KR101580111B1 - A Continuous Construction-Method with Steel Form for Pier Structure - Google Patents
A Continuous Construction-Method with Steel Form for Pier Structure Download PDFInfo
- Publication number
- KR101580111B1 KR101580111B1 KR1020150056282A KR20150056282A KR101580111B1 KR 101580111 B1 KR101580111 B1 KR 101580111B1 KR 1020150056282 A KR1020150056282 A KR 1020150056282A KR 20150056282 A KR20150056282 A KR 20150056282A KR 101580111 B1 KR101580111 B1 KR 101580111B1
- Authority
- KR
- South Korea
- Prior art keywords
- actuator
- steel
- construction
- steel foam
- slab
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
Description
In particular, the present invention relates to a bridging method, and more particularly, to a steel form which can continuously construct a slab by repeatedly using a foam moving along the course of a bogie, and which does not require complicated and troublesome disassembly and demolition processes after construction of the slab The present invention relates to a continuous construction structure and a construction method of a bridging structure.
In general, the port structures can be divided into pyloric type, gravity type, and dolphin link type according to the support type, and the structure type is determined by the natural condition and economical efficiency of the target place. In addition, Is a mooring facility with a surface water depth of 4.5m or more perpendicular to the direction of the sea of a pier installed to allow the ship to safely berthing and handling cargo and passengers,
In addition, the pylon-type harbor structure is widely used for seaside pier and marina, and is composed of a concrete plate made of concrete, such as a steel bar, a steel pile, a reinforced concrete pile, a reinforced concrete pail, Lt; / RTI >
In recent years, it has been widely used as a docking port by using a pier structure using steel pipe pile, and it is generally used in a region where the soft ground is deep.
As shown in FIGS. 1A to 1F, a construction procedure by a conventional method of constructing a suspended structure will be schematically described as follows.
First, a
The conventional method of constructing a piercing structure according to the related art is a method of installing a large amount of formwork and concrete through a complicated construction step and repeatedly performing work such as demolishing a beam, The construction period is lengthened and many construction and demolition costs are consumed.
In addition, the prior art brick-and-mortar construction method must be removed in order to prevent the support or slab form from falling into the water or the sea due to corrosion or aging. It may be mounted on a ship such as a barge, If the distance between the file and the file is small when the removed crane is used for demolition work, there is a problem that it is impossible to demolish the vessel due to difficulty in entering the vessel for demolition.
In addition, in the method of constructing a suspended structure according to the related art, there is a problem that the dismantled slab form is broken or deformed upon disassembly and can not be recycled, raising the cost of construction.
Therefore, in order to form a slab of a bridging type structure, a form is made of a steel form so that it can be selectively moved in the longitudinal / transverse direction of the structure to be installed and can be recycled for construction, demolition and reworking, There is a need for a continuous construction structure and a construction method of an improved piercing structure in which the installation and disassembly are simple and the curing quality of the slab is made constant according to the gap between the girders.
SUMMARY OF THE INVENTION Accordingly, the present invention has been made in view of the problems of the prior art as described above, and it is an object of the present invention to provide a continuous construction structure and construction method of a suspended structure using a steel foam capable of repeatedly performing a form function for slab construction while moving along a construction direction and a construction site A method is provided.
It is another object of the present invention to provide a steel bell which moves upward and downward in a bogie moving along a rail so that it can be easily detached from concrete to be easily disassembled and structurally deformed.
In addition, another object of the present invention is to improve the degree of completion of construction by uniformizing the quality of concrete pouring and curing processes by using standardized steel foams.
Another object of the present invention is to provide a method and apparatus for automatically moving upward and downward movement and spreading motion of a steel foam by using an actuator so that no operation error occurs and operation is quick and easy.
It is another object of the present invention to provide a method for constructing a concrete by using a steel foam, and a method for demolishing the concrete after curing.
Another object of the present invention is to make it easy to install and construct by using a steel form so that it is not necessary to dismantle and dismantle the same as a conventional formwork.
In order to accomplish the above object, the present invention provides a construction of a bridging structure used as a bridging facility of a port by constructing a girder and a slab on an upper part of a pile installed at a predetermined interval in the longitudinal direction and the transverse direction, A plurality of actuators are mounted on the bogie moving along the rails provided in the longitudinal direction and the transverse direction between the piles to perform a function of forming a concrete when the concrete is placed for constructing the slab in the space between the girder and the girder, The steel foam is lifted up to the upper end of the girder by the upward movement of the actuator to close the space between the girder and the girder and the concrete pouring and curing process for forming the slab is formed on the steel foam When the steel form is lowered by the actuator after roughing, the bogie moves along the rail to the position where the next slab is to be constructed It can be used in construction as it requires no separate over repeated slab formwork construction and provides a continuous structure and the construction method of the pier Structures Using Continuous steel construction can form the pier.
As described above, according to the present invention, it is possible to repeatedly perform the formwork function for the slab construction while moving along the construction direction and the construction site, thereby reducing the construction cost of the facility, and the repetitive installation process is unnecessary, thereby improving the workability.
In addition, the steel foam that moves up and down in the bogie moving along the rail can be easily detached from the concrete using the steel foam, so that it is easy to dismantle and the durability is improved due to no structural deformation.
In addition, by using the standardized steel foam, the quality of the concrete casting and curing process is uniform, thereby improving the degree of completion of construction.
In addition, by using the actuator, the upward and downward movement and the spreading operation of the steel foam are adopted in an automated manner, so that no operation error occurs, and the operation is quick and easy.
In addition, by using steel foam, it is easy to demolish concrete form construction and curing after curing, so that construction period can be drastically shortened and construction cost is reduced.
The use of the steel form facilitates the installation and construction, eliminating the disassembly and demolishing work as in the case of the existing system, thereby eliminating the economical, temporal, and risk burden of demolition.
Figs. 1A to 1F are diagrams showing a process of constructing a conventional bridge,
2 to 9 are views showing a process of constructing a pier using a pier construction structure according to the present invention,
FIG. 10 is a plan view illustrating a construction of a pier using a pier construction structure according to the present invention,
FIG. 11 is an operational flowchart showing a descending operation of the steel foam by the operation of the first and third actuators after the construction of the slab according to the present invention,
Fig. 12 is a view showing the operation of the second actuator after the construction of the slab according to the present invention,
13 is an operation chart of rotating the bogie and the first actuator according to the present invention,
14 is a view showing a process of attaching an auxiliary vane to an empty space generated by the folding and unfolding operation of the variable blade end of the steel foam,
15 is a view showing a process of mounting an auxiliary blade in a bolt or sliding manner to a fixed blade end to close an empty space of a steel foam.
BRIEF DESCRIPTION OF THE DRAWINGS The above and other features and advantages of the present invention will be more apparent from the following detailed description taken in conjunction with the accompanying drawings, in which: FIG.
As shown in FIGS. 2 to 15, the continuous construction structure of the bridging structure using the steel foam according to the present invention comprises a girder on the upper part of the
Here, the file (1) is installed at a predetermined interval on the sea where the bridges are to be installed, and the brackets (2) are installed on the upper side of the file (1).
A
The
That is, the
In this case, the connecting
In addition, the
The
The
That is, the
At this time, the
The
The
The
The
A
At this time, one end of the
That is, the operating
The
The
delete
The
The operation of the
When the
The
The
In addition, the first to
The upper surfaces of the
The bridging
The operation and effect of the bridging construction method using the bridging
As shown in FIGS. 2 to 12, the
A method of constructing the
A
Next, the
At this time, the
Next, the elevating operation is performed by operating the
That is, after the
When the
The
At this time, the supporting
After the
The
Thereafter, the
Next, the concrete is laid on the upper part of the
When the curing of the slab concrete placed on the upper part of the
At this time, if the coating layer is formed on the upper part of the
When the
When the
When the
Thereafter, in the moving operation, the
After completion of the movement of the
At this time, even if the
The
In addition, the bridging
The bridging
In addition, there is a problem that it is inconvenient for a worker to remove the slab formwork manually by completing the curing of the slab concrete after individually installing the slab formworks for each construction area, The
In addition, when the concrete is cured, there is a risk of a safety accident such as a fall because the worker has to dismantle the slab form individually when the concrete is cured. In order to demolish the slab form, The bridging
While the present invention has been particularly shown and described with reference to exemplary embodiments thereof, it is clearly understood that the same is by way of illustration and example only and is not to be construed as limited to the embodiments set forth herein. Various changes and modifications may be made by those skilled in the art.
1: File 2: Bracket
3: longitudinal beam 4: lateral beam
5: Girder Form 6: Girder
7: Strut 8: Slab formwork
8a: Slab 10: Rail
11: connecting rod 12: rail beam
20: carriage 21: frame
21a:
21c:
22: Roller 23: Reinforced frame
30:
31:
31b:
32: Fixed blade section 33: Variable blade section
33a: contact end 34: link
35: Hinge 36: Operation bar
36a: Supporting end 37: Auxiliary wing
40: first actuator 41: first cylinder
41a: rotation projection 42: first cylinder rod
50: second actuator 51: second cylinder
52: second cylinder rod 60: third actuator
61: third cylinder 62: third cylinder rod
100: a bridge construction structure 200: a pier
S1: moving space S2: slab space
Claims (22)
A girder 6 and a girder 6 which are raised on a bogie 20 moving along a rail 10 installed longitudinally and laterally between the piles 1 and formed respectively at upper ends of the piles 1, A steel foam 30 is formed by a plurality of actuators so as to function as a form when a concrete is placed for slab construction,
The rail 10 has a longitudinal beam 3 mounted on a bracket 2 mounted on a pile 1 and a rail beam 12 connected to a linkage 11 on one of the transverse beams 4, Respectively,
The upward movement of the actuator causes the steel foam 30 to rise to the upper end of the girder so as to close the space between the girder 6 and the girder 6 formed at the upper end of the pile 1, When the steel foam 30 is lowered by the actuator after the concrete is inserted and cured for forming the slab on the upper part of the slab 30, the bogie 20 moves along the rail 10 to the position where the next slab is to be constructed, Continuous construction structure of bridged structure using steel foil which can be used for construction and requires no additional slab formwork and continuous construction of bridges.
Characterized in that the first actuator (40) is configured to lift the roof plate (31) of the steel foam (30) upwardly beyond the longitudinal beam (3) and the transverse beam (4) Continuous construction of piercing structure using.
When the steel foam 30 is moved together with the carriage 20, the movable blade 33 is folded so as not to interfere with the pile 1, the bracket 2 and the linkage 11,
Wherein the steel foil (30) is elevated at a predetermined height so that a variable blade section (33) is unfolded for slab construction.
An operating bar 36 is provided below the link 34 in the manner of a hinge 35,
A second actuator 50 pushing the actuating bar 36 is formed below the roof plate 31,
When the actuating bar 36 is pressed by the second actuator 50, the variable wing end 33 is extended with respect to the connecting point of the link 34. When the pressing force of the second actuator 50 is released, Wherein the actuating bar (36) moved by the weight of the step (33) is pushed while rotating with respect to the hinge (35).
The operation bar 36 passes through one side of the case 31a provided at the lower part of the roof plate 31 and the stopper 31b provided inside the case 31a, (31b) in the unfolded state when the movable member (33) is unfolded.
The third actuator 60 mounted on the upper portion of the transverse beam 4 in a detachable manner is pushed up and brought into contact with the contact end 33a of the variable wing end 33 so that the fixed wing end 32 and the variable wing end 33) is aligned with the upper end of the girder. The continuous construction structure of the bridging structure using the steel foam.
When the variable wing end 33 is folded and unfolded, interference with the fixed wing end 32 does not occur due to the empty space 30a. When the variable wing end 33 is unfolded, the auxiliary wing 37) is provided on the continuous structure of the steel structure.
Wherein the auxiliary vane (37) is installed at a lower portion of the fixed vane end (32) using bolts.
A longitudinal beam 3 and a transverse beam 4 are installed on the upper part of the bracket 2 installed in the pile 1 and then a girder mold 5 is installed so that the concrete is laid and cured, and,
A rail 10 is installed on an upper part of a rail beam 12 connected to one of the longitudinal beam 3 and the transverse beam 4 and connected to the linkage 11, The truck 20 on which the loader 30 is mounted is installed so as to be positioned in the slab space between the girder 6 and the girder 6 respectively formed at the upper end of the pile 1,
The second actuator 50 installed on the lower part of the roof plate 31 of the steel foam 30 while raising the steel foam 30 to a predetermined height by operating the first actuator 40 installed on the truck 20, And the variable wing end 33 provided to be rotatably installed on the roof plate 31 is placed on a third actuator 60 installed in one of the longitudinal beam 3 and the lateral beam 4 ,
The third actuator 60 is elevated to raise the steel foam 30 to the upper portion of the girder 5 and then the reinforcement is connected to the girder 6 and the girder 6, And the slab concrete is placed and cured on the upper part of the steel foam 30,
When the slab concrete cures, the third actuator 60 descends the steel foam 30 and the first actuator 40 ascends to support the steel foam 30. When the slab concrete 30 is lowered, The first actuator 40 is rotated through the movement space formed between one of the longitudinal beam 3 and the lateral beam 4 and the rail beam 12 in the folded state by the self weight, ) Can move along the rail (10) and can be used repeatedly for construction, thereby eliminating the need for a separate slab form and allowing continuous construction of the bridges.
Characterized in that the first actuator (40) is configured to lift the roof plate (31) of the steel foam (30) upwardly beyond the longitudinal beam (3) and the transverse beam (4) Continuous construction method of piercing structure using.
When the steel foam 30 is moved together with the carriage 20, the movable blade 33 is folded so as not to interfere with the pile 1, the bracket 2 and the linkage 11,
Wherein the steel foil (30) is elevated at a predetermined height so that a variable blade section (33) is unfolded for slab construction.
An operating bar 36 is provided below the link 34 in the manner of a hinge 35,
A second actuator 50 pushing the actuating bar 36 is formed below the roof plate 31,
When the actuating bar 36 is pressed by the second actuator 50, the variable wing end 33 is extended with respect to the connecting point of the link 34. When the pressing force of the second actuator 50 is released, Wherein the actuating bar (36) moved by the weight of the step (33) is pushed while being rotated about the hinge (35).
The operation bar 36 passes through one side of the case 31a provided at the lower part of the roof plate 31 and the stopper 31b provided inside the case 31a, (31b) in the unfolded state of the steel plate (33).
The third actuator 60 is pushed up while contacting the contact end 33a of the variable wing end 33 so that the ends of the fixed wing end 32 and the variable wing end 33 coincide with the upper end of the girder Wherein the continuous structure is formed by using a steel foam.
When the variable wing end 33 is folded and unfolded, interference with the fixed wing end 32 does not occur due to the empty space 30a. When the variable wing end 33 is unfolded, the auxiliary wing 37) is provided on the upper surface of the steel structure (20).
Wherein the auxiliary wing (37) is installed at a lower portion of the fixed wing end (32) using bolts.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020150056282A KR101580111B1 (en) | 2015-04-22 | 2015-04-22 | A Continuous Construction-Method with Steel Form for Pier Structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020150056282A KR101580111B1 (en) | 2015-04-22 | 2015-04-22 | A Continuous Construction-Method with Steel Form for Pier Structure |
Publications (1)
Publication Number | Publication Date |
---|---|
KR101580111B1 true KR101580111B1 (en) | 2015-12-28 |
Family
ID=55085036
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020150056282A KR101580111B1 (en) | 2015-04-22 | 2015-04-22 | A Continuous Construction-Method with Steel Form for Pier Structure |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR101580111B1 (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106638167A (en) * | 2017-03-02 | 2017-05-10 | 陈永生 | High speed rail suspension bridge type cast-in-situ concrete roadbed hydraulic bearing support die replacing ground die |
CN108035200A (en) * | 2018-01-08 | 2018-05-15 | 国储运通轨道交通科技有限公司 | Bridge-type longeron damper rail system |
KR20180132224A (en) * | 2017-06-02 | 2018-12-12 | 코리아스틸폼 주식회사 | A method of constructing a bridge |
CN111206507A (en) * | 2020-02-05 | 2020-05-29 | 石家庄铁道大学 | Riding type supporting structure and simply-supported-then-continuous bridge construction method |
CN113832947A (en) * | 2021-11-05 | 2021-12-24 | 中铁第六勘察设计院集团有限公司 | Device and method for reinforcing multiple-track railway with small space passing under shield tunnel |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH07247682A (en) * | 1994-01-20 | 1995-09-26 | Mitsuo Sasaki | Movable slab form unit |
JP2002146760A (en) * | 2000-11-09 | 2002-05-22 | Taisei Corp | Floating type form supporting and construction method for water-surface building |
KR100583007B1 (en) | 2003-06-23 | 2006-05-25 | 주식회사 신원건설 | Sectional pier wharf |
KR20060103312A (en) * | 2006-09-09 | 2006-09-28 | 안철승 | Apparatus and manufacturing of preflex beam |
KR101095496B1 (en) | 2011-07-05 | 2011-12-19 | 주식회사 유일종합기술단 | Renewal construction method of decrepit open type wharf and gravity type structure of sheet pile a wharf |
KR101213262B1 (en) | 2010-06-15 | 2012-12-18 | 현대건설주식회사 | Pier structure and method for constructing pier structure |
KR101297127B1 (en) | 2011-07-07 | 2013-08-14 | 주식회사 장헌산업 | Landing pier structure construction method |
-
2015
- 2015-04-22 KR KR1020150056282A patent/KR101580111B1/en active IP Right Grant
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH07247682A (en) * | 1994-01-20 | 1995-09-26 | Mitsuo Sasaki | Movable slab form unit |
JP2002146760A (en) * | 2000-11-09 | 2002-05-22 | Taisei Corp | Floating type form supporting and construction method for water-surface building |
KR100583007B1 (en) | 2003-06-23 | 2006-05-25 | 주식회사 신원건설 | Sectional pier wharf |
KR20060103312A (en) * | 2006-09-09 | 2006-09-28 | 안철승 | Apparatus and manufacturing of preflex beam |
KR101213262B1 (en) | 2010-06-15 | 2012-12-18 | 현대건설주식회사 | Pier structure and method for constructing pier structure |
KR101095496B1 (en) | 2011-07-05 | 2011-12-19 | 주식회사 유일종합기술단 | Renewal construction method of decrepit open type wharf and gravity type structure of sheet pile a wharf |
KR101297127B1 (en) | 2011-07-07 | 2013-08-14 | 주식회사 장헌산업 | Landing pier structure construction method |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106638167A (en) * | 2017-03-02 | 2017-05-10 | 陈永生 | High speed rail suspension bridge type cast-in-situ concrete roadbed hydraulic bearing support die replacing ground die |
KR20180132224A (en) * | 2017-06-02 | 2018-12-12 | 코리아스틸폼 주식회사 | A method of constructing a bridge |
KR102003204B1 (en) * | 2017-06-02 | 2019-07-24 | 코리아스틸폼(주) | A method of constructing a bridge |
CN108035200A (en) * | 2018-01-08 | 2018-05-15 | 国储运通轨道交通科技有限公司 | Bridge-type longeron damper rail system |
CN111206507A (en) * | 2020-02-05 | 2020-05-29 | 石家庄铁道大学 | Riding type supporting structure and simply-supported-then-continuous bridge construction method |
CN113832947A (en) * | 2021-11-05 | 2021-12-24 | 中铁第六勘察设计院集团有限公司 | Device and method for reinforcing multiple-track railway with small space passing under shield tunnel |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101580111B1 (en) | A Continuous Construction-Method with Steel Form for Pier Structure | |
JP7568805B2 (en) | Method for moving heavy objects using a heavy object moving device and a heavy object moving device | |
KR101287455B1 (en) | System and method for launching upper structure of bridege | |
JP4403051B2 (en) | Corrugated steel web bridge construction method | |
CN103161126A (en) | Road bridge variable section hollow high pier slip-form construction method | |
CN111794119B (en) | Temporary supporting system and hoisting method for basket type steel box tie bar arch | |
CN112458918A (en) | High-pier hydraulic jacking integral steel frame platform formwork turnover construction system and construction method | |
US11098490B2 (en) | Self-lifting concrete form with platform adapted to accommodate horizontal reinforcing steel | |
CN212176540U (en) | Hydraulic climbing formwork system formwork | |
CN109629439B (en) | Construction method of single-tower cable-stayed bridge | |
KR101474554B1 (en) | harbor structures construction equipment and it's construction method | |
CN104532754B (en) | A kind of prestressed concrete box girder end-blocking template construction method | |
CN110468743B (en) | Movable hanging bracket for transformation of old bridge pier cap and construction method | |
CN103074871A (en) | Arc-shaped slope concrete sliding and lifting template | |
CN111236089A (en) | Uneven jacking system and uneven jacking construction method for existing bridge superstructure | |
CN212611890U (en) | Steel-concrete combined arch bridge crossing karst cave in tunnel | |
CN211872669U (en) | Uneven jacking system of current bridge superstructure | |
KR100478701B1 (en) | Pulling up, repair and reinforcement method for the upper structure of a bridge | |
CN111851252A (en) | Steel-concrete combined arch bridge crossing karst cave in tunnel and construction method thereof | |
CN112211112A (en) | Steel box girder installation method adopting double-guide-girder erection machine on existing bridge | |
CN110184957B (en) | Construction method of shed tunnel and steel corrugated plate combined type wind and snow prevention system | |
CN111395176A (en) | Construction method for lowering and dismantling movable formwork based on convenience | |
KR20130042721A (en) | Concrete filling apparatus using temporary bridge | |
CN107090772B (en) | Construction method of side span cast-in-place beam bracket of extra-large cable-stayed bridge | |
CN113073556B (en) | Construction method of movable formwork of downlink beam formwork combination |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GRNT | Written decision to grant |