CN110552372A - Superposed cable working well top plate structure and construction method thereof - Google Patents
Superposed cable working well top plate structure and construction method thereof Download PDFInfo
- Publication number
- CN110552372A CN110552372A CN201910864292.6A CN201910864292A CN110552372A CN 110552372 A CN110552372 A CN 110552372A CN 201910864292 A CN201910864292 A CN 201910864292A CN 110552372 A CN110552372 A CN 110552372A
- Authority
- CN
- China
- Prior art keywords
- steel
- shaped
- shaped steel
- beams
- channel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title abstract description 50
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 193
- 239000010959 steel Substances 0.000 claims abstract description 193
- 239000004567 concrete Substances 0.000 claims abstract description 22
- 238000000034 method Methods 0.000 claims abstract description 12
- 238000011065 in-situ storage Methods 0.000 claims abstract description 8
- 239000011150 reinforced concrete Substances 0.000 claims description 11
- 238000012423 maintenance Methods 0.000 claims description 4
- 230000002457 bidirectional effect Effects 0.000 claims description 3
- 239000011083 cement mortar Substances 0.000 claims description 3
- 210000001503 joint Anatomy 0.000 claims description 3
- 238000010586 diagram Methods 0.000 description 2
- 230000001360 synchronised effect Effects 0.000 description 2
- 230000015572 biosynthetic process Effects 0.000 description 1
- 238000005266 casting Methods 0.000 description 1
- 230000006835 compression Effects 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 230000008878 coupling Effects 0.000 description 1
- 238000010168 coupling process Methods 0.000 description 1
- 238000005859 coupling reaction Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000009415 formwork Methods 0.000 description 1
- 238000010030 laminating Methods 0.000 description 1
- 239000004570 mortar (masonry) Substances 0.000 description 1
- 238000011084 recovery Methods 0.000 description 1
- 238000010008 shearing Methods 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/12—Manhole shafts; Other inspection or access chambers; Accessories therefor
- E02D29/125—Manhole shafts; Other inspection or access chambers; Accessories therefor characterised by the lining of the shaft
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/12—Manhole shafts; Other inspection or access chambers; Accessories therefor
- E02D29/14—Covers for manholes or the like; Frames for covers
Landscapes
- Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Roof Covering Using Slabs Or Stiff Sheets (AREA)
Abstract
the invention relates to a roof structure and construction of a cable working well, in particular to a superposed roof structure of the cable working well and a construction method thereof, which is characterized by comprising an H-shaped steel main beam, a channel steel secondary beam, a steel plate and a poured concrete plate; two ends of each H-shaped steel main beam are respectively erected on L-shaped steps at the tops of two side walls of the cable working well, the channel steel secondary beams are positioned on the lower end surfaces of the upper flanges of the H-shaped steel main beams, two ends of each channel steel secondary beam are respectively welded with two adjacent H-shaped steel main beams, steel plates are fully paved on the channel steel secondary beams, and the steel plates are distributed in parallel to the H-shaped steel main beams; the shear steel members are welded on the upper end surfaces of the upper flanges of the H-shaped steel girders, the concrete slabs are cast in situ on the H-shaped steel girders and the full-spread steel plates, and the H-shaped steel girders are fixedly connected with cast-in-situ concrete plates through the shear steel members. The invention has the advantages that: construction convenience, construction process need not to set up the scaffold frame, can effectively shorten construction period, improve the efficiency of construction greatly to waterproof performance has been ensured. In addition, the steel support frame is fully utilized, and the stress performance of the top plate is improved.
Description
Technical Field
The invention relates to a roof structure and construction of a cable working well, in particular to a superposed cable working well roof structure and a construction method thereof.
background
the cable structures are underground engineering, and the open cut cable structures need to be subjected to roof construction during construction, and the construction mode thereof specifically refers to a mode-stripping type roof-laminating scheme in constructional engineering and is as follows: considering the thickness of the top plate, a scaffold and other auxiliary construction measures need to be built in the working well; secondly, a prefabricated template is supported at the top of the scaffold, then a concrete top plate is poured on the prefabricated plate, the template can be detached after the top plate reaches the strength, and then the support in the well is installed and constructed. The disadvantages of the construction mode are that:
1) during construction, as the top plate is large in thickness (250 mm-400 mm) and heavy in weight, auxiliary construction measures such as scaffolds and the like need to be set up in a working well to support the weight of the cast-in-place concrete top plate in the construction process and the forming process, and the space in the working well is limited, so that the construction is inconvenient, complicated and complex, and the safety is difficult to guarantee;
2) Because the scaffold needs to be fully distributed in the whole work well, during the construction of the top plate, namely from the beginning of the scaffold below the top plate to the completion of the pouring of the top plate, other construction projects such as pipeline construction and the like cannot be carried out and can be only carried out before or after the construction of the top plate, the construction period is influenced, and the construction efficiency is reduced;
in order to solve the problem of erecting the scaffold, the construction scheme of directly hoisting the prefabricated roof is adopted in the prior art, but the defects of the scheme are as follows: after the prefabricated top plate is directly hoisted in place, gaps exist, the cable work well has higher requirements on the waterproof performance of a structure, particularly the work well after a large number of accessory facilities are laid or the work well for directly installing connectors has higher waterproof grade, but the gaps formed by the prefabricated hoisting scheme are difficult to treat due to deep depth and long gaps, so the gaps are not treated or coated with mortar generally, the problems of insufficient waterproof performance, leakage and the like frequently occur in the operation process, and the application rate is low; in addition, the prefabricated roof also brings problems in transportation, hoisting and the like due to the thickness of the prefabricated roof.
Disclosure of Invention
the invention aims to provide a superposed cable working well top plate structure and a construction method thereof, which have the advantages of convenient construction, no need of erecting a scaffold, effective construction period shortening, construction efficiency improvement and waterproof performance guarantee.
the superposed cable work well top plate structure is realized by the following ways:
A superposed roof structure of a cable working well is characterized by comprising an H-shaped steel main beam, a channel steel secondary beam, a steel plate and a poured concrete plate, wherein the tops of two side walls of the cable working well are provided with L-shaped steps; two ends of each H-shaped steel main beam are respectively erected on L-shaped steps at the tops of two side walls of the cable work well, and one H-shaped steel main beam is distributed on each L-shaped step at intervals of a set distance; the channel steel secondary beams are positioned on the lower end faces of the upper flanges of the H-shaped steel main beams, two ends of each channel steel secondary beam are respectively welded with two adjacent H-shaped steel main beams, and one channel steel secondary beam is distributed on each H-shaped steel main beam at a set distance; fully laying steel plates on the channel steel secondary beam, wherein the steel plates are distributed in parallel to the H-shaped steel main beam; the shear steel members are welded on the upper end surfaces of the upper flanges of the H-shaped steel girders, the concrete slabs are cast in situ on the H-shaped steel girders and the full-spread steel plates, and the H-shaped steel girders are fixedly connected with cast-in-situ concrete plates through the shear steel members.
The construction method of the superposed cable work well roof structure is characterized by comprising the following steps:
1) when the cable working well is constructed and excavated, the upper end parts of the side walls of the two sides of the working well are of L-shaped step structures, grooves are oppositely excavated at set intervals along the longitudinal direction of the L-shaped steps, the bottoms of the grooves are leveled by cement mortar, and waterproof treatment is carried out;
2) providing a plurality of H-shaped steel main beams, channel steel secondary beams and steel plates, wherein the H-shaped steel main beams are erected on L-shaped steps on two sides, and two ends of the H-shaped steel main beams are correspondingly embedded into grooves in the L-shaped steps respectively;
3) Laying channel steel secondary beams: the channel steel secondary beams are distributed between two adjacent H-shaped steel main beams at intervals and are positioned on the lower end faces of the upper flanges of the H-shaped steel main beams, and the upper side faces of two ends of each channel steel secondary beam are respectively welded with the lower end faces of the upper flanges of the two adjacent H-shaped steel main beams in a butt joint mode;
4) laying steel plates: the thickness of the steel plate is smaller than that of the upper flange of the H-shaped steel main beam, and the steel plate is fully paved on the upper end face of the channel steel secondary beam installed between every two adjacent H-shaped steel main beams;
5) the upper end surface of the H-shaped steel girder is welded with a shear-resistant steel member, double-layer bidirectional steel bars are bound above the steel plates,
6) and pouring a reinforced concrete plate with the thickness of more than 250mm as a top plate, and backfilling and compacting after the maintenance reaches the design strength.
Like this, construct the superimposed steel support frame by H shaped steel girder, channel-section steel secondary beam and full-spread steel sheet, and reinforced concrete board passes through shear steel member and H shaped steel girder formation rigid coupling, and whole superimposed roof structure is from top to bottom according to the preface from this: the steel reinforced concrete slab is not less than 250mm in thickness, the full-spread steel plate that is used for supporting concrete face and pours, be used for supporting steel plate and reinforced concrete slab, prevent H shaped steel girder and channel-section steel secondary beam that the work progress warp. The H-shaped steel girder is used as the center, and other superposed components are connected or fixedly connected with the steel girder, so that a superposed steel support frame capable of supporting the reinforced concrete slab with the thickness of more than 250mm in rigidity and strength is formed, and the support guarantee can be obtained in the processes of pouring the reinforced concrete slab and maintaining. The construction method is convenient to construct, a scaffold is not required to be erected in the construction process, the construction method can be synchronous with other construction projects, the construction period can be effectively shortened, the construction efficiency is greatly improved, and the waterproof performance requirement of the cable working well is met.
in addition, pour the completion back, make superimposed steel support frame and reinforced concrete slab form a whole through the shear steel member, realize the effect of the two integrated common load bearing: on one hand, the steel support frame is fully utilized and directly used as a part of the top plate structure to bear force, so that the strength and rigidity of the top plate structure of the cable work well are greatly improved, and the stress performance is improved; on the other hand, after the pouring and maintenance are completed, the process of dismantling the supporting detachable formwork is not needed, and only the ground needs to be restored after direct soil filling, so that the operation is convenient and fast, and the integral structure after pouring is not influenced.
the invention can be further embodied as follows:
the upper surfaces of two ends of the channel steel secondary beam are welded and connected with the lower end surface of the upper flange of the H-shaped steel main beam.
The channel-section steel secondary beam is used for connecting the main beam and supporting the full-spread steel plate, so that the upper surface is required to be flush during welding, and the side surface of the channel-section steel secondary beam can be welded with a web plate of the H-shaped steel main beam to ensure connection.
The shear steel component is either a stud or a channel steel.
The shear steel member is used for connecting the concrete slab and the steel support frame, and therefore needs to be welded on the main beam, so that the concrete slab and the steel support frame mainly bearing the load together.
In summary, the invention provides a superposed cable shaft roof structure and a construction method thereof, wherein an H-shaped steel main beam is used as a center and a main stress structure is adopted, a channel steel secondary beam and a full-spread steel plate are used as steel structures for supporting construction pouring reinforced concrete plates and preventing deformation in the construction process, and a shearing-resistant steel component is used for realizing common stress of a superposed steel support frame and the concrete plates and bearing load. The invention has the advantages that: construction convenience, construction process need not to set up the scaffold frame, can be synchronous with other construction works, effectively shorten construction period, improve the efficiency of construction greatly to cable worker well waterproof performance requirement has been ensured. In addition, the steel support frame can be fully utilized, the stress performance of the top plate is improved, and the construction process is simplified.
Drawings
Fig. 1 is a schematic elevation structure view of a superposed cable work well roof structure according to the present invention;
FIG. 2 is a side view of the block diagram shown in FIG. 1;
FIG. 3 is a top view of the structural diagram shown in FIG. 2 (without the steel plate and the concrete slab);
fig. 4 is an enlarged schematic view of a partial structure of the folding steel support frame of the present invention.
the present invention will be further described with reference to the following examples.
Detailed Description
The best embodiment is as follows:
Referring to the attached drawings 1-4, the top of two side walls of a superposed cable work well top plate structure is provided with L-shaped steps 1 which comprise an H-shaped steel main beam 2, a channel steel secondary beam 3, a steel plate 4 and a poured concrete plate 5; two ends of an H-shaped steel main beam 2 are respectively erected on L-shaped steps 1 at the tops of two side walls of the cable work well, and one H-shaped steel main beam 2 is distributed on each L-shaped step 1 at intervals of a set distance; the channel steel secondary beams 3 are positioned on the lower end faces of the upper flanges of the H-shaped steel main beams 2, two ends of each channel steel secondary beam are respectively welded with two adjacent H-shaped steel main beams 2, and one channel steel secondary beam 3 is distributed on each H-shaped steel main beam 2 at a set distance; fully laying steel plates 4 on the channel steel secondary beams 3, wherein the steel plates 4 are distributed in parallel to the H-shaped steel main beam 2; the shear steel members 9 (refer to attached drawing 4) are welded on the upper end surfaces of the upper flanges of the H-shaped steel girders 2, the concrete slabs 5 are cast in situ on the H-shaped steel girders 2 and the full-spread steel plates 4, and the H-shaped steel girders 2 are fixedly connected with the cast-in-situ concrete slabs 5 through the shear steel members 9. The shear steel member 9 is either a stud or a channel steel.
Referring to fig. 1-4, a construction method of a superposed cable work well roof structure includes the following steps:
1) When the cable working well is constructed and excavated, the upper end parts of the side walls of two sides of the working well are of L-shaped step structures, a groove 6 is oppositely excavated along the longitudinal direction of the L-shaped step 1 at set intervals, the bottom of the groove 6 is leveled by adopting cement mortar, and water-proof treatment is carried out by adopting micro-expansion shrinkage concrete 8;
2) Providing a plurality of H-shaped steel main beams 2, channel steel secondary beams 3 and steel plates 4, wherein the H-shaped steel main beams 2 are erected on the L-shaped steps 1 on the two sides, and the two ends of each H-shaped steel main beam are correspondingly embedded into the grooves 6 on the L-shaped steps respectively;
3) laying channel steel secondary beams: the channel steel secondary beams 3 are distributed between two adjacent H-shaped steel main beams 2 at intervals and are positioned on the lower end surfaces of the upper flanges of the H-shaped steel main beams 2, and the upper side surfaces of two ends of the channel steel secondary beams 3 are respectively welded with the lower end surfaces of the upper flanges of the two adjacent H-shaped steel main beams 2 in a butt joint mode (see the attached drawing 4);
4) Laying steel plates: the thickness of the steel plate is less than that of the upper flange of the H-shaped steel main beam 2, 3-6 mm is taken, and the steel plate is fully paved on the upper end surface of the channel steel secondary beam 3 arranged between two adjacent H-shaped steel main beams 2;
5) The upper end surface of the H-shaped steel girder 2 is welded with a shear-resistant steel member 9, a double-layer bidirectional steel bar 7 is bound above the steel plate,
6) And pouring a reinforced concrete plate with the thickness of more than 250mm as a top plate, and backfilling and compacting after the maintenance reaches the design strength.
The design points of the invention comprise:
1) the roof of cable worker well is coincide beam slab structure, from last to being down:reinforced concrete slab with thickness not less than 250mm →Full-spread steel plate → for supporting concrete slab castingthe steel channel secondary beam and the H-shaped steel main beam are used for supporting steel plates and limiting deformation in the construction process.
2) In order to support the load together with the concrete slab and the steel girder bracket, shear-resistant studs are welded to the steel girder, so that the H-beam girder serves as a structure of a compression part of the permanent roof.
3) adopt superimposed beam slab formula structure, the roof of cable worker well need not set up detachable template alone again, with template and roof two unifications.
4) During roof construction, the scaffold that need not set up in the well and the template of dismantling the recovery can realize the inside and outside simultaneous construction of well, improve work efficiency greatly.
The parts of the invention not described are the same as the prior art.
Claims (4)
1. A superposed roof structure of a cable working well is characterized by comprising an H-shaped steel main beam, a channel steel secondary beam, a steel plate and a poured concrete plate, wherein the tops of two side walls of the cable working well are provided with L-shaped steps; two ends of each H-shaped steel main beam are respectively erected on L-shaped steps at the tops of two side walls of the cable work well, and one H-shaped steel main beam is distributed on each L-shaped step at intervals of a set distance; the channel steel secondary beams are positioned on the lower end faces of the upper flanges of the H-shaped steel main beams, two ends of each channel steel secondary beam are respectively welded with two adjacent H-shaped steel main beams, and one channel steel secondary beam is distributed on each H-shaped steel main beam at a set distance; fully laying steel plates on the channel steel secondary beam, wherein the steel plates are distributed in parallel to the H-shaped steel main beam; the shear steel members are welded on the upper end surfaces of the upper flanges of the H-shaped steel girders, the concrete slabs are cast in situ on the H-shaped steel girders and the full-spread steel plates, and the H-shaped steel girders are fixedly connected with cast-in-situ concrete plates through the shear steel members.
2. The superposed cable work well roof plate structure of claim 1, wherein the upper surfaces of the two ends of the channel steel secondary beam are welded with the lower end surfaces of the upper flanges of the H-shaped steel main beams.
3. a stacked cable work well roof structure according to claim 1, wherein the shear steel members are either studs or channels.
4. The method for constructing a laminated cable work well roof structure of claim 1, comprising the steps of:
1) when the cable working well is constructed and excavated, the upper end parts of the side walls of the two sides of the working well are of L-shaped step structures, grooves are oppositely excavated at set intervals along the longitudinal direction of the L-shaped steps, the bottoms of the grooves are leveled by cement mortar, and waterproof treatment is carried out;
2) Providing a plurality of H-shaped steel main beams, channel steel secondary beams and steel plates, wherein the H-shaped steel main beams are erected on L-shaped steps on two sides, and two ends of the H-shaped steel main beams are correspondingly embedded into grooves in the L-shaped steps respectively;
3) Laying channel steel secondary beams: the channel steel secondary beams are distributed between two adjacent H-shaped steel main beams at intervals and are positioned on the lower end faces of the upper flanges of the H-shaped steel main beams, and the upper side faces of two ends of each channel steel secondary beam are respectively welded with the lower end faces of the upper flanges of the two adjacent H-shaped steel main beams in a butt joint mode;
4) laying steel plates: the thickness of the steel plate is smaller than that of the upper flange of the H-shaped steel main beam, and the steel plate is fully paved on the upper end face of the channel steel secondary beam installed between every two adjacent H-shaped steel main beams;
5) The upper end surface of the H-shaped steel girder is welded with a shear-resistant steel member, double-layer bidirectional steel bars are bound above the steel plates,
6) and pouring a reinforced concrete plate with the thickness of more than 250mm as a top plate, and backfilling and compacting after the maintenance reaches the design strength.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910864292.6A CN110552372A (en) | 2019-09-12 | 2019-09-12 | Superposed cable working well top plate structure and construction method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910864292.6A CN110552372A (en) | 2019-09-12 | 2019-09-12 | Superposed cable working well top plate structure and construction method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110552372A true CN110552372A (en) | 2019-12-10 |
Family
ID=68740153
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910864292.6A Pending CN110552372A (en) | 2019-09-12 | 2019-09-12 | Superposed cable working well top plate structure and construction method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110552372A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111622267A (en) * | 2020-05-29 | 2020-09-04 | 中国电建集团中南勘测设计研究院有限公司 | Vertical shaft structure and construction method thereof |
CN113338153A (en) * | 2021-06-24 | 2021-09-03 | 中铁大桥勘测设计院集团有限公司 | Suspension bridge anchorage front anchor chamber assembly type top cover plate and construction process |
CN113482147A (en) * | 2021-06-28 | 2021-10-08 | 五冶集团上海有限公司 | Construction method of '0' -layer frame structure |
CN113882432A (en) * | 2021-09-01 | 2022-01-04 | 武汉市政工程设计研究院有限责任公司 | Rapid construction method for assembled top plate of small-area deep shaft |
CN115182383A (en) * | 2022-08-16 | 2022-10-14 | 上海市城市建设设计研究总院(集团)有限公司 | Deep-buried large-span open-cut tunnel structure in soft soil water-rich area and construction method thereof |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101413247A (en) * | 2008-12-03 | 2009-04-22 | 中交公路规划设计院有限公司 | Streamline steel-concrete folding case beam |
CN201254694Y (en) * | 2008-08-28 | 2009-06-10 | 四川省交通厅公路规划勘察设计研究院 | Combination bridge deck |
CN101748682A (en) * | 2010-01-22 | 2010-06-23 | 清华大学 | Steel-concrete composite beam adopting corrugated steel web and construction method thereof |
CN104947588A (en) * | 2015-07-06 | 2015-09-30 | 清华大学 | Steel pipe concrete-combination beam cable stayed bridge floor system and construction method thereof |
CN105887649A (en) * | 2016-04-21 | 2016-08-24 | 浙江交通职业技术学院 | Steel-concrete local prefabricated simply supported superposed beam structure adopting layering stud connector and manufacturing technique thereof |
CN106592965A (en) * | 2016-12-26 | 2017-04-26 | 中建四局第六建筑工程有限公司 | Quick support system of high-rise steel structure house composite floor slab |
CN207144538U (en) * | 2017-08-18 | 2018-03-27 | 中铁第四勘察设计院集团有限公司 | A kind of underground structure top board reserving hole temporary plugging structure |
CN108222347A (en) * | 2018-03-03 | 2018-06-29 | 北京工业大学 | A kind of big module welding overlapping beam slab of the assembled with plane girder temporary support |
-
2019
- 2019-09-12 CN CN201910864292.6A patent/CN110552372A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201254694Y (en) * | 2008-08-28 | 2009-06-10 | 四川省交通厅公路规划勘察设计研究院 | Combination bridge deck |
CN101413247A (en) * | 2008-12-03 | 2009-04-22 | 中交公路规划设计院有限公司 | Streamline steel-concrete folding case beam |
CN101748682A (en) * | 2010-01-22 | 2010-06-23 | 清华大学 | Steel-concrete composite beam adopting corrugated steel web and construction method thereof |
CN104947588A (en) * | 2015-07-06 | 2015-09-30 | 清华大学 | Steel pipe concrete-combination beam cable stayed bridge floor system and construction method thereof |
CN105887649A (en) * | 2016-04-21 | 2016-08-24 | 浙江交通职业技术学院 | Steel-concrete local prefabricated simply supported superposed beam structure adopting layering stud connector and manufacturing technique thereof |
CN106592965A (en) * | 2016-12-26 | 2017-04-26 | 中建四局第六建筑工程有限公司 | Quick support system of high-rise steel structure house composite floor slab |
CN207144538U (en) * | 2017-08-18 | 2018-03-27 | 中铁第四勘察设计院集团有限公司 | A kind of underground structure top board reserving hole temporary plugging structure |
CN108222347A (en) * | 2018-03-03 | 2018-06-29 | 北京工业大学 | A kind of big module welding overlapping beam slab of the assembled with plane girder temporary support |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111622267A (en) * | 2020-05-29 | 2020-09-04 | 中国电建集团中南勘测设计研究院有限公司 | Vertical shaft structure and construction method thereof |
CN113338153A (en) * | 2021-06-24 | 2021-09-03 | 中铁大桥勘测设计院集团有限公司 | Suspension bridge anchorage front anchor chamber assembly type top cover plate and construction process |
CN113482147A (en) * | 2021-06-28 | 2021-10-08 | 五冶集团上海有限公司 | Construction method of '0' -layer frame structure |
CN113882432A (en) * | 2021-09-01 | 2022-01-04 | 武汉市政工程设计研究院有限责任公司 | Rapid construction method for assembled top plate of small-area deep shaft |
CN113882432B (en) * | 2021-09-01 | 2022-09-16 | 武汉市政工程设计研究院有限责任公司 | Rapid construction method for assembled top plate of small-area deep shaft |
CN115182383A (en) * | 2022-08-16 | 2022-10-14 | 上海市城市建设设计研究总院(集团)有限公司 | Deep-buried large-span open-cut tunnel structure in soft soil water-rich area and construction method thereof |
CN115182383B (en) * | 2022-08-16 | 2024-02-02 | 上海市城市建设设计研究总院(集团)有限公司 | Deep-buried large-span open cut tunnel structure in soft soil water-rich area and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110552372A (en) | Superposed cable working well top plate structure and construction method thereof | |
US20160340855A1 (en) | Modular construction mold apparatus and method for constructing concrete buildings and structures | |
CN104060761B (en) | U-shaped steel concrete combination beam and construction method thereof | |
CN202559384U (en) | Prefabricated assembled pipe-jacking working well | |
CN109653233A (en) | Cushion cap single wall steel jacket box recoverable construction of bottom plates method | |
KR101600845B1 (en) | The horizontal structural frame and the underground construction methods using it | |
CN103603359A (en) | Deep foundation pit diagonal bracing support structure demolition method | |
CN112502714B (en) | Assembled shaft barrel structure and design and construction method | |
CN110847915A (en) | Construction process for jumping-cutting demolishing and subsection back-jacking of double-side-wall temporary support of shallow-buried fine sand layer | |
KR101011805B1 (en) | Method of constructing underground structure crossing pile bases in a pile-based ground and underground structure constructed using the same | |
CN110552706A (en) | Permanent-temporary combined shield hoisting hole sealing structure and method | |
CN110645022A (en) | Self-anchored formwork support system for connecting channel and construction method | |
JP2004263467A (en) | Reconstruction method using existing underground skeleton | |
CN212506301U (en) | Support system in combination assembled forever | |
JP4037187B2 (en) | Underground structure construction method and underground structure | |
CN107975064A (en) | Integral prefabricated fabricated construction technique for underground engineering | |
CN210712958U (en) | Prefabricated cast-in-situ superposed cable working well top plate | |
CN103243722A (en) | Construction method of novel inner support of foundation trench | |
CN211900603U (en) | Face combination shield structure hole of hoist enclosed construction forever | |
KR101485563B1 (en) | The horizontal structural frame | |
CN211447265U (en) | Laminated plate type edge member and solid shear wall horizontal connection structure | |
CN210459229U (en) | Support assembled in deep basal pit and trade and prop construction frock | |
KR100351135B1 (en) | Method of constructing arch ring of steel framed reinforced concrete arch bridge | |
CN115506634B (en) | Assembled platform canopy and construction method thereof | |
CN116289355B (en) | Construction method of long-distance translation assembly type module guide rail of large-span integral building |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |