KR101608624B1 - Method for lifting the height of tower - Google Patents

Method for lifting the height of tower Download PDF

Info

Publication number
KR101608624B1
KR101608624B1 KR1020150100855A KR20150100855A KR101608624B1 KR 101608624 B1 KR101608624 B1 KR 101608624B1 KR 1020150100855 A KR1020150100855 A KR 1020150100855A KR 20150100855 A KR20150100855 A KR 20150100855A KR 101608624 B1 KR101608624 B1 KR 101608624B1
Authority
KR
South Korea
Prior art keywords
tower
steel tower
line
arm
existing
Prior art date
Application number
KR1020150100855A
Other languages
Korean (ko)
Inventor
이종진
김호곤
여태선
고흥열
김병호
Original Assignee
한국전력공사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 한국전력공사 filed Critical 한국전력공사
Priority to KR1020150100855A priority Critical patent/KR101608624B1/en
Application granted granted Critical
Publication of KR101608624B1 publication Critical patent/KR101608624B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/34Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/34Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
    • E04H12/344Arrangements for lifting tower sections for placing additional sections under them
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/34Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
    • E04H12/348Arrangements for demolition towers or the like

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Electric Cable Installation (AREA)

Abstract

The present invention relates to a method for lifting a power transmission tower, which comprises: (S1) a step of performing basic construction for putting a tower in the external side of an existing tower; (S2) a step of stopping the line 1 on one side of the existing tower to protect a charging unit and to transmit power; (S3) a step of stopping the line 2 on the other side of the existing tower; (S4) a step of assembling the new tower on the part of the basic construction and installing an arm on one side; (S5) a step of moving in the air and adding the power line of the line 2 on the arm on one side of the new tower; (S6) a step of installing an arm on the other side of the new tower after stopping the power of the line 1; (S7) a step of moving in the air and adding the power line of the line 1 to the arm on the other side of the new tower and transmitting power; and (S8) a step of removing the existing tower. The present invention does not need to install a temporary line or to secure additional land and perform the construction for lifting a tower while minimizing the civil complaints.

Description

송전철탑 상향공법{METHOD FOR LIFTING THE HEIGHT OF TOWER}{METHOD FOR LIFTING THE HEIGHT OF TOWER}

본 발명은 송전철탑 상향공법에 관한 것으로, 보다 상세하게는 별도의 임시선로 구성없이 기설철탑의 위치에 기초를 보강한 후 기설철탑의 외측으로 높이제한 없이 철탑을 상향하는 인클로징 송전철탑 상향공법에 관한 것이다.BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of upending a transmission tower, and more particularly, to a method of upgrading a transmission tower by elevating the tower to an outside of an existing tower, .

최근 전력선을 중심으로 한 환경은 경제발전과 생활수준의 향상에 따라 지역개발활성화, 도시화 진전 및 자연과 생활환경에 대한 사회적 욕구 등에 의하여 대단히 어려워지고 있다.Recently, the environment centering on electric power lines has become very difficult due to the improvement of economic development and living standard, the activation of regional development, the progress of urbanization, and the social desire for nature and living environment.

이러한 환경변화의 영향으로 신설공사에서는 선로가 지나가는 주변 마을을 중심으로 대규모 반대 민원제기, 지가하락에 의한 과도한 보상요구, 환경보전에 대한 법적 규제, 적기 건설 지연에 따른 막대한 사회적 비용이 발생하는 악순환이 반복되고 있는 상황이다. 또한, 설비운영 측면에서는 유지·보수공사를 위한 용지확보와 기설 선로 철거 민원, 이설요구, 발전제약 비용 발생, 휴전의 어려움 등으로 적기 유지보수가 지체되는 실정이다.As a result of such environmental changes, the new construction project is facing a vicious cycle in which large-scale complaints are filed around neighboring villages where the railway passes, excessive demands for compensation due to land price decline, legal restrictions on environmental preservation, It is a situation that is repeated. In addition, in terms of facility operation, timely maintenance is delayed due to the need for maintenance and repair work, complaints about demolition of existing lines, relocation requests, power generation cost constraints, and difficulties with a ceasefire.

더욱이 60~70년대 경제개발 도상기에 건설된 선로는 명확한 지상고 기준이 정립되지 않은 상황에서 선로를 건설함으로써 저지상고 철탑이 다수를 차지하고 있으며, 선하지의 수목성장, 건조물 신·증축 등 시설물 개발에 의하여 안전 이격 거리 미달 개소가 더욱 증가하고 있는 추세이다.Moreover, railway lines constructed in the 60s and 70s economic development roads have not established clear ground level standards, and many railway towers have been built by constructing railway lines. The development of facilities such as tree growth, There is a tendency that the distance that the distance is less is increasing.

그런데, 기초 부동변위(고저차, 면거리) 발생 철탑, 주주재 변위, 만곡 발생 철탑의 경우 기개발한 154kV 지상고 상향[Hwlper-Tower]공법 적용이 불가한 문제점이 있다.However, there is a problem that it is impossible to apply the Hwlper-Tower method, which has been developed in the case of steel towers, main displacement, and curved steel towers, which have generated basic floating displacements (elevation difference and surface distance).

따라서, 154kV급 다회선 철탑 및 345kV급 철탑에도 대응할 수 있는 진일보된 송전철탑 상향공법 개발이 요구되고 있다. Therefore, it is required to develop an advanced method of upgrading transmission tower to cope with 154kV multi-line steel tower and 345kV class steel tower.

한국공개특허공보 제2013-0073377호(명칭:송전철탑 인상 장치, 공개일자:2013.07.03)Korean Patent Laid-Open Publication No. 2013-0073377 (entitled "Transmission Tower Towing Device, Date Published: 2013.07.03)

본 발명은 상기한 종래의 문제점을 해결하기 위해 제안된 것으로, 별도의 임시선로 구성 및 추가용지 확보 등의 필요없이 기설철탑의 위치에 기초를 보강한 후 기설철탑의 외측으로 높이제한 없이 신설철탑을 상향하고 기설철탑을 철거하는 송전철탑 상향공법을 제공하는데 그 목적이 있다.The present invention has been proposed in order to solve the above-mentioned problems of the prior art, and it is an object of the present invention to provide a new steel tower without restricting the height to the outside of the existing steel tower, The purpose of this is to provide a method of upgrading the transmission tower to remove the existing tower.

상기한 바와 같은 목적을 달성하기 위한 본 발명의 특징에 따르면, 본 발명은 S1) 기설철탑의 외측에 철탑각입 기초공사하는 단계와, S2) 상기 기설철탑의 일측 1회선 휴전하고 충전부 방호 후 송전하는 단계와, S3) 상기 기설철탑의 타측 2회선 휴전하는 단계와, S4) 상기 기초공사한 부분에 신설철탑 조립 및 일측 아암 설치하는 단계와, S5) 상기 신설철탑의 일측 아암에 상기 2회선의 전력선 공중이동 및 가선하는 단계와, S6) 상기 1회선의 휴전 후 신설철탑의 타측 아암 설치하는 단계와, S7) 상기 신설철탑의 타측 아암에 상기 1회선의 전력선 공중이동 및 가선하고 송전하는 단계와, S8) 상기 기설철탑을 철거하는 단계를 포함하는 것을 특징으로 한다.According to an aspect of the present invention for achieving the above object, there is provided a method of manufacturing a steel tower, comprising the steps of: S1) installing a steel tower on the outside of an existing steel tower; S2) A step S3) of interrupting the other two lines of the existing pylon; S4) a step of assembling a new pylon and installing a single arm on the pylon; b) installing a new pylon on one side of the new pylon; A step S6) of installing the other arm of the new steel tower after the interruption of the one line, S7) a step of aerial movement of the power line and transmission and transmission of the one line to the other arm of the new steel tower, S8) removing the existing steel tower.

상기 S1)단계는, 상기 기설철탑의 바깥측 4방향에 마이크로파일 시공하는 과정과, 상기 철탑기초 주각재를 연장조립하는 과정과, 상기 철탑기초 주각재 주변에 철근조립 및 거푸집 설치 후 콘크리트 타설하는 과정을 포함할 수 있다.The method of claim 1 or 2, wherein the step of S1) comprises the steps of: constructing microfiles in four directions on the outside of the existing steel tower; extending and assembling the steel tower main slab; installing reinforcing bars around the steel main frame, Process.

상기 S2)단계에서, 상기 충전부 방호는 상기 기설철탑의 일측 1회선 휴전 후 인접철탑에 검전 및 접지 시행하는 과정과, 상기 1회선 충전부에 방호 가이드바를 설치하는 과정과, 상기 방호 가이드바에 절연암을 설치하는 과정과, 상기 접지 철거 후 상기 1회선에 송전하는 과정을 포함할 수 있다.The method of claim 1 or 2, wherein in the step (S2), the charging of the charging part is performed by conducting detection and grounding of the adjacent steel towers after one side of one side of the existing iron tower is cut off and installing a protection guide bar to the one charging part, And a step of transmitting power to the one line after the ground is demolished.

상기 S4)단계는, 상기 기초공사한 부분에 신설철탑의 바디 조립 및 철탑 본조임을 시행하는 과정과, 상기 기설철탑의 2회선의 전력선을 탑체로 이동시킨 후 아암을 철거하는 과정과, 상기 신설철탑 일측에 아암을 설치하는 과정을 포함할 수 있다.The step S4) includes the steps of assembling the body of the new steel tower and the construction of the steel tower in the foundation part, removing the arm after moving the power line of the two wires of the existing steel tower to the tower, And a step of installing the arm on one side.

상기 S5)단계 후, 접지를 철거하고 송전하는 단계가 더 수행될 수 있다.After step S5), further grounding and transmission may be performed.

상기 S6)단계는, 상기 1회선의 휴전 후 인접철탑에 검전 및 접지 시행하는 과정과, 상기 1회선 충전부 방호 가이드바 및 절연암을 철거하는 과정과, 상기 기설철탑의 1회선의 전력선을 탑체로 이동시킨 후 아암을 철거하는 과정과, 상기 철거된 아암과 대응되는 방향에 신설철탑의 타측 아암을 설치하는 과정을 포함할 수 있다.The method of claim 1, wherein the step S6) comprises the steps of conducting detection and grounding of the adjacent steel towers after the one line is cut off, removing the guard bars and the insulation arm of the one- And then installing the other arm of the new steel tower in a direction corresponding to the removed arm.

상기 S7)단계는, 상기 신설철탑 타측 아암에 상기 1회선의 전력선 공중이동 및 가선하는 과정과, 상기 접지 철거 후 상기 1회선에 송전하는 과정을 포함할 수 있다.The step S7) may include a step of moving the power line by one line to the other arm of the new steel tower and conducting a power line transmission after the ground removal.

본 발명은 기설철탑의 기초를 보강한 후 1회선(#1T/L)과 2회선(#2T/L)을 교번 휴전시키면서 기설철탑의 외측으로 신설철탑을 조립하고, 전력선을 공중이동 및 가선하는 방법을 통해 기설철탑 위치에 신설철탑을 건설할 수 있다.The present invention reinforces the foundation of an existing steel tower and assembles a new steel tower outside the existing steel tower while alternately interrupting the first line (# 1T / L) and the second line (# 2T / L) You can build a new steel tower at the location of the existing tower.

이는 기존의 철탑 상향공법과 달리 임시선로 설치 및 추가 용지 확보 등을 필요로 하지 않으므로 민원을 최소화하면서 철탑 상향공사를 수행할 수 있으며, 기존의 전력선을 재활용할 수 있어 공사비용을 절감하고 공사기간도 획기적으로 감축할 수 있는 효과가 있다.This is because unlike the existing steel tower elevation method, there is no need to install a temporary railway and secure additional paper. Therefore, it is possible to carry out a steel tower elevation work with minimized civil complaints and reduce the construction cost by reusing existing power lines. There is an effect that can be dramatically reduced.

도 1은 본 발명에 의한 송전철탑 상향공법의 과정을 보인 순서도.
도 2는 본 발명에 의한 송전철탑 상향공법 중 S1단계로, 철탑각입 기초공사한 상태를 보인 도면.
도 3은 본 발명에 의한 송전철탑 상향공법 중 S2단계로, 기설철탑 일측 휴전(1회선) 및 충전부 방호(1회선)한 상태를 보인 도면.
도 4는 본 발명에 의한 송전철탑 상향공법 중 S3단계로, 기설철탑 타측 휴전(2회선)한 상태를 보인 도면.
도 5a 및 도 5b는 본 발명에 의한 송전철탑 상향공법 중 S4단계로, 신설철탑 조립 및 일측 아암 설치한 상태를 보인 도면.
도 6은 본 발명에 의한 송전철탑 상향공법 중 S5단계로, 전선 공중이동(2회선) 및 가선 후 송전(2회선)한 상태를 보인 도면.
도 7a 및 도 7b는 본 발명에 의한 송전철탑 상향공법 중 S6단계로, 기설철탑 일측 휴전(1회선) 및 신설철탑 타측 아암 설치한 상태를 보인 도면.
도 8은 본 발명에 의한 송전철탑 상향공법 중 S7단계로, 전선 공중이동(1회선) 및 가선 후 송전(1회선)한 상태를 보인 도면.
도 9는 본 발명에 의한 송전철탑 상향공법 중 S8단계로, 기설철탑을 철거하고 송전철탑이 상향된 상태를 보인 도면.
1 is a flowchart showing a process of a transmission tower elevating method according to the present invention.
FIG. 2 is a view showing a state in which a steel tower is erected in a step S1 of a method of upgrading a transmission tower according to the present invention.
FIG. 3 is a view showing a state in which one side of an existing steel tower is interrupted (one line) and a charging part is protected (one line) in step S2 of the method of upgrading a transmission tower of the present invention.
Fig. 4 is a view showing a state where the other side of the existing steel tower is stopped (two lines) in step S3 of the method of upgrading the transmission tower of the present invention. Fig.
FIGS. 5A and 5B are views showing a state in which a new steel tower is assembled and one arm is installed in step S4 of the method of upgrading a transmission tower of the present invention.
FIG. 6 is a view showing a state in which the wire is moved in the air (two lines) and the line is turned on (two lines) in step S5 of the method of upgrading the transmission tower of the present invention.
FIG. 7A and FIG. 7B are views showing a state in which an arm of one side of an existing steel tower and a side arm of a new steel tower are installed in step S6 of the method of upgrading a transmission tower of the present invention.
FIG. 8 is a view showing a state in which a wire is moved in the air (one line) and a line is transmitted (one line) in step S7 of the method of upgrading a transmission tower of the present invention.
FIG. 9 is a view showing a state in which an existing steel tower is removed and a transmission tower is raised in step S8 of the method of upgrading a transmission tower according to the present invention; FIG.

이하 본 발명의 바람직한 실시예를 첨부된 도면을 참조하여 상세하게 설명한다. Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.

본 발명의 송전철탑 상향공법은, 도 1에 도시된 바와 같이, S1) 철탑각입 기초공사하는 단계와, S2) 기설철탑의 일측 1회선 휴전하고 충전부 방호 후 송전하는 단계와, S3) 기설철탑의 타측 2회선 휴전하는 단계와, S4) 기초공사한 부분에 신설철탑 조립 및 일측 아암 설치하는 단계와, S5) 신설철탑의 일측 아암에 전력선 공중이동 및 가선하는 단계와, S6) 신설철탑의 타측 아암 설치하는 단계와, S7) 신설철탑의 타측 아암에 전력선 공중이동 및 가선하고 송전하는 단계와, S8) 기설철탑을 철거하는 단계를 포함한다. As shown in FIG. 1, the method of upgrading a transmission tower of the present invention comprises the steps of: S1) establishing a foundation for a steel tower; S2) transmitting one of the existing steel towers one after the other, (S6) a step of assembling a new tower and assembling a new tower to the first tower, S5) attaching a power line to the one arm of the tower, and S6) S7) a power line is moved to the other arm of the newly installed steel tower and the power is transmitted and conducted, and S8) the existing steel tower is removed.

송전철탑 상향공법은 기설철탑(1)의 외측에서 기초를 보강한 후 기설철탑(1)의 1회선을 휴전하고 신설철탑(20)을 조립 및 가선한 후 기설철탑(1)을 철거하는 엔클로징 공법으로, 기설철탑(1)의 위치에서 철탑 높이를 높일 수 있으며 기존의 전력선을 재활용할 수 있다. 기설철탑은 기존철탑을 의미한다.The transmission tower elevation method is a method in which the foundation is reinforced from the outside of the existing steel tower 1, the one of the existing steel tower 1 is shut off, the new steel tower 20 is assembled and guided, With the method, the height of the pylon can be increased at the location of the existing pylon (1), and existing power lines can be recycled. An existing steel tower means an existing steel tower.

송전철탑 상향공법은 편측 회선 휴전만으로 기설철탑의 위치에서 철탑 상향 시공이 가능하므로 154kV급 다회선 철탑 및 345kV급 송전철탑에도 적용할 수 있다. It is applicable to the 154kV multi-line tower and the 345kV transmission tower because it is possible to construct the tower upwards from the position of the existing tower by only one side line ceasefire.

S1)단계는, 기설철탑(1)의 외측에 철탑각입 기초공사하는 단계로, 상세하게는 기설철탑(1)의 위치에서 철탑각입 기초공사를 수행한다.Step S1) is a step of performing foundation work on the outside of the existing steel tower 1, specifically, the foundation of the steel tower is performed at the location of the existing steel tower 1. [

그 순서는, 철탑각입 기초공사 시공 전 주변의 구조물 및 지하매설물에 대한 조사를 우선 수행한다. 구조물이나 지하매설 등에 근접하여 시공할 경우 침하나 변형에 대해서도 검토하고 필요하면 방호 또는 이설, 철거한다. 가스관에 근접하여 작업하거나 가스관을 노출하고 작업할 경우에는 전문 감시원을 배치한다.The order should be preceded by a survey of surrounding structures and underground facilities before the construction of the pylon. If construction is carried out close to a structure or underground buried area, it should be examined for damage and deformation, and if necessary, protection or replacement should be carried out. If you are working close to a gas pipe or when you are working on exposing a gas pipe, arrange a professional guardian.

기초공사는 마이크로파일(Micro-PilS5) 시공, 역T형 독립기초 공법, 전면(MAT)기초 공법 중 안정성과 경제성을 고려하여 선택할 수 있으며, 본 실시예에서는 마이크로파일 시공을 선택하여 S1)단계를 수행한다.The foundation construction can be selected in consideration of stability and economy among the micro-pile construction (Micro-PilS5) construction, the inverted-T type independent foundation construction method, and the front (MAT) foundation construction method. In this embodiment, .

S1)단계는, 도 2에 도시된 바와 같이, 기설철탑(1)의 바깥측 4방향에 마이크로파일(5) 시공하는 과정과, 철탑기초 주각재(21)를 연장조립하는 과정과, 철탑기초 주각재(21) 주변에 강도 보강을 위한 철근조립 및 거푸집 설치 후 콘크리트 타설하여 기초 보강을 위한 기저부(25) 및 주체부(27)를 형성하는 과정을 포함할 수 있다.2, the step S1 includes the steps of constructing the micro pile 5 in the four outer sides of the existing pylon 1, extending and assembling the pile 21, And forming a base 25 and a main body 27 for reinforcing the base by placing reinforcing bars around the main plate 21 and assembling the reinforcing bars and installing the concrete after the formwork is installed.

마이크로파일(5) 시공은 진동 및 소음이 적어 도심지 공사에 적합하고 각도에 구애받지 않는 파일 설치가 가능하다.Microfiles (5) Construction is suitable for downtown construction due to low vibration and noise, and it is possible to install files at any angle.

마이크로파일 시공하는 과정은 1)천공(DrillinS7), 2)강관 케이싱 설치, 3)강봉(Thread bar) 설치, 3)강봉 커플러 연결, 4)그라우팅 작업 순으로 진행될 수 있다. Microfile construction can be done in the following order: 1) DrillinS7, 2) Steel pipe casing installation, 3) Steel bar installation, 3) Steel rod coupler connection, and 4) Grouting work.

기설철탑(1) 위치의 지면 천공 후, 천공된 부분에 토사층 홀의 원형 유지를 위해 케이싱(7)을 설치하고 케이싱(7)에 강봉(9)을 삽입하며, 케이싱(7)에 삽입되는 강봉(9)이 편심되지 않도록 3~4m간격으로 강봉의 외주면에 간격제(Centralizer)(11)를 설치한다. 강봉은 길이 및 현장 여건을 고려하여 커플러로 연결하여 설정된 길이를 확보할 수 있다. 케이싱(7)에 강봉(9)의 설치가 완료된 후에는 케이싱(7) 내로 그라우팅 재료(13)를 연속 공급하고 재료가 흘러 넘칠 때까지 수행한다.A casing 7 is provided in the perforated portion to retain the round hole of the soil layer hole and the steel bar 9 is inserted into the casing 7 and the steel bar 9 inserted into the casing 7 9 are not eccentric, a spacer (11) is provided on the outer circumferential surface of the steel bar at intervals of 3 to 4 m. The steel rod can be connected to the coupler considering the length and site conditions to secure the set length. After the completion of the installation of the steel bar 9 in the casing 7, the grouting material 13 is continuously supplied into the casing 7 and the operation is performed until the material overflows.

케이싱(7) 내로 공급되는 그라우팅 재료는 물, 시멘트, 혼화제를 포함할 수 있다. 예를 들어, 시멘트에 대한 물의 비율이 45% 이하, 혼화제는 시멘트 무게×배합율로 포함될 수 있으며, 배합순서는 물, 시멘트, 혼화제 순서이다.The grouting material fed into the casing (7) may comprise water, cement, admixture. For example, the ratio of water to cement may be less than 45%, and the admixture may include cement weight × compounding ratio, and the mixing order is water, cement, and admixture order.

그라우팅 전 적당한 배합비를 결정하기 위해 점성도 시험을 플로우 콘(Flow ConS5)으로 흐름 시간 측정 시험을 수행하는 것이 바람직하며, 흐름 시간(Flow TimS5) 측정은 배합 후 15분 이내에 실시하여 12초 이상 21초 이하가 되도록 한다.It is preferable to conduct a flow time measurement test with a flow cone (Flow ConS5) to determine an appropriate compounding ratio before grouting, and the flow time (Flow TimS5) measurement should be performed within 15 minutes after mixing, .

또한, 그라우팅 전 적당한 배합비를 결정하기 위해 팽창성(Expansibility) 및 블리딩(BleedinS7) 시험을 수행하는 것이 바람직하다. 팽창성 및 블리딩 시험은 직경 10cm, 높이 10cm의 플렉시 유리(plexiglass) 용기를 사용하여야 한다. 측정은 3시간 후와 24시간 후에 실시하며 아래 값을 측정한다. In addition, it is preferable to perform Expansibility and BleedinS7 tests to determine an appropriate blending ratio before grouting. The plexiglass container with a diameter of 10 cm and a height of 10 cm should be used for the swelling and bleeding test. Measurements are made after 3 and 24 hours and the following values are measured.

블리딩(%) : (△1÷S8)×100Bleeding (%): (? 1? S8) 100

팽창율(%) : (△2÷S8)×100Expansion ratio (%): (? 2 / S8) 占 100

△1는 (WATER LEVEL)-(AVERAGE OF GROUT MIX)이고, △2는 (AVERAGE OF GROUT MIX)-(FILLING LEVEL)이다.△ 1 is (WATER LEVEL) - (AVERAGE OF GROUT MIX), and △ 2 is (AVERAGE OF GROUT MIX) - (FILLING LEVEL).

그라우팅 후 마이크로파일의 인발재하시험을 수행한다. 인발재하시험은 마이크로파일의 하중변위 관계를 측정하여 설계 인발력 확보 여부를 확인하기 위해 실시한다.After the grouting, the pull-out test of the micro-files is carried out. Pull load test is performed to check the load displacement displacement of the micro pile to ascertain the design pulling force.

인발재하시험 후, 마이크로파일(5)에 스틸플레이트(15)를 설치하고 잠금너트(17)로 고정한다. 스틸플레이트(15) 및 잠금너트(17)는 설정된 치수의 것을 사용해야 하며, 모든 설치가 완료되면 마이크로파일(5)에 충격 및 손상을 가할 수 있는 유해요인이 없도록 관리한다.After the drawing load test, the steel plate 15 is attached to the micro pile 5 and fixed with the lock nut 17. [ The steel plate 15 and the lock nut 17 should be of a set size and managed so that there is no harmful factor that may impact and damage the micro pile 5 when all the installation is completed.

기설철탑(1) 각 주주재(3)의 바깥측 4방향에 상술한 과정의 마이크로파일 시공이 완료되면 굴착작업 완료 후 기설철탑(1)의 주주재(3)에 외측에 철탑기초 주각재(21)를 연장조립한다. When the micro pile construction of the above-described process is completed in the four outer sides of the main pylon 3 of the existing pylon 1, the pylon foundation main pylon 1 21).

철탑기초 주각재(21)의 연장조립은 기설철탑(1)의 각 외측을 철탑기초 주각재(21)가 감싸도록 설치하는 것이다.In the extension assembly of the steel tower foundation slab 21, each outside of the existing steel tower 1 is installed so as to surround the steel tower foundation slab 21.

철탑기초 주각재(21)의 연장조립은 굴착작업 완료 후 즉시 시행하고 콘크리트 타설까지 완료하여야 하며, 각 철탑기초 주각재(21)를 상호 연결하는 레그 단사재(23)까지 동시 조립하고 경사도를 조정한다. The extension of the base plate 21 of the steel tower is performed immediately after the completion of the excavation work and completed until the concrete is poured. The leg unit 23, which interconnects the base plate 21, do.

철탑기초 주각재(21)에 레그 단사재(23) 조립 후, 면거리, 대각거리, 고저차가 각입도면의 수치와 일치하는지 여부를 최종적으로 확인하고 오차가 있을 경우에는 셋팅장치 조절부를 이용하여 조정한다. 조정이 완료되면 철탑기초 주각재(21)가 흔들리지 않도록 볼트, 너트 등으로 견고하고 적절하게 고정한다.After assembling the leg unit (23) to the base plate (21) of the steel tower, it is finally checked whether the face distance, diagonal distance and height difference coincide with the numerical values in the drawing. If there is an error, do. When the adjustment is completed, fix the base plate of the steel tower (21) firmly and properly with bolts, nuts, etc. so as not to shake.

철근조립은 기저부(25) 및 주체부(27) 형성을 위한 그라우팅 전 콘크리트 강도 보강을 위한 것이다. 거푸집은 기저부(25)와 주체부(27)의 모양 형성을 위한 것이다.The rebar assembly is for reinforcement of the concrete strength before grouting to form the base portion 25 and the main body portion 27. The form is for forming the shape of the base portion 25 and the main body portion 27.

철근조립 및 거푸집 설치시 철근과 거푸집과의 간격은 스페이서를 사용하여 정확하게 유지시키며 철근의 이음은 강도 보강을 위해 한 단면에 모이지 않도록 상호 어긋난 위치에 있도록 하는 것이 바람직하다.It is desirable that the spacing between the reinforcing bars and the formwork be precisely maintained by using spacers and that the joints of the reinforcing bars be offset from each other so as not to be gathered on one end face in order to reinforce the strength.

거푸집 내부는 깨끗이 청소하고 콘크리트의 수분을 흡수하지 않도록 맑은 물을 뿌려 적셔주며 콘크리트의 운반시간 한도는 1.5시간 이내에 하도록 하는 것이 바람직하다. It is recommended to clean the inside of the formwork and spray it with clear water so as not to absorb the moisture of the concrete, and limit the carrying time of the concrete within 1.5 hours.

콘크리트 타설 후 거푸집은 평균 기온 20℃ 이상에서 4일 경과하면 해체할 수 있다. 거푸집 해체에 의해 철탑기초 주각재(21)의 하단 및 마이크로파일(5)을 감싸 철탑기초 주각재(21)를 지지하는 기저부(25)가 형성된다. After pouring the concrete, the form can be disassembled after 4 days at an average temperature of 20 ° C or higher. A bottom portion 25 for supporting the steel tower foundation slab 21 is formed by wrapping the lower end of the steel tower foundation slab 21 and the micro pile 5 by the form disassembly.

기저부(25)의 상부에서 각 철탑기초 주각재(21)를 감싸는 원형의 거푸집을 더 설치한다. 원형의 거푸집에 콘크리트는 레그 단사재(23)에서 30cm 정도 남게 타설하여 후술할 기설철탑(1)의 철거 후 잔여 물량(콘크리트)를 타설하고 마감 처리할 수 있도록 한다.Further, a circular mold for enclosing each steel tower base main wood 21 is further provided at the upper portion of the base portion 25. The concrete is inserted into the circular mold by about 30 cm from the leg monolith (23) so that the residual amount (concrete) of the existing pylon (1) to be described later can be laid and finished.

S2)단계는, 기설철탑의 일측 1회선 휴전하고 충전부 방호 후 송전한다.In step S2, one side of one side of the existing steel tower is cut off and the transmission is carried out after protecting the charging part.

도 3에 도시된 바와 같이, 철탑의 좌측회선(편측)을 1회선이라 하고 #1T/L로 표기하며, 철탑의 우측회선(반대편측)을 2회선이라 하고 #2T/L로 표기한다.As shown in Fig. 3, the left line (one side) of the steel tower is referred to as one line, and the right line (opposite side) of the steel tower is indicated as # 2T / L.

기설철탑(1)의 일측 1회선 휴전은 기설철탑(1)의 좌측회선을 휴전함을 의미한다.The one-line interruption of one side of the existing steel tower (1) means that the left side of the existing steel tower (1) is to be interrupted.

충전부(A) 방호는 기설철탑(1)의 일측 1회선 휴전 후, 휴전한 1회선의 전력선(a)을 인접철탑에 검전 및 접지 시행하는 과정과, 1회선 충전부(A)에 방호 가이드바(31)를 설치하는 과정과, 방호 가이드바(31)에 절연암(33)을 설치하는 과정과, 인접철탑에 접지한 전력선의 접지 철거 후 1회선에 송전하는 과정을 포함한다. The charging section A protection includes the steps of conducting the detection and grounding of the power line a for one line which has ceased after one line of one side of the existing steel tower 1 to the adjacent steel tower, 31, installing the insulation arm 33 on the protection guide bar 31, and disconnection of the grounded power line to the adjacent steel tower and transmission to one line.

충전부(A)는 기설철탑(1)에서 전력선이나 전기기기가 노출되어 감전의 위험이 있는 부분이다. 휴전한 1회선의 충전부(A)에 방호장치를 설치한다. 방호장치는 방호 가이드바(31)와 절연암(33)을 포함한다. The live part (A) is a part where there is a risk of electric shock due to the power line or the electric appliance being exposed in the existing steel tower (1). A protective device is installed in the live part (A) of the one line which has been interrupted. The protection device includes a protection guide bar (31) and an insulation arm (33).

방호 가이드바(31)는 평행하도록 두 개의 산형강을 배치하고, 그 두 산형강 사이를 하나 이상의 형강바로 연결하여 사다리 형상으로 형성한 것이다. 절연암 설치 위치를 도상 검토하고 절연암 설치 위치에 절연암 피팅을 설치할 수 있다. 본 실시예에서는, 사용전압에 맞는 절연암(33)을 방호 가이드바(31)의 각 형강바에 2개씩 설치한다. The protection guide bar (31) is formed by arranging two acid-shaped steel bars so as to be parallel to each other, and connecting the two mountain-shaped steel bars to one or more steel bars to form a ladder shape. Insulation arm installation position can be examined and insulation arm fitting can be installed at insulation arm installation position. In the present embodiment, two insulating arms 33 corresponding to the used voltage are provided for each of the shape steel bars of the protection guide bar 31. [

절연암(33)은 폴리머 절연암, 애자 등이 사용될 수 있다.The insulation arm 33 may be a polymer insulation arm, an insulator, or the like.

절연암(33) 설치 후에는 전력선(a)을 외측으로 밀어내면서 현수크램프에 전력선을 장착시킨 후 절연암(33)에 연결시킬 수 있다. 절연암(33)에 전력선(a)을 연결시키면 충전부 방호장치의 설치가 완료된다. 현수크램프는 전력선(a)을 절연암(33)에 설치하기 위한 금구이다.After the insulation arm 33 is installed, the power line a can be pushed outward and the power line can be attached to the suspension cramp and connected to the insulation arm 33. Connecting the power line (a) to the insulation arm (33) completes the installation of the charging unit protection device. The suspending cramp is a bracket for mounting the power line (a) to the insulating arm 33.

충전부 방호장치 외에도 충전부(A)를 절연효과가 있는 방호망 또는 절연덮개로 완전히 덮어 방호할 수도 있다. In addition to the live part protection device, the live part (A) can be completely covered with a protective net or insulated cover with insulation effect.

충전부(A) 방호 완료 후에는 최종 점검하고 접지를 철거한 후 1회선 송전한다.Charging part (A) After completion of protection, final inspection, remove the ground, and make one transmission.

S3)단계는, 우측회선인 기설철탑(1)의 타측 2회선을 휴전한다.Step S3) cuts off the other two lines of the existing pylon 1 as the right line.

도 4에 도시된 바와 같이, 철탑의 우측회선(반대편측)을 #2T/L로 표기된 2회선을 휴전한다. 1회선 휴전 후 충전부(A)에 방호장치 설치가 완료되면 1회선을 송전하고 2회선을 휴전한다. 2회선의 휴전 조작이 완료되면 2회선의 전력선을 작업구간의 인접철탑에 검전 및 접지 시행한다.As shown in Fig. 4, the two lines indicated by # 2T / L are cut off on the right line (opposite side) of the steel tower. When the protection device is installed in the live part (A) after one line shutdown, one line is transmitted and the two lines are shut off. When the two-line cease-fire operation is completed, the power line of the two lines is energized and grounded to the adjacent steel tower in the working area.

그에 따라, S3)단계에서, 1회전은 송전 상태이고 2회선은 휴전 상태이다.Accordingly, in step S3), one rotation is in the transmission state and the second line is in the arm state.

S4)단계는, 기초공사한 부분에 신설철탑(20) 조립 및 조립한 신설철탑(20)에 일측 아암(20b)을 설치한다.S4), the one-side arm 20b is installed in the new pylon 20 assembled and assembled with the newly built pylon 20 at the base construction.

S4)단계는, 기초공사한 부분에 신설철탑(20)의 바디(22) 조립 및 철탑 본조임을 시행하는 과정과, 기설철탑(1)의 2회선의 전력선(b)을 탑체로 이동시킨 후 아암(1b)을 철거하는 과정과, 신설철탑(20) 일측에 아암(20b)을 설치하는 과정을 포함한다.(B) of the two power lines of the existing pylon 1 are moved to the top of the tower, and the step (S4) is followed by a step of assembling the body (22) of the new pylon (20) (1b), and installing the arm (20b) on one side of the new steel tower (20).

도 5a에 도시된 바와 같이, 2회선의 휴전 조작이 완료된 상태에서 철탑기초 주각재(21)의 상부에 신설철탑(20)의 바디(22)를 조립한다. 신설철탑(20)의 바디(22) 조립은 자재 인상용 다이버 및 와이어를 설치하여 수행할 수 있다. 신설철탑(20)의 높이는 기설철탑(1)의 높이에 비해 높고 높이 제한이 없다.5A, the body 22 of the new pylon 20 is assembled to the upper part of the pylon main frame 21 in a state where the two-line shutdown operation is completed. The body 22 of the new steel tower 20 can be assembled by installing diver and wire for lifting the material. The height of the new steel tower 20 is higher than the height of the existing steel tower 1 and there is no height restriction.

신설철탑(20)의 바디(22) 조립이 완료되면 철탑 본조임을 통해 조립된 상태를 고정할 수 있다.When the assembly of the body 22 of the new steel tower 20 is completed, it is possible to fix the assembled state through the fact that it is the steel tower main body.

신설철탑(20)의 바디(22) 조립 및 고정 완료 후에는, 2회선의 전력선(b)에 설치되는 가선금구를 철거하고, 기설철탑(1)의 아암(1b)에 취부된 전력선(b)을 해체하여 기설철탑(1)의 탑체로 이동시킨다. After completion of the assembly and fixing of the body 22 of the new steel tower 20, the wire bracket provided on the power line b of the two lines is removed and the power line b mounted on the arm 1b of the existing steel tower 1, And moves it to the top of the existing steel tower 1. [

전력선(b)을 기설철탑(1)의 탑체로 이동시킨 후에는 기설철탑(1)의 애자련(미도시)과 아암(1b)을 순차적으로 철거한다. After the power line b is moved to the tower of the existing tower 1, the rotor 1 (not shown) and the arm 1b are sequentially removed.

기설철탑(1)의 아암(1b)에 취부된 전력선(b)을 해체하여 탑체로 이동시킨 후, 아암(1b)을 철거한 상태는 도 5b에 도시된 바와 같다.The state in which the electric power line b attached to the arm 1b of the existing steel tower 1 is disassembled and moved to the column body and the arm 1b is removed is as shown in Fig. 5B.

기설철탑(1)의 아암(1b)을 철거한 방향과 대응되는 신설철탑(20)의 일측에 아암(20b)을 설치한다. 신설철탑(20)의 아암(20b)은 기설철탑(1)의 철거되기 전 아암(1b) 높이에 비해 더 높은 높이에 설치된다.The arm 20b is installed on one side of the new pylon 20 corresponding to the direction in which the arm 1b of the existing pylon 1 is removed. The arm 20b of the new steel tower 20 is installed at a height higher than the height of the arm 1b before the existing steel tower 1 is dismantled.

S5)단계는, 신설철탑(20)의 일측 아암(20b)에 2회선의 전력선 공중이동 및 가선한다. Step S5) involves two lines of power line aerial movement and guidance to one arm 20b of the new steel tower 20. [

신설철탑(20)의 일측 아암(20b) 설치 후에는, 기설철탑(1)의 탑체로 이동시켰던 각 전력선(b)을 공중이동하여 신설철탑(20)의 일측 아암(20b)에 연결하는 가선 공사를 수행한다.After installation of the arm 20b on one side of the new steel tower 20, the electric wires b moved to the tower of the existing steel tower 1 are moved by air and connected to one arm 20b of the new steel tower 20, .

가선 공사 후, 전력선 이도측량 및 전력선 긴선 공사를 수행하며, 이후 전력선 부속 금구류를 설치하여 2회선 전력선(20b)의 공중이동 작업을 완료한다.After the cable construction, the power line idoration survey and the power line long line construction are carried out, and after that, the power line 20b is completed by installing the gold wire fittings of the power line.

2회선의 전력선(20b)이 공중이동되고 신설철탑(20)의 일측 아암(20b)에 가선된 상태는 도 6에 도시된 바와 같다. The state in which the power line 20b of two lines is moved in the air and is led to one arm 20b of the new steel tower 20 is as shown in Fig.

S5)단계 후, 접지를 철거하고 송전하는 단계가 더 수행된다. 즉, 작업이 완료되면, 접지를 철거하고 2회선에 송전한다.After step S5), further grounding and power transmission are performed. That is, when the work is completed, the ground is removed and two lines are transmitted.

공법 적용 결과, 1회선 휴전기간은 0.5일이고, 신설철탑의 바디 조립은 3일, 전력선 이동은 2일이 소요된다.As a result of applying the construction method, the one-line cease-fire period is 0.5 days, the body assembly of the new steel tower takes 3 days, and the power line movement takes 2 days.

S6)단계는, 1회선의 휴전 후 신설철탑(20)의 타측에 아암(20a)을 설치한다.In step S6, an arm 20a is installed on the other side of the new pylon tower 20 after the one line is shut off.

S6)단계는, 1회선의 휴전 후 인접철탑에 검전 및 접지 시행하는 과정과, 도 7a에 도시된 바와 같이, 1회선 충전부 방호 가이드바 및 절연암을 철거하는 과정과, 도 7b에 도시된 바와 같이, 기설철탑(1)의 1회선의 전력선(a)을 탑체로 이동시킨 후 아암(1a)을 철거하는 과정과, 철거된 아암(1a)과 대응되는 방향에 신설철탑(20)의 타측 아암(20a)을 설치하는 과정을 포함한다.Step S6) is a step of conducting detection and grounding to the adjacent steel towers after the one line is shut down, a process of demolishing the one-line charging portion guard bar and the insulation arm as shown in Fig. 7A, A process of removing the arm 1a after the power line a of one line of the existing steel tower 1 is moved to the column and the other arm of the new steel tower 20 in the direction corresponding to the removed arm 1a, (20a).

1회선의 휴전조작이 완료되면 작업구간 인접철탑에 검전 후 접지를 시행하고, 충전부 방호 가이드바(31) 및 절연암(33)을 철거한다. 다음으로 기설철탑(1)의 아암(1a)의 전력선(a) 긴선(취부)를 해체하여 탑체로 이동시킨다. 다음 기설철탑(1)의 애자련 및 아암(1a)을 철거한다.After completion of the one-line cease-fire operation, conduct grounding to the adjacent steel towers after disconnection and remove the charging unit protection guide bar (31) and insulation arm (33). Next, the power line (a) of the arm 1a of the existing steel tower 1 is disassembled and moved to the top body. The rotor of the next existing steel tower 1 and the arm 1a are removed.

기설철탑(1)의 일측 아암(1a) 철거 후 대응되는 신설철탑(20)의 타측 아암(20a)을 설치한다. The other arm 20a of the new steel tower 20 corresponding to the one arm 1a of the existing steel tower 1 is removed.

S7)단계는, 신설철탑(20)의 타측 아암(20a)에 1회선의 전력선(a) 공중이동 및 가선하고 송전한다. S7), the power line (a) of one line is aerial moved to the other arm 20a of the new steel tower 20 and guided.

S7)단계는, 도 8에 도시된 바와 같이, 신설철탑(20) 타측 아암(20a)에 1회선의 전력선(a) 공중이동 및 가선하는 과정과, 접지 철거 후 1회선에 송전하는 과정을 포함한다. Step S7) includes a process of aerial movement and guidance of one power line (a) to the other arm 20a of the new steel tower 20, and a process of transmission to one line after the grounding disconnection do.

신설철탑(20)의 타측 아암(20a) 설치 후에는, 기설철탑(1)의 탑체로 이동시켰던 각 전력선(a)을 공중이동하여 신설철탑(20)의 타측 아암(20a)에 연결하는 가선 공사를 수행한다.After the installation of the other arm 20a of the new steel tower 20, the electric wires a moved to the tower of the existing steel tower 1 are moved by air and connected to the other arm 20a of the new steel tower 20, .

가선 공사 후, 전력선 이도측량 및 전력선 긴선 공사를 수행하며, 이후 전력선 부속 금구류를 설치하여 1회선 전력선(a)의 공중이동 작업을 완료한다.After the cable construction, the power line idoration survey and the power line long line construction are carried out, and after that, the gold wire fixture attached to the power line is installed to complete the air movement work of the power line (a).

1회선의 전력선(a)이 공중이동되고 신설철탑(20)의 타측 아암(20a)에 가선된 상태는 도 8에 도시된 바와 같다. The state in which the power line a of one line is moved in the air and is led to the other arm 20a of the new steel tower 20 is as shown in Fig.

작업이 완료되면, 접지를 철거하고 1회선에 송전한다.When the work is completed, remove the ground and transmit it to one line.

공법 적용 결과, 기설철탑(1)의 1회선 휴전 및 신설철탑(20)의 타측 아암(20a) 조립과 전력선 이동은 1일, 긴선 1일이 소요된다.As a result of applying the method, the one-line cease-fire of the existing pylon 1, the assembly of the other arm 20a of the new pylon 20 and the power line movement takes one day and one day of the long line.

S8)단계는, 기설철탑(1)을 철거하는 단계를 포함한다. Step S8) includes a step of removing the existing steel tower 1.

1회선에 송전이 완료되면 기설철탑(1)을 철거한다. 기설철탑(1)의 철거는 기설철탑(1)의 주주재에서 상부 부분을 분리하고, 분리한 철거재는 신설철탑(20) 내측으로 밧줄을 연결하여 내린 후 제거할 수 있다. Once the transmission is completed on the 1st line, remove the existing steel tower (1). The demolition of the existing steel tower 1 can be carried out by separating the upper part from the main body of the existing steel tower 1 and removing the removed demolition material by connecting the tether to the inside of the new steel tower 20 and lowering it.

기설철탑(1)의 상부 부분 철거가 완료되면, 기설철탑(1)의 주주재를 절단하고 신설철탑(20)의 철탑기초 주각재(21) 부분의 잔여 물량에 콘크리트를 더 타설하고 마감하여 신설철탑(20)의 주체부(27)를 완성한다. When the upper part of the existing steel tower 1 is completely demolished, the main constituent of the existing steel tower 1 is cut, and concrete is further laid on the remaining amount of the steel tower main slab 21 portion of the new steel tower 20, The main body portion 27 of the steel tower 20 is completed.

그에 따라, 도 9에 도시된 바와 같은 기설철탑에 비해 상향된 송전철탑이 완성된다. As a result, the transmission tower is raised as compared with the existing tower shown in Fig.

참고로, 미설명 부호 29은 바닥을 메워 지면과 주체부(27)가 동일한 높이가 되도록 한 것이다.For reference, the reference numeral 29 denotes a case in which the bottom is filled with the main body 27 at the same height.

상술한 송전철탑 상향공법은, 1회선(#1T/L)과 2회선(#2T/L)을 교번 휴전시키면서 신설철탑(20)을 조립하고, 전력선을 공중이동 및 가선하는 방법을 통해 기설철탑(1) 위치에 신설철탑(20)을 건설할 수 있다.The above-mentioned transmission tower elevation method is a method in which a new steel tower 20 is assembled while alternately interrupting one line (# 1T / L) and two lines (# 2T / L) A new steel tower 20 can be constructed at the location (1).

이는 기존의 철탑 상향공법과 달리 임시선로 설치 및 추가 용지 확보 등을 필요로 하지 않으므로 민원을 최소화하면서 철탑 상향 공사를 수행할 수 있고, 기존의 전력선을 이용할 수 있어 공사비용을 절감하고 공사기간도 획기적으로 감축할 수 있다. This is because unlike the existing steel tower elevation method, there is no need to install a temporary railway and secure additional paper. Therefore, it is possible to carry out a steel tower elevation work with minimized civil complaints and reduce the construction cost by using the existing power line, .

본 발명의 권리범위는 위에서 설명된 실시예에 한정되지 않고 청구범위에 기재된 바에 의해 정의되며, 본 발명의 기술분야에서 통상의 지식을 가진 자가 청구범위에 기재된 권리범위 내에서 다양한 변형과 개작을 할 수 있다는 것은 자명하다.The scope of the present invention is not limited to the embodiments described above, but may be defined by the scope of the claims, and those skilled in the art may make various modifications and alterations within the scope of the claims It is self-evident.

1: 기설철탑 1a,1b: 아암
3: 주주재 5: 마이크로파일
7: 케이싱 9: 강봉
11: 간격제 13: 그라우팅 재료
15: 스틸플레이트 17: 잠금너트
20: 신설철탑 20a, 20b: 아암
21: 철탑기초 주각재 22: 바디
23: 레그 단사재 25: 기저부
27: 주체부 A: 충전부
31: 방호 가이드바 33: 절연암
a,b: 전력선
1: existing pylon 1a, 1b: arm
3: Main Presence 5: Micro file
7: casing 9: steel bar
11: gap 13: grouting material
15: Steel plate 17: Lock nut
20: new steel tower 20a, 20b:
21: steel tower foundation main wood 22: body
23: Leg leg material 25:
27: main part A: live part
31: Protection guide bar 33: Insulation arm
a, b: Power line

Claims (7)

S1) 기설철탑의 외측에 철탑각입 기초공사하는 단계;
S2) 상기 기설철탑의 일측 1회선 휴전하고 충전부 방호 후 송전하는 단계;
S3) 상기 기설철탑의 타측 2회선 휴전하는 단계;
S4) 상기 기초공사한 부분에 신설철탑 조립 및 일측 아암 설치하는 단계;
S5) 상기 신설철탑의 일측 아암에 상기 2회선의 전력선 공중이동 및 가선하는 단계;
S6) 상기 1회선의 휴전 후 신설철탑의 타측 아암 설치하는 단계;
S7) 상기 신설철탑의 타측 아암에 상기 1회선의 전력선 공중이동 및 가선하고 송전하는 단계; 및
S8) 상기 기설철탑을 철거하는 단계를 포함하고,
상기 S2)단계에서
상기 충전부 방호는
상기 기설철탑의 일측 1회선 휴전 후 인접철탑에 검전 및 접지 시행하는 과정과,
상기 1회선 충전부에 방호 가이드바를 설치하는 과정과,
상기 방호 가이드바에 절연암을 설치하는 과정과,
상기 접지 철거 후 상기 1회선에 송전하는 과정을 포함하며,
상기 S6)단계는,
상기 1회선의 휴전 후 인접철탑에 검전 및 접지 시행하는 과정과,
상기 1회선 충전부 방호 가이드바 및 절연암을 철거하는 과정과,
상기 기설철탑의 1회선의 전력선을 탑체로 이동시킨 후 아암을 철거하는 과정과,
상기 철거된 아암과 대응되는 방향에 신설철탑의 타측 아암을 설치하는 과정을 포함하는 것을 특징으로 하는 송전철탑 상향공법.
S1) stepping on the outside of the existing pylon;
S2) a step of interrupting one side of the existing iron tower and transmitting power after protecting the charging part;
S3) interrupting the other two lines of the existing steel tower;
S4) assembling a new pylon and installing a new arm on the foundation;
S5) aerial movement and routing of the two power lines to one arm of the new steel tower;
S6) installing the other arm of the new steel tower after the one-line shutdown;
S7) moving the power line by one line to the other arm of the new steel tower; And
S8) removing the existing steel tower,
In step S2)
The charging portion protection
A step of conducting surveillance and grounding to an adjacent steel tower after one-side shutdown of the existing steel tower,
Installing a protection guide bar on the one-line charging unit,
Installing an insulation arm on the protection guide bar;
And transmitting to the one line after the ground disconnection,
The step S6)
A step of detecting and grounding the adjacent steel towers after the one line is cut off,
Removing the one-line-charging-portion-protection-guide bar and the insulation arm;
Moving a power line of one line of the existing steel tower to a tower and then removing the arm;
And installing the other arm of the new steel tower in a direction corresponding to the demolished arm.
청구항 1에 있어서,
상기 S1)단계는,
상기 기설철탑의 바깥측 4방향에 마이크로파일 시공하는 과정과,
상기 철탑기초 주각재를 연장조립하는 과정과,
상기 철탑기초 주각재 주변에 철근조립 및 거푸집 설치 후 콘크리트 타설하는 과정을 포함하는 것을 특징으로 하는 송전철탑 상향공법.
The method according to claim 1,
The step (S1)
A step of constructing microfiles in four directions on the outside of the existing steel tower,
A step of extending and assembling the steel main frame,
And a step of assembling reinforcing bars around the base steel main frame and installing concrete after installing the formers.
삭제delete 청구항 1에 있어서,
상기 S4)단계는,
상기 기초공사한 부분에 신설철탑의 바디 조립 및 철탑 본조임을 시행하는 과정과,
상기 기설철탑의 2회선의 전력선을 탑체로 이동시킨 후 아암을 철거하는 과정과,
상기 신설철탑 일측에 아암을 설치하는 과정을 포함하는 것을 특징으로 하는 송전철탑 상향공법.
The method according to claim 1,
The step S4)
Performing a body assembly of a new steel tower and a steel tower as a foundation of the foundation,
Moving the power line of the two lines of the existing steel tower to the tower and removing the arm,
And installing an arm on one side of the new steel tower.
청구항 1에 있어서,
상기 S5)단계 후,
접지를 철거하고 송전하는 단계가 더 수행되는 것을 특징으로 하는 송전철탑 상향공법.
The method according to claim 1,
After the step S5)
Wherein the step of removing the ground and transmitting power is further performed.
삭제delete 청구항 1에 있어서,
상기 S7)단계는,
상기 신설철탑 타측 아암에 상기 1회선의 전력선 공중이동 및 가선하는 과정과,
상기 접지 철거 후 상기 1회선에 송전하는 과정을 포함하는 것을 특징으로 하는 송전철탑 상향공법.
The method according to claim 1,
The step S7)
A step of aerial movement and routing of the power line of the one line to the other arm of the new steel tower,
And a step of transmitting power to the one line after the ground removal.
KR1020150100855A 2015-07-16 2015-07-16 Method for lifting the height of tower KR101608624B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020150100855A KR101608624B1 (en) 2015-07-16 2015-07-16 Method for lifting the height of tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020150100855A KR101608624B1 (en) 2015-07-16 2015-07-16 Method for lifting the height of tower

Publications (1)

Publication Number Publication Date
KR101608624B1 true KR101608624B1 (en) 2016-04-01

Family

ID=55799485

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020150100855A KR101608624B1 (en) 2015-07-16 2015-07-16 Method for lifting the height of tower

Country Status (1)

Country Link
KR (1) KR101608624B1 (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107859411A (en) * 2017-10-26 2018-03-30 广州电力设计院 Steel pipe pole rainwater, condensate collection row's structure and high-voltage power transmission tower
CN108843117A (en) * 2018-09-25 2018-11-20 国网辽宁省电力有限公司锦州供电公司 Iron tower of power transmission line main material quick change method and its device
CN110616734A (en) * 2019-10-25 2019-12-27 中国电建集团贵州电力设计研究院有限公司 Reinforcement structure and reinforcement method for foundation of expanded tower foot plate type power transmission iron tower
CN110616733A (en) * 2019-10-25 2019-12-27 中国电建集团贵州电力设计研究院有限公司 Integral reinforcing device and method for foundation and component of power transmission tower
CN110629785A (en) * 2019-10-25 2019-12-31 中国电建集团贵州电力设计研究院有限公司 Anchor pier type power transmission iron tower foundation reinforcing structure and method
KR20200038744A (en) * 2018-10-04 2020-04-14 삼성물산 주식회사 Equipment Foundation Structure
KR20200039285A (en) * 2018-10-05 2020-04-16 한국전력공사 Apparatus and method for reinforcing basic of steel tower
CN114809782A (en) * 2022-04-25 2022-07-29 国网山西省电力公司朔州供电公司 Emergency processing method for power line iron tower displacement

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003259520A (en) * 2002-03-06 2003-09-12 Kanden Kogyo Inc Cable shifting construction method
JP2008208632A (en) 2007-02-27 2008-09-11 Tokyo Electric Power Co Inc:The Work method of steel tower
JP5482216B2 (en) * 2010-01-21 2014-05-07 東京電力株式会社 Steel tower reconstruction method
JP2015095933A (en) * 2013-11-11 2015-05-18 東京電力株式会社 Member replacement method of transmission line tower

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003259520A (en) * 2002-03-06 2003-09-12 Kanden Kogyo Inc Cable shifting construction method
JP2008208632A (en) 2007-02-27 2008-09-11 Tokyo Electric Power Co Inc:The Work method of steel tower
JP5482216B2 (en) * 2010-01-21 2014-05-07 東京電力株式会社 Steel tower reconstruction method
JP2015095933A (en) * 2013-11-11 2015-05-18 東京電力株式会社 Member replacement method of transmission line tower

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107859411A (en) * 2017-10-26 2018-03-30 广州电力设计院 Steel pipe pole rainwater, condensate collection row's structure and high-voltage power transmission tower
CN108843117A (en) * 2018-09-25 2018-11-20 国网辽宁省电力有限公司锦州供电公司 Iron tower of power transmission line main material quick change method and its device
CN108843117B (en) * 2018-09-25 2024-05-17 国网辽宁省电力有限公司锦州供电公司 Method and device for quickly replacing main material of transmission line iron tower
KR20200038744A (en) * 2018-10-04 2020-04-14 삼성물산 주식회사 Equipment Foundation Structure
KR102171659B1 (en) * 2018-10-04 2020-10-29 삼성물산 주식회사 Equipment Foundation Structure
KR20200039285A (en) * 2018-10-05 2020-04-16 한국전력공사 Apparatus and method for reinforcing basic of steel tower
KR102172176B1 (en) * 2018-10-05 2020-10-30 한국전력공사 Apparatus and method for reinforcing basic of steel tower
CN110616734A (en) * 2019-10-25 2019-12-27 中国电建集团贵州电力设计研究院有限公司 Reinforcement structure and reinforcement method for foundation of expanded tower foot plate type power transmission iron tower
CN110616733A (en) * 2019-10-25 2019-12-27 中国电建集团贵州电力设计研究院有限公司 Integral reinforcing device and method for foundation and component of power transmission tower
CN110629785A (en) * 2019-10-25 2019-12-31 中国电建集团贵州电力设计研究院有限公司 Anchor pier type power transmission iron tower foundation reinforcing structure and method
CN114809782A (en) * 2022-04-25 2022-07-29 国网山西省电力公司朔州供电公司 Emergency processing method for power line iron tower displacement

Similar Documents

Publication Publication Date Title
KR101608624B1 (en) Method for lifting the height of tower
CN102031784B (en) Slope protection pile pouring and cable bolting construction method for deep foundation pit
CN110306557B (en) Earth excavation method based on basement deep foundation pit engineering
CN207777770U (en) A kind of precast spliced pipe fitting jacking system
US7467910B2 (en) Prefabricated structure made of reinforced concrete with an integrated removable handling system
CN103643971B (en) Tunnel invert sizing end mould rapid constructing method
CN106759420B (en) A kind of prefabricated assembled transformer substation foundation structure
CN209686444U (en) A kind of structure for protecting electric power pipe culvert using top suspention plus lower support dual in situ
CN110485429A (en) A kind of prestressing force fashioned iron assembled combination inner support construction method
CN109680716A (en) A method of electric power pipe culvert is protected using top suspention plus lower support dual in situ
CN109629576B (en) Suspension protection system for water supply pipe crossing foundation pit and construction method
CN109695247B (en) Deep foundation pit temporary pipeline comprehensive arrangement system and construction method
CN110593307A (en) Construction method for pre-protection structure of underground comprehensive pipe gallery with top-span proposed tunnel
KR100924701B1 (en) Construction method for Utility-pipe conduit
CN111894641B (en) Treatment and construction process for tunnel to penetrate through super-huge water-containing cavity karst cave
CN107100083A (en) A kind of T-shaped high pier Cast-in-place Bent Cap formwork erecting structure and construction method
KR102084829B1 (en) Top-down method using precast-concrete colum
CN106968692B (en) Tunnel excavation supporting structure and construction method thereof
KR101401057B1 (en) Method to build underground structures using the pillars and the stigma and steel beam and slab structures are formed
CN104993440A (en) Lightning-protection manual grounding system and construction method by utilizing structure steel bar externally-connected downlead wire
CN106451271B (en) A kind of cable passageway portal structure and its installation method
CN114825187B (en) 220KV sea cable dike crossing restoration construction method for offshore wind farm foundation construction
KR101663374B1 (en) Streetlight Foundation Structure
CN105715094A (en) Protecting device for high-voltage line pole
CN206635786U (en) Prefabricated assembled transformer substation foundation structure

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20190219

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20200219

Year of fee payment: 5