KR100561034B1 - Connecting method for segmental prestressed preflex steel composite beam - Google Patents

Connecting method for segmental prestressed preflex steel composite beam Download PDF

Info

Publication number
KR100561034B1
KR100561034B1 KR1020030040886A KR20030040886A KR100561034B1 KR 100561034 B1 KR100561034 B1 KR 100561034B1 KR 1020030040886 A KR1020030040886 A KR 1020030040886A KR 20030040886 A KR20030040886 A KR 20030040886A KR 100561034 B1 KR100561034 B1 KR 100561034B1
Authority
KR
South Korea
Prior art keywords
composite beam
segmented
steel
lower flange
concrete
Prior art date
Application number
KR1020030040886A
Other languages
Korean (ko)
Other versions
KR20040110958A (en
Inventor
정재희
박은진
Original Assignee
정재희
박은진
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 정재희, 박은진 filed Critical 정재희
Priority to KR1020030040886A priority Critical patent/KR100561034B1/en
Publication of KR20040110958A publication Critical patent/KR20040110958A/en
Application granted granted Critical
Publication of KR100561034B1 publication Critical patent/KR100561034B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/07Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
    • E04F13/08Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
    • E04F13/0801Separate fastening elements
    • E04F13/0832Separate fastening elements without load-supporting elongated furring elements between wall and covering elements
    • E04F13/0853Separate fastening elements without load-supporting elongated furring elements between wall and covering elements adjustable perpendicular to the wall

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Rod-Shaped Construction Members (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

본 발명은 분절부가 블록아웃된 프리스트레스트 프리플렉스 강합성빔을 공장에서 제작한 후, 현장에서 일체화시키되 인장재의 정착 시 강합성빔 하부플랜지 콘크리트에 2차프리스트레스가 도입됨과 동시에 분절부에도 압축력이 도입될 수 있도록 하여, 강합성빔을 보다 확실하게 일체화시킬 수 있는 분절된 프리스트레스트 프리플렉스 강합성빔의 일체화방법에 관한 것이다. 본 발명에 의하여 분절된 프리스트레스트 프리플렉스 강합성빔을 현장에서 일체화함에 있어 현장 작업을 최소화시킬 수 있어 작업공기 및 공사비를 절약할 수 있으며, 장경간의 강합성빔 제작을 위한 제작 장소 확보의 어려움을 해결 할 수 있어 매우 경제적인 교량 시공이 가능하게 된다.According to the present invention, the prestressed preflex steel composite beam with the segmented block out is manufactured in the factory, and then integrated at the site, but the secondary prestress is introduced into the steel composite beam lower flange concrete at the time of fixing the tension member, and at the same time, the compressive force is introduced into the segmented portion. The present invention relates to a method for integrating a segmented prestressed preplex rigid composite beam, which can be more reliably integrated. Integrating the prestressed preflex steel composite beam segmented by the present invention in the field can minimize the field work, thereby saving the work air and construction cost, and the difficulty of securing the production place for the production of the steel composite beam between long diameters. It is possible to solve the problem, so it is possible to construct a very economical bridge.

강합성빔, 분절, 2차프리스트레싱Composite Beam, Segmented, Secondary Prestressing

Description

분절된 프리스트레스트 프리플렉스 강합성빔의 일체화방법{Connecting method for segmental prestressed preflex steel composite beam}Connecting method for segmental prestressed preflex steel composite beam}

도1a는 본 발명의 3분절된 강형(I형 강재)을 기계적으로 연결(볼트, 용접 )시켜 일체화된 I형 강재를 측면도 및 정면도로 도시한 것이며,Figure 1a is a side view and a front view of the I-shaped steel integrated by mechanically connecting (bolt, welding) of the three-segmented steel (I-shaped steel) of the present invention,

도1b는 상기 3분절된 I형 강재에 프리플렉션하중(Pf)을 가한 상태를 측면도 및 정면도로 도시한 것이고,Figure 1b is a side view and a front view showing a state in which the pre-flection load (Pf) is applied to the three-segment I-shaped steel,

도1c는 3분절된 I형 강재에 프리플렉션하중이 가해진 상태에서 중간강형에 인장재를 배치하고 1형 강재의 분절부를 제외한 상태에서 하부플랜지콘크리트를 타설, 양생시킨후 상기 프리플렉션하중을 제거한 상태를 측면도 및 정면도로 도시한 것이며,Figure 1c is a state in which the pre-flection load is applied to the three-segment I-type steel, the tension member is placed in the intermediate steel, and the lower flange concrete is poured and cured after excluding the segment of the type 1 steel. Shown in side and front views,

도1d는 프리플렉션하중(Pf)의 제거(릴리즈)에 의하여 1차프리스트레스가 도입된 강합성빔을 현장에 반입시키기 위하여 분절시킨 상태를 측면도 및 정면도로 도시한 것이며,FIG. 1D shows a side view and a front view showing a state in which the composite beam, in which the primary prestress is introduced, is introduced to the site by removing (releasing) the preflection load Pf.

도1e는 상기 분절된 강합성빔을 현장에 반입하여 다시 조립(볼트 또는 용접)시켜 일체화시킨 상태를 측면도 및 정면도로 도시한 것이며,FIG. 1E illustrates a side view and a front view of a state in which the segmented rigid composite beam is brought into the field and assembled again (bolt or welded) to be integrated;

도1f는 상기 일체화된 강합성빔을 교량하부구조물에 거치하고 상부슬래브를 타설, 양생하고, 하부플랜지콘크리트를 연결시킨 상태를 측면도 및 정면도로 도시 한 것이고,Figure 1f is a side view and a front view showing a state in which the integrated rigid composite beam is mounted on the bridge lower structure, the upper slab is poured, cured, and the lower flange concrete is connected.

도2a는 인장재를 강합성빔의 양단부에 설치한 정착장치를 이용하여 긴장 후 정착시켜 강합성빔에 2차 프리스트레스가 도입된 상태를 측면도 및 정면도로 도시한 것이다.Figure 2a is a side view and a front view showing a state in which the secondary prestress is introduced to the rigid composite beam by tensioning and fixing using a fixing device provided on both ends of the rigid composite beam.

도2b는 도2a에 추가적인 인장재가 강합성빔의 양단부의 정착장치에 긴장 후 정착되어 강합성빔에 추가적인 2차프리스트레스가 도입된 상태를 측면도 및 정면도로 도시한 것이며,FIG. 2B is a side view and a front view of a state in which an additional tension member is tensioned in the fixing device at both ends of the steel composite beam and additional secondary prestress is introduced in the steel composite beam in FIG.

도2c는 상기 도1c와 비교하여 중간강형에 인장재를 배치하지 않은 상태에서 분절부를 제외한 하부플랜지콘크리트가 타설, 양생된 강합성빔을 측면도 및 정면도로 도시한 것이며,FIG. 2C illustrates a side view and a front view of the steel composite beam in which the lower flange concrete, except for the segmented portion, is poured and cured in a state in which no tension member is disposed in the intermediate steel as compared to FIG.

도2d, 도2e, 도2f, 도2g, 도2h, 도2i 및 도2j는 도2c의 강합성빔에 2차 프리스트레스를 도입시키기 위한 인장재 설치예를 측면도 및 정면도로 도시한 것이다.2D, 2E, 2F, 2G, 2H, 2I and 2J show side and front views of an example of installing a tension member for introducing secondary prestress to the rigid composite beam of FIG. 2C.

도3a,도3b,도3c,도3d,도3e,도3f,도3g 및 도3h는 본 발명의 정착장치 및 인장재의 다양한 설치예를 측면도 및 정면도로 도시한 것이다.3A, 3B, 3C, 3D, 3E, 3F, 3G, and 3H show side and front views of various installation examples of the fixing device and the tension member of the present invention.

〈도면의 주요 부호의 설명〉<Explanation of main code of drawing>

100:I형 강재 200:인장재(비접착PC스트랜드 포함)100: I type steel 200: Tensile material (including non-bonded PC strand)

300:하부플랜지콘크리트 400:강합성빔300: lower flange concrete 400: steel composite beam

500:교량상부구조물콘크리트 600:정착장치500: bridge upper structure concrete 600: fixing device

본 발명은 분절된 프리스트레스트 프리플렉스 강합성빔의 일체화방법에 관한 것이다. 더욱 구체적으로 분절된 프리스트레스트 프리플렉스 강합성빔을 일체화하는 방법에 관한 것으로서, 종래 하나의 경간을 일괄 현장 제작하여야 하는 프리스트레스트 프리플렉스 강합성빔을 공장에서 제작 후 분절시켜 현장에 반입하여 다시 일체화시킴에 있어, 인장재에 의한 2차프리스트레스 도입 시 강합성빔의 하부플랜지콘크리트에 2차프리스트레스가 도입됨과 동시에 분절부에도 압축력이 도입될 수 있도록 하여, 분절부의 하부플랜지콘크리트를 확실하게 일체화 되도록 한 분절된 프리스트레스트 프리플렉스 강합성빔의 일체화방법에 관한 것이다.The present invention relates to a method of integrating a segmented prestressed preflex rigid composite beam. More specifically, the present invention relates to a method of integrating a segmented prestressed preflex steel composite beam, which is conventionally manufactured after the production of one pre-segmented prestressed preflex steel composite beam in a factory, and then segmented into a site to be integrated again. When the secondary prestress is introduced by the tension member, the secondary prestress is introduced to the lower flange concrete of the steel composite beam, and the compressive force is also introduced to the segment portion, so that the lower flange concrete of the segment portion is reliably integrated. The present invention relates to a method for integrating a prestressed preflex rigid composite beam.

본 발명과 관련되는 종래의 프리플렉스 강합성빔(Preflex Steel Composite Beam)은 1950년대 초반에 벨기에에서 개발된 교량용 빔으로써, 고장력 강판 등으로 제작한 I형 강재(I형 girder)에 일정한 하중(Pf하중)을 재하하여 미리 설계최대휨모멘트(Pf Moment)를 발생시킴으로써 처짐 변형을 수반시킨 상태에서, 하부플랜지에 일정단면의 콘크리트를 타설, 양생한 후 미리 재하한 상기 하중(Pf하중)을 제거하여 상기 수반된 처짐변형을 복귀시키는 과정에서 하부플랜지 콘크리트에 압축 프리스트레스를 도입시킨 것으로서, 일정한 지간 및 설계하중조건에서 PC빔(prestress concrete beam)교 등 다른 어떤 교량가설공법보다 형고가 상당히 낮아 형하 공간의 효율적인 활용을 도모할 수 있게 되는 등의 장점이 있어 현재 교량시공에 많이 이용되어 왔다.The conventional Preflex Steel Composite Beam related to the present invention is a bridge beam developed in Belgium in the early 1950s, and has a constant load on a type I steel (I type girder) made of high tensile steel sheet or the like. Pf load) to generate the design maximum bending moment in advance, and in the state accompanied with deflection deformation, remove the load (Pf load) previously loaded after placing and curing concrete of a certain section on the lower flange. Compression prestress was introduced into the lower flange concrete in the process of restoring the accompanying deflection deformation, and the mold height was considerably lower than any other bridge construction method such as a PC beam (prestress concrete beam) bridge under constant interval and design load conditions. It has been used in bridge construction because of its advantages such as being able to promote efficient use of it.

하지만 상기 프리플렉스 강합성빔은 다른 별도의 수단 없이 하부플랜지콘크 리트의 균열발생을 허용하지 않기 위한 목적으로 종래의 프리플렉스 강합성빔을 완전프리스트레싱 방식으로 설계할 경우 일정한 지간 및 하중조건에서 단면이 더욱더 커지고, 형고가 높아지게 되어 프리플렉스 강합성빔의 근본적인 장점을 모두 잃게 되므로 제한된 조건으로서 필연적으로 부분프리스트레싱(partial prestressing)으로 설계 및 시공할 수밖에 없었고,However, when the preflex rigid composite beam is designed in a completely prestressing manner for the purpose of not allowing cracking of the lower flange concrete without any other means, the preflex rigid composite beam has a cross section at a constant interval and load conditions. As they become larger and higher in shape, they lose all of the fundamental advantages of the preflex steel composite beam, which inevitably has to be designed and constructed with partial prestressing.

상기 부분프리스트레싱에 의한 설계방식을 따르는 경우, 하부플랜지콘크리트에 미리 도입시키는 프리스트레스 압축응력의 크기를 낮은 형고 유지라는 근본적인 장점을 고수하기 위하여 제한된 I형 강재의 형고 높이와 그에 따라 제한된 처짐 및 복귀 변형량의 크기를 기준으로 설계, 시공되므로, 하부플랜지콘크리트에 큰 크기의 인장응력(부득이한 경우 부분프리스트레싱에 의한 설계 시에도 고려될 수 없을 정도의 큰 인장응력)이 발생할 수밖에 없었다.In the case of following the partial prestressing design method, in order to adhere to the fundamental advantage of maintaining a low profile of the prestressed compressive stress introduced into the lower flange concrete, the limited height of the I-shaped steel and thus the limited deflection and return deformation Since it is designed and constructed on the basis of size, a large tensile stress (a large tensile stress that cannot be considered even when designing by partial prestressing) is inevitably generated in the lower flange concrete.

이에 상기 부분프리스트레싱 방식에 의한 설계방식의 채택 및 하부플랜지콘크리트에서의 과도한 인장응력 발생은 결국 하부플랜지콘크리트의 과도한 인장균열 및 처짐 현상 등을 초래하므로 강합성빔의 내구성 등에 있어 심각한 영향을 초래할 수밖에 없었다.Therefore, adopting the design method by the partial prestressing method and generating excessive tensile stress in the lower flange concrete eventually leads to excessive tensile cracking and deflection of the lower flange concrete, which inevitably causes serious effects on the durability of the steel composite beam. .

이에 종래의 프리플렉스 강합성빔의 장점인 낮은 형고를 그대로 유지하고 경제성을 그대로 유지하면서 완전프리스트레싱(full prestressing)으로 설계 제작하여 하부플랜지콘크리트의 인장균열과 그로 인한 과도한 처짐 및 급격한 피로강도의 저하를 방지하는 프리스트레스트 프리플렉스 강합성빔이 개발되었는데,Therefore, it is designed and manufactured with full prestressing while maintaining the low profile, which is the advantage of the conventional preflex steel composite beam, and maintaining the economical efficiency, thereby reducing the tensile cracking of the lower flange concrete, resulting in excessive sagging and rapid decrease in fatigue strength. A prestressed preflex composite beam has been developed to prevent

이 방법은 종래의 프리플렉스 강합성빔의 단면에서 하부플랜지콘크리트에 균 열발생 모멘트의 크기에 대처할 수 있도록, 하부플랜지콘크리트 양생 종료 후 미리 재하 하였던 일정 하중(Pf하중)을 제거하여, 하부플랜지콘크리트에 1차 프리스트레스를 도입시킨 후(release후) 하부플랜지콘크리트 내부에 미리 배치된 인장재(비접착 PC 스트랜드)를 인장하고, 정착장치로서 정착하여 하부플랜지콘크리트에 추가적인 2차 프리스트레스를 추가로 도입함으로써 이에 의한 강합성빔 내부의 저항모멘트를 증가시켜 기존의 프리플렉스 강합성빔의 형고를 그대로 유지하면서도 하부플랜지콘크리트에 인장응력이 전혀 발생하지 않는 완전프리스트레싱(full prestressing) 방식으로 설계가 이루어질 수 있도록 한 것이다.In order to cope with the magnitude of the crack generation moment in the lower flange concrete in the cross section of the conventional preflex rigid composite beam, the lower flange concrete is removed by removing the predetermined load (Pf load) previously loaded after the lower flange concrete curing is finished. After the primary prestress was introduced (after release) into the lower flange concrete, the tension member (non-bonded PC strand) pre-arranged in the lower flange concrete was tensioned and fixed as a fixing device to introduce additional secondary prestress to the lower flange concrete. By increasing the resistance moment inside the composite beam, the design of the composite beam can be designed in a full prestressing manner in which the tensile stress does not occur at all on the lower flange concrete while maintaining the shape of the existing composite beam. .

그러나 프리스트레스트 프리플렉스 강합성빔은 장경간의 경우 공장에서 다수의 I형 강재를 하나의 강재 I형 빔으로 연결하고, 하나의 경간을 형성하는 프리스트레스트 프리플렉스 강합성빔으로 현장에서 일괄 제작하여 설치해왔기 때문에 강합성빔 가설위치 부근에 넓은 제작장을 필요로 하고, 상당히 많은 강합성빔 제작장비를 현장에 투입하여야 하고, 투입된 장비 중 일회성 재료가 상당하여 공기 및 공사비의 증가요인으로 작용하고, 현장 작업의 비중이 공장제작에 비해 지나치게 많은 등, 프리스트레스트 프리플렉스 강합성빔 제작에 효율화를 도모할 필요성이 제기되었다.However, in case of long span, prestressed preflex steel composite beam is connected to a large number of I-type steels in a factory in one factory, and is fabricated and installed in the field as a prestressed preflex steel composite beam that forms one span. Since it requires a large production site near the location of the steel composite beam construction site, a large number of steel composite beam manufacturing equipment should be put in the field, and the one-off material among the input equipment is considerable, which acts as an increase factor of air and construction cost. The necessity of improving the efficiency of prestressed preflex steel composite beams has been raised.

본 발명의 목적은 분절된 프리스트레스트 프리플렉스 강합성빔의 현장에서의 일체화 작업에 있어 분절부 뿐만 아니라 강합성빔 전체에 걸쳐 하부플랜지콘크리트에 2차프리스트레스를 효율적으로 도입시킴으로서, 단순교 또는 연속교 방식의 프 리스트레스트 프리플렉스 강합성빔을 이용한 교량시공에 있어 장경간의 강합성빔 제작을 위한 제작 장소 확보의 어려움을 해결 할 수 있고, 현장에서의 노력을 최소화시켜 교량 시공공기 및 공사비를 절약하고, 공장제작을 통한 품질향상을 도모하기 위한 방법을 제공하는 것이다.SUMMARY OF THE INVENTION An object of the present invention is to provide a simple bridge or continuous bridge by efficiently introducing secondary prestress into the lower flange concrete not only at the segment but also throughout the composite beam in the field integration work of the segmented prestressed preflex steel composite beam. It is possible to solve the difficulty of securing the production place for the production of the long-span steel composite beam in the bridge construction using the pre-presisted preflex steel composite beam, and to save the bridge construction air and the construction cost by minimizing the effort in the field. It is to provide a way to improve the quality through factory production.

본 발명은 상기 기술적과제를 달성하기 위하여, 여러 분절로 나누어진 I형 강재를 하나로 일체화시킨 후 프리플렉션하중을 가한 상태에서, 분절부를 제외하고 전체 I형 강재에 하부플랜지콘크리트를 타설, 양생하고, 상기 프리플렉션하중을 제거하여 하부플랜지콘크리트에 1차프리스트레스를 도입시킨 강합성빔을 공장(또는 현장부근 제작장)에서 제작하고, 제작된 강합성빔을 여러 분절로 다시 분리시킨후, 운반차량을 이용하여 현장에 반입하여 다시 강합성빔을 하나의 강합성빔으로 연결하여 일체화 시키게 된다.The present invention, in order to achieve the above technical problem, by integrating the I-type steel divided into several segments into one and then applying the preloading load, pour the lower flange concrete to the entire I-type steel except for the segmented portion, After removing the pre-loading load, the steel composite beam in which primary prestress is introduced into the lower flange concrete is manufactured at a factory (or near the site), and the manufactured steel composite beam is separated into several segments, and then the transport vehicle is Bringing it to the site by using it, the composite steel beam is connected to one composite steel beam and integrated.

이때 강합성빔에 형성된 I형 강재는 볼트 접합이나 용접 등으로 일체화시키고, 분절부를 포함한 하부플랜지콘크리트의 경우에는 분절부에 콘크리트(팽창콘크리트 포함)의 타설 또는 에폭시 수지를 충진시켜 하부플랜지콘크리트가 연속되어 형성되도록 한 상태에서, 강합성빔 중 중간에 형성되는 강합성빔의 하부플랜지콘크리트 내부에 공장에서 제작 시 미리 배치된 인장재를(비접착PC스트랜드 포함) 강합성빔 양 단부 부근의 하부플랜지 콘크리트 상부 또는 하부에 긴장,정착함으로서, 상기 분절부뿐만 아니라 하부플랜지콘크리트 전체에 걸쳐 2차프리스트레스가 도입되도록 하여 분절된 강합성빔을 효율적으로 일체화되도록 하는 것을 특징으로 한 다.(또한 인장재를 미리 하부플랜지콘크리트에 형성시키지 않은 상태로 공장 제작된 강합성빔을 현장에서 일체화시킨 후, 하부플랜지 콘크리트 외부의 상부 또는 하부로 인장재를 설치하거나, 하부플랜지 콘크리트 하부에서 상부로 가로지르도록 인장재를 설치하여 긴장 정착시킴으로서 하부플랜지콘크리트를 일체화시킬 수 있으며, 상기 방법을 적절하게 혼용하여 하부플랜지콘크리트를 일체화시킬 수도 있다.)In this case, the I-type steel formed in the composite beam is integrated by bolting or welding, and in the case of the lower flange concrete including the segmented part, the lower flange concrete is continuously filled by placing concrete (including expanded concrete) or epoxy resin in the segmented part. And the lower flange concrete near both ends of the composite beam (including non-adhesive PC strands), which is pre-positioned at the time of manufacturing at the factory, inside the lower flange concrete of the composite beam formed in the middle of the composite beam. By tensioning or fixing the upper or lower portion, the secondary prestress is introduced not only in the segment portion but also throughout the lower flange concrete, so that the segmented rigid composite beam is efficiently integrated. The factory manufactured steel composite beam is not formed on the flange concrete. After integrating at the lower flange concrete, the tension material may be integrated by installing a tension member to the upper or lower portion of the lower flange concrete exterior or by installing a tension member to cross from the lower flange concrete to the upper, and the method may be appropriately integrated. The bottom flange concrete can be used in combination.)

이에 본 발명의 특징에 따른 분절된 프리스트레스트 프리플렉스 강합성빔의 일체화방법을 본 발명이 속하는 기술분야에서 통상의 지식을 가지는 자가 용이하게 실시할 수 있는 가장 바람직한 실시예를 첨부된 도면을 참조로 상세히 설명한다Accordingly, with reference to the accompanying drawings, the most preferred embodiment which can be easily carried out by the person skilled in the art the method of integrating the segmented prestressed preflex steel composite beam according to the characteristics of the present invention. I explain in detail

본 발명의 분절된 프리스트레스트 프리플렉스 강합성빔의 일체화방법은The method of integrating the segmented prestressed preflex rigid composite beam of the present invention

공장에서 분절된 강형(100a, 100b,100c)을 조립한 후 프리프렉션하중(Pf)을 가하는 단계; 양 단부의 분절된 강형(110a,100c)을 제외한 적어도 하나 이상의 중간강형(100b)의 하부플랜지 주위에 케이싱콘크리트 내부에 매립되도록 인장재(200)를 설치한 상태 또는 미리 인장재를 하부플랜지콘크리트에 형성시키지 않은 상태에서, 분절부(A)를 제외한 강형에 하부플랜지콘크리트(300a,300b,300c)를 형성시킨후 상기 프리플렉션하중을 제거하여 1차 프리스트레스가 도입된 강합성빔(400)을 제작하는 단계; 분절된 강합성빔(400a,400b,400c)을 현장에 반입한 후 조립하여 교량상부구조물 콘크리트의 형성 및 분절부를 연결하는 단계; 상기 인장재를 강합성빔에 긴장 후 정착시켜 2차프리스트레스를 강합성빔(400)에 도입시키는 단계;를 포함한다.Assembling the segmented steel (100a, 100b, 100c) at the factory and then applying a prefraction load (Pf); The tension member 200 is installed to be embedded in the casing concrete around the lower flange of the at least one intermediate steel member 100b except for the segmented steel members 110a and 100c at both ends, or the tension member is not formed in the lower flange concrete in advance. In the non-state state, after forming the lower flange concrete (300a, 300b, 300c) in the steel except for the segment (A) to remove the preflection load to produce a steel composite beam 400 in which the primary prestress is introduced ; Bringing the segmented rigid composite beams (400a, 400b, 400c) into the site and assembling them to form the bridge upper structure concrete and connect the segments; And tensioning the tension member in the rigid composite beam to introduce secondary prestress into the rigid composite beam 400.

도1a는 본 발명의 3분절된 강형(I형 강재)을 기계적으로 연결(볼트, 용접등) 시켜 일체화된 I형 강재를 측면도 및 정면도로 도시한 것이다.Figure 1a shows a side view and a front view of the integrated I-type steel by mechanically connecting (bolt, welding, etc.) of the three-segmented steel (I-type steel) of the present invention.

공장(또는 현장부근 제작장)에서 I형 강재는 규격화된 길이로 제작된 후 운반하기에 적합하도록 분절된다. 3분절하는 것이 일반적이라고 할 수 있지만 장지간에 걸친 강합성빔을 제작하기 위하여 길이가 긴 I형강재가 필요한 경우 3분절 이상으로 분절할 수도 있다.In factories (or near-site workshops), Type I steels are manufactured to standard lengths and then segmented to be suitable for transport. Although three-segmentation is common, it may be segmented into three or more segments if a long I-shaped steel is required to produce a long composite beam over long spans.

본 발명에서는 I형 강재를 분절된 단부 강형(100a, 100c)과 중간 강형(100b)으로 구분한다.(단부 강형을 제외한 중간강형은 개수에 관계없이 모두 중간강형으로 본다.) 이때 I형 강재의 상부 및 하부플랜지는 겹침덧판을 이용하여 제작할 수도 있다. 이는 중간강형의 경우 외부하중에 의한 휨모멘트를 가장 많이 받는 부위이기 때문에 강성을 높이기 위하여 일종의 보강재라고 할 수 있는 겹침덧판을 이용하여 상부플랜지 및 하부플랜지를 두껍게 제작하는 것이 바람직하기 때문이다.In the present invention, the I-type steel is divided into segmented end steels (100a, 100c) and the middle steel (100b). (All the middle steel except the end steel is regarded as intermediate steel regardless of the number.) The upper and lower flanges can also be manufactured using overlapping plates. This is because in the case of the intermediate steel, since it is the site receiving the most bending moment due to external load, it is preferable to manufacture the upper flange and the lower flange thickly using the overlap plate, which is a kind of reinforcement material, in order to increase the rigidity.

나아가 분절부는 되도록 상기 휨모멘트가 크게 작용하는 곳을 피하는 것이 바람직하며, 분절된 I형 강재를 서로 볼트, 용접 등과 같은 기계적 연결장치를 이용하여 서로 연결시킨다. 이로서 일체화된 I형 강재(100)가 완성된다.Furthermore, it is preferable to avoid the place where the bending moment acts as large as possible, and the segmented I-type steels are connected to each other by using a mechanical connection device such as bolts and welding. This completes the integrated I-shaped steel 100.

도1b는 상기 일체화된 3분절의 I형 강재(100)에 프리플렉션하중(Pf)을 가한 상태를 측면도 및 정면도로 도시한 것이다.Figure 1b is a side view and a front view showing a state in which the pre-flection load (Pf) is applied to the integrated three-piece I-shaped steel 100.

이는 상기 프리플렉션하중의 제거 시 I형 강재의 탄성복원력을 이용하여 후 술되는 분절부를 제외한 하부플랜지콘크리트에 1차적으로 프리스트레스를 도입시키기 위한 것으로서 그 크기, 재하위치 및 재하회수는 강합성빔의 설계요건에 따라 다양하게 변경될 수 있다.This is to introduce the prestress to the lower flange concrete, except for the segment, which is described later by using the elastic restoring force of the I-type steel when the preflection load is removed, and its size, loading position, and load recovery are designed for the composite beam. Various changes may be made depending on requirements.

도1c는 일체화된 I형 강재(100)에 프리플렉션하중이 가해진 상태에서 중간강형(100b)에 인장재(200)를 배치하고 I형 강재의 분절부(A)를 제외한 상태에서 하부플랜지콘크리트(300a,300b,300c)를 타설, 양생시키고 상기 프리플렉션하중을 제거하여 1차프리스트레스를 하부플랜지콘크리트에 도입된 강합성빔의 측면도 및 정면도를 도시한 것이다.FIG. 1C shows the lower flange concrete 300a in which the tension member 200 is disposed in the intermediate steel 100b in a state in which the pre-flection load is applied to the integrated I-type steel 100 and the segment A of the I-type steel is excluded. , 300b and 300c are placed and cured and the preflection load is removed to show the side and front views of the steel composite beam in which the primary prestress is introduced into the lower flange concrete.

즉, 프리플렉션하중이 가해져 다소 아래로 만곡된 I형 강재(100)의 중간강형(100b)의 하부플랜지 주위에 다수의 인장재(200, 비접착 PC 스트랜드포함)를 설치하고, 추후 타설 될 중간 강합성빔의 하부플랜지콘크리트의 단부 위로 돌출되도록 설치한 뒤, I형 강재의 분절부(A)를 제외한 양 단부강형(300a,300c) 및 중간강형(300b)의 하부플랜지에 콘크리트를 타설, 양생하여 분절된 I형 강재 각각에 하부플랜지콘크리트(300a,300b,300c)가 형성되도록 한 것이다.That is, a plurality of tension members (including 200, non-bonded PC strands) are installed around the lower flange of the intermediate steel 100b of the I-shaped steel 100, which is slightly curved due to the preflection load, and the intermediate steel to be poured later. After installation so as to protrude above the end of the lower flange concrete of the composite beam, the concrete is poured and cured in the lower flange of the both ends (300a, 300c) and the intermediate (300b) except for the segment (A) of the I-type steel Lower flange concrete (300a, 300b, 300c) is formed on each of the segmented I-type steel.

상기 프리플렉션하중을 제거하면, I형 강재의 탄성복원력에 의하여 I형 강재가 원래 형상으로 복원되면서, 하부플랜지콘크리트(300a,300b,300c)에 1차 프리스트레스가 도입된다. 이로서 일체화된 강합성빔(400)의 제작이 완성된다.When the preflection load is removed, the I-type steel is restored to its original shape by the elastic restoring force of the I-type steel, and the first prestress is introduced into the lower flange concretes 300a, 300b, and 300c. This completes the fabrication of the integrated composite steel beam 400.

도2c는 I형 강재의 각 하부플랜지콘크리트(300a,300b,300c)에 별도의 인장재(200)가 설치되지 않은 상태에서 I형 강재의 분절부(A)를 제외한 양 단부강형(300a,300c) 및 중간강형(300b)의 하부플랜지에 콘크리트가 타설, 양생된 상태의 일체화된 강합성빔(400)을 측면도 및 정면도로 도시한 것인데, 이는 인장재(200)를 미리 중간강형에 설치하지 않고, 도2d, 도2e, 도2f, 도2g, 도2h, 도2i 및 도2j와 같이 하부플랜지콘크리트 외부에 인장재(200)를 설치할 경우에 적용될 수 있는 강 합성빔(400)에 이용된다.Figure 2c is the both ends of the steel (300a, 300c) except for the segment (A) of the I-type steel in the state that no separate tension member 200 is installed in each lower flange concrete (300a, 300b, 300c) of the I-type steel And in the lower flange of the intermediate steel (300b) is shown in a side view and a front view of the integrated steel composite beam 400 in the concrete, the curing state, which is not installed in advance in the intermediate steel, the tension member 200, FIG. 2d, 2e, 2f, 2g, 2h, 2i and 2j is used in the steel composite beam 400 that can be applied when the tension member 200 is installed outside the lower flange concrete.

즉, 하부플랜지콘크리트에 2차프리스트레스를 도입하는 방식의 차이에 따라 공장에서 제작되는 강합성빔의 제작방식에 차이가 있을 수 있음을 도시한 것인데, 현장에서 인장재가 미리 설치되지 않은 분절된 강합성빔을 조립한 후, 강합성빔의 양단부의 하부플랜지콘크리트 상,하부에 걸쳐 인장재를 설치하고, 상기 양단부에 설치된 정착장치를 이용하여 인장재를 긴장 후 정착시키는 경우에 있어 이용되는 강합성빔이다.In other words, there is a difference in the method of fabricating the steel composite beam produced in the factory according to the difference in the method of introducing the second prestress to the lower flange concrete, the segmented steel composite without the pre-installed tensile material in the field After assembling the beam, a tension member is provided on the upper and lower portions of the lower flange concrete at both ends of the rigid composite beam, and is a rigid synthetic beam used when the tension member is fixed after tension using the fixing device provided at both ends.

도1d는 1차프리스트레스가 도입된 강합성빔(400)을 분절(분리)시킨 상태를 측면도 및 정면도로 도시한 것이다.FIG. 1D is a side view and a front view illustrating a state in which the steel composite beam 400 in which primary prestress is introduced is segmented (separated).

일체화된 강합성빔(400)을 서로 기계적으로 연결시키고 있는 I형 강재의 분절(A)의 기계적 연결(볼트, 용접등)을 제거시키면, 분절된 3개의 강합성빔(400a,400b,400c)이 준비된다. 이때 인장재(200)의 단부는 둥글게 말아올릴 수 있어 취급이 매우 간편하다는 장점이 있다.If the mechanical connection (bolt, welding, etc.) of the segment A of the I-type steel that mechanically connects the integrated steel composite beam 400 to each other is removed, the three steel composite beams 400a, 400b and 400c are segmented. This is ready. At this time, the end of the tension member 200 has a merit that it can be rolled up round and very easy to handle.

상기 도1a 내지 도1d까지의 공정은 공장에서 작업이 이루어지게 되며, 이로서 강합성빔의 제작에 있어 품질관리가 용이하다는 장점이 있으며, 작업부지조성에 의한 작업공기 및 공사비 상승요인을 막을 수 있고, 현장설비 설치 및 해체로 인한 공사비 상승요인을 방지할 수 있다는 장점이 있다.The process of Figure 1a to 1d is made in the factory, thereby having the advantage of easy quality control in the production of a composite beam, it is possible to prevent the increase of work air and construction costs by the work site composition In addition, it is possible to prevent an increase in construction costs due to installation and dismantling of on-site facilities.

도1e는 상기 분절된 강합성빔(400a,400b,400c)을 현장에 반입하여 다시 조립(볼트 또는 용접)시킨 상태를 측면도 및 정면도로 도시한 것이며, 도1f는 상기 조립된 강합성빔(400a,400b,400c)을 교각 및 교대와 같은 교량하부구조물에 거치하 고 상부슬래브(510), 복부콘크리트(520) 및 가로보와 같은 교량상부구조물 콘크리트(500)를 타설, 양생하고, 하부플랜지콘크리트(300a,300b,300c)를 서로 연결시킨 상태를 측면도 및 정면도로 도시한 것이다.FIG. 1E illustrates a state in which the segmented rigid composite beams 400a, 400b, and 400c are brought back into the field and assembled (bolt or welded), and a side view and a front view thereof, and FIG. 1F illustrates the assembled rigid composite beams 400a. , 400b, 400c) mounted on the bridge undercarriage, such as bridges and shifts, and pour the upper slab 510, the abdominal concrete 520 and the bridge superstructure concrete 500, such as crossbeams, curing, and lower flange concrete ( A side view and a front view show a state in which 300a, 300b, and 300c are connected to each other.

현장의 받침대 위에 설치되어 다시 일체로 볼트 또는 용접에 의하여 조립된 강합성빔(400)은 교대, 교각과 같은 교량하부구조물에 인양장치를 이용하여 거치한후, 상부슬래브콘크리트, 강합성빔용 복부콘크리트 및 가로보 등을 포함하는 교량상부구조물 콘크리트(500)가 타설, 양생된다. 즉 강합성빔을 교량상부구조물과 일체화시키는 작업이 진행된다.The steel composite beam 400, which is installed on the pedestal of the site and assembled by bolts or welding again, is mounted on the lower structure of bridges such as shifts and piers using a lifting device, and then the upper slab concrete and the abdominal concrete for the steel composite beam And the bridge upper structure concrete 500 including a cross beam and the like is poured and cured. That is, the work of integrating the steel composite beam with the upper structure of the bridge proceeds.

이때 강합성빔(400)을 형성하고 있는 I형 강재는 볼트 접합이나 용접 등으로 용이하게 일체화될 수 있지만, I형 강재를 둘러싸고 있는 하부플랜지콘크리트는 일체화하기가 용이하지 않으므로, 하부플랜지콘크리트를 효율적으로 일체화 연결시키기 위한 방법이 필요하게 된다.At this time, the I-type steel forming the steel composite beam 400 can be easily integrated by bolt bonding or welding, but the lower flange concrete surrounding the I-type steel is not easy to integrate, so the lower flange concrete is efficiently There is a need for a method for integral connection.

이에 먼저 공장 제작 시 미리 하부플랜지콘크리트 내부에 인장재(비접착 PC 스트랜드 포함)를 배치한 강합성빔의 양쪽 측면에 위치한 강합성빔과의 분절부에 콘크리트 및 모르타르를 타설하거나 에폭시 수지를 충진시켜 일단 각 하부플랜지콘크리트를 서로 연결시킨다.First of all, when the factory is manufactured, concrete and mortar are poured into the segment with the steel composite beam located on both sides of the steel composite beam in which the tension member (including the non-bonded PC strand) is disposed inside the lower flange concrete, Connect each lower flange concrete to each other.

이 경우, 활하중 등과 같은 2차적인 외부하중에 의한 하부플랜지콘크리트의 인장균열을 방지할 수 있는 2차프리스트레스가 각 하부플랜지콘크리트에 도입되기전의 상태인데, 이러한 2차프리스트레스의 도입은 본 발명에서 3가지 구체예로 제시된다.In this case, the secondary prestress, which can prevent the tensile cracking of the lower flange concrete due to the secondary external load such as the live load, is before the state is introduced into each lower flange concrete, the introduction of the secondary prestress is 3 In one embodiment are presented.

도2a는 첫 번째 구체예를 도시한 것으로서, 중간 강합성빔(400b)의 하부플랜지콘크리트 위로 노출되어 둥글게 말려진 인장재(200)를 길게 풀어 인장재의 양 단부를 강합성빔(400)의 양 단부까지 연장시킨 상태에서 강합성빔의 외부 양 단부 또는 하부플랜지 콘크리트 상면에 설치된 정착장치(600)에 긴장 후 정착시켜 하부플랜지콘크리트(300) 전체에 2차프리스트레스를 도입시키는 경우를 도시한 것이다. 이때 강합성빔의 하부플랜지콘크리트에 2차프리스트레스가 도입됨과 동시에 분절부에도 압축력을 도입할 수 있어 분절부의 하부플랜지콘크리트를 확실하게 일체화시킬 수 있어, 일괄 제작한 것과 동등한 2차프리스트레스를 강합성빔에 도입시킬 수 있게 된다.FIG. 2A illustrates the first embodiment, in which both ends of the tension member are extended by unrolling the rounded tension member 200 exposed to the lower flange concrete of the intermediate composite beam 400 b. Figure 2 illustrates a case where the secondary prestress is introduced into the lower flange concrete 300 by being fixed after fixing to the fixing device 600 installed on both outer ends or the lower flange concrete upper surface of the steel composite beam in the extended state. At this time, the secondary prestress is introduced to the lower flange concrete of the steel composite beam, and the compressive force can be introduced to the segmented portion, so that the lower flange concrete of the segmented portion can be reliably integrated, and the secondary prestress equivalent to the batch fabrication is made of the rigid composite beam. It can be introduced in.

이때, 슬래브 및 연결부위 타설 후 인장재를 긴장, 정착하는 것이 연결부위 및 강합성빔에 구조적으로 유리하므로 슬래브 타설 후 인장재를 긴장, 정착함이 바람직하지만, 작업의 편의에 따라 교량하부구조물에 거치하기 전에 하부플랜지콘크리트를 연결하고 인장재를 긴장, 정착할 수도 있다.At this time, it is preferable to tension and fix the tension member after placing the slab and the connecting part, because it is structurally advantageous to the connecting part and the steel composite beam. It is also possible to connect the lower flange concrete before and tension and settle the tension member.

도2b는 두 번째 구체예를 도시한 것으로서 도2a와 같이 2차프리스트레스를 도입시키되, 추가적으로 강합성빔 외부에 설치된 정착장치(600)에 인장재(200)를 더 설치하고 긴장 후 정착시킨 경우를 도시한 것인데, 이로서 강합성빔에는 2차프리스트레스를 시기적으로나 도입량으로나 시기를 달리하여 얼마든지 필요에 따라 조절하여 도입될 수 있게 됨을 알 수 있다. Figure 2b shows a second embodiment as shown in Figure 2a to introduce a second prestress, additionally showing the case where the tension member 200 is further installed in the fixing device 600 installed outside the rigid composite beam and tensioned and fixed In this way, it can be seen that the secondary synthetic prestress can be introduced into the composite synthetic beam in a timely manner, at an introduction amount, or at a different time.

도2d는 세 번째 구체예를 도시한 것으로서 도1c의 강합성빔(400)과는 달리 도2c의 강합성빔과 같이 인장재가 하부플랜지콘크리트에 포함되지 않은 경우에 있어 강합성빔에 2차프리스트레스를 도입시키는 예로서 강합성빔의 외부 양 단부의 하부플랜지콘크리트 상부에 설치된 정착장치(600)에 인장재(200)를 설치한 후, 긴장 후 정착시킨 경우이다.FIG. 2D illustrates a third embodiment. Unlike the composite beam 400 of FIG. 1C, unlike the composite beam 400 of FIG. 1C, the secondary prestress is applied to the composite beam when the tension member is not included in the lower flange concrete. As an example of introducing the tension member 200, the tension member 200 is installed in the fixing device 600 installed on the lower flange concrete at both outer ends of the steel composite beam, and then fixed after tension.

도2e는 도2d와는 달리 상기 정착장치가 강합성빔의 하부플랜지콘크리트 하부에 설치된 정착장치(600)에 인장재(200)를 설치한 후, 긴장 후 정착시킨 경우이며, 2e is a case where the fixing device is different from FIG. 2d after the tension member 200 is installed in the fixing device 600 installed under the lower flange concrete of the steel composite beam, and then fixed after tension.

도2f는 도2d 및 도2e의 인장재를 병행하여 강합성빔의 외부 양단부의 하부플랜지콘크리트 상부 및 하부에 설치된 정착장치(600)에 인장재(200)를 긴장 후 정착시킨 경우를 도시한 것이다.FIG. 2F illustrates a case where the tension member 200 is tensioned and fixed to the fixing device 600 installed on the upper and lower lower flange concretes of the outer both ends of the composite beam in parallel with the tension members of FIGS. 2D and 2E.

도2g는 연결되어 설치된 중간 강합성빔(400b)의 하부플랜지 콘크리트 하부에 인장재방향전환장치(610,일종의 새들)가 설치되고 정착장치가 강합성빔의 외부 양 단부의 하부플랜지콘크리트 상부에 설치된 경우에 있어, 인장재(200)를 상기 인장재방향전환장치를 거쳐 양 단부의 정착장치(600)에 설치하고 긴장 후 정착시킨 경우이다. Figure 2g is a tension material redirection device (610, a kind of saddle) is installed in the lower flange concrete lower portion of the intermediate rigid composite beam (400b) connected and the fixing device is installed on the upper upper flange of the lower flange of both ends of the composite beam In the case, the tension member 200 is installed in the fixing device 600 at both ends via the tension member redirection device and fixed after tension.

도2h는 도2d 및 도2g의 인장재(200)를 병행하여 강합성빔의 외부 양단부의 하부플랜지콘크리트 상부 및 하부에 설치된 정착장치(600)에 인장재(200)를 긴장 후 정착시킨 경우를 도시한 것이다.FIG. 2h illustrates a case where the tension member 200 is tensioned and fixed to the fixing device 600 installed on the upper and lower lower flange concrete portions of the outer both ends of the composite beam in parallel with the tension member 200 of FIGS. 2d and 2g. will be.

도2i는 연결된 중간 강합성빔(400b)의 하부플랜지 콘크리트 하부 및 상부에 인장재방향전환장치(610,일종의 새들)가 설치되고 정착장치가 강합성빔의 외부 양 단부의 하부플랜지콘크리트 상부에 설치된 경우에 있어, 인장재(200)를 상기 인장재방향전환장치(610)를 거쳐 양 단부의 정착장치(600)에 설치하고 긴장 후 정착시킨 경우이다. FIG. 2i illustrates a case in which a tension redirection device 610 (a kind of saddle) is installed on the lower flange concrete and the lower flange concrete of the connected intermediate rigid beam 400b, and the fixing device is installed on the lower flange concrete at both ends of the external composite beam. In this case, the tension member 200 is installed in the fixing device 600 at both ends via the tension member redirection device 610 and is fixed after tension.

도2j는 도2d 및 도2i의 인장재(200)를 병행하여 중간 강합성빔(400b)의 하부플랜지 콘크리트 하부 및 상부에 설치된 인장재방향전환장치(610,일종의 새들) 및 강합성빔의 외부 양단부의 하부플랜지콘크리트 상부에 설치된 정착장치(600)를 이용하여 인장재(200)를 긴장 후 정착시킨 경우를 도시한 것이다.FIG. 2J shows the tensioner redirection device 610 (a kind of saddle) and the outer both ends of the steel composite beam installed in the lower flange concrete upper and lower portions of the intermediate steel composite beam 400b in parallel with the tension member 200 of FIGS. 2D and 2I. The case where the tension member 200 is fixed after the tension member 200 is fixed by using the fixing device 600 installed on the upper portion of the lower flange concrete is illustrated.

도3a 내지 도3h는 도2a, 도2b, 도2d, 도2e, 도2f, 도2g, 도2h, 도2i 및 도2j의 강합성빔에 2차프리스트레스를 도입시킬 때 사용되는 정착장치(600)의 설치위치에 따른 구체예를 도시한 것인데,3A-3H show a fixing device 600 used to introduce secondary prestress into the rigid composite beam of FIGS. 2A, 2B, 2D, 2E, 2F, 2G, 2H, 2I, and 2J. ) Shows a specific example according to the installation position,

도3a의 경우 돌출된 제형의 정착장치(600)를 강합성빔의 외부 양 단부의 하부플랜지콘크리트 상부에 설치한 경우를 도시한 것이고,3a illustrates a case in which the fixing device 600 of the protruding formulation is installed on the upper portion of the lower flange concrete at the outer both ends of the composite beam.

도3b의 경우 돌출된 제형의 정착장치(600)를 강합성빔의 외부 양 단부 및 중간(중간 돌기(610)에서 인장재를 다시 긴장 후 정착시킬 수도 있다)의 하부플랜지콘크리 상부에 설치한 경우를 도시한 것이고,In the case of FIG. 3B, the fixing device 600 of the protruding formulation is installed on the upper side of the lower flange concrete of both the outer ends and the middle of the steel composite beam (which may be fixed after the tension member is re-tensioned in the intermediate protrusion 610). Shown,

도3c의 경우 돌출된 사각형의 정착장치(600)를 강합성빔의 외부 양 단부의 하부플랜지콘크리트 상부에 설치한 경우를 도시한 것이고, 정착장치 사이에는 쉬스관 같은 관에 인장재를 내재시키고 있으며,3c illustrates a case in which a protruding rectangular fixing device 600 is installed on upper portions of lower flange concretes at both ends of the external composite beam, and a tension member is embedded in a tube such as a sheath tube between the fixing devices.

도3d의 경우 상기 정착장치(600)로서 양 단부의 가로빔을 이용하고, 역시 정착장치 사이에는 쉬스관 같은 관에 인장재를 내재시키고 있으며, In the case of Fig. 3d, the horizontal beams at both ends are used as the fixing device 600, and a tension member is embedded in a tube such as a sheath tube between the fixing devices.

도3e의 경우 상기 정착장치(600)로서 양 단부의 가로빔을 이용하고, 가로빔 바로 안쪽에 별도의 정착돌기를 추가로 사용하는 경우를 도시한 것이고,3e illustrates a case in which the horizontal beams at both ends are used as the fixing device 600, and additional fixing protrusions are used immediately inside the horizontal beams.

도3f의 경우 상기 정착장치(600)로서 양 단부의 가로빔을 이용하고, 가로빔 바로 안쪽 및 하부플랜지콘크리트 상부 중간에 중간돌기(610)를 추가로 사용하는 경우를 도시한 것이고,3f illustrates a case in which the horizontal beams at both ends are used as the fixing device 600, and an intermediate protrusion 610 is additionally used right inside the horizontal beam and the upper middle of the lower flange concrete.

도3g의 경우 상기 정착장치(600)로서 양 단부의 가로빔(테이퍼 된 것)을 이용한 경우를 도시한 것이고,3G illustrates a case in which horizontal beams (tapered) at both ends are used as the fixing device 600,

도3h의 경우 상기 정착장치(600)로서 양 단부의 가로빔(테이퍼 된 것)을 이용하되 하부플랜지콘크리트 상부 중간에 2개의 중간돌기(610)를 추가로 사용하는 경우를 도시한 것이다. 3H illustrates a case in which horizontal beams (tapered) at both ends are used as the fixing device 600, but two middle projections 610 are additionally used in the upper middle of the lower flange concrete.

이와 같이 인장재의 정착장치의 설치 위치를 조절함에 따라 큰 응력을 받는 경간 중앙부에만 2차프리스트레스를 가할 수 있는 등 구조적, 재료적으로 효율화를 도모할 수 있다는 장점이 있다.As such, the secondary prestress can be applied only to the center portion of the span which is subjected to a large stress by controlling the installation position of the fixing device of the tension member, thereby achieving structural and material efficiency.

종래 하나의 경간을 현장에서 제작하던 프리스트레스트 프리플렉스 강합성빔을 공장에서 분절시켜 제작하고, 현장에서 인장재를 이용하여 2차프리스트레스를 가하여 분절된 강합성빔을 효과적으로 일체화시키기 위한 방법을 제공함으로서 장경간의 강합성빔 제작을 위한 제작장소 확보의 어려움을 해결하고, 현장에서의 노 력을 최소화시켜 공기 및 공사비를 절약하고, 공장제작을 통한 품질을 향상시킬 수 있으며, 2차프리스트레스를 가하는 정착장치의 위치결정을 통해 효율적인 2차프리스트레스 도입방법을 제공 즉, 인장재의 정착장치의 설치 위치를 조절함에 따라 큰 응력을 받는 경간 중앙부에만 2차프리스트레스를 가할 수 있는 등 구조적, 재료적으로 효율화를 도모할 수 있다.The prestressed preflex steel composite beam, which was previously manufactured in the field, was segmented and manufactured at the factory, and a method for effectively integrating the segmented steel composite beam by applying secondary prestress using a tension member in the field was provided. It is possible to solve the difficulty of securing the production place for the production of steel composite beams, to minimize the effort in the field, to save air and construction cost, to improve the quality through the factory production, and to apply the secondary prestress. Positioning provides an efficient method of introducing secondary prestresses. In other words, the secondary prestress can be applied only to the middle section of the span that is subjected to high stress by adjusting the installation position of the fixing device of the tension member. have.

Claims (8)

공장에서 분절된 강형을 조립한 후 프리플렉션하중을 가하는 단계;Assembling the segmented steel in the factory and applying a preflection load; 양 단부의 분절된 강형을 제외한 적어도 하나 이상의 중간강형의 하부플랜지 주위에 인장재를 설치한 상태에서, 분절부를 제외한 강형에 하부플랜지콘크리트를 형성시킨 후 상기 프리플렉션하중을 제거하여 1차프리스트레스가 도입된 강합성빔을 제작하는 단계; Primary prestress was introduced by removing the preflection load after forming the lower flange concrete in the steel except for the segmented portion while the tension member was installed around the lower flange of at least one intermediate steel except for the segmented steel at both ends. Manufacturing a rigid composite beam; 분절된 강합성빔을 현장에 반입한 후 조립하여 교량상부구조물 콘크리트의 형성 및 분절부를 연결하는 단계; 및Bringing the segmented rigid composite beam into the field and assembling the bridge to form the bridge upper structure concrete and connect the segmented portion; And 상기 인장재를 강합성빔에 긴장 후 정착시켜 2차프리스트레스를 하부플랜지콘크리트에 도입시키되, 인장재의 정착은 강합성빔의 외부 양 단부 또는 양 단부를 포함하여 중간에 다수 설치된 정착장치에 인장재의 양 단부를 긴장후 정착시켜 이루어지는 단계;를 포함하는 것을 특징으로 하는 분절된 프리스트레스트 프리플렉스 강합성빔의 일체화방법.The tension member is tensioned and fixed in the rigid composite beam to introduce the secondary prestress into the lower flange concrete, and the anchoring member is fixed to both ends of the tension member in the fixing device installed in the middle, including both external ends or both ends of the rigid composite beam. A method of integrating a segmented prestressed preplex rigid composite beam comprising: a step of fixing after tensioning. 제1항에 있어서, 상기 인장재는 비접착 PC 스트랜드로서, 중간강형이 형성된 분절된 강합성빔에 설치된 비접착 PC 스트랜드는 그 양 단부가 하부플랜지콘크리트 외부로 노출된 상태에서 둥글게 말아져 현장에 반입되는 것을 특징으로 하는 분절된 프리스트레스트 프리플렉스 강합성빔의 일체화방법.The non-bonded PC strand according to claim 1, wherein the tension member is a non-bonded PC strand, wherein the non-bonded PC strand installed in the segmented rigid composite beam having the intermediate steel is rolled round with both ends exposed to the outside of the lower flange concrete. A method of integrating a segmented prestressed preflex steel composite beam, characterized in that: 삭제delete 제 1항에 있어서, 상기 강합성빔 양 단부에 설치된 정착장치에 접착 텐던, 비접착 텐던 및 비접착 스트랜드 중 어느 하나인 인장재를 추가로 더 설치하여 긴장한 후 정착시켜, 2차프리스트레스를 강합성빔에 더 도입시키는 것을 특징으로 하는 분절된 프리스트레스트 프리플렉스 강합성빔의 일체화방법.The rigid composite beam according to claim 1, further comprising a tension member, which is any one of a bonded tendon, a non-bonded tendon, and an unbonded strand, is further tensioned and fixed to a fixing apparatus provided at both ends of the rigid composite beam. A method of incorporating a segmented prestressed preflex steel composite beam further comprising: 공장에서 분절된 강형을 조립한 후 프리플렉션하중을 가하는 단계;Assembling the segmented steel in the factory and applying a preflection load; 분절부를 제외한 강형에 하부플랜지콘크리트를 형성시킨 후 상기 프리플렉션하중을 제거하여 1차프리스트레스가 도입된 강합성빔을 제작하는 단계; Forming a lower flange concrete in the steel except for the segmented portion, and then removing the preflection load to produce a steel composite beam in which primary prestress is introduced; 분절된 강합성빔을 현장에 반입한 후 조립하여 교량상부구조물 콘크리트의 형성 및 분절부를 연결하는 단계;Bringing the segmented rigid composite beam into the field and assembling the bridge to form the bridge upper structure concrete and connect the segmented portion; 접착 텐던, 비접착 텐던 및 비접착 스트랜드 중 어느 하나인 인장재를 강합성빔에 긴장 후 정착시켜 2차프리스트레스를 하부플랜지콘크리트에 도입시키되, 상기 인장재의 정착은 강합성빔의 외부 양 단부 또는 양 단부를 포함하여 중간에 다수 설치된 정착장치에 접착 텐던, 비접착 텐던 및 비접착 스트랜드 중 어느 하나인 인장재를 긴장 후 정착시켜 이루어지는 단계;를 포함하는 것을 특징으로 하는 분절된 프리스트레스트 프리플렉스 강합성빔의 일체화방법.Tensile material, which is one of bonded tendons, non-bonded tendons, and non-bonded strands, is tensioned and fixed in the rigid composite beam to introduce secondary prestress into the lower flange concrete, wherein the fixing of the tensile member is performed at both ends or both ends of the outer composite beam. A step of tensioning and fixing the tension member, which is any one of a bonded tendon, a non-bonded tendon, and a non-bonded strand, in a plurality of fixing apparatuses installed in the middle of the segmented prestressed preflex composite beam; Integration method. 삭제delete 제6항에 있어서, 상기 정착장치는The method of claim 6, wherein the fixing device 하부플랜지콘크리트 상부면과 하부면 중 적어도 하나에 설치되는 방식1;Method 1 installed on at least one of the upper surface and the lower surface of the lower flange concrete; 하부플랜지콘크리트 상부면과 하부면을 가로질러서 설치되는 방식2; 및Method 2 installed across the lower flange concrete upper surface and the lower surface; And 상기 방식1 및 방식2가 조합된 방식 중 어느 하나로 설치되는 것을 특징으로 하는 분절된 프리스트레스트 프리플렉스 강합성빔의 일체화방법.The method of claim 1, wherein the method 1 and the method 2 are installed in one of a combination method. 제1항 또는 제5항에 있어서, 상기 분절부의 연결은 분절부에 팽창콘크리트를 포함한 콘크리트, 모르타르 및 에폭시수지 중 어느 하나를 분절부에 타설 또는 충진시켜 이루어지는 것을 특징으로 하는 분절된 프리스트레스트 프리플렉스 강합성빔의 일체화방법.The segmented prestressed preplex according to claim 1 or 5, wherein the segmented portion is formed by placing or filling any one of concrete, mortar, and epoxy resin including expanded concrete in the segmented portion. Method of integrating steel composite beams.
KR1020030040886A 2003-06-18 2003-06-18 Connecting method for segmental prestressed preflex steel composite beam KR100561034B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020030040886A KR100561034B1 (en) 2003-06-18 2003-06-18 Connecting method for segmental prestressed preflex steel composite beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020030040886A KR100561034B1 (en) 2003-06-18 2003-06-18 Connecting method for segmental prestressed preflex steel composite beam

Publications (2)

Publication Number Publication Date
KR20040110958A KR20040110958A (en) 2004-12-31
KR100561034B1 true KR100561034B1 (en) 2006-03-16

Family

ID=37383277

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020030040886A KR100561034B1 (en) 2003-06-18 2003-06-18 Connecting method for segmental prestressed preflex steel composite beam

Country Status (1)

Country Link
KR (1) KR100561034B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101298776B1 (en) 2010-09-09 2013-08-22 주식회사 이산 Method for Manufacturing Precast Prestressed Steel Concrete Composite Girder and Slab
KR101636889B1 (en) * 2015-06-08 2016-07-06 토웅이앤씨(주) Prestressed Concrete Girder
KR20160080869A (en) * 2014-12-29 2016-07-08 하승욱 Construction method of prestressed steel composite girder bridge

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100982974B1 (en) * 2009-12-21 2010-09-17 (주)아이브릿지코리아 Method for manufacturing multi-span continuous re-prestressed preflex composite bridge
KR101140433B1 (en) * 2011-08-11 2012-04-30 삼우건설 주식회사 Method for fabricating prestressed steel composite girder

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101298776B1 (en) 2010-09-09 2013-08-22 주식회사 이산 Method for Manufacturing Precast Prestressed Steel Concrete Composite Girder and Slab
KR20160080869A (en) * 2014-12-29 2016-07-08 하승욱 Construction method of prestressed steel composite girder bridge
KR101664165B1 (en) * 2014-12-29 2016-10-11 하승욱 Construction method of prestressed steel composite girder bridge
KR101636889B1 (en) * 2015-06-08 2016-07-06 토웅이앤씨(주) Prestressed Concrete Girder
WO2016200083A1 (en) * 2015-06-08 2016-12-15 토웅이앤씨(주) Prestressed concrete girder

Also Published As

Publication number Publication date
KR20040110958A (en) 2004-12-31

Similar Documents

Publication Publication Date Title
JP4040980B2 (en) Prestressed synthetic truss girder and manufacturing method thereof
KR101283535B1 (en) Fully-precast prestressed concrete girder bridges and construction method of such bridges
WO2000068508A1 (en) Prestressed concrete girder of adjustable load bearing capacity for bridge and adjustment method for load bearing capacity of bridge
KR100982974B1 (en) Method for manufacturing multi-span continuous re-prestressed preflex composite bridge
KR101913069B1 (en) Prestressed Steel-Concrete Composite Girder and Method for Fabricating thereof
KR100901803B1 (en) Method for composite girder and bridge construction method composite girder
KR100540374B1 (en) Bridge construction method using precast prestressed concrete beam manufacturing method for straight and curved bridge
KR100823448B1 (en) The improved seismic resistant continuation structure of prestressed concrete composite beam bridge and method thereof
KR100561034B1 (en) Connecting method for segmental prestressed preflex steel composite beam
KR101527752B1 (en) Construction method of prestressed composite girder bridge
KR102203826B1 (en) Prestressed Concrete Spliced Girder Bridge and Construction method thereof
KR20140076005A (en) segment type steel composite girder and its construction methods with intermediate anchorage device
KR19980071920A (en) Construction method of preflex composite type by factory production
KR20050001736A (en) Manufacturing method for steel-concrete composite girder using delayed composite effects and steel-concrete composite girder using the same
KR100274141B1 (en) Manufacturing method of preplex composite beem by divisional method
KR200342287Y1 (en) A structure of prestressed preflex steel composite beam prestressed by each construction steps
KR200302128Y1 (en) prestressed preflex steel composite beam possible to retensioning
KR101067717B1 (en) Process for producing prestressed concrete girder and concrete girder structure
US3835607A (en) Reinforced girders of steel and concrete
KR100244084B1 (en) Construction method of re-prestressed steel-concrete composite beam
KR20040091350A (en) Prestressed steel girder
KR100562758B1 (en) Manufacturing method of precast composite beam
KR100506573B1 (en) Steel beam constructed prestressing segmental component and construction method thereof
KR20210077874A (en) method of uniting the longitudinal steel on the lower flange of steel box girder bridge with tension introduced
KR20100074741A (en) Bridge and its construction method using tide arch hybrid girders having precast slabs

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130311

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20140311

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20150305

Year of fee payment: 10

LAPS Lapse due to unpaid annual fee