KR20010097315A - Pier scaffolding and the pier construction method for using pier scaffolding - Google Patents

Pier scaffolding and the pier construction method for using pier scaffolding Download PDF

Info

Publication number
KR20010097315A
KR20010097315A KR1020000021293A KR20000021293A KR20010097315A KR 20010097315 A KR20010097315 A KR 20010097315A KR 1020000021293 A KR1020000021293 A KR 1020000021293A KR 20000021293 A KR20000021293 A KR 20000021293A KR 20010097315 A KR20010097315 A KR 20010097315A
Authority
KR
South Korea
Prior art keywords
pier
scaffolding
piers
vertical
scaffold
Prior art date
Application number
KR1020000021293A
Other languages
Korean (ko)
Other versions
KR100377868B1 (en
Inventor
이영구
Original Assignee
배종렬
삼성물산 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 배종렬, 삼성물산 주식회사 filed Critical 배종렬
Priority to KR10-2000-0021293A priority Critical patent/KR100377868B1/en
Publication of KR20010097315A publication Critical patent/KR20010097315A/en
Application granted granted Critical
Publication of KR100377868B1 publication Critical patent/KR100377868B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

본 발명은 교각의 고소 작업 시에 발생되는 낙하 및 추락사고를 예방하고 수직철근으로 장철근을 조립하여 사용함에 따른 1회 콘크리트 타설 높이가 높아지며 시공조인트가 줄어들어 고품질과 안전을 확보할 수 있는 교각용 틀비계에 관한 것이다.The present invention prevents falling and fall accidents generated during the operation of bridge piers and increases the height of one-time concrete placing by assembling long steel bars with vertical rebars, and reduces construction joints, thereby ensuring high quality and safety. It's about scaffolding.

본 발명은 수직재(1), 수평난간대(2), 작업발판(3) 및 사다리 통로(4)로 구성되며, 수직재(1)는 교각의 주위로 2열로 배치되며 수평난간대(2)는 상기 2열의 수직재(1)사이에 고리형으로 다수단 설치되며 작업발판(3)은 상기 수평난간대(2)와 수직재(1)에 지지되어 수평으로 다수단 설치되며 사다리통로(4)는 상기 다수단의 작업발판(3)을 연결한다.The present invention consists of a vertical member (1), a horizontal handrail (2), a working step (3) and a ladder passage (4), the vertical member (1) is arranged in two rows around the piers and the horizontal handrail (2) is A plurality of stages are installed in a ring form between the vertical members 1 in a row, and the working scaffold 3 is supported by the horizontal handrail 2 and the vertical members 1 to be installed in multiple stages horizontally. Connect the working platform (3).

Description

교각용 틀비계 및 이를 이용한 교각 시공 방법{Pier scaffolding and the pier construction method for using pier scaffolding}Pier scaffolding and the pier construction method for using pier scaffolding}

본 발명은 교각용 틀비계에 관한 것이다. 보다 구체적으로, 교량공사 중에서 교각공사의 고소 작업 시에 예상되는 추락 및 낙하사고를 예방하고 교각의 수직철근으로 장철근을 사용함에 따라 콘크리트 1회 타설 높이가 높아짐으로써 시공조인트를 최소화하여 고품질로 시공이 가능한 교각용 틀비계에 관한 것이다.The present invention relates to a frame scaffold for piers. More specifically, the construction of high quality construction is minimized by minimizing construction joints by increasing the one-time height of concrete as it prevents falling and falling accidents expected during the work of pier construction in the bridge construction and uses the long rebar as the vertical rebar of the bridge. It is about possible scaffolding for bridge piers.

교량의 교각시공에 있어서 종래에는 철근조립, 거푸집작업, 콘크리트 타설 작업을 일정높이마다 한 단씩 설치공정과 해체공정을 반복하여 교각부 전체를 상부방향으로 완성해 나가는 시공방법을 사용하였다. 구체적인 예로서 교각부를 3단으로 나누어 시공하는 경우에 교각 하부에 장방형의 기초콘크리트를 타설한 상부에 강관비계를 일정높이로 사방으로 설치하고 강관비계와 동일한 높이로 교각부의 수직철근을 조립하여 1단을 완성한 후에 상기 강관비계를 해체하고 강재거푸집을 조립하여 설치한 후 강재 거푸집의 내부에 콘크리트를 타설한 후 강재거푸집을 해체하면 교각의 하부 1단의 시공이 완성되었다. 2단의 시공은 상기 1단의 설치된 강관비계를 연결하여 강관비계의 높이에 맞도록 높여서 제작하거나, 작업공간이 협소할 경우에는 강관비계를 해체 후 재조립하여 2단의 수직철근의 높이에 맞도록 높여서 시공하며, 시공방법과 순서는 선행한 교각부 1단의 공사와 동일하며 3단의 교각부 시공 역시 선행한 과정을 동일하게 반복하여 교각을 완성하였다.In the construction of bridge pier, conventionally, reinforcing bar assembly, formwork, and concrete placing work are performed by repeating the installation process and dismantling process one step at a certain height to complete the whole pier part upward. As a concrete example, in the case of construction by dividing the piers into three stages, the steel pipe scaffolding is installed in all directions at a certain height on the upper part where the rectangular foundation concrete is placed on the lower part of the piers, and the vertical bars of the piers are assembled at the same height as the steel pipe scaffolding. After the completion of dismantling the steel pipe scaffolding and assembling the steel formwork, and then installed concrete in the steel formwork and then dismantle the steel formwork, the construction of the lower stage of the piers was completed. Two-stage construction is made by connecting the steel pipe scaffolding installed in the first stage to meet the height of the steel pipe scaffolding, or if the work space is narrow, dismantle and reassemble the steel pipe scaffolding to match the height of the two vertical bars. The construction method and order are the same as the construction of the first piers, and the construction of the piers of the third piers completed the piers by repeating the same process.

종래의 시공방법은 품질, 안전, 경제 및 환경적인 측면에서 다음의 문제점이발생하였다.The conventional construction method has the following problems in terms of quality, safety, economy and environment.

품질적인 측면에서, 교각부의 철근조립 작업 시에 수직철근의 전도위험이 따르며 교각부를 여러 단으로 분할하여 상부로 시공함으로써 1회 콘크리트 타설 높이가 낮아서 시공 조인트가 여러 개소 발생하여 교량 시공 후에 교각을 보수하게 되는 주요 요인으로 작용하며 교각의 품질을 확보하기 어려운 문제점이 발생하였다.In terms of quality, the reinforcing risk of vertical reinforcing bars in the reinforcement work of bridge piers is to be carried out, and the piers are divided into several stages and constructed at the top. It acted as a major factor to make a difficult problem to secure the quality of the bridge.

안전적인 면에서, 비계의 설치작업과 해체작업 및 철근조립작업 모두 고소작업이므로 추락사고의 발생률이 매우 높고 수직철근의 전도를 방지하기 위한 버팀 줄이 오히려 기설치된 비계와 서로 간섭되어 설치된 수직철근이 전도되는 문제점이 발생하였다.In terms of safety, the installation work of the scaffolding, the dismantling work, and the reinforcing work of the reinforcing bars are all high-accuracy, so the fall rate is very high, and the support bars to prevent the fall of the vertical rebars are installed. There was a problem of falling.

경제적인 측면에서, 교각부의 전체 작업 공정을 살펴보면 철근조립작업 시에 비계를 설치하고 거푸집 조립 시 해체하는 등 동일한 작업이 설치와 해체가 반복되어 시공이 진행되므로 작업이 지연되어 그만큼의 손실이 발생하였다. 교각부의 1단에 해당하는 콘크리트 1회 타설 높이가 낮아서 교각부 전체를 여러 차례 나누어 시공함으로써 시공횟수가 증가하여 공기가 지연되며, 인건비, 고소작업에 투입되는 중장비와 인양장비의 비효율적인 사용으로 초과 발생되는 장비사용료 부담 등 시공원가 상승의 주요한 원인으로 작용하였다. 또한 현장에서 강관비계를 주로 사용하여강관비계의 설치와 해체 과정에서 해체 후 강관비계의 당초수량보다 감소하는 망실률이 높은 문제점이 발생하였다.Economically, when looking at the whole work process of the piers, the same work was repeatedly installed and dismantled. . As the height of the concrete, which is the first stage of the piers, is low, the construction time is increased by dividing the entire piers several times, which delays the air and exceeds the cost due to the inefficient use of heavy equipment and lifting equipment, which is put into labor cost and high place work. It was a major cause of the rise in city park prices, including the burden of equipment usage. In addition, the steel pipe scaffold is mainly used in the field, and during the installation and dismantling of the steel pipe scaffolding, there was a problem that the loss ratio was higher than the original quantity of the steel pipe scaffold after dismantling.

환경적인 측면에서, 잦은 설치와 해체공정으로 잔재되는 비계 및 각종 부속자재가 매몰되거나 방치되는 문제점이 발생하였다.In terms of environmental aspects, scaffolding and various subsidiary materials left by frequent installation and dismantling processes are buried or left unattended.

개발자는 이상과 같은 종래의 기술이 안고 있는 문제점을 개선하기 위하여 본 발명을 개발하였다.The developer has developed the present invention to improve the problems of the prior art as described above.

본 발명의 목적은 교각공사 고소 작업 시 예상되는 추락 및 낙하사고를 사전에 예방하는 교각용 틀비계를 제공하는 것이다.An object of the present invention is to provide a bridge scaffold for pier to prevent the fall and fall accidents expected in the work of pier construction sue.

본 발명의 다른 목적은 수직철근의 전도위험을 방지하여 장철근의 철근조립이 가능함에 따라 장철근을 안전하고 정확하게 시공하며 1회 콘크리트 타설 높이를 높여서 교각부의 시공조인트를 최소화한 고품질의 교각을 시공할 수 있는 교각용 틀비계를 제공하는 것이다.Another object of the present invention is to construct the reinforcing bars of the rebar to prevent the fall of the vertical reinforcing bars to be safe and accurate construction and to increase the height of one-time concrete placing can be constructed high-quality pier to minimize the construction joint of the piers To provide a scaffold for bridge piers.

도1은 교각용 틀비계를 교각 기초콘크리트 상부에 설치한 상태의 사시도이다.1 is a perspective view of a state in which the pier frame scaffold is installed on the pier foundation concrete.

도2는 교각의 1단의 콘크리트를 완성하고 교각 상단의 강재거푸집의 일부를 존치시키며 그 상단에 교각용 틀비계를 설치하는 모습을 나타낸 사시도이다.Figure 2 is a perspective view showing the completion of the concrete of the first stage of the piers, retaining a portion of the steel formwork at the top of the piers and installing a frame scaffold for piers on the top.

도3은 도2의 교각용 틀비계가 설치된 상태를 나타낸 단면도 및 측면도이다.3 is a cross-sectional view and a side view showing a state in which the piercing frame scaffold of FIG. 2 is installed.

도4는 다수개의 교각의 상단부에 교각용 틀비계를 설치한 단면도 및 측면도이다.4 is a cross-sectional view and a side view in which a pier frame scaffold is installed at upper ends of a plurality of piers.

<도면의 부호에 대한 간단한 설명><Short description of the symbols in the drawings>

1 : 수직재 2 : 수평난간대1: vertical material 2: horizontal railing

3 : 작업발판 4 : 사다리통로3: working step 4: ladder passage

5 : 연결통로 6 : 강재거푸집5: connecting passage 6: steel formwork

7 : 브라켓 8 : 수직철근7 Bracket 8 Vertical Rebar

9 : 교각기초콘크리트9: pier foundation concrete

본 발명인 교각용 틀비계는 수직재(1), 수평난간대(2), 작업발판(3) 및 사다리 통로(4)로 구성된다.Pier scaffolding of the present invention is composed of a vertical member (1), a horizontal handrail (2), a working scaffold (3) and a ladder passage (4).

수직재(1)는 교각의 주위로 2열이 배치되며 상기 2열로 배치된 수직재는 교각의 형상에 따라 원형, 타원형 또는 사각형으로 배치된다. 도1에는 원형 기중의 경우에 대해서 예시되어 있다. 수직재의 높이는 배근할 교각의 주철근의 길이와 비슷한 정도로 제작된다. 예를 들면 교각에 길이가 8M인 주철근을 배근 시에는 수직재의 높이는 8M정도로 제작된다.The vertical members 1 are arranged in two rows around the piers, and the vertical members arranged in the two rows are arranged in a circle, oval or square according to the shape of the piers. 1 is illustrated for the case of circular lift. The height of the vertical members is made to be similar to the length of the cast steel of the piers to be reinforced. For example, when reinforcing a cast iron reinforcing rod of 8M in a pier, the height of the vertical member is about 8M.

수평 난간대(2)는 상기 2열의 수직재(1)사이에 고리형으로 다수 단 설치되어안쪽 고리와 바깥쪽의 고리를 형성한다. 안쪽 고리는 교각 주철근의 시공위치와 거의 근접하며 수평재로는 일반적으로 사각파이프를 사용하며 교각이 원형 또는 타원형인 경우에는 상기 수평 난간대(2)는 곡면으로 가공된 부재를 사용한다.Horizontal railings (2) are installed in a plurality of stages in a ring-shaped between the two rows of vertical member (1) to form an inner ring and an outer ring. The inner ring is almost close to the construction position of the pier cast iron bar, and the horizontal member generally uses a square pipe, and when the pier is circular or elliptical, the horizontal handrail 2 uses a curved member.

작업발판(3)은 작업자가 올라서서 작업을 할 수 있는 발판으로써 상기 다수단의 수평 난간대(2)와 수직재(1)에 지지되며 수평으로 다수단이 설치된다. 안쪽의 수평 난간대(2)와 바깥쪽의 수평 난간대(2) 사이에 받침대를 일정간격으로 설치하고 설치한 받침대 위에 금속 또는 목재의 판재를 깔아 작업발판을 제작한다.The working scaffold 3 is a scaffold that allows the worker to work up and is supported by the horizontal handrail 2 and the vertical member 1 of the plurality of stages, and a plurality of stages are installed horizontally. Between the inner horizontal handrail (2) and the outer horizontal handrail (2) to install a pedestal at regular intervals and to install a working scaffold by laying a plate of metal or wood on the installed pedestal.

사다리통로(4)는 상기 설치된 다수 단의 작업발판(3)을 상하로 서로 연결하여교각 작업시에 상하로 이동이 가능하도록 한다.Ladder passage (4) is connected to each other up and down the installed step of the operation scaffold (3) to enable the movement up and down at the time of the pier operation.

상기 교각용 틀비계는 수직재(1)의 높이를 교각의 수직철근(8)의 길이와 동일한 단일부재를 사용하여 제작할 수도 있고, 상기 수직철근(8)의 길이 보다 짧은 규격으로 여러 개를 제작하여 수직으로 연결하여 사용할 수도 있다. 따라서 수직철근(8)의 길이가 긴 경우에는 필요에 따라 일정 단 더 연장하여 사용할 수도 있다.The pier frame scaffolding may be manufactured by using a single member having the same height as the length of the vertical reinforcement (8) of the vertical member (1), by manufacturing a plurality of shorter than the length of the vertical reinforcement (8) It can also be used vertically. Therefore, when the length of the vertical reinforcement (8) is long, it may be used to extend a certain step as needed.

상기 교각용 틀비계를 다수 단으로 제작한 후 상하로 연결할 경우에는 일반적으로 상하에 연결볼트를 사용하여 고정하며, 상기 교각용 틀비계를 해체에는 연결볼트를 풀어 해체한다.When the pier frame scaffold is manufactured in multiple stages and then connected up and down, it is generally fixed by using connecting bolts at the top and bottom.

상기 한 단의 틀비계는 원형 또는 사각형상의 단일모듈로 제작할 수도 있고 반원 또는 90도 간격으로 분할하여 2개 또는 4개의 부재를 조립하여 제작할 수도 있다.The frame scaffolding of one stage may be manufactured in a single module of a circular or rectangular shape, or may be manufactured by assembling two or four members by dividing at semicircular or 90 degree intervals.

다수개의 교각을 서로 인접하여 시공 시에는 도4에서 도시하는 바와 같이 별도의 연결통로(5)를 설치한다. 상기 연결통로(5)는 상기 인접한 교각에 설치된 교각용 틀비계의 작업발판(3)과 인접한 교각의 작업발판(3) 사이를 연결한다. 상기 연결통로(5)의 한쪽을 힌지로 시공하여 해체 시에 힌지를 풀어 해체한다.When constructing a plurality of bridges adjacent to each other, as shown in Figure 4 is provided with a separate connection passage (5). The connecting passage 5 connects between the working scaffold 3 of the pier scaffold installed in the adjacent piers and the working scaffold 3 of the adjacent piers. One side of the connecting passage 5 is constructed by a hinge to dismantle the hinge when dismantling.

본 발명의 교각용 틀비계를 이용하여 교각을 시공하는 방법에 대해 설명한다.The method of constructing a pier using the pier frame scaffold of the present invention will be described.

교각기초콘크리트(9)를 타설하여 양생한 후 수직재(1), 수평난간대(2), 작업발판(3) 및 사다리통로(4)로 구성되는 교각용 틀비계를 조립하여 상기 교각용 틀비계를 크레인으로 운반하여 상기 교각기초콘크리트(9) 상부의 수직철근(8) 시공위치에 얹어 놓는다.The bridge pier scaffolding is constructed by placing the bridge foundation concrete (9) and curing it, and then assembling the bridge pier scaffold consisting of the vertical material (1), the horizontal railing (2), the working platform (3) and the ladder passage (4). Transported by a crane and placed on the construction site of the vertical reinforcement (8) above the bridge foundation concrete (9).

상기 교각용 틀비계의 작업발판(3)에 올라서서 교각의 수직철근(8)을 배근한다. 상기 교각용 틀비계의 수평 난간대(2)는 교각의 수직철근(8)의 설치위치에 조립되어 있으므로 수직철근(8)을 상기 수평 난간대(2)에 지지시켜 수직철근(8)을 별도의 로프로 고정하지 않더라도 전도될 우려가 없다.On the working scaffold 3 of the pier scaffold, the vertical reinforcement 8 of the pier is reinforced. Since the horizontal handrail 2 of the pier frame scaffold is assembled at the installation position of the vertical reinforcing bar 8 of the pier, the vertical reinforcing bar 8 is supported on the horizontal handrail 2 so that the vertical reinforcing bar 8 is separated from the rope. There is no fear of falling even if it is not fixed.

상기 수직철근(8)의 조립이 완료된 후 크레인을 이용하여 상기 교각용 틀비계를 들어낸다.After the assembly of the vertical reinforcement (8) is completed using the crane lifting the frame scaffolding for the pier.

교각의 강재거푸집(6)을 지상에서 조립하여 크레인을 이용하여 설치한다. 상기 강재거푸집(6)은 일반적으로 수평으로 다수 단 분절되어 있으며 분절된 각각의 강재거푸집(6)의 상단에는 브라켓과 발판이 설치되며 콘크리트 타설 작업에 투입된 작업인부는 상기 브라켓과 발판을 이용하여 작업한다.Steel formwork (6) of the piers are assembled on the ground and installed using a crane. The steel formwork 6 is generally horizontally divided into a plurality of stages, and a bracket and a scaffold are installed at the top of each segmented steel formwork 6, and a worker who is put into the concrete placing work works by using the bracket and the scaffold. do.

콘크리트를 타설한 후 분절된 강재거푸집(6)의 최상단은 존치하고 나머지 하단부의 강재거푸집(6)은 탈형하고 상기 강재거푸집(6)의 최상단에 설치된 브라켓(7)에 크레인을 이용하여 교각용 틀비계를 운반하여 얹어서 상기 콘크리트 1단이 타설된 교각부의 상부의 수직철근(8)을 조립한다.After pouring concrete, the top end of the segmented steel formwork (6) remains and the remaining steel formwork (6) at the lower end is demoulded and the bracket (7) installed at the top of the steel formwork (6) using a crane frame for pier The scaffold is transported and mounted to assemble the vertical reinforcement 8 at the top of the pier where the first stage of concrete is poured.

상기의 과정을 반복하여 교각을 완성한다.Repeat the above process to complete the piers.

본 발명은 교각의 고소 작업시에 발생되는 낙하 및 추락사고를 예방하고 수직철근으로 장철근을 조립하여 사용함에 따른 1회 콘크리트 타설 높이가 높아짐으로써 시공조인트가 줄어들어 고품질시공과 안전을 확보할 수 있으며 설치와 이동의 반복공정이 생략되어 공기가 단축되고 공사비를 절감하는 효과가 있다.The present invention prevents falling and fall accidents occurring during the height of bridge piers and increases the one-time concrete placing height by assembling the long steel bars with vertical rebars, thereby reducing construction joints and ensuring high quality construction and safety. The repetitive process of moving and moving is omitted, which shortens the air and reduces the construction cost.

Claims (3)

교각의 주위로 2열로 배치된 수직재(1);Vertical members 1 arranged in two rows around the piers; 상기 2열의 수직재(1)사이에 고리형으로 설치된 다수단의 수평난간대(2);A plurality of horizontal handrails (2) installed in a ring form between the two rows of vertical members (1); 상기 수평난간대(2)와 수직재(1)에 지지되어 수평으로 설치된 다수단의 작업발판(3); 및,Multi-stage working scaffolding (3) horizontally supported by the horizontal handrail (2) and the vertical member (1); And, 상기 다수단의 작업발판(3)을 연결하는 사다리통로(4);Ladder passage (4) for connecting the plurality of working scaffold (3); 로 구성되는 것을 특징으로 하는 교각용 틀비계.Pier scaffolding, characterized in that consisting of. 제1항에서, 상기 작업발판(3)과 인접한 교각에 설치된 제1항의 교각용 틀비계의 작업발판(3) 사이에 연결통로(5)를 더 설치하는 것을 특징으로 하는 교각용 틀비계.The pier frame scaffold according to claim 1, further comprising a connecting passage (5) between the work platform (3) and the work platform (3) of the piercing frame scaffold of claim 1 installed in an adjacent pier. (a) 교각 기초 콘크리트를 타설하고;(a) placing pier foundation concrete; (b) 제1항의 상기 교각용 틀비계를 조립하고;(b) assembling the pier frame scaffold according to claim 1; (c) 상기 교각용 틀비계를 설치하고;(c) installing the pier frame scaffolding; (d) 상기 교각용 틀비계를 이용하여 교각의 수직철근을 배근하고;(d) reinforcing the vertical bars of the piers by using the pier frame scaffolding; (e) 상기 교각용 틀비계를 이동시키고;(e) moving the pier frame scaffolding; (f) 교각의 거푸집을 설치한 후 콘크리트를 타설하고;(f) cast concrete after installing the formwork for the piers; 상기 (c)에서 (f)의 단계를 반복하여 교각을 완성하는 단계로 구성되는 것을 특징으로 하는 교각용 틀비계.Pier scaffolding, characterized in that consisting of the step of completing the pier by repeating the steps of (c) to (f).
KR10-2000-0021293A 2000-04-21 2000-04-21 pier construction method using Pier scaffolding KR100377868B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR10-2000-0021293A KR100377868B1 (en) 2000-04-21 2000-04-21 pier construction method using Pier scaffolding

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR10-2000-0021293A KR100377868B1 (en) 2000-04-21 2000-04-21 pier construction method using Pier scaffolding

Publications (2)

Publication Number Publication Date
KR20010097315A true KR20010097315A (en) 2001-11-08
KR100377868B1 KR100377868B1 (en) 2003-03-26

Family

ID=19666162

Family Applications (1)

Application Number Title Priority Date Filing Date
KR10-2000-0021293A KR100377868B1 (en) 2000-04-21 2000-04-21 pier construction method using Pier scaffolding

Country Status (1)

Country Link
KR (1) KR100377868B1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106400687A (en) * 2016-06-12 2017-02-15 中交公局第二工程有限公司 Positioning assisting assembly jig for pier column reinforcing rib
CN108547227A (en) * 2018-06-07 2018-09-18 宁波交通工程建设集团有限公司 Modularization bridge pier inclosure structure and construction method
CN109958067A (en) * 2019-05-05 2019-07-02 中交一公局第三工程有限公司 Construction bracket apparatus and system
CN110886234A (en) * 2019-12-17 2020-03-17 中交路桥建设有限公司 Lengthening template for bridge pier column and construction method
CN116219892A (en) * 2022-12-31 2023-06-06 兰州交通大学 Intelligent adjustable assembled high-speed railway mound top support construction hydraulic support platform

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100625782B1 (en) * 2004-04-06 2006-09-20 정재용 Pier Structure having Precast Concrete Form and Constructing Method therefor
KR100804554B1 (en) * 2007-03-30 2008-02-20 한성산업(주) Steel stand for working reinforcing rod for bridge for constructing bridge pier

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09235704A (en) * 1996-02-29 1997-09-09 Japan Steel & Tube Constr Co Ltd Bridge pier reinforcing method and device thereof

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106400687A (en) * 2016-06-12 2017-02-15 中交公局第二工程有限公司 Positioning assisting assembly jig for pier column reinforcing rib
CN106400687B (en) * 2016-06-12 2018-09-25 中交一公局第二工程有限公司 A kind of pier stud reinforcing bar positioning auxiliary moulding bed
CN108547227A (en) * 2018-06-07 2018-09-18 宁波交通工程建设集团有限公司 Modularization bridge pier inclosure structure and construction method
CN108547227B (en) * 2018-06-07 2024-02-06 宁波交通工程建设集团有限公司 Modular pier surrounding cage structure and construction method
CN109958067A (en) * 2019-05-05 2019-07-02 中交一公局第三工程有限公司 Construction bracket apparatus and system
CN110886234A (en) * 2019-12-17 2020-03-17 中交路桥建设有限公司 Lengthening template for bridge pier column and construction method
CN116219892A (en) * 2022-12-31 2023-06-06 兰州交通大学 Intelligent adjustable assembled high-speed railway mound top support construction hydraulic support platform
CN116219892B (en) * 2022-12-31 2024-01-12 兰州交通大学 Intelligent adjustable assembled high-speed railway mound top support construction hydraulic support platform

Also Published As

Publication number Publication date
KR100377868B1 (en) 2003-03-26

Similar Documents

Publication Publication Date Title
KR20030093680A (en) The construction method of double-t girder bridge by underslung movable scaffolding system
KR100565865B1 (en) Construction method of concrete arch bridge
KR102059552B1 (en) Modular work platform of a long span bridge main tower rebar and construction method using the same
KR101889064B1 (en) Construction method of a long span bridge main tower
KR102477955B1 (en) Bridge pier and the construction method using maintained concrete mold
KR100377868B1 (en) pier construction method using Pier scaffolding
JP2924626B2 (en) Bridge pier construction method by self-elevating formwork method
JPH07310304A (en) Erection method of concrete arch
JP4136049B2 (en) Concrete pier construction method
KR200207380Y1 (en) A column&#39;s reinforcing rod for a round pier
JP4476096B2 (en) Construction method of large high-rise wind farm
KR100403989B1 (en) Bridge slab construction method and precast concrete plate applied therein
JPH07300817A (en) Concrete-filled steel pipe truss pier and construction method
JP3804191B2 (en) Construction method of hollow cylindrical housing
KR102381969B1 (en) Formwork for bridge piers and construction method of piers using the same
KR910007424B1 (en) Method for construction t - beam on the bridge
KR200253551Y1 (en) A sheeting structure of iron frame using a chain block
JPH03125755A (en) Constructing method for cylindrical multistoried structure
JPH07216822A (en) Bridge pier and construction method thereof by self-rising type form construction method
KR100584869B1 (en) Prestressed composite beam bridge unit and construction method of prestressed composite beam bridge using the bridge unit
CN214996342U (en) Integrated protection channel for stairwell
JPH0988348A (en) Method for constructing foundation beam
JP2812177B2 (en) Bridge pier construction method by slip form method
KR200361049Y1 (en) Prestressed composite beam bridge unit
JPH0881918A (en) Pipe and construction method thereof

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20090310

Year of fee payment: 7

LAPS Lapse due to unpaid annual fee