KR200232594Y1 - Supporting Structure for Concreting in Head of a Steel-Pile - Google Patents

Supporting Structure for Concreting in Head of a Steel-Pile Download PDF

Info

Publication number
KR200232594Y1
KR200232594Y1 KR2020010004331U KR20010004331U KR200232594Y1 KR 200232594 Y1 KR200232594 Y1 KR 200232594Y1 KR 2020010004331 U KR2020010004331 U KR 2020010004331U KR 20010004331 U KR20010004331 U KR 20010004331U KR 200232594 Y1 KR200232594 Y1 KR 200232594Y1
Authority
KR
South Korea
Prior art keywords
steel pipe
pipe pile
head
support
concrete
Prior art date
Application number
KR2020010004331U
Other languages
Korean (ko)
Inventor
오경환
임진규
Original Assignee
(주)한석엔지니어링건축사사무소
오경환
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)한석엔지니어링건축사사무소, 오경환 filed Critical (주)한석엔지니어링건축사사무소
Priority to KR2020010004331U priority Critical patent/KR200232594Y1/en
Application granted granted Critical
Publication of KR200232594Y1 publication Critical patent/KR200232594Y1/en

Links

Landscapes

  • Foundations (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

본 고안은 구조물의 기초공사시 강관말뚝의 두부와 기초콘크리트를 일체의 구조로 결합하기 위하여, 강관말뚝의 두부내 속채움콘크리트 타설을 위한 지지구조에 관한 것으로서, 강관말뚝(10)의 두부와 기초콘크리트(C)를 일체의 구조로 결합하기 위해 강관말뚝(10)의 두부내로 타설되는 속채움 콘크리트(A)를 지지하여 주는 구조에 있어서, 상기 강관말뚝(10)의 두부 내측으로 삽입되는 지지대(20)는 U자형태로 이루어지는 지지부재로서, 그 양단부가 각각 걸고리 형태로 절곡되어 강관말뚝(10)의 두부의 단부에 걸려지도록 형성된 걸고리부(21)와, 이 걸고리부(21)의 내측단으로부터 하측으로 절곡되어 각각 소정의 길이를 갖고 소정의 경사도를 갖고 하측으로 연장되는 수직간(22)과, 이 양측 수직간(22)의 하단에서 수평으로 절곡되어 연결되는 수평간(23)으로 구성되는 지지대(20)를 강관말뚝의 두부 단부에 적어도 2개이상을 설치하여서, 상기 지지대(20)들의 수평간(23)의 상측에 얹어져 설치되는 받침판(30)을 현수지지시켜 주도록 하는 지지구조를 제공함으로써, 시공작업이 용이할 뿐만 아니라, 공사기간을 단축시켜서 공사비용도 절감시켜 주는 것이다.The present invention relates to a support structure for filling concrete in the head of the steel pipe pile in order to combine the head of the steel pipe pile and the foundation concrete in an integral structure, the head and foundation of the steel pipe pile (10) In the structure for supporting the stuffed concrete (A) that is poured into the head of the steel pipe pile (10) in order to combine the concrete (C) in an integral structure, a support inserted into the head of the steel pipe pile (10) ( 20 is a U-shaped support member, the both ends of each of which is bent in the form of hooks hook hook portion 21 formed to be caught on the end of the head of the steel pipe pile 10, and the inner end of the hook portion 21 From the vertical space 22 which is bent downward from the vertical length 22, each having a predetermined length, and having a predetermined inclination, and extending downward, At least two support members 20 are formed at the head end of the steel pipe pile to support the support plates 30 suspended from the upper sides of the horizontal sections 23 of the support members 20. By providing the structure, not only the construction work is easy, but also the construction period is shortened, thereby reducing the construction cost.

Description

강관말뚝의 두부내 속채움콘크리트 타설을 위한 지지구조{Supporting Structure for Concreting in Head of a Steel-Pile}Supporting Structure for Concreting in Head of a Steel-Pile}

본 고안은 구조물의 기초공사시 연약지반의 기초를 보강하기 위해 정착되어진 강관말뚝의 두부와 기초콘크리트를 일체의 구조로 결합함에 있어서, 강관말뚝의 두부내로 철근조립체를 인입하여 속채움 콘크리의트 타설시 이를 지지하기 위하여강관말뚝의 두부 내에 설치되는 지지구조에 관한 것으로, 특히 강관말뚝의 두부 내부로 삽입되는 U자형의 지지대를 두부의 단부에 걸어 받침판을 현수지지하는 지지구조를 제공함으로써, 시공작업이 용이하여 공사기간을 단축시켜줄 뿐만 아니라, 공사비용도 절감시켜 주는 강관말뚝의 두부내 속채움콘크리트 타설을 위한 지지구조에 관한 것이다.The present invention combines the head of the steel pipe pile and the foundation concrete, which are fixed to reinforce the foundation of the soft ground, in the construction of the foundation. The present invention relates to a support structure installed in the head of a steel pipe pile to support a tooth, and in particular, by providing a support structure for suspending the support plate by hanging a U-shaped support inserted into the head of the steel pipe pile at the end of the head. The present invention relates to a supporting structure for filling concrete in the head of a steel pipe pile, which not only shortens the construction period due to its ease, but also reduces construction costs.

일반적으로 연약지반에 강관말뚝을 설치하여 구조물을 시공하는 경우, 항타기로 강관말뚝을 항타하여 강관말뚝의 선단을 견고한 지반에 정착시킨 후, 그 강관말뚝 위로 구조물의 하부구조인 기초콘크리트를 강관말뚝의 두부와 일체화시키는 구조로 이루어져 구조물의 하중을 정착된 강관말뚝을 통하여 견고한 지반상에서 지지하는 구조로 구축되어진다.In general, when constructing a structure by installing a steel pipe pile on a soft ground, the steel pipe pile is driven by a driving machine to fix the tip of the steel pipe pile on a solid ground, and then the foundation concrete, which is a substructure of the structure, is placed on the steel pipe pile. It consists of a structure that integrates with the head and is constructed to support the load of the structure on the solid ground through the steel pipe piles.

그런데, 구조물의 하부구조인 기초콘크리트를 강관말뚝과 일체화시키기 위해서는 중공으로 이루어진 강관말뚝의 두부 내에 속채움 콘크리트를 타설함에 있어, 강관말뚝의 두부내 삽입되는 보강철근 조립체를 지지하고, 추후 타설되는 콘크리트가 강관말뚝의 하측으로 흘러내리지 않도록 바닥거푸집의 역할을 하는 받침판을 지지하도록 강관말뚝의 두부에 지지구조부를 설치하게 된다.However, in order to integrate the foundation concrete, which is a substructure of the structure, with the steel pipe pile, in filling the concrete into the head of the hollow steel pipe pile, the reinforcing steel reinforcement assembly inserted into the head of the steel pipe pile is supported, and the concrete that is poured later The supporting structure is installed on the head of the steel pipe pile so as to support the supporting plate serving as the floor formwork so that the steel pipe pile does not flow down to the lower side of the steel pipe pile.

즉, 강관말뚝의 두부내에 수직·수평의 보강철근조립체를 설치하고, 수직의 보강철근들을 강관말뚝의 두부 상부로 노출시켜 기초콘크리트의 철근조립체에 일체로 연결하여 조립하게 된다.That is, vertical and horizontal reinforcing bar assemblies are installed in the head of the steel pipe pile, and vertical reinforcing bars are exposed to the upper part of the head of the steel pipe pile to be integrally connected to the reinforcing bar assembly of the foundation concrete.

이후, 기초콘크리트의 철근조립체와 강관말뚝의 두부내 삽입된 철근조립체가 일체로 조립연결된 상태에서 콘크리트를 타설함으로써, 철근조립체를 피복시키면서강관말뚝의 내측상단과 구조물의 하부구조인 기초콘크리트를 일체화시키는 구조로 구축되어지는 것이다.Subsequently, by pouring concrete while the reinforcing bar assembly of the foundation concrete and the reinforcing bar assembly inserted into the head of the steel pipe pile are integrally connected to each other, the inner concrete upper part of the steel pipe pile and the lower part of the structure are integrated while covering the reinforcing bar assembly. It is structured.

따라서, 기초콘크리트와 견고한 지반속에 정착된 강관말뚝의 상단이 일체화된 구조로 형성됨으로써, 기초콘크리트의 상부구조로부터 작용하는 적재하중이 기초콘크리트의 바닥면으로 분산되어 작용될 뿐만 아니라, 기초콘크리트의 구조와 일체로 결합되어진 강관말뚝을 통하여 견고한 지반으로 전달되기 때문에 구조물의 안정성을 도모할 수 있게 된다.Therefore, by forming the foundation concrete and the upper end of the steel pipe pile fixed in the solid ground, the loading load acting from the upper structure of the foundation concrete is distributed to the bottom surface of the foundation concrete, as well as the structure of the foundation concrete Since it is transmitted to the solid ground through the steel pipe pile that is integrally combined with the can ensure the stability of the structure.

상기와 같이, 강관말뚝의 두부내 속채움콘크리트 타설을 위한 지지구조와 관련된 종래의 기술로서는, 도1 및 도2의 도시와 같이, 그 지지구조부가 용접형태로 강관말뚝에 결합되어 적용된 기술로서, 견고한 지반에 정착된 강관말뚝(10)의 두부를 연약지반의 바닥면으로부터 20㎝ 정도만 노출되게 절단하고, 두부 상단에서 1m 아래부분의 내주면에 지지편(11)을 용접한 후, 그 지지편(11)의 상부에 원통관(12)을 거치시켜 강관말뚝의 내주면에 용접시킨 후, 원통관(12)의 상부에 다시 속채움 콘크리트(A)의 타설시 지지되는 받침판(13)을 거치시킨다.As described above, as a conventional technique related to the support structure for filling concrete in the head of the steel pipe pile, as shown in Figs. 1 and 2, the support structure is applied to the steel pipe pile in the welded form, After cutting the head of the steel pipe pile (10) fixed on the solid ground to expose only about 20cm from the bottom surface of the soft ground, weld the support piece 11 to the inner peripheral surface of 1m below the top of the head, the support piece ( 11) the cylindrical tube 12 is mounted on the upper portion of the steel pipe pile to weld to the inner circumferential surface of the cylindrical tube 12, the support plate 13, which is supported when placing the filling concrete (A) is mounted again.

상기와 같이 받침판(13)을 지지시킨 후에 연약지반의 바닥면과 강관말뚝(10)의 두부내 받침판 상에 일정두께의 버림콘크리트(B)를 타설하고, 강관말뚝(10)의 두부내로 수직·수평의 보강 철근조립체를 삽입하고, 이 철근조립체의 수직철근 (14)들이 강관말뚝(10)의 두부 상부로 노출되어서 기초콘크리트에 배근되는 수직·수평의 철근들에 조립 연결되면서 기초콘크리트의 철근조립체와 강관말뚝(10)의 두부내로 삽입된 보강 철근조립체를 일체로 조립 연결한다.After supporting the support plate 13 as described above, cast concrete (B) of a predetermined thickness on the bottom surface of the soft ground and the head support plate of the steel pipe pile 10, and vertically into the head of the steel pipe pile 10. Insert the horizontal reinforcing reinforcing bar assembly, and the vertical reinforcing bars 14 of the reinforcing bar assembly are exposed to the upper part of the head of the steel pipe pile 10 to be assembled and connected to the vertical and horizontal reinforcing bars which are placed on the foundation concrete. And connect the reinforcing reinforcing bar assembly inserted into the head of the steel pipe pile (10) integrally.

이후, 강관말뚝(10)의 내부에 삽입된 철근조립체의 강관말뚝(10)내로 속채움 콘크리트(A)를 타설한 후, 이어서 강관말뚝 외부의 기초콘크리트의 철근조립체가 매설되도록 기초구조부에도 콘크리트를 타설함으로써 강관말뚝의 두부와 구조물의 하부구조인 기초콘크리트를 일체의 구조로 성형시키게 된다.Then, after filling the filling concrete (A) into the steel pipe pile 10 of the reinforced steel assembly inserted into the steel pipe pile (10), and then the concrete to the foundation structure so that the reinforced assembly of the foundation concrete outside the steel pipe pile is embedded. By pouring, the head of the steel pipe pile and the foundation concrete, which is a substructure of the structure, are formed into an integral structure.

그러나, 상기와 같은 종래의 기술은 강관말뚝의 두부하단 1m부분 내주면에 지지편(11)과 원통관(12)을 용접하여 지지구조부를 형성함에 있어, 현실적으로 강관말뚝(10)의 관경이 작아 용접작업을 위한 작업자의 진입이 곤란하고, 안전하게 진입한다 하더라도 용접작업의 위험성이 상존할 뿐만 아니라, 용접작업이 현장에서 이루어지는 관계로 일정 품질을 확보할 수 없는 등 시공작업이 비효율적이고, 용접에 따른 지지구조부를 형성함에 있어 작업기간이 더 소요되는 문제점들을 갖고 있다.However, the prior art as described above is to form a support structure by welding the support piece 11 and the cylindrical tube 12 on the inner peripheral surface of the head of the lower end of the 1m portion of the steel pipe pile, the diameter of the steel pipe pile 10 is actually small welding It is difficult for the worker to enter the work and there is a risk of welding work even if it enters safely.In addition, the construction work is inefficient and cannot be secured due to the welding work being performed on site. In forming the structure, there is a problem that takes a longer working period.

한편, 다른 종래의 기술로서, 도3a 및 도3b에서 도시하는 바와 같이, 강관말뚝내 속채움 콘크리트 타설시 그 지지구조부가 볼트결합형태로 강관말뚝에 결합되어 적용된 기술로서, 이는 우선 강관말뚝(10)의 두부 측면부분에 타공위치를 표시한 후, 표시된 타공위치에 유압 타공기를 이용하여 볼트삽입구멍들을 형성한다.On the other hand, as another conventional technology, as shown in Figures 3a and 3b, when the filling concrete in the steel pipe pile, the supporting structure is applied to the steel pipe pile in the form of bolted coupling, which is first applied to the steel pipe pile (10) After marking the punching position on the head side of the head), the bolt insertion holes are formed by using a hydraulic punching machine at the marked punching position.

이후 단부 소정위치에 암나사홈(15)들이 구비된 십자형 연결구(16)를 일체로 형성한 공장제품을 강관말뚝(10)의 두부 내측에 삽입하여 상기 십자형 연결구(16)의 단부에 형성된 암나사홈(15)에 강관말뚝(10)에 형성된 볼트삽입구멍들을 일치시켜 강관말뚝의 외측에서 볼트(17)로 체결한 후, 십자형 연결구(16)의 상단 테두리부에 금속제의 덮개판(18)을 얹어 십자형 연결구(16)의 상단 테두리와 덮개판(18)을 용접하여 일체화시킨다.After inserting the factory product formed integrally with the cross-shaped connector 16 provided with female threaded grooves 15 at a predetermined end portion inside the head of the steel pipe pile 10, the female threaded groove formed at the end of the cross-shaped connector 16 ( 15) and the bolt insertion holes formed in the steel pipe pile (10) to match the bolt 17 from the outside of the steel pipe pile, and then put a metal cover plate (18) on the upper edge of the cross connector 16 The upper edge of the connector 16 and the cover plate 18 are welded together.

이후, 상기 덮개판(18)의 상면에 철근조립체를 고정시키고, 연약지반의 바닥면에 일정두게로 포설된 버림콘크리트(B)상에 배근되는 기초콘크리트의 철근조립체에 상기 덮개판의 상면에 고정되는 철근조립체를 일체로 조립 연결시킨 후, 콘크리트를 타설함으로써, 강관말뚝의 두부와 기초콘크리트(C)를 일체로 하는 구조를 구축하게 된다.Thereafter, the reinforcing bar assembly is fixed to the upper surface of the cover plate 18, and fixed to the upper surface of the cover plate to the reinforcing bar assembly of the foundation concrete, which is placed on the discarded concrete (B) laid at a predetermined thickness on the bottom surface of the soft ground. After assembling and connecting the reinforcing bar assemblies integrally, the concrete is poured, thereby constructing a structure in which the head of the steel pipe pile and the foundation concrete (C) are integrated.

그러나, 상기와 같은 종래의 기술도 강관말뚝 두부상단을 유압 타공기로 정확한 위치에 다수의 구멍들을 천공하는 작업과, 이 구멍들과 상기 원통형의 연결구를 지지하는 십자형의 보강부재의 단부측에 형성된 암나사부의 구멍을 일치시켜 볼트로 고정결합시키는 작업, 금속제의 덮개판 상부에 철근조립체를 고정시키는 작업등 번거로운 작업으로 인하여 시공이 비효율적일 뿐만 아니라, 현장에서 강관말뚝의 주면상 소정의 위치에 정확하게 타공을 하여야 하는 고도의 정밀시공이 요구됨으로써, 공사기간이 더 소요될 뿐만 아니라, 장치 및 부수자재 등을 사용함에 따른 공사비용이 증가되는 비경제적인 문제점들이 있었다.However, the prior art as described above is also formed in the end of the reinforcing member of the cross-shaped reinforcing member for drilling a plurality of holes in the correct position with a hydraulic perforator at the top of the steel pipe pile head The construction is not only inefficient due to the cumbersome work such as matching the holes of the female thread with the bolts and fixing the reinforcing steel assembly on the upper part of the metal cover plate, and precisely drilling holes in the predetermined position on the main surface of the steel pipe pile in the field. As a high precision construction is required to be, not only the construction period is longer, but also the cost of construction is increased due to the use of equipment and auxiliary materials.

따라서, 본 고안은 연약지반 구조물 시공에 따른 기초보강공사인 강관말뚝의 두부와 기초콘크리트를 일체화시키기 위하여, 강관말뚝의 두부 내측에 설치되는 지지구조부를 형성함에 있어, 상기 용접형태 및 볼트결합형태에 따른 종래기술의 문제점을 해결하고자 안출한 것으로, 강관말뚝 두부 상단에 걸고리형태로 걸려져 강관내부로 인입되는 'U'자 형상의 지지대를 이용하여 속채움 콘크리트 타설시 현수지지하는 받침판을 설치함으로써, 시공작업이 용이할 뿐만 아니라, 간단하여 공사기간을 단축시켜 주도록 하며, 또한, 그에 따라 공사비용을 절감시켜 주도록 하는 강관말뚝의 두부내 속채움콘크리트 타설을 위한 지지구조를 제공하는데 있다.Therefore, the present invention, in order to integrate the head of the steel pipe pile and the foundation concrete according to the construction of the soft ground structure, in forming the supporting structure installed inside the head of the steel pipe pile, the welding form and the bolt coupling form In order to solve the problems of the prior art according to the present invention, by using a 'U' shaped support that is hooked into the upper end of the steel pipe pile head and introduced into the steel pipe by installing a support plate to support the suspension during the filling of concrete, Not only the construction work is easy, but also to simplify the construction period, and also to reduce the construction cost accordingly to provide a supporting structure for the filling concrete in the head of the steel pipe pile to reduce the construction cost accordingly.

도1은 종래 일반적인 강관말뚝의 두부와 기초콘크리트를 일체화시킨 구조부의 단면도.1 is a cross-sectional view of a structural unit integrating the head of the conventional steel pipe pile and the foundation concrete.

도2는 종래기술로서, 강관말뚝내 속채움 콘크리트 타설시 그 지지구조부가 용접형태로 결합되어 적용된 상태를 나타낸 단면도.Figure 2 is a cross-sectional view showing a state in which the supporting structure is applied in the form of welding when pouring concrete in the steel pipe pile in the prior art.

도3a는 다른 종래기술로서, 강관말뚝내 속채움 콘크리트 타설시 그 지지구조부가 볼트결합형태로 이루어져 적용된 상태를 나타낸 단면도.Figure 3a is a cross-sectional view showing a state in which the support structure is made of bolted form when the concrete filling in the steel pipe pile in another prior art.

도3b는 도3a의 지지구조부에서 강관말뚝과 십자형의 연결구가 볼트결합되는 사시도.Figure 3b is a perspective view of the steel pipe pile and cross-shaped connector bolted to the support structure of Figure 3a.

도4는 본 고안에 따른 지지대와 받침판의 분리사시도.Figure 4 is an exploded perspective view of the support and the support plate according to the present invention.

도5는 본 고안에 따른 지지대와 받침판이 강관말뚝의 두부내 지지구조부를 형성하여 적용된 상태를 나타낸 단면도.Figure 5 is a cross-sectional view showing a state in which the support and the support plate according to the present invention is formed by forming a support structure in the head of the steel pipe pile.

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

10:강관말뚝 11:지지편 12:원통관10: steel pipe pile 11: support piece 12: cylinder tube

13:받침판 14:수직철근 15:암나사홈13: Support plate 14: Vertical rebar 15: Female thread groove

16:십자형 연결구 17:볼트 18:덮개판16: Cross connector 17: Bolt 18: Cover plate

20:지지대 21:걸고리부 22:수직간20: support 21: hook part 22: vertical

23:수평간 30:받침판 31:가이드홈23: horizontal 30: support plate 31: guide groove

A:속채움 콘크리트 B:버림콘크리트 C:기초콘크리트A: Stuffed concrete B: Cast concrete C: Foundation concrete

상기 목적을 달성하기 위한 본 고안은 강관말뚝(10)의 두부와 기초콘크리트 (C)를 일체의 구조로 결합하기 위해 강관말뚝(10)의 두부내로 타설되는 속채움 콘크리트(A)를 지지하여 주는 구조에 있어서,The present invention for achieving the above object is to support the stuffing concrete (A) that is poured into the head of the steel pipe pile (10) to combine the head of the steel pipe pile (10) and the base concrete (C) as an integral structure In structure,

상기 강관말뚝(10)의 두부 내측으로 삽입되는 지지대(20)는 U자형태로 이루어지는 지지부재로서, 그 양단부가 각각 걸고리 형태로 절곡되어 강관말뚝(10)의 두부의 단부에 걸려지도록 형성된 걸고리부(21)와, 이 걸고리부(21)의 내측단으로부터 하측으로 절곡되어 각각 소정의 길이를 갖고 수직으로 연장되는 수직간(22)과, 이 양측 수직간(22)의 하단에서 수평으로 절곡되어 연결되는 수평간(23)으로 구성되는 지지대(20)를 강관말뚝의 두부 단부에 적어도 2개이상을 방사상으로 설치하여서, 상기 지지대(20)들의 수평간(23)의 상측에 얹어져 설치되는 받침판(30)을 지지시켜 주도록 하는 것을 특징으로 하는 강관말뚝의 두부내 속채움콘크리트 타설을 위한 지지구조를 제공한다.The support 20 inserted into the head of the steel pipe pile 10 is a support member having a U-shape, and both ends thereof are bent in the form of hooks, and the hook portion is formed to be caught on the end of the head of the steel pipe pile 10. (21), the vertical section 22 which is bent downward from the inner end of the hook portion 21 and has a predetermined length, respectively, and extends vertically, and horizontally bent at the lower ends of the two vertical sections 22; Support plate 20 consisting of the horizontal bar 23 is connected to the radially installed at least two or more at the head end of the steel pipe pile, the support plate is installed on the upper side of the horizontal bar 23 of the support 20 Provides a support structure for filling concrete within the head of the steel pipe pile, characterized in that to support (30).

이하, 본 고안의 기술구성을 첨부도면을 참조하여 구체적으로 설명한다.Hereinafter, the technical configuration of the present invention will be described in detail with reference to the accompanying drawings.

도4는 본 고안에 따른 지지대와 받침판의 분리사시도이고, 도5는 본 고안에 따른 지지대와 받침판이 강관말뚝의 두부내 지지구조부를 형성하여 적용된 상태를 나타낸 단면도로서, 부호 20은 지지대이고, 부호 30은 받침판이다.Figure 4 is an exploded perspective view of the support and the support plate according to the present invention, Figure 5 is a cross-sectional view showing a state in which the support and the support plate according to the present invention is formed by forming a support structure in the head of the steel pipe pile, reference numeral 20 is a support, 30 is a support plate.

상기 지지대(20)는 U자형태로 이루어져서 강관말뚝의 내부로 인입되는 지지부재로서, 그 양단부가 각각 걸고리 형태로 절곡되어 강관말뚝(10)의 두부의 단부에 걸려지도록 형성된 걸고리부(21)와, 이 걸고리부(21)의 내측단으로부터 하측으로 절곡되어 각각 소정의 길이를 갖고 수직으로 연장되는 수직간(22)과, 이 양측 수직간(22)의 하단에서 수평으로 절곡되어 연결되는 수평간(23)으로 구성된다.The support 20 is formed as a U-shaped support member to be introduced into the inside of the steel pipe pile, the both ends of the hook portion 21 is formed to be hooked to the end of the head portion of the steel pipe pile 10 and The vertical section 22, which is bent downward from the inner end of the hook portion 21 and has a predetermined length, respectively, and extends vertically, and the horizontal section that is horizontally bent and connected at the lower ends of the two vertical sections 22, respectively. It consists of 23.

상기 수직간(22)은 강관말뚝의 두부내측으로 원활한 삽입이 가능하도록 수직에 가까운 소정의 경사도를 갖도록 형성되어 있으며, 상기 수평간(23)은 수평으로 뻗어, 받침판(30)의 저면에서 지지하여 주게 된다.The vertical section 22 is formed to have a predetermined inclination close to the vertical to enable the smooth insertion into the head of the steel pipe pile, the horizontal section 23 extends horizontally, to support from the bottom surface of the support plate 30 Given.

상기 받침판(30)은 강관말뚝의 두부내로 삽입되므로 강관말뚝의 내경보다 약간 작은 직경을 갖는 크기의 내수성 합판으로서, 상기 지지대(20)의 수평간(21)들의 상부에 얹어져서 추후 강관말뚝의 두부내로 속채움 콘크리트를 타설할 때 지지시켜 주는 지지판의 기능을 하는 부재이다.Since the support plate 30 is inserted into the head of the steel pipe pile, it is a water-resistant plywood having a diameter slightly smaller than the inner diameter of the steel pipe pile, and is mounted on the upper portions of the horizontal sections 21 of the support 20 so that the head of the steel pipe pile is later. It is a member that functions as a support plate to support when pouring concrete.

상기 지지대(20)의 수평간(23)들에 얹어지는 받침판(30)은 단순히 원형의 형태로 형성되어진 것을 강관말뚝의 두부내로 삽입하여 설치하여도 좋으나, 바람직하기는 그 테두리 단부상에 상기 지지대(20)의 수직간(22)들이 끼워지도록 상응하는 위치에 가이드홈(31)들이 형성되어진 것을 사용하는 것이 바람직하다. 이는 수직간 (22)들이 받침판(30)의 가이드홈(31)들내로 끼워짐으로써 받침판(30)이 유동되는 것을 방지하여 더욱 견고한 지지구조부를 형성해 주기 위해서이다.The support plate 30 mounted on the horizontal sections 23 of the support 20 may be simply inserted into the head of the steel pipe pile, which is formed in a circular shape, but is preferably provided on the edge end thereof. It is preferable to use that the guide grooves 31 are formed in the corresponding position so that the vertical bars 22 of the 20 are fitted. This is to prevent the support plate 30 from flowing by inserting the vertical sections 22 into the guide grooves 31 of the support plate 30 to form a more rigid support structure.

상술한 바와 같이 구성되는 본 고안의 강관말뚝내에 지지구조부를 형성하는 과정을 설명하면 다음과 같다.Referring to the process of forming the support structure in the steel pipe pile of the present invention configured as described above are as follows.

먼저, 연약지반에 구조물 시공을 위해 강관말뚝(10)을 항타한 후, 강관말뚝의 두부 상단이 연약지반의 바닥면으로부터 상측으로 대략 20㎝를 남겨두고, 자동절단기를 이용하여 돌출된 강관말뚝(10)의 두부를 절단한다.First, after driving the steel pipe pile 10 for the construction of the structure on the soft ground, the top of the head of the steel pipe pile left approximately 20 cm from the bottom surface of the soft ground, the steel pipe pile protruded using an automatic cutting machine ( Cut the head of 10).

그 다음에, 사전에 철근을 절곡시켜 걸고리부(21), 수직간(22) 및 수평간 (23)을 형성한 U자형태로 이루어진 지지대(20)를 강관말뚝(10)의 두부 내측으로 삽입하여, 상기 지지대(20)의 걸고리부(23)들이 강관말뚝(10)의 단부에 걸려지도록 한다.Next, the support 20 having a U-shape in which the hook portion 21, the vertical rod 22 and the horizontal rod 23 is formed by bending the rebar in advance is inserted into the head of the steel pipe pile 10. By doing so, the hook portion 23 of the support 20 to be caught on the end of the steel pipe pile (10).

이때, 상기 지지대(20)는 강관말뚝의 단부상에 적어도 2개이상 복수개의 지지대들을 방사상으로 설치하는 것이 바람직하다. 이는 받침판(30)의 상측으로 추후 설치되는 철근조립체와, 타설되는 속채움콘크리트(A)가 일측으로 편중되지 않도록 수평으로 균형되게 위치하도록 하기 위해서이다.At this time, the support 20 is preferably installed radially at least two or more support on the end of the steel pipe pile. This is for the rebar assembly to be installed later to the upper side of the support plate 30, and to be placed horizontally balanced so that the stuffing concrete (A) to be poured is not biased to one side.

한편, 강관말뚝의 두부내에 삽입되어 지지되는 지지대(20)들은 사전에 복수개를 일련의 조립체로서 연결되어진 철근조립체를 사용하는 것이 바람직하며, 이때 받침판 (30)들도 지지대(20)들과 사전에 일체로 조립시킬 수도 있다.On the other hand, the support 20 to be inserted into the head of the steel pipe pile is supported by using a reinforcing bar assembly, which is connected in advance as a plurality of assemblies, the support plate 30 is also in advance with the support (20) It can also be assembled integrally.

이는 지지대들을 여러 차례에 걸쳐 강관말뚝의 단부에 설치하는 것보다, 사전에 조립되어진 철근조립체를 한번의 설치작업으로 완료함으로써 강관말뚝상에 지지대 설치작업의 효율성을 제고하여 주기 때문이다.This is because the efficiency of installing the support on the steel pipe pile is improved by completing the pre-assembled reinforcing bar assembly in one installation rather than installing the supports at the end of the steel pipe pile several times.

상기와 같이, 지지대(20)의 걸고리부(23)들이 강관말뚝(10)의 단부에 걸려진후, 강관말뚝(10)의 두부 내측으로 받침판(30)을 삽입하여 상기 수평간(21)의 상측에 얹어지도록 현수지지시키고, 이후 강관말뚝(10)의 내주면과 받침판(30)과의 틈사이에는 추후 타설되는 콘크리트가 빠져나가지 않도록 실링재로 밀봉시킨다.As described above, after the hooks 23 of the support 20 are hooked to the end of the steel pipe pile 10, the support plate 30 is inserted into the head of the steel pipe pile 10 to the upper side of the horizontal section 21. Suspension support to be mounted on, and then sealed between the inner circumferential surface of the steel pipe pile 10 and the support plate 30 with a sealing material to prevent the concrete to be poured later.

상기와 같이 받침판(30)의 설치가 완료되면 그 받침판(30)의 상측으로 약간의 버림콘크리트(B)를 타설하고 그 상측으로 수직·수평의 보강 철근조립체를 인입하고 강관말뚝의 두부 상측으로 소정길이로 돌출된 수직철근(14)을 기초콘크리트에 배근되어진 철근조립체에 조립연결하여 하나의 철근구조체로 일체화시킨다.When the installation of the support plate 30 is completed as described above, a little cast concrete (B) is poured into the upper side of the support plate 30, the vertical and horizontal reinforcing reinforcing bar assembly is introduced into the upper side of the support plate 30, and predetermined to the upper side of the head of the steel pipe pile The vertical reinforcing bar 14 protruding in length is assembled to the reinforcing bar assembly, which is disposed on the foundation concrete, and integrated into one reinforcing bar structure.

이때, 연약지반의 바닥면에 일정두께의 버림콘크리트(B)를 타설한 이후에 기초콘크리트(C)에 배근되는 철근을 조립하는 것임을 밝혀 둔다.At this time, after placing the cast concrete (B) of a predetermined thickness on the bottom surface of the soft ground to reveal that the reinforcement is reinforced to the foundation concrete (C).

상기와 같이, 철근구조체를 일체로 한 이후, 상기 강관말뚝(10)의 두부 내측으로 속채움 콘크리트(A)를 타설함과 동시에 기초콘크리트의 철근구조체를 피복시키도록 콘크리트를 타설하여 기초콘크리트(C)와 강관말뚝의 단부를 일체의 구조로 성형시킨다.As described above, after the reinforcing structure is integrated, the concrete is poured to cover the reinforcing structure of the foundation concrete at the same time as the filling concrete (A) is poured into the head of the steel pipe pile (10). ) And the ends of the steel pipe piles into an integral structure.

이와 같이 하여 강관말뚝의 두부와 기초콘크리트를 일체화된 구조로 성형시킴으로써, 구조물의 기초공사를 완료하게 된다.In this way, by forming the head and the foundation concrete of the steel pipe pile into an integrated structure, the basic construction of the structure is completed.

상기에서 기재한 바와 같이, 강관말뚝의 두부와 기초콘크리트를 일체화의 구조로 결합되도록 설치되는 본 고안의 강관말뚝의 두부내 속채움콘크리트 타설을 위한 지지구조에 의하면,As described above, according to the support structure for filling concrete in the head of the steel pipe pile of the present invention is installed to combine the head of the steel pipe pile and the foundation concrete in an integrated structure,

종래 강관말뚝의 속채움콘크리트를 지지하는 지지구조부가 용접 또는 볼트결합형태로 이루어져서 시공작업이 까다로웠던 것과 달리, 단순히 강관말뚝의 두부 내측으로 U자형의 지지대를 삽입하여 지지대 양단부의 걸고리부를 강관말뚝의 두부 단부에 걸어서, 이 지지대의 수평간의 상측에 받침판을 얹어 현수지지하는 구조를 제공함으로써, 현장에서 간편하게 설치가 가능하여 시공작업이 용이할 뿐만 아니라, 공사기간을 단축시켜 주는 효과가 있다.Unlike the conventional construction structure, which supports the filled concrete of the steel pipe piles by welding or bolting, the construction work is difficult, simply by inserting a U-shaped support into the head of the steel pipe pile so that the hooks at both ends of the steel pipe piles By hanging on the head end of the support, by providing a structure for supporting the suspension by placing a support plate on the upper side between the horizontal of the support, it is possible to install easily in the field, not only easy construction work, but also shorten the construction period.

또한, 현장에서 U자형으로 철근을 절곡시킨 지지대와 내수성 합판의 받침판으로만 설치되어지기 때문에 종래의 용접작업, 볼트삽입구멍등을 형성하기 위한 강관말뚝의 타공작업에 따른 장비 및 부수자재가 필요없게 됨으로써, 경제적인 비용으로 시공이 가능한 효과가 있다.In addition, since it is installed only on the support plate of the U-shaped reinforcing bar and the support plate of the water-resistant plywood in the field, the equipment and auxiliary materials according to the conventional welding work, the drilling work of the steel pipe pile to form the bolt insertion hole, etc. are unnecessary. By doing so, there is an effect that can be constructed at an economic cost.

기타 강관말뚝의 두부를 속채움 콘크리트로 보강하여 기초콘크리트와 일체화함으로써, 구조적인 안정성을 갖도록 해주는 효과가 있다.By reinforcing the head of the other steel pipe piles with stuffed concrete, and integrated with the foundation concrete, there is an effect to have a structural stability.

이상에서 살펴본 바와 같이, 본 고안은 시공작업이 용이하고, 그에 따라 공사기간이 단축될 뿐만 아니라, 공사비용도 절감시켜 주는 등의 여러 효과를 갖는 매우 유용한 고안이다.As described above, the present invention is a very useful design having a number of effects, such as easy construction work, thereby shortening the construction period, and also reduce the construction cost.

Claims (3)

강관말뚝(10)의 두부와 기초콘크리트(C)를 일체의 구조로 결합하기 위해 강관말뚝(10)의 두부내로 타설되는 속채움 콘크리트(A)를 지지하여 주는 구조에 있어서,In the structure for supporting the stuffing concrete (A) that is poured into the head of the steel pipe pile 10 in order to combine the head of the steel pipe pile (10) and the base concrete (C) in an integrated structure, 상기 강관말뚝(10)의 두부 내측으로 삽입되는 지지대(20)는 U자형태로 이루어지는 지지부재로서, 그 양단부가 각각 걸고리 형태로 절곡되어 강관말뚝(10)의 두부의 단부에 걸려지도록 형성된 걸고리부(21)와, 이 걸고리부(21)의 내측단으로부터 하측으로 절곡되어 각각 소정의 길이를 갖고 소정의 경사도를 갖고 하측으로 연장되는 수직간(22)과, 이 양측 수직간(22)의 하단에서 수평으로 절곡되어 연결되는 수평간(23)으로 구성되는 지지대(20)를 강관말뚝의 두부 단부에 적어도 2개이상을 방사상으로 설치하여서, 상기 지지대(20)들의 수평간(23)의 상측에 얹어져 설치되는 받침판 (30)을 현수지지시켜 주도록 하는 것을 특징으로 하는 강관말뚝의 두부내 속채움콘크리트 타설을 위한 지지구조.The support 20 inserted into the head of the steel pipe pile 10 is a support member having a U-shape, and both ends thereof are bent in the form of hooks, and the hook portion is formed to be caught on the end of the head of the steel pipe pile 10. (21), a vertical gap 22 which is bent downward from the inner end of the hook portion 21, has a predetermined length, has a predetermined inclination, and extends downward, and the lower ends of the two vertical gaps 22; At least two or more radially installed on the head end of the steel pipe pile, the support 20 consisting of a horizontal space 23 is bent horizontally connected in the upper portion of the horizontal space 23 of the support 20 A support structure for pouring concrete within the head of the steel pipe pile, characterized in that to support the suspended support plate 30 is installed on the suspension. 제1항 또는 제2항에 있어서, 상기 강관말뚝(10)의 두부내로 삽입되어 지지되는 지지대(20)들은 철근조립체이며, 그 지지대(20)들과 받침판 (30)은 사전에 일체로 조립되어 연결된 것을 특징으로 하는 강관말뚝의 두부내 속채움콘크리트 타설을 위한 지지구조.According to claim 1 or 2, wherein the support 20 is inserted into the head of the steel pipe pile 10 is supported by the reinforcing bar assembly, the support 20 and the support plate 30 is integrally assembled in advance Support structure for placing concrete filling in the head of the steel pipe piles, characterized in that connected. 제1항에 있어서, 상기 받침판(30)에는 그 테두리 단부상에 상기 지지대(20)의 수직간(22)들이 끼워지도록 상응하는 위치에 가이드홈(31)들이 형성되어진 것을 특징으로 하는 강관말뚝의 두부내 속채움콘크리트 타설을 위한 지지구조.The method according to claim 1, wherein the support plate 30 is formed in the corresponding groove so that the guide grooves 31 are formed in the corresponding position so that the vertical intervals 22 of the support 20 on the edge end of the steel pipe pile Support structure for filling concrete in the head.
KR2020010004331U 2001-02-20 2001-02-20 Supporting Structure for Concreting in Head of a Steel-Pile KR200232594Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR2020010004331U KR200232594Y1 (en) 2001-02-20 2001-02-20 Supporting Structure for Concreting in Head of a Steel-Pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR2020010004331U KR200232594Y1 (en) 2001-02-20 2001-02-20 Supporting Structure for Concreting in Head of a Steel-Pile

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
KR10-2001-0008371A Division KR100420075B1 (en) 2001-02-20 2001-02-20 Supporting Structure for Concreting in Head of a Steel-Pile

Publications (1)

Publication Number Publication Date
KR200232594Y1 true KR200232594Y1 (en) 2001-10-06

Family

ID=73080859

Family Applications (1)

Application Number Title Priority Date Filing Date
KR2020010004331U KR200232594Y1 (en) 2001-02-20 2001-02-20 Supporting Structure for Concreting in Head of a Steel-Pile

Country Status (1)

Country Link
KR (1) KR200232594Y1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100437261B1 (en) * 2001-08-03 2004-06-23 비비엠코리아(주) steel pipe pile head reinforcement structure
KR100449520B1 (en) * 2001-08-21 2004-09-21 김미순 A Unit for Reinforcing a Head of a Steel Tube Pile and a Reinforcement Structure Using the Unit

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100437261B1 (en) * 2001-08-03 2004-06-23 비비엠코리아(주) steel pipe pile head reinforcement structure
KR100449520B1 (en) * 2001-08-21 2004-09-21 김미순 A Unit for Reinforcing a Head of a Steel Tube Pile and a Reinforcement Structure Using the Unit

Similar Documents

Publication Publication Date Title
KR100917044B1 (en) Concrete retaining wall construction method with dual wall jointed by anchor
JP4812324B2 (en) Retaining wall and its construction method
KR101973565B1 (en) Sheathing method for constructing both sheathing wall and cutoff collar by welding cutoff plate to phc pile with longitudinal plate
JP4433066B2 (en) Wall structure with permanent anchor construction, wall construction method with permanent anchor construction,
JP4013182B2 (en) Self-supporting mountain retaining wall method and self-supporting mountain retaining wall
KR20180124795A (en) An Earth Retaining Wall with Underground Buttresses and A Method of Constructing the same
JP2006104747A (en) Pier stud connection structure and pier stud connecting method
KR102286225B1 (en) Method for constructing underground structure busing PC integrating method without support
JP4123058B2 (en) Construction method of wall structure with permanent anchor construction, Wall structure with permanent anchor construction
KR100420075B1 (en) Supporting Structure for Concreting in Head of a Steel-Pile
KR100673475B1 (en) A pc girder member for frame of underground layer and assembling structure of frame of underground by using of it and the method therof
KR100461914B1 (en) Device fixing bar and structure for connecting head of steel pile and concrete footing of the same
KR200232594Y1 (en) Supporting Structure for Concreting in Head of a Steel-Pile
JP2004100157A (en) Retaining wall structure and its construction method
KR200370107Y1 (en) Forms for edge girder construction
KR20060064994A (en) A pile head reinforcement structure of precastconcrete pile
JP3603130B2 (en) Root-wound reinforcement structure for column bases such as steel columns
KR200376519Y1 (en) Bracket for supporting forms for perimeter girder construction
KR100562686B1 (en) The underground structure and it&#39;s construction method is using sheet pile and cast in a place concrete
KR200386881Y1 (en) A pile head reinforcement structure of precast concrete pile
KR20110103793A (en) Simple supported multiple reinforcement of steel pipe pile and reinforcing method using the same
JP5008683B2 (en) Pile head reinforcement member and pile head reinforcement structure using it
JP5280150B2 (en) Yamadome retaining wall and method of forming Yamadome retaining wall
KR200418842Y1 (en) Fixing structure between jointing portion of deep-decks
CN113089883A (en) Prefabricated constructional column assembling structure and method for building block wall

Legal Events

Date Code Title Description
U107 Dual application of utility model
REGI Registration of establishment
T201 Request for technology evaluation of utility model
T701 Written decision to grant on technology evaluation
G701 Publication of correction
LAPS Lapse due to unpaid annual fee