KR100562758B1 - Manufacturing method of precast composite beam - Google Patents

Manufacturing method of precast composite beam Download PDF

Info

Publication number
KR100562758B1
KR100562758B1 KR1020030030249A KR20030030249A KR100562758B1 KR 100562758 B1 KR100562758 B1 KR 100562758B1 KR 1020030030249 A KR1020030030249 A KR 1020030030249A KR 20030030249 A KR20030030249 A KR 20030030249A KR 100562758 B1 KR100562758 B1 KR 100562758B1
Authority
KR
South Korea
Prior art keywords
lower concrete
composite beam
concrete precast
prestress
precast member
Prior art date
Application number
KR1020030030249A
Other languages
Korean (ko)
Other versions
KR20040097796A (en
Inventor
황철동
Original Assignee
황철동
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 황철동 filed Critical 황철동
Priority to KR1020030030249A priority Critical patent/KR100562758B1/en
Publication of KR20040097796A publication Critical patent/KR20040097796A/en
Application granted granted Critical
Publication of KR100562758B1 publication Critical patent/KR100562758B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/02Bridges characterised by the cross-section of their bearing spanning structure of the I-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/28Concrete reinforced prestressed
    • E01D2101/285Composite prestressed concrete-metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/08Members specially adapted to be used in prestressed constructions

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

본 발명은 하부콘크리트 프리캐스트 부재에 긴장재를 긴장, 정착하여 소정의 압축 프리스트레스를 1차 도입시킨 상태에서, 강재주형을 하부콘크리트 프리캐스트부재에 합성시켜 서로 일체로 거동하도록 하는 프리캐스트 합성빔을 제작한 후, 하부콘크리트 프리캐스트 부재에 다시 2차 또는 2차 이상의 압축 프리스트레스를 도입시킨 프리캐스트 합성빔 제작방법에 관한 것으로서, 합성빔 제작공정이 간단하여 그 제작에 소요되는 공기단축 및 공사비 절감이 가능하고, 1차, 2차 또는 2차 이상에 걸친 프리스트레스 도입에 의하여 하부콘크리트 프리캐스트 부재에, 설계시 고려한 압축응력을 효율적으로 도입하여, 그 인장균열을 효율적으로 제어할 수 있어 합성빔의 강성 및 내구성을 향상시킬 수 있으며, 크리프(creep) 및 건조수축에 의한 응력(프리스트레스)손실을 줄일 수 있으며, 공장 또는 제작장에서 세그먼트로 분절 제작하여 설치하는 경우 합성빔의 품질관리 및 그 운반, 설치가 용이하여 보다 효율적인 합성빔의 설계 및 시공(운반 및 설치)이 가능한 프리캐스트 합성빔 제작 방법에 관한 것이다.According to the present invention, a precast composite beam is fabricated by synthesizing a steel mold to a lower concrete precast member in a state in which a tension member is tensioned and fixed to a lower concrete precast member to introduce a predetermined compression prestress. After that, the present invention relates to a precast composite beam manufacturing method in which a second or second compression prestress is introduced to a lower concrete precast member again, and the synthetic beam manufacturing process is simple, thereby reducing the air shortening and construction cost required for the production. In addition, by introducing prestress over the first, second, or second order, the compressive stress considered in the design can be efficiently introduced into the lower concrete precast member, so that the tensile crack can be controlled efficiently. It can improve durability and stress due to creep and dry shrinkage (priest S) It can reduce the loss, and when the segment is manufactured and installed in the factory or the manufacturing site, the quality control of the synthetic beam and its transportation and installation are easy, so that the design and construction (transportation and installation) of the composite beam can be more efficient. The present invention relates to a method for producing a cast composite beam.

합성빔, 프리스트레스, 긴장재, 세그먼트,프리플렉스Composite beam, prestress, tension material, segment, preflex

Description

프리캐스트 합성빔 제작방법{Manufacturing method of precast composite beam}Manufacturing method of precast composite beam

도1a 및 도1b는 종래의 프리플렉스 합성빔의 제작공정의 일부공종을 도시한 것이고,Figures 1a and 1b shows a part of the manufacturing process of the conventional preplex composite beam,

도1c는 종래의 리프리스트레스 프리플렉스 합성빔의 단면도를 도시한 것이다.Figure 1C shows a cross-sectional view of a conventional leafless preplex composite beam.

도2a는 본 발명의 전체지간을 일체로 제작한 프리캐스트 합성빔을 구성하는 강재주형을 도시한 것이고,Figure 2a shows a steel mold constituting the precast composite beam integrally fabricated the entire span of the present invention,

도2b는 본 발명의 1차 프리스트레스가 도입된 하부콘크리트 프리캐스트 부재 및 그 종단면도를 도시한 것이고, Figure 2b shows a lower concrete precast member and the longitudinal cross-sectional view of the primary prestress introduced in the present invention,

도2c는 본 발명의 강재주형과 하부콘크리트 프리캐스트 부재가 합성된 상태의 프리캐스트 합성빔 및 프리캐스트 합성빔에 2차 또는 2차 이상의 프리스트레스를 도입시킨 상태의 종단면도를 도시한 것이다.Figure 2c shows a longitudinal cross-sectional view of a state in which a secondary cast or a second or more prestress is introduced into a precast composite beam and a precast composite beam in which the steel mold and the lower concrete precast member of the present invention are synthesized.

도3a, 도3b 및 도3c는 본 발명의 강재주형과 하부콘크리트 프리캐스트 부재의 연결방법의 구체예를 도시한 것이다.Figures 3a, 3b and 3c shows a specific example of the connection method of the steel mold and the lower concrete precast member of the present invention.

도4는 본 발명의 프리캐스트 합성빔에 2차 또는 2차 이상의 압축 프리스트레스가 도입되는 경우, 강재주형의 상부플랜지에 인장력이 도입되는 개념도를 도시한 것이다.4 illustrates a conceptual diagram in which a tensile force is introduced into an upper flange of a steel mold when a secondary or secondary compression prestress is introduced into the precast composite beam of the present invention.

도5a, 도5b 및 도5c는 전체 지간을 분절하여 제작한 후 제작한 본 발명의 프리캐 스트 합성빔을 구성하는 강재주형, 1차 프리스트레스가 도입된 하부콘크리트 프리캐스트 부재 및 강재주형과 하부콘크리트 프리캐스트 부재가 연결된 상태의 프리캐스트 합성빔에 2차 또는 2차 이상의 프리스트레스가 도입된 상태를 도시한 것이다.Figures 5a, 5b and 5c is a steel mold constituting the precast composite beam of the present invention produced by segmenting the entire interval, the lower concrete precast member and the primary steel and the lower mold precast The second or second prestress is introduced into the precast composite beam in which the precast member is connected.

도6a 및 도6b는 본 발명의 프리캐스트 합성빔을 바닥판 콘크리트와 연결시키는 구체예를 도시한 것이다.Figures 6a and 6b show an embodiment of connecting the precast composite beam of the present invention with the bottom plate concrete.

<도면의 주요부호의 설명><Description of Major Symbols in Drawing>

300:프리캐스트 합성빔300: precast composite beam

310:하부콘크리트 프리캐스트 부재310: lower concrete precast member

320:강재주형320: steel casting

330a,330b:긴장재330a, 330b: Tension material

330c:긴장재수용수단330c: tension receptacle

340a,340b,340c:분절된 강재주형340a, 340b, 340c: segmented steel mold

350a,350b,350c:분절된 하부콘크리트 프리캐스트 부재350a, 350b, 350c: segmented lower concrete precast member

400:바닥판 콘크리트400: bottom plate concrete

본 발명은 프리캐스트 합성빔 제작방법에 관한 것으로서, 더욱 구체적으로는 하부콘크리트 프리캐스트 부재에 긴장재를 긴장, 정착하여 소정의 압축 프리스트레스를 1차 도입시킨 상태에서, 강재주형을 하부콘크리트 프리캐스트 부재에 합성시켜 서로 일 체로 거동하도록 하는 프리캐스트 합성빔을 제작한 후, 하부콘크리트 프리캐스트 부재에 다시 2차 또는 2차 이상의 압축 프리스트레스를 도입시킨 프리캐스트 합성빔 제작 방법에 관한 것이다. The present invention relates to a method for manufacturing a precast composite beam, and more particularly, in a state in which a tension member is tensioned and fixed to a lower concrete precast member and a predetermined compression prestress is introduced to the lower concrete precast member. The present invention relates to a precast composite beam fabrication method in which a precast composite beam is synthesized to be integrated with each other, and then a secondary or secondary compression prestress is introduced into the lower concrete precast member.

종래의 특허 제1163호(프리스트레스 합성빔의 제조방법)에 따른 강재주형 및 콘크리트를 합성시켜 제작한 교량용 합성빔 (프리플렉스 빔 등)의 제작과정을 살펴보면, 도1a와 같이 강재주형(100)에 소정의 프리플렉션 하중(P1)을 가한 뒤 하부플랜지에 콘크리트를 타설, 양생함으로서 케이싱콘크리트(200)를 형성시키고, 도1b와 같이 프리플렉션 하중을 제거하여, 강재주형의 탄성복원력에 의하여 케이싱콘크리트에 일종의 압축 프리스트레스를 도입시킴으로서, 외부하중에 대응한 강성 및 내구성을 확보(교량 완공 후 작용하는 활하중 등에 의한 케이싱 콘크리트의 인장균열 방지)할 수 있도록 하고 있다. 즉 외부하중에 의한 케이싱콘크리트에 발생하는 인장균열을 방지하기 위해 미리 강재주형에 프리플렉션 하중을 가하는 공종이 반드시 선행되었다.Looking at the manufacturing process of the composite steel beam (pre-plex beam, etc.) made by synthesizing the steel mold and concrete according to the prior patent No. 1163 (pre-stress composite beam manufacturing method), as shown in Figure 1a steel mold 100 Casing concrete 200 is formed by placing and curing concrete on the lower flange after applying a predetermined pre-flection load (P1) to the casing concrete, and removing the pre-flection load as shown in Figure 1b, the casing concrete by the elastic restoring force of the steel mold By introducing a kind of compression prestress into the body, it is possible to secure the rigidity and durability corresponding to the external load (prevention of tensile cracking of the casing concrete by the live load acting after the completion of the bridge). In other words, in order to prevent tensile cracking occurring in the casing concrete due to the external load, a model in which a pre-flection load is applied to the steel mold in advance is necessarily preceded.

또한, 다른 종래의 특허 제244084호의 프리플렉스 합성빔과 유사한 리프리스트레스 프리플렉스 강합성빔 제작방법의 제작과정을 살펴보면, 도1c와 같이 강재주형(100, I형강)미리 일정크기의 휨모멘트를 발생시키는 프리플렉션 하중을 재하하고, 하부플랜지에 콘크리트를 타설하여 케이싱콘크리트(200)를 형성시키고, 미리 재하한 프리플렉션하중을 제거하여 케이싱콘크리트에 1차 압축프리스트레스를 도입한 후, 미리 상기 케이싱콘크리트에 설치된 인장재(210)에 의하여 2차 압축프리스트레스를 도입하여, 결과적으로 케이싱콘크리트의 인장균열을 방지하는데는 효과적이나, 역시 외부하중에 의한 케이싱콘크리트에 발생하는 인장균열을 방지하기 위해 미리 강재주형에 프리플렉션 하중을 가하는 공종이 필수적이었다. In addition, looking at the manufacturing process of the leafless preflex steel composite beam manufacturing method similar to other conventional composite beams of Patent No. 244084, as shown in Figure 1c the steel mold (100, I-shaped steel) in advance to generate a predetermined bending moment Load the pre-fraction load, and cast the concrete on the lower flange to form the casing concrete 200, remove the pre-load load previously loaded to introduce the primary compression prestress to the casing concrete, and then to the casing concrete in advance Secondary compression prestress is introduced by the installed tension member 210, and as a result, it is effective to prevent the tensile cracking of the casing concrete, but also to prevent the tensile cracking occurring in the casing concrete caused by external load. It was essential to apply a reflection load.

이러한 상기 프리프렉션 하중 재하공종은 강재주형의 크기 및 길이에 따라 특수한 제작설비가 필요할 뿐만 아니라, 재하위치, 재하회수 및 재하하중의 크기를 정하는 작업의 품질관리가 용이하지 않았다는 문제점이 있었으며, 현장부근의 제작장에서 합성빔을 제작한 후, 현장에 반입하여 교량하부구조물에 설치하는 경우, 그 제작을 위한 작업부지의 조성, 운반로 확보가 필수적이어서 공사비 상승요인이 되었다는 것은 주지의 사실이었다.The prefraction load loading type requires a special manufacturing facility according to the size and length of the steel mold, and also has a problem in that quality control of load positioning, load recovery, and load loading is not easy. It was well known that the construction cost was increased because it was necessary to construct a work site for the fabrication and secure a transport route when the composite beam was manufactured at the production site and then installed on the bridge undercarriage.

이러한 프리플렉션 재하공종을 이용하여 교량용 합성빔 제작에 있어, 프리플렉션 하중 재하공종에 의한 문제점이 상기와 같았음에도 이를 해결하고자 하는 노력의 필요성은 대두되었으나, 실체적인 문제해결 방법에 대한 기술개발이 이루어지지 않고 있는 실정이었다.In the fabrication of composite beams for bridges using such a pre-loaded construction model, even though the problems caused by the pre-loading loading construction are as described above, the necessity to solve them has emerged. It was not happening.

이에 본 발명의 출원인은 프리플렉션 하중 재하공종과 같은 복잡한 공종 없이도 기존의 프리플렉션 재하공종을 이용하여 제작하는 합성빔과 동일한 형고를 가지는 효과를 유지하면서, 소요의 내구성 및 안전성을 확보할 수 있는 교량 거더용 합성빔을 개발하게 되었다Accordingly, the applicant of the present invention, while maintaining the effect of the same height as the composite beam manufactured by using the existing pre-flexion loading model without complicated work, such as pre-loading loading ball, bridges that can ensure the durability and safety of the required Developed composite beam for girder

본 발명의 목적은 콘크리트와 강재주형의 역학적거동의 장점만을 활용한 교량용 합성빔의 제작 및 시공에 있어서, 종래의 프리플렉션 하중재하 공종에 의해 케이싱콘크리트에 미리 프리스트레스를 도입하는 공종을 하부콘크리트 프리캐스트 부재 내에 길이방향으로 설치한 긴장재를 이용하여 프리스트레스를 도입하는 공종으로 대체하여 프리 프렉션 하중재하 공종 없이 소요의 합성빔을 제작함으로서 합성빔의 제작공종이 단순화되어 합성빔의 제작 및 시공의 공기단축이 가능하며, 강재주형 상, 하부 플랜지의 단면감소효과로 인하여 합성빔 제작을 위한 공사비 절감이 가능한 프리캐스트 합성빔 제작방법을 제공하는 것이다.It is an object of the present invention to manufacture a composite beam for a bridge utilizing only the merit of the mechanical behavior of concrete and steel molds. By using the tension member installed in the cast member in the longitudinal direction, the prestress is introduced and the required composite beam is manufactured without the prefraction load. It is possible to shorten, and to provide a precast composite beam manufacturing method that can reduce the construction cost for the composite beam production due to the cross-sectional reduction effect on the steel mold, the lower flange.

본 발명의 다른 목적은 하부콘크리트 프리캐스트 부재에 도입되는 프리스트레스에 있어, 품질관리가 용이한 공장에서, 1차적으로 직접 하부콘크리트 프리캐스트부재에, 설계시 고려한 응력수준으로 프리스트레스를 정확하게 도입시킬 수 있고, 합성빔의 하부콘크리트 프리캐스트 부재의 인장균열을 방지할 수 있는 것은 물론, 합성빔에 작용하는 자중, 활하중 및 크리프, 건조수축 등 콘크리트의 시간 의존적 응력(프리스트레스) 손실량도 충분히 보상할 수 있도록 프리스트레스를 2차 또는 2차 이상으로 하부콘크리트 프리캐스트 부재에 도입시킴으로서, 보다 효율적인 합성빔의 제작, 시공이 가능하며, 전체 지간을 일체로 또는 복수의 세그먼트로 공장에서 분할 제작한 후, 현장에 운반설치시켜 합성빔의 품질관리가 용이한 프리캐스트 합성빔 제작 및 시공방법을 제공하는 것이다.Another object of the present invention is to pre-stress introduced into the lower concrete precast member, in the factory easy to quality control, the pre-stress can be accurately introduced to the lower concrete precast member firstly at the stress level considered in the design, In addition, the prestress can prevent tension cracking of the lower concrete precast member of the composite beam, as well as the time-dependent stress (prestress) loss of concrete such as self-weight, live load, creep, and dry shrinkage acting on the composite beam. Is introduced into the lower concrete precast member in the second or second order, making it possible to manufacture and construct a more efficient composite beam. Precast composite beam for easy quality control of composite beams To provide a construction method.

본 발명은 프리캐스트 합성빔을 제작하기 위해, 기 제작된 강재주형을 따로 제작하고, 하부콘크리트 프리캐스트 부재의 경우 소정의 단면 및 길이를 가진 콘크리트 부재 내부에 길이방향으로 긴장재를 설치한 후, 하부콘크리트 프리캐스트 부재 양 단부에 긴장, 정착시킴으로서 소요의 프리스트레스가 1차적으로 도입되도록 한 상태에서(프리캐스트 화, 이 때 2차 또는 2차 이상의 프리스트레스 도입을 위한 긴장재수용수단 및 긴장 재를 미리 하부콘크리트 프리캐스트 부재에 설치한다.), 상기 강재주형과 하부콘크리트 프리캐스트 부재를 서로 합성한 후, 이를 현장에 운반하고, 추가적(2차 또는 2차 이상)으로 하부콘크리트 프리캐스트 부재에 소요의 프리스트레스가 도입되도록 하며, 프리캐스트 합성빔을 전체 지간에 걸쳐 또는 분절 제작하여 보다 효율적인 시공이 가능하도록 하며, 특히 전체지간에 걸쳐 하부콘크리트 프리캐스트 부재를 제작하는 경우 1차 프리스트레스 도입은 프리텐션 방식으로도 가능하며, 하부콘크리트 프리캐스트 부재와 강재주형을 비합성 상태로 연결한 상태에서 1차 프리스트레스를 하부콘크리트 프리캐스트 부재에 도입하고, 강재주형과 하부콘크리트 프리캐스트 부재와의 연결부를 그라우팅 등으로 연결(합성)한 후 2차 또는 2차 이상의 프리스트레스를 하부콘크리트 프리캐스트 부재에 도입하는 방식으로 제작할 수 있는 것을 그 기술적 특징으로 한다.According to the present invention, in order to fabricate the precast composite beam, a prefabricated steel mold is separately manufactured, and in the case of the lower concrete precast member, a tension member is installed in a longitudinal direction inside a concrete member having a predetermined cross section and a length, and then Tension and fixation at both ends of the concrete precast member allows the required prestress to be introduced first (precasting, in this case pre-tensioning means and re-stressing means for introducing the second or second prestress The steel mold and the lower concrete precast member are synthesized with each other, and then transported to the site, and the prestress required for the lower concrete precast member is additionally (secondary or second or higher). And precast composite beams over the entire span or segmented Efficient construction is possible.In particular, when manufacturing the lower concrete precast member over the entire area, the first prestress can be introduced by the pretension method, and the lower concrete precast member and the steel mold are connected in a non-synthetic state. In the state, the primary prestress is introduced to the lower concrete precast member, and the connection between the steel mold and the lower concrete precast member is connected (synthesized) by grouting or the like, and then the secondary or secondary prestress is connected to the lower concrete precast member. What can be produced by the introduction method is the technical characteristic.

이하 본 발명의 최선의 실시예를 도2 내지 도6을 기준으로 살펴본다.Best Mode for Carrying Out the Invention The best embodiment of the present invention will now be described with reference to FIGS.

본 발명의 프리캐스트 합성빔(300)은 강재주형(320)과 비합성 상태에서 하부콘크리트 프리캐스트 부재(310)에 긴장재를 이용하여 1차 압축 프리스트레스를 도입시키는 단계; 상기 하부콘크리트 프리캐스트 부재와 강재주형(320)을 연결시켜 합성빔을 제작하는 단계; 및 상기 하부콘크리트 프리캐스트부재에 적어도 2차 이상의 압축 프리스트레스를 추가로 도입시키는 단계; 를 포함한다.Precast composite beam 300 of the present invention comprises the steps of introducing a primary compression prestress using a tension material to the lower concrete precast member 310 in a non-synthetic state with the steel mold 320; Manufacturing a composite beam by connecting the lower concrete precast member and the steel mold 320; And further introducing at least a second or more compression prestress into the lower concrete precast member. It includes.

도2a 및 도2b는 본 발명의 프리캐스트 합성빔 제작에 필요한 강재주형(320)과 하부콘크리트 프리캐스트부재(310)를 각각 도시한 것이다.2A and 2B illustrate a steel mold 320 and a lower concrete precast member 310 required for fabricating the precast composite beam of the present invention, respectively.

상기 강재주형(320)은 도2a와 같이 통상 I형강재가 이용되지만, 사용목적에 따라 트러스 형태 및 파형 복부강판을 가지는 단면 등 기타 소요의 단면형상을 가진 다른 재 질의 강형이 이용될 수도 있다.The steel mold 320 is generally I-shaped steel, as shown in Figure 2a, but other material steel having a cross-sectional shape of the other required, such as the truss shape and the cross section having a corrugated abdominal steel may be used according to the purpose of use.

본 발명에서의 강재주형(320)은 합성빔의 제작에 있어 미리 프리플렉션 하중이 가해지지 않고, 기 제작된 강재주형 그대로 하부콘크리트 프리캐스트 부재에 연결된다는데 그 특징이 있다. 나아가 하부콘크리트 프리캐스트 부재(310)에 도입되는 1차 압축 프리스트레스에 의하여, 하부콘크리트 프리캐스트 부재가 위로 약간 만곡되어 제작되는 경우를 고려하여 강재주형도 하부콘크리트 프리캐스트 부재와의 용이한 연결을 위하여 하부콘크리트 프리캐스트 부재가 위로 만곡되는 만큼 위로 만곡되어 제작된다. The steel mold 320 according to the present invention is characterized in that it is connected to the lower concrete precast member as it is, without being pre-loaded in advance in the manufacture of the composite beam. Furthermore, considering the case in which the lower concrete precast member is slightly bent upward by the primary compression prestress introduced into the lower concrete precast member 310, the steel mold can be easily connected to the lower concrete precast member. The lower concrete precast member is bent upward as much as it is bent upward.

하부콘크리트 프리캐스트 부재(310)는 소정의 단면형상을 가진 부재로서, 그 길이, 강도, 프리스트레싱 방식(프리텐션 또는 포스트 텐션방식) 및 긴장재 설치 방식(접착식, 비접착식)은 강형의 길이, 사용 위치 및 기능상의 목적, 설계방식에 따라 변경될 수 있다.The lower concrete precast member 310 is a member having a predetermined cross-sectional shape, and its length, strength, prestressing method (pretension or post-tension method) and tension member installation method (adhesive, non-adhesive) are the length of the steel, the use position. And functional purpose and design method.

도2b의 경우, 하부콘크리트 프리캐스트 부재가 직육면체 형상 등(기타 다양한 형상으로서 제작될 수 있다)으로 제작되고, 그 길이는 강재주형의 길이에 대응하여 제작되고, 내부에는 길이방향(L방향)으로 다수의 긴장재(330a)가 설치되어 긴장장치에 의해 긴장된 후 하부콘크리트 프리캐스트 부재의 양 단부에 정착됨으로서, 하부콘크리트 프리캐스트 부재에 압축 프리스트레스가 1차적으로 도입된 상태를 도시한 것이다. 도2b의 아래쪽의 도시된 도면은 하부콘크리트 프리캐스트 부재(310)에 1차 프리스트레스가 도입된 상태를 종단면도로 도시한 것으로서, 상기 1차 프리스트레스는 하부콘크리트 프리캐스트 부재의 길이에 따라 단계적으로 도입될 수 있으며, 일정한 길이에 중복하여 도입될 수도 있음을 도시한 것이다.In the case of Fig. 2B, the lower concrete precast member is made into a rectangular parallelepiped shape or the like (which may be manufactured as various shapes), and the length thereof is manufactured to correspond to the length of the steel mold, and the length thereof is in the longitudinal direction (L direction). Since a plurality of tension members 330a are installed and tensioned by the tensioning device and then fixed at both ends of the lower concrete precast member, the compression prestress is primarily introduced into the lower concrete precast member. 2B shows a state in which the primary prestress is introduced into the lower concrete precast member 310 in a longitudinal sectional view, wherein the primary prestress is gradually introduced according to the length of the lower concrete precast member. It can be shown, it may be introduced in duplicate in a certain length.

하부콘크리트 프리캐스트 부재의 도면부호 330c는 긴장재가 추후 설치될 수 있도록 긴장재수용수단(쉬스 관 등)을 표시한다. 이는 추가적인 긴장재(330b) 설치, 긴장, 정착공종을 통해 소요의 압축 프리스트레스가 1차 도입되는 프리스트레스와 구분되어 시기를 달리하여 2차 또는 2차 이상으로 도입될 수 있음을 보여준다.Reference numeral 330c of the lower concrete precast member indicates a tension member receiving means (such as a sheath tube) so that the tension member can be installed later. This shows that the required compressive prestress can be introduced into the second or second order at different times by separating the prestress of the required first through the installation of additional tension material (330b), tension, and settling work.

하부콘크리트 프리캐스트 부재(310)는 공장에서 제작되어 품질관리가 매우 용이하다는 장점이 있으며, 특히 1차로 도입되는 프리스트레스의 경우 공장 또는 현장 부근 제작장에서 프리텐션 또는 포스트텐션 방식으로 설계에 따라 도입되도록 할 수 있어 제작 효율성이 향상된다는 장점이 있다.The lower concrete precast member 310 is manufactured in a factory and has an advantage of very easy quality control. Especially, in the case of the first prestress, the lower concrete precast member 310 is introduced according to a design by a pretension or posttension method in a factory or near a site. There is an advantage that the production efficiency can be improved.

도2c는 상기 강재주형(320) 및 하부콘크리트 프리캐스트 부재(310)를 서로 연결(합성)시킨 상태를 도시한 것인데, 하부콘크리트 프리캐스트 부재(310) 위에 강재주형(320)을 가능한 다양한 방식으로 부착시키되, 서로 일체 거동하도록 하여야 하며, 구체적인 연결예를 도시한 것이 도3a, 도3b 및 도3c이다.FIG. 2C illustrates a state in which the steel mold 320 and the lower concrete precast member 310 are connected to each other (synthesized), and the steel mold 320 is disposed on the lower concrete precast member 310 in various ways as possible. 3A, 3B, and 3C are attached to each other, but are to be integrated with each other.

도3b는 상부면에 다수의 구멍(311)이 형성된 하부콘크리트 프리캐스트 부재(310)를 도시한 것이고, 도3a는 상기 구멍에 대응하도록 I형강 하부플랜지 하부면에 돌출된 전단연결재(321)가 형성된 강재주형(320)을 도시한 것이고, 도3c는 하부콘크리트 프리캐스트 부재(310)와 강재주형(320)을 비합성상태로 연결한 상태에서 1차 프리스트레스를 도입하고, 모르타르 등과 같은 충진재로 그라우팅하여 합성시킨 후, 하부콘크리트 프리캐스트 부재(310)와 강재주형(320)이 서로 연결된 상태에서 2차 또는 2차 이상의 프리스트레스를 도입한 예를 도시한 것이다. 3B illustrates a lower concrete precast member 310 having a plurality of holes 311 formed in an upper surface thereof, and FIG. 3A illustrates a shear connector 321 protruding from a lower surface of an I-beam lower flange to correspond to the hole. Figure 3c shows the formed steel mold 320, Figure 3c introduces the primary prestress in a state in which the lower concrete precast member 310 and the steel mold 320 in a non-synthetic state, grouting with a filler such as mortar After synthesis, the lower concrete precast member 310 and the steel mold 320 is shown an example in which the secondary or secondary prestress is introduced in a state connected to each other.

이로서 강재주형(320) 및 하부콘크리트 프리캐스트 부재(310)가 서로 합성된 프 리캐스트 합성빔(300)이 도3c와 같이제작된다. 이러한 합성빔은 하부콘크리트 프리캐스트 부재와 미리 일체화된 상태의 강재주형에 직접 프리플렉션 하중이 가해져 상기 하부콘크리트 프리캐스트 부재에 프리스트레스가 도입되는 종래의 합성형 제작방법과는 달리, 별도로 제작된 강재주형이 1차 압축 프리스트레스가 도입된 하부콘크리트 프리캐스트 부재에 그대로 연결되는 방식을 채택하였기 때문에 강재주형에 압축프리스트레스가 함께 도입되지 않으며, 강재주형과 하부콘크리트 프리캐스트 부재를 합성시킨 후 합성빔에 2차로 프리스트레스를 추가 도입하여 교량거더용 합성빔을 제작함에 있어서도, 프리플렉션 재하공종과 같은 복잡한 공종이 없이 하부콘크리트 프리캐스트 부재에 발생하는 하중에 의한 인장균열을 방지할 수 있는 압축 프리스트레스 도입이 가능하다.Thus, the precast composite beam 300 in which the steel mold 320 and the lower concrete precast member 310 are combined with each other is manufactured as shown in FIG. 3C. Unlike the conventional composite type fabrication method in which the composite beam is directly preflected with a steel mold in a state previously integrated with the lower concrete precast member, the prestress is introduced into the lower concrete precast member. Since the primary compression prestress is adopted as it is connected to the lower concrete precast member in which it is introduced, the compression prestress is not introduced into the steel mold, and after the steel mold and the lower concrete precast member are synthesized, Even when the composite beam for the bridge girder is manufactured by introducing additional prestress, it is possible to introduce compression prestress that can prevent tensile cracking due to the load generated on the lower concrete precast member without complicated work such as pre-flection loading work.

나아가 하부콘크리트 프리캐스트 부재(310)에 긴장재(330a,300b)를 설치하여, 1차 및 2차(2차 이상도 가능함)에 걸쳐 프리스트레스를 직접 도입시킴으로서 소요의 프리스트레스 양을 필요한 양만큼 필요한 시기에 정확하게 계량하여 도입시킬 수 있고, 종래의 프리플렉스 합성빔에서 크게 발생하는 크리프, 건조수축 등의 콘크리트의 시간 의존적 응력(도입된 프리스트레스) 손실량을 충분히 제어하여 보상할 수 있다는 구조적 장점이 있다.Furthermore, by installing tension members 330a and 300b in the lower concrete precast member 310, the prestress is introduced directly through the primary and secondary (possibly even secondary), so that the required amount of prestress is required as necessary. It can be accurately measured and introduced, and there is a structural advantage that can sufficiently compensate for the time-dependent stress (introduced prestress) loss of concrete, such as creep, dry shrinkage, which occurs largely in a conventional preflex composite beam.

하부콘크리트 프리캐스트 부재(310)에 1차적으로 프리스트레스가 긴장재(330a)에 의하여 도입된 프리캐스트 합성빔(300)을 공장에서 제작하여 현장으로 운반한 후, 도2c와 같이 하부콘크리트 프리캐스트 부재(310)에 미리 형성시킨 긴장재수용수단(330c)에 긴장재(330b)를 전체지간에 걸쳐 삽입 설치한후, 양 단부에 긴장, 정착시키면, 하부콘크리트 프리캐스트 부재(310)에 2차적으로 프리스트레스가 도입 된다. 도2c 아래쪽에 도시된 도면은 하부콘크리트 프리캐스트 부재 및 강재주형이 연결된 상태에서 2차 프리스트레스가 하부콘크리트 프리캐스트 부재에 도입된 상태의 합성빔을 종단면도로 도시한 것이다.After manufacturing the precast composite beam 300 introduced preliminarily by the tension member 330a into the lower concrete precast member 310 at the factory and transporting it to the site, the lower concrete precast member 310 as shown in FIG. When the tension member 330b is inserted into the tension member accommodating means 330c formed in advance in the entire region, and is tensioned and fixed at both ends, prestress is introduced into the lower concrete precast member 310 secondly. do. FIG. 2C is a longitudinal cross-sectional view of the composite beam in which the secondary prestress is introduced into the lower concrete precast member while the lower concrete precast member and the steel mold are connected.

즉, 강재주형과 하부콘크리트 프리캐스트 부재가 비합성 상태에서 1차로 프리스트레스를 하부콘크리트 프리캐스트 부재에 도입시키는 것은 합성빔의 하부콘크리트 프리캐스트 부재에 설계상 소요의 압축 프리스트레스가 도입되도록 하는 것이라면, 2차 또는 2차 이상으로 추가 프리스트레스를 하부콘크리트 프리캐스트 부재에 도입시키는 것은 합성빔의 현장설치에 요구되는 합성빔의 자중 및 활하중에 대응하는 소요의 압축 프리스트레스를 도입시키는 것과 함께 크리프 및 건조수축에 의한 프리스트레스 손실 보완의 효과가 있으며, 도4와 같이 강재주형의 상부플랜지 상부에 인장력이 도입됨으로서 강재주형의 단면을 대폭 감소시킬 수 있는 효과가 있다.In other words, if the steel mold and the lower concrete precast member are first introduced into the lower concrete precast member in a non-synthesized state, if the compression prestress required by design is introduced into the lower concrete precast member of the composite beam, 2 The introduction of additional prestresses to the lower concrete precast members, secondary or secondary, is accompanied by creep and dry shrinkage, together with the introduction of the necessary compression prestresses corresponding to the self and live loads of the synthetic beams required for field installation of the composite beams. There is an effect of compensating for prestress loss, and as shown in FIG. 4, the tensile force is introduced into the upper flange of the steel mold, thereby greatly reducing the cross section of the steel mold.

따라서, 필요한 프리스트레스를 설계목적에 맞게 효율적으로 도입할 수 있으므로 강재주형 및 하부콘크리트 프리캐스트 부재의 설계, 시공관리와 품질관리가 효율적으로 달성될 수 있으며, 경제적인 부재의 단면설계가 가능하다는 장점이 있다.Therefore, the necessary prestress can be efficiently introduced according to the design purpose, so that the design, construction management, and quality control of the steel mold and the lower concrete precast member can be efficiently achieved, and the economical cross-sectional design of the member is possible. have.

최종적으로 현장에서 설치된 프리캐스트 합성빔 위에 상부슬래브 콘크리트를 설치함으로서 교랑을 완성할 수 있다.Finally, the bridge can be completed by installing the upper slab concrete on the precast composite beam installed in the field.

도5a 내지 도5c는 프리캐스트 합성빔(300)을 소정의 길이로 분절하여 제작하느 경우를 도시한 것이다.5A to 5C show a case in which the precast composite beam 300 is cut into a predetermined length and manufactured.

도5a와 같이 강재주형(340)의 경우에도 소정의 길이를 가지는 각 강재주형(340a,340b,340c)이 서로 볼트 및 플레이트와 같은 기계적 연결수단(350)을 이용하여 서로 연결되어 있으며(강형의 상부플랜지, 복부 및 하부플랜지 포함), 강재주형에 미리 프리플렉션 하중이 가해지지 않고, 기 제작된 강재주형 그대로 하부콘크리트 프리캐스트 부재(310)에 연결되고, 하부콘크리트 프리캐스트 부재(350a,350b,350c)에 도입되는 1차 프리스트레스에 의하여 하부콘크리트 프리캐스트 부재가 위로 약간 만곡되게 제작되는 경우를 고려하여 각 강재주형도 하부콘크리트 프리캐스트 부재와의 용이한 연결을 위하여 하부콘크리트 프리캐스트 부재가 위로 만곡되는 만큼 위로 만곡되어 제작된다.Even in the case of the steel mold 340 as shown in Figure 5a, each steel mold (340a, 340b, 340c) having a predetermined length is connected to each other using a mechanical connecting means 350 such as bolts and plates (steel type The upper flange, the abdomen and the lower flange), the pre-flection load is not applied to the steel mold in advance, and is connected to the lower concrete precast member 310 as the pre-fabricated steel mold, the lower concrete precast members (350a, 350b, Considering the case where the lower concrete precast member is slightly bent upward by the primary prestress introduced at 350c), the lower concrete precast member is bent upward for easy connection with the lower concrete precast member. It is bent upward as much as possible.

도5b는 하부콘크리트 프리캐스트 부재(350a,350b,350c)도 소정의 길이로 직육면체 형상을 포함한 다양한 형상으로 제작되고, 그 길이의 경우 강형의 길이에 대응하여 제작되며, 내부에는 길이방향(L방향)으로 다수의 긴장재(330a)가 설치되어 긴장, 정착되는 경우 하부콘크리트 프리캐스트 부재에는 압축 프리스트레스가 1차적으로 도입된 상태를 도시한 것으로서, 분절된 하부콘크리트 프리캐스트 부재가 서로 맞닿도록 설치된 상태에서 내부에 긴장재가 길이방향으로 설치되어 긴장 후 정착되면 분절 제작된 하부콘크리트 프리캐스트 부재가 서로 밀착 연결될 수 있다. 도면에는 도시하지 않았지만 각 하부콘크리트 프리캐스트 부재의 접합면에서는 요철을 형성시킨다던지, 전단키를 이용한다던지, 접착제를 도포 또는 충진시켜 각 하부콘크리트 프리캐스트 부재가 서로 밀착 연결될 수 있도록 하는 것이 바람직하다. 5b shows that the lower concrete precast members 350a, 350b, and 350c are also manufactured in various shapes including a rectangular parallelepiped shape with a predetermined length, and the length of the lower concrete precast members 350a, 350b, and 350c is corresponding to the length of the steel, and the length thereof is in the longitudinal direction (L direction). When a plurality of tension members 330a are installed and tensioned and fixed, the lower concrete precast member is a state in which compression prestress is first introduced, and the segmented lower concrete precast members are installed to abut each other. If the tension member is installed in the longitudinal direction inside the tension settled after the lower concrete precast member may be in close contact with each other. Although not shown in the drawings, it is preferable to form concavities and convexities at the joint surfaces of the respective lower concrete precast members, or to use a shear key, or to apply or fill an adhesive so that the lower concrete precast members can be closely connected to each other.

도5c는 상기 분절 제작된 후 서로 볼트, 용접 및 그라우팅 연결방법 등과 같은 기계적 연결수단으로 제작된 강형 및 긴장재 등으로 서로 밀착 연결된 하부콘크리트 프리캐스트 부재를 서로 연결시킨 상태를 도시한 것이며, 공장에서는 분절된 상태로 제작하 고, 현장에 운반한 후 조립하여 최종적인 합성빔을 제작해도 상관없다.Figure 5c shows the state of connecting the lower concrete precast members closely connected to each other by a rigid and tension material manufactured by mechanical connecting means such as bolts, welding and grouting connection method after the segment is manufactured, the segment in the factory The final composite beam may be manufactured by fabricating in the assembled state, transporting it on site and assembling.

합성빔의 길이가 장지간에 해당하는 경우 분절된 합성빔으로 공장에서 제작한 후, 현장에 운반함으로서 보다 효율적인 합성빔의 제작,운반 및 설치가 가능하다는 장점이 있다.If the length of the composite beam is long, it is advantageous to manufacture, transport and install the composite beam more efficiently by manufacturing it in the factory as a segmented composite beam and then transporting it to the site.

하부콘크리트 프리캐스트 부재를 도시한 도3b의 도면부호 330c는 긴장재(330b)가 추후 설치될 수 있도록 긴장재 수용수단(쉬스 관 등)을 표시하며, 추가적인 긴장재 설치, 긴장, 정착공정을 통해 소요의 프리스트레스가 상기 1차적으로 도입되는 프리스트레스와 구분되어 시기를 달리하여 2차 또는 2차 이상으로 도입될 수 있도록 하고 나아가 각 하부콘크리트 프리캐스트 부재의 연결을 위한 수단으로서도 이용된다.The reference numeral 330c of FIG. 3b showing the lower concrete precast member indicates tension member receiving means (such as a sheath tube) so that the tension member 330b can be installed later, and the required prestress through the additional tension member installation, tension, and fixing process. It is distinguished from the prestress introduced primarily so that it can be introduced into the second or second or more at different times, and is also used as a means for connecting each lower concrete precast member.

강형 및 하부콘크리트 프리캐스트 부재가 서로 일체화되어 거동하도록 제작된 프리캐스트 합성빔(300)은 전체 및 분절 제작된 후, 현장에 반입되어 2차 또는 2차 이상에 걸쳐 프리스트레스가 도입됨으로서 소요의 프리스트레스가 합성빔 전체지간에 도입되며, 합성빔이 설치된 상태에서 그 위에 상부슬래브 콘크리트가 설치(현장타설 및 프리캐스트화 된 상부슬래브)되면, 최종적인 교량시공이 완성될 수 있다.The precast composite beam 300, which is manufactured so that the rigid and lower concrete precast members are integrated with each other and behaves as a whole and is segmented, is brought into the field and the prestress is introduced to the secondary or the secondary or higher to obtain the required prestress. If the upper slab concrete is installed (in-place and precast upper slab) with the synthetic beam installed in the entire area, the final bridge construction can be completed.

이때 합성빔과 바닥판 콘크리트(400, 상부 바닥판)의 연결방법은 도6a와 같이 전단연결재(360) 등에 의하여 합성될 수도 있으며, 도6b와 같이 기존의 프리플렉스 합성빔과 같이 복부콘크리트(370)와 바닥판 콘크리트(400)에 전단연결재(360)가 형성된 합성빔이 매입되도록 하는 것도 가능하다.At this time, the connection method of the composite beam and the bottom plate concrete (400, the upper bottom plate) may be synthesized by the shear connector 360, as shown in Figure 6a, as shown in Figure 6b abdominal concrete (370) ) And the bottom beam concrete 400 is also possible to embed the composite beam formed with the shear connector 360.

본 발명의 프리캐스트 합성빔은 재료적 특성에 따른 부재력의 분포 및 특성을 합 리적으로 고려하여, 강재주형과 하부콘크리트가 비합성 상태에서 하부콘크리트 프리캐스트 부재에 1차로 압축 프리스트레스를 도입하고, 강재주형과 하부콘크리트 프리캐스트 부재를 합성시킨 후, 2차 또는 2차 이상에 걸쳐 추가적인 프리스트레스를 하부콘크리트 프리캐스트 부재)에 도입시킴으로서, 강재주형과 하부콘크리트 프리캐스트 부재의 합성단면에 프리스트레스를 도입시키는 종래의 프리플렉션 제작공법 또는 리프리스트레스 합성빔 제작 공법과 비교하여 강재주형의 상, 하부 플랜지 단면을 대폭 감소시켜 경제적이면서도, 종래의 프리플렉스 합성빔의 형고를 유지할 수 있다는 장점이 있다. 또한 1차 프리스트레스 도입에 따른 크리프 및 건조수축에 의한 시간 의존적 프리스트레스 손실을 2차 프리스트레스 추가 도입시 보완함으로서, 구조적으로 안전하고, 정확한 프리스트레스 도입과 단면감소효과에 따른 공사비 절감이 가능하다.









In the precast composite beam of the present invention, in consideration of the distribution and characteristics of the member force according to the material characteristics, the compression prestress is introduced first to the lower concrete precast member in a state in which the steel mold and the lower concrete are not synthesized. After synthesis of the mold and the lower concrete precast member, by introducing an additional prestress into the lower concrete precast member (secondary or second or higher), the prestress is introduced into the composite section of the steel mold and the lower concrete precast member. Compared with the pre-flection manufacturing method or the re-restless composite beam manufacturing method, the upper and lower flange cross-sections of the steel mold can be greatly reduced, which is economical and has the advantage of maintaining the mold height of the conventional preflex composite beam. In addition, by supplementing the time-dependent prestress loss due to creep and drying shrinkage due to the introduction of the first prestress, the construction cost is reduced by the introduction of the second prestress.









Claims (2)

강재주형과 비합성 상태에서 하부콘크리트 프리캐스트부재에 긴장재를 이용하여 1차 압축 프리스트레스를 도입시키는 단계; 상기 하부콘크리트 프리캐스트 부재와 기 제작된 강재주형을 연결시켜 합성빔을 제작하는 단계; 및 상기 하부콘크리트 프리캐스트부재에 적어도 2차 이상의 압축 프리스트레스를 추가로 도입시키는 단계;를 포함하며, 전체 지간의 길이로 또는 소정의 길이로 분절하여 제작된 후 연결되어 제작되는 것는 것을 특징으로 하는 프리캐스트 합성빔 제작방법.Introducing a first compression prestress by using a tension member to the lower concrete precast member in a non-synthetic state with the steel mold; Manufacturing a composite beam by connecting the lower concrete precast member and a pre-fabricated steel mold; And additionally introducing at least a second or more compression prestress into the lower concrete precast member, wherein the preconcrete is segmented into a length of the entire span or a predetermined length, and then connected and manufactured. Cast composite beam manufacturing method. 삭제delete
KR1020030030249A 2003-05-13 2003-05-13 Manufacturing method of precast composite beam KR100562758B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020030030249A KR100562758B1 (en) 2003-05-13 2003-05-13 Manufacturing method of precast composite beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020030030249A KR100562758B1 (en) 2003-05-13 2003-05-13 Manufacturing method of precast composite beam

Publications (2)

Publication Number Publication Date
KR20040097796A KR20040097796A (en) 2004-11-18
KR100562758B1 true KR100562758B1 (en) 2006-03-20

Family

ID=37375929

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020030030249A KR100562758B1 (en) 2003-05-13 2003-05-13 Manufacturing method of precast composite beam

Country Status (1)

Country Link
KR (1) KR100562758B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100983085B1 (en) 2010-01-13 2010-09-20 안창일 Composite member with tensile flange of closed and prestressed pipe type and the structure construction method

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100580327B1 (en) * 2004-01-15 2006-05-15 정지승 PSC beam with tensioned lower flange and construction method
KR100772657B1 (en) * 2006-03-30 2007-11-02 주식회사 인터컨스텍 Tendon assembly
KR102120266B1 (en) * 2019-05-16 2020-06-08 (주)성환이앤씨 A forming method for psc i girder of concrete separation installation type having a web reinforced with steel plate
KR102135731B1 (en) * 2019-12-09 2020-07-20 (주)에이치피엔지니어링건축사사무소 Fabrication method of priflex composite beam and composite beam manufactured by the method
CN116607399A (en) * 2023-07-18 2023-08-18 山东省交通规划设计院集团有限公司 Laminated combined beam structure suitable for large-span beam bridge and construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100983085B1 (en) 2010-01-13 2010-09-20 안창일 Composite member with tensile flange of closed and prestressed pipe type and the structure construction method

Also Published As

Publication number Publication date
KR20040097796A (en) 2004-11-18

Similar Documents

Publication Publication Date Title
KR101283535B1 (en) Fully-precast prestressed concrete girder bridges and construction method of such bridges
KR100540374B1 (en) Bridge construction method using precast prestressed concrete beam manufacturing method for straight and curved bridge
KR100727114B1 (en) Precast segment for constructing through bridges and the constructing method using it
KR20080103678A (en) Method for composite girder and bridge construction method composite girder
KR101034973B1 (en) Bridge and its construction method using tide arch hybrid girders by connecting precast blocks
KR100543745B1 (en) Manufacturing method for steel-concrete composite girder using delayed composite effects
KR100562758B1 (en) Manufacturing method of precast composite beam
KR101200563B1 (en) A Steel Composite Bridge Having Steel Plates Connected by Using Concrete Cross Beams and Its Constructing Method
KR101023172B1 (en) Segmental precast prestressed concrete girder and method for constructing the same
KR102120477B1 (en) Segmented girder structure and splicing method for the same
KR101232330B1 (en) Psc girder using core member and main beam, the making method and bridge construction method using the psc girder
KR101297706B1 (en) Construction method for prestressed girder using jack-up beam
KR101038714B1 (en) Bridge and its construction method using tide arch hybrid girders having precast slabs
KR100525054B1 (en) Prestressed concrete composite girder
KR100540373B1 (en) Bridge construction method using installing method for segment preflex composite beam
KR100583671B1 (en) Prestressed concrete beam manufactured by installing steel anchorage devices to various positions and reinforcing member to the upper and lower flanges, and construction method of bridge using the concrete beam
KR100712622B1 (en) Continuous Preflex Girder Structure Using Prestress in Parent Section Using Expanded Concrete and Its Construction Method
KR102169300B1 (en) Segmented prestressed girder with reinforced concrete and manufacturing method thereof
KR102327700B1 (en) Girder structure and construction method for continuity of supporting portion of girder using the same
KR20060032968A (en) Construction method of prestressed concrete temporary bridge that can be assembled and dismantled using lateral steel wire
KR100556721B1 (en) Prestressed composite girder manufactured by connection of prestressed composite beam units through precast coupling device and bridge construction method using the composite girder
KR100561034B1 (en) Connecting method for segmental prestressed preflex steel composite beam
KR100730018B1 (en) Prestressed steel-concrete composite and method for constructing the same
KR101684252B1 (en) Method of reinforcing continous portion in continuous bridge and its structure
JP2006169730A (en) Concrete bridge girder and method of forming the same

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130314

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20140314

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20150316

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20160314

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20170413

Year of fee payment: 12

LAPS Lapse due to unpaid annual fee