JP5482216B2 - Steel tower reconstruction method - Google Patents

Steel tower reconstruction method Download PDF

Info

Publication number
JP5482216B2
JP5482216B2 JP2010010808A JP2010010808A JP5482216B2 JP 5482216 B2 JP5482216 B2 JP 5482216B2 JP 2010010808 A JP2010010808 A JP 2010010808A JP 2010010808 A JP2010010808 A JP 2010010808A JP 5482216 B2 JP5482216 B2 JP 5482216B2
Authority
JP
Japan
Prior art keywords
steel tower
tower
temporary
foundation
existing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2010010808A
Other languages
Japanese (ja)
Other versions
JP2011151945A (en
Inventor
利人 志賀
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyo Electric Power Co Holdings Inc
Original Assignee
Tokyo Electric Power Co Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyo Electric Power Co Inc filed Critical Tokyo Electric Power Co Inc
Priority to JP2010010808A priority Critical patent/JP5482216B2/en
Publication of JP2011151945A publication Critical patent/JP2011151945A/en
Application granted granted Critical
Publication of JP5482216B2 publication Critical patent/JP5482216B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Electric Cable Installation (AREA)

Description

本発明は、鉄塔の建替工事のための鉄塔建替工法に関するものである。   The present invention relates to a steel tower rebuilding method for a steel tower rebuilding work.

電気事業者の発電所で発電された電気は、地上に建設された鉄塔に張架されている送電線を通じて長距離にわたって送電され、変電所で変電された後に需要家に供給される。送電線を張架する鉄塔は、経年等により老朽化した場合や、更に大容量の電気を送電する送電線を張架するために鉄塔の高さが不足する場合等に建替が必要となる。   Electricity generated at the power station of the electric power company is transmitted over a long distance through a transmission line stretched over a steel tower built on the ground, and after being transformed at the substation, it is supplied to consumers. A steel tower that stretches a transmission line needs to be rebuilt when it becomes obsolete due to aging, etc., or when the height of the steel tower is insufficient to stretch a transmission line that transmits a large amount of electricity. .

鉄塔の建替は、既設の鉄塔(以下、既設鉄塔と称する)を撤去し、新しい鉄塔(以下、新設鉄塔と称する)を設置する鉄塔の建替工事(以下、鉄塔建替工事と称する)により行われる。この際、既設鉄塔周辺の既設建造物の存在や、張架されている電線の配線等の都合上、新設鉄塔は、撤去される既設鉄塔と同じ位置、すなわち元位置に設置されることが多い。   Reconstruction of the steel tower is done by removing the existing steel tower (hereinafter referred to as the existing steel tower) and reconstructing the steel tower (hereinafter referred to as the steel tower rebuilding work) to install a new steel tower (hereinafter referred to as the new steel tower). Done. At this time, the new steel tower is often installed at the same position as the existing steel tower to be removed, i.e., the original position, due to the existence of existing buildings around the existing steel tower and the wiring of the stretched wires. .

当然ながら、元位置に新設鉄塔を建設する前には既設鉄塔を撤去する必要があった。しかしながら、既設鉄塔を撤去すると送電線を張架するものがなくなるため、工事期間中は送電を中断し、送電地域を停電せざるを得ないという事態が生じてしまう。そこで、長期間の停電を回避するために、従来では、既設鉄塔の替わりに送電線を張架する仮設鉄塔を建設する仮工事を行っていた(仮工事工法)。   Naturally, it was necessary to remove the existing steel tower before constructing the new steel tower in its original position. However, when the existing steel tower is removed, there is no longer anything that stretches the transmission line, so there will be a situation in which power transmission is interrupted during the construction period and power transmission areas must be interrupted. Therefore, in order to avoid a long-term power outage, a temporary construction for constructing a temporary steel tower that stretches a transmission line instead of the existing steel tower has been performed (temporary construction method).

図13は、従来の鉄塔建替工法としての仮工事工法を説明する図である。仮工事工法では、まず図13(a)に示すように、既設鉄塔10から離れた土地に仮設鉄塔20の仮基礎20aを施工し、仮基礎20a上に仮設鉄塔20を建設する(仮工事)。そして、図13(b)に示すように、既設鉄塔10に張架されている送電線12を仮設鉄塔20に移設する。その後、図13(c)に示すように、既設鉄塔10および既設鉄塔10の旧基礎10aを撤去する。   FIG. 13 is a diagram for explaining a temporary construction method as a conventional steel tower rebuilding method. In the temporary construction method, first, as shown in FIG. 13 (a), the temporary foundation 20a of the temporary tower 20 is constructed on the land away from the existing tower 10, and the temporary tower 20 is constructed on the temporary foundation 20a (temporary construction). . Then, as shown in FIG. 13 (b), the transmission line 12 stretched around the existing tower 10 is moved to the temporary tower 20. Then, as shown in FIG.13 (c), the existing steel tower 10 and the old foundation 10a of the existing steel tower 10 are removed.

既設鉄塔10およびその旧基礎10aが撤去されたら、図13(d)に示すように、既設鉄塔10が設置されていた用地(元位置)に新設鉄塔30の新基礎30aを施工し、新基礎30a上に新設鉄塔30を建設する。そして、図13(e)に示すように、仮設鉄塔20に張架されている送電線12を新設鉄塔30に移設する。その後、図13(f)に示すように、仮設鉄塔20および仮基礎20aを撤去し、鉄塔建替工事が完了する。   When the existing steel tower 10 and its old foundation 10a are removed, as shown in FIG. 13 (d), the new foundation 30a of the new steel tower 30 is constructed on the site (original position) where the existing steel tower 10 has been installed. A new tower 30 is constructed on 30a. Then, as shown in FIG. 13 (e), the transmission line 12 stretched around the temporary tower 20 is moved to the new tower 30. Then, as shown in FIG.13 (f), the temporary steel tower 20 and the temporary foundation 20a are removed, and a steel tower rebuilding construction is completed.

上述した仮工事工法であれば、送電を中断するのは、既設鉄塔10から仮設鉄塔20への送電線の移設時、および仮設鉄塔20から新設鉄塔30への送電線の移設時だけであり、通常は2ルートある送電線の内、1ルートの停電で移設するため需要家への負担は少ない。しかし、この仮工事工法を実施する場合、仮設鉄塔20の建設用地の地権者から契約の了解を得ることは勿論、仮設鉄塔20に移設した送電線12の線下となる土地の地権者からも契約の了解を得る必要があり、その契約等に煩雑な手続を要した。   With the temporary construction method described above, the transmission is interrupted only when the transmission line is transferred from the existing tower 10 to the temporary tower 20 and when the transmission line is transferred from the temporary tower 20 to the new tower 30. Usually, of the two routes of transmission lines, it will be relocated due to a power outage on one route, so the burden on the customer is small. However, when this temporary construction method is carried out, not only the landowner of the land for the construction of the temporary tower 20 obtains the agreement, but also the landowner of the land under the transmission line 12 moved to the temporary tower 20. It was necessary to obtain the consent of the contract, and complicated procedures were required for the contract.

また仮工事工法において仮設鉄塔20に送電線12を移設した場合、その前後(仮設鉄塔20の両側)の鉄塔に加わる荷重が増大する。すると、かかる鉄塔の強度が不足するため、鉄塔および基礎の補強が必要となり、工期の長期化およびコストの増大を招くという問題も有していた。   Moreover, when the power transmission line 12 is moved to the temporary tower 20 in the temporary construction method, the load applied to the steel towers before and after (on both sides of the temporary tower 20) increases. Then, since the strength of such a steel tower is insufficient, it is necessary to reinforce the steel tower and the foundation, and there is a problem that the construction period is prolonged and the cost is increased.

更に、仮設鉄塔20に移設される送電線12が、電圧170kV以上の電気を送電する超高圧送電線(特別高圧架空電線)であり、送電線12から所定範囲内に既設建造物がある場合には、送電線12が敷設できないという法令による制約があった。山間地等であれば、建造物がない土地もあるためこのような制約はさほど問題にならないが、建造物が密集している都市部では、この制約により用地の確保すら困難な場合もあった。他にも、仮工事工法は、仮設とはいえ鉄塔を1つ建設しなければならないため仮設鉄塔20の建設および撤去に多大な時間と費用を要し、工期の長期化およびコストの増大を招くという問題も有していた。   Furthermore, when the transmission line 12 to be relocated to the temporary tower 20 is an ultra-high-voltage transmission line (extra-high voltage overhead electric wire) that transmits electricity having a voltage of 170 kV or higher, and there is an existing building within a predetermined range from the transmission line 12 There is a restriction by law that the transmission line 12 cannot be laid. In the case of mountainous areas, etc., there are some buildings that do not have buildings, so such restrictions are not a problem. However, in urban areas where buildings are densely populated, it may be difficult to secure land. . In addition, the temporary construction method requires construction of one steel tower even though it is a temporary construction, so it takes a lot of time and money to construct and remove the temporary steel tower 20, leading to a long construction period and an increase in cost. There was also a problem.

上記のような理由から、近年では、仮工事工法に替えて包込工法が次第に普及している。包込工法としては、例えば特許文献1に、腕金よりも長い支持構造物を既設鉄塔に取り付け、ジャンパ線を介して送電線を支持構造物で支持した後に、既設鉄塔を包み込むようにして新設鉄塔を建設する鉄塔建て替え方法が開示されている。   For the above reasons, in recent years, the wrapping method has gradually become widespread instead of the temporary work method. For example, in Patent Document 1, a support structure longer than a brace is attached to an existing steel tower, and a power transmission line is supported by the support structure via a jumper line, and then the new steel tower is wrapped. A method for rebuilding a steel tower for constructing a steel tower is disclosed.

図14は、従来の鉄塔建替工法としての包込工法を説明する図である。一般的な包込工法についてより詳細に説明すると、まず図14(a)に示す既設鉄塔40の旧基礎40aからずれた位置に、図14(b)に示すように新設鉄塔50の新基礎50aを施工する。そして、図14(c)に示すように、既設鉄塔40を包み込むように新基礎50a上に新設鉄塔50を建設し、図14(d)に示すように、既設鉄塔40に張架されている送電線42を新設鉄塔50に移設する。その後、図14(e)に示すように既設鉄塔40を撤去することにより鉄塔建替工事が完了し、図14(f)に示す新設鉄塔50が完成する。   FIG. 14 is a diagram for explaining a wrapping method as a conventional steel tower rebuilding method. The general wrapping method will be described in more detail. First, the new foundation 50a of the new tower 50 as shown in FIG. 14 (b) at a position shifted from the old foundation 40a of the existing tower 40 shown in FIG. 14 (a). Install. And as shown in FIG.14 (c), the new steel tower 50 is constructed on the new foundation 50a so that the existing steel tower 40 may be wrapped, and it is stretched by the existing steel tower 40 as shown in FIG.14 (d). The power transmission line 42 is moved to the new steel tower 50. Thereafter, the existing tower 40 is removed as shown in FIG. 14 (e) to complete the tower rebuilding work, and the new tower 50 shown in FIG. 14 (f) is completed.

上記説明した包込工法によれば、仮設鉄塔20を建設することなく鉄塔を建て替えることができるため、仮設鉄塔20の建設用地や、仮設鉄塔20に送電線12を移設した場合に送電線12の線下となる土地を契約せずにすみ、煩雑な手続を削減することができる。また仮設鉄塔20に要するコストを削減し、且つ工期の短縮を図ることも可能となる。   According to the wrapping method described above, the steel tower can be rebuilt without constructing the temporary tower 20, and therefore, when the transmission line 12 is moved to the construction site of the temporary tower 20 or the temporary tower 20, It eliminates the need for contracting land under the line, and reduces complicated procedures. In addition, the cost required for the temporary steel tower 20 can be reduced, and the work period can be shortened.

特開2001−112131号公報JP 2001-112131 A

上述した包込工法によれば、仮工事工法よりもはるかに効率的に鉄塔建替工事を行うことが可能であった。しかし、再度図14を参照すると、新設鉄塔50自体は既設鉄塔40の用地(以下、既設用地と称する)内に収まっているものの、新設鉄塔50の建設に際して設けられる新基礎50aが既設用地外にまで及んでいる。   According to the wrapping method described above, it was possible to perform the steel tower rebuilding work more efficiently than the temporary construction method. However, referring again to FIG. 14, the new tower 50 itself is contained within the site of the existing tower 40 (hereinafter referred to as the existing site), but the new foundation 50 a provided in the construction of the new tower 50 is outside the existing site. It extends to.

新基礎50aが仮設鉄塔20のように一時的にのみ設置されるものであれば、既設用地周囲の土地を工期中のみ借地すればよいが、新設鉄塔50は次の建替まで永続的に使用されるため、新基礎50aも同様に永続的に設置されることとなる。このため、包込工法のように新設鉄塔50の構成要素が既設用地外にまで及ぶ場合には、新基礎50aがはみ出る周囲の土地を、買い増しまたは鉄塔が存在する限り借地しなくてはならない。   If the new foundation 50a is installed only temporarily like the temporary tower 20, the land around the existing site may be leased only during the construction period, but the new tower 50 will be used permanently until the next rebuilding. Therefore, the new foundation 50a is also permanently installed in the same manner. For this reason, when the components of the new steel tower 50 extend beyond the existing site as in the case of the enclosing method, the surrounding land where the new foundation 50a protrudes must be purchased or leased as long as the steel tower exists. .

しかしながら、一時的な借地は許容しても売却または半永久的な借地は許容しない地権者も多く、買い増しの交渉は困難がある。また土地の売買は土地の貸借よりも契約が複雑であるため、土地を買い増す場合には手続がより煩雑になってしまう。更に、既設用地周囲の土地に既存建造物がなければ買い増し交渉が可能であるが、都市部のように建造物が密集している地域には既設用地周囲の土地に既設建造物が設置されていることも多い。この場合、買い増し交渉を行う余地すらない。   However, there are many landowners who allow temporary lease land but do not permit sale or semi-permanent lease land, and it is difficult to negotiate for purchase. Also, since the purchase and sale of land is more complicated than the lease of land, the procedure becomes more complicated when buying more land. Furthermore, if there are no existing buildings around the existing site, it is possible to buy more and negotiate, but in areas where there are dense buildings such as urban areas, existing buildings are installed on the land around the existing site. There are many. In this case, there is no room for additional purchase negotiations.

したがって、包込工法は、新基礎が既設用地内に収まらず、且つ既設用地周囲の土地を買い増しまたは半永久的な借地ができない場合には適用することができないという問題を有していた。このため、包込工法が適用できない場合であっても、効率的に鉄塔建替工事を行うことが可能な鉄塔建替工法の開発が求められている。   Therefore, the enveloping method has a problem that it cannot be applied when the new foundation does not fit in the existing site and the land around the existing site cannot be purchased or semipermanently leased. For this reason, even if it is a case where an enveloping method cannot be applied, development of the tower rebuilding method which can perform a tower rebuilding work efficiently is calculated | required.

本発明は、このような課題に鑑み、土地の買い増しが不可能な場合であっても効率的に鉄塔建替工事を行うことができ、工期の短縮および工費の削減を図ることが可能な鉄塔建替工法を提供することを目的としている。   In view of such a problem, the present invention can efficiently perform the steel tower rebuilding work even when it is impossible to purchase additional land, and can shorten the construction period and reduce the construction cost. The purpose is to provide a steel tower rebuilding method.

上記課題を解決するために、本発明にかかる鉄塔建替工法の代表的な構成は、送電線を張架する既設鉄塔を撤去し、既設鉄塔が設置されていた位置に新設鉄塔を設置するための鉄塔建替工事に用いる鉄塔建替工法であって、既設鉄塔の基礎である旧基礎の周囲または内部に仮基礎を施工し、仮基礎上に仮設鉄塔下部を建設し、仮設鉄塔下部により既設鉄塔の上部を支持し、既設鉄塔の下部および既設鉄塔の旧基礎を撤去し、既設鉄塔の旧基礎が設けられていた位置に新基礎を施工し、新基礎上に既設鉄塔の上部を包囲するように新設鉄塔を建設し、送電線を既設鉄塔から新設鉄塔に移設し、既設鉄塔の上部および仮設鉄塔下部を撤去することを特徴とする。   In order to solve the above problems, the typical structure of the tower reconstruction method according to the present invention is to remove the existing tower over which the transmission line is stretched, and to install the new tower at the position where the existing tower was installed. This is a steel tower rebuilding method used for the steel tower rebuilding work, in which a temporary foundation is constructed around or inside the old foundation, which is the foundation of the existing steel tower, and the lower part of the temporary steel tower is constructed on the temporary foundation. Support the upper part of the tower, remove the lower part of the existing tower and the old foundation of the existing tower, construct the new foundation at the position where the old foundation of the existing tower was installed, and surround the upper part of the existing tower on the new foundation As described above, the new steel tower is constructed, the transmission line is transferred from the existing steel tower to the new steel tower, and the upper part of the existing steel tower and the lower part of the temporary steel tower are removed.

上記構成によれば、仮設鉄塔下部によって既設鉄塔上部を一時的に支持することにより、既設鉄塔の旧基礎と同じ位置に、新設鉄塔の新基礎を施工することができる。これにより、土地の買い増しが不可能な場合であっても効率的に鉄塔建替工事を行うことができ、工期の短縮および工費の削減を図ることができる。   According to the said structure, the new foundation of a new steel tower can be constructed in the same position as the old foundation of an existing steel tower by temporarily supporting the existing steel tower upper part by a temporary steel tower lower part. Thereby, even if it is not possible to purchase more land, the steel tower rebuilding work can be performed efficiently, and the construction period can be shortened and the construction cost can be reduced.

上記課題を解決するために、本発明にかかる鉄塔建替工法の他の構成は、送電線を張架する既設鉄塔を撤去し、既設鉄塔が設置されていた位置に新設鉄塔を設置するための鉄塔建替工事に用いる鉄塔建替工法であって、既設鉄塔の基礎である旧基礎の周囲または内部に仮基礎を施工し、仮基礎上に仮設鉄塔下部を建設し、仮設鉄塔下部上に既設鉄塔の上部を包囲するように新設鉄塔の上部を建設し、送電線を既設鉄塔から新設鉄塔に移設し、既設鉄塔および既設鉄塔の旧基礎を撤去し、既設鉄塔の旧基礎が設けられていた位置に新基礎を施工し、新基礎上に仮設鉄塔下部の内部に新設鉄塔の下部を建設し、新設鉄塔の下部により新設鉄塔の上部を支持し、仮設鉄塔下部を撤去することを特徴とする。   In order to solve the above-mentioned problem, another structure of the steel tower rebuilding method according to the present invention is to remove an existing steel tower that stretches a transmission line and to install a new steel tower at a position where the existing steel tower was installed. It is a steel tower rebuilding method used for steel tower rebuilding work, in which a temporary foundation is constructed around or inside the old foundation that is the foundation of the existing steel tower, a temporary steel tower lower part is constructed on the temporary foundation, and an existing steel tower is installed on the lower part of the temporary steel tower. The upper part of the new steel tower was constructed to surround the upper part of the steel tower, the transmission line was transferred from the existing steel tower to the new steel tower, the existing steel tower and the old foundation of the existing steel tower were removed, and the old foundation of the existing steel tower was provided A new foundation is constructed at the location, the lower part of the new tower is built inside the lower part of the temporary tower, the upper part of the new tower is supported by the lower part of the new tower, and the lower part of the temporary tower is removed .

上記構成によれば、仮設鉄塔下部によって新設鉄塔上部を一時的に支持することにより、既設鉄塔の旧基礎と同じ位置に、新設鉄塔の新基礎を施工することができる。これにより、土地の買い増しが不可能な場合であっても効率的に鉄塔建替工事を行うことができ、工期の短縮および工費の削減を図ることができる。   According to the said structure, the new foundation of a new steel tower can be constructed in the same position as the old foundation of an existing steel tower by temporarily supporting the upper part of a new steel tower by the temporary steel tower lower part. Thereby, even if it is not possible to purchase more land, the steel tower rebuilding work can be performed efficiently, and the construction period can be shortened and the construction cost can be reduced.

そして、上述した複数の鉄塔建替工法であれば、170kV以上の特別高圧架空電線路の周辺が市街化され仮設鉄塔を建設し送電線を移設する事が不可能な場合においても、既設鉄塔周辺の土地を一時的に借地することさえ出来れば、電気設備技術基準に抵触する事なく建替が可能となる。またかかる鉄塔建替工法では、既設鉄塔から新設鉄塔への電線移設は、送電線の移動方向が縦方向(下方から上方への移動)である。このため、建替対象となる鉄塔の前後の鉄塔に加わる荷重が増加することがない。したがって、前後の鉄塔およびその基礎の補強が不要となるため、工期の長期化およびコストの増大という問題が解決される。   In the case of the above-mentioned multiple steel tower rebuilding methods, even if the area around the extra high voltage overhead cableway of 170 kV or higher is urbanized and it is impossible to construct a temporary tower and relocate the transmission line, As long as the land can be temporarily leased, it can be rebuilt without violating the technical standards for electrical equipment. Moreover, in this steel tower rebuilding method, the electric wire transfer from the existing steel tower to the new steel tower is such that the moving direction of the transmission line is the vertical direction (moving from below to above). For this reason, the load added to the steel tower before and behind the steel tower used as rebuilding object does not increase. This eliminates the need to reinforce the front and rear steel towers and their foundations, thereby solving the problems of longer construction period and cost.

上記の仮基礎は、既設鉄塔の旧基礎を頂点とする四角形の4辺のうち、いずれかの対向する2辺に沿って2つ以上ずつの杭を打って施工されるとよい。かかる構成によれば、既設鉄塔を上方から見たときにその旧基礎を頂点とする四角形の4辺のうち、いずれかの対向する2辺、すなわち上辺および下辺に沿って、または左辺および右辺に沿って2以上の仮基礎が施工される。したがって、仮基礎および仮設鉄塔下部は、既設用地周囲の土地のうち、上辺および下辺に隣接する土地、または左辺および右辺に隣接する土地のいずれか一方の土地にしか及ばない。このため、仮基礎および仮設鉄塔下部の位置を選択することが可能となり、既設鉄塔周辺の対向する2辺に既設建造物がある場合においても効率的に鉄塔建替工事を行うことができるという利点がある。   The temporary foundation described above may be constructed by hitting two or more piles along any two opposing sides of the four sides of the quadrangle whose apex is the old foundation of the existing steel tower. According to such a configuration, when the existing steel tower is viewed from above, among the four sides of the quadrangle whose apex is the old foundation, any two opposing sides, that is, along the upper side and the lower side, or on the left side and the right side Two or more temporary foundations are constructed along. Accordingly, the temporary foundation and the lower part of the temporary tower extend only to one of the land around the existing site, the land adjacent to the upper side and the lower side, or the land adjacent to the left side and the right side. For this reason, it becomes possible to select the positions of the temporary foundation and the lower part of the temporary tower, and even if there are existing buildings on two opposite sides around the existing tower, the advantage that the tower rebuilding work can be performed efficiently There is.

上記の仮基礎は、既設鉄塔の旧基礎を頂点とする四角形の4辺すべてに沿って2つ以上ずつの杭を打って施工されるとよい。かかる構成によれば、既設鉄塔の旧基礎を頂点とする四角形の4辺に沿って設けられた8本以上の仮基礎上に仮設鉄塔下部が建設される。したがって、仮基礎の本数が多いため1本辺りの仮基礎にかかる荷重が軽減され、仮設鉄塔下部の安定性を向上させることができる。   The temporary foundation described above may be constructed by hitting two or more piles along all four sides of the quadrangle with the old foundation of the existing steel tower as the apex. According to such a configuration, the lower part of the temporary tower is constructed on eight or more temporary foundations provided along the four sides of a quadrangle whose apex is the old foundation of the existing tower. Therefore, since the number of temporary foundations is large, the load applied to one temporary foundation can be reduced, and the stability of the lower part of the temporary steel tower can be improved.

上記の仮基礎は、既設鉄塔の旧基礎を頂点とする四角形の4辺の各々の略中点に施工されるとよい。かかる構成によれば、仮基礎およびその上に建設される仮設鉄塔下部は、既設鉄塔の領域内に設けられる。したがって、それらは既設用地外には及ばないため、既設用地周囲の土地を借地する必要がない。また仮基礎が既設鉄塔の旧基礎を頂点とする四角形の4辺の各々の略中点に設けられることにより、かかる仮基礎上に建設される仮設鉄塔下部の上下方向の骨組みは、既設鉄塔の上下方向の骨組みを略45°回転させた位置に配設されることとなる。このため、既設鉄塔下部と仮設鉄塔下部との干渉が緩和され、作業効率の向上を図ることが可能となる。   Said temporary foundation is good to be constructed in the approximate middle point of each of the four sides of the quadrangle with the old foundation of the existing steel tower as the apex. According to such a configuration, the temporary foundation and the lower portion of the temporary steel tower constructed on the temporary foundation are provided in the area of the existing steel tower. Therefore, since they do not extend outside the existing site, it is not necessary to rent the land around the existing site. In addition, since the temporary foundation is provided at approximately the midpoint of each of the four sides of the quadrangle with the old foundation of the existing tower as a vertex, the vertical framework of the lower part of the temporary tower constructed on the temporary foundation is The frame in the vertical direction is disposed at a position rotated approximately 45 °. For this reason, the interference between the lower part of the existing steel tower and the lower part of the temporary steel tower is mitigated, and it becomes possible to improve the working efficiency.

上記の仮基礎は、既設鉄塔の旧基礎を頂点とする四角形の内側の対角線上に施工されるとよい。かかる構成によれば、仮基礎およびその上に建設される仮設鉄塔下部は、仮設鉄塔下部が既設鉄塔の内部に建設されるため、既設鉄塔の下部や新設鉄塔の下部と干渉することがない。これにより、仮設鉄塔下部が既設鉄塔の下部や新設鉄塔の下部の建設の支障となることがなく、作業効率を高めることが可能となる。   Said temporary foundation is good to be constructed on the diagonal inside the square which makes the old foundation of an existing steel tower a vertex. According to such a configuration, the temporary foundation and the lower part of the temporary steel tower constructed on the temporary foundation do not interfere with the lower part of the existing steel tower or the lower part of the new steel tower because the lower part of the temporary steel tower is built inside the existing steel tower. Thereby, the temporary steel tower lower part does not interfere with the construction of the lower part of the existing steel tower or the lower part of the new steel tower, and the work efficiency can be increased.

本発明によれば、土地の買い増しが不可能な場合であっても効率的に鉄塔建替工事を行うことができ、工期の短縮および工費の削減を図ることが可能な鉄塔建替工法を提供することができる。   According to the present invention, there is provided a steel tower rebuilding method capable of efficiently performing steel tower rebuilding work even when it is impossible to purchase additional land, and shortening the construction period and reducing the construction cost. Can be provided.

第1実施形態にかかる鉄塔建替工法を説明する概略図である。It is the schematic explaining the steel tower rebuilding method concerning 1st Embodiment. 第1実施形態にかかる鉄塔建替工法を説明する概略図である。It is the schematic explaining the steel tower rebuilding method concerning 1st Embodiment. 第1実施形態にかかる鉄塔建替工法を説明するフローチャートである。It is a flowchart explaining the steel tower rebuilding method concerning 1st Embodiment. 第2実施形態にかかる鉄塔建替工法を説明する概略図である。It is the schematic explaining the steel tower rebuilding method concerning 2nd Embodiment. 第2実施形態にかかる鉄塔建替工法を説明する概略図である。It is the schematic explaining the steel tower rebuilding method concerning 2nd Embodiment. 第3実施形態にかかる鉄塔建替工法を説明する概略図である。It is the schematic explaining the steel tower rebuilding method concerning 3rd Embodiment. 第3実施形態にかかる鉄塔建替工法を説明する概略図である。It is the schematic explaining the steel tower rebuilding method concerning 3rd Embodiment. 第4実施形態にかかる鉄塔建替工法を説明する概略図である。It is the schematic explaining the steel tower rebuilding method concerning 4th Embodiment. 第4実施形態にかかる鉄塔建替工法を説明する概略図である。It is the schematic explaining the steel tower rebuilding method concerning 4th Embodiment. 第5実施形態にかかる鉄塔建替工法を説明する概略図である。It is the schematic explaining the steel tower rebuilding method concerning 5th Embodiment. 第5実施形態にかかる鉄塔建替工法を説明する概略図である。It is the schematic explaining the steel tower rebuilding method concerning 5th Embodiment. 第5実施形態にかかる鉄塔建替工法を説明するフローチャートである。It is a flowchart explaining the steel tower rebuilding method concerning 5th Embodiment. 従来の鉄塔建替工法としての仮工事工法を説明する図である。It is a figure explaining the temporary construction method as a conventional steel tower rebuilding method. 従来の鉄塔建替工法としての包込工法を説明する図である。It is a figure explaining the wrapping construction method as the conventional steel tower rebuilding method.

以下に添付図面を参照しながら、本発明の好適な実施形態について詳細に説明する。かかる実施形態に示す寸法、材料、その他具体的な数値などは、発明の理解を容易とするための例示にすぎず、特に断る場合を除き、本発明を限定するものではない。なお、本明細書及び図面において、実質的に同一の機能、構成を有する要素については、同一の符号を付することにより重複説明を省略し、また本発明に直接関係のない要素は図示を省略する。   Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings. The dimensions, materials, and other specific numerical values shown in the embodiment are merely examples for facilitating understanding of the invention, and do not limit the present invention unless otherwise specified. In the present specification and drawings, elements having substantially the same function and configuration are denoted by the same reference numerals, and redundant description is omitted, and elements not directly related to the present invention are not illustrated. To do.

なお、実施形態の説明に用いる概略図では、既設鉄塔および旧基礎を実線、仮設鉄塔および仮基礎を一点鎖線、新設鉄塔および新基礎を太実線で示し、撤去する箇所を破線で示す。また概略図中、(a)(c)(e)(g)は鉄塔側面の概略図であり、(b)(d)(f)(h)は鉄塔上面の概略図である。   In the schematic diagram used in the description of the embodiment, the existing steel tower and the old foundation are indicated by a solid line, the temporary iron tower and the temporary foundation are indicated by an alternate long and short dash line, the new iron tower and the new foundation are indicated by a thick solid line, and a portion to be removed is indicated by a broken line. In the schematic diagrams, (a), (c), (e), and (g) are schematic diagrams of the side surface of the steel tower, and (b), (d), (f), and (h) are schematic diagrams of the top surface of the steel tower.

(第1実施形態)
図1および図2は、第1実施形態にかかる鉄塔建替工法を説明する概略図であり、図3は、第1実施形態にかかる鉄塔建替工法を説明するフローチャートである。第1実施形態にかかる鉄塔建替工法では、仮設鉄塔下部により既設鉄塔の根開きを拡大させる(以下、既設拡大根開きと称する)。
(First embodiment)
1 and 2 are schematic diagrams for explaining the steel tower rebuilding method according to the first embodiment, and FIG. 3 is a flowchart for explaining the steel tower rebuilding method according to the first embodiment. In the steel tower rebuilding method according to the first embodiment, the root opening of the existing steel tower is expanded by the lower part of the temporary steel tower (hereinafter referred to as the existing widening root opening).

第1実施形態にかかる鉄塔建替工法により既設鉄塔110を建て替える場合、まず図1(a)に示すように既設鉄塔110の基礎である旧基礎112の周囲に仮基礎122を施工する(ステップS172)。これにより、既設用地102の周囲には、図1(b)に示すように仮基礎122が設けられる。本実施形態では、仮基礎122は、既設鉄塔110の旧基礎112を頂点とする四角形の4辺のうち、いずれかの対向する2辺に沿って2つずつの杭を打って施工される。すなわち、図1(b)のように既設鉄塔110を上方から見たときに、その旧基礎112を頂点とする四角形の4辺のうち、いずれかの対向する2辺(本実施形態では左辺および右辺)に沿って2つの仮基礎122が施工される。   When rebuilding the existing steel tower 110 by the steel tower rebuilding method according to the first embodiment, first, the temporary foundation 122 is constructed around the old foundation 112 that is the foundation of the existing steel tower 110 as shown in FIG. 1A (step S172). ). Thereby, the temporary foundation 122 is provided around the existing site 102 as shown in FIG. In the present embodiment, the temporary foundation 122 is constructed by hitting two piles along any two opposing sides of the four sides of the quadrangle having the old foundation 112 of the existing tower 110 as a vertex. That is, when the existing steel tower 110 is viewed from above as shown in FIG. 1B, any two opposing sides (in the present embodiment, the left side and the left side) of the four sides of the quadrangle having the old foundation 112 as a vertex. Two temporary foundations 122 are constructed along the right side).

上記構成によれば、仮基礎122およびその上に建設される仮設鉄塔下部120は、既設用地102周囲の土地のうち、上辺および下辺に隣接する土地、または左辺および右辺に隣接する土地のいずれか一方の土地にしか及ばない。このため、鉄塔周辺の対向する2辺に既設建造物がある場合等において仮基礎122および仮設鉄塔下部120の位置を選択できるという利点がある。   According to the above configuration, the temporary foundation 122 and the temporary steel tower lower part 120 constructed on the temporary foundation 122 are either the land adjacent to the upper side and the lower side or the land adjacent to the left side and the right side of the land around the existing site 102. Only on one land. For this reason, there exists an advantage that the position of the temporary foundation 122 and the temporary steel tower lower part 120 can be selected in the case where there are existing buildings on two opposite sides around the steel tower.

なお、本実施形態においては、既設用地102周囲の土地のうち、左辺および右辺に隣接する土地に仮基礎122を設けたが、これに限定するものではなく、上辺および下辺に隣接する土地に設けてもよい。何れの辺に沿って設けるかは、既設鉄塔110の支配荷重を考慮して決定することが好ましい。また本実施形態では1辺に2つの仮基礎122を設けているが、これにおいても限定されず、3つ以上設けられてもよい。   In the present embodiment, the temporary foundation 122 is provided on the land adjacent to the left side and the right side of the land around the existing site 102. However, the present invention is not limited to this, and is provided on the land adjacent to the upper side and the lower side. May be. It is preferable to determine which side is provided in consideration of the dominant load of the existing tower 110. In this embodiment, two temporary foundations 122 are provided on one side, but this is not restrictive, and three or more temporary foundations may be provided.

次に、図1(c)に示すように、既設鉄塔110の下部(以下、既設鉄塔下部110bと称する)を包囲するように仮基礎122上に仮設鉄塔下部120を建設する(ステップS174)。このとき、仮基礎122が旧基礎112の周囲、すなわち既設用地102の周囲に施工されているため(図1(b)参照)、仮設鉄塔下部120も自ずと既設鉄塔下部110bの周囲に建設され、図1(d)に示すように、仮基礎122および仮設鉄塔下部120は既設用地102外にまで及んでしまう。しかし、後に説明するように仮基礎122および仮設鉄塔下部120は最終的には撤去されるため、既設用地102周囲の土地を買い増しする必要はなく、その土地を一時的に借地するだけで鉄塔建替工事を行うことができる。   Next, as shown in FIG.1 (c), the temporary steel tower lower part 120 is constructed on the temporary foundation 122 so that the lower part of the existing steel tower 110 (henceforth the existing steel tower lower part 110b) may be surrounded (step S174). At this time, since the temporary foundation 122 is constructed around the old foundation 112, that is, around the existing site 102 (see FIG. 1B), the temporary tower lower part 120 is also built around the existing tower lower part 110b, As shown in FIG. 1 (d), the temporary foundation 122 and the temporary steel tower lower portion 120 extend outside the existing site 102. However, as will be described later, since the temporary foundation 122 and the lower part of the temporary tower 120 are finally removed, there is no need to purchase additional land around the existing site 102, and it is only necessary to rent the land temporarily. Reconstruction work can be performed.

仮設鉄塔下部120を建設したら、既設鉄塔110と仮設鉄塔下部120を接続し、仮設鉄塔下部120により既設鉄塔110の上部(以下、既設鉄塔上部110aと称する)を支持する(ステップS176)。その後、図1(e)および(f)に示すように既設鉄塔下部110bを撤去し(ステップS178)、次いで図1(g)および(h)に示すように旧基礎112を撤去する(ステップS180)。   When the temporary steel tower lower part 120 is constructed, the existing steel tower 110 and the temporary steel tower lower part 120 are connected, and the upper part of the existing steel tower 110 (hereinafter referred to as the existing steel tower upper part 110a) is supported by the temporary steel tower lower part 120 (step S176). Thereafter, the existing steel tower lower portion 110b is removed as shown in FIGS. 1E and 1F (step S178), and then the old foundation 112 is removed as shown in FIGS. 1G and 1H (step S180). ).

既設鉄塔下部110bおよび旧基礎112を撤去したら、図2(a)に示すように旧基礎112が設けられていた位置に新基礎132を施工する(ステップS182)。そして、図2(c)に示すように、既設鉄塔上部110aを包囲するように新基礎132上に新設鉄塔130を建設する(ステップS184)。このとき、図2(b)に示すように新基礎132は、旧基礎112が設けられていた位置すなわち既設用地102内に設けられるため、新設鉄塔130も図2(d)に示すように既設用地内に建設されることとなる。   If the existing steel tower lower part 110b and the old foundation 112 are removed, the new foundation 132 will be constructed in the position where the old foundation 112 was provided as shown to Fig.2 (a) (step S182). And as shown in FIG.2 (c), the new steel tower 130 is constructed on the new foundation 132 so that the existing steel tower upper part 110a may be surrounded (step S184). At this time, as shown in FIG. 2 (b), the new foundation 132 is provided in the position where the old foundation 112 was provided, that is, in the existing site 102. Therefore, the new tower 130 is also installed as shown in FIG. 2 (d). It will be built on the site.

新設鉄塔130を建設したら、送電線104を既設鉄塔110から新設鉄塔130に移設する(ステップS186)。そして、図2(e)および(f)に示すように、既設鉄塔上部110aを撤去し(ステップS188)、仮設鉄塔下部120を撤去し(ステップS190)、仮基礎122を既設用地102周囲の土地から撤去する(ステップS192)。これにより、図2(g)および(h)に示すように新設鉄塔130が完成し、当該鉄塔建替工事が完了する。   When the new steel tower 130 is constructed, the transmission line 104 is moved from the existing steel tower 110 to the new steel tower 130 (step S186). Then, as shown in FIGS. 2E and 2F, the existing steel tower upper part 110a is removed (step S188), the temporary steel tower lower part 120 is removed (step S190), and the temporary foundation 122 is land around the existing site 102. (Step S192). Thereby, as shown to FIG.2 (g) and (h), the new steel tower 130 is completed and the said steel tower rebuilding construction is completed.

上記説明したように、第1実施形態にかかる鉄塔建替工法によれば、仮設鉄塔下部120を用いて既設鉄塔上部110aを一時的に支持することにより、既設鉄塔110の旧基礎112と同じ位置に新設鉄塔130の新基礎132を施工することができる。これにより、既設鉄塔110と同じ位置への新設鉄塔130の建設が可能となり、土地の買い増しが不可能な場合であっても効率的に鉄塔建替工事を行うことが可能となる。したがって、工期の短縮および工費の削減が図れる。そして、鉄塔建替工事の際に仮設されるのは仮基礎122および仮設鉄塔下部120のみであるため、仮設鉄塔の上部の建設および撤去に要する費用および時間を削減でき、鉄塔建替工事の効率化を図ることが可能となる。   As described above, according to the steel tower rebuilding method according to the first embodiment, the temporary steel tower lower part 120 is used to temporarily support the existing steel tower upper part 110a, thereby the same position as the old foundation 112 of the existing steel tower 110. The new foundation 132 of the new steel tower 130 can be constructed. As a result, it is possible to construct the new steel tower 130 at the same position as the existing steel tower 110, and it is possible to efficiently perform the steel tower rebuilding work even if it is not possible to purchase additional land. Therefore, the construction period can be shortened and the construction cost can be reduced. Since only the temporary foundation 122 and the lower part of the temporary tower 120 are temporarily installed during the rebuilding work, the cost and time required for the construction and removal of the upper part of the temporary tower can be reduced. Can be achieved.

(第2実施形態)
第2実施形態にかかる鉄塔建替工法は、第1実施形態と同様に既設拡大根開きであるが、旧基礎112を頂点とする四角形の4辺のすべての辺に沿って杭を打って仮基礎122を施工する点において第1実施形態と異なる。
(Second Embodiment)
The steel tower rebuilding method according to the second embodiment is an existing enlarged root opening as in the first embodiment, but the piles are struck along all four sides of the quadrangle with the old foundation 112 as a vertex. It differs from the first embodiment in that the foundation 122 is constructed.

図4および図5は、第2実施形態にかかる鉄塔建替工法を説明する概略図である。なお、第2実施形態の鉄塔建替工法の手順は第1実施形態の鉄塔建替工法と同様であるため、フローチャートについては図3を参照する。また第1実施形態の鉄塔建替工法の構成要素と実質的に同一の機能および構成を有する要素については、同一の符号を付することにより説明を省略する。   4 and 5 are schematic diagrams for explaining the steel tower rebuilding method according to the second embodiment. In addition, since the procedure of the steel tower rebuilding method of 2nd Embodiment is the same as that of the steel tower rebuilding method of 1st Embodiment, refer FIG. 3 for a flowchart. Moreover, about the element which has the function and structure substantially the same as the component of the steel tower rebuilding method of 1st Embodiment, description is abbreviate | omitted by attaching | subjecting the same code | symbol.

第2実施形態にかかる鉄塔建替工法により既設鉄塔110を建て替える場合、まず図4(a)に示すように既設鉄塔110の基礎である旧基礎112の周囲に仮基礎122を施工する(ステップS172)。これにより、既設用地102の周囲には図4(b)に示すように仮基礎122が設けられる。   When rebuilding the existing steel tower 110 by the steel tower rebuilding method according to the second embodiment, first, the temporary foundation 122 is constructed around the old foundation 112 that is the foundation of the existing steel tower 110 as shown in FIG. 4A (step S172). ). Thereby, the temporary foundation 122 is provided around the existing site 102 as shown in FIG.

本実施形態では、仮基礎122は、既設鉄塔110の旧基礎112を頂点とする四角形の4辺すべてに沿って2つずつの杭を打って施工される。したがって、1本辺りの仮基礎122にかかる荷重が軽減されるため、仮設鉄塔下部220の安定性が向上する。なお、本実施形態では、1辺に2つの仮基礎122を設けているが、これに限定するものではなく、3つ以上設けられてもよい。   In this embodiment, the temporary foundation 122 is constructed by hitting two piles along all four sides of a quadrangle having the old foundation 112 of the existing tower 110 as a vertex. Therefore, since the load applied to the temporary foundation 122 around one is reduced, the stability of the temporary steel tower lower portion 220 is improved. In the present embodiment, two temporary foundations 122 are provided on one side, but the present invention is not limited to this, and three or more temporary foundations may be provided.

次に、図4(c)に示すように、既設鉄塔110の下部を包囲するように仮基礎122上に仮設鉄塔下部220を建設する(ステップS174)。本実施形態においても仮基礎122が既設用地102の周囲に施工されているため((図4(b)参照))、図4(d)に示すように仮設鉄塔下部220も既設鉄塔下部110bの周囲にまで及んでしまう。しかし、仮基礎122および仮設鉄塔下部220も最終的には撤去されるため、既設用地102周囲の土地を一時的に借地するだけで鉄塔建替工事を行うことができる。   Next, as shown in FIG.4 (c), the temporary iron tower lower part 220 is constructed on the temporary foundation 122 so that the lower part of the existing iron tower 110 may be surrounded (step S174). Also in this embodiment, since the temporary foundation 122 is constructed around the existing site 102 (see FIG. 4B), as shown in FIG. 4D, the temporary steel tower lower part 220 is also a part of the existing steel tower lower part 110b. It extends to the surroundings. However, since the temporary foundation 122 and the temporary steel tower lower part 220 are finally removed, the steel tower rebuilding work can be performed only by temporarily renting the land around the existing site 102.

仮設鉄塔下部220を建設したら、既設鉄塔110と仮設鉄塔下部220を接続し、仮設鉄塔下部220により既設鉄塔上部110aを支持する(ステップS176)。その後、図4(e)および(f)に示すように既設鉄塔下部110bを撤去し(ステップS178)、次いで図4(g)および(h)に示すように旧基礎112を撤去する(ステップS180)。   When the temporary steel tower lower part 220 is constructed, the existing steel tower 110 and the temporary steel tower lower part 220 are connected, and the existing steel tower upper part 110a is supported by the temporary steel tower lower part 220 (step S176). Thereafter, the existing steel tower lower part 110b is removed as shown in FIGS. 4E and 4F (step S178), and then the old foundation 112 is removed as shown in FIGS. 4G and 4H (step S180). ).

そして、図5(a)に示すように旧基礎112が設けられていた位置に新基礎132を施工し(ステップS182)、図5(c)に示すように既設鉄塔上部110aを包囲するように新基礎132上に新設鉄塔130を建設する(ステップS184)。この場合においても、図5(b)に示すように新基礎132は既設用地102内に設けられるため、新設鉄塔130も図5(d)に示すように既設用地内に建設される。   Then, as shown in FIG. 5 (a), the new foundation 132 is constructed at the position where the old foundation 112 was provided (step S182), and as shown in FIG. 5 (c), the existing steel tower upper part 110a is surrounded. A new steel tower 130 is constructed on the new foundation 132 (step S184). Also in this case, since the new foundation 132 is provided in the existing site 102 as shown in FIG. 5 (b), the new steel tower 130 is also constructed in the existing site as shown in FIG. 5 (d).

新設鉄塔130を建設したら、送電線104を既設鉄塔110から新設鉄塔130に移設し(ステップS186)、図5(e)および(f)に示すように、既設鉄塔上部110aを撤去し(ステップS188)、仮設鉄塔下部220を撤去し(ステップS190)、仮基礎122を既設用地102周囲の土地から撤去する(ステップS192)。これにより、図5(g)および(h)に示すように新設鉄塔130が完成し、当該鉄塔建替工事が完了する。   When the new steel tower 130 is constructed, the transmission line 104 is moved from the existing steel tower 110 to the new steel tower 130 (step S186), and as shown in FIGS. 5E and 5F, the existing steel tower upper portion 110a is removed (step S188). ), The temporary steel tower lower part 220 is removed (step S190), and the temporary foundation 122 is removed from the land around the existing site 102 (step S192). Thereby, as shown to FIG.5 (g) and (h), the new steel tower 130 is completed and the said steel tower rebuilding construction is completed.

上記説明したように、第2実施形態にかかる鉄塔建替工法によっても、仮設鉄塔下部220を用いて既設鉄塔上部110aを一時的に支持し、既設鉄塔110の旧基礎112と同じ位置に新設鉄塔130の新基礎132を施工することができる。したがって、土地の買い増しが不可能な場合であっても効率的に鉄塔建替工事を行うことが可能となり、工期の短縮および工費の削減が図れる。   As described above, also in the steel tower rebuilding method according to the second embodiment, the existing steel tower upper part 110a is temporarily supported using the temporary steel tower lower part 220, and the new steel tower is located at the same position as the old foundation 112 of the existing steel tower 110. 130 new foundations 132 can be constructed. Therefore, even if it is not possible to purchase additional land, it is possible to efficiently perform the steel tower rebuilding work, and the construction period can be shortened and the construction cost can be reduced.

(第3実施形態)
第3実施形態にかかる鉄塔建替工法は、仮基礎122の数は第1実施形態と同様であるが、旧基礎112を頂点とする四角形の4辺の各々の略中点に杭を打って仮基礎122を施工する点において第1実施形態と異なる(既設ツイスト・脚間杭)。
(Third embodiment)
In the steel tower rebuilding method according to the third embodiment, the number of temporary foundations 122 is the same as that of the first embodiment, but a pile is struck at each of the substantially midpoints of the four sides of the quadrangle with the old foundation 112 as a vertex. It differs from 1st Embodiment in the point which constructs temporary foundation 122 (existing twist and pile between legs).

図6および図7は、第3実施形態にかかる鉄塔建替工法を説明する概略図である。なお、第3実施形態の鉄塔建替工法の手順は第1実施形態の鉄塔建替工法と同様であるため、フローチャートについては図3を参照する。また第1実施形態の鉄塔建替工法の構成要素と実質的に同一の機能および構成を有する要素については、同一の符号を付することにより説明を省略する。   6 and 7 are schematic diagrams for explaining the steel tower rebuilding method according to the third embodiment. In addition, since the procedure of the steel tower rebuilding method of 3rd Embodiment is the same as that of the steel tower rebuilding method of 1st Embodiment, refer FIG. 3 for a flowchart. Moreover, about the element which has the function and structure substantially the same as the component of the steel tower rebuilding method of 1st Embodiment, description is abbreviate | omitted by attaching | subjecting the same code | symbol.

第3実施形態にかかる鉄塔建替工法により既設鉄塔110を建て替える場合、まず図6(a)に示すように既設鉄塔110の基礎である旧基礎112を頂点とする四角形の4辺の各々の略中点(旧基礎の周囲または内部)に仮基礎122を施工する(ステップS172)。これにより、既設用地102の内部には図6(b)に示すように仮基礎122が設けられる。したがって、仮基礎122の上に建設される仮設鉄塔下部320は既設用地102内(既設鉄塔110の領域内)に設けられる。このため、仮基礎122および仮設鉄塔下部320を、共に既設用地102外に及ぶことなく設置できる。   When rebuilding the existing steel tower 110 by the steel tower rebuilding method according to the third embodiment, first, as shown in FIG. 6 (a), each of the four sides of the quadrangle having the old foundation 112 which is the foundation of the existing steel tower 110 as a vertex. The temporary foundation 122 is constructed at the midpoint (around or inside the old foundation) (step S172). Thereby, the temporary foundation 122 is provided in the existing site 102 as shown in FIG. Therefore, the temporary steel tower lower part 320 constructed on the temporary foundation 122 is provided in the existing site 102 (in the area of the existing steel tower 110). For this reason, both the temporary foundation 122 and the temporary steel tower lower part 320 can be installed without reaching the existing site 102.

次に、図6(c)に示すように、仮基礎122上に仮設鉄塔下部320を建設する(ステップS174)。本実施形態では、旧基礎112からなる四角形の4辺の各々の略中点に仮基礎122が設けられているため(図6(b)参照)、その上に建設される仮設鉄塔下部320の上下方向の骨組みは、既設鉄塔110の上下方向の骨組みを略45°回転させた位置に配設される。これにより、既設鉄塔下部110bと仮設鉄塔下部320との干渉が緩和され、作業効率の向上を図ることが可能となる。   Next, as shown in FIG.6 (c), the temporary steel tower lower part 320 is constructed on the temporary foundation 122 (step S174). In the present embodiment, since the temporary foundation 122 is provided at substantially the midpoint of each of the four sides of the quadrangle made of the old foundation 112 (see FIG. 6B), the temporary steel tower lower part 320 constructed on the temporary foundation 122 is provided. The vertical frame is disposed at a position obtained by rotating the vertical frame of the existing steel tower 110 by approximately 45 °. Thereby, interference with the existing steel tower lower part 110b and the temporary steel tower lower part 320 is relieved, and it becomes possible to aim at the improvement of work efficiency.

仮設鉄塔下部320を建設したら、既設鉄塔110と仮設鉄塔下部320を接続し、仮設鉄塔下部320により既設鉄塔上部110aを支持する(ステップS176)。その後、図6(e)および(f)に示すように既設鉄塔下部110bを撤去し(ステップS178)、次いで図6(g)および(h)に示すように旧基礎112を撤去する(ステップS180)。   When the temporary steel tower lower part 320 is constructed, the existing steel tower 110 and the temporary steel tower lower part 320 are connected, and the existing steel tower upper part 110a is supported by the temporary steel tower lower part 320 (step S176). Thereafter, the existing steel tower lower part 110b is removed as shown in FIGS. 6E and 6F (step S178), and then the old foundation 112 is removed as shown in FIGS. 6G and 6H (step S180). ).

そして、図7(a)に示すように旧基礎112が設けられていた位置に新基礎132を施工し(ステップS182)、図7(c)に示すように既設鉄塔上部110aを包囲するように新基礎132上に新設鉄塔130を建設する(ステップS184)。このとき、図7(b)に示すように新基礎132は既設用地102内に設けられるため、新設鉄塔130も図7(d)に示すように既設用地102内に建設される。その後、送電線104を既設鉄塔110から新設鉄塔130に移設し(ステップS186)、図7(e)および(f)に示すように、既設鉄塔上部110aを撤去し(ステップS188)、仮設鉄塔下部320を撤去する(ステップS190)。   Then, as shown in FIG. 7A, the new foundation 132 is constructed at the position where the old foundation 112 was provided (step S182), and as shown in FIG. 7C, the existing steel tower upper part 110a is surrounded. A new steel tower 130 is constructed on the new foundation 132 (step S184). At this time, since the new foundation 132 is provided in the existing site 102 as shown in FIG. 7B, the new tower 130 is also constructed in the existing site 102 as shown in FIG. 7D. Thereafter, the transmission line 104 is moved from the existing steel tower 110 to the new steel tower 130 (step S186), and as shown in FIGS. 7E and 7F, the existing steel tower upper portion 110a is removed (step S188), and the temporary steel tower lower portion is removed. 320 is removed (step S190).

既設鉄塔上部110aおよび仮設鉄塔下部320を撤去したら、仮基礎122を撤去する(ステップS192)。このとき、本実施形態では、仮基礎122は既設用地102内に施工されているためその全体を撤去する必要はない。したがって、仮基礎122のうち地面近傍部分のみを撤去する。これにより、撤去作業を簡略化することができ、それに要する時間およびコスト、ひいては工期の短縮および工事費用の削減を図ることが可能となる。そして、図7(g)および(h)に示すように新設鉄塔130が完成し、当該鉄塔建替工事が完了する。   If the existing steel tower upper part 110a and the temporary steel tower lower part 320 are removed, the temporary foundation 122 will be removed (step S192). At this time, in this embodiment, since the temporary foundation 122 is constructed in the existing site 102, it is not necessary to remove the whole. Accordingly, only the portion near the ground of the temporary foundation 122 is removed. As a result, the removal work can be simplified, and the time and cost required for the removal work can be shortened, and the construction period can be shortened and the construction cost can be reduced. And as shown in FIG.7 (g) and (h), the new steel tower 130 is completed and the said steel tower rebuilding construction is completed.

上記説明したように、第3実施形態にかかる鉄塔建替工法においても、仮設鉄塔下部320を用いることにより、既設鉄塔110の旧基礎112と同じ位置に新設鉄塔130の新基礎132を施工することができる。したがって、土地の買い増しをすることなく効率的に鉄塔建替工事を行うことが可能となる。またこの鉄塔建替工法では、旧基礎112を頂点とする四角形の4辺の各々の略中点に仮基礎122を施工することにより、既設鉄塔下部110bと仮設鉄塔下部320との干渉が緩和され、作業効率の向上が図れる。   As described above, also in the steel tower rebuilding method according to the third embodiment, the new foundation 132 of the new steel tower 130 is constructed at the same position as the old foundation 112 of the existing steel tower 110 by using the temporary steel tower lower part 320. Can do. Therefore, it is possible to efficiently perform the steel tower rebuilding work without purchasing additional land. Further, in this steel tower rebuilding method, by constructing the temporary foundation 122 at substantially the midpoint of each of the four sides of the quadrangle having the old foundation 112 as a vertex, interference between the existing steel tower lower part 110b and the temporary steel tower lower part 320 is alleviated. The work efficiency can be improved.

(第4実施形態)
第4実施形態にかかる鉄塔建替工法は、仮基礎122の数は第1実施形態と同様であるが、旧基礎112の内部に仮基礎122を施工し、仮設鉄塔下部により既設鉄塔110の根開きを縮小させる点において第1実施形態と異なる(以下、既設縮小根開きと称する)。
(Fourth embodiment)
In the steel tower rebuilding method according to the fourth embodiment, the number of temporary foundations 122 is the same as that of the first embodiment, but the temporary foundation 122 is constructed inside the old foundation 112 and the root of the existing steel tower 110 is formed by the lower part of the temporary steel tower. It differs from the first embodiment in that the opening is reduced (hereinafter referred to as an existing reduced root opening).

図8および図9は、第4実施形態にかかる鉄塔建替工法を説明する概略図である。なお、第4実施形態の鉄塔建替工法の手順は第1実施形態の鉄塔建替工法と同様であるため、フローチャートについては図3を参照する。また第1実施形態の鉄塔建替工法の構成要素と実質的に同一の機能および構成を有する要素については、同一の符号を付することにより説明を省略する。   8 and 9 are schematic diagrams for explaining the steel tower rebuilding method according to the fourth embodiment. In addition, since the procedure of the steel tower rebuilding method of 4th Embodiment is the same as that of the steel tower rebuilding method of 1st Embodiment, refer FIG. 3 for a flowchart. Moreover, about the element which has the function and structure substantially the same as the component of the steel tower rebuilding method of 1st Embodiment, description is abbreviate | omitted by attaching | subjecting the same code | symbol.

第4実施形態にかかる鉄塔建替工法により既設鉄塔110を建て替える場合、まず図8(a)および(b)に示すように既設鉄塔110の旧基礎112を頂点とする四角形の内側の対角線上、すなわち旧基礎112の内部に仮基礎122を施工する(ステップS172)。そして、図8(c)および(d)に示すように、仮基礎122上に仮設鉄塔下部420を建設する(ステップS174)。このように仮基礎122を旧基礎112の内部に設置することにより、仮設鉄塔下部420も自ずと既設鉄塔下部110b内部すなわち既設用地102内に建設されることとなる。したがって、既設鉄塔下部110bや新設鉄塔下部と仮設鉄塔下部420との干渉が緩和されるため、それらの撤去や建設の際の作業効率を高めることが可能となる。   When rebuilding the existing steel tower 110 by the steel tower rebuilding method according to the fourth embodiment, first, as shown in FIGS. 8 (a) and (b), on the diagonal line inside the square with the old foundation 112 of the existing steel tower 110 as the apex, That is, the temporary foundation 122 is constructed inside the old foundation 112 (step S172). Then, as shown in FIGS. 8C and 8D, the temporary steel tower lower portion 420 is constructed on the temporary foundation 122 (step S174). By installing the temporary foundation 122 inside the old foundation 112 in this way, the temporary steel tower lower part 420 is also built inside the existing steel tower lower part 110b, that is, in the existing site 102. Accordingly, interference between the existing steel tower lower part 110b or the newly installed steel tower lower part and the temporary steel tower lower part 420 is alleviated, so that it is possible to increase the work efficiency in removing or constructing them.

次に、既設鉄塔110と仮設鉄塔下部420を接続し、仮設鉄塔下部420により既設鉄塔上部110aを支持する(ステップS176)。その後、図8(e)および(f)に示すように既設鉄塔下部110bを撤去し(ステップS178)、次いで図8(g)および(h)に示すように旧基礎112を撤去する(ステップS180)。そして、図9(a)に示すように旧基礎112が設けられていた位置に新基礎132を施工し(ステップS182)、図9(c)に示すように既設鉄塔上部110aおよび仮設鉄塔下部420を包囲するように新基礎132上に新設鉄塔130を建設する(ステップS184)。本実施形態においても、図9(b)に示すように新基礎132は既設用地102内に設けられるため、新設鉄塔130も図9(d)に示すように既設用地102内に建設される。   Next, the existing steel tower 110 and the temporary steel tower lower part 420 are connected, and the existing steel tower upper part 110a is supported by the temporary steel tower lower part 420 (step S176). Thereafter, the existing steel tower lower part 110b is removed as shown in FIGS. 8E and 8F (step S178), and then the old foundation 112 is removed as shown in FIGS. 8G and 8H (step S180). ). Then, the new foundation 132 is constructed at the position where the old foundation 112 was provided as shown in FIG. 9A (step S182), and the existing steel tower upper part 110a and the temporary steel tower lower part 420 are shown in FIG. 9C. Is constructed on the new foundation 132 (step S184). Also in this embodiment, since the new foundation 132 is provided in the existing site 102 as shown in FIG. 9 (b), the new steel tower 130 is also constructed in the existing site 102 as shown in FIG. 9 (d).

既設鉄塔110に張架されている送電線104を新設鉄塔130に移設したら(ステップS186)、図9(e)および(f)に示すように、既設鉄塔上部110aを撤去し(ステップS188)、仮設鉄塔下部420を撤去し(ステップS190)、仮基礎122を撤去する(ステップS192)。本実施形態においても仮基礎122は既設用地102内に施工されているため、仮基礎122のうち地面近傍部分のみを撤去する。これにより、撤去作業の簡略化を図り、工期の短縮および工事費用の削減が可能となる。そして、図9(g)および(h)に示すように新設鉄塔130が完成し、当該鉄塔建替工事が完了する。   When the transmission line 104 stretched over the existing tower 110 is moved to the new tower 130 (step S186), as shown in FIGS. 9E and 9F, the existing tower upper portion 110a is removed (step S188). The temporary steel tower lower part 420 is removed (step S190), and the temporary foundation 122 is removed (step S192). Also in this embodiment, since the temporary foundation 122 is constructed in the existing site 102, only the portion near the ground of the temporary foundation 122 is removed. As a result, the removal work can be simplified, the construction period can be shortened, and the construction cost can be reduced. And as shown in FIG.9 (g) and (h), the new steel tower 130 is completed and the said steel tower rebuilding construction is completed.

上記説明したように、第4実施形態にかかる鉄塔建替工法においても、既設用地102内に設けられる仮設鉄塔下部420を用いることにより、既設鉄塔110と同じ位置に新設鉄塔130を建設することができ、鉄塔建替工事の効率化を図れる。また仮設鉄塔下部420が既設鉄塔110の内部に建設されることにより、既設鉄塔下部110bや新設鉄塔下部と仮設鉄塔下部420との干渉が緩和され、それらの撤去や建設の際の作業効率を高めることが可能となる。   As described above, also in the steel tower rebuilding method according to the fourth embodiment, the new steel tower 130 can be constructed at the same position as the existing steel tower 110 by using the temporary steel tower lower portion 420 provided in the existing site 102. It is possible to improve the efficiency of the steel tower rebuilding work. Further, by constructing the lower part of the temporary tower 420 inside the existing tower 110, the interference between the lower part 110b of the existing tower or the lower part of the new tower and the lower part 420 of the temporary tower is alleviated, and the working efficiency in removing or constructing them is increased. It becomes possible.

(第5実施形態)
第5実施形態にかかる鉄塔建替工法は、仮基礎122の数は第1実施形態と同様であるが、仮設鉄塔下部により、根開きを拡大させた状態で新設鉄塔を支持する点において第1実施形態と異なる(以下、新設拡大根開きと称する)。
(Fifth embodiment)
The steel tower rebuilding method according to the fifth embodiment is the same in the number of temporary foundations 122 as in the first embodiment, but is the first in that the new steel tower is supported by the lower part of the temporary steel tower with the root opening expanded. It is different from the embodiment (hereinafter referred to as a newly established root spread).

図10および図11は、第5実施形態にかかる鉄塔建替工法を説明する概略図であり、図12は、第5実施形態にかかる鉄塔建替工法を説明するフローチャートである。また第1実施形態の鉄塔建替工法の構成要素と実質的に同一の機能および構成を有する要素については、同一の符号を付することにより説明を省略する。   FIGS. 10 and 11 are schematic diagrams for explaining the steel tower rebuilding method according to the fifth embodiment, and FIG. 12 is a flowchart for explaining the steel tower rebuilding method according to the fifth embodiment. Moreover, about the element which has the function and structure substantially the same as the component of the steel tower rebuilding method of 1st Embodiment, description is abbreviate | omitted by attaching | subjecting the same code | symbol.

第5実施形態にかかる鉄塔建替工法により既設鉄塔110を建て替える場合、まず図10(a)および(b)に示すように既設鉄塔110の旧基礎112の周囲に仮基礎122を施工する(ステップS572)。そして、図10(c)および(d)に示すように、仮基礎122上に仮設鉄塔下部520を建設し(ステップS574)、仮設鉄塔下部520上に既設鉄塔110の上部を包囲するように新設鉄塔130の上部(以下、新設鉄塔上部130aと称する)を建設する(ステップS576)。   When rebuilding the existing steel tower 110 by the steel tower rebuilding method according to the fifth embodiment, first, the temporary foundation 122 is constructed around the old foundation 112 of the existing steel tower 110 as shown in FIGS. 10 (a) and 10 (b). S572). Then, as shown in FIGS. 10C and 10D, the temporary steel tower lower part 520 is constructed on the temporary foundation 122 (step S574), and the new steel tower 110 is newly installed on the temporary steel tower lower part 520 so as to surround the upper part of the existing steel tower 110. An upper part of the steel tower 130 (hereinafter referred to as a new steel tower upper part 130a) is constructed (step S576).

上述したように仮基礎は旧基礎112の周囲、すなわち既設用地102外に設けられるため、仮設鉄塔下部520も既設用地102外に設けられることとなる。しかし、本実施形態においても仮基礎122および仮設鉄塔下部520は新設鉄塔130建設後に撤去されるため、既設用地102周囲の土地を一時的に借地するだけで鉄塔建替工事を行うことができる。また仮設鉄塔下部520のみを建設することにより、従来のように仮設鉄塔全体を建設する場合と比較して費用および時間を削減でき、鉄塔建替工事の効率化が図れる。   As described above, since the temporary foundation is provided around the old foundation 112, that is, outside the existing site 102, the temporary steel tower lower part 520 is also provided outside the existing site 102. However, also in this embodiment, since the temporary foundation 122 and the temporary steel tower lower part 520 are removed after construction of the new steel tower 130, the steel tower rebuilding work can be performed only by temporarily renting the land around the existing site 102. Moreover, by constructing only the temporary steel tower lower part 520, costs and time can be reduced as compared with the conventional construction of the entire temporary steel tower, and the efficiency of the steel tower rebuilding work can be improved.

新設鉄塔上部130aを建設したら、送電線104を既設鉄塔110から新設鉄塔上部130aに移設する(ステップS578)。その後、図10(e)および(f)に示すように既設鉄塔110を撤去し(ステップS580)、図10(g)および(h)に示すように旧基礎112を撤去する(ステップS582)。   When the new steel tower upper part 130a is constructed, the transmission line 104 is moved from the existing steel tower 110 to the new steel tower upper part 130a (step S578). Thereafter, the existing tower 110 is removed as shown in FIGS. 10E and 10F (step S580), and the old foundation 112 is removed as shown in FIGS. 10G and 10H (step S582).

次に、図11(a)に示すように旧基礎112が設けられていた位置に新基礎132を施工し(ステップS584)、図11(c)および(d)に示すように新基礎132上且つ仮設鉄塔下部520の内部に新設鉄塔130の下部(以下、新設鉄塔下部130bと称する)を建設する(ステップS586)。そして、新設鉄塔上部130aと新設鉄塔下部130bを接続し、新設鉄塔下部130bにより新設鉄塔上部130aを支持する(ステップS588)。このとき、図11(b)に示すように新基礎132は既設用地102内に設けられているため、新設鉄塔下部130bも図11(d)に示すように既設用地102内に建設され、新設鉄塔130が完成する。   Next, as shown in FIG. 11 (a), the new foundation 132 is constructed at the position where the old foundation 112 was provided (step S584), and as shown in FIGS. 11 (c) and (d), on the new foundation 132. In addition, a lower part of the new steel tower 130 (hereinafter referred to as a new steel tower lower part 130b) is constructed inside the temporary steel tower lower part 520 (step S586). Then, the new tower upper portion 130a and the new tower lower portion 130b are connected, and the new tower upper portion 130a is supported by the new tower lower portion 130b (step S588). At this time, since the new foundation 132 is provided in the existing site 102 as shown in FIG. 11 (b), the new steel tower lower part 130b is also constructed in the existing site 102 as shown in FIG. 11 (d). The steel tower 130 is completed.

新設鉄塔130が完成したら、図11(e)および(f)に示すように、仮設鉄塔下部520を撤去し(ステップS590)、仮基礎122を既設用地102周囲の土地から撤去する(ステップS592)。これにより、図11(g)および(h)に示すように既設用地102外の構造物がなくなり、当該鉄塔建替工事が完了する。   When the new tower 130 is completed, as shown in FIGS. 11E and 11F, the lower part of the temporary tower 520 is removed (step S590), and the temporary foundation 122 is removed from the land around the existing site 102 (step S592). . Thereby, as shown in FIGS. 11 (g) and 11 (h), there is no structure outside the existing site 102, and the steel tower rebuilding work is completed.

上記説明したように、第5実施形態にかかる鉄塔建替工法によれば、仮設鉄塔下部120を用いて新設鉄塔上部130aを一時的に支持することにより、旧基礎112と同じ位置に新基礎132を施工することができ、既設鉄塔110と同じ位置への新設鉄塔130の建設が可能となる。したがって、かかる鉄塔建替工法によっても、既設用地102周囲の土地の買い増しが不可能な場合であっても借地のみで効率的に鉄塔建替工事を行うことができ、工期の短縮および工費の削減が図れる。また仮設鉄塔下部520のみを建設することにより、従来の仮工事工法に比べて費用および時間を削減でき、鉄塔建替工事の効率化を図ることが可能となる。   As described above, according to the tower rebuilding method according to the fifth embodiment, the new foundation 132 is placed at the same position as the old foundation 112 by temporarily supporting the upper part 130a of the new tower using the lower part 120 of the temporary tower. It is possible to construct a new steel tower 130 at the same position as the existing steel tower 110. Therefore, even with this tower rebuilding method, even if it is not possible to purchase additional land around the existing site 102, the tower rebuilding work can be carried out efficiently only on leased land, and the construction period can be shortened and the construction cost reduced. Reduction can be achieved. Further, by constructing only the lower part of the temporary tower 520, costs and time can be reduced as compared with the conventional temporary work method, and the efficiency of the rebuilding work of the tower can be improved.

なお、上記の第5実施形態では、既設鉄塔110の旧基礎112の周囲に仮基礎122を施工する場合を例示したが、これに限定するものではなく、仮基礎を旧基礎112の内部に施工してもよい。したがって、第3実施形態において説明した既設ツイスト・脚間杭は、第5実施形態のように仮設鉄塔下部520により新設鉄塔上部130aを支持する場合にも適用可能である。   In addition, in said 5th Embodiment, although the case where the temporary foundation 122 was constructed around the old foundation 112 of the existing steel tower 110 was illustrated, it is not limited to this, and a temporary foundation is constructed in the inside of the old foundation 112. May be. Therefore, the existing twist and inter-leg pile described in the third embodiment can be applied to the case where the new steel tower upper part 130a is supported by the temporary steel tower lower part 520 as in the fifth embodiment.

上述したように、本実施形態にかかる鉄塔建替工法によれば、建替対象となる既設鉄塔の周辺が市街化され仮設鉄塔を建設して送電線を移設すること(包込工法を適用すること)が不可能な場合においても、既設鉄塔周辺の土地を一時的に借地するだけで、電気設備技術基準に抵触する事なく170kV以上の特別高圧架空電線を張架する鉄塔の建替工事を行うことが可能となる。また本実施形態にかかる鉄塔建替工法では、既設鉄塔から新設鉄塔への電線移設は、送電線の移動方向が縦方向(下方から上方への移動)であるため、建替対象となる鉄塔の前後の鉄塔に加わる荷重が増加することがない。したがって、前後の鉄塔およびその基礎の補強が不要となり、工期の短期化およびコストの削減が可能となる。   As described above, according to the steel tower rebuilding method according to the present embodiment, the area around the existing steel tower to be rebuilt is urbanized, a temporary steel tower is constructed, and the transmission line is moved (the enclosing method is applied). Even if this is not possible, it is necessary to rent the land around the existing steel tower temporarily, and reconstruct the steel tower over which a special high-voltage overhead electric wire of 170 kV or more will be stretched without violating the electrical equipment technical standards. Can be done. In addition, in the steel tower rebuilding method according to the present embodiment, in the wire transfer from the existing steel tower to the new steel tower, the moving direction of the transmission line is the vertical direction (moving from the bottom to the top). The load applied to the front and rear steel towers does not increase. Therefore, it is not necessary to reinforce the front and rear steel towers and the foundations thereof, and it is possible to shorten the construction period and reduce costs.

以上、添付図面を参照しながら本発明の好適な実施形態について説明したが、本発明はかかる実施形態に限定されないことは言うまでもない。当業者であれば、特許請求の範囲に記載された範疇内において、各種の変更例または修正例に想到し得ることは明らかであり、それらについても当然に本発明の技術的範囲に属するものと了解される。   As mentioned above, although preferred embodiment of this invention was described referring an accompanying drawing, it cannot be overemphasized that this invention is not limited to this embodiment. It will be apparent to those skilled in the art that various changes and modifications can be made within the scope of the claims, and these are naturally within the technical scope of the present invention. Understood.

本発明は、鉄塔の建替工事のための鉄塔建替工法として利用することができる。   The present invention can be used as a steel tower rebuilding method for a steel tower rebuilding work.

102…既設用地、104…送電線、110…既設鉄塔、110a…既設鉄塔上部、110b…既設鉄塔下部、112…旧基礎、120…仮設鉄塔下部、122…仮基礎、130…新設鉄塔、130a…新設鉄塔上部、130b…新設鉄塔下部、132…新基礎、220・320・420・520…仮設鉄塔下部 DESCRIPTION OF SYMBOLS 102 ... Existing site, 104 ... Transmission line, 110 ... Existing steel tower, 110a ... Existing steel tower upper part, 110b ... Existing steel tower lower part, 112 ... Old foundation, 120 ... Temporary steel tower lower part, 122 ... Temporary foundation, 130 ... New steel tower, 130a ... New steel tower upper part, 130b ... New steel tower lower part, 132 ... New foundation, 220/320/420/520 ... Temporary steel tower lower part

Claims (6)

送電線を張架する既設鉄塔を撤去し、該既設鉄塔が設置されていた位置に新設鉄塔を設置するための鉄塔建替工事に用いる鉄塔建替工法であって、
前記既設鉄塔の基礎である旧基礎の周囲または内部に仮基礎を施工し、
前記仮基礎上に仮設鉄塔下部を建設し、
前記仮設鉄塔下部により前記既設鉄塔の上部を支持し、
前記既設鉄塔の下部および該既設鉄塔の旧基礎を撤去し、
前記既設鉄塔の旧基礎が設けられていた位置に新基礎を施工し、
前記新基礎上に前記既設鉄塔の上部を包囲するように前記新設鉄塔を建設し、
前記送電線を前記既設鉄塔から前記新設鉄塔に移設し、
前記既設鉄塔の上部および前記仮設鉄塔下部を撤去することを特徴とする鉄塔建替工法。
A tower rebuilding method used for a tower rebuilding work for removing an existing tower over which a transmission line is stretched and installing a new tower at a position where the existing tower was installed,
A temporary foundation is constructed around or inside the old foundation, which is the foundation of the existing steel tower,
Construction of the lower part of the temporary tower on the temporary foundation,
The upper part of the existing steel tower is supported by the lower part of the temporary steel tower,
Removing the lower part of the existing steel tower and the old foundation of the existing steel tower;
Install the new foundation at the position where the old foundation of the existing steel tower was established,
The new tower is constructed so as to surround the upper part of the existing tower on the new foundation,
Relocating the transmission line from the existing tower to the new tower,
A steel tower rebuilding method, wherein an upper part of the existing steel tower and a lower part of the temporary steel tower are removed.
送電線を張架する既設鉄塔を撤去し、該既設鉄塔が設置されていた位置に新設鉄塔を設置するための鉄塔建替工事に用いる鉄塔建替工法であって、
前記既設鉄塔の基礎である旧基礎の周囲または内部に仮基礎を施工し、
前記仮基礎上に仮設鉄塔下部を建設し、
前記仮設鉄塔下部上に前記既設鉄塔の上部を包囲するように前記新設鉄塔の上部を建設し、
前記送電線を前記既設鉄塔から前記新設鉄塔に移設し、
前記既設鉄塔および該既設鉄塔の旧基礎を撤去し、
前記既設鉄塔の旧基礎が設けられていた位置に新基礎を施工し、
前記新基礎上に前記仮設鉄塔下部の内部に前記新設鉄塔の下部を建設し、
前記新設鉄塔の下部により前記新設鉄塔の上部を支持し、
前記仮設鉄塔下部を撤去することを特徴とする鉄塔建替工法。
A tower rebuilding method used for a tower rebuilding work for removing an existing tower over which a transmission line is stretched and installing a new tower at a position where the existing tower was installed,
A temporary foundation is constructed around or inside the old foundation, which is the foundation of the existing steel tower,
Construction of the lower part of the temporary tower on the temporary foundation,
The upper part of the new steel tower is constructed so as to surround the upper part of the existing steel tower on the lower part of the temporary steel tower,
Relocating the transmission line from the existing tower to the new tower,
Removing the existing tower and the old foundation of the existing tower;
Install the new foundation at the position where the old foundation of the existing steel tower was established,
The lower part of the new steel tower is constructed inside the lower part of the temporary steel tower on the new foundation,
Support the upper part of the new steel tower by the lower part of the new steel tower,
The steel tower rebuilding method, wherein the lower part of the temporary steel tower is removed.
前記仮基礎は、前記既設鉄塔の旧基礎を頂点とする四角形の4辺のうち、いずれかの対向する2辺に沿って2つ以上ずつの杭を打って施工されることを特徴とする請求項1または2に記載の鉄塔建替工法。   The temporary foundation is constructed by hitting two or more piles along two opposing sides of four sides of a quadrangle having the old foundation of the existing tower as a vertex. Item 3. The tower rebuilding method according to item 1 or 2. 前記仮基礎は、前記既設鉄塔の旧基礎を頂点とする四角形の4辺すべてに沿って2つ以上ずつの杭を打って施工されることを特徴とする請求項1または2に記載の鉄塔建替工法。   3. The tower building according to claim 1, wherein the temporary foundation is constructed by hitting two or more piles along all four sides of a quadrilateral having the old foundation of the existing tower as an apex. Replacement method. 前記仮基礎は、前記既設鉄塔の旧基礎を頂点とする四角形の4辺の各々の略中点に施工されることを特徴とする請求項1または2に記載の鉄塔建替工法。   3. The tower rebuilding method according to claim 1, wherein the temporary foundation is constructed at substantially the midpoint of each of the four sides of a quadrangle having the old foundation of the existing tower as a vertex. 4. 前記仮基礎は、前記既設鉄塔の旧基礎を頂点とする四角形の内側の対角線上に施工されることを特徴とする請求項1に記載の鉄塔建替工法。   The steel tower rebuilding method according to claim 1, wherein the temporary foundation is constructed on a diagonal line inside a quadrangle having the old foundation of the existing steel tower as a vertex.
JP2010010808A 2010-01-21 2010-01-21 Steel tower reconstruction method Active JP5482216B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2010010808A JP5482216B2 (en) 2010-01-21 2010-01-21 Steel tower reconstruction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2010010808A JP5482216B2 (en) 2010-01-21 2010-01-21 Steel tower reconstruction method

Publications (2)

Publication Number Publication Date
JP2011151945A JP2011151945A (en) 2011-08-04
JP5482216B2 true JP5482216B2 (en) 2014-05-07

Family

ID=44538414

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2010010808A Active JP5482216B2 (en) 2010-01-21 2010-01-21 Steel tower reconstruction method

Country Status (1)

Country Link
JP (1) JP5482216B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101608624B1 (en) * 2015-07-16 2016-04-01 한국전력공사 Method for lifting the height of tower
CN106253133A (en) * 2016-08-17 2016-12-21 国家电网公司 A kind of wire coaster

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6863038B2 (en) * 2017-04-21 2021-04-21 東京電力ホールディングス株式会社 Tower rebuilding method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101608624B1 (en) * 2015-07-16 2016-04-01 한국전력공사 Method for lifting the height of tower
CN106253133A (en) * 2016-08-17 2016-12-21 国家电网公司 A kind of wire coaster
CN106253133B (en) * 2016-08-17 2018-03-30 国家电网公司 A kind of wire coaster

Also Published As

Publication number Publication date
JP2011151945A (en) 2011-08-04

Similar Documents

Publication Publication Date Title
JP5482216B2 (en) Steel tower reconstruction method
CN102242570A (en) Method for reinforcing transmission line iron tower
CN103236656B (en) Column suspension type crossing structure and operating method thereof
JP6863038B2 (en) Tower rebuilding method
CN105019419B (en) Jacket, jacket basic platform and jacket method of construction
JP4340001B2 (en) Branching method for overhead transmission lines
CN201238184Y (en) Dual-loop steel pipe column for wires with 2X630 and 4X300 cross section of 220kV power transmission line
JP2008208632A (en) Work method of steel tower
CN101870425A (en) A new type of wire take-up machine
CN103452285B (en) Anechoic room earth screen
Wu et al. Post-evaluation indicator framework for wind farm planning in China
CN205592494U (en) Articulated type cable support
CN210685558U (en) Double-loop cross-shaped cross-lapping structure on four loops on same tower
CN210888814U (en) Workover rig inclined to one side room support device
CN205822595U (en) Beam body hole to be provided reinforcement processes the arrangement of reinforcement of structure
JP2019146352A (en) Steel tower rebuilding method
JP3208666U (en) Reinforcing bar binding structure used for walls
Sanders et al. Windmill erection and maintenance: Challenges for crane design
Bortnik Transmission line compaction using high phase order transmission
JP3424067B2 (en) Tower raising method
CN216240088U (en) Electric power protective fence
CN207728103U (en) A kind of working protection network of bridge
CN221942020U (en) A socket-and-socket scaffolding full-height erection edge protection construction structure
Garzillo et al. Offshore grids in Europe: The strategy of Ireland for 2020 and beyond
CN221029938U (en) A water conservancy slope protection net

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20121217

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20131121

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20140121

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20140203

R150 Certificate of patent or registration of utility model

Ref document number: 5482216

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350