KR20020005788A - mobile and fixative bridge maintaining system - Google Patents

mobile and fixative bridge maintaining system Download PDF

Info

Publication number
KR20020005788A
KR20020005788A KR1020000039182A KR20000039182A KR20020005788A KR 20020005788 A KR20020005788 A KR 20020005788A KR 1020000039182 A KR1020000039182 A KR 1020000039182A KR 20000039182 A KR20000039182 A KR 20000039182A KR 20020005788 A KR20020005788 A KR 20020005788A
Authority
KR
South Korea
Prior art keywords
bridge
inspection
vertical
work
running rail
Prior art date
Application number
KR1020000039182A
Other languages
Korean (ko)
Other versions
KR100401251B1 (en
Inventor
황무영
Original Assignee
황무영
한국모노레일주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Family has litigation
First worldwide family litigation filed litigation Critical https://patents.darts-ip.com/?family=19677034&utm_source=google_patent&utm_medium=platform_link&utm_campaign=public_patent_search&patent=KR20020005788(A) "Global patent litigation dataset” by Darts-ip is licensed under a Creative Commons Attribution 4.0 International License.
Application filed by 황무영, 한국모노레일주식회사 filed Critical 황무영
Priority to KR10-2000-0039182A priority Critical patent/KR100401251B1/en
Publication of KR20020005788A publication Critical patent/KR20020005788A/en
Application granted granted Critical
Publication of KR100401251B1 publication Critical patent/KR100401251B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/10Railings; Protectors against smoke or gases, e.g. of locomotives; Maintenance travellers; Fastening of pipes or cables to bridges
    • E01D19/106Movable inspection or maintenance platforms, e.g. travelling scaffolding or vehicles specially designed to provide access to the undersides of bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges

Abstract

PURPOSE: A mobile bridge examination traveler is provided to repair the front face of a bridge by being combined with a traveling rail, to economically use the traveling rail by making the traveling rail installed, removed and transferred easily, to be installed without any additional reinforcing facility by reducing the weight, and to examine many bridges at a time. CONSTITUTION: A mobile bridge examination traveler comprises a base structure having plates(29-1) for walking on the bottom face of a truss structured cantilever(29) installed on the side of a bridge structure; a traveling rail unit having a planar rear face and fixing a rack rail having rack gear pitches via a clamp; a power unit including a driver(21) generating power using such fuel as gasoline; a hanging unit connecting the traveling rail unit with an examination unit; and the examination unit consisting of two vertical trusses(33), a planar plate(32) fixed on the lower end of the vertical trusses and a truss reinforcing material supporting the vertical trusses. The bridge examination traveler easily examines and repairs a bridge.

Description

이동식교량점검작업차{mobile and fixative bridge maintaining system}Mobile and fixative bridge maintaining system

본 발명은 교량의 안전진단에서부터 점검및 보수작업에 이르기까지 폭 넓게 사용하는 이동식교량점검작업 시스템에 관한 것이다. 특히 주점검대는 상설고정형으로 교각에 고정설치되는 동시에 필요시에 주행레일과 결합하여 고정 상태를 해제하여 이동하면서 다리 전체에 대한 보수점검을 가능하도록 구성한 이동식 교량점검작업차이다.The present invention relates to a mobile bridge inspection work system widely used from the safety diagnosis of the bridge to the inspection and maintenance work. In particular, the main inspection stand is a permanent bridge fixed type fixed to the piers and, at the same time, it is a mobile bridge inspection work vehicle configured to enable the maintenance of the whole bridge while releasing the fixed state by moving with the running rail when necessary.

현재까지의 교량관리시스템장비를 비교해 보면 다음과 같다.The following is a comparison of the bridge management system equipment.

국내의 각종 시설물및 장비는 점검용과 작업용으로 그 용도가 제한되어 있어 점검및 작업 전체에 폭넓게 적용하는 데는 한계가 있다.Various facilities and equipments in Korea are limited in their use for inspection and work, so there is a limit to their wide application to inspection and work as a whole.

첫째, 고정식 점검로는 교량, 고가교등의 교좌장치등에 대한 집중점검을 위해 일반적으로 설치되지만 교량에 대한 접근률이 극히 떨어져 교량 점검효과가 투자비에 못 미친다 할 수 있다.First, the fixed inspection is generally installed for the intensive inspection of bridges, bridges, etc., but the access rate to the bridge is extremely low, so the bridge inspection effect is less than the investment cost.

둘째, 점검및 단순보수공사에 범용적으로 사용되고 있는 굴절차와 고소작업차는 교량에 고정 부착되지 않기 때문에 해상, 강상 혹은 계곡등에는 사용상에 문제가 있고 불가피하게 교통통제를 해야하는 문제가 따른다.Second, because the refraction and aerial work vehicles, which are used for inspection and simple repair work, are not fixed to the bridge, there is a problem in the sea, river, or valley, and the traffic control is inevitable.

셋째, 교량의 보수작업에 일반적으로 설치되는 고정비계(일명 공중비계)는 점검용으로는 맞지 않으며 작업성을 인정한다 해도 안전사고가 빈발하여 치명적 단점으로 지적되고 있다.Third, fixed scaffolds (aka aerial scaffolds), which are generally installed in the repair work of bridges, are not suitable for inspection, and even if the workability is recognized, safety accidents are frequent and pointed out as fatal drawbacks.

넷째, (다경간용)상설형점검차는 이론적으로 점검과 부분보수용으로 그 용도가 폭 넓게 인정되고 있지만, 교각간의 통과를 위하여 여러 축방향의 유압시스템과 거대한 트러스구조를 설치하여야 하므로 자중이 무겁고 설치비용이 높아서 일부 특수한 교량외에는 일반적인 교량에 범용으로 적용하기 어렵다.Fourthly, the multi-period permanent inspection is widely used for inspection and partial repair, but it has heavy weight because it has to install hydraulic system and huge truss structure in various axial directions for the passage between piers. Due to the high installation cost, it is difficult to apply general purpose to general bridge except some special bridge.

다섯째, 점검과 보수용으로 사용되는 이동비계(일명 랙크작업차)는 경량, 저가라는 장점이 있지만 일부 교량(교각형태가 문형주형태)을 제외하고는 교각통과가 어려워 크레인과 같은 중장비의 보조를 받아서 이설하고 있다.Fifth, mobile scaffolds (aka rack work vehicles) used for inspection and repair have the advantages of light weight and low cost, but except for some bridges (bridge type is a column type column type), it is difficult to pass through the pier. I receive it and move it.

본 발명은 상기한 이동비계(랙크작업차)의 교각통과상의 단점을 해소하기 위하여 구동부는 교각을 통과할 수 있도록 하고, 점검대(작업대)는 각 경간마다 별도 설치하여 그 경간만에서라도 이동을 가능하도록 한 것이다. 즉, 각 경간내에서는 점검대가 상설형으로 설치되어 교좌부에 대한 상시점검은 언제든지 가능함은 물론 주행레일과 결합하면 자유로운 이동이 가능해져 교량 하면에 대한 전면보수작업 또한 가능하다. 또한 주행레일의 설치, 해체, 이설이 쉬워서 부담없이 주행레일을 임대 사용할 수 있으며, 점검대는 경량이어서 기존의 부하내구성이 약한 구교량에도 교량자체에 대한 별도의 보강설비가설작업이 필요없이 설치할 수가 있다. 또다른 효과로 점검대는 조립식으로 구성되어져 필요하다면 임의로 해체, 보관할 수도 있고, 최소의 점검대 수량으로 그 인근의 다수 교량을 점검할 수있게 하였다.The present invention allows the drive unit to pass through the pier in order to solve the drawback of the pier passing of the mobile scaffold (rack work car), the inspection platform (work table) can be installed separately for each span can move only in the span. I did it. That is, in each span, the inspection stand is installed as a permanent type, and the inspection of the bridge part is possible at any time, as well as free movement is possible when combined with the running rail, so that the front surface maintenance work on the bottom of the bridge is also possible. In addition, it is easy to install, dismantle, and relocate the running rail so that the running rail can be rented without any burden.The inspection platform is lightweight, so that the existing bridges with weak load durability can be installed without additional reinforcement installation work on the bridge itself. . Another effect is that the inspection platform is prefabricated so that it can be freely dismantled and stored if necessary, and the multiple bridges in the vicinity can be inspected with the minimum number of inspection stations.

도1은 본 발명의 교량점검작업차가 강교에 설치된 상태를 전체적으로 보여주는 정면도,1 is a front view showing the overall state of the bridge inspection work of the present invention installed on the steel bridge,

도2는 본 발명의 교량점검작업차에 대한 설치상태를 보여주는 상세측면도,Figure 2 is a detailed side view showing the installation state for the bridge inspection work vehicle of the present invention,

도3은 본 발명의 교량점검작업차에 대한 설치상태를 보여주는 정면상세도Figure 3 is a front detail showing the installation state for the bridge inspection work vehicle of the present invention

도4는 본 발명의 교량점검작업차에 대한 설치상태를 보여주는 측면도,Figure 4 is a side view showing the installation state for the bridge inspection work vehicle of the present invention,

도5는 본 발명의 콘크리트교량에 대한 설치상태를 전체적으로 보여주는 정면도,5 is a front view showing the installation state for the concrete bridge of the present invention as a whole,

도6은 본발명의 콘크리트교량에 대한 설치상태중에 좌, 우측점검대를 보여주는 정면도,Figure 6 is a front view showing the left and right inspection stand in the installation state for the concrete bridge of the present invention,

도7은 본 발명의 콘크리트교량에 대한 설치상태중에 주점검대를 보여주는 정면도Figure 7 is a front view showing the main inspection stand during the installation state for the concrete bridge of the present invention

도8은 본 발명의 콘크리트교량에 대한 설치상태를 전체적으로 보여주는 측면도Figure 8 is a side view showing the installation state for the concrete bridge of the present invention as a whole

도9는 본 발명의 I비임을 이용한 설치상태를 보여주는 정면도,9 is a front view showing the installation state using the I beam of the present invention,

도10은 본 발명의 I비임을 이용한 설치상태를 보여주는 측면도Figure 10 is a side view showing the installation state using the I beam of the present invention

도 11은 본 발명의 주점검로를 달아 내리는 설치형태의 정면도Figure 11 is a front view of the installation form to run down the main inspection of the present invention

도12는 본 발명의 주점검로를 달아 내리는 설치형태의 측면도Figure 12 is a side view of the installation form running down the main inspection of the present invention

<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for the main parts of the drawings>

11:강교의 주점검대 , 11-1:콘크리트 교량의 주점검로, 12:랙크레일 플레이트, 13:클램프, 14:랙크기어산, 15:주행레일, 15-1:트러스형태의 주행레일, 21:구동차, 23-1:상부종동차, 23-2:하부종동차, 24-1:2차 상부종동차, 24-2:2차 하부종동차, 29:캔틸레바, 29-1:보행플레이트, 31:1차수직연결봉, 32:평판플레이트, 33:수직 트러스, 37:장출작업대, 37-1:장출작업대 안치용 수평바아, 40:트러스보강재, 50:좌,우측점검대, 51:브라켓 행거, 54:상부점검대, 55:2차수직연결봉, 57:하부점검대, 58:수직작업대, 60:수직작업대용 구동차, 61:수직작업대용 종동차, 62:모멘트 방지용 지지롤라, 63:수직작업대용 진행레일, 71:I비임 고정용 브라켓, 72:I비임, 73:I비임용 구동차:, 74:I비임용 종동차:, 81:수평연결봉, 91:브라켓, 92:수직방향의 고정식 행거, 93:가새, 94:고정용 클립11: Steel bridge main checkpoint, 11-1: Concrete bridge check main road, 12: Rack rail plate, 13: Clamp, 14: Rack gear mountain, 15: Running rail, 15-1: Truss running rail, 21: driving car, 23-1: upper driven car, 23-2: lower driven car, 24-1: secondary upper driven car, 24-2: secondary lower driven car, 29: cantilever, 29-1: walking Plate, 31: 1st vertical connecting rod, 32: flat plate, 33: vertical truss, 37: loading work bench, 37-1: horizontal bar for placing working bench, 40: truss reinforcement, 50: left and right check table, 51: bracket Hanger, 54: Upper check table, 55: 2nd vertical connecting rod, 57: Lower check table, 58: Vertical work bench, 60: Drive car for vertical work bench, 61: Follower for vertical work bench, 62: Support roller for moment prevention, 63: Running rail for vertical workbench, 71: I beam fixing bracket, 72: I beam, 73: I beam drive car :, 74: I beam driven car :, 81: horizontal connecting rod, 91: bracket, 92: vertical direction Stationary hanger, 93: Brace, 94: Fastening clip

본 발명은 기존의 상설형점검차의 단점인 엄청난 중량과 가격 부담을 제거하고자 교량의 용접플렌지부나 플레이트부에 특수하게 제작한 레일이나 I비임과 같은 레일장치를 설치하고 이것에 수직트러스, 평판플레이트, 트러스보강재로 점검대를 구성하여 준 다음 자력에 의하여 이동이 가능하도록 구동차를 부착하여 주었으며, 이들 장치들이 모두 조립식으로 구성되어져 임의로 해체조립이 가능하도록 하였다.The present invention is to install a rail device such as a rail or I beam specially manufactured in the weld flange portion or plate portion of the bridge to eliminate the enormous weight and cost burden of the conventional permanent inspection car and vertical trusses, flat plate, After constructing the inspection stand with truss reinforcement, the driver car was attached to move by magnetic force, and these devices were all assembled to make disassembly and assembly possible.

또한 비계식이 갖는 안전성의 문제를 해소하기 위하여 상설고정식과 동일한 형태의 고정방법을 채용하여 비계식이 갖는 단점을 극복하였다.In addition, in order to solve the safety problem of scaffolding, we overcome the disadvantages of scaffolding by adopting the same type of fixing method as the permanent fixation formula.

본 발명은 강교 형태의 다리는 물론이고 좌우로 길게 캔틸레버가 연장되어 일반적인 수단으로는 접근하기 어려운 형태의 콘크리트형 다리에도 본 발명의 주행장치와 조립시스템을 순차로 설치할 수 있어서 어떠한 형태의 교량에도 적용이 가능한 이동식교량점검작업차의 제공에 목적이 있다.The present invention can be applied to any type of bridges, since the traveling device and the assembly system of the present invention can be installed in order not only steel bridge type bridges but also cantilever extends from side to side and can be difficult to access by general means. The aim is to provide this possible portable bridge inspection vehicle.

본 발명은 강교, 콘크리트교의 종방향으로 설치된 주행레일부와The present invention and the running rail portion installed in the longitudinal direction of the steel bridge, concrete bridge

상기한 주행레일부에 설치된 상태에서, 주점검대를 이동시키는 역할을 하는 엔진, 밧데리 기타 동력 발생 장치로 구성된 동력발생부와In the state installed in the running rail portion, the power generating unit consisting of an engine, a battery, and other power generating device for moving the main inspection stand and

상기한 동력발생부와 수평연결봉으로 결합되어 구동차에 의해 견인되어지면서 수직트러스, 평판플레이트, 트러스보강재등으로 박스형태로 만들어진 주점검대(주작업대)가 이동식 교량점검장치의 주요구성요소이다.The main inspection stand (main work bench) made of a box type of vertical truss, flat plate, truss reinforcement and the like is coupled to the power generating unit and the horizontal connecting rod and towed by a driving vehicle, and is a main component of the mobile bridge inspection apparatus.

본 발명에 대한 구체적인 실시예를 첨부한 도면에 의하여 설명한다.Specific embodiments of the present invention will be described with reference to the accompanying drawings.

교량의 종류는 상당히 다양하지만 가장 대표적으로 스틸박스형, 플레이트거더형과 같은 강교가 있고 구조상 캔틸레바 부분이 크게 돌출된 형태의 콘크리트교량의 2가지가 있으며, 이외에도 트러스교, 사장교, 현수교와 같은 특수교량이 있다. 여기서는 스틸박스형과 콘크리트 교량을 대표적인 예시로 하여 설치와 작동관계를 설명한다. 그러나 본 발명의 이동식점검보수장치와 그 설치방법은 거의 유사하므로 약간의 변형과 부수적인 장치의 설치로 실시가 가능한 모든 것이 본 발명의 범주에 속한다.There are various types of bridges, but most of them are steel bridges such as steel box type and plate girder type, and there are two types of concrete bridges with protruding cantilever parts.In addition, there are special bridges such as truss bridges, cable-stayed bridges, and suspension bridges. There is this. Here, the steel box type and concrete bridge will be described as a representative example to explain the installation and operation relationship. However, since the mobile inspection and repairing apparatus of the present invention and its installation method are almost similar, everything that can be implemented with a slight modification and installation of ancillary apparatus is within the scope of the present invention.

도 1 은 본 발명의 장치가 강교에 설치된 상태를 전체적으로 보여주는 정면도, 도 2 는 본 발명의 교량점검작업차에 대한 설치상태를 보여주는 상세측면도, 도 3 은 본 발명의 교량점검작업차에 대한 설치상태를 보여주는 정면상세도, 도 4 는 본 발명의 교량점검작업차에 대한 설치상태를 전체적으로 보여주는 측면도이다.1 is a front view showing a state in which the apparatus of the present invention is installed on a steel bridge as a whole, Figure 2 is a detailed side view showing an installation state for the bridge inspection work of the present invention, Figure 3 is an installation for the bridge inspection work of the present invention Detailed front view showing the state, Figure 4 is a side view showing an overall installation state for the bridge inspection work vehicle of the present invention.

강교에 설치한 경우를 보다 구체적으로 설명하면If the installation in the steel bridge in more detail

강교의 교각구조물측면에 역삼각구조에 다수의 종횡의 지지바들이 설치되는 캔틸레버(29)를 설치하여 그 저면에 보행용 플레이트(29-1)를 다수개 설치한 베이스구조체와,A base structure in which a cantilever 29 is installed on a side of a pier structure of a steel bridge in which a plurality of longitudinal and horizontal support bars are installed, and a plurality of walking plates 29-1 are provided on the bottom thereof;

강교의 용접후렌지 혹은 플레이트부에, 랙크기어(14)가 부착된 랙크레일(15)을 클램프(13)에 의하여 고정한 주행레일부와The traveling rail part which fixed the rack rail 15 with the rack gear 14 to the welding flange or plate part of the steel bridge by the clamp 13,

휘발유등과 같은 연료를 에너지원으로 하여 동력을 발생하는 구동차(21)를 포함하는 동력부와A power unit including a drive car 21 for generating power by using fuel such as gasoline as an energy source;

구동차(21)로부터 견인력을 전달받으면서 주행레일부(15)와 주점검대(11)를 연결해주는 행잉부와Hanging unit for connecting the running rail unit 15 and the main inspection stand 11 while receiving the traction force from the drive car 21 and

랙크기어가 상단에 부착된 두 개의 수직트러스(33)와 그 안쪽 하단에 안치되는 평판플레이트(32),그리고 두 개의 수직트러스(33)를 상호 보강 지지하는 트러스 보강재(40)로 구성된 박스형태의 주점검대(11)로 구성되어 있다.Box-shaped rack consisting of two vertical trusses 33 attached to the top of the rack gear, a flat plate 32 placed on the inner bottom thereof, and a truss reinforcement 40 to mutually reinforce the two vertical trusses 33 The main inspection stand 11 is comprised.

본 발명의 주행레일부는 수많은 래크기어산(14)이 플레이트부(12)에 부착된 형태로서, 교량의 형태에 따라서 각종 조립식 클램프(13)를 이용하여 가설할 수도 있고 필요에 따라 교량에 EYE형 브라켓트를 고정 부착하여 주행레일을 설치할 수도 있다. 주행레일의 행잉 피치가 불가피하게 멀 수밖에 없는 경우에는 트러스 형태의 주행레일(15-1)을 사용할 수도 있다.The running rail portion of the present invention is a form in which many rack gear mounts 14 are attached to the plate portion 12, and may be temporarily installed using various prefabricated clamps 13, depending on the shape of the bridge, or EYE type if necessary. It is also possible to install the running rail by fixing the bracket. If the running pitch of the running rail is inevitably far, the truss-type running rail 15-1 may be used.

본 발명에서 구동차(21)는 주행레일부에 설치되어 주점검대(11)를 견인하는 기능을 하는데, 그 스스로 내연기관이나 밧데리등의 동력을 내장할 수도 있고, 아니면 (발전기나 기타 전원으로부터 급전받아 구동하는) 모타만 장착된 형태일수도 있다. 상기한 구동차(21)와 구동차를 콘트롤하는 전기판넬(일명 콘트롤박스)의 표면에는 각종 콘트롤 스위치들이 설치되어 속도와 방향, 그리고 여러 안전장치를 임의로 제어가능토록 하였다.In the present invention, the drive car 21 is installed in the running rail portion to function to pull the main inspection stand 11, itself may be internally built in power such as an internal combustion engine or battery, or (feeding from a generator or other power supply) It may also be equipped with only a motor. Various control switches are installed on the surface of the driving vehicle 21 and the electric panel (aka control box) for controlling the driving vehicle to control the speed, direction, and various safety devices arbitrarily.

본발명에서 행잉부는 그 기능이 구동차(21)로부터의 견인력을 주점검대(11)에 전달하는 기능을 하는데 그 구성은 수평연결봉(81), 상부종동차(23-1), 하부종동차(23-2), 그리고 상부,하부종동차 사이에 1차수직연결봉(31)등으로 구성된다. 상부종동차는 주행레일에, 하부종동차는 주점검대에 각각 부착되어 있으며 특히 상부종동차는 수평연결봉으로 구동차에 연결되어 있어 구동차에 의해 견인하도록 되어 있다.In the present invention, the hanging portion has a function to transfer the traction force from the driving vehicle 21 to the main inspection stand 11, the configuration of which is a horizontal connecting rod 81, the upper driven car 23-1, the lower driven car ( 23-2) and the first vertical connecting rod 31 between the upper and lower driven cars. The upper follower is attached to the running rail and the lower follower is attached to the main inspection stand. In particular, the upper follower is connected to the driving vehicle by a horizontal connecting rod and is towed by the driving vehicle.

본 발명에서 주점검대(작업대)는 랙크기어가 상단에 부착된 두 개의 수직트러스(33)와 그 안쪽 하단에 안치되는 평판플레이트(32),그리고 두 개의 수직트러스를 상호 보강 지지하는 트러스 보강재(40)로 구성되어 있다. 두 개의 수직트러스는 주점검대의 기본후레임으로서 '최소자중의 최대적재중량'을 위해 여러 트러스형태가 적용된다. 또한 수직트러스 상단에 랙크기어산이 부착되어 있는데 그 용도는 교량의 하부에서 폭방향으로 점검대를 설치하거나 측면 이동을 용이하게 하기 위한 것뿐만아니라 그 위에 별도의 수직작업대(58)등 각종 옵션 장비를 안착시켜 좌우로 구동시킬 때 '진행 레일' 기능을 하기도 한다. 별도의 평판플레이트(32)를 바닥에 포설하여 작업자가 안정된 작업이 가능하도록 하였다. 평판플레이트의 형태는 데크플레이트, EX-METAL, 일반 타공발판등이 적용 가능하다. 트러스 보강재(40)는 두개의 수직트러스(33)를 상호 지지 보강하는 역할을 한다. 주행레일의 개소에 따라 장출작업대 안치용 수평바아(37-1)와 장출작업대(37)를 부가 설치하여 주행레일부의 연장설치 혹은 해체등의 작업시에 사용하거나 다른 작업을 할 수도 있다.In the present invention, the main inspection stand (working table) is a rack gear having two vertical trusses 33 attached to the top and a flat plate 32 placed on the inner bottom thereof, and a truss reinforcement for mutually supporting the two vertical trusses ( 40). The two vertical trusses are the basic frame of the main inspection frame and several truss types are applied for the 'maximum load weight of the smallest element'. In addition, a rack gear mount is attached to the top of the vertical truss, and its purpose is not only to install the inspection stand in the width direction at the bottom of the bridge or to facilitate the side movement, but also to install various optional equipment such as a separate vertical work platform 58 thereon. It also functions as a 'going rail' when seated and driven left and right. A separate flat plate 32 was installed on the floor to allow the worker to work stably. Deck plate, EX-METAL, and other perforated scaffold can be used as flat plate types. The truss reinforcement 40 serves to mutually support and reinforce the two vertical trusses 33. Depending on the location of the running rails, the horizontal bar 37-1 for mounting the loading platform and the loading platform 37 may be additionally installed to be used for the extension or disassembly of the running rail, or other work.

도 5 ~ 도 8은 본 발명의 콘크리트교량에 대한 설치상태를 보여주는 정면도, 측면도를 도시한 또다른 실시예를 도시하고 있다.5 to 8 show another embodiment showing a front view, a side view showing an installation state for the concrete bridge of the present invention.

상기한 강교와 동일한 원리로 운용되지만 콘크리트 교량은 특수하게 캔틸레바 부분이 크게 돌출되어 있으므로 '좌, 우측점검대(50)'라는 별도의 개념이 도입되어야 한다. 만약 좌,우측점검대를 별도로 설치하지 않으면 주점검대(11-1)의 본래의 목적을 충족시키기 위해 주점검대의 크기가 거대해져야 하며, 교각에 부착되는 캔틸레바 위에 주점검대을 안치할 때 측면 돌출길이가 길어져 주점검대의 자중의 분할 위치가 부적절할 수도 있다.Although operated on the same principle as the above-mentioned steel bridge, concrete bridges have a special concept of 'left and right check table 50' because the cantilever portion is particularly protruded. If the left and right checkpoints are not installed separately, the main checkpoint should be large to meet the original purpose of the main checkpoint (11-1), and when the main checkpoint is placed on the cantilever attached to the piers The protruding length may be increased, and the position of division of the weight of the main checkpoint may be inappropriate.

우선 주행레일은 본교에 앙카링하여 EYE TYPE의 브라켓을 부착할 수도 있고 이와같은 보조장치의 설치없이 주행레일을 설치하려면 브라켓행거(51)를 방호벽등에 안착시켜 주행레일을 걸 수도 있다.First, the running rail may be anchored to the main school to attach the bracket of EYE TYPE, or to install the running rail without the installation of such an auxiliary device, the bracket hanger 51 may be seated on a firewall or the like to hang the running rail.

이 주행레일에서부터 하측으로 복합적인 기능을 갖는 좌,우측 점검대가 설치되는데 이 좌, 우측점검대의 기능은 우선 캔틸레바 점검이 가능해야하며 캔틸레바점검용 수직작업대(58)등의 장비를 스스로 탑재해서 주점검대(11-1)의 설치비용부담을 최소화해야 한다. 특히 주의할 것은 좌,우측 점검대는 교각을 만나면 주점검대와 분리되어 각각 외줄의 주행레일(15-1)을 주행하며 독자적으로 교각을 통과해야 하는데 이 때 주점검대와의 분해, 조립이 쉽고 안전해야 한다. 따라서 회전모멘트를 방지하기 위해서 상부점검대(54), 하부점검대(57)와 수직작업대(58)등의 무게중심을 주행레일의 직하방향에 두었다. 따라서 최악의 경우 작업자가 끝단으로 움직여도 점검대의 자중으로 그 흔들림은 극히 미미하다. 그리고 좌,우측점검대의 하부점검대(57)를 직접 주행레일로부터 행잉하지 않고 상부점검대(54)로부터 4점지지하여 주점검대로부터 하부점검대를 분리할 때 그 모멘트변화를 줄였다. 또한 모멘트방지용 회전롤라(62), 발란스웨이트등으로 모멘트 방지를 지원하였다.The left and right checkpoints are installed from the running rail to the lower side, which has a complex function. The functions of the left and right checkpoints must first be able to check the cantilever. The installation cost of main checkpoint 11-1 should be minimized. In particular, the left and right checkpoints are separated from the main checkpoint when they meet the pier, and each of them runs on a running rail (15-1) of the outer line and must pass the pier independently. In this case, it is easy to disassemble and assemble with the main checkpoint. It must be safe. Therefore, in order to prevent the rotation moment, the center of gravity of the upper check table 54, the lower check table 57 and the vertical work table 58 is placed in the direction directly below the running rail. Therefore, in the worst case, even if the worker moves to the end, the shaking is very small due to the weight of the check table. In addition, the lower check stand 57 of the left and right check stands was supported by four points from the upper check stand 54 without hanging directly from the running rail, thereby reducing the moment change when the lower check stand was separated from the main check stand. In addition, the moment prevention rotation roller 62, the balance weight, and supported the moment prevention.

그 구조를 구체적으로 살펴 보면, 브라켓행거(51)가 하측으로 연장되어져 주행레일을 설치한 후, 이 주행레일에 구동차(21)와 상부종동차(23-1), 하부종동차 (23-2), 1차수직연결봉(31)등과 함께 상부점검대(54)를 설치한다. 이어서 2차 상부종동차(24-1), 2차수직연결봉(55), 2차하부종동차(24-2)에 의하여 하부점검대(57)가 설치된다. 상기한 상부점검대(54)와 하부점검대(57) 사이에 수직작업대(58)를 내장토록 하였다. 수직작업대는 그 하측에 수직작업대용 구동차(60)를 설치하였고 수직작업대용 진행레일(63)과 종동차(61)를 이용하여 좌우로 이동할 수가 있고 또한 수직작업대는 작업플레이트의 상하 이동이 가능해서 교량의 하부 어느 위치에 대하여도 접근이 가능토록 하였다.Looking specifically at the structure, after the bracket hanger 51 is extended to install the running rail, the drive rail 21, the upper driven car 23-1, the lower driven car 23-2 ), The upper inspection stand 54 is installed together with the primary vertical connecting rod 31 and the like. Subsequently, the lower inspection table 57 is installed by the secondary upper driven vehicle 24-1, the secondary vertical connecting rod 55, and the secondary lower driven vehicle 24-2. The vertical work bench 58 was built between the upper check bench 54 and the lower check bench 57. Vertical workbench is installed on the lower side of the vertical workbench driving car 60 and can be moved left and right using the vertical workbench running rail 63 and the driven car 61, and the vertical workbench is capable of moving the work plate up and down Access to any location on the lower part of the bridge was made possible.

발명의 또다른 실시예로 도 9, 도 10에 도시하듯이 주행레일부와 구동부를 일부 변경한 것으로 주행레일은 I비임을 사용하고, 구동차와 상부종동차를 I비임에 맞추어 개조한 것이다.As another embodiment of the present invention, as shown in FIGS. 9 and 10, the driving rail part and the driving part are partially changed, and the driving rail uses the I beam, and the driving car and the upper driven car are adapted to the I beam.

강교의 경우는 용접프렌지 혹은 플레이트에 브라켓(71)을 용접한 후 여기에 I비임을 부착하여 준 주행레일부와,In the case of steel bridges, after the bracket 71 is welded to the welded flange or plate, the running rail part attached to the I beam is attached thereto;

(랙크기어에 맞는) 피니언기어가 내장된 구동차(21) 대신에 I비임에 맞는 회전롤라 TYPE의 구동차(73)및 종동차(74)가 설치된다.Instead of the drive car 21 in which the pinion gear is built (fitting the rack gear), the drive car 73 and the driven car 74 of the rotary roller type suitable for the I beam are provided.

콘크리트교량의 경우에는 상기한 강교와 동일한 형태로 주행레일로서 I비임과 그것에 맞는 구동부가 변경되어지는데 다만 콘크리트교량의 캔틸레버가 좌우로 길게 노출되어져 있으므로 브라켓행거(51)를 이용하거나 앙카링하여 주행레일을 설치한다. 기타 원리는 상술한 내용과 동일하다.In the case of the concrete bridge, the I beam and the driving part corresponding thereto are changed as the running rails in the same form as the above-mentioned steel bridge. Install it. Other principles are the same as the above.

발명의 또다른 실시예로 도 11, 도 12에 도시하듯이 주점검로를 캔틸레바 (29)에 안치하지 않고 직접 본교량에 달아 내려 고정하는 방법이다. EYE TYPE의 브라켓(91)을 교량에 부착한 후 주점검로의 넓이에 따라 수직방향의 고정식 행거(92)를 적정하게 배치하여 주점검로를 달아 내린다. 또한 수평방향의 흔들림을 방지하기 위해 고정용 가새(93)로 보완한다.As another embodiment of the present invention, as shown in Figs. 11 and 12, the main inspection path is directly fixed to the main bridge without being placed on the cantilever 29. After attaching the bracket 91 of the EYE TYPE to the bridge, the fixed hanger 92 in the vertical direction is appropriately arranged according to the width of the main inspection path, and the main inspection path is put down. It is also supplemented with fixing braces 93 to prevent horizontal shaking.

이상의 전체적인 구조적 특징에 따른 작동원리를 정리하면, 점검대가 상시고정형으로 각경간마다 교각에 고정설치되는 동시에 필요시에 고정상태를 해제하여 이동하면서 다리 전체에 대한 보수점검이 가능하도록 하였다.In summary, the operation principle according to the overall structural features, the inspection stand is fixed to the pier at each interval in the form of fixed and fixed, and at the same time release the fixed state to move the maintenance of the entire bridge is possible.

구동차(21)가 랙크기어가 있는 주행레일(15)에 설치되고 그 주행레일은 클램프(13) 또는 브라켓행거(51)에 의하여 교량에 부착되며 마지막으로 주점검대(11)는 평상시에는 교각 측면에 부착된 캔틸레바(29)에 안치되어 있다가 유사시 행잉부에 의하여 주행레일과 결합하며 한 경간의 작업이 끝나면 다시 주점검로는 분리되고 구동부는 주행레일을 따라 계속 주행하여 교각을 통과하면 다시 다음 경간의 주점검로와 다시 결합하면서 점검및 보수작업을 계속 진행한다.The drive car 21 is installed on the running rail 15 with the rack gear, and the running rail is attached to the bridge by the clamp 13 or the bracket hanger 51. Finally, the main inspection stand 11 is normally pier side. It is settled in the cantilever 29 attached to it, and when it is in need, it is combined with the running rail by the hanging part, and when the work of one span is finished, the main inspection path is separated again, and the driving part continues to travel along the running rail and passes through the piers again. Continue with the inspection and repair work, re-combine with the main inspection of the next span.

이상 본발명의 구조에 따른 이동식교량점검작업차의 효과는 다음과 같다.The effects of the mobile bridge inspection work vehicle according to the structure of the present invention are as follows.

상설형 점검차의 경우는 교각통과의 어려움을 유압장치를 이용한 거대한 트러스 구조물로 그 해답을 찾음으로 해서 십여톤이나 되는 자중을 교량의 가장 취약부위인 캔틸레바에 설치함으로써 그 원리의 우월함에도 불구하고 실제 유지보수가 필요한 기존 교량에는 설치가 불가능한 채 신설장대교량에만 극히 제한적으로 설치되고 있는 실정이다. 또한 사장교와 같은 장대교량조차 중량이 집중되는 상설형점검차는 발란스 유지에 좋지 않다는 것이 정평이다. 또한 그 자중으로 인해 교량의 보수작업시 필요한 작업공간및 적재하중에도 한계가 있어서 보수작업시는 별도의 장비 또는 재래식 고정 비계를 설치할 수 밖에 없는 중복투자의 경제적인 문제점을 안고 있다.In the case of the permanent inspection car, the difficulty of passage of the bridge is found by the huge truss structure using the hydraulic system, and the solution of about ten tons is installed in the cantilever, the weakest part of the bridge, despite the superiority of the principle. Existing bridges that require maintenance cannot be installed and are currently being installed only on new bridges. In addition, even long bridges such as cable-stayed bridges, the permanent type inspection car with a heavy weight is not good for maintaining balance. In addition, due to its own weight, there is a limit to the work space and loading load required for the repair work of the bridge, and therefore, there is an economic problem of overlapping investment, which requires installation of separate equipment or conventional fixed scaffolding during the repair work.

반면에 본 발명은 점검용과 작업용 장비가 별도로 필요하지 않는 통합적인 효과를 기대할 수 있는 시스템이다. 또한 교량의 유지보수에 시간적 공간적인 제약을 없어지게 되었다. 즉, 이동식 점검대가 매경간마다 존재하므로 신속한 점검도 가능하지만 유사시 주행레일과 결합되면 동시다발적인 전면적인 긴급점검도 가능하다. 그리고 점검대의 자중이 경량이어서 별도의 보강 필요없이 기존교량에 조차 설치 가능하여 기존교량에 조차 다경간용 상설형점검차의 효과를 기대할 수 있다. 또한 전면보수작업시 흔히 설치되는 고정비계(공중비계)의 설치, 해체시 발생될 수 있는 안전사고를 줄일 수 있게 되었다.On the other hand, the present invention is a system that can expect the integrated effect that does not require separate inspection and work equipment. In addition, the time and space constraints on bridge maintenance have been eliminated. In other words, since the mobile inspection platform exists every interval, quick inspection is possible, but when combined with a running rail in case of emergency, it is possible to carry out a comprehensive and comprehensive emergency inspection simultaneously. And because the weight of the inspection platform is light, it can be installed even on the existing bridge without the need for additional reinforcement. In addition, safety accidents that can occur during the installation and dismantling of fixed scaffolds (air scaffolds), which are commonly installed during maintenance work, can be reduced.

경제적인 면에서는 교량의 점검 및 보수가 각각 별도의 장치가 아니고 통합운용되므로 교량관리에 대한 중복 투자를 피할 수 있게 되었다. 그리고 기존의 상설형에 비하여 구조상 유압시스템일 필요도 없고 거대한 트러스 구조물일 필요도 없으므로 저가로 운행가능하게 되었다.In terms of economics, the inspection and repair of the bridges are not separate devices, but integrated operation, thereby avoiding redundant investment in bridge management. And since it does not need to be a hydraulic system or a huge truss structure in comparison with the existing permanent type, it can be operated at low cost.

이러한 저가 설비의 효과를 극대화하기 위한 방안으로 첫째, I비임 주행레일을 선택적으로 사용할 수도 있다. 랙크기어가 부착된 랙크레일은 분해, 조립이 용이한 장점이 있지만 그 제작단가가 비싼 편이어서 교량이 길면 길수록 주행레일 가격이 부담되어 가격경쟁력에서의 우위가 일부 상쇄될 수 있다. 만약 사용자가 주행레일을 이설해서 사용하고자 하거나, 아니면 아치교량이나 램프교처럼 어쩔 수없이 주행레일이 구배가 지는 경우를 제외하고는 I비임을 주행레일로 고정 부착해서 사용해도 문제는 없다. 둘째, 주점검로 안치용 캔틸레바 대신에 주점검로를 본교량에서 달아 내리는 간단한 행잉방법을 사용할 수도 있다.In order to maximize the effect of such low-cost equipment, firstly, the I-beam running rail may be selectively used. Rack rails with rack gears have advantages in that they can be easily disassembled and assembled, but the manufacturing cost is high, so the longer the bridge, the higher the running rail price, and some of the advantages in price competitiveness can be offset. If the user wants to relocate and use the running rail, or the driving rail is unavoidably inclined, such as an arch bridge or a ramp bridge, the I beam can be fixed and used as the running rail. Second, in place of the cantilever for placing the main inspection, a simple hanging method may be used to run the main inspection off the main bridge.

Claims (10)

강교의 교각구조물측면에 트러스구조의 캔틸레버(29)를 설치하되 그 저면에 보행용 플레이트(29-1)를 다수개 설치한 베이스구조체와,A base structure in which a truss cantilever 29 is installed on the side of the pier structure of the steel bridge, and a plurality of walking plates 29-1 are installed on the bottom thereof; 강교의 용접프렌지 혹은 플레이트부에 일면이 접하도록 평면구조(12)의 배면을 갖으면서 그 반대면에는 다수의 랙크기어산(14)이 형성된 랙크레일(15)을 클램프(13)에 의하여 고정한 주행레일부와,The rear surface of the planar structure 12 has one surface in contact with a welded flange or plate portion of a steel bridge, and on the opposite side, a rack rail 15 having a plurality of rack gear mounts 14 formed thereon is fixed by the clamp 13. Rail section, 휘발유등과 같은 연료를 에너지원으로 하여 동력을 발생하는 구동차(21)를 포함한 동력부와,A power unit including a drive car 21 for generating power by using fuel such as gasoline as an energy source; 구동차로부터 견인력을 전달받으면서 주행레일부와 점검대를 연결해주는 행잉부와,Hanging unit for connecting the running rail unit and the inspection stand while receiving the traction force from the drive car, 랙크기어가 상단에 부착된 두개의 수직트러스(33)와 그 안쪽 하단에 안치되는 평판 플레이트(32), 그리고 두개의 수직트러스를 상호 보강 지지하는 트러스 보강재(40)로 조립된 점검대로 구성된 교량의 이동식교량점검작업차.The rack consists of two vertical trusses 33 attached to the top, a flat plate 32 placed on the inner bottom thereof, and a truss reinforcement 40 for mutually reinforcing and supporting the two vertical trusses. Mobile bridge inspection work vehicle. 제 1 항에 있어서,The method of claim 1, 주행레일부는 다수의 래크기어산(14)이 플레이트부(12)에 부착된 형태로서, 교량의 형태에 따라서 조립식 클램프(13), EYE형 브라켓트 혹은 트러스 형태의 주행레일(15-1)중의 어느하나를 선택하여 설치하며,The running rail portion is formed by attaching a plurality of rack gear mounts 14 to the plate portion 12, and according to the shape of the bridge, any of the prefabricated clamp 13, EYE bracket or truss-type running rail 15-1. Choose one to install, 랙크기어는 평철의 웨이브가공 혹은 통쇠중의 어느하나로 제조설치하는 것을특징으로 하는 교량의 이동식 교량점검작업차The rack gear is a mobile bridge inspection vehicle for bridges, characterized in that it is manufactured and installed in either flat iron wave processing or shackles. 제 1 항에 있어서,The method of claim 1, 구동차(21)는 주행레일부에 설치되어 주점검대(11)를 견인하도록 내연기관 혹은 밧데리등의 동력에 의하여 작동하는 것으로서, 구동차(21)와 구동차를 콘트롤하는 전기판넬(일명 콘트롤박스)의 표면에 설치된 콘트롤 스위치들에 의하여 속도와 방향, 그리고 여러 안전장치를 임의로 제어가능토록 한 것을 특징으로 하는 교량의 이동식 교량점검작업차.The driving car 21 is installed on the running rail part and is operated by a power of an internal combustion engine or a battery so as to tow the main inspection stand 11, and the driving car 21 and an electric panel (aka control box) that controls the driving car. Mobile bridge inspection vehicle of a bridge, characterized in that the control switch installed on the surface to control the speed, direction, and various safety devices arbitrarily. 제 1 항에 있어서,The method of claim 1, 행잉부는 수평연결봉(81), 상부종동차(23-1), 하부종동차(23-2), 그리고 상부,하부종동차 사이에 1차수직연결봉(31)등으로 구성되며, 상부종동차는 주행레일에, 하부종동차는 주점검대에 각각 부착되어 있으며 상부종동차는 수평연결봉(81)으로 구동차에 연결되어 있어 구동차에 의해 견인하도록 하는 것을 특징으로 하는 교량의 이동식 교량점검작업차.The hanging part consists of a horizontal connecting rod 81, an upper follower 23-1, a lower follower 23-2, and a first vertical connecting rod 31 between the upper and lower follower cars. On the running rail, the lower driven car is attached to the main inspection stand, respectively, the upper driven car is connected to the driving car by the horizontal connecting rod 81, the mobile bridge inspection work of the bridge, characterized in that to be towed by the driving car. 제 1 항에 있어서,The method of claim 1, 주점검대(작업대)는 랙크기어가 상단에 부착된 두 개의 수직트러스(33)와 그 안쪽 하단에 안치되는 평판플레이트(32),그리고 두 개의 수직트러스를 상호 보강 지지하는 트러스 보강재(40)로 구성되며,The main inspection stand (work table) includes two vertical trusses 33 having a rack gear attached to the top, a flat plate 32 placed at the bottom of the inner side thereof, and a truss reinforcement 40 which mutually reinforces the two vertical trusses. Is composed, 수직트러스 상단에 랙크기어산이 부착되면서 평판플레이트(32)의 형태는 데크플레이트, EX-METAL, 일반 타공발판중의 어느하나가 적용 가능한 것을 특징으로 하는 교량의 이동식 교량점검작업차.The rack-mounted gear mount is attached to the top of the vertical truss, the flat plate 32 is a mobile bridge inspection work of the bridge, characterized in that any one of the deck plate, EX-METAL, perforated scaffolding is applicable. 좌우로 캔틸레버가 길게 노출된 콘크리트교량에서On concrete bridges with long exposed cantilevers from side to side 브라켓행거(51)가 하측으로 연장되어져 주행레일을 설치한 후, 이 주행레일에 구동차(21)와 상부종동차(23-1), 하부종동차 (23-2), 1차수직연결봉(31)등과 함께 상부점검대(54)를 설치하며,After the bracket hanger 51 extends downward to install the travel rails, the drive rails 21, the upper driven cars 23-1, the lower driven cars 23-2, and the primary vertical connecting rod 31 are mounted on the traveling rails. And the upper inspection stand (54) 2차 상부종동차(24-1), 2차수직연결봉(55), 2차하부종동차(24-2)에 의하여 하부점검대(57)가 설치되도록 하고,The lower inspection table 57 is installed by the secondary upper driven vehicle 24-1, the secondary vertical connecting rod 55, and the secondary lower driven vehicle 24-2. 상기한 상부점검대(54)와 하부점검대(57) 사이에 수직작업대(58)를 내장토록 하되 수직작업대는 그 하측에 수직작업대용 구동차(60)를 설치하였고 수직작업대용 진행레일(63)과 종동차(61)를 이용하여 좌우로 이동할 수 있으며, 수직작업대는 작업플레이트의 상하 이동이 가능하도록 구성한 교량의 이동식 교량점검작업차.The vertical work table 58 is built between the upper check table 54 and the lower check table 57, but the vertical work table has a drive rail 60 for the vertical work table installed thereon, and a running rail 63 for the vertical work table. And can be moved left and right using the driven car 61, the vertical work platform is a mobile bridge inspection work of the bridge configured to enable the vertical movement of the work plate. 제 6 항에 있어서,The method of claim 6, 좌, 우측점검대의 회전모멘트를 방지하기 위해서 상부(54), 하부점검대(57)와 수직작업대(58)등의 무게중심을 주행레일의 직하방향에 두었으며 좌,우측점검대의 하부점검대(57)를 직접 주행레일로부터 행잉하지 않고 상부점검대(54)로부터 4점지지하였다. 또한 모멘트방지용 회전롤라(62), 발란스웨이트등으로 모멘트 방지를 지원하는 것을 특징으로 하는 교량의 이동식 교량점검작업차.In order to prevent the rotation moment of the left and right checkpoints, the center of gravity of the upper 54, lower checker 57 and the vertical workbench 58 is placed under the running rail, and the lower checkpoints of the left and right checkpoints ( 57) was supported by four points from the upper inspection stand 54 without hanging directly from the running rails. In addition, a mobile bridge inspection work of the bridge, characterized in that the moment prevention rotation roller 62, the balance weight to support the moment prevention. 제 1 항에 있어서,The method of claim 1, 강교의 교각구조물측면에 트러스구조의 캔틸레버(29)를 설치하되 그 저면에 보행용 플레이트(29-1)를 다수개 설치한 베이스구조체로 구성되어 있으며 보강 목적으로, 교각 앞뒤에 있는 캔틸레바를 교각 상단면 위에서 각종 형강으로 서로 연결할 수도 있는 것을 특징으로 하는 교량의 이동식 교량점검작업차.The cantilever 29 of truss structure is installed on the side of the pier structure of the steel bridge, and it is composed of a base structure in which a plurality of walking plates 29-1 are installed on the bottom thereof. Mobile bridge inspection vehicle of the bridge, characterized in that can also be connected to each other by various steel on the upper surface. 제 1 항에 있어서,The method of claim 1, 강교의 경우에 용접프렌지 혹은 플레이트에 브라켓(71)을 용접한 후 여기에 I비임을 부착하고, I비임에 맞는 회전롤라 TYPE의 구동차(73)및 종동차(74)가 설치되며,In the case of steel bridge, after welding the bracket 71 to the welding flange or plate, I beam is attached thereto, and the driving car 73 and the driven car 74 of the rotary roller type suitable for the I beam are installed. 콘크리트교량의 경우에는 주행레일로서 I비임과 이것에 알맞는 구동부를 설치하되 브라켓행거(51)를 이용하거나 앙카링하여 주행레일을 설치하는 것을 특징으로 하는 교량의 이동식 교량점검작업차.In the case of a concrete bridge, the bridge is a mobile bridge inspection work of the bridge, characterized in that to install a driving rail suitable for the I beam and the same as the running rail, but using a bracket hanger (51) or anchoring. 교량의 하부구조에 대한 점검보수를 위한 점검대에 있어서,In the inspection platform for maintenance of the undercarriage of the bridge, 주점검로를 EYE TYPE의 브라켓(91)을 교량에 부착한 후 주점검로의 넓이에 따라 수직방향의 고정식 행거(92)를 적정배치하여 주점검로를 하향식으로 현수시킨 다음, 수평방향의 흔들림을 방지하기 위해 고정용 가새(93)로 보완한 형태의 이동식 교량점검작업차.After attaching the main point follower to the bridge, the bracket 91 of the EYE TYPE is attached to the bridge, and then the fixed hanger 92 in the vertical direction is appropriately placed in accordance with the width of the main follower to suspend the main follower downwardly, and then the horizontal shaking Mobile bridge inspection work of the type supplemented with a fixing brace (93) to prevent the.
KR10-2000-0039182A 2000-07-10 2000-07-10 mobile and fixative bridge maintaining system KR100401251B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR10-2000-0039182A KR100401251B1 (en) 2000-07-10 2000-07-10 mobile and fixative bridge maintaining system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR10-2000-0039182A KR100401251B1 (en) 2000-07-10 2000-07-10 mobile and fixative bridge maintaining system

Publications (2)

Publication Number Publication Date
KR20020005788A true KR20020005788A (en) 2002-01-18
KR100401251B1 KR100401251B1 (en) 2003-10-11

Family

ID=19677034

Family Applications (1)

Application Number Title Priority Date Filing Date
KR10-2000-0039182A KR100401251B1 (en) 2000-07-10 2000-07-10 mobile and fixative bridge maintaining system

Country Status (1)

Country Link
KR (1) KR100401251B1 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100472096B1 (en) * 2001-12-27 2005-02-23 용마기술개발주식회사 inner moving inspection device for girder of bridge
KR100823638B1 (en) * 2007-06-15 2008-04-21 주식회사 에코카 Tunnel and bridge emergency and multipurpose management vehicle
KR101011893B1 (en) * 2008-07-01 2011-02-01 이연철 Movable carrier for repairing and maintaining of arch type structure
CN103174089A (en) * 2011-12-22 2013-06-26 湖北华舟重工有限责任公司 Fast pin inserting and extracting device for movable bridge
CN108487624A (en) * 2018-05-25 2018-09-04 广州丰利达安防科技有限公司 Attachment type raise scaffold
KR102558279B1 (en) * 2023-03-23 2023-07-24 주식회사 임성 Safety work structure for construction of post-type footbridge and deck roads

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111305111A (en) * 2017-11-30 2020-06-19 胡张艳 Road separation warning guardrail convenient to maintenance

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57174506A (en) * 1981-04-20 1982-10-27 Kayaba Industry Co Ltd Bridge inspection car for long and large bridge
JPH0765295B2 (en) * 1989-09-25 1995-07-19 株式会社宮地鐵工所 Movable scaffolding device for bridge and its assembling method
JP3606528B2 (en) * 1994-08-01 2005-01-05 米山工業株式会社 Mobile suspension scaffold device
JPH0868198A (en) * 1994-08-26 1996-03-12 Yoneyama Kogyo Kk Moving type suspended scaffold device
KR0160244B1 (en) * 1996-01-25 1999-01-15 전장열 Working stand for both bridge construction and management
KR200197369Y1 (en) * 2000-05-04 2000-09-15 영신기공주식회사 Working automobile for check and maintenance of bridges

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100472096B1 (en) * 2001-12-27 2005-02-23 용마기술개발주식회사 inner moving inspection device for girder of bridge
KR100823638B1 (en) * 2007-06-15 2008-04-21 주식회사 에코카 Tunnel and bridge emergency and multipurpose management vehicle
KR101011893B1 (en) * 2008-07-01 2011-02-01 이연철 Movable carrier for repairing and maintaining of arch type structure
CN103174089A (en) * 2011-12-22 2013-06-26 湖北华舟重工有限责任公司 Fast pin inserting and extracting device for movable bridge
CN103174089B (en) * 2011-12-22 2016-05-04 湖北华舟重工应急装备股份有限公司 A kind of movable type bridge fast insert-pull pin assembly
CN108487624A (en) * 2018-05-25 2018-09-04 广州丰利达安防科技有限公司 Attachment type raise scaffold
CN108487624B (en) * 2018-05-25 2023-12-15 广州丰利达安防科技有限公司 Attached lifting scaffold
KR102558279B1 (en) * 2023-03-23 2023-07-24 주식회사 임성 Safety work structure for construction of post-type footbridge and deck roads

Also Published As

Publication number Publication date
KR100401251B1 (en) 2003-10-11

Similar Documents

Publication Publication Date Title
JP3340681B2 (en) Construction method of overhanging girder bridge using corrugated steel web
US11634877B2 (en) Method for removal of temporary support system for road bridge pre-fabricated small box girder-type concealed bent cap, and equipment therefor
JP5319216B2 (en) Bridge girder erection device and bridge girder erection method
CN106400701B (en) A kind of list girder low level balanced cantilever assembly Bridge Erector
KR101391637B1 (en) Constrution methoed for Prestressed Composite Truss girder using steel truss member
CN212052327U (en) Movable type dismounting and hoisting tool for temporary supporting system of small box girder type hidden cover beam of road and bridge prefabrication
CN102395731B (en) Overhead form traveller and method
JP2000265417A (en) Moving timbering construction method for bridge floor slab overhang section
KR100987297B1 (en) Repair and inspection apparatus of bridge
JP2006077521A (en) Bridge constructing apparatus
KR20020005788A (en) mobile and fixative bridge maintaining system
KR20160109081A (en) Carriage for Bridge
JP2008050811A (en) Movable suspended scaffolding apparatus
CN111335182A (en) Portable single-rail bridge girder erection machine and steel column and steel girder installation method in bridge erecting process
KR101003403B1 (en) Moving bridge inspection equipment
CN210140770U (en) Cast-in-place bridge formwork support system device
JP3225933U (en) Railing-mounted scaffolding and its scaffolding support
JP6873435B2 (en) Suspended scaffolding and its erection method
CN209894497U (en) Adjustable structural mechanics test platform
KR100377529B1 (en) Working platform for bridge construction
CN207646620U (en) The movable construction platform of prefabricated wide cut beam slab
KR100367028B1 (en) A self propelled working platform for construction and maintenance of bridge
RU121262U1 (en) MOBILE SPAN STRUCTURE OF THE BRIDGE
JPS6041165B2 (en) Equipment for cantilevering bridge structures made of reinforced concrete or prestressed concrete into sections.
KR0160244B1 (en) Working stand for both bridge construction and management

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E902 Notification of reason for refusal
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20100929

Year of fee payment: 8

LAPS Lapse due to unpaid annual fee