KR102027480B1 - Construction method for the rahmen bridge using facing of geosynthetics reinforced soil retaining wall - Google Patents

Construction method for the rahmen bridge using facing of geosynthetics reinforced soil retaining wall Download PDF

Info

Publication number
KR102027480B1
KR102027480B1 KR1020190025609A KR20190025609A KR102027480B1 KR 102027480 B1 KR102027480 B1 KR 102027480B1 KR 1020190025609 A KR1020190025609 A KR 1020190025609A KR 20190025609 A KR20190025609 A KR 20190025609A KR 102027480 B1 KR102027480 B1 KR 102027480B1
Authority
KR
South Korea
Prior art keywords
reinforcement
support frame
crushed stone
shift
vertical
Prior art date
Application number
KR1020190025609A
Other languages
Korean (ko)
Inventor
강대화
Original Assignee
지반이엔씨 주식회사
강대화
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 지반이엔씨 주식회사, 강대화 filed Critical 지반이엔씨 주식회사
Priority to KR1020190025609A priority Critical patent/KR102027480B1/en
Application granted granted Critical
Publication of KR102027480B1 publication Critical patent/KR102027480B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention provides a construction method for a Rahmen bridge using a front wall of a reinforced soil retaining wall, which comprises the following steps of: constructing a base portion in a lower portion of a front side of each of reinforced soil planned on both sides; constructing a plan reinforced soil body on a rear surface of the constructed base portion; forming an abutment at an upper side of the base portion; and constructing a bridge in the shape of connecting upper portions of the abutment at both sides. The step of forming the abutment more comprises the following steps of: installing a base rebar to form an upper abutment of the plan reinforced soil body and the base portion, and connecting the plan reinforced soil body to the installed base rebar using a connection rebar; and installing an L-shaped upper bending beam portion at an upper side of the abutment.

Description

보강토 옹벽의 전면벽체를 활용한 라멘교 구축 방법{Construction method for the rahmen bridge using facing of geosynthetics reinforced soil retaining wall}Construction method for the rahmen bridge using facing of geosynthetics reinforced soil retaining wall}

본 발명은 교량 설치방법에 관한 것으로서, 더욱 상세하게는 라멘교 구축방법에 관한 것이다.The present invention relates to a bridge installation method, and more particularly to a ramen bridge construction method.

도 1은 종래 교량에 적용되는 하중 및 휨모멘트를 개략적으로 나타낸 도면이다. 도 1에 도시된 바와 같이, 기초적인 다리의 상부와 하부구조는 강절로 연결됨으로써 전체 구조의 강성을 높임과 동시에 지간 내에 발생하는 휨모멘트의 크기를 줄이는 대신 이를 교대가 부담하게 되어 교대 하단에 작용하는 휨모멘트가 크게 증가하게 된다. 따라서, 교대의 두께가 두꺼워지고, 교대 하부 기초의 크기가 커지는 등의 단점이 발생한다.1 is a view schematically showing a load and a bending moment applied to a conventional bridge. As shown in Fig. 1, the upper and lower structures of the basic bridge are connected to the steel sections, thereby increasing the rigidity of the entire structure and at the same time reducing the magnitude of the bending moment occurring in the ground, and acting on the lower ends of the shifts. The bending moment is greatly increased. Therefore, disadvantages arise such that the thickness of the alternation becomes thick and the size of the alternating lower foundation increases.

도 2은 종래 라멘교의 시공순서를 개략적으로 나타낸 도면이다. 종래의 라멘교는 지지 지반을 풍화암 이상의 견고한 지반으로 하고 있다. 따라서, 기반암이 조기에 출현하지 않으면 말뚝으로 교대기초를 지지한다. 2 is a view schematically showing a construction procedure of a conventional ramen bridge. Conventional ramen bridges are made of solid support over weathered rock. Thus, if bedrock does not emerge early, it supports the shift foundation with piles.

그리고, 이와 같은 라멘교는 기초와 교대를 구축하고 상부 슬리브(또는 거더)와 교대를 강결하는 순으로 시공한다. 이렇게 라멘교가 구축되고 나면, 배면은 뒤채움흙으로 채워진다. 그런데 도 3(c)와 같이 배면 뒤채움흙의 토체자중에 의한 수평토압이 교대에 추가로 작용하게 되므로, 교대과 교대기초의 크기가 커지게 된다.In addition, such a ramen bridge is constructed in the order of establishing the foundation and the shift, and tightening the upper sleeve (or the girder) and the shift. After this ramen bridge is built, the back is filled with backfilling soil. By the way, as shown in Fig. 3 (c), the horizontal earth pressure caused by the weight of the earth body of the backfilling soil is additionally acted on the shift, the size of the shift and the basis of the shift is increased.

도 3과 도 4는 종래 합성형 라멘교에서 H빔 형태로 이루어지는 교대 상부에 설치된 빔과 거더 기초를 이루는 슬리브빔의 접합방법을 나타내고 있다.3 and 4 illustrate a method of joining a beam installed on an alternating upper portion of an H-beam shape and a sleeve beam forming a girder in a conventional composite ramen bridge.

도 3 및 도 4와 같이 종래에는 상기 양 빔(11, 12)이 수직으로 변상 접촉된 상태를 이루며 이음보드(13)를 이용 결합되는데, 이 경우 결합 전단부에 걸리는 응력에 약한 경향이 있다. As shown in FIGS. 3 and 4, the beams 11 and 12 are coupled in vertical contact with each other using a joint board 13, in which case there is a tendency to be weak in the stress applied to the front end of the coupling.

이를 보완하기 위해 도 5와 같은 방식의 기술도 제시되고 있으나, 이 경우에도 수직방향 하중에는 강한 구조적 내구성을 가져올 수 있으나, 슬리브 길이방향에 교차되는 수평방향 전단응력에는 취약하다.In order to compensate for this, a technique of the same method as shown in FIG. 5 is also proposed, but even in this case, it may bring strong structural durability to the vertical load, but is vulnerable to the horizontal shear stress that crosses the sleeve longitudinal direction.

한편, 교대에 걸리는 배면토사의 수평토압을 줄일 수 있도록 종래의 보강토 옹벽의 전면벽체를 라멘교의 교대로 활용하는 방법은, 도 6과 같이, 전면벽체 블록 또는 판넬 자체의 붕괴위험과 시간이 지남에 따라서 변형으로 인하여 결국 교대 또한 파손이 가능하게 되는 문제점이 발생하게 된다.On the other hand, the method of alternately utilizing the front wall of the conventional reinforcement soil retaining wall in order to reduce the horizontal earth pressure applied to the back ground sewage alternately, as shown in Figure 6, the risk of collapse of the front wall block or panel itself over time Therefore, a problem arises that the alteration also can be broken eventually due to the deformation.

이에 따라서, 안정적이면서도 경제적인 시공이 가능한 라멘교 설치방법이 요구되는 실정이다.Accordingly, there is a need for a method of installing a ramen bridge that is stable and economical in construction.

이에 따라서, 안정적이면서도 경제적인 시공이 가능한 교량 설치방법이 요구되는 실정이다.Accordingly, there is a need for a bridge installation method capable of stable and economical construction.

KRKR 10-2002-001514110-2002-0015141 AA

본 발명은 상술한 종래의 문제점 및 제결점을 해결하기 위하여 안출된 것으로서, 본 발명은 교량에 걸리는 측하중 및 모멘트를 최소화하여 전체 교량의 안전성을 획기적으로 향상시킬 수 있는 라멘교 시공방법을 제공하는데 그 목적이 있다.The present invention has been made to solve the above-mentioned problems and drawbacks, the present invention provides a method for constructing a ramen bridge that can significantly improve the safety of the entire bridge by minimizing the side load and moment applied to the bridge The purpose is.

또한, 본 발명은 교대의 설치 및 빔 설치 시 조립부의 결합 정도가 향상되도록 이루어지는 라멘교 시공방법을 제공하는데 그 목적이 있다.In addition, it is an object of the present invention to provide a ramen bridge construction method is made so that the coupling degree of the assembly portion is improved when the alternating installation and beam installation.

본 발명의 과제들은 이상에서 언급한 과제들로 제한되지 않으며, 언급되지 않은 또 다른 과제들은 아래의 기재로부터 당업자에게 명확하게 이해될 수 있을 것이다.The objects of the present invention are not limited to the above-mentioned objects, and other objects that are not mentioned will be clearly understood by those skilled in the art from the following description.

상기한 목적을 달성하기 위하여, 본 발명은 양측으로 계획된 보강토체 각각의 전방측 하부에 기초부를 구축하는 단계; 상기 구축된 기초부 배면에 계획보강토체를 구축하는 단계; 상기 기초부 상측으로 교대를 형성하는 단계; 및 상기 양측 교대 상부를 연결하는 형태로 교량을 구축하는 단계;를 포함하며, 상기 교대를 형성하는 단계는, 상기 구축된 계획보강토체와 상기 기초부 상측 교대를 형성하기 위하여 기초철근을 설치하고 상기 설치된 기초철근을 연결철근을 이용 상기 계획보강토체와 연결되도록 하는 단계; 및 상기 교대 상측에 "ㄱ"자형 상부절곡빔부를 설치하는 단계;를 더 포함하는 보강토 옹벽의 전면벽체를 활용한 라멘교 구축 방법을 제공한다.In order to achieve the above object, the present invention comprises the steps of building a base in the lower front side of each of the reinforcement soil is planned to both sides; Constructing a plan reinforcement body on the constructed base portion back; Forming an alternating portion above the base portion; And constructing a bridge in a form of connecting the upper sides of the shifts, and the forming of the shifts includes installing the foundation reinforcement to form the constructed plan reinforced body and the upper portion of the foundation. Connecting the installed basic reinforcement to the plan reinforced body using a connecting reinforcing bar; It provides a ramen bridge construction method using the front wall of the retaining soil retaining wall further comprising the step of installing a "b" shaped upper bending beam portion on the upper side of the shift.

여기서, 상기 계획보강토체는, 원지반을 다지는 단계와, 상기 다져진 원지반에 주보강재를 설치하는 단계와, 상기 주보강재의 상부로 지지틀을 설치하는 단계와, 상기 지지틀의 상부로 보조보강재를 설치하는 단계와, 상기 설치된 보조보강재의 상부로 쇄석을 포설한 후 상기 보조보강재의 전단을 상기 포설된 쇄석의 외부를 밀착된 상태로 감싸도록 회전시키되, 회전된 상기 보조보강재에 있어 쇄석에 밀착되지 않은 부분이 상기 지지틀의 후방측으로 길이방향을 따라 지지틀의 상부에 놓이도록 하는 단계와, 상기 주보강재의 전단을 상기 쇄석이 상기 지지틀의 전방에 밀착되게 위치된 상태를 유지하도록 함과 동시에 상기 보조보강재와 함께 상기 쇄석의 외부를 밀착된 상태로 감싸도록 하며, 회전된 상기 주보강재에 있어 쇄석에 밀착되지 않은 부분이 상기 지지틀의 후방측으로 길이방향을 따라 지지틀의 상부에 놓이도록 하는 단계와, 상기 지지틀의 후방측으로 길이방향을 따라 밀착되도록 설치된 상기 주보강재 및 보조보강재를 상기 지지틀에 고정시키는 단계와, 상기 쇄석이 상기 지지틀의 전방에 밀착되게 설치된 상태를 유지한 채로 상기 쇄석이 설치된 후방측으로 뒤채움흙이 포설되는 단계를 포함하여 구성된 단위보강토체를 완성하는 단계를 포함하며, 상기 완성된 단위보강토체를 계획고까지 다층으로 축조하여 이루어질 수 있다.Here, the planed reinforcement body, the step of crushing the base plate, the step of installing the main reinforcement material on the chopped base plate, the step of installing the support frame to the upper portion of the main reinforcement material, and install the auxiliary reinforcement material to the upper portion of the support frame And installing the crushed stone to the upper portion of the installed auxiliary stiffener, and then rotating the shear of the auxiliary stiffener to cover the outside of the installed crushed stone in close contact, but not being in close contact with the crushed stone in the rotated auxiliary stiffener. Allowing the portion to lie on the upper side of the support frame along the longitudinal direction toward the rear side of the support frame; and maintaining the front end of the main reinforcement to keep the crushed stone in close contact with the front of the support frame. The outer reinforcement of the crushed stone with the auxiliary reinforcement to be in close contact, the portion of the main reinforcement that is not in close contact with the crushed stone Positioning the main reinforcement and the auxiliary reinforcement to be in close contact with the support frame in the longitudinal direction toward the rear side of the support frame in the longitudinal direction toward the rear side of the support frame; Comprising the step of completing the unit reinforcement body comprising the step of laying the backfill soil to the rear side where the crushed stone is installed while maintaining the state in which the crushed stone is in close contact with the front of the support frame, the completed unit It can be achieved by constructing the reinforcement soil in multiple layers up to the planned height.

또한, 상기 교대는 파셜교대부와 빔부가 교번 배치됨과 동시에 상기 파셜교대부가 최상단에 배치된 형태를 이루도록 설치되며, 상기 최상단에 배치된 파셜교대부 상측으로 상기 상부절곡빔부가 설치되며, 양측 교대 상부에 설치된 상기 상부절곡빔부를 연결하는 형태로 슬리브빔부가 설치되며, 상기 상부절곡빔부는 연결수평빔과 연결수직빔을 구비하되, 상기 연결수직빔이 소정 길이 상기 연결수평빔의 일측으로 돌출된 상태로 이루어지며, 상기 슬리브빔부는 중앙수평빔과 중앙수직빔을 구비하되, 상기 중앙수직빔은 양측으로 상기 연결수평빔의 돌출된 길이에 대응되도록 각각 함몰된 형태로 이루어져, 상기 상부절곡빔부와 슬리브빔부를 길이방향을 따라서 연결 시 상기 연결수직빔이 상기 한 쌍의 중앙수평빔 내측에 삽입되면서 상기 중앙수직빔과 변상 치합되는 형태로 이루어질 수 있다.In addition, the shift is installed so that the partial shift portion and the beam portion are alternately arranged and at the same time the partial shift portion is arranged at the top, and the upper bent beam portion is installed above the partial shift portion disposed at the uppermost portion, and both shift upper portions The sleeve beam unit is installed in the form of connecting the upper bent beam portion installed in the, the upper bent beam portion is provided with a connection horizontal beam and a connection vertical beam, the connection vertical beam protrudes to one side of the connection horizontal beam a predetermined length The sleeve beam portion includes a central horizontal beam and a central vertical beam, the central vertical beams are formed in recessed shapes so as to correspond to the protruding length of the connection horizontal beam on both sides, and the upper bent beam portion and the sleeve When the beam unit is connected along the longitudinal direction, the connecting vertical beam is inserted into the pair of central horizontal beams, thereby providing the center vertical beams. And it may be formed of a made up coupling type.

또한, 상기 상부절곡빔부와 슬리브빔부가 연결된 상태에서 상기 상부절곡빔부와 슬리브빔부를 결합하는 이음보드가 더 구비될 수 있다.In addition, a joint board may be further provided to couple the upper bent beam part and the sleeve beam part while the upper bent beam part and the sleeve beam part are connected to each other.

상기와 같이 구성된 본 발명 라멘교 구축방법은 다음과 같은 효과가 있다.The ramen bridge construction method of the present invention configured as described above has the following effects.

본 발명의 일 실시예에 따른 라멘교는 교대 측부에 계획보강토체를 적용한 후, 계획보강토체에 연결하는 형태로 교대를 구축함으로써 전체적으로 교대에 걸리는 측부 하중 및 모멘트를 최소화하고 교대에 수직하중만이 전달되도록 함으로써 전체 교랑의 구조적 안정성을 획기적으로 향상시킬 수 있는 효과를 가져온다.Ramen bridge according to an embodiment of the present invention, after applying the planed reinforcement to the alternating side, by building a shift in the form of connecting to the planed reinforcement body to minimize the side load and moment to be applied to the overall shift and only vertical load to the shift This ensures a significant improvement in the structural stability of the entire bridge.

또한, 본 발명은 교대 하부 기초부 상측으로 파셜교대부와 빔부가 연속 적용되되 기초부와 빔부 또는 파셜교대부의 기본 구성이 분리된 상태로 이루어지도록 함으로써, 기초부에 걸리는 편심모멘트가 대폭 감소되어 기초 폭을 상당히 감소시킬 수 있게 된다.In addition, the present invention by applying the partial shift portion and the beam portion continuously applied to the upper base of the alternating lower portion, but the basic configuration of the base portion and the beam portion or partial alternating portion is separated, thereby reducing the eccentric moment of the base portion significantly The width can be reduced considerably.

또한, 본 발명은 교량 상부를 이루는 거더부를 상부절곡빔부와 슬리브빔부가 연결되는 형태로 이루어지도록 하되, 상부절곡빔부와 슬리브빔부의 수직부가 엇갈려 배치되도록 함으로써 양 부재들의 연결부에서 구조적 안전성을 확보할 수 있게 되며 설치 작업의 용이성을 증대시킬 수 있게 된다.In addition, the present invention is to be made in the form of the upper girder beam portion and the sleeve beam portion is connected to the girder portion forming the bridge, the vertical bending portion of the upper bent beam portion and the sleeve beam portion is arranged to be secured structural safety at the connecting portion of both members It will be possible to increase the ease of installation work.

본 발명의 효과들은 이상에서 언급한 효과들로 제한되지 않으며, 언급되지 않은 또 다른 효과들은 청구범위의 기재로부터 당업자에게 명확하게 이해될 수 있을 것이다.The effects of the present invention are not limited to the above-mentioned effects, and other effects not mentioned will be clearly understood by those skilled in the art from the description of the claims.

도 1은 종래 교량에 걸리는 하중 및 모멘트를 개략적으로 나타낸 도면;
도 2는 종래 라멘교가 구축되는 모습 및 교대에 걸리는 측부하중을 개략적으로 나타낸 도면;
도 3 및 도 4는 종래 기술에 따른 거더를 이루는 상부빔들의 연결모습을 개략적으로 나타낸 도면들;
도 5는 종래 기술에 따른 거더를 이루는 상부빔들의 다른 형태에 따른 연결모습을 나타낸 도면;
도 6은 옹벽이 붕괴되는 모습을 나타낸 사진;
도 7 내지 도 9는 기초부를 구축한 후에 단위보강토체를 적층하여 계획보강토체를 구축하는 모습을 나타낸 도면들;
도 10은 단위보강토체를 구축하는 모습을 개략적으로 나타낸 도면;
도 11 및 도 12는 기초부 상측으로 교대가 형성되는 과정을 개략적으로 나타낸 도면들;
도 13 및 도 14는 상기 구축된 양측 교대 상부를 연결하는 거더부가 형성되는 모습을 순차적으로 나타낸 도면들;
도 15는 상부절곡빔부와 슬리브빔부가 연결되는 모습을 개략적으로 나타낸 분해사시도;
도 16은 상부절곡빔부와 슬리브빔부가 연결된 후 이음보드가 적용된 모습을 나타낸 측면도;
도 17은 상부절곡빔부와 슬리브빔부가 연결되는 다른 형태를 나타낸 측면도; 및
도 18은 세 개의 교대가 적용된 교량을 개략적으로 나타낸 사시도이다.
1 is a view schematically showing a load and a moment applied to a conventional bridge;
2 is a view schematically showing a state in which a conventional ramen bridge is constructed and side loads applied to the alternating bridges;
3 and 4 schematically show the connection of the upper beams forming a girder according to the prior art;
5 is a view showing a connection according to another form of the upper beams forming a girder according to the prior art;
6 is a photograph showing the collapse of the retaining wall;
7 to 9 are diagrams showing a state to build a plan reinforced soil by stacking the unit reinforced soil after building the foundation;
10 is a view schematically showing how to build a unit reinforced soil;
11 and 12 are views schematically showing a process in which the shift is formed above the base portion;
13 and 14 are views sequentially showing a state in which a girder portion is formed connecting the alternating upper sides of the constructed;
15 is an exploded perspective view schematically showing how the upper bent beam portion and the sleeve beam portion are connected;
16 is a side view showing a state in which the joint board is applied after the upper bent beam portion and the sleeve beam portion is connected;
17 is a side view showing another form in which the upper bent beam portion and the sleeve beam portion are connected; And
18 is a perspective view schematically showing a bridge to which three shifts are applied.

이하 본 발명의 목적이 구체적으로 실현될 수 있는 본 발명의 바람직한 실시예를 첨부된 도면을 참조하여 설명한다. 본 실시예를 설명함에 있어서, 동일 구성에 대해서는 동일 명칭 및 동일 부호가 사용되며 이에 따른 부가적인 설명은 생략하기로 한다.DETAILED DESCRIPTION Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings. In the description of this embodiment, the same name and the same reference numerals are used for the same configuration and additional description thereof will be omitted.

이하 본 발명의 목적이 구체적으로 실현될 수 있는 본 발명의 바람직한 실시예를 첨부된 도면을 참조하여 설명한다. 본 실시예를 설명함에 있어서, 동일 구성에 대해서는 동일 명칭 및 동일 부호가 사용되며 이에 따른 부가적인 설명은 생략하기로 한다.DETAILED DESCRIPTION Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings. In the description of this embodiment, the same name and the same reference numerals are used for the same configuration and additional description thereof will be omitted.

도 7 내지 도 9는 기초부를 구축한 후에 단위보강토체를 적층하여 계획보강토체를 구축하는 모습을 나타낸 도면들이며, 도 10은 단위보강토체를 구축하는 모습을 개략적으로 나타낸 도면이다.7 to 9 are diagrams showing a state of constructing the reinforced structure by stacking the unit reinforcement body after building the foundation, Figure 10 is a view showing a state of constructing the unit reinforcement body.

먼저, 도 7에 도시된 바와 같이, 양측으로 구축하고자 하는 교대와 계획보강토체 각각의 전방측으로 지형 하부에 기초부(120)를 구축하는 단계를 수행한다. First, as shown in FIG. 7, the foundation 120 is formed in the lower part of the terrain to the front side of each of the shifts and the plan reinforcement bodies to be built on both sides.

상기 기초부(120)는 지형에 매립된 상태로 구축됨이 바람직하다. 그리고, 상기 기초부(120)는 콘크리트재로 이루어지고 프리캐스트 방식이 적용될 수 있다.The foundation 120 is preferably built in a state buried in the terrain. In addition, the base 120 may be made of concrete and a precast method may be applied.

다음으로는 상기 양측 기초부(120) 각각의 후방측으로 라멘교를 구축하고자 하는 지형주변을 정리한 후에 정리된 지형 양측으로 소정 이격된 위치에 계획보강토체(112)를 구축하는 단계를 수행한다. Next, after arranging the periphery of the terrain to build the ramen bridge to the rear side of each of the two sides of the base 120, the step of constructing the plan reinforced soil 112 in a predetermined spaced position on both sides of the arranged terrain.

상기 계획보강토체(112)는 단위보강토체(110)가 계획고까지 다층으로 적층되는 방식으로 축조되어 이루어지게 되는데, 상기 단위보강토체(110)는 쇄석(106)과, 상기 쇄석(106)을 감싸는 상태로 포설된 면상의 보조보강재(105)와, 상기 보조보강재(105)가 쇄석(106)을 감싼 상태를 일정하게 유지하도록 보조보강재(105)의 전단을 지지해 주는 강재로 된 지지틀(103)과, 상기 지지틀(103)에 포설되어 상부의 지지틀(103)과 쇄석(106)과 상기 쇄석(106)의 후방에 채워지는 뒤채움흙(107)과, 상기 지지틀(103)과 보조보강재(105)와 쇄석(106)을 동시에 감싸는 상태로 원지반에 포설된 망상의 주보강재(101)로 구성될 수 있다.The planned reinforcement body 112 is constructed in a manner that the unit reinforcement body 110 is laminated in a multi-layer up to the planned height, the unit reinforcement body 110 is a crushed stone 106 and the crushed stone 106 Support frame made of steel supporting the front end of the auxiliary reinforcing material 105 and the auxiliary reinforcing material 105 in a wrapped state and the auxiliary reinforcing material 105 to maintain a constant state of wrapping the crushed stone 106 ( 103, backfilling soil 107 which is installed in the support frame 103 and filled in the rear of the support frame 103, the crushed stone 106, and the crushed stone 106, and the support frame 103. The secondary reinforcing material 105 and the crushed stone 106 may be composed of a reticulated main reinforcement 101 installed on the ground at the same time.

여기서 상기 쇄석(106)은 단위보강토체(110) 전면부의 다짐이 효과적으로 이루어지도록 하고, 구축된 계획보강토체(112)의 압축변형을 최소화하는 역할을 수행하게 된다.Here, the crushed stone 106 serves to effectively compact the front portion of the unit reinforcement body 110 and to minimize the compression deformation of the constructed reinforcement structure body 112.

그리고, 상기 주보강재(101)는 토목섬유로 이루어지며, 상기 보조보강재(105)는 면상으로서 상기 주보강재(101)보다 조밀한 격자들로 이루어진 면상의 토목섬유로 이루어진다.The main reinforcing material 101 is made of geotextiles, and the auxiliary reinforcing material 105 is made of planar geotextiles composed of lattice denser than the main reinforcing material 101 as a plane.

또한, 상기 보조보강재(105)는 쇄석(106)을 긴밀히 감싸 쇄석(106)의 유출을 막을 수 있도록 유연한 격자 구조가 촘촘한 지오그리드(geogrid)가 적용됨이 바람직하다.In addition, the auxiliary reinforcing material 105 is tightly wrapped around the crushed stone 106, it is preferable to apply a geogrid (geogrid) having a compact lattice structure to prevent the outflow of the crushed stone 106.

여기서, 상기 보조보강재(105)가 연성으로서 변형률이 커서 충분한 강성을 유지하지 못하더라도 외측의 주보강재(101)가 충분한 강성을 갖고 있기 때문에 마찰에 대한 저항성을 충분히 확보할 수 있어서 지지틀(103)과 보조보강재(105) 사이가 벌어지지 않게 되며, 이로 인해 시공 중에 쇄석(106)이 유실되거나 뒤채움흙(107)이 허물어지는 현상 없이 정상적인 단위보강토체(110)의 축조가 가능해진다.Here, even if the auxiliary reinforcing material 105 is ductile, the strain rate is large, and thus the main reinforcing material 101 does not maintain sufficient rigidity, since the outer main reinforcing material 101 has sufficient rigidity, sufficient resistance to friction can be ensured, thereby supporting the support frame 103. Between the auxiliary reinforcement 105 is not opened, and thus construction of the normal unit reinforcement body 110 is possible without the phenomenon that the crushed stone 106 is lost or the backfilling soil 107 is collapsed during construction.

그리고, 상기 지지틀(103)은 철근(121)이 종횡방향으로 교차 연결된 수평망 형태로서, 전단이 상부로 절곡되도록 구성된다. 상기 지지틀(103)의 전단은 쇄석(106)이 전방으로 함몰되지 않도록 지지해주는 동시에 완성된 단위보강토체(110)의 전면이 일정한 수직평활도를 유지할 수 있도록 기준을 잡아주게 된다.In addition, the support frame 103 is a horizontal mesh form in which the reinforcing bars 121 are crossed in the longitudinal and horizontal directions, and the front end is bent upward. The front end of the support frame 103 supports the crushed stone 106 is not recessed forward and at the same time to set the standard so that the front surface of the completed unit reinforced soil 110 can maintain a constant vertical smoothness.

한편, 상기 주보강재(101)와 보조보강재(105) 및 지지틀(103)은 쇄석(106)의 포설과정에서 유동되는 것을 방지하기 위하여 지지핀(104)으로 고정됨이 바람직하다.On the other hand, the main reinforcing material 101, auxiliary reinforcing material 105 and the support frame 103 is preferably fixed to the support pin 104 to prevent flow in the installation process of the crushed stone 106.

도 11 및 도 12는 상기 기초부 상측으로 교대가 형성되는 과정을 개략적으로 나타낸 도면들이다.11 and 12 are diagrams schematically illustrating a process of forming an alternating portion above the base portion.

도시된 바와 같이, 상기 계획보강토체가 구축된 후에는 상기 기초부(120) 상측으로 교대(130)를 형성하는 단계를 수행하게 된다.As shown in the drawing, after the planned reinforcement soil is constructed, the step of forming the shift 130 above the foundation 120 is performed.

상기 교대(130)는 철근을 배근하고 거푸집을 구축한 후 콘크리트를 타설하여 콘크리트 옹벽이 전체적으로 구축되는 방식이 적용되거나 하나의 빔이 수직방향으로 설치 적용되는 형태를 이룰 수도 있으나, 본 실시예의 경우에는 도시된 바와 같이, 프리캐스트 방식 또는 현장 타설 방식으로 이루어지는 파셜교대부(132)와 철질재질로 이루어지고 H빔 형태의 빔부(134)가 교대가 구축되는 상하 높이방향을 따라서 교번 배치되어 계획된 높이까지 연속 적용되는 방식으로 이루어진다.The shift 130 may be a form in which the concrete retaining wall is constructed as a whole by applying the reinforcement to the reinforcing bars and building the formwork, or one beam is installed in the vertical direction, but in the present embodiment As shown, the partial shift portion 132 made of a precast method or in-site casting method and the steel material and the H-beam beam portion 134 is alternately arranged along the up and down height direction in which the alternating construction to the planned height It is done in a continuous application way.

이때, 최상단에는 파셜교대부(132)가 배치된 형태를 이룬다.At this time, the partial shift portion 132 is formed at the top end.

그리고, 상기 파셜교대부(132)는 최상단에 "ㄱ"자 형태의 상부절곡빔부(140)가 양측 교대에 절곡 돌출된 방향이 서로 대면된 형태를 이루도록 배치된다.In addition, the partial shift portion 132 is arranged such that the upper bending beam portion 140 having a “a” shape at the top end is formed to face each other in a protruding direction.

이때, 상기 상부절곡빔부(140) 하측에는 상기 파셜교대부(132) 상부면에 평행한 설치플레이트(137)가 구비되며, 상기 설치플레이트(137)가 상기 파셜교대부(132)에 볼트(139)결합될 수 있다.In this case, an installation plate 137 parallel to an upper surface of the partial shift unit 132 is provided below the upper bending beam unit 140, and the installation plate 137 is bolted to the partial shift unit 132. Can be combined.

한편, 자세히 도시되어 있지는 않으나, 기초철근이 일정 높이까지 상기 파셜교대부(132)와 빔부(134) 외측에 적용되고 상기 기초철근 외측에 거푸집이 적용되어 후술하는 바와 같이 거푸집 내측으로 콘크리트가 타설되도록 할 수 있다.On the other hand, although not shown in detail, the base reinforcement is applied to the partial shift portion 132 and the beam 134 outside to a certain height and the formwork is applied to the outside of the base reinforcement so that concrete is poured into the form as described below can do.

이때, 상기 기초철근 또는 빔부(134)와 상기 계획보강토체(112)의 지지틀(103)은 용접 등의 방식으로 별도의 강성을 가지는 연결철근(138)을 이용 서로 결합된 상태를 이루도록 하여 최종 구축된 계획보강토체(112)와 교대(130)가 일체화된 상태를 이루도록 함이 바람직하며, 상기 연결철근(138)의 양단부는 상기 지지틀(103) 또는 기초철근 등에 용접 결합된 형태를 이룰 수도 있다.In this case, the base reinforcement or beam portion 134 and the support frame 103 of the planned reinforced earth body 112 is connected to each other by using a connecting reinforcement 138 having a separate stiffness by welding or the like. It is preferable to form a plan reinforced reinforcement body 112 and the shift 130 is integrated, and both ends of the connecting reinforcement 138 may form a welded joint to the support frame 103 or the basic reinforcement. have.

최종적으로는 상기 기초철근 외측에 거푸집을 적용한 후 상기 파셜교대부(132)와 빔부(134) 외부를 동시에 덮어 감싸는 형태로 콘크리트가 타설되어 최종 교대(130)가 구축된다.Finally, after the formwork is applied to the outer side of the reinforcing bar, concrete is poured in the form of covering the exterior of the partial shift unit 132 and the beam unit 134 at the same time to form a final shift 130.

도 13 및 도 14는 상기 구축된 양측 교대 상부를 연결하는 거더부(188)가 형성되는 모습을 순차적으로 나타낸 도면들이다.13 and 14 are views sequentially showing a state in which the girder 188 is formed to connect the constructed upper sides alternately.

도시된 바와 같이, 상기 양측 파셜교대부(132) 상부에 구비된 상부절곡빔부(140)에 일측과 타측이 연결되는 형태로 슬리브빔부(150)를 설치하는 과정을 수행하게 된다.As shown, the process of installing the sleeve beam portion 150 in a form in which one side and the other side is connected to the upper bent beam portion 140 provided on the upper sides of the partial shift portion 132.

그리고, 상기 양측 상부절곡빔부(140) 하부로는 상부절곡빔부(140)의 형태에 대응하는 형태로 절곡된 보강콘트리트부(187)가 적용됨이 바람직하다.In addition, the reinforcement concrete portion 187 that is bent in a form corresponding to the shape of the upper bending beam portion 140 may be applied to both lower upper bending beam portions 140.

한편, 상기 상부절곡빔부(140)와 슬리브빔부(150)의 결합관계를 나타낸 도 15 및 도 16에 도시된 바와 같이, 상기 상부절곡빔부(140)는 상부에 수평하게 절곡된 부위가 한 쌍의 연결수평빔(141)과 상기 연결수평빔(141)의 중앙부를 수직으로 가로지르며 설치되는 연결수직빔(143)을 포함하여 이루어지되, 상기 연결수직빔(143)이 소정 길이(L) 상기 연결수평빔(141)의 일측으로 돌출된 상태로 이루어진다.Meanwhile, as shown in FIGS. 15 and 16 illustrating a coupling relationship between the upper bent beam part 140 and the sleeve beam part 150, the upper bent beam part 140 has a pair of horizontally bent portions on the upper part. It comprises a connection horizontal beam 141 and a connection vertical beam 143 is installed to traverse the center portion of the connection horizontal beam 141 vertically, the connection vertical beam 143 is a predetermined length (L) of the connection It is made to protrude to one side of the horizontal beam (141).

그리고, 상기 슬리브빔부(150)도 한 쌍의 중앙수평빔(151)과 중앙수직빔(153)을 구비하되, 상기 중앙수직빔(153)은 양측으로 상기 연결수평빔(141)의 돌출된 길이(L)에 대응되도록 각각 내측으로 인입된 형태로 이루어진다.In addition, the sleeve beam unit 150 also includes a pair of central horizontal beams 151 and a central vertical beam 153, wherein the central vertical beams 153 protrude lengths of the connection horizontal beams 141 to both sides. It is made of a form drawn in each so as to correspond to (L).

이에 따라서, 상기 상부절곡빔부(140)와 슬리브빔부(150)를 길이방향을 따라서 연결 시 상기 연결수직빔(143)이 상기 슬리브빔부(150)의 중앙수평빔(151) 내측에 삽입되면서 연결수직빔(143)과 중앙수직빔(153)이 변상 치합되는 형태로 이루어지게 된다.Accordingly, the connection vertical beam 143 is inserted into the center horizontal beam 151 of the sleeve beam part 150 when the upper bent beam part 140 and the sleeve beam part 150 are connected in the longitudinal direction, and the connection vertical beam is vertically connected. The beam 143 and the central vertical beam 153 are made to be in the form of a matched mesh.

여기서, 상기 연결수직빔(143)의 높이가 H라 할때, H/2 는 L 보다 작은 상태 즉, H/2 < L상태를 이루도록 함이 바람직하다.Here, when the height of the connection vertical beam 143 is H, it is preferable to make H / 2 smaller than L, that is, H / 2 <L state.

그리고, 도 16에서와 같이, 상기 상부절곡빔부(140)와 슬리브빔부(150)가 치합된 상태에서 상기 연결수직빔(143)과 중앙수직빔(153)의 연결 부위에는 이음보드(160)와 결합볼트(162)를 이용 상기 양 부재를 견고하게 결합시킴이 바람직하다.In addition, as shown in FIG. 16, in the state where the upper bent beam part 140 and the sleeve beam part 150 are engaged with each other, a joint board 160 and a connection part of the connection vertical beam 143 and the center vertical beam 153 are provided. It is preferable to firmly couple both members using the coupling bolt 162.

이와 같이 돌출된 연결수직빔(143)과 인입된 중앙수직빔(153)을 구비하는 상부절곡빔부(140)와 슬리브빔부(150)의 결합은 상기 연결수직빔(143)과 인입된 중앙수직빔(153)을 이용하여 상기 양 부재의 일차 고정 작업이 용이하게 이루어짐은 물론 구조적으로 보다 견고한 결합상태를 이룰 수 있게 된다.The combination of the upper bending beam portion 140 and the sleeve beam portion 150 having the connection vertical beam 143 protruding and the center vertical beam 153 protruded in this way is the connection of the vertical vertical beam 143 and the center vertical beam introduced. By using 153, the primary fixing operation of both members can be easily performed, and structurally more firmly coupled can be achieved.

다른 형태로서 도 17에서와 같이, 상기 연결수직빔(143)와 중앙수직빔(153)의 접합 부위가 상측에서 하측으로 지그재그 형태로 이단 절곡된 형태를 이루도록 할 수도 있다.As another embodiment, as shown in FIG. 17, the junction portion of the connection vertical beam 143 and the center vertical beam 153 may be formed in a two-fold bent shape in a zigzag form from the upper side to the lower side.

이 경우에도 상기 양 부재(140, 150)의 일차 고정 작업이 용이하게 이루어짐은 물론 구조적으로 보다 견고한 결합상태를 이룰 수 있게 된다.In this case, as well as the primary fixing operation of the two members (140, 150) is easily made, it is possible to achieve a more structurally secure coupling state.

다시 도 13 및 도 14을 참조하면, 상기 상부절곡빔부(140)와 슬리브빔부(150)를 결합하고 상기 상부절곡빔부(140)와 슬리브빔부(150)의 결합 및 설치가 완료된 후에는, 상기 결합된 상부절곡빔부(140)와 슬리브빔부(150) 상측으로 기초철근(173)을 배근한 후에, 주변 지형과 상부절곡빔부(140)와 슬리브빔부(150) 상측부를 덮어 감싸는 형태로 모르타르나 콘크리트 등을 이용한 교대 상부 채움부(180)를 구축함으로써 최종 거더부(188) 구축이 완료된다.Referring back to FIGS. 13 and 14, after coupling the upper bent beam part 140 and the sleeve beam part 150 and the coupling and installation of the upper bent beam part 140 and the sleeve beam part 150 are completed, the coupling is performed. After reinforcing the basic reinforcing bar 173 toward the upper bent beam part 140 and the sleeve beam part 150, the mortar or concrete, etc. in a form to cover the surrounding topography and the upper bent beam part 140 and the sleeve beam part 150. The final girder 188 construction is completed by constructing the alternating upper filling unit 180.

한편, 이와 같은 라멘교는 도 18에서와 같이, 세 개 이상의 교대(130)가 적용되도록 하되, 인접한 교대(130) 상부를 연결하는 형태로 교대가 적용될 수도 있다.On the other hand, such a ramen bridge, as shown in Figure 18, three or more shifts 130 to be applied, the shift may be applied in the form of connecting the upper portion of the adjacent shift (130).

이 경우 중앙에 위치되는 교대 상부에는 상부가 양측으로 나뉘어져 절곡된 "T"자 형태의 상부절곡빔부(240)가 적용될 수 있을 것이다.In this case, the upper portion of the upper portion of the bent beam portion 240, which is bent and divided into two sides, may be applied.

이상과 같이 본 발명에 따른 바람직한 실시예를 살펴보았으며, 앞서 설명된 실시예 이외에도 본 발명이 그 취지나 범주에서 벗어남이 없이 다른 특정 형태로 구체화될 수 있다는 사실은 해당 기술에 통상의 지식을 가진 이들에게는 자명한 것이다. 그러므로, 상술된 실시예는 제한적인 것이 아니라 예시적인 것으로 여겨져야 하고, 이에 따라 본 발명은 상술한 설명에 한정되지 않고 첨부된 청구항의 범주 및 그 동등 범위 내에서 변경될 수도 있다.As described above, a preferred embodiment according to the present invention has been described, and the fact that the present invention can be embodied in other specific forms in addition to the above-described embodiments without departing from the spirit or scope thereof has ordinary skill in the art. It is obvious to them. Therefore, the above-described embodiments should be regarded as illustrative rather than restrictive, and thus, the present invention is not limited to the above description and may be modified within the scope of the appended claims and their equivalents.

112: 계획보강토체 110: 단위보강토체
120: 기초부 130: 교대
132: 파셜교대부 134: 빔부
140: 상부절곡빔부 141: 연결수평빔
143: 연결수직빔 150: 슬리브빔부
151: 중앙수평빔 153: 중앙수직빔
112: planned reinforced soil 110: unit reinforced soil
120: base 130: shift
132: partial shift unit 134: beam unit
140: upper bending beam portion 141: connecting horizontal beam
143: connection vertical beam 150: sleeve beam portion
151: center horizontal beam 153: center vertical beam

Claims (4)

양측으로 계획된 보강토체 각각의 전방측 하부에 기초부를 구축하는 단계; 상기 구축된 기초부 배면에 계획보강토체를 구축하는 단계; 상기 기초부 상측으로 교대를 형성하는 단계; 및 상기 양측 교대 상부를 연결하는 형태로 교량을 구축하는 단계;를 포함하며,
상기 교대를 형성하는 단계는 상기 구축된 계획보강토체와 상기 기초부 상측 교대를 형성하기 위하여 기초철근을 설치하고 상기 설치된 기초철근을 연결철근을 이용 상기 계획보강토체와 연결되도록 하는 단계; 및 상기 교대 상측에 "ㄱ"자형 상부절곡빔부를 설치하는 단계;를 더 포함하며,
상기 계획보강토체는, 원지반을 다지는 단계와, 상기 다져진 원지반에 주보강재를 설치하는 단계와, 상기 주보강재의 상부로 지지틀을 설치하는 단계와, 상기 지지틀의 상부로 보조보강재를 설치하는 단계와, 상기 설치된 보조보강재의 상부로 쇄석을 포설한 후 상기 보조보강재의 전단을 상기 포설된 쇄석의 외부를 밀착된 상태로 감싸도록 회전시키되, 회전된 상기 보조보강재에 있어 쇄석에 밀착되지 않은 부분이 상기 지지틀의 후방측으로 길이방향을 따라 지지틀의 상부에 놓이도록 하는 단계와, 상기 주보강재의 전단을 상기 쇄석이 상기 지지틀의 전방에 밀착되게 위치된 상태를 유지하도록 함과 동시에 상기 보조보강재와 함께 상기 쇄석의 외부를 밀착된 상태로 감싸도록 하며, 회전된 상기 주보강재에 있어 쇄석에 밀착되지 않은 부분이 상기 지지틀의 후방측으로 길이방향을 따라 지지틀의 상부에 놓이도록 하는 단계와, 상기 지지틀의 후방측으로 길이방향을 따라 밀착되도록 설치된 상기 주보강재 및 보조보강재를 상기 지지틀에 고정시키는 단계와, 상기 쇄석이 상기 지지틀의 전방에 밀착되게 설치된 상태를 유지한 채로 상기 쇄석이 설치된 후방측으로 뒤채움흙이 포설되는 단계를 포함하여 구성된 단위보강토체를 완성하는 단계를 포함하며, 상기 완성된 단위보강토체를 계획고까지 다층으로 축조하여 이루어지며,
상기 교대는 파셜교대부와 빔부가 교번 배치됨과 동시에 최상단에 상기 파셜교대부가 배치된 형태를 이루도록 설치되며,
상기 최상단에 배치된 파셜교대부 상측으로 상기 상부절곡빔부가 설치되며,
상기 상부절곡빔부의 하측에는 상기 파셜교대부 상부면에 평행한 설치플레이트가 볼트결합을 통해 구비되고,
양측 교대 상부에 설치된 상기 상부절곡빔부를 연결하는 형태로 슬리브빔부가 설치되며,
상기 상부절곡빔부는 연결수평빔과 연결수직빔을 구비하되, 상기 연결수직빔이 소정 길이 상기 연결수평빔의 일측으로 돌출된 상태로 이루어지며,
상기 슬리브빔부는 중앙수평빔과 중앙수직빔을 구비하되, 상기 중앙수직빔은 양측으로 상기 연결수평빔의 돌출된 길이에 대응되도록 각각 함몰된 형태로 이루어져, 상기 상부절곡빔부와 슬리브빔부를 길이방향을 따라서 연결 시 상기 연결수직빔이 한 쌍의 중앙수평빔 내측에 삽입되면서 상기 중앙수직빔과 변상 치합되는 형태로 이루어지되, 상기 연결수직빔이 상기 연결수평빔의 일측으로 돌출된 길이를 L이라 하고 상기 연결수평빔 사이 길이를 H라 할 때, H/2 < L상태를 이루도록 하며,
상기 상부절곡빔부와 슬리브빔부가 연결된 상태에서 상기 상부절곡빔부와 슬리브빔부를 결합하는 이음보드가 더 구비되되, 상기 이음보드는 상기 연결수평빔과 상기 중앙수평빔이 연결된 상태에서 상기 연결수평빔과 상기 중앙수평빔에 동시에 결합되는 이음보드와, 상기 연결수직빔과 상기 중앙수직빔이 연결된 상태에서 상기 연결수직빔과 상기 중앙수직빔에 동시에 결합하는 이음보드로 각각 나뉘어 구비되며,
상기 양측 상부절곡빔부 하부로는 상기 상부절곡빔부의 형태에 대응하는 형태로 절곡된 보강콘트리트부가 슬리브빔부의 단부를 지지하도록 밀착 적용되는,
보강토 옹벽의 전면벽체를 활용한 라멘교 구축 방법.
Constructing a foundation in the lower portion of the front side of each of the reinforcement soils planned for both sides; Constructing a plan reinforcement body on the constructed base portion back; Forming an alternating portion above the base portion; And constructing a bridge in a form of connecting the upper sides of the alternate parts.
The forming of the shift may include installing a foundation reinforcement and connecting the installed foundation reinforcement with a connection reinforcement body to form the constructed reinforced structure and the upper portion of the foundation; And installing a "b" shaped upper bent beam part on the upper side of the shift.
The planned reinforcement body, the step of crushing the base plate, the step of installing the main reinforcement material on the chopped base plate, the step of installing the support frame to the top of the main reinforcement material, the step of installing the auxiliary reinforcement to the top of the support frame And, after installing the crushed stone to the upper portion of the installed auxiliary reinforcement and the front end of the auxiliary reinforcement is rotated to wrap in close contact with the outside of the installed crushed stone, the portion of the auxiliary reinforcement is not in close contact with the crushed stone Placing the upper portion of the support frame along the longitudinal direction toward the rear side of the support frame; and maintaining the front end of the main reinforcement to keep the crushed stone in close contact with the front of the support frame; The outer portion of the crushed stone to be in close contact with, and the portion of the main reinforcing material that is not in close contact with the crushed stone is Placing an upper portion of the support frame along the longitudinal direction toward the rear side of the support frame, and fixing the main reinforcement and the auxiliary reinforcement installed on the support frame to be closely adhered along the longitudinal direction toward the rear side of the support frame; Comprising the step of completing the unit reinforcement body comprising the step of laying the backfilling soil to the rear side where the crushed stone is installed while maintaining the state in which the crushed stone is in close contact with the front of the support frame, the completed unit reinforcement body It is made by building a multi-layer up to the planned height,
The shift is provided so that the partial shift portion and the beam portion are alternately arranged and at the same time the partial shift portion is arranged at the top.
The upper bending beam part is installed above the partial shift part disposed at the top end,
On the lower side of the upper bending beam part is provided an installation plate parallel to the upper surface of the partial shift portion through the bolt coupling,
The sleeve beam portion is installed in the form of connecting the upper bent beam portion installed on both sides of the shift,
The upper bending beam part includes a connection horizontal beam and a connection vertical beam, wherein the connection vertical beam is formed to protrude to one side of the connection horizontal beam by a predetermined length.
The sleeve beam portion includes a center horizontal beam and a center vertical beam, and the center vertical beams are formed in recessed shapes so as to correspond to the protruding lengths of the connection horizontal beams on both sides thereof, and the upper bent beam portion and the sleeve beam portion in the longitudinal direction. The connecting vertical beam is inserted into the pair of central horizontal beams and connected to the central vertical beams while connecting the vertical vertical beams. The length of the connecting vertical beams protruding toward one side of the connecting horizontal beams is L. When the length between the connecting horizontal beam is H, H / 2 <L to achieve a state,
A joint board is further provided to couple the upper bending beam part and the sleeve beam part in a state in which the upper bending beam part and the sleeve beam part are connected. The joint board is connected to the connection horizontal beam in a state in which the connection horizontal beam and the central horizontal beam are connected. And a joint board coupled to the central horizontal beam at the same time, and a joint board coupled to the joint vertical beam and the central vertical beam at the same time in which the connection vertical beam and the central vertical beam are connected.
The reinforcement concrete portion bent in a shape corresponding to the shape of the upper bent beam portion is applied in close contact with the lower sides of the upper bent beam portion to support an end of the sleeve beam portion.
Ramen bridge construction method using front wall of reinforced earth retaining wall.
삭제delete 삭제delete 삭제delete
KR1020190025609A 2019-03-06 2019-03-06 Construction method for the rahmen bridge using facing of geosynthetics reinforced soil retaining wall KR102027480B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020190025609A KR102027480B1 (en) 2019-03-06 2019-03-06 Construction method for the rahmen bridge using facing of geosynthetics reinforced soil retaining wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020190025609A KR102027480B1 (en) 2019-03-06 2019-03-06 Construction method for the rahmen bridge using facing of geosynthetics reinforced soil retaining wall

Publications (1)

Publication Number Publication Date
KR102027480B1 true KR102027480B1 (en) 2019-11-04

Family

ID=68578143

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020190025609A KR102027480B1 (en) 2019-03-06 2019-03-06 Construction method for the rahmen bridge using facing of geosynthetics reinforced soil retaining wall

Country Status (1)

Country Link
KR (1) KR102027480B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102257896B1 (en) 2020-10-26 2021-05-28 김준영 Construction method of integrated reinforcement soil retaining wall replacement that is safe from lateral load during construction and integrated reinforcement soil retaining wall integrated shift that was constructed by the construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020015141A (en) 2000-08-21 2002-02-27 이계안 Wire connection device
KR101000552B1 (en) * 2010-04-02 2010-12-14 지반이엔씨 주식회사 Reinforced concrete and reinforced geosynthetic soil retaining wall, and construction method for thereof
KR20160148416A (en) * 2015-06-16 2016-12-26 주식회사 길교이앤씨 Steel-Concrete Composite Rahmen Bridge
KR101887032B1 (en) * 2017-12-04 2018-08-16 (주)케이모듈 Prefabricated small river bridge having steel wire coupler

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020015141A (en) 2000-08-21 2002-02-27 이계안 Wire connection device
KR101000552B1 (en) * 2010-04-02 2010-12-14 지반이엔씨 주식회사 Reinforced concrete and reinforced geosynthetic soil retaining wall, and construction method for thereof
KR20160148416A (en) * 2015-06-16 2016-12-26 주식회사 길교이앤씨 Steel-Concrete Composite Rahmen Bridge
KR101887032B1 (en) * 2017-12-04 2018-08-16 (주)케이모듈 Prefabricated small river bridge having steel wire coupler

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102257896B1 (en) 2020-10-26 2021-05-28 김준영 Construction method of integrated reinforcement soil retaining wall replacement that is safe from lateral load during construction and integrated reinforcement soil retaining wall integrated shift that was constructed by the construction method

Similar Documents

Publication Publication Date Title
KR100720321B1 (en) Auto-syncronized supporting system controlling to recover and offset displacement and repulsive force occurred according to working load, and constructing method of the supporting system
KR100634726B1 (en) Form system for construction of underground slab and method for constructing underground slab and breast wall using the same
KR100969586B1 (en) Rhamen bridge and construction method there of
KR102063701B1 (en) Construction method for the rahmen bridge using reinforced wall and approach slab
KR20030019937A (en) Device of Innovative Prestressed Scaffolding System for Improving Workability
KR101255027B1 (en) Precast rahmen type box culvert
KR102027480B1 (en) Construction method for the rahmen bridge using facing of geosynthetics reinforced soil retaining wall
KR100383268B1 (en) method for underground construction of building by using permanent structural member as strut for support retaining wall
KR102369701B1 (en) Transitional zone available deformation absorption and subsidence reduction and constructing method therefor
KR100657655B1 (en) Assembly pile for method of ground improvement
JP6685570B1 (en) PC basic structure and construction method thereof
KR101200994B1 (en) Earth retaining system and construction using separate type pedestal and wale bearing supporter
KR101198286B1 (en) Non-wale strut system for top-down construction and top-down construction method thereby
JP3958319B2 (en) Prestressed temporary construction method
KR102482690B1 (en) Bridge foundation construction method using formwork integrated PC panels
KR101733928B1 (en) panel type retaining wall with a continuous beam structure
KR20100118482A (en) To use reclamation steel perimeter beam and slab diaphragm effect in order for one side of the basement outer wall continuous construct was possible ,which the basement infrastructure construction method
JP5021526B2 (en) Construction method of underpass and connecting structure of superstructure girder and underground wall
KR20080103260A (en) Reinforcing bar assembly for separate concrete pours and strut system method utilizing the same
JP5559075B2 (en) Underground structure
KR102106573B1 (en) The tunnel structure using corrugated multi plate and the construction method using the same
KR100858712B1 (en) Corner connecting apparatus of temporary soil sheathing work
KR101736009B1 (en) Top-Down Construction Method For Underground Structure
JP5679849B2 (en) Underground structure
KR102490879B1 (en) Reinforced earth retaining wall and construction method using H pile

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant