KR101025320B1 - Apparatus for forming underground dome concrete structure and constructing method using the same - Google Patents

Apparatus for forming underground dome concrete structure and constructing method using the same Download PDF

Info

Publication number
KR101025320B1
KR101025320B1 KR1020100140353A KR20100140353A KR101025320B1 KR 101025320 B1 KR101025320 B1 KR 101025320B1 KR 1020100140353 A KR1020100140353 A KR 1020100140353A KR 20100140353 A KR20100140353 A KR 20100140353A KR 101025320 B1 KR101025320 B1 KR 101025320B1
Authority
KR
South Korea
Prior art keywords
dome
foam
concrete structure
forming
underground
Prior art date
Application number
KR1020100140353A
Other languages
Korean (ko)
Inventor
고엄식
김대황
Original Assignee
(주)유경기술단
고엄식
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)유경기술단, 고엄식 filed Critical (주)유경기술단
Priority to KR1020100140353A priority Critical patent/KR101025320B1/en
Application granted granted Critical
Publication of KR101025320B1 publication Critical patent/KR101025320B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/04Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for structures of spherical, spheroid or similar shape, or for cupola structures of circular or polygonal horizontal or vertical section; Inflatable forms
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/32Arched structures; Vaulted structures; Folded structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • E04G11/22Sliding forms raised continuously or step-by-step and being in contact with the poured concrete during raising and which are not anchored in the hardened concrete; Arrangements of lifting means therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

PURPOSE: An apparatus for forming a domed underground concrete structure and a construction method using the same are provided to achieve excellent durability and waterproofing performance of a domed underground concrete structure by preventing discontinuous faces. CONSTITUTION: An apparatus for forming a domed underground concrete structure comprises vertical supports(100) which are installed on the floor of a domed section, pulling members(200) which are installed on the top of the vertical supports, a dome side molding form(300) for molding the lateral side of a dome, a dome top molding form(400) which is raised and lowered by the pulling members, and a jack support(500) which is vertically installed on the floor of the domed section and supports the bottom of the dome top molding form raised by the pulling members up to the forming position.

Description

지하 돔 콘크리트 구조물의 성형장치 및 이를 이용한 시공방법{Apparatus for forming underground dome concrete structure and constructing method using the same}Apparatus for forming underground dome concrete structure and constructing method using the same}

본 발명은 지하 돔 콘크리트 구조물을 신속하고 간편하게 시공할 수 있도록 한 지하 돔 콘크리트 구조물의 성형장치 및 이를 이용한 시공방법에 관한 것이다.The present invention relates to a molding apparatus for a basement dome concrete structure and a construction method using the same so that the construction of the underground dome concrete structure quickly and simply.

일반적으로 도심지 또는 산악지역의 교통시설, 하수처리장, 분묘처리장, 방사성 폐기물 처리시설 등은 지하에 돔 콘크리트 구조물을 갖추고 있다.Generally, transportation facilities, sewage treatment plants, graveyard treatment plants, and radioactive waste treatment facilities in urban or mountain areas are equipped with a dome concrete structure underground.

이러한 지하 돔 콘크리트 구조물은 지하에 돔부를 굴착한 다음, 굴착된 돔부에 거푸집을 설치하고 콘크리트를 타설하여 돔 콘크리트 구조물을 완성하는 순서로 시공된다.The underground dome concrete structure is constructed in the order to excavate the dome in the basement, and then install the formwork in the excavated dome portion and cast concrete to complete the dome concrete structure.

종래의 지하 돔 콘크리트 구조물의 시공은 국내등록특허 제10-0833527호의 "캡슐형 또는 동굴형 지하구조물의 미경화 콘크리트 성형틀"을 통해 알려져 있다.The construction of the conventional underground dome concrete structure is known through the "uncured concrete molding frame of the capsule-type or cave-type underground structure" of Korean Patent No. 10-0833527.

도 1에 도시된 바와 같이, 종래의 돔 콘크리트 구조물의 시공은 굴착된 캡슐형 또는 동굴형 지하구조물 내에서 요크장치(11)를 매개로 구동되는 작동잭(12)을 통해 미들데크(13)와 행거데크(14)가 슬라이딩 이동하면서 단계적으로 돔부의 수직벽체면(10a)을 성형하고, 상기 미들데크(13)와 행거데크(14)의 상부에 일체화된 아치데크(15)를 설치하여 돔부의 천정면을 성형하도록 구성되어 있다.As shown in FIG. 1, the construction of a conventional dome concrete structure includes a middle deck 13 and an operation jack 12 driven through a yoke device 11 in an excavated capsule or cave type underground structure. As the hanger deck 14 slides and moves, the vertical wall surface 10a of the dome portion is formed step by step, and the arch deck 15 integrated with the middle deck 13 and the hanger deck 14 is installed to install the dome portion. It is comprised so that a ceiling surface may be shape | molded.

이와 같은 성형틀은 기존의 동바리를 이용한 거푸집 설치작업을 생략함으로써 빠른 시공이 이루어지도록 기대하고 있으나, 다음과 같은 많은 문제점이 있다.Such a molding mold is expected to be made quickly by eliminating the formwork installation work using the existing copper bar, but there are many problems as follows.

첫째, 성형이 완료된 이후 해체작업이 매우 까다롭다는 문제가 있다.First, there is a problem that the dismantling work is very difficult after the molding is completed.

즉, 작동잭(12) 및 요크장치(11)가 미경화콘크리트 타설공간에 위치되어 있기 때문에 일단 상승된 아치데크(15)와 미들데크(13)와 행거데크(14)는 미경화콘크리트가 타설된 상태에서는 하강이 불가능하다. 따라서, 작업자는 돔부의 천정면의 성형이 완료된 후에 고소에 위치된 아치데크(15)를 비롯하여 미들데크(13)와 행거데크(14)의 해체작업을 수행하여야 하므로 작업환경이 매우 까다롭고 안전사고의 위험도 대단히 높다. 아울러, 고소에서 해체된 장비들을 돔부의 바닥까지 견인할 수 있는 대형장비가 필수적으로 요구된다.That is, since the operation jack 12 and the yoke device 11 are located in the unhardened concrete placing space, the uncured concrete is poured into the arch deck 15, the middle deck 13, and the hanger deck 14 once raised. It is impossible to descend in the closed state. Therefore, the operator has to perform the dismantling work of the middle deck 13 and the hanger deck 14 including the arch deck 15 located at the height after completion of the molding of the ceiling surface of the dome part, so that the working environment is very demanding and safety accident The risk is also very high. In addition, large equipment capable of towing the equipment dismantled at the height to the bottom of the dome is essential.

둘째, 미경화콘크리트가 아치데크(15)로 타설되면 작동잭(12)만으로는 엄청난 하중의 아치데크(15)를 지탱할 수 없기 때문에 수직벽체면(10a)에 별도의 지지물(20)들을 설치하고 상기 지지물(20)들을 미들데크(13) 단부에 고정시켜 행거데크(14)를 지탱하도록 해야 하는데, 이와 같은 지지물(20)들의 설치로 인해 다음과 같은 많은 문제점이 발생된다.Second, when the unhardened concrete is cast into the arch deck 15, since the operation jack 12 alone cannot support the arch deck 15 with a great load, the additional support 20 is installed on the vertical wall surface 10a. The supports 20 should be fixed to the ends of the middle deck 13 so as to support the hanger deck 14, and the installation of the supports 20 causes many problems as follows.

우선, 다수의 지지물(20)들을 수직벽체면(10a)에 체결시키는 과정에서 수직벽체면(10a)이 손상되는 문제와 추후 이를 보수해야 하는 추가작업의 문제가 발생된다.First of all, in the process of fastening the plurality of supports 20 to the vertical wall surface 10a, a problem of damage to the vertical wall surface 10a and a problem of additional work to be repaired later occurs.

그리고, 수직벽체면(10a)의 성형을 위해 타설된 미경화콘크리트가 완전히 경화될 때까지 장시간을 대기하여야 하므로 작업이 장기화되는 문제가 있다.In addition, since a long time should be waited until the uncured concrete poured for the molding of the vertical wall surface 10a is completely cured, there is a problem in that the work is prolonged.

또한, 이후 돔상부벽체면의 성형을 위해 아치데크(15)로 타설되는 미경화콘크리트와 완전히 경화된 수직벽체면(10a) 상단면 사이에 타설경계면이 생기는 문제가 발생된다. 타설경계면은 콘크리트 구조물에 불연속면을 제공함으로써 구조물의 내구성을 떨어뜨리고 방수성을 취약하게 만드는 대표적인 인자임을 감안할 때 시공된 콘크리트 구조물의 내구성과 방수성이 크게 불량해진다.In addition, a problem arises that a pour boundary surface is formed between the uncured concrete that is poured into the arch deck 15 and the top surface of the hardened vertical wall surface 10a to form the dome upper wall surface. Considering that the pour boundary is a representative factor that reduces the durability of the structure by providing a discontinuous surface to the concrete structure and makes the waterproofness weak, the durability and waterproofness of the constructed concrete structure are greatly deteriorated.

뿐만 아니라, 상기 지지물(20)은 수직벽체면(10a)에 체결되는 구조로 이루어져 있기 때문에 아치데크(15)로부터 전달되는 수직하중을 효과적으로 지지해주지 못하는 구조적 취약점을 안고 있다. 따라서, 상기 지지물(20)들이 아치데크(15)로 타설된 미경화콘크리트로부터 전달되는 엄청난 하중을 감당하지 못하면서 파손될 경우 내부의 성형구조물 전체가 붕괴되는 심각한 조업사고로 이루어질 수도 있다.In addition, the support 20 has a structural weakness that does not effectively support the vertical load transmitted from the arch deck 15 because it is made of a structure that is fastened to the vertical wall surface (10a). Therefore, the support 20 may be a serious operation accident in which the entire molded structure collapses when the support 20 is broken while failing to bear the enormous load transmitted from the uncured concrete cast into the arch deck 15.

국내등록특허공보 제10-0833527호(2007.11.01. 공개)Domestic Patent Publication No. 10-0833527 (published Nov. 1, 2007)

본 발명은 상기한 문제점들을 해결하기 위해 안출된 것으로서, 지하 돔 콘크리트 구조물의 시공이 신속하고 연속적으로 이루어지도록 한 지하 돔 콘크리트 구조물의 성형장치 및 이를 이용한 시공방법을 제공하는데 그 목적이 있다.The present invention has been made to solve the above problems, an object of the present invention is to provide a molding apparatus and construction method using the underground dome concrete structure to make the construction of the underground dome concrete structure quickly and continuously.

또한, 본 발명은 성형폼의 지지구조가 구조적으로 안정할 뿐만 아니라, 수직벽체면을 손상시키지 않으면서 간단한 구조로 이루어지게 되는 지하 돔 콘크리트 구조물의 성형장치 및 이를 이용한 시공방법을 제공하는데 그 목적이 있다.In addition, the present invention is to provide a molding apparatus and construction method using the underground dome concrete structure that is not only structurally stable, but also a simple structure without damaging the vertical wall surface. have.

또한, 본 발명은 해체가 용이한 지하 돔 콘크리트 구조물의 성형장치 및 이를 이용한 시공방법을 제공하는데 그 목적이 있다.In addition, an object of the present invention is to provide an apparatus for forming a underground dome concrete structure easy to dismantle and a construction method using the same.

상기 목적을 달성하기 위해, 본 발명의 지하 돔 콘크리트 구조물의 성형장치는 돔부의 바닥에 설치된 복수의 수직지지대와, 상기 수직지지대의 상단에 고정 설치된 견인부재와, 돔 측부를 성형하는 돔 측부성형폼과, 상기 견인부재를 통해 승강하는 돔 상부성형폼과, 상기 견인부재를 통해 성형위치까지 상승한 상기 성형폼의 하단을 지지해주도록 상기 돔부의 바닥에 수직으로 설치되는 잭서포트을 포함하여 구성됨을 특징으로 한다.In order to achieve the above object, the molding apparatus of the underground dome concrete structure of the present invention is a plurality of vertical supports installed on the bottom of the dome portion, the traction member fixed to the upper end of the vertical support, and the dome side forming foam for forming the dome side And a jack support installed vertically on the bottom of the dome portion to support the lower end of the dome forming mold, which is elevated through the towing member, and the lower end of the forming foam raised to the molding position through the towing member. do.

그리고 본 발명의 지하 돔 콘크리트 구조물의 성형방법은 굴착된 돔부의 바닥에 수직지지대들이 설치되는 단계와, 상기 수직지지대를 통해 견인부재가 설치되는 단계와, 돔부의 바닥에서 돔 측부성형폼이 조립되는 단계와, 돔부의 바닥에서 돔 상부성형폼이 가조립되는 단계와, 돔 측부성형폼으로 타설되는 미경화콘크리트에 의해 돔 측부에 콘크리트 구조물이 성형되는 단계와, 상기 견인부재에 의해 돔 상부성형폼이 성형위치까지 상승되는 단계와, 돔 상부성형폼의 조립이 완료되는 단계와, 돔부 바닥에 잭서포트가 설치되어 돔 상부성형폼의 하단이 지지되는 단계와, 돔 상부성형폼으로 타설되는 미경화콘크리트에 의해 돔 상부에 콘크리트 구조물이 성형되는 단계를 포함하여 구성된다.And the method of forming the underground dome concrete structure of the present invention is the step of installing vertical supports on the bottom of the excavated dome portion, the step of installing the towing member through the vertical support, the dome side forming foam is assembled from the bottom of the dome portion A step of preliminarily assembling the dome upper forming foam at the bottom of the dome part, forming a concrete structure on the dome side by uncured concrete poured into the dome side forming foam, and the dome upper forming foam by the towing member. The step of raising to the molding position, the step of assembling the dome upper forming foam is completed, the jack support is installed on the bottom of the dome part to support the lower end of the upper dome forming foam, and the uncured concrete cast into the dome upper forming foam. It is configured to include the step of forming a concrete structure on top of the dome.

상기와 같이 구성된 본 발명의 지하 돔 콘크리트 구조물의 성형장치 및 이를 이용한 시공방법에 따르면, 성형폼에 가해지는 하중이 잭서포트를 통해 분산되므로 종래와는 달리 아치데크를 지지시키기 위한 별도의 지지부재를 돔 측부에 형성된 콘크리트 구조물에 설치하거나 이를 위해 돔 측부에 형성된 콘크리트 구조물의 양생이 완료될 때까지 장시간을 대기하지 않아도 되고 시공과정에서는 잭로드와 요크부재를 해체하지 않아도 된다.According to the molding apparatus of the underground dome concrete structure of the present invention configured as described above and the construction method using the same, since the load applied to the molding foam is distributed through the jack support, a separate support member for supporting the arch deck unlike the conventional It is not necessary to wait for a long time until it is installed on the concrete structure formed on the dome side or curing of the concrete structure formed on the dome side, and it is not necessary to dismantle the jack rod and yoke member in the construction process.

따라서, 연속적인 시공이 가능해지면서 시공기간을 크게 단축할 수 있는 효과가 있으며, 이로 인해 타설경계면이 발생되지 않아 완성된 콘크리트구조물의 내구성과 방수성이 매우 뛰어난 효과가 있고, 지지부재를 설치하는 과정에서 설치면에 손상을 가하고 손상된 부위를 보수해야 하는 작업도 뒤따르지 않아 종래에 비해 작업성이 매우 뛰어난 효과도 기대할 수 있다.Therefore, the continuous construction is possible, and the construction period can be greatly shortened. As a result, no pour boundary surface is generated, so the durability and waterproofness of the finished concrete structure are very excellent, and in the process of installing the supporting member. Damage to the installation surface and repair work to the damaged site is not followed, the workability is very excellent compared to the conventional can be expected.

또한, 본 발명은 성형이 완료된 이후에도 견인부재가 여전히 성형폼을 지지해주고 있으므로 성형폼을 바닥까지 하강시켜 해체작업을 수행할 수 있게 되므로 종래와는 달리 고소에서 해체된 장비들을 돔부의 바닥까지 견인하는 대형장비가 요구되지 않는 것은 물론 해체작업이 매우 용이하고 고소에서의 작업이 배제되므로 안전사고의 위험을 최소화할 수 있는 효과가 있다.In addition, the present invention, since the towing member is still supporting the molding foam even after the molding is completed, it is possible to perform the dismantling work by lowering the molding foam to the floor, unlike conventional, towing the equipment dismantled at the height to the bottom of the dome Not only does not require large equipment, but also the dismantling work is very easy and the work at the height is excluded, thereby minimizing the risk of safety accidents.

도 1은 종래의 다른 지하 돔 콘크리트 구조물 성형장치의 사용상태 단면도.
도 2는 본 발명에 따른 지하 콘크리트 구조물 성형장치의 사용상태 단면도.
도 3은 본 발명에 따른 지하 콘크리트 구조물 성형장치의 사용상태 평면도.
도 4는 도 2의 Ⅳ-Ⅳ선에 따른 단면도.
도 5는 본 발명에 따른 지하 콘크리트 구조물 성형장치의 사용상태 단면도로서 수직지지대가 성형폼의 내측에 위치된 상태를 나타내는 도면.
도 6은 본 발명을 구성하는 견인부재의 일예를 나타내는 도면.
도 7은 본 발명을 구성하는 성형폼와 돔부의 벽면의 요부단면 상세도.
도 8은 본 발명을 구성하는 성형폼의 다른 실시예를 나타내는 요부단면 상세도.
도 9는 본 발명에 따른 지하 콘크리트 구조물 성형장치의 사용상태 단면도로서, 돔 상부성형폼이 철골프레임만으로 가조립상태를 나타내는 도면.
도 10은 본 발명에 따른 지하 콘크리트 구조물 성형장치의 사용상태 단면도로서, 돔 상부성형폼이 돔 측부성형폼의 상단 이상의 높이에 대해서만 정상대로 조립된 상태를 나타내는 도면.
도 11은 본 발명을 구성하는 돔 상부성형폼의 다른 실시예에 따른 지하 콘크리트 구조물 성형장치의 사용상태 단면도.
도 12는 도 11의 ⅩⅡ-ⅩⅡ선에 따른 단면도.
도 13a 내지 13h는 각각 본 발명에 따라 지하 돔 콘크리트 구조물을 시공하는 과정을 순서대로 나타내는 도면.
도 14a 내지 14i는 각각 본 발명의 다른 실시예에 따라 지하 돔 콘크리트 구조물을 시공하는 과정을 순서대로 나타내는 도면.
1 is a cross-sectional view of the use of the conventional conventional underground dome concrete structure forming apparatus.
Figure 2 is a cross-sectional view of the use state of the underground concrete structure forming apparatus according to the present invention.
Figure 3 is a plan view of the use state of the underground concrete structure forming apparatus according to the present invention.
4 is a cross-sectional view taken along line IV-IV of FIG. 2;
5 is a cross-sectional view showing a state in which the vertical support is positioned inside the forming foam as a state of use of the apparatus for forming an underground concrete structure according to the present invention.
Figure 6 is a view showing an example of the traction member constituting the present invention.
Figure 7 is a sectional view of the main portion of the wall surface of the molded foam and the dome portion constituting the present invention.
8 is a sectional view showing the main portion of another embodiment of the molding foam constituting the present invention.
9 is a cross-sectional view showing the state of use of the apparatus for forming an underground concrete structure according to the present invention.
10 is a cross-sectional view showing a state of use of the apparatus for forming an underground concrete structure according to the present invention, in which the dome upper forming foam is assembled as normal only for a height higher than the upper end of the dome side forming foam.
Figure 11 is a cross-sectional view of the use of the apparatus for forming the underground concrete structure according to another embodiment of the dome upper forming foam constituting the present invention.
12 is a cross-sectional view taken along the line II-XIII of FIG. 11.
Figure 13a to 13h is a view showing in sequence the process of constructing the underground dome concrete structure according to the present invention, respectively.
Figures 14a to 14i are views showing in sequence the process of constructing an underground dome concrete structure according to another embodiment of the present invention, respectively.

본 발명의 특징 및 이점들은 첨부도면에 의거한 다음의 바람직한 실시예에 대한 상세한 설명으로 더욱 명백해질 것이다. 이에 앞서, 본 명세서 및 청구범위에 사용된 용어나 단어는 발명자가 그 자신의 발명을 가장 최선의 방법으로 설명하기 위해 용어의 개념을 적절하게 정의할 수 있다는 원칙에 입각하여 본 발명의 기술적 사상에 부합하는 의미와 개념으로 해석되어야만 한다.The features and advantages of the present invention will become more apparent from the following detailed description of preferred embodiments with reference to the accompanying drawings. Prior to this, the terms or words used in the present specification and claims are defined in the technical spirit of the present invention on the basis of the principle that the inventor can appropriately define the concept of the term in order to explain his invention in the best way. It must be interpreted to mean meanings and concepts.

이하, 본 발명의 일 실시예를 도면을 참조하여 상세히 설명함에 있어, 동일한 구성에 대해서는 동일한 부호를 사용하며, 명료성을 위하여 가능한 중복되지 않게 상이한 부분만을 주로 설명한다.DETAILED DESCRIPTION Hereinafter, one embodiment of the present invention will be described in detail with reference to the drawings. Like reference numerals refer to like elements, and only different parts will be mainly described so as not to overlap for clarity.

도 2 내지 도 4에 도시된 바와 같이, 본 발명에 따른 지하 돔 콘크리트 구조물의 성형장치는 돔부의 바닥에 설치된 복수의 수직지지대(100)와, 상기 수직지지대(100)의 상단에 고정 설치된 견인부재(200)와, 돔 측부를 성형하는 돔 측부성형폼(300)과, 상기 견인부재(200)를 통해 승강하는 일체형 돔 상부성형폼(400)과, 상기 견인부재(200)를 통해 성형위치까지 상승한 상기 돔 상부성형폼(400)의 하단을 지지해주도록 상기 돔부의 바닥에 수직으로 설치되는 잭서포트(500)로 구성된다.As shown in Figures 2 to 4, the molding apparatus of the underground dome concrete structure according to the present invention is a plurality of vertical support 100 is installed on the bottom of the dome portion, the traction member is fixed to the upper end of the vertical support 100 200, the dome side forming foam 300 for forming the dome side, the integrated dome upper forming foam 400 which is elevated through the towing member 200, and to the molding position through the towing member 200 It is composed of a jack support 500 which is installed perpendicular to the bottom of the dome portion to support the lower end of the dome upper forming foam (400).

상기 수직지지대(100)는 돔부의 바닥 가장자리를 따라 일정간격으로 원형배치되며, 돔 상부성형폼(400)의 하중을 상당부분 감당하여야 하므로 돔 상부성형폼(400)의 하중을 감안하여 설치수량을 결정하도록 한다.The vertical support 100 is circularly arranged at regular intervals along the bottom edge of the dome part, and the amount of installation in consideration of the load of the dome upper forming foam 400 is required because the load of the dome upper forming foam 400 must be substantially covered. Make a decision.

상기 수직지지대(100)는 도 2에 도시된 바와 같이 이후 조립될 돔 상부성형폼(400)의 외측에 설치될 수도 있고, 도 5에 도시된 바와 같이 조립될 돔 상부성형폼(400)의 내측에 설치될 수도 있다. 이와 같이 상기 수직지지대(100)가 조립될 돔 상부성형폼(400)의 내측과 설치되는 경우, 수직지지대(100)가 미경화콘크리트 타설위치에서 벗어나게 되므로 성형작업이 완료된 이후 수직지지대(100)를 재사용이 가능한 이점이 있다. 본 실시예에서는 수직지지대(100)가 성형폼의 외측에 설치된 것을 도시하고 설명한다.The vertical support 100 may be installed outside the dome top forming foam 400 to be assembled later, as shown in Figure 2, the inner side of the dome top forming foam 400 to be assembled as shown in FIG. It can also be installed in. As such, when the vertical support 100 is installed with the inner side of the dome upper forming foam 400 to be assembled, the vertical support 100 is moved out of the uncured concrete placing position, so that the vertical support 100 is completed after the molding operation is completed. There is an advantage that can be reused. In this embodiment, it is shown and described that the vertical support 100 is installed on the outside of the forming foam.

상기 수직지지대(100)의 상부에는 돔 상부성형폼(400)을 승강시키기 위한 견인부재(200)가 설치된다. 그리고 상기 수직지지대(100)는 돔부의 바닥에 설치된 보조수직지지대(110)를 통해 더욱 견고하게 지지되도록 할 수도 있다.The upper portion of the vertical support 100 is provided with a traction member 200 for elevating the dome upper forming foam 400. The vertical support 100 may be supported more firmly through the auxiliary vertical support 110 installed at the bottom of the dome.

상기 견인부재(200)는 수직지지대(100)의 상단에 설치되며 돔 상부성형폼(400)에 형성된 개구부(401)를 통과하여 돔 상부성형폼(400)의 하단에 연결된 잭로드(210)와, 상기 수직지지대(100)의 상부에 설치되어 상기 잭로드(210)와 협동하면서 상기 돔 상부성형폼(400)을 수직으로 상승시키는 유압잭(220)으로 구성된다.The towing member 200 is installed on the upper end of the vertical support 100 and the jack rod 210 connected to the lower end of the dome upper forming foam 400 through the opening 401 formed in the dome upper forming foam 400 and The hydraulic jack 220 is installed above the vertical support 100 to vertically lift the dome upper forming foam 400 while cooperating with the jack rod 210.

또한, 도 6에 도시된 바와 같이, 상기 견인부재(200)는 돔 상부성형폼(400)의 하단에 고정된 견인로프(230)와, 수직지지대(100)의 상부에 설치되며 돔 상부성형폼(400)에 형성된 개구부(401)를 통과한 견인로프(230)가 권취된 견인도르레(240)와, 상기 견인도르레(240)를 구동시키는 구동모터(250)로 구성될 수도 있다.In addition, as shown in Figure 6, the towing member 200 is a towing rope 230 fixed to the lower end of the dome upper forming foam 400, and is installed on the upper portion of the vertical support 100 and the dome upper forming foam The tow rope 230 passing through the opening 401 formed in the 400 may be configured to be a tow pulley 240 wound up, and a drive motor 250 to drive the tow pulley 240.

본 발명에 따르면, 돔부의 바닥에는 돔 측부성형폼(300)을 지지해 주면서 성형 완료된 콘크리트 구조물의 구조적 강도를 향상시켜 주기 위한 수직철물(120)들이 설치된다. 상기 수직철물(120)은 돔부의 바닥에 매설된 상태로 설치되는 것이 바람직하며, 별도의 간격유지구(111)를 통해 돔 측부성형폼(300)과 일정거리를 유지하도록 조립된다. 그리고, 수직철물(120)들은 별도의 연결철물(112)을 통해 상호연결되도록 하는 것이 바람직하다.According to the present invention, vertical hardware 120 is installed at the bottom of the dome to support the dome side forming foam 300 and improve the structural strength of the finished concrete structure. The vertical hardware 120 is preferably installed in the state of being buried in the bottom of the dome, it is assembled to maintain a certain distance with the dome side forming foam 300 through a separate spacing holding 111. And, the vertical hardware 120 is preferably to be interconnected through a separate connecting hardware (112).

한편, 상기 수직철물(120)은 구조적 강도를 향상시키도록 상,하부가 개방된 중공의 프레임과 상기 중공부에 콘크리트가 충전된 구조를 갖도록 하는 것이 바람직하다.On the other hand, the vertical hardware 120 is preferably to have a structure filled with concrete in the hollow frame and the hollow top and bottom open to improve the structural strength.

도 7에 도시된 바와 같이, 상기 돔 상부성형폼(400)은 돔형상의 철골프레임(410) 구조로 이루어진다. 상기 철골프레임(410)의 외측면에는 이격부재(420)가 고정되며, 상기 이격부재(420)의 외측으로 폼 패널(430)이 조립된다. 따라서, 상기 폼 패널(430)은 이격부재(420)를 통해 철골프레임(410)의 외측으로부터 일정거리를 유지한 상태로 조립된다. 상기 폼 패널(430)은 돔부 형상에 대응되는 형상을 갖는 다수의 패널들로 이루어져 있다.As shown in FIG. 7, the dome upper forming foam 400 has a dome-shaped steel frame 410 structure. Spacer member 420 is fixed to the outer surface of the steel frame 410, the foam panel 430 is assembled to the outside of the spacer member 420. Thus, the foam panel 430 is assembled while maintaining a predetermined distance from the outside of the steel frame 410 through the spacer 420. The foam panel 430 is composed of a plurality of panels having a shape corresponding to the shape of the dome portion.

이 경우, 상기 돔부의 벽면에는 성형 완료된 콘크리트 구조물의 구조적 강도를 향상시켜 주기 위한 고정철물(440)들이 조립되며, 상기 폼 패널(430)들은 상기 고정철물(440)들과 간격유지구(460)을 통해 일정거리를 유지한 상태로 조립된다. 그리고 상기 고정철물(440)의 하단은 수직철물(120)의 상단과 맞대기 용접 또는 볼트 체결을 통해 일체로 연결된다.In this case, fixing hardware 440 is assembled on the wall surface of the dome part to improve structural strength of the finished concrete structure, and the foam panels 430 are spaced apart from the fixing hardware 440. It is assembled while maintaining a certain distance through. The lower end of the fixed hardware 440 is integrally connected to the upper end of the vertical hardware 120 through butt welding or bolting.

또한, 상기 고정철물(440)은 돔부의 벽면과 연결부재(A)를 통해 견고하게 고정될 수 있다. In addition, the fixing hardware 440 may be firmly fixed through the wall surface and the connection member (A) of the dome part.

또한, 상기 고정철물(440)들은 별도의 연결철물(450)들로써 상호 연결되도록 하는 것이 바람직하다. 상기 연결철물(450)은 통상의 철근이 바람직하다. 이 경우, 상기 연결철물(450)은 인접한 폼 패널(430)의 고정철물(440)이나 연결철물(450)들과 상호연결된다.In addition, the fixed hardware 440 is preferably to be connected to each other as a separate connecting hardware (450). The connecting hardware 450 is preferably a conventional rebar. In this case, the connecting hardware 450 is interconnected with the fixing hardware 440 or the connecting hardware 450 of the adjacent foam panel 430.

아울러, 상기 고정철물(440)들은 돔부 벽면을 향해 다열배치될 수도 있다.In addition, the fixing hardware 440 may be arranged in multiple rows toward the dome wall.

그리고, 각 고정철물(440)들은 상호간에 일정한 간격 및 폼 패널(430)과의 일정한 간격을 유지할 수 있도록 별도의 이격부재(445)를 통해 상호연결되는 것이 바람직하다.In addition, each of the fixing hardware 440 is preferably interconnected through a separate spacer 445 so as to maintain a constant distance from each other and a constant gap with the foam panel 430.

한편, 도 8에 도시된 바와 같이, 상기 돔 상부성형폼(400)의 다른 실시예로서, 상기 돔 상부성형폼(400)은 돔형상의 철골프레임(410)과, 상기 철골프레임(410)의 외측에 고정되는 이격부재(420)와, 외측면에 고정철물(440)들이 일정거리를 두고 고정된 상태로 상기 이격부재(420)를 통해 철골프레임(410)의 외측에 일정거리를 두고 조립된 폼 패널(430)들로 구성될 수도 있다. 즉, 폼 패널(430)의 외측에 고정철물(440)들이 이미 고정되어 있는 것이다. 이 경우, 작업현장에서 폼 패널(430)에 고정철물(440)을 고정시키는 작업과, 돔부 벽면에 고정철물(440)을 고정시키는 작업들을 수행하지 않아도 되므로 시공기간이 짧아지고 돔 상부성형폼(400)의 설치도 간편해진다. 그리고 최하단에 위치한 고정철물(440)의 하단은 수직철물(120)의 상단과 맞대기 용접 또는 볼트체결을 통해 일체로 연결된다.On the other hand, as shown in Figure 8, as another embodiment of the dome upper forming foam 400, the dome upper forming foam 400 is a dome-shaped steel frame 410, the outer side of the steel frame 410 Spacer member 420 fixed to the form, the fixed hardware 440 on the outer surface in a fixed state at a predetermined distance to the outer space of the steel frame 410 through the spacer member 420 assembled to form a form It may also be composed of panels 430. That is, the fixing hardware 440 is already fixed to the outside of the foam panel 430. In this case, since the fixing work 440 to the foam panel 430 and the fixing hardware 440 to the dome wall do not need to be performed at the work site, the construction period is shortened and the upper molding form of the dome ( Installation of the 400 is also simplified. And the lower end of the fixed hardware 440 located at the lower end is connected integrally with the top of the vertical hardware 120 through butt welding or bolting.

본 발명에 따르면, 도 9에 도시된 바와 같이, 상기 돔 상부성형폼(400)들은 조립 및 승강과정에서 미리 조립된 돔 측부성형폼(300)과 간섭이 발생되므로 철골프레임(410)만으로 가조립하고 성형위치로 완전히 상승된 상태에서 완전한 조립이 이루어지도록 한다. 즉, 철골프레임(410)만 조립하고, 성형위치로 완전히 상승된 상태에서 나머지 이격부재와 폼 패널을 비롯하여 고정철물과 연결철물 등을 조립하는 것이다.According to the present invention, as shown in Figure 9, the dome upper forming foam 400 is pre-assembled by the steel frame 410 only because the interference occurs with the pre-assembled dome side forming foam 300 in the assembling and lifting process Allow complete assembly while fully elevated to the molding position. That is, only the steel frame 410 is assembled, and assembling the rest of the spaced member and the foam panel, the fixed hardware and the connecting hardware, etc. in a fully raised state.

또는, 도 10에 도시된 바와 같이, 상기 돔 상부성형폼(400)는 돔 측부성형폼(300)의 상단 이상의 높이에 대해서만 정상대로 조립하고 그 이하는 상기와 같이 돔 측부성형폼(300)과의 간섭이 발생되지 않도록 이격부재(420)와 폼 패널(430)을 배제시켜 가조립한 다음 성형위치까지 완전히 상승된 상태에서 가조립된 부분을 정상적으로 조립하는 것이다.Alternatively, as shown in FIG. 10, the dome upper forming foam 400 is assembled as normal only for the height of the upper end or higher of the dome side forming foam 300 and the lower dome side forming foam 300 is formed as described above. After the preliminary assembly by excluding the spacer member 420 and the foam panel 430 so as not to cause interference, the assembled parts are normally assembled in a completely raised state to the molding position.

한편, 도 11 및 도 12에 도시된 바와 같이, 상기 돔 상부성형폼의 또 다른 실시예로서, 상기 돔 상부성형폼(400)은 돔형상의 철골프레임(410)과, 상기 철골프레임(410)의 외측에 고정되는 이격부재(420)와, 상기 이격부재(420)를 통해 철골프레임(410)의 외측에 일정거리를 두고 조립되는 폼 패널(430)들과, 돔 측벽으로 돌출되게 돔 상부성형폼(400)에 설치된 가설작업대(470)로 구성될 수도 있다.On the other hand, as shown in Figure 11 and 12, as another embodiment of the dome upper forming foam, the dome upper forming foam 400 is a dome-shaped steel frame 410 and the steel frame 410 Spacer member 420 fixed to the outside, the foam panel 430 is assembled at a predetermined distance to the outside of the steel frame 410 through the spacer 420, and the dome upper molding foam to protrude to the dome side wall It may be composed of a temporary work table 470 installed in (400).

상기 가설작업대(470)는 작업자가 탑승한 상태에서 여러가지 작업을 수행하여야 하고 돔 상부성형폼(400), 고정철물(440) 및 연결철물(450) 등의 조립에 필요한 갖가지 자재(B)들을 안전하게 적재시켜 놓을 수 있도록 안전난간이 구비되어 있다.The temporary work bench 470 must perform various tasks in a state where the operator is on board, and various materials (B) required for assembling the dome upper forming foam 400, the fixing hardware 440, and the connecting hardware 450 safely. Safety railings are provided for loading.

이 경우, 돔부의 벽면을 따라 작업프레임(480)이 설치되며, 상기 작업프레임(480)에는 견인부재(481)들이 설치된다. 상기 견인부재(481)들은 돔 상부성형폼(400), 고정철물(440) 및 연결철물(450) 등의 조립에 필요한 자재(B)들을 공급해 준다.In this case, the work frame 480 is installed along the wall surface of the dome, and the work frame 480 is provided with traction members 481. The towing members 481 supply materials B necessary for assembling the dome upper forming foam 400, the fixing hardware 440, and the connecting hardware 450.

상기 작업프레임(480)은 구조적 강도를 향상시키기 위하여 별도의 연결부재(A)를 통해 돔부의 벽면에 고정되도록 할 수도 있다.The work frame 480 may be fixed to the wall surface of the dome part through a separate connecting member (A) to improve structural strength.

도시하지는 않았으나, 상기 작업프레임(480)은 구조적 강도를 향상시키기 위하여 내부에 콘크리트가 타설될 수도 있다. 이 경우, 콘크리트 내부에 철골이나 메쉬를 여러 층에 걸쳐 매설시켜 구조적 강도를 더욱 향상시킬 수도 있다.Although not shown in the drawing, the work frame 480 may be concrete poured therein to improve structural strength. In this case, it is possible to further enhance the structural strength by laying steel or mesh in the concrete over several layers.

그리고 가설작업대(470)가 설치되는 부위에 폼 패널(430)이 설치되지 않는다. 따라서, 상기 가설작업대(470)가 설치되는 부위는 작업자가 출입할 수 있는 통로가 된다. 상기 가설작업대(470)가 설치되는 부위는 이후 가설작업대(470)가 철거되면 별도의 마감폼 패널(미도시)을 통해 마감되며, 이 상태에서 미경화콘트리트가 타설된다.And the foam panel 430 is not installed in the site where the temporary work bench 470 is installed. Therefore, the site where the temporary work bench 470 is installed is a passage through which an operator can enter and exit. The site where the temporary work bench 470 is installed is then finished through a separate finishing foam panel (not shown) when the temporary work bench 470 is removed, and uncured concrete is poured in this state.

한편, 상기 작업프레임(480)은 돔 상부성형폼이 완전히 상승된 상태에서 간격유지구(460)를 통해 돔 상부성형폼(400)과 일정거리를 유지한 상태로 연결된다.(도 14f 참조)On the other hand, the work frame 480 is connected to the dome upper forming form 400 while maintaining a certain distance through the gap retaining hole 460 in the state where the dome upper forming form is fully raised (see Fig. 14f).

그리고, 상기 작업프레임(480)과 돔 상부성형폼(400) 사이에는 내부강재(490)가 더 설치될 수 있다. 이 경우, 상기 내부강재(490)는 돔부의 바닥에 설치된 수직연결철물(491)과 상기 수직연결철물(491)들과 연결되는 수평연결철물(492)로 구성되며, 상기 수직연결철물(491)과 수평연결철물(492)들의 연결작업은 상기 돔 상부성형폼(400)에 설치된 가설작업대(470)를 통해 수행되도록 한다.In addition, an internal steel 490 may be further installed between the work frame 480 and the dome upper forming foam 400. In this case, the inner steel 490 is composed of a vertical connecting hardware 491 and the horizontal connecting hardware 492 is connected to the vertical connecting hardware 491 is installed on the bottom of the dome, the vertical connecting hardware (491) And the connection of the horizontal connection hardware 492 is to be performed through the temporary work platform 470 installed on the dome upper forming foam (400).

즉, 작업프레임(480)에 설치된 견인부재(481)가 상기 가설작업대(470)에 내부강재(490)들을 포함하는 자재(B)들을 적재시켜 놓으면, 작업자가 상기 가설작업대(470)에 탑승한 상태에서 미리 적재된 내부강재(490)들을 이용하여 돔 상부성형폼(400)이 승강함에 따라 돔부의 바닥에서부터 상부로 내부강재(490)들을 연장설치하는 것이다.That is, when the towing member 481 installed on the work frame 480 loads the materials B including the internal steels 490 on the temporary working table 470, the operator boards the temporary working table 470. As the dome upper forming foam 400 is elevated using the internal steels 490 preloaded in a state, the internal steels 490 are extended from the bottom of the dome to the upper part.

상기 가설작업대(470)는 수직연결철물(491)과 수평연결철물(492)들의 연결작업을 작업자가 용이하게 수행할 수 있도록 돔 상부성형폼(400)의 철골프레임(410)에 견고하게 고정된 상태로 돔부의 벽면을 향해 돌출되도록 설치된다.The temporary working table 470 is firmly fixed to the steel frame 410 of the dome upper forming foam 400 so that an operator can easily perform the connection of the vertical connecting hardware 491 and the horizontal connecting hardware 492. It is installed so that it may protrude toward the wall surface of a dome part in a state.

따라서, 돔부의 벽면을 향해 돌출된 상기 가설작업대(470)의 단부가 수평상태를 유지할 수 있도록 상기 작업프레임(480)에는 수직지지바(미도시)가 결합될 수 있다. 이 경우, 상기 수직지지바의 하단은 돔 상부성형폼(400)이 성형위치까지 완전히 상승했을 때 상기 가설작업대(470)의 단부에 체결된다. 아울러, 상기 수직지지바는 가설작업대(470)의 하부를 지지하도록 돔 성형폼(400)의 철골프레임(410)에 수직으로 설치되어도 무방하다.Accordingly, a vertical support bar (not shown) may be coupled to the work frame 480 so that an end portion of the temporary work bench 470 protruding toward the wall surface of the dome portion may maintain a horizontal state. In this case, the lower end of the vertical support bar is fastened to the end of the temporary working table 470 when the dome upper forming foam 400 is fully raised to the molding position. In addition, the vertical support bar may be installed vertically to the steel frame 410 of the dome forming foam 400 to support the lower portion of the temporary working table 470.

이와 같이 돔 상부성형폼(400)이 설치되면, 작업프레임(480)과 견인부재(481)로 인해 돔 상부성형폼(400)의 조립이 신속하고 간편하게 이루어지게 되고, 작업프레임(480)이 보강재 역할을 수행하므로 고정철물과 같은 별도의 보강부재의 설치가 요구되지 않는다. 아울러, 내부강재(490)의 설치작업이 돔 상부성형폼(400)이 상승하는 과정에서 함께 이루어지기 때문에 시공기간을 크게 단축할 수 있게 된다.When the dome upper forming foam 400 is installed as described above, the assembly of the dome upper forming foam 400 is made quickly and easily due to the work frame 480 and the towing member 481, and the work frame 480 is reinforced. It does not require the installation of a separate reinforcing member, such as a fixed hardware. In addition, since the installation work of the internal steel 490 is made in the process of raising the dome upper forming foam 400, the construction period can be greatly shortened.

본 발명에 따르면, 도 2 내지 도 4에 도시된 바와 같이, 상기 돔 상부성형폼(400)의 일측에는 미경화콘크리트가 타설될 수 있도록 개방부(402)가 형성된다. 상기 개방부(402)는 해당부위에 폼 패널(430)을 조립하지 않도록 하여 형성시킨다. 상기 개방부(402)는 미경화콘크리트의 타설된 이후에 별도의 마감폼 패널을 통해 마감된다.According to the present invention, as shown in Figures 2 to 4, an opening portion 402 is formed on one side of the dome upper forming foam 400 so that uncured concrete can be poured. The opening part 402 is formed so as not to assemble the foam panel 430 on the corresponding part. The opening part 402 is finished through a separate finishing foam panel after pouring of uncured concrete.

상기 돔 상부성형폼(400)의 하단에는 수평지지대(411)들이 설치되어 돔 상부성형폼(400)의 구조적 강도를 향상시켜 준다. 그리고 상기 수평지지대(411)의 상부에는 돔 상부성형폼(400)의 내측에서 철골프레임(410)을 지지하는 보조지지대(412)들이 설치된다. 또한, 상기 보조지지대(412)는 승강이 가능하도록 설치되고, 보조지지대(412)들을 통해 미경화콘크리트 공급장치(413)가 돔 상부성형폼(400)측으로 원활하게 공급될 수 있도록 하는 것이 바람직하다.Horizontal supports 411 are installed at the lower end of the dome upper forming foam 400 to improve the structural strength of the dome upper forming foam 400. In addition, an auxiliary support 412 for supporting the steel frame 410 inside the dome upper forming form 400 is installed on the upper side of the horizontal support 411. In addition, the auxiliary support 412 is installed to enable the lifting, it is preferable to allow the uncured concrete supply device 413 to be smoothly supplied to the dome upper forming foam 400 through the auxiliary support (412).

한편, 돔부의 바닥에는 돔 상부성형폼(400)의 하부를 지지하는 잭서포트(500)들이 설치된다. 상기 잭서포트(500)는 성형위치까지 최대한 상승된 돔 상부성형폼(400)의 철골프레임(410)의 하단을 지지하도록 설치되어 돔 상부성형폼(400)의 상부로 타설되는 고하중의 미경화콘크리트로부터 돔 상부성형폼(400)을 안정적으로 지탱시켜 주는 역할도 수행한다.Meanwhile, jack supports 500 supporting the lower portion of the dome upper forming foam 400 are installed at the bottom of the dome portion. The jack support 500 is installed so as to support the lower end of the steel frame 410 of the dome upper forming foam 400 as far as possible to form the high load uncured to the upper portion of the dome upper forming foam 400 It also serves to stably support the dome upper forming foam 400 from concrete.

한편, 상기 돔 상부성형폼(400)을 구성하는 폼 패널(430)들 중 돔부의 최상단을 이루는 폼 패널(430)의 중앙에는 미경화콘크리트 및 그라우팅 몰탈을 주입하기 위한 주입공(431)이 형성되어 있다.Meanwhile, an injection hole 431 for injecting uncured concrete and grouting mortar is formed at the center of the foam panel 430 forming the uppermost part of the dome portion among the foam panels 430 constituting the upper dome forming foam 400. It is.

아울러, 상기 돔부의 바닥에는 상기 수직철물(120)들의 설치위치를 지정해 주는 안내패널(600)이 더 고정되는 것이 바람직하다. 상기 안내패널(600)에는 돔부의 바닥에 설치될 수직철물(120)과 연결철물(112)들을 비롯하여 수직지지대(100)의 위치를 안내해 주기 위한 통공(610)들이 형성되어 있다. 따라서, 작업자는 미리 지정된 위치에 안내패널(600)을 깔아 움직이지 않도록 바닥에 고정한 다음, 상기 통공(610)의 위치에 수직철물(120)과 연결철물(112) 및 수직지지대(100)를 설치하면 되는 것이다. 상기 수직철물(120)은 고정철물(440)의 하단에 연결되는 부재로서 상기 고정철물(440)이 돔 상부성형폼(400)의 성형위치를 결정해 주는 주요부재임을 감안할 때, 상기 안내패널(600)을 이용하여 수직철물(120)의 설치위치를 정밀하게 관리하는 것은 매우 중요하며, 이는 상기 안내패널(600)을 통해 매우 신속하고 간편하게 수행될 수 있게 된다.In addition, the bottom of the dome portion is preferably fixed to the guide panel 600 for specifying the installation position of the vertical hardware (120). The guide panel 600 is formed with a through hole 610 for guiding the position of the vertical support 100, including the vertical hardware 120 and the connecting hardware 112 to be installed on the bottom of the dome. Therefore, the operator installs the guide panel 600 at a predetermined position to fix the floor so as not to move, and then install the vertical hardware 120, the connecting hardware 112 and the vertical support 100 at the position of the through hole 610. You can do it. The vertical hardware 120 is a member connected to the lower end of the fixed hardware 440, considering that the fixed hardware 440 is the main member that determines the molding position of the dome upper forming foam 400, the guide panel ( It is very important to precisely manage the installation position of the vertical hardware 120 using 600, which can be performed very quickly and simply through the guide panel 600.

또한, 상기 안내패널(600)의 바닥에는 돔부의 바닥으로부터 일정거리를 유지할 수 있도록 다리(620)가 구비될 수 있다. 이 경우, 상기 안내패널(600)은 다리(620)가 돔부의 기초를 위해 돔부의 바닥으로 타설되는 미경화콘크리트에 매설되면서 돔부의 바닥에 견고하게 고정된다.In addition, the bottom of the guide panel 600 may be provided with a leg 620 to maintain a predetermined distance from the bottom of the dome. In this case, the guide panel 600 is firmly fixed to the bottom of the dome while the bridge 620 is embedded in the uncured concrete to be poured into the bottom of the dome for the base of the dome.

또한, 상기 안내패널(600)은 돔부의 바닥에만 설치되지 않고 고정철물(440)의 중간에 수평설치되어 고정철물(440)들 간의 일정한 간격유지 및 작업발판으로의 사용이 가능하도록 하는 것이 바람직하다.In addition, the guide panel 600 is preferably installed horizontally in the middle of the fixed hardware 440 instead of being installed only on the bottom of the dome, it is preferable to maintain a constant interval between the fixed hardware 440 and to use as a work platform. .

한편, 상기 안내패널의 다른 실시예로서, 도 11 및 도 12에 도시된 바와 같이, 상기 안내패널(500a)은 작업프레임(480)의 위치를 지정해주거나 내부강재(490)의 수직연결철물(491)의 설치위치를 지정해 주기 위한 통공을 구비할 수도 있다.On the other hand, as another embodiment of the guide panel, 11 and 12, the guide panel 500a is provided with a through hole for specifying the position of the work frame 480 or the installation position of the vertical connecting hardware 491 of the inner steel 490. You may.

이와 같이 구성된 본 발명의 지하 돔 콘크리트 구조물의 성형장치를 이용한 성형방법은 다음과 같다.The molding method using the molding apparatus of the underground dome concrete structure of the present invention configured as described above is as follows.

먼저, 도 13a에 도시된 바와 같이, 굴착된 돔부 바닥에 안내패널(600)을 미리 정해진 위치에 깔아 놓고 돔부의 바닥을 콘크리트로 기초시공한다. 이때 미리 지정된 안내패널(600)들의 통공(610)에 수직철물(120)과 수직지지대(100)들을 설치하여 기초시공시 돔부의 바닥에 매설된 상태로 견고하게 고정되도록 한다.First, as shown in FIG. 13A, the guide panel 600 is laid at a predetermined position on the bottom of the excavated dome part, and the bottom of the dome part is constructed with concrete. In this case, the vertical hardware 120 and the vertical supporters 100 are installed in the through holes 610 of the predetermined guide panels 600 to be firmly fixed in the state of being buried in the bottom of the dome part during the foundation construction.

도 13b에 도시된 바와 같이, 수직지지대(100)가 설치되면 수직지지대(100)의 상부에 견인부재(200)가 설치된다. 본 실시예에서는 잭로드(210)가 설치된 견인부재(200)를 예를 들어 도시하고 설명한다.As shown in FIG. 13B, when the vertical support 100 is installed, the traction member 200 is installed on the upper portion of the vertical support 100. In the present embodiment, the towing member 200 provided with the jack rod 210 is illustrated and described as an example.

견인부재(200)가 설치되면, 돔 측부성형폼(300)이 조립되기 시작하고 간격유지구(111)를 통해 수직철물(120)과 돔 측부성형폼(300)이 일정간격을 유지하도록 연결된다.When the towing member 200 is installed, the dome side forming foam 300 starts to be assembled, and the vertical hardware 120 and the dome side forming foam 300 are connected to each other to maintain a predetermined interval through the gap retaining hole 111. .

이와 동시에 돔부의 바닥에서는 돔 상부성형폼(400)이 가조립된다. 상기 돔 상부성형폼(400)은 돔 측부성형폼(300)과의 간섭이 방지되도록 철골프레임(410)만 조립된 형태로 가조립되거나, 도시된 바와 같이 돔 측부성형폼(300)의 상단보다 낮은 부위에 한하여 이격부재(420)가 조립되지 않은 형태로 가조립된다.At the same time, the dome upper forming foam 400 is temporarily assembled at the bottom of the dome. The dome upper forming foam 400 is prefabricated in a form in which only the steel frame 410 is assembled to prevent interference with the dome side forming foam 300, or as shown, lower than the top of the dome side forming foam 300. Only the portion of the spacer member 420 is assembled in an unassembled form.

아울러, 상기 돔 상부성형폼(400)의 하단에 수평지지대(411)들이 설치되고, 상기 수평지지대(411)의 상부에는 철골프레임(410)을 지지하도록 보조지지대(412)들이 설치된다. 이와 같이 수평지지대(411)와 보조지지대(412)의 설치가 완료되면 상기 수평지지대(411)와 보조지지대(412)를 통해 미경화콘크리트 공급장치(413)가 설치된다.In addition, horizontal supports 411 are installed at a lower end of the dome upper forming foam 400, and auxiliary supports 412 are installed on the upper portion of the horizontal support 411 to support the steel frame 410. As such, when the installation of the horizontal support 411 and the auxiliary support 412 is completed, the uncured concrete supply device 413 is installed through the horizontal support 411 and the auxiliary support 412.

도 13c에 도시된 바와 같이, 돔 상부성형폼(400)이 가조립되는 동안에 돔부 바닥에 설치된 수직철물(120)과 연결철물(112)은 돔 상부로 연장설치된다. 즉, 수직철물(120)과 연결철물(112)의 상부에 각각 고정철물(440)과 연결철물(450)을 돔 형상을 따라 돔 상부로 연장설치되는 것이다. 이때, 상기 고정철물(440)은 돔부의 벽면에 미리 설치된 연결부재(A)를 통해 돔부 벽면에 견고하게 고정되는 한편, 연결철물(450)을 통해 양측방향의 고정철물(440)들과 서로 견고하게 연결된다. 그리고 상하방향의 고정철물(440)들은 용접 또는 볼트체결을 통해 일체로 연결된다.As shown in FIG. 13C, the vertical hardware 120 and the connecting hardware 112 installed on the bottom of the dome portion are extended to the upper part of the dome while the dome upper forming foam 400 is temporarily assembled. That is, the fixed hardware 440 and the connecting hardware 450 are extended to the upper part of the dome, respectively, on the upper part of the vertical hardware 120 and the connecting hardware 112. In this case, the fixing hardware 440 is firmly fixed to the wall of the dome part through the connection member (A) pre-installed on the wall surface of the dome part, while the fixing hardware 440 of both sides through the connection hardware 450 is firmly mutually. Is connected. And up and down fixing irons 440 are connected integrally by welding or bolting.

본 발명에 따르면, 폼 패널(430)에 미리 고정철물(440)과 연결철물(450)이 조립되어 있을 수도 있다. 즉, 도 8에 도시된 바와 같이, 상기 폼 패널(430)의 외측에 간격유지구(460)가 설치되고, 이 간격유지구(460)를 통해 폼 패널(430)들의 외측면에 일정거리를 두고 고정철물(440)들이 설치되는 것이다. 그리고 양측방향의 고정철물(440)들이 연결철물(450)을 통해 서로 연결되고 상하방향의 고정철물(440)들이 용접 또는 볼트체결을 통해 일체로 연결된다. 따라서, 이와 같은 경우는 수직철물(120)과 연결철물(112)의 상부에 각각 고정철물(440)과 연결철물(450)을 돔 형상을 따라 돔 상부로 연장설치하는 작업이 요구되지 않는다.According to the present invention, the fixed hardware 440 and the connecting hardware 450 may be assembled to the foam panel 430 in advance. That is, as shown in Figure 8, the gap retaining hole 460 is installed on the outside of the foam panel 430, through the gap retaining hole 460 to a predetermined distance to the outer surface of the foam panels 430. Leave the fixed hardware 440 is to be installed. In addition, the fixing hardware 440 in both directions is connected to each other through the connecting hardware 450, and the fixing hardware 440 in the vertical direction is integrally connected by welding or bolting. Therefore, in such a case, it is not required to extend the fixing hardware 440 and the connecting hardware 450 to the upper part of the dome along the dome shape, respectively, on the upper part of the vertical hardware 120 and the connecting hardware 112.

한편, 돔 상부성형폼(400)의 가조립이 완료되거나 진행 중, 돔 측부성형폼(300)의 조립이 완료되면 돔 측부성형폼(300)측으로 미경화콘크리트가 타설되면서 돔 측벽에 콘크리트구조물이 성형되기 시작한다. 그리고 돔 상부성형폼(400)의 가조립이 완료되면 견인부재(200)가 돔 상부성형폼(400)에 연결되고 견인부재(200)가 구동되면서 돔 상부성형폼(400)은 상승된다.Meanwhile, when the temporary assembly of the dome upper forming foam 400 is completed or in progress, the assembling of the dome side forming foam 300 is completed, the concrete structure is formed on the sidewall of the dome while uncured concrete is poured onto the dome side forming foam 300. It begins to be. When the temporary assembly of the dome upper forming foam 400 is completed, the traction member 200 is connected to the dome upper forming foam 400 and the traction member 200 is driven while the dome upper forming foam 400 is raised.

도 13d에 도시된 바와 같이, 돔 상부성형폼(400)이 완전히 상승하여 성형위치에 도달하면, 돔 상부성형폼(400)의 상승동작도 중지된다. 그리고 이 상태에서 가조립 상태의 돔 상부성형폼(400)은 완전하게 조립된다. 아울러, 간격유지구(460)를 이용하여 돔부 벽면에 미리 설치된 고정철물(440)의 외측에 일정거리를 두고 폼 패널(430)이 결속된다.As shown in FIG. 13D, when the dome top forming foam 400 is fully raised to reach the molding position, the lifting operation of the dome top forming foam 400 is also stopped. In this state, the dome top forming foam 400 in the assembled state is completely assembled. In addition, the foam panel 430 is bound at a predetermined distance to the outside of the fixing hardware 440 pre-installed on the wall of the dome part by using the spacing holder 460.

한편, 도 8에 도시된 바와 같이 폼 패널(430)에 미리 고정철물(440)과 연결철물(450)이 조립된 돔 상부성형폼(400)의 경우에는, 가조립상태의 돔 상부성형폼(400)이 완전하게 조립될 때, 돔 상부성형폼(400)의 최하단에 조립되는 고정철물(440)의 하단이 돔 벽면에 설치되어 있는 수직철물(120)의 상단에 맞대기 용접 또는 볼트체결을 통해 견고하게 연결되도록 하여 돔 상부성형폼(400)의 고정철물(440)과 돔 벽면의 수직철물(120)이 단일 구조체를 이루도록 한다.Meanwhile, as shown in FIG. 8, in the case of the dome upper forming foam 400 in which the fixed hardware 440 and the connecting hardware 450 are assembled in the foam panel 430, the dome upper forming foam 400 in the temporarily assembled state is shown. ) Is completely assembled, the bottom of the fixed hardware 440 assembled to the bottom of the dome upper forming foam 400 is firmly welded or bolted to the top of the vertical hardware 120 installed on the dome wall The fixed hardware 440 of the dome upper forming foam 400 and the vertical hardware 120 of the dome wall form a single structure.

그리고 고정철물(440)들은 별도의 연결부재(A)를 통해 돔부의 벽면에 고정시켜 돔 상부성형폼(400)이 구조적으로 안전성을 확보할 수 있도록 한다.And the fixing hardware 440 is fixed to the wall surface of the dome portion through a separate connection member (A) to ensure the dome upper forming foam 400 structurally secure.

이러한 돔 상부성형폼(400)과 돔부의 벽면과의 고정작업은 돔 측부에 콘크리트구조물의 성형작업과 동시에 진행되며, 돔 측부에 콘크리트구조물의 성형작업이 완료되기 이전에 종료되도록 한다.The fixing of the dome upper forming foam 400 and the wall surface of the dome proceeds simultaneously with the molding work of the concrete structure on the dome side, and ends before the molding work of the concrete structure is completed on the dome side.

아울러, 돔 상부성형폼(400)으로 미경화콘크리트의 타설이 이루어지기 이전에 돔 상부성형폼(400)의 하단에 잭서포트(500)를 설치하여 돔 상부성형폼(400)의 하중이 분산되도록 한다.In addition, the jack support 500 is installed at the lower end of the dome upper forming form 400 before the uncured concrete is poured into the dome upper forming form 400 so that the load of the dome upper forming form 400 is distributed. do.

본 발명에 따르면, 돔 측부성형폼(300)으로 미경화콘크리트가 타설되는 동안에 돔 상부성형폼(400)의 조립과 잭서포트(500)의 설치가 모두 완료되므로 돔 측부의 성형작업과 돔 상부의 성형작업을 연속적으로 수행할 수 있게 되므로 타설경계면이 형성되지 않는다. 따라서, 돔 상부성형폼(400)의 조립과 잭서포트(500)의 설치가 모두 완료되는 시점을 감안하여 돔 측부성형폼(300)으로 미경화콘크리트가 타설되는 시점을 조절하는 것이 바람직하다.According to the invention, the dome side molding form 300, uncured concrete assembly and jack support 500, the installation is complete all of the dome top molding form 400, while the placement because of the shaping operation of the dome side and a dome top Since the molding operation can be carried out continuously, no pour boundary is formed. Therefore, it is preferable to adjust the timing at which the uncured concrete is poured into the dome side forming foam 300 in consideration of the timing at which both the assembly of the dome upper forming foam 400 and the installation of the jack support 500 are completed.

도 13e에 도시된 바와 같이, 잭서포트(500)의 설치가 완료되면, 미경화콘크리트공급장치가 제거되고, 개구부(401)와 개방부(402)가 마감폼 패널으로 마감되어 미경화콘크리트가 누설되지 않도록 모두 폐쇄된다.As shown in FIG. 13E, when the installation of the jack support 500 is completed, the uncured concrete supply device is removed, and the opening 401 and the opening 402 are finished with a finishing foam panel, so that the uncured concrete is leaked. They are all closed.

개구부(401)와 개방부(402)가 폐쇄되면, 돔 상부성형폼(400)의 최상단을 이루는 폼 패널(430)의 중앙에 형성된 주입공(431)으로 미경화콘크리트가 천천히 주입된다. 이때 상기 돔 상부성형폼(400)은 잭서포트(500) 및 돔부의 벽면을 통해 하중이 분산되므로, 타설된 미경화콘크리트의 엄청난 하중에도 불구하고 매우 안정된 설치상태를 유지할 수 있게 된다.When the opening 401 and the opening 402 are closed, the uncured concrete is slowly injected into the injection hole 431 formed at the center of the foam panel 430 forming the uppermost part of the dome upper forming foam 400. At this time, since the load is distributed through the jack support 500 and the wall of the dome portion, the dome upper forming foam 400 can maintain a very stable installation state despite the enormous load of the uncured concrete that is poured.

도 13f에 도시된 바와 같이, 일정시간이 경과하여 주입된 미경화콘크리트가 경화되면, 상기 주입공(431)에 상기 미경화콘크리트 공급파이프 대신 그라우팅 몰탈 공급파이프(414)가 삽입되고 그라우팅 몰탈(F)이 고압 주입된다. 그라우팅 몰탈(F)은 미경화콘크리트가 타설되지 못한 돔부의 최상단에 형성된 빈 공간을 채우게 된다.As shown in FIG. 13F, when the uncured concrete is hardened after a certain time has elapsed, a grouting mortar supply pipe 414 is inserted into the injection hole 431 instead of the uncured concrete supply pipe and grout mortar (F). ) Is injected at high pressure. The grouting mortar (F) fills the empty space formed at the top of the dome portion in which uncured concrete is not poured.

돔 상부에 콘크리트구조물이 성형되면, 돔 측부 성형폼(300)이 해체된다.When the concrete structure is formed on the dome, the dome side forming foam 300 is dismantled.

그리고 돔 측부성형폼(300)이 해체되는 동안, 돔 상부성형폼(400)의 폼 패널(430)과 간격유지구(460)와의 연결이 모두 해제되며, 잭서포트(500)가 제거된 다음 견인부재(200)가 동작되면서 돔 상부성형폼(400)이 서서히 하강한다. 이때, 돔 상부성형폼(400)이 하강하는 과정에서 수직지지대(100) 또는 견인부재(200)와 돔 상부성형폼(400)이 간섭되므로 마감폼 패널이 제거되면서 개구부(401)가 다시 개방된다. 또한, 돔 상부성형폼(400)은 하강과정에서 성형완료된 돔 측벽의 콘크리트구조물을 손상시키지 않도록 도 13c와 같은 가조립 상태가 되도록 일부를 미리 해체시키는 것이 좋다.And while the dome side forming foam 300 is dismantled, all the connections between the foam panel 430 and the gap retention zone 460 of the dome upper forming foam 400 are released, and the jack support 500 is removed and then towed. As the member 200 is operated, the dome upper forming foam 400 is gradually lowered. At this time, since the vertical support 100 or the towing member 200 and the dome upper forming foam 400 interfere with the upper dome forming foam 400, the finishing foam panel is removed, and the opening 401 is opened again. . In addition, the dome upper forming foam 400 is preferably dismantled in advance so as to be in a prefabricated state as shown in FIG.

도 13g에 도시된 바와 같이, 돔 상부성형폼(400)이 바닥까지 하강하면 수직지지대(100)의 일부와 견인부재(200) 및 돔 상부성형폼(400)이 해체된다. 따라서, 작업자는 성형이 완료된 이후 돔 상부성형폼(400)의 해체작업을 돔부의 바닥에서 수행하게 되므로 매우 용이하게 수행할 수 있게 된다.As shown in FIG. 13G, when the dome top forming foam 400 descends to the bottom, a part of the vertical support 100, the towing member 200, and the dome top forming foam 400 are dismantled. Therefore, since the operator performs the dismantling of the dome upper forming foam 400 after the molding is completed, it can be performed very easily.

이와 같은 일련의 작업을 모두 수행하면, 도 13h와 같은 지하 돔 콘크리트 구조물이 완성된다.When all of these series of operations are performed, the underground dome concrete structure as shown in FIG. 13H is completed.

한편, 돔 상부성형폼(400)은 돔 측부의 성형이 완료되어 돔 측부성형폼(300)이 모두 해체된 이후에 가조립되어도 무방하다. 이 경우, 돔 측부성형폼(300)과 돔 상부성형폼(400)의 조립이 함께 이루어지지 않게 되므로 돔 측부성형폼(300)의 조립시 작업공간 확보 측면에서 유리하다.On the other hand, the dome upper forming foam 400 may be temporarily assembled after the molding of the dome side is completed and all the dome side forming foam 300 is dismantled. In this case, since the assembly of the dome side forming foam 300 and the dome upper forming foam 400 is not made together, it is advantageous in terms of securing a working space when assembling the dome side forming foam 300.

한편, 본 발명의 다른 실시예로서, 도 11 및 도 12에 도시된 돔 상부성형폼이 적용된 지하 돔 콘크리트 구조물의 성형장치를 이용한 성형방법은 다음과 같다.On the other hand, as another embodiment of the present invention, the molding method using the molding apparatus of the underground dome concrete structure to which the dome upper forming foam shown in Figure 11 and 12 is applied as follows.

먼저, 도 14a에 도시된 바와 같이, 굴착된 돔부의 바닥에 안내패널(500a)을 미리 정해진 위치에 깔아 놓고 돔부의 바닥을 콘크리트로 기초시공한다. 이때 미리 지정된 안내패널(500a)들의 통공에 수직지지대(100)를 비롯하여 견인부재(200)과 작업프레임(480)과 내부강재의 수직연결철물(491)들을 설치하여 기초시공시 돔부의 바닥에 매설되어 견고하게 고정되도록 한다.First, as shown in FIG. 14A, the guide panel 500a is laid at a predetermined position on the bottom of the excavated dome portion, and the bottom of the dome portion is constructed with concrete. In this case, the vertical support 100 is installed in the through holes of the predetermined guide panels 500a, and the vertical connection hardware 491 of the towing member 200, the working frame 480, and the internal steel are installed at the bottom of the dome part during the basic construction. To be firmly fixed.

도 14b에 도시된 바와 같이, 돔부의 바닥의 기초가 완성되면, 돔부의 바닥에 매설된 작업프레임(480)이 상부로 연장되면서 완전하게 조립된다 상기 작업프레임(480)은 용접 또는 볼트체결을 통해 일체로 연결된다. 그리고 작업프레임(480)에 견인부재(481)가 설치된다. 본 실시예에서는 전동 도르레 방식의 견인부재(481)를 예를 들어 도시하였다. 아울러, 작업프레임(480)의 구조적 강도가 향상되도록 별도의 연결부재(A)를 통해 돔 측벽에 작업프레임(480)이 고정된다.As shown in FIG. 14B, when the base of the bottom of the dome is completed, the work frame 480 embedded in the bottom of the dome is extended upward and completely assembled. The work frame 480 is welded or bolted. It is connected in one piece. And the towing member 481 is installed in the working frame 480. In this embodiment, the electric pulley type traction member 481 is shown as an example. In addition, the work frame 480 is fixed to the sidewall of the dome through a separate connecting member (A) so that the structural strength of the work frame 480 is improved.

도 14c에 도시된 바와 같이, 견인부재(481)의 설치가 완료되면, 돔 측부성형폼(300)이 조립된다. 상기 돔 측부성형폼(300)은 간격유지구(111)를 통해 수직연결철물(491)과 일정간격을 유지하도록 조립된다.As shown in FIG. 14C, when the installation of the towing member 481 is completed, the dome side forming foam 300 is assembled. The dome side forming foam 300 is assembled to maintain a constant distance with the vertical connection hardware 491 through the gap retaining hole (111).

도 14d에 도시된 바와 같이, 돔 측부성형폼(300)의 설치되기 완료되면, 돔부의 바닥에서는 돔 상부성형폼(400)이 가조립된다. 상기 돔 상부성형폼(400)은 돔 측부성형폼(300)과의 간섭이 방지되도록 철골프레임(410)만 조립된 형태로 가조립될 수도 있고, 도시된 바와 같이 돔 측부성형폼(300)의 상단보다 낮은 부위에 한하여 이격부재(420)이 조립되지 않은 형태로 가조립될 수도 있다. 이 경우, 상기 돔 상부성형폼(400)은 돔 형상으로 철골프레임(410)이 조립된 다음 철골프레임(410)의 외측으로 이격부재(420)가 설치되고, 돔 측벽을 향해 돌출되게 가설작업대(470)가 상기 철골프레임(410) 또는 이격부재(420)를 통해 견고하게 설치되며, 상기 가설작업대(470)가 설치된 부위를 제외하고 상기 이격부재(420)의 외측으로 폼 패널(430)들이 고정되는 순서에 의해 조립된다.As shown in FIG. 14D, when the installation of the dome side forming foam 300 is completed, the dome upper forming foam 400 is temporarily assembled at the bottom of the dome portion. The dome upper forming foam 400 may be pre-assembled in a form in which only the steel frame 410 is assembled to prevent interference with the dome side forming foam 300, as shown in the upper end of the dome side forming foam 300 Only the lower portion of the spacer 420 may be preassembled in an unassembled form. In this case, the dome upper forming foam 400 is a steel frame 410 is assembled in a dome shape, then the spacer member 420 is installed to the outside of the steel frame 410, the temporary work table to protrude toward the side wall of the dome ( 470 is firmly installed through the steel frame 410 or the spacer 420, the foam panel 430 is fixed to the outside of the spacer 420 except for the portion where the temporary working table 470 is installed Are assembled in the order that they become.

아울러, 상기 돔 상부성형폼(400)의 하단에 수평지지대(411)들이 설치되고 상기 수평지지대(411)의 상부에는 철골프레임(410)을 지지하도록 보조지지대(412)들이 설치된다. 이와 같이, 수평지지대(411)와 보조지지대(412)의 설치가 완료되면 상기 수평지지대(411)와 보조지지대(412)를 통해 미경화콘크리트 공급장치(413)가 설치된다.In addition, the horizontal support 411 is installed at the lower end of the dome upper forming foam 400, and the auxiliary support 412 is installed on the upper portion of the horizontal support 411 to support the steel frame 410. As such, when the installation of the horizontal support 411 and the auxiliary support 412 is completed, the uncured concrete supply device 413 is installed through the horizontal support 411 and the auxiliary support 412.

한편, 돔 상부성형폼(400)의 조립은 작업프레임(480)에 설치된 견인부재(481)를 통해 자재들을 공급받아 쉽고 간편하게 이루어지게 되며, 가설작업대(470)의 설치가 완료되면, 상기 견인부재(481)를 통해 내부강재의 설치를 위한 자재(B)들이 가설작업대(470)에 적재된다.On the other hand, the assembly of the dome upper forming foam 400 is made easily and simply by receiving the material through the towing member 481 installed in the work frame 480, the installation of the temporary work bench 470, the towing member Materials 4 for installing the internal steel are loaded on the temporary working table 470 through the 481.

그리고, 돔 측부성형폼(300)의 조립이 완료되면, 돔 측부성형폼(300)측으로 미경화콘크리트가 타설되면서 돔 측벽에 콘크리트 구조물이 성형되기 시작한다. 이때, 미경화콘크리트의 타설은 돔 측부성형폼(300)의 높이가 낮을 경우 돔 상부성형폼(400)에 설치된 미경화콘크리트공급장치(413)을 이용하면 되고, 만일 돔 측부성형폼(300)의 높이가 높아서 상기 미경화콘크리트공급장치(413)의 설치위치보다 타설위치가 높은 경우에는 별도의 미경화콘크리트공급장치를 통해 타설이 이루어지도록 하면 된다.Then, when the assembly of the dome side forming foam 300 is completed, the concrete structure is formed on the dome side wall while the uncured concrete is poured onto the dome side forming foam 300. In this case, when the height of the dome side molding foam 300 is low, the pouring of the uncured concrete may be performed using the uncured concrete supply device 413 installed in the upper molding foam 400, and the dome side molding foam 300 If the height is higher than the installation position of the uncured concrete supply device 413, the casting position may be made through a separate uncured concrete supply device.

돔 측벽에 콘크리트 구조물이 성형되는 동안 돔 상부성형폼(400)의 제작이 완료되며, 돔 상부성형폼(400)의 제작이 완료되면, 견인부재(200)가 돔 상부성형폼(400)에 연결된다.While the manufacturing of the dome upper forming foam 400 is completed while the concrete structure is formed on the sidewall of the dome, when the manufacturing of the dome upper forming foam 400 is completed, the traction member 200 is connected to the dome upper forming foam 400. do.

도 14e에 도시된 바와 같이, 견인부재(200)가 돔 상부성형폼(400)에 연결되면, 견인부재(200)가 구동되면서 돔 상부성형폼(400)이 단계적으로 상승하게 되는데 이 과정에서 돔 상부성형폼(40)의 가설작업대(470)에 적재된 자재(B)를 이용하여 내부강재(490)의 조립이 지속적으로 이루어진다.As shown in FIG. 14E, when the towing member 200 is connected to the dome upper forming form 400, the dome upper forming form 400 is raised in stages while the towing member 200 is driven. The assembly of the inner steel 490 is made continuously using the material B loaded on the temporary working table 470 of the upper forming foam 40.

내부강재(490)의 조립은 돔부의 바닥에 매설된 수직연결철물(491)을 돔 상부로 연장시킴과 동시에 연장된 수직연결철물(491)들을 수평연결철물(492)들로 상호 연결시켜 이루어진다. 아울러 수직연결철물(491)들은 별도의 띠철근(493)을 통해 일정한 폭을 유지하도록 연결된다.The inner steel 490 is assembled by extending the vertical connecting hardware 491 embedded in the bottom of the dome to the upper part of the dome and interconnecting the vertical connecting hardwares 491 to the horizontal connecting hardwares 492. In addition, the vertical connection hardware 491 is connected to maintain a constant width through a separate band reinforcement (493).

도 14f에 도시된 바와 같이, 돔 상부성형폼(400)이 완전히 상승하여 성형위치에 도달하면, 돔 측벽의 콘크리트구조물의 성형은 완료된 상태가 되며, 돔 상부성형폼(400)의 상승동작도 중지된다. 돔 상부성형폼(400)의 상승동작이 중지되면, 돔 상부성형폼(400)의 하단에 잭서포트(500)가 설치되어 돔 상부성형폼(400)의 하중을 분산시킨다.As shown in FIG. 14F, when the dome upper forming foam 400 is fully raised to reach the molding position, the molding of the concrete structure of the dome sidewall is completed, and the lifting operation of the dome upper forming foam 400 is also stopped. do. When the upward movement of the dome upper forming foam 400 is stopped, the jack support 500 is installed at the lower end of the dome upper forming foam 400 to distribute the load of the dome upper forming foam 400.

그리고 돔 상부성형폼(400)은 작업프레임(480)에 미리 설치된 간격유지구(460)를 통해 내부강재(490)와 일정거리를 두고 결속된다. 또한, 작업프레임(480)에 수직지지바(미도시)를 설치하고 가설작업대(470)가 수평상태를 유지하도록 수직지지바와 가설작업대(470)의 단부를 결합시킬 수도 있다.In addition, the dome upper forming foam 400 is bound with a predetermined distance from the internal steel 490 through a gap retaining hole 460 pre-installed in the work frame 480. In addition, a vertical support bar (not shown) may be installed on the work frame 480, and the end portions of the vertical support bar and the temporary work bench 470 may be coupled to keep the temporary work bench 470 horizontal.

한편, 하부에 설치된 가설작업대(470)는 돔 상부와 간섭되므로 철거되며, 돔 상부성형폼(400)의 상단에 설치된 가설작업대(470)를 통해 내부강재(490)의 마지막 조립을 진행한다.On the other hand, the temporary work bench 470 installed on the lower side is removed because it interferes with the dome, and the last assembly of the internal steel 490 through the temporary work bench 470 installed on the upper part of the dome upper forming form 400.

이와 같이 돔 상부성형폼(400)이 완전히 상승하여 성형위치에 도달한 상태에서 내부강재(490)의 조립이 진행되는 동안, 돔 상부성형폼의 개방부(402)를 통해 미경화콘크리트가 타설된다. 그 결과 돔 측벽과 돔 상부의 성형작업이 연속적으로 이루어지게 되면서 타설경계면이 생기지 않는다.As such, while the dome upper forming foam 400 is fully raised to reach the molding position, the assembly of the internal steel 490 is performed, and the uncured concrete is poured through the opening 402 of the dome upper forming foam. . As a result, the molding work on the dome sidewall and the upper part of the dome is continuously performed, and no pour boundary surface is formed.

도 14g에 도시된 바와 같이, 내부강재(490)의 조립이 완료되면, 가설작업대(470)가 철거된 부위를 비롯하여 돔 상부성형폼(400)에 구비된 개구부(401)와 개방부(402)에 마감폼 패널이 결합되어 미경화콘크리트가 누설되지 않도록 모두 폐쇄된다.As shown in FIG. 14G, when the assembly of the internal steel 490 is completed, the opening 401 and the opening 402 provided in the dome upper forming form 400, including the site where the temporary working table 470 is removed. The finishing foam panels are coupled to each other so that uncured concrete is not leaked.

그리고, 돔 상부성형폼(400)의 최상단을 이루는 폼 패널의 중앙에 형성된 주입공(431)으로 미경화콘크리트가 천천히 주입된다. 이때, 상기 돔 상부성형폼(400)은 잭서포트(500) 및 돔부의 벽면을 통해 하중이 분산되므로, 타설된 미경화콘크리트의 엄청난 하중에도 불구하고 매우 안정된 설치상태를 유지할 수 있게 된다.Then, the uncured concrete is slowly injected into the injection hole 431 formed in the center of the foam panel forming the uppermost part of the dome upper forming foam 400. In this case, since the load is distributed through the jack support 500 and the wall surface of the dome portion, the dome upper forming foam 400 can maintain a very stable installation state despite the enormous load of the uncured concrete.

일정시간이 경과하여 주입된 미경화콘크리트가 경화되면, 상기 주입공(431)에 상기 미경화콘크리트 공급파이프 대신 그라우팅 몰탈 공급파이프(414)가 삽입되고 그라우팅 몰탈이 고압 주입된다. 그라우팅 몰탈은 미경화콘크리트가 타설되지 못한 돔부 최상단에 형성된 빈 공간을 채우게 된다.When the uncured concrete is hardened after a certain time has elapsed, the grouting mortar supply pipe 414 is inserted into the injection hole 431 instead of the uncured concrete supply pipe, and the grouting mortar is injected at a high pressure. The grouting mortar fills the empty space formed at the top of the dome where uncured concrete is not poured.

이와 같이 돔 상부에 콘크리트구조물이 성형되는 동안 돔 측부성형폼은 모두해체된다. 그리고 돔 상부에 콘크리트구조물의 성형이 완료되면, 돔 상부성형폼(400)과 간격유지구(460)와의 연결이 모두 해제되고, 잭서포트(500)가 제거된 다음 견인부재(200)가 동작되면서 돔 상부성형폼(400)이 서서히 하강한다. 이때, 돔 상부성형폼(400)이 하강하는 과정에서 수직지지대(100) 또는 견인부재(200)와 돔 상부성형폼(400)이 간섭되므로 마감폼 패널은 미리 제거되어 개구부(401)가 다시 개방되도록 한다. 또한, 돔 상부성형폼(400)은 하강과정에서 성형완료된 돔 측벽의 콘크리트구조물을 손상시키지 않도록 도 14d와 같은 가조립 상태가 되도록 일부를 미리 해체시키는 것이 좋다.As such, the dome side forming foam is dismantled while the concrete structure is formed on the dome. When the molding of the concrete structure is completed on the upper part of the dome, all of the connection between the upper dome forming foam 400 and the space maintaining hole 460 is released, and the jack support 500 is removed and then the towing member 200 is operated. The dome upper forming foam 400 is gradually lowered. At this time, since the vertical support 100 or the towing member 200 and the dome upper forming foam 400 interfere with the upper dome forming foam 400, the finishing foam panel is removed in advance, and the opening 401 is opened again. Be sure to In addition, the dome upper forming foam 400 may be dismantled in advance so as to be in a prefabricated state as shown in FIG.

도 14h에 도시된 바와 같이, 돔 상부성형폼(400)이 바닥까지 하강하면 돔 내부로 돌출된 수직지지대(100)의 상단 일부와, 견인부재(200) 및 돔 상부성형폼(400)이 모두 해체되면서 도 14i와 같은 지하 돔 콘크리트 구조물이 완성된다. 따라서, 작업자는 성형이 완료된 이후 돔 상부성형폼의 해체작업을 돔부의 바닥에서 수행하게 되므로 매우 용이하게 수행할 수 있게 된다.As shown in FIG. 14H, when the dome top forming foam 400 descends to the bottom, a part of the upper end of the vertical support 100 protruding into the dome, and the towing member 200 and the dome top forming foam 400 are both As it is dismantled, the underground dome concrete structure as shown in FIG. 14i is completed. Therefore, since the operator performs the dismantling of the dome upper forming foam after the molding is completed, it can be performed very easily.

한편, 돔 상부성형폼(400)은 돔 측부의 성형이 완료되어 돔 측부성형폼(300)이 모두 해체된 이후에 가조립되어도 무방하다. 이 경우, 돔 측부성형폼(300)과 돔 상부성형폼(400)의 조립이 함께 이루어지지 않게 되므로 돔 측부성형폼(300)의 조립시 작업공간 확보 측면에서 유리하다.On the other hand, the dome upper forming foam 400 may be temporarily assembled after the molding of the dome side is completed and all the dome side forming foam 300 is dismantled. In this case, since the assembly of the dome side forming foam 300 and the dome upper forming foam 400 is not made together, it is advantageous in terms of securing a working space when assembling the dome side forming foam 300.

이와 같이, 도면을 참조하여 본 발명의 바람직한 실시예에 대해 상술하였으나 본 발명은 전술한 실시예에 한정되지 않으며, 본 발명이 속하는 기술분야에서 통상의 지식을 가진자가 본 발명의 사상을 벗어나지 않고 변형 가능하며, 이러한 변형은 본 발명의 권리범위에 속할 것이다.As described above, preferred embodiments of the present invention are described above with reference to the drawings, but the present invention is not limited to the above-described embodiments, and those skilled in the art may modify the present invention without departing from the spirit of the present invention. Possible, such modifications will fall within the scope of the invention.

100...수직지지대 111,460...간격유지구
112,450...연결철물 120...수직철물
200,481...견인부재 210...잭로드
220...유압잭 230...견인로프
240...견인도르레 250...구동모터
300...돔 측부성형폼 400...돔 상부성형폼
401...개구부 402...개방부
410...철골프레임 420...이격부재
430...폼 패널 431...주입공
440...고정철물 460...간격유지구
470...가설작업대 480...작업프레임
490...내부강재 491...수직연결철근
492...수평연결철근 500...잭서포트
600...안내패널 A...연결부재
B...자재
100 ... vertical support 111,460 ... spacing zone
112,450 Connecting hardware 120 Vertical hardware
200,481 ... Traction member 210 ... Jack Rod
220.Hydraulic jack 230 ... towing rope
240 towing pulley 250 driving motor
300 ... Dome Side Forming Foam 400 ... Dome Top Forming Foam
401 ... opening 402 ... opening
410 steel frame 420 spacer
430 foam panel
440 ... fixed hardware 460 ... spacing zone
470 Temporary Workbench 480 Working Frame
490 Internal steel 491 Vertical reinforcing bars
492 ... Horizontal connecting bar 500 ... Jack support
600 ... Information panel A ... connection member
B ... Material

Claims (34)

돔부의 바닥에 설치된 복수의 수직지지대;
상기 수직지지대의 상단에 고정 설치된 견인부재;
돔 측부를 성형하는 돔 측부성형폼;
상기 견인부재를 통해 승강하는 돔 상부성형폼; 및
상기 견인부재를 통해 성형위치까지 상승한 상기 돔 상부성형폼의 하단을 지지해주도록 상기 돔부의 바닥에 수직으로 설치되는 잭서포트를 포함하여 구성됨을 특징으로 하는 지하 돔 콘크리트 구조물의 성형장치.
A plurality of vertical supports installed on the bottom of the dome portion;
A towing member fixed to an upper end of the vertical support;
A dome side forming foam for forming the dome side;
A dome upper forming foam for elevating through the towing member; And
And a jack support vertically installed on the bottom of the dome portion to support a lower end of the dome upper forming foam which rises to the molding position through the towing member.
제 1항에 있어서,
상기 돔 상부성형폼의 상부에는 상기 수직지지대 또는 견인부재가 통과하도록 개구부가 형성되고,
상기 개구부와 수직지지대 또는 견인부재와의 틈새는 성형과정에서 타설되는 미경화콘크리트가 누설되지 않도록 마감폼 패널을 이용하여 막도록 한 것을 특징으로 하는 지하 돔 콘크리트 구조물의 성형장치.
The method of claim 1,
An opening is formed at an upper portion of the dome upper forming foam to allow the vertical support or the pulling member to pass therethrough,
The gap between the opening and the vertical support or the traction member is to prevent the uncured concrete to be poured in the molding process by using a finishing foam panel, characterized in that for molding the underground dome concrete structure.
제 1항에 있어서,
돔 부의 바닥에는 돔 측부성형폼을 지지해 주는 수직철물들이 설치된 것을 특징으로 하는 지하 돔 콘크리트 구조물의 성형장치.
The method of claim 1,
Molding apparatus for underground dome concrete structure, characterized in that the vertical hardware is installed on the bottom of the dome side supporting the dome side forming foam.
제 3항에 있어서,
상기 수직철물은 별도의 이격부재를 통해 돔 측부성형폼과 일정거리를 유지하도록 조립되며, 돔부의 벽면과 연결부재를 통해 견고하게 고정된 것을 특징으로 하는 지하 돔 콘크리트 구조물의 성형장치.
The method of claim 3, wherein
The vertical hardware is assembled to maintain a certain distance with the dome side forming foam through a separate spacer member, the molding apparatus of the underground dome concrete structure, characterized in that it is firmly fixed through the wall and the connection member of the dome.
제 1항에 있어서,
상기 돔 상부성형폼은
돔형상의 철골프레임;
상기 철골프레임의 외측에 고정되는 이격부재; 및
상기 이격부재를 통해 상기 철골프레임의 외측에 일정거리를 두고 조립되는 폼 패널들로 구성된 것을 특징으로 하는 지하 돔 콘크리트 구조물의 성형장치.
The method of claim 1,
The dome upper molding foam
Domed steel frame;
Spacer member fixed to the outside of the steel frame; And
Molding apparatus for the underground dome concrete structure, characterized in that consisting of foam panels are assembled at a certain distance on the outside of the steel frame through the spacer member.
제 5항에 있어서,
폼 패널들의 외측면에는 상기 돔부의 벽면에 설치된 고정철물들이 일정거리를 두고 조립되는 것을 특징으로 하는 지하 돔 콘크리트 구조물의 성형장치.
6. The method of claim 5,
Forming apparatus of the underground dome concrete structure, characterized in that the fixed steel is installed on the outer surface of the foam panel on the wall surface of the dome part at a certain distance.
제 1항에 있어서,
상기 돔 상부성형폼은
돔형상의 철골프레임;
상기 철골프레임의 외측에 고정되는 이격부재; 및
외측면에 고정철물들이 일정거리를 두고 고정된 상태로 상기 이격부재를 통해 철골프레임의 외측에 일정거리를 두고 조립되는 폼 패널들로 구성된 것을 특징으로 하는 지하 돔 콘크리트 구조물의 성형장치.
The method of claim 1,
The dome upper molding foam
Domed steel frame;
Spacer member fixed to the outside of the steel frame; And
Forming apparatus of the underground dome concrete structure, characterized in that consisting of foam panels are assembled at a certain distance on the outside of the steel frame through the spacer member in a fixed state fixed to the outer surface at a certain distance.
제 6항 또는 제 7항에 있어서,
상기 고정철물들은 별도의 연결철물을 통해 상호 연결된 것을 특징으로 하는 지하 돔 콘크리트 구조물의 성형장치.
The method according to claim 6 or 7,
Forming apparatus of the underground dome concrete structure, characterized in that the fixed hardware are interconnected through a separate connecting hardware.
제 6항 또는 제 7항에 있어서,
상기 고정철물들은 별도의 연결부재를 통해 돔부의 벽면에 고정되도록 한 것을 특징으로 하는 지하 돔 콘크리트 구조물의 성형장치.
The method according to claim 6 or 7,
Forming apparatus of the underground dome concrete structure, characterized in that the fixing hardware is fixed to the wall surface of the dome portion through a separate connecting member.
제 5항에 있어서,
상기 돔 상부성형폼은 돔부의 벽면을 따라 설치된 작업프레임과 상기 작업프레임에 설치된 견인부재들을 통해 자재를 공급받아 조립되도록 한 것을 특징으로 하는 지하 돔 콘크리트 구조물의 성형장치.
6. The method of claim 5,
The dome upper forming foam is a molding apparatus for the underground dome concrete structure, characterized in that the material supplied through the work frame is installed along the wall surface of the dome and the towing members installed on the work frame.
제 10항에 있어서,
상기 작업프레임은 별도의 연결부재를 통해 돔부의 벽면에 고정된 것을 특징으로 하는 지하 돔 콘크리트 구조물의 성형장치.
The method of claim 10,
The work frame is a molding apparatus of an underground dome concrete structure, characterized in that fixed to the wall surface of the dome portion through a separate connecting member.
제 10항 또는 제 11항에 있어서,
상기 작업프레임은 간격유지구를 통해 성형폼과 일정거리를 유지한 상태로 연결된 것을 특징으로 하는 지하 돔 콘크리트 구조물의 성형장치.
The method according to claim 10 or 11,
The work frame is a molding apparatus of an underground dome concrete structure, characterized in that connected to the state maintaining a constant distance from the molding foam through the gap retaining zone.
제 10항에 있어서,
상기 작업프레임과 돔 상부성형폼 사이에는 내부강재가 더 설치된 것을 특징으로 하는 지하 돔 콘크리트 구조물의 성형장치.
The method of claim 10,
Molding apparatus for the underground dome concrete structure, characterized in that the inner steel is further installed between the work frame and the dome upper forming foam.
제 13항에 있어서,
상기 내부강재는 돔부의 바닥에 설치된 수직연결철물과, 상기 수직연결철물들과 연결되는 수평연결철물인 것을 특징으로 하는 지하 돔 콘크리트 구조물의 성형장치.
The method of claim 13,
The inner steel is a vertical connecting hardware installed on the bottom of the dome portion, the forming apparatus of the underground dome concrete structure, characterized in that the horizontal connecting hardware connected to the vertical connecting hardware.
제 14항에 있어서,
상기 수직연결철물과 수평연결철물들의 연결작업은 돔부의 벽면을 향해 돌출되도록 상기 성형폼에 설치된 가설작업대를 통해 수행되도록 한 것을 특징으로 하는 지하 돔 콘크리트 구조물의 성형장치.
The method of claim 14,
The connecting device of the vertical connecting hardware and the horizontal connecting hardware is a molding apparatus of the underground dome concrete structure, characterized in that it is carried out through a temporary work table installed in the forming foam to protrude toward the wall surface of the dome.
제 1항에 있어서,
상기 돔 상부성형폼의 일측은 미경화콘크리트가 타설될 수 있도록 개방부를 가지며, 상기 개방부는 미경화콘크리트의 타설된 이후에 별도의 마감폼 패널을 통해 마감되도록 한 것을 특징으로 하는 지하 돔 콘크리트 구조물의 성형장치.
The method of claim 1,
One side of the dome upper forming foam has an opening to be cast uncured concrete, the opening is to be finished through a separate finishing foam panel after the casting of the uncured concrete of the underground dome concrete structure Molding apparatus.
제 1항에 있어서,
상기 견인부재는
수직지지대의 상단에 설치되며 하단이 돔 상부성형폼과 연결된 잭로드; 및
상기 수직지지대의 상부에 설치되어 상기 잭로드와 협동하면서 상기 돔 상부성형폼을 수직으로 상승시키는 유압잭으로 구성된 것을 특징으로 하는 지하 돔 콘크리트 구조물의 성형장치.
The method of claim 1,
The towing member is
Jack rod is installed on the top of the vertical support and the bottom is connected to the dome upper forming foam; And
It is installed on top of the vertical support forming apparatus of the underground dome concrete structure, characterized in that composed of a hydraulic jack for vertically raising the dome upper forming foam while cooperating with the jack rod.
제 1항에 있어서,
상기 견인부재는
돔 상부성형폼의 상부에 고정된 견인로프;
수직지지대의 상부에 설치되며 상기 견인로프가 권취된 견인도르레; 및
상기 견인도르레를 구동시키는 구동모터로 구성된 것을 특징으로 하는 지하 돔 콘크리트 구조물의 성형장치.
The method of claim 1,
The towing member is
A towing rope fixed to the upper portion of the dome upper forming foam;
A towing pulley installed at an upper portion of the vertical support and tow up the towing rope; And
Molding apparatus for the underground dome concrete structure, characterized in that consisting of a drive motor for driving the towing pulley.
제 1항에 있어서,
상기 돔 상부성형폼을 구성하는 폼 패널들 중 돔부의 최상단을 이루는 폼 패널의 중앙에는 미경화콘크리트 및 그라우팅 몰탈을 주입하기 위한 주입공이 형성된 것을 특징으로 하는 지하 돔 콘크리트 구조물의 성형장치.
The method of claim 1,
Forming apparatus of the underground dome concrete structure, characterized in that the injection hole for injecting uncured concrete and grouting mortar is formed in the center of the foam panel forming the top of the dome of the foam panels forming the upper dome forming foam.
제 6항 또는 제 7항에 있어서,
상기 고정철물들의 설치위치를 지정해 주는 안내패널이 돔부의 바닥에 더 고정되는 것을 특징으로 하는 지하 돔 콘크리트 구조물의 성형장치.
The method according to claim 6 or 7,
Forming apparatus of the underground dome concrete structure, characterized in that the guide panel for designating the installation position of the fixed hardware is further fixed to the bottom of the dome.
제 6항 또는 제 7항에 있어서,
상기 고정철물들의 중간에는 고정철물들이 일정간격을 유지할 수 있도록 하면서 작업발판으로도 사용할 수 있도록 안내패널이 수평으로 설치되는 것을 특징으로 하는 지하 돔 콘크리트 구조물의 성형장치.
The method according to claim 6 or 7,
Forming apparatus of the underground dome concrete structure, characterized in that the guide panel is horizontally installed to be used as a working scaffold while maintaining the fixed interval in the middle of the fixed hardware.
제 10항에 있어서,
상기 작업프레임의 설치위치를 지정해 주는 안내패널이 돔부의 바닥에 더 고정되는 것을 특징으로 하는 지하 돔 콘크리트 구조물의 성형장치.
The method of claim 10,
Forming apparatus of the underground dome concrete structure, characterized in that the guide panel for designating the installation position of the work frame is further fixed to the bottom of the dome.
제 14항에 있어서,
상기 내부강재의 수직연결철물의 설치위치를 지정해 주는 안내패널이 돔부의 바닥에 더 고정되는 것을 특징으로 하는 지하 돔 콘크리트 구조물의 성형장치.
The method of claim 14,
Forming apparatus of the underground dome concrete structure, characterized in that the guide panel for specifying the installation position of the vertical connecting hardware of the inner steel is further fixed to the bottom of the dome.
굴착된 돔부의 바닥에 수직지지대들이 설치되는 단계;
상기 수직지지대의 상단에 견인부재가 설치되는 단계;
돔부의 바닥에서 돔 측부성형폼이 조립되는 단계;
돔부의 바닥에서 돔 상부성형폼이 가조립되는 단계;
돔 측부성형폼으로 타설되는 미경화콘크리트에 의해 돔 측부에 콘크리트 구조물이 성형되는 단계;
상기 견인부재에 의해 돔 상부성형폼이 성형위치까지 상승되는 단계;
돔 상부성형폼의 조립이 완료되는 단계;
돔부 바닥에 잭서포트가 설치되어 돔 상부성형폼의 하단이 지지되는 단계; 및
돔 상부성형폼으로 타설되는 미경화콘크리트에 의해 돔 상부에 콘크리트 구조물이 성형되는 단계를 포함하여 구성됨을 특징으로 하는 지하 콘크리트 구조물의 성형방법.
Installing vertical supports on the bottom of the excavated dome;
Installing a traction member on an upper end of the vertical support;
Assembling the dome side forming foam at the bottom of the dome portion;
Pre-assembling the dome upper forming foam at the bottom of the dome;
Forming a concrete structure on the dome side by uncured concrete poured into the dome side forming foam;
Raising a dome upper forming foam to a molding position by the traction member;
Completing the assembly of the dome upper forming foam;
A jack support is installed at the bottom of the dome to support the bottom of the dome upper forming foam; And
The method of forming an underground concrete structure, comprising the step of forming a concrete structure on the upper part of the dome by the uncured concrete poured into the dome upper forming foam.
굴착된 돔부의 바닥에 수직지지대들이 설치되는 단계;
상기 수직지지대의 상단에 견인부재가 설치되는 단계;
돔부의 바닥에서 돔 측부성형폼이 조립되는 단계;
돔 측부성형폼으로 타설되는 미경화콘크리트에 의해 돔 측부에 콘크리트 구조물이 성형되는 단계;
돔부의 바닥에서 돔 상부성형폼이 가조립되는 단계;
상기 견인부재에 의해 돔 상부성형폼이 성형위치까지 상승되는 단계;
돔 상부성형폼의 조립이 완료되는 단계;
돔부 바닥에 잭서포트가 설치되어 돔 상부성형폼의 하단이 지지되는 단계; 및
돔 상부성형폼으로 타설되는 미경화콘크리트에 의해 돔 상부에 콘크리트 구조물이 성형되는 단계를 포함하여 구성됨을 특징으로 하는 지하 콘크리트 구조물의 성형방법.
Installing vertical supports on the bottom of the excavated dome;
Installing a traction member on an upper end of the vertical support;
Assembling the dome side forming foam at the bottom of the dome portion;
Forming a concrete structure on the dome side by uncured concrete poured into the dome side forming foam;
Pre-assembling the dome upper forming foam at the bottom of the dome;
Raising a dome upper forming foam to a molding position by the traction member;
Completing the assembly of the dome upper forming foam;
A jack support is installed at the bottom of the dome to support the bottom of the dome upper forming foam; And
The method of forming an underground concrete structure, comprising the step of forming a concrete structure on the upper part of the dome by the uncured concrete poured into the dome upper forming foam.
제 24항 또는 제 25항에 있어서,
상기 돔부의 바닥에서 돔 측부성형폼이 조립되는 단계 이전에 굴착된 돔부의 바닥에 수직철물을 설치하는 단계를 더 거치도록 한 것을 특징으로 하는 지하 콘크리트 구조물의 성형방법.
The method of claim 24 or 25,
And forming a vertical hardware on the bottom of the excavated dome portion before the assembling of the dome side forming foam from the bottom of the dome portion.
제 24항 또는 제 25항에 있어서,
상기 수직지지대를 통해 견인부재가 설치되는 단계 이후에 돔부의 벽면에 연결부재가 설치되는 단계를 거치도록 하고,
상기 돔 상부에 콘크리트 구조물이 성형되는 단계 이전에 돔 상부성형폼과 연결부재가 연결되는 단계를 거치도록 한 것을 특징으로 하는 지하 콘크리트 구조물의 성형방법.
The method of claim 24 or 25,
After the step of installing the traction member through the vertical support to go through the step of installing the connection member on the wall surface of the dome,
Forming method of the underground concrete structure, characterized in that the step of connecting the dome upper forming foam and the connecting member before the step of forming the concrete structure on the dome.
제 24항 또는 제 25항에 있어서,
상기 수직지지대를 통해 견인부재가 설치되는 단계 이후에 돔부의 벽면에 고정철물이 설치되는 단계를 거치도록 하고;
상기 돔 상부에 콘크리트 구조물이 성형되는 단계 이전에, 돔 상부성형폼과 상기 고정철물이 연결되는 단계를 거치도록 한 것을 특징으로 하는 지하 콘크리트 구조물의 성형방법.
The method of claim 24 or 25,
After the step of installing the traction member through the vertical support to go through the step of installing the fixing hardware on the wall surface of the dome;
Before the concrete structure is formed on the upper part of the dome, the method of forming an underground concrete structure, characterized in that the step of passing through the step of connecting the dome upper forming foam and the fixed hardware.
제 28항에 있어서,
상기 돔부의 벽면에 고정철물이 설치되는 단계 이후에, 연결철물을 통해 상기 고정철물들이 상호연결되는 단계를 더 거치도록 한 것을 특징으로 하는 지하 콘크리트 구조물의 성형방법.
The method of claim 28,
After the fixed steel is installed on the wall surface of the dome portion, the method of forming an underground concrete structure, characterized in that further through the step of connecting the fixed hardware through a connecting hardware.
제 24항 또는 제 25항에 있어서,
상기 돔 상부에 콘크리트 구조물이 성형되는 단계 이후에, 잭서포트가 제거되는 단계와, 견인부재를 통해 돔 상부성형폼이 바닥까지 하강하는 단계와, 수직지지대와 견인부재와 돔 상부성형폼이 모두 해체되는 단계를 더 거치도록 한 것을 특징으로 하는 지하 돔 콘크리트 구조물의 성형방법.
The method of claim 24 or 25,
After the concrete structure is formed on the upper part of the dome, the jack support is removed, the dome upper forming form descends to the floor through the towing member, and the vertical support, the towing member, and the dome upper forming form are dismantled. The method of forming an underground dome concrete structure, characterized in that the step further through.
제 24항 또는 제25항에 있어서,
상기 돔부의 바닥에서 돔 상부성형폼이 가조립되는 단계 이전에, 돔부를 따라 작업프레임이 설치되는 단계와 상기 작업프레임에 견인부재가 설치되는 단계를 더 거치도록 한 것을 특징으로 하는 지하 돔 콘크리트 구조물의 성형방법.
The method of claim 24 or 25,
Before the step of assembling the dome upper forming foam at the bottom of the dome, the step of installing the work frame along the dome and the step of installing the towing member on the work frame further characterized in that Molding method.
제 31항에 있어서,
상기 돔부의 바닥에서 돔 상부성형폼이 가조립되는 단계는
돔형상의 철골프레임이 조립되는 단계와,
상기 철골프레임의 외측에 이격부재가 설치되는 단계와,
돔 측벽으로 돌출되게 상기 철골프레임에 가설작업대가 설치되는 단계와,
상기 가설작업대가 설치된 부위를 제외하고 상기 이격부재를 통해 상기 철골프레임의 외측에 일정거리를 두고 폼 패널들이 조립되는 단계로 구성된 것을 특징으로 하는 지하 돔 콘크리트 구조물의 성형방법.
32. The method of claim 31,
The step of pre-assembling the dome upper forming foam at the bottom of the dome portion
Dome-shaped steel frame is assembled,
Spaced member is installed on the outside of the steel frame;
Installing a temporary workbench on the steel frame to protrude toward the side wall of the dome;
Forming method of the underground dome concrete structure, characterized in that the foam panel is assembled with a predetermined distance to the outside of the steel frame frame through the spacer except for the installation site of the temporary work platform.
제 31항에 있어서,
상기 돔부의 바닥에서 돔 상부성형폼이 가조립되는 단계 이후에, 작업프레임과 돔 상부성형폼 사이에 내부강재가 설치되는 단계를 거치도록 하고,
상기 내부강재가 설치되는 단계 이후에는 상기 가설작업대를 철거하고 마감 폼 패널을 통해 가설작업대가 설치된 부위를 마감하는 단계를 거치도록 한 것을 특징으로 하는 지하 돔 콘크리트 구조물의 성형방법.
32. The method of claim 31,
After the dome top forming foam is temporarily assembled at the bottom of the dome, the internal steel is installed between the work frame and the dome top forming foam,
After the step of installing the internal steel, the method of forming an underground dome concrete structure, characterized in that to go through the step of removing the temporary work platform and finishing the site where the temporary work platform is installed through the finishing foam panel.
제 32항에 있어서,
상기 내부강재가 설치되는 단계 이전에, 상기 작업프레임에 설치된 견인부재들을 통해 상기 내부강재가 가설작업대에 공급되는 단계를 더 거치도록 한 것을 특징으로 하는 지하 돔 콘크리트 구조물의 성형방법.
The method of claim 32,
Before the internal steel is installed, the method of forming the underground dome concrete structure, characterized in that further through the step of supplying the internal steel to the temporary work platform through the traction members installed in the work frame.
KR1020100140353A 2010-12-31 2010-12-31 Apparatus for forming underground dome concrete structure and constructing method using the same KR101025320B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020100140353A KR101025320B1 (en) 2010-12-31 2010-12-31 Apparatus for forming underground dome concrete structure and constructing method using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020100140353A KR101025320B1 (en) 2010-12-31 2010-12-31 Apparatus for forming underground dome concrete structure and constructing method using the same

Publications (1)

Publication Number Publication Date
KR101025320B1 true KR101025320B1 (en) 2011-03-29

Family

ID=43939500

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020100140353A KR101025320B1 (en) 2010-12-31 2010-12-31 Apparatus for forming underground dome concrete structure and constructing method using the same

Country Status (1)

Country Link
KR (1) KR101025320B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108678258A (en) * 2018-06-20 2018-10-19 中国建筑局(集团)有限公司 Large-span hemispherical reinforced concrete dome structure and construction method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR0163653B1 (en) * 1995-11-14 1998-12-15 유성용 Supporting device for a sludge tank
KR20090040712A (en) * 2007-10-22 2009-04-27 보림기계공업 주식회사 Steel materials mold for underground box construction formation
KR20090126064A (en) * 2008-06-03 2009-12-08 (주)성풍건설 Wall and dome form
KR100988890B1 (en) 2008-04-22 2010-10-20 (주)성풍건설 Method for constructing dome building

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR0163653B1 (en) * 1995-11-14 1998-12-15 유성용 Supporting device for a sludge tank
KR20090040712A (en) * 2007-10-22 2009-04-27 보림기계공업 주식회사 Steel materials mold for underground box construction formation
KR100988890B1 (en) 2008-04-22 2010-10-20 (주)성풍건설 Method for constructing dome building
KR20090126064A (en) * 2008-06-03 2009-12-08 (주)성풍건설 Wall and dome form

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108678258A (en) * 2018-06-20 2018-10-19 中国建筑局(集团)有限公司 Large-span hemispherical reinforced concrete dome structure and construction method thereof
CN108678258B (en) * 2018-06-20 2024-04-19 中国建筑一局(集团)有限公司 Large-span hemispherical reinforced concrete dome structure and construction method thereof

Similar Documents

Publication Publication Date Title
KR20090047575A (en) Slip form for concrete lining of shaft tunnel and method constructing concrete lining of shaft tunnel
CN103104091A (en) Sliding mold whole lifting platform and construction method
WO2008141038A1 (en) Multi-story building
KR20200032316A (en) Method for Forming Top-down-typed Underground Strucutre using Trus-typed Support
KR100767952B1 (en) Pass way construction method below the existing foundation
KR101889064B1 (en) Construction method of a long span bridge main tower
KR101174675B1 (en) Combination structure of precast concrete beam and precast concrete column
KR102001526B1 (en) Vertical Ball Squeezing Device for Top-Down Method and Vertical Ball Squeezing Method
CN104153579A (en) Pouring formwork structure for non-standard layer structure and construction method
KR101025317B1 (en) Apparatus for forming underground dome concrete structure and constructing method using the same
KR101116254B1 (en) High-rise structure construction method by lifting up table-form
KR101013450B1 (en) Apparatus for forming underground concrete structure in which dome is integrated to vertical tunnel and constructing method using the same
CN206956979U (en) A kind of Linear shear wall with fore-set
KR20060096706A (en) Deck suspension top-down method of sub-structure
KR101025320B1 (en) Apparatus for forming underground dome concrete structure and constructing method using the same
KR20120122800A (en) Apparatus for forming underground dome structure by oil pressure type lift and constructing method using the same
KR20120122790A (en) Apparatus for forming underground dome structure by oil pressure type lift and constructing method using the same
KR100816493B1 (en) Slip form for forming concrete wall of vertical tunnel and method for construction of the concrete wall
KR101249660B1 (en) Earth pressure supporting method of walls trench applying construction of none- excavation underground structure
KR100297929B1 (en) Slip form for excavation molding in vertical tunnel
KR200390421Y1 (en) Top-down substructure by deck suspension
CN112922029A (en) Shaft-up and shaft-down channel for constructing ultra-deep shaft by reverse construction method and building method thereof
KR19990044841A (en) Slip Foam Yoke Device for Forming Perforated Wall of Vertical Tunnel>
CN111058622A (en) Large steel mould cast-in-place column construction method adopting binding and lapping mode for column steel bars
KR102705411B1 (en) Concrete wall construction device of vertical shaft using slip form

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
LAPS Lapse due to unpaid annual fee