KR20020012670A - A Bridge Establishing Method Using Fabricated Jack Support Unit - Google Patents

A Bridge Establishing Method Using Fabricated Jack Support Unit Download PDF

Info

Publication number
KR20020012670A
KR20020012670A KR1020000045837A KR20000045837A KR20020012670A KR 20020012670 A KR20020012670 A KR 20020012670A KR 1020000045837 A KR1020000045837 A KR 1020000045837A KR 20000045837 A KR20000045837 A KR 20000045837A KR 20020012670 A KR20020012670 A KR 20020012670A
Authority
KR
South Korea
Prior art keywords
support
bridge
prefabricated
slab
jack
Prior art date
Application number
KR1020000045837A
Other languages
Korean (ko)
Inventor
김정현
Original Assignee
김정현
코벡주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김정현, 코벡주식회사 filed Critical 김정현
Priority to KR1020000045837A priority Critical patent/KR20020012670A/en
Publication of KR20020012670A publication Critical patent/KR20020012670A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

PURPOSE: A slab installation method of a rahmen bridge, a slab bridge and a girder bridge using a prefabricated jack bearing device is provided to heighten convenience by excluding a concrete foundation work by processing a construction work without using an existing timbering. CONSTITUTION: A slab installation method of a rahmen bridge, a slab bridge and a girder bridge using a prefabricated jack bearing device comprises the steps of: installing a pier and an abutment temporarily at regular intervals on a space for installing a bridge; installing a prefabricated jack bearing device(300) to the upper part of the pier and the abutment; placing a hydraulic jack and a cross beam on a bearing plate body of the prefabricated jack bearing device(300) and installing a form supporter(130); installing a slab(150) temporarily by using the form; and removing the jack, the cross beam, the prefabricated jack bearing device(300) and the form supporter(130).

Description

조립식 잭 받침장치를 이용한 교량 라멘교와 슬라브교 및 거더교의 슬라브 설치 방법{A Bridge Establishing Method Using Fabricated Jack Support Unit}Slab installation of bridge ramen bridge, slab bridge and girder bridge using prefabricated jack support device {A Bridge Establishing Method Using Fabricated Jack Support Unit}

본 발명은 다리의 상판 구조물인 슬라브를 제작하기 위한 공법에 관한 것이다.The present invention relates to a method for manufacturing a slab that is the upper plate structure of the bridge.

일반적으로 다리를 설치하는 공법에는 여러 경우가 있는 바, 가장 널리 사용되고 있는 공법은 교각과 교대를 가설후 다수개의 서포트를 이용하여 다리의 상판을 완성하는 방법이다.In general, there are many cases of the bridge installation method, the most widely used method is the method of completing the top plate of the bridge using a number of supports after the construction of the bridge and the shift.

즉, 콘크리트를 양생하여 다리의 상판을 형성하는 종래의 교량 건설 방법을 살펴보면, 통상의 방식으로 다수의 서포트를 조밀하게 세우고 그 상부에 거푸집 하우징을 지지하며, 그 상부로 철근을 배근하고 콘크리트 치기를 하여 양생함으로써 다리의 슬라브를 형성하고, 나중에 이들 가설물을 해체함으로써 다리의 상판을 완성한다.In other words, in the conventional bridge construction method of curing concrete to form the upper plate of the bridge, a plurality of supports are erected in a conventional manner, the formwork housing is supported on the upper part, the reinforcing bar is reinforced to the upper part, By curing the slabs of the legs, and later dismantle these temporary objects to complete the upper plate of the legs.

그러나, 지반이 무른 경우 서포트를 설치하기 위해 지반을 정리해야 하고, 더불어서 기초 콘크리트 타설이 필수 사항이 되므로, 기초 공사가 추가되어 공사기간이 증가할 뿐만 아니라, 슬라브 공사가 마무리 되면 나중에 기초 콘크리트를 폐기품으로 처리해야 하므로 공사비의 추가 요인이 된다.However, if the ground is soft, the ground must be cleaned to install the support, and in addition, the foundation concrete is required, so that the foundation period is added and the construction period is increased, and when the slab construction is completed, the foundation concrete is later discarded. As it must be processed as a product, it is an additional factor of construction cost.

또한, 상기 거푸집을 지지하기 위한 서포트는 매우 조밀해 설치됨으로써 시공과정에서 균형이 맞지 않을 경우에 이를 수정하는 것이 거의 불가능 하며, 따라서 거푸집 붕괴사고로 이어지는 문제점을 발생시킨다.In addition, since the support for supporting the formwork is very dense, it is almost impossible to correct it when it is not balanced in the construction process, thus causing a problem leading to the form collapse accident.

특히, 하천이나 고가도로등의 여건과 하수관이나 케이블등의 장애물이 있을 시에는 서포트를 이용하기가 용이하지 않으므로 결국 시공이 불가능 하게 되며, 상기와 같이 서포트를 이용하는 방식도 낮은 다리의 설치에서나 가능하기 때문에, 교량의 높이가 10M이상 넘어가면 매우 비 경제적인 공법이 되고, 또한 우천이나 호우시에는 서포트의 변형과 함께 교량의 바닥면이 침하되어 재설치를 해야 하는 등 시공이 난이하고 복잡해지는 문제점이 있었다.In particular, when there are obstacles such as rivers and overpasses, and obstacles such as sewer pipes or cables, the support is not easy to use, and thus the construction is impossible. If the height of the bridge is more than 10M, it becomes a very uneconomical method, and in the case of rain or heavy rain, there is a problem that the construction is difficult and complicated, such as the bottom surface of the bridge sinks and needs to be reinstalled.

한편, 종래의 다른예로 기존에 통행량이 있는 도로상을 크로스 하는 교량의 설치시 비계틀의 형상 구조와 비슷한 가설벤트를 도로를 피하여서 교대나 교각의 주변에 지지 설치하도록 하면서 그들 사이에 H빔을 가설후 거푸집을 설치하는 공법이었다.Meanwhile, in another conventional example, when installing a bridge that crosses a road with a traffic volume, a H-beam between them while supporting a temporary vent similar to the shape structure of a scaffold frame is installed around a shift or a pier, avoiding the road. After the hypothesis was to install the formwork.

그러나, 이 경우 역시 상기 가설벤트를 지지하기 위해 교대나 교각의 주변 바닥에 지반정리 및 기초 콘크리트 작업이 필수적이며, 이로 인한 폐기물 처리의 문제점이 있고, 역시 하천이나 고가도로 지장물의 여건시 시공이 곤란해진다.However, in this case, the ground clearance and foundation concrete work on the bottom of the shift or bridge pier is also essential to support the temporary vent, there is a problem of waste treatment, and also difficult construction of rivers and elevated road obstacles .

또한, 가설벤트와 H빔 등은 중량과다로 시공의 어려움이 있고, 교량이 높을 수록 비경제적이며, 호우시 기초 콘크리트의 저부가 토사에 휩쓸려 침하 발생의 우려가 있다.In addition, temporary construction and H-beams are difficult to install due to overweight, the higher the bridge is uneconomical, there is a fear that the bottom of the base concrete during heavy rain is swept away by the soil.

본 발명은 상기와 같은 문제점을 해결코자 하는 것으로,The present invention is to solve the above problems,

조립식 받침장치(잭 받침장치)를 교량이나 교각에 설치하고, 상기 조립식 받침장치 상부에 거푸집 지지대를 설치하며, 상기 거푸집 지지대에 거푸집을 설치토록 함으로써, 기존의 동바리를 이용하지 않고 작업을 진행하여 기초 콘크리트 작업을 진행하지 않아도 되는 편리함을 제공코자 하는데 그 목적이 있다.By installing a prefabricated support device (jack support device) on a bridge or piers, installing a formwork support on the prefabricated support device, and installing the formwork on the formwork support, the work is carried out without using existing clubs. The purpose is to provide the convenience of not having to proceed with concrete work.

상기 목적을 달성하기 위해,In order to achieve the above object,

본 발명은 다리를 건설할 공간에 일정한 간격을 두고 교각 및 교대를 가설하는 교각 및 교대 가설 공정과;The present invention provides a pier and alternating construction process for constructing bridges and shifts at regular intervals in a space for constructing a bridge;

상기 교각 및 교대의 상부에 인상용 잭 받침장치를 설치하는 잭 받침 설치 공정과;A jack support installation process for installing an impression jack support device on an upper portion of the pier and the shift;

상기 잭 받침장치의 받침판체에 잭 및 크로스 빔을 올려놓고 그 상부에 거푸집 지지대를 설치하는 거푸집 지지대 설치 공정과;A mold support installation step of placing a jack and a cross beam on the support plate body of the jack support device and installing a form support on the upper portion thereof;

상기 거푸집 지지대 상부에 거푸집을 설치하는 거푸집 설치 공정과;Formwork installation process for installing the formwork on the formwork support;

상기 거푸집을 이용하여 슬래브를 가설하는 슬래브 가설 공정과;A slab construction process of installing a slab using the formwork;

상기 공정에서 슬래브 가설이 완성되면 잭과 크로스빔과 잭 받침장치 및 거푸집 지지대를 철거하는 철거 공정으로 이루어지는 것이 특징이다.When the slab hypothesis is completed in the above process is characterized in that the demolition process of removing the jack, crossbeam and jack support device and formwork support.

도 1은 본 발명에 있어서 교각 및 교대 가설 공정도.1 is a pier and alternating construction process diagram in the present invention.

도 2는 본 발명에 있어서 조립식 잭 받침장치 가설 공정도.Figure 2 is a prefabricated jack restraint construction process diagram in the present invention.

도 3은 본 발명의 인상용 잭 및 거푸집 지지대 가설 공정도.Figure 3 is an impression jack and formwork supporting process of the present invention.

도 4는 본 발명의 거푸집 설치 공정도.Figure 4 is a formwork installation process of the present invention.

도 5는 본 발명의 슬래브 가설 공정도.5 is a slab temporary process of the present invention.

도 6은 본 발명의 철거작업에 있어서 인상용 잭 해체 공정도.Figure 6 is a jack dismantling process of the impression in the demolition work of the present invention.

도 7은 본 발명의 철거작업에 있어서 조립식 받침장치 해체 공정도.Figure 7 is a prefabricated dismantling process diagram of the demolished work of the present invention.

도 8a는 본 발명의 조립식 잭 받침장치 구성도.Figure 8a is a block diagram of the prefabricated jack support device of the present invention.

도 8b는 본 발명의 조립식 잭 받침장치 구성의 제 1 실시예도.Figure 8b is a first embodiment of a prefabricated jack support device configuration of the present invention.

도 8c는 본 발명의 조립식 잭 받침장치 구성의 제 2 실시예도.Figure 8c is a second embodiment of a prefabricated jack support device configuration of the present invention.

도 9는 본 발명의 조립식 잭 받침장치 구성의 제 3 실시예도.Figure 9 is a third embodiment of a prefabricated jack support device configuration of the present invention.

도 10은 본 발명의 거푸집 지지대를 설치한 상태도.10 is a state in which the formwork support of the present invention is installed.

도 11a는 본 발명의 조립식 잭 받침장치 구성의 제 4 실시예도.Figure 11a is a fourth embodiment of a prefabricated jack support device configuration of the present invention.

도 11b는 본 발명을 라멘교에 적용한 상태도.11B is a state diagram in which the present invention is applied to a ramen bridge.

도 12는 일반적인 판형교 구성도.12 is a general plate-shaped bridge configuration.

도 13은 일반적인 PC빔교 구성도.Figure 13 is a general PC beam bridge configuration diagram.

도 14는 일반적인 스틸 박스교 구성도.14 is a general steel box bridge configuration diagram.

도 15a는 본 발명의 PC빔교 설치 구성도.Figure 15a is a configuration diagram of the PC beam bridge installation of the present invention.

도 15b는 본 발명의 PC빔교 일부 확대도.15B is an enlarged view of a portion of a PC beam bridge of the present invention.

도 15c는 본 발명의 PC빔교의 다른 설치 상태도.Fig. 15C is another installation state of the PC beam bridge of the present invention.

도 16은 본 발명의 판형교 설치 상태도.Figure 16 is a plate-shaped bridge installation state of the present invention.

도 17은 본 발명의 스틸 박스교 설치 상태도.Figure 17 is a steel box bridge installation state of the present invention.

* 도면의 주요부분에 대한 부호의 설명 *Explanation of symbols on the main parts of the drawings

10: 수직연결판 20, 30: 베이스판10: vertical connecting plate 20, 30: base plate

40: 받침판체 50: 받침철물40: support plate 50: support hardware

100: 교각 110: 인상용 유압잭100: pier 110: impression hydraulic jack

120: 크로스빔 130: 거푸집 지지대120: crossbeam 130: formwork support

140: 거푸집 150: 슬래브140: formwork 150: slab

160: 인장잭 170: 와이어160: tension jack 170: wire

200: 교대 210: 수직 연결판200: shift 210: vertical connecting plate

220: 버팀편 230: 보강편220: support piece 230: reinforcement piece

300: 조립식 잭 받침장치 400: 판형교300: prefabricated jack support device 400: plate bridge

500: PC빔교 600: 스틸 박스교500: PC beam bridge 600: Steel box bridge

이하에서 도면을 참조로 본 발명을 보다 상세히 설명하면 다음과 같다.Hereinafter, the present invention will be described in more detail with reference to the accompanying drawings.

도 1 - 도 7은 본 발명에 있어서, 슬라브교 가설 방법을 나타낸 것으로,1 to 7 illustrate the Slavic bridge hypothesis method according to the present invention.

먼저, 도 1은 교각(100) 및 교대(200) 가설 상황을 도시한 것으로, 본 발명은 하천이나 장애물이 존재하여 기존의 동바리 설치가 불가능한 상황을 동시에 표현하고 있다.First, FIG. 1 illustrates a temporary construction of a bridge 100 and a shift 200, and the present invention simultaneously represents a situation in which existing installations are impossible due to the presence of rivers or obstacles.

그러나, 기존의 동바리 설치가 불가능하거나 또는 가능한 것과 상관없이 본발명을 이용할 수 있음은 물론이다.However, it is a matter of course that the present invention can be used irrespective of whether or not existing installations are possible.

도 2는 본 발명에서 교각(100) 및 교대(200)의 가설이 완료된 후 조립식 잭 받침장치(300)를 교각 및 교대 상부에 설치하는 것을 나타내고 있는바, 여기서 교각(100)에 설치되는 조립식 잭 받침장치(300)는, 도 8a과 같이 교각 상부 폭방향의 일측에 놓여질 수 있도록 직각으로 형성되어지며, 수평한 양단에 소정의 길이와 폭으로서 연장되는 수평 연결판(10)들을 가지는 일측 베이스판(20)과,Figure 2 shows the installation of the prefabricated jack support device 300 on the pier and the alternating top after the construction of the pier 100 and alternating 200 in the present invention, where the prefabricated jack is installed on the pier 100 The supporting device 300 is formed at right angles so as to be placed on one side of the pier upper width direction as shown in FIG. 8A, and has one side base plate having horizontal connecting plates 10 extending at a predetermined length and width at both horizontal ends thereof. 20,

상기 일측 베이스판(20)과 상응하는 형상으로서 일체형으로 연결되는 수평 연결판(10)들을 가지며 그 일측 베이스판(20)과 대향되는 위치의 교각 상부 폭방향의 타측에 놓여지는 타측 베이스판(30)과,The other base plate 30 having horizontal connecting plates 10 integrally connected in a shape corresponding to the one side base plate 20 and placed on the other side of the piercing upper width direction at a position opposite to the one base plate 20. )and,

상기 일측 및 타측 베이스판(20, 30) 각각의 외측 코너부에 배치 고정되어지며 그 일측 및 타측 베이스판(20, 30) 들의 외측에 각기 수평하게 돌출되는 받침판체(40)를 가지는 한쌍의 받침철물(50)로써 구성된다.A pair of supports having a base plate 40 is fixed to the outer corner of each of the one side and the other base plate 20, 30 and protrudes horizontally on the outside of the one side and the other base plate (20, 30), respectively. It consists of the hardware 50.

상기에서 베이스판(20, 30)은 도 8b와 같이 교각축과 일직선 방향으로 절개한 상태에서 각각 제작후 설치 지점에서 조립하여 완성할 수 있고, 또는 도 8c와 같이 교각축과 직각 방향으로 절개한 상태에서 각각 제작후 설치 지점에서 조립하여 완성할 수 있다.In the above base plate 20, 30 can be completed by assembling at the installation point after fabrication in the state cut in a straight line with the pier shaft as shown in Figure 8b, or cut in a direction perpendicular to the pier shaft as shown in Figure 8c It can be completed by assembling at the installation point after each manufacturing in the state.

본 발명의 슬라브교 슬라브 설치 공정에서는 사이드에서 조립할 수 있는 공간이 확보되지 않기 때문에, 교각축과 일직선 방향으로 절개한 상태에서 받침장치를 제작하여 교각의 상부에 위치시킨후 교각의 전면부와 후면부에서 조립하여 완성한다.In the slab bridge slab installation process of the present invention, since the space to be assembled on the side is not secured, the support device is manufactured in the state of cutting in the direction of the pier shaft and placed in the upper part of the pier, and then at the front and rear portions of the pier. Assemble and complete.

그리고, 교대부(200)에는 한쌍의 받침장치를 설치할 수 없기 때문에 도 9와 같은 형태로 이루어진 일개의 받침판체(40)를 가지는 잭 받침장치(300a)를 설치하게 되는바, 교대(200)의 상부면에 일개의 받침판체(40)를 갖는 조립식 잭 받침장치(300a)를 위치시키고 교대(200)의 상부면과 볼팅하여 결합시키도록 한다.Since the pair of supporting devices cannot be installed in the shifting part 200, the jack supporting device 300a having one supporting plate body 40 having the same shape as that of FIG. 9 is installed. The prefabricated jack support device 300a having one support plate body 40 on the upper surface is bolted and coupled to the upper surface of the shift 200.

도 3은 상기와 같이 조립식 잭 받침방치(300, 300a)의 조립이 완료된 후 잭 받침장치(300, 300a)의 상부에 유압 잭(110)을 설치하고, 상기 유압 잭(110) 상부에 크로스 빔(120)을 설치하며, 상기 크로스빔(120) 상부에 거푸집 지지대(130)가 설치됨을 보여주고 있다.3, after the assembly of the prefabricated jack support units 300 and 300a is completed as described above, the hydraulic jack 110 is installed on the jack support devices 300 and 300a, and the cross beam is provided on the hydraulic jack 110. 120 is installed, and shows that the formwork support 130 is installed on the crossbeam 120.

상기에서 크로스빔(120)은 거푸집 지지대(130)를 지지하며, 동시에 상기 크로스빔(120)은 인상용 유압잭(110)의 압력을 받아 상승되어 거푸집 지지대(130)의 높이가 일정해지도록 하는 역할을 한다.The cross beam 120 supports the form support 130, and at the same time the cross beam 120 is raised by the pressure of the hydraulic jack 110 for raising the role of the form support 130 to be constant. Do it.

상기와 같이 조립식 잭 받침장치(300, 300a)와 인상용 유압잭(110)과 크로스빔(120)과 거푸집 지지대(130)가 완성되면 도 10과 같은 형태가 된다.When the prefabricated jack support device 300, 300a, the lifting hydraulic jack 110, the crossbeam 120 and the form support 130 as described above is completed as shown in FIG.

이후, 도 4와 같은 거푸집(140)을 거푸집 지지대(130) 상부에 올려놓고, 도 5와 같이 철근배근 및 콘크리트 타설공정을 하여 슬래브(150)를 가설하는 작업을 완료하게 된다.Subsequently, the formwork 140 as shown in FIG. 4 is placed on the formwork support 130, and as shown in FIG. 5, the reinforcement and concrete pouring process is completed to install the slab 150.

상기와 같이 슬래브(150)의 가설이 완료되면 도 7에 도시한 바와같이, 조립식 잭 받침장치(300, 300a)를 철거하는 작업에 들어가게 되는바, 철거 순서는 조립식 잭 받침장치(300, 300a)로 부터 직각 돌출되어 고정되는 받침철물(50)과 받침판체(40)를 조립식 잭 받침장치(300, 300a)로 부터 분리하여 떼어 내고 이어 거푸집 지지대(130)를 탈거하게 된다.As described above, when the construction of the slab 150 is completed as described above, as shown in FIG. 7, the prefabricated jack support devices 300 and 300a are removed from the bar, and the removal order is the prefabricated jack support devices 300 and 300a. Detach the support hardware 50 and the support plate body 40 is fixed to protrude at right angles from the prefabricated jack support device (300, 300a) and then remove the formwork support (130).

이때 상기 거푸집 지지대(130)의 탈거는 도 6에 도시한 바와같이, 슬래브(150) 상부에 인장잭(160)을 설치하고 상기 인장잭(160)으로 부터 슬래브(150)의 하수구멍(도시하지 않음)을 관통하는 와이어(170)를 이용하여 거푸집 지지대(130)를 일정한 높이에 고정시켜 슬래브 가설상태 점검 및 작업대로 활용할 수 있다.At this time, removal of the formwork support 130, as shown in Figure 6, the tension jack 160 is installed on the upper slab 150 and the sewage hole of the slab 150 from the tension jack 160 (not shown) By using the wire 170 penetrating through) to fix the formwork support 130 to a certain height can be utilized to check the slab construction status and workbench.

상기와 같이 거푸집 지지대(130)를 이용하는 경우는 교량이 비교적 높은 경우에 이용하며, 높이가 낮은 교량은 도 7과 같이 잭 받침장치(300, 300a)를 탈거하면서 거푸집 지지대(130)를 곧바로 탈거하면 된다.When using the formwork support 130 as described above is used when the bridge is relatively high, the low bridge is to remove the formwork support 130 immediately while removing the jack support device (300, 300a) as shown in FIG. do.

한편, 상기와 같은 슬래브교는 교좌장치(1)를 설치후 슬래브(150)가 타설되기 때문에 조립식 잭 받침장치(300)를 교각위에 올려놓고 조립이 가능하나, 라멘교는 교좌장치를 별도로 설치하지 않고 교각에 슬래브를 타설하기 때문에 기존의 동바리를 적용하지 않는 상태에서 라멘교의 슬래브를 타설하기 위해서는 다른 방법이 적용되어야 한다.On the other hand, the slab bridge as described above can be assembled by mounting the prefabricated jack support device 300 on the pier because the slab 150 is poured after installing the bridge device (1), but the ramen bridge does not install the bridge device separately Since the slab is cast on the pier, other methods should be applied to lay the slab of the Ramen bridge without applying the existing club.

이를 위해 본 발명에서는 교각이나 교대를 가설시 상부면에 앙카 볼트(240)를 내설하고, 상기 앙카 볼트에 수직 연결판을 고정하고, 상기 수직연결판에 버팀편 및 보강빔를 설치하는 잭 받침 장치를 고정하게 된다.To this end, in the present invention, when installing a piers or shifts, anchor bolt 240 is installed on the upper surface, and a vertical connection plate is fixed to the anchor bolt, and a jack support device for installing a support piece and a reinforcing beam on the vertical connection plate. It will be fixed.

즉, 라멘교에 사용되어지는 잭 받침 장치(300b)는 도 11a와 같이, 수직 연결판(210)과, 버팀편(220) 및 보강빔(230)으로 이루어지며, 상기와 같이 잭받침장치(300b)의 설치가 완료되면, 그 위에 거푸집 지지대(130)를 설치하고, 상기 거푸집 지지대(130) 상부에 슬래브를 타설하게 된다.That is, the jack support device 300b to be used in the ramen bridge is made of a vertical connecting plate 210, the support piece 220 and the reinforcing beam 230, as shown in Figure 11a, the jack support device ( When the installation of 300b) is completed, the formwork support 130 is installed thereon, and the slab is poured on the formwork support 130.

상기와 같은 라멘교의 슬래브 타설을 마치게 되면 도 11b와 같은 형태이며, 이후 철거 공정에 있어서는 슬래브교와 동일하다.When the slab casting of the ramen bridge as described above is finished as shown in Figure 11b, in the subsequent demolition process is the same as the slab bridge.

한편, 교량의 시공 형태에서 크게 슬래브교와 거더교로 구분할 수 있으며, 상기에서는 슬래브교에 있어서 본 발명을 적용한 형태를 나타내었는바, 이하에서는 거더교에 본 발명을 적용하여 거푸집 공사를 시행하는 것을 설명하기로 한다.On the other hand, in the construction form of the bridge can be largely divided into slab bridges and girder bridges, in the above-described form of the present invention applied to the slab bridges, the following describes the implementation of the formwork by applying the present invention to the girder bridge Shall be.

먼저, 일반적인 거더교는 도 12과 같이 스틸 플래이트(410)가 슬레브를 지지하는 판형교(400)와, 도 13과 같이 PC 빔이나 T빔(510)이 슬레브를 지지하는 PC빔교(500)와, 도 14와 같이 스틸 플래이트 박스(610)가 슬레브를 지지하는 스틸 박스교(600)로 크게 구분할 수 있는바, 상기와 같은 거더교에 있어서 거푸집 타설 공정을 위해서는 모두 별도의 브라켓(420)을 일정간격마다 설치하여야 하는 불편함이 있었다.First, the general girder bridge is a plate-shaped bridge 400 in which the steel plate 410 supports the slab as shown in FIG. 12, and the PC beam bridge 500 in which the PC beam or the T-beam 510 supports the slab as shown in FIG. 13. And, as shown in Figure 14, the steel plate box 610 can be largely divided into a steel box bridge 600 supporting the slab, in the girder bridge as described above, all the separate brackets 420 for the formwork placing process There was an inconvenience to be installed at regular intervals.

즉, 판형교(400)는 도 12에서와 같이 스틸 플레이트(410)의 양 사이드에 브라켓(420)을 설치하고 상기 브라켓(420)과 스틸 플레이트(410) 상부면으로 거푸집을 설치한후 콘크리트를 양생하여 슬래브(430)를 완성하였고, 도 13에 도시한 바와같이, PC빔교(500) 역시 지지용 빔(510)의 양 사이드에 브라켓(520)을 설치하고 상기 브라켓(520)과 지지용 빔(510) 상부면으로 거푸집을 설치한후 콘크리트를 양생하여 슬래브(530)를 완성하였으며, 도 14와 같이 스틸 박스교(600) 역시 스틸 박스(610) 양 사이드에 브라켓(620)을 설치하고 상기 브라켓(620)과 스틸박스(610) 상부면으로 거푸집을 설치한후 콘크리트를 양생하여 슬래브(630)를 완성하였다.That is, the plate-shaped bridge 400 is installed on both sides of the steel plate 410 as shown in Figure 12 and the formwork to the upper surface of the bracket 420 and the steel plate 410 after installing the concrete After curing the slab 430 was completed, as shown in Figure 13, the PC beam bridge 500 also installed brackets 520 on both sides of the support beam 510, the bracket 520 and the support beam (510) After installing the formwork to the upper surface and curing the slab 530 was completed, the steel box bridge 600 also installed brackets 620 on both sides of the steel box 610 as shown in FIG. After installing the formwork to the bracket 620 and the upper surface of the steel box 610, the concrete was cured to complete the slab 630.

따라서, 상기와 같은 거더교의 슬래브를 완성하기 위해서는 일정간격을 두고 브라켓(420, 520, 620)을 설치해야 하므로 슬래브 공사에 많은 시간이 필요할 뿐만 아니라, 브라켓(420, 520, 620)을 사람 손으로 일일이 설치해야 하므로, 작업 인부의 안전사고가 매우 빈번하게 일어나는 문제점이 있었다.Therefore, in order to complete the slab of the girder bridge as described above, since the brackets 420, 520, and 620 should be installed at a predetermined interval, not only a lot of time is required for the slab construction, but also the brackets 420, 520, and 620 with human hands. Since it must be installed one by one, there was a problem that accidents occur very frequently of workers.

본 발명은 상기와 같은 문제를 해결코자 하는 것으로, 거푸집 지지수단으로써 브라켓을 설치하는 대신에, 교량 축선상으로 거푸집 지지대를 설치하여 거푸집을 지지토록 하였으며, 상기 거푸집 지지대는 교각이나 교대에 설치되어지는 조립식 브라켓과 인상용 잭을 이용토록 하였다.The present invention is to solve the above problems, instead of installing the bracket as the formwork support means to install the formwork support on the bridge axis to support the formwork, the formwork support is installed on the piers or shifts Prefabricated brackets and impression jacks were used.

즉, 본 발명의 조립식 브라켓과 인상용 잭을 이용한 슬래브 설치 공정은, 다리를 건설할 공간에 일정한 간격을 두고 교각 및 교대를 가설하는 교각 및 교대 가설 공정과;That is, the slab installation process using the prefabricated bracket and the impression jack of the present invention, the bridge and alternating hypothesis step of the construction of the bridge and alternating at regular intervals in the space to build the bridge;

상기 교각 및 교대의 상부에 인상용 잭 받침장치를 설치하는 잭 받침 장치 설치 공정과;A jack support device installation step of installing an impression jack support device on an upper portion of the pier and the shift;

상기 잭 받침장치의 받침판체에 잭 및 크로스 빔을 올려놓고, 그 상부에 거푸집 지지대를 설치하되 빔 사이에서 빔과 같은 높이의 거푸집 지지대를 설치하는 거푸집 지지대 설치 공정과;Placing the jack and the cross beam on the support plate body of the jack support device, and installing the formwork support on the upper part of the formwork supporter for installing the formwork support with the same height between the beams;

상기 거푸집 지지대 상부에 거푸집을 설치하는 거푸집 설치 공정과;Formwork installation process for installing the formwork on the formwork support;

상기 거푸집을 이용하여 슬래브를 가설하는 슬래브 가설 공정과;A slab construction process of installing a slab using the formwork;

상기 공정에서 슬래브 가설이 완성되면 잭과 크로스빔과 잭 받침장치 및 거푸집 지지대를 철거하는 철거 공정으로 이루어진다.When the slab hypothesis is completed in the above process, the demolition process consists of removing the jack, the cross beam, the jack support device and the formwork support.

상기와 같이 이루어지는 본 발명의 거더교 슬래브 설치 공법은, 거더교의 모든 형식에 이용될 수 있는바, 일정한 형태의 지지빔으로써 슬래브를 지지하도록 하는 거더교에서 슬래브 타설을 위한 거푸집 지지용 브라켓을 대신하여 H형강이나 'ㄷ'자 형강을 교량 축 방향으로 설치하여 지푸집을 지지토록 함으로써 가능하다.Girder bridge slab installation method of the present invention made as described above, can be used in all types of girder bridge bar H-shaped steel in place of the formwork support bracket for slab casting in the girder bridge to support the slab with a support beam of a certain form In addition, it is possible to install the 'c' shaped steel in the axial direction of the bridge to support the die.

즉, PC빔교(500)는 도 15a 및 도 15b와 같이 지지용 빔(510) 양 사이드에 거푸집 지지대(130)가 설치되어 있으며, 상기 거푸집 지지대(130)의 하단에는 크로스 빔(120)이 위치하여 지지하고 상기 크로스빔 하단에는 유압잭(110)이 설치되어 크로스빔(120)을 지지하며, 상기 유압잭(110)은 조립식 잭 받침장치(300) 상부에 위치하고, 상기 조립식 잭 받침장치(300)는 교량에 고정 지지되어 거푸집 지지대(130)와 슬래브(530)의 무게를 교각으로 집중시키고 있다.That is, the PC beam bridge 500 is provided with formwork support 130 on both sides of the support beam 510, as shown in Figure 15a and 15b, the cross beam 120 is located at the bottom of the formwork support 130 Hydraulic jack 110 is installed at the bottom of the crossbeam to support the crossbeam 120, the hydraulic jack 110 is located above the prefabricated jack support device 300, the prefabricated jack support device 300 It is fixed to the bridge and concentrates the weight of the formwork support 130 and the slab 530 to the piers.

여기서 크로스 빔(120)과 유압잭(110) 및 조립식 잭 받침장치(300)는 도 15a와 같이 지지용 빔(510)의 하단에 설치할 수가 있고 또한 도 15c와 같이 지지용 빔(510) 사이에 설치할 수도 있다.Here, the cross beam 120, the hydraulic jack 110, and the assembled jack support device 300 may be installed at the lower end of the support beam 510 as shown in FIG. 15A, and may be installed between the support beam 510 as shown in FIG. 15C. It may be.

거더교의 한 종류인 판형교(400) 역시 도 16에 도시한 바와같이, 슬래브(430)를 지지토록 제작되는 스틸 플레이트(410) 양 사이드에 거푸집 지지대(130)가 설치되어 있으며, 상기 거푸집 지지대(130)의 하단에는 크로스 빔(120)이 위치하여 지지하고 상기 크로스빔(120) 하단에는 유압잭(110)이 설치되어 크로스 빔(120)을 지지하며, 상기 유압잭(110)은 조립식 잭 받침장치(300) 상부에 위치하고, 상기 조립식 잭 받침장치(300)는 교량에 고정 지지되어 거푸집 지지대(130)와 슬래브(430)의 무게를 교각으로 집중시키고 있다.As shown in FIG. 16, the plate-shaped bridge 400, which is a type of girder bridge, is provided with formwork supports 130 on both sides of the steel plate 410, which is manufactured to support the slab 430, and the formwork support ( A cross beam 120 is positioned and supported at a lower end of the 130, and a hydraulic jack 110 is installed at a lower end of the cross beam 120 to support the cross beam 120, and the hydraulic jack 110 is a prefabricated jack support device ( Located at the top 300, the prefabricated jack support device 300 is fixedly supported on the bridge to concentrate the weight of the formwork support 130 and the slab 430 to the piers.

또한 거더교의 다른 한 종류인 스틸 박스교(600) 역시 도 17에 도시한 바와같이, 슬래브(630)를 지지토록 제작되는 스틸 박스(620) 양 사이드에 거푸집 지지대(130)가 설치되어 있으며, 상기 거푸집 지지대(130)의 하단에는 크로스 빔(120)이 위치하여 지지하고 상기 크로스빔(120) 하단에는 유압잭(110)이 설치되어 크로스 빔(120)을 지지하며, 상기 유압잭(110)은 조립식 잭 받침장치(300) 상부에 위치하고, 상기 조립식 잭 받침장치(300)는 교량에 고정 지지되어 거푸집 지지대(130)와 슬래브(630)의 무게를 교각으로 집중시키고 있다.In addition, as shown in FIG. 17, the steel box bridge 600, which is another type of girder bridge, is provided with formwork supports 130 on both sides of the steel box 620 manufactured to support the slab 630. A cross beam 120 is positioned and supported at the bottom of the form support 130, and a hydraulic jack 110 is installed at the bottom of the cross beam 120 to support the cross beam 120, and the hydraulic jack 110 is a prefabricated jack. Located on the upper portion of the support device 300, the prefabricated jack support device 300 is fixed to the bridge to concentrate the weight of the formwork support 130 and the slab 630 to the piers.

상기에서 거더교 설치 공정에 이용되는 조립식 잭 받침장치의 구성은 슬라브교에 이용되는 조립식 브라켓의 구성과 동일하다.The configuration of the prefabricated jack support device used in the girder bridge installation process is the same as the configuration of the prefabricated bracket used for the slab bridge.

결국, 본 발명은 거더교 설치 공정에 있어서, 종래의 브라켓 설치 공정을 생략할 수 있고, 그 대신에 조립식 잭 받침장치(300)와 인상용 유압잭(110) 상부에 거푸집 지지대(130)를 설치토록 함으로써 가능하며, 이에 따라 일정간격마다 브라켓을 모두 설치해야 하는 불편함을 없앨 수 있고, 공기를 단축하며 작업자의 안전에 보다 만전을 기할 수 있게 된다.As a result, the present invention can omit the conventional bracket installation step in the girder bridge installation step, and instead install the formwork support 130 on the prefabricated jack support device 300 and the lifting hydraulic jack 110 instead. It is possible, thereby eliminating the inconvenience of having to install all the brackets at regular intervals, it is possible to shorten the air and more fully ensure the safety of the operator.

또한, 철거 과정에 있어서도 종래에는 지지용 빔 사이에 설치되는 브라켓 철거를 위해서 일일이 작업 인부가 위험을 무릅쓰고 작업을 진행해야 하나, 본 발명을 이용하게 되면 중장비를 이용하여 철거작업을 진행하므로 신속한 철거 작업이 가능하고, 동시에 작업인부의 안전사고를 미연에 방지할 수 있는 부수적인 효과를노릴 수 있다.In addition, even in the process of demolition, in order to remove the brackets installed between the support beams in the prior art, the worker must work at risk, but the demolition work is carried out using heavy equipment. It is possible to work, and at the same time, it can have side effects that can prevent the accident of workers.

따라서, 본 발명을 이용하게 되면 슬래브교나 라멘교 및 거더교의 슬래브를 설치하는데 있어서, 조립식 받침장치와 인상용 잭 및 거푸집 지지수단으로써 거푸집 설치공정을 뒷받침 하기 때문에 기존의 동바리를 전혀 이용하지 않고도 슬래브 타설 공정을 가능토록 하여 교량 건설 작업이 매우 용이하며, 철거 작업에 있어서도 매우 유리하다.Therefore, when using the present invention, in installing the slab of the slab bridge, ramen bridge and girder bridge, slab casting without using the existing copper bar at all because it supports the formwork installation process as a prefabricated support device, impression jack and formwork support means. The construction of the bridge makes it very easy to build bridges and is very advantageous in demolition work.

Claims (9)

다리를 건설할 공간에 일정한 간격을 두고 교각 및 교대를 가설하는 교각 및 교대 가설 공정과;A piers and shift construction process for constructing bridges and shifts at regular intervals in the space where a bridge is to be constructed; 상기 교각 및 교대의 상부에 인상용 조립식 잭 받침장치를 설치하는 조립식 잭 받침 설치 공정과;A prefabricated jack support installation process of installing a prefabricated jack support device for raising on the pier and the shift; 상기 조립식 잭 받침장치의 받침판체에 잭 및 크로스 빔을 올려놓고 그 상부에 거푸집 지지대를 설치하는 거푸집 지지대 설치 공정과;A mold support installation step of placing the jack and the cross beam on the support plate body of the assembled jack support device and installing the form support on the upper portion thereof; 상기 거푸집 지지대 상부에 거푸집을 설치하는 거푸집 설치 공정과;Formwork installation process for installing the formwork on the formwork support; 상기 거푸집을 이용하여 슬래브를 가설하는 슬래브 가설 공정과;A slab construction process of installing a slab using the formwork; 상기 공정에서 슬래브 가설이 완성되면 잭과 크로스빔과 조립식 잭 받침장치 및 거푸집 지지대를 철거하는 철거 공정으로 이루어지는 것을 특징으로 하는 조립식 받침장치를 이용한 슬라브교의 슬라브 설치 방법.The slab installation method of the slab bridge using the prefabricated support device characterized in that when the slab hypothesis is completed in the process comprises a demolition process of removing the jack and the cross beam and the prefabricated jack support device and the formwork support. 다리를 건설할 공간에 일정한 간격을 두고 교각 및 교대를 가설하는 교각 및 교대 가설 공정과;A piers and shift construction process for constructing bridges and shifts at regular intervals in the space where a bridge is to be constructed; 미리 제작된 교량용 빔을 상기 교각 및 교대에 축방향으로 설치하는 교량용 빔 설치 공정과;A bridge beam installation step of axially installing prefabricated bridge beams in the bridges and bridges; 상기 교각 및 교대의 상부에 인상용 조립식 잭 받침장치를 설치하는 조립식잭 받침 장치 설치 공정과;A prefabricated jack support device installation process of installing a prefabricated jack support device for the impression on the pier and the shift; 상기 조립식 잭 받침장치의 받침판체에 잭 및 크로스 빔을 올려놓고, 그 상부에 거푸집 지지대를 설치하되, 교량용빔 사이에서 빔과 같은 높이의 거푸집 지지대를 설치하는 거푸집 지지대 설치 공정과;Placing the jack and the cross beam on the support plate body of the prefabricated jack support device, and installing the formwork support on the upper portion, and installing the formwork support having the same height as the beam between the bridge beams; 상기 거푸집 지지대 상부에 거푸집을 설치하는 거푸집 설치 공정과;Formwork installation process for installing the formwork on the formwork support; 상기 거푸집을 이용하여 슬래브를 가설하는 슬래브 가설 공정과;A slab construction process of installing a slab using the formwork; 상기 공정에서 슬래브 가설이 완성되면 잭과 크로스빔과 조립식 잭 받침장치 및 거푸집 지지대를 철거하는 철거 공정으로 이루어지는 것을 특징으로 하는 조립식 받침장치를 이용한 거더교의 슬라브 설치 방법.The slab installation method of the girder bridge using the prefabricated support device, characterized in that the slab construction is completed when the jack and the cross beam and the prefabricated jack support device and the formwork support to demolish. 다리를 건설할 공간에 일정한 간격을 두고 교각 및 교대를 가설하되 앙카바를 매립한 상태에서 가설하는 앙카바와 교각 및 교대 가설 공정과;An anchor and pier and alternating process for constructing bridges and shifts at regular intervals in the space for constructing bridges, while laying the anchors; 상기 앙카바에 수직 연결판을 고정하고, 상기 수직연결판에 버팀편 및 보강빔를 설치하는 조립식 잭 받침 장치 설치 공정과;A prefabricated jack support device installation process of fixing a vertical connecting plate to the anchor bar and installing a support piece and a reinforcing beam on the vertical connecting plate; 상기 조립식 잭 받침장치의 받침판체에 잭 및 크로스 빔을 올려놓고, 그 상부에 거푸집 지지대를 설치하는 거푸집 지지대 설치 공정과;A mold support installation step of placing a jack and a cross beam on the support plate body of the assembled jack support device, and installing a form support on the upper portion thereof; 상기 거푸집 지지대 상부에 거푸집을 설치하는 거푸집 설치 공정과;Formwork installation process for installing the formwork on the formwork support; 상기 거푸집을 이용하여 슬래브를 가설하는 슬래브 가설 공정과;A slab construction process of installing a slab using the formwork; 상기 공정에서 슬래브 가설이 완성되면 잭과 크로스빔과 조립식 잭 받침장치및 거푸집 지지대를 철거하는 철거 공정으로 이루어지는 것을 특징으로 하는 조립식 받침장치를 이용한 라멘교의 슬라브 설치 방법.When the slab hypothesis is completed in the above step, the slab installation method of the ramen bridge using a prefabricated support device, characterized in that the demolition process of removing the jack and the cross beam and the prefabricated jack support device and formwork support. 제 1 항 또는 제 2 항에 있어서,The method according to claim 1 or 2, 교각 상부에 위치한 각 교좌장치들을 중심으로 일측 및 타측 베이스판을 거치시키고 조립 연결하여서 교각의 축방향으로 받침장치를 설치하고, 받침장치 양측의 받침철물들 각각의 받침판체 상에 인상용 잭을 대향되게 안치시키며, 안치된 인상용 잭들을 작동시켜 거푸집 지지대를 떠받쳐 거푸집 타설 공정을 수행하는 것을 특징으로 하는 조립식 받침장치를 이용한 슬라브 설치 방법.Mounting and assembling one side and the other base plate around each bridge device located on the top of the bridge and installing the support device in the axial direction of the bridge, and facing the jack on the support plate of each of the supporting hardware on both sides of the support device The slab installation method using a prefabricated support device, characterized in that for holding the formwork by holding the formwork by placing the jacks to raise the impression. 제 1 항에 있어서,The method of claim 1, 상기 조립식 받침장치는 교량 축방향으로 2등분되어 교량 상부에 고정후 정면 및 후면에서 조립되어지는 것을 특징으로 하는 조립식 받침장치를 이용한 슬라브교 슬라브 설치 방법.The prefabricated support device is a slab bridge slab installation method using a prefabricated support device, characterized in that the assembly in front and rear after being fixed in the bridge axially divided into two upper portions. 제 2 항에 있어서,The method of claim 2, 상기 조립식 받침장치는 교량 축방향으로 2등분 하거나, 교량 축 직각방향으로 2등분 한 것중 어느 하나를 선택하고, 교량 상부에 조립식 받침장치를 고정후 정면과 후면 또는 중간지점에서 조립되어지는 것을 특징으로 하는 조립식 받침장치를 이용한 거더교 슬라브 설치 방법.The prefabricated support device is any one of the two divided in the axial direction of the bridge, or divided into two in the direction perpendicular to the bridge axis, and after fixing the prefabricated support device on the top of the bridge, characterized in that it is assembled at the front and rear or intermediate points Girder bridge slab installation method using a prefabricated support device. 제 1 항 또는 제 2 항에 있어서,The method according to claim 1 or 2, 상기 철거 공정은, 조립식 잭 받침장치의 받침판체를 철거후 슬래브 상부에 인장 잭을 설치하고 슬라브에 미리 제작되어지는 배수구멍을 통해 와이어로써 거푸집 지지대를 연결하며, 거푸집 지지대를 일정길이로 하강한 상태에서 슬래브 가설상태 점검 및 작업대로 활용하는 공정을 더 포함하는 것을 특징으로 하는 조립식 받침장치 철거 방법.In the dismantling process, after removing the supporting plate body of the prefabricated jack support device, the tension jack is installed on the upper part of the slab, and the form support is connected by wire through a drain hole that is prefabricated in the slab, and the form support is lowered to a certain length. Method for dismantling the prefabricated support device, characterized in that it further comprises a step of utilizing the slab construction status and the workbench at work. 제 1 항 또는 제 2 항에 있어서,The method according to claim 1 or 2, 상기 거푸집 지지대는 H형강이나 'ㄷ'자 형강를 포함한 지지구조물 중에서 선택된 어느 하나인 것을 특징으로 하는 조립식 받침장치를 이용한 슬래브 설치방법.Wherein the formwork support is a slab installation method using a prefabricated support device, characterized in that any one selected from the support structure, including H-shaped steel or '' '. 제 3 항에 있어서,The method of claim 3, wherein 받침 장치는 수직 연결판과, 버팀편 및 보강빔으로 이루어지며, 상기와 같이 조립식 잭 받침장치의 설치가 완료되면, 그 위에 거푸집 지지대를 설치하고, 상기 거푸집 지지대 상부에 슬래브를 타설공정을 수행하는 것을 특징으로 하는 조립식 받침장치를 이용한 라멘교의 슬라브 설치 방법.The supporting device is composed of a vertical connecting plate, a bracing piece and a reinforcing beam, and when the installation of the prefabricated jack supporting device is completed as described above, a formwork support is installed thereon, and a slab is placed on the formwork support. Slave installation method of the ramen bridge using the prefabricated support device characterized in that.
KR1020000045837A 2000-08-08 2000-08-08 A Bridge Establishing Method Using Fabricated Jack Support Unit KR20020012670A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020000045837A KR20020012670A (en) 2000-08-08 2000-08-08 A Bridge Establishing Method Using Fabricated Jack Support Unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020000045837A KR20020012670A (en) 2000-08-08 2000-08-08 A Bridge Establishing Method Using Fabricated Jack Support Unit

Publications (1)

Publication Number Publication Date
KR20020012670A true KR20020012670A (en) 2002-02-20

Family

ID=19682217

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020000045837A KR20020012670A (en) 2000-08-08 2000-08-08 A Bridge Establishing Method Using Fabricated Jack Support Unit

Country Status (1)

Country Link
KR (1) KR20020012670A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100454405B1 (en) * 2002-07-05 2004-10-26 김정현 Method for changing steel bridge of supporting rail into concreat bridge
KR101025019B1 (en) * 2008-11-27 2011-03-25 삼표건설 주식회사 Sheet pile composition rigid-frame bridge using temporary installation vent and constructing method thereof
KR101136363B1 (en) * 2010-06-09 2012-04-18 다일산업주식회사 Frame for Rehmen Structure
KR20210089382A (en) * 2020-01-08 2021-07-16 주식회사 이오닉스 A temporary bridge dismantlement system and Method for dismantlement

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6131501A (en) * 1984-07-20 1986-02-14 三菱重工業株式会社 Construction of track beam
JPS62185905A (en) * 1986-02-07 1987-08-14 岡部株式会社 Moving type mold frame construction method of slab of high bridge
JPS62189208A (en) * 1986-02-14 1987-08-19 株式会社熊谷組 Method for moving timbering main material and bracket of moving timbering
JPH10266134A (en) * 1997-03-25 1998-10-06 Oriental Constr Co Ltd Construction method of bridge utilizing stretched cable
KR19990001958A (en) * 1997-06-18 1999-01-15 김정현 Jack restraint device for raising upper structure of bridge and repairing method using the same
KR19990001957A (en) * 1997-06-18 1999-01-15 김정현 Jack restraint device to raise superstructure of bridge

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6131501A (en) * 1984-07-20 1986-02-14 三菱重工業株式会社 Construction of track beam
JPS62185905A (en) * 1986-02-07 1987-08-14 岡部株式会社 Moving type mold frame construction method of slab of high bridge
JPS62189208A (en) * 1986-02-14 1987-08-19 株式会社熊谷組 Method for moving timbering main material and bracket of moving timbering
JPH10266134A (en) * 1997-03-25 1998-10-06 Oriental Constr Co Ltd Construction method of bridge utilizing stretched cable
KR19990001958A (en) * 1997-06-18 1999-01-15 김정현 Jack restraint device for raising upper structure of bridge and repairing method using the same
KR19990001957A (en) * 1997-06-18 1999-01-15 김정현 Jack restraint device to raise superstructure of bridge

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100454405B1 (en) * 2002-07-05 2004-10-26 김정현 Method for changing steel bridge of supporting rail into concreat bridge
KR101025019B1 (en) * 2008-11-27 2011-03-25 삼표건설 주식회사 Sheet pile composition rigid-frame bridge using temporary installation vent and constructing method thereof
KR101136363B1 (en) * 2010-06-09 2012-04-18 다일산업주식회사 Frame for Rehmen Structure
KR20210089382A (en) * 2020-01-08 2021-07-16 주식회사 이오닉스 A temporary bridge dismantlement system and Method for dismantlement

Similar Documents

Publication Publication Date Title
KR100958014B1 (en) Construction method of steel composite girder bridge
KR100837608B1 (en) J.K Bracket Method
KR100949601B1 (en) Method for broadening width of existing bridge without Temporary road
CN105735139A (en) Supporting system for construction of cast-in-situ box beam in overpass and construction method of box beam
JPH09310492A (en) Self elevating type form device and elevating method thereof
JP5015049B2 (en) Pier extension method
KR20020012670A (en) A Bridge Establishing Method Using Fabricated Jack Support Unit
KR20080099061A (en) Psc beam for connection steel width step of psc bridges
JP4477467B2 (en) Bridge structure and its replacement method
JP2980567B2 (en) How to replace the bearing device
KR100324704B1 (en) Formwork method using no prop for the floor concrete of the bridge
JP2018178588A (en) Bridge construction method
KR100469638B1 (en) Support construction for slab of prestressed concrete beam of bridge
JPH05280012A (en) Movable formwork process and device used therefor
KR910007424B1 (en) Method for construction t - beam on the bridge
JPH11222812A (en) Changing method of height of structure
KR20010097315A (en) Pier scaffolding and the pier construction method for using pier scaffolding
KR910007423B1 (en) Method for construction p.c - beam on the bridge
JP2000129633A (en) Erection method for bridge floor slab
KR200402793Y1 (en) Rail and roller Type device for hanging scaffold of bridge slab
KR200253546Y1 (en) A short pillar propping up a veranda floor equipment
KR102381969B1 (en) Formwork for bridge piers and construction method of piers using the same
CN114293769B (en) Spanning type bent frame and mounting method thereof
CN219754221U (en) Can have enough to meet need and use and enclose fender basis
KR960011365B1 (en) Construction method of steel-frame/steel concrete beam

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E601 Decision to refuse application