JPH11222812A - Changing method of height of structure - Google Patents

Changing method of height of structure

Info

Publication number
JPH11222812A
JPH11222812A JP10038164A JP3816498A JPH11222812A JP H11222812 A JPH11222812 A JP H11222812A JP 10038164 A JP10038164 A JP 10038164A JP 3816498 A JP3816498 A JP 3816498A JP H11222812 A JPH11222812 A JP H11222812A
Authority
JP
Japan
Prior art keywords
concrete
height
easily breakable
changing
reinforcement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP10038164A
Other languages
Japanese (ja)
Other versions
JP3472952B2 (en
Inventor
Tadayoshi Ishibashi
忠良 石橋
Shinichiro Nozawa
伸一郎 野澤
Toshiyuki Yamauchi
俊幸 山内
Masaaki Ooyato
理明 大屋戸
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
East Japan Railway Co
Original Assignee
East Japan Railway Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by East Japan Railway Co filed Critical East Japan Railway Co
Priority to JP03816498A priority Critical patent/JP3472952B2/en
Publication of JPH11222812A publication Critical patent/JPH11222812A/en
Application granted granted Critical
Publication of JP3472952B2 publication Critical patent/JP3472952B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

PROBLEM TO BE SOLVED: To easily change the height of a structure by demolishing an easily breakable part of the vertical concrete part of the structure and vertically connecting the reinforcing members in the inside of the concrete body and placing concrete in the periphery of the connection part of the reinforcing members. SOLUTION: An easily breakable part 2 constituted of low strength concrete is formed at a part of a vertical concrete member 1 such as a column of an elevated bridge, a pier of a bridge, or a column of a concrete building. When changing the height of a structure, after the structure upper than the easily breakable part 2 has been temporarily supported by a lifter 4, the low strength concrete of the easily breakable part 2 is chipped off and the height of structure is changed by extension or contraction of the lifter 4. Further, when the structure is raised up, additional reinforcing members are added and the upper and lower reinforcing members are integrally unified and then, the connection part of the reinforcing members are surrounded by forms to place aditional concrete in the forms. In this way, the height of a structure can be easily changed.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、構造物の高さ変更
方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for changing the height of a structure.

【0002】[0002]

【従来の技術】例えば鉄道の高架化を行う場合に、一時
期を一定の高さで車両を通過させ、その後の関連施設の
構築の進展に伴って高さを変更するような要求が生じ
る。このような既設の構造物の高さを変更するために、
従来は仮設の構造物を構築して使用し、変更時期には仮
設構造物を完全に撤去してその跡に新たな構造物を構築
するような方法を採用していた。
2. Description of the Related Art For example, when a railway is elevated, there is a demand that a vehicle be passed at a certain height for a period of time, and that the height be changed as the construction of related facilities progresses thereafter. In order to change the height of such existing structures,
Conventionally, a temporary structure has been constructed and used, and at the time of change, a method has been adopted in which the temporary structure is completely removed and a new structure is constructed in its place.

【0003】[0003]

【本発明が解決しようとする課題】上記のような方法は
高さの変更の前後でまったく別の構造物を構築する方法
である。したがって、仮設の構造物の構築と、その後の
撤去の作業が必要となり、工事費が著しく増大してしま
う。さらに仮設の構造物であって、実際の使用期間が短
い場合でも、仮設構造物を構築するだけで長い工期を必
要とし、不経済なものであった。以上のような問題は、
鉄道の高架橋の仮設だけでなく一般の土木、建築におけ
る鉄筋コンクリート構造物においても同様の問題であっ
た。
The above-mentioned method is a method of constructing a completely different structure before and after changing the height. Therefore, construction of a temporary structure and subsequent removal work are required, which significantly increases construction costs. Furthermore, even in the case of a temporary structure, even if the actual use period is short, simply constructing the temporary structure requires a long construction period, which is uneconomical. The above problems are
Similar problems were encountered not only with temporary construction of railway viaducts, but also with general civil engineering and reinforced concrete structures in buildings.

【0004】本発明は上記したような従来の問題を解決
するためになされたもので、一時期は一定の高さで構造
物を構築しておき、その後に簡易に高さを変更すること
ができる、構造物の高さ変更方法を提供することを目的
とする。
SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned conventional problems, and a structure can be constructed at a certain height for a while, and then the height can be easily changed. It is an object of the present invention to provide a method for changing the height of a structure.

【0005】[0005]

【課題を解決するための手段】上記のような目的を達成
するために、本発明の構造物の高さ変更方法は構造物の
コンクリート製鉛直部に破壊容易な部分を構成してお
き、高さを変更する時期に破壊容易部を解体し、破壊容
易部よりも上方の構造物の高さを変更した後に、コンク
リート内部の補強材を上下に連結し、その後に補強材連
結部の周囲にコンクリートを打設して行う構造物の高さ
変更方法を特徴としたものである。
In order to achieve the above object, a method of changing the height of a structure according to the present invention comprises a portion which is easily broken in a concrete vertical portion of the structure. At the time of changing the height, disassemble the easily breakable part, change the height of the structure above the easily breakable part, connect the reinforcement inside the concrete up and down, and then around the reinforcement joint It features a method of changing the height of a structure by casting concrete.

【0006】[0006]

【本発明の実施の態様】以下図面を参照しながら本発明
の構造物の高さ変更方法の実施例について説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of a method for changing the height of a structure according to the present invention will be described below with reference to the drawings.

【0007】<イ>構造物の構成。 本発明の高さ変更方法に使用する構造物は、事前に特殊
な構成を採用する。すなわち本発明の構造物には、将来
の高さ変更を予定して構造物のコンクリート製の鉛直部
1、例えば高架橋の柱部、橋梁の橋脚、あるいはコンク
リート建築物の柱、壁などの一部に、破壊容易な部分2
を構成しておく。鉛直部1以外の部分がすべてコンクリ
ート製の構造物、あるいは他の部分は鋼材などの構造物
にも採用できる。
<A> Structure of the structure. The structure used in the height changing method of the present invention adopts a special configuration in advance. That is, in the structure of the present invention, a vertical portion 1 made of concrete of the structure, for example, a pillar portion of a viaduct, a pier of a bridge, or a part of a pillar, a wall, etc. of a concrete building is planned for a future height change. And easily breakable part 2
Is configured. All parts other than the vertical part 1 can be used for structures made of concrete, or the other parts can be used for structures made of steel or the like.

【0008】<ロ>破壊容易部の構成。 破壊容易部2は、例えば低強度のコンクリートで構成す
る。また、破壊容易部2の内部の補強材が鉄筋である場
合には、その部分の鉄筋を重ね継手によって構成してお
く。あるいは、破壊容易部2として図13に示すよう
に、上下2か所に縁切り材9を水平方向に配置し、その
間には鉛直部1の他の位置と同等のコンクリートを打設
する。鉛直部1の縁切りを行う縁切り部材としては、鋼
板、紙、合成樹脂製の板、シートなどに剥離剤を塗布し
たものを利用できる。鋼板以外は穴明けが簡単であるか
ら鉄筋群の位置に合わせて開口して、水平の縁切り横断
面を構成することができる。鋼板の場合には鉄筋群の位
置に合わせて開口することもできるが、あるいは鉄筋群
の中心、その他鉄筋の位置を避けて配置しておくことも
できる。
<B> Configuration of the breakable portion. The easily breakable portion 2 is made of, for example, low-strength concrete. When the reinforcing material inside the easily breakable portion 2 is a reinforcing bar, the reinforcing bar at that portion is formed by a lap joint. Alternatively, as shown in FIG. 13, as the easily breakable portion 2, the edge cutting members 9 are horizontally arranged at two upper and lower portions, and concrete equivalent to the other position of the vertical portion 1 is poured between them. As a trimming member for trimming the vertical portion 1, a member obtained by applying a release agent to a steel plate, paper, a synthetic resin plate, a sheet, or the like can be used. Since the holes other than the steel plate are easily drilled, they can be opened in accordance with the position of the reinforcing bar group to form a horizontal marginal cross section. In the case of a steel plate, the opening can be formed in accordance with the position of the reinforcing bar group, or it can be disposed so as to avoid the center of the reinforcing bar group and other positions of the reinforcing bars.

【0009】<ハ>鋼板による包囲。 構造物を支持する橋脚などの一部を低強度のコンクリー
トで構成し、または補強材が鉄筋である場合には重ね継
手とし、あるいは縁切り材9を配置すれば、当然にコン
クリート製鉛直部1の強度がその部分で低下してしま
う。そのために破壊容易部2の周囲を鋼板3で包囲し、
閉合してコンクリートの変形を拘束する。(図3)その
結果、鉄筋の引張力の伝達に必要な鉄筋−コンクリート
間の付着力と、コンクリートの軸方向圧縮耐力を確保す
ることができる。なお、図では説明の簡単のために帯鉄
筋の記載を省略してあるが、帯鉄筋を設置しても構築は
可能である。
<C> Surrounding by a steel plate. If a part of a bridge pier or the like supporting a structure is made of low-strength concrete, or if the reinforcing material is a reinforcing bar, it is a lap joint, or if a rim material 9 is arranged, naturally the concrete vertical portion 1 can be formed. The strength is reduced at that point. Therefore, the periphery of the easily breakable part 2 is surrounded by the steel plate 3,
Close and restrain concrete deformation. (FIG. 3) As a result, it is possible to secure the adhesive force between the reinforcing bar and the concrete required for transmitting the tensile force of the reinforcing bar and the axial compressive strength of the concrete. Although illustration of the strip reinforcing bars is omitted in the figure for simplicity of description, construction is possible even if strip reinforcing bars are installed.

【0010】<ニ>破壊容易部2の解体。 高さを変更する場合には、構造物の周囲に足場などの支
持架台41を組み、その上にジャッキなどの昇降装置4
を設置する。そして高さを変更する時期になったら、破
壊容易部2よりも上方の構造物をジャッキなどの昇降装
置4によって仮受けする。そして、破壊容易部2の周囲
を包囲した鋼板3をガスバーナーなどによって切断して
撤去する。(図4) 鋼板3の撤去後には低強度コンクリートをピックなどで
はつり、除去する(図5)。すると、コンクリート内部
の鉄筋、鉄骨などの補強材5が露出するので、必要があ
ればガスで切断する。あるいは上下の縁切り材9の間の
コンクリート91を破壊する。この場合には破壊部の上
下には縁切り材9が存在するから、除去すべきでない鉛
直部1のコンクリートに影響をあたえることなく、確実
に解体を行うことができる。この場合に周囲のコンクリ
ートを解体した後に必要に応じて補強材5を切断すれ
ば、中央部分のコンクリートをブロック92状態のまま
撤去することもできる。(図14)
<D> Dismantling of the easily breakable portion 2. When changing the height, a support base 41 such as a scaffold is assembled around the structure, and a lifting device 4 such as a jack is mounted thereon.
Is installed. Then, when it is time to change the height, the structure above the easy-to-break portion 2 is temporarily received by the lifting device 4 such as a jack. Then, the steel plate 3 surrounding the periphery of the easily breakable portion 2 is cut off by a gas burner or the like and removed. (FIG. 4) After the steel plate 3 is removed, the low-strength concrete is hung with a pick or the like and removed (FIG. 5). Then, the reinforcing material 5 such as a reinforcing bar or a steel frame inside the concrete is exposed. If necessary, the reinforcing material 5 is cut with gas. Alternatively, the concrete 91 between the upper and lower edge cutting members 9 is broken. In this case, since the edging material 9 exists above and below the fractured portion, the demolition can be performed reliably without affecting the concrete of the vertical portion 1 that should not be removed. In this case, if the surrounding concrete is dismantled and the reinforcing material 5 is cut as necessary, the concrete in the central portion can be removed in the state of the block 92. (FIG. 14)

【0011】<ホ>高さの変更。 その後に、構造物を支持していた昇降装置4の伸張、あ
るいは短縮によって、解体した破壊容易部2よりも上方
の構造物の高さの変更を行う。(図2、6)昇降装置4
を伸張すれば、破壊容易部2よりも上方の構造物を上昇
させることができる。昇降装置4を短縮すれば、破壊容
易部2よりも上方の構造物を下降させることができる。
なお、昇降装置4としては、ジャッキ以外にも構造物の
重量によってクレーンなどの吊り上げ装置を使用するこ
とができる。
<E> Change in height. After that, the height of the structure above the disassembled easy-to-break portion 2 is changed by extending or shortening the lifting device 4 supporting the structure. (FIGS. 2, 6) Lifting device 4
Is extended, the structure above the easily breakable portion 2 can be raised. If the lifting device 4 is shortened, the structure above the easily breakable portion 2 can be lowered.
In addition, as the lifting device 4, a lifting device such as a crane can be used depending on the weight of the structure other than the jack.

【0012】<ニ>補強材5の連結。 高さを変更した後、上下部分から露出した補強材5を連
結する。(図7) 上方の構造物を上昇させた場合には、補強材5の長さが
不足するから、追加補強材6を追加する。補強材が鉄筋
の場合、追加補強材6の一端は上側の鉄筋に圧接し、追
加補強材6の他端は下側の鉄筋に溶接する。こうして、
継ぎ目のない1本の鉄筋と同等の引張、付着性能を確保
することができる。追加補強材6を追加した部分には、
上述の溶接以前に帯鉄筋を配筋する。なお、鉄筋コンク
リートではなく、鉄骨コンクリートなどの構造であって
も、追加補強材6を追加することによって同様の効果を
達成することができる。
<D> Reinforcement material 5 connection. After changing the height, the reinforcing members 5 exposed from the upper and lower portions are connected. (FIG. 7) When the upper structure is raised, the length of the reinforcing member 5 is insufficient, so the additional reinforcing member 6 is added. When the reinforcing member is a reinforcing bar, one end of the additional reinforcing member 6 is pressed against the upper reinforcing bar, and the other end of the additional reinforcing member 6 is welded to the lower reinforcing bar. Thus,
It is possible to secure the same tensile and adhesive performance as a single seamless reinforcing bar. In the part where additional reinforcement 6 is added,
Arrange the reinforcing bar before the above-mentioned welding. It should be noted that the same effect can be achieved by adding the additional reinforcing member 6 to a structure such as steel frame concrete instead of reinforced concrete.

【0013】<ホ>追加コンクリートの打設。 上下の補強材5を一体化した後、その後に補強材5連結
部の周囲を型枠7で包囲し、型枠7の内部に追加コンク
リート8を打設する。(図8) 追加するコンクリート8の大部分には普通コンクリート
を使用し、最後に補助型枠82で包囲した状態で無収縮
モルタル81などを注入してコンクリート8の硬化時の
体積の減少を防止して一体化する。(図9)
<E> Casting of additional concrete. After the upper and lower reinforcing members 5 are integrated, the periphery of the connecting portion of the reinforcing members 5 is thereafter surrounded by the formwork 7, and additional concrete 8 is cast inside the formwork 7. (Fig. 8) Normal concrete is used for most of the concrete 8 to be added, and finally the non-shrink mortar 81 is injected in the state of being surrounded by the auxiliary formwork 82 to prevent the volume of the concrete 8 from decreasing upon hardening. And integrate. (FIG. 9)

【0014】<ヘ>他の実施例。 以上の実施例では破壊容易部2を1か所に設置する場合
について説明した。しかし図11に示すように、構造物
のコンクリート製鉛直部1、例えば柱の上下2か所に破
壊容易部2を構成しておくこともできる。高さを下降す
る時期になったら、前記の工程と同様の作業によって2
か所の破壊容易部2を解体する。その後に解体した上下
の破壊容易部2間の鉛直部1を撤去する。(図11の右
側) そして破壊容易部2よりも上の部分を下降した後に補強
材5を上下に連結して周囲にコンクリートを打設する。
また、以上の実施例ではすべての部分をコンクリートで
構成した構造物について説明したが、図12に示すよう
に鉛直部1以外は鋼材の構造物2で構成した構造物にお
いても同様に採用することができる。
<F> Another embodiment. In the above embodiment, the case where the easily breakable part 2 is installed at one place has been described. However, as shown in FIG. 11, it is also possible to form the easily breakable portions 2 at the vertical portion 1 made of concrete of the structure, for example, at two places above and below the pillar. When it is time to lower the height, 2
Dismantle the easily breakable parts 2 at the places. Thereafter, the vertical part 1 between the upper and lower easily breakable parts 2 disassembled is removed. (The right side of FIG. 11) Then, after descending the portion above the easy-to-break portion 2, the reinforcing material 5 is connected up and down and concrete is poured around the periphery.
In the above embodiment, a structure in which all parts are made of concrete has been described. However, as shown in FIG. 12, a structure other than the vertical part 1 may be similarly used in a structure made of a steel material structure 2. Can be.

【0015】[0015]

【本発明の効果】本発明の構造物の高さ変更方法は以上
説明したように、高さの変更を行う場合に、仮設の構造
物を必要とせず、将来も使用する構造物自体の高さを上
昇し、あるいは下降する方法である。したがって次のよ
うな効果を得ることができる。 <イ>仮設構造物の構築、撤去の作業、費用、および工
期を必要とせず、従来の方法と比較して大幅な経済効果
を期待することができる。 <ロ>解体の容易な部分を事前に配置しておき、所定の
時期になったらその部分を解体して構造物の昇降を行う
方法である。したがって簡単な作業によって、必要とす
る高さへの変更を簡単に行うことができる。 <ハ>解体部分は充分に補強してあり、解体後には補強
材の連結を確実に行うことができるから、高さを変更す
る以前、以降の構造物の安全を確保することができる。 <ニ>一時的に使用する仮設の構造物を構築しないか
ら、仮設構造物の廃棄にともなう環境の汚染を押さえる
ことができる。 <ホ>仮設の構造物は一般には経済的、工期的な理由か
ら確実な騒音対策を取ることが困難である。その点本発
明の方法は、仮設の構造物を使用せず、最初から騒音の
発生の少ない、将来も使用する構造物自体を使用するも
のである。したがって、周囲の環境に与える騒音を最小
限に抑制することができる。
As described above, the method for changing the height of a structure according to the present invention does not require a temporary structure when changing the height, and the height of the structure itself to be used in the future is not required. It is a method of ascending or descending. Therefore, the following effects can be obtained. <B> The construction and removal work, cost, and construction period of the temporary structure are not required, and a great economic effect can be expected as compared with the conventional method. <B> This is a method in which a portion that is easy to dismantle is arranged in advance, and at a predetermined time, that portion is disassembled and the structure is raised and lowered. Therefore, the required height can be easily changed by a simple operation. <C> Since the disassembled portion is sufficiently reinforced and the reinforcing members can be securely connected after disassembly, the safety of the structure before and after changing the height can be ensured. <D> Since a temporary structure to be used temporarily is not constructed, environmental pollution caused by disposal of the temporary structure can be suppressed. <E> In general, it is difficult to take measures against noise for temporary structures for economic and construction reasons. In this regard, the method of the present invention does not use a temporary structure, but uses a structure that is less likely to generate noise from the beginning and that will be used in the future. Therefore, the noise given to the surrounding environment can be minimized.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の構造物の高さ変更前の状態の説明図。FIG. 1 is an explanatory diagram of a state before a height of a structure according to the present invention is changed.

【図2】構造物の高さを変更した状態の説明図。FIG. 2 is an explanatory diagram of a state in which the height of a structure is changed.

【図3】施工順序の説明図。FIG. 3 is an explanatory view of a construction order.

【図4】施工順序の説明図。FIG. 4 is an explanatory view of a construction order.

【図5】施工順序の説明図。FIG. 5 is an explanatory view of a construction order.

【図6】施工順序の説明図。FIG. 6 is an explanatory view of a construction order.

【図7】施工順序の説明図。FIG. 7 is an explanatory view of a construction order.

【図8】施工順序の説明図。FIG. 8 is an explanatory view of a construction order.

【図9】施工順序の説明図。FIG. 9 is an explanatory view of a construction order.

【図10】施工順序の説明図。FIG. 10 is an explanatory view of a construction order.

【図11】他の実施例の説明図。FIG. 11 is an explanatory view of another embodiment.

【図12】他の実施例の説明図。FIG. 12 is an explanatory diagram of another embodiment.

【図13】縁切り材を設置する状態の説明図。FIG. 13 is an explanatory diagram of a state in which a trimming material is installed.

【図14】縁切り材を設置して解体する状態の説明図。FIG. 14 is an explanatory view of a state in which a trimming member is installed and disassembled.

フロントページの続き (72)発明者 大屋戸 理明 東京都渋谷区代々木二丁目二番二号 東日 本旅客鉄 道株式会社内Continuation of front page (72) Inventor Riaki Oyato 2-2-2 Yoyogi, Shibuya-ku, Tokyo East Japan Railway Company

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】構造物のコンクリート製鉛直部に、破壊容
易な部分を構成しておき、 高さを変更する時期に、破壊容易部を解体し、 破壊容易部よりも上方の構造物の高さを変更した後に、 コンクリート内部の補強材を上下に連結し、 その後に補強材連結部の周囲にコンクリートを打設して
行う、 構造物の高さ変更方法。
An easily breakable portion is formed in a concrete vertical portion of a structure, and when the height is changed, the easily breakable portion is disassembled, and the height of the structure above the easily breakable portion is reduced. A method of changing the height of a structure by connecting the reinforcement inside the concrete up and down after changing the height, and then pouring concrete around the connection of the reinforcement.
【請求項2】構造物のコンクリート製鉛直部に、破壊容
易な部分を構成しておき、 高さを変更する時期に、破壊容易部を解体し、 破壊容易部よりも上方の構造物を上昇させた後に、 コンクリート内部の補強材を上下に連結し、 その後に補強材連結部の周囲にコンクリートを打設して
行う、 構造物の高さ変更方法。
2. An easily breakable portion is formed in a vertical portion made of concrete of a structure, and when the height is changed, the easily breakable portion is disassembled, and the structure above the easily breakable portion is raised. A method of changing the height of a structure, in which the reinforcement inside the concrete is connected vertically and then concrete is poured around the connection of the reinforcement.
【請求項3】構造物のコンクリート製鉛直部に、破壊容
易な部分を構成しておき、 高さを変更する時期に、破壊容易部を解体し、 破壊容易部よりも上方の構造物を下降させた後に、 コンクリート内部の補強材を上下に連結し、 その後に補強材連結部の周囲にコンクリートを打設して
行う、 構造物の高さ変更方法。
An easily breakable portion is formed in a vertical portion made of concrete of the structure, and when the height is changed, the easily breakable portion is dismantled, and the structure above the easily breakable portion is lowered. A method of changing the height of a structure, in which the reinforcement inside the concrete is connected vertically and then concrete is poured around the connection of the reinforcement.
【請求項4】構造物のコンクリート製鉛直部の上下2か
所に破壊容易な部分を構成しておき、 高さを変更する
時期に、2か所の破壊容易部を解体し、 解体した破壊容易部間の部材を撤去した後に、 コンクリート内部の補強材を上下に連結し、 その後に補強材連結部の周囲にコンクリートを打設して
行う、 構造物の高さ変更方法。
4. An easy-to-break portion is formed at two locations above and below a concrete vertical portion of the structure, and at the time of changing the height, the two easy-to-break portions are dismantled and dismantled. A method of changing the height of a structure by removing the members between the easy parts, connecting the reinforcement inside the concrete up and down, and then pouring concrete around the reinforcement connection.
【請求項5】破壊容易部には低強度コンクリートを充填
し、 その周囲を鋼板で包囲して閉合してコンクリートの変形
を拘束するように構成した、 請求項1、2、3、4記載の、構造物の高さ変更方法。
5. The structure according to claim 1, wherein the easily breakable portion is filled with low-strength concrete, and the periphery thereof is surrounded by a steel plate and closed to restrain the deformation of the concrete. How to change the height of the structure.
【請求項6】破壊容易部には、鉛直部のコンクリートと
縁切りする部材を2か所に水平に設置しておき、 その周囲を鋼板で包囲して閉合してコンクリートの変形
を拘束するように構成した、 請求項1、2、3、4記載の、構造物の高さ変更方法。
6. In the easily breakable part, a member for cutting off the vertical part of the concrete is installed horizontally at two places, and the periphery thereof is surrounded by a steel plate and closed to restrain the deformation of the concrete. The method for changing the height of a structure according to claim 1, wherein the method is configured.
JP03816498A 1998-02-04 1998-02-04 How to change the height of the structure Expired - Lifetime JP3472952B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP03816498A JP3472952B2 (en) 1998-02-04 1998-02-04 How to change the height of the structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP03816498A JP3472952B2 (en) 1998-02-04 1998-02-04 How to change the height of the structure

Publications (2)

Publication Number Publication Date
JPH11222812A true JPH11222812A (en) 1999-08-17
JP3472952B2 JP3472952B2 (en) 2003-12-02

Family

ID=12517773

Family Applications (1)

Application Number Title Priority Date Filing Date
JP03816498A Expired - Lifetime JP3472952B2 (en) 1998-02-04 1998-02-04 How to change the height of the structure

Country Status (1)

Country Link
JP (1) JP3472952B2 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100617395B1 (en) * 2006-01-17 2006-09-01 정언섭 Building repairing system through column raising
KR100877596B1 (en) 2008-03-03 2009-01-07 제일구조건설(주) Building repairing method using column reinforcing member
CN102493367A (en) * 2011-12-06 2012-06-13 中铁六局集团有限公司 Non-blasting construction method for dismantling pier to land bridge
JP2012144918A (en) * 2011-01-13 2012-08-02 Railway Technical Research Institute Construction method for replacing railway viaduct column
JP2017515028A (en) * 2014-05-02 2017-06-08 ソルタンシュ フレシネ ソシエテ パー アクション サンプリフィエ Method for expanding the space below a stone arch bridge and a stone arch bridge
CN111576197A (en) * 2020-05-08 2020-08-25 中冶南方城市建设工程技术有限公司 Assembled bridge abutment capable of relieving bumping at bridge head and construction method thereof

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100617395B1 (en) * 2006-01-17 2006-09-01 정언섭 Building repairing system through column raising
KR100877596B1 (en) 2008-03-03 2009-01-07 제일구조건설(주) Building repairing method using column reinforcing member
JP2012144918A (en) * 2011-01-13 2012-08-02 Railway Technical Research Institute Construction method for replacing railway viaduct column
CN102493367A (en) * 2011-12-06 2012-06-13 中铁六局集团有限公司 Non-blasting construction method for dismantling pier to land bridge
JP2017515028A (en) * 2014-05-02 2017-06-08 ソルタンシュ フレシネ ソシエテ パー アクション サンプリフィエ Method for expanding the space below a stone arch bridge and a stone arch bridge
CN111576197A (en) * 2020-05-08 2020-08-25 中冶南方城市建设工程技术有限公司 Assembled bridge abutment capable of relieving bumping at bridge head and construction method thereof
CN111576197B (en) * 2020-05-08 2021-12-07 中冶南方城市建设工程技术有限公司 Assembled bridge abutment capable of relieving bumping at bridge head and construction method thereof

Also Published As

Publication number Publication date
JP3472952B2 (en) 2003-12-02

Similar Documents

Publication Publication Date Title
JP2790986B2 (en) Bridge pier construction method and construction method
JP2859158B2 (en) Structure of mounting part of concrete wall railing
JP2994222B2 (en) Construction method of cast-in-place slab of precast concrete girder and its formwork
KR101309004B1 (en) Rahmen bridge and constructing method thereof
CN114134820A (en) Formwork support and construction method for I-shaped composite beam cast-in-place bridge deck
JPH11222812A (en) Changing method of height of structure
JP2980567B2 (en) How to replace the bearing device
KR101309005B1 (en) Rahmen bridge and constructing method thereof
CN114016417A (en) Top cover plate capping construction bottom template and method for oblique hollow pier
JPH07300817A (en) Concrete-filled steel pipe truss pier and construction method
CN210396103U (en) Connecting piece for shear wall template system, external wall panel and shear wall template system
JP3466961B2 (en) Reinforcement method for existing load-bearing walls with openings
JP2006225961A (en) Pier head structure and its construction method
JP5872332B2 (en) Seismic reinforcement method for buildings
JP2001329700A (en) Temporary jointing method for column during building demolition in jack system
JP2009150067A (en) Method of and structure for renewing existing bearing apparatus
KR20170026791A (en) Precast panel structure and construction method thereof
JPH08253947A (en) Installation method for form-support in reverse placing method of concrete
KR20020012670A (en) A Bridge Establishing Method Using Fabricated Jack Support Unit
JP3202101B2 (en) Construction method of balustrade in concrete structure with balustrade
KR200256837Y1 (en) Pier sheeting support structure using an assembly band and support
CN216947881U (en) Formwork support of I-shaped composite beam cast-in-situ bridge deck
CN215889432U (en) Bent frame erecting structure
JPH0988348A (en) Method for constructing foundation beam
JP3511153B2 (en) Joint structure of concrete filled beam

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20070919

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080919

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090919

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100919

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110919

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120919

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130919

Year of fee payment: 10

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term