KR100988580B1 - Installation method of safety net hang in midair for wiring using established pylons - Google Patents

Installation method of safety net hang in midair for wiring using established pylons Download PDF

Info

Publication number
KR100988580B1
KR100988580B1 KR1020100041470A KR20100041470A KR100988580B1 KR 100988580 B1 KR100988580 B1 KR 100988580B1 KR 1020100041470 A KR1020100041470 A KR 1020100041470A KR 20100041470 A KR20100041470 A KR 20100041470A KR 100988580 B1 KR100988580 B1 KR 100988580B1
Authority
KR
South Korea
Prior art keywords
wire
transmission line
rope
pylon
net
Prior art date
Application number
KR1020100041470A
Other languages
Korean (ko)
Inventor
박승기
Original Assignee
(주)한누리
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)한누리 filed Critical (주)한누리
Priority to KR1020100041470A priority Critical patent/KR100988580B1/en
Application granted granted Critical
Publication of KR100988580B1 publication Critical patent/KR100988580B1/en

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G7/00Overhead installations of electric lines or cables
    • H02G7/18Devices affording mechanical protection in the event of breakage of a line or cable, e.g. net for catching broken lines
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/02Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables

Landscapes

  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

PURPOSE: A method for installing an air guard net for a stringing is provided to prevent a transmission line from being separated by surrounding the side and lower side of the transmission line with a guard network. CONSTITUTION: A basis wire is connected between pylons(1,1'). A pair of upper wires(20) are connected to the basis wire. A guard net(30) is connected between the pair of upper wires. The guard net includes a side fixing loop, a lower fixing loop, a space maintaining loop, and a movement preventing loop. The upper end of the side fixing loop is connected to the upper wire. The lower side fixing loop is connected to the lower side of the side fixing loop. The space maintaining loop regularly maintains the space between adjacent side fixing loops. The movement preventing loop is fixed to the ground.

Description

기존 철탑을 이용한 가선용 공중 보호망 설치공법{Installation method of safety net hang in midair for wiring using established pylons}Installation method of safety net hang in midair for wiring using established pylons}

본 발명은 철탑과 철탑 사이에 기초와이어와 상단와이어를 연선하고, 송전선의 하부에 위치하는 보호망을 상단와이어에 연결하여 안전사고가 우려되는 개소로 잡아당겨 철탑발받침 없이 송전선이 낙하되여도 안전하게 받칠 수 있는 기존 철탑을 이용한 가선용 공중 보호망 설치공법에 관한 것이다.The present invention stranded the base wire and the top wire between the pylon and the pylon, and connected to the top wire of the protection net located on the lower portion of the transmission line to the top wire to pull safely to the place where safety accidents are concerned, even if the transmission line falls safely without supporting the tower The present invention relates to a method of installing a public protective net for a ship using an existing steel tower.

우리나라 전력계통은 지속적인 경제성장에 따른 전력수요의 꾸준한 증가로 경제적인 전력수송, 전력공급의 신뢰도 향상 및 효율적인 국토 사용을 위하여 대전력 수송 송전선로로 성장하였다. 이에 따라 송전철탑의 대형화, 대용량 전선 사용 및 다도체화 등 송전선로가 대규모로 건설되고 있다.The power system of Korea has grown into a large power transmission line for economic power transportation, improved reliability of power supply and efficient land use due to the steady increase in power demand caused by continuous economic growth. As a result, transmission lines are being built on a large scale, such as large transmission towers, the use of large-capacity wires, and multi-conductors.

가공송전선로 가선작업 시 횡단해야 할 주요 장애 공작물은 송전선로, 배전선로, 전차선 등 전력선일 경우가 대부분을 차지하고 있다. 이러한 전력선 횡단을 위한 보호망 설치 시, 감전사고 예방 및 전력계통 사고를 미연에 방지하기 위해서는 선로휴전이 수반되어야 한다. 하지만 현실적으로 전력선은 극히 단시간 휴전, 2회선 중 1회선 휴전 또는 일체의 휴전작업이 곤란한 경우가 대부분이어서 위험에 노출된 상태로 보호망을 설치할 수밖에 없는 공사 여건으로 선로사고가 자주 발생하였다.The main obstacles to be traversed during overhead line work are power lines such as transmission lines, distribution lines and tram lines. When the protection network is installed for the power line crossing, line interruption must be accompanied to prevent electric shock accidents and power system accidents. However, in reality, power lines are often short-time truces, one-line truce of two lines or any truce work is difficult, so the accidents frequently occurred due to the construction conditions in which the protection network was in danger of being exposed to danger.

이러한 문제점을 해결하기 위하여 도 1에 도시된 바와 같이, 가공송전선(1)이 횡단하는 주요 장애 공작물의 양측에 철탑발받침대(3)를 설치하고, 철탑발받침대(3) 사이에 그물망(4)을 설치하여 가공송전선 낙하되어도 안전사고를 예방할 수 있도록 하였다.In order to solve this problem, as shown in Figure 1, the pylon footrest (3) is installed on both sides of the main obstacle workpiece traversed by the overhead transmission line (1), and the net (4) between the pylon footrest (3) It was installed to prevent safety accidents even if the overhead transmission line fell.

그러나, 종래의 철탑발받침대(3)를 사용하는 그물망(4)을 설치하는 경우 지형적인 영향으로 철탑발받침대(3)의 설치하기 어려운 부분이 발생하거나 또는 가공송전선 설치시 다수의 철탑발받침대를 설치해야 하는 문제가 있다. 또한, 철탑발받침대의 시공을 인허가 시간 및 소요비용이 별도로 소요되는 문제가 있다.However, in the case of installing the net 4 using the conventional pylon footrest (3) is difficult to install the portion of the pylon footrest (3) due to the topographical influence, or when installing the overhead transmission line, There is a problem that needs to be installed. In addition, there is a problem in that the time required for the licensing of the construction of the pylon footrest is required separately.

그리고, 가공송전선(1)이 낙하되는 경우 가공송전선의 무게로 인하여 그물망(4)에서 이탈되어 지하로 낙하되는 문제가 있다.In addition, when the overhead transmission line 1 falls, there is a problem of falling from the net 4 and falling underground due to the weight of the overhead transmission line.

본 발명은 철탑과 철탑 사이에 기초와이어와 상단와이어를 연선하고, 송전선의 하부에 위치하는 보호망을 상단와이어에 연결하여 안전사고가 우려되는 개소로 잡아당겨 철탑발받침 없이 송전선이 낙하되여도 안전하게 받칠 수 있는 기존 철탑을 이용한 가선용 공중 보호망 설치공법을 제공하는 데 있다.The present invention stranded the base wire and the top wire between the pylon and the pylon, and connected to the top wire of the protection net located on the lower portion of the transmission line to the top wire to pull safely to the place where safety accidents are concerned, even if the transmission line falls safely without supporting the tower It is to provide a method of installing a public protective net for wires using existing steel towers.

본 발명의 다른 해결과제는 보호망이 송전선의 측면과 하부를 감싸기 때문에 송전선이 낙하되더라도 보호망 내에 위치하기 때문에 송전선이 보호망 외부로 낙하되는 것을 방지할 수 있는 기존 철탑을 이용한 가선용 공중 보호망 설치공법을 제공하는 데 있다.Another problem of the present invention is to protect the side and the bottom of the power transmission line because the transmission line is dropped even if the transmission line is located in the protection net provides a public protection net installation method using a conventional steel tower that can prevent the transmission line from falling outside the protection net. There is.

본 발명의 기존 철탑을 이용한 가선용 공중 보호망 설치공법은 기초와이어(10)를 철탑과 철탑 사이의 최상부로 연결하는 기초와이어 연선단계와, 기초와이어(10)에 한쌍의 상단와이어(20)를 연결하고 기초와이어(10)를 잡아당겨 상단와이어가 송전선의 양측 상부에 위치하는 철탑의 최상부에 연결하는 상단와이어 연선단계와, 송전선의 측면과 하부를 감싸는 보호망(30)을 한쌍의 상단와이어(20)에 연결하는 보호망 장착단계와, 보호망(30)을 설치하면서 상단와이어(20)를 잡아당겨 안전사고가 우려되는 지점의 송전선 하부에 위치시키는 보호망(30)을 위치시키는 보호망 연선단계로 이루어지며,
상기 보호망(30)은 상단와이어(20)에 상단이 체결되고 하단이 송전선의 하부로 연장된 측면고정로프(31)와, 송전선의 하부에 위치하며 서로 마주하는 측면고정로프(31)의 하단에 체결되어 송전선의 낙하시 지면으로 떨어지는 것을 방지하는 하부고정로프(32)와, 송전선의 하부에 위치하며 전후방으로 서로 이웃하는 측면고정로프(31)의 하부에 체결되어 거리를 일정하게 유지시키는 간격유지로프(33)와, 최초와 최후 측면고정로프의 하단에서 연장되어 지면에 고정되어 흔들림을 최소화시키는 움직임방지로프(34)로 이루어진 것을 특징으로 한다.
Method of installing a wire protection net using the existing steel tower of the present invention is the basic wire stranding step of connecting the base wire 10 to the top between the pylon and the pylon, and connects a pair of top wire 20 to the base wire 10 And the top wire twisted pair step of connecting the top wire to the top of the pylon located on both sides of the transmission line by pulling the base wire 10, and a pair of top wire 20 to the protection net 30 surrounding the side and the bottom of the transmission line It consists of a protective net mounting step to connect to, and the protective net twisted wire step of placing the protective net 30 to be located at the bottom of the transmission line of the safety accident by pulling the top wire 20 while installing the protective net 30,
The protection net 30 is fastened to the upper end of the wire 20, the lower end of the side fixed rope 31 extending to the lower portion of the power transmission line, and the lower side of the side fixing rope 31 located on the lower side of the power transmission line facing each other The lower fixing rope 32 which is fastened to prevent falling to the ground when the transmission line falls, and is maintained at the bottom of the side fixing rope 31 which is located at the lower part of the transmission line and is adjacent to each other in the front and rear to maintain the distance to maintain a constant distance. Rope 33, and extending from the lower end of the first and last side fixing rope is fixed to the ground is characterized by consisting of a movement preventing rope 34 to minimize shaking.

바람직하게, 기초와이어 연선단계는 헬기연선방법을 이용한 것을 특징으로 한다.Preferably, the basic wire stranding step is characterized in that using the helicopter twisted pair method.

바람직하게, 기초와이어는 와이어 또는 나일론 로프인 것을 특징으로 한다.Preferably, the foundation wire is characterized in that the wire or nylon rope.

삭제delete

바람직하게, 측면고정로프(31)의 상단에는 작업 연선을 감싸는 링형상의 상부와이어크립(35)이 고정되고, 측면고정로프의 하단에는 링형상의 하부와이어크립(36)이 고정되며, 하부와이어크립(36)에는 하부고정로프(32)와 전후방 간격유지로프(33)가 각각 고정되는 것을 특징으로 한다.Preferably, the upper end of the side fixing rope 31 is a ring-shaped upper wire creep 35 is wrapped around the twisted line, the lower end of the side fixing rope ring-shaped wire creep 36 is fixed, the lower wire The creep 36 is characterized in that the lower fixing rope 32 and the front and rear interval maintaining rope 33 is fixed, respectively.

본 발명의 기존 철탑을 이용한 가선용 공중 보호망 설치공법에 의하면, 철탑과 철탑 사이에서 송전선의 낙하시 안전사고가 우려되는 지역에 기존의 철탑발받침을 설치할 필요없이 간단하게 보호망을 설치할 수 있는 장점이 있다.According to the construction method of the aerial protection net for the wire using the existing steel tower of the present invention, there is an advantage that can easily install the protection net without the need to install the existing pylon footrest in the area of safety accidents when the transmission line falls between the pylon and the tower have.

또한, 보호망이 송전선의 측면과 하부를 감싸기 때문에 송전선이 낙하되더라도 보호망 내에 위치하기 때문에 송전선이 보호망 외부로 낙하되는 것을 방지할 수 있다.In addition, since the protection net surrounds the side and the bottom of the transmission line, even if the transmission line falls, the transmission line can be prevented from falling outside the protection net because it is located in the protection net.

또한, 기존의 철탑발받침을 이용하여 보호망을 설치할 때 설치비용 및 설치기간을 절약할 수 있는 장점이 있다.In addition, there is an advantage that can save the installation cost and installation period when installing the protection net using the existing pylon footrest.

또한, 산을 통과하는 송전선의 설치시 산림회손을 방지할 수 있는 장점이 있다.In addition, there is an advantage that can prevent forest damage when installing the transmission line passing through the mountain.

또한, 기존의 철탑발받침을 설치하는 경우 안전사고를 방지하기 위하여 송전선을 휴전할 필요가 있으나, 본 발명은 무정전으로 보호망을 설치할 수 있다.In addition, in the case of installing the existing pylon footrest it is necessary to cease the transmission line in order to prevent safety accidents, the present invention can be installed in the protection net uninterrupted.

도 1은 일반적인 철탑 보호망의 설치사시도.
도 2는 본 발명에 따른 철탑 보호망 설치상태도.
도 3은 본 발명에 따른 기초와이어의 설치상태도.
도 4a 및 도 4b는 본 발명에 따른 상단와이어의 설치상태도.
도 5는 본 발명에 따른 보호망의 사시도.
도 6은 본 발명에 따른 보호망의 설치상태도.
도 7은 본 발명에 따른 철탑 보호망 설치과정의 플로챠트.
1 is a perspective view of the installation of a general pylon protection net.
Figure 2 is a state of installation of the tower protection net according to the invention.
Figure 3 is an installation state of the base wire according to the present invention.
Figure 4a and 4b is an installation state of the top wire according to the present invention.
5 is a perspective view of a protective net according to the present invention.
6 is an installation state of the protection net according to the invention.
7 is a flowchart of the installation process of the tower protection net according to the present invention.

이하, 첨부된 도면을 참조하여 본 발명에 따른 기존 철탑을 이용한 가선용 공중 보호망 설치공법에 대하여 자세히 설명한다.Hereinafter, with reference to the accompanying drawings will be described in detail with respect to the construction method of the public protective net for the wire using the existing steel tower according to the present invention.

본 발명의 기존 철탑을 이용한 가선용 공중 보호망 설치공법은 기초와이어(10)를 철탑(1)과 철탑(1') 사이의 최상부로 연결하는 기초와이어 연선단계와, 기초와이어(10)에 한쌍의 상단와이어(20)를 연결하고 기초와이어(10)를 잡아당겨 송전선의 상부에 위치하도록 철탑(1)과 철탑(1') 사이의 최상부에 연결하는 상단와이어 연선단계와, 한쌍의 상단와이어(20)에 송전선을 감싸도록 보호망(30)을 각각 연결하는 보호망 장착단계와, 보호망(30)을 설치하면서 상단와이어(20)를 잡아당겨 안전사고가 우려되는 지점의 송전선 하부에 위치시키는 보호망(30)을 위치시키는 보호망 연선단계로 이루어진다.The construction method of the aerial protection net for wire using the existing steel tower of the present invention is a twisted pair of foundation wires connecting the foundation wire 10 to the uppermost portion between the pylon 1 and the pylon 1 ', and a pair of foundation wires 10. A top wire twisted pair step of connecting the top wire 20 and connecting the top wire 20 to the uppermost portion between the pylon 1 and the pylon 1 'so as to be positioned on the top of the power transmission line, and a pair of top wires 20 Protection net mounting step of connecting the protection net 30 to each of the transmission line to surround the transmission line), while installing the protection net 30 to pull the upper wire 20 while the safety net is located in the lower transmission line of the safety concerns point 30 It consists of a twisted pair of guard nets to position the.

도 2 내지 도 6을 참조하여 본 발명의 기존 철탑을 이용한 가선용 공중 보호망 설치공법에 대하여 자세히 살펴본다.With reference to Figures 2 to 6 will be described in detail with respect to the installation method of the public protective net for the wire using the existing steel tower of the present invention.

도 3에 도시된 바와 같이, 기초와이어 연선단계는 철탑(1)과 철탑(1') 사이의 최상부에 위치하도록 기초와이어(10)를 연결한다. 기초와이어(10)는 철탑의 송전선이 좌우측에 각각 위치하는 경우 철탑 최상부의 좌,우측에 각각 연선된다. 기초와이어의 연선은 인력으로 연결하는 인력연선방법 또는 헬기로 연결하는 헬기연선방법 등을 사용할 수 있으며, 특히, 헬기연선방법을 사용하는 것이 바람직하다. 이때, 철탑(1)과 철탑(1')에는 기초와이어(10)를 쉽게 움직이기 위한 롤러가 설치되며, 기초와이어(10)는 견인장치에 연결되어 견인되면서 이동시키는 것이 바람직하다. 또한 기초와이어(10)는 12mm 와이어를 사용하며, 와이어의 무게를 절감하기 위하여 강도가 높은 나일론 로프로 대체하여 사용할 수 있다.As shown in FIG. 3, the twisted pair of foundation wires connects the foundation wires 10 to be positioned at the top between the pylon 1 and the pylon 1 ′. The base wire 10 is stranded on the left and right sides of the top of the tower when the transmission lines of the tower are respectively located on the left and right sides. The twisted pair of basic wires may be a twisted pair method of connecting by a manpower or a helicopter twisted pair method of connecting by a helicopter, and in particular, it is preferable to use a helicopter twisted pair method. In this case, a roller for easily moving the foundation wire 10 is installed on the pylon 1 and the pylon 1 ', and the foundation wire 10 is preferably connected to the towing apparatus and moved while being towed. In addition, the base wire 10 uses a 12mm wire, in order to reduce the weight of the wire can be used to replace the high strength nylon rope.

도 4a 및 4b에 도시된 바와 같이, 상단와이어 연선단계는 철탑(1)과 철탑(1') 사이의 최상부에 한쌍의 상단와이어(20)가 송전선의 상부에 위치하도록 연결한다. 상단와이어(20)는 와이어로프 2조로서 일측의 철탑(1)에 연결된 기초와이어(10)에 연결되면 타측의 철탑(1')으로 잡아당겨 연결된다. 이때, 상단와이어(20)가 설치되는 위치에 롤러를 설치하고, 와이어 견인장치를 이용하여 잡아당기는 것이 바람직하다. 또한, 상단와이어(20)는 18mm 와이어를 사용하며, 강도가 높은 나일론 로프를 사용하여 무게를 줄일 수 있다.As shown in Figures 4a and 4b, the upper wire stranding step is connected so that the pair of the top wire 20 is located at the top of the power transmission line at the top between the pylon (1) and the pylon (1 '). When the upper wire 20 is connected to the base wire 10 connected to the iron tower 1 on one side as two wire ropes, the upper wire 20 is pulled and connected to the other steel tower 1 '. At this time, it is preferable to install the roller at the position where the upper wire 20 is installed, and pull it using a wire traction device. In addition, the top wire 20 uses 18mm wire, it is possible to reduce the weight by using a high strength nylon rope.

도 5에 도시된 바와 같이, 보호망 장착단계는 송전선을 감싸하는 보호망(30)을 상단와이어(20)에 각각 연결한다. 이때, 보호망(30)의 하부는 송전선의 6~8m 하부에 위치하는 것이 바람직하다.As shown in FIG. 5, the protective net mounting step connects the protective net 30 surrounding the transmission line to the upper wire 20, respectively. At this time, the lower portion of the protection net 30 is preferably located in the lower 6 ~ 8m of the transmission line.

이러한 보호망(30)은 상단와이어(20)에 상단이 체결되고 하단이 송전선의 하부로 연장된 측면고정로프(31)와, 송전선의 하부에 위치하며 서로 마주하는 측면고정로프(31)의 하단에 체결되어 송전선의 낙하시 지면으로 떨어지는 것을 방지하는 하부고정로프(32)와, 송전선의 하부에 위치하며 전후방으로 서로 이웃하는 측면고정로프(31)의 하부에 체결되어 거리를 일정하게 유지시키는 간격유지로프(33)와, 최초와 최후 측면고정로프의 하단에서 연장되어 지면에 고정되어 흔들림을 최소화시키는 움직임방지로프(34)로 이루어진다. The protection net 30 is fastened to the upper end of the wire 20, the lower end of the side fixed rope 31 extending to the lower portion of the power transmission line, and the lower side of the side fixing rope 31 located on the lower side of the power transmission line facing each other The lower fixing rope 32 which is fastened to prevent falling to the ground when the transmission line falls, and is maintained at the bottom of the side fixing rope 31 which is located at the lower part of the transmission line and is adjacent to each other in the front and rear to maintain the distance to maintain a constant distance. Rope 33, and extending from the lower end of the first and last side fixing rope is fixed to the ground consisting of a movement preventing rope 34 to minimize shaking.

이때, 측면고정로프(31)의 상단은 고리로 형성되어 작업 연선을 감싸하는 링형상의 상부와이어크립(35)에 고정된다. 또한, 측면고정로프(31)의 하단은 고리로 형성되며 링형상의 하부와이어크립(36)이 연결되고, 하부와이어크립(36)에 하부고정로프(32)와 전후방 간격유지로프(33)가 각각 고정된다.At this time, the upper end of the side fixing rope 31 is formed in a ring is fixed to the ring-shaped upper wire creep 35 surrounding the working strand. In addition, the lower end of the side fixing rope 31 is formed of a ring is connected to the ring-shaped lower wire creep 36, the lower wire crepe 36 to the lower fixing rope 32 and the front and rear space maintaining rope 33 Each is fixed.

도 6에 도시된 바와 같이, 보호망 연선단계는 보호망(30)이 설치된 상단와이어(20)를 잡아당겨 안전사고가 우려되는 지점의 송전선 하부에 보호망(30)을 위치시킨다. 이때, 보호망(30)은 상단와이어(20)가 일측 철탑(1)에서 타측 철탑(1')으로 이동되는 동안에 순차적으로 설치는 것이 바람직하다.As shown in FIG. 6, the twisted-pair wire protection step pulls the upper wire 20 in which the protection net 30 is installed, and places the protection net 30 under the transmission line at a point where a safety accident is concerned. In this case, the protection net 30 is preferably installed sequentially while the upper wire 20 is moved from one side of the pylon (1) to the other side of the tower (1 ').

도 7을 참조하여 이와 같은 구성을 갖는 본 발명의 기존 철탑을 이용한 가선용 공중 보호망 설치 공정을 설명하면 다음과 같다.Referring to Figure 7 describes the installation process of the public protection net for the household using the existing steel tower of the present invention having such a configuration as follows.

송전철탑의 최상부 중에서 기초와이어(10)가 놓이는 위치와 상단와이어(20)가 놓여지는 위치에 각각 롤러를 설치한다.Rollers are installed at positions where the base wire 10 is placed and the top wires 20 are placed among the tops of the transmission tower.

먼저, 헬기연선방법 등을 이용하여 기초와이어(10)를 철탑(1)과 철탑(1') 사이의 최상부에 설치된 롤러에 올려놓고 견인장치 등으로 잡아당겨 설치한다(단계 S1). 통상 철탑에는 송전선이 좌우측에 설치되기 때문에 좌측 및 우측에 설치되는 기초와이어를 순차적으로 연선한다.First, the base wire 10 is placed on a roller installed at the uppermost portion between the pylon 1 and the pylon 1 'by using a helicopter twisted line method or the like, and is pulled and installed by a traction device or the like (step S1). In general, since the transmission line is installed on the left and right sides of the pylon, the foundation wires installed on the left and right sides are sequentially stranded.

그 후, 일측 철탑(1)의 기초와이어(10) 끝단에 와이어로프 2조로 이루어진 상단와이어(20)를 롤러에 올려놓은 상태로 연결하고, 타단의 기초와이어(10)를 견인장치 등으로 잡아당겨 타측 철탑(1')으로 이동시킨다(단계 S2). 타측 철탑(1')으로 이동된 상단와이어(20)는 롤러에 올려놓아 상단와이어(20)가 송전선의 상부에 위치하도록 한다.Thereafter, the top wire 20 made of two sets of wire ropes is connected to the end of the base wire 10 of one side of the pylon 1 on a roller, and the base wire 10 of the other end is pulled by a traction device or the like. It moves to the other steel tower 1 '(step S2). The upper wire 20 moved to the other steel tower 1 'is placed on a roller so that the upper wire 20 is positioned above the power transmission line.

철탑(1)과 철탑(1') 사이에 상단와이어(20)가 설치되면, 송전선의 측면과 하부를 감싸는 보호망(30)을 일측 철탑의 상단와이어(20)에 연결하면서 타측의 상단와이어(20)를 잡아당겨 안전사고가 우려되는 지점의 송전선 하부로 이동시킨다(단계 S3, S4). 이와 같은 보호망(30)은 송전선로의 측면에 위치하는 측면고정로프(31)와, 송전선의 하부에 위치하는 하부고정로프(32) 및 측면고정로프(31)의 간격을 일정하게 유지시키는 간격유지로프(33)가 하부와이어크립(36)으로 연결되어 제작되며, 완성된 보호망(30)은 내측으로 송전선이 위치하도록 감싸게 된다. 이에 따라 송전선의 설치시 송전선이 지면으로 낙하되더라도 낙하되는 송전선은 보호망(30) 내부로 낙하되어 안전사고를 예방할 수 있다.When the upper wire 20 is installed between the pylon 1 and the pylon 1 ', the upper wire 20 of the other side is connected to the upper wire 20 of one of the pylons to connect the protection net 30 surrounding the side and the bottom of the transmission line ) And move it to the lower part of the transmission line at the point where the safety accident is concerned (steps S3 and S4). The protection net 30 maintains the gap between the side fixing rope 31 positioned on the side of the transmission line, the lower fixing rope 32 and the side fixing rope 31 positioned below the power transmission line. The rope 33 is manufactured by being connected to the lower wire creep 36, and the completed protection net 30 is wrapped to position the transmission line inward. Accordingly, even when the transmission line falls to the ground when the transmission line is installed, the falling transmission line may fall into the protection net 30 to prevent a safety accident.

한편, 철탑(1)과 철탑(1') 사이에 송전선의 설치가 완료되면(단계 S5), 상단와이어(20)를 일측의 철탑(1)으로 잡아당기면서 보호망(30)을 상단와이어(20)에서 분리하여 회수한다(단계 S6). 보호망(30)은 와이어크립(35,36)으로 연결되기 때문에 쉽게 분해할 수 있다.On the other hand, when the installation of the transmission line is completed between the pylon (1) and the pylon (1 ') (step S5), while pulling the upper wire 20 to the one side of the pylon (1), the wire 30 to the upper wire (20) ) To recover it (step S6). The guard net 30 can be easily disassembled because it is connected to the wire clips 35 and 36.

보호망(30)의 제거가 완료되면 일측 철탑(1)으로 상단와이어(20)를 잡아당겨 회수하고(단계 S7), 다시 상단와이어(20)에 연결된 기초와이어(10)를 잡아당겨 회수한다(단계 S8).When the removal of the protection net 30 is completed, the upper wire 20 is pulled and recovered by the one side steel tower 1 (step S7), and the basic wire 10 connected to the upper wire 20 is pulled and recovered (step S8).

1, 1' : 철탑 10 : 기초와이어
20 : 상단와이어 30 : 보호망
31 : 측면고정로프 32 : 하부고정로프
33 : 간격유지로프 35 : 상부와이어크립
36 : 하부와이어크립
1, 1 ': steel tower 10: foundation wire
20: upper wire 30: protection net
31: side fixing rope 32: lower fixing rope
33: spacing rope 35: upper wire creep
36: lower wire creep

Claims (5)

기초와이어(10)를 철탑(1)과 철탑(1') 사이의 최상부로 연결하는 기초와이어 연선단계와,
기초와이어(10)에 한쌍의 상단와이어(20)를 연결하고 기초와이어(10)를 잡아당겨 상단와이어가 송전선의 양측 상부에 위치하는 철탑(1)과 철탑(1') 사이의 최상부에 연결하는 상단와이어 연선단계와,
송전선의 측면과 하부를 감싸는 보호망(30)을 한쌍의 상단와이어(20)에 연결하는 보호망 장착단계와,
보호망(30)을 설치하면서 상단와이어(20)를 잡아당겨 안전사고가 우려되는 지점의 송전선 하부에 위치시키는 보호망(30)을 위치시키는 보호망 연선단계로 이루어지며,
상기 보호망(30)은 상단와이어(20)에 상단이 체결되고 하단이 송전선의 하부로 연장된 측면고정로프(31)와,
송전선의 하부에 위치하며 서로 마주하는 측면고정로프(31)의 하단에 체결되어 송전선의 낙하시 지면으로 떨어지는 것을 방지하는 하부고정로프(32)와,
송전선의 하부에 위치하며 전후방으로 서로 이웃하는 측면고정로프(31)의 하부에 체결되어 거리를 일정하게 유지시키는 간격유지로프(33)와,
최초와 최후 측면고정로프의 하단에서 연장되어 지면에 고정되어 흔들림을 최소화시키는 움직임방지로프(34)로 이루어진 것을 특징으로 하는 기존 철탑을 이용한 가선용 공중 보호망 설치공법.
A foundation wire stranding step of connecting the foundation wire 10 to the top between the pylon 1 and the pylon 1 ',
A pair of top wires 20 are connected to the base wire 10 and the base wires 10 are pulled to connect the top wires to the uppermost portion between the pylon 1 and the pylon 1 'located at both upper portions of the transmission line. The upper wire stranded phase,
A protective net mounting step of connecting the protective net 30 surrounding the side and the bottom of the transmission line to a pair of upper wires 20;
While installing the guard net 30 is made of a guard net twisted wire step to position the guard net 30 to be located on the lower transmission line of the point where the safety accident is concerned by pulling the upper wire 20,
The protection net 30 is the upper side is fixed to the top wire 20 and the lower side fixed rope 31 extending to the lower portion of the transmission line,
A lower fixing rope 32 which is located at a lower portion of the transmission line and is fastened to the lower end of the side fixing ropes 31 facing each other to prevent falling to the ground when the transmission line falls;
A spacing maintaining rope 33 positioned at a lower portion of the power transmission line and fastened to a lower portion of the side fixing ropes 31 adjacent to each other in the front and rear, and maintaining a constant distance;
Method for installing a wire protection net using a conventional steel tower, characterized in that consisting of a movement preventing rope (34) which is fixed to the ground extending from the bottom of the first and last side fixed rope to minimize shaking.
청구항 1에 있어서, 기초와이어 연선단계는 헬기연선방법을 이용한 것을 특징으로 하는 기존 철탑을 이용한 가선용 공중 보호망 설치공법.The method of claim 1, wherein the wire stranding step is based on a helicopter twisted wire method. 청구항 1에 있어서, 기초와이어는 와이어 또는 나일론 로프인 것을 특징으로 하는 기존 철탑을 이용한 가선용 공중 보호망 설치공법.The method of claim 1, wherein the basic wire is a wire or nylon rope, the aerial protection net installation method using a conventional steel tower. 삭제delete 청구항 1에 있어서, 측면고정로프(31)의 상단에는 작업 연선을 감싸는 링형상의 상부와이어크립(35)이 고정되고, 측면고정로프의 하단에는 링형상의 하부와이어크립(36)이 연결되며, 하부와이어크립(36)에는 하부고정로프(32)와 전후방 간격유지로프(33)가 각각 고정되는 것을 특징으로 하는 기존 철탑을 이용한 가선용 공중 보호망 설치공법.The method of claim 1, wherein the upper end of the side fixing rope 31 is a ring-shaped upper wire creep 35 is wrapped around the working strand, the lower end of the side fixing rope ring-shaped wire creep 36 is connected, The lower wire creep 36, the lower fixing rope 32 and the front and rear spacing maintaining rope 33 is fixed to each other, the method of installing a wire protection net for a wire using an existing steel tower.
KR1020100041470A 2010-05-03 2010-05-03 Installation method of safety net hang in midair for wiring using established pylons KR100988580B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020100041470A KR100988580B1 (en) 2010-05-03 2010-05-03 Installation method of safety net hang in midair for wiring using established pylons

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020100041470A KR100988580B1 (en) 2010-05-03 2010-05-03 Installation method of safety net hang in midair for wiring using established pylons

Publications (1)

Publication Number Publication Date
KR100988580B1 true KR100988580B1 (en) 2010-10-18

Family

ID=43135593

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020100041470A KR100988580B1 (en) 2010-05-03 2010-05-03 Installation method of safety net hang in midair for wiring using established pylons

Country Status (1)

Country Link
KR (1) KR100988580B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101181453B1 (en) 2011-07-06 2012-09-11 한국전력공사 Apparatus for protection net and method for installing and demounting protection net using the same
EP3125381A1 (en) * 2015-07-28 2017-02-01 Amec Foster Wheeler Group Limited Transmission line replacement system & method
CN114221251A (en) * 2021-10-29 2022-03-22 中国电建集团贵州电力设计研究院有限公司 Lapping method for iron tower wiring above live wire

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010070603A (en) * 2001-05-26 2001-07-27 신은상 Installation Method of Electric Wire in Transmission Tower
JP2004140917A (en) * 2002-10-17 2004-05-13 Toko Electrical Construction Co Ltd Stringing protector and stringing method
JP2007037314A (en) 2005-07-28 2007-02-08 Kurihara Kogyo Co Ltd Electric wire relaying method and protective net used for it
JP2009247126A (en) 2008-03-31 2009-10-22 Kansai Electric Power Co Inc:The Personnel safety net

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010070603A (en) * 2001-05-26 2001-07-27 신은상 Installation Method of Electric Wire in Transmission Tower
JP2004140917A (en) * 2002-10-17 2004-05-13 Toko Electrical Construction Co Ltd Stringing protector and stringing method
JP2007037314A (en) 2005-07-28 2007-02-08 Kurihara Kogyo Co Ltd Electric wire relaying method and protective net used for it
JP2009247126A (en) 2008-03-31 2009-10-22 Kansai Electric Power Co Inc:The Personnel safety net

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101181453B1 (en) 2011-07-06 2012-09-11 한국전력공사 Apparatus for protection net and method for installing and demounting protection net using the same
EP3125381A1 (en) * 2015-07-28 2017-02-01 Amec Foster Wheeler Group Limited Transmission line replacement system & method
CN114221251A (en) * 2021-10-29 2022-03-22 中国电建集团贵州电力设计研究院有限公司 Lapping method for iron tower wiring above live wire
CN114221251B (en) * 2021-10-29 2024-01-23 中国电建集团贵州电力设计研究院有限公司 Overlap joint method for iron tower wiring above electrified connection lead

Similar Documents

Publication Publication Date Title
CN108736377B (en) Live crossing system for paying-off construction crossing power line and application method thereof
KR100988580B1 (en) Installation method of safety net hang in midair for wiring using established pylons
CN106838465B (en) The existing pipe excavation of underground pipe gallery protects construction method
KR20080044012A (en) Barehand method to live line for 765kv double circuit transmission lines using a helicopter
CN202500374U (en) Multifunctional fixing support applied for telegraph pole
CN103001146B (en) Usage method of steel pipe pole operation platform
KR20210048308A (en) A preventing falling apparatus for power pole
CN105586832A (en) Suspension type catwalk surface net mounting system
CN106229890B (en) Construction protection structure for crossing obstacle overhead line
CN206287856U (en) A kind of new OCS Messenger Wire suspended structure
CN102916371A (en) Overhead ground wire repair method and device
CN202611568U (en) Insulation trestle ladder
CN206471750U (en) A kind of across obstacle Poling Construction protection structure
CN109256721A (en) A kind of helicopter live-line maintenance operation hanging basket
CN205442567U (en) Steel -pipe pole operation platform
CN203722136U (en) Insulation rope net apparatus for railway crossing tension stringing construction
JP2005333789A (en) Construction method of hanging sheave type line shifting by forming net
CN102611057A (en) Crossing mesh
CN107217912B (en) A kind of superelevation physical isolation construction method for neighbouring high-speed rail Business Line construction
KR20160114885A (en) Guide ring rope for transmission lines
KR101767344B1 (en) Uninterruptible bypass cable for towing vehicle
EP3125381B1 (en) Transmission line replacement system & method
KR200446267Y1 (en) Connection apparatus of light weight buffer metal for high-tension wire
GB2558231A (en) Method and apparatus for deploying a supporting net when replacing overhead conductors
CN203787851U (en) Maintenance device used for power supply and power transmission lines

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130930

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20141013

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20151012

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20161111

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20170810

Year of fee payment: 8