KR102059552B1 - Modular work platform of a long span bridge main tower rebar and construction method using the same - Google Patents

Modular work platform of a long span bridge main tower rebar and construction method using the same Download PDF

Info

Publication number
KR102059552B1
KR102059552B1 KR1020170132363A KR20170132363A KR102059552B1 KR 102059552 B1 KR102059552 B1 KR 102059552B1 KR 1020170132363 A KR1020170132363 A KR 1020170132363A KR 20170132363 A KR20170132363 A KR 20170132363A KR 102059552 B1 KR102059552 B1 KR 102059552B1
Authority
KR
South Korea
Prior art keywords
unit
bridge
work
reinforcement
work platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
KR1020170132363A
Other languages
Korean (ko)
Other versions
KR20190041189A (en
Inventor
정운
박건영
김기남
박상혁
윤의택
Original Assignee
현대건설(주)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 현대건설(주) filed Critical 현대건설(주)
Priority to KR1020170132363A priority Critical patent/KR102059552B1/en
Publication of KR20190041189A publication Critical patent/KR20190041189A/en
Application granted granted Critical
Publication of KR102059552B1 publication Critical patent/KR102059552B1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/10Railings; Protectors against smoke or gases, e.g. of locomotives; Maintenance travellers; Fastening of pipes or cables to bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

본 발명은, 장대교량 주탑용 철근 선시공 작업대 및 이를 이용하는 시공방법에 관한 것으로, 작업자가 철근 시공 작업을 위해 이동할 수 있는 이동경로를 형성하는 발판 플레이트와, 상기 발판 플레이트의 일측에 상기 발판 플레이트와 교차하는 방향을 연결되어 상기 작업자의 추락을 방지하는 난간을 포함하는 작업유닛; 및 상기 작업유닛을 상기 상승형 거푸집과 연결시키며, 상기 작업유닛의 높이를 조절할 수 있도록 상기 작업유닛의 하측에 적어도 하나 이상 구비되는 위치조절유닛을 포함한다.The present invention relates to a reinforcement construction work platform for a long bridge main column and a construction method using the same, and a scaffold plate for forming a moving path that can be moved by the worker for the reinforcement construction work, and crosses the scaffold plate on one side of the scaffold plate A work unit including a handrail connected to a direction to prevent the worker from falling; And a position adjusting unit connected to the work unit with the raised formwork and provided with at least one lower side of the work unit to adjust the height of the work unit.

Description

장대교량 주탑용 철근 선시공 작업대 및 이를 이용하는 시공방법{Modular work platform of a long span bridge main tower rebar and construction method using the same}Modular work platform of a long span bridge main tower rebar and construction method using the same}

본 발명은 장대교량 주탑용 철근 선시공 작업대 및 이를 이용하는 시공방법에 관한 것으로서, 보다 상세하게는 공사기간을 단축하며, 안전하고 신속하게 주탑을 시공할 수 있는 장대교량 주탑용 철근 선시공 작업대 및 이를 이용하는 시공방법에 관한 것이다.The present invention relates to a reinforcement construction work platform for pole bridge main tower and a construction method using the same, in more detail, to shorten the construction period, the construction of the reinforcement construction work pole for the bridge bridge pylon to construct the main tower safely and quickly It is about a method.

일반적으로 현수교나 사장교의 주탑은 일반 교량의 교각들과 달리 교량상판의 위쪽으로 더욱 연장된 구조로 이루어져서 주탑 상부에서 와이어나 체인 등 케이블 구조의 연결력으로 교량상판을 잡아주는 구조로 이루어진다.In general, the main tower of the suspension bridge or cable-stayed bridge, unlike the bridges of general bridges, is made of a structure that extends further upwards of the bridge deck to hold the bridge deck by the connection force of the cable structure such as wires or chains at the top of the tower.

상기와 같은 주탑은 여러 가지 형태의 구조가 있지만 대부분 교량의 폭 방향과 대응하도록 간격을 띄우고 제1 레그부 및 제2 레그부가 세워진 상태로 형성된 콘크리트 구조물 형태를 이루면서, 교량의 길이 방향으로 적어도 두 군데 이상의 지점에 형성된다.The main column as described above has a structure of various forms, but at least two places in the longitudinal direction of the bridge while forming a concrete structure formed with the first leg portion and the second leg portion spaced apart to correspond to the width direction of most bridges It is formed at the above point.

그리고 주탑을 시공하는 작업은, 기 출원된 등록특허 제10-1047527호(주탑 시공용 이동식 거푸집장치)에 개시된 바와 같은 거푸집 장치를 간격을 띄우고 배치한 상태에서 하부에서 상부를 향하여 거푸집 장치를 순차적으로 옮겨가면서 시공하는 방식으로 진행된다.And the construction work of the pylon, the formwork device as disclosed in the previously registered Patent No. 10-1047527 (movable formwork for the pylon construction) spaced apart the arrangement of the formwork device from the bottom toward the top sequentially The construction is carried out by moving.

그런데 이러한 방식으로 주탑을 시공할 때에는, 하부에서 타설된 콘크리트가 완전히 경화되어야만 거푸집 장치를 하부에서 상부로 옮긴 후 시공을 이어갈 수 있었다. 이와 같이 전 공정이 완료되어야만 다음 공정을 진행할 수 있기 때문에 공사기간이 길어지고, 비용이 증가하는 원인이 된다. By the way, when constructing the main tower in this way, the concrete poured from the bottom must be completely cured to move the formwork from the bottom to the top and then continue the construction. In this way, only the entire process is completed, so that the next process can proceed, resulting in a long construction period and an increase in costs.

또한, 거푸집 장치에는 작업자용 발판이 구비되어 있어 거푸집 장치를 상부로 옮긴 후 시공을 이어갈 때, 하부와 상부의 철근을 연결하는 작업 등이 작업자용 발판에서 이루어지는데 이때 작업자가 발판에서 추락하는 안전사고가 발생되는 문제점도 있었다.In addition, the formwork device is equipped with a footrest for the worker, when moving the formwork to the upper part and continue construction, connecting the reinforcing bar of the lower part and the upper part is performed on the footrest for the worker, in which case the worker falls from the footrest. There was also a problem that occurred.

대한민국등록특허 제10-0904516호Korea Patent Registration No. 10-0904516

본 발명은 공사기간을 단축하며, 안전하고 신속하게 주탑을 시공할 수 있는 장대교량 주탑용 철근 선시공 작업대 및 이를 이용하는 시공방법을 제공하는 것을 목적으로 한다.It is an object of the present invention to shorten the construction period, and to provide a reinforcement work platform for the long bridge bridge pylon can be constructed safely and quickly and the construction method using the same.

본 발명은, 장대교량의 주탑의 철근을 선시공할 수 있도록 상승형 거푸집의 상측에 설치되는 장대교량 주탑용 철근 선시공 작업대에 있어서, 작업자가 철근 시공 작업을 위해 이동할 수 있는 이동경로를 형성하는 발판 플레이트와, 상기 발판 플레이트의 일측에 상기 발판 플레이트와 교차하는 방향을 연결되어 상기 작업자의 추락을 방지하는 난간을 포함하는 작업유닛; 및 상기 작업유닛을 상기 상승형 거푸집과 연결시키며, 상기 작업유닛의 높이를 조절할 수 있도록 상기 작업유닛의 하측에 적어도 하나 이상 구비되는 위치조절유닛을 포함하며, 상기 장대교량 주탑용 철근 선시공 작업대는 하나 이상의 상기 위치조절유닛 상에 상기 작업유닛이 결합된 작업대 단위 모듈로 이루어지되, 상기 작업대 단위 모듈이 복수 개가 수평방향으로 연결되어 상기 철근을 설치하기 위한 작업공간을 형성하는 장대교량 주탑용 철근 선시공 작업대를 제공한다.The present invention is a reinforcement work platform for pole bridge pylons installed on the upper side of the elevated formwork so as to be able to pre-install the reinforcement of the pylons of the long bridge, the scaffolding plate to form a moving path that can be moved by the worker for the construction work And a work unit connected to one side of the scaffolding plate in a direction intersecting with the scaffolding plate to prevent a fall of the worker; And a position adjusting unit which connects the work unit with the raised formwork and has at least one lower side of the work unit to adjust the height of the work unit, wherein the reinforcement construction work platform for the pole bridge main column is at least one. The work unit unit module is coupled to the work unit on the position control unit, the work unit unit module is connected to the plurality of horizontal direction to form a work space for installing the reinforcing bar bridge pylon reinforcement work platform to provide.

본 발명의 다른 측면에 따르면, 본 발명은, 장대교량의 주탑의 철근을 선시공할 수 있도록 상승형 거푸집의 상측에 설치되는 장대교량 주탑용 철근 선시공 작업대를 이용하는 시공방법에 있어서, a) 상기 상승형 거푸집의 상측에 상기 장대교량 주탑용 철근 선시공 작업대를 설치하는 단계; b) 기초 또는 상기 상승형 거푸집 내부에 타설된 콘크리트가 양생되면, 상기 주탑의 뼈대를 이루는 철근을 설치하는 단계; c) 상기 상승형 거푸집을 설정 높이만큼 상승시키는 단계; d) 상기 장대교량 주탑용 철근 선시공 작업대를 해체하는 단계; e) 상기 상승형 거푸집 내부로 콘크리트를 타설하는 단계; 및 f) 상기 콘크리트가 타설된 후 설정 시간이 지나면, 해제한 상기 장대교량 주탑용 철근 선시공 작업대를 조립하는 단계를 포함하며, 상기 b) 단계 내지 상기 f) 단계를 한번 이상 반복하고, 상기 장대교량 주탑용 철근 선시공 작업대는, 작업자가 철근 시공 작업을 위해 이동할 수 있는 이동경로를 형성하는 발판 플레이트와, 상기 발판 플레이트의 일측에 상기 발판 플레이트와 교차하는 방향을 연결되어 상기 작업자의 추락을 방지하는 난간을 포함하는 작업유닛; 및 상기 작업유닛을 상기 상승형 거푸집과 연결시키며, 상기 작업유닛의 높이를 조절할 수 있도록 상기 작업유닛의 하측에 적어도 하나 이상 구비되는 위치조절유닛을 포함하며, 상기 a) 단계에서는, 상기 장대교량 주탑용 철근 선시공 작업대는 하나 이상의 상기 위치조절유닛 상에 상기 작업유닛이 결합된 작업대 단위 모듈로 이루어지되, 상기 작업대 단위 모듈이 복수 개가 수평방향으로 연결되어 상기 철근을 설치하기 위한 작업공간을 형성하는 장대교량 주탑용 철근 선시공 작업대를 이용한 시공방법을 제공한다. According to another aspect of the present invention, the present invention, in the construction method using a reinforcement work platform for the long bridge pylons installed on the upper side of the formwork to be able to pre-install the reinforcement of the pylons of the long bridge, a) the Installing a reinforcing work platform for the long bridge main column; b) installing the reinforcing bars forming the skeleton of the pylon when the concrete poured in the foundation or the raised formwork is cured; c) raising the raised formwork by a set height; d) dismantling the reinforcement work platform for the main bridge bridge tower; e) pouring concrete into the raised formwork; And f) assembling the reinforcement work platform for the pole bridge pylon which has been released after a set time has passed after the concrete has been poured, repeating steps b) to f) one or more times, and the pole bridge. The reinforcement work platform for the main tower includes a scaffold plate for forming a moving path through which the worker can move for rebar construction work, and a railing connected to one side of the scaffold plate to cross the scaffold plate to prevent the worker from falling. A work unit comprising a; And a position adjusting unit connected to the work unit with the raised formwork and provided with at least one lower side of the work unit to adjust the height of the work unit, wherein in the step a), Reinforcement work platform is composed of a workbench unit module coupled to the work unit on one or more of the position control unit, a plurality of the workbench unit modules are connected in the horizontal direction to form a work bridge for installing the reinforcing bars Provides construction method using reinforcement work platform for pylon.

본 발명에 따른 장대교량 주탑용 철근 선시공 작업대 및 이를 이용하는 시공방법은 다음과 같은 효과가 있다. Reinforcement construction work platform for pole bridge main column according to the present invention and the construction method using the same has the following effects.

첫째, 장대교량 주탑용 철근 선시공 작업대를 이용하여 타설된 콘크리트가 완전히 경화되기 전, 새롭게 연장되는 주탑의 철근들을 연결 설치하고 상승형 거푸집을 상승시켜 연장 콘크리트를 타설하기 때문에 장대교량의 주탑 전체를 시공하는 공사기간을 단축하는 효과를 얻을 수 있다. First, before the concrete is completely hardened by using the reinforcement construction work platform for the pole bridge pylon, the reinforcing bars of the newly extended pylon are connected and the elevated formwork is raised to build the extension concrete. The effect of shortening the construction period can be obtained.

둘째, 장대교량 주탑용 철근 선시공 작업대가 작업유닛과 하나 이상의 위치조절유닛이 결합된 작업대 단위 모듈로 이루어지므로 다양한 크기의 주탑에 대응하여 장대교량 주탑용 철근 선시공 작업대의 크기를 변경할 수 있다. Second, since the reinforcement construction work platform for the long bridge bridge is made of a workbench unit module combined with a work unit and one or more position control units, it is possible to change the size of the reinforcement work platform for the long bridge bridge pylons in response to various sizes of pylons.

도 1에는 본 발명의 일 실시예에 따른 장대교량 주탑용 철근 선시공 작업대가 도시된 개략 도이다.
도 2 내지 도 6에는 도 1에 따른 투잡용 철근 선시공 작업대의 구성이 도시된 개략도이다.
도 7에는 본 발명의 일 실시예에 따른 장대교량 주탑용 철근 선시공 작업대를 이용한 시공방법이 도시된 블록도이다.
도 8 내지 도 15에는 도 7의 시공방법에 따른 시공과정이 도시된 개략도이다.
Figure 1 is a schematic diagram showing a reinforcement construction work platform for pole bridge pylon according to an embodiment of the present invention.
2 to 6 is a schematic view showing the configuration of the reinforcing rod construction work platform for FIG.
Figure 7 is a block diagram showing the construction method using the reinforcement construction work platform for pole bridge main column according to an embodiment of the present invention.
8 to 15 is a schematic diagram showing the construction process according to the construction method of FIG.

도 1 내지 도 15에는 본 발명에 따른 장대교량 주탑용 철근 선시공 작업대 및 이를 이용하는 시공방법에 대해 도시되어 있다.1 to 15 are shown for the reinforcement construction work platform for pole bridge main column according to the present invention and a construction method using the same.

먼저, 도 1 내지 도 6을 참조하여 본 발명의 일 실시예에 따른 장대교량 주탑용 철근 선시공 작업대(1000)를 설명하면 다음과 같다. 상기 장대교량 주탑용 철근 선시공 작업대(1000)는 주탑을 시공하기 위한 상승형 거푸집(10)의 상측에 설치된다. 본 발명의 일 실시예에 따른 상기 장대교량 주탑용 철근 선시공 작업대(1000)에 대한 구체적인 설명에 앞서, 상기 상승형 거푸집(10)을 간략히 설명하여 보면 다음과 같다.First, referring to FIGS. 1 to 6, a reinforcing work platform 1000 for a long bridge main pylon according to an embodiment of the present invention will be described. The reinforcement construction work platform 1000 for the main bridge bridge tower is installed on the upper side of the raised formwork (10) for the construction of the main tower. Prior to the detailed description of the reinforcement construction work platform 1000 for the long bridge bridge main tower according to an embodiment of the present invention, briefly described the rise formwork 10 as follows.

상기 상승형 거푸집(10)은 콘크리트가 타설되는 거푸집(15)과, 상기 거푸집(15)을 상승시키는 유압장비유닛(13, 11) 및 상기 거푸집(15)의 상측에 작업자가 철근 연결 작업을 할 수 있는 발판(17)을 포함한다. 이와 같은 구성의 상기 상승형 거푸집(10)의 상측에 상기 장대교량 주탑용 철근 선시공 작업대(1000)가 설치된다.The raised formwork 10 is a formwork to the concrete 15, the hydraulic equipment unit (13, 11) for raising the formwork 15 and the worker on the upper side of the formwork 15 can be connected to the reinforcing bar And a footrest 17. On the upper side of the raised formwork 10 of such a configuration, the reinforcement construction work platform 1000 for the long bridge main column is installed.

상기 장대교량 주탑용 철근 선시공 작업대(1000)는 작업유닛(110), 위치조절유닛(130, 150)을 포함하는 작업대 단위 모듈(100)로 이루어진다. The pole bridge reinforcement construction work platform for the main tower 1000 is composed of a work unit unit module 100 including a work unit 110, the position adjusting units (130, 150).

보다 구체적으로 설명하면, 상기 작업유닛(110)은 발판 플레이트(111)와 난간(113)을 포함한다. 상기 발판 플레이트(111)는 작업자가 장대교량 주탑용 철근을 시공할 수 있도록 이동경로를 제공하는 것으로, 일반적으로 직사각형의 평면 플레이트로 형성된다. In more detail, the work unit 110 includes a scaffold plate 111 and a railing 113. The scaffold plate 111 provides a moving path for the operator to construct the reinforcing bar for the long bridge pylon, generally formed of a rectangular flat plate.

상기 난간(113)은 상기 발판 플레이트(111)의 일측에 상기 발판 플레이트(111)와 교차하는 방향으로 형성된다. 상기 난간(113)은 상기 발판 플레이트(111) 상에서 이동하며 작업하는 작업자가 추락하는 것을 방지한다. 상기 난간(113)은 예시적으로 복수 개의 프레임(113a, 113b)들을 수직방향 및 수평방향으로 배치하고 연결하여 형성한다. 그러나 이러한 구조적 특징은 본 실시예에 한정되는 것일 뿐 다양한 구조적 특징을 갖도록 형성될 수 있다.The handrail 113 is formed in a direction crossing the scaffold plate 111 on one side of the scaffold plate 111. The handrail 113 moves on the scaffold plate 111 and prevents the worker from falling. For example, the railing 113 is formed by arranging and connecting the plurality of frames 113a and 113b in a vertical direction and a horizontal direction. However, these structural features are only limited to the present embodiment and may be formed to have various structural features.

상기 위치조절유닛(130, 150)은 상기 작업유닛(110)의 하측에 구비되어 상승형 거푸집(10)과 상기 작업유닛(110)을 연결한다. 상기 위치조절유닛(130, 150)은 적어도 하나 이상 구비된다. 본 실시예에서는 도면을 참조하는 바와 같이 두 개의 상기 위치조절유닛(130, 150)이 구비된다. The position adjusting unit (130, 150) is provided on the lower side of the work unit 110 to connect the raised formwork 10 and the work unit (110). The position adjusting unit (130, 150) is provided with at least one. In the present embodiment, two position adjusting units 130 and 150 are provided as shown in the drawings.

본 실시예에서 하나의 상기 위치조절유닛은 복수 개의 프레임(131, 133, 151, 153)들을 직육면체 형상이 되도록 수평방향 및 수직방향을 배치하고 조립하여 형성된다. 그러나 상기 위치조절유닛이 직육면체 형상으로 형성되는 것은 본 실시예에 한정되는 것이므로 다양한 형상으로 형성될 수 있다. In the present embodiment, the one position adjusting unit is formed by arranging and assembling a horizontal direction and a vertical direction to form a plurality of frames 131, 133, 151, and 153 in a rectangular parallelepiped shape. However, since the position adjusting unit is formed in a rectangular parallelepiped shape, the position adjusting unit may be formed in various shapes.

한편, 본 실시예에서는 모든 상기 위치조절유닛의 높이와 두께가 동일하게 형성된다. 그러나 각각의 상기 위치조절유닛의 폭은 다르게 형성된다.On the other hand, in this embodiment, the height and thickness of all the position adjusting unit is formed equal. However, the width of each positioning unit is formed differently.

상기 작업대 단위 모듈(100)은 본 실시예에서는 도 1을 참조하는 바와 같이 하나의 상기 작업유닛(110)의 하측에 두 개의 상기 위치조절유닛(130, 150)을 결합하여 이루어진다. 이와 같은 구성은 본 실시예에 한정되는 것이므로, 상기 위치조절유닛은 하나만 구비될 수도 있고 복수 개 구비될 수도 있다.The work bench unit module 100 is made by combining the two position adjusting units (130, 150) in the lower side of the work unit 110, as shown in Figure 1 in this embodiment. Since such a configuration is limited to the present embodiment, only one position adjusting unit may be provided or a plurality of position adjusting units may be provided.

즉, 상기 작업대 단위 모듈(100) 복수 개가 연결되어 주탑의 뼈대를 이루며, 콘크리트에 매립될 철근들을 설치하기 위한 작업공간(101)을 형성하면서 상기 장대교량 주탑용 철근 선시공 작업대(1000)가 제작된다. 도 4에는 본 실시예에 따른 상기 장대교량 주탑용 철근 선시공 작업대(1000)가 도시되어 있다.That is, the plurality of workbench unit modules 100 are connected to form a skeleton of the main tower, while forming the work space 101 for installing the reinforcing bars to be embedded in concrete, the reinforcement construction work platform 1000 for the long bridge bridge main tower is manufactured. . 4 shows the reinforcement construction work platform 1000 for the long bridge main column according to the present embodiment.

도 4를 참조하여 보면, 상기 작업대 단위 모듈(100a, 100b)이 수평방향으로 연속되며 연결되어 상호 마주하는 한 쌍의 제1 면(1001)과 제2 면(1003)을 형성하고, 상기 작업대 단위 모듈(100c)이 수평방향을 연속되며 연결되어 상호 마주하는 한 쌍의 제3 면(1005)과 제4 면(1007)을 형성한다. 그리고 상기 제3 면(1005)과 상기 제4 면(1007)이 상기 제1 면(1001)과 상기 제2 면(1003)의 연결하여 작업공간(101)이 형성된 상기 장대교량 주탑용 철근 선시공 작업대(1000)를 형성한다.Referring to FIG. 4, the work platform unit modules 100a and 100b are connected in a horizontal direction to form a pair of first and second surfaces 1001 and 1003 facing each other, and the work platform unit The module 100c is connected in a horizontal direction and forms a pair of third and fourth surfaces 1005 and 1007 facing each other. In addition, the third surface 1005 and the fourth surface 1007 connect the first surface 1001 and the second surface 1003 to form a work space 101. To form 1000.

한편, 상기 장대교량 주탑용 철근 선시공 작업대(1000)는 보조 발판유닛(200)을 더 포함한다. 상기 보조 발판유닛(200)은 상기 작업대 단위 모듈(100)들에 의해 형성된 상기 작업공간에서 작업자가 작업할 수 있도록 상기 작업대 단위 모듈(100) 내측에 결합된다.On the other hand, the reinforcement construction work platform 1000 for the main bridge bridge further includes an auxiliary scaffolding unit 200. The auxiliary scaffolding unit 200 is coupled to the inside of the workbench unit module 100 so that an operator can work in the work space formed by the workbench unit modules 100.

상기 보조 발판유닛(200)은 보조 발판 플레이트(210)와 보조 브라켓(230, 250)을 포함한다. 상기 보조 발판 플레이트(210)는 상기 발판 플레이트(111)와 나란하게 결합되는 것으로 상기 발판 플레이트(111)와 마찬가지로 예를 들면 직사각형의 평면 플레이트로 형성된다. The auxiliary scaffolding unit 200 includes an auxiliary scaffolding plate 210 and auxiliary brackets 230 and 250. The auxiliary scaffold plate 210 is coupled to be parallel to the scaffold plate 111 and is formed of, for example, a rectangular flat plate like the scaffold plate 111.

상기 보조 브라켓(230, 250)은 상기 보조 발판 플레이트(210)의 하측에 구비며, 상기 위치조절유닛(130, 150)에 결합되어 상기 보조 발판유닛(200)을 고정한다. 상기 보조 브라켓(230, 250)은 상기 보조 발판 플레이트(210)의 하측에 상기 보조 발판 플레이트(210)와 수직방향으로 배치되는 제1 보조 브라켓(250)과, 상기 보조 발판 플레이트(210)의 하측에 상기 보조 발판 플레이트(210)에 대해 대각선 방향으로 배치되는 제2 보조 브라켓(230)을 포함한다.The auxiliary brackets 230 and 250 are provided at the lower side of the auxiliary scaffolding plate 210 and are coupled to the position adjusting units 130 and 150 to fix the auxiliary scaffolding unit 200. The auxiliary brackets 230 and 250 may include a first auxiliary bracket 250 disposed vertically with the auxiliary scaffold plate 210 at a lower side of the auxiliary scaffold plate 210 and a lower side of the auxiliary scaffold plate 210. The second auxiliary bracket 230 is disposed in a diagonal direction with respect to the auxiliary scaffold plate 210.

상기 제1 보조 브라켓(250)과 상기 제2 보조 브라켓(230)이 상기 보조 발판 플레이트(210)를 지지하면서 상기 위치조절유닛(130, 150)에 결합되어 상기 보조 발판유닛(200)을 고정시키는 것이다.The first auxiliary bracket 250 and the second auxiliary bracket 230 are coupled to the position adjusting units 130 and 150 while supporting the auxiliary scaffold plate 210 to fix the auxiliary scaffolding unit 200. will be.

한편, 상기 보조 발판 플레이트(210)는 상기 보조 브라켓(230, 250)들을 제외한 단독으로 상기 위치조절유닛(130, 150)에 설치될 수도 있다. 상기 보조 발판 플레이트(210)가 상기 위치조절유닛(130, 150)에 결합됨으로써 작업자가 상기 주철근(1)들을 고정시키는 띠철근(3)들의 설치 작업을 보다 편리하게 진행할 수 있다.On the other hand, the auxiliary scaffold plate 210 may be installed in the position adjusting unit (130, 150) alone except for the auxiliary bracket (230, 250). Since the auxiliary scaffold plate 210 is coupled to the position adjusting units 130 and 150, a worker may perform the installation work of the band reinforcing bars 3 to fix the main reinforcing bars 1 more conveniently.

상기 장대교량 주탑용 철근 선시공 작업대(1000)는 적어도 하나 이상의 철근 지지프레임(310, 330)을 더 포함한다. 상기 철근 지지프레임(310, 330)은 상기 제1 면(1001)과 상기 제2 면(1003)을 연결하거나 상기 제3 면(1005)과 상기 제4 면(1007)을 연결하며, 상기 작업공간(101)에 구비되어 상기 철근(1)의 일측이 연결되어 상기 철근(1)을 지지한다. The reinforcement construction work platform 1000 for the long bridge main column further includes at least one reinforcing bar support frame 310 or 330. The reinforcing support frames 310 and 330 connect the first surface 1001 and the second surface 1003 or the third surface 1005 and the fourth surface 1007, and the workspace It is provided at 101 and one side of the reinforcing bar 1 is connected to support the reinforcing bar (1).

본 실시예에서는 도 6을 참조하는 바와 같이, 두 개의 상기 철근 지지프레임(310, 330)들을 포함하며, 하나는 상기 제1 면(1001)과 상기 제2 면(1003)을 연결하고 다른 하나는 상기 제3 면(1005)과 상기 제4 면(1007)을 연결한다.In this embodiment, as shown in FIG. 6, two reinforcing support frames 310 and 330 are included, one connecting the first surface 1001 and the second surface 1003 and the other The third surface 1005 and the fourth surface 1007 are connected to each other.

상기 철근(1)은 일측이 기초에 매립된 철근의 단부 또는 전 시공단계에서 콘크리트에 매립된 철근의 단부와 연결되며, 상기 철근(1)의 타측이 상기 철근 지지프레임(310, 330)에 연결되어 고정된다. 특히, 주탑의 형상에 따라 상기 철근(1)은 기울어져 설치되는데, 상기 철근(1)의 타측이 상기 철근 지지프레임(310, 330)에 연결됨으로써 상기 철근(1)의 기울기를 유지할 수 있다.The reinforcing bar 1 is connected to the end of the reinforcing bar embedded in one side or the end of the reinforcing bar embedded in concrete in the pre-construction step, the other side of the reinforcing bar 1 is connected to the reinforcing support frame (310, 330) Is fixed. In particular, the reinforcing bar 1 is installed inclined according to the shape of the main column, the other side of the reinforcing bar 1 is connected to the reinforcing support frame 310, 330 can maintain the inclination of the reinforcing bar (1).

한편, 상기 철근 지지프레임(310, 330)은 양 측 각각이 절곡되어 있다. 그리고 상기 발판 플레이트(111)에는 상기 발판 플레이트(111)의 길이방향을 따라 연장되며 오목한 홈(111a)이 형성되어 있어, 상기 철근 지지프레임(310, 330)의 절곡된 일측이 상기 홈(111a)에 끼워져 고정된다. 이와 같은 상기 철근 지지프레임(310, 330)의 고정 구조는 본 실시예에 한정되는 것일 뿐이므로 다양한 방법으로 상기 철근 지지프레임(310, 330)이 고정될 수 있다.On the other hand, the reinforcing support frames 310 and 330 are bent at both sides, respectively. In addition, the scaffold plate 111 extends along the longitudinal direction of the scaffold plate 111 and is formed with a concave groove 111a, so that one side of the reinforcing support frames 310 and 330 is bent into the groove 111a. It is fitted in and fixed. Since the fixing structure of the reinforcing support frames 310 and 330 is limited to the present embodiment, the reinforcing support frames 310 and 330 may be fixed in various ways.

한편, 도면에는 도시되지 않았으나 상기 작업유닛(111)은 상기 위치조절유닛(130, 150) 상에서 수평방향으로 이동하여 작업자의 작업 위치를 조정할 수 있다. 또한, 상기 작업대 단위 모듈(100)의 외측에는 안전망을 설치하여 작업자의 추락을 방지할 수 있다. On the other hand, although not shown in the drawing, the work unit 111 may move in a horizontal direction on the position adjusting units 130 and 150 to adjust the work position of the worker. In addition, by installing a safety net on the outside of the work unit unit module 100 can prevent the fall of the worker.

이하에서는 도 7 내지 도 15를 참조하여 상기 장대교량 주탑용 철근 선시공 작업대(1000)를 이용하여 시공하는 방법에 대해 설명한다.Hereinafter, with reference to FIGS. 7 to 15 will be described a method of construction using the reinforcement construction work platform 1000 for the long bridge main column.

상기 장대교량 주탑용 철근 선시공 작업대(1000)를 이용하여 시공하기 위해서는 먼저, 상승형 거푸집(10)의 상측에 상기 장대교량 주탑용 철근 선시공 작업대(1000)를 설치한다.(S105) 상기 장대교량 주탑용 철근 선시공 작업대(1000)의 외측에는 안전망을 설치하여 작업자가 상기 장대교량 주탑용 철근 선시공 작업대(1000)에서 추락하는 등의 안전사고 발생을 예방할 수 있다.In order to construct using the reinforcement construction work platform 1000 for the long bridge bridge, first, install the reinforcement construction work platform for the long bridge bridge pylon on the upper side of the climbing formwork (S105). Safety nets are installed on the outside of the reinforcement work platform 1000 to prevent a worker from falling down from the reinforcement work platform 1000 for the long bridge bridge pylon.

전술한 바와 같이, 상기 장대교량 주탑용 철근 선시공 작업대(1000)는 상기 작업유닛(110)과, 상기 위치조절유닛(130, 150)이 결합된 작업대 단위 모듈(100)을 크레인으로 인양하여 상기 상승형 거푸집(10) 상측에 설치한다.As described above, the reinforcement construction work platform 1000 for the main bridge bridge lift the work unit unit 100, the work unit 110 and the position control unit (130, 150) coupled to the lifting type by the crane It is installed above the formwork (10).

상기 장대교량 주탑용 철근 선시공 작업대(1000)가 설치되면, 기초 또는 이전 공정에서 콘크리트가 타설된 후 설정 시간이 지나면 상기 철근 지지프레임(310, 330)을 상기 장대교량 주탑용 철근 선시공 작업대(1000)에 조립하고(S110), 기초 또는 이전 공정에서 설치되어 콘크리트에 매립된 주철근과 새롭게 설치될 주철근(1)과 상기 주철근(1)들을 고정시키는 띠철근(3)들을 설치한다.(S115) When the reinforcement construction work platform 1000 for the main bridge bridge is installed, the reinforcing support work platform for the reinforcement bridge for the main bridge bridge (310, 330) after a predetermined time after the concrete is poured in the foundation or the previous process Assembled in (S110), and installed in the foundation or the previous process to install the cast iron reinforcement and the cast iron reinforcement (1) and the reinforcing bars (3) for fixing the cast iron (1) to be newly installed (S115).

상기 주철근(1)들과 상기 띠철근(3)들을 설치하기 위해서는 상기 작업공간(101)에 상기 보조 발판유닛(200)을 설치하거나 상기 위치조절유닛(130, 150)에 상기 보조 발판 플레이트(210)를 설치할 수 있다.In order to install the main reinforcing bars (1) and the band reinforcing bars (3), the auxiliary scaffolding unit 200 is installed in the work space 101 or the auxiliary scaffolding plate 210 in the position adjusting units (130, 150). ) Can be installed.

그리고 상기 주철근(1)의 타측은 상기 철근 지지프레임(310, 330)에 연결되어 상기 주철근(1)의 기울기를 유지할 수 있다.The other side of the main reinforcing bar 1 may be connected to the reinforcing bar supporting frames 310 and 330 to maintain the inclination of the main reinforcing bar 1.

상기 주철근(1)들과 상기 띠철근(3)들의 설치가 완료되면, 상기 상승형 거푸집(10)을 설정 높이 상승한다.(S120) 그리고 상기 장대교량 주탑용 철근 선시공 작업대(1000)의 일부를 해체한다.(S125) 이때, 상기 작업대 단위 모듈(100a, 100b, 100c)들이 연결되어 형성된 상기 제1 면(1001), 상기 제2 면(1003), 상기 제3 면(1005) 및 상기 제4 면(1007)을 분리하여 해체하는 것이다. When the installation of the main reinforcing bars (1) and the band reinforcing bars (3) is completed, the raised formwork 10 is raised to a set height. (S120) And dismantle part of the reinforcement construction work platform for the pole bridge main tower (1000) In this case, the first surface 1001, the second surface 1003, the third surface 1005, and the fourth surface formed by connecting the work unit unit modules 100a, 100b, and 100c to each other. It is to disassemble and separate (1007).

상기 장대교량 주탑용 철근 선시공 작업대(1000)가 해체되면 호퍼를 통해 콘크리트를 상기 상승형 거푸집(10)의 내부로 타설한다. 상기 콘크리트에 의해 상기 주철근(1)들과 상기 띠철근(3)들이 매립되는데, 이때 상기 주철근(1)의 상측 일부는 다음 공정에서 새로운 주철근(1)들과 연결될 수 있도록 콘크리트의 외부로 노출시킨다.When the reinforcement construction work platform 1000 for the long bridge main column is dismantled, the concrete is poured into the inside of the raised formwork 10 through a hopper. The main reinforcing bars 1 and the band reinforcing bars 3 are embedded by the concrete, and the upper part of the main reinforcing bars 1 is exposed to the outside of the concrete to be connected to the new main reinforcing bars 1 in the next process. .

상기 콘크리트가 타설된 시점으로부터 설정 시간이 지나면 해체했던 상기 장대교량 주탑용 철근 선시공 작업대(1000)를 다시 조립한다.(S135) 그리고 상기 철근 지지프레임(310, 330)을 조립하는 단계(S110)부터 상기 콘크리트가 양생되면 상기 장대교량 주탑용 철근 선시공 작업대(1000)를 다시 조립하는 단계(S115)를 1회 이상 반복하면서 상기 주탑을 시공을 완료한다.After setting time elapses from the time when the concrete is poured, the assembled reinforcement work platform 1000 for the long bridge bridge pylon was disassembled again (S135) and assembling the reinforcing support frames 310 and 330 (S110). When the concrete is cured, repeating the step (S115) of re-assembling the reinforcement construction work platform 1000 for the main bridge bridge to complete the construction of the main tower.

본원발명의 장대교량 주탑용 철근 선시공 조립대와 이를 이용하는 시공방법으로 주탑을 시공하면, 공사기간을 단축시키는 효과를 갖는다. 종래에는 주탑의 일부를 먼저 시공하고 상기 주탑의 일부 상측에서 다시 주탑의 일부를 연장 시공하기 위해서는 하측에 먼저 시공된 주탑의 일부가 완전히 양생될 때까지 대기해야 했기 때문에 낭비되는 시간이 많았다. 그러나 본 발명에 따른 장대교량 주탑용 철근 선시공 작업대를 이용하면, 하측에 주탑의 일부를 시공한 뒤 먼저 시공된 주탑의 일부가 완전히 양생되기 전, 새로운 철근(주철근 및 띠철근)들을 시공할 수 있고 먼저 시공된 주탑의 일부가 완전히 양생된 후에는 콘크리트를 타설하기만 하면 되므로 시공속도가 빨라지는 효과를 갖는다. 따라서 공사기간을 단축하는 효과를 갖게 된다.When constructing the main tower by the reinforcement pre-assembly assembly pole for the main bridge bridge tower of the present invention and the construction method using the same, it has the effect of shortening the construction period. In the related art, in order to construct a part of the main tower first, and to extend a part of the main tower again from the upper part of the main tower, a lot of time was wasted because it had to wait until the part of the main tower constructed below was completely cured. However, using the reinforcement construction work platform for the pole bridge main column according to the present invention, after the construction of a part of the main tower on the lower side before the first part of the main tower is completely cured, new reinforcing bars (cast reinforcing bars and strips) can be constructed First of all, the construction of the main tower is completely cured. Therefore, the construction period is shortened.

본 발명은 도면에 도시된 실시예를 참고로 설명되었으나 이는 예시적인 것에 불과하며, 본 기술 분야의 통상의 지식을 가진 자라면 이로부터 다양한 변형 및 균등한 다른 실시예가 가능하다는 점을 이해할 것이다. 따라서 본 발명의 진정한 기술적 보호 범위는 첨부된 특허청구범위의 기술적 사상에 의하여 정해져야 할 것이다.Although the present invention has been described with reference to the embodiments shown in the drawings, this is merely exemplary, and it will be understood by those skilled in the art that various modifications and equivalent other embodiments are possible. Therefore, the true technical protection scope of the present invention will be defined by the technical spirit of the appended claims.

1000: 장대교량 주탑용 철근 선시공 작업대
100, 100a, 100b, 100c: 작업대 단위 모듈
110: 작업유닛 111: 발판 플레이트
113: 난간 130, 150: 위치조절유닛
210: 보조 발판 플레이트 230, 250: 보조 브라켓
310, 330: 철근 지지프레임
1000: Reinforcement work platform for long bridge main column
100, 100a, 100b, 100c: workbench unit module
110: work unit 111: scaffolding plate
113: handrail 130, 150: position control unit
210: auxiliary scaffold plate 230, 250: auxiliary bracket
310, 330: Reinforcing bar support frame

Claims (11)

장대교량의 주탑의 철근을 선시공할 수 있도록 상승형 거푸집의 상측에 설치되는 장대교량 주탑용 철근 선시공 작업대에 있어서,
작업자가 철근 시공 작업을 위해 이동할 수 있는 이동경로를 형성하는 발판 플레이트와, 상기 발판 플레이트의 일측에 상기 발판 플레이트와 교차하는 방향을 연결되어 상기 작업자의 추락을 방지하는 난간을 포함하는 작업유닛; 및
상기 작업유닛을 상기 상승형 거푸집과 연결시키며, 상기 작업유닛의 높이를 조절할 수 있도록 상기 작업유닛의 하측에 적어도 하나 이상 구비되는 위치조절유닛을 포함하며,
상기 장대교량 주탑용 철근 선시공 작업대는 하나 이상의 상기 위치조절유닛 상에 상기 작업유닛이 결합된 작업대 단위 모듈로 이루어지되, 상기 작업대 단위 모듈이 복수 개가 수평방향으로 연결되어 상기 철근을 설치하기 위한 작업공간을 형성하고,
상기 장대교량 주탑용 철근 선시공 작업대는,
작업자가 상기 작업공간 내측으로 이동하여 작업할 수 있도록 상기 작업대 단위 모듈의 내측에 결합되되, 착탈 가능한 보조 발판유닛을 더 포함하는 장대교량 주탑용 철근 선시공 작업대.
In the reinforcement construction work platform for pole bridge pylon installed on the upper side of the rising formwork so that the reinforcement of the pylon tower of the pole bridge can be pre-installed,
A work unit including a scaffold plate forming a moving path through which a worker can move for reinforcing work, and a railing connected to one side of the scaffold plate to cross the scaffold plate to prevent the worker from falling; And
And a position adjusting unit connected to the work unit with the raised formwork and provided with at least one lower side of the work unit to adjust the height of the work unit.
The pole bridge reinforcement construction work platform for the main tower is composed of a work unit unit module coupled to the work unit on one or more of the position control unit, a plurality of work unit unit modules are connected in a horizontal direction to install the reinforcing bar Form the
The reinforcement construction work platform for the long bridge bridge tower,
Reinforcement construction work platform for the long bridge bridge pylon is coupled to the inside of the workbench unit module so that the worker can move to work inside the work space, the auxiliary scaffold unit removable.
청구항 1에 있어서,
상기 위치조절유닛은,
복수 개의 프레임들을 직육면체 형상이 되도록 수평방향 및 수직방향 배치하여 조립하는 장대교량 주탑용 철근 선시공 작업대.
The method according to claim 1,
The position adjusting unit,
A reinforcing work platform for reinforcing poles for a long bridge bridge, which assembles a plurality of frames in a horizontal and vertical direction so as to form a rectangular parallelepiped shape.
청구항 1에 있어서,
상기 장대교량 주탑용 철근 선시공 작업대는,
복수 개의 상기 작업대 단위 모듈들이 수평방향을 연속 연결되어 상호 마주하는 한 쌍의 제1 면 및 제2 면을 형성하고,
복수 개의 상기 작업대 단위 모듈들이 수평방향으로 연속 연결되어 상호 마주하는 한 쌍의 제3 면 및 제4면을 형성하며,
상기 제1 면과 상기 제2 면 각각이 상기 제3 면과 상기 제4 면을 연결하여 상기 작업공간을 형성하는 장대교량 주탑용 철근 선시공 작업대.
The method according to claim 1,
The reinforcement construction work platform for the long bridge bridge tower,
The plurality of workbench unit modules are continuously connected in a horizontal direction to form a pair of first and second surfaces facing each other,
A plurality of workbench unit modules are continuously connected in a horizontal direction to form a pair of third and fourth surfaces facing each other,
Reinforcement work platform for a long bridge bridge pylon for each of the first surface and the second surface is connected to the third surface and the fourth surface to form the working space.
삭제delete 청구항 1에 있어서,
상기 보조 발판유닛은,
상기 발판 플레이트에 나란하게 결합되는 보조 발판 플레이트; 및
상기 보조 발판 플레이트 하측에 구비되며, 상기 위치조절유닛의 내측에 결합되는 보조 브라켓을 포함하는 장대교량 주탑용 철근 선시공 작업대.
The method according to claim 1,
The auxiliary scaffolding unit,
An auxiliary scaffold plate coupled side by side to the scaffold plate; And
Reinforcement work platform for the long bridge bridge pylon is provided on the side of the auxiliary scaffold plate, including an auxiliary bracket coupled to the inner side of the positioning unit.
장대교량의 주탑의 철근을 선시공할 수 있도록 상승형 거푸집의 상측에 설치되는 장대교량 주탑용 철근 선시공 작업대에 있어서,
작업자가 철근 시공 작업을 위해 이동할 수 있는 이동경로를 형성하는 발판 플레이트와, 상기 발판 플레이트의 일측에 상기 발판 플레이트와 교차하는 방향을 연결되어 상기 작업자의 추락을 방지하는 난간을 포함하는 작업유닛; 및
상기 작업유닛을 상기 상승형 거푸집과 연결시키며, 상기 작업유닛의 높이를 조절할 수 있도록 상기 작업유닛의 하측에 적어도 하나 이상 구비되는 위치조절유닛을 포함하며,
상기 장대교량 주탑용 철근 선시공 작업대는 하나 이상의 상기 위치조절유닛 상에 상기 작업유닛이 결합된 작업대 단위 모듈로 이루어지되, 상기 작업대 단위 모듈이 복수 개가 수평방향으로 연결되어 상기 철근을 설치하기 위한 작업공간을 형성하고,
상기 장대교량 주탑용 철근 선시공 작업대는,
복수 개의 상기 작업대 단위 모듈들이 수평방향을 연속 연결되어 상호 마주하는 한 쌍의 제1 면 및 제2 면을 형성하고,
복수 개의 상기 작업대 단위 모듈들이 수평방향으로 연속 연결되어 상호 마주하는 한 쌍의 제3 면 및 제4면을 형성하며,
상기 제1 면과 상기 제2 면 각각이 상기 제3 면과 상기 제4 면을 연결하여 상기 작업공간을 형성하고,
상기 장대교량 주탑용 철근 선시공 작업대는,
상기 제1 면과 상기 제2 면을 연결하거나 상기 제3면과 상기 제4 면을 연결하며, 상기 작업공간에 구비되어 상기 철근을 지지하도록 적어도 하나 이상의 철근 지지프레임을 더 포함하는 장대교량 주탑용 철근 선시공 작업대.
In the reinforcement construction work platform for pole bridge pylon installed on the upper side of the rising formwork so that the reinforcement of the pylon tower of the pole bridge can be pre-installed,
A work unit including a scaffold plate forming a moving path through which a worker can move for reinforcing work, and a railing connected to one side of the scaffold plate to cross the scaffold plate to prevent the worker from falling; And
And a position adjusting unit connected to the work unit with the raised formwork and provided with at least one lower side of the work unit to adjust the height of the work unit.
The pole bridge reinforcement construction work platform for the main tower is composed of a work unit unit module coupled to the work unit on one or more of the position control unit, a plurality of work unit unit modules are connected in a horizontal direction to install the reinforcing bar Form the
The reinforcement construction work platform for the long bridge bridge tower,
The plurality of workbench unit modules are continuously connected in a horizontal direction to form a pair of first and second surfaces facing each other,
A plurality of workbench unit modules are continuously connected in a horizontal direction to form a pair of third and fourth surfaces facing each other,
Each of the first and second surfaces connects the third and fourth surfaces to form the workspace.
The reinforcement construction work platform for the long bridge bridge tower,
Long bridge bridge main tower for connecting the first surface and the second surface or the third surface and the fourth surface, and further comprising at least one reinforcing bar supporting frame provided in the workspace to support the reinforcing bar Rebar construction work bench.
청구항 6에 있어서,
상기 발판 플레이트의 일측에는 길이방향을 따라 길게 연장되는 홈이 형성되고,
상기 철근 지지프레임의 단부가 상기 홈에 끼워져 고정되는 장대교량 주탑용 철근 선시공 작업대.
The method according to claim 6,
One side of the scaffold plate is formed with a groove extending in the longitudinal direction,
Reinforcement work platform for the long bridge bridge pylon is fixed to the end of the reinforcing bar supporting frame is inserted into the groove.
장대교량의 주탑의 철근을 선시공할 수 있도록 상승형 거푸집의 상측에 설치되는 장대교량 주탑용 철근 선시공 작업대를 이용하는 시공방법에 있어서,
a) 상기 상승형 거푸집의 상측에 상기 장대교량 주탑용 철근 선시공 작업대를 설치하는 단계;
b) 기초 또는 상기 상승형 거푸집 내부에 타설된 콘크리트가 양생되면, 상기 주탑의 뼈대를 이루는 철근을 설치하는 단계;
c) 상기 상승형 거푸집을 설정 높이만큼 상승시키는 단계;
d) 상기 장대교량 주탑용 철근 선시공 작업대를 해체하는 단계;
e) 상기 상승형 거푸집 내부로 콘크리트를 타설하는 단계; 및
f) 상기 콘크리트가 타설된 후 설정 시간이 지나면, 해제한 상기 장대교량 주탑용 철근 선시공 작업대를 조립하는 단계를 포함하며,
상기 b) 단계 내지 상기 f) 단계를 한번 이상 반복하고,
상기 장대교량 주탑용 철근 선시공 작업대는,
작업자가 철근 시공 작업을 위해 이동할 수 있는 이동경로를 형성하는 발판 플레이트와, 상기 발판 플레이트의 일측에 상기 발판 플레이트와 교차하는 방향을 연결되어 상기 작업자의 추락을 방지하는 난간을 포함하는 작업유닛; 및
상기 작업유닛을 상기 상승형 거푸집과 연결시키며, 상기 작업유닛의 높이를 조절할 수 있도록 상기 작업유닛의 하측에 적어도 하나 이상 구비되는 위치조절유닛을 포함하며,
상기 a) 단계에서는,
상기 장대교량 주탑용 철근 선시공 작업대는 하나 이상의 상기 위치조절유닛 상에 상기 작업유닛이 결합된 작업대 단위 모듈로 이루어지되, 상기 작업대 단위 모듈이 복수 개가 수평방향으로 연결되어 상기 철근을 설치하기 위한 작업공간을 형성하는 장대교량 주탑용 철근 선시공 작업대를 이용한 시공방법.
In the construction method using the reinforcement work platform for the pole bridge pylon installed on the upper side of the rising formwork so that the reinforcement of the pole tower of the pole bridge can be pre-installed,
a) installing the reinforcing work platform for the long bridge main column on the upper side of the raised formwork;
b) installing the reinforcing bars forming the skeleton of the pylon when the concrete poured in the foundation or the raised formwork is cured;
c) raising the raised formwork by a set height;
d) dismantling the reinforcement work platform for the main bridge bridge tower;
e) pouring concrete into the raised formwork; And
f) if the set time passes after the concrete is poured, assembling the reinforcement work platform for the pole bridge pylons released;
Repeat steps b) to f) one or more times;
The reinforcement construction work platform for the long bridge bridge tower,
A work unit including a scaffold plate forming a moving path through which a worker can move for reinforcing work, and a railing connected to one side of the scaffold plate to cross the scaffold plate to prevent the worker from falling; And
And a position adjusting unit connected to the work unit with the raised formwork and provided with at least one lower side of the work unit to adjust the height of the work unit.
In step a),
The pole bridge reinforcement construction work platform for the main tower is composed of a work unit unit module coupled to the work unit on one or more of the position control unit, a plurality of work unit unit modules are connected in a horizontal direction to install the reinforcing bar Construction method using the reinforcement work platform for the long bridge bridge pylon to form a.
청구항 8에 있어서,
상기 장대교량 주탑용 철근 선시공 작업대는,
복수 개의 상기 작업대 단위 모듈들이 수평방향을 연속 연결되어 상호 마주하는 한 쌍의 제1 면 및 제2 면을 형성하고,
복수 개의 상기 작업대 단위 모듈들이 수평방향으로 연속 연결되어 상호 마주하는 한 쌍의 제3 면 및 제4면을 형성하며,
상기 제1 면과 상기 제2 면 각각이 상기 제3 면과 상기 제4 면을 연결하여 상기 작업공간을 형성하고,
상기 제1 면과 상기 제2 면을 연결하거나 상기 제3면과 상기 제4 면을 연결하며, 상기 작업공간에 구비되어 상기 철근을 지지하도록 적어도 하나 이상의 철근 지지프레임을 더 포함하며,
상기 b) 단계를 실행하기 이전에 상기 철근 지지프레임을 상기 작업유닛에 연결하여 설치하는 장대교량 주탑용 철근 선시공 작업대를 이용한 시공방법.
The method according to claim 8,
The reinforcement construction work platform for the long bridge bridge tower,
The plurality of workbench unit modules are continuously connected in a horizontal direction to form a pair of first and second surfaces facing each other,
A plurality of workbench unit modules are continuously connected in a horizontal direction to form a pair of third and fourth surfaces facing each other,
Each of the first and second surfaces connects the third and fourth surfaces to form the workspace.
Further comprising at least one reinforcing bar supporting frame connecting the first surface and the second surface or connecting the third surface and the fourth surface, and is provided in the workspace to support the reinforcing bar,
Construction method using the reinforcement work platform for the long bridge bridge pylon to connect and install the reinforcing bar support frame to the work unit before the step b).
청구항 8에 있어서,
상기 장대교량 주탑용 철근 선시공 작업대는,
작업자가 상기 작업공간 내측으로 이동하여 작업할 수 있도록 상기 작업대 단위 모듈의 내측에 결합되되, 착탈 가능한 보조 발판유닛을 더 포함하며,
상기 b) 단계를 실행하는 동안, 상기 작업대 단위 모듈의 내측에 상기 보조 발판유닛을 설치하여 작업자가 상기 작업공간 내측으로 이동하며 상기 철근을 설치하는 장대교량 주탑용 철근 선시공 작업대를 이용한 시공방법.
The method according to claim 8,
The reinforcement construction work platform for the long bridge bridge tower,
Is coupled to the inside of the workbench unit module so that the worker can move to work inside the work space, and further comprises a removable auxiliary scaffolding unit,
During the step b), by installing the auxiliary scaffolding unit in the interior of the workbench unit module, the worker moves to the inside of the work space, the construction method using the reinforcement work platform for the pole bridge pylon for installing the reinforcing bar.
청구항 9에 있어서,
상기 b) 단계에서는,
기초 또는 상기 상승형 거푸집에 타설된 콘크리트로부터 상단이 돌출된 주철근에 새로운 주철근을 연결하고, 복수 개의 새로운 주철근을 고정시키는 띠철근을 연결 설치하며,
상기 띠철근을 연결 설치하기 위해 상기 위치조절유닛에 보조 발판 플레이트를 설치하는 장대교량 주탑용 철근 선시공 작업대를 이용한 시공방법.
The method according to claim 9,
In step b),
Connecting a new main reinforcing bar to the main reinforcing bar protruding from the concrete laid on the foundation or the rising formwork, and connecting the band reinforcing bars for fixing a plurality of new main reinforcing bars,
Construction method using the reinforcement work platform for the long bridge bridge pylon to install the auxiliary scaffold plate in the position adjustment unit to connect the band reinforcement.
KR1020170132363A 2017-10-12 2017-10-12 Modular work platform of a long span bridge main tower rebar and construction method using the same Active KR102059552B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020170132363A KR102059552B1 (en) 2017-10-12 2017-10-12 Modular work platform of a long span bridge main tower rebar and construction method using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020170132363A KR102059552B1 (en) 2017-10-12 2017-10-12 Modular work platform of a long span bridge main tower rebar and construction method using the same

Publications (2)

Publication Number Publication Date
KR20190041189A KR20190041189A (en) 2019-04-22
KR102059552B1 true KR102059552B1 (en) 2019-12-26

Family

ID=66283156

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020170132363A Active KR102059552B1 (en) 2017-10-12 2017-10-12 Modular work platform of a long span bridge main tower rebar and construction method using the same

Country Status (1)

Country Link
KR (1) KR102059552B1 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112663502B (en) * 2020-12-18 2022-06-17 中交第二航务工程局有限公司 Integral hoisting matching butt joint method for variable cross-section tower column segment steel bar part
CN112942107B (en) * 2021-01-13 2023-02-17 中铁七局集团武汉工程有限公司 Hydraulic creeping formwork construction process in cable tower construction process
CN114411564A (en) * 2022-02-25 2022-04-29 中交一公局第二工程有限公司 Novel guardrail steel bar installation device and construction method
CN114517449B (en) * 2022-03-22 2024-02-27 中铁大桥局第七工程有限公司 Cross-connection cross brace construction platform for arch bridge

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101641340B1 (en) * 2015-03-05 2016-07-20 서보산업 주식회사 Gang form cage having safety upper and lower worktable

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100904516B1 (en) 2009-03-02 2009-06-25 (주)신흥이앤지 Prefabricated Pylon and Construction Method

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101641340B1 (en) * 2015-03-05 2016-07-20 서보산업 주식회사 Gang form cage having safety upper and lower worktable

Also Published As

Publication number Publication date
KR20190041189A (en) 2019-04-22

Similar Documents

Publication Publication Date Title
KR100969992B1 (en) Pier Formwork System
KR101243775B1 (en) Apparatus of Constructing Bridge and Method of Constructing Bridge by Using the Same
KR101889064B1 (en) Construction method of a long span bridge main tower
JP3940211B2 (en) Construction method of horizontal beams for concrete main tower.
CN103243654B (en) Mounting method for steel anchor beam of cable-stayed bridge and assembly jig and cable bent tower mounting platform used in method
KR102059552B1 (en) Modular work platform of a long span bridge main tower rebar and construction method using the same
KR101101209B1 (en) Cantilevered part of bridge slab using precast permanent support and construction method
KR100968068B1 (en) How to form multiple horizontal structural members
CN102472050A (en) Sheet formwork system
KR101798539B1 (en) High Construction Pier Apparatus
TW202035837A (en) Beam and slab structure and construction method
JP4516585B2 (en) Internal staircase for building and its construction method
KR20200032316A (en) Method for Forming Top-down-typed Underground Strucutre using Trus-typed Support
KR102089758B1 (en) Formwork structure supported by column unit
JP2016204983A5 (en)
KR100997106B1 (en) Pier jig system
KR101140884B1 (en) Gangform device constructed for wall and constructing method this using
EP3403798B1 (en) Mobile structure and procedure for the prefabrication of desirably prestressed concrete bars
KR100966083B1 (en) Pier and the construction method for the same
KR100377868B1 (en) pier construction method using Pier scaffolding
KR102255700B1 (en) Truss footboard table apparatus
CN104372948A (en) Elevator shaft formwork lifting frame
KR101291517B1 (en) Composite girder construction method using t shape steel plate
KR101413725B1 (en) Supporting apparatus fo girder pannel
KR102786972B1 (en) Form auto climbing system having form setting frame, and concrete wall construction method using the same

Legal Events

Date Code Title Description
A201 Request for examination
PA0109 Patent application

St.27 status event code: A-0-1-A10-A12-nap-PA0109

PA0201 Request for examination

St.27 status event code: A-1-2-D10-D11-exm-PA0201

D13-X000 Search requested

St.27 status event code: A-1-2-D10-D13-srh-X000

D14-X000 Search report completed

St.27 status event code: A-1-2-D10-D14-srh-X000

PG1501 Laying open of application

St.27 status event code: A-1-1-Q10-Q12-nap-PG1501

E902 Notification of reason for refusal
PE0902 Notice of grounds for rejection

St.27 status event code: A-1-2-D10-D21-exm-PE0902

E13-X000 Pre-grant limitation requested

St.27 status event code: A-2-3-E10-E13-lim-X000

P11-X000 Amendment of application requested

St.27 status event code: A-2-2-P10-P11-nap-X000

P13-X000 Application amended

St.27 status event code: A-2-2-P10-P13-nap-X000

E701 Decision to grant or registration of patent right
PE0701 Decision of registration

St.27 status event code: A-1-2-D10-D22-exm-PE0701

GRNT Written decision to grant
PR0701 Registration of establishment

St.27 status event code: A-2-4-F10-F11-exm-PR0701

PR1002 Payment of registration fee

St.27 status event code: A-2-2-U10-U11-oth-PR1002

Fee payment year number: 1

PG1601 Publication of registration

St.27 status event code: A-4-4-Q10-Q13-nap-PG1601

R18-X000 Changes to party contact information recorded

St.27 status event code: A-5-5-R10-R18-oth-X000

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 4

R18-X000 Changes to party contact information recorded

St.27 status event code: A-5-5-R10-R18-oth-X000

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 5

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 6

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 7