KR100992999B1 - Slope-reinforcement anchor for inducing soil nailing reinforcement effect and methode there of - Google Patents

Slope-reinforcement anchor for inducing soil nailing reinforcement effect and methode there of Download PDF

Info

Publication number
KR100992999B1
KR100992999B1 KR1020090081210A KR20090081210A KR100992999B1 KR 100992999 B1 KR100992999 B1 KR 100992999B1 KR 1020090081210 A KR1020090081210 A KR 1020090081210A KR 20090081210 A KR20090081210 A KR 20090081210A KR 100992999 B1 KR100992999 B1 KR 100992999B1
Authority
KR
South Korea
Prior art keywords
steel wire
packer
anchor
reinforcement
coupled
Prior art date
Application number
KR1020090081210A
Other languages
Korean (ko)
Inventor
김성례
Original Assignee
김성례
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김성례 filed Critical 김성례
Priority to KR1020090081210A priority Critical patent/KR100992999B1/en
Application granted granted Critical
Publication of KR100992999B1 publication Critical patent/KR100992999B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/80Ground anchors
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/46Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/54Piles with prefabricated supports or anchoring parts; Anchoring piles
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/08Members specially adapted to be used in prestressed constructions
    • E04C5/12Anchoring devices

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

PURPOSE: A permanent anchor for reinforcing a slope and soil nailing and a construction method thereof are provided to stabilize tensile force by enduring tensile stress using a reinforced concrete column. CONSTITUTION: A permanent anchor(100) for reinforcing a slope and soil nailing comprises an anchor(110), a free anchor(120), and a packer(130). The anchor has multiple rods(111a), pressure plates(112,112a), and a cage(111). The pressure plates are coupled to both ends of the rods. The free anchor is connected to the anchor. The packer is adhered to a perforated hole in order to separate the anchor and the free anchor from the ground.

Description

소일 네일링 보강효과를 얻는 사면보강용 영구앵커 및 그 시공방법{Slope-reinforcement anchor for inducing soil nailing reinforcement effect and methode there of}Slope-reinforcement anchor for inducing soil nailing reinforcement effect and methode there of}

본 발명은, 사면이나 법면을 보강하는 앵커에 관한 것으로, 보다 상세하게는 앵커 정착장의 케이지에 콘크리트를 주입하여 형성하는 철근콘크리트 기둥과 자유장의 강선에 콘크리트를 주입하여 형성하는 철근콘크리트 기둥이 지반강도를 증진시켜 각각 앵커기능과 소일 네일링의 기능을 동시에 얻을 수 있도록 하는 소일 네일링 보강효과를 얻는 사면보강용 영구앵커 및 그 시공방법에 관한 것이다.The present invention relates to anchors for reinforcing slopes or slopes, and more specifically, reinforced concrete columns formed by injecting concrete into cages of anchor anchorages and reinforced concrete columns formed by injecting concrete into steel wires of free-fields. The present invention relates to a permanent anchor for slope reinforcement, and a construction method thereof, which obtains a soil nailing reinforcement effect so that the anchor function and the soil nailing function can be simultaneously obtained.

일반적으로 산업이 발전함에 따라 도로건설이나 단지조성 등에서 발생하는 산지의 사면붕괴나 슬라이딩을 억제하기 위해 사면보강방법이 시행되고 있으며 이 사면보강방법은 시공 목적에 따라, 활동력 감소방법, 저항력 증강방법, 표면보호공법 등의 여러 가지로 구분되고, 이 중 저항력 증강공법의 대표적인 것으로 락볼트, 앵커, 소일 네일링, 계단식 옹벽 등이 있다.In general, as the industry develops, slope reinforcement methods are implemented to suppress slope collapse and sliding of mountainous areas occurring in road construction or complex construction, and this slope reinforcement method is used to reduce activity, increase resistance, It is divided into various kinds of surface protection method, and the like, and the representative of the resistance augmentation method is a rock bolt, anchor, soil nailing, step retaining wall.

상기 사면보강공법 중 앵커는 지반보강 뿐만 아니라, 건물, 교량 등의 구조물의 부유를 방지하는 보강체로 사용하며, 자세하게는 시멘트 페이스트 혹은 콘크리트 주입에 의해서 지중에 매설된 인장재의 선단부에 앵커 정착체가 형성되고 그것이 앵커 두부에서 인장재와 구조물이 역학적으로 연결된 상태를 앵커라 하며, 인장재에 가해지는 힘은 앵커 정착체와 앵커 두부의 구조물을 통하여 지반에 전달되는 원리를 이용한 것이다.In the slope reinforcement method, the anchor is used as a reinforcement to prevent floating of structures such as buildings and bridges as well as ground reinforcement. Specifically, anchor anchors are formed at the tip of the tension member embedded in the ground by cement paste or concrete injection. The anchor is a state in which the tension member and the structure are dynamically connected at the anchor head, and the force applied to the tension member is based on the principle of transmission to the ground through the anchor fixture and the anchor head structure.

이러한 앵커는 정착장과 자유장으로 구분되며, 상기 정착장이 지지구조물의 역할을 하게 된다.These anchors are divided into anchorages and freefields, and the anchorages serve as support structures.

그러나 종래의 앵커는 지면에 매설된 정착장에 따라 정착력이 결정되나, 자유장이 공간으로 형성되어 있으므로 인장재의 인장력 감소로 인해 정착력이 떨어지면서 강성이 유지되지 않는 문제점이 있었다.However, in the conventional anchor, the anchoring force is determined according to the anchorage embedded in the ground, but since the free field is formed as a space, there is a problem that the rigidity is not maintained while the anchoring force is decreased due to the reduction of the tensile force of the tension member.

또한, 앵커 정착을 위한 기구가 정착체의 축 중심에 위치하여 인장 응력에 저항하지 못하므로 정착체가 균열 등 손상되는 문제점이 있었다.In addition, since the mechanism for anchor anchoring is located at the center of the shaft of the anchorage and does not resist tensile stress, there is a problem that the anchorage is damaged.

이에 상술한 바와 같은 종래의 제반결함을 감안하여 이루어진 것으로, 본 발명의 목적은, 강선의 일단부를 호스로 감싸면서 케이지가 설치된 정착장으로 콘크리트가 타설되어 형성된 철근콘크리트 기둥의 정착제가 정착장의 선단부 즉, 지압판으로부터 인장응력을 견딜 수 있도록 하는 소일 네일링 보강효과를 얻는 사면보강용 영구앵커 및 그 시공방법을 제공함에 있다.In view of the above-mentioned conventional defects, the object of the present invention is to wrap the one end of the steel wire with a hose, the fixing agent of the reinforced concrete column formed by the concrete is poured into the anchorage is installed cage, the end of the anchorage In addition, the present invention provides a permanent anchor for slope reinforcement, and a construction method thereof, which achieves a nail nailing reinforcement effect to withstand tensile stresses from acupressure plate.

또한, 본 발명의 다른 목적은, 호스로 감싸지 않은 자유장의 강선에 콘크리트를 타설하여 형성되는 철근콘크리트 기둥이 구조체의 강성을 유지하도록 함으로써 철근콘크리트 기둥이 지반강도를 증진시킬 수 있을 뿐만 아니라 앵커를 시공하면서도 동시에 소일 네일링 공법의 효과를 얻을 수 있는 소일 네일링 보강효과를 얻는 사면보강용 영구앵커 및 그 시공방법을 제공함에 있다.In addition, another object of the present invention, the reinforced concrete column formed by pouring concrete to the steel wire of the free field not wrapped with a hose to maintain the rigidity of the structure, the reinforced concrete column can not only increase the ground strength, but also anchor construction At the same time, the present invention provides a permanent anchor for slope reinforcement, and a construction method for reinforcing soil nailing, in which the effect of the soil nailing method can be obtained.

본 발명 사면보강용 영구앵커는, 사면보강용 앵커로서,The permanent anchor for slope reinforcement of the present invention is an anchor for slope reinforcement,

양단부에 나사산이 형성되는 다수의 봉체가 구비되고, 상기 봉체 양단부에 결합고정되는 지압판이 구비되며, 상기 지압판의 타단부에 위치하도록 강선에 결합되어 패커를 지지하는 패커가이드판을 포함하는 케이지가 구비된 정착장과;A plurality of rods having a thread formed on both ends is provided, the pressure plate is coupled to the both ends of the rod is provided, the cage is provided with a packer guide plate coupled to the steel wire to support the packer to be located on the other end of the pressure plate Anchorages;

상기 정착장과 강선으로 연결하는 자유장과;A free field connecting the anchorage with a steel wire;

상기 정착장과 자유장 및 상기 자유장과 지면을 분리하도록 천공홀에 밀착되는 각각의 패커와;Each packer in close contact with a perforation hole to separate the anchorage field and the free field and the free field and the ground;

상기 정착장에 결합되는 강선은 호스로 감싸고, 상기 자유장의 강선은 호스로 감싸지 않은 상태에서 순차적으로 각각 타설되는 콘크리트에 의해 철근콘크리트 기둥이 형성되도록 구성되는 것을 특징으로 하는 것이다.The steel wire coupled to the anchorage is wrapped with a hose, the steel wire of the free field is characterized in that the reinforced concrete pillars are formed by concrete that is poured in sequence in the state not wrapped with a hose.

또한, 본 발명 사면보강용 영구앵커 시공방법은, 사면보강용 영구앵커 시공방법으로서, 케이지로 결합한 강선의 일단부를 호스로 감싸 정착장을 형성하고, 상기 강선의 타단부에 자유장을 연결하는 앵커를 형성하는 단계와;In addition, the present invention, the permanent anchor construction method for slope reinforcement, the permanent anchor construction method for slope reinforcement, the one end of the steel wire combined with the cage is formed with a hose to form a anchorage, the anchor for connecting the free field to the other end of the steel wire Forming a;

상기 앵커를 지면에 형성된 천공홀에 투입하는 단계와;Injecting the anchor into a drilling hole formed in the ground;

상기 정착장과 자유장을 분리하는 패커에 공기를 주입하여 천공홀 내면에 밀착시키는 단계와;Injecting air into the packer separating the anchorage field and the free field to closely contact the inner surface of the hole;

상기 패커에 의해 분리된 정착장에 콘크리트가 하부에서 상부로 채워지도록 주입하여 철근콘크리트 기둥의 정착체가 형성되도록 하는 단계와;Injecting concrete into the anchorage separated by the packer so that the concrete is filled from the lower portion to the upper portion so that the anchoring body of the reinforced concrete column is formed;

상기 정착장과 자유장을 분리하는 패커에 주입된 공기를 빼고, 상기 자유장과 지면을 분리하는 패커에 공기를 주입하여 천공홀 내면에 밀착시키는 단계와;Removing air injected into the packer separating the fixing field and the free field, injecting air into the packer separating the free field and the ground, and contacting the inner surface of the hole;

상기 패커에 의해 분리된 자유장에 콘크리트가 하부에서 상부로 채워지도록 주입하여 철근콘크리트 기둥이 양생되도록 하는 단계를 포함하는 것을 특징으로 하는 것이다.It is characterized in that it comprises a step of curing the reinforced concrete column by injecting the concrete to be filled from the bottom to the top in the free field separated by the packer.

본 발명 소일 네일링 보강효과를 얻는 사면보강용 영구앵커 및 그 시공방법에 의하면, 강선의 일단부를 호스로 감싸면서 케이지가 설치된 정착장이 천공홀에 투입된 상태에서 주입되는 공기에 의해 패커가 확장되어 천공홀에 밀착되도록 한 후, 정착장으로 콘크리트가 타설되어 형성되는 철근콘크리트 기중의 정착제가 지반으로부터 빠지지 않는 인장응력을 견딜 수 있으므로 안정된 인장력을 발휘할 수 있는 이점을 가질 수 있는 것이다.According to the present invention, the permanent anchor for slope reinforcement to obtain the soil nailing reinforcement effect and the construction method, the packer is expanded by the air injected in the state in which the cage is installed into the drilling hole while the one end of the steel wire is wrapped in a hose and drilled After being in close contact with the hole, the fixing agent in the reinforced concrete lifter, which is formed by pouring concrete into the anchorage, can withstand the tensile stress that does not fall out of the ground, thereby having the advantage of exhibiting stable tensile force.

또한, 본 발명 소일 네일링 보강효과를 얻는 사면보강용 영구앵커 및 그 시공방법에 의하면, 패커로 분리되면서 호스로 감싸지 않은 자유장의 강선에 콘크리트를 타설하므로 강선의 인장력감소가 없어 재 긴장할 필요가 없으며, 앵커의 압축과 양생된 철근콘크리트 기둥이 지반강도를 증시킬 수 있을 뿐만 아니라 앵커를 시공하면서도 소일 네일링 공법의 효과를 얻을 수 있는 이점을 가질 수 있는 것이다.In addition, according to the present invention the permanent anchor for slope reinforcement and the construction method to obtain the soil nailing reinforcement effect, since the concrete is placed on the steel wire of the free field that is separated by the packer and is not wrapped with a hose, there is no need to re-tension because there is no decrease in tensile force of the steel wire In addition, the compression of the anchor and the reinforced concrete pillars will not only increase the ground strength, but also have the advantage of achieving the effect of the soil nailing method while constructing the anchor.

이하, 첨부된 도면에 의거하여 본 발명의 일 실시예를 상세히 설명한다. 도 1은 본 발명의 분리사시도이고, 도 2는 본 발명의 결합상태도이다.Hereinafter, an embodiment of the present invention will be described in detail with reference to the accompanying drawings. 1 is an exploded perspective view of the present invention, Figure 2 is a combined state diagram of the present invention.

본 발명 사면보강용 영구앵커는, 사면보강용 앵커(100)로서, 양단부에 나사산이 형성되는 다수의 봉체(111a)가 구비되고, 상기 봉체(111a) 양단부에 결합고정되는 지압판(112)(112a)가 구비되며, 상기 지압판(112')의 타단부에 위치하도록 강선(121)에 결합되어 패커(130)를 지지하는 패커가이드판(114)을 포함하는 케이지(111)가 구비된 정착장(110)이 구성되고, 상기 정착장(110)과 강선(121)으로 연결하는 자유장(120)이 구성되며, 상기 정착장(110)과 자유장(120) 및 상기 자유장(120)과 지면을 분리하도록 천공홀(10)에 밀착되는 각각의 패커(130)(130')가 구성되고, 상기 정착장(110)에 결합되는 강선(121)은 호스(111')로 감싸고, 상기 자유장(120)의 강선(121)은 호스(111')로 감싸지 않은 상태에서 순차적으로 각각 타설되는 콘크리트에 의해 철근콘크리트 기둥이 형성되도록 구성되는 것으로, 이를 좀더 구체적으로 설명하면 다음과 같다.In the present invention, the permanent anchor for slope reinforcement is provided with a plurality of rods 111a having threads formed at both ends as anchors for slope reinforcement, and are provided with acupressure plates 112 and 112a fixed to both ends of the rods 111a. And a fixing unit having a cage 111 coupled to the steel wire 121 so as to be positioned at the other end of the pressure plate 112 'and including a packer guide plate 114 supporting the packer 130. 110 is configured, the free field 120 is connected to the anchorage 110 and the steel wire 121, the anchorage 110 and the free field 120 and the free field 120 and the ground Each packer 130 and 130 ′ in close contact with the drilling hole 10 are configured to separate the wires, and the steel wire 121 coupled to the fixing unit 110 is wrapped with a hose 111 ′, and the free field Steel wire 121 of 120 is formed so that reinforced concrete pillars are formed by concrete that is poured in sequence in the state not wrapped with a hose (111 ') This will be described in more detail as follows.

삭제delete

상기 케이지(111)는, 상기 봉체(111a)의 일단부에 고정되는 지압판(112)에 결합된 강선(121)을 수용하여 보호하도록 밀착되는 캡(113)을 더 포함하여 구비된다.The cage 111 is further provided with a cap 113 that is in close contact to receive and protect the steel wire 121 coupled to the pressure plate 112 is fixed to one end of the rod (111a).

상기 지압판(112)(112')은, 상기 봉체(111a)가 결합되도록 가장자리에 방사상으로 제1결합공(112a)이 관통되고, 상기 강선(121)이 결합되도록 내부에 방사상으로 제2결합공(112b)이 관통된다.The pressure plate (112, 112 '), the first coupling hole (112a) radially penetrates the edge so that the rod (111a) is coupled, the second coupling hole radially therein so that the steel wire 121 is coupled 112b is penetrated.

상기 패커가이드판(114)은, 상기 강선(121)이 결합되도록 내부에 방사상으로 강선결합공(114a)이 관통되면서 일측면에 패커(130)를 고정시키도록 돌출되는 후크(114b)를 포함하여 형성된다.The packer guide plate 114 includes a hook 114b protruding to fix the packer 130 on one side while the steel wire coupling hole 114a penetrates radially therein so that the steel wire 121 is coupled thereto. Is formed.

상기 패커가이드판(114)에 콘크리트 주입호스(H1)와 배출호스(H2)가 결합되도록 관통되는 인렛홀(114c)과 아울렛홀(114d)을 더 포함하여 형성된다.The packer guide plate 114 further includes an inlet hole 114c and an outlet hole 114d penetrated to couple the concrete injection hose H1 and the discharge hose H2.

상기 지압판(112)(112')에 방사상으로 관통된 제1결합공(112a)에 각각 결합된 다수의 봉체(111a)를 묶어 고정하는 고정타이(115)를 더 포함하여 구비된다.It is further provided with a fixing tie 115 for tying and fixing a plurality of rods (111a) respectively coupled to the first coupling hole (112a) radially penetrated to the pressure plate (112, 112 ').

또한, 상기 자유장(120)은, 상기 정착장(110)에 일단부가 고정되는 다수의 강선(121)이 구비되고, 상기 다수의 강선(121)을 수용하여 결합되도록 결합공(122a)이 형성된 지면지압판(122)이 구비되며, 상기 강선(121)을 수용하여 유동하지 않도록 하는 적어도 하나 이상의 스패서(123)가 구비되고, 상기 강선(121)이 결합되어 패커(130')를 지지하는 패커가이드판(124)을 포함하여 구비된다.In addition, the free field 120 is provided with a plurality of steel wires 121, one end of which is fixed to the fixing field 110, the coupling hole 122a is formed to receive and couple the plurality of steel wires 121 A ground pressure plate 122 is provided, and at least one spacer 123 for accommodating the steel wire 121 and not flowing therein is provided, and the steel wire 121 is coupled to support the packer 130 '. It is provided including a guide plate 124.

상기 스패서(123)는 강선(121)을 수용하여 결합되도록 외주면에 방사상으로 결합홈(123a)이 형성되는 것이 바람직하다.The spacer 123 preferably has a coupling groove 123a formed radially on an outer circumferential surface of the spacer 123 so as to receive and couple the steel wire 121.

상기 스패서(123)의 결합홈(123a)에 결합된 강선(121)을 고정시키는 타이로 드(125)를 더 포함하여 구비되는 것이 바람직하다.It is preferable to further include a tie rod 125 for fixing the steel wire 121 coupled to the coupling groove 123a of the spacer 123.

상기 패커가이드판(124)은, 상기 강선(121)이 결합되도록 내부에 방사상으로 강선결합공(124a)이 관통되면서 일측면에 패커(130')를 고정시키도록 돌출되는 후크(124b)를 포함하여 형성된다.The packer guide plate 124 includes a hook 124b protruding to fix the packer 130 'on one side while the steel wire coupling hole 124a penetrates radially therein so that the steel wire 121 is coupled thereto. Is formed.

상기 패커가이드판(124)에 콘크리트 주입호스(H1)와 배출호스(H2)가 결합되도록 관통되는 인렛홀(124c)과 아울렛홀(124d)을 더 포함하여 형성된다.The packer guide plate 124 further includes an inlet hole 124c and an outlet hole 124d that are penetrated to couple the concrete injection hose H1 and the discharge hose H2.

다음은 상기와 같이 구성된 본 발명의 제작 및 시공과정을 설명한다.The following describes the manufacturing and construction process of the present invention configured as described above.

먼저, 앵커(100)의 정착장(110)과 자유장(120)을 연결하는 강선(121)의 단부, 즉, 정착장(110)에 위치하는 강선(121)을 케이지(111)의 호스(111')가 감싸도록 결합한 후, 상기 호스(111')가 결합된 강선(121)에 제2결합공(112b)이 결합되도록 대향하게 지압판(112)(112')을 결합한다.First, the end of the steel wire 121 connecting the anchorage field 110 and the free field 120 of the anchor 100, that is, the steel wire 121 located in the anchorage field 110, the hose of the cage 111 ( 111 ') is coupled to wrap, and the pressure plate 112 and 112' are coupled to the steel wire 121 to which the hose 111 'is coupled to face the second coupling hole 112b.

상기 지압판(112)(112')의 제2결합공(112b)에 결합되는 강선(121)의 일반적인 고정은 쐐기형 강재를 사용하여 고정하는 것이 바람직하다.General fixing of the steel wire 121 is coupled to the second coupling hole (112b) of the pressure plate (112, 112 ') is preferably fixed using a wedge-shaped steel.

또한, 상기 케이지(111)의 봉체(111a) 나사산에 너트(N)를 체결한 상태에서 상기 너트(N)가 체결된 다수의 봉체(111a) 단부가 지압판(112)(112')에 방사상으로 관통된 제1결합공(112a)으로 각각 돌출되도록 결합한 후, 너트(N)로 체결하여 고정시킨다.Further, in the state in which the nut N is fastened to the thread 111a of the cage 111, the ends of the plurality of rods 111a to which the nut N is fastened radially to the pressure plate 112 and 112 ′. After coupling to each protruded through the first coupling hole (112a), and fastened by fixing with a nut (N).

이때, 상기 봉체(111a)에 캡(113)을 결합하는데, 상기 캡(113)은 쐐기형 강재로 고정된 강선(121)의 단부를 수용하면서 봉체(111a)를 통해 지압판(112)에 밀 착되고, 상기 지압판(112)에 밀착된 캡(113)은 봉체(111a)의 나사산에 체결되는 너트(N)에 의해 고정된다.At this time, the cap 113 is coupled to the rod body 111a. The cap 113 is in close contact with the pressure plate 112 through the rod body 111a while accommodating an end portion of the steel wire 121 fixed by the wedge-shaped steel. And, the cap 113 in close contact with the pressure plate 112 is fixed by a nut (N) fastened to the thread of the rod (111a).

여기서 상기 지압판(112)(112')에 방사상으로 관통된 제1결합공(112a)에 각각 결합된 다수의 봉체(111a)를 고정타이(115)로 묶어 움직임을 방지할 수 있는 것이다.Here, the plurality of rods 111a respectively coupled to the first coupling holes 112a radially penetrated to the pressure plate 112 and 112 'may be bundled with the fixing tie 115 to prevent movement.

상기 지압판(112') 상부에 패커(130)가 결합된 패커가이드판(114)을 결합하는데, 상기 패커가이드판(114)의 강선결합공(114a)에 강선(121)이 결합되며, 상기 강선결합공(114a)에는 패킹재가 구비되어 강선결합공(114a)과 강선(121) 사이의 공간을 밀폐시켜 타설되는 콘크리트가 새어 나오지 못하게 하면서 정착장(110)의 조립을 완료하게 된다.The packer guide plate 114 to which the packer 130 is coupled to the upper portion of the pressure plate 112 'is coupled, the steel wire 121 is coupled to the steel wire coupling hole 114a of the packer guide plate 114, the steel wire The coupling hole 114a is provided with a packing material to seal the space between the steel wire coupling hole 114a and the steel wire 121 to complete the assembly of the anchorage 110 while preventing the leaking concrete from leaking out.

또한, 상기 정착장(110)에 결합된 자유장(120)의 강선(121)은 호스(111')로 감싸지 않은 상태에서 적어도 하나 이상의 스패서(123)를 통해 결합하는데, 이는 자유장의 강선(121)에 콘크리트가 직접 타설되어 양생되므로 네일링 효과를 얻을 수 있기 때문이며, 상기 스패서(123)에 방사상으로 형성된 결합홈(123a)에 강선(121)이 결합되고, 상기 결합홈(123a)에 결합된 강선(121)은 타이로드(125)를 통해 스패서(123)에 고정되며, 상기 강선(121)의 단부에 패커가이드판(124)의 강선결합공(124a)이 결합된다.In addition, the steel wire 121 of the free field 120 coupled to the fixing field 110 is coupled through at least one or more spacers 123 in a state in which the steel wire 121 of the free field 120 is not wrapped with the hose 111 ', which is a wire of the free field ( Since the concrete is directly poured into the curing 121 to obtain a nailing effect, the steel wire 121 is coupled to the coupling groove 123a formed radially in the spacer 123, the coupling groove 123a The combined steel wire 121 is fixed to the spacer 123 through the tie rod 125, the steel wire coupling hole 124a of the packer guide plate 124 is coupled to the end of the steel wire 121.

상기 강선결합공(124a)에는 패킹재가 구비되어 강선결합공(124a)과 강선(121) 사이의 공간을 밀폐시켜 타설되는 콘크리트가 새어 나오지 못하게 하고, 상기 패커가이드판(124)의 후크(124b)에는 패커(130')가 결합되어 있으므로 자유장(120)의 조립이 완료되면서 앵커(100)가 완성된다.The steel wire coupling hole 124a is provided with a packing material to seal the space between the steel wire coupling hole 124a and the steel wire 121 to prevent the concrete from leaking out, and the hook 124b of the packer guide plate 124. Since the packer 130 'is coupled to the anchor 100 is completed as the assembly of the free field 120 is completed.

상기의 과정으로 완성된 본 발명의 설치과정은, 도 3에 도시된 바와 같이, 지반에 천공된 천공홀(10)에 앵커(100)를 결합하는데, 상기 앵커(100)의 정착장(110)이 천공홀(10)에 먼저 삽입된 후, 자유장(120)이 결합되도록 한다.Installation process of the present invention completed in the above process, as shown in Figure 3, to couple the anchor 100 to the drilled hole 10 in the ground, the anchorage 110 of the anchor 100 After being inserted into the drilling hole 10 first, the free field 120 is coupled.

이때, 상기 정착장(110)과 자유장(120)의 패커가이드판(114)(124)에 관통된 인렛홀(114c)(124c)에는 콘크리트 주입호스(H1)가 결합되고, 상기 패커가이드판(114)(124)에 관통된 아웃렛홀(114d)(124d)에는 배출호스(H2)가 결합되어 있어야 한다.At this time, the concrete injection hose (H1) is coupled to the inlet holes (114c, 124c) penetrated through the packer guide plates 114 and 124 of the fixing station 110 and the free field 120, the packer guide plate Outlet holes 114d and 124d penetrated through the 114 and 124 outlet hoses H2 should be coupled.

상기 앵커(100)가 천공홀(10)에 결합되면, 도 4 내지 도 6에 도시된 바와 같이, 별도의 공기주입구(미도시)를 통해 패커(130)에 공기를 주입하고, 주입되는 공기에 의해 패커(130)는 팽창되면서 천공홀(10) 내주면에 밀착된 상태에서 정착장(110)과 자유장(120)의 패커가이드판(114)(124) 인렛홀(114c)(124c)에 결합된 콘크리트 주입호스(H1)를 통해 정착장(110)으로 콘크리트를 주입한다.When the anchor 100 is coupled to the drilling hole 10, as shown in Figures 4 to 6, injects air into the packer 130 through a separate air inlet (not shown), to the injected air The packer 130 is expanded and coupled to the packer guide plates 114, 124, inlet holes 114c, 124c of the anchorage field 110 and the free field 120 while being in close contact with the inner circumferential surface of the drilling hole 10. The concrete is injected into the fixing station 110 through the concrete injection hose (H1).

상기 정착장(110)으로 주입되는 콘크리트는 케이지(111)와 정착장(110)에 위치한 천공홀(10)에 충진되는데, 상기 천공홀(10)과 케이지(111)에 충진되는 콘크리트가 호스(111')가 감싼 강선(121)의 단부와 케이지(111)를 수용하도록 충진되면서 패커가이드판(114)에 밀착됨과 동시에 아웃렛홀(114d)에 결합된 배출호스(H2)로 정착장(110)에 위치한 공기 및 충진이 완료된 콘크리트가 배출되면, 콘크리트의 주입을 중단시킨 상태에서 주입호스(H1)와 배출호스(H2)의 단부를 자유장(120) 내부로 이동시켜 양생시킨다.Concrete injected into the anchorage 110 is filled in the cage 111 and the drilling hole 10 located in the anchorage 110, the concrete filled in the drilling hole 10 and the cage 111 is a hose ( 111 ') is filled to accommodate the end of the wrapped steel wire 121 and the cage 111 while being in close contact with the packer guide plate 114 and at the same time as the discharge hose (H2) coupled to the outlet hole (114d) When the air and the filling is located in the concrete is discharged, the end of the injection hose (H1) and the discharge hose (H2) in the suspended state of the concrete is moved to the free field 120 to cure.

여기서 상기 정착장(110)의 케이지(111)와 상기 정착장(110)에 위치한 강 선(121)이 정착장(110)에 충진되는 콘크리트의 골조가 되는 것이다.Here, the cage 111 of the anchorage 110 and the steel wire 121 located in the anchorage 110 become a frame of concrete filled in the anchorage 110.

상기 정착장(110)에 충진된 콘크리트가 양생되면, 도 7 내지 도 10에 도시된 바와 같이, 패커(130)에 주입된 공기를 별도의 공기주입구(미도시)에서 흡입하여 공기를 빼낸 상태에서 패커(130')에 공기를 주입한다.When the concrete filled in the fixing station 110 is cured, as shown in Figure 7 to 10, in the air injected into the packer 130 in a separate air inlet (not shown) in the state to extract the air Air is injected into the packer 130 '.

상기 패커(130')는 주입되는 공기에 의해 팽창되면서 천공홀(10)에 내주면에 밀착된 상태에서 자유장(120)에 위치한 주입호스(H1)를 통해 콘크리트를 주입하여 자유장(120)에 충진한다.The packer 130 ′ is inflated by the injected air and injected concrete through the injection hose H1 located in the free field 120 while being in close contact with the inner circumferential surface of the drilling hole 10 to the free field 120. Fill.

상기 자유장(120)에 충진되는 콘크리트는 호스(111')가 감싸지 않은 강선(121) 및 상기 강선(121)이 결합홈(123a)에 결합되면서 타이로드(125)로 고정시킨 스패서(123)를 수용하도록 충진되면서 패커가이드판(124)에 밀착됨과 동시에 아웃렛홀(124d)에 결합된 배출호스(H2)로 자유장(120)에 위치한 공기 및 충진이 완료된 콘크리트가 배출되는데, 상기 강선(121)과 스패서(123)가 자유장(120)의 콘크리트의 골조가 되는 것이며, 상기 콘크리트의 주입을 중단시킨 상태에서 상기 주입호스(H1)와 배출호스(H2)를 자유장(120) 외부로 이동시킨 후, 양생시킨다.The concrete filled in the free field 120 is a steel wire 121 that is not wrapped around the hose 111 'and a spacer 123 fixed to the tie rod 125 while the steel wire 121 is coupled to the coupling groove 123a. ) Is filled to accommodate the packer guide plate 124 and at the same time as the discharge hose (H2) coupled to the outlet hole (124d) is discharged air and the concrete is completed in the free field 120 is discharged, the steel wire ( 121) and the spacer 123 is to be a frame of the concrete of the free field 120, the injection hose (H1) and the discharge hose (H2) outside the free field 120 in the state of stopping the injection of the concrete Move to and cure.

상기 자유장(120)에 주입되는 콘크리트가 양생되면, 상기 패커(130')의 공기를 뺀 후, 상기 자유장(120)의 강선(121)을 결합공(122a)에 결합시키면서 지면지압판(122)을 천공홀(10) 주변에 밀착시킨 상태에서 상기 지면지압판(122)과 강선(121)을 별도의 고정물로 고정시키면 된다.When the concrete injected into the free field 120 is cured, after removing the air of the packer 130 ', the ground pressure plate 122 while coupling the steel wire 121 of the free field 120 to the coupling hole (122a) ) In the state in close contact with the perforation hole 10, the ground pressure plate 122 and the steel wire 121 may be fixed by a separate fixture.

상기의 과정으로 형성된 정착장(110)의 정착체 즉, 콘크리트 기둥에 의해 앵커(100)가 지반으로 딸려 나가는 것에 대하여 앵커두부인 지면지압판(122)을 통하 여 정착제에 인장력을 가해 지반강도를 증진시키면서 자유장(120)에 양생된 콘크리트 기둥이 지지할 수 있게 되는 것이다.The ground strength is applied by applying a tensile force to the fixing agent through the ground pressure plate 122, which is the anchor head, for anchoring the anchor 100 to the ground by the fixing body, that is, the concrete pillar formed by the above process. While increasing, the concrete pillars cured in the free field 120 will be able to support.

이상과 같이 본 발명은, 비록 한정된 실시예와 도면에 의해 설명되었으나, 본 명세서 및 청구범위에 사용된 용어나 단어는 통상적이거나 사전적인 의미로 한정되어 해석되어서는 아니되며, 본 발명의 기술적 사상에 부합하는 의미와 개념으로 해석되어야만 한다. 따라서, 본 명세서에 기재된 실시예와 도면에 도시된 구성은 본 발명의 일실시예에 불과할 뿐이고, 본 발명의 기술적 사상을 모두 대변하는 것은 아니므로, 본 발명의 청구범위를 벗어나지 않는 한도 내에서 다양한 균등물과 변형예들이 있을 수 있음을 이해하여야 한다.As described above, the present invention, although described by the limited embodiments and drawings, terms or words used in the present specification and claims are not limited to the ordinary or dictionary meanings and should not be interpreted, the technical spirit of the present invention It must be interpreted to mean meanings and concepts. Therefore, the configuration shown in the embodiments and drawings described herein are only one embodiment of the present invention, and do not represent all of the technical spirit of the present invention, various changes within the scope of the claims of the present invention It should be understood that there may be equivalents and variations.

도 1은 본 발명의 분리사시도1 is an exploded perspective view of the present invention

도 2는 본 발명의 결합상태도2 is a combined state of the present invention

도 3은 본 발명을 천공홀에 결합하는 상태도3 is a state diagram for coupling the present invention to the drilling hole

도 4 내지 도 6은 본 발명의 정착장에 콘크리트를 주입하여 충진하는 상태도4 to 6 is a state diagram of filling the concrete in the anchorage of the present invention

도 7 내지 도 10은 본 발명의 자유장에 콘크리트를 주입하여 충진하는 상태도7 to 10 is a state diagram in which the concrete is injected into the free field of the present invention

<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for the main parts of the drawings>

100: 앵커 110: 정착장100: anchor 110: anchorage

111: 케이지 112,112': 지압판111: cage 112,112 ': pressure plate

113: 캡 114: 패커가이드판113: Cap 114: Packer Guide

115: 고정타이 120: 자유장115: fixed tie 120: free field

121: 강선 122: 지면지압판121: steel wire 122: ground pressure plate

123: 스패서 124: 패커가이드판123: Spaser 124: Packer Guide Edition

130,130': 패커130,130 ': Packer

Claims (11)

사면보강용 앵커로서,As an anchor for slope reinforcement, 양단부에 나사산이 형성되는 다수의 봉체가 구비되고, 상기 봉체 양단부에 결합고정되는 지압판이 구비되며, 상기 지압판의 타단부에 위치하도록 강선에 결합되어 패커를 지지하는 패커가이드판을 포함하는 케이지가 구비된 정착장과;A plurality of rods having a thread formed on both ends is provided, the pressure plate is coupled to the both ends of the rod is provided, the cage is provided with a packer guide plate coupled to the steel wire to support the packer to be located on the other end of the pressure plate Anchorages; 상기 정착장과 강선으로 연결하는 자유장과;A free field connecting the anchorage with a steel wire; 상기 정착장과 자유장 및 상기 자유장과 지면을 분리하도록 천공홀에 밀착되는 각각의 패커와;Each packer in close contact with a perforation hole to separate the anchorage field and the free field and the free field and the ground; 상기 정착장의 강선은 호스로 감싸고, 상기 자유장의 강선은 호스로 감싸지 않은 상태에서 순차적으로 각각 타설되는 콘크리트에 의해 철근콘크리트 기둥이 형성되도록 구성되는 것을 특징으로 하는 소일 네일링 보강효과를 얻는 사면보강용 영구앵커.The steel wire of the anchorage is wrapped with a hose, the steel wire of the free field is reinforced for slope reinforcement to obtain the reinforcement of the soil nailing, characterized in that the reinforced concrete pillars are formed by concrete, each of which is poured in sequence in a state not wrapped with a hose Permanent anchor. 삭제delete 청구항 1에 있어서,The method according to claim 1, 상기 봉체의 일단부에 고정되는 지압판에 결합된 강선을 수용하여 보호하도록 밀착되는 캡을 더 포함하여 구비되는 것을 특징으로 하는 소일 네일링 보강효과를 얻는 사면보강용 영구앵커.Permanent reinforcement for slopes to obtain a soil nailing reinforcement effect, characterized in that it further comprises a cap in close contact to receive and protect the steel wire coupled to the pressure plate fixed to one end of the rod. 청구항 1에 있어서,The method according to claim 1, 상기 지압판은, 상기 봉체가 결합되도록 가장자리에 방사상으로 제1결합공이 관통되고, 상기 강선이 결합되도록 내부에 방사상으로 제2결합공이 관통되는 것을 특징으로 하는 소일 네일링 보강효과를 얻는 사면보강용 영구앵커.The acupressure plate, the first coupling hole radially penetrates the edge so that the rod body is coupled, the second coupling hole radially penetrates inside so that the steel wire is coupled Permanent reinforcement for slope reinforcement to obtain the nailing reinforcement effect anchor. 청구항 4에 있어서,The method according to claim 4, 상기 지압판에 방사상으로 관통된 제1결합공에 각각 결합된 다수의 봉체를 묶어 고정하는 고정타이를 더 포함하여 구비되는 것을 특징으로 하는 소일 네일링 보강효과를 얻는 사면보강용 영구앵커.Permanent anchor for slope reinforcement to obtain a nail nail reinforcing effect, characterized in that it further comprises a fixing tie for tying and fixing a plurality of rods respectively coupled to the first coupling hole radially penetrated to the pressure plate. 청구항 1에 있어서, 자유장은,The method according to claim 1, wherein the free field, 상기 정착장에 일단부가 고정되는 다수의 강선과;A plurality of steel wires having one end fixed to the anchorage; 상기 다수의 강선을 수용하여 결합되도록 결합공이 형성된 지면지압판과;A ground pressure plate having a coupling hole formed to receive and couple the plurality of steel wires; 상기 강선을 수용하여 유동하지 않도록 하는 적어도 하나 이상의 스패서와;At least one spacer for accommodating the steel wire so as not to flow; 상기 강선이 결합되어 패커를 지지하는 패커가이드판을 포함하여 구비되는 것을 특징으로 하는 소일 네일링 보강효과를 얻는 사면보강용 영구앵커.Permanent anchor for slope reinforcement to obtain the nailing reinforcement effect, characterized in that the steel wire is coupled to include a packer guide plate for supporting the packer. 청구항 6에 있어서, The method according to claim 6, 상기 스패서는 강선을 수용하여 결합되도록 외주면에 방사상으로 결합홈이 형성되는 것을 특징으로 하는 소일 네일링 보강효과를 얻는 사면보강용 영구앵커.The spacer is a permanent anchor for slope reinforcement to obtain a soil nailing reinforcing effect, characterized in that the coupling groove is formed radially on the outer circumferential surface so as to receive and combine the steel wire. 청구항 6 또는 청구항 7에 있어서,The method according to claim 6 or 7, 상기 스패서의 결합홈에 결합된 강선을 고정시키는 타이로드를 더 포함하여 구비되는 것을 특징으로 하는 소일 네일링 보강효과를 얻는 사면보강용 영구앵커.Permanent anchor for slope reinforcement to obtain a nail nail reinforcement effect, characterized in that it further comprises a tie rod for fixing the steel wire coupled to the coupling groove of the spacer. 청구항 1 또는 청구항 6에 있어서,The method according to claim 1 or 6, 상기 패커가이드판은, 상기 강선이 결합되도록 내부에 방사상으로 강선결합공이 관통되면서 일측면에 패커를 고정시키도록 돌출되는 후크를 포함하여 형성되는 것을 특징으로 하는 소일 네일링 보강효과를 얻는 사면보강용 영구앵커.The packer guide plate is a slope reinforcement for obtaining a nail nail reinforcement effect, characterized in that it comprises a hook protruding to fix the packer on one side while the steel wire coupling hole penetrates radially therein so that the steel wire is coupled. Permanent anchor. 청구항 9에 있어서,The method according to claim 9, 상기 패커가이드판에 콘크리트 주입호스와 배출호스가 결합되도록 관통되는 인렛홀과 아울렛홀을 더 포함하여 형성되는 것을 특징으로 하는 소일 네일링 보강효과를 얻는 사면보강용 영구앵커.Permanent reinforcing permanent anchor to obtain a nail nail reinforcement effect, characterized in that the packer guide plate further comprises an inlet hole and an outlet hole through which the concrete injection hose and the discharge hose is coupled. 사면보강용 영구앵커 시공방법으로서,As a permanent anchor construction method for slope reinforcement, 케이지로 결합한 강선의 일단부를 호스로 감싸 정착장을 형성하고, 상기 강선의 타단부에 자유장을 연결하는 앵커를 형성하는 단계와;Wrapping the one end of the steel wire joined by a cage to form a anchorage, and forming an anchor connecting the free field to the other end of the steel wire; 상기 앵커를 지면에 형성된 천공홀에 투입하는 단계와;Injecting the anchor into a drilling hole formed in the ground; 상기 정착장과 자유장을 분리하는 패커에 공기를 주입하여 천공홀 내면에 밀착시키는 단계와;Injecting air into the packer separating the anchorage field and the free field to closely contact the inner surface of the hole; 상기 패커에 의해 분리된 정착장에 콘크리트가 하부에서 상부로 채워지도록 주입하여 철근콘크리트 기둥의 정착체가 형성되도록 하는 단계와;Injecting concrete into the anchorage separated by the packer so that the concrete is filled from the lower portion to the upper portion so that the anchoring body of the reinforced concrete column is formed; 상기 정착장과 자유장을 분리하는 패커에 주입된 공기를 빼고, 상기 자유장과 지면을 분리하는 패커에 공기를 주입하여 천공홀 내면에 밀착시키는 단계와;Removing air injected into the packer separating the fixing field and the free field, injecting air into the packer separating the free field and the ground, and contacting the inner surface of the hole; 상기 패커에 의해 분리된 자유장에 콘크리트가 하부에서 상부로 채워지도록 주입하여 철근콘크리트 기둥이 양생되도록 하는 단계를 포함하는 것을 특징으로 하는 소일 네일링 보강효과를 얻는 사면보강용 영구앵커 시공방법.The permanent anchor construction method for slope reinforcement to obtain a soil nailing reinforcement effect comprising the step of injecting the concrete to fill the free field separated by the packer from the bottom to the top to cure the reinforced concrete column.
KR1020090081210A 2009-08-31 2009-08-31 Slope-reinforcement anchor for inducing soil nailing reinforcement effect and methode there of KR100992999B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020090081210A KR100992999B1 (en) 2009-08-31 2009-08-31 Slope-reinforcement anchor for inducing soil nailing reinforcement effect and methode there of

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020090081210A KR100992999B1 (en) 2009-08-31 2009-08-31 Slope-reinforcement anchor for inducing soil nailing reinforcement effect and methode there of

Publications (1)

Publication Number Publication Date
KR100992999B1 true KR100992999B1 (en) 2010-11-09

Family

ID=43409484

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020090081210A KR100992999B1 (en) 2009-08-31 2009-08-31 Slope-reinforcement anchor for inducing soil nailing reinforcement effect and methode there of

Country Status (1)

Country Link
KR (1) KR100992999B1 (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101187845B1 (en) * 2011-12-09 2012-10-04 김상운 Ground anchor structure provided pretension at the settled part and inner inserted staying tool
CN103741688A (en) * 2013-12-18 2014-04-23 中国矿业大学(北京) Split type total-length grouting and anchoring device
KR20160089972A (en) 2015-01-21 2016-07-29 부경대학교 산학협력단 Mounting structure of eco-friendly debris flow mitigation structure and its installation method
WO2016208990A1 (en) * 2015-06-25 2016-12-29 (주)현이앤씨 Anchor having fixing device at side of pressure plate to depress land slope and method of installing same
KR20170119873A (en) * 2016-04-20 2017-10-30 주식회사 장평건설 Earth anchor assembly for soft ground
KR101918930B1 (en) * 2016-11-18 2018-11-15 주식회사 정원지오텍 Front compression backward tension type removable U-turn anchor structure and Removable U-turn anchoring method using the same
KR101957263B1 (en) * 2018-07-10 2019-03-13 곽근우 Retaining wall assembly and construction method thereof
KR102120216B1 (en) * 2019-11-21 2020-06-08 산이건설 주식회사 Leading end reinforcement head for the soil nail
KR102120217B1 (en) * 2019-11-21 2020-06-08 산이건설 주식회사 Leading end reinforcement head for the soil nail
KR102237400B1 (en) 2020-10-06 2021-04-07 한태웅 nailing anchor and the method of constructing nailing anchor
CN114319343A (en) * 2022-01-06 2022-04-12 中冶成都勘察研究总院有限公司 Construction method of enlarged head anchor cable for expansive soil area
KR102430434B1 (en) 2021-09-03 2022-08-08 임월선 Ground reinforcement structure capable of passive and active reinforcement at the same time and its construction method
CN117758766A (en) * 2024-02-22 2024-03-26 大连金普新区市政管理有限公司 Reinforcing apparatus for construction foundation soil slope

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100270603B1 (en) * 1997-06-09 2000-11-01 정문선 Earth amchor
KR100576053B1 (en) * 2003-09-24 2006-05-08 한주이엔씨 주식회사 Soil nailing by extended packer grouting and construction method
KR100773920B1 (en) * 2007-05-03 2007-11-07 주식회사 도담이앤씨 Pre-tention soil nailing system and method for reinforcing inclined earth using the same

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100270603B1 (en) * 1997-06-09 2000-11-01 정문선 Earth amchor
KR100576053B1 (en) * 2003-09-24 2006-05-08 한주이엔씨 주식회사 Soil nailing by extended packer grouting and construction method
KR100773920B1 (en) * 2007-05-03 2007-11-07 주식회사 도담이앤씨 Pre-tention soil nailing system and method for reinforcing inclined earth using the same

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101187845B1 (en) * 2011-12-09 2012-10-04 김상운 Ground anchor structure provided pretension at the settled part and inner inserted staying tool
CN103741688A (en) * 2013-12-18 2014-04-23 中国矿业大学(北京) Split type total-length grouting and anchoring device
KR20160089972A (en) 2015-01-21 2016-07-29 부경대학교 산학협력단 Mounting structure of eco-friendly debris flow mitigation structure and its installation method
WO2016208990A1 (en) * 2015-06-25 2016-12-29 (주)현이앤씨 Anchor having fixing device at side of pressure plate to depress land slope and method of installing same
KR101757975B1 (en) * 2015-06-25 2017-07-13 서동현 Anchor having a fixing device at a side of pressure plate to depress the land slope and method of installing the same
CN108474192A (en) * 2015-06-25 2018-08-31 Hyun工程建设株式会社 There is the anchor and its installation method of fixing device for forcing down the pressing plate side on ground slope
KR20170119873A (en) * 2016-04-20 2017-10-30 주식회사 장평건설 Earth anchor assembly for soft ground
KR101918930B1 (en) * 2016-11-18 2018-11-15 주식회사 정원지오텍 Front compression backward tension type removable U-turn anchor structure and Removable U-turn anchoring method using the same
KR101957263B1 (en) * 2018-07-10 2019-03-13 곽근우 Retaining wall assembly and construction method thereof
KR102120216B1 (en) * 2019-11-21 2020-06-08 산이건설 주식회사 Leading end reinforcement head for the soil nail
KR102120217B1 (en) * 2019-11-21 2020-06-08 산이건설 주식회사 Leading end reinforcement head for the soil nail
KR102237400B1 (en) 2020-10-06 2021-04-07 한태웅 nailing anchor and the method of constructing nailing anchor
KR102430434B1 (en) 2021-09-03 2022-08-08 임월선 Ground reinforcement structure capable of passive and active reinforcement at the same time and its construction method
CN114319343A (en) * 2022-01-06 2022-04-12 中冶成都勘察研究总院有限公司 Construction method of enlarged head anchor cable for expansive soil area
CN117758766A (en) * 2024-02-22 2024-03-26 大连金普新区市政管理有限公司 Reinforcing apparatus for construction foundation soil slope
CN117758766B (en) * 2024-02-22 2024-04-19 大连金普新区市政管理有限公司 Reinforcing apparatus for construction foundation soil slope

Similar Documents

Publication Publication Date Title
KR100992999B1 (en) Slope-reinforcement anchor for inducing soil nailing reinforcement effect and methode there of
US10358920B2 (en) Tunnel construction method using pre-support and post-support and apparatus suitable for same
KR101070072B1 (en) A multistaged equipment of pipe grouting by double packer system and its construction
KR100631103B1 (en) Grout bag reinforcing method for underground caves
WO2014182074A1 (en) Method for reinforcing pillar part of adjacently constructed parallel tunnels with reinforcing rods and excavation method
KR101496923B1 (en) Extension pressure type anchor
KR100967897B1 (en) Construction methods using apparatus for reinforcing inclined plane used in retaining wall
KR101045727B1 (en) A multistaged equipment of pipe grouting by double packer system and its constructing method
KR100729667B1 (en) Composition anchor one thing practicable tension and compression
KR101056027B1 (en) Combined structure of edge prestressed concrete composite pile with tension member and expansion foundation
KR100908085B1 (en) Ground adhering soil nailing structure and ground reinforcement method using the same
KR101898338B1 (en) Anker assembly for anchoring weak foundation
KR100941669B1 (en) Re-injection device and construction method by pressure for underground anchor-pile
ES2715996T3 (en) Arrangement for high strength anchoring of a tensioning element that has a tensioning bar in a construction piece as well as a procedure for the production of such an anchor
KR100773920B1 (en) Pre-tention soil nailing system and method for reinforcing inclined earth using the same
KR101202845B1 (en) Hybrid ground reinforcing method by earth anchor and soil nail
KR100991248B1 (en) Foundation construction method of micro pile using pack and pile used in the same
JP2008223432A (en) Earthquake resisting construction method of structure, earthquake-resisting reinforcement construction method of structure, construction method of structure, earthquake resisting structure of structure, tubular member, anchor and anchor installation method
KR100862387B1 (en) Tensional kit for top-down constructing of acupressure lasting anchor and top-down constructing method of acupressure lasting anchor using this
KR101449560B1 (en) Sealing type land pressing plate and slope stabilization method using the same
KR100944199B1 (en) Prestressed concrete anchor body structure using together poly bar nail
KR101129357B1 (en) Fountain tensile soil nail structure and method for constructing thereby
KR101270832B1 (en) Concrete-Filled Tube Type Rotary File
KR101121119B1 (en) Foundation construction method of micro pile with pack
KR102221759B1 (en) Ground and slope reinforcement anchor grouting device

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20131104

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20160310

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20170303

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20180427

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20190321

Year of fee payment: 10