KR101250486B1 - Bridge railway ballasting construction method using temporary bent - Google Patents

Bridge railway ballasting construction method using temporary bent Download PDF

Info

Publication number
KR101250486B1
KR101250486B1 KR1020120060034A KR20120060034A KR101250486B1 KR 101250486 B1 KR101250486 B1 KR 101250486B1 KR 1020120060034 A KR1020120060034 A KR 1020120060034A KR 20120060034 A KR20120060034 A KR 20120060034A KR 101250486 B1 KR101250486 B1 KR 101250486B1
Authority
KR
South Korea
Prior art keywords
upper structure
temporary
induction
bridge
temporary vent
Prior art date
Application number
KR1020120060034A
Other languages
Korean (ko)
Inventor
김성재
정택술
Original Assignee
브릿지테크놀러지(주)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 브릿지테크놀러지(주) filed Critical 브릿지테크놀러지(주)
Priority to KR1020120060034A priority Critical patent/KR101250486B1/en
Application granted granted Critical
Publication of KR101250486B1 publication Critical patent/KR101250486B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

PURPOSE: A ballast method for a railway bridge using a temporary bent is provided to set a ballast upper structure on an accurate position after safely and quickly moving the ballast upper structure, thereby more quickly and effectively implementing the ballast of the railway bridge. CONSTITUTION: A ballast method for a railway bridge using a temporary bent includes: a step of installing a transverse rail at the sides of a ballastless bridge installed at an abutment and a pier; a step of installing a temporary bent(200) at the transverse rail so that the temporary bent of which the lower portion is equipped with rollers and directly moves along the transverse rail; a step of assembling and completing a ballast upper structure(100) on the upper surface of the temporary bent; a step of removing the ballastless bridge, moving the temporary bent on the ballast-upper structure along the transverse rail, and then settling the temporary bent on a position in which the ballastless railway bridge is installed; and a step of restoring the temporary bent along the transverse rail. [Reference numerals] (AA) Longitudinal direction; (BB) Transverse direction; (CC) Steel plate; (DD,EE) Position control;

Description

가설벤트를 이용한 철도교의 유도상화 공법{BRIDGE RAILWAY BALLASTING CONSTRUCTION METHOD USING TEMPORARY BENT}BRIDGE RAILWAY BALLASTING CONSTRUCTION METHOD USING TEMPORARY BENT}

본 발명은 가설벤트를 이용한 철도교의 유도상화 공법에 관한 것이다. 더욱 구체적으로 철도교를 교체함에 있어 미리 유도상 상부구조물을 프리캐스트 방식으로 제작하고, 기존 철도교 측방에 가설벤트를 설치한 후, 상기 유도상 상부구조물을 가설벤트와 함께 제거된 기존 무도상 교량의 위치에 밀어 넣어 종래 무도상 교량을 유도상화 시키는 가설벤트를 이용한 철도교의 유도상화 공법에 관한 것이다.The present invention relates to an induction fire process of a railway bridge using a temporary vent. More specifically, in replacing the railway bridge, the induction upper structure is manufactured in advance by the precast method, and after installing the temporary vent on the side of the existing railway bridge, the position of the existing ballless bridge in which the inductive upper structure is removed together with the temporary vent The present invention relates to an induction virtualization method of a railway bridge using a temporary vent that induces an inverse phase of a conventional ballless bridge.

철도교에 있어 유도상은 레일 및 이를 받치고 있는 침목에 충격흡수 등을 위한 자갈이 깔려있는 상태를 말한다. 반면 무도상은 상기 자갈이 깔려 있지 않은 상태를 말한다.In railroad bridges, induction phases refer to a condition where gravel is laid on the rails and sleepers supporting them for shock absorption. On the other hand, the ball phase refers to a state in which the gravel is not laid.

일반적으로 과거에 시공된 대부분의 철도교는 강교로써 도 1a와 같이 무도상으로 설치되어있다.In general, most railway bridges constructed in the past are steel bridges, which are installed on the ball as shown in FIG. 1A.

구체적으로 살펴보면 상기 무도상의 철도교는 평행하게 길이방향으로 설치된 한 쌍의 레일(61)을 일정 간격의 폭 방향으로 설치되는 침목(62)이 지지하도록 설치되어 있고, 침목(62)의 하부로는 거더(63)가 길이방향으로 설치되어 있으며, 상기 거더(63)는 거더의 교대 또는 교각(64)의 상면에 형성된 교좌장치(65)에 의하여 지지되도록 설치되어 있다.In detail, the ballless railway bridge is provided to support the pair of rails 61 installed in the longitudinal direction in parallel in the width direction at a predetermined interval to support the sleepers 62, the lower portion of the sleepers 62 63 is provided in the longitudinal direction, and the girder 63 is provided to be supported by the alternating device 65 formed on the upper surface of the alternating girder or the pier 64.

이러한 철도교는 열차가 진행함에 따라 매우 큰 동하중이 걸린다.These railway bridges take very large dynamic loads as the train proceeds.

따라서 침목은 어느 정도의 하중이 흡수되기 좋게 하기 위해 목재침목을 사용하게 되는데 자갈이 깔려 있지 않을 경우 충격흡수가 잘 되지 않아 침목과 접촉되는 레일(10) 또는 거더(30)와 침목(20)의 접촉면에 손상이 발생하고 이러한 손상이 심화됨에 따라 열차의 주행 소음이 심하게 발생하게 된다.Therefore, the sleeper uses a wooden sleeper to absorb a certain amount of load, but when the gravel is not laid, the shock absorber is not well absorbed, so that the sleeper 10 or the girder 30 and the sleeper 20 are in contact with the sleeper. As the damage occurs on the contact surface and the damage is intensified, the running noise of the train becomes severe.

또한 열차의 과중한 충격하중이 거더를 통하여 교좌장치, 교각 등에 직접적으로 작용하므로 이들에 피로 및 손상(균열) 등이 빈번하게 발생할 수밖에 없었다.In addition, because the heavy impact load of the train directly acts on the bridge system, bridge, etc. through the girders, fatigue and damage (cracking), etc. were inevitable frequently.

따라서 기존 무도상 철도교를 유도상화 시키는 보강 방법이 소개된 바 있다.Therefore, a reinforcement method was introduced to induce the existing ball-free railway bridge.

이러한 방법 중의 하나는 기존 무도상의 철도교에 슬래브(상부구조물)를 현장타설 콘크리트로 새로이 시공하고 자갈을 까는 방법인데, 이러한 방법은 콘크리트 타설을 위한 동바리, 거푸집의 설치 등을 요구할 수밖에 없어 시공성이 떨어지고 공사 중 열차통행을 차단해야 하는 문제가 있다.One of these methods is to newly install slabs (upper structures) and cast gravel on existing martial arts railroad bridges, and this method requires the installation of clubs and formwork for concrete placement. There is a problem that must be blocked.

이에 최근에는 슬래브를 프리캐스트 방식으로 미리 제작하여 철도교 측방에서 가설벤트를 이용하여 신속하게 슬래브를 설치하는 방법이 소개된 바 있다.Recently, a method of quickly manufacturing a slab using a temporary vent on the side of a railway bridge by prefabricating the slab has been introduced.

도 1b는 이러한 프리캐스트 슬래브(50)를 가설벤트(20)를 이용하여 설치하는 방법을 도시한 것이다.FIG. 1B illustrates a method of installing such a precast slab 50 using a temporary vent 20.

즉, 철도교의 교대(10A) 및 교각(10B) 간격과 동일한 간격을 가지며, 상기 교대 및 교각에 대하여 수직한 방향으로 높이조정을 위한 클램프(22), 철골들(23,24,25)들로 구성되며 베이스콘크리트(10C)에 고정 설치된 가설벤트(20)를 설치하게 된다.That is, it has the same interval as the alternating bridge 10A and pier 10B interval of the railway bridge, the clamp 22 for the height adjustment in the direction perpendicular to the alternating and bridge piers, steel plates (23, 24, 25) It is configured to install a temporary vent 20 fixed to the base concrete (10C).

또한 철도교의 교대의 강 안쪽 및 교각의 전후방으로 각각 브라켓(30)을 설치하고,In addition, the brackets 30 are respectively installed in the inner side of the river and the front and rear of the bridge of the railway bridge,

상기 가설벤트의 상부 수평 프레임(21) 상에 레일(R)을 설치하여 상부에 롤러(42)가 구비된 이동대차(40)를 설치하게 된다.The rail R is installed on the upper horizontal frame 21 of the temporary vent to install the moving cart 40 having the roller 42 thereon.

이에 새로운 프리캐스트 슬래브(50)를 별도로 제작하고 기존 철로, 침목(C), 거더로 구성된 철도교(C)를 철거하고, 이동대차(40)에 실려진 신규 프리캐스트 슬래브(50)를 새로이 교대, 교각에 받침(60)을 이용하여 설치하는 방식으로 철도교의 유도상화를 가능하도록 하는 것이다.Accordingly, a new precast slab 50 is manufactured separately, and a railway bridge (C) composed of existing railroad tracks, sleepers (C), and girder is replaced, and a new precast slab (50) loaded on the mobile truck 40 is newly shifted, It is to enable the induction of the railway bridge in a way that is installed using the support 60 in the pier.

이에 가설벤트(20)를 철도교의 교대 및 교각과 하천의 물이 흐르는 방향에 대하여 일직선으로 설치하여 강수량이 많은 우기에도 통수 단면적이 줄어들지 않게 하므로 수량에 의한 압력과 부유물 등으로 인한 교대 및 교각에 타격을 방지하는 프로텍터(PROTECTOR)의 기능을 가져 교량의 안전을 유지하는 효과가 있고 Thus, the temporary vent 20 is installed in a straight line with respect to the direction of the alternating and pier of the railway bridge and the flow of water in the river, so that the cross-sectional area of the passage does not decrease even in the rainy season with heavy rainfall. Has the function of protector to prevent the effect of keeping the bridge safe

가설벤트 상에서 프리캐스트 슬래브(50)를 제작하거나 공장에 미리 제작된 프리캐스트 슬래브(50)를 안착시켜 자주식 이동대차의 이동에 의하여 콘크리트 슬래브를 정 위치에 신속히 적치 장착하여 열차의 운행 시간의 중지 없이 교체 가능하게 하여 시공성 및 품질이 양호하며, 안정적인 시공을 할 수 있는 효과가 있다.The precast slab 50 is manufactured on the temporary construction or the precast slab 50 pre-fabricated in the factory is seated, and the concrete slab is quickly and correctly installed in the right position by the movement of the self-propelled trolley without stopping the train operation time. By making it replaceable, the workability and quality are good and there is an effect that can be stable construction.

하지만 이러한 방법은 추후 설치된 침목, 레일 등의 정확한 연속성 및 기능을 확보하기 위하여 최종 연결될 프리캐스트 슬래브(50)의 정확한 세팅이 중요하게 되지만 실제 작업을 하다보면 프리캐스트 슬래브(50)를 정확하게 연결위치에 세팅하는 작업이 용이하지 않다는 문제점이 있었다.However, in this method, it is important to accurately set the precast slab 50 to be finally connected in order to secure accurate continuity and function of the sleepers, rails, etc. installed in the future, but in practice, the precast slab 50 is correctly There was a problem that setting was not easy.

나아가 이러한 방법은 교각, 교대까지 가설벤트(20)를 연장 설치해야 하고 교대, 교각 각각에 브라켓(30)을 설치하기 때문에 공사비가 증가하는 문제점이 있었다.Furthermore, this method has a problem in that the construction cost increases because it is necessary to extend the temporary construction 20 to the pier, alternating and to install the bracket 30 on each of the alternating and pier.

즉, 프리캐스트 슬래브(50)의 최종 종방향 및 횡방향으로 위치를 미세 조정하여 미리 설치된 프리캐스트 슬래브(50)와 연속적으로 설치할 필요가 발생하는데 가설벤트의 상부 수평 프레임(21) 상에 설치된 레일과 이동대차(40)를 이용하여 프리캐스트 슬래브(50)를 이동시키다 보니 상기 레일에 의하여 이동대차(40)의 위치가 구속되어 프리캐스트 슬래브(50)의 정확한 세팅위치가 어렵다는 문제점이 있었다.That is, it is necessary to continuously adjust the position in the final longitudinal direction and the transverse direction of the precast slab 50 and install it continuously with the precast slab 50 installed in advance. The rail provided on the upper horizontal frame 21 of the temporary vent As a result of moving the precast slab 50 by using the moving cart 40, the position of the moving cart 40 is constrained by the rail, so that the correct setting position of the precast slab 50 is difficult.

이에 실제 현장에서는 이러한 프리캐스트 슬래브(50)의 세팅 위치를 변경하기 위하여 무리하게 대차 등의 위치를 조정하려다가 대차 및 상부 수평 프레임(21) 사이에 설치된 레일이 전도되는 등 안전사고가 발생하는 경우가 발생하게 되었다.In practice, safety accidents such as the rails installed between the bogie and the upper horizontal frame 21 are conducted when the position of the bogie is excessively adjusted in order to change the setting position of the precast slab 50. It happened.

특히, 곡선 철도교의 경우 새로운 상부구조물(프리캐스트 슬래브)을 설치하기 위해서는 종방향 및 횡방향 구배를 정확히 맞추어야 하는데 이러한 작업은 가설벤트에 의하여 운반된 상부구조물에 의해서는 한계가 있을 수밖에 없다는 문제점이 있었다.In particular, in the case of curved railway bridges, in order to install a new superstructure (precast slab), the longitudinal and transverse gradients must be precisely aligned. This work has a problem that the superstructure carried by the temporary construction is limited. .

이에 본 발명은 가설벤트를 철도교의 측방에 설치한 후, 상기 가설벤트를 이용하여 유도상화를 위한 상부구조물의 설치에 있어서, 유도상 상부구조물을 보다 안전하면서도 신속하게 이동시킨 후 유도상 상부구조물의 정확한 위치 세팅이 가능하도록 함으로서 철도교의 유도상화를 보다 신속하고 효과적으로 수행할 수 있는 가설벤트를 이용한 철도교의 유도상화 공법 제공을 해결하고자 하는 기술적 과제로 한다.Therefore, the present invention is to install a temporary vent on the side of the railway bridge, in the installation of the upper structure for induction burn using the temporary vent, the induction upper structure of the induction phase superstructure after moving more safely and quickly It is a technical problem to solve the provision of the induction virtualization method of railroad bridges using temporary vents that can perform the induction virtualization of railroad bridges more quickly and effectively.

상기 기술적 과제를 달성하기 위하여 본 발명은According to an aspect of the present invention,

첫째, 철도교의 유도상 상부구조물은 프리캐스트로 제작하여 현장에 반입하여 가설벤트 상면에서 완성시킬 수 있도록 함으로서 보다 신속하게 철도교의 유도상화가 가능하도록 하였다.First, the induction phase superstructures of railway bridges were manufactured by precast and brought to the site to be completed on the upper surface of temporary vents.

둘째, 상기 유도상 상부구조물은 철도교의 측방에 설치된 가설벤트에 적치되도록 한 상태에서 가설벤트 하부에 설치된 횡방향 레일을 따라 유도상 상부구조물이 가설벤트와 함께 이동되도록 하여 종래 대차 및 대차를 이동시키기 위한 구동수단을 별도로 별도 구비하지 않아도 유도상 상부구조물 이동이 가능하여 시공성 및 경제성을 최적화시키게 된다.Secondly, the induction upper structure is moved to the conventional bogie and bogie by moving the induction superstructure along the lateral rail installed under the temporary vent in a state where it is placed on the temporary vent installed on the side of the railway bridge. It is possible to move the upper structure induction phase without having to provide a separate drive means for optimizing the workability and economics.

이에 상기 가설벤트 하부에는 횡방향으로 레일을 설치하고, 상기 횡방향 레일을 따라 유도상 상부구조물이 적치된 가설벤트가 직접 이동하여 유도상 상부구조물을 교대, 교각에 설치하도록 하게 된다.Accordingly, a rail is installed in a transverse direction under the temporary vent, and a temporary tent in which an induction upper structure is stacked is moved directly along the transverse rail so that the induction upper structure is alternately installed at the pier.

셋째, 상기 유도상 상부구조물을 정확한 위치에 세팅시키기 위하여 가설벤트 상면에는 슬라이딩패드를 고정 설치하고, 상기 슬라이딩패드 상면에 지지수단을 설치하여 지지수단이 슬라이딩패드 상면에서 유압잭을 포함하는 위치제어수단에 의하여 슬라이딩되면서 상기 지지수단에 지지되도록 설치된 유도상 상부구조물의 위치를 정확하게 조정할 수 있도록 하였다.Third, in order to set the induction upper structure in the correct position, a sliding pad is fixedly installed on the upper surface of the temporary vent, and a support means is installed on the upper surface of the sliding pad so that the support means includes a hydraulic jack on the upper surface of the sliding pad. By sliding it was to be able to accurately adjust the position of the induction upper structure installed to be supported by the support means.

이를 위하여 본 발명은To this end,

(a)교대, 교각에 설치된 무도상 교량의 측방에 횡방향 레일을 설치하는 단계; (b)상기 하부에 롤러가 형성되어 횡방향 레일을 따라 직접 이동하도록 가설벤트를 횡방향 레일에 설치하는 단계; (c)상기 가설벤트 상면에서 유도상 상부구조물을 조립하여 완성시키는 단계; (d)상기 무도상 교량을 제거하고 유도상 상부구조물이 상면에 설치된 가설벤트를 횡방향레일을 따라 이동시켜 무도상 철도교가 설치된 위치에 안착시키는 단계; 및 (e)상기 가설벤트를 횡방향 레일을 따라 복귀시키는 단계를 포함하며,(a) installing a transverse rail on the side of the ballless bridge installed on the bridge, the bridge; (b) installing a temporary vent on the transverse rail so that a roller is formed at the lower portion to move directly along the transverse rail; (c) assembling and completing the induction superstructure on the upper surface of the temporary vent; (d) removing the martial arts-free bridge and moving a temporary vent installed on the upper surface of the inductive superstructure along a transverse rail and seating at a location where the martial arts-free railway bridge is installed; And (e) returning the temporary vent along the transverse rail,

상기 (d)단계는, 가설벤트 상면에 슬라이딩패드를 고정 설치하고, 상기 슬라이딩패드 상면에서 슬라이딩 되도록 지지수단을 설치하고, 상기 유도상 상부구조물이 상면에 설치된 지지수단에 유압잭을 포함하는 위치제어수단을 연결하여, 상기 위치제어수단의 작동에 의하여 지지수단이 슬라이딩패드 상면에서 슬라이딩 되면서 지지수단 상면에 설치된 유도상 상부구조물의 위치를 조정할 수 있도록 있도록 하며, 상기 지지수단은 상부구조물 인상용 잭을 이용하고, 상기 위치제어수단은 하우징에 장착된 유압잭 및 유압실린더를 포함하여 구성되도록 하고, 상기 유압실린더는 지지수단의 측면에 연결되어 유압실린더의 작동에 의하여 상부구조물이 지지된 지지수단을 슬라이딩패드 상면에서 원하는 위치로 조정할 수 있도록 하는 가설벤트를 이용한 철도교의 유도상화 공법을 제공한다.In the step (d), the sliding pad is fixedly installed on the upper surface of the temporary vent, the support means is installed to slide on the upper surface of the sliding pad, and the position control means including the hydraulic jack on the supporting means installed on the upper surface of the inductive phase. By connecting the support means to be able to adjust the position of the induction upper structure installed on the upper surface of the support means while the support means is slid from the upper surface of the sliding pad by the operation of the position control means, the support means using a jack for lifting the upper structure The position control means includes a hydraulic jack mounted on the housing and a hydraulic cylinder, wherein the hydraulic cylinder is connected to the side of the support means and supports the support means on which the upper structure is supported by the operation of the hydraulic cylinder. Iron with hypothetical vents that allow the operator to adjust to the desired position Provide Taoist induction technique.

본 발명의 범위는 상기 상세한 설명보다는 후술하는 특허청구범위에 의하여 나타내어지며, 특허청구범위의 의미 및 범위 그리고 그 균등 개념으로부터 도출되는 모든 변경 또는 변형된 형태가 본 발명의 범위에 포함되는 것으로 해석되어야 한다.The scope of the present invention is shown by the following claims rather than the above description, and all changes or modifications derived from the meaning and scope of the claims and their equivalents should be construed as being included in the scope of the present invention. do.

본 발명에 의하여 상부구조물을 프리캐스트로 제작하여 신속하게 철도교의 유도상화를 위한 시공이 가능하게 된다. According to the present invention, the upper structure is made of precast, and construction for rapid induction of the railway bridge is possible.

이때 상기 상부구조물은 다양한 형상이 가능하게 되는데 슬래브와 거더가 서로 일체화된 방식으로 제작하되, 세그먼트로 제작하여 현장에서 조립 시공할 수 있도록 함으로서 제작, 운반 및 시공의 효율성이 증진될 수 있도록 하였다.At this time, the upper structure is capable of a variety of shapes, but the slab and the girder are manufactured in an integrated manner, but by making a segment to be assembled in the field so that the efficiency of manufacturing, transport and construction can be improved.

또한, 상부구조물을 가설벤트와 함께 이동시켜 설치하게 되므로 상부구조물을 가설벤트에서 이동시키기 위한 별도의 대차 등의 운용이 필요 없어 시공성이 증진되고 경제성을 확보할 수 있으며 상부구조물의 전도 등의 안전사고를 방지할 수 있게 된다.In addition, since the upper structure is moved together with the temporary vent and installed, it is not necessary to operate a separate truck for moving the upper structure from the temporary vent, thereby improving construction performance and securing economic feasibility and safety accidents such as conduction of the upper structure. Can be prevented.

또한, 가설벤트를 레일에 의하여 이동시키는 경우 가설벤트가 레일에 의하여 위치가 구속되므로 레일 설치 방향의 직각방향으로는 상부구조물의 이동 및 위치 조정이 어렵지만 본 발명은 슬라이딩패드, 지지수단(상부구조물 인상용 잭)과 유압잭을 포함하는 위치제어수단을 이용하여 현장에서 간단하게 상부구조물의 위치 변경이 가능하여 상부구조물의 정밀시공이 가능하며, 특히 곡선형 철도교에 있어 정밀한 시공이 가능하게 된다.In addition, when the temporary vent is moved by the rail, the temporary vent is constrained by the rail, so that the movement and position adjustment of the upper structure is difficult in the direction perpendicular to the rail installation direction, but the present invention provides a sliding pad and a support means (upper upper structure). It is possible to simply change the position of the upper structure in the field by using the position control means including the jack) and the hydraulic jack, it is possible to precise construction of the upper structure, especially in the curved railway bridge.

이에 상부구조물을 정확한 위치에 시공할 수 있어 상부구조물에 설치되는 침목, 레일 등의 연속성을 확보할 수 있어 시공성 및 사용성을 확보할 수 있게 된다.Accordingly, the upper structure can be constructed at the correct position, thereby securing the continuity of the sleepers and rails installed in the upper structure, thereby ensuring the constructability and usability.

도 1a는 종래 무도상 철도교의 단면도,
도 1b 및 도 1c는 종래 가설벤트를 이용한 철도교의 유도상화 시공사시도 및 단면도,
도 2는 본 발명의 상부구조물의 제작 사시도,
도 3은 본 발명의 슬라이딩패드와 유압잭을 포함하는 위치제어수단을 이용한 상부구조물의 위치 조정 사시도,
도 4a, 도 4b, 도 4c, 도 4d 및 도 4e는 본 발명에 의한 가설벤트를 이용한 철도교 교체공법의 순서도
도 5는 본 발명의 본 발명에 의한 가설벤트를 이용한 철도교 교체공법 사시도이다.
Figure 1a is a cross-sectional view of a conventional ballless railway bridge,
1B and 1C are cross-sectional views and induction diagrams of induction burn construction of a railway bridge using a conventional temporary vent,
Figure 2 is a perspective view of the production of the upper structure of the present invention,
Figure 3 is a perspective view of the position adjustment of the upper structure using the position control means including a sliding pad and the hydraulic jack of the present invention,
4a, 4b, 4c, 4d and 4e is a flow chart of the railroad bridge replacement method using a temporary vent according to the present invention
5 is a perspective view of a railway bridge replacement method using a temporary vent according to the present invention.

아래에서는 첨부한 도면을 참조하여 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자가 용이하게 실시할 수 있도록 본 발명의 실시예를 상세히 설명한다. 그러나 본 발명은 여러 가지 상이한 형태로 구현될 수 있으며 여기에서 설명하는 실시예에 한정되지 않는다. 그리고 도면에서 본 발명을 명확하게 설명하기 위해서 설명과 관계없는 부분은 생략하였으며, 명세서 전체를 통하여 유사한 부분에 대해서는 유사한 도면 부호를 붙였다.DETAILED DESCRIPTION Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings so that those skilled in the art may easily implement the present invention. The present invention may, however, be embodied in many different forms and should not be construed as limited to the embodiments set forth herein. In the drawings, parts irrelevant to the description are omitted in order to clearly describe the present invention, and like reference numerals designate like parts throughout the specification.

[ 본 발명의 유도상 상부구조물(100) ][Induction phase structure 100 of the present invention]

상기 유도상 상부구조물(100)은 철도교의 유도상화를 위한 교량이라 할 수 있다. 이러한 교량은 프리캐스트 방식으로 제작된 것을 이용하게 된다.The induction upper structure 100 may be referred to as a bridge for induction of the railway bridge. These bridges are made of a precast method.

철도교에 사용되는 유도상 상부구조물(100)도 종방향 및 횡방향으로 일정한 길이와 폭을 가지게 된다.The induction superstructure 100 used for the railway bridge also has a constant length and width in the longitudinal and transverse directions.

이에 다양한 철도교의 종방향 길이에 따라 다수의 상부구조물을 종방향으로 연결하여 시공해야 하는데 문제는 횡방향 폭이 커질 경우 1개의 유도상 상부구조물도 그 크기가 매우 커질 수밖에 없다는 문제점이 있다.Accordingly, a plurality of superstructures must be connected in the longitudinal direction according to the longitudinal length of various railway bridges, and the problem is that when the width of the transverse width is increased, the size of one induction superstructure is very large.

이에 유도상 상부구조물의 제작 및 차량 운반도 제한적이게 되고 가설벤트 상면에 적치하는 작업도 현장에서 어려워지게 된다.Therefore, the construction of the induction upper structure and the vehicle transportation are also limited, and the work on the upper surface of the temporary vent becomes difficult in the field.

이에 본 발명은 도 2와 같이 유도상 상부구조물(100)을 종방향으로는 일정한 길이(L)를 가지도록 하되 횡방향으로 서로 연결되도록 다수의 세그먼트로 제작하게 된다.Accordingly, the present invention is to have a predetermined length (L) in the inverted upper structure 100 in the longitudinal direction as shown in Figure 2 to be produced in a number of segments to be connected to each other in the transverse direction.

이에 상기 유도상 상부구조물(100)은 저형고로서 중공박스 구조물로 제작되도록 하되 몸통부(110)와 상부플랜지(120)로 형성되도록 제작된다.Accordingly, the induction upper structure 100 is manufactured to be made of a hollow box structure as a low solid body, but is formed to be formed of the trunk portion 110 and the upper flange 120.

상기 몸통부(110)는 박스체 형태로 무게를 줄이기 위하여 내부에는 EPS(111)가 매립되는 형태로 형성되도록 하고, 상기 몸통부(110)의 상부에는 슬래브 역할을 확장 상부플랜지(120)로 형성되어 있다.The body portion 110 is formed in the form of a shape in which the EPS 111 is embedded in the inside to reduce the weight in the form of a box, the upper portion of the body portion 110 is formed as an extended upper flange 120 It is.

이때 상기 몸통부(110)에는 횡방향으로 관통공(112)이 형성되어 있어 횡방향 긴장재(130)에 의하여 서로 일체화되도록 제작된다.At this time, the through-hole 112 in the transverse direction is formed in the body portion 110 is manufactured to be integrated with each other by the transverse tension member (130).

이에 횡방향으로 적어도 2개 이상의 세그먼트 상부구조물을 서로 연결시킴에 있어 횡방향 긴장재(130)와 상부플랜지 연결부의 연결홈에 충진된 그라우팅재(140, 현장 타설 콘크리트 등)를 이용하여 서로 일체화시키게 되는데, 이러한 작업은 공장에서 세그먼트 상부구조물을 제작하고, 현장에 반입한 후 가설벤트 상면에서 이루어지게 된다.Therefore, in connecting at least two or more segment upper structures to each other in the transverse direction, it is integrated with each other using grouting material (140, cast-in-place concrete, etc.) filled in the connecting groove of the transverse tension member 130 and the upper flange connection. This work is done on the top of the construction vent after the construction of the segment superstructure at the factory, brought to the site.

이에 상기 유도상 상부구조물(100) 상면에는 방호벽, 난간 등이 측방에 설치되고 침목(150)과 철로(160)가 설치되어 상면에 자갈(170) 등이 포설되는 등의 유도상화가 이루어지게 함으로서 시공성을 충분히 확보할 수 있도록 하게 된다.In the upper surface of the induction phase structure 100, a barrier, a railing, etc. are installed on the side, and the sleeper 150 and the railroad 160 are installed so that the induction of the gravel 170 is installed on the upper surface. It will be able to secure the constructability enough.

[ 본 발명의 유도상 상부구조물(100)의 위치 조정 ][Adjusting the position of the induction upper structure 100 of the present invention]

후술되지만 도 4a와 같이 상기 유도상 상부구조물(100)은 가설벤트(200) 상면에 임시받침(211)에 적치되어 가설벤트(200)에 안착되며 가설벤트(200)와 함께 횡방향으로 이동된다.Although it will be described later, as shown in FIG. 4A, the induction upper structure 100 is placed on the temporary support 211 on the upper surface of the temporary vent 200 to be seated on the temporary vent 200, and moved horizontally together with the temporary vent 200. .

이러한 이동은 종래 무도상 철도교의 철로, 침목 및 거더를 제거한 위치가 되는데 이러한 위치에 정확하게 유도상 상부구조물(100)이 위치할 수 있도록 가설벤트(200)의 위치는 설계 시부터 정확하게 이동경로가 정해져야 한다.This movement is the position of removing the tracks, sleepers and girders of the conventional martial arts railroad bridge, the position of the temporary vent 200 is precisely determined from the design so that the induction phase superstructure 100 can be located exactly in this position Should.

하지만 시공 상의 오차 등에 의하여 가설벤트의 위치가 정밀하게 시공되지 않으면 유도상 상부구조물(100)의 위치를 정확하게 설치하기가 쉽지 않다.However, if the position of the temporary vent is not precisely installed due to an error in construction, it is not easy to accurately install the position of the upper structure 100 in induction phase.

이에 본 발명은 설사 가설벤트(200)가 이동레일(300)에 의하여 이동레일 직각방향으로 위치가 구속되더라도 유도상 상부구조물(100)의 위치를 가설벤트 상면에서 다소 조정할 수 있도록 하는 수단을 제공하게 된다.Therefore, the present invention provides a means for adjusting the position of the induction upper structure 100 somewhat on the upper surface of the temporary vent even if the diarrhea temporary vent 200 is restrained in the direction perpendicular to the movable rail by the movable rail 300. do.

이러한 수단은 슬라이딩패드(410)와 상기 슬라이딩패드의 위치를 조정하기 위한 유압잭을 포함하는 위치제어수단(420)을 포함하는 위치조정수단(400)이다.This means is a position adjusting means 400 including a sliding pad 410 and a position control means 420 including a hydraulic jack for adjusting the position of the sliding pad.

먼저 상기 슬라이딩패드(410)는 그 명칭과 같이 가설벤트(200) 상면에 고정 설치된 판재 형태의 부재인데 마찰계수가 매우 작은 테프론 재질로 제작된 것을 이용하되 내부에는 스틸플레이트가 매립되어 있어 중량물의 저면에 설치되는 경우라도 충분한 내구성이 확보될 수 있게 된다.First, the sliding pad 410 is a member in the form of a plate fixed to the upper surface of the temporary vent 200 as its name is used made of a Teflon material with a very small coefficient of friction, but the inside of the steel plate is embedded in the bottom of the heavy Sufficient durability can be ensured even when installed in the.

이러한 슬라이딩패드(410)는 가설벤트(200) 상면에 설치되어 위치가 고정되며 상기 슬라이딩패드(410) 상면에 상구구조물 인상용 잭인 지지수단(210)이 설치되어 있다.The sliding pad 410 is installed on the upper surface of the temporary vent 200, the position is fixed, the support means 210 that is a jack for lifting the upper structure is installed on the upper surface of the sliding pad 410.

이에 슬라이딩패드(410)와 지지수단(210)에 의하여 유도상 상부구조물(100)이 지지되어 있는데 슬라이딩패드(410) 상면에 설치된 지지수단(210)을 일정 방향으로 밀어주게 되면 슬라이딩패드와 지지수단이 서로 접하는 부위는 마찰계수가 매우 작아 적은 힘으로도 지지수단(210)에 의하여 지지 설치된 유도상 상부구조물(100)의 위치를 조정할 수 있게 된다.The induction upper structure 100 is supported by the sliding pad 410 and the support means 210. When the support means 210 installed on the upper surface of the sliding pad 410 is pushed in a predetermined direction, the sliding pad and the support means are supported. The portions in contact with each other can adjust the position of the induction upper structure 100 supported by the support means 210 with a small frictional coefficient with a very small force.

이때 지지수단(210)을 밀어주는 힘을 제공하는 수단이 유압잭을 포함하는 위치제어수단(420)이다.At this time, the means for providing a force for pushing the support means 210 is a position control means 420 including a hydraulic jack.

즉, 위치제어수단(420)에 의하여 지지수단(210)이 슬라이딩패드(410) 상면에서 유도상 상부구조물(100)의 위치를 원하는 위치로 조정할 수 있는 것이다.That is, by the position control means 420, the support means 210 can adjust the position of the inductive upper structure 100 on the sliding pad 410 to the desired position.

이에 상기 위치제어수단(420)의 유압잭(421)은 하우징(422)에 장착되고, 상기 유압잭(421)에는 지지수단(210)의 측면에 연결되어 유압실린더(423)의 작동에 의하여 상부구조물이 지지된 지지수단(210)을 슬라이딩 패드 상면에서 원하는 위치로 조정할 수 있게 된다.The hydraulic jack 421 of the position control means 420 is mounted to the housing 422, the hydraulic jack 421 is connected to the side of the support means 210 to the upper structure by the operation of the hydraulic cylinder 423 Supported support means 210 can be adjusted to a desired position on the upper surface of the sliding pad.

이에 상기 위치제어수단(420)은 소형화가 가능하여 휴대 및 설치가 매우 용이하고 작동도 쉽다는 장점이 있게 된다.Accordingly, the position control means 420 can be miniaturized, so that the position control means 420 is very easy to carry and install and easy to operate.

이때 상기 위치제어수단(420)은 지지수단(210)의 측면 어디라도 설치가 가능하여 임시받침에 의한 상부구조물의 위치(종방향 및 횡방향)를 자유롭게 조정할 수 있게 된다.At this time, the position control means 420 can be installed anywhere on the side of the support means 210 to be able to freely adjust the position (vertical and transverse direction) of the upper structure by the temporary support.

이때 상기 지지수단(210)은 상부구조물 인상용 잭을 이용하면 되며 상기 상부구조물 인상용 잭 외주면에 고리를 형성시키고 상기 고리에 유압실린더(423)가 연결되도록 하여 지지수단(210)에 위치제어수단(420)이 연결되도록 할 수 있다.At this time, the support means 210 is to use a jack for lifting the upper structure and to form a ring on the outer peripheral surface of the jack for lifting the upper structure and the hydraulic cylinder 423 is connected to the ring position control means in the support means 210 420 may be connected.

[ 본 발명의 가설벤트를 이용한 철도교 교체공법 ][Railway Bridge Replacement Method Using Temporary Vent of the Present Invention]

도 4a 내지 도 4e는 본 발명에 의한 가설벤트를 이용한 철도교 교체공법을 순서대로 도시한 것이다.4a to 4e sequentially illustrate the railway bridge replacement method using a temporary vent according to the present invention.

먼저, 도 4a와 같이 기존 철도교(500)는 교대, 교각(510) 상부에 무도상 거더(520), 침목(530), 철로(540) 및 난간(550)이 설치되어 있으며 본 발명은 이러한 거더(520), 침목(530), 철로(540) 및 난간(550)을 제거하고 유도상 상부구조물(100)을 새로이 설치하게 된다.First, as shown in Figure 4a, the existing railroad bridge 500, the girder 520, the sleeper 530, railroad 540 and railings 550 are installed on the top of the bridge, pier 510 and the present invention is such a girder 520, the sleeper 530, the railroad 540 and the railings 550 are removed and the superstructure 100 is newly installed.

이를 이해 상기 교대, 교각(510) 측방으로 사이사이(경간 사이)에 가설벤트(200) 이동을 위한 횡방향 레일(300)을 먼저 설치하게 된다.To understand this, the transverse rail 300 for moving the temporary vent 200 between the alternating, pier 510 side (between the span) first to be installed.

이러한 횡방향 레일(300)은 횡방향으로 연장되도록 하되 유도상 상부구조물(100)의 위치를 고려하여 서로 이격되도록 설치하게 되는데 가설벤트의 설치개수에 따라 경간 사이에 한 쌍을 설치하게 된다.The transverse rail 300 is to be extended in the transverse direction but installed so as to be spaced apart from each other in consideration of the position of the upper structure 100 induction phase is installed between the span according to the number of installation of the temporary vents.

즉 각 경간에 도 1b와 같이 다수의 가설벤트(200)를 설치하여 다수의 상부구조물을 설치하는 경우 보다 신속하게 상부구조물을 설치할 수 있으므로 이는 현장 여건 등을 고려하여 설치하면 된다.That is, when installing a plurality of upper structures by installing a plurality of temporary vents 200 in each span as shown in Figure 1b it can be installed in consideration of the site conditions, such as to install the upper structure more quickly.

이러한 횡방향 레일(300)을 따라 이동하도록 설치되는 것이 가설벤트(200)이다.The temporary vent 200 is installed to move along the lateral rail 300.

상기 가설벤트(200)는 하면에 레일(300)을 따라 이동할 수 있도록 롤러(220)가 설치된다.The temporary vent 200 is provided with a roller 220 to move along the rail 300 on the lower surface.

이에 가설벤트(200)는 롤러(220)에 의하여 횡방향 레일(300)을 따라 직접 횡방향으로 이동하게 됨을 알 수 있다.Accordingly, the temporary vent 200 may be directly moved in the horizontal direction along the horizontal rail 300 by the roller 220.

종전에는 가설벤트가 고정 설치되는 방식으로 설치하였으므로 이럴 경우 대차를 이용하여 상부구조물을 이동시켜야 했는데 본 발명은 이러한 방식을 탈피하여 가설벤트(200) 상면에 유도상 상부구조물(100)을 적치하고, 유도상 상부구조물(100)과 가설벤트(200)를 함께 횡방향 레일(300)을 따라 이동될 수 있도록 한 것이다.Previously, the temporary construction was installed in such a way that it was installed. In this case, the upper structure had to be moved by using a trolley. The present invention avoids this method and places the induction upper structure 100 on the upper surface of the temporary construction 200. The induction phase superstructure 100 and the temporary vent 200 are to be moved along the transverse rail 300 together.

이럴 경우 보다 안전하게 유도상 상부구조물(100)을 신속하게 설치할 수 있으며, 유도상 상부구조물(100)을 가설벤트(200) 상면에서 조립할 수 있어 보다 효율적이고 신속한 가설벤트 운용이 가능하게 된다.In this case, the induction phase upper structure 100 can be quickly installed more safely, and the induction phase upper structure 100 can be assembled on the upper surface of the temporary vent 200 to enable more efficient and faster temporary vent operation.

이에 상기 가설벤트(200) 상면에는 유도상 상부구조물(100)을 지지하기 위한 임시받침(211)이 다수 설치되며, 도 4a에는 상기 임시받침(211) 사이에 상부구조물 인상용 잭인 지지수단(210)이 가설벤트 상면에 고정된 슬라이딩패드(410, 도 4d 참조)에 설치되어 있음을 알 수 있다.Accordingly, a plurality of temporary supports 211 are provided on the upper surface of the temporary vent 200 to support the inductive upper structure 100, and in FIG. 4A, support means 210 which are jacks for raising the upper structure between the temporary supports 211. ) Is installed on the sliding pad 410 (see FIG. 4D) fixed to the upper surface of the temporary vent.

상기 가설벤트(200)의 높이 및 크기는 상부구조물의 크기 등을 이용하여 철골조립체로 제작된 것을 이용하면 된다.The height and size of the temporary vent 200 may be made of steel assembly using the size of the upper structure.

또한 상기 가설벤트(200) 상면에 적치시킬 유도상 상부구조물(100)은 도 2와 같이 세그먼트 상부구조물로 제작 및 현장에 반입시켜 놓게 되다.In addition, the induction upper structure 100 to be placed on the upper surface of the temporary vent 200 is manufactured as a segment upper structure and brought into the site as shown in FIG.

다음으로는 도 4b와 같이 상기 세그먼트 상부구조물을 인양용 와이어 등을 이용하여 가설벤트(200)에 적치하고, 1 경간에 설치되는 유도상 상부구조물(100)로 가설벤트(200) 상면에서 조립 설치하게 된다.Next, as shown in FIG. 4B, the segment upper structure is placed on the temporary vent 200 by using a lifting wire, and then assembled on the upper surface of the temporary vent 200 by an induction upper structure 100 installed in one span. Done.

이러한 세그먼트 상부구조물은 가설벤트(200) 상면에 설치된 임시받침(211) 상면에 지지되도록 설치하게 된다.The segment upper structure is installed to be supported on the temporary support 211, the upper surface of the temporary vent 200 is installed.

이에 세그먼트 상부구조물을 도 2와 같이 횡방향으로 접하도록 세팅하고,Thus, the segment superstructure is set in contact with the transverse direction as shown in FIG.

상기 세그먼트 상부구조물의 상부플랜지 연결부의 연결홈에 충진된 그라우팅재(140, 현장 타설 콘크리트 등)를 이용하여 서로 연결시킨 다음.After connecting to each other using a grouting material (140, cast-in-place concrete, etc.) filled in the connecting groove of the upper flange connection of the segment upper structure.

상기 세그먼트 상부구조물의 몸통부(110)에 형성된 관통공(112)에 횡방향 긴장재(130)를 삽입하고 긴장 및 정착시켜 서로 완전하게 일체화시게 된다.The transverse tension member 130 is inserted into the through hole 112 formed in the trunk portion 110 of the segment upper structure, and is tensioned and fixed to completely integrate with each other.

이에 상기 세그먼트 상부구조물 상면에는 방호벽, 난간 등이 측방에 설치되고 침목(150)과 철로(160)가 설치되기 이전의 상태가 된다.Accordingly, the upper surface of the upper structure of the segment is provided with a barrier, a railing, and the like, before the sleeper 150 and the railroad line 160 are installed.

나아가 유도상화 시키기 위하여 침목(150)과 철로(160)를 설치하고, 자갈(170,도상)을 포설하여 가설벤트에서 상부구조물 조립 및 유도상화가 가능하도록 하게 된다.Further, the sleeper 150 and the railroad line 160 are installed to induce induction, and the gravel 170 is installed to allow the assembly of the upper structure and the induction in the temporary construction.

이와 같이 가설벤트(200) 상면에서 새로운 유도상 상부구조물(100)을 조립 설치 및 유도상화 시키게 되면 완성된 유도상 상부구조물을 인양하는 것과 대비하여 무게가 크지 않아 기중기 운용에 유리하여 시공성이 매우 증진되는 효과가 있다.As such, when the new guided upper structure 100 is assembled and installed on the upper surface of the temporary vent 200, the weight is not large as compared with lifting the completed guided upper structure. It is effective.

또한 인양하중에 의하여 조립 설치된 유도상 상부구조물(100)에 작용하는 단면력을 고려하지 않아도 된다는 구조적 장점도 있게 된다.In addition, there is also a structural advantage that does not have to consider the cross-sectional force acting on the induction upper structure 100 assembled by the lifting load.

다음으로는 도 4c와 같이 기존 철도교(500)를 철거하게 된다. 이러한 철거 작업은 열차운행에 방해가 되지 않는 시간적, 공간적 범위에서 가설벤트에서 새로운 유도상 상부구조물(100) 준비가 완료되기 이전에 작업하면 되며 역시 기중기 등을 이용하여 분리 철거하는 방식으로 작업하면 된다.Next, as shown in Figure 4c is to remove the existing railway bridge (500). Such demolition work may be performed before the preparation of a new induction superstructure 100 at the temporary installation in a temporal and spatial range that does not interfere with the train operation. .

다음으로는 도 4d와 같이 새로운 유도상 상부구조물(100)을 가설벤트(200)와 함께 이동시켜 기존 철도교(500)가 제거된 위치에 새로운 유도상 상부구조물(100)을 세팅하게 된다.Next, as shown in FIG. 4D, the new induction phase superstructure 100 is moved together with the temporary vent 200 to set the new induction phase superstructure 100 at a position where the existing railway bridge 500 is removed.

앞서 살펴본 것과 같이 새로운 유도상 상부구조물(100)은 임시받침(211)에 의하여 지지되어 있으며, 슬라이딩패드(410)와 위치제어수단(420)을 포함하는 위치조정수단(400)이 지지수단(210)과 함께 별도로 임시받침(211) 사이사이에 설치되어 있다.As described above, the new inductive upper structure 100 is supported by the temporary support 211, and the positioning means 400 including the sliding pad 410 and the position control means 420 is supported by the support means 210. ) And is installed between the temporary support 211 separately.

이에 새로운 유도상 상부구조물(100)을 가설벤트(200)와 함께 이동시킨 다음 새로운 유도상 상부구조물(100)을 설치해야 할 위치에 정확하게 세팅되도록 도 3과 같이 상기 위치조정수단(400)을 이용하게 된다.Therefore, the new guided upper structure 100 is moved together with the temporary vent 200, and then the position adjusting means 400 is used as shown in FIG. Done.

즉, 상부구조물 인상용 잭인 지지수단(210)을 상승시켜 유도상 상부구조물(100)을 인상시키고, 상기 지지수단(210)에 연결된 유압잭인 위치제어수단(420)을 작동시켜 유도상 상부구조물(100)을 종방향 및 횡방향으로 정확한 위치에 세팅되도록 하게 된다.That is, by raising the support means 210 which is a jack for raising the upper structure, the induction upper structure 100 is raised, and the position control means 420 which is a hydraulic jack connected to the support means 210 is operated to induce the upper structure ( 100) to be set at the correct position in the longitudinal and transverse directions.

이에 최종 위치가 세팅되면 교대, 교각 위에 교량받침을 새로이 교체하여 새로운 교량받침 또는 기존 교량받침에 그대로 상부구조물 인상용 잭인 지지수단(210)을 하강시켜 유도상 상부구조물(100)을 안착시키게 된다.When the final position is set to replace the bridge bearings on the bridges, bridges newly replace the new bridge bearings or jacks for lifting the upper structure as it is in the existing bridge bearings to seat the upper structure 100 induction.

물론 이때 임시받침(210)은 재활용하게 되고 위치조정수단(400)도 재활용이 하게 된다.Of course, the temporary support 210 is recycled and the position adjustment means 400 is also recycled.

이때 기존 철도교(500)는 전부 또는 일부를 상부구조물로 교체하게 되면 이도 역시 열차통행에 방해가 되지 않는 시간적, 공간적 범위에서 진행하면 된다.At this time, if the existing railway bridge 500 is replaced with all or part of the upper structure, this also has to proceed in a time and space range that does not interfere with the passage of the train.

이에 도 4e와 같이 새로운 유도상 상부구조물(100) 설치가 완료되면 가설벤트(200)를 다시 원위치로 복귀시키게 되어 유도상 상부구조물(100) 설치를 완료하게 된다.When the new induction phase upper structure 100 is installed as shown in FIG. 4e, the temporary vent 200 is returned to its original position, thereby completing the installation of the induction phase upper structure 100.

이때 가설벤트(200)는 종방향으로 이동시켜 추가로 유도상 상부구조물(100) 교체작업을 실시할 수 있으며 한꺼번에 상부구조물 전체를 교체할 경우에는 가설벤트와 횡방향 레일을 철거하여 현장 작업을 마무리 하게 된다.At this time, the temporary vent 200 may be moved in the longitudinal direction to perform additional induction upper structure 100 replacement work, and in the case of replacing the entire upper structure at once, remove the temporary vent and transverse rails to finish the field work. Done.

이로서 도 5와 같이 종방향 및 횡방향으로 다수의 상부구조물이 모두 설치되면 철로를 서로 연결시켜 열차통행이 가능하도록 하고 자갈도상은 이미 완료된 상태이므로 추가 작업은 필요 없게 됨을 알 수 있다.Thus, when a plurality of upper structures are installed in the longitudinal and transverse directions as shown in FIG. 5, the trains can be connected by connecting the rails to each other, and the gravel phase is already completed, and thus no additional work is required.

100: 유도상 상부구조물 110: 몸통부
120: 상부플랜지 130: 횡방향 긴장재
150: 침목 160: 철로
170: 자갈 200: 가설벤트
210: 지지수단 220: 롤러
300: 레일 400: 위치조정수단
410: 슬라이딩패드 420: 위치제어수단
421: 유압잭 422: 하우징
423: 유압실린더 500: 기존 무도상 교량
100: induction upper structure 110: body portion
120: upper flange 130: transverse tension material
150: sleeper 160: railroad
170: Gravel 200: Temporary Vent
210: support means 220: roller
300: rail 400: position adjusting means
410: sliding pad 420: position control means
421: hydraulic jack 422: housing
423: hydraulic cylinder 500: conventional ballless bridge

Claims (4)

(a)교대, 교각에 설치된 무도상 교량(500)의 측방에 횡방향 레일(300)을 설치하는 단계; (b)하부에 롤러(220)가 형성되어 상기 횡방향 레일(300)을 따라 직접 이동하도록 가설벤트(200)를 횡방향 레일에 설치하는 단계; (c)상기 가설벤트(200) 상면에서 유도상 상부구조물(100)을 조립하여 완성시키는 단계; (d)상기 무도상 교량(500)을 제거하고 유도상 상부구조물(100)이 상면에 설치된 가설벤트(200)를 횡방향레일(300)을 따라 이동시켜 무도상 철도교(500)가 설치된 위치에 안착시키는 단계; 및 (e)상기 가설벤트(200)를 횡방향 레일(300)을 따라 복귀시키는 단계를 포함하며,
상기 (d)단계는, 가설벤트(200) 상면에 슬라이딩패드(410)를 고정 설치하고, 상기 슬라이딩패드 상면에서 슬라이딩 되도록 유도상 상부구조물(100)이 상면에 설치된 지지수단(210)을 설치하고, 상기 지지수단(210)에 유압잭을 포함하는 위치제어수단(420)을 연결하여 상기 위치제어수단(420)의 작동에 의하여 지지수단(210)이 슬라이딩패드(410) 상면에서 슬라이딩 되면서 유도상 상부구조물(100)의 위치를 조정할 수 있도록 하며,
상기 지지수단(210)은 상부구조물 인상용 잭을 이용하고, 상기 위치제어수단(420)은 하우징(422)에 장착된 유압잭(421) 및 유압실린더(423)를 포함하여 구성되도록 하고, 상기 유압실린더(423)는 지지수단(210)의 측면에 연결되어 유압실린더(423)의 작동에 의하여 상부구조물이 지지된 지지수단(210)을 슬라이딩패드(410) 상면에서 원하는 위치로 조정할 수 있도록 하는 것을 특징으로 하는 가설벤트를 이용한 철도교의 유도상화 공법.
(a) shifting, installing a transverse rail 300 on the side of the ballless bridge 500 installed in the piers; (b) installing a temporary vent (200) on the transverse rail such that a roller (220) is formed at the bottom to move directly along the transverse rail (300); (c) assembling and completing the induction upper structure 100 on the upper surface of the temporary vent 200; (d) removing the ballless bridge 500 and moving the temporary tent 200 installed on the induction upper structure 100 along the transverse rail 300 to the position where the ballless railway bridge 500 is installed. Seating; And (e) returning the temporary vent 200 along the transverse rail 300.
In the step (d), the sliding pad 410 is fixedly installed on the upper surface of the temporary vent 200, and the supporting means 210 is installed on the inductive upper structure 100 on the upper surface so as to slide on the upper surface of the sliding pad. By connecting the position control means 420 including the hydraulic jack to the support means 210, the support means 210 is slid from the upper surface of the sliding pad 410 by the operation of the position control means 420. To adjust the position of the structure 100,
The support means 210 uses an upper structure lifting jack, and the position control means 420 is configured to include a hydraulic jack 421 and a hydraulic cylinder 423 mounted on the housing 422, the hydraulic pressure The cylinder 423 is connected to the side of the support means 210 to adjust the support means 210, the upper structure is supported by the operation of the hydraulic cylinder 423 to the desired position on the upper surface of the sliding pad 410 Induction virtualization method of railway bridge using temporary vents.
제 1항에 있어서, 상기 (c)단계는
상기 유도상 상부구조물(100)은 세그먼트 상부구조물을 현장에 반입하는 단계;
상기 세그먼트 상부구조물을 가설벤트(200) 상면에 적치하는 단계;
상기 세그먼트 상부구조물을 횡방향으로 조립하여 상부구조물을 완성시키는 단계; 및
상기 완성된 상부구조물을 유도상화 시키는 단계;를 포함하는 것을 특징으로 하는 가설벤트를 이용한 철도교의 유도상화 공법.
The method of claim 1, wherein step (c)
The inductive superstructure 100 is a step of bringing the segment superstructure into the field;
Placing the segment superstructure on an upper surface of the temporary vent 200;
Assembling the segment upper structure laterally to complete the upper structure; And
Induction phase engineering method of a railway bridge using a temporary construction, characterized in that it comprises a; inducing phase of the completed upper structure.
삭제delete 제 2항에 있어서,
상기 세그먼트 상부구조물은 내부에 EPS(111)가 매립된 몸통부(110)와 상부플랜지(120)를 포함하여 형성된 중공박스 구조물로 제작되도록 상기 몸통부(110)에는 횡방향으로 관통공(112)이 형성되어 있어 횡방향 긴장재(130)에 의하여 서로 일체화되도록 제작되도록 하되, 상기 몸통부(110) 상면에는 침목(150)과 철로(160)가 설치되고 자갈(170)이 포설되어 세그먼트 상부구조물의 조립과 유도상화가 가설벤트 상면에서 이루지도록 하는 것을 특징으로 하는 가설벤트를 이용한 철도교의 유도상화 공법.
The method of claim 2,
The segment upper structure is a through-hole 112 in the transverse direction so that the body portion 110 is made of a hollow box structure formed by including the body portion 110 and the upper flange 120 embedded in the EPS (111) therein. Is formed to be made to be integrated with each other by the transverse tension member 130, the upper surface of the body portion 110, the sleeper 150 and the railroad line 160 is installed and the gravel 170 is installed in the segment upper structure of Induction virtualization method of a railway bridge using a temporary vent, characterized in that the assembly and induction ignition on the upper surface of the temporary vent.
KR1020120060034A 2012-06-04 2012-06-04 Bridge railway ballasting construction method using temporary bent KR101250486B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020120060034A KR101250486B1 (en) 2012-06-04 2012-06-04 Bridge railway ballasting construction method using temporary bent

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020120060034A KR101250486B1 (en) 2012-06-04 2012-06-04 Bridge railway ballasting construction method using temporary bent

Publications (1)

Publication Number Publication Date
KR101250486B1 true KR101250486B1 (en) 2013-04-03

Family

ID=48442292

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020120060034A KR101250486B1 (en) 2012-06-04 2012-06-04 Bridge railway ballasting construction method using temporary bent

Country Status (1)

Country Link
KR (1) KR101250486B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101372842B1 (en) * 2013-08-20 2014-04-01 주식회사 인터컨스텍 Apparatus for repairing ballasting rail bridge using double chain driving, and method for the same
KR102275469B1 (en) 2020-09-17 2021-07-12 코벡 주식회사 Temporary bents for a railway catenary and construction methods thereof
KR102275474B1 (en) 2020-09-17 2021-07-12 코벡 주식회사 Construction method of structures on tramway catenary

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101071115B1 (en) * 2008-09-23 2011-10-10 삼표이앤씨 주식회사 Shoe construction method for prefabricated prestressed girder and prefabricated prestressed girder bridge construction method
KR101105005B1 (en) * 2009-03-06 2012-01-16 장신찬 Replacement construction method using new bridge having traverse beam
KR101120466B1 (en) * 2011-08-22 2012-02-29 (주)평화엔지니어링 Lifting apparatus and structure construction method using the same

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101071115B1 (en) * 2008-09-23 2011-10-10 삼표이앤씨 주식회사 Shoe construction method for prefabricated prestressed girder and prefabricated prestressed girder bridge construction method
KR101105005B1 (en) * 2009-03-06 2012-01-16 장신찬 Replacement construction method using new bridge having traverse beam
KR101120466B1 (en) * 2011-08-22 2012-02-29 (주)평화엔지니어링 Lifting apparatus and structure construction method using the same

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101372842B1 (en) * 2013-08-20 2014-04-01 주식회사 인터컨스텍 Apparatus for repairing ballasting rail bridge using double chain driving, and method for the same
KR102275469B1 (en) 2020-09-17 2021-07-12 코벡 주식회사 Temporary bents for a railway catenary and construction methods thereof
KR102275474B1 (en) 2020-09-17 2021-07-12 코벡 주식회사 Construction method of structures on tramway catenary

Similar Documents

Publication Publication Date Title
CN102979041B (en) Soft overhead reinforcing jacking method for construction of span box bridge of jacking block of underpass turnout group of railway
CN102653931B (en) Elastic supporting vibration isolation member ballast bed
KR100757958B1 (en) Insert reclamation apparatus for construction of linear induction motor panel in linear induction motor
KR100891961B1 (en) The construction infrastructure the use road the martial art as a matter of bridge of the bridge which is old in the railroad or the railroad respects the induction event a method of construction which shifts the bridge and the system
KR100863734B1 (en) Guide way structure for magnetic levitation train
KR100692952B1 (en) Railroad crane and method for carrying out replacement of an upper structure of a railway bridge utilizing the same
KR101250486B1 (en) Bridge railway ballasting construction method using temporary bent
KR100556219B1 (en) A method for changing plate-girder bridge of railway bridge into slab bridge by using temporary construction bents.
KR100454406B1 (en) Method and apparatus for changing steel bridge of supporting rail into concrete bridge using temporary bent
KR100454405B1 (en) Method for changing steel bridge of supporting rail into concreat bridge
KR100664996B1 (en) Old and new bridge superstructure urgent exchange equipment and a method
JP6374353B2 (en) How to build a bridge
CN102659027B (en) Variable-span transit method for girder-erecting gantry crane
KR101082418B1 (en) mold apparatus for forming concrete slab of bridge
KR100478701B1 (en) Pulling up, repair and reinforcement method for the upper structure of a bridge
CN112211112A (en) Steel box girder installation method adopting double-guide-girder erection machine on existing bridge
KR100881598B1 (en) Method for construction of track for linear induction motor panel in linear induction motor
KR20020082728A (en) Process and frame for substituting steel girder of a railway bridge for concrete slab
CN202298390U (en) Ballastless track rush repair device
KR100907141B1 (en) Mobile crane installation structure and method for replacing an upper structure of a railway bridge using the same
KR101372842B1 (en) Apparatus for repairing ballasting rail bridge using double chain driving, and method for the same
KR100638578B1 (en) Method for carrying out replacement of an upper structure of a railway bridge
CN104164838A (en) Light combined type beam moving trolley
CN209177871U (en) Platform structure for memorial archway continuously hoisting
KR101653559B1 (en) Method of repairing railway

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20160329

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20190305

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20200218

Year of fee payment: 8