KR20020042316A - Constructing method for the filling out abutement of bridge and its structure - Google Patents

Constructing method for the filling out abutement of bridge and its structure Download PDF

Info

Publication number
KR20020042316A
KR20020042316A KR1020000072140A KR20000072140A KR20020042316A KR 20020042316 A KR20020042316 A KR 20020042316A KR 1020000072140 A KR1020000072140 A KR 1020000072140A KR 20000072140 A KR20000072140 A KR 20000072140A KR 20020042316 A KR20020042316 A KR 20020042316A
Authority
KR
South Korea
Prior art keywords
drainage
bridge
alternating
constructing
concrete
Prior art date
Application number
KR1020000072140A
Other languages
Korean (ko)
Other versions
KR100433653B1 (en
Inventor
김동환
Original Assignee
김동환
주식회사 대한건설엔지니어링
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김동환, 주식회사 대한건설엔지니어링 filed Critical 김동환
Priority to KR10-2000-0072140A priority Critical patent/KR100433653B1/en
Publication of KR20020042316A publication Critical patent/KR20020042316A/en
Application granted granted Critical
Publication of KR100433653B1 publication Critical patent/KR100433653B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)

Abstract

PURPOSE: A process for producing abutment back-filing drainage of bridge and a structure for the same are provided by minimizing earth pressure-resistance by water inflow generated behind of the abutment to extend public time of the bridge and to easily manage the bridge. CONSTITUTION: The process comprises steps of: building riverbank portions at both sides of the bridge; striking and inserting a steel H pile(50) into a support layer by a base pile to support the abutment(100); forming a cast for the drainage at the riverbank side and introducing a concrete to produce a base portion(10) provided with the abutment drainage(20); introducing the concrete to complete the abutment; forming stepwise filled portion on the base side to form a 'U' shaped precast water route drainage(30); and forming a hollowed pipe(40) at a position with reduced earth pressure-resistance on step portions of the drainage.

Description

교량의 교대 뒷채움 배수로 시공방법 및 그 구조 {Constructing method for the filling out abutement of bridge and its structure}Constructing method for the filling out abutement of bridge and its structure}

본 발명은 일반적인 교량에 적용할 수 있는 교량의 배수로 시공방법 및 그구조에 관한 것으로, 교대 배면에 발생하는 유입수에 의한 토압 저항력을 최소화하여 교량의 공용수명을 연장하고 유지관리가 쉬운 교량의 교대 뒷채움 배수로 시공방법 및 그 구조에 관한 것이다.The present invention relates to a bridge drainage construction method and its structure that can be applied to a general bridge, and to minimize the earth pressure resistance caused by the inflow water generated on the back of the bridge to extend the common life of the bridge and easy backfill of the bridge easy to maintain It relates to a drainage construction method and its structure.

종래의 일반교량은 교대에 다열 지지말뚝을 설치한 후 말뚝 위로 벽체 교대를 완성한다. 이때 교각이 존재하는 경우에는 교각 상부에 베어링을 설치한 후 주형을 거치 하도록 시공하였다.Conventional general bridges complete the wall shift over the pile after installing the multi-row support piles on the shift. At this time, if a pier exists, the bearing was installed on the upper part of the pier, and the construction was performed to mount the mold.

교량은 사하중, 활하중, 교대에 발생하는 흙의 자중 및 토압에 저항하도록 설계가 되므로 교대 구체의 크기가 매우 클 뿐만 아니라 교대 구체가 부동(不動)의 구조물이므로 변위 발생을 허용치 않으며 또한 이러한 상부하중 및 자중을 교대가 지지하기 위하여 다열의 지지말뚝을 사용하게 된다.Since the bridge is designed to resist dead load, live load, earth load and earth pressure in the shift, the alternating sphere is very large and the alternating sphere is a floating structure that does not allow displacement. The alternating support piles are used to support their own weight.

그러한 교대는 도로와 인접되므로 흙의 자중 및 토압을 고려하여 시공함과 동시에 유입되는 유실수로 인하여 발생되는 토압으로 구조의 변위를 일으킬 수 있는 문제점이 있다.Since such shifts are adjacent to the road, there is a problem that may cause a displacement of the structure due to the earth pressure generated due to the loss of the incoming water at the same time the construction in consideration of the weight and soil pressure of the soil.

또한, 종래 교대 뒷채움시 배수로를 형성하여 사용하고 있으나, 배수로 역할을 수행하기보다는 단지 형식에 가까운 상태로 배수로의 역할에 가까운 문제점이 있었다.In addition, the conventional shift backfill is used to form a drainage, but there is a problem close to the role of the drainage in a state close to the form rather than to serve as a drainage.

따라서, 본 발명은 종래의 문제점을 감안하여 안출한 것으로 본 발명의 목적은 교대 배면에 발생하는 유입수에 의한 토압 저항력을 최소화하여 교량의 공용수명을 연장하고 유지관리가 쉬운 교량의 교대 뒷채움 배수로 시공방법 및 구조를 제공하는 데 그 목적이 있다.Accordingly, the present invention has been made in view of the conventional problems, and an object of the present invention is to minimize the earth pressure resistance caused by the inflow water generated on the alternating back surface to extend the common life of the bridge and easy to maintain the alternating backfill drainage construction method of the bridge And to provide a structure.

본 발명의 다른 목적은 교대에 작용하는 유실수에 의한 토압을 최소화하기 위한 구조를 제공하는 데 있다.Another object of the present invention is to provide a structure for minimizing earth pressure caused by lost water acting on the alternating.

이러한 목적을 달성하기 위한 본 발명은 중, 소형, 대형 교량의 교대부에서 유입수에 의한 토압변화에 따른 구조물의 피해를 최소화하여 교량 수명을 연장할 수 있는 교대의 배수로를 시공하여 달성하였다.The present invention for achieving the above object was achieved by constructing the alternate drainage path to extend the bridge life by minimizing the damage of the structure due to the change in earth pressure by the inflow water in the alternating portion of the small, large bridge.

또한, 본 발명은 교량 양측 교대 제방부의 성토 공정을 시공단계; 교대를 지지하기 위하여 사용되는 기초 말뚝으로 강재 H 말뚝을 지지층까지 항타 관입하는 시공단계와; 상기 강재 H 말뚝에 기초부 콘크리트를 타설시 제방측에 배수로 형성하도록 거푸집을 형성하여 콘크리트를 타설하여 배수로가 형성된 교대 기초부를 시공단계와; 교대를 콘크리트로 타설하여 교대를 완성하는 단계와; 기초면을 계단형 다짐부를 형성하여 토압저항을 큰 저면에 공극률이 큰 뒷채움재료의 사용과 더불어 뒷채움 저면에 장착되는 "∪"형 프리캐스트 도수로 배수관 시공단계와; 그 상단의 계단부에 토압저항이 작은 위치에 유공관을 시공하는 단계로 배수로를 시공하여 신속한 배수와 많은 량의 유입수를 배출할 수 있도록 이루어진 교량의 교대 배수를 달성하였다,In addition, the present invention the construction step of the filling process of both sides of the bridge embankment; A construction step of driving the steel H pile into the support layer as a foundation pile used to support the shift; A step of constructing an alternating foundation portion in which a drainage path is formed by pouring concrete by forming a formwork to form drainage on the embankment side when the foundation concrete is poured into the steel H pile; Placing shifts in concrete to complete the shifts; A step of constructing a "∪" -type precast raceway drain pipe mounted on the bottom of the back fill with the use of a back fill material having a large porosity on the bottom to form a stepped compaction on the base surface; The construction of drainage pipes was carried out in the step of constructing the perforated pipe at the position of small earth pressure resistance in the upper part of the stairs to achieve the rapid drainage and the alternating drainage of the bridge that can discharge a large amount of influent.

도 1은 본 발명의 바람직한 실시예의 교량의 교대 뒷채움 배수로 시공방법 에 의한 그 구조를 도시한 단면도,1 is a cross-sectional view showing the structure by the alternating backfill drainage construction method of the bridge of a preferred embodiment of the present invention,

도 2는 본 발명의 바람직한 실시예의 교량의 교대 뒷채움 배수로 시공방법 에 의한 그 구조를 도시한 절취 사시도이다.Figure 2 is a perspective view showing the structure of the alternating backfill drainage construction method of the bridge of the preferred embodiment of the present invention.

* 도면의 주요부분에 대한 부호의 설명 *Explanation of symbols on the main parts of the drawings

10 : 교대 기초부20 : 교대 배수로10: shift foundation 20: shift drain

30 : "U"형 콘크리트 구조물의 배수로40 : 유공관30: drainage path of "U" type concrete structure 40: perforated pipe

50 : 말뚝60 : 뒷채움부50: pile 60: backfill

70 : 빔100 : 교대70: beam 100: shift

이하, 첨부된 도면들을 참조하여 본 발명의 바람직한 실시 예을 상세히 설명한다.Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 1 내지 도 2에 도시된 바와 같이, 본 발명의 교량의 배수로 시공방법은 교량 양측 교대 제방부의 성토 공정을 시공단계; 교대를 지지하기 위하여 사용되는 기초 말뚝으로 강재 H 말뚝(50)을 지지층까지 항타 관입하는 시공단계와; 상기 강재 H 말뚝에 교대기초부(10) 콘크리트를 타설시 제방측에 배수로 형성하도록 거푸집을 형성하여 콘크리트를 타설하여 교대배수로(20)가 형성된 기초부를 시공단계와; 교대를 콘크리트로 타설하여 교대를 완성하는 단계와; 기초면을 계단형 다짐부를 형성하여 토압저항을 큰 저면에 공극률이 큰 뒷채움재료의 사용과 더불어 뒷채움 저면에 장착되는 "∪"형 프리캐스트 도수로 배수관(30) 시공단계와; 그 상단의 계단부에 토압저항이 작은 위치에 유공관(40)을 시공하는 단계로 배수로를 시공하여 완성하였다.As shown in Figures 1 to 2, the drainage construction method of the bridge of the present invention is a construction step of the fill process of the bridge embankment on both sides of the bridge; A construction step of driving the steel H pile 50 into the support layer as a foundation pile used to support the shift; A step of constructing a foundation on which the alternating drainage part 20 is formed by forming a formwork so as to form a drainage on the embankment side when the alternating foundation part 10 concrete is poured into the steel H pile; Placing shifts in concrete to complete the shifts; A step of constructing a "∪" -type precast raceway drain pipe 30 mounted on the bottom of the back filling together with the use of a back filling material having a large porosity on the bottom to form a stepped compaction on the base surface; The drainage passage was completed in the step of constructing the perforated pipe 40 at a position where the earth pressure resistance was small in the step portion of the upper end.

먼저, 상기 교대 제방부 시공단계는 계획고까지 성토된 지반의 안정 및 잔류 침하에 대한 확인을 위하여 소정의 대기기간을 갖도록 한다. 성토부의 이상 유무가 확인된 후, H형 말뚝을 지지층까지 항타 관입하고 말뚝은 변위에 필요한 유연성을 확보하기 위하여 일반적으로 일렬로 시공하며 힘이 받는 방향에 대하여 약축으로 시공한다.First, the alternating embankment construction step has a predetermined waiting period for checking the stability and residual settlement of the ground formed up to the planned height. After confirming the abnormality of the fill part, the H-type pile is driven through to the support layer and the pile is generally installed in a line in order to secure the flexibility required for displacement.

상기 교대 기초부(20)를 시공시 충분한 설계 허용지지력을 확보할 수 있을 때까지 말뚝을 항타한 후, 말뚝(50)의 머리부를 매입하여 하부 교대 기초부(10)를 콘크리트를 타설시 기초부 상단에 배수로(20)를 형성하도록 거푸집을 형성하여 "U"형 배수로를 형성하여 교대상부에서 유입되는 유입수를 배출하도록 하여 토압을 줄여 교대의 변위를 최소화하였다.When the alternating foundation 20 is installed, the pile is driven until a sufficient design allowable bearing force can be secured, and then the head of the pile 50 is embedded to install the lower alternating foundation 10 in the concrete foundation. Forming a form to form a drainage channel 20 on the top to form a "U" type drainage to discharge the inflow water flowing from the bridge to minimize the displacement of the shift by reducing the earth pressure.

다음, 교대(100) 벽체의 시공이 완료된 후에는 뒷채움 작업 실시전 양쪽 교대 벽체 후면에 계단구조의 배수로 설치하며, 저면부에는 교대 뒷채움의 저면에는 "U"형 콘크리트 구조물의 배수로(20)를 형성하고, 상기 그 상단 계단부에 설치한 유공관(40)을 내설한 계단식 구조를 형성하였다.Next, after the completion of the construction of the shift 100 wall is installed as a drainage of the staircase structure on the rear of both shift walls before the back filling operation, and the bottom portion of the shift back fill to form a drainage 20 of the "U" -type concrete structure And the stepped structure which built the perforated pipe 40 installed in the said upper step part was formed.

상기 교대 뒷채움부(60)에 우수가 침투하게 되며 저면 콘크리트 구조물 배수로에 침투된 우수가 뒷채움부에 누적됨이 없이 교량 밖으로 신속히 배수하여 수압에 의한 토압 영향을 최소화하도록 하였다.Rainfall penetrates the backfill portion 60 and alternately, the rainwater penetrating into the bottom concrete structure drainage drains out of the bridge quickly without accumulating in the backfill portion, thereby minimizing the effect of earth pressure due to water pressure.

한편, 상기 유공관(40)은 토압의 압력이 작은 곳에서 설치되어 도로측에 가깝게 유공관을 설치한 후에는 뒷채움을 시공한다.On the other hand, the perforated pipe 40 is installed in a place where the pressure of the earth pressure is small, after installing the perforated pipe close to the side of the road to construct the backfill.

상기 뒷채움 재료로 입자가 크고 점착력이 작고 내부 마찰각이 큰 재료를 사용하여 배수가 잘 이루어지도록 하였다.As the backfill material, a material having a large particle, a small adhesive force, and a large internal friction angle was used to drain well.

예컨대, 본 발명은 상술한 실시예에 한정되지 아니하며, 특허청구범위에서 청구한 본 발명의 요지를 벗어남이 없이 본 발명이 속하는 기술분야에 통상의 지식을 가진 자라면 다양한 변형 실시가 가능한 것임은 물론이고, 그와 같은 변경은 본 발명의 청구범위내에 있게 된다.For example, the present invention is not limited to the above-described embodiment, and various modifications can be made by those skilled in the art without departing from the gist of the present invention as claimed in the claims. Such changes are intended to be within the scope of the present invention.

본 발명은 상기 실시 예를 통하여 설명한 바와 같이, 중, 소형 및 대형 교량에 대하여 교대부 뒷채움부에 유입되는 유입수로 인하여 발생되는 교대의 변위를최소화시키고 유입량이 많은 지층에서 더욱 필요한 구조로 배수로를 교대의 기초부에 형성한 구조는 교대를 상부 유입수를 빠르게 배출하여 토압을 죄소화한 효과가 있다. 또한,뒷채움부를 계단형 구조로 형성하여 배수로 구조물과 유공관을 토압력에 적응되느 공법을 사용하여 교대를 포함한 교량의 수명을 연장하는 효과가 있으므로 교량건설산업상 매우 유용한 발명인 것이다.As described through the above embodiment, the present invention minimizes the displacement caused by the inflow water flowing into the backfill portion of the medium, small and large bridges, and alternates the drainage passages with a more necessary structure in the inflow layer. The structure formed at the base of the shift has the effect of reducing the earth pressure by quickly discharging the upper influent. In addition, it is a very useful invention in the bridge construction industry because it has the effect of extending the life of the bridge including the shift by using a method of adapting the drainage structure and the perforated pipe to the earth pressure by forming the backfill part in a stepped structure.

Claims (3)

교량 양측 교대 제방부의 성토 공정을 시공단계; 교대를 지지하기 위하여 사용되는 기초 말뚝으로 강재 H 말뚝을 지지층까지 항타 관입하는 시공단계와; 상기 강재 H 말뚝에 기초부 콘크리트를 타설시 제방측에 배수로 형성하도록 거푸집을 형성하여 콘크리트를 타설하여 배수로가 형성된 교대 기초부를 시공단계와; 교대를 콘크리트로 타설하여 교대를 완성하는 단계와; 기초면을 계단형 다짐부를 형성하여 토압저항을 큰 저면에 공극률이 큰 뒷채움재료의 사용과 더불어 뒷채움 저면에 장착되는 "∪"형 프리캐스트 도수로 배수관 시공단계와; 그 상단의 계단부에 토압저항이 작은 위치에 유공관을 시공하는 단계로 배수로를 시공하여 이루어진 교량의 교대 배수로 시공방법.Constructing the fill process of both sides of the bridge embankment; A construction step of driving the steel H pile into the support layer as a foundation pile used to support the shift; A step of constructing an alternating foundation portion in which a drainage path is formed by pouring concrete by forming a formwork to form drainage on the embankment side when the foundation concrete is poured into the steel H pile; Placing shifts in concrete to complete the shifts; A step of constructing a "∪" -type precast raceway drain pipe mounted on the bottom of the back fill with the use of a back fill material having a large porosity on the bottom to form a stepped compaction on the base surface; A method of constructing alternating drainage bridges for bridges formed by constructing drainage pipes in a step of constructing a perforated pipe at a position of low earth pressure resistance in a step portion of the upper end thereof. 교량의 교대 뒷채움 배수로 에 있어서,In the shift backfill drainage of the bridge, 상기 교대 기초부(10)의 상단에 교대배수로(20)가 교대(100)와 일체로 형성된 구조를 갖는 것을 특징으로 하는 교량의 교대 뒷채움 배수로 구조.The alternating backfill drainage structure of the bridge, characterized in that the alternating drainage passage 20 is formed integrally with the shift 100 at the top of the shift base portion 10. 제 2 항에 있어서, 상기 교량의 교대 뒷채움 배수로는 교대 뒷채움의 배수로가 계단형으로 형성되고, 그 저면에는 콘크리트 구조물의 "U"형 배수로(30)를 형성하고, 상기 그 상단 계단부에 설치한 유공관(40)을 내설한 계단식 구조를 갖는 것을 특징으로 하는 교량의 교대 뒷채움 배수로 구조.3. The alternating backfill drainage channel of the bridge according to claim 2, wherein the alternating backfill drainage channel is formed in a stepped shape, and at the bottom thereof, a "U" type drainage channel 30 of a concrete structure is formed, Alternate backfill drainage structure of the bridge, characterized in that it has a stepped structure in which the perforated pipe (40).
KR10-2000-0072140A 2000-11-30 2000-11-30 Constructing method for the filling out abutement of bridge KR100433653B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR10-2000-0072140A KR100433653B1 (en) 2000-11-30 2000-11-30 Constructing method for the filling out abutement of bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR10-2000-0072140A KR100433653B1 (en) 2000-11-30 2000-11-30 Constructing method for the filling out abutement of bridge

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR2020000033687U Division KR200237328Y1 (en) 2000-12-01 2000-12-01 Trembling excluding device using oil tube while base rock blasting

Publications (2)

Publication Number Publication Date
KR20020042316A true KR20020042316A (en) 2002-06-05
KR100433653B1 KR100433653B1 (en) 2004-06-07

Family

ID=27678796

Family Applications (1)

Application Number Title Priority Date Filing Date
KR10-2000-0072140A KR100433653B1 (en) 2000-11-30 2000-11-30 Constructing method for the filling out abutement of bridge

Country Status (1)

Country Link
KR (1) KR100433653B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020025856A (en) * 2001-12-28 2002-04-04 이기홍 Prevention of approach slab settlement by applying non-com paction abutment backfilling method
CN114045742A (en) * 2021-08-13 2022-02-15 中铁三局集团有限公司 Construction method of large-span inverted siphon pipe bridge abutment
CN114351567A (en) * 2021-12-31 2022-04-15 安徽省交通规划设计研究总院股份有限公司 Novel road and bridge connection structure and construction method

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100705715B1 (en) * 2003-12-01 2007-04-10 주식회사 삼양사 embankment method of backfill construction
KR100733592B1 (en) * 2004-11-09 2007-07-03 주식회사 도영엔지니어링 Backfill system of integral bridge and its construction method to minimize the backfill pressure and to prevent the approach slab from its settlement
CN103161311B (en) * 2011-12-19 2016-01-20 中国建筑第七工程局有限公司 Large diameter reinforced concrete pipe road crosses the construction method of abutment

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020025856A (en) * 2001-12-28 2002-04-04 이기홍 Prevention of approach slab settlement by applying non-com paction abutment backfilling method
CN114045742A (en) * 2021-08-13 2022-02-15 中铁三局集团有限公司 Construction method of large-span inverted siphon pipe bridge abutment
CN114351567A (en) * 2021-12-31 2022-04-15 安徽省交通规划设计研究总院股份有限公司 Novel road and bridge connection structure and construction method
CN114351567B (en) * 2021-12-31 2024-04-26 安徽省交通规划设计研究总院股份有限公司 Road bridge connection structure and construction method

Also Published As

Publication number Publication date
KR100433653B1 (en) 2004-06-07

Similar Documents

Publication Publication Date Title
KR101216511B1 (en) Method for constructing a abutment of integral abutment bridge
KR20080061580A (en) Precast concrete file and method for constructing thereof
KR100654936B1 (en) Method for constructing retaining wall
KR20020042316A (en) Constructing method for the filling out abutement of bridge and its structure
KR101271290B1 (en) Underground reclamation type water storage tank having a assembling structure
KR101017127B1 (en) Connecting Structure between Foundation and Pier, and Construction Method thereof
JP3648219B2 (en) Precast flexible box culvert and its construction method
KR20090043625A (en) Method for constructing underground slabs using asymmetric girder
JP2001329545A (en) Bridge pier foundation construction method and floor slab for bridge pier
KR101045019B1 (en) Installation structure of block type breast wall and its construction method
KR200420394Y1 (en) Precast concrete block for cantilever retaining wall
KR200224496Y1 (en) Structure for the filling out abutement of bridge
KR100493516B1 (en) Micro pile and assembly foundation reinforcement structure member and its method for pier
KR100531214B1 (en) Construction method composed of sheet piles and wales for the circular temporary work area of the open cassion
KR101077242B1 (en) Construction method of basement structure using retaining wall and steel column
KR100722198B1 (en) Strut system of temporary retaining wall and subgrade external wall construction method utilizing the same
KR100902640B1 (en) Waterway culvert using steel sheet piles and its construction method
KR200265492Y1 (en) Impervious wall structures at inlet and outlet of channel concrete box
EP1887146A2 (en) Method for producing an aqueduct
CN109457725B (en) H-shaped concrete plate assembled ecological retaining wall
KR200357964Y1 (en) Block for retaining wall
CN112854231B (en) Foundation pit construction method for water saturation layer
CN111794340B (en) Drainage pipeline structure and construction method thereof
KR102426192B1 (en) File fof retaining wall and construction method using file
KR102676285B1 (en) Non-excavation construction structure for constructing a precast structure by minimizing face collapse

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
N231 Notification of change of applicant
FPAY Annual fee payment

Payment date: 20120507

Year of fee payment: 9

LAPS Lapse due to unpaid annual fee