KR101089729B1 - The wall for the bridge post foundation construction - Google Patents

The wall for the bridge post foundation construction Download PDF

Info

Publication number
KR101089729B1
KR101089729B1 KR1020080128564A KR20080128564A KR101089729B1 KR 101089729 B1 KR101089729 B1 KR 101089729B1 KR 1020080128564 A KR1020080128564 A KR 1020080128564A KR 20080128564 A KR20080128564 A KR 20080128564A KR 101089729 B1 KR101089729 B1 KR 101089729B1
Authority
KR
South Korea
Prior art keywords
wall
pier
foundation construction
excavation
slope
Prior art date
Application number
KR1020080128564A
Other languages
Korean (ko)
Other versions
KR20100069986A (en
Inventor
김태흥
천경식
Original Assignee
주식회사 바우 컨설탄트
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 바우 컨설탄트 filed Critical 주식회사 바우 컨설탄트
Priority to KR1020080128564A priority Critical patent/KR101089729B1/en
Publication of KR20100069986A publication Critical patent/KR20100069986A/en
Application granted granted Critical
Publication of KR101089729B1 publication Critical patent/KR101089729B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/01Flat foundations
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0061Production methods for working underwater
    • E02D2250/0076Drilling
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron

Abstract

본 발명은 교각 기초시공용 벽체에 관한 것으로, 더욱 상세하게는 비탈면에 교각을 설치하기 위한 기초시공에 있어서, 교각이 설치될 비탈면 일부에 원형형상으로 굴착부가 굴착되고, 굴착부의 내측면을 따라 형성되되 상측에서 하측으로 일정깊이만큼 단계적으로 층을 이루며 벽체가 형성된다.The present invention relates to a wall for piling foundation construction, and more particularly, in the basic construction for installing the piers on the slope, the excavation portion is excavated in a circular shape on a portion of the slope on which the pier is to be installed, and is formed along the inner surface of the excavation portion. Then, a wall is formed by forming a layer step by step from the upper side to the lower side.

상기와 같은 본 발명에 의하면, 교각을 견고하게 지지할 수 있음은 물론, 종래 교각 설치부위의 상측부를 굴착하여 옹벽 등을 설치하는 작업을 생략할 수 있어 공정을 감소시키고, 자연환경의 훼손을 최소화하여 친환경적인 작업을 이룰 수 있다.According to the present invention as described above, it is possible not only to firmly support the pier, but also to excavate the upper part of the conventional pier installation site to install the retaining wall, so as to reduce the process, minimize the damage to the natural environment Environmentally friendly work.

교각, 기초시공, 비탈면, 굴착, 벽체 Pier, foundation construction, slope, excavation, wall

Description

교각 기초시공용 벽체{The wall for the bridge post foundation construction}Wall for the bridge post foundation construction

본 발명은 기초시공에 관한 것으로, 더욱 상세하게는 교각이 설치될 비탈면 일부에 원형형상으로 굴착부가 굴착되고, 굴착부의 내측면을 따라 형성되되 상측에서 하측으로 일정깊이만큼 단계적으로 층을 이루는 벽체를 구비하여 교각을 견고하게 지지할 수 있음은 물론, 종래 교각 설치부위의 상측부를 굴착하여 옹벽 등을 설치하는 작업을 생략할 수 있어 공정을 감소시키고, 자연환경의 훼손을 최소화하여 친환경적인 작업을 이룰 수 있는 교각 기초시공용 벽체에 관한 것이다.The present invention relates to a basic construction, more specifically, the excavation portion is excavated in a circular shape on a portion of the slope to be installed piers, formed along the inner surface of the excavation portion of the wall to form a step by step depth from the upper side to the lower side In addition to supporting the pier firmly, it is also possible to omit the work to install the retaining wall by excavating the upper side of the conventional pier installation site, reducing the process, minimizing the damage of the natural environment to achieve eco-friendly work The present invention relates to a pier foundation wall.

일반적으로, 다리 및 고가도로 등을 건설하기 위해 다수의 교각이 구비되고, 이 교각은 설치되는 지형에 기초공사를 통해 지반을 형성 후, 설치된다.In general, a plurality of pier is provided for the construction of bridges and overpasses, the pier is installed after the ground is formed through the foundation work on the terrain to be installed.

도 1은 종래 교각 설치를 위한 비탈면 기초시공을 도시한 도면이다.1 is a view showing a slope base construction for a conventional pier installation.

도면에서 도시한 바와 같이, 교각(3)이 설치될 비탈면(1)에 굴착부(2)를 형성하고, 이 굴착부(2)에 교각(3)을 설치하게 된다.As shown in the figure, the excavation part 2 is formed in the inclined surface 1 in which the pier 3 is to be installed, and the pier 3 is provided in this excavation part 2.

굴착부(2)는 교각(3)이 설치되도록 저면이 평평하게 형성되고, 저면의 상측 일부를 경사지게 굴착한 후 다짐으로써 굴착부(2) 상측에 위치된 흙이나 바위 등이 떨어지는 것을 방지하게 된다.The excavation portion 2 is formed in the bottom surface is flat so that the pier (3) is installed, and by digging inclined after the upper portion of the bottom to prevent the soil or rocks located above the excavation portion 2 to fall. .

그리고 다져진 경사면에서 흙이나 바위 등이 떨어지는 것을 방지하기 위해 별도의 망이나 옹벽(미 도시) 등을 설치하고 있다.In addition, to prevent the falling of dirt and rocks on the slope, which is set up a separate net or retaining wall (not shown) is installed.

그러나 이러한 굴착부(2)는 교각(3)이 설치되는 부분 외에 상측 일부의 비탈면(1)을 굴착하여야 함으로, 작업부위가 증가되고, 이에 따른 작업 비용이 발생되어 전체 비용이 증가되는 문제점이 있다.However, since the excavation part 2 should excavate the slope 1 of the upper part in addition to the part where the pier 3 is installed, the work area is increased, and thus, the work cost is generated and the overall cost is increased. .

또한, 교각(3) 설치부분 외에 굴착된 굴착부(2)에 의해 산악지형 환경의 광범위한 파괴를 초래하여 흙이나 돌 등이 떨어지거나 산사태 등의 자연재해가 발생되는 문제점이 있다.In addition, due to the excavation (2) excavated in addition to the installation portion of the pier (3) causes a wide range of destruction of the mountainous terrain environment, there is a problem that a natural disaster such as soil or stones fall or landslides occur.

이러한 자연재해를 방지하기 위해 그물망이나 옹벽 등을 더 구비하게 되는데, 이 대비책은 근본적인 해결책이 아니기 때문에, 초기 설치비용 및 유지 보수에 따라 비용이 지속적으로 발생되는 문제점이 있으며, 건설은 자연환경 파괴라는 부정적인 사회인식이 저변에 깔려있다.In order to prevent such natural disasters, a net or retaining wall is further provided. Since the countermeasure is not a fundamental solution, there is a problem that costs are continuously generated according to the initial installation cost and maintenance, and construction is called the destruction of the natural environment. Negative social awareness is underpinned.

이에 본 발명은 상기와 같은 문제점들을 해소하기 위해 안출된 것으로써, 교각이 설치될 비탈면 일부에 원형형상으로 굴착하여 굴착부를 형성하고, 이 굴착부의 내측면을 따라 상측에서 하측으로 일정깊이만큼 단계적으로 층을 이루는 벽체를 설치하여 종래 교각설치 부위를 비롯한 상측 비탈면을 굴착하는 공정과 굴착된 면을 보강하는 작업을 생략할 수 있어 작업 시간을 단축시키고, 비용을 절감시켜 작업 효율성을 향상시킬 수 있다.Accordingly, the present invention has been devised to solve the above problems, and excavated in a circular shape to a portion of the inclined surface on which the pier is to be installed to form an excavation, step by step to a predetermined depth from the upper side to the lower side along the inner surface of the excavation portion By installing a layered wall, it is possible to omit the process of excavating the upper slope and the reinforcement of the excavated surface, including the conventional pier installation site can shorten the work time, reduce the cost and improve the work efficiency.

그리고 벽체를 하측으로 갈수록 두께를 두껍게 형성하여 벽체를 안정되게 형성할 수 있고, 비탈면 상측에서 가해지는 하중을 지지할 수 있다.In addition, the thickness of the wall toward the lower side can be formed thicker to form a stable wall, it can support the load applied from the upper side of the slope.

또한, 비탈면 상측에 위치된 벽체 면의 상단부가 비탈면 상측으로 기울어지도록 형성하여 비탈면 상측에서 가해지는 하중을 더욱 용이하고 견고하게 지지할 수 있는 교각 기초시공용 벽체를 제공하는 것이 목적이다.In addition, an object of the present invention is to provide an pier foundation construction wall which is formed so that the upper end of the wall surface located on the inclined surface is inclined upwardly on the inclined surface to more easily and firmly support the load applied on the inclined surface.

상기 목적을 이루기 위한 본 발명은, 비탈면에 교각을 설치하기 위한 기초시공에 있어서, 상기 교각이 설치될 비탈면 일부에 원기둥형상으로 굴착부가 굴착되고, 상기 굴착부의 내측면을 따라 형성되되 상측에서 하측으로 일정깊이만큼 단계적으로 층을 이루도록 형성된다.In the present invention for achieving the above object, in the basic construction for installing the piers on the inclined surface, the excavation portion is excavated in a cylindrical shape to a portion of the inclined surface to be installed the piers, formed along the inner surface of the excavated portion from the upper side to the lower side It is formed to form layers step by step to a certain depth.

바람직하게, 상기 벽체는 하측으로 갈수록 두께가 점진적으로 증가된다.Preferably, the wall gradually increases in thickness toward the lower side.

그리고 상기 벽체는 상단측으로 갈수록 직경이 점진적으로 증가되도록 외측으로 상향 경사지도록 형성된다.And the wall is formed to be inclined upwardly outward so that the diameter gradually increases toward the top side.

또한, 상기 벽체는 철근과 콘크리트로 이루어진다.In addition, the wall is made of steel and concrete.

그리고 상기 벽체는 강판이나 파형강판 중 선택된 어느 하나 이상으로 이루어진다.The wall is made of at least one selected from steel sheets and corrugated steel sheets.

또한, 상기 각 층을 이루는 벽체의 높이는 1 ~ 1.5m이다.In addition, the height of each wall forming each layer is 1 to 1.5m.

그리고 상기 교각이 설치된 벽체의 내측부에는 마감재가 채워진다.And the finishing material is filled in the inner portion of the wall where the pier is installed.

또한, 상기 벽체는 보강지지구가 더 구비되어 굴착부와의 고정력을 증가시켜 지지력을 향상시킨다.In addition, the wall is further provided with a reinforcing support to increase the fixing force with the excavation portion to improve the supporting force.

그리고 상기 보강지지구는 앵커이다.And the reinforcing support is an anchor.

또한, 상기 벽체는 타원형 링 형상으로 형성되되, 긴 지름을 갖는 방향을 하중이 상대적으로 큰 비탈면 방향을 향하도록 설치한다.In addition, the wall is formed in the shape of an oval ring, the direction having a long diameter is installed so as to face the direction of the slope with a relatively large load.

상기한 바와 같이, 본 발명에 의한 교각 기초시공용 벽체에 의하면, 교각이 설치된 비탈면 부위만 원형으로 굴착하고, 굴착된 부위에 상단에서 하측으로 벽체를 단계별로 형성함에 따라 교각을 견고하게 지지할 수 있음은 물론, 종래 교각 설치부위의 상측부를 굴착하여 옹벽 등을 설치하는 작업을 생략할 수 있어 공정을 감소시키고, 자연환경의 훼손을 최소화하여 친환경적인 작업을 이룰 수 있게 하는 매우 유용하고 효과적인 발명이다.As described above, according to the pier foundation wall according to the present invention, only the inclined surface portion in which the pier is installed is excavated in a circular shape, and the pier can be firmly supported by forming the wall stepwise from the top to the bottom in the excavated portion. Of course, it is a very useful and effective invention to reduce the process, to minimize the damage to the natural environment to achieve environmentally friendly work by excavating the upper side of the conventional pier installation portion can be omitted to install the retaining wall, etc. .

이하, 본 발명의 바람직한 실시 예를 첨부된 도면을 참조하여 설명한다.Hereinafter, preferred embodiments of the present invention will be described with reference to the accompanying drawings.

또한, 본 실시 예는 본 발명의 권리범위를 한정하는 것은 아니고 단지 예시로 제시된 것이며, 그 기술적 요지를 이탈하지 않는 범위 내에서 다양한 변경이 가능하다.In addition, the present embodiment is not intended to limit the scope of the present invention, but is presented by way of example only, and various modifications may be made without departing from the technical gist of the present invention.

도 2는 본 발명에 따른 교각 기초시공용 벽체를 도시한 도면이고, 도 3은 본 발명에 따른 교각 기초시공용 벽체를 이용한 시공상태를 도시한 도면이며, 도 4는 본 발명에 따른 교각 기초시공용 벽체의 다른 실시 예를 도시한 도면이고, 도 5는 본 발명에 따른 교각 기초시공용 벽체의 또 다른 실시 예를 도시한 도면이며, 도 6은 본 발명에 따른 교각 기초시공용 벽체의 보강지지구가 설치된 상태를 도시한 도면이고, 도 7은 본 발명에 따른 교각 기초시공용 타원형 벽체를 도시한 도면이다.Figure 2 is a view showing a pier foundation wall according to the present invention, Figure 3 is a view showing a construction state using the pier foundation construction wall according to the present invention, Figure 4 is a pier foundation based on the present invention 5 is a view showing another embodiment of the common wall, Figure 5 is a view showing another embodiment of the bridge foundation construction wall according to the present invention, Figure 6 is a reinforcement of the bridge foundation construction wall according to the present invention Figure is a view showing a state in which the earth is installed, Figure 7 is a view showing an oval wall for piling foundation construction according to the present invention.

도면에서 도시한 바와 같이, 교각 기초시공용 벽체(200)는 상하방향으로 다단으로 적층되도록 형성되어 교각(3)이 설치된 비탈면(1)에 원기둥형상으로 굴착된 굴착부(100)에 설치된다.As shown in the figure, the piers foundation construction wall 200 is formed to be stacked in multiple stages in the vertical direction is installed in the excavation portion 100 excavated in a cylindrical shape on the slope (1) on which the pier 3 is installed.

벽체(200)는 굴착된 비탈면(1) 굴착부(100)의 상단에서 하측으로 단계별로 형성되어 완성되는 것으로, 굴착부(100)의 굴착시, 일정깊이 굴착한 다음, 굴착한 깊이만큼 벽체(200)를 형성하고, 벽체(200)가 형성된 굴착부(100)의 하측을 다시 굴착한 후, 먼저 설치된 벽체(200) 하측에 다른 벽체(200)를 형성함으로써, 완성된다.The wall 200 is completed by being formed step by step from the top of the excavated slope (1) excavation portion 100 to the lower side, when excavation of the excavation portion 100, excavated to a certain depth, the wall as much as the excavated depth ( 200 is formed, and the lower side of the excavation part 100 on which the wall 200 is formed is excavated again, and then another wall 200 is formed below the wall 200 provided first, thereby completing.

이러한, 벽체(200)는 도 3에 도시한 바와 같이, 내측에 교각(3)이 설치되는 것으로, 벽체(200)가 형성된 굴착부(100)의 저면에 교각(3)을 설치하고, 설치된 교각(3)과 벽체(200) 사이에 마감재(300)가 충진되어 작업이 마무리된다.As shown in FIG. 3, the wall 200 is provided with a pier 3 at an inner side thereof. The pier 3 is provided on the bottom of the excavation part 100 on which the wall 200 is formed, and the pier is provided. Finishing material 300 is filled between the (3) and the wall 200 is finished the work.

이때, 한 번의 작업으로 이루어지는 굴착깊이는 1 ~ 1.5m이고, 각 벽체(200)는 이에 대응되도록 높이(ℓ)가 1 ~ 1.5m로 형성되어 굴착부(100)에 설치된다.At this time, the excavation depth made by a single operation is 1 ~ 1.5m, each wall 200 is installed in the excavation portion 100 is formed with a height (L) 1 ~ 1.5m to correspond to this.

그리고 벽체(200)는 철근과 콘크리트로 구성되거나 경우에 따라, 강판이나 파형강판 중 선택된 어느 하나 이상으로 구성될 수 있는 것으로, 굴착된 비탈면을 지지할 수 있는 것이면 사용 가능하다.The wall 200 may be made of reinforcing steel and concrete, or in some cases, may be made of one or more selected from steel sheets or corrugated steel sheets, and may be used as long as it can support the excavated slope.

또한, 마감재(300)는 굴착부(100)에서 굴착한 흙을 사용함이 가장 바람직하나 경우에 따라 철근과 큰크리트를 사용하여 벽체(200) 내측을 충진 함에 따라 교각(3)을 더욱 견고하게 지지할 수 있다.In addition, the finishing material 300 is most preferably to use the soil excavated from the excavation portion 100, but in some cases using the reinforcing bar and large concrete to fill the wall 200 inside more firmly supports the piers (3) can do.

또한, 도 4에서 도시한 바와 같이, 벽체(200)는 하측으로 갈수록 그 형성 두께가 증가되도록 형성되어 상측이나 비탈면(1) 상측에서 가해지는 하중을 용이하게 지지할 수 있다.In addition, as shown in FIG. 4, the wall 200 is formed to increase in thickness toward the lower side thereof, so that the wall 200 may easily support a load applied from an upper side or an inclined surface 1.

이때, 벽체(200)의 형성 면 중 비탈면(1)의 상단측에 형성된 면이 비탈면(1)의 하단측에 형성된 면보다 상대적으로 더 두껍게 형성되어 비탈면(1) 상단측에서 가해지는 하중을 더욱 용이하게 지지하는 것이 바람직하다.At this time, the surface formed on the upper end side of the inclined surface 1 of the formed surface of the wall 200 is formed relatively thicker than the surface formed on the lower side of the inclined surface 1 to facilitate the load applied on the upper side of the inclined surface 1. It is desirable to support it.

이러한, 벽체(200)의 내측에는 굴착된 흙이나 철근 및 콘크리트로 형성된 마감재(300)가 충진되어 교각(3)을 견고하게 지지하게 된다.The inside of the wall 200 is filled with a finish 300 formed of excavated soil or reinforcement and concrete to firmly support the pier (3).

그리고 벽체(200)는 도 5에서 도시한 바와 같이, 하단에서 상단측으로 갈수 록 직경이 점진적으로 증가되도록 형성된다.And the wall 200 is formed so that the diameter gradually increases from the bottom to the top side, as shown in FIG.

이는 비탈면(1)에 굴착된 굴착부(100)로 하중이나 외부적인 힘을 지지하기 위한 것으로, 종래 교각(3) 설치부 상측을 경사지게 굴착하고, 그물망이나 옹벽 등을 설치하여 산사태나 함몰 등을 방지하는 효과를 얻기 위함이다.This is to support a load or an external force by the excavation portion 100 excavated to the slope 1, and to excavate the upper side of the conventional pier (3) installation inclined, and to install a net or retaining wall to prevent landslides and depressions. This is to obtain the effect of preventing.

이러한, 벽체(200)를 설치하기 위해 굴착부(100)를 저면에서 상측으로 갈수록 직경이 점진적으로 굴착시키고, 이 굴착부(100)에 벽체(200)를 설치함에 따라 지지력을 향상시킬 수 있다.In order to install the wall 200, the diameter of the excavation part 100 gradually increases from the bottom to the upper side, and the supporting force may be improved by installing the wall 200 in the excavation part 100.

이때, 벽체(200)는 비탈면(1)의 상측에 위치된 면의 경사각이 다른 면의 경사각보다 더욱 경사지게 형성하여 가해지는 하중이 높은 면을 더욱 용이하게 지지함이 바람직하다.At this time, the wall 200 is preferably formed so that the inclination angle of the surface located on the upper side of the slope 1 is more inclined than the inclination angle of the other surface to more easily support the surface with a high load applied.

그리고 벽체(200)는 도 6에서 도시한 바와 같이, 면을 따라 다수의 보강지지구(400)가 더 구비되는 것으로, 굴착부(100)와의 고정력을 증가시켜 지지력을 향상시킨다.And the wall 200, as shown in Figure 6, is further provided with a plurality of reinforcement support 400 along the surface, to improve the holding force by increasing the fixing force with the excavation portion (100).

이러한 보강지지구(400)는 앵커 및 쏘일 네일(Soil Nail) 중 선택된 어느 하나 이상으로 사용되며, 벽체(200)를 통과하여 굴착부(100)의 측면에 고정된다.The reinforcement support 400 is used as one or more selected from the anchor and the Soil Nail, and is fixed to the side of the excavation portion 100 through the wall 200.

이때, 보강지지구(400)는 굴착부(100)의 상황에 따라 다르게 사용되며, 굴착부(100) 주변 지역이 암석으로 형성될 경우, 암석에 일정길이로 고정시키고, 토사일 경우, 그 고정길이를 증가시켜 벽체(200)를 용이하게 고정시키게 된다.At this time, the reinforcing support 400 is used differently depending on the situation of the excavation part 100, when the area around the excavation part 100 is formed of a rock, fixed to the rock to a certain length, in the case of earth and sand, the fixing By increasing the length it is easy to fix the wall 200.

한편, 도 7에 도시한 바와 같이, 벽체(200)는 타원형 링 형상으로 형성될 수 도 있다.On the other hand, as shown in Figure 7, the wall 200 may be formed in an oval ring shape.

이 타원형 벽체(200)는 긴 지름을 갖는 방향을 하중이 상대적으로 큰 비탈면(1) 방향을 향하도록 설치하는 것으로, 비탈면을 따라 하측으로 가해지는 하중을 용이하게 지지할 수 있다.The elliptical wall 200 is provided in a direction having a long diameter in the direction of a slope 1 having a relatively large load, and can easily support a load applied downward along the slope.

도 1은 종래 교각 설치를 위한 비탈면 기초시공을 도시한 도면이고,1 is a view showing a slope base construction for a conventional pier installation,

도 2는 본 발명에 따른 교각 기초시공용 벽체를 도시한 도면이며,2 is a view showing the wall for piling foundation construction according to the present invention,

도 3은 본 발명에 따른 교각 기초시공용 벽체를 이용한 시공상태를 도시한 도면이고,3 is a view showing a construction state using the wall for piling foundation construction according to the present invention,

도 4는 본 발명에 따른 교각 기초시공용 벽체의 다른 실시 예를 도시한 도면이며,4 is a view showing another embodiment of the bridge foundation construction wall according to the present invention,

도 5는 본 발명에 따른 교각 기초시공용 벽체의 또 다른 실시 예를 도시한 도면이고,5 is a view showing another embodiment of the wall for piling foundation construction according to the present invention,

도 6은 본 발명에 따른 교각 기초시공용 벽체의 보강지지구가 설치된 상태를 도시한 도면이며,Figure 6 is a view showing a state in which the reinforcement support of the bridge foundation construction wall according to the present invention is installed,

도 7은 본 발명에 따른 교각 기초시공용 타원형 벽체를 도시한 도면이다.7 is a view showing an oval wall for piling foundation construction according to the present invention.

< 도면의 주요 부분에 대한 부호의 설명 ><Description of Symbols for Main Parts of Drawings>

1 : 비탈면 3 : 교각1: slope 3: pier

100 : 굴착부 200 : 벽체100: excavation 200: wall

300 : 마감재 400 : 보강지지구300: finishing material 400: reinforcing support

ℓ : 각 벽체 높이ℓ: height of each wall

Claims (10)

비탈면에 교각을 설치하기 위한 기초시공에 있어서,In the basic construction for installing the piers on the slope, 상기 교각이 설치될 비탈면 일부에 원기둥형상으로 굴착부가 굴착되고, 상기 굴착부의 내측면을 따라 형성되되 상측에서 하측으로 일정깊이만큼 단계적으로 층을 이루도록 벽체가 형성되며,The excavation portion is excavated in a cylindrical shape to a portion of the slope surface to be installed the pier, the wall is formed to form a layer by a predetermined depth from the upper side to the lower side is formed along the inner surface of the excavation portion, 상기 벽체는 보강지지구가 더 구비되어 굴착부와의 고정력을 증가시켜 지지력을 향상시키는 것을 특징으로 하는 교각 기초시공용 벽체.The wall is a pier foundation construction wall, characterized in that the reinforcing support is further provided to improve the holding force by increasing the fixing force with the excavation. 제1항에 있어서,The method of claim 1, 상기 벽체는 하측으로 갈수록 두께가 점진적으로 증가되는 것을 특징으로 하는 교각 기초시공용 벽체.The wall is pier foundation construction wall, characterized in that the thickness gradually increases toward the lower side. 제1항에 이어서,Following claim 1 상기 벽체는 상단측으로 갈수록 직경이 점진적으로 증가되도록 외측으로 상향 경사지도록 형성되는 것을 특징으로 하는 교각 기초시공용 벽체.The wall is pier foundation construction wall, characterized in that formed to be inclined upwardly outward so that the diameter gradually increases toward the top side. 제1항에 있어서,The method of claim 1, 상기 벽체는 철근과 콘크리트로 이루어지는 것을 특징으로 하는 교각 기초시 공용 벽체.The wall is a common wall when piling foundation, characterized in that made of reinforcing steel and concrete. 제1항에 있어서,The method of claim 1, 상기 벽체는 강판이나 파형강판 중 선택된 어느 하나 이상으로 이루어지는 것을 특징으로 하는 교각 기초시공용 벽체.The wall is pier foundation construction wall, characterized in that made of at least one selected from steel sheet or corrugated steel sheet. 제1항에 있어서,The method of claim 1, 상기 각 층을 이루는 벽체의 높이는 1 ~ 1.5m인 것을 특징으로 하는 교각 기초시공용 벽체.The height of the wall constituting each layer is a piling foundation construction wall, characterized in that 1 ~ 1.5m. 제1항에 있어서,The method of claim 1, 상기 교각이 설치된 벽체의 내측부에는 마감재가 채워지는 것을 특징으로 하는 교각 기초시공용 벽체.The inner part of the wall in which the pier is installed, the wall for piling foundation construction, characterized in that the finishing material is filled. 삭제delete 제1항에 있어서,The method of claim 1, 상기 보강지지구는 앵커인 것을 특징으로 하는 교각 기초시공용 벽체.The reinforcing support is pier foundation construction wall, characterized in that the anchor. 제1항에 있어서,The method of claim 1, 상기 벽체는 타원형 링 형상으로 형성되되, 긴 지름을 갖는 방향을 하중이 상대적으로 큰 비탈면 방향을 향하도록 설치하는 것을 특징으로 하는 교각 기초시공용 벽체.The wall is formed in the shape of an oval ring, pier foundation construction wall, characterized in that installed in the direction having a long diameter toward the slope surface direction relatively large load.
KR1020080128564A 2008-12-17 2008-12-17 The wall for the bridge post foundation construction KR101089729B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020080128564A KR101089729B1 (en) 2008-12-17 2008-12-17 The wall for the bridge post foundation construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020080128564A KR101089729B1 (en) 2008-12-17 2008-12-17 The wall for the bridge post foundation construction

Publications (2)

Publication Number Publication Date
KR20100069986A KR20100069986A (en) 2010-06-25
KR101089729B1 true KR101089729B1 (en) 2011-12-07

Family

ID=42367887

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020080128564A KR101089729B1 (en) 2008-12-17 2008-12-17 The wall for the bridge post foundation construction

Country Status (1)

Country Link
KR (1) KR101089729B1 (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004211479A (en) 2003-01-08 2004-07-29 Nippon Hume Corp Connection part structure for structure of nonuniform section using prestressed concrete well

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004211479A (en) 2003-01-08 2004-07-29 Nippon Hume Corp Connection part structure for structure of nonuniform section using prestressed concrete well

Also Published As

Publication number Publication date
KR20100069986A (en) 2010-06-25

Similar Documents

Publication Publication Date Title
JP2007321452A (en) Construction method for bridge and bridge structure thereof
CN102031760A (en) Anti-rockfall method for subgrade in rock deposit zone
JP4281567B2 (en) Reinforcement structure of existing pier foundation and reinforcement method of existing pier foundation
CN107059882A (en) Arch anchor net and Anchor-Pile Retaining Structure structure
CN104532868A (en) Anchored high bearing platform grouped pile foundation building method for high-steep deformation slope area bridge
JP2019510909A (en) Interlocking stabilization system to stabilize slopes or unconstrained ground surfaces
CN109024662A (en) Method of the anchor pile underpinning without basement building underground space increasing layer
CN211200426U (en) Anti-sliding supporting and retaining structure for miniature steel pipe pile retaining wall
CN108999142A (en) The construction method of dome rectangular light-duty caisson and pile foundation combined type deep water breakwater
KR101653606B1 (en) Method for constructing integral abutment bridge
JP7338119B2 (en) Floating control structure and reversed construction method
KR102116085B1 (en) A Eco-friendly retain wall structure
KR100447331B1 (en) execution method of landscape architecture for cutting ground using blasting stone and landscape architecture apparatus using the same
KR101089729B1 (en) The wall for the bridge post foundation construction
KR102123205B1 (en) Construction method and mounting structure of retaining wall structure using reinforcing metal and connecting metal
KR101140787B1 (en) Bridge post foundation construction method
KR100433653B1 (en) Constructing method for the filling out abutement of bridge
JP2021063404A (en) Improvement structure and improvement method of existing quay wall
KR101677235B1 (en) Embankment structure for constructing using floating-type pile on soft ground, and construction method for the same
JP2004211502A (en) Foundation reinforcing structure
KR100346947B1 (en) The SEN Retaining Wall
CN109024470A (en) The rectangular light-duty caisson of dome and pile foundation combined type breakwater
JP7193065B2 (en) Reverse construction method
KR102376019B1 (en) Corrugated steel wall
JP5945167B2 (en) Basic construction method, photovoltaic panel construction method and building construction method

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20141126

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20151127

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20161125

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20171121

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20181128

Year of fee payment: 8