KR100346947B1 - The SEN Retaining Wall - Google Patents

The SEN Retaining Wall Download PDF

Info

Publication number
KR100346947B1
KR100346947B1 KR1019990035997A KR19990035997A KR100346947B1 KR 100346947 B1 KR100346947 B1 KR 100346947B1 KR 1019990035997 A KR1019990035997 A KR 1019990035997A KR 19990035997 A KR19990035997 A KR 19990035997A KR 100346947 B1 KR100346947 B1 KR 100346947B1
Authority
KR
South Korea
Prior art keywords
retaining wall
concrete
triangular pyramid
inverted triangular
existing
Prior art date
Application number
KR1019990035997A
Other languages
Korean (ko)
Other versions
KR20010019548A (en
Inventor
이창남
Original Assignee
이창남
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 이창남 filed Critical 이창남
Priority to KR1019990035997A priority Critical patent/KR100346947B1/en
Publication of KR20010019548A publication Critical patent/KR20010019548A/en
Application granted granted Critical
Publication of KR100346947B1 publication Critical patent/KR100346947B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0258Retaining or protecting walls characterised by constructional features
    • E02D29/0266Retaining or protecting walls characterised by constructional features made up of preformed elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • E02D29/0233Retaining or protecting walls comprising retention means in the backfill the retention means being anchors
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/16Shapes
    • E02D2200/1678Shapes triangular

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Retaining Walls (AREA)

Abstract

본 발명은 콘크리트로 된 역삼각뿔을 이용하여 기존 석축을 보강하는 구조 및 그 공사방법에 관한 것으로, 기존 석축에 콘크리트 역삼각뿔을 설치하여 콘크리트 역삼각뿔의 자중이 석축으로 향하는 성질을 이용하여 기존 석축의 지지력을 높이는 기존 석축의 보강 방법에 관한 것이다.The present invention relates to a structure for reinforcing an existing masonry using an inverted triangular pyramid made of concrete, and to a method of constructing the same. The present invention relates to a method of reinforcing existing stone slabs to increase bearing capacity.

본 발명은 기존 석축(1)의 기초(2)를 관통하여 지지 말뚝(12)을 심고, 상기 말뚝(12)이 꼭지점이 되는 콘크리트 역삼각뿔(11)을 상기 기존 석축(1)과 일체가 되도록 형성하는 단계로 이루어지는 기존 석축의 보강방법을 제공한다.The present invention is to plant the support pile 12 through the foundation (2) of the existing stone shaft (1), so that the concrete inverted triangular pyramid (11) that the pile 12 is a vertex to be integrated with the existing stone shaft (1) It provides a method of reinforcing the existing masonry consisting of the step of forming.

또한 본 발명은 옹벽 하단부 경질지반(3a)을 굴착할 때 경사면을 그대로 둔 채 기초(2)를 설치하고, 역삼각뿔(31)을 가진 경사면 옹벽(30)을 설치하고, 상기 경질지반(3a) 상부의 연약지반(3b)에 도달하면 경사면을 완만하게 정리하고, 상기 경사면 옹벽 후면에 짐받이 콘크리트(32)를 설치하고, 상기 짐받이 콘크리트 위에 경사지워 잡석이나 흙을 메우고, 상기 역삼각뿔(31)을 가진 경사면 옹벽을 완성하 는 단계로 공사하는 신설 옹벽의 공사방법도 제공한다.In addition, the present invention, when excavating the retaining wall bottom hard ground (3a) is provided with the base 2 while leaving the inclined surface intact, and installs the inclined surface retaining wall 30 having an inverted triangular pyramid 31, the hard ground (3a) When the upper surface of the soft ground (3b) is reached, the slope is smoothly arranged, and the bearing concrete 32 is installed on the rear surface of the inclined surface retaining wall. It also provides a method of constructing a new retaining wall that is being constructed to complete the retained slope retaining wall.

Description

석축 보강 및 옹벽 공사방법{The SEN Retaining Wall}Masonry reinforcement and retaining wall construction method {The SEN Retaining Wall}

본 발명은 콘크리트로 된 역삼각뿔을 이용하여 기존 석축을 보강하는 방법에 관한 것이다. 더욱 구체적으로, 기존 석축에 콘크리트 역삼각뿔을 설치하고 콘크리트 역삼각뿔의 자중이 기존 석축으로 향하는 성질을 이용하여 기존 석축의 지지력을 높이는 석축의 보강 방법에 관한 것이다.The present invention relates to a method for reinforcing an existing stone shaft using an inverted triangular pyramid made of concrete. More specifically, the present invention relates to a method of reinforcing a stone shaft to install a concrete inverted triangular pyramid in the existing stone shaft and to increase the bearing capacity of the existing stone shaft using the property of the weight of the concrete inverted triangular pyramid toward the existing stone shaft.

제1도는 기존 석축의 단면도이다.1 is a cross-sectional view of an existing stone shaft.

석축(1)은 돌로 쌓아 만든 축대로 경사지의 비탈면에 견치석ㆍ각석 등을 쌓아올려 토사의 붕괴를 방지하는 구조물이다. 석축의 하단에는 기초(2)를 설치하고 그 위에 돌을 쌓아 지반(3)의 토압을 견디는 구조를 가진다.A stone shaft (1) is a structure that prevents the collapse of earth and sand by stacking vertebral and kerbstones on the slope of the slope as an axis made of stone. At the lower end of the stonework, a foundation 2 is installed and stones are stacked thereon to withstand the earth pressure of the ground 3.

견치석의 뒷면을 시멘트 모르타르나 콘크리트로 채워가며 쌓는 찰쌓기식 석축은 중력식 옹벽의 역할을 어느 정도 기대할 수 있으나 견치석의 뒷면을 잡석이나 흙으로 채워가며 쌓는 메쌓기 석축은 토압을 지탱할 능력이 거의 없다. 이와 같이 종래에 쌓는 석축 그 자체는 구조적으로 별로 큰 내력을 기대할 수 없는 것이어서 경질지반을 경사지게 절단한 면이 우수에 노출되었을 때에 씻기거나 풍화하는 것을 방지하는 표면보호재의 역할을 기대하는 정도이다.The piled-up stacks that fill the back of the cantilever with cement mortar or concrete can play some role as gravity retaining walls, but the stacked stacks that fill the back of the cantilever with soil or rubble have little ability to support earth pressure. As such, the conventionally stacked masonry itself cannot be expected to have a very large structural strength, so it is expected to play a role of a surface protection material that prevents washing or weathering when the surface of the hard ground inclinedly cut is exposed to rainwater.

석축을 쌓는 경사각은 지반 종류에 따라 달라지며, 만약 흙의 안식각과 같은 경사각으로 쌓는다면 붕괴의 위험이 없는 것은 당연하나 안전 위주로 경사각을 완만하게 하면 석축의 높이가 높아짐에 따라 대지의 활용도가 떨어지므로 위험을 무릅쓰고 급경사를 고집하는 경향이 있어 붕괴할 위험이 많다.The inclination angle for stacking stones depends on the type of ground, and if it is stacked at the same inclination angle of soil, there is no danger of collapse. At risk, they tend to stick to steep slopes, so there is a high risk of collapse.

근래에 와서는 석축을 쌓는 공사비가 상승하여 석축을 신축하는 일이 거의 없지만 노후화된 기존 석축을 원상으로 보수하는 일도 쉽지 않은 형편이다. 따라서 기존 석축을 보강하거나, 신축하는 경사지에 적용할 신공법의 옹벽 기술이 요청된다. 그리고 석축의 경사로 인한 대지가 잠식된 것을 활용할 수 있는 옹벽 기술도 요청된다.In recent years, the cost of constructing stone stocks has risen, so it is hard to build new ones, but it is not easy to repair old masonry. Therefore, there is a need for a new retaining wall technology to be applied to the slopes to reinforce or expand existing masonry. There is also a need for retaining wall technology that can take advantage of the erosion of the earth due to the slope of the stonework.

발명자는 기존 석축을 보강하여 안정성을 증가시키고 대지의 활용도를 높일 수 있는 기존 석축 보강 방법을 개발하였다.The inventors have developed an existing masonry reinforcement method that can increase the stability of the existing masonry and increase the utilization of the site.

또한 발명자는 신축 옹벽의 경사각을 크게(경사가 급하게) 하여 토공사의 양을 줄일 수 있는 신설 옹벽의 공사방법도 개발하였다.In addition, the inventors have developed a method for constructing a new retaining wall that can reduce the amount of earthworks by increasing the inclination angle of the new retaining wall.

본 발명의 목적은 기존 석축을 보강하는 방법을 제공하는 것이다.It is an object of the present invention to provide a method for reinforcing an existing stonework.

본 발명의 다른 목적은 경사면을 보강하는 신설 옹벽의 공사방법을 제공하는 것이다.Another object of the present invention is to provide a construction method of a new retaining wall to reinforce the inclined surface.

본 발명의 또 다른 목적은 기존 석축 상단부 공간을 활용하는 방법을 제공하는 것이다.Still another object of the present invention is to provide a method of utilizing an existing stone top space.

제1도는 기존 석축의 단면도이다.1 is a cross-sectional view of an existing stone shaft.

제2도는 본 발명으로 기존 석축을 보강하는 구조의 개념도이다2 is a conceptual diagram of a structure for reinforcing existing stone masonry with the present invention

제3도는 본 발명으로 기존 석축을 보강하는 구조의 보강도면이다.3 is a reinforcement drawing of a structure for reinforcing an existing masonry with the present invention.

제4도는 제3도의 A-A 단면도이다.4 is a cross-sectional view taken along line A-A of FIG.

제5도는 본 발명의 변형예로서 신설 옹벽의 단면도이다.5 is a cross-sectional view of a new retaining wall as a modification of the present invention.

* 도면의 주요 부호 설명 *Description of the major signs

1: 기존 석축 2: 기초1: existing stonework 2: foundation

3: 지반 11: 콘크리트 역삼각뿔3: Soil 11: Concrete Inverted Triangular Pyramid

12: 말뚝 13: 콘크리트 슬래브12: pile 13: concrete slab

21: 기둥 22: 프레임21: pillar 22: frame

23: 타이 빔 24: 수평철근23: tie beam 24: horizontal rebar

25: ㅅ-자형 철근 26: 리브 라스(Rib Lath)25: S-shaped rebar 26: Rib Lath

30: 신설 옹벽30: new retaining wall

31: 콘크리트 역삼각뿔 32: 짐받이 콘크리트31: concrete inverted triangular pyramid 32: bearing concrete

33: 옹벽 상단 슬래브 34: 키(key)33: retaining wall upper slab 34: key

첨부한 도면에 따라 본 발명을 상세하게 설명한다.The present invention will be described in detail with reference to the accompanying drawings.

제2도는 본 발명으로 기존 석축을 보강하는 구조의 개념도이다.2 is a conceptual diagram of a structure for reinforcing existing stone masonry with the present invention.

본 발명의 보강 구조에서는 기존 석축(1)의 경사면을 기준면으로 활용한다. 원래 석축에서 경사각은 필수적이며, 경사각의 크기는 석축 뒷면의 토질과 석축 높이에 따라 달라지는데 석축을 축조한 후 짧은 기간이라도 붕괴하지 않고 견딜 수 있다면 그 경사각은 적정 값에 근접한다는 것을 뜻한다. 따라서 석축 하단에 연직 방향으로 세우는 면과 기존 석축 경사면 사이에 생기는 역삼각형 쐐기(C0-C1-B0-A0, C1-C2-B1-A1, ....) 단면을 가진 무거운 질량의 강체를 제작하여 부착한다면 기존 석축의 안전성을 높이게 된다.In the reinforcing structure of the present invention, the slope of the existing stone shaft 1 is used as a reference plane. In the original stone shaft, the angle of inclination is essential, and the size of the angle depends on the soil quality and the height of the stone. Therefore, the inverted triangle wedge (C 0 -C 1 -B 0 -A 0 , C 1 -C 2 -B 1 -A 1, .... ) If manufactured and attached to the heavy mass of the heavy body with the will increase the safety of the existing masonry.

기존 석축의 기초나 지반이 약하면 쐐기의 중량으로 인하여 기초가 침하할 우려가 있다. 따라서 강체의 중량을 지지수단을 사용하여 직접 경질 지반에 전달되게 한다면 침하할 우려는 없어지고 강체가 경사면에 놓이게 됨으로 생기는 수평분력은 지지체가 부담하게 된다.If the foundation or ground of the existing masonry is weak, there is a fear that the foundation sinks due to the weight of the wedge. Therefore, if the weight of the rigid body is directly transferred to the hard ground by using the support means, there is no fear of sinking, and the horizontal component generated by the rigid body lying on the inclined surface is burdened by the support.

본 발명에서는 강체로서 콘크리트 역삼각뿔(11)을 형성하고 역삼각뿔의 꼭지점에 기존 석축(1)의 기초(2)를 관통하여 지지수단인 말뚝(12)을 설치하여 해결한다.In the present invention, a concrete inverted triangular pyramid (11) is formed as a rigid body, and it is solved by installing a pile (12) as a supporting means through the foundation (2) of the existing stone shaft (1) at the vertex of the inverted triangular pyramid.

석축은 견치석이 경사각을 가지고 누워 있어 뒷면 흙을 누르는 힘이 석축 배면의 흙이 절토면을 경계로 하여 미끄러져 내리려는 힘보다 클 때 안전성이 보장된다. 그러므로 석축을 쌓은 후 무너지지 않고 버티고 있을 때 석축 경사면을 눌러 주면 눌러 준 만큼 석축에 여력이 생기는 것은 당연하다.The stone masonry is laid with an inclination angle, so safety is ensured when the pressing force of the soil on the back side is greater than the sliding force of the soil on the back side of the stone. Therefore, it is natural that there is room for the stonework as much as it is pushed when the stonework slope is pressed when the stonework is standing and not falling down.

석축을 누르는 방법에서 옹벽 전체를 삼각형 단면을 가진 콘크리트로 덮을 수 있지만 콘크리트 량이 많아지고 효율도 떨어진다. 효율(즉 모멘트)을 높이기 위해서는 A0점을 기준으로 할 때 A0-B0선에서 될 수 있는 대로 먼 곳에 무게 중심이 있어야 한다. 그리고 옹벽은 대체로 단조롭기 때문에 주변 경관과 어울리지 못하는 점을 고려할 필요가 있다. 효율성을 살리고 미관을 고려할 때 가장 최적의 형태로 콘크리트 역삼각뿔이 도출된다.In the method of pressing the stone slabs, the entire retaining wall can be covered with concrete with a triangular cross-section, but the amount of concrete is high and the efficiency is low. To increase efficiency (ie moment), the center of gravity should be as far from the A 0 -B 0 line as possible based on the A 0 point. And because the retaining wall is generally monotonous, it is necessary to consider that it does not fit with the surrounding landscape. In terms of efficiency and aesthetics, the concrete inverted triangular pyramid is derived in the most optimal form.

역삼각뿔 형상을 가진다면 연속된 삼각기둥 형상에 비해 콘크리트 량은 1/3이지만 모멘트는 2/3에 이르므로 2배의 효율을 가진다. 그리고 콘크리트 역삼각뿔의 표면의 질감에 변화를 주거나 색깔을 달리함으로서 조형 효과도 가져온다.If it has an inverted triangular pyramid shape, the concrete amount is 1/3 compared to the continuous triangular prism shape, but the moment is 2/3, so the efficiency is doubled. In addition, by changing the texture of the surface of the concrete inverted triangular pyramid or by changing the color, it also brings a molding effect.

그리고 역삼각뿔의 상단에 콘크리트 슬래브(13)로서 바닥을 형성하면 석축 위 대지가 부족한 것을 확장하여 활용할 수 있는 수단도 제공한다.And by forming the floor as a concrete slab 13 on the top of the inverted triangular pyramid also provides a means to expand and utilize the lack of land on the stonework.

제3도는 본 발명으로 기존 석축을 보강하는 구조의 보강도면이고, 제4도는 제3도의 A-A 단면도이다. 제3도와 제4도를 참조하며 보강 구조 및 그 공사방법을 설명한다.Figure 3 is a reinforcement drawing of the structure to reinforce the existing masonry with the present invention, Figure 4 is a cross-sectional view A-A of FIG. With reference to FIG. 3 and FIG. 4, a reinforcement structure and its construction method are demonstrated.

기존 석축(1)이 설치된 기초(2)를 관통하여 적당한 간격마다 구멍을 뚫고(core boring) 경질지반까지 천공한다. 천공한 구멍에 시멘트 모르터를 넣고 지지용 말뚝(12)을 박고 기둥(21)을 연장설치한다.It penetrates through the foundation (2) on which the existing stone shaft (1) is installed and drills at a suitable interval (core boring) to the hard ground. Put the cement mortar in the perforated hole, put the support pile (12) and extend the pillar (21).

기존 석축(1)의 경사면에 기둥(21)과 삼각뿔이 만들어지도록 강관, 각관, 형강, 채널 등의 철재로 된 프레임(22)를 설치하고 프레임의 끝을 삼각형 타이빔(23)으로 연결한다. 상기 기둥(21)과 프레임(22)과 타이 빔(23)으로 만들어지는 삼각뿔의 경사면 평면에 수평철근(24)을 배근한다. 수평철근은 철재에 일정 간격으로 구멍을 뚫어 볼트와 너트를 사용하여 프레임에 고정시켜도 된다. 수평철근과 교차하여 수직철근(도시하지 않음)을 배근한다.On the inclined surface of the existing stone shaft (1) to install a steel frame, such as steel pipe, square tube, section steel, channel so that the pillar 21 and the triangular pyramid and connect the end of the frame with a triangular tie beam (23). The horizontal reinforcing bar 24 is placed on the inclined plane of the triangular pyramid made of the pillar 21, the frame 22, and the tie beam 23. Horizontal rebar may be drilled at regular intervals in steel and fixed to the frame using bolts and nuts. Cross the horizontal reinforcement and reinforce the vertical reinforcement (not shown).

기둥(21)과 프레임(22)과 타이 빔(22)으로 만들어지는 삼각뿔 표면에 ㅅ-자형으로 가공한 철근(25)을 배근하고 상기 ㅅ-자형 철근(25) 위에 리브 라스(26, Rib Lath)를 설치한다.Ribbed lath (26, Rib Lath) is placed on the S-shaped reinforcing bar 25 by placing the S-shaped reinforcing bar 25 on the triangular pyramid surface made of the pillar 21, the frame 22 and the tie beam 22. Install).

상기 기둥(21)과 프레임(22)과 타이 빔(23)을 만들어지는 삼각뿔 표면 외의 다른 경사면에는 리브 라스(26)를 부착한다.A rib lath 26 is attached to another inclined surface other than the triangular pyramid surface from which the pillar 21, the frame 22, and the tie beam 23 are made.

상기 리브 라스(26)가 부착된 경사면에 리브 라스를 거푸집으로 하여 경사면과 리브 라스 사이에 콘크리트를 타입한다.The rib lath is formed on the inclined surface to which the rib lath 26 is attached to form a concrete between the inclined surface and the rib lath.

기둥(21)과 프레임(22)과 타이 빔(22)을 만들어지는 삼각뿔 표면에 ㅅ-자형으로 가공한 철근(25)을 배근하고 상기 ㅅ-자형 철근(25) 위에 리브 라스(26, Rib Lath)를 설치한 부위에 리브 라스를 거푸집으로 삼아 콘크리트를 타설하여 콘크리트 역삼각뿔(11)을 형성시킨다.Rib lath (26, Rib Lath) is placed on the S-shaped reinforcement bar 25 by reinforcing the S-shaped reinforcing bar 25 on the triangular pyramid surface from which the pillar 21, the frame 22, and the tie beam 22 are made. The concrete is installed by placing the rib lath as a formwork on the site where) is installed to form a concrete inverted triangle pyramid (11).

콘크리트 역삼각뿔(11)의 표면과 다른 경사면에 쇼트크리트(Shotcrete)를 쏘아붙이고 필요시 표면을 색상으로 처리한다.Shotcrete is shot on an inclined surface different from the surface of the concrete inverted triangular pyramid 11, and the surface is treated with color if necessary.

역삼각뿔(11)의 상단 즉 옹벽의 상단에 콘크리트 슬래브(13)를 더 만들면 한정된 대지를 활용하고 슬래브(13)의 자중과 적재하중은 석축의 안정에 기여하게 된다.If the concrete slab 13 is further made at the upper end of the inverted triangular pyramid 11, that is, the retaining wall, the limited land is used, and the self-load and the loading load of the slab 13 contribute to the stabilization of the masonry.

본 발명의 보강법은 구체예에 의해 설명했지만 본 발명에서 형성시키는 역삼각뿔은 기존 석축의 경사도, 지반 상태 등에 따라 석축 경사각이 지나치게 작은 때(즉 완만한 때)는 기둥을 연직방향이 아닌 경사를 가지도록 설치하여 시각적인 안정감을 주고 콘크리트 사용량을 줄일 수 있다. 그리고 기존 석축의 높이가 높아 한 번에 역삼각뿔을 형성할 수 없을 때에는 2-3단으로 축조해도 무방하다.Although the reinforcing method of the present invention has been described by the specific examples, the inverted triangular pyramids formed in the present invention are characterized by the inclination of the column not in the vertical direction when the inclination angle of the stone shaft is too small (that is, when it is gentle) according to the inclination, ground state, etc. of the existing stone shaft. It can be installed to have visual stability and reduce the amount of concrete used. In addition, when the height of the existing stone shafts cannot be formed at one time, a triangle pyramid may be constructed.

제5도는 본 발명의 변형예로서 신설 옹벽의 단면도이다.5 is a cross-sectional view of a new retaining wall as a modification of the present invention.

본 변형예는 기존 석축에 안전성을 추가하는 보강 공법과는 달리 옹벽을 신축할 때 역삼각뿔 콘크리트 덩어리와 상부 슬래브의 하중 외에 적극적으로 옹벽에 하중을 추가하는 방법이다.Unlike the reinforcement method, which adds safety to existing masonry, this modification is a method of actively adding load to the retaining wall in addition to the load of the inverted triangular pyramid concrete mass and the upper slab.

재래식 일반 옹벽은 옹벽 뒷면과 흙의 안식각 사이 쐐기 형태의 흙이 미끄러져 내리려는 것을 방지해야 하므로 역T형 옹벽이나 L형 옹벽은 기초 위에 흙을 메워 그 무게로서 토압을 상쇄시킨다. 따라서 역T형 옹벽이나 L형 옹벽은 기초 길이가 클수록 안전하게 되는데 그 목적을 위하여 옹벽 뒷면 흙파기 량이 많아지는 부작용이 있다. 그리고 기초 길이가 길면 모멘트 값이 커져서 단면이 커지며 공사비가 추가되는 단점이 있다.Conventional general retaining walls must prevent wedge-shaped soil from slipping between the back of the retaining wall and the angle of repose of the soil, so an inverted T or L retaining wall fills the soil on the foundation to offset the earth pressure by its weight. Therefore, the inverted T-shaped retaining wall or L-shaped retaining wall becomes safer as the foundation length increases, and there is a side effect of increasing the amount of dirt excavated on the back of the retaining wall. In addition, if the foundation length is long, the moment value is increased, the cross section is increased, and there is a disadvantage in that the construction cost is added.

위 단점을 해소하면서 좋은 효과를 얻기 위하여 신설 옹벽(30)은 옹벽 하단부 경질지반(3a)을 굴착할 때 경사면을 그대로 둔 채 공사해 올라가다가 상부 연약지반(3b)에 도달하면 경사면을 완만하게 정리한 후 경사면 콘크리트 옹벽 후면에 철근콘그리트 기초 겸 슬래브를 부착하여 짐받이 콘크리트(32)로 활용하는 것이다. 이것은 마치 지게의 짐받이와 같은 원리로 별도 거푸집을 설치하지 않아도 되므로시공이 간편하다. 슬래브와 그 위에 메우는 흙은 지지점인 A에서 멀기 때문에 안전성을 확보하는 데 효과가 크다.In order to solve the above shortcomings and obtain a good effect, the new retaining wall 30 is constructed with the slope intact when excavating the hard ground 3a at the bottom of the retaining wall. Then, the reinforced concrete foundation and slab is attached to the rear surface of the inclined concrete retaining wall to be used as a load bearing concrete (32). This is the same principle as the fork tray, so it is not necessary to install a separate formwork, so construction is easy. The slab and the soil it fills up are far from the support point A, which is very effective in ensuring safety.

본 변형예에서 콘크리트 역삼각뿔(31)을 형성하는 것은 보강 공법과 마찬가지이고 신설공법일 경우에는 처음부터 기초의 크기를 알맞게 설계할 수 있으므로 별도의 말뚝(12)을 설치하지 않아도 되지만 기초의 크기를 줄이기 위해 말뚝을 설치해도 무방하다.In the present modified example, the formation of the concrete inverted triangular pyramid 31 is the same as the reinforcement method, and in the case of the new construction method, since the size of the foundation can be appropriately designed from the beginning, it is not necessary to install a separate pile 12, but the size of the foundation You can install a pile to reduce it.

본 변형예에서는 옹벽의 상단에 슬래브(33)를 설치하는 것은 필수적이지만 신설하는 구조물이므로 상기 슬래브(33)의 옹벽의 반대쪽에 키(34, key)를 추가로 더 설치하면 옹벽의 안전성이 더 보장되고 상기 키(34)를 옹벽 위 대지에 신설되는 구조물의 일부로 활용하면 구조물의 하중까지 옹벽의 안전에 기여하게 된다.In the present modification, it is essential to install the slab 33 on the top of the retaining wall, but since it is a new structure, additional key 34 on the opposite side of the retaining wall of the slab 33 further ensures the safety of the retaining wall. If the key 34 is used as a part of the new structure on the retaining wall, it contributes to the safety of the retaining wall until the load of the structure.

본 발명은 기존 석축 위에 콘크리트로 된 역삼각뿔을 형성시킴으로서 기존 석축을 효과적으로 보강할 수 있다. 기존 석축이 대개 건축물이 밀집하고 대지가 좁은 지역에 있어 철거하고 다시 설치하기가 매우 곤란했지만 본 발명을 사용하면 쉽게 보강할 수 있다. 그리고 기존 석축이나 옹벽이 밋밋한 형태를 가져 도시 미관상 호감을 주지 않는데 비해 본 발명의 형태는 삼각뿔 형태를 가져 돌출감과 질감이 있고 각 면을 여러 가지 색깔로 처리할 수 있어 도시 미관을 좋게 하는 효과도 있다. 또한 옹벽 상부를 대지로 활용할 수 있는 수단도 제공하게 되었다.The present invention can effectively reinforce the existing masonry by forming an inverted triangular pyramid of concrete on the existing masonry. Existing stone masonry is usually difficult to demolish and re-install because the building is dense and the site is narrow, it can be easily reinforced using the present invention. In addition, the existing stone masonry or retaining wall has a flat shape, which does not give a good aesthetic appearance, while the shape of the present invention has a triangular pyramid shape, which has a sense of protrusion and texture, and each surface can be treated in various colors, thereby improving the aesthetic appearance of the city. . It also provided a means to utilize the upper part of the retaining wall as a site.

신설 옹벽에 적용하는 변형예는 흙파기 량을 대폭 줄이며 옹벽 상부의 대지의 활용도를 높이고 옹벽 상부에 설치되는 구조물의 하중을 옹벽 구조에 활용함으로서 경제적으로 옹벽을 건설할 수 있게 되었다.The modifications applied to the new retaining wall can significantly reduce the amount of excavation, increase the utilization of the land at the top of the retaining wall, and make the retaining wall economically by utilizing the load of the structure installed on the retaining wall.

Claims (8)

기존 석축(1)의 기초(2)를 관통하여 지지 말뚝(12)을 심고;Planting the support pile 12 through the foundation 2 of the existing stone shaft 1; 상기 말뚝(12)이 꼭지점이 되는 콘크리트 역삼각뿔(11)을 상기 기존 석축(1)과 일체가 되도록 형성하는 단계;Forming a concrete inverted triangular pyramid (11) at which the pile (12) is a vertex to be integrated with the existing stone stack (1); 로 이루어지는 것을 특징으로 하는 기존 석축의 보강방법.Reinforcement method of the existing masonry, characterized in that consisting of. 제1항에서, 상기 기존 석축(1)의 상단과 상기 콘크리트 역삼각뿔(11)을 덮는 콘크리트 슬래브(13)를 더 형성하는 것을 특징으로 하는 기존 석축의 보강방법.2. The method according to claim 1, further comprising a concrete slab (13) covering the upper end of the existing stone (1) and the concrete inverted triangular pyramid (11). 제1항에서, 상기 콘크리트 역삼각뿔(11)은 상기 기존 석축(1)의 경사면에 기둥(21)과 프레임(22)을 설치하고 상기 철재(12)의 끝을 타이 빔(23)으로 연결하여 역삼각뿔을 형성하고;In claim 1, the concrete inverted triangular pyramid (11) is installed on the inclined surface of the existing stone shaft (1), the pillar 21 and the frame 22 is installed by connecting the end of the steel 12 with a tie beam (23) Forms an inverted triangular pyramid; 상기 기둥(21)과 상기 프레임(22)과 상기 타이 빔(22)으로 만들어지는 역삼각뿔의 경사면 평면에 수평철근 및 수직철근을 배근하고;Reinforcing horizontal and vertical rebars on the inclined plane of the inverted triangular pyramid made of the pillars 21, the frames 22 and the tie beams 22; 상기 기둥(21)과 상기 프레임(22)과 상기 타이 빔(23)을 만들어지는 역삼각뿔의 표면에 ㅅ-자형 철근(25)을 돌출 배근하고;Projecting and reinforcing the S-shaped reinforcement 25 on the surface of the inverted triangular pyramid from which the pillar 21, the frame 22, and the tie beam 23 are made; 상기 ㅅ-자형 철근(25) 위에 리브 라스(26, Rib Lath)를 설치하고; 그리고Installing a rib lath (26) on the S-shaped rebar (25); And 상기 ㅅ-자형 철근(25)을 배근한 내부 공간에 콘크리트를 타설하는 단계;Placing concrete in an inner space in which the S-shaped rebar 25 is disposed; 로 콘크리트 역삼각뿔(11)을 형성하는 것을 특징으로 하는 기존 석축의 보강방법.Reinforcement method of the existing stonework, characterized in that to form a concrete inverted triangular pyramid (11). 제3항에서, 상기 기존 석축(1)의 경사면에서 상기 기둥(21)과 상기 프레임(22)과 상기 타이 빔(23)을 만들어지는 경사면 평면 외의 경사면에 리브 라스(26)를 부착하고; 그리고A rib lath (26) is attached to an inclined surface other than the inclined surface on which the pillar (21), the frame (22) and the tie beam (23) are made on the inclined surface of the existing stone shaft (1); And 상기 리브 라스(26)가 부착된 경사면에 상기 리브 라스(26) 사이에 콘크리트를 타입하는 단계;Type concrete between the rib laths (26) on the inclined surface to which the rib laths (26) are attached; 를 더 포함하는 것을 특징으로 하는 기존 석축의 보강방법.Reinforcement method of the existing stonework, characterized in that it further comprises. 제3항 또는 제4항에서, 쇼트크리트(Shotcrete)를 쏘아붙이는 단계를 더 포함하는 것을 특징으로 하는 기존 석축의 보강방법.The method according to claim 3 or 4, further comprising the step of shooting shotcrete (Shotcrete). 옹벽 하단부 경질지반(3a)을 굴착할 때 경사면을 그대로 둔 채 기초(2)를 설치하고;When excavating the retaining wall lower end hard ground 3a, the foundation 2 is provided with the slope intact; 역삼각뿔(31)을 가진 경사면 옹벽(30)을 설치하고;An inclined retaining wall 30 having an inverted triangular pyramid 31 is installed; 상기 경질지반(3a) 상부의 연약지반(3b)에 도달하면 경사면을 완만하게 정리하고;When the hard ground (3a) is reached to the soft ground (3b) to gently clean up the inclined surface; 상기 경사면 옹벽 후면에 철근콘그리트 기초 겸 슬래브를 부착하여 짐받이 콘크리트(32)를 설치하고;Attaching reinforced concrete foundation and slab to the rear surface of the inclined retaining wall to install the bearing concrete (32); 상기 짐받이 콘크리트(32) 위에 잡석 또는 흙으로 경사면을 조정하고;Adjusting the inclined surface with rubble or soil on the bearing concrete (32); 상기 역삼각뿔(31)을 가진 경사면 옹벽을 완성하는 단계;Completing an inclined retaining wall having the inverted triangular pyramid (31); 로 공사하는 것을 특징으로 하는 신설 옹벽의 공사방법.Construction method of new retaining wall characterized in that constructing by. 제6항에서, 상기 역삼각뿔(31)을 가진 옹벽(30)의 상단에 슬래브(33)를 더 설치하는 것을 특징으로 하는 신설 옹벽의 공사방법.The method of claim 6, wherein the slab (33) is further provided on the top of the retaining wall (30) having the inverted triangular pyramid (31). 제7항에서, 상기 슬래브(33)의 옹벽의 반대쪽에 키(34, key)를 추가로 더 설치하는 것을 특징으로 하는 신설 옹벽의 공사방법.8. The method for constructing a new retaining wall according to claim 7, further comprising a key (34, key) on the opposite side of the retaining wall of the slab (33).
KR1019990035997A 1999-08-27 1999-08-27 The SEN Retaining Wall KR100346947B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1019990035997A KR100346947B1 (en) 1999-08-27 1999-08-27 The SEN Retaining Wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1019990035997A KR100346947B1 (en) 1999-08-27 1999-08-27 The SEN Retaining Wall

Publications (2)

Publication Number Publication Date
KR20010019548A KR20010019548A (en) 2001-03-15
KR100346947B1 true KR100346947B1 (en) 2002-07-31

Family

ID=19609036

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1019990035997A KR100346947B1 (en) 1999-08-27 1999-08-27 The SEN Retaining Wall

Country Status (1)

Country Link
KR (1) KR100346947B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106836275A (en) * 2017-04-13 2017-06-13 中国地质科学院探矿工艺研究所 Landscape eco-friendly retaining wall for rapidly protecting tillite slope and implementation method

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107974876A (en) * 2017-12-14 2018-05-01 中铁二院工程集团有限责任公司 Existing railway increases road construction dike multiline pile earth-retaining construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106836275A (en) * 2017-04-13 2017-06-13 中国地质科学院探矿工艺研究所 Landscape eco-friendly retaining wall for rapidly protecting tillite slope and implementation method
CN106836275B (en) * 2017-04-13 2019-04-12 中国地质科学院探矿工艺研究所 Landscape eco-friendly retaining wall for rapidly protecting tillite slope and implementation method

Also Published As

Publication number Publication date
KR20010019548A (en) 2001-03-15

Similar Documents

Publication Publication Date Title
US6280121B1 (en) Reinforced retaining wall
AU2014237379B2 (en) Precast concrete retaining wall
US6050749A (en) Concrete masonry unit for reinforced retaining wall
CN104988948A (en) Rib plate type retaining wall and construction method thereof
CN211200426U (en) Anti-sliding supporting and retaining structure for miniature steel pipe pile retaining wall
JP5259510B2 (en) Retaining wall and its construction method
KR100473375B1 (en) Retaining wall using phc pile
CN207987961U (en) A kind of rockmass high slope anchor pole and earth-retaining wall composite construction
KR100346947B1 (en) The SEN Retaining Wall
CN1036729C (en) The method of supporting deep-foundation side wall
KR102116085B1 (en) A Eco-friendly retain wall structure
KR100447331B1 (en) execution method of landscape architecture for cutting ground using blasting stone and landscape architecture apparatus using the same
KR101045019B1 (en) Installation structure of block type breast wall and its construction method
JP6860895B2 (en) Retaining wall and its construction method
KR200167837Y1 (en) The sen retaining wall
KR200413303Y1 (en) Stone stacked wall structure using steel beam
CN211228589U (en) Retaining structure
KR20020028527A (en) A concrete brick and constructing method thereof
KR100383124B1 (en) Method of Constructing Stons for Embankment
CN219118228U (en) Assembly type soil retaining greening water permeable member
KR102285192B1 (en) A Eco-friendly retain wall structure
KR102600811B1 (en) Artificial stone stacking structure for holding wall and construction method for holding
KR102605191B1 (en) Upper part reinforcement type retaining wall structure and retaining wall construction method
KR101058628B1 (en) Retaining wall construction structure using landscape stones
KR200424468Y1 (en) latticed assembly of retaing wall with soil nailing

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20060616

Year of fee payment: 5

LAPS Lapse due to unpaid annual fee