CN111576222A - A kind of construction method of steel pipe pile plank road type green road - Google Patents

A kind of construction method of steel pipe pile plank road type green road Download PDF

Info

Publication number
CN111576222A
CN111576222A CN202010371817.5A CN202010371817A CN111576222A CN 111576222 A CN111576222 A CN 111576222A CN 202010371817 A CN202010371817 A CN 202010371817A CN 111576222 A CN111576222 A CN 111576222A
Authority
CN
China
Prior art keywords
steel pipe
pipe pile
pile
construction method
hoop
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010371817.5A
Other languages
Chinese (zh)
Inventor
蔡剑波
颜日锦
郑凤宜
符传立
张茂诚
刘文辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Municipal Engineering Design & Research Institute Co Ltd
Original Assignee
Guangzhou Municipal Engineering Design & Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Municipal Engineering Design & Research Institute Co Ltd filed Critical Guangzhou Municipal Engineering Design & Research Institute Co Ltd
Priority to CN202010371817.5A priority Critical patent/CN111576222A/en
Publication of CN111576222A publication Critical patent/CN111576222A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D18/00Bridges specially adapted for particular applications or functions not provided for elsewhere, e.g. aqueducts, bridges for supporting pipe-lines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/28Prefabricated piles made of steel or other metals
    • E02D5/285Prefabricated piles made of steel or other metals tubular, e.g. prefabricated from sheet pile elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/18Placing by vibrating

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

本发明公开了一种钢管桩栈道型碧道的施工方法,包括以下步骤:S10.将钢管桩沉桩;S20.在所述钢管桩的桩顶设置支架;S30.在所述支架上架设支撑体系;S40.在所述钢管桩中浇筑混凝土,形成钢筋混凝土桩;S50.在所述支撑体系上搭设模板,绑扎钢筋,浇筑混凝土,形成碧道梁板;S60.拆除所述支架、支撑体系和模板。其能够克服目前传统预制或者现浇钢筋混凝土桩栈道在施工及使用等方面存在的问题,便于沉桩施工,扰动更小。

Figure 202010371817

The invention discloses a construction method of a steel pipe pile plank road type green road, which comprises the following steps: S10. sinking a steel pipe pile; S20. setting a bracket on the top of the steel pipe pile; S30. placing a bracket on the support Set up a support system; S40. Pour concrete in the steel pipe piles to form reinforced concrete piles; S50. Set up a template on the support system, bind steel bars, pour concrete to form Bidao beam slabs; S60. Remove the Brackets, support systems and formwork. It can overcome the problems existing in the construction and use of the current traditional prefabricated or cast-in-place reinforced concrete pile plank road, facilitates the pile driving construction, and has less disturbance.

Figure 202010371817

Description

一种钢管桩栈道型碧道的施工方法A kind of construction method of steel pipe pile plank road type green road

技术领域technical field

本发明用于碧道建设领域,特别是涉及一种钢管桩栈道型碧道的施工方法。The invention is used in the field of green road construction, in particular to a construction method of a steel pipe pile plank road type green road.

背景技术Background technique

在有临河建筑物阻隔,用地条件受限的河岸段,建成顺河岸的人行和单车行的栈道型碧道,健全河道沿线的可达性和休闲亲水性,是对栈道与碧道相结合的一种技术创新。In the section of the river bank that is blocked by buildings near the river and the land conditions are limited, build a plank road-type blue road for pedestrians and bicycles along the river bank, improve the accessibility and leisure hydrophilicity along the river, and it is a combination of the plank road and the blue road. a technological innovation.

现有技术中,碧道大多采用钢筋混凝土预制方桩或管桩作为支撑,这种结构形式的碧道,行洪断面占用大,存在洪水风险。而且,针对岸线用地紧张的河段,往往无法在陆上施工,对沿岸旧有建筑物、堤岸保护的要求很高的河段,也很难在水中通过设置围堰、断流方式进行施工。此外,碧道顶部结构铺设时需要自地面起设脚手架,钢筋混凝土预制方桩或管桩以及脚手架对河床及行洪阻碍较大。In the prior art, most of the green roads are supported by reinforced concrete prefabricated square piles or pipe piles. The green roads in this structural form occupy a large flood section, and there is a risk of flooding. Moreover, for the river sections with tight shoreline land, it is often impossible to construct on land. For the river sections with high requirements for the protection of old buildings and embankments along the coast, it is also difficult to set up cofferdams and cut off the flow in the water. . In addition, scaffolding needs to be set up from the ground when laying the top structure of the green road, and the reinforced concrete prefabricated square piles or pipe piles and the scaffolding will greatly hinder the riverbed and flood flow.

发明内容SUMMARY OF THE INVENTION

本发明的目的在于至少解决现有技术中存在的技术问题之一,提供一种钢管桩栈道型碧道的施工方法,其能够克服目前传统预制或者现浇钢筋混凝土桩栈道在施工及使用等方面存在的问题,便于沉桩施工,扰动更小。The object of the present invention is to solve at least one of the technical problems existing in the prior art, and to provide a construction method of a steel pipe pile plank road type green road, which can overcome the current traditional prefabricated or cast-in-place reinforced concrete pile plank road in construction and use, etc. It is convenient for pile driving construction, and the disturbance is smaller.

本发明解决其技术问题所采用的技术方案是:The technical scheme adopted by the present invention to solve its technical problems is:

一种钢管桩栈道型碧道的施工方法,包括以下步骤:A construction method of a steel pipe pile plank road type green road, comprising the following steps:

S10.将钢管桩沉桩;S10. Drive the steel pipe pile;

S20.在所述钢管桩的桩顶设置支架;S20. A bracket is arranged on the top of the steel pipe pile;

S30.在所述支架上架设支撑体系;S30. erecting a support system on the bracket;

S40.在所述钢管桩中浇筑混凝土,形成钢筋混凝土桩;S40. Concrete is poured in the steel pipe pile to form a reinforced concrete pile;

S50.在所述支撑体系上搭设模板,绑扎钢筋,浇筑混凝土,形成碧道梁板;S50. Set up a template on the support system, bind steel bars, and pour concrete to form Bidao beam slabs;

S60.拆除所述支架、支撑体系和模板。S60. Remove the bracket, support system and formwork.

在一些实施例中,所述支架包括抱箍,所述箍环抱紧在所述钢管桩的桩顶,所述箍环沿周向设有多个支撑结构。In some embodiments, the bracket includes a hoop, the hoop is fastened on the top of the steel pipe pile, and the hoop is provided with a plurality of supporting structures in the circumferential direction.

在一些实施例中,所述箍环包括多个箍环组件,多个所述箍环组件连接,并在内部限定出抱紧所述钢管桩的箍口。In some embodiments, the hoop includes a plurality of hoop assemblies, the plurality of hoop assemblies are connected, and internally define a hoop opening for gripping the steel pipe pile.

在一些实施例中,所述箍环组件包括弧形板,所述弧形板的两端设有沿径向的耳座,相邻的所述箍环组件通过耳座上的紧固件连接,所述紧固件能够调节相邻所述箍环组件耳座的间距。In some embodiments, the hoop assembly includes an arc-shaped plate, two ends of the arc-shaped plate are provided with radial ear seats, and the adjacent hoop assemblies are connected by fasteners on the ear seats , the fastener can adjust the distance between the adjacent ear seats of the hoop assembly.

在一些实施例中,所述支撑结构包括焊接在所述弧形板外周面上的肋板,多个所述肋板的顶部端面齐平。In some embodiments, the support structure includes ribs welded on the outer peripheral surface of the arc-shaped plate, and the top end surfaces of a plurality of the ribs are flush.

在一些实施例中,所述支撑体系包括In some embodiments, the support system includes

横梁,所述横梁沿碧道横向搭设在相邻钢管桩的支架上;A beam, the beam is horizontally erected on the brackets of the adjacent steel pipe piles along the green road;

纵梁,所述纵梁沿碧道纵向搭设在所述横梁上;longitudinal beams, the longitudinal beams are erected on the transverse beams along the longitudinal direction of the green road;

模板平台,铺设在所述纵梁顶部。A formwork platform is laid on top of the stringers.

在一些实施例中,沿碧道纵向,两根横梁夹住所述钢管桩的桩顶。In some embodiments, along the longitudinal direction of the green road, two beams clamp the top of the steel pipe pile.

在一些实施例中,所述钢管桩采用振动沉桩或钻孔沉桩,钢管桩沉桩完成后遮蔽钢管桩的顶部管口。In some embodiments, the steel pipe pile adopts vibratory pile driving or bored pile driving, and the top nozzle of the steel pipe pile is shielded after the steel pipe pile driving is completed.

在一些实施例中,还包括In some embodiments, it also includes

S51.安装碧道两侧安全防护栏杆,铺装平台面。S51. Install safety railings on both sides of the green road and pave the platform surface.

在一些实施例中,步骤S10中,清除桩位处河床面块石障碍,在水上浮驳上,将钢管桩沉桩;还包括S61.疏浚河床,扩大行洪断面。In some embodiments, in step S10, the block stone obstacle on the river bed surface at the pile position is removed, and the steel pipe pile is sunk on the water floating barge; it also includes S61. Dredging the river bed and expanding the flooding section.

上述技术方案中的一个技术方案至少具有如下优点或有益效果之一:One of the technical solutions in the above-mentioned technical solutions has at least one of the following advantages or beneficial effects:

1.在有临河建筑物阻隔,用地条件受限的河岸段,建成顺河岸的人行和单车行栈道型碧道,健全了河道沿线的可达性和休闲亲水性。1. In the section of the river bank that is blocked by buildings near the river and the land conditions are limited, a plank road for pedestrians and bicycles along the river bank is built, which improves the accessibility and leisure hydrophilicity along the river.

2.面对河道行洪过流断面紧张,但又有栈道建设需求的河岸,相对于传统的钢筋混凝土预制方桩或管桩的栈道,钢管桩桩径小,结构紧凑,行洪断面占用小;钢管桩对河岸稳定有一定的加固作用,适当疏浚河床后,河道行洪断面有所扩大,降低了洪水风险。2. In the face of the river bank where the section of the river channel is tight, but there is a need for plank road construction, compared with the traditional plank road of reinforced concrete prefabricated square piles or pipe piles, the steel pipe pile has a small diameter, a compact structure, and occupies a flood-carrying section. Small; steel pipe piles have a certain reinforcement effect on the stability of the river bank. After the river bed is properly dredged, the flood section of the river channel is enlarged, which reduces the flood risk.

3.岸线用地紧张的河段,往往无法在陆上施工,而且对沿岸旧有建筑物、堤岸保护的要求很高,钢管桩截面面积小,可采用水上振动沉桩,施工速度快,水上施工,不设围堰、不断流,桩径小挤土效应小,施工对堤岸扰动小,安全性好。3. In the river sections with tight shoreline land, it is often impossible to construct on land, and the requirements for the protection of old buildings and embankments along the coast are very high. For water construction, there is no cofferdam, continuous flow, small pile diameter, small soil squeeze effect, little disturbance to the embankment, and good safety.

4.可利用桩顶设置支架、支撑体系、模板,不用自地面起设脚手架,施工期间对河床及行洪无额外影响,支模板更加便利。4. The top of the pile can be used to set up brackets, support systems, and formwork, and there is no need to set up scaffolding from the ground. During construction, there is no additional impact on the river bed and flooding, and the formwork is more convenient.

本发明的附加方面和优点将在下面的描述中部分给出,部分将从下面的描述中变得明显,或通过本发明的实践了解到。Additional aspects and advantages of the present invention will be set forth, in part, from the following description, and in part will be apparent from the following description, or may be learned by practice of the invention.

附图说明Description of drawings

本发明的上述和/或附加的方面和优点从结合下面附图对实施例的描述中将变得明显和容易理解,其中:The above and/or additional aspects and advantages of the present invention will become apparent and readily understood from the following description of embodiments taken in conjunction with the accompanying drawings, wherein:

图1是本发明一个实施例桩顶支架、支撑体系结构示意图;1 is a schematic structural diagram of a pile top bracket and a support system according to an embodiment of the present invention;

图2是图1所示的一个实施例抱箍松弛状态下结构示意图;Fig. 2 is the structural schematic diagram of the embodiment shown in Fig. 1 under the relaxed state of the hoop;

图3是图2中A-A处截面图;Figure 3 is a sectional view at A-A in Figure 2;

图4是本发明一个实施例模板平台、桩内填充混凝土示意图;4 is a schematic diagram of a formwork platform and a pile filled with concrete according to an embodiment of the present invention;

图5是本发明一个实施例抱箍箍紧状态结构示意图;5 is a schematic structural diagram of a hoop-fastened state according to an embodiment of the present invention;

图6是本发明一个实施例碧道梁板结构示意图;Fig. 6 is the structural schematic diagram of Bidao beam-slab according to an embodiment of the present invention;

图7是本发明一个实施例施工完成后栈道型碧道结构示意图。7 is a schematic structural diagram of a plank road-type green road after the construction of one embodiment of the present invention is completed.

具体实施方式Detailed ways

本部分将详细描述本发明的具体实施例,本发明之较佳实施例在附图中示出,附图的作用在于用图形补充说明书文字部分的描述,使人能够直观地、形象地理解本发明的每个技术特征和整体技术方案,但其不能理解为对本发明保护范围的限制。This part will describe the specific embodiments of the present invention in detail, and the preferred embodiments of the present invention are shown in the accompanying drawings. Each technical feature and overall technical solution of the invention should not be construed as limiting the protection scope of the invention.

本发明中,如果有描述到方向(上、下、左、右、前及后)时,其仅是为了便于描述本发明的技术方案,而不是指示或暗示所指的技术特征必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。In the present invention, if there is a description of a direction (up, down, left, right, front and rear), it is only for the convenience of describing the technical solution of the present invention, rather than indicating or implying that the technical features referred to must have specific characteristics Orientation, construction and operation in a particular orientation, and therefore should not be construed as limiting the invention.

本发明中,“若干”的含义是一个或者多个,“多个”的含义是两个以上,“大于”“小于”“超过”等理解为不包括本数;“以上”“以下”“以内”等理解为包括本数。在本发明的描述中,如果有描述到“第一”“第二”仅用于区分技术特征为目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量或者隐含指明所指示的技术特征的先后关系。In the present invention, "several" means one or more, "multiple" means two or more, "greater than", "less than", "exceeding", etc. are understood as not including this number; "above", "below" and "within" " etc. are understood to include the original number. In the description of the present invention, if it is described that "first" and "second" are only used for the purpose of distinguishing technical features, it should not be understood as indicating or implying relative importance or implying the number of indicated technical features or Implicitly indicates the order of the indicated technical features.

本发明中,除非另有明确的限定,“设置”“安装”“连接”等词语应做广义理解,例如,可以是直接相连,也可以通过中间媒介间接相连;可以是固定连接,也可以是可拆卸连接,还可以是一体成型;可以是机械连接,也可以是电连接或能够互相通讯;可以是两个元件内部的连通或两个元件的相互作用关系。所属技术领域技术人员可以结合技术方案的具体内容合理确定上述词语在本发明中的具体含义。In the present invention, unless otherwise clearly defined, words such as "set", "install" and "connect" should be understood in a broad sense, for example, it may be directly connected or indirectly connected through an intermediate medium; it may be a fixed connection or a The detachable connection can also be integrally formed; it can be a mechanical connection or an electrical connection or can communicate with each other; it can be the internal communication between the two elements or the interaction relationship between the two elements. Those skilled in the art can reasonably determine the specific meanings of the above words in the present invention in combination with the specific content of the technical solutions.

本发明的实施例提供了一种钢管桩栈道型碧道的施工方法,包括以下步骤:An embodiment of the present invention provides a construction method of a steel pipe pile plank road-type green road, comprising the following steps:

S10.参见图1,清除桩位处河床面块石障碍,沉桩设备在水上浮驳上,将钢管桩1沉桩,钢管桩1作为碧道的主体结构之一,沿碧道的延伸方向设置多个,本发明采用了结构紧凑的钢管桩1,代替了截面面积较大的钢筋混凝土桩,作为碧道的支撑结构;由于钢管桩1具有强度高、直径小的特点,用在河岸施工上,不但带来施工上的便利、提高了施工效率,对河岸的扰动降低,沉桩后进一步加固了河岸,同时避免了钢筋混凝土桩桩径大,过于阻水的问题;S10. Referring to Figure 1, remove the block stone obstacles on the river bed surface at the pile position, the pile driving equipment is floated on the water, and the steel pipe pile 1 is piled, and the steel pipe pile 1 is used as one of the main structures of the green road. A plurality of extension directions are arranged, and the present invention adopts the steel pipe pile 1 with a compact structure, instead of the reinforced concrete pile with a larger cross-sectional area, as the supporting structure of the green road; because the steel pipe pile 1 has the characteristics of high strength and small diameter, Used in river bank construction, it not only brings convenience in construction, improves construction efficiency, but also reduces disturbance to the river bank.

S20.参见图1,在钢管桩1的桩顶设置支架2,支架2与钢管桩1可拆卸连接;S20. Referring to Figure 1, a bracket 2 is provided on the top of the steel pipe pile 1, and the bracket 2 is detachably connected to the steel pipe pile 1;

S30.参见图1,在支架2上架设支撑体系3,支撑体系3在多个钢管桩1之间形成连续的支撑结构,为混凝土浇筑等施工工作提供平台和支撑,以便作进一步的钢管混凝土灌注、栈道梁板浇注施工,而不影响河道行洪;S30. Referring to FIG. 1, a support system 3 is erected on the support 2, and the support system 3 forms a continuous support structure between a plurality of steel pipe piles 1, and provides a platform and support for construction work such as concrete pouring, so as to make further steel pipe concrete Pouring, plank road beam and slab pouring construction, without affecting the flood flow of the river;

S40.参见图4、图5,在钢管桩1中浇筑混凝土,形成钢筋混凝土桩,其中,通过钢管桩1表面防腐和管桩内植筋和填充细石混凝土,钢管桩1碧道的耐久性可以得到进一步保障;S40. Referring to Fig. 4 and Fig. 5, concrete is poured in the steel pipe pile 1 to form a reinforced concrete pile, wherein, through the surface anti-corrosion of the steel pipe pile 1 and the planting of reinforcing bars in the pipe pile and the filling of fine stone concrete, the steel pipe pile 1 is a green road. The durability can be further guaranteed;

S50.参见图6,在支撑体系3上搭设模板,绑扎钢筋,浇筑混凝土,形成碧道梁板4;S50. Referring to Figure 6, set up a formwork on the support system 3, bind steel bars, and pour concrete to form the Bidao beam slab 4;

S60.拆除支架2、支撑体系3和模板,完成施工。S60. Remove the bracket 2, the support system 3 and the formwork to complete the construction.

该技术方案具有以下优势:This technical solution has the following advantages:

1.在有临河建筑物阻隔,用地条件受限的河岸段,建成顺河岸的人行和单车行栈道型碧道,健全了河道沿线的可达性和休闲亲水性。1. In the section of the river bank that is blocked by buildings near the river and the land conditions are limited, a plank road for pedestrians and bicycles along the river bank is built, which improves the accessibility and leisure hydrophilicity along the river.

2.面对河道行洪过流断面紧张,但又有栈道建设需求的河岸,相对于传统的钢筋混凝土预制方桩或管桩的栈道,钢管桩1桩径小,结构紧凑,行洪断面占用小;钢管桩1对河岸稳定有一定的加固作用,适当疏浚河床后,河道行洪断面有所扩大,降低了洪水风险。2. In the face of the river bank where the section of the river channel is tight, but there is a need for plank road construction, compared with the traditional plank road with reinforced concrete prefabricated square piles or pipe piles, the steel pipe pile 1 has a small diameter, a compact structure, and a flood-carrying section. The occupation is small; the steel pipe pile 1 has a certain reinforcement effect on the stability of the river bank. After the river bed is properly dredged, the flood section of the river channel is enlarged, which reduces the flood risk.

3.岸线用地紧张的河段,往往无法在陆上施工,而且对沿岸旧有建筑物、堤岸保护的要求很高,钢管桩1截面面积小,可采用水上振动沉桩,施工速度快,水上施工,不设围堰、不断流,桩径小挤土效应小,施工对堤岸扰动小,安全性好。3. In the river section with tight shoreline land, it is often impossible to construct on land, and the requirements for the protection of old buildings and embankments along the coast are very high. , Water construction, no cofferdam, continuous flow, small pile diameter, small soil squeeze effect, small disturbance to the embankment, and good safety.

4.可利用桩顶设置支架2、支撑体系3、模板,不用自地面起设脚手架,施工期间对河床及行洪无额外影响,支模板更加便利。4. The top of the pile can be used to set up the bracket 2, the supporting system 3, and the formwork, and there is no need to set up the scaffolding from the ground. During the construction, there is no additional impact on the river bed and flooding, and the formwork is more convenient.

支架2与钢管桩1可拆卸连接,例如在一些实施例中,参见图2、图5,支架2包括抱箍,箍环抱紧在钢管桩1的桩顶,即通过从外周抱紧钢管桩1的连接方式,固定在钢管桩1的桩顶,连接更加方便,而且在碧道施工完毕后,拆除也更加简便,不受已成型的碧道结构影响。The bracket 2 is detachably connected to the steel pipe pile 1. For example, in some embodiments, referring to FIG. 2 and FIG. 5, the bracket 2 includes a hoop, and the hoop is fastened on the top of the steel pipe pile 1, that is, through the outer circumference of the steel pipe pile. The connection method of the pipe pile 1 is fixed on the pile top of the steel pipe pile 1, the connection is more convenient, and after the construction of the green road is completed, the dismantling is also easier, and it is not affected by the formed green road structure.

参见图2、图3,箍环沿周向设有多个支撑结构21,支撑体系3搭接在支撑结构21上,多个支撑结构21沿箍环的周向分布,使得箍环在钢管桩1上的安装方向具有更多的选择性,施工更加便利。2 and 3, the hoop is provided with a plurality of supporting structures 21 in the circumferential direction, the support system 3 is overlapped on the supporting structure 21, and the plurality of supporting structures 21 are distributed along the circumferential direction of the hoop, so that the hoop is in the steel pipe pile 1. The installation direction on the upper has more selectivity, and the construction is more convenient.

箍环包括多个箍环组件,例如在图2所示的实施例中,箍环包括两个呈半圆形的箍环组件,可以理解的是,箍环组件可以设置两个以上。多个箍环组件连接,并在内部限定出抱紧钢管桩1的箍口22。即多个箍环组件连接形成环形结构,以箍紧在钢管桩1桩顶。当施工完毕后,将多个箍环组件松弛,并由钢管桩1上取下。The hoop includes a plurality of hoop assemblies. For example, in the embodiment shown in FIG. 2 , the hoop includes two semicircular hoop assemblies. It is understood that more than two hoop assemblies may be provided. A plurality of hoop assemblies are connected, and internally define a hoop opening 22 for holding the steel pipe pile 1 tightly. That is, a plurality of hoop assemblies are connected to form an annular structure, so as to be fastened to the top of the steel pipe pile 1 . After the construction is completed, the plurality of hoop assemblies are loosened and removed from the steel pipe pile 1 .

在一些实施例中,参见图2,箍环组件包括弧形板23,弧形板23的两端设有沿径向的耳座24,相邻的箍环组件通过耳座24上的紧固件25连接,紧固件25可采用螺栓等,紧固件25能够调节相邻箍环组件耳座24的间距,以使箍环能够抱紧钢管桩1。In some embodiments, referring to FIG. 2 , the hoop assembly includes an arc-shaped plate 23 , two ends of the arc-shaped plate 23 are provided with radial ear seats 24 , and the adjacent hoop assemblies are fastened on the ear seats 24 The fasteners 25 can be connected by bolts, etc. The fasteners 25 can adjust the distance between the ear seats 24 of the adjacent hoop assemblies, so that the hoop can hold the steel pipe pile 1 tightly.

支撑结构21可采用支撑柱、支撑块、支撑板等,例如在图2、图3所示的一些实施例中,支撑结构21包括焊接在弧形板23外周面上的肋板,肋板沿钢管桩1高度方向设置,以使其承载能力更强。多个肋板的顶部端面齐平,以为支撑体系3提供稳定的支撑。The support structure 21 can be a support column, a support block, a support plate, etc. For example, in some embodiments shown in FIG. 2 and FIG. The steel pipe pile 1 is set in the height direction to make its bearing capacity stronger. The top end faces of the plurality of ribs are flush to provide stable support for the support system 3 .

参见图1,在一些实施例中,支撑体系3包括横梁31、纵梁32和模板平台33,横梁31和纵梁32可采用工字梁、钢管梁等,横梁31沿碧道横向搭设在相邻钢管桩1的支架2上;纵梁32沿碧道纵向搭设在横梁31上,横梁31和纵梁32相互垂直,为顶部的模板平台33提供稳定支撑,模板平台33铺设在纵梁32顶部。通过模板平台33,铺设混凝土泵送管,输送细石混凝土灌注到钢管桩1中,填充振密混凝土,在钢管桩1中形成实心的钢筋混凝土桩,进一步增加桩基的强度和耐久性。1, in some embodiments, the support system 3 includes beams 31, longitudinal beams 32 and a formwork platform 33. The beams 31 and longitudinal beams 32 can be I-beams, steel pipe beams, etc. On the bracket 2 of the adjacent steel pipe pile 1; the longitudinal beam 32 is erected on the beam 31 along the longitudinal direction of the green road, and the transverse beam 31 and the longitudinal beam 32 are perpendicular to each other, providing stable support for the formwork platform 33 at the top, and the formwork platform 33 is laid on the longitudinal beam 32 top. Through the formwork platform 33, the concrete pumping pipe is laid, and the fine stone concrete is poured into the steel pipe pile 1, filled with vibrating concrete, and a solid reinforced concrete pile is formed in the steel pipe pile 1, which further increases the strength and durability of the pile foundation. .

在一些实施例中,沿碧道纵向,两根横梁31夹住钢管桩1的桩顶,即紧贴钢管桩1的两侧均架设横梁31,以充分利用箍环提供的支撑结构21,而且受力更加平衡,结构稳定性更高。In some embodiments, along the longitudinal direction of the green road, two beams 31 clamp the top of the steel pipe pile 1, that is, the beams 31 are erected on both sides of the steel pipe pile 1 to make full use of the support structure 21 provided by the hoop. , and the force is more balanced and the structural stability is higher.

钢管桩1采用振动沉桩或钻孔沉桩,例如在一些实施例中,清除桩位处河床面块石障碍,挖掘机换振动锤,在水上浮驳上,将钢管桩1振动沉桩,如周边建筑物较老旧,则可采用钻孔沉桩,进一步减少沉桩扰动,保障栈道沿线构筑物安全。The steel pipe pile 1 adopts vibratory pile driving or drilling pile driving. For example, in some embodiments, the block stone obstacle on the river bed surface at the pile position is removed, the excavator is replaced with a vibrating hammer, and the steel pipe pile 1 is vibrated and sunk on the water floating barge. For piles, if the surrounding buildings are old, bored piles can be used to further reduce the disturbance of piles and ensure the safety of structures along the plank road.

沉好的钢管桩1,需注意桩顶防水,即钢管桩1沉桩完成后遮蔽钢管桩1的顶部管口,遮蔽的方法不限,例如在一些实施例中,采用套塑料袋的方法,袋口向下,扎紧,可防止雨水灌入。For the sunk steel pipe pile 1, it is necessary to pay attention to the waterproofing of the top of the pile, that is, after the steel pipe pile 1 is sunk, the top nozzle of the steel pipe pile 1 is covered, and the method of covering is not limited. For example, in some embodiments, a plastic bag is used. The method, the mouth of the bag is down, and it is tied tightly to prevent rainwater from pouring in.

在一些实施例中,还包括In some embodiments, it also includes

S51.参见图7,安装碧道两侧安全防护栏杆41,铺装平台面42,提升碧道的安全性。S51. Referring to Figure 7, install the safety guard rails 41 on both sides of the green road, and pave the platform surface 42 to improve the safety of the green road.

S61.疏浚河床,扩大行洪断面,降低了洪水风险。S61. Dredging the river bed to expand the flood section and reduce the flood risk.

在本说明书的描述中,参考术语“示例”、“实施例”或“一些实施例”等的描述意指结合该实施例或示例描述的具体特征、结构、材料或者特点包含于本发明的至少一个实施例或示例中。在本说明书中,对上述术语的示意性表述不一定指的是相同的实施例或示例。而且,描述的具体特征、结构、材料或者特点可以在任何的一个或多个实施例或示例中以合适的方式结合。In the description of this specification, a description with reference to the terms "example", "embodiment" or "some embodiments" etc. means that a particular feature, structure, material or characteristic described in connection with the embodiment or example is included in at least one aspect of the present invention in one embodiment or example. In this specification, schematic representations of the above terms do not necessarily refer to the same embodiment or example. Furthermore, the particular features, structures, materials or characteristics described may be combined in any suitable manner in any one or more embodiments or examples.

当然,本发明创造并不局限于上述实施方式,熟悉本领域的技术人员在不违背本发明精神的前提下还可作出等同变形或替换,这些等同的变型或替换均包含在本申请权利要求所限定的范围内。Of course, the present invention is not limited to the above-mentioned embodiments, and those skilled in the art can make equivalent modifications or replacements without departing from the spirit of the present invention, and these equivalent modifications or replacements are included in the claims of the present application. within a limited range.

Claims (10)

1. A construction method of a steel pipe pile channel type pipeline is characterized by comprising the following steps:
s10, sinking the steel pipe pile;
s20, arranging a support on the pile top of the steel pipe pile;
s30, erecting a support system on the support;
s40, pouring concrete in the steel pipe pile to form a reinforced concrete pile;
s50, erecting a template on the support system, binding reinforcing steel bars, and pouring concrete to form a pavement beam slab;
and S60, removing the support, the support system and the template.
2. The construction method of the steel pipe pile stack type pipeline according to claim 1, characterized in that: the support comprises a hoop, the hoop is tightly held on the pile top of the steel pipe pile, and a plurality of supporting structures are arranged on the hoop along the circumferential direction.
3. The construction method of the steel pipe pile stack type pipeline according to claim 2, characterized in that: the hoop comprises a plurality of hoop components which are connected and define a hoop mouth holding the steel pipe pile inside.
4. The construction method of the steel pipe pile stack type pipeline according to claim 3, characterized in that: the hoop component comprises an arc plate, the two ends of the arc plate are provided with lug seats along the radial direction, the hoop component is adjacent to the lug seats and connected through a fastening piece on the lug seats, and the fastening piece can adjust the distance between the lug seats of the hoop component.
5. The construction method of the steel pipe pile stack type pipeline according to claim 4, characterized in that: the supporting structure comprises rib plates welded on the outer peripheral surfaces of the arc-shaped plates, and the top end faces of the rib plates are flush.
6. The construction method of the steel pipe pile stack type pipeline according to claim 1, characterized in that: the support system comprises
The cross beam is transversely erected on the bracket of the adjacent steel pipe pile along the road;
the longitudinal beams are longitudinally erected on the cross beam along the green road;
and the template platform is laid on the top of the longitudinal beam.
7. The construction method of the steel pipe pile stack type pipeline according to claim 6, characterized in that: and the pile top of the steel pipe pile is clamped by two cross beams along the longitudinal direction of the pipeline.
8. The construction method of the steel pipe pile stack type pipeline according to claim 1, characterized in that: the steel pipe pile adopts vibration pile sinking or drilling pile sinking, and the top mouth of pipe of steel pipe pile is shielded to the completion back of steel pipe pile sinking.
9. The construction method of the steel pipe pile stack type pipeline according to claim 1, characterized in that: also comprises
And S51, installing safety protection railings on two sides of the road and paving the platform surface.
10. The construction method of the steel pipe pile stack type pipeline according to claim 1, characterized in that: in the step S10, removing block stone barriers on the river bed surface at the pile position, floating on water, and piling the steel pipe pile; and S61, dredging a river bed and expanding a flood discharge section.
CN202010371817.5A 2020-05-06 2020-05-06 A kind of construction method of steel pipe pile plank road type green road Pending CN111576222A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010371817.5A CN111576222A (en) 2020-05-06 2020-05-06 A kind of construction method of steel pipe pile plank road type green road

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010371817.5A CN111576222A (en) 2020-05-06 2020-05-06 A kind of construction method of steel pipe pile plank road type green road

Publications (1)

Publication Number Publication Date
CN111576222A true CN111576222A (en) 2020-08-25

Family

ID=72109119

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010371817.5A Pending CN111576222A (en) 2020-05-06 2020-05-06 A kind of construction method of steel pipe pile plank road type green road

Country Status (1)

Country Link
CN (1) CN111576222A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115217067A (en) * 2022-08-25 2022-10-21 广东城华工程咨询有限公司 Green plant ecological retaining wall combined green road and design and construction method thereof
CN116905486A (en) * 2023-07-28 2023-10-20 中铁建设集团中原建设有限公司 Construction method of rock-socketed miniature steel pipe pile gallery road foundation

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006083519A (en) * 2004-09-14 2006-03-30 Kajima Corp Three-dimensional intersection construction method
CN108193587A (en) * 2017-12-30 2018-06-22 贵阳铝镁设计研究院有限公司 A kind of device of aluminium alloy assembled trestle and preparation method thereof
CN207567641U (en) * 2017-11-22 2018-07-03 广州市艺杰园林建设工程有限公司 A kind of lake surface sightseeing plank road structure
CN108708284A (en) * 2018-05-24 2018-10-26 中铁七局集团有限公司勘测设计研究院 A kind of steel trestle construction method for resisting flood discharge bed scour
CN208577931U (en) * 2018-06-26 2019-03-05 上海市园林工程有限公司 A kind of strutting system of trestle near water
CN110924307A (en) * 2019-11-28 2020-03-27 中铁广州工程局集团桥梁工程有限公司 Trestle construction method for bare rock geology

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006083519A (en) * 2004-09-14 2006-03-30 Kajima Corp Three-dimensional intersection construction method
CN207567641U (en) * 2017-11-22 2018-07-03 广州市艺杰园林建设工程有限公司 A kind of lake surface sightseeing plank road structure
CN108193587A (en) * 2017-12-30 2018-06-22 贵阳铝镁设计研究院有限公司 A kind of device of aluminium alloy assembled trestle and preparation method thereof
CN108708284A (en) * 2018-05-24 2018-10-26 中铁七局集团有限公司勘测设计研究院 A kind of steel trestle construction method for resisting flood discharge bed scour
CN208577931U (en) * 2018-06-26 2019-03-05 上海市园林工程有限公司 A kind of strutting system of trestle near water
CN110924307A (en) * 2019-11-28 2020-03-27 中铁广州工程局集团桥梁工程有限公司 Trestle construction method for bare rock geology

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115217067A (en) * 2022-08-25 2022-10-21 广东城华工程咨询有限公司 Green plant ecological retaining wall combined green road and design and construction method thereof
CN116905486A (en) * 2023-07-28 2023-10-20 中铁建设集团中原建设有限公司 Construction method of rock-socketed miniature steel pipe pile gallery road foundation

Similar Documents

Publication Publication Date Title
CN109339065B (en) A method for supporting construction caps of deep-water exposed bedrock densely-arranged piles
CN110847020B (en) Steel pipe pile steel trestle end and construction method
CN108708284B (en) A kind of steel trestle construction method for resisting flood discharge bed scour
KR101011805B1 (en) Method of constructing underground structures crossing the pile foundation and underground structures constructed using the same
CN110670433A (en) A construction structure for building roads on soft soil foundations
CN115045179A (en) Upper-bridge and lower-tunnel combined construction structure and construction method
CN211368349U (en) Steel trestle end of steel pipe pile
CN116240766B (en) Construction method of widening the embankment with soft permeable pipe drainage foam concrete
JP2000345502A (en) Boundary junction structure and method of widening road boundary
JP3316163B2 (en) Widening road and its construction method
JP2002121727A (en) Steel slit dam structure
JP3648219B2 (en) Precast flexible box culvert and its construction method
KR100433653B1 (en) Constructing method for the filling out abutement of bridge
JP4506316B2 (en) Road leveling structure
CN219604069U (en) Soft permeable pipe drainage foam concrete widened air quality embankment
KR100902640B1 (en) Waterway culvert using steel sheet piles and its construction method
CN217399721U (en) A kind of support structure in soft soil area
KR100493516B1 (en) Micro pile and assembly foundation reinforcement structure member and its method for pier
KR102426192B1 (en) File fof retaining wall and construction method using file
CN110344440A (en) A kind of method and structure using reinforced concrete supporting beam in-situ conservation pipeline
CN115478495A (en) A cover plate culvert reinforcement device and construction method that utilizes the flexibility of corrugated steel
KR100227536B1 (en) Bell type caisson foundation method
JP3593752B2 (en) Retaining wall structure and built flat land structure or built road structure on steep slopes
CN212714461U (en) Laying tool for steel pipe pile channel type pavement
CN115305949A (en) Road shoulder retaining wall structure and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200825