KR101006756B1 - Vegetation net constructing on inclined plane or waterside and the method thereof - Google Patents

Vegetation net constructing on inclined plane or waterside and the method thereof Download PDF

Info

Publication number
KR101006756B1
KR101006756B1 KR1020100081010A KR20100081010A KR101006756B1 KR 101006756 B1 KR101006756 B1 KR 101006756B1 KR 1020100081010 A KR1020100081010 A KR 1020100081010A KR 20100081010 A KR20100081010 A KR 20100081010A KR 101006756 B1 KR101006756 B1 KR 101006756B1
Authority
KR
South Korea
Prior art keywords
vegetation
filler
net
network
filling
Prior art date
Application number
KR1020100081010A
Other languages
Korean (ko)
Inventor
천기화
Original Assignee
(주)한동알앤씨
한국신기술산업(주)
에스씨종합건설(주)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)한동알앤씨, 한국신기술산업(주), 에스씨종합건설(주) filed Critical (주)한동알앤씨
Priority to KR1020100081010A priority Critical patent/KR101006756B1/en
Application granted granted Critical
Publication of KR101006756B1 publication Critical patent/KR101006756B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • E02B3/122Flexible prefabricated covering elements, e.g. mats, strips
    • AHUMAN NECESSITIES
    • A01AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
    • A01GHORTICULTURE; CULTIVATION OF VEGETABLES, FLOWERS, RICE, FRUIT, VINES, HOPS OR SEAWEED; FORESTRY; WATERING
    • A01G24/00Growth substrates; Culture media; Apparatus or methods therefor
    • A01G24/40Growth substrates; Culture media; Apparatus or methods therefor characterised by their structure

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

PURPOSE: A vegetative net and an establishing method thereof are provided to be installed regardless of the size of an installation area and to improve cohesive power and durability. CONSTITUTION: A vegetative net comprises a net body(11), a filler(12) and a filler protection inner fabric(13). The net body is formed in a cylinder structure in order to keep the shape. A filler is charged inside the net body. The filler protection inner fabric is made of a natural fiber. The filler protection inner fabric is installed between the net body and the filler.

Description

하천의 법면과 수변에 설치하는 식생망 및 그 시공공법{Vegetation Net Constructing on Inclined Plane or Waterside and the Method Thereof}Vegetation Net Constructing on Inclined Plane or Waterside and the Method Thereof}

본 발명은 하천, 호소, 조정지 등의 법면과 수변의 피복 보호와 녹화를 목적으로 하는 하천에 설치하는 식생망 및 그 시공공법에 관한 것으로, 더욱 상세하게는 식생 안정이 용이하고 현지 식생종을 유지하는 빠른 녹화를 위한 2중 구조로 생태계를 복원하며, 홍수 및 재해에 안전하고 높은 밀착력과 내구성을 가지며 넓은 면적이나 좁은 면적에 상관없이 계속 시공 가능하여 공사기간을 단축할 수 있고, 지형에 구애받지 않고 시공이 가능한 식생망 및 그 시공공법에 관한 것이다.
The present invention relates to a vegetation net installed in the river for the protection and greening of the surface and water surface of rivers, lakes, control ponds, etc., and more particularly, the vegetation stability and easy to maintain local vegetation species It is a double structure for fast greening, which restores the ecosystem, is safe against floods and disasters, has high adhesion and durability, and can be constructed continuously regardless of a large or small area, which can shorten the construction period. It is about vegetation net which can be constructed without construction, and its construction method.

하천, 호소, 해안가등의 육지와 물의 경계를 이루는 수변경계부는 유수에 의한 침식과 퇴적, 침수와 건조가 반복되면서 독특한 생태계를 구성한다. 그럼에도 불구하고 현재의 각종 유수천변 정리상황은 이와 같은 생태계의 구성이 자연 상태에서 반복적으로 자연순환될 수 없도록 인공적인 암석, 콘크리트와 같은 호안부재들로 정리하고 있으나 침식이 방지되기는 커녕 오히려 유수에 의한 세굴현상과 식생식물의 전멸로 인한 침식과 자연파괴 그리고 오염이 심화되고 있다.The water change account, which forms the boundary between land and water, such as rivers, lakes, and coasts, constitutes a unique ecosystem with repeated erosion and deposition, flooding and drying. Nevertheless, the current situation of various riverside cleanup is organized by artificial rocks and concrete revetment members such that the composition of the ecosystem cannot be recirculated naturally in the natural state. Erosion, natural destruction, and pollution due to scour and destruction of vegetation are intensifying.

특히, 어패류 서식처의 폐쇄로 인한 생태계의 파괴, 그리고 생태계의 파괴로 자연정화작용의 상실에 따른 2차, 3차의 또 다른 공해문제를 야기하고 있어, 녹색공간이 부족한 도시민에게 하천변의 공간을 녹지로 재활용하자는 제안이 나오고 있다.In particular, the destruction of ecosystems due to the closure of fish and shellfish habitats, and the destruction of ecosystems, cause second and third pollution problems due to the loss of natural purification. The proposal to recycle the waste is coming out.

대표적으로 사용되는 콘크리트호안부재는 초기에는 다양한 형태의 구조물이 조직적으로 수변경계와 경사부에 설치되므로 상당히 정리된 느낌을 주며, 마치 현대문명의 상징처럼 인식되고 있으나 콘크리트에는 어떠한 생물체도 생존하지 못하고 유수천변에 서식하여야 할 각종 식물들이 멸종되어 버린다. 그결과 식물체가 번성하면서 구성하는 치밀한 뿌리조직이 없이 단순한 콘크리트와 암석재에 의지한 구조물이 그 하천이나 호소등의 바닥이 세굴과 침식의 작용으로 파괴되면서 콘크리트 나 암석의 지지기반이 사라지면서 스스로 붕괴되어 버리게 된다. 따라서 일정한 기간이 경과하면 재시공이 불가피하다. 더욱 심각한 것은 생태계의 혼란과 파괴로 인한 어패류, 각종 저서동식물, 습지미생물 등에 대한 서식처의 파괴로 인한 각종 부작용의 문제는 더욱 심각하여 하천의 자연정화작용자체를 붕괴시키고 있어 최근 한강의 경우 멸종 어종이 속출하고 있는 것이 현재의 실정이다.Representative concrete revetment members are used in the early stages because various types of structures are systematically installed in the water change system and inclined parts, giving a considerably organized feeling. Although it is recognized as a symbol of modern civilization, no living creatures survive in concrete Plants that need to live on the banks of the rivers are extinct. As a result, the structure relies on simple concrete and rock without the dense root structure that the plant thrives, and the floor of the river or lake is destroyed by scour and erosion, and the supporting base of concrete or rock disappears. It becomes. Therefore, reconstruction is inevitable after a certain period of time. More seriously, the problems of various side effects due to destruction of habitats for shellfish, various benthic plants, and wetland microorganisms due to the disruption and destruction of ecosystems are more serious and are disrupting the natural cleansing effect of rivers. It is the present situation that is succeeding one after another.

이상의 인공구조물이 갖는 단점을 해소하기 위하여 식생식물로 구성된 섶단 혹은 욋가지들을 경사면과 기초부에 설치하여 식생대의 성장환경을 조성하는 방법들이 일부분 제시되고 있다. 또 다른 방법으로는 부직포를 경사부에 포장하고 다시 여러가지 식생식물을 식재하는 방법도 있으나 주로 화학섬유사로 구성된 부직포가 식물체의 활착에 거의 도움을 주지 못하고 다양한 식물천이현상이 방해되기 때문에 시험단계에 머물고 있다. 또 다른 방법으로 접착성분과 토양 모재를 각종 식물종자와 비료를 혼합하여 경사면에 포장처리함으로써 식생대를 구성하는 방법이 주로 공사법면부에 시공하고 있으나 이러한 공법이 유수가 흐르는 곳에 적용시 유수가 한번만 흐르게 되면 대부분 유실되어 전혀 적용가능성이 없다.In order to solve the drawbacks of the above artificial structures, some methods of creating growth environments for vegetation zones have been proposed by installing alveolar lobes or vegetation composed of vegetation plants on slopes and foundations. Another method is to wrap the nonwoven fabric on the inclined part and replant various vegetation plants. However, the nonwoven fabric composed mainly of chemical fiber yarns has little help in the plant's activity and the various plant transition phenomena are hindered. have. Another method is to construct vegetation zones by mixing various plant seeds and fertilizers with adhesive components and soil base materials on the slopes. However, when the flow is applied only once when flowing water flows, Most are lost and have no applicability at all.

또 다른 방법으로 일부 유럽에서 적용하는 공법으로 코코넛섬유사를 일정한 로프로 가연(twising)한 다음 종횡으로 배치하여 겹치는 부분을 매듭처리하여 매듭부를 구성한 마름모꼴 형태의 통공이 구성되도록 한 다음 이것을 원통형으로 구성하고, 그 내부에 섬유사를 충전하여 준 호안부재가 일부 사용되고 있다. 그런데 이와 같은 구성은 하천의 유속, 토양구조, 식생의 천이형태 등에 맞추어 적용하기 어려울 뿐 아니라 가장 단점으로 지적되는 것은 식물이 안정적인 뿌리구조를 형성하기 전에 분해되어져 로프가 절단되면서 식물체 지지구조인 원통형 구조가 붕괴되어버리는 것이다.Another method applied in some European countries is to twist the coconut fiber yarn with a certain rope, and then arrange it vertically and horizontally to knot the overlapping parts so that a rhombic through-hole consisting of a knot is formed and then formed into a cylindrical shape. In addition, a part of the revetment member which filled the fiber yarn therein is used. However, such a configuration is not only difficult to apply to the flow rate of the river, the soil structure, and the transition form of the vegetation, but also to be pointed out as the most disadvantage is that the cylindrical structure, which is a plant support structure, is decomposed before the plant forms a stable root structure and the rope is cut. Will collapse.

로프의 절단 원인은 제작상 얇은 로프로 만든 망체의 강도에 따른 문제도 있으나 구조적으로 매듭부를 구성하므로서 불규칙하게 작용하는 압력에 의하여 일부가 팽창하는 경우 팽창압을 이기지 못하고 부분적으로 망체용 로프가 절단되는 것이다. 따라서 충전된 재질이 외부로 노출되어지는 단점을 개선하기 위하여 자연계에서 분해가 되지 않도록 나일론, 폴리에스터, 고무등과 같은 합성재질의 로프로 재시공하는 것이 현재의 실정이다. 이런 재시공의 문제는 사용된 합성섬유가 전혀 분해가 되지 않는 재질로 이루어져 활착을 이루어야 할 식물체의 뿌리부분 성장을 억제하며, 억지로 얽혀진 다른 천연재와의 결속이 해체되면 결국 유수에 의하여 수중이나 하천변 등에 휩쓸려 나가는 단점이 있는 것이다. 즉, 다양한 유속의 변화, 갈수기와 홍수기의 반복적인 부침, 각종 토사의 유입이나 유출현상에 맞추어 알맞은 충전압력과 망체의 내구성을 확보하지 못하고 단지 내부에 천연섬유사를 사용한다는 사실에만 집착하고 있어 성공적인 효과를 거두지 못하고 있다.
The cause of the cutting of the rope is a problem due to the strength of the mesh made of a thin rope, but it is structurally constituted by a knot, so when the portion is inflated due to an irregularly acting pressure, the rope for the mesh is partially cut. will be. Therefore, in order to improve the disadvantage that the filled material is exposed to the outside, it is presently re-installed with a rope of synthetic material such as nylon, polyester, rubber and so on so as not to be decomposed in nature. The problem of this reconstruction is that the synthetic fibers used are made of materials that do not decompose at all, thus inhibiting the growth of the root part of the plant to be swelled. There is a drawback to being swept away from the back. In other words, they are obsessed with the fact that natural fiber yarns are used only in the interior, without securing proper filling pressure and durability of meshes in accordance with various flow rate changes, repetitive ups and downs in dry and flooding seasons, and inflow or outflow of various soils. It is not working.

상기와 같은 문제점을 해결하기 위하여 본 발명은 경사면의 균배 1 대 1.5 이상의 완균배에서 유속 6m/s이하의 하천의 법면이나 수변에서 식생 안정이 용이하고 현지 식생종을 유지하며 빠른 녹화를 위한 2중 구조를 가지고, 홍수 및 재해에 안전하고 높은 밀착력과 내구성을 가지며 넓은 면적이나 좁은 면적에 상관 없이 계속 시공 가능하여 공사기간을 단축할 수 있고, 지형에 구애받지 않고 시공이 가능한 식생망 및 그 시공공법을 제공함에 있다.
In order to solve the above problems, the present invention is easy to maintain the vegetation stability on the surface or water surface of the stream of 6m / s or less in the slower than 1 / 1.5 or more of the inclined surface of the slope to maintain the local vegetation species and double for rapid greening Vegetation net and construction method that have structure, safe to flood and disaster, have high adhesion and durability, can continue construction regardless of large area or small area, and can shorten construction period, and can be constructed regardless of terrain In providing.

본 발명은 하천, 호소, 조정지, 절토(切土)지 경사면의 유실을 방지하고 수변의 피복 보호와 녹화를 위하여 하천, 호소, 조정지, 절토(切土)지 법면에 연속으로 설치하여 식물이 자랄 수 있게 제작된 식생망과 그 시공공법에 관한 것이다.The present invention prevents the loss of slopes of rivers, lakes, control ponds, cuts, and continuously installs on the surface of rivers, lakes, lakes, cuts, and cuts for plant protection and greening. It is about the vegetation net which was made and the construction method.

상기 식생망은 형태를 유지하기 위하여 통형 구조체로 만든 망체와; 상기 망체의 내부에 충전되어 파종될 씨앗이나 현지토에 포함된 씨앗이 뿌리를 내리고 상기 식생망의 하중을 유지하는 충전재와; 상기 망체와 충전재의 사이에 설치되고 상기 망체의 내부를 둘러싸게 설치되어 일정 시간이 지나면 부분분해가 일어나며 내부에 충전된 상기 충전재가 빠져 나오지 못하게 하는 천연섬유로 된 충전재보호내부천으로 구성되고, 상기 충전재는 현지 식생종을 유지하고 빠른 녹화를 위해서 현지토에 퇴비, 비료, 영양소를 섞어서 사용하며, 상기 충전재보호내부천은 통기성과 보온성이 있으며 섬유가 서로 얽히도록 기계적인 처리로 만든 천연섬유가 사용되고, 상기 충전재보호내부천에는 씨앗을 주입하기 위하여 형성된 5~25mm의 지름인 원형 구멍이 사방 연속으로 1~15cm의 간격으로 뚫여 있는 구조이다.The vegetation network is a mesh made of a cylindrical structure to maintain the shape; A filler to fill the inside of the mesh and seed to be sown, or seeds contained in local soil, to take root and maintain the load of the vegetation network; It is installed between the mesh and the filler and is installed to surround the inside of the mesh is made up of a filler protection inner cloth made of natural fibers to prevent partial decomposition occurs after the predetermined time and the filler filled therein, and the Filler is used to mix local compost, fertilizer and nutrients to local vegetation and fast greening, and the filling protection inner fabric is breathable and warm and natural fibers made by mechanical treatment to make fibers intertwine In the filling material protection fabric, a circular hole having a diameter of 5 to 25 mm formed for injecting seeds is continuously drilled at intervals of 1 to 15 cm in all directions.

식생망 시공공법은 충전재 계량 및 교반하는 제1단계와; 상기 충전재를 충전하여 식생망을 만드는 제2단계와; 상기 식생망을 운반하는 제3단계와; 상기 식생망을 1차 부설하는 제4단계와; 상기 식생망에 앵커를 타설하고 2차 부설하는 작업을 반복하는 제5단계와; 상기 식생망 포설을 마무리하는 제6단계로 구성된다.Vegetation net construction method is the first step of measuring and stirring the filler; A second step of filling the filler to create a vegetation network; Carrying out the vegetation network; A fourth step of laying the vegetation network first; A fifth step of repeating the operation of placing the anchor and placing the anchor in the vegetation network; The sixth step of finishing the vegetation net laying.

상기 제1단계는 현지토를 사용하여 충전토를 준비하는 제1-1단계와; 퇴비, 비료, 영양소를 준비하는 단계인 제1-2단계와; 상기 충전토 및 퇴비, 비료, 영양소를 계량하는 제1-3단계와, 계량된 상기 충전토 및 퇴비, 비료, 영양소를 교반하고 혼합하여 충진재를 완성하는 제1-4단계로 구성된다.The first step is the first-first step of preparing a filling earth using local soil; Steps 1 and 2, which are steps of preparing compost, fertilizer, and nutrients; The first and third steps of measuring the filling soil and compost, fertilizer, nutrients, and the first and fourth steps to complete the filler by stirring and mixing the measured filling soil and compost, fertilizer, nutrients.

상기 제2단계는 상기 망체 내부에 충전재보호내부천을 삽입하는 제2-1단계와, 상기 충전재보호내부천의 내부로 상기 충전재를 충전하는 제2-2단계와, 충전을 완료하고 상기 식생망을 마감하는 제2-3단계로 구성된다.The second step is a step 2-1 of inserting a filler protective inner fabric into the mesh body, and a second step 2-2 of filling the filler into the filler protective inner fabric, the filling is completed and the vegetation network Consists of 2-3 steps to finish.

상기 제5단계는 상기 식생망이 하나씩 따로 따로 설치되고, 상기 식생망을 설치한 정확한 위치를 잡은 제5-1단계와, 정확한 위치를 잡은 상기 식생망을 천연섬유제의 로프를 이용하여 앵커로 로프의 양쪽을 고정하는 제5-2계가 반복하여 시행된다.In the fifth step, the vegetation nets are separately installed one by one, and the 5-1 step of accurately positioning the vegetation nets is installed, and the vegetation nets having the correct positions are anchored using a rope made of natural fiber. The 5-2 system fixing both sides of is repeated.

상기 제5단계와 6단계 사이에 식생망에 씨앗을 주입하는 단계가 추가될 수도 있다.Injecting seeds into the vegetation network between the fifth and sixth step may be added.

상술한 방법에 의해 본 발명의 해결하려는 과제를 해결할 수 있다.
The problem to be solved of the present invention can be solved by the method described above.

본 발명의 하천의 법면과 수변에 설치하는 식생망 및 그 시공공법에 따르면 식생 안정이 용이하고, 현지 식생종을 유지하는 빠른 녹화를 위한 2중 구조로 생태계를 복원하며, 로프와 앵커로 결합시키므로 홍수 및 재해에 안전하고 높은 밀착력과 내구성을 가지고, 넓은 면적이나 좁은 면적에 상관 없이 계속 시공 가능하여 공사기간을 단축할 수 있고, 지형에 구애받지 않고 시공이 가능하다.
According to the vegetation net and the construction method installed on the water surface and the water surface of the present invention is easy to stabilize the vegetation, and to restore the ecosystem in a double structure for fast greening to maintain the local vegetation species, and combines with rope and anchor It is safe against floods and disasters, has high adhesion and durability, and can be constructed continuously regardless of a large area or a small area, which can shorten the construction period and can be constructed regardless of the terrain.

도 1은 본 발명의 하천의 법면과 수변에 설치하는 식생망 및 그 시공공법에 따른 식생망 설치도
도 2는 본 발명의 하천의 법면과 수변에 설치하는 식생망 및 그 시공공법에 따른 식생망 단면도 및 망체 확대도
도 3은 본 발명의 하천의 법면과 수변에 설치하는 식생망 및 그 시공공법에 따른 제1시공공법 순서도
도 4는 본 발명의 하천의 법면과 수변에 설치하는 식생망 및 그 시공공법에 따른 제2시공공법 순서도
도 5는 본 발명의 하천의 법면과 수변에 설치하는 식생망 및 그 시공공법에 따른 제3시공공법 순서도
도 6은 본 발명의 하천의 법면과 수변에 설치하는 식생망 및 그 시공공법에 따른 앵커 정면도
도 7은 본 발명의 하천의 법면과 수변에 설치하는 식생망 및 그 시공공법에 따른 식생망 이동 사시도
1 is a vegetation net installed on the water surface and the water surface of the river according to the present invention and the vegetation network installation according to the construction method
Figure 2 is a vegetation network and the enlarged view of the vegetation network according to the construction method and the vegetation network installed on the water surface and waterside of the river of the present invention
Figure 3 is a flow chart of the first construction method according to the vegetation network and its construction method installed on the water surface and waterside of the stream of the present invention
Figure 4 is a flow chart of the second construction method according to the vegetation network and its construction method installed on the water surface and the water surface of the stream of the present invention
Figure 5 is a flow chart of the third construction method according to the vegetation network and its construction method installed on the water surface and the water surface of the stream of the present invention
Figure 6 is a front view of the anchor according to the vegetation network and its construction method installed on the water surface and waterside of the river of the present invention
Figure 7 is a perspective view of the vegetation network installed on the water surface and the water surface of the river according to the present invention and the vegetation network movement method according to the construction method

먼저, 본 발명의 구체적인 설명에 들어가기에 앞서, 본 발명에 관련된 공지 기술 또는 구성에 대한 구체적인 설명이 본 발명의 요지를 불필요하게 흐릴 수 있다고 판단되는 경우에는 그 상세한 설명은 생략한다.DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS First, a detailed description of known functions and configurations incorporated herein will be omitted when it may make the subject matter of the present invention rather unclear.

또한, 후술되는 용어들은 본 발명에서의 기능을 고려하여 정의된 용어들로서 이는 사용자, 운용자의 의도 또는 관례 등에 따라 달라질 수 있으므로, 그 정의는 본 발명에 따른 "하천의 법면과 수변에 설치하는 식생망 및 그 시공공법"을 설명하는 본 명세서 전반에 걸친 내용을 토대로 내려져야 할 것이다.In addition, the terms to be described later are defined in consideration of functions in the present invention, which may vary according to the intention or custom of the user or the operator, and the definition of the term is "vegetation network installed on the surface of the river and on the waterfront". And the construction method "will be made based on the contents throughout the specification.

이하, 본 발명을 첨부 도면에 의거 상세히 설명한다.Hereinafter, the present invention will be described in detail with reference to the accompanying drawings.

도 1은 본 발명의 하천의 법면과 수변에 설치하는 식생망 및 그 시공공법에 따른 식생망 설치도이고, 도 2는 본 발명의 하천의 법면과 수변에 설치하는 식생망 및 그 시공공법에 따른 식생망 단면도 및 망체 확대도이며, 도 3은 본 발명의 하천의 법면과 수변에 설치하는 식생망 및 그 시공공법에 따른 제1시공공법 순서도이고, 도 4는 본 발명의 하천의 법면과 수변에 설치하는 식생망 및 그 시공공법에 따른 제2시공공법 순서도이며, 도 5는 본 발명의 하천의 법면과 수변에 설치하는 식생망 및 그 시공공법에 따른 제3시공공법 순서도이고, 도 6은 본 발명의 하천의 법면과 수변에 설치하는 식생망 및 그 시공공법에 따른 앵커 정면도이며, 도 7은 본 발명의 하천의 법면과 수변에 설치하는 식생망 및 그 시공공법에 따른 식생망 이동 사시도이다.1 is a vegetation net installed on the legal surface and the water surface of the river according to the present invention and the vegetation network installation method according to the construction method, Figure 2 is a vegetation net installed on the legal surface and water surface of the stream of the present invention and the construction method Vegetation network cross-sectional view and an enlarged view of the network, Figure 3 is a vegetation network installed on the water surface and the water surface of the stream of the present invention, the first construction method flow chart according to the construction method, Figure 4 is a flow chart of the river surface and water surface of the present invention Figure 2 is a flowchart of the second construction method according to the vegetation network to be installed and its construction method, Figure 5 is a flow chart of the third construction method according to the vegetation network and the construction method installed on the water surface and water surface of the stream of the present invention, Figure 6 Vegetation nets installed on the water surface and the waterfront of the river of the invention and the anchor front view according to the construction method thereof, Figure 7 is a vegetation network installed on the water surface and waterfront of the river of the present invention and vegetation network moving perspective view according to the construction method.

도 1에 도시되어 있는 것 같이 식생망(1)은 하천, 호소, 조정지, 절토(切土)지 경사면의 유실을 방지하고 수변의 피복 보호와 녹화를 위하여 하천, 호소, 조정지, 절토(切土)지 법면에 상기 식생망(1)을 연속으로 설치하여 식물이 자랄 수 있게 제작된다.As shown in Fig. 1, the vegetation net 1 prevents the loss of slopes of rivers, lakes, ponds, and cuts, and protects and greens the watersheds. The vegetation nets (1) are continuously installed on the surface of the branch to make the plants grow.

상기 식생망(1)는 1 대 1.5 이상의 완균배 즉 33.6도 이하의 경사면에서 사용되어지며 하천의 유속은 6m/s 이하이고, 단위면적(㎡)당 상기 식생망(1)의 중량은 타입에 따라 200~400kg 정도 된다.The vegetation net (1) is used on the inclined surface of less than 1 to 1.5, or less than 33.6 degrees, the flow rate of the river is less than 6m / s, the weight of the vegetation net (1) per unit area (m 2) It is about 200 ~ 400kg.

상기 식생망(1)은 형태를 유지하기 위하여 통형 구조체로 만든 망체(11)와; 상기 망체(11)의 내부에 충전되어 파종될 씨앗이나 현지토에 포함된 씨앗이 뿌리를 내리고 상기 식생망의 하중을 유지하는 충전재(12)와; 상기 망체(11)와 충전재(12)의 사이에 설치되고 상기 망체(11)의 내부를 둘러싸게 설치되어 일정 시간이 지나면 부분분해가 일어나며 내부에 충전된 상기 충전재(12)가 빠져 나오지 못하게 하는 천연섬유로 된 충전재보호내부천(13)으로 구성된다.The vegetation net (1) and the net body 11 made of a cylindrical structure to maintain the shape; Filling 12 to fill the inside of the net 11 and the seed to be sown or seed contained in the local soil takes root and maintain the load of the vegetation network; It is installed between the mesh 11 and the filler 12 and installed to surround the inside of the mesh 11 so that a partial decomposition occurs after a certain time and prevents the filler 12 charged therein from coming out. It consists of a filler protection inner fabric 13 made of fibers.

상기 충전재(12)는 현지 식생종을 유지하고 빠른 녹화를 위해서 현지토에 퇴비, 비료, 영양소를 섞어서 사용한다.The filler 12 is used to maintain the local vegetation species and to mix the compost, fertilizer, nutrients in the local soil for fast greening.

상기 충전재보호내부천(13)은 통기성과 보온성이 있으며 섬유가 서로 얽히도록 기계적인 처리로 만든 천연섬유가 사용되고, 상기 충전재보호내부천(13)에는 씨앗을 주입하기 위하여 형성된 5~25mm의 지름인 원형 구멍(131)이 사방 연속으로 1~15cm의 간격으로 뚫여 있다.The filler protective inner fabric 13 is breathable and warm and natural fibers made of a mechanical treatment so that the fibers are entangled with each other, the filler protective inner fabric 13 has a diameter of 5 ~ 25mm formed to inject seeds Circular holes 131 are continuously drilled at intervals of 1 to 15 cm in all directions.

상기 망체(11)는 천연섬유사, 화학섬유사 또는 철망을 사용하며, 천연섬유사로는 마닐라삼 섬유를 사용할 수도 있고, 화학섬유사는 석유화학제품으로 제조한 PE 등을 사용할 수 있다.The mesh 11 may use natural fiber yarn, chemical fiber yarn or wire mesh. Manila hemp fiber may be used as the natural fiber yarn, and chemical fiber yarn may use PE made of petrochemical products.

마닐라삼 섬유를 여러가닥 모아서 일정한 방향으로 꼬아 제1단계의 줄, 즉 얀(yarn)을 만들고, 이것을 몇 가닥 모아 반대방향으로 꼬아서 제2단계의 줄, 즉 스트랜드(strand)를 구성하며, 이것을 다시 3~4가닥(보통 3가닥) 모아 반대방향으로 꼬아서 로프를 만든 마닐라 로프를 사용하는 것이 유연하고 탄력성이 풍부하며 가벼워 바람직하며, 철망을 사용할 때는 고용융아연도금 처리가 된 것을 사용해야 한다.Gather several strands of manila hemp fiber and twist them in a certain direction to make a string of the first stage, or yarn, and then gather several strands and twist them in the opposite direction to form a strand of the second stage, or strand. Manila rope made of 3 ~ 4 strands (usually 3 strands) and twisted in the opposite direction is preferred to be flexible, elastic, and light, and high-strength galvanized should be used when using wire mesh.

상기 식생망(1)의 길이는 3~10m이나 설치 장소에 따라 더 짧게 만들 수도 있으며, 상기 망체(11)는 원통형상으로 직경 10~50cm, 길이는 3~10m이나 상기 충전재(12) 충전시 하부는 수평을 이루게 되어 충전 후에는 원통 형상은 아니고 도 1과 같은 모양을 갖는다.The length of the vegetation net (1) may be made shorter depending on the installation place 3 ~ 10m, the network 11 is cylindrical shape 10 ~ 50cm in diameter, the length is 3 ~ 10m but when filling the filler 12 The lower part becomes horizontal, and after filling, it is not a cylindrical shape but has a shape as shown in FIG. 1.

상기 망체(11)에는 가로 1~7cm, 세로 1~7cm의 체눈(111)을 가지면서 식물이 성장하는데 문제가 없도록 한다.The mesh 11 has a body 1111 of 1 to 7cm in width and 1 to 7cm in length so that there is no problem in the growth of the plant.

상기 충전재(12)는 현지 식생종을 유지하고 빠른 녹화를 위해서 현지토와 퇴비, 비료, 영양소 혼합으로 이루어지며, 현지토를 사용하여 충전토를 준비하고 퇴비, 비료, 영양소를 준비단계 이후 상기 충전토 및 퇴비, 비료, 영양소을 계량하며, 계량된 상기 충전토 및 퇴비, 비료, 영양소을 일정 비율로 넣어 교반하여 혼합하여 단위면적(㎡)당 상기 식생망패드(A)의 중량이 200~400kg가 되도록 한다.The filler 12 is made of a mixture of local soil and compost, fertilizers, nutrients for maintaining the local vegetation species and fast greening, preparing the filling soil using the local soil and then filling the compost, fertilizer, nutrients after the preparation step To measure the soil and compost, fertilizers, nutrients, and put the measured filling soil and compost, fertilizers, nutrients in a certain ratio and mixed so that the weight of the vegetation mesh pad (A) per unit area (㎡) to 200 ~ 400kg do.

상기 충전재보호내부천(13)은 통기성과 보온성이 있으며 섬유가 서로 얽히도록 기계적인 처리로 만든 천연섬유가 사용되고, 상기 충전재보호내부천(13)에는 씨앗을 주입하기 위하여 형성된 5~25mm의 지름인 원형 구멍이 사방 연속으로 1~15cm의 간격으로 뚫여 있으며, 상기 충전재가 누설되지 않도록 한쪽을 막고 완전 충전 후 나머지 한쪽도 막는다.The filler protective inner fabric 13 is breathable and warm and natural fibers made of a mechanical treatment so that the fibers are entangled with each other, the filler protective inner fabric 13 has a diameter of 5 ~ 25mm formed to inject seeds Circular holes are continuously drilled at intervals of 1 to 15 cm in all directions, and one side is blocked so that the filler does not leak, and the other side is also blocked after full filling.

도 2-1에 도시되어 있는 것 같이 상기 식생망(1)은 형태를 유지하기 위하여 통형 구조체로 만든 망체(11)와; 상기 망체(11)의 내부에 충전되어 파종된 씨앗이나 현지토에 포함된 씨앗이 뿌리를 내리고 상기 식생망의 하중을 유지하는 충전재(12)와; 상기 망체(11)와 충전재(12)의 사이에 설치되고 상기 망체(11)의 내부를 둘러싸게 설치되어 일정 시간이 지나면 부분분해가 일어나며 내부에 충전된 상기 충전재(12)가 빠져 나오지 못하게 하는 천연섬유로 된 충전재보호내부천(13)으로 구성된다.As shown in Fig. 2-1, the vegetation net 1 includes a net body 11 made of a tubular structure to maintain its shape; A filler 12 filling the inside of the net 11 and seeded or seed contained in local soil to take root and maintain the load of the vegetation net; It is installed between the mesh 11 and the filler 12 and installed to surround the inside of the mesh 11 so that a partial decomposition occurs after a certain time and prevents the filler 12 charged therein from coming out. It consists of a filler protection inner fabric 13 made of fibers.

도 2-2에 도시되어 있는 것 같이 상기 충전재보호내부천(13)은 통기성과 보온성이 있으며 섬유가 서로 얽히도록 기계적인 처리로 만든 천연섬유가 사용되고, 상기 충전재보호내부천(13)에는 씨앗을 주입하기 위하여 형성된 5~25mm의 지름인 원형 구멍(131)이 사방 연속으로 1~15cm의 간격으로 뚫여 있으며, 상기 원형 구멍(131)으로 씨앗을 주입할 수 있다.As shown in Fig. 2-2, the filler protection inner fabric 13 is breathable and warmth, and natural fibers made of a mechanical treatment are used so that the fibers are entangled with each other, and the filler protection inner fabric 13 has seeds. A circular hole 131 having a diameter of 5 to 25 mm formed to be injected is drilled at intervals of 1 to 15 cm continuously in all directions, and seeds may be injected into the circular hole 131.

도 2-3에 도시되어 있는 것 같이 상기 망체에는 가로 1~7cm, 세로 1~7cm의 체눈(111)을 가지며 마닐라 로프 또는 철망으로 제작된다.As shown in Fig. 2-3, the mesh has a body 111 having a width of 1 to 7 cm and a length of 1 to 7 cm, and is made of a manila rope or a wire mesh.

도 3에 도시되어 있는 것 같이 상기 식생망(1)의 제1시공공법의 순서는 충전재 계량 및 교반하는 제1단계와; 상기 충전재를 충전하여 식생망(1)을 만드는 제2단계와; 상기 식생망(1)을 운반하는 제3단계와; 상기 식생망(1)을 1차 부설하는 제4단계와; 상기 식생망(1)에 앵커를 타설하고 2차 부설하는 작업을 반복하는 제5단계와; 상기 식생망(1) 포설을 마무리하는 제6단계로 구성되며, 상기 식생망(1)은 형태를 유지하기 위하여 통형 구조체로 만든 망체(11)와; 상기 망체(11)의 내부에 충전되어 파종될 씨앗이나 현지토에 포함된 씨앗이 뿌리를 내리고 상기 식생망의 하중을 유지하는 충전재(12)와; 상기 망체(11)와 충전재(12)의 사이에 설치되고 상기 망체(11)의 내부를 둘러싸게 설치되어 일정 시간이 지나면 부분분해가 일어나며 내부에 충전된 상기 충전재(12)가 빠져 나오지 못하게 하는 천연섬유로 된 충전재보호내부천(13)으로 구성되고, 상세한 내용은 상술한 바와 같다.As shown in FIG. 3, the order of the first construction method of the vegetation net 1 includes a first step of measuring and stirring the filler; A second step of filling the filler to create a vegetation network (1); A third step of transporting the vegetation network (1); A fourth step of laying the vegetation network 1 first; A fifth step of repeating the work of placing the anchor and placing the anchor in the vegetation network (1); The vegetation network (1) consists of a sixth step of finishing the installation, the vegetation network (1) and the net body 11 made of a cylindrical structure to maintain the shape; Filling 12 to fill the inside of the net 11 and the seed to be sown or seed contained in the local soil takes root and maintain the load of the vegetation network; It is installed between the mesh 11 and the filler 12 and installed to surround the inside of the mesh 11 so that a partial decomposition occurs after a certain time and prevents the filler 12 charged therein from coming out. It consists of a filler protection inner fabric 13 made of fibers, details of which are as described above.

상기 제1단계는 현지토를 사용하여 충전토를 준비하는 제1-1단계와; 퇴비, 비료, 영양소를 준비하는 단계인 제1-2단계와; 상기 충전토 및 퇴비, 비료, 영양소를 계량하는 제1-3단계와, 계량된 상기 충전토 및 퇴비, 비료, 영양소를 교반하고 혼합하여 충진재를 완성하는 제1-4단계로 구성된다.The first step is the first-first step of preparing a filling earth using local soil; Steps 1 and 2, which are steps of preparing compost, fertilizer, and nutrients; The first and third steps of measuring the filling soil and compost, fertilizer, nutrients, and the first and fourth steps to complete the filler by stirring and mixing the measured filling soil and compost, fertilizer, nutrients.

상기 제2단계는 상기 망체(11) 내부에 충전재보호내부천(13)을 삽입하는 제2-1단계와, 상기 충전재보호내부천(13)의 내부로 상기 충전재를 충전하는 제2-2단계와, 충전을 완료하고 상기 식생망(1)을 마감하는 제2-3단계로 구성된다.The second step is a step 2-1 of inserting the filler protective inner fabric 13 into the net body 11, and the second step of filling the filler into the filler protective inner cloth 13; And, it is composed of a 2-3 step to complete the filling and closing the vegetation net (1).

상기 제3단계는 크레인에 운반용 지그(21)를 설치하는 제3-1단계와, 상기 상기 운반용 지그(21) 위에 상기 식생망(1)을 올려 놓는 제3-2단계와, 상기 운반용 지그(21)가 설치된 크레인의 붐대를 들고 부설 위치까지 상기 크레인(2)을 이동하는 제3-3단계로 구성된다.The third step is a step 3-1 for installing the transport jig 21 in the crane, the step 3-2 for placing the vegetation network 1 on the transport jig 21, and the transport jig ( 21) is configured to carry out the boom of the crane is installed, the third step of moving the crane (2) to the installation position.

상기 제4단계는 상기 식생망(1)를 부설할 위치의 법면을 정리하여 부설 준비를 하는 제4-1단계와, 상기 크레인(2)에서 상기 식생망(1)을 내려서 1차로 일렬로 부설하는 제4-2단계로 구성된다.The fourth step is a step 4-1 for arranging the surface of the position to install the vegetation network (1) to prepare for laying, and laying down the vegetation network (1) in the crane 2 first line It consists of the 4-2 step.

상기 제5단계는 상기 식생망(1)이 하나씩 따로 따로 설치되고, 상기 식생망(1)을 설치한 정확한 위치를 잡은 제5-1단계와, 정확한 위치를 잡은 상기 식생망(1)을 천연섬유제의 로프를 이용하여 앵커로 로프의 양쪽을 고정하는 제5-2계가 반복하여 시행된다.In the fifth step, the vegetation nets 1 are separately installed one by one, and the fifth and fifth steps in which the vegetation nets 1 are installed and the vegetation nets 1 in which the correct positions are made are natural. Repeatedly, the 5-2 system is used to fix both sides of the rope with anchors using fiber ropes.

각 단계별로 세부적으로 설명하면 다음과 같다.Each step will be described in detail as follows.

상기 제1단계는 식생망(1)에 충전하기 위하여 충전할 현지토와 퇴비, The first step is the local soil and compost to be charged to the vegetation network (1),

비료, 영양소를 계량하고 교반하는 단계로서 상기 식생망(1)에 충전할 내용물은 흙만 충전할 경우에는 유실의 우려와 중량이 적게 나가는 단점이 있고 현지토만 충전 시에는 식물이 자랄 수 있는 영양분이 부족하므로 현지토와 퇴비, 비료, 영양소를 일정 비율로 혼합하여 식물도 잘 자랄 수 있고 유실도 방지하며 소정의 중량도 유지할 수 있게 하는 것이다.As a step of measuring and stirring fertilizers and nutrients, the contents to be filled in the vegetation net (1) have the disadvantage of loss of weight and less weight when filling only soil, and nutrients that can grow plants when filling local soil. Because of the lack of local soil, compost, fertilizers, and nutrients in a certain ratio of the plant to grow well, to prevent loss and to maintain a certain weight.

상기 제1-1단계는 현지토를 사용하기 위하여 사용할 현지토를 확인하여 이물질이 적고 충전에 적합한 현지토를 선택하여 공사 장소로 이동시켜, 체나 바이브레이팅 스크린으로 불순물을 제거하여 충전토를 준비하는 단계이다.Step 1-1 is to check the local soil to be used in order to use the local soil by selecting a local soil that is less foreign matter and suitable for filling to move to the construction site, to remove the impurities with a sieve or vibrating screen to prepare the filling soil Step.

상기 제1-2단계는 상기 충전토와 혼합할 퇴비, 비료, 영양소를 준비하는 단계로서 퇴비는 퇴비에 이물질을 제거하기 위하여 15mm와 50mm 스크린이 부착된 바이브레이팅 스크린을 사용하여 선별하는 것이 바람직하다.Step 1-2 is a step of preparing compost, fertilizer, nutrients to be mixed with the filling soil, the compost is preferably screened using a vibrating screen attached to the 15mm and 50mm screen to remove foreign matter in the compost. .

비료는 질소, 인산, 칼리 3성분 중 2성분 이상을 함유하는 복합비료를 사용하고, 식물이 성장에 필요한 원소 , C, H, O 등 16개의 필수 원소를 포함하여 비료에 없는 영양소를 함유하는 것이 바람직하다.Fertilizer is a compound fertilizer containing two or more of the three components of nitrogen, phosphoric acid and kali, and contains nutrients not included in the fertilizer including 16 essential elements such as C, H, O, etc. desirable.

상기 제1-3단계는 이물질을 제거하고 일정 크기로 분리한 상기 충전토와 퇴비, 비료, 영양소를 일정 비율로 혼합하기 위하여 계량하는 단계로서 보통 하부를 열 수 있는 사각기둥 형태의 계량용기을 사용하며 0.5㎥이나 1.0㎥의 용기를 사용하고, 상기 계량용기는 크레인이나 포크레인으로 이동하고 들 수 있도록 로프가 부착되어 있다.Step 1-3 is a step of weighing to remove the foreign matter and separating the filling soil and compost, fertilizer, and nutrients separated into a predetermined size at a predetermined ratio, using a square column type measuring container, which can usually be opened at the bottom. A container of 0.5 m 3 or 1.0 m 3 is used, and the weighing container is attached with a rope so that it can be moved by a crane or a fork crane.

상기 충전토와 퇴비, 비료, 영양소의 혼합 비율은 상기 식생망패드(A)의 설치 장소에 따라 상이하며 보통 부피 비율로 1 대 2 ~ 1 대 10의 비율로 계량하여 혼합한다.The mixing ratio of the filling soil and the compost, fertilizers, nutrients is different depending on the installation place of the vegetation net pad (A) and is usually mixed in a volume ratio of 1 to 2 to 1 to 10.

상기 제1-4단계는 상기 제1-3단계에서 일정 비율로 계량한 충전토와 퇴비, 비료, 영양소를 교반 혼합하는 단계로서 쇼벨이나 포크레인과 같은 장비를 이용하여 충분히 교반 혼합하여 균일하게 혼합되도록 해야 한다.Steps 1-4 are a step of stirring and mixing the filling soil, compost, fertilizer, and nutrients measured at a predetermined ratio in Steps 1 to 3 so that they are sufficiently stirred and mixed by using equipment such as shovel or fork lane. Should be.

제2단계는 상기 식생망(1)를 제조하는 과정으로서 제2-1단계는 상기 망체(11) 내에 충전재보호내부천(13)을 삽입하는 단계로서 파이프에 상기 충전재보호내부천(13)을 감싸고 상기 충전재보호내부천(13)이 풀리지 않도록 테이프나 끈으로 보강하고 상기 파이프를 상기 망체(11) 안으로 넣어서 상기 충전재보호내부천(13)을 상기 망체(11) 안으로 삽입시키며 상기 충전재보호내부천(13)의 파이프 끝 부분은 밀봉하여 끝쪽으로 상기 충전재(12)가 누설되지 않도록 한다.The second step is a process of manufacturing the vegetation net (1) and the second step-1 is a step of inserting the filler protection inner cloth 13 in the net body 11, the filler protection inner cloth 13 in the pipe Wrap and reinforce with tape or string so that the filler protection inner fabric 13 does not loosen and insert the pipe into the mesh 11 to insert the filler protection inner fabric 13 into the mesh 11 and the filler protection inner fabric The pipe end of (13) is sealed to prevent leakage of the filler material 12 toward the end.

제2-2단계는 상기 충전재보호내부천(13)이 삽입된 상기 망체(11)에 상기 충전재(12)를 충전하는 단계로서 상기 충전재보호내부천(13)을 상기 망체(11)에 삽입하면서 함께 삽입된 상기 파이프로 상기 충전재를 밀어 넣어 충전한 후 상기 파이프를 빼내는 방법을 사용하는 것이 바람직하며 다른 충전방법을 사용할 수도 있으며, 상기 충전재(12)는 상술한 것과 같이 제1단계에서 충전토와 퇴비, 비료, 영양소를 일정 비율로 혼합한 것을 사용한다. Step 2-2 is a step of filling the filler 12 in the net body 11 into which the filler inner fabric 13 is inserted, while inserting the filler inner fabric 13 into the net body 11. It is preferable to use a method of removing the pipe after pushing and filling the filler with the pipe inserted together, and another filling method may be used, and the filler 12 is filled with the filling soil in the first step as described above. Use a combination of compost, fertilizer, and nutrients in a proportion.

제2-3단계는 상기 망체(11)에 상기 충전재(12)의 충전을 완료하고 상기 망체(12) 및 상기 충전재보호내부천(13) 마감하여 상기 충전재(12)가 누설되지 않록 하여 식생망(1)의 제조를 완료한다.In step 2-3, the filling of the filler 12 to the net body 11 is completed and the netting 12 and the filler protective inner cloth 13 are finished to prevent the filler 12 from leaking. The manufacture of (1) is completed.

제3단계는 상기 식생망(1)를 운반하는 단계로서 제3-1단계는 크레인에 상기 식생망(1)을 다수 개 올려서 이동할 운반용 지그(21)를 부착하는 단계로서 상기 운반용 지그(21)에는 상부측으로 상기 크레인의 후크와 연결할 수 있는 로프(211)가 구비되고 하부측으로 상기 식생망(1)을 올리는 패드(213)와 연결할 수 있는 로프(212)가 구비된다. The third step is to transport the vegetation net (1), the third step is to attach the transport jig 21 to move the plurality of vegetation net (1) to the crane to carry the jig (21) The upper side is provided with a rope 211 that can be connected to the hook of the crane and the lower side is provided with a rope 212 that can connect with the pad 213 to raise the vegetation net (1).

상기 운반용 지그(21)의 크기는 가로는 1.5~3m 정도이고, 세로는 상기 식생망(1)의 세로 크기를 고려한 크기로서 3~8m가 바람직하며, 상기 운반용 지그(21)는 철재로 만들어진다.The size of the transport jig 21 is about 1.5 to 3m in width, the length is in consideration of the vertical size of the vegetation net (1) 3 to 8m is preferable, the transport jig 21 is made of steel.

제3-2단계는 상기 식생망(1)을 상기 패드에 올리는 단계이며 상기 식생망(1)의 파손을 방지하고 형태를 유지할 수 있게 올리는 것이 바람직하다.Step 3-2 is to raise the vegetation net (1) to the pad and it is preferable to raise the vegetation net (1) to prevent damage and maintain the shape.

제3-3단계는 상기 운반용 지그(21)에 올려진 상기 식생망(1)을 크레인으로 들어 부설위치로 크레인을 이동하는 단계이다.Step 3-3 is a step of moving the crane to the laying position by lifting the vegetation net (1) mounted on the carrying jig 21 with a crane.

제4단계는 상기 식생망(1)을 1차 부설하는 단계로서 제4-1단계는 설치할 장소인 법면이나 수계를 정리하여 지면이 울퉁불퉁하지 않고 일정한 높이로 되도록 하는 단계로서 수중 시공도 가능하므로 수중에 부설 시에는 수중도 일정 높이로 정비하여 부설 후 평면을 이루도록 해야 한다.The fourth step is the step of laying the vegetation net 1 first, and the step 4-1 is the step of arranging the legal surface or the water system, which is the place to be installed, so that the ground is not bumpy and has a constant height. In the case of installation, the water should be maintained at a certain height to form a flat surface after installation.

제4-2단계는 정리된 법면이나 수계에 상기 식생망(1)를 내려 놓아 일정하게 1차 배열하여 부설하는 단계이며, 부설할 지면이 곡면일 때는 상기 식생망(1)을 구부려 1차 부설하여야 한다. Step 4-2 is a step in which the vegetation net 1 is laid down on a regular surface or in a water system, and the primary vegetation net 1 is regularly arranged and laid. When the ground to be laid is a curved surface, the vegetation net 1 is bent and placed first. shall.

제5단계는 부설된 상기 식생망(1)이 유실되거나 위치가 변경되지 않도록 하기 위하여 앵커(14)를 타설하고 2차부설 단계로서, 상기 제4단계에서 1차 부설한 상기 식상망(1)은 하나씩 따로 따로 설치되며, 제5-1단계는 상기 식싱망(1)의 정확한 위치를 잡는 2차 부설되는 제5-1단계와 정확한 위치를 잡은 상기 식생망(1)을 천연섬유제의 로프(15)를 이용하여 앵커(14)로 상기 로프(15)의 양쪽을 고정하는 제5-2계가 반복하여 시행된다. The fifth step is to install the anchor 14 so that the laid vegetation network (1) is not lost or the position is changed, and the second laying step, the food network (1) first laid in the fourth step Are installed separately one by one, and step 5-1 is a step of step 5-1 which is placed secondly to take the correct position of the fishing net 1 and the vegetation net 1 which has taken the correct position is made of natural fiber rope ( The 5-2 system which fixes both sides of the rope 15 with the anchor 14 using 15) is repeatedly performed.

즉 제5-1단계와 제5-2단계를 시행한 후 다시 반복해서 계속 제5-1단계와 제5-2단계를 시행하여 상기 식생망(1)을 하나 하나씩 로프로 앵커링 하고 따로 부설하며, 앵커링되는 장소가 겹치지 않도록 상기 앵커(14)를 박는게 바람직하다.That is, after performing the steps 5-1 and 5-2 and repeating the steps again and again, steps 5-1 and 5-2 are carried out to anchor the vegetation network 1 with ropes one by one and lay them separately. , It is preferable to anchor the anchor 14 so that the anchoring places do not overlap.

상기 앵커(14)는 위로 뽑히기 어렵게 다수 개의 날개(141)가 부착되고 100% 리사이클 되는 수지 또는 천연재료 재질로 제작된 것을 사용하고 보통 50~150cm 간격으로 상기 앵커(14)를 타설하는 것이 바람직하며, 날개(141)는 충분한 두께와 강도를 가져 물의 힘에 의해 뽑히려는 힘에 부러지지 않아야 한다.The anchor 14 is made of a resin or natural material that is attached to a plurality of wings 141 and 100% recycled hard to be pulled up, it is preferable to cast the anchor 14 at intervals of 50 ~ 150cm usually , Wings 141 should have sufficient thickness and strength so as not to be broken by the force to be pulled by the force of water.

제5-2단계의 상기 식생망(1)을 천연섬유제의 로프(15)를 이용하여 앵커(14)로 로프(15)의 양쪽을 고정하는 간격은 50~150cm 이다.The interval of fixing both sides of the rope 15 with the anchor 14 using the vegetation net 1 of step 5-2 using the rope 15 made of natural fibers is 50-150 cm.

상기 로프(15)의 양끝에는 상기 앵커(14)로 앵커링할 때 빠져나오지 않고 박기 좋도록 고리모양의 앵커홀이 형성되는 것이 바람직하며 상기 앵커홀은 상기 앵커(14)가 타이트하게 들어갈 정도로 구멍이 작고, 앵커링 완료 후 앵커머리(142)가 상기 앵커홀에서 빠져 나오지 않도록 적으며, 또한 상기 앵커(14)의 앵커머리(142)도 3~7cm 정도로 큰게 바람직하며, 앵커바디(143)의 직경도 5~20mm 사이이며 길이도 40cm 이상은 되어 충분한 깊이로 매설되도록 하는 것이 바람직하다.At both ends of the rope 15, it is preferable that a ring-shaped anchor hole is formed so as not to escape when anchoring with the anchor 14, and the anchor hole has a hole such that the anchor 14 enters tightly. Small, so that the anchor head 142 after the anchoring is completed so as not to escape from the anchor hole, and also the anchor head 142 of the anchor 14 is preferably about 3 ~ 7cm large, and also the diameter of the anchor body 143 It is preferably between 5 and 20mm and the length is more than 40cm so that it is buried to a sufficient depth.

제6단계는 상기 식생망(1)과 식생망의 사이 사이의 틈새를 포장하고 보강 마무리하는 단계로서 지형에 의해 틈새가 발생하는 곳은 포장하고 앵커링이 제대로 되지 않은 곳도 보강하여 상기 식생망(1)의 설치를 마무리 한다.The sixth step is to wrap and reinforce the gap between the vegetation network (1) and the vegetation network, where the gap is generated by the terrain is paved and reinforces even where the anchoring is not properly reinforces the vegetation network ( 1) to finish the installation.

상술한 단계를 거쳐 시공한 법면은 시공 직후에도 강고한 호안을 형성하며 시딩된 종자와 현지토에 포함되어 있는 종자에 의해 현지 생태계를 변화시키지 않는 식생의 빠른 생착이 가능하며 높은 밀착력과 내구성을 가져 홍수 및 재해에 안전하다.The surface of the building, which has been constructed through the above-mentioned steps, forms a strong revetment even after construction, and enables fast engraftment of vegetation without altering the local ecosystem by the seeded seeds and seeds contained in the local soil, and has high adhesion and durability. Safe to floods and disasters.

또한 상기 식생망(1)에 사용된 재료 및 상기 앵커(14) 및 로프(15)는 시간이 지나면 단계적으로 부식하여 환경오염이 되지 않고 100% 리사이클되는 장점이 있다.In addition, the material used in the vegetation net (1) and the anchor 14 and the rope 15 has the advantage that it is 100% recycled over time to corrode step by step without environmental pollution.

도 4에 도시되어 있는 것 같이 상기 식생망(1)의 제2시공방공의 순서는 제1시공방공의 순서와 제5단계까지는 동일하고 식생망에 씨앗을 식재하는 단계가 추가 되었으며 대별적으로는 아래와 같다.As shown in FIG. 4, the order of the second construction works of the vegetation net 1 is the same as the order of the first construction works and the fifth step is added, and the step of planting seeds in the vegetation network is added. It looks like this:

제2시공공법의 순서는 충전재 계량 및 교반하는 제1단계와; 상기 충전재를 충전하여 식생망(1)을 만드는 제2단계와; 상기 식생망(1)을 운반하는 제3단계와; 상기 식생망(1)을 1차 부설하는 제4단계와; 상기 식생망(1)에 앵커를 타설하고 2차 부설하는 작업을 반복하는 제5단계와; 상기 식생망(1)의 원형 구멍(131)에 씨앗을 식재하는 제6단계와; 상기 식생망(1) 포설을 마무리하는 제7단계로 구성되며, 상기 식생망(1)은 전술한 부분과 동일하다.The sequence of the second construction method is the first step of weighing and stirring the filler; A second step of filling the filler to create a vegetation network (1); A third step of transporting the vegetation network (1); A fourth step of laying the vegetation network 1 first; A fifth step of repeating the work of placing the anchor and placing the anchor in the vegetation network (1); A sixth step of planting seeds in the circular holes 131 of the vegetation network 1; Comprising a seventh step of finishing the vegetation net (1) laid, the vegetation net (1) is the same as the above-mentioned part.

각 단계별로 세부적 설명은 제1단계에서 5단계는 제1시공공법과 동일하고 제7단계는 제1시공공법의 6단계와 동일하므로 제6단계만 설명한다.Detailed description of each step will be described only in the sixth step because the first to fifth steps are the same as the first construction method and the seventh step is the same as the sixth step of the first construction method.

제6단계는 상기 식생망(1)의 원형 구멍(131)에 씨앗을 식재하는 단계로서, 상기 원형 구멍(131)에 씨앗홈을 파는 제6-1단계와, 상기 씨앗홈에 씨앗을 주입한는 제6-2단계와, 상기 씨앗홈을 메우는 제6-3단계로 구성된다.The sixth step is a step of planting the seed in the circular hole 131 of the vegetation net (1), the 6-1 step of selling seed grooves in the circular hole 131, and injecting seeds into the seed groove Step 6-2 and step 6-3 to fill the seed groove.

제6단계에서 사용하는 씨앗은 현지에서 자라는 식물의 씨앗을 사용하여 식생 안정이 용이하고, 현지 식생종을 유지하는 빠른 녹화를 위한 2중 구조로 생태계를 복원할 수 있도록 한다.Seeds used in the sixth step are used for seeding of plants that grow locally, so that the vegetation can be stabilized easily and the ecosystem can be restored with a double structure for fast greening that maintains local vegetation species.

또한 상기 식생망(1)에 사용된 재료 및 상기 앵커(14) 및 로프(15)는 시간이 지나면 단계적으로 부식하여 환경오염이 되지 않고 100% 리사이클되는 장점이 있다.In addition, the material used in the vegetation net (1) and the anchor 14 and the rope 15 has the advantage that it is 100% recycled over time to corrode step by step without environmental pollution.

도 5에 도시되어 있는 것 같이 상기 식생망(1)의 제3시공공법의 순서는 제1시공방법의 순서와 제6단계까지는 동일하고 제7단계에서 식생망에 씨앗, 비료, 영양소를 스프레이하는 단계가 추가 되었으며 대별적으로는 아래와 같다.As shown in FIG. 5, the order of the third construction method of the vegetation net 1 is the same as the order of the first construction method until the sixth step, and the seeds, fertilizers, and nutrients are sprayed on the vegetation network in the seventh step. Steps have been added and are generally as follows:

상기 식생망(1)의 제3시공공법의 순서는 충전재 계량 및 교반하는 제1단계와; 상기 충전재를 충전하여 식생망(1)을 만드는 제2단계와; 상기 식생망(1)을 운반하는 제3단계와; 상기 식생망(1)을 1차 부설하는 제4단계와; 상기 식생망(1)에 앵커를 타설하고 2차 부설하는 작업을 반복하는 제5단계와; 상기 식생망(1) 포설을 마무리하는 제6단계와; 식생망에 씨앗, 비료, 영양소를 스프레이하는 제7단계로 구성되며, 제6단계까지는 상기 제1시공공법과 동일하다.The order of the third construction method of the vegetation net (1) is the first step of measuring and stirring the filler; A second step of filling the filler to create a vegetation network (1); A third step of transporting the vegetation network (1); A fourth step of laying the vegetation network 1 first; A fifth step of repeating the work of placing the anchor and placing the anchor in the vegetation network (1); A sixth step of finishing laying the vegetation net (1); It consists of a seventh step of spraying seeds, fertilizers and nutrients to the vegetation net, up to the sixth step is the same as the first construction method.

상기 제7단계는 씨앗, 비료, 영양소를 혼합하는 제7-1단계와, 혼합된 씨앗, 비료, 영양소를 인력이나 기계로서 뿌리는 제7-2단계로 이루어지며, 본 제3시공공법은 물의 범람이 없는 법면에 시공하는 것이 바람직하며, 우기가 지난 가을철이나 초봄에 시공할 때 사용하는 것이 바람직하다.The seventh step consists of the 7-1 step of mixing the seeds, fertilizers, nutrients, and the 7-2 step of spraying the mixed seeds, fertilizers, nutrients as a manpower or machine, the third construction method of water It is preferable to install on the surface where there is no flooding, and to use when installing during the autumn or early spring of the rainy season.

도 6에 도시되어 있는 것 같이 상기 앵커(14)는 지면에 박히는 앵커본체(143)와 상기 앵커 본체(143)에 부착되어 위로 뽑히기 어렵게 다수 개의 날개(141)와 앵커링할 때 때려주는 앵커머리(142)로 구성되며, 100% 리사이클 되는 수지 또는 천연재료 재질로 제작된다.As shown in Figure 6, the anchor 14 is attached to the anchor body 143 and the anchor body 143 that is embedded in the ground, the anchor head that hits when anchored with a plurality of wings 141 difficult to be pulled up ( 142) and is made of 100% recycled resin or natural materials.

상기 앵커(14)의 앵커머리(142)는 3~7cm 정도로 큰게 바람직하며, 앵커바디(143)의 직경은 5~20mm 사이이며 길이도 40cm 이상은 되어 충분한 깊이로 매설되도록 하는 것이 바람직하다.The anchor head 142 of the anchor 14 is preferably about 3 ~ 7cm large, the diameter of the anchor body 143 is preferably between 5 ~ 20mm and 40cm or more in length to be embedded to a sufficient depth.

도 7에 도시되어 있는 것 같이 크레인(2)에 상기 식생망(1)을 다수 개 올려서 이동할 운반용 지그(21)를 부착하며, 상기 운반용 지그(21)에는 상부측으로 상기 크레인의 후크와 연결할 수 있는 로프(211)가 구비되고 하부측으로 상기 식생망(1)을 올리는 패드(213)와 연결할 수 있는 로프(212)가 구비된다. As illustrated in FIG. 7, a plurality of vegetation nets 1 are attached to the crane 2 to attach the transport jig 21 to be moved, and the transport jig 21 may be connected to the hook of the crane to the upper side. A rope 211 is provided and a rope 212 is provided to connect with a pad 213 that raises the vegetation net 1 to the lower side.

상기 운반용 지그(21)의 크기는 가로는 1.5~3m 정도이고, 세로는 상기 식생망(1)의 세로 크기를 고려한 크기로서 3~8m가 바람직하며, 상기 운반용 지그(21)는 철재로 만들어진다..The size of the transport jig 21 is about 1.5 to 3m in width, the length is in consideration of the vertical size of the vegetation net (1) 3 to 8m is preferable, the transport jig 21 is made of steel. .

상술할 것 같이 본 발명의 하천의 법면과 수변에 설치하는 식생망 및 그 시공공법에 따르면 식생 안정이 용이하고, 현지 식생종을 유지하는 빠른 녹화를 위한 2중 구조로 생태계를 복원하며, 로프와 앵커로 결합시키므로 홍수 및 재해에 안전하고 높은 밀착력과 내구성을 가지고, 넓은 면적이나 좁은 면적에 상관 없이 계속 시공 가능하여 공사기간을 단축할 수 있고, 지형에 구애받지 않고 시공이 가능하다.
According to the vegetation net and the construction method installed on the water surface and water surface of the present invention as described above, the vegetation stability is easy, and the ecosystem is restored to a double structure for fast greening to maintain the local vegetation species, As it is combined with anchors, it is safe against floods and disasters, has high adhesion and durability, and can be continuously constructed regardless of a large area or a small area, thereby shortening the construction period and allowing construction regardless of the terrain.

1: 식생망 11 : 망체
12 : 충전재 13 : 충전재보호내부천
131 : 원형 구멍 14 : 앵커
141 : 날개 142 : 앵커머리
143 : 앵커본체 15 : 로프
2 : 크레인 21 : 운반용 지그
1: vegetation network 11: network
12: filling material 13: filling material protection inner cloth
131: circular hole 14: anchor
141: wing 142: anchor head
143: anchor body 15: rope
2: crane 21: jig for transport

Claims (10)

하천, 호소, 조정지, 절토(切土)지 경사면의 유실을 방지하고 수변의 피복 보호와 녹화를 위하여 하천, 호소, 조정지, 절토(切土)지 법면에 연속으로 설치하여 식물이 자랄 수 있게 제작된 식생망(1)에 있어서,
상기 식생망(1)은 형태를 유지하기 위하여 통형 구조체로 만든 망체(11)와;
상기 망체(11)의 내부에 충전되어 파종될 씨앗이나 현지토에 포함된 씨앗이 뿌리를 내리고 상기 식생망의 하중을 유지하는 충전재(12)와;
상기 망체(11)와 충전재(12)의 사이에 설치되고 상기 망체(11)의 내부를 둘러싸게 설치되어 일정 시간이 지나면 부분분해가 일어나며 내부에 충전된 상기 충전재(12)가 빠져 나오지 못하게 하는 천연섬유로 된 충전재보호내부천(13)으로 구성되고,
상기 충전재(12)는 현지 식생종을 유지하고 빠른 녹화를 위해서 현지토에 퇴비, 비료, 영양소를 섞어서 사용하며,
상기 충전재보호내부천(13)은 통기성과 보온성이 있으며 섬유가 서로 얽히도록 기계적인 처리로 만든 천연섬유가 사용되고, 상기 충전재보호내부천(13)에는 씨앗을 주입하기 위하여 형성된 5~25mm의 지름인 원형 구멍(131)이 사방 연속으로 1~15cm의 간격으로 뚫여 있는 하천의 법면과 수변에 설치되는 식생망
Plants can be grown continuously by installing on river, lakes, lakes, cuts, and cuts to prevent loss of slopes on rivers, lakes, pads, and cuts. In the vegetation net (1) which became
The vegetation net (1) and the net body 11 made of a cylindrical structure to maintain the shape;
Filling 12 to fill the inside of the net 11 and the seed to be sown or seed contained in the local soil takes root and maintain the load of the vegetation network;
It is installed between the mesh 11 and the filler 12 and installed to surround the inside of the mesh 11 so that a partial decomposition occurs after a certain time and prevents the filler 12 charged therein from coming out. Made of fiber-filled inner fabric (13),
The filler (12) is used to maintain the local vegetation species and mixed with compost, fertilizer, nutrients in the local soil for quick greening,
The filler protective inner fabric 13 is breathable and warm and natural fibers made of a mechanical treatment so that the fibers are entangled with each other, the filler protective inner fabric 13 has a diameter of 5 ~ 25mm formed to inject seeds Vegetation net is installed on the water surface and the water surface of the river where the circular holes 131 are continuously drilled at intervals of 1 to 15 cm in all directions.
제1항에 있어서,
상기 망체(11)는 천연섬유사, 화학섬유사 또는 철망을 사용하는 것을 특징으로 하는 하천의 법면과 수변에 설치되는 식생망
The method of claim 1,
The net 11 is a vegetation net installed on the water surface and the water surface of the river, characterized in that using natural fiber yarn, chemical fiber yarn or wire mesh
제1항에 있어서,
상기 식생망(1)의 길이는 3~10m이고, 상기 망체(11)는 원통형상으로 직경 10~50cm, 길이는 3~10m이며, 상기 망체(11)에는 가로 1~7cm, 세로 1~7cm의 체눈(111)을 가지는 것을 특징으로 하는 하천의 법면과 수변에 설치되는 식생망
The method of claim 1,
The vegetation net (1) has a length of 3 ~ 10m, the net body 11 is cylindrical in diameter 10 ~ 50cm, the length is 3 ~ 10m, the net 11 is 1 ~ 7cm in width, 1 ~ 7cm in length Vegetation net which is installed in the water surface and the water surface of the river characterized by having the trunk 111
충전재 계량 및 교반하는 제1단계와;
상기 충전재를 충전하여 식생망(1)을 만드는 제2단계와;
상기 식생망(1)을 운반하는 제3단계와;
상기 식생망(1)을 1차 부설하는 제4단계와;
상기 식생망(1)에 앵커를 타설하고 2차 부설하는 작업을 반복하는 제5단계와;
상기 식생망(1) 포설을 마무리하는 제6단계로 구성되는 하천의 법면에 설치되는 식생망 시공방법에 있어서,
상기 식생망(1)은 형태를 유지하기 위하여 통형 구조체로 만든 망체(11)와;
상기 망체(11)의 내부에 충전되어 파종될 씨앗이나 현지토에 포함된 씨앗이 뿌리를 내리고 상기 식생망의 하중을 유지하는 충전재(12)와;
상기 망체(11)와 충전재(12)의 사이에 설치되고 상기 망체(11)의 내부를 둘러싸게 설치되어 일정 시간이 지나면 부분분해가 일어나며 내부에 충전된 상기 충전재(12)가 빠져 나오지 못하게 하는 천연섬유로 된 충전재보호내부천(13)으로 구성되고,
상기 충전재(12)는 현지 식생종을 유지하고 빠른 녹화를 위해서 현지토에 퇴비, 비료, 영양소를 섞어서 사용하며,
상기 충전재보호내부천(13)은 통기성과 보온성이 있으며 섬유가 서로 얽히도록 기계적인 처리로 만든 천연섬유가 사용되고,
상기 충전재보호내부천(13)에는 씨앗을 주입하기 위하여 형성된 5~25mm의 지름인 원형 구멍(131)이 사방 연속으로 1~15cm의 간격으로 뚫여 있으며,
상기 제1단계는 현지토를 사용하여 충전토를 준비하는 제1-1단계와; 퇴비, 비료, 영양소를 준비하는 단계인 제1-2단계와; 상기 충전토 및 퇴비, 비료, 영양소를 계량하는 제1-3단계와, 계량된 상기 충전토 및 퇴비, 비료, 영양소를 교반하고 혼합하여 충진재를 완성하는 제1-4단계로 구성되고,
상기 제2단계는 상기 망체(11) 내부에 충전재보호내부천(13)을 삽입하는 제2-1단계와, 상기 충전재보호내부천(13)의 내부로 상기 충전재를 충전하는 제2-2단계와, 충전을 완료하고 상기 식생망(1)을 마감하는 제2-3단계로 구성되며,
상기 제5단계는 상기 식생망(1)이 하나씩 따로 따로 설치되고, 상기 식생망(1)을 설치한 정확한 위치를 잡은 제5-1단계와, 정확한 위치를 잡은 상기 식생망(1)을 천연섬유제의 로프(15)를 이용하여 앵커(14)로 상기 로프(15)의 양쪽을 고정하는 제5-2단계가 반복하여 시행되는 하천의 법면과 수변에 설치하는 식생망 시공공법
A first step of metering and stirring the filler;
A second step of filling the filler to create a vegetation network (1);
A third step of transporting the vegetation network (1);
A fourth step of laying the vegetation network 1 first;
A fifth step of repeating the work of placing the anchor and placing the anchor in the vegetation network (1);
In the vegetation network construction method installed on the surface of the river consisting of the sixth step of finishing the vegetation network (1) laying,
The vegetation net (1) and the net body 11 made of a cylindrical structure to maintain the shape;
Filling 12 to fill the inside of the net 11 and the seed to be sown or seed contained in the local soil takes root and maintain the load of the vegetation network;
It is installed between the mesh 11 and the filler 12 and installed to surround the inside of the mesh 11 so that a partial decomposition occurs after a certain time and prevents the filler 12 charged therein from coming out. Made of fiber-filled inner fabric (13),
The filler (12) is used to maintain the local vegetation species and mixed with compost, fertilizer, nutrients in the local soil for quick greening,
The filler protection inner cloth 13 is breathable and warmth and natural fibers made of a mechanical treatment to intertwine the fibers are used,
The filler protective inner fabric 13 is a circular hole 131 having a diameter of 5 to 25mm formed to inject seeds in all four consecutive intervals of 1 to 15cm,
The first step is the first-first step of preparing a filling earth using local soil; Steps 1 and 2, which are steps of preparing compost, fertilizer, and nutrients; Comprising the first and third steps of measuring the filling soil and compost, fertilizer, nutrients, and the first and fourth steps to complete the filling material by stirring and mixing the measured filling soil and manure, fertilizer, nutrients,
The second step is a step 2-1 of inserting the filler protective inner fabric 13 into the net body 11, and the second step of filling the filler into the filler protective inner cloth 13; And, it is composed of the 2-3 steps to complete the filling and closing the vegetation network (1),
In the fifth step, the vegetation nets 1 are separately installed one by one, and the fifth and fifth steps in which the vegetation nets 1 are installed and the vegetation nets 1 in which the correct positions are made are natural. Vegetation net construction method installed on the water surface and the water surface of the river where the 5-2 step of fixing both sides of the rope 15 with the anchor 14 using the fiber rope 15 is repeated.
제 4항에 있어서,
상기 제3단계는 크레인에 운반용 지그(21)를 설치하는 제3-1단계와, 상기 운반용 지그(21) 위에 상기 식생망(1)을 올려 놓는 제3-2단계와, 상기 운반용 지그(21)가 설치된 크레인의 붐대를 들고 부설 위치까지 상기 크레인(2)을 이동하는 제3-3단계로 구성되고,
상기 제4단계는 상기 식생망(1)를 부설할 위치의 법면을 정리하여 부설 준비를 하는 제4-1단계와, 상기 크레인(2)에서 상기 식생망(1)을 내려서 1차로 일렬로 부설하는 제4-2단계로 구성되는 것을 특징으로 하는 하천의 법면과 수변에 설치하는 식생망 시공공법
The method of claim 4, wherein
The third step is a step 3-1 to install the transport jig 21 to the crane, the step 3-2 to put the vegetation network 1 on the transport jig 21, and the transport jig 21 ) Is composed of the third step of lifting the boom of the installed crane and moving the crane (2) to the laying position,
The fourth step is a step 4-1 for arranging the surface of the position to install the vegetation network (1) to prepare for laying, and laying down the vegetation network (1) in the crane 2 first line Vegetation net construction method installed on the water surface and water surface of the river, characterized in that consisting of the 4-2 step
충전재 계량 및 교반하는 제1단계와;
상기 충전재를 충전하여 식생망(1)을 만드는 제2단계와;
상기 식생망(1)을 운반하는 제3단계와;
상기 식생망(1)을 1차 부설하는 제4단계와;
상기 식생망(1)에 앵커를 타설하고 2차 부설하는 작업을 반복하는 제5단계와;
상기 식생망(1)에 씨앗을 주입하는 제6단계와;
상기 식생망(1) 포설을 마무리하는 제7단계로 구성되는 하천의 법면에 설치되는 식생망 시공방법에 있어서,
상기 식생망(1)은 형태를 유지하기 위하여 통형 구조체로 만든 망체(11)와;
상기 망체(11)의 내부에 충전되어 파종될 씨앗이나 현지토에 포함된 씨앗이 뿌리를 내리고 상기 식생망의 하중을 유지하는 충전재(12)와;
상기 망체(11)와 충전재(12)의 사이에 설치되고 상기 망체(11)의 내부를 둘러싸게 설치되어 일정 시간이 지나면 부분분해가 일어나며 내부에 충전된 상기 충전재(12)가 빠져 나오지 못하게 하는 천연섬유로 된 충전재보호내부천(13)으로 구성되고,
상기 충전재(12)는 현지 식생종을 유지하고 빠른 녹화를 위해서 현지토에 퇴비, 비료, 영양소를 섞어서 사용하며,
상기 충전재보호내부천(13)은 통기성과 보온성이 있으며 섬유가 서로 얽히도록 기계적인 처리로 만든 천연섬유가 사용되고,
상기 충전재보호내부천(13)에는 씨앗을 주입하기 위하여 형성된 5~25mm의 지름인 원형 구멍(131)이 사방 연속으로 1~15cm의 간격으로 뚫여 있으며,
상기 제1단계는 현지토를 사용하여 충전토를 준비하는 제1-1단계와; 퇴비, 비료, 영양소를 준비하는 단계인 제1-2단계와; 상기 충전토 및 퇴비, 비료, 영양소를 계량하는 제1-3단계와, 계량된 상기 충전토 및 퇴비, 비료, 영양소를 교반하고 혼합하여 충진재를 완성하는 제1-4단계로 구성되고,
상기 제2단계는 상기 망체(11) 내부에 충전재보호내부천(13)을 삽입하는 제2-1단계와, 상기 충전재보호내부천(13)의 내부로 상기 충전재를 충전하는 제2-2단계와, 충전을 완료하고 상기 식생망(1)을 마감하는 제2-3단계로 구성되며,
상기 제5단계는 상기 식생망(1)이 하나씩 따로 따로 설치되고, 상기 식생망(1)을 설치한 정확한 위치를 잡은 제5-1단계와, 정확한 위치를 잡은 상기 식생망(1)을 천연섬유제의 로프(15)를 이용하여 앵커(14)로 상기 로프(15)의 양쪽을 고정하는 제5-2계가 반복하여 시행되며,
상기 제6단계는 상기 충전재보호내부천(13)의 원형 구멍(131)에 씨앗을 심을 수 있는 씨앗홈을 파는 제6-1단계와, 상기 씨앗홈에 상기 씨앗을 넣는 제6-2단계와, 상기 씨앗홈을 메우는 제6-3단계로 구성되는 하천의 법면과 수변에 설치하는 식생망 시공공법
A first step of metering and stirring the filler;
A second step of filling the filler to create a vegetation network (1);
A third step of transporting the vegetation network (1);
A fourth step of laying the vegetation network 1 first;
A fifth step of repeating the work of placing the anchor and placing the anchor in the vegetation network (1);
A sixth step of injecting seeds into the vegetation network (1);
In the vegetation net construction method installed on the surface of the river consisting of the seventh step of finishing the vegetation net (1) laying,
The vegetation net (1) and the net body 11 made of a cylindrical structure to maintain the shape;
Filling 12 to fill the inside of the net 11 and the seed to be sown or seed contained in the local soil takes root and maintain the load of the vegetation network;
It is installed between the mesh 11 and the filler 12 and installed to surround the inside of the mesh 11 so that a partial decomposition occurs after a certain time and prevents the filler 12 charged therein from coming out. Made of fiber-filled inner fabric (13),
The filler (12) is used to maintain the local vegetation species and mixed with compost, fertilizer, nutrients in the local soil for quick greening,
The filler protection inner cloth 13 is breathable and warmth and natural fibers made of a mechanical treatment to intertwine the fibers are used,
The filler protective inner fabric 13 is a circular hole 131 having a diameter of 5 to 25mm formed to inject seeds in all four consecutive intervals of 1 to 15cm,
The first step is the first-first step of preparing a filling earth using local soil; Steps 1 and 2, which are steps of preparing compost, fertilizer, and nutrients; Comprising the first and third steps of measuring the filling soil and compost, fertilizer, nutrients, and the first and fourth steps to complete the filling material by stirring and mixing the measured filling soil and manure, fertilizer, nutrients,
The second step is a step 2-1 of inserting the filler protective inner fabric 13 into the net body 11, and the second step of filling the filler into the filler protective inner cloth 13; And, it is composed of the 2-3 steps to complete the filling and closing the vegetation network (1),
In the fifth step, the vegetation nets 1 are separately installed one by one, and the fifth and fifth steps in which the vegetation nets 1 are installed and the vegetation nets 1 in which the correct positions are made are natural. The 5-2 system which fixes both sides of the rope 15 with the anchor 14 using the fiber rope 15 is repeatedly performed,
The sixth step is the 6-1 step of selling seed grooves for planting seeds in the circular hole 131 of the filler protection inner fabric 13, and the 6-2 step of putting the seeds in the seed grooves; , Vegetation net construction method installed on the water surface and the water surface of the river consisting of 6-3 steps to fill the seed groove
제 6항에 있어서,
상기 제3단계는 크레인(2)에 운반용 지그(21)를 설치하는 제3-1단계와, 상기 운반용 지그(21) 위에 상기 식생망(1)을 올려 놓는 제3-2단계와, 상기 운반용 지그(21)가 설치된 크레인의 붐대를 들고 부설 위치까지 상기 크레인(2)을 이동하는 제3-3단계로 구성되고,
상기 제4단계는 상기 식생망(1)를 부설할 위치의 법면을 정리하여 부설 준비를 하는 제4-1단계와, 상기 크레인(2)에서 상기 식생망(1)을 내려서 1차로 일렬로 부설하는 제4-2단계로 구성되는 것을 특징으로 하는 하천의 법면과 수변에 설치하는 식생망 시공공법
The method of claim 6,
The third step is a step 3-1 to install the transport jig 21 on the crane 2, the step 3-2 to put the vegetation net 1 on the transport jig 21, and the transport It consists of the third to third steps of lifting the boom of the crane with the jig 21 is installed, and moving the crane 2 to the laying position,
The fourth step is a step 4-1 for arranging the surface of the position to install the vegetation network (1) to prepare for laying, and laying down the vegetation network (1) in the crane 2 first line Vegetation net construction method installed on the water surface and water surface of the river, characterized in that consisting of the 4-2 step
제 4항 내지 제 7항 중 어느 한 항에 있어서,
상기 앵커(14)는 위로 뽑히기 어렵게 다수 개의 날개(141)가 부착되고 100% 리사이클 되는 수지 또는 천연재료 재질로 제작되는 것을 특징으로 하는 하천의 법면과 수변에 설치되는 식생망 시공방법
The method according to any one of claims 4 to 7,
The anchor 14 is difficult to be pulled up a plurality of wings 141 is attached to the vegetation net construction method is installed on the water surface and water surface, characterized in that made of a resin or natural material that is 100% recycled
제 4항 또는 제 5항에 있어서,
상기 식생망(1) 포설을 마무리하는 제6단계 이후에 씨앗, 비료, 영양소를 물에 섞어 스프레이로 뿌려주는 제7단계가 추가되는 것을 특징으로 하는 하천의 법면과 수변에 설치되는 식생망 시공방법
The method according to claim 4 or 5,
After the sixth step of finishing the vegetation nets (1) laid, the seventh step of spraying the seeds, fertilizers and nutrients mixed with water and sprayed by spraying method is installed on the water surface and the water surface of the river
제 4항 내지 제 7항 중 어느 한 항에 있어서,
제5-2단계의 상기 식생망(1)을 천연섬유제의 로프를 이용하여 앵커(14)로 로프(15)의 양쪽을 고정하는 간격이 50~150cm 인 것을 특징으로 하는 하천의 법면과 수변에 설치되는 식생망 시공방법
The method according to any one of claims 4 to 7,
The vegetation nets (1) of the 5-2 step using a natural fiber rope to anchor both sides of the rope 15 with the anchor 14 is characterized in that the interval of the river and the water surface, characterized in that 50 ~ 150cm Vegetation net construction method established
KR1020100081010A 2010-08-20 2010-08-20 Vegetation net constructing on inclined plane or waterside and the method thereof KR101006756B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020100081010A KR101006756B1 (en) 2010-08-20 2010-08-20 Vegetation net constructing on inclined plane or waterside and the method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020100081010A KR101006756B1 (en) 2010-08-20 2010-08-20 Vegetation net constructing on inclined plane or waterside and the method thereof

Publications (1)

Publication Number Publication Date
KR101006756B1 true KR101006756B1 (en) 2011-01-10

Family

ID=43615959

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020100081010A KR101006756B1 (en) 2010-08-20 2010-08-20 Vegetation net constructing on inclined plane or waterside and the method thereof

Country Status (1)

Country Link
KR (1) KR101006756B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101477711B1 (en) * 2013-01-23 2014-12-30 씨에스이(주) Construction method using Porous concrete with loess, soil

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040027374A (en) * 2002-09-25 2004-04-01 암콜 인터내셔널 코포레이션 Hydraulic barrier
KR100496118B1 (en) * 2004-02-02 2005-06-16 충청북도 Method to keep a green slope surface
KR200427374Y1 (en) 2006-07-06 2006-09-25 (주)천수녹화조경 Anchor for reinforcing a slope
KR100765494B1 (en) * 2006-08-11 2007-10-10 김학기 Naturalflow barrier and the method for construction
KR20080111706A (en) * 2007-06-19 2008-12-24 이미경 Plantable gabion for river bank and construction method thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040027374A (en) * 2002-09-25 2004-04-01 암콜 인터내셔널 코포레이션 Hydraulic barrier
KR100496118B1 (en) * 2004-02-02 2005-06-16 충청북도 Method to keep a green slope surface
KR200427374Y1 (en) 2006-07-06 2006-09-25 (주)천수녹화조경 Anchor for reinforcing a slope
KR100765494B1 (en) * 2006-08-11 2007-10-10 김학기 Naturalflow barrier and the method for construction
KR20080111706A (en) * 2007-06-19 2008-12-24 이미경 Plantable gabion for river bank and construction method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101477711B1 (en) * 2013-01-23 2014-12-30 씨에스이(주) Construction method using Porous concrete with loess, soil

Similar Documents

Publication Publication Date Title
CN107893422B (en) A kind of reinforcement type ecological slope protection structure and its construction method
CN107574828B (en) Ecological restoration method for slope with irregular high and steep rocky slope and application
EP2031133B1 (en) A slope planting structure
CN103290854A (en) Fast construction method of rock slope protection
KR20090014058A (en) Vegetation method reinforced soil slopes with geotextile curtain wall combined with steel buckel and anchor nails
KR100839669B1 (en) Planting mat for afforested slope and executing structure thereof
CN110593281A (en) High-steep rock slope ecological protection system and construction method thereof
CN113235623A (en) Thick-layer base material foreign soil spray-seeding structure suitable for ecological restoration of high and steep slope and construction method thereof
KR101043361B1 (en) A vegetation mesh bag and constructing method of ecological gabion used it
CN211621621U (en) Plant biological bag protection device for high and steep rocky slope
CN211849496U (en) High steep rock slope ecological protection system
JPH11323938A (en) Greening construction method
CN211531989U (en) A plant living bag and restore domatic system for ecological bank protection
KR101006756B1 (en) Vegetation net constructing on inclined plane or waterside and the method thereof
KR100774880B1 (en) High and low wire entanglements directly connection of a fixing method construction stone
JP3429422B2 (en) Flexible seawall and greening method
CN208649992U (en) In situ for hard slope formula shore protection plants raw formula ecology transformation bank protection structure
CN201821698U (en) Plant-climbing rack for ecological rehabilitation
KR100994740B1 (en) Vegetation net pad constructing on inclined plane or waterside and the method thereof
KR101482203B1 (en) Structure of slantface tree-planted and plant method thereof
JP3722726B2 (en) Vegetation mat for slope construction
JP2000064249A (en) Greening revetment material
KR200461490Y1 (en) Vegetation Mat
JP2912938B1 (en) Greening method for flooded slopes using bamboo with excellent wave and water resistance
CN112854265A (en) Ecological restoration construction method for high and steep rock surface and ecological vertical bag used in construction method

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20131210

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20141128

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20161201

Year of fee payment: 7

LAPS Lapse due to unpaid annual fee