KR100913945B1 - Retaining of shutter type for construction and engineering work - Google Patents

Retaining of shutter type for construction and engineering work Download PDF

Info

Publication number
KR100913945B1
KR100913945B1 KR1020090034878A KR20090034878A KR100913945B1 KR 100913945 B1 KR100913945 B1 KR 100913945B1 KR 1020090034878 A KR1020090034878 A KR 1020090034878A KR 20090034878 A KR20090034878 A KR 20090034878A KR 100913945 B1 KR100913945 B1 KR 100913945B1
Authority
KR
South Korea
Prior art keywords
panel
construction
hinge
sides
shutter
Prior art date
Application number
KR1020090034878A
Other languages
Korean (ko)
Inventor
장재균
Original Assignee
주식회사 지에이엔지니어링건축사사무소
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 지에이엔지니어링건축사사무소 filed Critical 주식회사 지에이엔지니어링건축사사무소
Priority to KR1020090034878A priority Critical patent/KR100913945B1/en
Application granted granted Critical
Publication of KR100913945B1 publication Critical patent/KR100913945B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/15Geometrical or physical properties including at least a hinge
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2220/00Temporary installations or constructions
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Abstract

A retaining shutter for construction and engineering work is provided to minimize soil and water entering the work space. A retaining shutter for construction and engineering work comprises an upright panel(10), a horizontal support panel(20), an up-down connection panel(30), and a finishing element(40). The upright panel has guide grooves(12) with open top on the front sides, equally-spaced bolt holes on the top, and a hinge connection part(16) on the bottom. The horizontal support panel has front hinge joint protrusions(22) which are hinged to the hinge connection part and equipped with anti-skid shock-absorbing pads(26), and rear hinge joint protrusions(24). The up-down connection panel has a hinge connection part(32) is hinged on the rear hinge joint protrusions, and up-down insert protrusions on the rear sides. The finishing element has vertical through holes to be bolted on the top of the upright panel, and is equipped with anti-skid shock-absorbing pads(44) on both ends.

Description

건축 및 토목공사용 셔터형 흙막이{retaining of shutter type for construction and engineering work} Retaining of shutter type for construction and engineering work}

본 발명은 건축 및 토목공사용 셔터형 흙막이에 관한 것으로서, 보다 상세하게는 흙막이의 설치가 계단 형태로 이루어질 수 있게 수개의 흙막이를 상호간에 다단 절첩이 가능하되, 슬라이딩을 이룰 수 있는 셔터 형태로 연결 구성하여 주어, 실사용시 설치 및 해체를 신속 용이하게 이룰 수 있고, 토압 하중을 분산 지지하여 설치 안정성을 향상시켜 줄 수 있으며, 보관상의 편의성을 향상시켜 줄 수 있도록 한 건축 및 토목공사용 셔터형 흙막이에 관한 것이다. The present invention relates to a shutter-type mudguard for construction and civil engineering, and more specifically, it is possible to fold several mudles to each other so that installation of the mudguard can be made in a staircase form, but in a shutter-type shutter structure that can achieve sliding. It is possible to quickly and easily install and dismantle in actual use, to improve the installation stability by supporting distributed earth pressure load, and to provide a shutter-type mudguard for construction and civil engineering to improve the convenience of storage. will be.

흙막이 구조물이란, 건설공사 현장에서 비탈지거나 굴토해낸 자리에 설치되어, 낙석이나 파편의 비산을 방지하며, 기초공사 등을 위한 굴토구간의 터파기시 흙벽이 무너져 내리는 것을 방지하기 위하여 임시적으로 설치되는 구조물을 일컫는다.An earthquake structure is a structure that is installed at a site that is sloped or excavated at a construction site, to prevent rockfall or debris from scattering, and to be temporarily installed in order to prevent the earth wall from falling down during the excavation of the excavation section for foundation work. It is called.

일반적으로 건설현장의 지하공사에 있어서는 흙을 파낸 뒤 주위의 토사가 붕괴되는 것을 방지하기 위하여 임시적으로 흙막이 공사가 선행되는데, 상기 간이 흙막이 구조물이란 이와 같은 흙막이 공사를 위해 설치되는 구조물로서, 간이 흙막이 벽체, 토류판 또는 토류벽 등이라 불리우기도 한다.In general, the underground construction of the construction site is temporarily preceded by the earthquake construction to prevent the collapse of the soil around the earth after digging, the simple earthquake structure is a structure installed for such a earthquake construction, a simple earthen wall Also called earth plate or earth wall.

도 5는 종래의 간이 흙막이 구조물의 구성을 개략적으로 도시한 구성도이다.5 is a configuration diagram schematically showing the configuration of a conventional simple earthenware structure.

도시된 바와 같이, 종래의 간이 흙막이 구조물은 상호 홈부가 마주 보도록 수직하게 설치된 복수개의 H 빔(1)과, 상기 홈부에 삽입지지되어 후방의 흙더미 등이 전방을 향하여 무너지는 것을 방지하기 위한 흙막이 수단(100)를 포함하여 구성된다.As shown in the drawing, a conventional simple earthenware structure includes a plurality of H beams (1) vertically installed to face each other, and earthenment means for preventing insertion of the earthen piles of the rear side to be supported by being inserted into the grooves. It comprises 100.

종래에는 흙막이 수단으로서 소정 규격의 목재판을 적층하여 벽체를 형성하고, 그 적층된 목재판을 고정하기 위하여 끼움목(쐐기)을 설치한 구조를 채용하는 것이 일반적이었다.Conventionally, it was common to employ a structure in which a wooden board of a predetermined standard is laminated to form a wall, and fittings (wedges) are provided in order to fix the laminated wooden board.

이와 같은 간이 흙막이 구조물은 어디까지나 공사중 토사 붕괴 등으로부터 현장을 보호한다는 임시적인 용도로서 것으로서, 지하공사가 완료된 후에는 그 흙막이 구조물에 의해 형성된 내부 공간이 지하 구조물 등에 의해 충진되게 되므로, 더이상 쓸모가 없게 되는 것이다.Such a simple earthenware structure is a temporary use to protect the site from earth and earth collapse during construction, and after the underground construction is completed, the internal space formed by the earthenware structure is filled by the underground structure, which is no longer useful. Will be.

그런데, 종래에 있어서는, 지하공사의 완료 후 간이 흙막이 구조물을 철거할 수 있는 별도의 수단을 강구하고 있지 아니하였는 바, 지하공사의 완료와 함께 간이 흙막이 구조물도 지하에 매몰되어 그 구조물에 사용된 자재의 재활용이 불가능하다는 문제점을 안고 있었다.However, in the related art, since a separate means for dismantling the simple earthenware structure was not devised after the completion of the underground work, the simple earthenware structure was also buried underground and used for the structure. The problem was that recycling was impossible.

이에 최근에는 이러한 문제점을 해소하기 위해 도 6에 도시된 바와 같이 적층되어 배치되며, 끝단에 끝단 결합공(135)이 형성된 복수의 흙막이 수단(100a, 100b, 100c); 및 상기 흙막이 수단(100a)의 일단을 상측에 위치한 타 흙막이 수 단(100b)의 일단에 연결하고, 타단을 하측에 위치한 타 흙막이 수단(100c)의 일단에 연결하여, 전체적이 흙막이 수단(100a, 100b, 100c)이 지그재그 구조로 결합되도록 상기 끝단 결합공(135)과 결합하는 복수의 끝단연결수단(200); 을 포함하고, 상기 끝단 결합공(135)은 장공으로 형성되고, 상기 끝단연결수단(200)은, 상하에 위치한 흙막이 수단 사이에 배치된 결합부재(231); 및 상기 결합부재(231)에 결합되며, 상기 끝단 결합공에 이동할 수 있도록 삽입되는 힌지축(233a, 233b);을 포함하는 것을 특징으로 하는 흙막이 조립체(출원번호 10-2005-0038885호)가 제안된 바 있다.In order to solve such a problem, a plurality of earth blocking means 100a, 100b, and 100c are stacked and arranged as shown in FIG. 6 and have end coupling holes 135 formed at the ends thereof. And one end of the earth blocking means 100a connected to one end of the other earth blocking means 100b located on the upper side, and the other end connected to one end of the other earth blocking means 100c located on the lower side, so that the entire earth blocking means 100a, A plurality of end connection means 200 coupled to the end coupling holes 135 such that 100b and 100c are coupled in a zigzag structure; It includes, the end coupling hole 135 is formed in a long hole, the end connection means 200, the coupling member 231 disposed between the earth blocking means located above and below; And a hinge shaft (233a, 233b) coupled to the coupling member 231 and inserted into the end coupling hole so as to be movable in the end coupling hole (Application No. 10-2005-0038885). It has been.

이는 건설공사의 간이 흙막이 공사에 사용되는 자재를 공사 완료후 철거하여 재활용 가능하고, 끝단 결합공 혹은 연결수단 결합공이 장공으로 형성됨으로써, 해체 작업시, 개별 흙막이 수단이 하측에 위치한 흙막이 수단에 대해서 이격된 상태에서 회동할 수 있으므로, 해체 작업이 용이한 장점이 있는 반면, 구조적인 여러 문제점으로 인해 실사용시 다음과 같은 여러 문제점이 있었다.This can be recycled by dismantling the materials used for the construction of the simple earthquake in the construction work, and the end joining hole or the connecting means joining hole is formed as a long hole, so that during the dismantling work, the individual blocking means is separated from the earth blocking means located below. Since it can be rotated in a closed state, the dismantling work is easy, while there are several problems in practical use due to various structural problems.

이를 순서에 의거하여 나열 설명하면 다음과 같다.If you list them in order, they are as follows.

첫째, 흙막이 수단의 양측에 길이 조정이 가능하게 연결 설치된 연결부재가 적층 연결시 소정의 이격 거리를 형성하게 되는 구조적인 문제로 인해 긴밀한 흙막이 기능을 제공하지 못하여 다량의 토사와 침출수를 공사를 위한 작업 공간으로 전달시키는 문제점이 있었다.First, due to the structural problem that the connecting members installed to be adjustable in length on both sides of the retaining means to form a predetermined separation distance when the laminated connection is connected, the work for the construction of a large amount of soil and leachate can not be provided due to the tight retaining function There was a problem to deliver to space.

둘째, 일반적인 흙막이와 별다름이 없이 수직의 설치 상태를 이루어 토압을 지지함으로 이를 지지하기 위한 "H"빔의 타설을 기존 흙막이 시설과 별반 차이 없 이 깊게 타설해야 하는 구조적인 문제점이 있었다.Second, there was a structural problem in that the installation of the "H" beam to support the earth pressure by supporting the earth pressure by forming the vertical installation state without any difference from the general earthenment block without deeply different from the existing earthenment facility.

셋째, 재사용을 위한 일련의 준비 작업이 매우 불편한 문제점이 있었다.Third, a series of preparation work for reuse was very inconvenient.

즉, 재사용을 위해선 힌지 기능을 제공하기 위한 끝단연결수단과 연결부재 전후면에 형성된 구멍 내에 낀 토사를 모두 재거하여야만 재사용을 위한 작동이 가능한 구조적 문제점이 있었기 때문이다. That is, for reuse, there is a structural problem that can be operated for reuse only by removing all the soil stuck in the hole formed in the front and rear end connecting means and the connecting member for providing a hinge function.

넷째, 이동 보관이 용이하지 않은 문제점이 있었다.Fourth, there was a problem that the mobile storage is not easy.

즉, 흙막이 수단이 부피가 작고 가벼운 물품으로의 제작이 불가한 사각관 형태를 이루고 있기 때문이다. That is, because the earth block means forms a square tube form that is impossible to produce a small and light article.

본 발명은 상기와 같은 문제점을 해결하기 위한 것으로서, The present invention is to solve the above problems,

흙막이 판넬의 설치가 계단 형태로 이루어질 수 있게 수개의 흙막이 판넬을 상호간에 다단 절첩이 가능하되, 슬라이딩을 이룰 수 있는 셔터 형태로 연결 구성하여 주어, 실사용시 설치 및 해체를 신속 용이하게 이룰 수 있고, 토압 하중을 분산 지지하여 설치 안정성을 향상시켜 줄 수 있으며, 보관상의 편의성을 향상시켜 줄 수 있도록 한 건축 및 토목공사용 셔터형 흙막이를 제공함에 그 목적이 있다.Multiple panels can be folded in multiple stages so that the installation of the panel can be done in the form of stairs, and it is possible to make the installation and disassembly quickly and easily by connecting and configuring the shutter in the form of sliding. The purpose of the present invention is to provide a shutter-type mudguard for building and civil engineering that can improve the installation stability by supporting the earth pressure load in a distributed manner.

이와 같은 목적을 달성하기 위하여, 본 발명은 In order to achieve the above object, the present invention

양측 전면에는 상부가 개구된 가이드홈이 형성되어 있고, 상부에는 수개의 볼트공이 등간격으로 형성되어 있으며, 하부에는 힌지연결구가 형성되어 있는 기립 판넬과;A guide panel having an upper opening at both front surfaces thereof, a plurality of bolt holes formed at equal intervals at an upper portion thereof, and a rising panel having a hinge connector formed at a lower portion thereof;

전방 양측에는 상기 기립판넬의 하부에 형성되어 있는 힌지연결구와 회동가능하게 힌지 연결되어 있되, 미끄럼방지완충패드가 설치 고정되어 있는 전방힌지연결돌기가 형성되어 있고, 후방 양측에는 후방힌지연결돌기가 형성되어 있는 수평버팀판넬와;The front both sides are hinged rotatably with the hinge connector formed on the bottom of the standing panel, the front hinge connecting projection is fixed to the non-slip buffer pad is installed, the rear hinge connecting projection is formed on both sides of the rear A horizontal brace panel;

상부에는 상기 수평버팀판넬의 후방 힌지연결돌기와 회동가능하게 힌지 연결되어 있는 힌지연결구가 형성되어 있고, 양측 후면에는 승하강삽입돌기가 형성되어 있는 승,하강연결판넬과;A hinge connector that is hingedly connected to the rear hinge connecting protrusion of the horizontal brace panel to be rotatably hinged, and on both rear sides thereof, a lifting and lowering connecting panel having a lifting insertion protrusion formed thereon;

상기 기립판넬의 상부에 볼트 고정이 가능하게 상하로 관통된 관통공이 수개 형성되어 있되, 상부 후면 양측 모서리부에는 미끄럼방지완충패드가 설치 고정되어 있는 마감구;를 일체로 포함하여 구성됨을 특징으로 한다.A plurality of through-holes are formed in the upper part of the standing panel to be fixed to the upper and lower sides to allow bolts to be fixed, and both ends of the upper rear end have a non-slip buffer pad installed and fixed thereto. .

이와 같이, 본 발명은 흙막이의 설치가 계단 형태로 이루어질 수 있게 수개의 흙막이를 상호간에 다단 절첩이 가능하되, 슬라이딩을 이룰 수 있는 셔터 형태로 연결 구성하여 주어, As described above, the present invention is possible to fold several mudles between each other so that the installation of the mudguards can be made in the form of a staircase, it is configured to connect in the form of a shutter that can achieve sliding,

실사용시 긴밀한 형태의 흙막이 기능을 제공함에 따라 다량의 토사와 침출수가 공사를 위한 작업 공간으로 전달되는 문제를 최소화 할 수 있게 된다.By providing a close-fitting barrier function in practical use, it is possible to minimize the problem that large amounts of soil and leachate are transferred to the work space for construction.

그리고, 흙막이의 설치가 계단 형태로 이루어지게 됨에 따라 전달되는 토압의 하중을 분산 지지할 수 있어 안정적인 설치 상태를 장기간 유지 보존할 수 있게 됨은 물론이고, 이러한 흙막이의 설치를 위한 "H"빔의 타설 작업을 기존 흙막이 시설처럼 깊게 타설하지 않아도 되는 장점이 있으므로 안전성 향상과 더불어 시공을 위한 소요 시간을 단축 시킬 수 있는 효과가 있다.In addition, since the installation of the retaining wall is made in the form of a staircase, it is possible to distribute and support the load of the earth pressure transmitted, as well as to maintain and maintain a stable installation state for a long time, as well as placing the "H" beam for installing the retaining wall. There is an advantage that the work does not need to be poured as deeply as a conventional earthquake facility, so there is an effect to improve safety and shorten the time required for construction.

또한 재사용시에는 전면으로 개구된 가이드홈에 낀 토사만 제거하면 되고, 이러한 토사 제거 작업시에는 상기 마감구의 해체를 이루어 작업하면 되기 때문에 재사용이 용이한 장점이 있고, 가볍고 부피가 작은 절첩이 가능한 판넬로 조립 형성되어 있어 이동 보관이 용이한 장점이 있어, 사용 편의성을 향상시켜 줄 수 있도록 한 효과가 있다. In addition, when reusing, only the soil stuck in the guide groove opened to the front is removed, and when removing the soil, the dismantling of the finish is performed, so there is an advantage of easy reuse, and light and bulky folding panels are possible. As it is formed to be assembled, there is an advantage of easy to move and store, there is an effect to improve the ease of use.

기타 실시예의 구체적인 사항들은 상세한 설명 및 도면들에 포함되어 있다.Specific details of other embodiments are included in the detailed description and drawings.

본 발명의 이점 및 특징, 그리고 그것들을 달성하는 방법은 첨부되는 도면과 함께 상세하게 후술되어 있는 실시예를 참조하면 명확해질 것이다.Advantages and features of the present invention, and methods for achieving them will be apparent with reference to the embodiments described below in detail in conjunction with the accompanying drawings.

그러나 본 발명은 이하에서 개시되는 실시예에 한정되는 것이 아니라 서로 다른 다양한 형태로 구현될 것이며, 단지 본 실시예는 본 발명의 개시가 완전하도록 하며, 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자에게 발명의 범주를 완전하게 알려주기 위해 제공되는 것이며, 본 발명은 청구항의 범주에 의해 정의될 뿐이다.However, the present invention is not limited to the embodiments disclosed below, but will be implemented in various forms, and only the present embodiments are intended to complete the disclosure of the present invention, and those skilled in the art to which the present invention pertains. It is provided to fully inform the scope of the invention, and the invention is defined only by the scope of the claims.

이하, 첨부된 도면을 참조로 하여 본 발명을 상세하게 설명하면 다음과 같다.Hereinafter, the present invention will be described in detail with reference to the accompanying drawings.

도 1은 발명에 따른 건축 및 토목공사용 셔터형 흙막이의 구성 상태를 도시한 사시도이고, 도 2은 발명에 따른 건축 및 토목공사용 셔터형 흙막이의 구성 상태를 도시한 분해 사시도이며, 도 3은 발명에 따른 건축 및 토목공사용 셔터형 흙막이의 사용을 위한 조립 상태를 도시한 사시도이고, 도 4는 발명에 따른 건축 및 토목공사용 셔터형 흙막이의 설치 상태를 도시한 설치단면도이다.1 is a perspective view showing the configuration of the shutter-type mudguard for construction and civil works according to the invention, Figure 2 is an exploded perspective view showing the configuration of the shutter-type mudguard for construction and civil works according to the invention, Figure 3 4 is a perspective view showing the assembly state for the use of the construction and civil engineering shutter-type mudguard according to the invention, Figure 4 is an installation cross-sectional view showing the installation state of the construction and civil engineering shutter-type mudguard according to the invention.

도시된 바와 같이 본 발명은 크게, 일정거리를 두고 타설된 "H"빔(1)과 "H"빔(1) 사이에 횡설 위치하여 토압 하중을 직접적으로 전달 받게되는 기립판넬(10)과, 상기 기립판넬(10)의 하부에 힌지 연결되어 상기 기립판넬(10) 기울림 설치를 가능하게 하는 수평버팀판넬(20)과, 상기 수평버팀판넬(20)의 일측에 힌지 연결되어 있되, 타 기립판넬(10´)과의 연결을 가능하게 하는 승,하강연결판넬(30)과, 상기 기립판넬(10)의 상부를 마감하는 마감구(40)로 구성되어 있다.As shown in the present invention, a standing panel 10 which is placed horizontally between the "H" beam 1 and the "H" beam 1 that has been placed at a predetermined distance is directly receiving a earth pressure load, and The hinge is connected to the lower portion of the standing panel 10, the horizontal bracing panel 20 to allow the mounting of the standing panel 10 inclined, and the hinge is connected to one side of the horizontal bracing panel 20, the other standing Up and down connection panel 30 to enable the connection with the panel (10 ') is composed of a finisher 40 for closing the upper portion of the standing panel (10).

여기서, 상기 기립판넬(10)은 양측 전면에는 상부가 개구된 가이드홈(12)이 형성되어 있고, 상부에는 수개의 볼트공(14)이 등간격으로 형성되어 있으며, 하부에는 힌지연결구(16)가 형성되어 있고, 상기 수평버팀판넬(20)은 전방 양측에는 상기 기립판넬(10)의 하부에 형성되어 있는 힌지연결구(16)와 회동가능하게 힌지 연결되어 있되, 미끄럼방지완충패드(26)가 설치 고정되어 있는 전방힌지연결돌기(22)가 형성되어 있고, 후방 양측에는 후방힌지연결돌기(24)가 형성되어 있다.Here, the standing panel 10 has a guide groove 12 having an upper opening at both front surfaces thereof, a plurality of bolt holes 14 formed at equal intervals, and a hinge connector 16 at a lower portion thereof. Is formed, the horizontal support panel 20 is hinged rotatably connected to the hinge connector 16 formed in the lower side of the standing panel 10 on both front sides, non-slip buffer pad 26 is The front hinge connecting protrusion 22 is fixed to the installation, and the rear hinge connecting protrusion 24 is formed on both rear sides.

그리고, 상기 승,하강연결판넬(30)은 상부에는 상기 수평버팀판넬(20)의 후방 힌지연결돌기(24)와 회동가능하게 힌지 연결되어 있는 힌지연결구(32)가 형성되어 있고, 양측 후면에는 승하강삽입돌기(34)가 형성되어 있으며, 상기 마감구(40)는 상기 기립판넬(10)의 상부에 볼트(2) 고정이 가능하게 상하로 관통된 관통공(42)이 수개 형성되어 있되, 상부 후면 모서리부 양측에는 미끄럼방지완충패드(44)가 설치 고정되어 있다.In addition, the lifting and lowering connection panel 30 has a hinge connector 32 which is hinged to the rear hinge connecting projection 24 of the horizontal support panel 20 to be rotatable at the top, both sides of the rear Ascending and descending insertion protrusions 34 are formed, and the finish opening 40 has a plurality of through-holes 42 penetrated up and down to enable the bolt 2 to be fixed to the top of the standing panel 10. On both sides of the upper rear corner, an anti-slip buffer pad 44 is installed and fixed.

도면중 미설명 부호 28은 "힌지핀"이다In the drawing, reference numeral 28 denotes a "hinge pin".

이와 같이 구성되어 있는 본 고안의 작용을 도면을 참조하여 설명하면 다음 과 같다.Referring to the drawings the operation of the present invention configured as described above is as follows.

이해를 돕기 위해 먼저 설치 방법을 순서에 의거하여 설명하기로 한다.To help understand, first, the installation method will be described in order.

설치를 위해선 먼저 기립판넬(10)과 수평버팀판넬(20) 그리고 승,하강연결판넬(30) 및 마감구(40)를 일체가 되도록 조립하여 이루어진 흙막이(R)를 시공을 위한 높이 거리 만큼 수개(R1,R2,R3...) 연결 조립한다.For the installation, first, the standing panel 10, the horizontal bracing panel 20, and the soil barrier R formed by assembling the connecting panel 30 and the finishing tool 40 as one unit as many as the height distance for construction. (R1, R2, R3 ...) Assemble and assemble.

이때 연결 조립은 일 단위체의 흙막이(R1)를 구성하고 있는 승,하강연결판넬(30)의 양 후면에 형성되어 있는 승하강삽입돌기(34)를 타 단위체 흙막이(R2)를 구성하고 있는 기립판넬(10)의 양 전면에 형성되어 있는 가이드홈(12) 내에 삽입 위치시킨 후 마감구(40)를 체결하는 과정을 연속 반복하여 이루면 된다.At this time, the connection assembly is an upright panel constituting the unit block (R2) other than the lifting inserting protrusions 34 formed on both rear sides of the lifting and lowering connection panel (30) constituting the unit (R1) of one unit. After inserting into the guide grooves 12 formed on both front surfaces of the 10, the process of fastening the finish opening 40 may be repeatedly performed.

여기서 연결 조립되는 각 흙막이(R1,R2,R3...)의 초기 상태는 도 4의 상부(파선으로 도시)에 도시된 바와 같이 일 단위체의 흙막이(R1)를 구성하고 있는 승,하강연결판넬(30)의 승하강삽입돌기(36)가 이를 삽입 연결하고 있는 타 흙막이(R2) 기립판넬(10)의 가이드홈(12) 내의 하부에 위치되도록 하여, 이와 연결된 수평버팀판넬(20)과 기립판넬(10) 역시 수직상태가 되도록 한다. Here, the initial state of each of the connecting blocks (R1, R2, R3 ...) is as shown in the upper portion (shown with a broken line) of Figure 4 ascending, descending connecting panel constituting a single block of soil (R1) The lifting and lowering insertion projection 36 of the 30 is positioned in the lower portion of the guide groove 12 of the other soil barrier R2 standing panel 10 to which it is inserted, so as to stand up with the horizontal support panel 20 connected thereto. The panel 10 is also vertical.

이러한 과정을 거쳐 의도한 높이를 이룰 수 있는 흙막이(R)이의 연결 조립과정이 완료되면 일정 간격을 두고 타설된 "H"빔(1)의 사이 공간 상부로 부터 연결 조립된 흙막이(R)를 정 위치시킨 후 최하부에 연결 위치된 흙막이(R1)부터 차례대로 슬라이딩 삽입 설치함과 동시에 되메움 작업 역시 차례대로 실시하면 모든 설치가 완료된다.Through this process, when the connecting assembly of the retaining blocks R which can achieve the intended height is completed, the assembled retaining blocks R are connected from the upper part of the space between the “H” beams 1 that are placed at regular intervals. After placing the sliding insert (R1) located in the bottom connected to the bottom in order to install the slide and at the same time backfilling is also carried out in order to complete all installation.

이를 더욱 구체적으로 설명하면, "H"빔(1) 사이에 슬라이딩 삽입되는 흙막 이(R)중 최초로 삽입 위치되는 흙막이(R1) 기립판넬(10)의 기울림만을 인위 조정하여 위치시키고, 뒤이어 따라 삽입 위치되는 흙막이(R2,R3...)는 "H"빔(1) 사이에 삽입 후 먼저 삽입 위치된 흙막이(R1)의 기립판넬(10) 가이드홈(12) 하부에 삽입 위치되어 있던 승,하강연결판넬(30)의 승하강삽입돌기(34)가 상기 가이드홈(12)의 상부로 위치되도록 잡아당겨 이동 시킨 상태에서 최초 위치되는 흙막이(R1) 기립판넬(10)의 전면에 되메움을 하면 된다.In more detail, it is positioned by adjusting only the inclination of the standing wall (R1) standing panel 10, which is inserted for the first time among the holding screen (R) inserted between the "H" beam (1), followed by After inserting between the "H" beams 1, the retaining blocks R2 and R3 are inserted into the bottom of the standing grooves 10 of the guide panel 12 of the standing panel 10 of the retaining blocks R1. The pull-up insertion protrusion 34 of the lower connection panel 30 is pulled back to be positioned above the guide groove 12, and moved back to the front of the soil barrier R1 standing panel 10 which is initially positioned. You can do

그리고, 이렇게 잡아 당겨진 승,하강연결판넬(30)의 상부에 힌지 연결되어 있던 수평버팀판넬(20) 상부가 전방으로 기울어지도록 위치 변경시켜 "H"빔(1)의 일 내측면에 맞닿아 지지되도록 하는 과정을 연속 반복하면 의도한 계단형태의 흙막이(R)의 설치가 가능해진다. Then, the upper portion of the horizontal support panel 20 hinged to the upper portion of the pulled up / down connecting panel 30 thus pulled is changed to be inclined forward to be brought into contact with one inner surface of the “H” beam 1. Repeatedly repeating the process to enable the installation of the intended stairwell (R).

여기서 수평버팀판넬(20) 전방 양측과 마감구(40) 상부 후면 모서리부 양측에 설치 고정되어 있는 미끄럼방지완충패드(26),(44)는 설치과정에서 "H"빔(1)과 긴밀한 접촉상태를 이루게 됨은 물론이고 미끄러짐 현상이 방지되어 설치 상태를 안정되게 이룰 수 있게 되고, 상호간의 파손현상을 방지할 수 있게 된다. Here, the non-slip buffer pads 26 and 44, which are fixed to both front sides of the horizontal support panel 20 and both sides of the upper end of the upper end 40, are in intimate contact with the "H" beam 1 during the installation process. It is possible to achieve the state as well as to prevent the sliding phenomenon to achieve a stable installation state, it is possible to prevent the mutual damage phenomenon.

이와 같이 설치가 이루어지는 흙막이(R)는 상술한 바와 같이 설치 단면이 계단 형상을 이루게 됨에 따라 실사용시 전달되는 토압의 하중을 분산 지지할 수 있어 안정적인 설치 상태를 장기간 유지 보존할 수 있게 됨은 물론이고, 이러한 흙막이(R)의 설치를 위한 "H"빔(1)의 타설 작업을 기존 흙막이 시설처럼 깊게 타설하지 않아도 된다.As described above, since the installation section is formed in the step shape as described above, the earthen barrier R which is installed as described above can distribute and support the load of earth pressure transmitted during actual use, so that the stable installation state can be maintained for a long time, as well as The installation work of the "H" beam (1) for the installation of such a barrier (R) does not have to be poured as deeply as a conventional barrier.

또한 셔터형 구조로 형성되어 있어 실사용시 긴밀한 형태의 흙막이(R) 기능 을 제공함에 따라 다량의 토사와 침출수가 공사를 위한 작업 공간으로 전달되는 문제현상을 최소화 할 수 있게 된다.In addition, it is formed in a shutter-type structure to provide a close form (R) function in the real use, it is possible to minimize the problem phenomenon that a large amount of soil and leachate is transferred to the work space for construction.

그리고, 재사용시에는 전면으로 개구된 가이드홈(12)에 낀 토사만 제거하면 되고, 이러한 토사 제거 작업시에는 상기 마감구(40)의 해체를 이루어 작업하면 되기 때문에 재사용이 용이하고, 가볍고 부피가 작은 절첩이 가능한 판넬로 조립 형성되어 있어 이동 보관이 용이하다. And, when reusing, only the soil stuck in the guide grooves 12 opened to the front only need to be removed, and during such a soil removal work is to be made by dismantling the finish 40, easy to reuse, light and bulky It is easy to move and store because it is assembled by panel that can be folded small.

또한, 해체시에는 최상부에 위치한 흙막이(R)이를 상부로 잡아당기기만 하면 수평 상태를 이루어 기립판넬(10)의 하부 버팀을 이루고 있던 수평버팀판넬(20)의 버팀 상태가 해제되며 인출이 용이한 수직 상태를 이루게 됨에 따라 해체를 신속 용이하게 이룰 수 있게 된다.In addition, during dismantling, simply pull the top of the soil barrier (R) located at the top to form a horizontal state, thereby releasing the brace of the horizontal brace panel (20), which forms the lower brace of the standing panel (10), and is easy to withdraw. As the vertical state is achieved, the dismantling can be performed quickly and easily.

도 1은 본 발명에 따른 건축 및 토목공사용 셔터형 흙막이의 구성 상태를 도시한 사시도, 1 is a perspective view showing a configuration state of the shutter-type mudguard for construction and civil works according to the present invention;

도 2은 본 발명에 따른 건축 및 토목공사용 셔터형 흙막이의 구성 상태를 도시한 분해 사시도, Figure 2 is an exploded perspective view showing the configuration of the shutter-type mudguard for construction and civil works according to the invention,

도 3은 본 발명에 따른 건축 및 토목공사용 셔터형 흙막이의 사용을 위한 조립 상태를 도시한 사시도, Figure 3 is a perspective view showing the assembled state for the use of construction and civil engineering shutter type muddle according to the present invention,

도 4는 본 발명에 따른 건축 및 토목공사용 셔터형 흙막이의 설치 상태를 도시한 설치단면도,Figure 4 is an installation cross-sectional view showing the installation state of the construction and civil engineering shutter type muddle according to the invention,

도 5는 종래의 간이 흙막이 구조물의 구성을 개략적으로 도시한 구성도,5 is a configuration diagram schematically showing the configuration of a conventional simple earthenware structure,

도 6은 또다른 종래 흙막이 조립체의 구성 상태를 도시한 사시도.Figure 6 is a perspective view showing the configuration of another conventional retainer assembly.

*도면의 주요 부분에 대한 부호의 설명** Description of the symbols for the main parts of the drawings *

1 : "H"빔 2 : 볼트1: "H" beam 2: bolt

R : 흙막이R: earth shield

10 : 기립판넬 12 : 가이드홈10: standing panel 12: guide groove

14 : 볼트공 16 : 힌지연결구14: bolt hole 16: hinge connector

20 : 수평버팀판넬 22 : 전방힌지연결돌기20: Horizontal bracing panel 22: Front hinge connection protrusion

24 : 후방힌지연결돌기 26 : 미끄럼방지완충패드24: rear hinge connecting projection 26: non-slip buffer pad

28 : 힌지핀28: hinge pin

30 : 승,하강연결판넬 32 : 힌지연결구30: Up and down connection panel 32: Hinge connector

34 : 승하강삽입돌기 34: raising and lowering insertion protrusion

40 : 마감구 42 : 관통공40: finish hole 42: through hole

44 ; 미끄럼방지완충패드44; Anti-slip Shock Pad

Claims (1)

양측 전면에는 상부가 개구된 가이드홈이 형성되어 있고, 상부에는 수개의 볼트공이 등간격으로 형성되어 있으며, 하부에는 힌지연결구가 형성되어 있는 기립판넬과;A guide panel having an upper opening at both front surfaces thereof, a plurality of bolt holes formed at equal intervals at an upper portion thereof, and a rising panel having a hinge connector formed at a lower portion thereof; 전방 양측에는 상기 기립판넬의 하부에 형성되어 있는 힌지연결구와 회동가능하게 힌지 연결되어 있되, 미끄럼방지완충패드가 설치 고정되어 있는 전방힌지연결돌기가 형성되어 있고, 후방 양측에는 후방힌지연결돌기가 형성되어 있는 수평버팀판넬와;The front both sides are hinged rotatably with the hinge connector formed on the bottom of the standing panel, the front hinge connecting projection is fixed to the non-slip buffer pad is installed, the rear hinge connecting projection is formed on both sides of the rear A horizontal brace panel; 상부에는 상기 수평버팀판넬의 후방 힌지연결돌기와 회동가능하게 힌지 연결되어 있는 힌지연결구가 형성되어 있고, 양측 후면에는 승하강삽입돌기가 형성되어 있는 승,하강연결판넬과;A hinge connector that is hingedly connected to the rear hinge connecting protrusion of the horizontal brace panel to be rotatably hinged, and on both rear sides thereof, a lifting and lowering connecting panel having a lifting insertion protrusion formed thereon; 상기 기립판넬의 상부에 볼트 고정이 가능하게 상하로 관통된 관통공이 수개 형성되어 있되, 상부 후면 양측 모서리부에는 미끄럼방지완충패드가 설치 고정되어 있는 마감구;를 일체로 포함하여 구성됨을 특징으로 하는 건축 및 토목공사용 셔터형 흙막이.A plurality of through-holes are formed in the upper portion of the standing panel to be fixed to the upper and lower bolts to be fixed, the upper and rear corners of the upper rear end has a non-slip buffer pad is installed and fixed; integrally comprising a Shutter retainers for construction and civil engineering.
KR1020090034878A 2009-04-22 2009-04-22 Retaining of shutter type for construction and engineering work KR100913945B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020090034878A KR100913945B1 (en) 2009-04-22 2009-04-22 Retaining of shutter type for construction and engineering work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020090034878A KR100913945B1 (en) 2009-04-22 2009-04-22 Retaining of shutter type for construction and engineering work

Publications (1)

Publication Number Publication Date
KR100913945B1 true KR100913945B1 (en) 2009-08-25

Family

ID=41210228

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020090034878A KR100913945B1 (en) 2009-04-22 2009-04-22 Retaining of shutter type for construction and engineering work

Country Status (1)

Country Link
KR (1) KR100913945B1 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101386527B1 (en) 2013-11-07 2014-04-17 (주)리드엔지니어링건축사사무소 Retaining wall panel of folding type for public works
KR101535875B1 (en) * 2014-10-27 2015-07-27 (주)리드엔지니어링건축사사무소 Retaining wall panel for public works
KR101830627B1 (en) * 2017-04-19 2018-02-21 주식회사 리드엔지니어링건축사사무소 Retaining wall panel for public works
KR101958934B1 (en) * 2018-09-28 2019-03-15 임전수 Sheathing Assembly for Civil Engineering Work
KR20220052212A (en) * 2020-10-20 2022-04-27 주식회사성진종합건설 board unit for soil retaining wall
CN115404874A (en) * 2022-07-31 2022-11-29 王新华 Building deep foundation pit structure convenient to prevent long-pending soil in foundation ditch edge
KR102625663B1 (en) * 2023-03-30 2024-01-16 주식회사 솔아이텍 Temporary panel structure for retaining of earth

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05295732A (en) * 1992-04-21 1993-11-09 Daiwa Tsushin Kensetsu Kk Crosswise sheet pile removing method
JPH11217823A (en) 1998-01-30 1999-08-10 Azuma Kigyo Kk Earth retaining method in cut and cover tunneling work of ground and steel sheet pile used therefor
KR100573798B1 (en) 2005-04-01 2006-04-27 박경혜 Structure for constructing a wall for retaining of earth
KR100732943B1 (en) 2005-03-10 2007-06-27 윤은중 Assembly for retaining wall

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05295732A (en) * 1992-04-21 1993-11-09 Daiwa Tsushin Kensetsu Kk Crosswise sheet pile removing method
JPH11217823A (en) 1998-01-30 1999-08-10 Azuma Kigyo Kk Earth retaining method in cut and cover tunneling work of ground and steel sheet pile used therefor
KR100732943B1 (en) 2005-03-10 2007-06-27 윤은중 Assembly for retaining wall
KR100573798B1 (en) 2005-04-01 2006-04-27 박경혜 Structure for constructing a wall for retaining of earth

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101386527B1 (en) 2013-11-07 2014-04-17 (주)리드엔지니어링건축사사무소 Retaining wall panel of folding type for public works
KR101535875B1 (en) * 2014-10-27 2015-07-27 (주)리드엔지니어링건축사사무소 Retaining wall panel for public works
KR101830627B1 (en) * 2017-04-19 2018-02-21 주식회사 리드엔지니어링건축사사무소 Retaining wall panel for public works
KR101958934B1 (en) * 2018-09-28 2019-03-15 임전수 Sheathing Assembly for Civil Engineering Work
KR20220052212A (en) * 2020-10-20 2022-04-27 주식회사성진종합건설 board unit for soil retaining wall
KR102492201B1 (en) * 2020-10-20 2023-01-26 주식회사성진종합건설 board unit for soil retaining wall
CN115404874A (en) * 2022-07-31 2022-11-29 王新华 Building deep foundation pit structure convenient to prevent long-pending soil in foundation ditch edge
CN115404874B (en) * 2022-07-31 2023-11-03 山西恒昱建设工程有限公司 Building deep foundation pit structure convenient to prevent foundation pit edge soil accumulation
KR102625663B1 (en) * 2023-03-30 2024-01-16 주식회사 솔아이텍 Temporary panel structure for retaining of earth

Similar Documents

Publication Publication Date Title
KR100913945B1 (en) Retaining of shutter type for construction and engineering work
US3184893A (en) Contact foundation method
KR101094827B1 (en) Structure of variable temporary retaning wall
KR100967497B1 (en) Method for constructing an underground structure
KR100975764B1 (en) The store install and retaining wall which the deactivation is easy
KR20200124949A (en) Anchor Tension way sheathing structure and sheathing method of construction
KR101467147B1 (en) Subway platform construction method using semi-rigid connection
KR100566721B1 (en) Prefab type land-side protection wall device
KR101474338B1 (en) Furlable earth retaining structure for provisional facilities and construction method thereof
KR101386527B1 (en) Retaining wall panel of folding type for public works
KR101436119B1 (en) Holding apparatus for CFT column and the construction method of the CFT column using it
KR20120109418A (en) Inclined earth retaining structure method
KR100732943B1 (en) Assembly for retaining wall
KR100472077B1 (en) Structure for temporary retaining wall and method thereof
KR100629148B1 (en) Temporary facilities structure for basic work of construction
KR20190002845U (en) Braced wall
KR20120088929A (en) Structure of Temporary Retaning wall
KR101545330B1 (en) Prefab type land-side protection wall device
KR100716278B1 (en) Assembly for retaining wall
KR102655594B1 (en) Safety temparary facilities structure
JP2784644B2 (en) Assembling temporary fence
KR100679866B1 (en) Equipment of steel mold for construction work
KR101535875B1 (en) Retaining wall panel for public works
KR200354769Y1 (en) Temporary facilities structure for basic work of construction
CN212835405U (en) Foundation pit excavation protective structure

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130109

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20140107

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20150810

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20160314

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20170328

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20180309

Year of fee payment: 10