KR20200124949A - Anchor Tension way sheathing structure and sheathing method of construction - Google Patents
Anchor Tension way sheathing structure and sheathing method of construction Download PDFInfo
- Publication number
- KR20200124949A KR20200124949A KR1020190048455A KR20190048455A KR20200124949A KR 20200124949 A KR20200124949 A KR 20200124949A KR 1020190048455 A KR1020190048455 A KR 1020190048455A KR 20190048455 A KR20190048455 A KR 20190048455A KR 20200124949 A KR20200124949 A KR 20200124949A
- Authority
- KR
- South Korea
- Prior art keywords
- anchor
- pile
- wire
- post
- post pile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
- 238000000034 method Methods 0.000 title claims abstract description 32
- 238000010276 construction Methods 0.000 title description 17
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 53
- 239000010959 steel Substances 0.000 claims abstract description 53
- 238000009412 basement excavation Methods 0.000 claims abstract description 22
- 238000009434 installation Methods 0.000 claims description 35
- 238000013459 approach Methods 0.000 claims description 5
- 238000005553 drilling Methods 0.000 claims description 5
- 230000008878 coupling Effects 0.000 claims description 2
- 238000010168 coupling process Methods 0.000 claims description 2
- 238000005859 coupling reaction Methods 0.000 claims description 2
- 239000000463 material Substances 0.000 abstract description 7
- 239000002689 soil Substances 0.000 description 15
- 230000004888 barrier function Effects 0.000 description 8
- 238000006073 displacement reaction Methods 0.000 description 4
- 230000003014 reinforcing effect Effects 0.000 description 3
- 230000000903 blocking effect Effects 0.000 description 2
- 238000009435 building construction Methods 0.000 description 2
- 239000003673 groundwater Substances 0.000 description 2
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
- 125000006850 spacer group Chemical group 0.000 description 1
- 210000003813 thumb Anatomy 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/06—Foundation trenches ditches or narrow shafts
- E02D17/08—Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
- E02D5/76—Anchorings for bulkheads or sections thereof in as much as specially adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2600/00—Miscellaneous
- E02D2600/30—Miscellaneous comprising anchoring details
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
본 발명은 지주말뚝의 후방으로 어스앵커를 설치하여 지주말뚝 상단을 인장되게 함으로 해서 터파기 쪽에 별도의 지보재를 설치하지 않아도 지주말뚝이 터파지 작업공간으로 넘어지거나 붕괴되는 등의 염려가 없도록 하여, 특히 도심의 좁은 공간 내에서도 안전한 터파기 작업을 저비용으로 수월하게 제공할 수 있는 앵커 인장식 흙막이 구조 및 흙막이 공법을 제공코자 하는 것이다.
즉, 본 발명은 터파기 경계에 설치되는 지주말뚝과; 상기 지주말뚝의 바깥쪽으로 지주말뚝 보다 깊은 심도로 시공되는 앵커가 하단에 구비된 와이어 또는 강봉을 포함하는 어스앵커와; 상기 지주말뚝 바깥쪽으로 위치하도록 지주말뚝의 상단에 일단을 고정한 수평지지부재와; 상기 수평지지부재에 직각으로 안치 결합되어 인장공간을 제공하는 한 쌍의 앵커지지대와; 상기 앵커지지대에 안치된 상태에서 인장공간을 통해서 인출되는 상기 와이어 또는 강봉을 인장하는 앵커브래킷을 포함하는 흙막이 구조 및 이를 시공하는 방법을 제공한 것이다.In the present invention, by installing an earth anchor to the rear of the post pile so that the upper part of the post pile is tensioned, there is no concern that the post pile falls or collapses into the trenching work space without installing a separate support material on the excavation side. The goal is to provide an anchor tension-type retaining structure and a retaining method that can easily provide safe excavation work at low cost even within a narrow space in the city.
That is, the present invention and the post pile installed at the boundary of the trench; An earth anchor including a wire or steel bar provided at the lower end of the anchor installed at a depth greater than that of the post pile to the outside of the post pile; A horizontal support member fixing one end to the upper end of the post pile so as to be positioned outside the post pile; A pair of anchor supports installed at right angles to the horizontal support member to provide a tensile space; It is to provide a retaining structure including an anchor bracket for tensioning the wire or steel bar drawn out through a tensioning space while being placed in the anchor support and a method of constructing the same.
Description
본 발명은 토목공사나 건축공사 현장에서 일정 간격으로 세워지는 지주말뚝에 토류판을 설치하는 앵커 인장식 흙막이 구조 및 흙막이 공법에 관한 것으로서, 보다 구체적으로는 지주말뚝의 후방으로 어스앵커를 설치하여 지주말뚝 상단을 인장되게 함으로 해서 터파기 쪽에 별도의 지보재를 설치하지 않아도 지주말뚝이 터파지 작업공간으로 넘어지거나 붕괴되는 등의 염려가 없도록 하여, 특히 도심의 좁은 공간 내에서도 안전한 터파기 작업을 저비용으로 수월하게 제공할 수 있는 앵커 인장식 흙막이 구조 및 흙막이 공법을 제공코자 하는 것이다.The present invention relates to an anchor tension-type soil barrier structure and a soil barrier construction method for installing earth plates on a pillar pile erected at regular intervals in a civil engineering or building construction site, and more specifically, an earth anchor installed at the rear of the pillar pile to the top of the pillar pile. By being tensioned, there is no fear that the stakes may fall or collapse into the trenching work space even without installing a separate support material on the trenching side.Especially, safe trenching work can be easily provided at low cost even within a narrow urban area. It is intended to provide an anchor tension type retaining structure and a retaining method.
일반적으로 흙막이 공법이란 지하공사를 원활하게 할 수 있도록 굴토벽면의 붕괴나 토사의 유입을 방지하기 위한 목적으로 설치되는 가설구조물로써 안전성과 시공성은 물론 경제성도 동시에 요구되는 시설이다.In general, the earth protection method is a temporary structure installed for the purpose of preventing the collapse of the excavation wall or the inflow of soil so that the underground works can be performed smoothly, and it is a facility that requires both safety and construction and economical efficiency.
또한, 흙막이 공법은 H.PILE+토류판설치공법이나 SHEET PILE설치공법 및 조립식 간이 흙막이 설치공법등이 주로 사용되고 있으며 설치현장의 토질 및 지하수위등 제반조건 등에 따라 적합한 공법이 선택되어 설치되며 지하매설물의 노선선정, 매설형태(매설폭 및 심도)결정, 토압계산, 안전율적용, 흙막이의 필요, 강도계산, 공사비비교, 흙막이 공법의 선정 및 설계 시공순으로 결정된다.In addition, H.PILE + earth plate installation method, sheet pile installation method, and prefabricated simple earth block installation method are mainly used for the earth protection method. Appropriate method is selected and installed according to various conditions such as soil quality and groundwater level of the installation site. It is decided in the order of selection, determination of buried type (buried width and depth), earth pressure calculation, safety factor application, need for earth protection, strength calculation, comparison of construction, selection of earth protection method and design construction.
흙막이 공법의 일반적인 예의 지지말뚝 토류판 공법은 수직하게 설치된 복수개의 지지말뚝(H 빔)과, 이들 지지말뚝 사이에 결합되어 후방의 흙더미가 전방으로 무너지는 것을 방지하는 토류판을 포함하는 구성으로 이루어진다.The support pile earth plate construction method of a general example of the earth protection method consists of a structure including a plurality of support piles (H beams) vertically installed, and an earth plate that is coupled between the support piles to prevent the rear pile of soil from collapsing forward.
이때 토류판으로는 소정 규격의 목재판 또는 강재판이 사용되며, 이를 적층하여 벽체를 형성하고, 그 적층된 토류판을 고정하기 위하여 끼움목(쐐기)을 설치한 구조를 갖는다.At this time, a wooden plate or a steel plate of a predetermined standard is used as the earth plate, which is laminated to form a wall, and has a structure in which a clamp (wedge) is installed to fix the laminated earth plate.
이와 같은 지지말뚝 흙막이 공법은 고심도의 터파기 공사를 수행하는 경우, H 빔만으로는 배후토사의 토압에 저항할 수 없으므로, 이를 보강하기 위하여 터파기 공사구간 쪽에 많은 수의 지보재(Strut, Earth Anchor, Raker 등)를 사용해야 하는데, 이러한 방식은 공사기간이 많이 소요되고 비경제적일 뿐만 아니라, 작업공간의 확보를 어렵게 하고, 구조적으로 비효율적이므로 주변지반 침하의 우려가 높고, 상부두부 변위가 상대적으로 크게 발생하므로 배면부 지반의 이완이 크게 발생하는 문제점이 발생하였다.In the case of high-depth dug construction, such a supporting pile soil blocking method cannot resist the earth pressure of the rear soil with only the H beam, so a large number of support materials (Strut, Earth Anchor, etc.) Raker, etc.), which takes a long construction period and is not economical, and makes it difficult to secure a working space and is structurally inefficient, so there is a high risk of subsidence of the surrounding ground and a relatively large displacement of the upper head. Therefore, there was a problem that large relaxation of the ground on the back side occurred.
상기와 같은 문제점을 해결하기 위한 선행기술로 대한민국 등록특허공보(B1)등록 제10-0964993호(2010.06.21.)에는 고심도의 터파기 작업을 수행하는 경우에도 지보재(Strut, Earth Anchor, Raker 등) 없이 배후토사의 토압에 충분히 저항하도록 하고, 흙막이 구조물의 전체적인 변위의 발생을 억제할 수 있도록 하는 고심도 2열 억지말뚝 흙막이 공법을 제시하고 있으며 이러한 2열 흙막이 공법을 통하여 배후토사의 토압에 충분히 저항하도록 하고 흙막이 구조물의 전체적인 변위발생을 억제할 수 있는 기술이 제공되었다.As a prior art for solving the above problems, Korean Registered Patent Publication (B1) Registration No. 10-0964993 (2010.06.21.) discloses support materials (Strut, Earth Anchor, Raker) even when high-depth excavation is performed. Etc.) to sufficiently resist the earth pressure of the rear soil and suppress the occurrence of the overall displacement of the soil barrier structure. A technology has been provided that allows sufficient resistance and suppresses the occurrence of overall displacement of the retaining structure.
상기와 같은 2열 흙막이 공법의 구성적 특징을 살펴보면 도 4에 도시한 바와 같이 1열 엄지말뚝과 2열 억지말뚝을 일정간격 이격된 상태로 지면과 수직되게 근입한 상태에서 상부를 연결부재를 통하여 연결함으로써 대략 "П"의 형태로 말뚝을 설치함으로써 기존 1열의 말뚝을 이용한 흙막이 공법에 비하여 더욱 우수하게 배후토사의 압력에 충분히 저항함으로써 흙막이 말뚝의 변형을 방지할 수 있는 공법이 개시되어 있다.Looking at the constitutional features of the two-row earthing method, as shown in Fig. 4, in a state in which the first row thumb piles and the second row restraint piles are spaced apart from each other and perpendicularly to the ground, the upper part is connected through a connecting member. By connecting the piles in the form of approximately "P", a construction method capable of preventing the deformation of the piles has been disclosed by sufficiently resisting the pressure of the rear soil more excellently than the existing one-row piles.
그러나 상기와 같이 2열 억지말뚝 흙막이 공법 또한 1열 흙막이 공법에 비하여 높은 토압에 대한 저항치수가 높은 것은 확인할 수 있으나 구조적인 휨으로 인해 변위가 크게 발생하는 문제점이 계속하여 발생하였다.However, as described above, it can be confirmed that the resistance dimension against high earth pressure is higher than that of the two-row impeding pile earthing method and the first row earthing method, but there has been a problem that large displacement occurs due to structural warpage.
또한, 이러한 2열 억지말뚝의 저항력을 높이기 위하여 말뚝의 내측으로 앵커 또는 레일을 부가적으로 설치함으로써 흙막이 공사의 공기가 길어지고 설치비가 증가하는 문제점이 발생하였다.In addition, by additionally installing an anchor or rail inside the pile in order to increase the resistance of these two-row restrained piles, there was a problem in that the duration of the earth protection work was lengthened and the installation cost was increased.
또 다른 선행기술로는 대한민국 등록특허공보(B1)10-1262357호(2013.05.08.)의 지주식 흙막이 공법이 제공되고 있으며, 그 구성은 보링장치(미도시)로 일정간격을 두고 다수개의 흙막이용 지주구멍을 천공하는 구멍천공단계와, 천공된 지주구멍에 제1지주말뚝과 제2지주말뚝을 각각 근입하는 지주설치단계와, 상기 제1지주말뚝과 제2지주말뚝의 상단 연결부분을 결속수단을 이용하여 연결하는 결속단계와, 상기 제1지주말뚝과 제2지주말뚝이 연결된 상태에서 제1지주말뚝의 일측면이 노출되도록 지면을 굴착하는 굴착단계와, 상기 노출된 제1지주말뚝과 노출된 제1지주말뚝 사이에 흙막이판을 설치하는 흙막이판 설치단계;를 포함하고, 상기 제2지주말뚝은 하단부에 고정부가 가접(假接)되어 인발부와 고정부로 분할 형성하고 상기 제2지주말뚝의 외주면에 하나 이상의 와이어가 밀착되며 끝부분을 피복하여 노출된 강선이 고정부에 연결되는 지주식 흙막이 공법에 있어서, 상기 고정부는 일측이 상기 제2지주말뚝의 끝부분에 가접되며 표면에 여러 개의 구멍을 갖는 강관과, 상기 강관의 내부에 형성되는 여러 개의 스페이스와, 상기 강관 내부에서 여러 개의 스페이서를 연결고정하는 결속선 및 상기 강관의 내부에 삽입되며 와이어로부터 피복되어 노출된 하나 이상의 강선을 포함하며, 여기서, 상기 강관의 외측에 콘크리트를 타설함으로서 콘크리트가 강관의 구멍을 통하여 강관의 내부와 외부로 고르게 타설되어 고정부와 내부에 삽입된 강선을 견고하게 양생한 것으로 이루어진 지주식 흙막이 공법을 제공하고 있다.As another prior art, the post-type soil barrier method of Korean Registered Patent Publication (B1) 10-1262357 (2013.05.08.) is provided, and the configuration is a boring device (not shown) to prevent multiple soil barriers at regular intervals. A hole drilling step of drilling a hole for a pillar, a post installation step of inserting the first and second stakes into the perforated post holes, respectively, and the upper connection portion of the first and second stakes A binding step of connecting using a binding means; an excavation step of excavating the ground so that one side of the first pillar is exposed while the first and second pillars are connected, and the exposed first pillar and Includes; Including, the second holding pile is divided into a drawing portion and a fixed portion formed by temporary welding (假接) a fixing portion at the lower end of the second pillar pile, and the second In the column type soiling method in which one or more wires are closely adhered to the outer circumferential surface of the holding pile and the exposed steel wire is connected to the fixed part by covering the end, the fixing part is temporarily bonded to the end of the second pile A steel pipe having a plurality of holes, a plurality of spaces formed inside the steel pipe, a binding line connecting and fixing several spacers inside the steel pipe, and at least one steel wire inserted into the inside of the steel pipe and covered by a wire and exposed Including, wherein, by pouring concrete on the outside of the steel pipe, the concrete is evenly poured into the inside and outside of the steel pipe through the hole in the steel pipe, and the holding part and the steel wire inserted therein are firmly cured. Has been provided.
이러한 구성의 경우 제1지주말뚝과 제2지주말뚝을 각각 경사지게 설치하여 상단이 서로 만나도록 한 것으로 시공성이 떨어지고, 장소가 협소한 도심지역에서 경사진 제1지주말뚝과 제2지주말뚝을 시공하는 지주구멍을 천공하기 위한 공간확보에 어려움이 있어 현장 적용에 어려움이 있었다.In this configuration, the first and second stakes are installed in an inclined manner so that the tops meet each other, so constructability is poor, and the construction of the inclined first and second stakes in an urban area where the space is narrow. There was a difficulty in securing the space for drilling the post hole, so it was difficult to apply it to the field.
이에 본 발명자는 상기한 종래 흙막이 공법을 장소가 협소한 도심지역 작용에 어려움이 있음에 이를 해결코자 본 발명을 연구 개발한 것이다.Accordingly, the present inventor has researched and developed the present invention in order to solve this problem because the conventional earth-blocking method has difficulty in functioning in an urban area with a narrow place.
즉, 본 발명에서는 터파기 경계에 지주말뚝을 세우고, 그 후방으로 어스앵커를 설치하여 지주말뚝에 지지되도록 설치한 어스앵커의 와이어 또는 강봉을 인장되게 하여 터파기 쪽에 별도의 지보재를 설치하지 않아도 지주말뚝이 터파기 작업공간으로 넘어지거나 붕괴되는 등의 염려가 없도록 함으로 해서 도심의 좁은 공간 내에서도 안전한 터파기 작업을 저비용으로 수월하게 제공할 수 있는 앵커 인장식 흙막이 구조 및 흙막이 공법을 제공코자 하는 것이다.In other words, in the present invention, a post pile is erected at the boundary of the trench, and the wire or steel bar of the earth anchor installed to be supported by the post pile is tensioned by installing an earth anchor to the rear of the trench. The goal is to provide an anchor tension-type soil barrier structure and a soil barrier construction method that can easily provide safe excavation work at low cost even within a narrow urban area by preventing the risk of the piles falling or collapsing into the excavation work area.
과제 해결 수단으로 본 발명에서는 첫째 터파기 경계에 설치되는 지주말뚝과; 상기 지주말뚝의 바깥쪽으로 지주말뚝 보다 깊은 심도로 시공되는 앵커가 하단에 구비된 와이어 또는 강봉을 포함하는 어스앵커와; 상기 지주말뚝 바깥쪽으로 위치하도록 지주말뚝의 상단에 일단을 고정한 수평지지부재와; 상기 수평지지부재에 직각으로 안치 결합되어 인장공간을 제공하는 한 쌍의 앵커지지대와; 상기 앵커지지대에 안치된 상태에서 인장공간을 통해서 인출되는 상기 와이어 또는 강봉을 인장하는 앵커브래킷을 포함하는 것을 특징으로 한다.In the present invention as a means of solving the problem, the first post pile installed at the boundary of the trench; An earth anchor including a wire or steel bar provided at the lower end of the anchor installed at a depth greater than that of the post pile to the outside of the post pile; A horizontal support member fixing one end to the upper end of the post pile so as to be positioned outside the post pile; A pair of anchor supports installed at right angles to the horizontal support member to provide a tensile space; It characterized in that it comprises an anchor bracket for tensioning the wire or steel bar drawn out through the tension space in a state placed in the anchor support.
둘째 터파기 경계에 설치되는 지주말뚝과; 상기 지주말뚝의 바깥쪽으로 지주말뚝 보다 깊은 심도로 시공되는 앵커가 하단에 구비된 와이어 또는 강봉을 포함하는 어스앵커와; 상기 지주말뚝 바깥쪽으로 위치하도록 지주말뚝의 상단에 일단을 고정한 수평지지부재와; 상기 수평지지부재에 직각으로 안치 결합되는 앵커지지대와; 상기 앵커지지대에 형성된 인장용 구멍을 인출되는 상기 와이어 또는 강봉을 인장하도록 앵커지지대에 설치한 앵커인장용 콘을 포함하는 것을 특징으로 한다.Second, a post pile installed at the boundary of the trench; An earth anchor including a wire or steel bar provided at the lower end of the anchor installed at a depth greater than that of the post pile to the outside of the post pile; A horizontal support member fixing one end to the upper end of the post pile so as to be positioned outside the post pile; An anchor support mounted at a right angle to the horizontal support member; It characterized in that it comprises a cone for anchor tension installed on the anchor support to tension the wire or steel bar drawn out through the tensioning hole formed in the anchor support.
셋째 상기 와이어 또는 강봉은 앵커에서 지주말뚝 쪽으로 점차 거리가 가까워지도록 경사지게 설치한 것을 특징으로 한다.Third, the wire or steel rod is characterized in that it is installed in an inclined manner so that the distance from the anchor to the stake pile gradually approaches.
넷째 상기 와이어 또는 강봉은 앵커에서 분리 가능하도록 구성한 것을 특징으로 한다.Fourth, the wire or steel bar is characterized in that it is configured to be detachable from the anchor.
다섯째 터파기 경계에 지주구멍을 천공하고 지주말뚝을 근입하는 지주말뚝 설치단계와; 상기 지주말뚝의 바깥쪽으로 지주말뚝 보다 깊은 심도로 앵커구멍을 천공하고 지중에 앵커를 성형하며 아울러 와이어 또는 강봉의 하단을 앵커에 고정하여 수직 또는 앵커에서 지주말뚝 쪽으로 점차 거리가 가까워지도록 경사지게 인장되도록 하는 어스앵커 설치단계와; 상기 지주말뚝의 상단에 일단이 고정되도록 지주말뚝 바깥쪽으로 위치하게 수평지지부재를 설치하는 수평지지부재 설치단계와; 상기 수평지지부재의 상측으로 수평지지부재와 직각으로 한 쌍의 앵커지지대를 안치 결합하여 인장공간이 제공되도록 하는 앵커지지대 설치단계와; 앵커지지대 사이에 형성된 인장공간으로 인출되는 와이어 또는 강봉을 인장하도록 앵커지지대에 앵커브래킷을 안치하는 앵커브래킷 설치단계와; 상기 와이어 또는 강봉을 앵커브래킷에 결합하여 인장하는 인장단계를 포함하는 것을 특징으로 한다.A fifth step of installing a post pile in which a post hole is drilled at the boundary of the trench and a post pile is inserted; An anchor hole is drilled to the outside of the pillar pile to a deeper depth than the pillar pile, and the anchor is formed in the ground, and the lower end of the wire or steel bar is fixed to the anchor so that the distance from the vertical or anchor to the pillar pile is gradually approached. Earth anchor installation step; A horizontal support member installation step of installing a horizontal support member positioned outside the post pile so that one end is fixed to the upper end of the post pile; An anchor support installation step of installing and coupling a pair of anchor supports to the upper side of the horizontal support member at a right angle to the horizontal support member to provide a tension space; An anchor bracket installation step of placing the anchor bracket on the anchor support to tension the wire or steel bar drawn out into the tensioning space formed between the anchor supports; It characterized in that it comprises a tensioning step of bonding the wire or steel bar to the anchor bracket and tensioning.
여섯째 상기 인장단계는 터파기가 일정 깊이로 이루어진 후 적어도 한번 이상 더 행하여 지주말뚝을 인장하는 와이어 또는 강봉이 항상 인장 상태를 유지할 수 있도록 한 것을 특징으로 한다.Sixth, the tensioning step is characterized in that the trenching is performed at least once more after the excavation is made to a certain depth so that the wire or steel bar for tensioning the post pile can always maintain the tensioned state.
본 발명에서 제공하는 앵커 인장식 흙막이 구조 및 흙막이 공법을 사용하는 경우 하기와 같은 효과가 있다.In the case of using the anchor tension type retaining structure and the retaining method provided by the present invention, there are the following effects.
-앵커가 지주말뚝 보다 깊음 심도로 설치된 상태로 제공되며, 앵커와 결합된 와이어 또는 강봉이 지주말뚝 상단을 인장하여 터파기 작업공간 바깥쪽으로 당기게 되므로 지주말뚝이 터파기 공간 쪽으로 넘어지거나 붕괴되는 등의 염려를 일소할 수 있다.-The anchor is provided in a state that is installed at a deeper depth than the pillar pile, and the wire or steel bar combined with the anchor stretches the top of the pillar pile and pulls it to the outside of the excavation work space. Can be wiped out.
- 터파기 쪽에 별도의 지보재나 띠장 등의 설치를 최소화 할 수 있으므로 작업공간 확보가 용이하며, 작업성을 향상시킬 수 있다.-It is easy to secure work space and improve workability as it can minimize the installation of separate support materials or strips on the excavation side.
-좁은 공간 내에서 어스앵커 시공이 가능하므로, 도심의 좁은 공간에서의 공사비용을 대폭 절감할 수 있다.-As earth anchor construction is possible in a narrow space, construction costs in a narrow space in the city center can be drastically reduced.
도 1은 본 발명에서 제공하는 앵커 인장식 흙막이 구조의 바람직한 예를 보인 사시도
도 2는 도 1의 평면도
도 3은 도 1의 측단면도
도 4는 본 발명 앵커 인장식 흙막이 구조에서 와이어 또는 강봉을 경사지게 설치한 예를 보인 측단면도
도 5는 본 발명 앵커 인장식 흙막이 구조에서 하나의 앵커지지대를 설치한 예를 보인 측단면도
도 6은 본 발명에 제공하는 앵커 인장식 흙막이 공법에 따른 시공단계를 보인 순서도1 is a perspective view showing a preferred example of the anchor tension retaining structure provided by the present invention
Figure 2 is a plan view of Figure 1
Figure 3 is a side cross-sectional view of Figure 1
4 is a side cross-sectional view showing an example in which a wire or steel bar is installed in an inclined manner in the present invention anchor tension type retaining structure
Figure 5 is a side cross-sectional view showing an example of installing one anchor support in the present invention anchor tension retaining structure
Figure 6 is a flow chart showing the construction step according to the anchor tension type retaining method provided in the present invention
이하 본 발명에서 제공하는 앵커 인장식 흙막이 구조 및 흙막이 공법의 바람직한 실시례를 첨부 도면에 의거하여 설명한다.Hereinafter, a preferred embodiment of the anchor tension type retaining structure and the retaining method provided by the present invention will be described with reference to the accompanying drawings.
도 1은 본 발명에서 제공하는 앵커 인장식 흙막이 구조의 바람직한 예를 보인 사시도를 도시한 것이고, 도 2는 도 1의 평면도, 도 3은 도 1의 측단면도를 각각 도시한 것이다.1 is a perspective view showing a preferred example of the anchor tension type retaining structure provided by the present invention, FIG. 2 is a plan view of FIG. 1, and FIG. 3 is a side cross-sectional view of FIG.
토목공사나 건축공사 현장에서 통상 터파기를 할 때 터파기 할 경계에 라인을 긋고, 이 라인을 따라 일정간격으로 지주구멍을 천공하여 H빔 구성의 지주말뚝(2)을 설치하고, 지주말뚝(2)들 사이에는 토류판(3)을 끼워 토사가 터파기 지역으로 유입되는 것을 차단하게 되는데, 이때 종래에는 지주말뚝(2)이 터파기 공간으로 붕괴되는 등의 위험성을 해소할 수 있도록 터파기 공사구간 쪽에 많은 수의 지보재(Strut, Earth Anchor, Raker 등)를 사용하게 되는데, 본 발명에서는 이와 같은 문제점을 해결할 수 있도록 앵커 인장식 흙막이 구조(1)를 개발한 것이다.When digging in a civil engineering or building construction site, a line is drawn at the boundary to be dug, and a pillar hole is drilled at regular intervals along this line to install a pillar pile (2) in an H-beam configuration, and a pillar pile (2). An earth plate (3) is inserted between the fields to block the inflow of earth and sand into the excavation area. In this case, in this case, it is located on the side of the excavation construction section so as to eliminate the risk of collapse of the pillar pile (2) into the excavation area A large number of support materials (Strut, Earth Anchor, Raker, etc.) are used. In the present invention, an anchor tension type retaining structure (1) has been developed to solve such a problem.
특히 본 발명에서 제공하는 앵커 인장식 흙막이 구조(1)는 도심의 협소한 작업공간에서도 효과적으로 터파기가 제공되도록 한 것으로, 터파기 경계를 따라 설치되는 지주말뚝(2)의 바깥쪽으로 지주말뚝(2) 보다 깊은 심도로 앵커(41)를 시공하고, 이 앵커(41)에 하단이 결합된 와이어 또는 강봉(42)을 지상으로 인출하는 구성의 어스앵커(4)를 적용하여 지주말뚝(2)의 후방에 위치하게 한다.In particular, the anchor tension-type earth retaining structure (1) provided by the present invention is to provide effective digging even in a narrow working space in the city center, and to the outside of the post pile (2) installed along the digging boundary, the post pile (2) The
이때 앵커(41)는 지주말뚝(2)의 바깥쪽 또는 지주말뚝(2)과 지주말뚝(2) 사이의 바깥쪽에 설치할 수 있으며, 바람직하기로는 지주말뚝(2)과 지주말뚝(2) 사이의 바깥쪽에 위치되게 한다. 또한 상기 앵커(41)에 하단이 결합된 와이어 또는 강봉(42)은 앵커(41)에 일체로 하단이 고정되도록 구성하거나, 분리 가능한 구조로 결합할 수 있다.At this time, the
상기 와이어 또는 강봉(42)은 도 4에 도시된 바와 같이 앵커(41)에서 지주말뚝(2) 쪽으로 점차 거리가 가까워지도록 경사지게 설치한다. 이러한 와이어 또는 강봉(42)의 설치는 지주말뚝(2)의 인장을 보다 안정적으로 제공할 수 있다.The wire or
상기 지주말뚝(2)의 상단에는 터파기 경계의 바깥쪽으로 향하도록 수평지지부재(5)가 설치된다. 수평지지부재(5)는 지주말뚝(2)의 위쪽이나 상단 후방에 선택적으로 결합될 수 있으며, 보강리브(51)를 이용하여 수평지지부재(5)를 보강할 수 있다.A
상기 수평지지부재(5)의 설치는 지주말뚝(2)의 높이를 일정하게 수평으로 정리한 상태에서 동일한 높이에서 설치하여 수평상태를 제공할 수 있도록 한다.The
상기와 같이 설치되는 수평지지부재(5)의 상측으로는 한 쌍의 앵커지지대(6)가 설치된다. 앵커지지대(6)는 수평지지부재(5)에 직각으로 안치 결합되며, 2개의 앵커지지대(6) 사이에 인장공간(7)이 제공될 수 있도록 한다.A pair of
그리고 상기 한 쌍의 앵커지지대(6) 상측으로는 앵커(41)에 하단이 결합된 와이어 또는 강봉(42)의 상단에 위치되도록 앵커브래킷(8)을 설치하고, 인장공간(7)을 통해서 인출되는 상기 와이어 또는 강봉(42)을 인장할 수 있도록 구성한다.And an anchor bracket (8) is installed so that the upper end of the pair of anchor supports (6) is located at the upper end of the wire or steel bar (42) with the lower end coupled to the anchor (41), and is drawn out through the tension space (7). It is configured to be able to tension the wire or steel bar (42).
상기 앵커브래킷(8)은 구체적으로 도시하고 있지는 않았지만 와이어 또는 강봉(42)을 인장 후 클램핑할 수 있는 앵커인장용 콘이 내장된 구성으로, 공지된 다양한 제품들을 선택하여 사용하면 된다.The
도 5는 본 발명 앵커 인장식 흙막이 구조에서 하나의 앵커지지대를 설치한 예를 보인 측단면도를 도시한 것이다.Figure 5 is a side cross-sectional view showing an example of installing one anchor support in the present invention anchor tension type retaining structure.
이는 수평지지부재(5)의 상측으로는 하나의 앵커지지대(6)를 설치하고 이 설치되어 인장용 구멍(6a)을 천공한 후 그 상측으로 앵커인장용 콘(9)을 설치하여 인장용 구멍(6a)을 통해서 인출되는 상기 와이어 또는 강봉(42)을 인장할 수 있도록 구성한 것이다.For this, an
도 6은 본 발명에 제공하는 앵커 인장식 흙막이 공법에 따른 시공단계를 보인 순서도를 도시한 것이다.Figure 6 shows a flow chart showing the construction step according to the anchor tension type retaining method provided in the present invention.
본 발명에 제공하는 앵커 인장식 흙막이 공법은 1)지주말뚝 설치단계(S10)와, 2)어스앵커 설치단계(S20)와, 3)수평지지부재 설치단계(S30)와, 4)앵커지지대 설치단계(S40)와, 5)앵커브래킷 설치단계(S50)와, 6)인장단계(S60)를 순차적으로 행하여 이루어지는 것으로, 이하에서 이들 방법을 보다 구체적으로 설명한다.The anchor tension type earthen blocking method provided in the present invention includes: 1) a post pile installation step (S10), 2) an earth anchor installation step (S20), 3) a horizontal support member installation step (S30), and 4) an anchor support installation Steps (S40), 5) anchor bracket installation step (S50), and 6) tensioning step (S60) are sequentially performed, and these methods will be described in more detail below.
1)지주말뚝 설치단계(S10)1) Post pile installation step (S10)
설계 및 측량 작업으로 터파기 경계에 라인을 긋고, 이 라인을 따라 오거머신 등을 이용하여 일정한 간격으로 지주구멍을 일정깊이로 천공하고, 오거를 인발함과 동시에 지주말뚝(2)을 근입하는 방법으로 지주말뚝(2)을 설치한다.By designing and surveying, a line is drawn at the boundary of the excavation, and a post hole is drilled to a certain depth at regular intervals using an auger machine along this line, and the auger is pulled out and the post pile (2) is inserted. Install the post pile (2) by the method.
지주구멍을 천공할 때 지하수 등으로 인해 토사가 유실되는 지역 등에서는 콘크리트 구성의 흙막이 벽체를 시공하는 방법이 바람직하다.In areas where soil is lost due to groundwater, etc. when drilling the pillar hole, it is preferable to construct a concrete wall covering.
2)어스앵커 설치단계(S20)2) Earth anchor installation step (S20)
상기와 같이 터파기 경계를 따라 지주말뚝(2)이 설치되면, 지주말뚝(2)의 바깥쪽으로 어스앵커(4)를 설치한다.When the post pile (2) is installed along the digging boundary as described above, the earth anchor (4) is installed outside the post pile (2).
지주말뚝(2)은 터파기 심도에 부합하는 깊이로 설치되나, 어스앵커(4)는 암반층이나 자갈층 등에 하단이 지주말뚝(2) 보다 깊은 심도로 앵커구멍을 천공하고, 지중에 앵커(41)를 성형하여 지지력을 제공할 수 있도록 하며, 아울러 와이어 또는 강봉(42)의 하단을 앵커(41)에 설치한다.The post pile (2) is installed to a depth corresponding to the depth of excavation, but the earth anchor (4) drills an anchor hole at a depth deeper than the post pile (2) at the bottom of the rock layer or gravel layer, and the anchor (41) in the ground. It is formed to provide a supporting force, and the lower end of the wire or
이때 와이어 또는 강봉(42)은, 도 3에 도시된 바와 같이 앵커(41)에서 수직으로 인장되게 설치하거나, 도 4와 같이 앵커(41)에서 지주말뚝(2) 쪽으로 점차 거리가 가까워지도록 경사지게 인장되도록 설치할 수 있다.At this time, the wire or
또한 상기 와이어 또는 강봉(42)은 앵커(41)에 하단이 고정되도록 설치하거나 분리형으로 설치하여 터파기 공사 등이 완료된 상태에서, 와이어 또는 강봉(42)을 철거할 수 있도록 구성한다.In addition, the wire or
3)수평지지부재 설치단계(S30)3) Horizontal support member installation step (S30)
수평지지부재 설치단계(S30)는 상기 지주말뚝(2)의 상단에 일단이 고정되도록 지주말뚝(2) 바깥쪽으로 위치하게 수평지지부재(5)를 설치하는 단계이다.The horizontal support member installation step (S30) is a step of installing the
수평지지부재(5)는 지주말뚝(2)의 상부에 용접하여 일체형으로 결합하거나, 상단 후방에 용접하여 일체형으로 결합토록 하면 된다.The
수평지지부재(5)를 설치하기 전에 지주말뚝(2)을 동일한 높이로 정리한 후해 행해야 하며, 수평지지부재(5)를 지지하기 위한 보강리브(51)를 부가 설치할 수 있음은 당연하다.Before installing the
4)앵커지지대 설치단계(S40)4) Anchor support installation step (S40)
상기와 같이 지주말뚝(2)에 수평지지부재(5)를 설치한 상태에서 수평지지부재(5)의 상측으로 앵커지지대(6)를 안치하여 결합한다.As described above, in the state where the
앵커지지대(6)는 지주말뚝(2)과 최대한 멀리 떨어지도록 2열로 수평지지부재(5)에 결합되며, 앵커지지대(6) 사이에는 인장공간(7)을 형성하여 상기 어스앵커 설치단계(S20)에서 지상으로 인출되어 있는 와이어 또는 강선이 인장공간(7)으로 내입되게 한다.The anchor support (6) is coupled to the horizontal support member (5) in two rows so as to be as far away as possible from the post pile (2), and a tension space (7) is formed between the anchor support (6), and the earth anchor installation step (S20) The wire or steel wire drawn out from) to the ground is inserted into the tension space (7).
또한 상기 앵커지지대(6)는 도 5에 도시된 바와 같이 일정 간격으로 인장용 구멍(6a)이 천공된 싱글 타입으로 제공할 수 있음은 당연하다.In addition, it is natural that the
5)앵커브래킷 설치단계(S50)5) Anchor bracket installation step (S50)
상기와 같이 수평지지대 상측으로 싱글 또는 2열의 앵커지지대(6)가 설치되면, 인장공간(7)으로 인출되는 와이어 또는 강봉(42)의 상부에 위치되도록 앵커브래킷(8)을 앵커지지대(6) 상측에 안차한다.When a single or two rows of anchor supports 6 are installed above the horizontal support as described above, the
6)인장단계(S60)6) Tensile step (S60)
인장단계(S60)는 상기와 같이 인장공간(7)으로 인출되는 와이어 또는 강봉(42)을 앵커지지대(6)에 안치되어 있는 앵커브래킷(8)에 결합하여 인장하는 단계이다.The tensioning step (S60) is a step of combining the wire or
상기 인장단계(S60)는 터파기가 일정 깊이로 이루어진 후 적어도 한번 이상 더 행하여 지주말뚝(2)을 인장하는 와이어 또는 강봉(42)이 항상 인장 상태를 유지할 수 있도록 함이 바람직하다.The tensioning step (S60) is preferably performed at least once more after the excavation is made to a certain depth so that the wire or
도면중 미설명 부호 9는 지주말뚝(2) 내측으로 터파기한 상태에서 지주말뚝(2)에 수평으로 설치한 띠장을 도시한 것이다.In the drawings, unexplained reference numeral 9 denotes a strip length installed horizontally on the
이상과 같이 제공되는 본 발명의 앵커 인장식 흙막이 구조(1) 및 흙막이 공법을 사용하는 경우 좁은 공간 내에서 앵커(41) 시공이 가능하므로, 도심의 좁은 공간에서의 공사비용을 대폭 절감할 수 있으며, 터파기 쪽에 별도의 지보재나 띠장 등의 설치를 최소화 할 수 있으므로 작업공간 확보가 가능하여 작업 효율성을 극대화 할 수 있으면서도 지주말뚝(2)이 터파기 공간 쪽으로 넘어지거나 붕괴되는 등의 염려를 일소할 수 있게 되는 것이다.In the case of using the anchor tension type retaining structure (1) and the retaining method of the present invention provided as described above, since the
본 발명의 상세한 설명에서는 구체적인 실시례에 관해 설명하고 있으나, 본 발명의 범주에서 벗어나지 않는 한도 내에서 다양한 변형이 가능함은 물론이다. 그러므로 본 발명의 보호 범위는 설명된 실시례에 국한되어 정해져서는 안 되며, 후술하는 청구범위 뿐만 아니라 균등한 것들에 의해 정해져야 한다.In the detailed description of the present invention, specific embodiments are described, but various modifications are possible without departing from the scope of the present invention. Therefore, the scope of protection of the present invention should not be defined by being limited to the described embodiments, and should not be determined by the claims to be described later as well as equivalents.
1:앵커 인장식 흙막이 구조 2:지주말뚝
3:토류판 4:어스앵커
41:앵커 42:와이어 또는 강봉
5:수평지지부재 51:보강리브
6:앵커지지대 6a:인장용 구멍
7:인장공간 8:앵커브래킷
S10:지주말뚝 설치단계
S20:어스앵커 설치단계
S30:수평지지부재 설치단계
S40:앵커지지대 설치단계
S50:앵커브래킷 설치단계
S60:인장단계1: Anchor tension type earthen barrier structure 2: Pillars
3: Earth version 4: Earth anchor
41: anchor 42: wire or steel bar
5: horizontal support member 51: reinforcing rib
6: Anchor support 6a: Tension hole
7: Tensile space 8: Anchor bracket
S10: post pile installation step
S20: Earth anchor installation step
S30: horizontal support member installation step
S40: Anchor support installation step
S50: Anchor bracket installation step
S60: Tension stage
Claims (6)
상기 지주말뚝(2)의 바깥쪽으로 지주말뚝(2) 보다 깊은 심도로 시공되는 앵커(41)가 하단에 구비된 와이어 또는 강봉(42)을 포함하는 어스앵커(4)와;
상기 지주말뚝(2) 바깥쪽으로 위치하도록 지주말뚝(2)의 상단에 일단을 고정한 수평지지부재(5)와;
상기 수평지지부재(5)에 직각으로 안치 결합되어 인장공간(7)을 제공하는 한 쌍의 앵커지지대(6)와;
상기 앵커지지대(6)에 안치된 상태에서 인장공간(7)을 통해서 인출되는 상기 와이어 또는 강봉(42)을 인장하는 앵커브래킷(8)을 포함하는 것을 특징으로 하는 앵커 인장식 흙막이 구조.
A post pile (2) installed at the boundary of the excavation;
An earth anchor 4 including a wire or steel bar 42 provided at the lower end of the anchor 41, which is constructed to the outside of the pillar pile 2 at a depth deeper than the pillar pile 2;
A horizontal support member (5) fixing one end to the upper end of the post pile (2) so as to be positioned outside the post pile (2);
A pair of anchor supports (6) mounted at right angles to the horizontal support member (5) to provide a tension space (7);
An anchor tension type retaining structure, characterized in that it comprises an anchor bracket (8) for tensioning the wire or steel bar (42) drawn out through the tensioning space (7) while being placed in the anchor support (6).
상기 지주말뚝(2)의 바깥쪽으로 지주말뚝(2) 보다 깊은 심도로 시공되는 앵커(41)가 하단에 구비된 와이어 또는 강봉(42)을 포함하는 어스앵커(4)와;
상기 지주말뚝(2) 바깥쪽으로 위치하도록 지주말뚝(2)의 상단에 일단을 고정한 수평지지부재(5)와;
상기 수평지지부재(5)에 직각으로 안치 결합되는 앵커지지대(6)와;
상기 앵커지지대(6)에 형성된 인장용 구멍(6a)을 인출되는 상기 와이어 또는 강봉(42)을 인장하도록 앵커지지대(6)에 설치한 앵커인장용 콘(9)을 포함하는 것을 특징으로 하는 앵커 인장식 흙막이 구조.
A post pile (2) installed at the boundary of the excavation;
An earth anchor 4 including a wire or steel bar 42 provided at the lower end of the anchor 41, which is constructed to the outside of the pillar pile 2 at a depth deeper than the pillar pile 2;
A horizontal support member (5) fixing one end to the upper end of the post pile (2) so as to be positioned outside the post pile (2);
An anchor support (6) mounted at a right angle to the horizontal support member (5);
An anchor, characterized in that it comprises an anchor tension cone (9) installed on the anchor support (6) to tension the wire or steel bar (42) from which the tensioning hole (6a) formed in the anchor support (6) is drawn out Tension type earth protection structure.
상기 와이어 또는 강봉(42)은 앵커(41)에서 지주말뚝(2) 쪽으로 점차 거리가 가까워지도록 경사지게 설치한 것을 특징으로 하는 앵커 인장식 흙막이 구조.
The method according to claim 1 or 2;
The wire or steel bar 42 is an anchor tension type retaining structure, characterized in that it is installed obliquely so that the distance from the anchor 41 to the holding pile (2) gradually approaches.
상기 와이어 또는 강봉(42)은 앵커(41)에서 분리 가능하도록 구성한 것을 특징으로 하는 앵커 인장식 흙막이 구조.
The method according to claim 1 or 2;
The wire or steel rod 42 is an anchor tension type retaining structure, characterized in that configured to be detachable from the anchor (41).
상기 지주말뚝(2)의 바깥쪽으로 지주말뚝(2) 보다 깊은 심도로 앵커구멍을 천공하고 지중에 앵커(41)를 성형하며 아울러 와이어 또는 강봉(42)의 하단을 앵커(41)에 고정하여 수직 또는 앵커(41)에서 지주말뚝(2) 쪽으로 점차 거리가 가까워지도록 경사지게 인장되도록 하는 어스앵커 설치단계(S20)와;
상기 지주말뚝(2)의 상단에 일단이 고정되도록 지주말뚝(2) 바깥쪽으로 위치하게 수평지지부재(5)를 설치하는 수평지지부재 설치단계(S30)와;
상기 수평지지부재(5)의 상측으로 수평지지부재(5)와 직각으로 한 쌍의 앵커지지대(6)를 안치 결합하여 인장공간(7)이 제공되도록 하는 앵커지지대 설치단계(S40)와;
앵커지지대(6) 사이에 형성된 인장공간(7)으로 인출되는 와이어 또는 강봉(42)을 인장하도록 앵커지지대(6)에 앵커브래킷(8)을 안치하는 앵커브래킷 설치단계(S50)와;
상기 와이어 또는 강봉(42)을 앵커브래킷(8)에 결합하여 인장하는 인장단계(S60)를 포함하는 것을 특징으로 하는 앵커 인장식 흙막이 공법.
A post pile installation step (S10) of drilling a post hole at the boundary of the dug and inserting the post pile (2);
An anchor hole is drilled to the outside of the pillar pile (2) to a deeper depth than the pillar pile (2), and the anchor 41 is formed in the ground, and the lower end of the wire or steel bar 42 is fixed to the anchor 41 to vertically Or an earth anchor installation step (S20) to be tensioned obliquely so that the distance from the anchor 41 to the post pile 2 gradually approaches;
A horizontal support member installation step (S30) of installing a horizontal support member 5 to be positioned outward of the post pile 2 so that one end is fixed to the upper end of the post pile 2;
An anchor support installation step (S40) of installing and coupling a pair of anchor supports (6) at a right angle to the horizontal support member (5) above the horizontal support member (5) to provide a tension space (7);
An anchor bracket installation step (S50) of placing the anchor bracket 8 on the anchor support 6 so as to tension the wire or steel bar 42 drawn out into the tension space 7 formed between the anchor support 6;
Anchor tension type retaining method comprising a tensioning step (S60) of bonding and tensioning the wire or steel rod (42) to the anchor bracket (8).
상기 인장단계(S60)는 터파기가 일정 깊이로 이루어진 후 적어도 한번 이상 더 행하여 지주말뚝(2)을 인장하는 와이어 또는 강봉(42)이 항상 인장 상태를 유지할 수 있도록 한 것을 특징으로 하는 앵커 인장식 흙막이 공법.The method according to claim 5;
The tensioning step (S60) is performed at least once more after the excavation is made to a certain depth so that the wire or steel bar 42 for tensioning the post pile 2 always maintains a tensile state. Method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020190048455A KR20200124949A (en) | 2019-04-25 | 2019-04-25 | Anchor Tension way sheathing structure and sheathing method of construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020190048455A KR20200124949A (en) | 2019-04-25 | 2019-04-25 | Anchor Tension way sheathing structure and sheathing method of construction |
Publications (1)
Publication Number | Publication Date |
---|---|
KR20200124949A true KR20200124949A (en) | 2020-11-04 |
Family
ID=73571422
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020190048455A Ceased KR20200124949A (en) | 2019-04-25 | 2019-04-25 | Anchor Tension way sheathing structure and sheathing method of construction |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR20200124949A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113107019A (en) * | 2021-03-30 | 2021-07-13 | 建研地基基础工程有限责任公司 | Pre-buried anchor rod connecting structure passing through pre-built building and construction method thereof |
KR102315422B1 (en) | 2020-12-21 | 2021-10-19 | 최진호 | Pile reinforcement unit for Temporary earth retaining walls using a Turnover racket and an Anchor and Temporary earth retaining walls having this same |
KR20230030532A (en) | 2022-08-19 | 2023-03-06 | 오용환 | Thumb pile using guide bracket and ground anchor and construction method of retaining temporary facility using the same |
KR20230147400A (en) * | 2022-04-14 | 2023-10-23 | 김상효 | Retaining wall structure using prestressed reinforcing pile and construction method thereof |
KR102648051B1 (en) | 2023-11-20 | 2024-03-15 | 주식회사 조은이엔지 | Self-supporting structure with back-row type bracing device and its construction method |
CN118292465A (en) * | 2024-06-05 | 2024-07-05 | 太原理工大学 | Combined flexible self-balancing foundation pit support device |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100964993B1 (en) | 2008-02-04 | 2010-06-21 | 코오롱건설주식회사 | Thorough 2-row Thumb Pile Retaining |
KR101262357B1 (en) | 2011-03-25 | 2013-05-08 | 임재욱 | Inclined Earth Retaining Structure Method |
-
2019
- 2019-04-25 KR KR1020190048455A patent/KR20200124949A/en not_active Ceased
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100964993B1 (en) | 2008-02-04 | 2010-06-21 | 코오롱건설주식회사 | Thorough 2-row Thumb Pile Retaining |
KR101262357B1 (en) | 2011-03-25 | 2013-05-08 | 임재욱 | Inclined Earth Retaining Structure Method |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR102315422B1 (en) | 2020-12-21 | 2021-10-19 | 최진호 | Pile reinforcement unit for Temporary earth retaining walls using a Turnover racket and an Anchor and Temporary earth retaining walls having this same |
CN113107019A (en) * | 2021-03-30 | 2021-07-13 | 建研地基基础工程有限责任公司 | Pre-buried anchor rod connecting structure passing through pre-built building and construction method thereof |
KR20230147400A (en) * | 2022-04-14 | 2023-10-23 | 김상효 | Retaining wall structure using prestressed reinforcing pile and construction method thereof |
KR20230030532A (en) | 2022-08-19 | 2023-03-06 | 오용환 | Thumb pile using guide bracket and ground anchor and construction method of retaining temporary facility using the same |
KR102648051B1 (en) | 2023-11-20 | 2024-03-15 | 주식회사 조은이엔지 | Self-supporting structure with back-row type bracing device and its construction method |
CN118292465A (en) * | 2024-06-05 | 2024-07-05 | 太原理工大学 | Combined flexible self-balancing foundation pit support device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR20200124949A (en) | Anchor Tension way sheathing structure and sheathing method of construction | |
KR101274974B1 (en) | Earth retaining wall and construction method thereof | |
US20110142550A1 (en) | Method for constructing a chair-type, self-supported earth retaining wall | |
KR101973565B1 (en) | Sheathing method for constructing both sheathing wall and cutoff collar by welding cutoff plate to phc pile with longitudinal plate | |
KR102234513B1 (en) | Block type reinforcement retaining wall structure and constructing method for the same | |
KR101241566B1 (en) | Method for Constructing Cap Beam Combined Wale For Retaining Wall | |
KR20170005991A (en) | soil retaining wall using PHC pile and its construction method | |
KR100967497B1 (en) | Method for constructing an underground structure | |
KR20140055639A (en) | A execution method of architecture beam | |
KR100933660B1 (en) | Masonry support structure and construction method | |
KR101176592B1 (en) | Earth retaining wall structure constructing method using prestressed tendon | |
KR100831332B1 (en) | Underground wall for civil engineering and construction method | |
KR101078080B1 (en) | Earth retaining wall and it's construction method using the precast pile and ground reinforcement | |
KR101021915B1 (en) | Order temporary construction method for earthquake construction | |
KR20120109418A (en) | Inclined earth retaining structure method | |
KR101054696B1 (en) | Top-down construction method for underground structure with slurry wall retained by slab diaphragm effect | |
KR101296857B1 (en) | Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same | |
KR20230130783A (en) | Self-supporting retaining structure and its construction method | |
KR102184900B1 (en) | Temporary retaining wall structure using circular steel pipe and construction method thereof | |
KR102490872B1 (en) | Reinforced earth retaining wall and construction method using tensile force of steel rod piles | |
KR102617795B1 (en) | Retaining wall system combine H-piles with steel reinforcement structure | |
KR100967496B1 (en) | Device for constructing an underground structure | |
KR102272494B1 (en) | Slope reinforcement structure using support and tension and Its Construction method | |
KR100673475B1 (en) | PC girder member for base frame frame, assembly structure and method of construction | |
KR20190002845U (en) | Braced wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PA0109 | Patent application |
Patent event code: PA01091R01D Comment text: Patent Application Patent event date: 20190425 |
|
PA0201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
PE0902 | Notice of grounds for rejection |
Comment text: Notification of reason for refusal Patent event date: 20200929 Patent event code: PE09021S01D |
|
PG1501 | Laying open of application | ||
E601 | Decision to refuse application | ||
PE0601 | Decision on rejection of patent |
Patent event date: 20201230 Comment text: Decision to Refuse Application Patent event code: PE06012S01D Patent event date: 20200929 Comment text: Notification of reason for refusal Patent event code: PE06011S01I |