KR101104298B1 - Through bridge construction method by side beam and slab by box structure without lateral prestressing - Google Patents

Through bridge construction method by side beam and slab by box structure without lateral prestressing Download PDF

Info

Publication number
KR101104298B1
KR101104298B1 KR1020110002700A KR20110002700A KR101104298B1 KR 101104298 B1 KR101104298 B1 KR 101104298B1 KR 1020110002700 A KR1020110002700 A KR 1020110002700A KR 20110002700 A KR20110002700 A KR 20110002700A KR 101104298 B1 KR101104298 B1 KR 101104298B1
Authority
KR
South Korea
Prior art keywords
slab
bridge
concrete
longitudinal
support
Prior art date
Application number
KR1020110002700A
Other languages
Korean (ko)
Inventor
김성재
정택술
엄기하
민태영
이진호
Original Assignee
브릿지테크놀러지(주)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 브릿지테크놀러지(주) filed Critical 브릿지테크놀러지(주)
Priority to KR1020110002700A priority Critical patent/KR101104298B1/en
Application granted granted Critical
Publication of KR101104298B1 publication Critical patent/KR101104298B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

PURPOSE: A construction method of a through bridge formed by integrating a side beam and a slab without horizontal strain is provided to reduce construction time by integrating side a slab with side beams through filling concrete. CONSTITUTION: A construction method of a through bridge formed by integrating a side beam and a slab without horizontal strain is as follows. Bridge lower structures(200) having abutments and piers(210) are installed in a longitudinal direction. Beams are connected between the top surfaces of the bridge lower structures using a lifting device. Each beam comprises a hollow box-shaped body(111) and a lower support(112). Side beams(110) are installed in both sides of the top surface of the bridge lower structures. Slabs(120) are formed between the top surface of the bridge lower structures and are integrated with the side beams.

Description

횡방향 긴장없이 중공박스체로 제작되는 측면빔과 슬래브를 일체화시켜 시공되는 하로교 시공방법{THROUGH BRIDGE CONSTRUCTION METHOD BY SIDE BEAM AND SLAB BY BOX STRUCTURE WITHOUT LATERAL PRESTRESSING}THROUGH BRIDGE CONSTRUCTION METHOD BY SIDE BEAM AND SLAB BY BOX STRUCTURE WITHOUT LATERAL PRESTRESSING}

본 발명은 횡방향 긴장없이 중공박스체로 제작되는 측면빔과 슬래브를 일체화시켜 시공되는 하로교 시공방법에 관한 것이다. 더욱 구체적으로 슬래브가 양 측면빔 내측 하부에 위치하도록 한 하로교 시공방법에 관한 것으로서 가시설 시스템을 이용하지 않고서도 하로교를 시공할 수 있도록 하되 슬래브와 양 측면빔을 일체화시키기 위한 횡방향 긴장재를 사용하지 않으면서 횡방향 폭을 크게 연장시킬 수 있는 횡방향 긴장없이 중공박스체로 제작되는 측면빔과 슬래브를 일체화시켜 시공되는 하로교 시공방법에 관한 것이다.The present invention relates to a construction method of a bridge construction that is constructed by integrating the side beam and the slab made of a hollow box body without transverse tension. More specifically, it relates to the construction method of the bridge construction in which the slab is located at the lower side of both side beams, so that the construction of the bridge construction can be carried out without using the provisional system, but without using the transverse tension material for integrating the slab and the side beams. It relates to a construction method of a bridge construction that is constructed by integrating the side beam and the slab made of a hollow box body without lateral tension that can greatly extend the width in the lateral direction.

하로교(THROUGH BRIDGE)는 슬래브의 위치에 따른 교량형식이다.THROUGH BRIDGE is a bridge type depending on the position of the slab.

즉 하로교는 슬래브(노면)가 종방향 거더 하부에 위치되도록 한 교량이다.In other words, the bridge is a bridge in which the slab (surface) is positioned below the longitudinal girder.

이러한 하로교 방식으로 최근 적용된 교량이 경전철 시공에 사용된 바 있는 UCB(U-TYPE CHANNEL BRIDGE, 채널브리지)이다.The bridge that has been recently applied in this way is the UCB (U-TYPE CHANNEL BRIDGE, channel bridge) that has been used for light rail construction.

도 1a는 상기 하로교인 채널브리지(10,UCB)와 PSC 거더교(20)의 시공단면도를 비교 도시한 것인데, PSC 거더교 보다 형고가 낮아 주행 중 시야확보에 유리하고, 슬래브 접속구간의 토공량 감소에 의하여 시공성 및 공사비가 절감될 수 있다는 장점이 있다.Figure 1a is a cross-sectional view of the construction cross-section of the channel bridge (10, UCB) and the PSC girder bridge (20), which is lower than the PSC girder bridge is advantageous for securing visibility during driving, by reducing the earthwork volume of the slab connection section There is an advantage that the workability and construction cost can be reduced.

이러한 채널브리지의 종래 시공방법으로서 채널브리지용 U형 세그먼트를 풀-스테이징 방법으로 설치할 수 있는데 이럴 경우 동바리와 같은 가시설 시스템을 반드시 설치해야 하므로 현장여건상 이를 설치할 수 없는 경우도 있고, 가시설 시스템의 시공비가 너무 큰 비중을 차지하는 경우가 많았다.As a conventional construction method of such a channel bridge, a U-segment for channel bridge can be installed by a full-stage method. In this case, a temporary facility such as a copper bar must be installed. Often accounted for too much.

이에 도 1b와 같이 교량 상부에서 U형 세그먼트(10)를 교량 진행방향으로 런칭시스템(30)을 이용하여 시공하는 방법이 소개되어 있다.Thus, as shown in FIG. 1B, a method of constructing the U-shaped segment 10 using the launching system 30 in the bridge traveling direction is introduced.

하지만 이러한 런칭시스템은 채널브리지용 U형 세그먼트(10)를 제작하여 교각 및 교대 상부로 인양하는 작업을 반복하여 종방향으로 서로를 연결시키는 방식으로 운영하다보니 고가의 런칭시스템(30)에 문제가 발생할 경우 달리 공사를 진행할 수 없어 공사가 중단될 수 밖에 없다는 문제점이 있었다.However, such a launching system has a problem in the expensive launching system 30 because the U-shaped segment 10 for the channel bridge is manufactured and operated by repeatedly connecting the bridges in the longitudinal direction by lifting the bridges and the upper portions of the shifts. In case of occurrence, there was a problem that construction could be stopped because other construction could not proceed.

도 1c는 다른 종래 하로교 시공방법을 도시한 것인데, 먼저 교각과 같은 교량 하부구조(50) 사이에 ㄱ자형 가설프레임(60)을 설치하고, 상기 ㄱ자형 가설프레임(60)에 얹어지도록 U형 프리캐스트 세그먼트(70)를 설치한 후, 도 1d와 같이 종방향으로 배치된 긴장재(72)에 의하여 프리캐스트 세그먼트(70)를 서로 압착 연결시키는 방법이 소개되어 있다.Figure 1c shows another conventional Haro bridge construction method, first to install the U-shaped temporary frame 60 between the bridge substructure 50, such as a bridge, U-shaped free to be mounted on the U-shaped temporary frame 60 After installing the cast segment 70, a method of press-bonding the precast segments 70 to each other by a tension member 72 arranged in the longitudinal direction as shown in FIG. 1D is introduced.

이때 상기 U형 프리캐스트 세그먼트(70)는 도 1e와 같이 슬래브(71)에 횡방향으로 긴장재(73)에 의하여 미리 프리스트레스가 도입되도록 한 것을 이용하게 되는데 이는 슬래브(71)의 폭에 따른 강성을 증진시키기 위한 것이고, U형 프리캐스트 세그먼트(70)의 시공과는 달리 상관이 없음을 알 수 있다.At this time, the U-shaped precast segment 70 is to use the pre-stress is introduced in advance by the tension member 73 in the transverse direction to the slab 71 as shown in Figure 1e, which is the rigidity according to the width of the slab 71 It is intended to enhance, and it can be seen that there is no correlation unlike the construction of the U-shaped precast segment 70.

하지만, 이러한 하로교 시공방법도 ㄱ자형 가설프레임(60)을 설치해야 하는 등 가시설 설치를 위한 노력과 비용이 요구되기 때문에 하로교 시공에 있어 보다 간단하면서도 구조적으로도 안정적인 하로교 시공방법 개발에 대한 필요성이 요구되었다.However, such a method of construction of the bridge construction requires the effort and cost for installing the temporary facilities, such as the installation of the L-shaped temporary frame 60. Therefore, there is a need for a more simple and structurally stable construction of the construction bridge construction method for the construction of the bridge construction. It became.

도 1e는 다른 종래 하로교의 제작방법을 도시한 것인데, 특히 프리플렉스 빔(40)을 제작하되, 하부플랜지 콘크리트(41) 각 내측면 하부에 수평으로 돌출된 돌출부(42)를 형성시키고, 상기 돌출부(42)에 프리캐스트 콘크리트 슬래브(50)가 얹어지도록 설치한 다음,FIG. 1E illustrates another conventional method of manufacturing a bridge, in particular, a preflex beam 40 is fabricated, and a protrusion 42 is formed horizontally protruding from the lower inner surface of each lower flange concrete 41, and the protrusion is formed. (42) is installed so that the precast concrete slab 50 is mounted,

상기 프리캐스트 콘크리트 슬래브(50)와 프리플렉스 빔(40)은 돌출철근(43,44)들에 의하여 서로 연결되도록 하고, 상기 돌출철근(43,44)이 연결되는 부위를 콘크리트(45)로 마감하도록 하로교를 제작하는 방법이 소개되어 있다.The precast concrete slab 50 and the preflex beam 40 are connected to each other by the protruding reinforcement (43,44), and finish the portion where the protruding reinforcement (43,44) is connected with concrete 45 How to make Haro Bridge is introduced.

이러한 하로교 제작은 종래 종방향으로 서로 연결되는 프리캐스트 방식의 U형 세그먼트(10)를 제작하는 방식과는 차별화되지만 상기 돌출부(42)에 슬래브의 자중 및 활하중이 작용할 경우 자칫 구조적으로 취약할 수 밖에 없었다.This bridge construction is different from the conventional method of manufacturing a precast U-shaped segment 10 connected to each other in the longitudinal direction, but when the self-weight and live load of the slab acts on the protrusions 42, they are structurally weak. There was no.

나아가, 상기 도 1e에 의한 하로교는 프리플렉스 빔(40)과 슬래브(50)를 이용하는 방식인데, 횡방향 폭을 충분히 확보하기 위하여 슬래브(50)에 횡방향 긴장재에 의하여 프리스트레스를 도입시키는 방식을 채택하고 있음을 알 수 있다.In addition, the haro bridge according to FIG. 1E uses a preflex beam 40 and a slab 50, and adopts a method of introducing a prestress to the slab 50 by a transverse tension member in order to sufficiently secure the transverse width. It can be seen that.

하지만 이러한 방식은 프리플렉스 빔(40)의 양 외측면에서 횡방향 긴장재를 긴장 및 정착시키는 작업공간이 부족하여 가설장치를 설치해야 하는 등 시공성 및 작업성이 떨어질 수 밖에 없었고, 프리플렉스 빔을 사용하다 보니 아무래도 공사비가 증가될 수 밖에 없었으며 슬래브(50)의 자중이 클 수 밖에 없어 역시 횡방향 폭을 충분히 확보하기에 부족함이 있을 수 밖에 없었다.However, this method is inferior in workability and workability, such as the need to install a temporary device due to the lack of a work space for tensioning and fixing the transverse tension material on both outer surfaces of the preflex beam 40, using a preflex beam As a result, the construction cost was inevitably increased, and because the weight of the slab 50 was large, there was also a shortage of sufficient width to secure the transverse width.

이에 본 발명은 하로교를 시공함에 있어 중량이 크지 않으면서도 하로교를 구성하는 양 측면빔과 슬래브를 서로 효과적으로 일체화시킬 수 있도록 하면서도, 특히 횡방향으로 양 측면빔과 슬래브를 횡방향 긴장재에 의하여 일체화시키지 않도록 할 수 있는 하로교 시공방법 제공을 그 해결하고자 하는 기술적 과제로 한다.Accordingly, the present invention enables to effectively integrate both side beams and slabs constituting the halo bridge with each other, while not having a large weight in the construction of the haro bridge, and in particular, so as not to integrate the both side beams and the slab in the transverse direction by the transverse tension member. Provision of the construction method of the Haro bridge can be made a technical problem to be solved.

이에 본 발명은The present invention

교대, 교각을 포함하는 교량 하부구조)를 종방향으로 설치하는 단계;Alternating, longitudinally installing bridge substructures including piers;

중공 사각박스체 형태의 몸통부와 상기 몸통부 하부 내측면에 일체로 돌출되어 형성된 하부지지체를 포함하는 빔으로서 양중장치를 이용하여 상기 교량 하부구조의 상면 사이에 1경간씩 종방향으로 거치시켜 연결시키되, 횡방향으로 이격되도록 양 측면빔을 설치하는 단계; 및Hollow rectangular box-shaped body portion and a beam including a lower support formed integrally protruding on the lower inner surface of the body portion by using a lifting device in the longitudinal direction between the upper surface of the bridge substructure by one longitudinal connection Installing both side beams so as to be spaced apart in the transverse direction; And

상기 양 측면빔의 하부지지체 상면 사이에 횡방향으로 슬래브를 형성시켜 양 측면빔과 일체화시키는 단계를 포함하되,Including a slab in the transverse direction between the upper surface of the lower support of the both side beams to integrate with both side beams,

상기 교량 하부구조의 지점부(A)에 위치한 양 측면빔의 종방향 연결부위에는 횡방향으로 현장타설콘크리트를 타설에 의한 지점부콘크리트로 형성시키고, 상기 지점부콘크리트와 상기 슬래브)는 종방향 긴장재에 의하여 서로 압착되어 일체화되도록 하되,Longitudinal concrete is formed on the longitudinal connection of both side beams located at the point A of the bridge substructure with point concrete by casting, and the point concrete and the slab are longitudinal tension members. To be integrated with each other by pressing,

상기 슬래브는 횡방향으로 연장된 경량 중공박스체를 종방향으로 서로 연결시킨 것을 이용하도록 하며, 양 단부 저면이 양 측면빔의 하부지지체 상면에 고무패드를 포함하는 받침에 지지되도록 한 상태에서 양 단부면과 양 측면빔의 몸통부 내측면 사이 공간에는 채움콘크리트가 타설되어 슬래브가 양 측면빔 및 지점부콘크리트와 일체화 되도록 하는 횡방향 긴장없이 중공박스체로 제작되는 측면빔과 슬래브를 일체화시켜 시공되는 하로교 시공방법을 제공한다.The slab is connected to each other in the longitudinal direction of the lightweight hollow box body extending in the lateral direction, both ends in the state that the bottom of both ends is supported by the support including the rubber pad on the upper surface of the lower support of both side beams Filling concrete is placed in the space between the side surface and the inner side of the trunk of both side beams, which is constructed by integrating the side beam and the slab made of hollow box without transverse tension to make the slab integrate with both side beams and the branch concrete. Provide construction method.

말하자면 본 발명은 하로교에 있어 슬래브가 양 측면빔에 단순지지되도록 하고, 채움콘크리트에 의하여 슬래브와 측면빔이 서로 일체화되도록 하게 된다. 이에 기본적으로 슬래브와 측면빔은 서로 힌지연결로 연결되도록 함을 알 수 있다.In other words, in the present invention, the slab is simply supported on both side beams in the bridge, and the slab and the side beams are integrated with each other by filling concrete. Basically, it can be seen that the slab and the side beams are connected to each other by hinged connections.

또한 바람직하게는 상기 양 측면빔은Also preferably the both side beams

EPS 블록이 매립된 사각박스체 형태로 제작된 것으로서 하부에는 길이방향으로 종방향 긴장재가 형성되도록 하여 프리스트레스가 도입되도록 제작된 몸통부; 및 상기 몸통부의 하부 내측면에는 사각박스체 형태로 돌출형성되며 슬래브의 자중을 지지할 수 있도는 단면높이를 가진 하부지지체;를 포함하도록 제작하되,A body part which is manufactured in the form of a rectangular box body in which an EPS block is embedded, and a lower part of which is formed in the longitudinal direction so that a longitudinal tension member is formed and a prestress is introduced; And a lower support having a cross-sectional height formed on the lower inner surface of the body to protrude in the form of a rectangular box and support the weight of the slab.

상기 하부지지체 상부의 몸통부 내측면에는 횡방향으로 수평연장되어 하방으로 절곡되면서 하부지지체 상면에 하단이 고정되는 ㄱ자형 연결철근가 형성된 것이 이용되도록 하는 횡방향 긴장없이 중공박스체로 제작되는 측면빔과 슬래브를 일체화시켜 시공되는 하로교 시공방법을 제공한다.Side beam and slab made of hollow box body without lateral tension, so that the inner side of the upper part of the lower support is horizontally extended in the horizontal direction and bent downward while the L-shaped connecting reinforcing bar is fixed to the upper surface of the lower support. Provides the construction method of the bridge construction to be integrated.

또한 바람직하게는Also preferably

상기 슬래브는The slab is

EPS 블록이 길이방향으로 매립되며 종방향으로 종방향 긴장재가 삽입되도록 길이방향의 직각방향으로 종방향 홀이 형성된 중공 박스체 구조물인 몸통부; 및 상기 몸통부의 하부 외측면에 돌출된 형성된 지지부로써 인접한 슬래브의 하부돌출지지부 상면 사이에 설치된 마감판이 지지되도록 형성된 하부돌출지지부;를 포함하도록 제작된 것이 이용되도록 하는 횡방향 긴장없이 중공박스체로 제작되는 측면빔과 슬래브를 일체화시켜 시공되는 하로교 시공방법을 제공한다.A body part which is a hollow box structure having a longitudinal hole in a longitudinal direction in which the EPS block is embedded in the longitudinal direction and a longitudinal tension member is inserted in the longitudinal direction; And a lower protrusion support part formed to support a closing plate installed between the lower protrusion support parts of adjacent slabs as a formed support part protruding from the lower outer surface of the body part. Provides a construction method of the bridge bridge that is constructed by integrating the side beam and the slab.

또한 바람직하게는Also preferably

상기 마감판이 설치된 인접한 슬래브의 종방향 이격공간에는 무수축콘크리트가 충전되어 슬래브가 종방향으로 서로 일체화되도록 하는 횡방향 긴장없이 중공박스체로 제작되는 측면빔과 슬래브를 일체화시켜 시공되는 하로교 시공방법을 제공한다.The longitudinal separation space of the adjacent slab in which the finishing plate is installed is filled with non-contraction concrete to provide a construction method by which the side beam made of a hollow box body and the slab are integrally constructed without the transverse tension so that the slab is integrated with each other in the longitudinal direction. do.

또한 바람직하게는Also preferably

상기 슬래브의 단부면에는 횡방향으로 수평연장되어 하방으로 절곡되면서 다사 슬래브의 단부면으로 연장되어 고정된 ㄷ 자형 연결철근이 더 형성되어 양 측면빔의 ㄱ자형 연결철근과 서로 겹쳐지도록 한 상태에서 채움부 종방향철근이 겹쳐진 양 연결철근을 종방향으로 관통하도록 하여 상기 연결철근들과 채움부 종방향철근이 채움콘크리트에 의하여 매립되도록 하는 하로교 시공방법을 제공한다.An end surface of the slab is horizontally extended to be bent downwards and further formed with a c-shaped connecting rebar extending and fixed to the end surface of the multi-slab slab so as to overlap each other with the L-shaped connecting bars of both side beams. Provides a method of construction of a bridgeway so that the secondary reinforcing bars penetrate the overlapping connecting bars in the longitudinal direction so that the connecting bars and the filling section longitudinal reinforcing bars are filled by the filling concrete.

이러한 연결철근들은 슬래브와의 충분히 일체성 확보를 위한 것이라 할 수 있으며, ㄱ자형 연결철근에 의하여 채움부(B)에 있어 작용하는 수직력을 효과적으로 저항하도록 하면서 채움부 종방향 철근에 의한 채움부의 종방향 보강이 가능하게 된다.These connecting reinforcing bars can be said to ensure sufficient integrity with the slab, and the longitudinal direction of the filling part by the longitudinal longitudinal reinforcing bars while effectively resisting the vertical force acting on the filling part (B) by the L-shaped connecting bars. Reinforcement becomes possible.

또한 바람직하게는Also preferably

상기 받침 주위에는 무수축콘크리트에 의한 지지부를 더 형성시켜 받침과 상기 지지부에 작용하는 슬래브 하중이 양 측면빔에 분산 전달되도록 하는 횡방향 긴장없이 중공박스체로 제작되는 측면빔과 슬래브를 일체화시켜 시공되는 하로교 시공방법을 제공한다.The side beam and the slab, which are made of a hollow box body without a lateral tension to allow the slab load acting on the support and the support portion to be distributed and transmitted to both side beams by further forming a support part by non-concrete concrete around the support part, are constructed. Provide the construction method of Haro Bridge.

본 발명에 의한 하로교는 공장에서 미리 양 측면빔과 슬래브가 프리캐스트 제품으로 생상되기 때문에 품질관리에 유리하고,Haro bridge according to the present invention is advantageous in quality control because both side beams and slabs are produced in advance as a precast product in the factory,

1 스판을 한꺼번에 설치함에도 2개의 측면빔을 먼저 설치하고, 측면빔 사이에 슬래브를 따로 설치하는 방식으로 시공하기 때문에 공장에서 제작된 측면빔과 슬래브를 운반 및 시공에 있어 대형 중장비가 동원될 필요도 없으며, 고가의 가설시스템 또는 런칭시스템을 이용하지 않기 때문에 매우 경제적이고,1 Even though the span is installed at the same time, two side beams are installed first, and the slabs are installed separately between the side beams, so that large heavy equipment needs to be mobilized in the transportation and construction of the factory-made side beams and slabs. It is very economical because it does not use expensive construction system or launching system.

측면빔 및 슬래브는 공장에서 현장까지 운반함에 있어어도 종래 교량용 거더와 마찬가지로 운반 및 거치할 수 있기 때문에 작업의 효율성을 증진시킬 수 있으며, 슬래브가 측면빔의 하부플랜지에 얹어지도록 설치함으로서 구조적으로 안정적인 시공이 가능하며,Side beams and slabs can be transported and mounted like a conventional bridge girders even when transporting from the factory to the site, thereby increasing work efficiency. The slab is mounted on the lower flange of the side beams to provide structural stability. Construction is possible,

또한, 종래 하로교는 그 횡방향 폭이 제한적일 수 밖에 없었으나 본 발명에 의한 하로교는 중량이 크지 않도록 제작하기 때문에 시공성이 매우 뛰어날 뿐만 아니라, 슬래브의 양 단부를 측면빔에 단순 지지되도록 설치하고, 채움 콘크리트에 의하여 측면빔과 슬래브를 일체화시키기 때문에 횡방향긴장재의 작업공종이 배제되어 전체적인 시공공기를 단축할 수 있게 된다.In addition, the conventional haro bridge had a limited width in the lateral direction, but the haro bridge according to the present invention is excellent in workability because it is manufactured so that the weight is not large, and is installed and filled so that both ends of the slab are simply supported by the side beams. Since the side beam and the slab are integrated by the concrete, the construction work of the transverse tensioning material is excluded, and thus the overall construction air can be shortened.

또한 종래 하로교와는 달리 지점부에 있어서는 현장타설에 의한 지점부콘크리트에 의하여 지점부를 형성시키고, 상기 지점부콘크리트에 슬래브를 종방향으로 일체화시키기 때문에 슬래브에 작용하는 하중이 양 측면빔과 교량 하부구조에 효율적으로 분산시킬 수 있어 구조적으로 매우 효율적인 하로교 시공이 가능하게 된다.In addition, unlike the conventional Haro bridge, in the point portion, the point portion is formed by the point concrete by spot casting, and the slab is vertically integrated with the point concrete so that the load acting on the slab is applied to both side beams and the bridge substructure. It can be efficiently dispersed in the structure, it is possible to construct a very efficient bridge construction.

본 발명의 범위는 상기 상세한 설명보다는 후술하는 특허청구범위에 의하여 나타내어지며, 특허청구범위의 의미 및 범위 그리고 그 균등 개념으로부터 도출되는 모든 변경 또는 변형된 형태가 본 발명의 범위에 포함되는 것으로 해석되어야 한다.The scope of the present invention is shown by the following claims rather than the above description, and all changes or modifications derived from the meaning and scope of the claims and their equivalents should be construed as being included in the scope of the present invention. do.

도 1a는 하로교 및 PSC 거더교의 비교단면도이며,
도 1b는 종래 채널브리지(UCB)의 가시설 시스템을 이용한 시공사진이며,
도 1c는 종래 하로교용 U형 프리캐스트 세그먼트의 시공사시도이며,
도 1d는 종래 도 1c에 의한 하로교용 U형 프리캐스트 세그먼트의 사시도이며,
도 1e는 종래 프리플렉스 빔과 슬래브를 이용한 하로교 제작단면도이며,
도 2a 및 도 2b는 본 발명에 의한 하로교의 구성도들,
도 3a, 도 3b, 도 3c 및 도 3d는 본 발명의 하로교 시공순서도이다.
Figure 1a is a cross-sectional comparison of the Haro Bridge and PSC girder bridge,
Figure 1b is a construction photograph using the provisional system of the conventional channel bridge (UCB),
1C is a constructional view of a conventional U-shaped precast segment for a downhill bridge,
1D is a perspective view of a U-shaped precast segment for a downlink according to the conventional FIG. 1C,
FIG. 1E is a cross-sectional view of the fabrication of a halo bridge using a conventional preflex beam and a slab.
2a and 2b is a schematic view of the halo bridge according to the present invention,
3A, 3B, 3C, and 3D are a flowchart illustrating a construction method of the bridge bridge of the present invention.

아래에서는 첨부한 도면을 참조하여 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자가 용이하게 실시할 수 있도록 본 발명의 실시예를 상세히 설명한다. 그러나 본 발명은 여러 가지 상이한 형태로 구현될 수 있으며 여기에서 설명하는 실시예에 한정되지 않는다. 그리고 도면에서 본 발명을 명확하게 설명하기 위해서 설명과 관계없는 부분은 생략하였으며, 명세서 전체를 통하여 유사한 부분에 대해서는 유사한 도면 부호를 붙였다.DETAILED DESCRIPTION Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings so that those skilled in the art may easily implement the present invention. The present invention may, however, be embodied in many different forms and should not be construed as limited to the embodiments set forth herein. In the drawings, parts irrelevant to the description are omitted in order to clearly describe the present invention, and like reference numerals designate like parts throughout the specification.

<본 발명에 의한 하로교의 구성><Configuration of Haro Bridge according to the present invention>

본 발명은 하로교(100)를 양 측면빔(110)과 슬래브(120)를 포함하여 구성되도록 한다.According to the present invention, the bridge 100 is configured to include both side beams 110 and the slab 120.

먼저 도 2a와 같이 양 측면빔(110)을 제작하여야 하는데, 이는 교량용 거더와 형상은 유사하지만 하로교용 측면빔이기 때문에 그 작용과 가능은 상이하다.First, both side beams 110 should be manufactured as shown in FIG.

즉, 하로교에서는 작용하중을 대부분 양 측면빔(110)이 부담하도록 하기 때문에 이러한 측면빔이 단면설계가 매우 중요하다. In other words, since the side beam 110 to bear most of the working load in the Haro Bridge, such a side beam cross section design is very important.

이에 합성빔(도 1e와 같은 프리플렉스 빔)을 이용할 수도 있겠지만 이러한 합성빔은 고가의 강재를 이용하기 때문에 경제성이 떨어지므로 본 발명은 중공 박스체 형태의 프리스트레스트 철근콘크리트로 제작된 측면빔(110)을 이용하게 된다.The composite beam (preflex beam as shown in Figure 1e) may be used, but because the composite beam is inexpensive because it uses expensive steel, the present invention is a side beam 110 made of prestressed reinforced concrete in the form of a hollow box Will be used.

이러한 본 발명의 측면빔(110)은 크게 몸통부(111)와 하부지지체(112)로 크게 구성된다.The side beam 110 of the present invention is largely composed of a body portion 111 and the lower support (112).

먼저, 상기 몸통부(111)는 제작시 거푸집 내부에 EPS 블록(113)이 매립되도록 하여 전체 자중을 크게 줄이도록 하되 횡방향 폭보다 높이가 더 큰 사각박스체 형태로 제작되도록 하며 하부 내부에는 길이(종)방향으로 긴장재(114)가 형성되도록 하여 프리스트레스가 도입되도록 제작된다.First, the body portion 111 is to be embedded in the formwork during the EPS block 113 is embedded to reduce the overall weight significantly, but to be produced in the form of a rectangular box body having a height greater than the width in the horizontal direction, the length inside the lower The tension member 114 is formed in the (longitudinal) direction so that the prestress is introduced.

상기 몸통부(111)의 하부 내측면에는 수평방향(횡방향)으로 하부지지체(112)가 역시 사각박스체 형태로 돌출형성되어 있다.On the lower inner surface of the body portion 111, the lower support 112 in the horizontal direction (lateral direction) is also formed in the form of a rectangular box body.

이러한 하부지지체(112)는 상당한 높이(H)를 가지도록 형성시킴을 알 수 있는데 본 발명의 슬래브(120)가 상기 하부지지체(112)의 상면에 지지되도록 설치하기 때문에 본 발명의 하부지지체(112)는 슬래브의 하중에 저항하기 위한 충분한 높이를 가지도록 제작하는 것이 중요하기 때문이다.It can be seen that the lower support 112 is formed to have a significant height (H), because the slab 120 of the present invention is installed to be supported on the upper surface of the lower support 112, the lower support 112 of the present invention. This is because it is important to make) to have a sufficient height to withstand the load of the slab.

또한 상기 하부지지체(112) 상부 공간에는 몸통부(111) 내측면으로부터 돌출 형성된 ㄱ형 연결철근(115)이 배근되도록 하여 후술되는 슬래브(120)의 ㄷ자형 연결철근(126)과 서로 연결되도록 하게 된다.In addition, the a-type connecting reinforcing bar 115 protruding from the inner surface of the body portion 111 is arranged in the upper space of the lower support 112 so as to be connected to the c-shaped connecting reinforcing bar 126 of the slab 120 to be described later. .

상기 ㄱ형 연결철근(115)은 하부지지체(112) 상부의 몸통부(111) 내측면으로부터 횡방향으로 수평연장되어 하방으로 절곡되면서 하부지지체(112) 상면에 하단이 고정되도록 하게 되는데 이는 후술되는 채움부(B)에 있어 작용하는 수직력을 효과적으로 저항하도록 하면서 채움부 종방향철근에 의한 채움부의 종방향 보강이 가능하도록 하는 공간 형성을 위한 것이라 할 수 있다.The a-type connecting reinforcement 115 is horizontally extended from the inner surface of the body portion 111 of the upper portion of the lower support 112 is bent downward so that the lower support is fixed to the upper surface of the lower support 112, which will be described below. In order to effectively resist the vertical force acting on the portion (B) can be said to form a space to enable the longitudinal reinforcement of the filling portion by the filling portion longitudinal reinforcement.

이러한 ㄱ형 연결철근(115)은 후술되는 슬래브(120)의 ㄷ자형 연결철근(126)과 대응하는 위치가 되도록 종방향으로 다수가 이격되도록 형성시키게 된다.The a-type connecting reinforcement 115 is formed to be spaced apart in the longitudinal direction to be a position corresponding to the c-shaped connecting reinforcement 126 of the slab 120 to be described later.

이때 본 발명의 측면빔(110)은 EPS 블록(113)이 차지하는 공간만큼 철근콘크리트가 배제되므로 중량이 현저하게 줄어들게 됨을 알 수 있어 제작, 운반 및 시공에 있어 매우 시공성이 커질 수 있도록 함을 알 수 있다.In this case, the side beam 110 of the present invention can be seen that the weight is significantly reduced because the reinforced concrete is excluded as much as the space occupied by the EPS block 113, so that the construction can be very large in manufacturing, transportation and construction have.

또한 상기 하부지지체(112)의 상면에는 합성고무패드와 같은 받침(116)이 미도시된 앵커볼트에 의하여 고정되도록 하여 슬래브(120)의 양 단부면이 지지되도록 하게 된다.In addition, the support 116, such as a synthetic rubber pad is fixed to the upper surface of the lower support 112 by an anchor bolt not shown so that both end surfaces of the slab 120 is supported.

이러한 측면빔(110)은 미리 공장에서 일정한 단면크기를 가지도록 제작된 프리캐스트 방식의 측면빔으로 제작하여 이를 현장에 운반하여 교량 하부구조(200)에 거치하는 방식으로 시공된다.The side beam 110 is manufactured by a precast side beam made in advance in the factory to have a predetermined cross-sectional size is carried in the field to be mounted in a way that is mounted on the bridge substructure 200.

또한 상기 측면빔(110)은 2개가 서로 좌우대칭으로 배치되도록 한쌍을 제작하고, 이러한 한쌍의 측면빔(110)이 1경간(교각과 교각 사이 또는 교각과 교대 사이)에 해당하는 길이(L)를 가지도록 제작하게 된다.In addition, the side beam 110 is made of a pair so that the two are arranged symmetrically with each other, the length of the pair of side beam 110 corresponding to one span (between pier and piers or between the piers and alternating) (L) Will be produced to have.

이에 교각과 같은 지점부에서는 측면빔(110)이 서로 종방향으로 서로 접하여 서로 연결되도록 하되 이는 후술되는 지점부 콘크리트(230)와 일체화된다. 또한 이러한 지점부 콘크리트(230)는 종방향 긴장재(128)에 의하여 슬래브(120)와 압착 연결된다.In the point portion, such as a piers, the side beams 110 are in contact with each other in the longitudinal direction of each other, but are integrated with the concrete portion 230, which will be described later. In addition, the point concrete 230 is press-connected with the slab 120 by the longitudinal tension member (128).

다음으로 슬래브(120)는 한쌍의 측면빔(110) 내측면 사이에 얹어져 지지되도록 그 횡방향 폭이 정해진 중공 박스체 구조물이다.Next, the slab 120 is a hollow box structure whose transverse width is defined so as to be supported between the inner side surfaces of the pair of side beams 110.

이러한 슬래브(120)도 자중을 감소시키기 위하여 중공박스체 형태로 제작되어 횡방향으로 연장된 경량 중공박스체로서 양 측면빔 사이에 횡방향으로 연장되도록 배치되며, 종방향으로 다수를 인접시켜 설치한 후 서로 종방향으로 연결 설치하게 된다.The slab 120 is also manufactured in the form of a hollow box to reduce its own weight, and is a lightweight hollow box body extending in the lateral direction and is disposed to extend in the lateral direction between both side beams. After that, they are connected to each other in the longitudinal direction.

이에 상기 슬래브(120)는 크게 몸통부(121)와 하부돌출지지부(122)로 크게 구성된다.The slab 120 is largely composed of a body portion 121 and the lower protrusion support portion 122.

상기 몸통부(121)는 역시 제작시 거푸집 내부에 EPS 블록(123)이 매립되도록 하여 전체 자중을 크게 줄이도록 하되 사각박스체 형태로 제작되도록 하게 되며 개략 중앙부에는 길이방향으로 종방향 긴장재(128)가 삽입되도록 종방향 홀(124)가 형성되도록 한다.The body portion 121 is also to be embedded in the formwork during the EPS block 123 is embedded in the form of a rectangular box body to greatly reduce the total weight, but in the longitudinal direction of the longitudinal tension member 128 in the longitudinal direction The longitudinal hole 124 is formed so that it is inserted.

이러한 종방향 홀(124)는 몸통부(121)의 연장방향인 길이방향과 직각으로 횡방향으로 이격 설치되도록 형성시키게 된다.The longitudinal holes 124 are formed to be spaced apart in the transverse direction at right angles to the longitudinal direction, which is the extending direction of the body portion 121.

상기 하부돌출지지부(122)는 몸통부(121)의 하부 외측면에 돌출된 형성된 지지부로써 인접한 슬래브(120)의 하부돌출지지부(122) 상면 사이에 설치된 마감판(125)이 지지되도록 하는 역할을 하도록 하게 된다.The lower protrusion support part 122 serves to support the closing plate 125 installed between the upper bottom protrusion support part 122 surfaces of the adjacent slab 120 as a support part protruding from the lower outer surface of the body part 121. Will be done.

또한 상기 슬래브(120)의 양 단부면에는 돌출 형성된 ㄷ자형 연결철근(126)이 배치되도록 하여 앞서 살펴본 측면빔(110)의 ㄱ자형 연결철근(115)과 서로 연결되도록 하게 된다.In addition, protruding U-shaped connecting bars 126 are formed on both end surfaces of the slab 120 so as to be connected to the L-shaped connecting bars 115 of the side beam 110 described above.

즉, 상기 ㄷ자형 연결철근(126)은 슬래브(120)의 단부면에는 횡방향으로 수평연장되어 하방으로 절곡되면서 다사 슬래브의 단부면으로 연장되어 고정되도록 형성되어 양 측면빔의 ㄱ자형 연결철근(115)과 서로 겹쳐지도록 한 상태에서 채움부 종방향철근(129)가 겹쳐진 양 연결철근(115,126)을 종방향으로 관통하도록 하여 상기 연결철근들과 채움부 종방향철근(129)이 채움콘크리트(220)에 의하여 매립되도록 하게 된다.That is, the U-shaped connecting reinforcing bars 126 are horizontally extended in the end surface of the slab 120 and are bent downward so as to extend and be fixed to the end surfaces of the multi-slab slab, so as to form the L-shaped connecting bars of both side beams ( 115 and the connecting reinforcing bars and the filling section longitudinal reinforcing bars (129) are filled with concrete 220 so as to penetrate both connecting bars (115, 126) overlapping the filling section longitudinal reinforcing bars (129) in the state to overlap with each other By landfill.

역시 본 발명의 슬래브(120)도 EPS 블록(123)이 차지하는 공간만큼 철근콘크리트가 배제되므로 중량이 현저하게 줄어들게 됨을 알 수 있어 제작, 운반 및 시공에 있어 매우 시공성이 커질 수 있도록 함을 알 수 있으며 횡방향 폭을 충분히 확보할 수 있게 됨을 알 수 있다.In addition, since the slab 120 of the present invention also excludes the reinforced concrete as much as the space occupied by the EPS block 123, it can be seen that the weight is significantly reduced, so that the construction can be very large in manufacturing, transportation and construction. It can be seen that the width in the lateral direction can be sufficiently secured.

이러한 슬래브(120)는 측면빔을 구성하는 하부지지체 상면에 설치된 받침(116)에 지지되도록 설치하게 된다.The slab 120 is installed to be supported by the support 116 installed on the upper surface of the lower support constituting the side beam.

또한 도 2b와 같이 상기 슬래브(120)는 현장에 운반하여 종방향으로 서로 인접하도록 설치하는데 종방향으로 인접한 슬래브(120)가 서로 결합될 수 있도록 종방향 긴장재(128)가 각각의 슬래브에 형성된 종방향 홀(124)에 삽입되어 긴장후 슬래브의 전면 및 후면에 정착되도록 하게 된다.Also, as shown in FIG. 2B, the slab 120 is transported to a site and installed to be adjacent to each other in the longitudinal direction. A longitudinal tension member 128 is formed in each slab so that the adjacent slabs 120 in the longitudinal direction may be coupled to each other. It is inserted into the direction hole 124 to be fixed to the front and rear of the slab after tension.

또한 도 2b와 같이 종방향으로 서로 인접한 슬래브(120)의 종방향 이격공간에는 마감판(125) 상부로 무수축콘크리트(127)가 충전되도록 하여 슬래브(120)가 서로 종방향으로 일체화되도록 하게 된다.In addition, the longitudinal space of the slab 120 adjacent to each other in the longitudinal direction as shown in Figure 2b is to be filled with non-concrete concrete 127 to the top of the finishing plate 125 so that the slab 120 is integrated with each other in the longitudinal direction. .

이러한 슬래브(120)는 하로교(100)를 구성할 수 있도록 양 측면빔(110)을 구성하는 하부지지체 상면에 형성되도록 설치되며, 슬래브 상면에는 표장층이 형성되어 통상의 교량용 슬래브로 기능하게 된다.The slab 120 is installed to be formed on the upper surface of the lower support constituting both side beams 110 so as to configure the halo bridge 100, the top layer of the slab is formed with a coat layer to function as a conventional bridge slab. .

결국, 본 발명에 의한 하로교는 종래와 달리 U형 단위 세그먼트 다수를 종방향으로 서로 연결시켜 1경간의 하로교를 시공하거나, 1경간에 걸친 전체 하로교 세그먼트를 교량 하부구조에 거치하는 방식으로 시공되는 것이 아니라,As a result, the haro bridge according to the present invention is constructed by connecting a plurality of U-shaped unit segments in the longitudinal direction to each other in the longitudinal direction, or by constructing a whole bridge structure over the span by mounting the entire haro bridge segment over the bridge substructure. not,

먼저, 공장등에서 제작된 양 측면빔(110)을 먼저 교량 하부구조(200)에 설치한 다음 그 내측면 하부에 슬래브(120)를 얹어 시공함으로서 종래 하로교를 시공하기 위하여 필연적으로 사용될 수밖에 없는 가시설 또는 런칭시스템을 사용하지 않아도 됨을 알 수 있다.First, both side beams 110 manufactured in factories, etc. are first installed on the bridge substructure 200, and then the slab 120 is installed on the lower side of the inner side to construct the conventional inevitably used for construction of the Haro bridge or You can see that you do not need to use a launch system.

<본 발명에 의한 하로교의 시공방법><Construction method of Haro Bridge according to the present invention>

교량에 따라 그 연장길이에는 차이가 있으나 다경간으로 시공해야 하는 경우가 대부분이이므로, 본 발명에서는 2경간을 기준으로 설명한다.Although there is a difference in the extension length depending on the bridge, it is most often required to construct a multi-span, so the present invention will be described based on two spans.

먼저, 도 3a와 같이 교량 하부구조(200)로써 교각(210) 3개를 이격 시공하게 된다.First, as shown in FIG. 3a, three bridges 210 are spaced apart as the bridge substructure 200.

이때, 교각과 교각 사이의 연장길이를 통상 1경간이라고 하는데 이러한 1경간의 길이는 미리 정해져 있으므로 이를 기준으로 양 측면빔(110)의 길이를 정하면 된다.At this time, the extension length between the bridge piers and the piers is generally referred to as one span. Since the length of the one span is predetermined, the lengths of both side beams 110 may be determined based on this.

이때 상기 교각(210)이 설치되는 부위를 지점부(A)라 하는데 이러한 지점부는 휨 부모멘트가 크게 발생하는 부위라 할 수 있어 본 발명에서는 이러한 지점부는 지점부콘크리트(230)에 의하여 마감하게 된다.At this time, the site where the pier 210 is installed is called the point A, and this point may be referred to as a site where a large bending moment occurs. In the present invention, the point is closed by the point concrete 230. .

교각 시공이 완료되면 교각과 교각의 종방향 상면 사이에 공장등에서 제작되어 현장에 반입된 한쌍의 측면빔(110)을 기중기와 같은 양중장치로 서로 횡방향으로 이격시켜 거치하게 된다.When the pier construction is completed, a pair of side beams 110, which are manufactured in factories, etc., brought into the site between the pier and the longitudinal upper surface of the pier, are laterally spaced apart from each other by a lifting device such as a crane.

이때, 미리 교각의 상면에는 교량받침을 설치하여 상기 교량받침에 양 측면빔(110)의 단부 저면이 지지되도록 한다.At this time, the bridge bearing is installed on the upper surface of the bridge in advance so that the end surfaces of both side beams 110 are supported by the bridge bearing.

다음으로 도 3b와 같이 본 발명의 슬래브(120)를 양 측면빔(110)의 바닥지지체 상부 몸통부 내측면 사이에 횡방향으로 연장되도록 하되 양 단부저면이 양 측면빔(110)의 하부지지체(112)에 설치된 받침(116)에 지지되도록 설치하게 된다.Next, the slab 120 of the present invention as shown in Figure 3b so as to extend in the transverse direction between the inner surface of the upper body of the bottom support of the both side beams 110, but both end bottoms of the lower support of the both side beams 110 ( 112 is installed to be supported by the support 116 installed in.

나아가 상기 슬래브(120)는 종방향으로 서로 인접하도록 다수를 설치하게 된다.Furthermore, the slab 120 is installed a plurality so as to be adjacent to each other in the longitudinal direction.

이때 양 측면빔(110)과 슬래브(120)의 ㄱ자형 및 ㄷ자형 연결철근들(115,126)도 서로 겹쳐지도록 하고 채움부 종방향철근(129)과 함께 채움부콘크리트(220)에 의하여 서로 결합되도록 하게 된다.At this time, the L-shaped and C-shaped connecting bars 115 and 126 of both side beams 110 and the slab 120 are also overlapped with each other, and are coupled to each other by the filling part concrete 220 together with the filling part longitudinal reinforcing bars 129. Done.

이때, 상기 받침(116) 주위의 슬래브(120)의 저면에는 무수축콘크리트에 의한 지지부(117)를 형성시켜 슬래브(120)의 자중이 하부지지체(112)의 상면에 분산되도록 한다.At this time, the bottom portion of the slab 120 around the support 116 is formed by the support portion 117 by the non-contraction concrete so that the self-weight of the slab 120 is dispersed on the upper surface of the lower support (112).

다음으로는 도 3c와 같이 종방향으로 서로 인접한 슬래브(120)의 하부돌출지지부(122) 상면 사이에 설치된 마감판(125)을 설치하고, 상기 마감판(125) 상부에 무수축콘크리트(127)를 충전시켜 슬래브의 종방향으로 일체화시키게 된다.Next, as shown in FIG. 3c, the finishing plate 125 is installed between the upper surface of the lower protrusion support 122 of the slab 120 adjacent to each other in the longitudinal direction, and the non-concrete concrete 127 is disposed on the finishing plate 125. Charged to integrate the longitudinal direction of the slab.

이때 상기 슬래브(120)에 형성된 종방향 홀(124)은 서로 연통되도록 미리 종방향 이격공간에 플라스티 관을 이용하여 종방향 홀(124)이 폐색되지 않도록 한다.At this time, the longitudinal hole 124 formed in the slab 120 is in contact with each other in advance so that the longitudinal hole 124 is not blocked by using a plastic tube in the longitudinal separation space.

이에 상기 종방향 홀(124)에 종방향 긴장재(128)을 삽입시킨 후 상기 종방향 긴장재(125)의 양 단부를 슬래브의 전면과 후면에서 긴장 후 정착되도록 하여 슬래브(120)가 종방향으로 압착될 수 있도록 하게 된다.The longitudinal tension member 128 is inserted into the longitudinal hole 124 and both ends of the longitudinal tension member 125 are tensioned at the front and rear surfaces of the slab to be fixed after the slab 120 is pressed in the longitudinal direction. To be possible.

이러한 슬래브(120)는 교각(210) 주위까지 인접하도록 설치하게 되며 교각 상면의 공간에는 슬래브(120)와 일체화되도록 지점부콘크리트(230)를 타설하여 지점부에 있성 슬래브(120)와 지점부콘크리트(230)가 서로 합성되도록 하게 된다.The slab 120 is installed so as to be adjacent to the pier 210 around, and in the space of the top of the pier to install the point concrete 230 so as to be integrated with the slab 120, the point slab 120 and the point concrete 230 may be combined with each other.

이에 지점부에 발생하는 휨 부모멘트는 지점부콘크리트와 교각과 상기 지점부콘크리트와 종방향으로 일체화된 슬래브(120)에 의하여 충분히 저항되도록 함을 알 수 있다.Accordingly, it can be seen that the bending parent generated at the point portion is sufficiently resisted by the slab 120 integrally formed in the longitudinal direction with the point concrete and the piers.

다음으로는 도 3d와 같이 양 측면빔의 몸통부 내측면과 슬래브(120)의 양 단부면 사이에 채움콘크리트(220)를 타설하여 일체화시키게 된다.Next, as shown in FIG. 3d, the filling concrete 220 is poured between the inner side surfaces of the body parts of both side beams and both end surfaces of the slab 120 to be integrated.

이에 본 발명의 하로교는 채움콘크리트(220)에 의하여 슬래브와 양 측면빔이 서로 일체화되도록 함을 알 수있으며, 상기 채움 콘크리트는 지점부콘크리트(230)와도 일체화되므로 전체적으로 매우 큰 휨 강성을 가진 하로교 시공이 가능하게 됨을 알 수 있다.Therefore, the haro bridge of the present invention can be seen that the slab and both side beams are integrated with each other by the filling concrete 220, the filling concrete is also integrated with the branch concrete 230, the construction of the Haro bridge with very large bending rigidity as a whole It can be seen that this is possible.

이에 상기 슬래브(120) 상면에 미도시된 포장층을 형성시킴으로서 최종 하로교 시공이 가능하게 됨을 알 수 있다.Thus, by forming a pavement layer (not shown) on the upper surface of the slab 120 it can be seen that the final bridge construction is possible.

100: 하로교
110: 양 측면빔
111: 몸통부
112: 하부지지체
113: EPS 블록
114: 종방향 긴장재
115: ㄱ자형 연결철근
116: 받침
117: 지지부
120: 슬래브
121: 몸통부
122: 하부돌출지지부
123: EPS 블록
124: 종방향 홀
125: 마감판
126: ㄷ자형 연결철근
127: 무수축 콘크리트
128: 종방향긴장재
129: 채움부 종방향긴장재
200: 교량 하부구조
210: 교각
220: 채움콘크리트
230: 지점부콘크리트
100: Halo Bridge
110: both side beams
111: torso
112: lower support
113: EPS Block
114: longitudinal tension member
115: L-shaped connecting bar
116: support
117: support
120: slab
121: torso
122: lower protrusion support
123: EPS Block
124: longitudinal hole
125: finish plate
126: U-shaped connecting bar
127: non-contraction concrete
128: longitudinal tension material
129: longitudinal tension material
200: bridge infrastructure
210: piers
220: filled concrete
230: branch concrete

Claims (6)

교대, 교각을 포함하는 교량 하부구조(200)를 종방향으로 설치하는 단계;
중공 사각박스체 형태의 몸통부(111)와 상기 몸통부 하부 내측면에 일체로 돌출되어 형성된 하부지지체(112)를 포함하는 빔으로서 양중장치를 이용하여 상기 교량 하부구조의 상면 사이에 1경간씩 종방향으로 거치시켜 연결시키되, 횡방향으로 이격되도록 양 측면빔(110)을 설치하는 단계; 및
상기 양 측면빔(110)의 하부지지체 상면 사이에 횡방향으로 슬래브(120)를 형성시켜 양 측면빔(110)과 일체화시키는 단계를 포함하되,
상기 교량 하부구조(200)의 지점부(A)에 위치한 양 측면빔의 종방향 연결부위에는 횡방향으로 현장타설콘크리트를 타설에 의한 지점부콘크리트로 형성시키고, 상기 지점부콘크리트(230)와 상기 슬래브(120)는 종방향 긴장재(128)에 의하여 서로 압착되어 일체화되도록 하되,
상기 슬래브(120)는 횡방향으로 연장된 경량 중공박스체를 종방향으로 서로 연결시킨 것을 이용하도록 하며, 양 단부 저면이 양 측면빔의 하부지지체 상면에 고무패드를 포함하는 받침(116)에 지지되도록 한 상태에서 양 단부면과 양 측면빔의 몸통부 내측면 사이 공간에는 채움콘크리트가 타설되어 슬래브가 양 측면빔 및 지점부콘크리트(220)와 일체화 되도록 시공되며,
상기 양 측면빔(120)은, EPS 블록(113)이 매립된 사각박스체 형태로 제작된 것으로서 하부에는 길이방향으로 종방향 긴장재(114)가 형성되도록 하여 프리스트레스가 도입되도록 제작된 몸통부(111); 및 상기 몸통부(111)의 하부 내측면에는 사각박스체 형태로 돌출형성되며 슬래브의 자중을 지지할 수 있도는 단면높이를 가진 하부지지체(112);를 포함하도록 제작하되, 상기 하부지지체 상부의 몸통부(111) 내측면에는 횡방향으로 수평연장되어 하방으로 절곡되면서 하부지지체 상면에 하단이 고정되는 ㄱ자형 연결철근(115)가 형성된 것이 이용되도록 하며,
상기 슬래브(120)의 단부면에는 횡방향으로 수평연장되어 하방으로 절곡되면서 다사 슬래브의 단부면으로 연장되어 고정된 ㄷ 자형 연결철근(116)이 더 형성되어 양 측면빔의 ㄱ자형 연결철근(115)과 서로 겹쳐지도록 한 상태에서 채움부 종방향철근(127)이 겹쳐진 양 연결철근(115,126)을 종방향으로 관통하도록 하여 상기 연결철근들과 채움부 종방향철근(127)이 채움콘크리트(220)에 의하여 매립되도록 하는 것을 특징으로 하는 횡방향 긴장없이 중공박스체로 제작되는 측면빔과 슬래브를 일체화시켜 시공되는 하로교 시공방법.
Installing a bridge substructure 200 including a shift and a pier in a longitudinal direction;
A beam comprising a body part 111 in the form of a hollow rectangular box body and a lower support body 112 formed integrally protruding from the inner bottom surface of the body part by one span between the upper surfaces of the bridge substructures using a lifting device. Mounting by mounting in the longitudinal direction, but installing both side beams 110 to be spaced apart in the transverse direction; And
Including the slab 120 in the transverse direction between the upper surface of the lower support of the both side beams 110 to integrate with both side beams 110,
In the longitudinal connection portion of both side beams located in the branch portion (A) of the bridge substructure (200) to form the site-casting concrete in the horizontal direction by the point portion concrete, the point portion concrete 230 and the The slab 120 is compressed to each other by the longitudinal tension member 128 to be integrated,
The slab 120 is used to connect the light hollow hollow body extending in the longitudinal direction to each other in the longitudinal direction, the bottom of both ends is supported by the support 116 including a rubber pad on the upper surface of the lower support of both side beams Filled concrete is placed in the space between both end faces and the inner side of the trunk of both side beams so that the slab is integrated with both side beams and the branch concrete 220.
The both side beams 120 are manufactured in the form of a rectangular box body in which the EPS block 113 is embedded, and a lower portion of the trunk portion 111 is formed so that the longitudinal tension member 114 is formed in the longitudinal direction to introduce the prestress. ); And a lower support 112 protruding in the form of a rectangular box on the lower inner surface of the body portion 111 and having a cross-sectional height capable of supporting the weight of the slab. The inner side of the body portion 111 is horizontally extended in the horizontal direction and bent downward so that the lower end is fixed to the upper surface of the lower support body is formed so that the connection bar 115 is formed,
An end surface of the slab 120 is horizontally extended in the horizontal direction and bent downward while the c-shaped connecting rebar 116 is further extended and fixed to the end surface of the multi-slab slab is formed a-shaped connecting bars (115) of both side beams ) So that the connecting rods and the filling section longitudinal reinforcing bars 127 are filled with concrete 220 by penetrating both connecting bars 115 and 126 overlapped with the filling section longitudinal reinforcing bars 127. The construction method of the aarrow bridge, which is constructed by integrating the side beam and the slab made of a hollow box body without lateral tension, characterized in that it is buried by.
삭제delete 제 1항에 있어서,
상기 슬래브(120)는
EPS 블록(123)이 길이방향으로 매립되며 종방향으로 종방향 긴장재(114)가 삽입되도록 길이방향의 직각방향으로 종방향 홀(124)가 형성된 중공 박스체 구조물인 몸통부(121); 및 상기 몸통부(121)의 하부 외측면에 돌출된 형성된 지지부로써 인접한 슬래브(120)의 하부돌출지지부(122) 상면 사이에 설치된 마감판(125)이 지지되도록 형성된 하부돌출지지부(122);를 포함하도록 제작된 것이 이용되도록 하는 것을 특징으로 하는 횡방향 긴장없이 중공박스체로 제작되는 측면빔과 슬래브를 일체화시켜 시공되는 하로교 시공방법.
The method of claim 1,
The slab 120 is
A body portion 121 which is a hollow box structure in which the EPS block 123 is embedded in the longitudinal direction and the longitudinal hole 124 is formed in the longitudinal direction in the longitudinal direction so that the longitudinal tension member 114 is inserted in the longitudinal direction; And a lower protrusion support part 122 formed to support a closing plate 125 installed between upper and lower protrusion support parts 122 of the adjacent slab 120 as a support part protruding from the lower outer surface of the body part 121. Haro bridge construction method is constructed by integrating the side beam and the slab made of a hollow box body without lateral tension, characterized in that to be used to include.
제 3항에 있어서,
상기 마감판(125)이 설치된 인접한 슬래브(120)의 종방향 이격공간에는 무수축콘크리트(127)가 충전되어 슬래브(120)가 종방향으로 서로 일체화되도록 하는 것을 특징으로 하는 횡방향 긴장없이 중공박스체로 제작되는 측면빔과 슬래브를 일체화시켜 시공되는 하로교 시공방법.
The method of claim 3,
Hollow box without transverse tension, characterized in that the non-concrete concrete 127 is filled in the longitudinal separation space of the adjacent slab 120 is installed with the closing plate 125 so that the slab 120 is integrated with each other in the longitudinal direction. The construction method of Haro Bridge which is constructed by integrating the side beam and the slab made of a sieve.
삭제delete 제 1항에 있어서,
상기 받침(116) 주위에는 무수축콘크리트에 의한 지지부(117)를 더 형성시켜 받침과 상기 지지부에 작용하는 슬래브 하중이 양 측면빔에 분산 전달되도록 하는 것을 특징으로 하는 횡방향 긴장없이 중공박스체로 제작되는 측면빔과 슬래브를 일체화시켜 시공되는 하로교 시공방법.
The method of claim 1,
The support 117 is formed by the non-concrete concrete around the support 116, so that the slab load acting on the support and the support is distributed to both side beams. The construction method of the bridge is constructed by integrating the side beam and the slab.
KR1020110002700A 2011-01-11 2011-01-11 Through bridge construction method by side beam and slab by box structure without lateral prestressing KR101104298B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020110002700A KR101104298B1 (en) 2011-01-11 2011-01-11 Through bridge construction method by side beam and slab by box structure without lateral prestressing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110002700A KR101104298B1 (en) 2011-01-11 2011-01-11 Through bridge construction method by side beam and slab by box structure without lateral prestressing

Publications (1)

Publication Number Publication Date
KR101104298B1 true KR101104298B1 (en) 2012-01-11

Family

ID=45614043

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110002700A KR101104298B1 (en) 2011-01-11 2011-01-11 Through bridge construction method by side beam and slab by box structure without lateral prestressing

Country Status (1)

Country Link
KR (1) KR101104298B1 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101338898B1 (en) * 2013-06-07 2013-12-10 이형훈 Beam with connection member and the construction method using the same
KR101489352B1 (en) 2013-04-10 2015-02-06 주식회사 비엔지컨설턴트 Torsion Reinforcing Structure and Bridge Girders having such reinforcing structure
CN104727228A (en) * 2015-03-31 2015-06-24 中铁工程机械研究设计院有限公司 Telescopic landing leg device for tunnel bridge construction machine
KR20180033470A (en) * 2018-03-14 2018-04-03 인하대학교 산학협력단 Precast concrete slab partially of non-composite continuous girder bridge and construction method thereof
CN112797962A (en) * 2021-01-04 2021-05-14 中铁城际规划建设有限公司 Pushing construction monitoring structure and method for prestressed concrete continuous beam bridge
CN114837101A (en) * 2022-06-21 2022-08-02 中铁十八局集团有限公司 Height-adjustable cushion seat

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005344402A (en) * 2004-06-04 2005-12-15 Dps Bridge Works Co Ltd Precast concrete floor slab, and composite floor panel using the same
KR20060022050A (en) * 2004-09-06 2006-03-09 재단법인 포항산업과학연구원 Railway bridge using preflex steel girder and precast concrete deck
KR20090045826A (en) * 2007-11-02 2009-05-08 삼표이앤씨 주식회사 Prefabricated rahmen bridge construction
KR20100034098A (en) * 2008-09-23 2010-04-01 삼표이앤씨 주식회사 Shoe construction method for prefabricated prestressed girder and prefabricated prestressed girder bridge construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005344402A (en) * 2004-06-04 2005-12-15 Dps Bridge Works Co Ltd Precast concrete floor slab, and composite floor panel using the same
KR20060022050A (en) * 2004-09-06 2006-03-09 재단법인 포항산업과학연구원 Railway bridge using preflex steel girder and precast concrete deck
KR20090045826A (en) * 2007-11-02 2009-05-08 삼표이앤씨 주식회사 Prefabricated rahmen bridge construction
KR20100034098A (en) * 2008-09-23 2010-04-01 삼표이앤씨 주식회사 Shoe construction method for prefabricated prestressed girder and prefabricated prestressed girder bridge construction method

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101489352B1 (en) 2013-04-10 2015-02-06 주식회사 비엔지컨설턴트 Torsion Reinforcing Structure and Bridge Girders having such reinforcing structure
KR101338898B1 (en) * 2013-06-07 2013-12-10 이형훈 Beam with connection member and the construction method using the same
CN104727228A (en) * 2015-03-31 2015-06-24 中铁工程机械研究设计院有限公司 Telescopic landing leg device for tunnel bridge construction machine
CN104727228B (en) * 2015-03-31 2016-05-25 中铁工程机械研究设计院有限公司 Tunnel Bridge Erector telescopic support leg device
KR20180033470A (en) * 2018-03-14 2018-04-03 인하대학교 산학협력단 Precast concrete slab partially of non-composite continuous girder bridge and construction method thereof
KR102098187B1 (en) * 2018-03-14 2020-04-07 인하대학교 산학협력단 Precast concrete slab partially of non-composite continuous girder bridge and construction method thereof
CN112797962A (en) * 2021-01-04 2021-05-14 中铁城际规划建设有限公司 Pushing construction monitoring structure and method for prestressed concrete continuous beam bridge
CN114837101A (en) * 2022-06-21 2022-08-02 中铁十八局集团有限公司 Height-adjustable cushion seat
CN114837101B (en) * 2022-06-21 2024-04-19 中铁十八局集团有限公司 Cushion seat with adjustable height

Similar Documents

Publication Publication Date Title
KR101104298B1 (en) Through bridge construction method by side beam and slab by box structure without lateral prestressing
KR100742206B1 (en) Steel-concrete composite rahmen bridge and construction method thereof
KR101318773B1 (en) T-shaped composite girder segment integrated by i-shaped girder filled with concrete and slab and construction method of slab by prefabrication of the t-shaped composite girder segment
JP2007077630A (en) Continuous girder using precast main-girder segment, and its erection method
KR101097273B1 (en) Through bridge using arch reinfocing member and construction method therefor
KR101260863B1 (en) Rhamen bridge having prestressed concrete girder of arch-shaped and construction method thereof
KR101551451B1 (en) Steel plate girder improved coner fixing capacity and rahmen or box type structure construction method using the same
KR101538516B1 (en) A box girder using steel and foam concrete insertion, and method for construction bridge using the same
KR100483083B1 (en) Composite Deck having Frame and Concrete
JP3844743B2 (en) Box girder bridge structure and its construction method
KR101071642B1 (en) Through bridge construction method by psc side beam and slab
KR20090024511A (en) Hybrid deep deck of constructing long span slim floor and structure using hybrid deep deck
KR20120136071A (en) Composite beam with partially filled concrete
KR101998822B1 (en) Composite rahmen bridge, steel girder for that and construction method of composite rahmen bridge
KR101329443B1 (en) Precast concrete frame and its construction method for buildings using precast concrete slab continued by post tensioning
KR100978463B1 (en) Method making a prestressed girder added prestress to the steel plate
KR101232329B1 (en) Integral bridge and construction method using arched and concrete-filled tube
KR20130090709A (en) Construction method for corrugated steel plate web-psc composite beam
KR101043710B1 (en) Through bridge construction method by side beam and slab by box structure without lateral prestressing
KR100889140B1 (en) The assembly type hollow slab
KR101824963B1 (en) Hybrid composite girder and construction method therewith
KR101426155B1 (en) The hybrid rahmen structure which can add prestress on steel girder of horizontal member by gap difference of connection face between vertical member and steel girder of horizontal member
KR101293646B1 (en) Bridge construction method using arch support connection member
KR101008555B1 (en) Hybrid girder for underpass and underpass using the same
KR102325276B1 (en) Half Precast Concrete continuous slab and construction method of the same

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
AMND Amendment
E601 Decision to refuse application
X091 Application refused [patent]
AMND Amendment
X701 Decision to grant (after re-examination)
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20141224

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20160105

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20190103

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20191203

Year of fee payment: 9