KR101385971B1 - A construction method for tunnelling - Google Patents

A construction method for tunnelling Download PDF

Info

Publication number
KR101385971B1
KR101385971B1 KR1020130104343A KR20130104343A KR101385971B1 KR 101385971 B1 KR101385971 B1 KR 101385971B1 KR 1020130104343 A KR1020130104343 A KR 1020130104343A KR 20130104343 A KR20130104343 A KR 20130104343A KR 101385971 B1 KR101385971 B1 KR 101385971B1
Authority
KR
South Korea
Prior art keywords
tunnel
shotcrete
excavation
pillar
trailing
Prior art date
Application number
KR1020130104343A
Other languages
Korean (ko)
Inventor
함정아
Original Assignee
함정아
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 함정아 filed Critical 함정아
Priority to KR1020130104343A priority Critical patent/KR101385971B1/en
Application granted granted Critical
Publication of KR101385971B1 publication Critical patent/KR101385971B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/383Waterproofing; Heat insulating; Soundproofing; Electric insulating by applying waterproof flexible sheets; Means for fixing the sheets to the tunnel or cavity wall
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/006Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by making use of blasting methods
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/01Methods or apparatus for enlarging or restoring the cross-section of tunnels, e.g. by restoring the floor to its original level

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The present invention relates to a method of constructing a tunnel, which includes the steps of: (a) burying a plurality of pillar reinforcements in a longitudinal direction of a tunnel by a preset length from the ground of a tunnel starting point at a pillar part to be formed between prior and posterior tunnels while being spaced apart from each other; (b) excavating the prior tunnel; (c) casting shotcrete on an excavation surface of the prior tunnel; (d) mounting a reinforcement on the excavation surface of the prior tunnel at the pillar part, casting shotcrete, and mounting a steel rib on the excavation surface of the prior tunnel; (e) forming a perforation at the pillar part between the pillar reinforcements horizontally toward the posterior tunnel to be excavated from the excavation surface of the prior tunnel; (f) inserting and settling the reinforcement into the perforation; (g) excavating the posterior tunnel; (h) casting the shotcrete on an excavation surface of the posterior tunnel; (i) installing the reinforcement on the excavation surface of the pillar part of the posterior tunnel, casting shotcrete, and mounting the steel rib on the posterior tunnel; (j) mounting bearing plates on an entrance and an exit of the reinforcement exposed from the excavation surfaces of the prior and posterior tunnels; and (k) Inserting a tension member into the reinforcement member and fixing the tension member by pulling the tension member. According to the present invention, since the distance between the prior and posterior tunnels can be reduced to 1.5 times or less of a tunnel excavation width, the area of a land used for tunnel construction can be reduced. Accordingly, the cost required for the land purchase is reduced.

Description

터널 시공공법{A construction method for tunnelling}A construction method for tunnelling

본 발명은 터널 시공공법에 관한 것이다.
The present invention relates to a tunnel construction method.

도 1은 선후행 터널이 병렬로 형성되는 종래의 병설터널을 도시한 사시도이다. 종래의 병설터널의 경우, 일반적으로 터널 굴착 폭을 기준으로 1.5배 이상을 선행 터널(1)과 후행 터널(2) 사이의 이격거리(3)로 두고 있다. 이는, 선행 터널(1)과 후행 터널(2) 사이에 형성되는 필러부(4)의 안정성을 확보하기 위한 것이다.1 is a perspective view showing a conventional parallel tunnel in which the preceding and following tunnels are formed in parallel. In the case of the conventional parallel tunnel, the distance between the preceding tunnel 1 and the following tunnel 2 is generally set at 1.5 times or more based on the tunnel excavation width. This is to ensure the stability of the pillar portion 4 formed between the preceding tunnel 1 and the trailing tunnel 2.

그러나, 터널 시공 장소의 지형조건 등에 의해 선행 터널과 후행 터널 사이의 이격 거리 확보가 어려운 경우가 있다. 종래의 경우에는 터널이 형성될 중앙부에 먼저 중앙터널을 시공하여 콘크리트 기둥을 만들고, 그 양 옆으로 본선터널을 굴착하는 2아치 터널굴착방식이 널리 사용되고 있다.However, it is sometimes difficult to secure the separation distance between the preceding tunnel and the following tunnel due to the terrain conditions of the tunnel construction site. In the conventional case, a two-arch tunnel excavation method for constructing a concrete column by first constructing a central tunnel at a central portion where a tunnel is to be formed and then excavating a main tunnel to both sides thereof is widely used.

하지만, 앞서 언급한 2아치 터널굴착방식의 경우, 선후행 터널이 형성될 중앙부에 먼저 중앙터널을 시공하여 콘크리트 기둥을 만들고 그 옆으로 터널을 확장 굴착함에 따라, 공정이 복잡하여 공기가 길고, 공사비가 많이 소요되는 단점이 있다. 또한, 모든 하중이 중앙벽체에 집중됨에 따라 구조적으로 불안정하고, 중앙벽체 상부로 형성되는 골짜기에 누수현상이 자주 발생하는 문제점이 있다.
However, in the case of the two-arch tunnel excavation method mentioned above, the central tunnel where the trailing tunnel is to be formed is first constructed with concrete pillars, and the tunnel is extended and excavated to the side. It takes a lot of disadvantages. In addition, as all loads are concentrated on the central wall, structural instability is caused, and water leakage occurs frequently in the valleys formed above the central wall.

본 발명은 상기한 문제점을 해결하고자, 선행터널과 후행터널 사이에 충분한 이격거리의 형성이 어려운 경우에도 시공가능한 터널 시공공법을 제공하고자 한다.
The present invention is to solve the above problems, to provide a tunnel construction method that can be constructed even if it is difficult to form a sufficient separation distance between the preceding tunnel and the trailing tunnel.

본 발명의 일례에 따른 터널 시공공법은, (a) 선행터널과 후행터널 사이에 형성될 필러부에 터널시작점의 지반으로부터 기설정된 길이까지 복수의 필러부 보강재를 터널 길이 방향으로 이격 설치하는 단계; (b) 선행터널을 굴착하는 단계; (c) 상기 선행터널의 굴착면에 숏크리트를 타설하는 단계; (d) 상기 필러부에 상기 선행터널의 숏크리트면으로부터 굴착 예정인 후행터널을 향하여 수평방향으로 상기 복수의 필러부 보강재 사이로 천공홀을 형성시키는 단계; 및 (e) 상기 천공홀에 보강 부재를 삽입 및 정착시키는 단계를 포함하며, 상기 (b) 단계에서는 상기 선행터널의 다른 굴착면과 비교하여 필러부측 굴착면을 많이 굴착하고, 상기 (c) 단계에서는 상기 선행터널의 다른 굴착면과 비교하여 상기 필러부측 굴착면에 숏크리트를 두껍게 타설하며, 상기 천공홀은 상기 숏크리트가 두껍게 타설된 상기 필러부측 굴착면에 형성되고, 상기 천공홀에 삽입된 보강 부재는 상기 숏크리트면에서 돌출되고, 상기 숏크리트가 두껍게 타설된 부분의 상기 숏크리트면에 지압판이 설치된다. Tunnel construction method according to an embodiment of the present invention, (a) a step of installing a plurality of filler reinforcement in the tunnel length direction from the ground of the tunnel starting point to a predetermined length in the pillar to be formed between the preceding tunnel and the trailing tunnel; (b) digging the preceding tunnel; (c) placing shotcrete on the excavation surface of the preceding tunnel; (d) forming a hole in the pillar portion between the plurality of pillar portion reinforcement in a horizontal direction toward a trailing tunnel to be excavated from the shotcrete surface of the preceding tunnel; And (e) inserting and fixing a reinforcing member in the drilling hole, and in step (b), excavating a lot of the filler part side drilling surface in comparison with other drilling surfaces of the preceding tunnel, and (c) step Compared to other excavation surface of the preceding tunnel, the shotcrete is thickly placed on the pillar-side excavation surface, the drilling hole is formed on the filler-side excavation surface on which the shotcrete is thickly poured, the reinforcing member inserted into the drilling hole Protrudes from the shotcrete surface, the pressure plate is installed on the shotcrete surface of the portion where the shotcrete is thickly placed.

또한, 상기 (a) 단계에서 상기 복수의 필러부 보강재는 상기 터널시작점의 지반 보다 전방으로 돌출되도록 설치되며, 상기 터널시작점의 지반 보다 전방으로 돌출된 필러부 보강재에는 콘크리트 또는 숏크리트가 타설될 수 있다.In addition, in the step (a), the plurality of pillar reinforcement may be installed to protrude forward than the ground of the tunnel starting point, and concrete or shotcrete may be poured on the pillar reinforcement protruding forward than the ground of the tunnel starting point. .

또한, 상기 (c) 단계에서, 상기 선행터널의 필러부측 굴착면에는 상기 숏크리트를 대신하여 콘크리트가 타설될 수 있다.In addition, in the step (c), concrete may be poured in place of the shotcrete on the filler side of the preceding tunnel.

또한, 상기 (c) 단계 이후에는, (c') 상기 선행터널의 필러부측 굴착면을 보강하는 단계를 더 포함할 수 있다.In addition, after the step (c), (c ') may further comprise the step of reinforcing the filler side side drilling surface of the preceding tunnel.

또한, 상기 (c')에서는, 상기 선행터널의 필러부측 굴착면에 이형 철근을 격자형으로 배치하여 이루어진 철근 격자망을 설치하고, 상기 철근 격자망에 숏크리트를 타설할 수 있다.Further, in the above (c '), a reinforcing lattice network formed by arranging deformed reinforcing bars in a lattice shape on the pillar-side excavation surface of the preceding tunnel can be provided, and shotcrete can be poured on the reinforcing lattice network.

또한, 상기 (c) 단계 이후에는, (c'') 상기 선행터널의 굴착면에 강지보재를 설치하는 단계를 더 포함할 수 있다.In addition, after the step (c), (c '') may further comprise the step of installing the rigid material on the excavation surface of the preceding tunnel.

또한, 상기 (c'') 단계는, 상기 강지보재의 잭업을 위해 좌우측 바닥면에 기초가 설치되는 단계를 포함할 수 있다.In addition, the step (c '') may include the step of installing the base on the left and right bottom surface for the jack-up of the steel retainer.

또한, 상기 (c'') 단계는, 상기 선행터널의 바닥면에도 강지보재가 설치되어 상기 굴착면에 설치된 강지보재와 폐합되는 단계를 포함할 수 있다.In addition, the step (c '') may include the step of closing the rigid material is installed on the bottom surface of the preceding tunnel is installed on the excavation surface.

또한, 상기 (c) 단계 이후에는, (c''') 상기 선행터널의 굴착면 중 필러부측 굴착면을 제외한 나머지 굴착면에 록볼트를 시공하는 단계를 더 포함할 수 있다.In addition, after the step (c), (c '' ') may further include the step of constructing a rock bolt on the remaining excavation surface other than the filler side of the excavation surface of the preceding tunnel.

또한, 상기 선행터널의 굴착 시 상하반 분할 굴착하는 경우, 상반의 좌우 측벽의 하단에는 상기 강지보재의 고정을 위한 보강 록볼트가 체결될 수 있다.In addition, when digging the upper and lower half during the excavation of the preceding tunnel, a reinforcement lock bolt for fixing the rigid retaining material can be fastened to the lower end of the left and right side walls of the upper half.

또한, 상기 (e) 단계는, 상기 천공홀과 상기 보강 부재 사이를 압력 그라우팅하는 단계를 포함할 수 있다.In addition, step (e) may include pressure grouting between the drilling hole and the reinforcing member.

또한, 상기 (e) 단계에서, 상기 보강 부재는 굴착 예정인 후행터널의 필러부측 예정 굴착면 보다 돌출되도록 설치될 수 있다.In addition, in the step (e), the reinforcing member may be installed to protrude more than the predetermined excavation surface of the filler portion side of the trailing tunnel to be excavated.

또한, 상기 (e) 단계의 보강 부재는 이중강관 또는 굴곡강관일 수 있다.In addition, the reinforcing member of the step (e) may be a double steel pipe or a bent steel pipe.

또한, 상기 선행터널의 필러부측 굴착면은 일부가 지반으로부터 수직으로 굴착될 수 있다.In addition, a part of the pillar-side drilling surface of the preceding tunnel may be partially excavated vertically from the ground.

또한, 상기 필러부의 수직으로 굴착된 굴착면에는, 마제형 또는 난형으로 숏크리트 또는 콘크리트 타설이 이루어질 수 있다.In addition, a shotcrete or concrete pouring may be made in the drilling surface vertically excavated surface of the pillar portion in a horseshoe or egg shape.

또한, 상기 선행터널의 굴착에서 상기 필러부 근처는 기계굴착 또는 제어발파가 적용될 수 있다.In addition, mechanical drilling or control blasting may be applied near the pillar part in the drilling of the preceding tunnel.

또한, 상기 숏크리트의 최종 타설면에는 방수시트가 설치될 수 있다.In addition, the waterproof sheet may be installed on the final pouring surface of the shotcrete.

또한, 상기 필러부의 상부에는 상향으로 경사지게 보강 록볼트 또는 강관다단 그라우팅이 설치될 수 있다.In addition, a reinforcing rock bolt or steel pipe multi-stage grouting may be installed on the upper portion of the pillar to be inclined upwardly.

또한, 상기 필러부 보강재는, 상기 터널시작점으로부터 기설정된 길이 이후에는 상기 필러부측 굴착면으로부터 중심방향으로 경사지게 설치될 수 있다.
The filler reinforcement may be installed to be inclined toward the center from the pillar-side excavation surface after a predetermined length from the tunnel starting point.

본 발명의 다른 예에 따른 터널 시공공법은, (a) 선행터널을 굴착하는 단계; (b) 상기 선행터널의 굴착면에 숏크리트를 타설하는 단계; (c) 상기 선행터널의 필러부측 굴착면에 보강체 설치 및 숏크리트를 타설하고, 상기 선행터널의 굴착면에 강지보재를 설치하는 단계; (d) 상기 필러부에 상기 선행터널의 숏크리트면으로부터 굴착 예정인 후행터널을 향하여 수평방향으로 천공홀을 형성시키는 단계; (e) 상기 천공홀에 보강 부재를 삽입 및 정착시키는 단계; (f) 후행터널을 굴착하는 단계; (g) 상기 후행터널의 굴착면에 숏크리트를 타설하는 단계; (h) 상기 후행터널의 필러부측 굴착면에 보강체 설치 및 숏크리트를 타설하고, 상기 후행터널에 강지보재를 설치하는 단계; (i) 상기 선행터널 및 후행터널에서 상기 보강 부재가 돌출되어 있는 숏크리트면에 지압판을 설치하는 단계; 및 (j) 상기 보강 부재에 인장재를 삽입하고 상기 인장재를 당겨 고정하는 단계를 포함하고, 상기 (a) 단계 및 상기 (f) 단계에서는 상기 선행터널 및 후행터널의 다른 굴착면과 비교하여 상기 필러부측 굴착면을 많이 굴착하고, 상기 (c) 단계 및 상기 (g) 단계에서는 상기 선행터널 및 후행터널의 다른 굴착면과 비교하여 상기 필러부측 굴착면에 숏크리트를 두껍게 타설하고, 상기 천공홀은 상기 선행터널 및 후행터널에서 숏크리트가 두껍게 타설된 부분에 형성된다.Tunnel construction method according to another embodiment of the present invention, (a) excavating the preceding tunnel; (b) placing shotcrete on an excavation surface of the preceding tunnel; (c) installing a reinforcement and shotcrete on the pillar-side excavation surface of the preceding tunnel, and installing the steel sheet on the excavation surface of the preceding tunnel; (d) forming a hole in the horizontal direction toward the trailing tunnel to be excavated from the shotcrete surface of the preceding tunnel in the pillar portion; (e) inserting and fixing a reinforcing member in the drilling hole; (f) digging a trailing tunnel; (g) placing shotcrete on the excavation surface of the trailing tunnel; (h) installing a reinforcement and shotcrete on the pillar-side excavation surface of the trailing tunnel, and installing the steel retaining material in the trailing tunnel; (i) installing a pressure plate on the shotcrete surface on which the reinforcing member protrudes from the preceding tunnel and the subsequent tunnel; And (j) inserting a tension member into the reinforcement member and pulling the tension member to fix the tension member. In the steps (a) and (f), the filler is compared with other drilling surfaces of the preceding tunnel and the following tunnel. Excavate a lot of side excavation surface, and in the steps (c) and (g), shotcrete is thickly placed on the pillar part excavation surface in comparison with other excavation surfaces of the preceding tunnel and the following tunnel, and the drilling hole is The shotcrete is formed in the thickened part of the preceding tunnel and the following tunnel.

삭제delete

또한, 상기 (e) 단계에서, 상기 보강 부재는 상기 선행터널에서 후행터널 방향으로 삽입하여 정착시키고, 상기 (i) 단계 이전에, 후행터널의 굴착으로 후행터널측 필러부에 노출된 보강 부재의 말단을 절단하고 상기 보강 부재 내부로 인장재를 삽입 및 인장하고, 상기 보강 부재 내부로 그라우팅을 실시할 수 있다.
Further, in the step (e), the reinforcing member is inserted and fixed in the direction of the trailing tunnel in the preceding tunnel, and before the step (i) of the reinforcing member exposed to the trailing tunnel side pillar by excavation of the trailing tunnel. The distal end may be cut, a tension member may be inserted into and pulled into the reinforcing member, and grouting may be performed into the reinforcing member.

또한, 본 발명의 또 다른 예에 따른 터널 시공공법은, (a) 선행터널을 굴착하는 단계; (b) 상기 선행터널의 굴착면에 숏크리트를 타설하는 단계; (c) 상기 선행터널의 필러부에 보강체를 설치하고, 상기 선행터널에 강지보재를 설치하는 단계; (d) 후행터널을 굴착하는 단계; (e) 상기 후행터널의 굴착면에 숏크리트를 타설하는 단계; (f) 상기 후행터널의 필러부에 보강체를 설치하고, 상기 후행터널에 강지보재를 설치하는 단계; (g) 상기 필러부에 상기 후행터널의 숏크리트면으로부터 상기 선행터널의 숏크리트면까지 상기 선행터널을 향하여 수평방향으로 천공홀을 형성시키는 단계; (h) 상기 천공홀에 보강 부재를 삽입 및 정착시키는 단계; (i) 상기 선행터널 및 후행터널에서 보강 부재가 노출되는 숏크리트면에 지압판을 설치하는 단계; 및 (j) 상기 보강 부재에 인장재를 삽입하고 상기 인장재를 당겨 고정하는 단계를 포함하고, 상기 (a) 단계 및 상기 (d) 단계에서는 상기 선행터널 및 후행터널의 다른 굴착면과 비교하여 상기 필러부측 굴착면을 보다 많이 굴착하고, 상기 (b) 단계 및 상기 (e) 단계에서는 상기 선행터널 및 후행터널의 다른 굴착면과 비교하여 상기 필러부측 굴착면에 숏크리트를 두껍게 타설하고, 상기 천공홀은 선행터널 및 후행터널에서 숏크리트가 두껍게 타설된 부분에 형성된다.
In addition, the tunnel construction method according to another embodiment of the present invention, (a) excavating the preceding tunnel; (b) placing shotcrete on an excavation surface of the preceding tunnel; (c) installing a reinforcement in the pillar portion of the preceding tunnel and installing the steel retaining material in the preceding tunnel; (d) drilling a trailing tunnel; (e) placing shotcrete on the excavation surface of the trailing tunnel; (f) installing a reinforcement in the pillar portion of the trailing tunnel and installing the steel retaining material in the trailing tunnel; (g) forming a hole in the pillar in a horizontal direction from the shotcrete surface of the trailing tunnel to the shotcrete surface of the preceding tunnel toward the preceding tunnel; (h) inserting and fixing a reinforcing member in the drilling hole; (i) installing an acupressure plate on the shotcrete surface to which the reinforcing member is exposed in the preceding tunnel and the subsequent tunnel; And (j) inserting a tension member into the reinforcing member and pulling the tension member to fix the tension member. In the steps (a) and (d), the filler is compared with other drilling surfaces of the preceding tunnel and the following tunnel. More excavation of the side excavation surface, and in the steps (b) and (e), the shotcrete is thickly placed on the filler side excavation surface in comparison with the other excavation surfaces of the preceding tunnel and the following tunnel. The shotcrete is formed in the thickened part of the preceding tunnel and the following tunnel.

삭제delete

또한, 본 발명의 또 다른 예에 따른 터널 시공공법은, (a) 선행터널을 굴착하는 단계; (b) 상기 선행터널의 굴착면에 숏크리트를 타설하는 단계; (c) 상기 선행터널의 필러부에 보강체를 설치하고, 상기 선행터널에 강지보재를 설치하는 단계; (d) 후행터널을 굴착하는 단계; (e) 상기 후행터널의 굴착면에 숏크리트를 타설하는 단계; (f) 상기 후행터널의 필러부에 보강체를 설치하고, 상기 후행터널에 강지보재를 설치하는 단계; (g) 상기 필러부에 상기 후행터널의 숏크리트면으로부터 상기 선행터널의 숏크리트면까지 상기 선행터널을 향하여 수평방향으로 천공홀을 형성시키는 단계; (i) 상기 천공홀에 인장형 보강 부재를 삽입시키는 단계; (j) 상기 선행터널 및 후행터널에서 보강 부재가 노출되는 숏크리트면에 지압판을 설치하는 단계; 및 (k) 상기 인장형 보강 부재를 당겨 고정하는 단계를 포함하고, 상기 (a) 단계 및 상기 (d) 단계에서는 상기 선행터널 및 후행터널의 다른 굴착면과 비교하여 상기 필러부측 굴착면을 보다 많이 굴착하고, 상기 (b) 단계 및 상기 (e) 단계에서는 상기 선행터널 및 후행터널의 다른 굴착면과 비교하여 상기 필러부측 굴착면에 숏크리트를 두껍게 타설하고, 상기 천공홀은 선행터널 및 후행터널에서 숏크리트가 두껍게 타설된 부분에 형성된다.
In addition, the tunnel construction method according to another embodiment of the present invention, (a) excavating the preceding tunnel; (b) placing shotcrete on an excavation surface of the preceding tunnel; (c) installing a reinforcement in the pillar portion of the preceding tunnel and installing the steel retaining material in the preceding tunnel; (d) drilling a trailing tunnel; (e) placing shotcrete on the excavation surface of the trailing tunnel; (f) installing a reinforcement in the pillar portion of the trailing tunnel and installing the steel retaining material in the trailing tunnel; (g) forming a hole in the pillar in a horizontal direction from the shotcrete surface of the trailing tunnel to the shotcrete surface of the preceding tunnel toward the preceding tunnel; (i) inserting a tensile reinforcement member into the drilling hole; (j) installing the acupressure plate on the shotcrete surface to which the reinforcing member is exposed in the preceding tunnel and the subsequent tunnel; And (k) pulling and fixing the tensile reinforcing member, and in the step (a) and the step (d), the filler part side excavation surface is compared with other excavation surfaces of the preceding tunnel and the following tunnel. Excavate a lot, and in the step (b) and the step (e), shotcrete is thickly placed on the pillar-side excavation surface in comparison with the other excavation surfaces of the preceding tunnel and the following tunnel, and the perforated hole is the preceding tunnel and the trailing tunnel. In shotcrete is formed in the thickly cast part.

삭제delete

또한, 본 발명의 또 다른 예에 따른 터널 시공공법은, (a) 선행터널을 굴착하는 단계; (b) 상기 선행터널의 굴착면에 숏크리트를 타설하는 단계; (c) 후행터널을 굴착하는 단계; (d) 상기 후행터널의 굴착면에 숏크리트를 타설하는 단계; (e) 상기 선행터널과 후행터널 사이의 필러부에 상기 후행터널의 숏크리트면으로부터 상기 선행터널의 숏크리트면까지 상기 선행터널을 향하여 수평방향으로 천공홀을 형성시키는 단계; (f) 상기 천공홀에 인장형 보강 부재를 삽입시키는 단계; (g) 상기 선행터널 및 후행터널에서 인장형 보강 부재가 노출되는 숏크리트면에 지압판을 설치하는 단계; 및 (h) 상기 인장형 보강 부재를 당겨 고정하는 단계를 포함하고, 상기 (a) 단계 및 상기 (c) 단계에서는 상기 선행터널 및 후행터널의 다른 굴착면과 비교하여 필러부측 굴착면을 보다 많이 굴착하고, 상기 (b) 단계 및 상기 (d) 단계에서는 상기 선행터널 및 후행터널의 다른 굴착면과 비교하여 상기 필러부측 굴착면에 숏크리트를 두껍게 타설하고, 상기 천공홀은 선행터널 및 후행터널에서 숏크리트가 두껍게 타설된 부분에 형성된다.
In addition, the tunnel construction method according to another embodiment of the present invention, (a) excavating the preceding tunnel; (b) placing shotcrete on an excavation surface of the preceding tunnel; (c) digging the trailing tunnel; (d) placing shotcrete on the excavation surface of the trailing tunnel; (e) forming a hole in the horizontal direction toward the preceding tunnel from the shotcrete surface of the trailing tunnel to the shotcrete surface of the preceding tunnel in the pillar portion between the preceding tunnel and the trailing tunnel; (f) inserting a tensile reinforcement member into the drilling hole; (g) installing acupressure plate on the shotcrete surface to which the tension type reinforcing member is exposed in the preceding tunnel and the following tunnel; And (h) pulling and fixing the tensile reinforcing member, and in the step (a) and the step (c), the filler part side excavation surface is more than the other excavation surfaces of the preceding tunnel and the following tunnel. In the step (b) and the step (d), the shotcrete is thickly placed on the pillar-side excavation surface in comparison with the other excavation surfaces of the preceding tunnel and the following tunnel, and the drilling hole is formed in the preceding tunnel and the trailing tunnel. Shotcrete is formed in the thickly casted part.

삭제delete

본 발명을 통해, 선행터널과 후행터널 사이의 이격거리를 터널 굴착 폭을 기준으로 1.5배 이하로 줄일 수 있으므로 터널 건설에 사용되는 토지의 면적이 감소하는 효과가 있다. 이에 따라, 토지 매입에 소요되는 비용이 감소된다.Through the present invention, since the separation distance between the preceding tunnel and the trailing tunnel can be reduced to 1.5 times or less based on the tunnel excavation width, the area of the land used for the tunnel construction is reduced. Accordingly, the cost of land purchase is reduced.

또한, 공간의 제약에 의해 선행터널과 후행터널 사이의 이격거리를 터널 굴착 폭을 기준으로 1.5배로 할 수 없는 경우에도 시공이 가능하다는 장점이 있다.In addition, there is an advantage that the construction is possible even when the separation distance between the preceding tunnel and the trailing tunnel cannot be 1.5 times based on the tunnel excavation width due to space limitation.

또한, 2아치 터널굴착방식과 비교하여, 공기 단축, 공사비 감소, 및 구조적 안정성 향상 등의 장점을 갖는다.
In addition, compared with the two-arch tunnel excavation method, it has advantages such as shortening the air, reducing construction costs, and improving structural stability.

도 1은 종래의 터널 시공공법을 도시하는 사시도이다.
도 2 내지 도 10은 본 발명의 일례에 따른 터널 시공공법을 시공순서에 따라 도시한 도면이다.
1 is a perspective view showing a conventional tunnel construction method.
2 to 10 is a view showing a tunnel construction method according to an embodiment of the present invention in the construction order.

이하, 본 발명의 일부 실시예들을 예시적인 도면을 통해 상세하게 설명한다. 각 도면의 구성요소들에 참조부호를 부가함에 있어서, 동일한 구성요소들에 대해서는 비록 다른 도면상에 표시되더라도 가능한 한 동일한 부호를 가지도록 하고 있음에 유의해야 한다. 또한, 본 발명의 실시예를 설명함에 있어, 관련된 공지 구성 또는 기능에 대한 구체적인 설명이 본 발명의 실시예에 대한 이해를 방해한다고 판단되는 경우에는 그 상세한 설명은 생략한다.Hereinafter, some embodiments of the present invention will be described in detail with reference to exemplary drawings. It should be noted that, in adding reference numerals to the constituent elements of the drawings, the same constituent elements are denoted by the same reference symbols as possible even if they are shown in different drawings. In the following description of the embodiments of the present invention, a detailed description of known functions and configurations incorporated herein will be omitted when it may make the difference that the embodiments of the present invention are not conclusive.

또한, 본 발명의 실시예의 구성 요소를 설명하는 데 있어서, 제 1, 제 2, A, B, (a), (b) 등의 용어를 사용할 수 있다. 이러한 용어는 그 구성 요소를 다른 구성 요소와 구별하기 위한 것일 뿐, 그 용어에 의해 해당 구성 요소의 본질이나 차례 또는 순서 등이 한정되지 않는다. 어떤 구성 요소가 다른 구성요소에 "연결", "결합" 또는 "접속"된다고 기재된 경우, 그 구성 요소는 그 다른 구성요소에 직접적으로 연결되거나 접속될 수 있지만, 각 구성 요소 사이에 또 다른 구성 요소가 "연결", "결합" 또는 "접속"될 수도 있다고 이해되어야 할 것이다.
In describing the components of the embodiment of the present invention, terms such as first, second, A, B, (a), and (b) may be used. These terms are intended to distinguish the constituent elements from other constituent elements, and the terms do not limit the nature, order or order of the constituent elements. When a component is described as being "connected", "coupled", or "connected" to another component, the component may be directly connected or connected to the other component, Quot; may be "connected,""coupled," or "connected. &Quot;

이하에서는 본 발명의 일례에 따른 터널 시공공법에 대하여 도면을 참조하여 상세히 설명한다.Hereinafter, a tunnel construction method according to an example of the present invention will be described in detail with reference to the accompanying drawings.

도 2는 굴착 예정인 선행터널과 후행터널 사이에 형성될 필러부에 필러부 보강재가 설치된 모습을 도시한다.FIG. 2 illustrates a state in which a filler portion reinforcing material is installed in a pillar portion to be formed between a preceding tunnel and a trailing tunnel to be excavated.

도 2의 (a)를 참조하면, 선행터널(100)과 후행터널(200)의 굴착에 앞서 선행터널(100)과 후행터널(200) 사이에 형성되는 필러부(300)에 보강을 위한 복수의 필러부 보강재(310)가 터널 길이 방향으로 이격 설치된다. 복수의 필러부 보강재(310)는, 일례로서 행과 열을 맞추어 이격 설치될 수 있으며 후술할 것이나 복수의 필러부 보강재(310) 사이로는 천공홀(320)이 형성될 수 있다. 따라서, 복수의 필러부 보강재(310)의 행과 열 간의 이격거리는 이후에 형성될 천공홀(320)의 크기에 의해 결정될 수 있다.Referring to Figure 2 (a), prior to the excavation of the preceding tunnel 100 and the trailing tunnel 200, a plurality of reinforcement for the filler portion 300 formed between the preceding tunnel 100 and the trailing tunnel 200. Filler portion reinforcement 310 is installed spaced apart in the tunnel longitudinal direction. The plurality of pillar reinforcing members 310 may be spaced apart from each other in rows and columns as an example, and will be described later, but a plurality of pillar part reinforcing members 310 may be formed with a perforation hole 320. Thus, the separation distance between the rows and columns of the plurality of pillar reinforcement 310 may be determined by the size of the punched hole 320 to be formed later.

도 2의 (b)를 참조하면, 필러부 보강재(310)는, 터널시작점(10)의 지반으로부터 기설정된 길이(약 10 내지 50m)까지 터널 길이 방향으로 설치된다. 다만, 필러부 보강재(310)는, 일례로서 터널시작점(10)의 지반 보다 적어도 일부가 전방으로 돌출되도록 설치될 수 있다. 이 경우, 터널시작점(10)의 지반 보다 전방으로 돌출된 필러부 보강재(310)에는 콘크리트 또는 숏크리트(311)를 타설하여 강도를 보강하고 미관을 향상시킬 수 있다.Referring to FIG. 2B, the filler part reinforcing material 310 is installed in the tunnel length direction from the ground of the tunnel starting point 10 to a predetermined length (about 10 to 50 m). However, the filler reinforcing member 310 may be installed so that at least a portion of the pillar reinforcing member 310 protrudes forward from the ground of the tunnel starting point 10. In this case, concrete or shotcrete 311 may be poured into the filler part reinforcing material 310 protruding forward from the ground of the tunnel starting point 10 to reinforce strength and improve aesthetics.

도 3은 선행터널이 굴착된 모습을 도시하는 정면도이다.3 is a front view showing a state in which the preceding tunnel is excavated.

도 3을 참조하면, 필러부(300)에 필러부 보강재(310)가 설치된 이후, 선행터널(100)이 굴착된다. 선행터널(100)은, 터널시작점(10)의 지반으로부터 기설정된 길이까지 터널 길이 방향으로 굴착된다. 선행터널(100)은, 굴착 예정선에 따라 굴착될 수 있다.Referring to FIG. 3, after the filler part reinforcing material 310 is installed in the filler part 300, the preceding tunnel 100 is excavated. The preceding tunnel 100 is excavated in the tunnel length direction from the ground of the tunnel starting point 10 to a predetermined length. The preceding tunnel 100 may be excavated according to the excavation schedule.

또한, 선행터널(100)은, 일례로서 상반과 하반을 구분하여 상반을 먼저 굴착하고 하반을 나중에 굴착할 수 있으며, 필러부(300)와 접하지 않는 측과 접하는 측으로 구분하여 필러부(300)와 접하지 않는 측은 발파를 통해 굴착하고 필러부(300)와 접하는 측은 진동 제어 발파 또는 기계 굴착 등을 통해 굴착할 수 있다. 다만, 선행터널(100)의 굴착 방식은 위의 실시예에 제한되지 않는다.In addition, the preceding tunnel 100, for example, by dividing the upper half and the lower half to excavate the upper half first, and later excavation of the lower half, divided into the side in contact with the side that does not contact the filler portion 300 to the filler portion 300 The side not in contact with the excavation may be excavated through blasting, and the side in contact with the filler 300 may be excavated through vibration control blasting or mechanical excavation. However, the excavation method of the preceding tunnel 100 is not limited to the above embodiment.

또한, 선행터널(100)의 굴착은, 선행터널(100)의 필러부측 굴착면(102)과 선행터널(100)의 다른 굴착면(101)으로 구분하여 진행될 수 있다. 선행터널(100)의 필러부측 굴착면(102)은 선행터널(100)의 다른 굴착면(101)과 비교하여 많이 굴착될 수 있다. 일례로서, 필러부측 굴착면(102)이 다른 굴착면(101) 보다 5 내지 50cm 많이 굴착될 수 있다. 이와 같이 선행터널(100)의 필러부측 굴착면(102)이 상대적으로 많이 굴착되는 것은 후술할 것이나 숏크리트 또는 콘크리트의 타설 두께를 두껍게 하기 위한 것이다. 만약, 필러부측 굴착면(102)이 다른 굴착면(101) 보다 5 내지 50cm 많이 굴착된 경우라면, 필러부측 굴착면(102)에 다른 굴착면(101) 보다 5 내지 50cm 두껍게 숏크리트 또는 콘크리트가 타설될 수 있다.In addition, the excavation of the preceding tunnel 100 may be performed by dividing into the excavation surface 102 of the pillar part side of the preceding tunnel 100 and the other excavating surface 101 of the preceding tunnel 100. The filler part side drilling surface 102 of the preceding tunnel 100 may be excavated more than the other drilling surface 101 of the preceding tunnel 100. As an example, the filler portion side excavation surface 102 may be excavated 5 to 50 cm more than the other excavation surface 101. As described above, the pillar portion side excavation surface 102 of the preceding tunnel 100 is excavated relatively much, but to increase the thickness of the shotcrete or concrete. If the filler part side excavation surface 102 is excavated 5 to 50 cm more than the other excavation surface 101, the shotcrete or concrete is poured 5 to 50 cm thicker than the other excavation surface 101 on the filler part side excavation surface 102. Can be.

또한, 선행터널(100)의 필러부측 굴착면(102)은, 도 3에 도시된 바와 같이 적어도 일부가 바닥면(20)으로부터 수직으로 굴착될 수 있다. 이 경우, 후술할 것이나 보강 부재(330)에 삽입되는 인장재에 의해 지압판(340)이 필러부(300)에 전달하는 압력이 필러부(300) 전반에 균등하게 전달될 수 있는 장점이 있다. 다시 말해, 필러부(300)가 곡선인 경우 보다 직선으로 구비되는 경우 균등한 압력전달에 유리하다는 것이다.In addition, the pillar-side drilling surface 102 of the preceding tunnel 100, at least a portion may be excavated vertically from the bottom surface 20, as shown in FIG. In this case, it will be described later, but there is an advantage that the pressure transmitted from the pressure plate 340 to the filler part 300 by the tension member inserted into the reinforcing member 330 can be evenly transmitted to the entire filler part 300. In other words, when the filler part 300 is provided in a straight line rather than curved, it is advantageous for even pressure transmission.

도 4는 선행터널의 굴착면에 숏크리트를 타설한 모습을 도시하는 정면도이다.4 is a front view illustrating a state in which shotcrete is poured on an excavation surface of the preceding tunnel.

도 4를 참조하면, 선행터널(100)의 굴착면(101,102)에는 숏크리트(110)가 타설된다. 이때, 타설되는 숏크리트(110)는 강섬유 보강 숏크리트, 섬유 보강 숏크리트, 고강도 숏크리트 및 일반 숏크리트 중 어느 하나 일 수 있다.Referring to FIG. 4, shotcrete 110 is poured into the excavation surfaces 101 and 102 of the preceding tunnel 100. In this case, the shotcrete 110 to be poured may be any one of steel fiber reinforced shotcrete, fiber reinforced shotcrete, high strength shotcrete and general shotcrete.

또한, 숏크리트(110)의 타설면에는 방수시트가 설치될 수 있다. 이 경우, 터널의 완공 후 터널 내부로 물이 들어오는 현상을 방지할 수 있다.In addition, a waterproof sheet may be installed on the pouring surface of the shotcrete 110. In this case, it is possible to prevent water from entering the tunnel after completion of the tunnel.

일례로서, 선행터널(100)의 굴착면(101,102)은 필러부측 굴착면(102)과 다른 굴착면(101)으로 구분되어 숏크리트(110)의 두께가 다르게 타설된다. 선행터널(100)의 필러부측 굴착면(102)에는, 도 4에 도시된 바와 같이 선행터널(100)의 다른 굴착면(101)에 타설된 숏크리트(111)의 두께 보다 더 두꺼운 폭의 숏크리트(112)가 타설될 수 있다. 이와 같이, 더 두꺼운 폭의 숏크리트(112)가 타설된 필러부측 굴착면(102)은 다른 굴착면(101)가 비교하여 상대적으로 강도가 보강되는 효과를 갖게 된다.As an example, the excavation surfaces 101 and 102 of the preceding tunnel 100 are divided into the excavation surface 101 and the other excavation surface 101 of the filler portion side, and the shotcrete 110 is poured in a different thickness. On the pillar-side drilling surface 102 of the preceding tunnel 100, as shown in FIG. 4, a shotcrete having a width thicker than the thickness of the shotcrete 111 cast on the other drilling surface 101 of the preceding tunnel 100 ( 112 may be poured. In this way, the filler portion side excavation surface 102 in which the thicker shotcrete 112 is poured has the effect that the strength is relatively increased compared to other excavation surfaces 101.

또한, 앞서 언급한 바와 같이 선행터널(100)의 필러부측 굴착면(102)의 적어도 일부가 바닥면(20)으로부터 수직으로 굴착된 경우라면, 상기 수직으로 굴착된 굴착면(102)에 마제형 또는 난형으로 숏크리트 또는 콘크리트 라이닝 타설이 이루어질 수 있다. 이를 통해, 선행터널(100)의 전체적인 단면의 형상이 좌우대칭을 이루는 마제형 또는 난형이 될 수 있는 것이다.In addition, as described above, if at least a part of the pillar-side excavation surface 102 of the preceding tunnel 100 is excavated vertically from the bottom surface 20, a horseshoe or Occasionally shotcrete or concrete lining can be made. Through this, the shape of the overall cross section of the preceding tunnel 100 may be a horseshoe type or ovoid forming a left-right symmetry.

또한, 굴착면(101,102)에 타설되는 숏크리트(110)는 다수회에 걸쳐 타설될 수 있다. 이 경우, 편의상 1차 숏크리트, 2차 숏크리트와 같이 호칭할 수 있을 것이다.In addition, the shotcrete 110 that is poured on the excavation surfaces 101 and 102 may be cast a plurality of times. In this case, it may be referred to as primary shotcrete or secondary shotcrete for convenience.

또한, 선행터널(100)의 필러부측 굴착면(102)에는 숏크리트를 대신하여 콘크리트가 타설될 수 있다. 이 경우, 상대적인 강도 보강의 효과를 갖게 된다.In addition, concrete may be poured in place of the shotcrete on the filler part side drilling surface 102 of the preceding tunnel 100. In this case, it has the effect of relative strength reinforcement.

도면에 도시된 것은 아니지만, 굴착면(101,102)에 숏크리트(110)가 타설된 이후에는 필러부측 굴착면(102)을 보강하는 공정이 추가될 수 있다. 필러부측 굴착면(102)의 보강은, 필러부측 굴착면(102)에 이형 철근을 격자형으로 배치하여 이루어진 철근 격자망을 설치하고, 상기 철근 격자망에 숏크리트를 타설하여 이루어질 수 있다. Although not shown in the drawings, after the shotcrete 110 is poured on the excavation surfaces 101 and 102, a process of reinforcing the filler part side excavation surface 102 may be added. The reinforcement of the pillar-side excavation surface 102 may be performed by installing a reinforcing grid mesh formed by arranging the deformed rebars in a lattice shape on the pillar-side excavation surface 102, and pouring shotcrete into the reinforcement grid.

또한, 굴착면(101,102)에 숏크리트(110)가 타설된 이후에 상기 굴착면(101,102)에 강지보재를 설치하는 공정이 추가될 수 있다. 또한, 터널 주변 지반상태에 따라 강지보재의 잭업공정이 추가될 수 있다. 이 경우, 선행터널(100)의 바닥면(20) 좌우측에는 강지보재의 잭업을 위한 기초가 설치될 수 있다. 상기한 강지보재는 굴착면(101,102) 뿐만 아니라 선행터널(100)의 바닥면(20)에도 설치되어 굴착면(101,102)에 설치된 강지보재와 폐합될 수 있다.In addition, after the shotcrete 110 is poured on the excavating surfaces 101 and 102, a process of installing the rigid holding material on the excavating surfaces 101 and 102 may be added. In addition, depending on the ground conditions around the tunnel may be added jackup process of the reserve. In this case, on the left and right sides of the bottom surface 20 of the preceding tunnel 100, a base for jack-up of the retaining material may be installed. The stiffeners may be installed on the bottom surface 20 of the preceding tunnel 100 as well as the excavated surfaces 101 and 102 and may be closed with the stiffeners installed on the excavated surfaces 101 and 102.

만약, 선행터널(100)의 굴착을 상하반으로 분할하여 상반 먼저 굴착하는 경우라면, 상반의 좌우 측벽의 하단에는 강지보재의 고정을 위한 보강 록볼트가 체결될 수 있다. 이후, 하반의 굴착이 진행되면 상반의 굴착면에 보강 록볼트에 의해 고정되어 있는 강지보재와 하반에 설치되는 강지보재를 폐합하는 과정을 통해 강지보재의 설치를 완료할 수 있다.If the excavation of the preceding tunnel 100 is divided into upper and lower halves and the first half is excavated first, reinforcement rock bolts for fastening the rigid retainer may be fastened to the lower left and right side walls of the upper half. Subsequently, when the drilling of the lower half proceeds, the installation of the steel reserve may be completed through a process of closing the steel retainer fixed on the excavation surface of the upper half by the reinforcing rock bolt and the retained steel retainer installed in the lower half.

또한, 굴착면(101,102)에 숏크리트(110)가 타설된 이후에 상기 굴착면(101,102) 중 필러부측 굴착면(102)을 제외한 나머지 굴착면(101)에 록볼트를 설치하는 공정이 추가될 수 있다.In addition, after the shotcrete 110 is poured on the excavating surfaces 101 and 102, a process of installing rock bolts on the other excavating surfaces 101 other than the filler part side excavating surface 102 among the excavating surfaces 101 and 102 may be added. have.

도 5는 필러부에 이격 설치된 필러부 보강재 사이로 천공홀을 형성한 모습을 도시하는 정면도이다.FIG. 5 is a front view illustrating a hole formed between the filler part reinforcing members spaced apart from the filler part.

도 5를 참조하면, 천공홀(320)은, 필러부(300)에 선행터널(100)의 필러부측 굴착면(102)으로부터 굴착 예정인 후행터널(200)을 향하여 수평방향으로 복수의 필러부 보강재(310) 사이로 형성된다. 천공홀(320)의 직경은, 후술할 것이나 천공홀(320)에 삽입되어 정착될 보강 부재(330)의 직경을 고려하여 결정될 수 있다.Referring to FIG. 5, the drill hole 320 includes a plurality of pillar part reinforcement in a horizontal direction toward the trailing tunnel 200 which is to be excavated from the filler part side drilling surface 102 of the preceding tunnel 100 in the pillar part 300. It is formed between (310). The diameter of the drilling hole 320 will be described later, but may be determined in consideration of the diameter of the reinforcing member 330 to be inserted into and fixed in the drilling hole 320.

또한, 천공홀(320)은, 후행터널(200)의 예정 굴착면 보다 돌출되도록 굴착될 수 있다. 이는, 이후 천공홀(320)에 삽입될 보강 부재(330)가 후행터널(200)의 굴착 후 후행터널(200)의 필러부측 굴착면(202) 보다 돌출되도록 설치되기 위함이다.In addition, the drilling hole 320 may be excavated to protrude more than a predetermined excavation surface of the trailing tunnel 200. This is to be installed so that the reinforcing member 330 to be inserted into the drilling hole 320 protrudes beyond the pillar portion side drilling surface 202 of the trailing tunnel 200 after the trailing tunnel 200 is excavated.

도 6은 천공홀에 보강 부재를 삽입 및 정착시킨 모습을 도시하는 정면도이다.FIG. 6 is a front view illustrating a state in which a reinforcing member is inserted and fixed in a drilling hole. FIG.

도 6을 참조하면, 천공홀(320)에는 보강 부재(330)가 삽입 및 정착된다. 보다 상세히, 천공홀(320)에는 상기 천공홀(320)의 직경 보다 작은 직경을 갖는 보강 부재(330)가 삽입 및 정착될 수 있다. 이 때, 천공홀(320)과 보강 부재(330) 사이에는 압력 그라우팅이 실시될 수 있다. 이 경우, 천공홀(320)과 보강 부재(330) 사이 뿐만 아니라 천공홀(320)의 둘레를 형성하는 지반의 공극 사이에도 그라우팅 액이 주입되므로 필러부(300) 지반의 강도를 보강하는 효과를 얻을 수 있다.Referring to FIG. 6, the reinforcing member 330 is inserted and fixed in the drilling hole 320. In more detail, the reinforcing member 330 having a diameter smaller than the diameter of the drilling hole 320 may be inserted and fixed in the drilling hole 320. At this time, pressure grouting may be performed between the drilling hole 320 and the reinforcing member 330. In this case, since the grouting liquid is injected not only between the punching hole 320 and the reinforcing member 330 but also between the pores of the ground forming the periphery of the punching hole 320, the filler 300 has the effect of reinforcing the strength of the ground. You can get it.

또한, 천공홀(320)에 삽입되는 보강 부재(330)는, 이중강관 또는 굴곡강관이 사용될 수 있다.In addition, the reinforcing member 330 inserted into the drilling hole 320, double steel pipe or bent steel pipe may be used.

또한, 필러부(300)의 상부에는, 도 6에 도시된 바와 같이 보강 록볼트(350) 또는 강관 다단 그라우팅이 상향으로 경사지게 설치될 수 있다. 이 경우, 필러부(300)의 강도 보강 효과를 기대할 수 있다.In addition, the upper portion of the filler portion 300, as shown in Figure 6, the reinforcement rock bolt 350 or steel pipe multi-stage grouting may be installed to be inclined upward. In this case, the strength reinforcement effect of the pillar part 300 can be expected.

도 7은 후행터널이 굴착된 모습을 도시하는 정면도이다.7 is a front view showing a state in which the trailing tunnel is excavated.

도 7을 참조하면, 후행터널(200)은, 터널시작점(10)의 지반으로부터 기설정된 길이까지 터널 길이 방향으로 굴착된다. 후행터널(200)은, 굴착 예정선에 따라 굴착될 수 있다.Referring to FIG. 7, the trailing tunnel 200 is excavated in the tunnel length direction from the ground of the tunnel starting point 10 to a predetermined length. The trailing tunnel 200 may be excavated according to the excavation schedule.

또한, 후행터널(200)은, 일례로서 상반과 하반을 구분하여 상반을 먼저 굴착하고 하반을 나중에 굴착할 수 있으며, 필러부(300)와 접하지 않는 측과 접하는 측으로 구분하여 필러부(300)와 접하지 않는 측은 발파를 통해 굴착하고 필러부(300)와 접하는 측은 진동 제어 발파 또는 기계 굴착 등을 통해 굴착할 수 있다. 다만, 후행터널(200)의 굴착 방식은 위의 실시예에 제한되지 않는다.In addition, the trailing tunnel 200, as an example, may divide the upper half and the lower half to dig the upper half first, and later excavate the lower half, and may be divided into the side in contact with the side that is not in contact with the pillar part 300, and the pillar part 300. The side not in contact with the excavation may be excavated through blasting, and the side in contact with the filler 300 may be excavated through vibration control blasting or mechanical excavation. However, the excavation method of the trailing tunnel 200 is not limited to the above embodiment.

또한, 후행터널(200)의 굴착은, 후행터널(200)의 필러부측 굴착면(202)과 후행터널(200)의 다른 굴착면(201)으로 구분하여 진행될 수 있다. 후행터널(200)의 필러부측 굴착면(202)은 후행터널(200)의 다른 굴착면(201)과 비교하여 많이 굴착될 수 있다. 이와 같이 후행터널(200)의 필러부측 굴착면(202)이 상대적으로 많이 굴착되는 것은 후술할 것이나 숏크리트 또는 콘크리트의 타설 두께를 두껍게 하기 위한 것이다. In addition, the excavation of the trailing tunnel 200 may be performed by dividing the pillar-side drilling surface 202 of the trailing tunnel 200 and the other drilling surface 201 of the trailing tunnel 200. The filler part side drilling surface 202 of the trailing tunnel 200 may be excavated more than the other drilling surface 201 of the trailing tunnel 200. As described above, the filler portion side excavation surface 202 of the trailing tunnel 200 is relatively excavated to increase the thickness of the shotcrete or concrete.

또한, 후행터널(200)의 필러부측 굴착면(202)은, 적어도 일부가 바닥면(20)으로부터 수직으로 굴착될 수 있다. 이 경우, 후술할 것이나 보강 부재(330)에 삽입되는 인장재에 의해 지압판(340)이 필러부(300)에 전달하는 압력이 필러부(300) 전반에 균등하게 전달될 수 있는 장점이 있다. 즉, 필러부(300)가 곡선인 경우 보다 직선으로 구비되는 경우 균등한 압력전달에 유리함은 앞서 살핀 바와 같다.In addition, at least a portion of the pillar-side digging surface 202 of the trailing tunnel 200 may be excavated vertically from the bottom surface 20. In this case, it will be described later, but there is an advantage that the pressure transmitted from the pressure plate 340 to the filler part 300 by the tension member inserted into the reinforcing member 330 can be evenly transmitted to the entire filler part 300. In other words, when the filler part 300 is provided in a straight line rather than in a curved shape, the advantage of equal pressure transfer is as described above.

이외에도 후행터널(200)의 굴착에 대한 설명은 앞서 설명한 선행터널(200)의 굴착에 대한 설명이 적용될 수 있다.In addition to the description of the excavation of the trailing tunnel 200, the description of the excavation of the preceding tunnel 200 may be applied.

도 8은 후행터널의 굴착면에 숏크리트를 타설한 모습을 도시하는 정면도이다.8 is a front view showing a state in which shotcrete is poured on an excavation surface of a trailing tunnel.

도 8을 참조하면, 후행터널(200)의 굴착면(201,202)에는 숏크리트(210)가 타설된다. 이때, 타설되는 숏크리트(210)는 강섬유 보강 숏크리트, 섬유 보강 숏크리트, 고강도 숏크리트 및 일반 숏크리트 중 어느 하나 일 수 있다.Referring to FIG. 8, shotcrete 210 is poured into the excavation surfaces 201 and 202 of the trailing tunnel 200. In this case, the shotcrete 210 to be poured may be any one of steel fiber reinforced shotcrete, fiber reinforced shotcrete, high strength shotcrete, and general shotcrete.

또한, 숏크리트(210)의 타설면에는 방수시트가 설치될 수 있다. 이 경우, 터널의 완공 후 터널 내부로 물이 들어오는 현상을 방지할 수 있다.In addition, a waterproof sheet may be installed on the pouring surface of the shotcrete 210. In this case, it is possible to prevent water from entering the tunnel after completion of the tunnel.

일례로서, 후행터널(200)의 굴착면(201,202)은 필러부측 굴착면(202)과 다른 굴착면(201)으로 구분되어 숏크리트(210)의 두께가 다르게 타설된다. 후행터널(200)의 필러부측 굴착면(202)에는, 후행터널(200)의 다른 굴착면(201)에 타설된 숏크리트(211)의 두께 보다 더 두꺼운 폭의 숏크리트(212)가 타설될 수 있다. 이와 같이, 더 두꺼운 폭의 숏크리트(212)가 타설된 필러부측 굴착면(202)은 다른 굴착면(201)가 비교하여 상대적으로 강도가 보강되는 효과를 갖게 된다.As an example, the excavation surfaces 201 and 202 of the trailing tunnel 200 are divided into pillar-side excavation surfaces 202 and other excavation surfaces 201, and the shotcrete 210 is poured in a different thickness. On the pillar-side digging surface 202 of the trailing tunnel 200, a shotcrete 212 having a width thicker than the thickness of the shotcrete 211 cast on the other digging surface 201 of the trailing tunnel 200 may be poured. . In this way, the filler portion side excavation surface 202 on which the thicker shotcrete 212 is poured has an effect that the strength is relatively increased compared to other excavation surfaces 201.

또한, 앞서 언급한 바와 같이 후행터널(200)의 필러부측 굴착면(202)의 적어도 일부가 바닥면(20)으로부터 수직으로 굴착된 경우라면, 상기 수직으로 굴착된 굴착면(202)에 마제형 또는 난형으로 숏크리트 또는 콘크리트 라이닝 타설이 이루어질 수 있다. 이를 통해, 후행터널(200)의 전체적인 단면의 형상이 좌우대칭을 이루는 마제형 또는 난형이 될 수 있는 것이다.In addition, as described above, if at least a part of the filler portion-side drilling surface 202 of the trailing tunnel 200 is vertically excavated from the bottom surface 20, a horseshoe or Occasionally shotcrete or concrete lining can be made. Through this, the shape of the overall cross section of the trailing tunnel 200 may be a horseshoe type or ovoid forming a left-right symmetry.

또한, 굴착면(201,202)에 타설되는 숏크리트(210)는 선행터널(100)에서와 마찬가지로 다수회에 걸쳐 타설될 수 있다.In addition, the shotcrete 210 cast on the excavation surfaces 201 and 202 may be cast a plurality of times as in the preceding tunnel 100.

또한, 후행터널(200)의 필러부측 굴착면(202)에는 숏크리트를 대신하여 콘크리트가 타설될 수 있다. 이 경우, 상대적인 강도 보강의 효과를 갖게 된다.In addition, concrete may be poured in place of the shotcrete on the pillar-side digging surface 202 of the trailing tunnel 200. In this case, it has the effect of relative strength reinforcement.

또한, 필러부측 굴착면(202)의 보강 공정과 굴착면(101,102)에 대한 강지보재 설치 공정은 앞서 기재한 선행터널에서의 설명이 적용될 수 있다.In addition, the reinforcing process of the filler part side excavation surface 202 and the process of installing the rigid holding material for the excavation surfaces 101 and 102 may be applied to the description in the preceding tunnel described above.

도 9는 선행터널 및 후행터널의 굴착면으로부터 노출된 보강 부재의 입구단 및 출구단에 지압판이 설치된 모습을 도시하는 정면도이다.9 is a front view showing a state in which the pressure plate is installed at the inlet end and the outlet end of the reinforcing member exposed from the excavation surface of the preceding tunnel and the following tunnel.

도 9를 참조하면, 선행터널(100) 및 후행터널(200)의 굴착면(102,202)으로부터 노출된 보강 부재(330)의 입구단 및 출구단에는 지압판(340)이 설치된다. 이후, 보강 부재(330)에는 인장재(미도시)가 삽입된다. 삽입된 인장재는 당겨진 상태로 고정되어 지압판(340)이 필러부(300)를 가압하는 상태를 유지시킨다. 다만, 보강 부재(330)와 인장재를 대신하여 인장형 보강 부재(미도시)가 사용될 수 있음에 유의하여야 한다.Referring to FIG. 9, the pressure plate 340 is installed at the inlet and outlet ends of the reinforcing members 330 exposed from the excavation surfaces 102 and 202 of the preceding tunnel 100 and the following tunnel 200. Thereafter, a tension member (not shown) is inserted into the reinforcing member 330. The inserted tension member is fixed in a pulled state to keep the pressure plate 340 pressing the pillar part 300. However, it should be noted that a tension type reinforcement member (not shown) may be used in place of the reinforcement member 330 and the tension member.

이와 같은 필러부(300) 보강 공정 이후, 필러부(300)를 제외한 굴착면(101,201)은 숏크리트 타설 또는 콘크리트 라이닝이 실시될 수 있다. 이를 통해, 굴착면(101,201)의 강도 보강 및 외관 향상의 효과를 갖게 된다.After the filler part 300 reinforcement process, the excavation surfaces 101 and 201 except for the filler part 300 may be shotcreted or concrete lining. Through this, it has the effect of reinforcing strength and appearance improvement of the excavating surface (101,201).

도 10은, 터널시작점의 지반에서 설치된 필러부 보강재의 후방에서의 필러부 보강재의 설치 모습을 도시하는 단면도이다.FIG. 10 is a cross-sectional view showing the installation of a filler portion reinforcing member in the rear of the filler portion reinforcing member provided in the ground of the tunnel starting point. FIG.

도 10을 참조하면, 터널시작점(10)으로부터 기설정된 길이까지는 필러부 보강재(300)가 터널 길이 방향으로 터널 진행방향과 나란하게 설치되고, 터널시작점(10)으로부터 기설정된 길이 이후에는 필러부측 굴착면(102,202)으로부터 필러부(300)의 중심방향으로 경사지게 설치될 수 있다. 단, 필러부 보강재(300)가 경사지게 설치되는 경우에도 천공홀(320)의 굴착 예정 부분은 지나지 않도록 복수의 필러부 보강재(300)간 행을 맞추어 설치될 수 있다.Referring to FIG. 10, the filler part reinforcing material 300 is installed in the tunnel length direction in parallel with the tunnel traveling direction from the tunnel start point 10 to the predetermined length, and the pillar part side excavation after the preset length from the tunnel start point 10. The surfaces 102 and 202 may be installed to be inclined toward the center of the pillar part 300. However, even when the filler part reinforcing material 300 is installed to be inclined, the excavation scheduled portion of the drilling hole 320 may be installed so as to match rows between the plurality of filler part reinforcing materials 300.

위의 공정을 통해 완공된 터널은, 선행터널과 후행터널 사이의 이격거리가 터널 굴착 폭을 기준으로 1.5배 이하로 시공된 경우에도 안정한 상태를 유지할 수 있는 장점이 있다.
Tunnel completed through the above process, there is an advantage that can be maintained stable even when the separation distance between the preceding tunnel and the trailing tunnel is less than 1.5 times the tunnel excavation width.

이하에서는 본 발명의 다른 실시예에 따른 터널 시공공법을 설명한다.Hereinafter, a tunnel construction method according to another embodiment of the present invention will be described.

본 발명의 다른 실시예에 따른 터널 시공공법은 앞서 설명한 본 발명의 일례에 따른 터널 시공공법과 천공홀(320) 형성, 및 보강 부재(330)의 삽입 및 정착 시기에서 차이가 있을 뿐이므로, 본 발명의 일례에 따른 시공공법에 대한 설명 중 천공홀(320) 형성, 및 보강 부재(330)의 삽입 및 정착에 대한 설명을 제외하고는 본 실시예에서도 적용될 수 있다.Tunnel construction method according to another embodiment of the present invention because there is only a difference in the tunnel construction method according to an example of the present invention described above and the formation of the drilling hole 320, and the insertion and fixing of the reinforcing member 330, In the description of the construction method according to an example of the invention can be applied in the present embodiment except for the description of the formation of the drilling hole 320, and the insertion and fixing of the reinforcing member 330.

본 발명의 다른 실시예에 따른 터널 시공공법에서는, 후행터널(200)을 굴착하고 숏크리트(210) 타설 이후에 천공홀(320)을 형성한다. 일례로서, 후행터널(200)의 굴착면(202)으로부터 선행터널(100)을 향하여 수평방향으로 복수의 필러부 보강재(310) 사이로 천공홀(320)을 형성한다. 다만, 이와 같은 기재가 선행터널(100)으로부터 후행터널(200) 방향으로 천공홀(320)을 형성하는 것을 배제하는 것은 아니다.In the tunnel construction method according to another embodiment of the present invention, the trailing tunnel 200 is excavated and the drilling hole 320 is formed after the shotcrete 210 is placed. As an example, the drilling hole 320 is formed between the plurality of pillar part reinforcement 310 in the horizontal direction from the excavation surface 202 of the trailing tunnel 200 toward the preceding tunnel 100. However, this description does not exclude the formation of the drilling hole 320 in the direction of the trailing tunnel 200 from the preceding tunnel 100.

필러부(300)에 천공홀(320)이 형성되면 필러부(300) 지반상태에 따라 선택적으로 보강 부재(330)의 삽입 및 정착, 또는 인장재가 설치된다. 보강 부재(330)의 삽입과 정착 및 인장재에 대하여는 본 발명의 일례에 따른 터널 시공공법에 대한 설명이 적용될 수 있다.
When the punching hole 320 is formed in the filler part 300, the insertion and fixing of the reinforcing member 330 is selectively installed according to the ground state of the filler part 300, or a tension member is installed. Regarding the insertion, fixing, and tension member of the reinforcing member 330, the description of the tunnel construction method according to an example of the present disclosure may be applied.

이상에서, 본 발명의 실시예를 구성하는 모든 구성 요소들이 하나로 결합하거나 결합하여 동작하는 것으로 설명되었다고 해서, 본 발명이 반드시 이러한 실시예에 한정되는 것은 아니다. 즉, 본 발명의 목적 범위 안에서라면, 그 모든 구성 요소들이 하나 이상으로 선택적으로 결합하여 동작할 수도 있다. 또한, 이상에서 기재된 "포함하다", "구성하다" 또는 "가지다" 등의 용어는, 특별히 반대되는 기재가 없는 한, 해당 구성 요소가 내재할 수 있음을 의미하는 것이므로, 다른 구성 요소를 제외하는 것이 아니라 다른 구성 요소를 더 포함할 수 있는 것으로 해석되어야 한다. 기술적이거나 과학적인 용어를 포함한 모든 용어들은, 다르게 정의되지 않는 한, 본 발명이 속하는 기술 분야에서 통상의 지식을 가진 자에 의해 일반적으로 이해되는 것과 동일한 의미가 있다. 사전에 정의된 용어와 같이 일반적으로 사용되는 용어들은 관련 기술의 문맥상의 의미와 일치하는 것으로 해석되어야 하며, 본 발명에서 명백하게 정의하지 않는 한, 이상적이거나 과도하게 형식적인 의미로 해석되지 않는다.While the present invention has been described in connection with what is presently considered to be the most practical and preferred embodiment, it is to be understood that the invention is not limited to the disclosed embodiments. That is, within the scope of the present invention, all of the components may be selectively coupled to one or more of them. Furthermore, the terms "comprises", "comprising", or "having" described above mean that a component can be implanted unless otherwise specifically stated, But should be construed as including other elements. All terms, including technical and scientific terms, have the same meaning as commonly understood by one of ordinary skill in the art to which this invention belongs, unless otherwise defined. Commonly used terms, such as predefined terms, should be interpreted to be consistent with the contextual meanings of the related art, and are not to be construed as ideal or overly formal, unless expressly defined to the contrary.

이상의 설명은 본 발명의 기술 사상을 예시적으로 설명한 것에 불과한 것으로서, 본 발명이 속하는 기술 분야에서 통상의 지식을 가진 자라면 본 발명의 본질적인 특성에서 벗어나지 않는 범위에서 다양한 수정 및 변형이 가능할 것이다. 따라서, 본 발명에 개시된 실시예들은 본 발명의 기술 사상을 한정하기 위한 것이 아니라 설명하기 위한 것이고, 이러한 실시예에 의하여 본 발명의 기술 사상의 범위가 한정되는 것은 아니다. 본 발명의 보호 범위는 아래의 청구범위에 의하여 해석되어야 하며, 그와 동등한 범위 내에 있는 모든 기술 사상은 본 발명의 권리범위에 포함되는 것으로 해석되어야 할 것이다.
The foregoing description is merely illustrative of the technical idea of the present invention and various changes and modifications may be made by those skilled in the art without departing from the essential characteristics of the present invention. Therefore, the embodiments disclosed in the present invention are intended to illustrate rather than limit the scope of the present invention, and the scope of the technical idea of the present invention is not limited by these embodiments. The scope of protection of the present invention should be construed according to the following claims, and all technical ideas falling within the scope of the same shall be construed as falling within the scope of the present invention.

100 : 선행터널
200 : 후행터널
300 : 필러부
100: preceding tunnel
200: trailing tunnel
300: pillar part

Claims (29)

(a) 선행터널과 후행터널 사이에 형성될 필러부에 터널시작점의 지반으로부터 기설정된 길이까지 복수의 필러부 보강재를 터널 길이 방향으로 이격 설치하는 단계;
(b) 선행터널을 굴착하는 단계;
(c) 상기 선행터널의 굴착면에 숏크리트를 타설하는 단계;
(d) 상기 필러부에 상기 선행터널의 숏크리트면으로부터 굴착 예정인 후행터널을 향하여 수평방향으로 상기 복수의 필러부 보강재 사이로 천공홀을 형성시키는 단계; 및
(e) 상기 천공홀에 보강 부재를 삽입 및 정착시키는 단계를 포함하며,
상기 (b) 단계에서는 상기 선행터널의 다른 굴착면과 비교하여 필러부측 굴착면을 많이 굴착하고, 상기 (c) 단계에서는 상기 선행터널의 다른 굴착면과 비교하여 상기 필러부측 굴착면에 숏크리트를 두껍게 타설하며,
상기 천공홀은 상기 숏크리트가 두껍게 타설된 상기 필러부측 굴착면에 형성되고,
상기 천공홀에 삽입된 보강 부재는 상기 숏크리트면에서 돌출되고,
상기 숏크리트가 두껍게 타설된 부분의 상기 숏크리트면에 지압판이 설치되는 터널 시공공법.
(A) installing a plurality of pillar reinforcement in the tunnel length direction from the ground of the tunnel starting point to a predetermined length in the pillar to be formed between the preceding tunnel and the trailing tunnel;
(b) digging the preceding tunnel;
(c) placing shotcrete on the excavation surface of the preceding tunnel;
(d) forming a hole in the pillar portion between the plurality of pillar portion reinforcement in a horizontal direction toward a trailing tunnel to be excavated from the shotcrete surface of the preceding tunnel; And
(e) inserting and fixing a reinforcing member in the drilling hole,
In the step (b), the filler part side excavation surface is excavated more than the other excavation surface of the preceding tunnel, and in step (c), the shotcrete is thickened on the filler side excavation surface in comparison with the other excavation surface of the preceding tunnel. Pouring,
The drilling hole is formed on the filler portion of the excavation surface on which the shotcrete is thickly poured,
The reinforcing member inserted into the drilling hole protrudes from the shotcrete surface,
Tunnel construction method wherein the pressure plate is installed on the shotcrete surface of the portion where the shotcrete is thickly cast.
제 1 항에 있어서,
상기 (a) 단계에서 상기 복수의 필러부 보강재는 상기 터널시작점의 지반 보다 전방으로 돌출되도록 설치되며,
상기 터널시작점의 지반 보다 전방으로 돌출된 필러부 보강재에는 콘크리트 또는 숏크리트가 타설되는 터널 시공공법.
The method according to claim 1,
In the step (a), the plurality of filler reinforcement is installed to protrude forward than the ground of the tunnel starting point,
Tunnel construction method in which concrete or shotcrete is poured into the filler portion reinforcement protruding forward from the ground of the tunnel starting point.
제 1 항에 있어서,
상기 (c) 단계에서, 상기 선행터널의 필러부측 굴착면에는 상기 숏크리트를 대신하여 콘크리트가 타설되는 터널 시공공법.
The method according to claim 1,
In the step (c), the tunnel construction method in which the concrete portion is poured in place of the shotcrete on the filler side side of the preceding tunnel.
제 1 항에 있어서,
상기 (c) 단계 이후에는,
(c') 상기 선행터널의 필러부측 굴착면을 보강하는 단계를 더 포함하는 터널 시공공법.
The method according to claim 1,
After step (c),
(C ') tunnel construction method further comprising the step of reinforcing the pillar-side drilling surface of the preceding tunnel.
제 4 항에 있어서,
상기 (c')에서는, 상기 선행터널의 필러부측 굴착면에 이형 철근을 격자형으로 배치하여 이루어진 철근 격자망을 설치하고, 상기 철근 격자망에 숏크리트를 타설하는 터널 시공공법.
5. The method of claim 4,
In (c '), a tunnel construction method for installing a reinforcing lattice network formed by arranging deformed reinforcing bars in a lattice shape on the pillar side of the preceding tunnel, and placing shotcrete on the reinforcing lattice network.
제 1 항에 있어서,
상기 (c) 단계 이후에는,
(c'') 상기 선행터널의 굴착면에 강지보재를 설치하는 단계를 더 포함하는 터널 시공공법.
The method according to claim 1,
After step (c),
(c '') tunnel construction method further comprising the step of installing the steel retaining material on the excavation surface of the preceding tunnel.
제 6 항에 있어서,
상기 (c'') 단계에서 상기 선행터널의 굴착면에 설치하는 상기 강지보재의 형상은 터널 굴착 형상 또는 숏크리트 타설 후 터널 형상인 터널 시공공법.
The method according to claim 6,
In the step (c ''), the shape of the steel retaining material installed on the excavation surface of the preceding tunnel is a tunnel construction method or tunnel construction after shotcrete casting.
제 6 항에 있어서,
상기 (c'') 단계는, 상기 강지보재의 잭업을 위해 좌우측 바닥면에 기초가 설치되는 단계를 포함하는 터널 시공공법.
The method according to claim 6,
The (c '') step, the tunnel construction method comprising the step of installing the base on the left and right bottom surface for jackup of the retaining material.
제 6 항에 있어서,
상기 (c'') 단계는, 상기 선행터널의 바닥면에도 강지보재가 설치되어 상기 굴착면에 설치된 강지보재와 폐합되는 단계를 포함하는 터널 시공공법.
The method according to claim 6,
The (c '') step, the tunnel construction method comprising the step of closing the rigid material is installed on the bottom surface of the preceding tunnel is installed on the excavation surface.
제 1 항에 있어서,
상기 (c) 단계 이후에는,
(c''') 상기 선행터널의 굴착면 중 필러부측 굴착면을 제외한 나머지 굴착면에 록볼트를 시공하는 단계를 더 포함하는 터널 시공공법.
The method according to claim 1,
After step (c),
(C ''') tunnel construction method further comprising the step of constructing a rock bolt on the remaining excavation surface other than the filler side side excavation surface of the preceding tunnel.
제 6 항에 있어서,
상기 선행터널의 굴착 시 상하반 분할 굴착하는 경우, 상반의 좌우 측벽의 하단에는 상기 강지보재의 고정을 위한 보강 록볼트가 체결되는 터널 시공공법.
The method according to claim 6,
In the case of dividing the upper and lower half during the excavation of the preceding tunnel, the tunnel construction method is fastened to the bottom of the left and right side walls of the upper half reinforcement lock bolt for fixing the steel retaining material.
제 1 항에 있어서,
상기 (e) 단계는, 상기 천공홀과 상기 보강 부재 사이를 압력 그라우팅하는 단계를 포함하는 터널 시공공법.
The method according to claim 1,
The step (e), the tunnel construction method comprising the step of pressure grouting between the drilling hole and the reinforcing member.
제 1 항에 있어서,
상기 (e) 단계에서, 상기 보강 부재는 굴착 예정인 후행터널의 필러부측 예정 굴착면 보다 돌출되도록 설치되는 터널 시공공법.
The method according to claim 1,
In the step (e), the reinforcing member is installed in the tunnel construction method so as to protrude more than the predetermined excavation surface of the filler side of the trailing tunnel to be excavated.
제 1 항에 있어서,
상기 (e) 단계의 보강 부재는 이중강관 또는 굴곡강관인 터널 시공공법.
The method according to claim 1,
The reinforcing member of the step (e) is a tunnel construction method of double steel pipe or bent steel pipe.
제 1 항에 있어서,
상기 선행터널의 필러부측 굴착면은 일부가 지반으로부터 수직으로 굴착되는 터널 시공공법.
The method according to claim 1,
The tunnel construction method of the pillar-side drilling surface of the preceding tunnel is partially excavated vertically from the ground.
제 15 항에 있어서,
상기 필러부의 수직으로 굴착된 굴착면에는, 마제형 또는 난형으로 숏크리트 또는 콘크리트 타설이 이루어지는 터널 시공공법.
16. The method of claim 15,
Tunnel construction method that the shotcrete or concrete is poured in a horseshoe or egg shape on the vertical excavated surface of the filler portion.
제 1 항에 있어서,
상기 선행터널의 굴착에서 상기 필러부 근처는 기계굴착 또는 제어발파가 적용되는 터널 시공공법.
The method according to claim 1,
Tunnel construction method in which the excavation of the preceding tunnel is applied to the mechanical portion or control blasting near the pillar portion.
제 1 항에 있어서,
상기 숏크리트의 최종 타설면에는 방수시트가 설치되는 터널 시공공법.
The method according to claim 1,
Tunnel construction method that the waterproof sheet is installed on the final pouring surface of the shotcrete.
제 1 항에 있어서,
상기 필러부의 상부에는 상향으로 경사지게 보강 록볼트 또는 강관다단 그라우팅이 설치되는 터널 시공공법.
The method according to claim 1,
Tunnel construction method is installed on the upper portion of the filler inclined upwardly reinforced rock bolt or steel pipe multi-stage grouting.
제 1 항에 있어서,
상기 필러부 보강재는, 상기 터널시작점으로부터 기설정된 길이 이후에는 상기 필러부측 굴착면으로부터 중심방향으로 경사지게 설치되는 터널 시공공법.
The method according to claim 1,
The pillar portion reinforcing material is a tunnel construction method is installed to be inclined in the center direction from the pillar-side excavation surface after a predetermined length from the tunnel start point.
(a) 선행터널을 굴착하는 단계;
(b) 상기 선행터널의 굴착면에 숏크리트를 타설하는 단계;
(c) 상기 선행터널의 필러부측 굴착면에 보강체 설치 및 숏크리트를 타설하고, 상기 선행터널의 굴착면에 강지보재를 설치하는 단계;
(d) 상기 필러부에 상기 선행터널의 숏크리트면으로부터 굴착 예정인 후행터널을 향하여 수평방향으로 천공홀을 형성시키는 단계;
(e) 상기 천공홀에 보강 부재를 삽입 및 정착시키는 단계;
(f) 후행터널을 굴착하는 단계;
(g) 상기 후행터널의 굴착면에 숏크리트를 타설하는 단계;
(h) 상기 후행터널의 필러부측 굴착면에 보강체 설치 및 숏크리트를 타설하고, 상기 후행터널에 강지보재를 설치하는 단계;
(i) 상기 선행터널 및 후행터널에서 상기 보강 부재가 돌출되어 있는 숏크리트면에 지압판을 설치하는 단계; 및
(j) 상기 보강 부재에 인장재를 삽입하고 상기 인장재를 당겨 고정하는 단계를 포함하고,
상기 (a) 단계 및 상기 (f) 단계에서는 상기 선행터널 및 후행터널의 다른 굴착면과 비교하여 상기 필러부측 굴착면을 많이 굴착하고,
상기 (c) 단계 및 상기 (g) 단계에서는 상기 선행터널 및 후행터널의 다른 굴착면과 비교하여 상기 필러부측 굴착면에 숏크리트를 두껍게 타설하고,
상기 천공홀은 상기 선행터널 및 후행터널에서 숏크리트가 두껍게 타설된 부분에 형성되는 터널 시공공법.
(a) digging the preceding tunnel;
(b) placing shotcrete on an excavation surface of the preceding tunnel;
(c) installing a reinforcement and shotcrete on the pillar-side excavation surface of the preceding tunnel, and installing the steel sheet on the excavation surface of the preceding tunnel;
(d) forming a hole in the horizontal direction toward the trailing tunnel to be excavated from the shotcrete surface of the preceding tunnel in the pillar portion;
(e) inserting and fixing a reinforcing member in the drilling hole;
(f) digging a trailing tunnel;
(g) placing shotcrete on the excavation surface of the trailing tunnel;
(h) installing a reinforcement and shotcrete on the pillar-side excavation surface of the trailing tunnel, and installing the steel retaining material in the trailing tunnel;
(i) installing a pressure plate on the shotcrete surface on which the reinforcing member protrudes from the preceding tunnel and the subsequent tunnel; And
(j) inserting a tension member into the reinforcement member and pulling and fixing the tension member;
In the steps (a) and (f), the filler part side excavation surface is excavated more than the other excavation surfaces of the preceding tunnel and the following tunnel,
In the steps (c) and (g), the shotcrete is thickly placed on the pillar-side drilling surface in comparison with the other drilling surfaces of the preceding tunnel and the following tunnel.
The drilling hole is a tunnel construction method is formed in the portion where the shotcrete is thickly cast in the preceding tunnel and the subsequent tunnel.
삭제delete 제 21 항에 있어서,
상기 (e) 단계에서, 상기 보강 부재는 상기 선행터널에서 후행터널 방향으로 삽입하여 정착시키고,
상기 (i) 단계 이전에, 후행터널의 굴착으로 후행터널측 필러부에 노출된 보강 부재의 말단을 절단하고 상기 보강 부재 내부로 인장재를 삽입 및 인장하고, 상기 보강 부재 내부로 그라우팅을 실시하는 터널 시공공법.
22. The method of claim 21,
In the step (e), the reinforcing member is fixed by inserting in the direction of the trailing tunnel in the preceding tunnel,
Before the step (i), the tunnel for cutting the end of the reinforcing member exposed to the trailing tunnel side pillar by excavation of the trailing tunnel, inserting and tensioning the tension member into the reinforcing member, and grouting into the reinforcing member. Construction method.
(a) 선행터널을 굴착하는 단계;
(b) 상기 선행터널의 굴착면에 숏크리트를 타설하는 단계;
(c) 상기 선행터널의 필러부에 보강체를 설치하고, 상기 선행터널에 강지보재를 설치하는 단계;
(d) 후행터널을 굴착하는 단계;
(e) 상기 후행터널의 굴착면에 숏크리트를 타설하는 단계;
(f) 상기 후행터널의 필러부에 보강체를 설치하고, 상기 후행터널에 강지보재를 설치하는 단계;
(g) 상기 필러부에 상기 후행터널의 숏크리트면으로부터 상기 선행터널의 숏크리트면까지 상기 선행터널을 향하여 수평방향으로 천공홀을 형성시키는 단계;
(h) 상기 천공홀에 보강 부재를 삽입 및 정착시키는 단계;
(i) 상기 선행터널 및 후행터널에서 보강 부재가 노출되는 숏크리트면에 지압판을 설치하는 단계; 및
(j) 상기 보강 부재에 인장재를 삽입하고 상기 인장재를 당겨 고정하는 단계를 포함하고,
상기 (a) 단계 및 상기 (d) 단계에서는 상기 선행터널 및 후행터널의 다른 굴착면과 비교하여 상기 필러부측 굴착면을 보다 많이 굴착하고,
상기 (b) 단계 및 상기 (e) 단계에서는 상기 선행터널 및 후행터널의 다른 굴착면과 비교하여 상기 필러부측 굴착면에 숏크리트를 두껍게 타설하고,
상기 천공홀은 선행터널 및 후행터널에서 숏크리트가 두껍게 타설된 부분에 형성되는 터널 시공공법.
(a) digging the preceding tunnel;
(b) placing shotcrete on an excavation surface of the preceding tunnel;
(c) installing a reinforcement in the pillar portion of the preceding tunnel and installing the steel retaining material in the preceding tunnel;
(d) drilling a trailing tunnel;
(e) placing shotcrete on the excavation surface of the trailing tunnel;
(f) installing a reinforcement in the pillar portion of the trailing tunnel and installing the steel retaining material in the trailing tunnel;
(g) forming a hole in the pillar in a horizontal direction from the shotcrete surface of the trailing tunnel to the shotcrete surface of the preceding tunnel toward the preceding tunnel;
(h) inserting and fixing a reinforcing member in the drilling hole;
(i) installing an acupressure plate on the shotcrete surface to which the reinforcing member is exposed in the preceding tunnel and the subsequent tunnel; And
(j) inserting a tension member into the reinforcement member and pulling and fixing the tension member;
In the steps (a) and (d), the filler part side excavation surface is excavated more than the other excavation surfaces of the preceding tunnel and the following tunnel,
In the steps (b) and (e), the shotcrete is thickly placed on the pillar-side excavation surface in comparison with the other excavation surfaces of the preceding tunnel and the subsequent tunnel,
The drilling hole is a tunnel construction method that is formed in the thick portion of the shotcrete in the preceding tunnel and the following tunnel.
삭제delete (a) 선행터널을 굴착하는 단계;
(b) 상기 선행터널의 굴착면에 숏크리트를 타설하는 단계;
(c) 상기 선행터널의 필러부에 보강체를 설치하고, 상기 선행터널에 강지보재를 설치하는 단계;
(d) 후행터널을 굴착하는 단계;
(e) 상기 후행터널의 굴착면에 숏크리트를 타설하는 단계;
(f) 상기 후행터널의 필러부에 보강체를 설치하고, 상기 후행터널에 강지보재를 설치하는 단계;
(g) 상기 필러부에 상기 후행터널의 숏크리트면으로부터 상기 선행터널의 숏크리트면까지 상기 선행터널을 향하여 수평방향으로 천공홀을 형성시키는 단계;
(i) 상기 천공홀에 인장형 보강 부재를 삽입시키는 단계;
(j) 상기 선행터널 및 후행터널에서 보강 부재가 노출되는 숏크리트면에 지압판을 설치하는 단계; 및
(k) 상기 인장형 보강 부재를 당겨 고정하는 단계를 포함하고,
상기 (a) 단계 및 상기 (d) 단계에서는 상기 선행터널 및 후행터널의 다른 굴착면과 비교하여 상기 필러부측 굴착면을 보다 많이 굴착하고,
상기 (b) 단계 및 상기 (e) 단계에서는 상기 선행터널 및 후행터널의 다른 굴착면과 비교하여 상기 필러부측 굴착면에 숏크리트를 두껍게 타설하고,
상기 천공홀은 선행터널 및 후행터널에서 숏크리트가 두껍게 타설된 부분에 형성되는 터널 시공공법.
(a) digging the preceding tunnel;
(b) placing shotcrete on an excavation surface of the preceding tunnel;
(c) installing a reinforcement in the pillar portion of the preceding tunnel and installing the steel retaining material in the preceding tunnel;
(d) drilling a trailing tunnel;
(e) placing shotcrete on the excavation surface of the trailing tunnel;
(f) installing a reinforcement in the pillar portion of the trailing tunnel and installing the steel retaining material in the trailing tunnel;
(g) forming a hole in the pillar in a horizontal direction from the shotcrete surface of the trailing tunnel to the shotcrete surface of the preceding tunnel toward the preceding tunnel;
(i) inserting a tensile reinforcement member into the drilling hole;
(j) installing the acupressure plate on the shotcrete surface to which the reinforcing member is exposed in the preceding tunnel and the subsequent tunnel; And
(k) pulling and fixing the tensile reinforcing member,
In the steps (a) and (d), the filler part side excavation surface is excavated more than the other excavation surfaces of the preceding tunnel and the following tunnel,
In the steps (b) and (e), the shotcrete is thickly placed on the pillar-side excavation surface in comparison with the other excavation surfaces of the preceding tunnel and the subsequent tunnel,
The drilling hole is a tunnel construction method that is formed in the thick portion of the shotcrete in the preceding tunnel and the following tunnel.
삭제delete (a) 선행터널을 굴착하는 단계;
(b) 상기 선행터널의 굴착면에 숏크리트를 타설하는 단계;
(c) 후행터널을 굴착하는 단계;
(d) 상기 후행터널의 굴착면에 숏크리트를 타설하는 단계;
(e) 상기 선행터널과 후행터널 사이의 필러부에 상기 후행터널의 숏크리트면으로부터 상기 선행터널의 숏크리트면까지 상기 선행터널을 향하여 수평방향으로 천공홀을 형성시키는 단계;
(f) 상기 천공홀에 인장형 보강 부재를 삽입시키는 단계;
(g) 상기 선행터널 및 후행터널에서 인장형 보강 부재가 노출되는 숏크리트면에 지압판을 설치하는 단계; 및
(h) 상기 인장형 보강 부재를 당겨 고정하는 단계를 포함하고,
상기 (a) 단계 및 상기 (c) 단계에서는 상기 선행터널 및 후행터널의 다른 굴착면과 비교하여 필러부측 굴착면을 보다 많이 굴착하고,
상기 (b) 단계 및 상기 (d) 단계에서는 상기 선행터널 및 후행터널의 다른 굴착면과 비교하여 상기 필러부측 굴착면에 숏크리트를 두껍게 타설하고,
상기 천공홀은 선행터널 및 후행터널에서 숏크리트가 두껍게 타설된 부분에 형성되는 터널 시공공법.
(a) digging the preceding tunnel;
(b) placing shotcrete on an excavation surface of the preceding tunnel;
(c) digging the trailing tunnel;
(d) placing shotcrete on the excavation surface of the trailing tunnel;
(e) forming a hole in the horizontal direction toward the preceding tunnel from the shotcrete surface of the trailing tunnel to the shotcrete surface of the preceding tunnel in the pillar portion between the preceding tunnel and the trailing tunnel;
(f) inserting a tensile reinforcement member into the drilling hole;
(g) installing acupressure plate on the shotcrete surface to which the tension type reinforcing member is exposed in the preceding tunnel and the following tunnel; And
(h) pulling and fixing the tensile reinforcing member,
In the steps (a) and (c), the filler part side excavation surface is excavated more than the other excavation surfaces of the preceding tunnel and the following tunnel,
In the steps (b) and (d), the shotcrete is thickly placed on the pillar-side excavation surface in comparison with the other excavation surfaces of the preceding tunnel and the subsequent tunnel,
The drilling hole is a tunnel construction method that is formed in the thick portion of the shotcrete in the preceding tunnel and the following tunnel.
삭제delete
KR1020130104343A 2013-08-30 2013-08-30 A construction method for tunnelling KR101385971B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020130104343A KR101385971B1 (en) 2013-08-30 2013-08-30 A construction method for tunnelling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020130104343A KR101385971B1 (en) 2013-08-30 2013-08-30 A construction method for tunnelling

Publications (1)

Publication Number Publication Date
KR101385971B1 true KR101385971B1 (en) 2014-04-16

Family

ID=50657860

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020130104343A KR101385971B1 (en) 2013-08-30 2013-08-30 A construction method for tunnelling

Country Status (1)

Country Link
KR (1) KR101385971B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101669669B1 (en) * 2015-04-30 2016-10-26 주식회사 성우사면 Construction methods of approaching dual tunnel
KR101854660B1 (en) * 2017-08-09 2018-05-03 우경기술주식회사 Closed tunnel filler part reinforcement structure using large diameter steel pipe and construction method thereof
KR20200101127A (en) 2019-02-19 2020-08-27 동의대학교 산학협력단 A tunnel support and method constructing the tunnel support

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100880351B1 (en) * 2007-05-07 2009-01-23 현대건설주식회사 Steel invert connection structure for tunnel capable of controlling a prestress
JP2010281174A (en) * 2009-06-08 2010-12-16 Shimizu Corp Excavation method for proximity twin tunnel
KR101149895B1 (en) * 2011-09-26 2012-05-30 주식회사 성우사면 Reinforcement block for pillar of tunnel
KR101244257B1 (en) * 2012-11-14 2013-03-18 주식회사 성우사면 Method for digging tunnel

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100880351B1 (en) * 2007-05-07 2009-01-23 현대건설주식회사 Steel invert connection structure for tunnel capable of controlling a prestress
JP2010281174A (en) * 2009-06-08 2010-12-16 Shimizu Corp Excavation method for proximity twin tunnel
KR101149895B1 (en) * 2011-09-26 2012-05-30 주식회사 성우사면 Reinforcement block for pillar of tunnel
KR101244257B1 (en) * 2012-11-14 2013-03-18 주식회사 성우사면 Method for digging tunnel

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101669669B1 (en) * 2015-04-30 2016-10-26 주식회사 성우사면 Construction methods of approaching dual tunnel
KR101854660B1 (en) * 2017-08-09 2018-05-03 우경기술주식회사 Closed tunnel filler part reinforcement structure using large diameter steel pipe and construction method thereof
KR20200101127A (en) 2019-02-19 2020-08-27 동의대학교 산학협력단 A tunnel support and method constructing the tunnel support

Similar Documents

Publication Publication Date Title
KR101244257B1 (en) Method for digging tunnel
KR101685088B1 (en) Construction method for tunneling
JP2017089104A (en) Structure and method for constructing tunnel lining body
KR20110033650A (en) Method for underground roadway using slurry wall method
KR101096664B1 (en) Construction method of approaching duel tunnel and pressing unit of pillar using the same
KR101385971B1 (en) A construction method for tunnelling
KR101524303B1 (en) The wall members and underground wall, underground wall construction method using the same
KR101695715B1 (en) Construction method for underground structure
KR20090116452A (en) Composite wall using angled channel
KR101521556B1 (en) Underground wall construction method using wall members
KR102129608B1 (en) Semi open cut type tunnel construction method at low overburden
KR101521558B1 (en) Underground wall construction method using the wall members
KR101616505B1 (en) Side wall structure using retaining member and sub-concrete structure construction method therewith
KR101720213B1 (en) C.i.p. method using pile assembly
KR100862387B1 (en) Tensional kit for top-down constructing of acupressure lasting anchor and top-down constructing method of acupressure lasting anchor using this
KR102391702B1 (en) The hybrid truss frame compsited by mix stress member for reinforcement of earth retaining concrete pile and composite wall structure using the same
CN106640118B (en) A kind of underground cavern crown structure, underground chamber and Cavity Construction method
KR100941437B1 (en) 2 arch tunnel construction method for upper girder void proofing and efficient construction
KR20180040095A (en) Construction method for soil retaining wall using cap slab
KR101809554B1 (en) Structure using key-block and sheetfile
CN113006079A (en) Foundation pit extension support body and foundation pit extension support method
JP2011157719A (en) Earth retaining method
KR20110034831A (en) Method for non excavated excavating construction using steel pipe and steel pipe with hole
KR101516746B1 (en) Construction method for girder and construction method for underground structure without temporary structure using the same
KR100322623B1 (en) An accessory for concrete block attachment

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E90F Notification of reason for final refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
J204 Invalidation trial for patent
J501 Disposition of invalidation of trial
FPAY Annual fee payment

Payment date: 20170404

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20180223

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20200312

Year of fee payment: 7