직파일(15)과 띠장(13,46)사이에 편기된 각도에 의하여 간격이 형성되면 상기 시스템의 변위회복과 하중상쇄가 직접전달이 않되므로 이렇게 형성된 간격내에 하중분산쐐받침판(70)을 설치하여 편기된 각도를 보상해주도록 하여 편기된 수직파일에 직각으로 띠장이 설치되고 상기 띠장에 수직재가 자동적으로 수직설치되도록 하기 위함이다.       Fig. 16 is a view showing that the bands are horizontally installed by installing a load-distributing wedge support plate on a vertical pile arranged to install the bands of the synchronizer support system of the present invention, and the soil excavation surface is not a straight line. Since the vertical pile 15 installed along the surface is knitted and installed at a predetermined angle, the bands 13 and 46 installed in the longitudinal direction of the vertical pile at regular intervals on the side of the knitted vertical pile are installed in the future. Since the vertical member 44 must be installed at right angles to the bands 13 and 46 to manage the displacement and the load due to the external load by adjusting the load displacement interlocking and the displacement interlocking of the fixing device 60 installed at the lower portion of the vertical member. When the gap is formed between the vertical pile 15 and the bands 13 and 46 knitted at a predetermined angle, the displacement recovery and the lower Since the offset is not directly transmitted, the load distribution wedge plate 70 is installed within the gap thus compensated for the biased angle so that the belt is installed at right angles to the knitted vertical pile and the vertical material is automatically installed vertically on the band. To do this.

상기 하중분산쐐기받침판(70)은 하중흡수분산에 효율적인 침목(72)과 지압에 변형이 않되도록 철판(71)으로 구성된 다각형의 일정한 두께를 갖는 것으로서, 도면에서보는바와 편기된 수직파일에 띠장이 직각으로 설치될 때 수직파일과 띠장에 일정한 간격이 형성되는데 상기 간격에 상기 하중분산쐐받침판을 끼워 띠장에 설치된 수직재에 설치된 하중변위연동 및 고정장치에 의해 직접하중 상쇄 및 변위회복량이 도입될때에도 아무런 구조적인 영향없이 상기 매카니즘이 수직재를 통하여 거더에 직접 전달될 수 있도록 하기 위함이다.      The load-distributing wedge support plate 70 has a constant thickness of a polygon composed of a sleeper 72 and the iron plate 71 so as not to be deformed to the pressure of the load absorbing dispersion, as shown in the drawing and banded in the vertical pile When installed at right angles, a certain distance is formed between the vertical pile and the band, and the load-distributing interlock and fixing device installed on the vertical member installed on the band by inserting the load-distributing wedge plate in the gap does not cause any direct load offset and displacement recovery. This is to allow the mechanism to be directly transmitted to the girder through the vertical material without structural influence.

본 고안은 지하구조물을 설치하기 위하여 굴착공사를 할때 토사가 붕괴되는 것을 방지하기 위하여 흙막이벽으로 활용하여 토압이나 수압에 의하여 발생되는 응력과 변위를 설계관리치와 연동하여 컴퓨터에 미리 입력된 프로그램에 의하여 자동으로 변위량과 외부하중을 도입하여 현장에 설치하고, 기설치된 거더에 작용하는 외력에 의한 변위와 하중을 상쇄시키고 또한 현장계측치와 피드백에 의해 상호연동시켜 재차 내부하중과 변위를 조절하면서 토압을 지지하도록 하거나 또는 콘크리트구조물의 설치를 위한 거푸집의 하부에 설치되어 콘크리트를 타설하면서 발생되는 응력과 변위를 설계관리치와 연동하여 컴퓨터에 미리 입력된 프로그램에 의하여 자동으로 변위량과 내부하중을 도입하여 현장에 설치하고, 이 설치된 거더에 작용하는 외력에 의한 변위와 하중을 상쇄시키면서, 또한 현장계측치와 피드백에 의해 상호연동시켜 재차 내부하중과 변위를 조절하면서 콘크리트 구조물을 지지하도록 하기 위한 흙막이벽 및 구조물지지동바리용 싱크로나이즈지지시스템에 관한 것으로서,        This design utilizes the earthen wall to prevent the earth and sand from collapsing during the excavation work to install the underground structure. Automatically introduces displacement and external load to install on site, offsets displacement and load caused by external force acting on existing girder, and interlocks by on-site measurement and feedback to adjust internal load and displacement again. It is installed in the lower part of the formwork for supporting the concrete structure, or the stress and displacement generated when placing concrete, in conjunction with the design management value, automatically introduces the displacement and internal load by the program pre-inputted on the computer. Installed on site, and the external force acting on this installed girder It is related to a retaining wall and a synchronized support system for a structural support bar, to offset the displacement and the load caused by the load, and to support the concrete structure by mutually interlocking by on-site measurement and feedback.

레이커버팀대를 이용하여 다단계로 굴착을 할수 있도록 적용깊이를 확대 할 수 있고, 버팀대수를 대폭절감하므로서 공간 활용을 극대화할 수 있는 등 효율성을 극대화하면서 공기단축과 자재절감을 통한 공사비의 절감으로 인한 경제성 제고를 함과 동시에 띠장과 버팀대로 지지하던 종래의 방식에도 적용할 수 있도록 하므로서 본 고안의 시스템의 호환성을 제고하도록 하고, 강재사용을 최소화하여 경제성을 높힘과 동시에 작업 공간을 확보하여 공기를 단축할 수 있도록 하면서 단계별 굴착이나 되메우기에 따른 하중 변화에 피드백하고 콘트롤하면서 하중변화에 따른 변위에 적절하게 대응 할 수 있도록 하여 보다 안정적으로 공사시공이 성역화하여 진행될 수 있도록 하는 경제적이면서, 시스템의 효율성을 증대시킴과 동시에 종래의 방법에도 적용할 수 있도록 호환성을 갖도록 한 매우 적용성이 넓은 유용한 시스템의 시공방법인 것이다.       It is possible to increase the depth of application for excavation in multiple stages using the lay cover team, maximize the space utilization by greatly reducing the number of props, and maximize the efficiency while reducing the construction cost by reducing the air and materials. In addition to improving the compatibility of the system of the present invention by improving the compatibility of the system of the present invention, while also being able to be applied to the conventional method that was supported by the belt and braces, it is possible to reduce the air by minimizing the use of steel to increase the economy and at the same time to secure the working space It is possible to feed back and control the load change due to the excavation or backfilling step by step, and to respond to the displacement according to the load change appropriately, thereby increasing the efficiency and economic efficiency of the construction work. At the same time, the conventional method It is a method of constructing a very useful and useful system that is compatible to use.

도1은 종래기술로서 레이커스트러트를 1단으로 설치하여 토압을 지지하도록 한 흙막이벽을 보여주는 도면.       1 is a view showing the retaining wall to support the earth pressure by installing a raker strut in one stage in the prior art.

도2는 종래기술인 띠장과 수평버팀대와 중간파일로 이루어진 흙막이벽을 보여주는 도면.       Figure 2 is a view showing the retaining wall made of a prior art belt and the horizontal brace and the intermediate pile.

도3은 종래기술인 버팀대와 띠장으로 이뤄진 흙막이벽의 띠장에 프리스트레스 압축력이 도입된 수평PS 강선이 설치된 보강띠장을 부착하여 보강한 것을 보여주는 도면.       Figure 3 is a view showing that the reinforcing strips attached to the reinforcement bands installed with a horizontal PS steel wire introduced pre-stressing force to the strip of the earth wall made of a brace and the strip of the prior art.

도4는 종래기술로서 버팀대와 띠장으로 이루어진 흙막이벽의 띠장에 다수개의 간격재와 이 간격재에 프리스트레스 압축력이 도입된 PS 강선을 설치한 보강띠장을 설치하여 보강한 것을 보여주는 도면.       Figure 4 is a view showing the reinforcement by installing a reinforcement belt installed with a plurality of spacers and the PS steel wire introduced prestressing compressive force to the spacer of the earth wall made of a brace and the band as a prior art.

도5는 종래기술로서 구체콘크리트를 전체강관지주로 지지하도록 한 것을 보여주는 도면.       5 is a view showing that to support the concrete concrete as a whole steel pipe column in the prior art.

도6은 종래기술로서 교각 기초위에 가설벨트를 설치하고 그 위에 설치되는 구체슬래브를 지지하도록 설치한 것을 보여주는 도면.       Figure 6 is a view showing that the installation to support the concrete slab is installed on the installation of the temporary belt on the piling foundation in the prior art.

도7은 본 고안의 싱크로나이즈레이커거더지지시스템이 수직파일과 띠장을 지지하여 토압에 의한 반력과 변위를 상쇄회복하도록 흙막이벽을 설치한 것을 보여주는 도면.       7 is a view showing that the synchronizer raker girder support system of the present invention supports the vertical pile and the band to install the retaining wall to offset the reaction force and displacement caused by earth pressure.

도8은 본 고안의 싱크로나이즈지지시스템을 띠장거더에 설치하여 토압에 의한 반력과 변위를 상쇄하도록 흙막이벽을 설치한 것을 보여주는 도면.       8 is a view showing the installation of the retaining wall to offset the reaction force and displacement caused by earth pressure by installing the synchronizer support system of the present invention to the band girders.

도9는 본 고안의 싱크로나이즈지지시스템이 흙막이벽의 토압에 의한 반력과 변위를 상쇄하는 것을 자동으로 연동조절하는 과정을 보여주는 도면.       9 is a view showing a process for automatically adjusting the synchronizing support system of the present invention to offset the reaction force and displacement caused by the earth pressure of the earth wall.

도10은 본 고안의 싱크로나이즈지지시스템이 구체슬래브의 하부에 설치되어 구체콘크리트슬래브에 발생되는 반력과 변위를 상쇄회복제어하는 과정을 보여주는 도면.       10 is a view illustrating a process of canceling control of reaction force and displacement generated in a concrete concrete slab by installing a synchronizer support system of the present invention in a lower portion of a concrete slab;

도11은 본 고안의 싱크로나이즈지지시스템의 수직재의 하부에 설치되는 하중변위연동 및 고정장치에 인장케이블이 설치된 상태를 보여주는 도면.       Figure 11 is a view showing a state in which the tension cable is installed in the load displacement interlocking and fixing device installed on the lower portion of the vertical member of the synchronizer support system of the present invention.

도12는 본 고안의 싱크로나이즈지지시스템의 하중변위연동 및 고정장치의 설치, 변위연동, 고정장치를 보여주는 도면.       Figure 12 is a view showing the load displacement interlocking and the installation, displacement interlocking, fixing device of the synchronized support system of the present invention.

도13은 본 고안의 하중변위연동 및 고정장치의 잭하부지지판을 보여주는 도면.       Figure 13 is a view showing the lower jack support plate of the load displacement linkage and fixing device of the present invention.

도14는 본 고안의 하중변위연동 및 고정장치의 잭상부지지판을 보여주는 도면.       14 is a view showing a jack upper support plate of the load displacement interlocking and fixing device of the present invention.

도15는 도14의 단면 A-A를 보여주는 도면.       Fig. 15 shows a cross section A-A of Fig. 14;

도16은 본 고안의 싱크로나이즈지지시스템을 띠장에 설치하기 위하여 편기된 수직파일에 하중분산쐐기받침판을 설치하여 띠장이 수평으로 설치되게 한 것을 보여주는 도면.      Figure 16 is a view showing that the belt length is installed horizontally by installing a load-distributing wedge support plate on the vertical pile knitted in order to install the synchronizer support system of the present invention.

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

10 : 흙막이벽 11 : 레이커스트러트        10: retaining wall 11: Raker Strut

12 : 스크류잭 13 : 띠장        12: screw jack 13: strip

14 : 토사 15 : 수직파일        14: earth and sand 15: vertical pile

16 : 터파기선 17 : 레이커지지기초        16: breaker ship 17: raker support base

18 : 브레이싱 19 : 중간파일        18 bracing 19: intermediate file

20 : 수평버팀대 21 : 긴장정착장치        20: horizontal brace 21: tension fixing device

22 : PS 강선 23 : 보강띠장        22: PS steel wire 23: reinforcing band

24 : 간격재 25 : 압축프리스트레스힘         24: Spacer 25: Compression Free Stress

30 : 구조물지지동바리 31 : 구체콘크리트        30: structure supporting bridge 31: concrete concrete

32 : 거푸집 33 : 강관지주        32: formwork 33: steel pipe holder

35 : 종거더        35: bell girder

36 : 횡빔 37 : 교각        36 side beams 37 pier

38 : 기초 39 : 가설벤트        38: foundation 39: hypothesis

40 : 싱크로나이즈지지시스템 41 : 하중전달버팀대        40: synchronized support system 41: load transfer brace

42 : 고정장치 43 : 인장케이블        42: fixing device 43: tension cable

44 : 수직재 45 : 레이커거더        44: vertical 45: raker girder

46 : 띠장거더 47 : 인장력        46: strip girders 47: tensile force

48 : 컴퓨터 49 : 피드백        48: Computer 49: Feedback

50 : 유압실린더 51 : 유압호스        50: hydraulic cylinder 51: hydraulic hose

53 : 하중계        53: load meter

54 : 변위계 55 : 변위회복량        54: displacement meter 55: displacement recovery amount

56 : 연동변위량 57 : 내부반력        56: interlock displacement 57: internal reaction

58 : 아이슬랜드공법 59 : 단계별굴착선        58: Iceland Method 59: Drilling Steps

60 : 하중변위연동 및 고정장치 61 : 스티프너        60: load displacement interlocking and fixing device 61: stiffener

62 : 잭하부지지판 63 : 고장력볼트        62: jack lower support plate 63: high tension bolt

64 : 잭 65 : 잭상부지지판        64: jack 65: jack upper support plate

66 : 인장케이블가이드판 67 : 스프링와샤너트        66: tension cable guide plate 67: spring and nut

70 : 하중분산쐐기받침판 71 : 보강철판        70: load distribution wedge support plate 71: reinforcing steel plate

72 : 하중분산받침목        72: load distribution support

Claims (8)

토사굴착면에 연하여 일정한 간격으로 수직파일을 설치하고 토사를 수직으로 굴착하면서 발생되는 토압이나 변위를 지지하기 위하여 상기 수직파일의 내측에 일정한 간격을 두고 횡으로 설치된 띠장과,        A band installed horizontally at regular intervals on the inner side of the vertical pile to support the earth pressure or displacement generated by installing vertical piles at regular intervals in connection with the earth excavation surface, and excavating the soil vertically; 상기 수직파일의 상부에 설치된 띠장에 레이커거더의 상부와 접하게 설치하면서 일정한 각도를 유지하도록 하여 경사지게 설치된 레이커거더와,        A raker girder inclined to maintain a constant angle while being installed to be in contact with the upper portion of the raker girder on a belt installed at the upper portion of the vertical pile; 상기 레이커거더의 하부는 최종터파기선의 굴착면에 설치된 기초 위에 설치하고,       The lower part of the raker girder is installed on the foundation installed on the excavation surface of the final breaker ship, 상기 레이커거더(45)상에는 단계별 굴착에 따라 설치되는 수직파일(15)에 횡으로 설치된 띠장(13)과 직각되는 위치에 설치된 수직재로서, 상기 수직재의 길이는 토압의 크기와 비례하여 증가 또는 감소하게 수직재를 설치하고,        On the raker girder 45 is a vertical member installed at a position perpendicular to the band 13 is installed horizontally on the vertical pile (15) installed by the stepwise excavation, the length of the vertical member to increase or decrease in proportion to the size of the earth pressure Install vertical materials, 상기 수직재(44)의 끝단부에 설치된 하중변위연동 및 고정장치(60)와,        Load displacement interlocking and fixing device (60) installed at the end of the vertical member (44), 상기 장치(60)에 접하여 인장케이블(43)을 설치하면서 레이커거더의 양단부에 설치된 고정장치(42)에 상기 인장케이블을 정착하고,       Fixing the tension cable in the fixing device 42 provided on both ends of the raker girder while installing the tension cable 43 in contact with the device 60, 상기 수직파일(15)을 중심으로 아이슬랜드 공법으로 1단계, 2단계등 다단계로 굴착하면서 각각 횡띠장(13)을 설치하면서, 단계적으로 상기 횡띠장과 상기 거더에 설치된 수직재와 직각으로 스크류잭(12)이 부착된 하중전달버팀대를 힌지연결하고,        The jack jack 12 is installed at right angles with the vertical strips installed in the horizontal strips and the girder step by step while installing the horizontal strips 13 while excavating in multiple stages such as the first step and the second step by the Icelandic method around the vertical piles 15. Hinged load transfer brace with) 상기 수직재(44) 끝단부에 설치된 하중변위연동 및 고정장치(60)에 유압잭(64)을 삽입하고, 상기 잭의 스트로크를 변위 및 하중 설계관리치와 상기 거더(45) 및 수직재(44)에 부착된 변위계(54)와 하중계(53)의 계측결과를 컴퓨터에 연동시켜 직접복귀 및 상쇄하도록 하고, 상기 유압잭의 스트로크를 인장케이블(43)에 연동시킬 때 잭(64)은 반력대 역할을 하면서 인장력이 작용하도록 하여 흙막이벽을 지지하도록 하는 것에 특징이 있는 작용하중에 따라 발생되는 변위와 반력을 직접회복 및 상쇄하도록 제어하는 자동싱크로나이즈지지시스템.       The hydraulic jack 64 is inserted into the load displacement interlocking and fixing device 60 installed at the end of the vertical member 44, and the stroke of the jack is inserted into the displacement and load design management value and the girder 45 and the vertical member 44. The measurement results of the attached displacement gauge 54 and the load gauge 53 are interlocked with a computer to directly return and cancel. The jack 64 acts as a reaction force when the stroke of the hydraulic jack is interlocked with the tension cable 43. An automatic synchronization support system that directly controls and offsets displacements and reaction forces generated by an action load, characterized by supporting tension walls to support the retaining walls. 토사굴착면에 연하여 일정한 간격으로 수직파일(15)을 설치하고 토사를 수직으로 굴착하면서 상기 수직파일(15) 내측에 일정한 간격을 두고 횡으로 띠장거더(46)를 설치한 후에 상기 띠장거더(46)의 양단부에 스크류잭(12)이 부착된 수평버팀대(20)를 설치하여 띠장거더(46)를 지지하도록 하고,       After installing the vertical pile 15 at regular intervals in connection with the earth excavation surface and excavating the earth and sand vertically, after installing the girders 46 horizontally at regular intervals inside the vertical pile 15, the band girders ( 46 is installed on both ends of the screw jack 12 is attached to the horizontal brace 20 to support the band girders 46, 상기 띠장거더(46)의 양측단부에 설치된 고정장치(42)와, 일정한 간격을 두고 수직재(44)를 설치하되 상기 수직재(44)의 길이를 중앙부는 길게하면서, 양측에 설치되는 수직재(44)의 길이를 점차 작게한 수직재(44)를 설치하고,       The vertical device 44 is installed on both sides of the strip girders 46 and the vertical member 44 is installed at regular intervals, and the vertical member 44 is installed on both sides while the length of the vertical member 44 is extended to the center portion. Install the vertical member 44, the length of which is gradually reduced, 상기 수직재(44)의 일측단부에 설치된 하중변위연동 및 고정장치(60)와,       A load displacement interlocking and fixing device (60) installed at one end of the vertical member (44), 상기 띠장거더(46)의 양측에 설치된 고정장치(42)에 인장케이블(43)을 정착하면서 상기 인장케이블(43)이 상기 수직재(44)의 하부에 설치된 하중변위연동 및 고정장치(60)에 접하게 설치하고,        While the tension cable 43 is fixed to the fixing device 42 installed on both sides of the strip girders 46, the tension cable 43 is connected to the load displacement interlocking and fixing device 60 installed at the lower portion of the vertical member 44. Install it, 상기 하중변위연동 및 고정장치에 설치된 유압잭의 스트로크를 설계관리치와 실제현장계측치 결과를 컴퓨터에 입력시켜 피드백하여 연동시켜 흙막이벽의 토압을 지지하도록 하는 것에 특징이 있는 작용하중에 따라 발생되는 변위와 반력을 직접회복 및 상쇄하도록 제어하는 자동싱크로나이즈지지시스템.       The displacement generated according to the working load characterized in that the stroke of the hydraulic jack installed in the load displacement interlocking device and the fixing device is connected to the computer by feeding the design management value and the actual field measurement result to the feedback to support the earth pressure of the retaining wall. Automatic synchronization support system that controls direct recovery and offset. 교각(37)사이의 지반 상에 기초(38)를 설치하고, 그 위에 가설벤트(39)를 설치하고,        A foundation 38 is installed on the ground between the piers 37, and a temporary vent 39 is installed thereon. 상기 가설벤트(39)위에 종거더(35)를 설치한 후에 상기 종거더(35) 위에 일정한 간격을 두고 횡으로 설치된 횡빔(36)과, 상기 횡빔 위에 구체슬래브를 형성하기 위하여 설치된 거푸집(32)과,       After installing the vertical girders 35 on the temporary vents 39, the horizontal beams 36 horizontally installed at regular intervals on the vertical girders 35, and the formwork 32 installed to form a concrete slab on the horizontal beams. and, 상기 종거더(35)의 하부에 일정한 간격을 두고 수직재(44)를 설치하되, 상기 수직재(44)의 길이를 중앙부는 길게하면서, 양측에 설치되는 수직재(44)의 길이를 점차 작게한 수직재(44)를 설치하고,        Vertical member 44 is installed at a lower portion of the vertical girder at regular intervals, while the length of the vertical member 44 is increased in the center, while the vertical member 44 is gradually reduced in length. 44) install 상기 수직재(44)의 하부에 설치된 하중변위연동 및 고정장치(60)와,       Load displacement interlocking and fixing device 60 is installed in the lower portion of the vertical member 44, 상기 종거더(35)의 양측에 설치된 고정장치(42)에 인장케이블(43)을 정착하면서 상기 인장케이블(43)이 상기 수직재(44)의 하부에 설치된 하중변위연동 및 고정장치(60)에 접하게 설치하고,        While the tension cable 43 is fixed to the fixing device 42 installed on both sides of the vertical girder 35, the tension cable 43 is connected to the load displacement interlocking and fixing device 60 installed at the lower portion of the vertical member 44. Install it, 상기 종거더에 설치된 하중계와 변위계등의 계측값을 컴퓨터에 연동시켜 계측치, 설계관리치등과 피드백을 통해 자동으로 유압실린더시스템을 작동하여 하중과 변위제어를 하도록 하면서, 상기 거푸집에 콘크리트를 타설하여 교량등의 구체콘크리트 구조물을 설치하도록 하는 것에 특징이 있는 작용하중에 따라 발생되는 변위와 반력을 직접회복 및 상쇄하도록 제어하는 자동싱크로나이즈지지시스템.       Placing concrete on the formwork while controlling the load and displacement by operating the hydraulic cylinder system automatically through the measured values, design management values, and feedback by interlocking the measured values such as the load gauge and the displacement meter installed on the vertical girder with a computer. An automatic synchronization support system that controls the direct recovery and offset of displacements and reaction forces generated by a working load characterized by installing concrete concrete structures such as bridges. 제 1항 내지 제3항중의 어느 한항에 있어서,       The method according to any one of claims 1 to 3, 상기 싱크로나이즈지지시스템을 컴퓨터에 연동시켜 하중변위 제어를 하는 것은 레이커거더(45), 따장거더(46) 및 종거더(54)에 직각으로 설치된 수직재(44)의 끝단부에 부착된 하중변위연동 및 고정장치(60)에 유압잭(64)을 삽입하고, 그 장치(60) 끝에 접하여 설치된 인장케이블(43)을 반력대로 이용하여 설계에서 요구되는 변위량과 하중을 잭의 스트로크를 조절하여 내부하중과 변위를 미리 도입한 상태의 시스템(40)을 설계위치에 설치하고, 이를 상기 거더(45,46,54)상에 작용하는 외부하중에 의한 변위회복(55)과 하중을 상쇄하는 매카니즘을 갖도록 하며, 상기 거더상에는 변위계(54)와 하중계(58)을 설치하여 컴퓨터(48)에 연결시켜 설계관리치를 피드백(49)하여 허용치를 벗어나거나 또는 벗어날 염려가 있을 경우 상호 연동된 유압실린더(50)를 작동하여 유압호스(51)를 통해 전달되어 유압잭(64)의 스트로크를 재차 연동(56)시켜 설계관리치내로 조절하도록 변위량을 회복(55)하거나 하중을 상쇄(57)하도록 하여 토압등의 외부하중을 지지하도록 하는 것에 특징이 있는 작용하중에 따라 발생되는 변위와 반력을 직접회복 및 상쇄하도록 제어하는 자동싱크로나이즈지지시스템.       Controlling the load displacement by interlocking the synchronizer support system with a computer includes load displacement interlocking attached to the end of the vertical member 44 installed at right angles to the raker girder 45, the column girder 46, and the longitudinal girder 54. Insert the hydraulic jack 64 into the fixing device 60, and use the tension cable 43 installed in contact with the end of the device 60 as a reaction force to adjust the stroke of the jack and the internal load and displacement by adjusting the stroke of the jack. Is installed in the design position, and has a mechanism for canceling the load and displacement recovery 55 by the external load acting on the girders (45, 46, 54), On the girder, a displacement gauge 54 and a load gauge 58 are installed and connected to the computer 48 to feed back the design management value 49 to operate the hydraulic cylinders 50 interlocked when there is a risk of deviation or deviation from the allowable value. Hydraulic arc It is transmitted through the switch 51 so that the stroke of the hydraulic jack 64 is interlocked (56) again to recover the displacement amount (55) or offset the load (57) to adjust the design management value so as to support external load such as earth pressure. Automatic synchronization support system that controls to directly recover and offset the displacement and reaction forces generated by the working load characterized by. 제 1항내지 제3항중의 어느 한 항에 있어서,       The method according to any one of claims 1 to 3, 상기 싱크로나이즈지지시스템의 내부하중과 변위는 하중변위연동 및 고정장치에 유압잭을 삽입하고, 상기 잭의 스트로크를 상하로 연동하여 도입시키고, 상기 내부하중과 변위의 도입된 상태를 보존하기 위하여 고장력볼트와 스프링와샤너트로 고정시키며, 상기 내부하중과 변위의 도입시 인장케이블이 반력대 역할을 하여 인장력이 도입되도록 하여 외부하중과 변위를 상쇄하는 것에 특징이 있는 작용하중에 따라 발생되는 변위와 반력을 직접회복 및 상쇄하도록 제어하는 자동싱크로나이즈지지시스템.       The internal load and the displacement of the synchronizer support system are inserted into the hydraulic jack into the load displacement linkage and the fixing device, and the stroke of the jack is interlocked up and down to introduce the high tension bolt and the high tension bolt to preserve the introduced state of the internal load and the displacement. It is fixed with spring and shant, and the tension cable acts as a reaction band when the internal load and the displacement are introduced so that the tensile force is introduced to offset the external load and the displacement. Automatic synchronization support system that controls recovery and offset. 제 1항 내지 제3항중의 어느 한항에 있어서,        The method according to any one of claims 1 to 3, 상기 수직재의 하부에 연결된 하중변위연동 및 고정장치는 스티프너와 잭하부지지판을 상기 수직재에 연결고정시키도록 하고, 상기 잭하부지지판의 하부에 잭을 설치할 수 있는 공간을 확보하기 위하여 일정한 간격을 두고 잭상부지지판을 설치하되, 상기 잭상,하부지지판의 모서리부를 고장력볼트와 스프링와샤너트로 상호 연결하고, 상기 잭상부지지판의 하부에 인장케이블을 안내할 수 있는 인장케이블가이드판을 양측에 설치하면서 상기 인장케이블가이드판의 사이에 인장케이블을 설치할 때 인장케이블을 밀착접촉되도록 중앙부가 볼록한 곡률면이 되도록 상기 잭상부지지판을 설치하는 것에 특징이 있는 작용하중에 따라 발생되는 변위와 반력을 직접회복 및 상쇄하도록 제어하는 자동싱크로나이즈지지시스템.       The load displacement interlocking and fixing device connected to the lower part of the vertical member allows the stiffener and the lower jack support plate to be fixed to the vertical member, and the jack is spaced at regular intervals to secure a space for installing the jack at the lower part of the lower jack support plate. The upper support plate is installed, and the upper and lower edges of the support plate are interconnected with high-tension bolts and springs and shoulders, and the tension cable guide plate for guiding the tension cable to the lower part of the upper support plate to the tension while installing the tension When the tension cable is installed between the cable guide plates, the jack upper support plate is installed so that the center portion becomes a convex curvature surface so that the tension cable is in close contact with the cable guide plate so as to directly recover and offset the displacement and reaction force generated by the working load. Automatic synchrogenizing support system to control. 제 6항에 있어서,       The method of claim 6, 상기 인장케이블가이드판은 잭상부지지판의 하부에 인장케이블을 안내할 수 있도록 강판으로 개복박스형태로 부착설치한 다음 상기 박스내에 인장케이블을 설치하여 이탈하지 않도록 한 것에 특징이 있는 작용하중에 따라 발생되는 변위와 반력을 직접회복 및 상쇄하도록 제어하는 자동싱크로나이즈지지시스템.       The tension cable guide plate is installed in the form of a lap box with a steel plate to guide the tension cable to the lower part of the upper support plate of the jack, and then installs the tension cable in the box so as not to be released according to the characteristic load. Automatic synchronization support system to directly control and offset the displacement and reaction force. 제 1항 또는 제2항에 있어서,       The method according to claim 1 or 2, 상기 수직파일과 띠장이 일정한 각도로 편기되어 설치되어 있을 경우에는 상기 수직파일과 상기 띠장에 간격이 형성된 틈내에 삼각형의 일정한 두께를 갖는 하중분산쐐받침판을 삽입설치하여 편기된 각도를 보상해주도록 한 것에 특징이 있는 작용하중에 따라 발생되는 변위와 반력을 직접회복 및 상쇄하도록 제어하는 자동싱크로나이즈지지시스템.      When the vertical pile and the strip are knitted at a predetermined angle, a load distribution wedge plate having a constant thickness of a triangle is inserted into the gap between the vertical pile and the strip to compensate for the knitting angle. An automatic synchronization support system that controls the direct recovery and offset of displacements and reaction forces generated by the working loads.
KR20-2005-0010855U 2005-04-19 2005-04-19 Auto-syncronized supporting system controlling to recover and offset displacement and repulsive force occurred according to working load KR200390445Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR20-2005-0010855U KR200390445Y1 (en) 2005-04-19 2005-04-19 Auto-syncronized supporting system controlling to recover and offset displacement and repulsive force occurred according to working load

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR20-2005-0010855U KR200390445Y1 (en) 2005-04-19 2005-04-19 Auto-syncronized supporting system controlling to recover and offset displacement and repulsive force occurred according to working load

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
KR1020050032351A Division KR100720321B1 (en) 2005-04-19 2005-04-19 Auto-syncronized supporting system controlling to recover and offset displacement and repulsive force occurred according to working load, and constructing method of the supporting system

Publications (1)

Publication Number Publication Date
KR200390445Y1 true KR200390445Y1 (en) 2005-07-25

Family

ID=43691696

Family Applications (1)

Application Number Title Priority Date Filing Date
KR20-2005-0010855U KR200390445Y1 (en) 2005-04-19 2005-04-19 Auto-syncronized supporting system controlling to recover and offset displacement and repulsive force occurred according to working load

Country Status (1)

Country Link
KR (1) KR200390445Y1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100711711B1 (en) 2006-09-05 2007-04-25 (주)써포텍 Light single wale by using pre-stressed support method
KR100733720B1 (en) * 2006-02-15 2007-07-04 (주)핸스건설 Droop prevention structure of steel pipe strut and main girder
KR100742221B1 (en) 2006-08-21 2007-07-24 (주)리튼브릿지 Temporary system for land-side protection wall
KR102436499B1 (en) * 2021-10-21 2022-08-26 (주)세니츠코퍼레이션 Emergency reinforcing method for retaining wall using water bag

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100733720B1 (en) * 2006-02-15 2007-07-04 (주)핸스건설 Droop prevention structure of steel pipe strut and main girder
KR100742221B1 (en) 2006-08-21 2007-07-24 (주)리튼브릿지 Temporary system for land-side protection wall
KR100711711B1 (en) 2006-09-05 2007-04-25 (주)써포텍 Light single wale by using pre-stressed support method
KR102436499B1 (en) * 2021-10-21 2022-08-26 (주)세니츠코퍼레이션 Emergency reinforcing method for retaining wall using water bag

Similar Documents

Publication Publication Date Title
KR100720321B1 (en) Auto-syncronized supporting system controlling to recover and offset displacement and repulsive force occurred according to working load, and constructing method of the supporting system
CN102418345B (en) Apparatus for fixing steel wire of wale
KR100633795B1 (en) Fixing structure of assembling type wale
KR100958014B1 (en) Construction method of steel composite girder bridge
CN106968257B (en) Concrete-fabricated profile steel mixed supporting system for ultra-large deep foundation pit and construction method thereof
KR100983861B1 (en) Integral composite slab bridge without abutments, supports, and expansion joints, and construction method thereof
KR101111594B1 (en) Method for constructing underground structure
US10094088B1 (en) Sheet pile retaining wall system
CN103711056A (en) Steel tool type temporary construction road and construction method thereof
CN111705795A (en) Prefabricated anchor pier for slope reinforcement and post-cast lattice beam assembly integral construction method
CN110552372A (en) Superposed cable working well top plate structure and construction method thereof
KR200390445Y1 (en) Auto-syncronized supporting system controlling to recover and offset displacement and repulsive force occurred according to working load
KR100745401B1 (en) Non-support, non-expension joint and non-abutment slab bridge having synchronized supporting post system, and installing method thereof
KR101102434B1 (en) Making of steel sheathing panel for earth retaining and this and construction technique
KR101710075B1 (en) PC Method for constructing underground structure having Precast wall using Hpile and underground structure constructed by the same
KR20110060291A (en) Made of iron soil retaining plate and its support structure for form and retaining-wall vertical reinforcement
CN212200464U (en) Large prefabricated lattice beam structure for slope reinforcement
KR100802037B1 (en) Side move prevention structure of a rahmen bridge
JP3958319B2 (en) Prestressed temporary construction method
KR101710718B1 (en) Method for connecting precast wall and slab, and underground structure constructed by the same
KR102027480B1 (en) Construction method for the rahmen bridge using facing of geosynthetics reinforced soil retaining wall
KR101973657B1 (en) Inverted Arcuate Structure to prevent Lateral Flow of the Bridge Abutments and Reparing Method using the Same
KR101710716B1 (en) Underground structure having Precast wall using H­pile
KR101827619B1 (en) Retaining wall earth pressure support technique
KR100858712B1 (en) Corner connecting apparatus of temporary soil sheathing work

Legal Events

Date Code Title Description
U107 Dual application of utility model
REGI Registration of establishment
T201 Request for technology evaluation of utility model
T701 Written decision to grant on technology evaluation
G701 Publication of correction
EXTG Extinguishment