KR20030042267A - method for manufacturing prestressed composite beam by division mode - Google Patents

method for manufacturing prestressed composite beam by division mode Download PDF

Info

Publication number
KR20030042267A
KR20030042267A KR1020010072981A KR20010072981A KR20030042267A KR 20030042267 A KR20030042267 A KR 20030042267A KR 1020010072981 A KR1020010072981 A KR 1020010072981A KR 20010072981 A KR20010072981 A KR 20010072981A KR 20030042267 A KR20030042267 A KR 20030042267A
Authority
KR
South Korea
Prior art keywords
concrete
casing concrete
curing
joint
lower casing
Prior art date
Application number
KR1020010072981A
Other languages
Korean (ko)
Other versions
KR100476837B1 (en
Inventor
서동영
박우영
Original Assignee
(주)스틸엔콘크리트
주식회사 도우엔지니어즈
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)스틸엔콘크리트, 주식회사 도우엔지니어즈 filed Critical (주)스틸엔콘크리트
Priority to KR10-2001-0072981A priority Critical patent/KR100476837B1/en
Publication of KR20030042267A publication Critical patent/KR20030042267A/en
Application granted granted Critical
Publication of KR100476837B1 publication Critical patent/KR100476837B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/02Bridges characterised by the cross-section of their bearing spanning structure of the I-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/28Concrete reinforced prestressed
    • E01D2101/285Composite prestressed concrete-metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/04Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal
    • E04C3/10Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal prestressed

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

PURPOSE: A manufacturing method of a prestressed composite beam is provided to have a good command of chamber for a joint and to place compressive force evenly. CONSTITUTION: The manufacturing method of a prestressed composite beam comprises the steps of: chambering a spot to be divided using a unified steel beam according to a plan of a prestressed beam in a factory; adding preflexion load on the chambered steel beam; at the state of adding preflexion load, placing and curing lower casing concrete on a spot excluding a split line out of a lower flange of a steel beam; after curing the lower casing concrete surface, removing preflexion load and cutting off a part where lower casing concrete isn't placed into many members; lining up each member on a temporary support in a job site, and fixing a joint of each member to the ground by a wire rope; lifting up the temporary support to be chambered, then placing and curing joint casing concrete(8) on a joint of each member; after curing the joint casing concrete(8), descending the temporary support slowly and adding compressive force on joint concrete.

Description

프리스트레스트 합성빔의 분할제작방법 {method for manufacturing prestressed composite beam by division mode}Method for manufacturing prestressed composite beam by division mode

본 발명은 프리스트레스트 합성빔의 새로운 제작방법에 관한 것이다.The present invention relates to a new method of fabricating a prestressed composite beam.

종래의 부재분할형 프리스트레스트 합성빔은 차량 수송 상의 문제 등으로 인하여 공장에서는 강형만 제작하고 교량 시공현장으로 운반한 후 넓게 확보된 작업장에서 부재를 용접하고 제작대 상에서 프리스트레스트 합성빔으로 완성한 후 대형 크레인을 이용하여 교각 위에 가설한 후 상부 바닥판 콘크리트를 타설하는 순으로 시공해 왔다.Conventional member split type prestressed composite beams are manufactured only in the factory due to problems in transportation, and transported to the bridge construction site, welded the members in a widely secured workshop, and finished with prestressed composite beams on the production platform. Construction has been carried out in the order of placing concrete on top of the bridge using cranes and then placing concrete on the upper deck.

교량 시공현장에서는 적어도 3000㎡ 이상의 넓은 프리스트레스트 합성빔 제작용 작업장이 필요하다. 또, 현장의 프리스트레스트 합성빔 제작 작업장은 넓고 평탄해햐 되고, 또 보재를 용접할 때에는 바람 등의 영향이 적고 거리상 교량 가설현장과 가까워야한다. 이러한 조건들을 충족시키기 위해서는 부대비용이 막대하고, 현장에서의 부재 용접작업은 품질관리가 곤란하다.Bridge construction sites require a workshop for the production of wide prestressed composite beams of at least 3000 m2. In addition, the prestressed composite beam production workshop on the site should be wide and flat, and the welding of the beams should be less influenced by wind and closer to the bridge construction site on the street. In order to meet these conditions, the cost is enormous, and on-site member welding is difficult to control quality.

종래의 부재분할형 프리스트레스트 합성빔용 강형, 즉 부재는 도 1에 예시한 바와 같이 필요한 길이의 강재를 3,4등분하여 복수의 부재로 하고, 각 부재의 연결부는 용접 또는 연결판과 고장력 보울트를 사용하여 연결한 다음에 연결부에 꺽임하중재하 등의 방법으로 압축력을 도입한다. 각 부재의 연결부는 프리플렉션 하중에 의한 강형의 변형을 고려하여 접촉예각을 둔다.Conventional member splitting type prestressed composite beam steel, that is, the member is divided into three or four pieces of steel having a required length as illustrated in FIG. 1 to form a plurality of members, and the connecting portion of each member is welded or a connecting plate and a high tension bolt. After the connection is made, the compressive force is introduced by a method such as bending load. The connection part of each member gives a contact acute angle in consideration of the deformation of the steel by the preflection load.

각 부재의 연결부에 솟음을 주어 제작된 강형에 프리플렉션 하중을 가하여 강형이 휘어지게 한다. 이 상태에서 도 2와 같이 강형의 하부 플랜지에 하부 케이싱 콘크리트를 타설하고, 하부 케이싱 콘크리트가 양생되면 프리플렉션 하중을 서서히 제거하는 방법으로 제작하였다.The joints of each member are raised to apply the deflection load to the manufactured steels so that the steels are bent. In this state, as shown in FIG. 2, the lower casing concrete is poured into the lower flange of the steel, and when the lower casing concrete is cured, the preflection load is gradually removed.

하지만 이 방법은 각 부재의 연결부에 대한 솟음량을 정확히 제어하기 곤란하고, 꺽임하중을 재하할 때 연결부에서의 급격한 굴곡으로 인하여 균등한 압축력을 도입하기도 어려웠다.However, this method is difficult to precisely control the amount of rise to the connection part of each member, and it is difficult to introduce even compressive force due to the sudden bending at the connection part when loading the bending load.

따라서 본 발명의 목적은 부재들의 연결부에 대한 솟음량의 정확성을 도모하고, 균등하게 압축력을 도입히며, 교량 시공현장의 작업장 점유면적에 구애받지 않고 간편하게 조립하여 시공할 수 있는 프리스트레스트 합성빔을 제공하는 것이다.Accordingly, an object of the present invention is to provide a prestressed composite beam that promotes the accuracy of the rising amount of the connecting portion of the members, evenly compressive force, and can be easily assembled and constructed regardless of the occupational footprint of the bridge construction site. It is.

본 발명은 공장에서 부재간 이음새가 없는 단일 강재로 강형을 제작하여 솟음량 및 꺽임하중 재하 등의 공정에서 발생할 수 있는 오차를 최소화한다.The present invention minimizes the errors that may occur in processes such as rising amount and bending load by making a steel mold with a single steel without a member between parts in a factory.

또, 상기 단일형 강형에 프리플렉션 하중이 재하된 상태에서 하부 플랜지에서 분할되는 부위를 제외하고 하부 케이싱 콘크리트를 타설하여 양생시킨 후 플리플렉션 하중이 제거된 상태에서 하부 케이싱 콘크리트가 타설되지 아니한 부위를 분할하여 압축력을 도입함으로서 균등한 압축력을 도입한다.In addition, after the curing of the lower casing concrete except for the portion divided from the lower flange in the state of the pre-flection load is loaded on the single-type steel, the portion of the lower casing concrete is not poured in the state where the removal of the flexion load is removed By introducing a compressive force, an even compressive force is introduced.

그리고 상기 각 부재를 교량 공사현장으로 운반하여 임시받침 위에 얹어서 압축력을 도입한 상태에서 연결부의 하부 플랜지에 연결부 케이싱 콘크리트를 타설하여 양생시킨 후에 서서히 임시받침을 제거하여 연결부 케이싱 콘크리트에 압축력을 도입합으로서 완벽한 능력을 발휘하는 프리스트레스트 합성빔을 얻는 것을 특징으로 한다.Then, each member is transported to the bridge construction site, placed on the temporary support, and the compressive force is introduced, and the joint casing concrete is poured into the lower flange of the connection to cure, and then the temporary support is gradually removed to introduce the compressive force to the connecting casing concrete. It is characterized by obtaining a prestressed composite beam exhibiting perfect capability.

도 1은 프리플렉션 하중이 걸리는 부위를 예시한 종래 프리스트레스트 합성빔의 정면도1 is a front view of a conventional prestressed composite beam illustrating the site under preflection load;

도 2는 도 1의 부재분해도2 is an exploded view of the member of FIG.

도 3은 본 발명의 단초를 제공하는 프리스트레스트 합성빔용 강형의 정면도3 is a front view of a steel for prestressed composite beams providing the sheath of the present invention

도 4는 프리플렉션 하중이 걸린 상태의 정면도4 is a front view of a state in which a preflection load is applied;

도 5는 프리플렉션 하중이 걸린 상태에서 하부 플랜지에 하부 케이싱 콘크리트를 타설한 경우의 정면도5 is a front view in the case where the lower casing concrete is poured on the lower flange while the preflection load is applied;

도 6은 하부 케이싱 콘크리트 양생 후 꺽임하중을 제거하여 릴리즈된Figure 6 is released by removing the bending load after curing the lower casing concrete

프리스트레스트빔을 분할한 프리스트레스트 합성빔 부재의 정면도Front view of the prestressed composite beam member divided into prestressed beams

도 7은 교량 시공현장에서 상기 프리스트레스트 합성빔 부재를 임시받침으로 지지한 가운데 조립한 프리스트레스트 합성빔의 정면도7 is a front view of the prestressed composite beam assembled while supporting the prestressed composite beam member as a temporary support at a bridge construction site;

도 8은 조립된 프리스트레스트 합성빔에 고정장치로 지상에 고정시킨8 is fixed to the ground by the fixing device to the assembled prestressed composite beam

상태의 정면도Front view of the condition

도 9는 프리스트레스트 합성빔의 연결부에 연결부 콘크리트를 타설한 경우의 정면도9 is a front view in the case where the connection concrete is poured into the connection portion of the prestressed composite beam

도 10은 임시받침이 제거된 상태의 정면도10 is a front view of a state where the temporary support is removed

도 11은 상기 프리스트레스트 합성빔을 교각 위에 설치한 상태도11 is a state diagram in which the prestressed composite beam is installed on a piers;

도 12는 프리스트레스트 합성빔의 상판 콘크리트 및 복부 콘크리트를 타설한 상태도12 is a state diagram in which the top concrete and the abdominal concrete of the prestressed composite beam

<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for the main parts of the drawings>

1 : 강형1a,a',b : 부재1: Steel type 1a, a ', b: member

2 : 솟음3 : 프리플렉션 하중2: rising 3: preflection load

4 : 하부 플랜지5 : 하부 케이싱 콘크리트4: lower flange 5: lower casing concrete

6 : 임시받침7 : 강재6: temporary support 7: steel

8 : 연결부 콘크리트8: connection concrete

도 3에서, 강형(1)은 설계한대로 전체를 단일체로 하고, 공장에서 분할될 지점에 소정의 솟음(2)을 준다.In FIG. 3, the rigid 1 is unitary as designed and gives a predetermined rise 2 to the point to be split at the plant.

도 4에서, 솟음(2)이 주어진 강형(1)에 프리플렉션 하중(3)을 가하여아래로휘어지게 한다.In FIG. 4, the rise 2 is bent downward by applying a preflection load 3 to a given rigid 1.

도 5에서, 프리플렉션 하중(5)이 재하된 상태에서 강형(1)의 하부 플랜지(4)중 분할선 부위를 제외한 부위에 하부 케이싱 콘크리트(5)를 타설한다. 그리고 하부 케이싱 콘크리트(5)가 양생되면 서서히 프리플렉션 하중(5)을 제거한다.In FIG. 5, the lower casing concrete 5 is poured in the part except the dividing line part of the lower flange 4 of the steel mold 1 in the state which the preflection load 5 was loaded. Then, when the lower casing concrete 5 is cured, the preflection load 5 is gradually removed.

도 6에서, 하부 케이싱 콘크리트(5)가 타설되지 아니한 부위(6)를 절단하여 복수의 부재(1a,1b,1a')로 분할하여 교량 시공현장으로 운반한다.In Figure 6, the lower casing concrete (5) is cut to the portion (6) is not poured, divided into a plurality of members (1a, 1b, 1a ') and transported to the bridge construction site.

도 7에서, 교량 시공현장에 유압잭 등의 임시받침(6)에 각 부재(1a,1b,1a')를 일렬로 올려 놓는다.In Fig. 7, each member 1a, 1b, 1a 'is placed in a row on a temporary support 6 such as a hydraulic jack at a bridge construction site.

도 8에서, 각 부재(1a,1b,1a')의 연결부위를 와이어 로우프 등의 강재(7)로 지상에 고정한다.In Fig. 8, the connecting portions of the respective members 1a, 1b, 1a 'are fixed to the ground with steel materials such as wire ropes.

도 9에서, 이 상태에서 임시받침(6)을 올려 솟음 준 후 각 연결부에 고강도 콘크리트를 타설하여 연결부 케이싱 콘크리트(8)를 양생한다.In Fig. 9, after raising the temporary support 6 in this state, the high-strength concrete is poured into each connection portion to cure the connection casing concrete 8.

도 10에서, 연결부 케이싱 콘크리트(8)가 양생이 완료되면 임시받침(6)을 서서히 내려서 연결부 콘크리트(8)에 압축력을 도입한다. 그 후 임시받침(6)과 강재(7)를 제거한다.In FIG. 10, when curing of the connection casing concrete 8 is completed, the temporary support 6 is slowly lowered to introduce a compressive force to the connection concrete 8. Then remove the temporary support (6) and the steel (7).

도 11에서, 이런 순서로 조립하여 완성된 프리스트레스트 합성빔(9)을 교각(10) 상단에 가설하고, 도 12와 같이 상부 플랜지(11) 위에는 상판 콘크리트(12)를 그리고 웨브에는 복부 콘크리트(13)를 타설하는 식으로 교량을 시공한다.In FIG. 11, the prestressed composite beam 9 completed by assembly in this order is hypothesized on the top of the piers 10, and as shown in FIG. 12, the top concrete 12 is formed on the upper flange 11, and the abdominal concrete ( Construct the bridge by pouring 13).

이상과 같은 본 발명의 부재분할형 프리스트레스트 합성빔은 단일체형 강형에 솟음과 프리플렉션 하중을 재하하여 하부 케이싱 콘크리트를 타설 양생한 후에 분할함으로서 부재 연결부에 대한 솟음량을 정확히 구사할 수 있고 또한 압축력도 균등하게 도입할 수 있다.The member split type prestressed composite beam of the present invention as described above is capable of accurately using the amount of rise to the member joint by dividing after curing the lower casing concrete by loading and preflection load on the monolithic steel, and also compressive force. It can be introduced evenly.

또, 교량 시공현장으로 운반하여 조립하고 거기다 임시받침으로 솟음을 가한 상태에서 연결부 콘크리트를 타설하여 양생하고 임시받침을 제거하여 완성할 때 그 점유면적을 저게 차지하므로 부지난과 비용부담을 덜 수 있다.In addition, it is possible to reduce the burden and cost burden because it occupies the occupied area when the concrete is connected and cured by removing the temporary support while completing the transportation by assembling the bridge construction site and raising it with temporary support. .

Claims (1)

공장에서 프리스트레스트 빔의 설계장대로 단일화한 강형을 사용하여, 분할될 지점에 소정의 솟음을 주는 단계와; 솟음이 주어진 강형에 프리플렉션 하중을 가하는 단계와; 프리플렉션 하중이 재하된 상태에서 강형의 하부 플랜지중 분할선 부위를 제외한 부위에 하부 케이싱 콘크리트를 타설허여 양생하는 단계와; 하부 케이싱 콘크리트가 양생된 후 프리플렉션 하중을 제거하고 하부 케이싱 콘크리트가 타설되지 아니한 부위를 절단하여 복수의 부재로 분할하는 단계와; 교량 시공현장에서 임시받침 위에 각 부재를 일렬로 올려 놓고 각 부재의 연결부위를 와이어 로우프 등의 강재로 지상에 고정하는 단계와; 임시받침을 올려 솟음을 준 다음에 각 부재의 연결부에 연결부 케이싱 콘크리트를 타설하여 양생하는 단계와; 연결부 케이싱 콘크리트 양생 후 임시받침을 서서히 내려서 연결부 콘크리트에 압축력을 도입하는 단계로 이루어지는 프리스트레스트 합성빔의 분할제작방법.Giving a predetermined rise to a point to be divided, using a steel unit which is unified according to the design length of the prestressed beam in the factory; Applying a preflection load to the steel given the rise; Placing and curing curing of the lower casing concrete at a portion other than the dividing line portion of the lower flange of the steel under the pre-loading load; Removing the preflection load after the lower casing concrete is cured and cutting a portion of the lower casing concrete in which the lower casing concrete is not poured and dividing it into a plurality of members; Placing each member in a row on a temporary support at a bridge construction site and fixing the connection portion of each member to the ground with steel such as a wire rope; Raising the temporary support and pouring the casing concrete at the connection part of each member to cure; Connection casing After curing the concrete, the temporary supporting beam is gradually lowered to introduce a compressive force to the connection concrete.
KR10-2001-0072981A 2001-11-22 2001-11-22 method for manufacturing prestressed composite beam by division mode KR100476837B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR10-2001-0072981A KR100476837B1 (en) 2001-11-22 2001-11-22 method for manufacturing prestressed composite beam by division mode

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR10-2001-0072981A KR100476837B1 (en) 2001-11-22 2001-11-22 method for manufacturing prestressed composite beam by division mode

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR2020010036007U Division KR200266419Y1 (en) 2001-11-22 2001-11-22 prestressed composite beam

Publications (2)

Publication Number Publication Date
KR20030042267A true KR20030042267A (en) 2003-05-28
KR100476837B1 KR100476837B1 (en) 2005-03-18

Family

ID=29570833

Family Applications (1)

Application Number Title Priority Date Filing Date
KR10-2001-0072981A KR100476837B1 (en) 2001-11-22 2001-11-22 method for manufacturing prestressed composite beam by division mode

Country Status (1)

Country Link
KR (1) KR100476837B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020041798A (en) * 2002-05-09 2002-06-03 영 제 박 The method of construction in a more than three span continous composite girder bridges with a lifting up and down inner supports, simultaneously
KR20020050196A (en) * 2002-05-04 2002-06-26 영 제 박 The method of construction without a lifting up for a multi-span continous composite girder
KR101104297B1 (en) * 2011-03-28 2012-01-11 주식회사 도화엔지니어링 Preflex girder making method and bridge construction method using the same

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101194932B1 (en) 2011-05-06 2012-10-25 유호토건(주) Manufacturing method of steel beam with essentric prestressing plate
KR101527752B1 (en) * 2013-09-17 2015-06-12 구호원 Construction method of prestressed composite girder bridge

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100274141B1 (en) * 1998-09-28 2000-12-15 이무일 Manufacturing method of preplex composite beem by divisional method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020050196A (en) * 2002-05-04 2002-06-26 영 제 박 The method of construction without a lifting up for a multi-span continous composite girder
KR20020041798A (en) * 2002-05-09 2002-06-03 영 제 박 The method of construction in a more than three span continous composite girder bridges with a lifting up and down inner supports, simultaneously
KR101104297B1 (en) * 2011-03-28 2012-01-11 주식회사 도화엔지니어링 Preflex girder making method and bridge construction method using the same

Also Published As

Publication number Publication date
KR100476837B1 (en) 2005-03-18

Similar Documents

Publication Publication Date Title
KR100380637B1 (en) Prestressed concrete girder of adjustable load bearing capacity for bridge and adjustment method for load bearing capacity of bridge
CA2717260A1 (en) Method for constructing precast coping for bridge
US5301483A (en) Composite, prestressed structural member and method of forming same
KR101860512B1 (en) Method for reinforcing cross section installation of ground and underwater structure using integral mold module
US5867855A (en) Method for connecting precast concrete girders
KR100476837B1 (en) method for manufacturing prestressed composite beam by division mode
KR101562767B1 (en) The temporary bridge using prestress steel materials and prestress tendon and foundation method of temporary bridge
KR100767388B1 (en) Segment girder construction method for bridge
KR100438013B1 (en) Method of division manufacturing and construction of prestressed composite beam using supporting members
KR19980071920A (en) Construction method of preflex composite type by factory production
KR100700916B1 (en) The preflex type and loading device with 3 loading point
US5553439A (en) Composite, prestressed structural members and methods of forming same
KR200266419Y1 (en) prestressed composite beam
KR102222019B1 (en) Camber Connection Supporter of bent pressed girder and Bridge construction method therewith
KR100561034B1 (en) Connecting method for segmental prestressed preflex steel composite beam
KR100430243B1 (en) Prestressed composition pile and the manufacturing process
KR20020067078A (en) The method of preflex composite beam made by using the hunch concrete represtressing the lower casing concrete
KR100402146B1 (en) The method of a continuous preflex composite girder with shifting up and down
JP7012486B2 (en) Bridge construction method
CN112482193A (en) Method for applying compressive stress to concrete slab in hogging moment area of combination beam, main beam and cable-stayed bridge
KR20110093158A (en) Concrete forming load steel complex girder and this construction technique
KR20020023602A (en) Bridge slab construction method and precast concrete plate applied therein
KR100449230B1 (en) Method for manufacturing H-type rolled steel beam by prestressing H-type rolled steel manufactured using high intensity steel plate and bolt, and method for constructing bridge using the H-type rolled steel beam
KR200230089Y1 (en) Shifting up and down system of continuous preflex composite girder on temporary support
KR102485849B1 (en) Manufacturing method of pre-flex composite beam that causes bulging due to plastic deformation of steel beam

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20110307

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20140305

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20150310

Year of fee payment: 11

LAPS Lapse due to unpaid annual fee