KR100437261B1 - steel pipe pile head reinforcement structure - Google Patents
steel pipe pile head reinforcement structure Download PDFInfo
- Publication number
- KR100437261B1 KR100437261B1 KR10-2001-0072460A KR20010072460A KR100437261B1 KR 100437261 B1 KR100437261 B1 KR 100437261B1 KR 20010072460 A KR20010072460 A KR 20010072460A KR 100437261 B1 KR100437261 B1 KR 100437261B1
- Authority
- KR
- South Korea
- Prior art keywords
- steel pipe
- pipe pile
- support
- support plate
- ring
- Prior art date
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/226—Protecting piles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/223—Details of top sections of foundation piles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2600/00—Miscellaneous
- E02D2600/20—Miscellaneous comprising details of connection between elements
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
- Foundations (AREA)
Abstract
본 발명은 종래 기술의 용접방식과 속채움방식에서의 현장 용접의 문제점을 해결하여 강관말뚝의 결합구 보강구조의 조립성 개선 및 품질을 향상시키고, 또한 초기 인장력에 대한 취약한 구조를 개선할 수 있도록 하는 강관말뚝의 머리부 보강구조를 제공하는 것으로, 강관말뚝의 상부로부터 삽입 설치되어 속채움되는 콘크리트를 받침하고 동시에 그 상부에 설치된 연결링을 통해 보강철근의 하단과 연결되어 지지하는 받침판과, 이 받침판에 수직으로 설치된 복수의 로드를 매개로 연결되어 받침판을 지지하도록 강관말뚝의 상부에 볼트 체결 지지되는 체결링과 지지링으로 이루어진 결합구와, 상기 강관말뚝의 내부 둘레에 볼트 체결되어 강관말뚝에 속채움된 콘크리트의 초기 인장력과 압축력에 대항하도록 복수의 버팀블록으로 구성된 강관말뚝의 머리부 보강구조에 있어서, 상기 결합구를 구성하는 체결링과 지지링을 적어도 1개 이상으로 등분 분할하여 강관말뚝의 치수공차에 대응하도록 한 것을 특징으로 한다.The present invention is to solve the problem of the field welding in the welding method and the filling method of the prior art to improve the assemblability and quality of the coupling reinforcing structure of the steel pipe pile, and also to improve the weak structure against the initial tensile force To provide a reinforcing structure of the head of the steel pipe pile to support, the supporting plate is inserted from the top of the steel pipe pile to support the concrete filling and at the same time connected to the bottom of the reinforcing steel reinforcement through the connection ring installed on the top, A coupling port consisting of a coupling ring and a support ring that is bolted and supported on an upper portion of the steel pipe pile to support the supporting plate by connecting a plurality of rods vertically installed on the supporting plate, and bolted around an inner circumference of the steel pipe pile to be connected to the steel pipe pile. Steel pipe pile consisting of multiple support blocks to counter the initial tensile and compressive forces of filled concrete In the head unit structure reinforced by dividing equally the locking ring and the support ring constituting the coupler by one or more characterized in that at least one so as to correspond to the dimensional tolerances of the steel pipe pile.
Description
본 발명은 토목 또는 건축 구조물의 기초로서 사용되는 강관말뚝에 관한 것으로, 특히 강관말뚝의 머리부를 기초콘크리트와 결합하는 강관말뚝의 머리부 보강구조에 관한 것이다.The present invention relates to a steel pipe pile used as a foundation of civil engineering or building structures, and more particularly, to a head reinforcing structure of a steel pipe pile that couples the head of the steel pipe pile with the foundation concrete.
기존의 도로교 표준시방서에는 강관의 둘레에 철근을 용접하는 용접방식과 강관 내부에 콘크리트를 채우는 속채움방식이 있으나 용접방식의 경우 현장용접의 문제점으로 인한 품질상의 문제가 항상 대두되어 왔으며, 속채움방식의 경우도 좁은 강관 내부에 미끄럼 방지턱을 설치하기 위해 내부에 현장 용접을 해야 하는 문제점을 안고 있어 현장 적용시 어려움이 많았다.Conventional road bridge standard specifications include a welding method for welding reinforcing steel bars and a filling method for filling concrete inside the steel pipe. However, the welding method has always raised quality problems due to problems of field welding. In the case of also had a problem in the field welding to install the non-slip jaw inside the narrow steel pipe had a lot of difficulties in the field application.
따라서 본 발명은 상기와 같은 종래 기술의 용접방식과 속채움방식에서의 현장 용접의 문제점을 해결하여 강관말뚝의 결합구 보강구조의 조립성 개선 및 품질을 향상시키고, 또한 초기 인장력에 대한 취약한 구조를 개선할 수 있도록 하는 강관말뚝의 머리부 보강구조를 제공하는데 그 목적이 있다.Therefore, the present invention solves the problem of the field welding in the welding method and the filling method of the prior art as described above to improve the assemblability and quality of the reinforcing structure of the coupler reinforcing steel pipe pile, and also to provide a weak structure against the initial tensile force Its purpose is to provide a head reinforcement structure for steel pipe piles that can be improved.
상기의 목적을 달성하기 위해 본 발명은,The present invention to achieve the above object,
강관말뚝의 상부로부터 삽입 설치되어 속채움되는 콘크리트를 받침하고 동시에 그 상부에 설치된 연결링을 통해 보강철근의 하단과 연결되어 지지하는 받침판과, 이 받침판에 수직으로 설치된 복수의 로드를 매개로 연결되어 받침판을 지지하도록 강관말뚝의 상부에 볼트 체결 지지되는 체결링과 지지링으로 이루어진 결합구와, 상기 강관말뚝의 내부 둘레에 볼트 체결되어 강관말뚝에 속채움된 콘크리트의 초기 인장력과 압축력에 대항하도록 복수의 버팀블록으로 구성된 강관말뚝의 머리부 보강구조에 있어서,The bearing plate is inserted from the upper part of the steel pipe pile to support the filled concrete, and at the same time, the support plate is connected to and supported by the lower end of the reinforcing bar through the connecting ring installed at the upper part thereof, and a plurality of rods vertically installed on the support plate are connected to each other. A coupler consisting of a coupling ring and a support ring bolted to the upper portion of the steel pipe pile to support the support plate, and a plurality of bolts fastened around the inside of the steel pipe pile to counter the initial tensile and compressive force of the concrete filled in the steel pipe pile In the head reinforcement structure of the steel pipe pile consisting of a support block,
상기 결합구를 구성하는 체결링과 지지링을 적어도 1개 이상으로 등분 분할하여 강관말뚝의 치수공차에 대응하도록 한 것을 특징으로 한다.The coupling ring and the support ring constituting the coupler is divided into at least one or more, characterized in that to correspond to the dimensional tolerance of the steel pipe pile.
또한 본 발명은,In addition, the present invention,
강관말뚝의 상부로부터 삽입 설치되어 속채움되는 콘크리트를 받침하고 동시에 그 상부에 설치된 연결링을 통해 보강철근의 하단과 연결되어 지지하는 받침판과, 이 받침판에 수직으로 설치되고 그 상부가 절곡되어 강관말뚝의 상부 주연에 걸어져 상기 받침판을 지지하는 로드로 이루어진 결합구와, 상기 강관말뚝의 내부 둘레에 분할된 복수 형태로 하여 단계적으로 볼트 체결 설치되어 강관말뚝에 속채움된 콘크리트의 초기 인장력과 압축력에 대항하도록 하는 버팀링과 버팀블록으로 구성된 것을 특징으로 한다.Support plate inserted and installed from the upper part of the steel pipe pile to support the filled concrete and at the same time connected to and supported by the lower end of the reinforcing bar through the connecting ring installed on the upper part, and vertically installed on the support plate and the upper part of the steel pipe pile Coupled to the upper periphery of the coupling sphere consisting of a rod for supporting the support plate, and divided into a plurality of forms around the inner circumference of the steel pipe pile bolt installation step by step against the initial tensile and compressive force of concrete filled in the steel pipe pile It is characterized by consisting of the bracing and the bracing block.
또한 본 발명은,In addition, the present invention,
강관말뚝의 상부로부터 삽입 설치되어 속채움되는 콘크리트를 받침하는 받침판과, 이 받침판에 수직으로 설치되고 그 상부가 절곡되어 강관말뚝의 상부 주연에 걸어져 상기 받침판을 지지하는 로드로 이루어진 결합구와, 상기 강관말뚝의 둘레에 복수 형성된 구멍을 통해 하단이 절곡되어 직접 설치되는 보강철근과, 상기 강관말뚝의 내부 둘레에 분할된 복수 형태로 하여 단계적으로 볼트 체결 설치되어 강관말뚝에 속채움된 콘크리트의 초기 인장력과 압축력에 대항하도록 하는 버팀링과 버팀블록으로 구성된 것을 특징으로 한다.A coupling plate comprising a support plate inserted from an upper portion of the steel pipe pile to support the filled concrete, a rod installed vertically on the support plate and bent at an upper portion thereof to be hooked on the upper periphery of the steel pipe pile to support the support plate; Initial reinforcement of concrete reinforced in steel pipe piles by bolts installed step by step in a plurality of forms divided into inner circumferences of the steel pipe piles by bending the lower ends through a plurality of holes formed in the periphery of the steel pipe piles. And a bracing and bracing block configured to counteract the compression force.
또한 본 발명은,In addition, the present invention,
강관말뚝의 상부로부터 삽입 설치되어 속채움되는 콘크리트를 받침하고 동시에 그 상부에 설치된 연결링을 통해 보강철근의 하단과 연결되어 지지하는 받침판 및 이 받침판이 강관말뚝 내에 고정되도록 받침판의 하부에 설치되는 탄성링과, 상기 강관말뚝의 내부 둘레에 분할된 복수 형태로 하여 단계적으로 볼트 체결 설치되어 강관말뚝에 속채움된 콘크리트의 초기 인장력과 압축력에 대항하도록 하는 버팀링과 버팀블록으로 구성된 것을 특징으로 한다.The support plate inserted from the upper part of the steel pipe pile to support the filled concrete, and at the same time, the support plate connected to and supported by the lower end of the reinforcing steel through the connection ring installed on the upper part, and the elastic plate installed at the lower part of the support plate so that the support plate is fixed in the steel pipe pile. Ring and a plurality of forms divided into the inner circumference of the steel pipe piles is characterized in that it consists of braces and brace blocks to be installed in step by bolt fastening to counteract the initial tensile and compressive forces of the concrete filled in the steel pipe piles.
또한 본 발명은,In addition, the present invention,
강관말뚝의 상부로부터 삽입 설치되어 속채움되는 콘크리트를 받침하는 받침판 및 이 받침판이 강관말뚝 내에 고정되도록 받침판의 하부에 설치되는 탄성링과, 상기 강관말뚝의 둘레에 복수 형성된 구멍을 통해 하단이 절곡되어 직접 설치되는 보강철근과, 상기 강관말뚝의 내부 둘레에 분할된 복수 형태로 하여 단계적으로 볼트 체결 설치되어 강관말뚝에 속채움된 콘크리트의 초기 인장력과 압축력에 대항하도록 하는 버팀링과 버팀블록으로 구성된 것을 특징으로 한다.The bottom plate is bent through a plurality of holes formed in the bottom of the support plate and the support plate is inserted from the top of the steel pipe pile to support the filled concrete and the support plate is fixed to the steel pipe pile and the periphery formed around the steel pipe pile It consists of a reinforcing steel that is directly installed, and a brace and a support block that is installed in a plurality of forms divided around the inner circumference of the steel pipe pile so as to counteract the initial tensile and compressive forces of the concrete filled in the steel pipe pile. It features.
또한 본 발명은 상기에서 버팀링의 대응위치 강관 외경에 삽입되는 내경을 가지는 외부 버팀링을 더 추가해서 된 것을 특징으로 한다.In another aspect, the present invention is characterized in that it further added to the outer brace having an inner diameter inserted into the outer diameter of the corresponding position of the brace ring.
그리고 상기의 버팀블록은 그 단면이 L자형으로 걸림턱을 가지게 형성되게 한 것을 특징으로 한다.And the brace block is characterized in that the cross section is formed to have a locking jaw in the L-shape.
도 1은 본 발명의 강관말뚝 머리부 보강구조의 1실시 예의 분리 사시도.1 is an exploded perspective view of one embodiment of the steel pipe pile head reinforcement structure of the present invention.
도 2는 도 1의 결합 단면도.2 is a cross-sectional view of FIG.
도 3은 본 발명의 강관말뚝 머리부 보강구조의 2실시 예의 분리 사시도.Figure 3 is an exploded perspective view of two embodiments of the steel pipe pile head reinforcement structure of the present invention.
도 4는 도 3의 결합단면도.4 is a cross-sectional view of the combination of FIG.
도 5a, 5b는 도 3에 도시된 버팀링의 변형 예의 사시도.5A and 5B are perspective views of a modification of the bracing shown in FIG. 3.
도 6a, 6b는 본 발명의 강관말뚝 머리부 보강구조의 3실시 예의 결합 사시도.Figure 6a, 6b is a perspective view of the combination of three embodiments of the steel pipe pile head reinforcement structure of the present invention.
도 7은 본 발명의 강관말뚝 머리부 보강구조의 4실시 예의 결합 사시도.Figure 7 is a perspective view of the four embodiments of the steel pipe pile head reinforcement structure of the present invention.
도 8은 본 발명의 강관말뚝 머리부 보강구조의 5실시 예의 결합 사시도.8 is a perspective view of the five embodiments of the steel pipe pile head reinforcement structure of the present invention.
도 9a는 본 발명에서 외부 버팀링을 부설한 단면 일예도.Figure 9a is an exemplary cross-sectional view of laying the external support in the present invention.
도 9b는 본 발명의 버팀블록의 다른 예의 사시도.Figure 9b is a perspective view of another example of the brace block of the present invention.
<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for the main parts of the drawings>
10 : 강관말뚝 20 : 결합구10: steel pipe pile 20: coupling sphere
22 : 받침판 24, 40 : 로드22: support plate 24, 40: rod
26 : 체결링 28 : 지지링26: fastening ring 28: support ring
30 : 버팀블록 32 : 철근 고정용 클립30: Bracing block 32: Clip for fixing the rebar
34 : 버팀링 36 : 탄성링34: Bracing 36: Elastic Ring
100 : 보강철근100: rebar
이하에서 본 발명의 바람직한 실시 예를 첨부된 도면에 의거 상세히 설명하기로 한다.Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings.
도 1은 본 발명의 강관말뚝 머리부 보강구조의 1실시 예의 분리 사시도이고, 도 2는 도 1의 결합 단면도를 도시한 것이다.1 is an exploded perspective view of an embodiment of a steel pipe pile head reinforcement structure of the present invention, Figure 2 is a cross-sectional view of the combination of FIG.
도 1 및 도 2에 도시된 바와 같이 도면부호 10은 강관말뚝으로서, 토목 또는 건축구조물의 기초로서 항타하여, 그 상부를 절단기로 절단하여 강관말뚝(10)의 상단 수평을 유지되게 하고, 이 강관말뚝(10)의 둘레에는 복수의 제1체결구멍(12) 및 제2체결구멍(14)이 통상의 유압타공기를 통해 천공된다.1 and 2, the reference numeral 10 is a steel pipe pile, driven as a foundation of a civil engineering or building structure, the upper part is cut by a cutting machine to maintain the top level of the steel pipe pile 10, this steel pipe In the circumference of the pile 10, a plurality of first fastening holes 12 and second fastening holes 14 are drilled through a conventional hydraulic perforator.
도면부호 20은 상기 강관말뚝(10)의 상부인 머리부에 설치되는 결합구를 도시한 것이다.Reference numeral 20 shows a coupler installed in the head which is the upper portion of the steel pipe pile (10).
상기 결합구(20)는 받침판(22)과 로드(24) 및 일체로 된 체결링(26)과 지지링(28)으로 구성된다.The coupler 20 is composed of a support plate 22 and the rod 24 and the integral fastening ring 26 and the support ring 28.
상기 받침판(22)은 강관말뚝(10)의 상부로부터 삽입되어 강관말뚝(10)에 속채움되는 콘크리트를 받침하게 되며, 받침판(22)의 상부 중앙으로 링 형태의 연결링(22a)이 설치되어 이 연결링(22a)의 둘레에 일정 간격으로 천공된 구멍을 통해하단이 굽힘된 보강철근(100)이 연결 설치된다.The support plate 22 is inserted from the top of the steel pipe pile 10 to support the concrete filled in the steel pipe pile 10, the ring-shaped connection ring 22a is installed in the upper center of the support plate 22 The reinforcing bar 100, which is bent at the lower end, is connected to the connection ring 22a through holes drilled at regular intervals.
상기 받침판(22)에는 복수 개의 로드(24)가 일정 간격으로 수직되게 설치되며, 로드(24)의 하단이 받침판(22)에 용접 또는 너트 체결방식으로 설치된다.A plurality of rods 24 are vertically installed at predetermined intervals on the support plate 22, and a lower end of the rod 24 is installed on the support plate 22 by welding or nut fastening.
상기 로드(24)의 상부는 강관말뚝(10)의 상부에 형성된 제1체결구멍(12)을 통해 볼트(25) 체결되는 체결링(26)과 용접으로 연결되고, 이 체결링(26)에 강관말뚝(10)의 상단 둘레에 지지되는 지지링(28)이 일체로 설치되어 받침판(22)을 받침하게 되며, 상기 강관말뚝(10)의 내부 둘레에는 제2체결구멍(14)을 통해 볼트(29) 체결되어 강관말뚝(10)에 속채움된 콘크리트의 초기 인장력과 압축력에 대항하도록 복수의 버팀블록(30)이 설치된다.The upper part of the rod 24 is connected by welding to the fastening ring 26 fastened to the bolt 25 through the first fastening hole 12 formed in the upper portion of the steel pipe pile 10, the fastening ring 26 A support ring 28 supported around the upper end of the steel pipe pile 10 is integrally installed to support the support plate 22, and a bolt through the second fastening hole 14 is formed in the inner circumference of the steel pipe pile 10. (29) A plurality of support blocks 30 are installed to counteract the initial tensile and compressive forces of the concrete fastened to the steel pipe pile (10).
상기에서 결합구(20)를 구성하는 체결링(26)과 지지링(28)은 4등분으로 분할되어 구성되어 있다. 이에 따라 강관말뚝(10)의 치수공차에 유연하게 대응할 수 있고, 또한 조립틈새를 없애 목표하는 강도를 발휘할 수 있다.The fastening ring 26 and the support ring 28 constituting the coupler 20 is divided into four parts. Thereby, it can respond flexibly to the dimension tolerance of the steel pipe pile 10, and can exhibit a target intensity by eliminating an assembly gap.
즉, 항타된 강관말뚝(10) 상부 둘레가 변형되어 내경치수가 국부적 또는 전체적으로 작아질 수 있다. 상기 체결링(26)과 지지링(28)이 폐쇄된 단일 링 형태 아닌 분할되고 그 사이에 조립틈새가 확보되어 있기 때문에 강관말뚝(10)의 치수변형에 유연하게 대응할 수 있으며, 상기 분할된 체결링(26)이 볼트로 강관말뚝(10)에 체결될 때 체결링(26)이 개별적으로 체결되므로 조임시 틈새를 없애 목표하는 강도를 얻을 수 있게 되는 것이다.That is, the inner circumference of the driven steel pipe pile 10 may be deformed so that the inner diameter may be locally or entirely reduced. Since the fastening ring 26 and the support ring 28 are not divided into a closed single ring shape and an assembly gap is secured therebetween, the fastening ring 26 and the support ring 28 can flexibly respond to the dimensional deformation of the steel pipe pile 10, and the divided fastening. When the ring 26 is fastened to the steel pipe pile 10 by bolts, the fastening ring 26 is individually fastened so that the target strength can be obtained by eliminating gaps when tightening.
도면중 미설명부호 32는 철근 고정용 클립으로, 강관말뚝(10)의 상부 지지링 (28)을 통해 설치되어 연결링(22a)을 통해 설치된 보강철근(100)이 수직된 자세를유지시키기 위해 보조적으로 사용되는 것이다.In the drawing, reference numeral 32 is a clip for fixing the reinforcing bar, which is installed through the upper support ring 28 of the steel pipe pile 10 to maintain the vertical posture of the reinforcing bar 100 installed through the connection ring 22a. It is used as an auxiliary.
한편 상기에서 버팀블록(30)은 세레이션이 형성된 세레이션볼트(도시생략)를 통해 강관말뚝(10)에 형성된 제2체결구멍(14)을 통해 억지끼움 됨으로서 강관말뚝 (10)에 속채움된 콘크리트의 초기 인장력과 압축력에 더 크게 대항할 수 있게 된다.Meanwhile, the support block 30 is filled into the steel pipe pile 10 by being forced through the second fastening hole 14 formed in the steel pipe pile 10 through the serration bolt (not shown) in which the serration is formed. Greater resistance to the initial tensile and compressive forces of concrete.
상기와 같이 구성된 본 발명의 실시 예에 따르면, 강관말뚝(10)의 상부에 결합구(20) 버팀링(30) 및 보강철근(100)의 설치작업을 완료한 다음 강관말뚝(10)의 내부로 콘크리트를 속채움으로 충진하여 작업을 완료한다.According to the embodiment of the present invention configured as described above, after completing the installation work of the coupling hole 20, the brace 30 and the reinforcing bar 100 on the upper portion of the steel pipe pile (10) the inside of the steel pipe pile (10) The work is completed by filling the concrete with filling.
도 3은 본 발명의 강관말뚝 머리부 보강구조의 2실시 예의 분리 사시도이고, 도 4는 도 3의 결합단면도를 도시한 것이다.Figure 3 is an exploded perspective view of a second embodiment of the steel pipe pile head reinforcement structure of the present invention, Figure 4 shows a cross-sectional view of the coupling of FIG.
도시된 바와 같이 강관말뚝(10)의 상부로부터 삽입 설치되어 속채움되는 콘크리트를 받침하고 동시에 그 상부에 설치된 연결링(22a)을 통해 보강철근(100)의 하단과 연결되어 지지하는 받침판(22)과, 이 받침판(22)에 수직으로 설치되고 그 상부가 절곡되어 강관말뚝(10)의 상부 주연에 걸어져 상기 받침판(22)을 지지하는 로드(40)로 이루어진 결합구(20a)와, 상기 강관말뚝(10)의 내부 둘레에 분할된 복수 형태로 하여 단계적으로 볼트 체결 설치되어 강관말뚝(10)에 속채움된 콘크리트의 초기 인장력과 압축력에 대항하도록 하는 버팀링(34)과 버팀블록(30)으로 구성된 것이다.As shown, the support plate 22 is inserted from the top of the steel pipe pile 10 to support the concrete filling and at the same time connected to and supported by the lower end of the reinforcing bar 100 through the connection ring 22a installed on the upper support plate 22. And, the coupling sphere 20a made of a rod 40 which is installed perpendicular to the support plate 22 and the upper portion is bent to the upper periphery of the steel pipe pile 10 to support the support plate 22, and the Reinforcing bolting step by step in the form of a plurality of partitions around the inner periphery of the steel pipe pile 10 to support the initial tensile and compressive force of the concrete filled in the steel pipe pile (10) and the support block (34) and the support block (30) ).
상기에서 로드(40)의 하단은 받침판(22)에 너트로 체결 설치할 수 있고 용접으로 설치할 수 있다.In the above, the lower end of the rod 40 can be fastened and installed with a nut on the support plate 22 and can be installed by welding.
그리고 상기 버팀링(34)이 2등분으로 분할 구성되어 강관말뚝(10)의 치수공차에 유연하게 대응할 수 있고, 또한 조립틈새를 없애 목표하는 강도를 발휘할 수 있다.In addition, the support ring 34 is divided into two parts to flexibly cope with the dimensional tolerances of the steel pipe pile 10, and can also achieve the target strength by eliminating the assembly gap.
즉, 항타된 강관말뚝(10) 상부 둘레가 변형되어 축소된 경우 상기 버팀링 (34)이 폐쇄된 링 형태 아닌 분할되고 그 사이에 조립틈새가 확보되어 있기 때문에 강관말뚝(10)의 치수변형에 유연하게 대응할 수 있으며, 상기 분할된 버팀링(34)이 볼트로 강관말뚝(10)에 체결될 때 버팀링(34)이 개별적으로 체결되어 조임시 틈새를 없애 목표하는 강도를 얻을 수 있게 되는 것이다.That is, when the upper circumference of the driven steel pipe pile 10 is deformed and reduced, the support ring 34 is divided into a closed ring shape, and the assembly gap is secured therebetween, so that the dimensional deformation of the steel pipe pile 10 is reduced. It can be flexibly responded, and when the divided buttress ring 34 is fastened to the steel pipe pile 10 by bolts, the buttress ring 34 is individually fastened to obtain a target strength by eliminating gaps when tightening. .
한편 상기에서 버팀링(34)과 버팀블록(30)은 세레이션이 형성된 세레이션볼트(도시생략)를 통해 강관말뚝(10)에 형성된 제1체결구멍(12)과 제2체결구멍(14)을 통해 억지끼움 됨으로서 강관말뚝(10)에 속채움된 콘크리트의 초기 인장력과 압축력에 더 크게 대항할 수 있게 된다.Meanwhile, the support ring 34 and the support block 30 have the first fastening hole 12 and the second fastening hole 14 formed in the steel pipe pile 10 through serration bolts (not shown) having serrations formed therein. By being pushed through the steel pipe pile 10 can be more largely opposed to the initial tensile and compressive forces of the concrete stuffed.
또한 도 5a, 5b는 본 발명의 버팀링(34)의 변형 예를 도시한 것으로, 도 5a로 도시된 버팀링(34)은 링에 엠보싱(34a)을 주어 링의 강도를 보강한 것이며, 도 5b로 도시된 버팀링(34)은 링의 중간에 로드(40)가 지지되도록 걸림턱(34b)을 복수로 형성한 것이다.5a and 5b show a modified example of the brace ring 34 of the present invention. The brace ring 34 shown in FIG. 5a is provided by embossing 34a on the ring to reinforce the strength of the ring. The bracing ring 34 shown in 5b is formed with a plurality of locking jaws 34b so that the rod 40 is supported in the middle of the ring.
도 6a, 6b는 본 발명의 강관말뚝 머리부 보강구조의 3실시 예의 결합 사시도를 도시한 것이다.Figure 6a, 6b shows a perspective view of the combination of three embodiments of the steel pipe pile head reinforcement structure of the present invention.
도시된 바와 같이 강관말뚝(10)의 상부로부터 삽입 설치되어 속채움되는 콘크리트를 받침하는 받침판(22)과, 이 받침판(22)에 수직으로 설치되고 그 상부가절곡되어 강관말뚝(10)의 상부 주연에 걸어져 상기 받침판(22)을 지지하는 로드 (40)로 이루어진 결합구(20b)와, 상기 강관말뚝(10)의 둘레에 복수 형성된 구멍을 통해 하단이 절곡되어 직접 설치되는 보강철근(100)과, 상기 강관말뚝(10)의 내부 둘레에 분할된 복수 형태로 하여 단계적으로 볼트 체결 설치되어 강관말뚝(10)에 속채움된 콘크리트의 초기 인장력과 압축력에 대항하도록 하는 버팀링(34)과 버팀블록(30)으로 구성된 것이다.As shown, the support plate 22 is inserted from the upper portion of the steel pipe pile 10 to support the filled concrete, and is installed perpendicular to the support plate 22 and the upper portion is bent to the upper portion of the steel pipe pile 10 Reinforcing bars (100b) formed of a rod (40) supporting the support plate (22) supported by the circumference and a plurality of holes formed in the periphery of the steel pipe pile (10), the lower end of which is directly installed by reinforcement (100) ), And the brace ring (34) to be installed in a plurality of forms divided into the inner circumference of the steel pipe pile (10) against the initial tensile and compressive force of the concrete filled in the steel pipe pile (10) and It is composed of a bracing block (30).
상기의 3실시 예에서 앞서 설명된 2실시 예와 다른 점은 보강철근(100)을 강관말뚝(10)에 구멍을 천공하여 도 6a와 같이 강관말뚝(10)의 외부측 또는 도 6b와 같이 내부측에서 직접 설치한 것이 다르며, 이와 같은 실시 예는 결합구(20b)의 구성을 간단히 하고 또한 보강철근(100)의 조립을 간단히 할 수 있다.In the third embodiment, the difference from the second embodiment described above is that the reinforcing bar 100 is drilled in the steel pipe pile 10 so as to form an inner side of the steel pipe pile 10 as shown in FIG. 6A or 6B. The direct installation is different from the side, such an embodiment can simplify the configuration of the coupler (20b) and simplify the assembly of the reinforcing bars (100).
도 7은 본 발명의 강관말뚝 머리부 보강구조의 4실시 예의 결합 사시도를 도시한 것이다.Figure 7 shows a perspective view of the combination of four embodiments of the steel pipe pile head reinforcement structure of the present invention.
도시된 바와 같이 강관말뚝(10)의 상부로부터 삽입 설치되어 속채움되는 콘크리트를 받침하고 동시에 그 상부에 설치된 연결링(22a)을 통해 보강철근(100)의 하단과 연결되어 지지하는 받침판(22) 및 이 받침판(22)이 강관말뚝(10) 내에 고정되도록 받침판(22)의 하부에 설치되는 탄성링(36)과, 상기 강관말뚝(10)의 내부 둘레에 분할된 복수 형태로 하여 단계적으로 볼트 체결 설치되어 강관말뚝(10)에 속채움된 콘크리트의 초기 인장력과 압축력에 대항하도록 하는 버팀링(34)과 버팀블록(30)으로 구성된 것이다.As shown, the support plate 22 is inserted from the top of the steel pipe pile 10 to support the concrete filling and at the same time connected to and supported by the lower end of the reinforcing bar 100 through the connection ring 22a installed on the upper support plate 22. And a plurality of forms of elastic rings 36 installed at a lower portion of the support plate 22 so that the support plate 22 is fixed in the steel pipe pile 10, and divided into a plurality of forms around the inside of the steel pipe pile 10. The fastening is installed consists of a support block 34 and the support block 30 so as to counteract the initial tensile and compressive force of the concrete filled in the steel pipe pile (10).
상기 4실시 예의 다른 점은 받침판(22)을 강관말뚝(10) 내에서 빠지지 않고고정상태를 유지시키기 위해서 탄성링(36)을 설치한 것이다. 이에 따라 받침판(22)을 지지하는 로드가 생략되어 전체 구성을 간단히 할 수 있고, 또한 탄성링(36) 단부의 절단으로 여유틈새를 갖고 있게 되어 탄성링(36)이 탄성을 발휘하면서 받침판 (22)을 받쳐주게 되는 것이다.Another difference of the above four embodiments is that the support plate 22 is provided with an elastic ring 36 to maintain a fixed state without falling out of the steel pipe pile (10). As a result, the rod supporting the support plate 22 is omitted, thereby simplifying the overall configuration, and having a clearance therebetween by cutting the end of the elastic ring 36, thereby supporting the support plate 22 while the elastic ring 36 exhibits elasticity. ) Will be supported.
도 8은 본 발명의 강관말뚝 머리부 보강구조의 5실시 예의 결합 사시도를 도시한 것이다.Figure 8 shows a perspective view of the combination of five embodiments of the steel pipe pile head reinforcement structure of the present invention.
도시된 바와 같이 강관말뚝(10)의 상부로부터 삽입 설치되어 속채움되는 콘크리트를 받침하는 받침판(22) 및 이 받침판(22)이 강관말뚝(10) 내에 고정되도록 받침판(22)의 하부에 설치되는 탄성링(36)과, 상기 강관말뚝(10)에 내부 또는 외부 둘레에 그 하단이 절곡되어 직접 설치되는 보강철근(100)과, 상기 강관말뚝(10)의 내부 둘레에 분할된 복수 형태로 하여 단계적으로 볼트 체결 설치되어 강관말뚝에 속채움된 콘크리트의 초기 인장력과 압축력에 대항하도록 하는 버팀링(34)과 버팀블록(30)으로 구성된 것으로, 상기 받침판(22)을 철판 대신 합판으로 대용함으로서 비용을 절감할 수 있다.As shown, the support plate 22 is inserted from the top of the steel pipe pile 10 to support the filled concrete and the support plate 22 is installed in the lower portion of the support plate 22 to be fixed in the steel pipe pile (10) The elastic ring 36, the reinforcement reinforcement 100 is bent directly installed on the inner or outer circumference of the steel pipe pile 10, and a plurality of forms divided into the inner circumference of the steel pipe pile 10 It is composed of the brace ring 34 and the brace block 30 to counteract the initial tensile and compressive force of the concrete filled in the steel pipe pile by installing the bolt fastening step by step, the support plate 22 is replaced by plywood instead of steel plate Can reduce the cost.
상기에서 버팀링(34)은 바람직하게 2개로 분할 구성되어 그 결합공차를 수용하는 것이 바람직할 것이다.The bracing 34 is preferably divided into two to accommodate the coupling tolerances.
한편 상기 실시예들 중에서 버팀링(34)을 갖는 모든 실시예에서 이 버팀링의 대응위치 강관 외경에 삽입되는 내경을 가지는 외부 버팀링(34)을 더 추가해서 구성될 수도 있다. 이는 강관 두부 상부에 버팀콘크리트를 칠때 걸림응력을 갖는 작용은 물론 버팀링(34)과 더불어서 강관에 보다 더 강한 체결력을 가질 수 있을 것이다.On the other hand, in all of the embodiments having the buttressing 34 in the above embodiments may be configured by further adding an external buttressing 34 having an inner diameter that is inserted into the outer diameter of the corresponding position steel pipe of the buttressing. This may have a stronger clamping force on the steel pipe with the support ring 34, as well as the action of the locking stress when hitting the bracing concrete on the top of the steel pipe head.
한편, 버팀블록 역시 그 단면이 "L"자형으로써 걸림턱(30A)을 가지게 형성함으로써 강관의 두부 내부에 채워지는 콘크리트와 강관 두부의 결합력을 보다 양호하게 할 수 있을 것이다.On the other hand, the bracing block also has a locking jaw (30A) in the cross-section of the "L" shaped to be able to make the coupling force of the concrete and the steel pipe head filled inside the head of the steel pipe better.
이상에서 설명한 바와 같이 본 발명의 강관말뚝 머리부 보강구조에 있어 결합구의 다양한 실시 예에 의하여 결합구를 간단히 하여 비용을 절감하고, 강관말뚝의 치수변형에 따른 체결링 또는 버팀링의 분할에 의한 조립을 원활히 하면서 동시에 체결시 조립틈새를 없애 목표하는 강도를 발휘할 수 있는 효과를 갖고, 속채움된 콘크리트의 강도를 향상시킬 수 있는 효과와 함께 현장 용접을 없애 조립공정을 간단히 하여 시공성 및 경제성을 갖는 효과를 갖는다.As described above, in the steel pipe pile head reinforcing structure according to the present invention, various embodiments of the coupler simplify the coupler, thereby reducing the cost, and assembling by dividing the fastening ring or the brace according to the dimensional deformation of the steel pipe pile. It has the effect of smoothing out the assembly gap during fastening and at the same time, exerting the target strength, and improving the strength of the filled concrete, and simplifying the assembly process by eliminating on-site welding. Has
Claims (8)
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020010047064 | 2001-08-03 | ||
KR20010047064 | 2001-08-03 |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20030012779A KR20030012779A (en) | 2003-02-12 |
KR100437261B1 true KR100437261B1 (en) | 2004-06-23 |
Family
ID=27717955
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR10-2001-0072460A KR100437261B1 (en) | 2001-08-03 | 2001-11-20 | steel pipe pile head reinforcement structure |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR100437261B1 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100625948B1 (en) | 2005-10-31 | 2006-09-18 | 주식회사 파일텍씨앤이 | Reinforcement device for foundation of steel pipe pile |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100458323B1 (en) * | 2002-01-30 | 2004-12-03 | (주)서영기술단 | The upper part reinforcement structure of a steel pipe for base construction |
KR20040095391A (en) * | 2003-04-28 | 2004-11-15 | (주)피에스테크 | reinforced structure and method combining the head of concrete pile with concrete foundation |
KR100755164B1 (en) * | 2005-12-13 | 2007-09-04 | 주식회사 동국철강 | A steel pipe file head augmentation device which uses integral socket |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR200201561Y1 (en) * | 2000-06-03 | 2000-11-01 | 이달훈 | Head reinforcement structure of steel pipe pile |
KR20000064205A (en) * | 2000-08-29 | 2000-11-06 | 배정효 | Reinforcement structure for a foundation pile |
KR20010066973A (en) * | 2000-08-02 | 2001-07-12 | 김성환 | Head reinforced apparatus for steel pipe piles |
KR200232594Y1 (en) * | 2001-02-20 | 2001-10-06 | (주)한석엔지니어링건축사사무소 | Supporting Structure for Concreting in Head of a Steel-Pile |
KR20020044618A (en) * | 2000-12-06 | 2002-06-19 | 김성환 | Head rein forced apparatus for steel pipe piles |
KR20020089026A (en) * | 2001-05-22 | 2002-11-29 | 한국도로공사 | steel pipe pile connecting head reinforce ment structure |
-
2001
- 2001-11-20 KR KR10-2001-0072460A patent/KR100437261B1/en active IP Right Grant
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR200201561Y1 (en) * | 2000-06-03 | 2000-11-01 | 이달훈 | Head reinforcement structure of steel pipe pile |
KR20010066973A (en) * | 2000-08-02 | 2001-07-12 | 김성환 | Head reinforced apparatus for steel pipe piles |
KR20000064205A (en) * | 2000-08-29 | 2000-11-06 | 배정효 | Reinforcement structure for a foundation pile |
KR20020044618A (en) * | 2000-12-06 | 2002-06-19 | 김성환 | Head rein forced apparatus for steel pipe piles |
KR200232594Y1 (en) * | 2001-02-20 | 2001-10-06 | (주)한석엔지니어링건축사사무소 | Supporting Structure for Concreting in Head of a Steel-Pile |
KR20020089026A (en) * | 2001-05-22 | 2002-11-29 | 한국도로공사 | steel pipe pile connecting head reinforce ment structure |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100625948B1 (en) | 2005-10-31 | 2006-09-18 | 주식회사 파일텍씨앤이 | Reinforcement device for foundation of steel pipe pile |
Also Published As
Publication number | Publication date |
---|---|
KR20030012779A (en) | 2003-02-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100675985B1 (en) | A bracing for reinforcing support | |
KR102274029B1 (en) | Method for reinforcing the Earthquake of a concrete columns | |
KR101674823B1 (en) | Beam section enlargement method using socket shaped anchor | |
KR20040044810A (en) | joint structure of precast bridge slab and girder and bridge construction method using the same | |
KR20200004056A (en) | Device for reinforcing the Earthquake of a concrete columns and Methods | |
KR100437261B1 (en) | steel pipe pile head reinforcement structure | |
KR100461914B1 (en) | Device fixing bar and structure for connecting head of steel pile and concrete footing of the same | |
KR101257667B1 (en) | Retrofit of buildings structure and method of retrofitting | |
KR200207380Y1 (en) | A column's reinforcing rod for a round pier | |
KR200386881Y1 (en) | A pile head reinforcement structure of precast concrete pile | |
JPH0827784A (en) | Reinforcement arranging spacer and foundation pile construction method | |
KR100437260B1 (en) | steel pipe pile connecting head reinforce ment structure | |
KR100534079B1 (en) | Construction method of strut | |
KR100626326B1 (en) | concrete structure | |
KR960001730B1 (en) | Assembling pier, the pier structure, and its working method | |
CN110258790B (en) | Vertical dry type connecting node with shear key groove for prefabricated frame column and construction method | |
CN112878508A (en) | Repairable assembly type reinforced concrete column-steel beam column joint and construction method thereof | |
KR200490975Y1 (en) | H-beam safety-connecting device | |
KR200392061Y1 (en) | coupling structure of steel reinforcement | |
CN219825647U (en) | Shock-resistant steel beam and concrete column rigid joint point | |
KR102336377B1 (en) | Reusable Variable Concrete Form Assembly for Column Structure | |
KR100465287B1 (en) | A rein forcement unit for a head of H-beam used as a pile | |
KR200362827Y1 (en) | concrete structure | |
CN215053882U (en) | Hoop type beam column node for converting tensile force into shear force | |
CN115045527B (en) | Building concrete column reinforcing node and reinforcing method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
N231 | Notification of change of applicant | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20130531 Year of fee payment: 10 |
|
FPAY | Annual fee payment |
Payment date: 20140523 Year of fee payment: 11 |
|
FPAY | Annual fee payment |
Payment date: 20150528 Year of fee payment: 12 |
|
FPAY | Annual fee payment |
Payment date: 20160526 Year of fee payment: 13 |
|
FPAY | Annual fee payment |
Payment date: 20170601 Year of fee payment: 14 |
|
FPAY | Annual fee payment |
Payment date: 20190603 Year of fee payment: 16 |