JPH05295732A - Crosswise sheet pile removing method - Google Patents

Crosswise sheet pile removing method

Info

Publication number
JPH05295732A
JPH05295732A JP12824392A JP12824392A JPH05295732A JP H05295732 A JPH05295732 A JP H05295732A JP 12824392 A JP12824392 A JP 12824392A JP 12824392 A JP12824392 A JP 12824392A JP H05295732 A JPH05295732 A JP H05295732A
Authority
JP
Japan
Prior art keywords
sheet pile
horizontal sheet
piles
pile
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP12824392A
Other languages
Japanese (ja)
Other versions
JP2911016B2 (en
Inventor
Tatsuo Otsuka
達雄 大塚
Tadashi Takigasaki
正 瀧ケ崎
Tetsuo Kamiyama
鉄男 神山
Katsuro Wakabayashi
克郎 若林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
DAIWA TSUSHIN KENSETSU KK
Nippon Telegraph and Telephone Corp
Original Assignee
DAIWA TSUSHIN KENSETSU KK
Nippon Telegraph and Telephone Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by DAIWA TSUSHIN KENSETSU KK, Nippon Telegraph and Telephone Corp filed Critical DAIWA TSUSHIN KENSETSU KK
Priority to JP12824392A priority Critical patent/JP2911016B2/en
Publication of JPH05295732A publication Critical patent/JPH05295732A/en
Application granted granted Critical
Publication of JP2911016B2 publication Critical patent/JP2911016B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

PURPOSE:To remove crosswise sheet piles of sheathing wall, which is likely to cause depression of a road. CONSTITUTION:Steel piles 3 such as H-shape, etc., are struck in the ground, and between them 3 crosswise sheet piles 4 are set over in a laminate. At laminating, hook members 9 each having a hang-up member 10 are in advance fixed to the undermost sheet pile 4a. They 10 are coupled with the sheet piles 4 situated in the upper part using a backing strip. After constructing a sheathing wall as intended 1, the hang-up members 10 are pulled up followed by raising of the sheet piles 4 in the laminated state, and then the piles 4 are taken off one by one from the steel piles 3.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明はケーブル敷設用の地下構
造物の構築のため、土留壁として使用される横矢板の撤
去工法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for removing a horizontal sheet pile used as a retaining wall for constructing an underground structure for laying a cable.

【0002】[0002]

【従来の技術】土留壁として使用された横矢板を地中に
埋め殺した場合には、横矢板の経時的な腐食によって地
中に空洞が出来たり、横矢板が地中の水みちの形成の原
因となって道路陥没、地盤沈下等の原因となるばかりで
なく、将来的な新たな地下構造物の構築の際の障害とな
るため、土留壁が不要となった時点で横矢板を地中から
撤去する必要がある。
2. Description of the Related Art When a horizontal sheet pile used as a retaining wall is buried in the ground, cavities are formed in the ground due to corrosion of the horizontal sheet pile, or the horizontal sheet pile forms a water channel in the ground. Not only cause road collapse and ground subsidence, but also hinder the construction of new underground structures in the future. It is necessary to remove it from the inside.

【0003】ところで、かかる横矢板を用いた土留壁の
構築に関しては、従来、特公昭52−50449号公
報、実公昭61−33071号公報、実開公55−85
133号公報等に開示された技術がある。特公昭52−
50449号公報は山留壁として横矢板を使用するもの
であるが、この山留壁から横矢板を引き抜く旨の記載が
あるだけで、その具体的な撤去工法については開示され
ていない。又、実公昭61−33071号公報は埋め戻
し後の土砂流出防止のため、H鋼杭間に埋め殺し用の横
矢板を取り付けるものであり、横矢板の埋め殺しを示唆
するだけである。更に、実開公55−85133号公報
は山留用杭に関する技術であり、横矢板の撤去工法に関
しては、何等の記載がない。
By the way, as to the construction of the retaining wall using such a horizontal sheet pile, the Japanese Patent Publication No. 52-50449, Japanese Utility Model Publication No. 61-33071, and Japanese Utility Model Publication No. 55-85 have been used.
There is a technique disclosed in Japanese Patent No. 133, etc. Japanese Examined Sho 52-
Japanese Patent No. 50449 uses a horizontal sheet pile as a mountain retaining wall, but only describes that the horizontal sheet pile is pulled out from the mountain retaining wall, and does not disclose a concrete removing method. In addition, Japanese Utility Model Publication No. 61-33071 discloses that a horizontal sheet pile for burying is attached between H steel piles in order to prevent sediment outflow after backfilling, and only suggests burying of the horizontal sheet pile. Furthermore, Japanese Utility Model Publication No. 55-85133 is a technology relating to piles for mountain retaining, and there is no description about the method for removing the horizontal sheet pile.

【0004】[0004]

【発明が解決しようとする課題】従って、上述した従来
技術には、横矢板の撤去に関しての開示がなく、これら
の従来技術からは横矢板の撤去が不可能であり、依然と
して横矢板の埋め殺しに起因した諸問題は解決されてい
ないのが実情である。
Therefore, the above-mentioned prior art does not disclose the removal of the lateral sheet pile, and the lateral sheet pile cannot be removed from these prior arts, and the lateral sheet pile is still buried. The fact is that the problems caused by are not solved.

【0005】本発明は上記事情を考慮してなされたもの
であり、その目的は横矢板の埋め殺しに起因する道路陥
没、地盤沈下党の諸問題を解決した横矢板の撤去工法を
提供することにある。
The present invention has been made in view of the above circumstances, and an object thereof is to provide a method for removing a horizontal sheet pile that solves various problems of the road subsidence caused by the burying of the horizontal sheet pile and the ground subsidence party. It is in.

【0006】[0006]

【課題を解決するための手段】前記目的を達成するた
め、本発明は地中に打設された鋼杭に掛け渡される横矢
板の内、少なくとも最下段の横矢板に吊上げ部材が連結
されているフック部材を取り付けて横矢板を順次積層す
ると共に、前記吊上げ部材と上段部分の横矢板を結合
し、この状態で前記吊上げ部材を引き上げながら横矢板
を鋼杭間から取り外すことを特徴としている。
In order to achieve the above-mentioned object, the present invention has a lifting member connected to at least the lowermost horizontal sheet pile among the horizontal sheet piles that are stretched over steel piles that are driven into the ground. It is characterized in that the hook members are attached and the horizontal sheet piles are sequentially laminated, the lifting member and the horizontal sheet piles in the upper part are coupled, and in this state, the horizontal sheet piles are removed from between the steel piles while pulling up the lifting member.

【0007】[0007]

【作用】上記構成では、横矢板のフック部材に吊上げ部
材を係着し、同部材を引き上げると、積層状態の複数の
横矢板を同時に鋼杭に沿って上方に移動する。この時、
各横矢板は吊上げ部材に結合しているため、積層状態が
崩れることなく円滑に引き上げることが出来る。そし
て、横矢板の結合を解除することにより、横矢板を鋼杭
から1枚づつ取り外すことが出来る。
In the above structure, when the lifting member is attached to the hook member of the horizontal sheet pile and the member is pulled up, the plurality of stacked horizontal sheet piles are simultaneously moved upward along the steel pile. At this time,
Since each horizontal sheet pile is connected to the lifting member, the stacked state can be smoothly pulled up without breaking the stacked state. Then, the horizontal sheet piles can be removed one by one from the steel pile by releasing the connection of the horizontal sheet piles.

【0008】[0008]

【実施例】以下、本発明を図示する実施例に基づいて具
体的に説明する。尚、各実施例において、同一の要素は
同一の符号を付して対応させてある。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be specifically described below based on illustrated embodiments. In each embodiment, the same elements are designated by the same reference numerals and correspond to each other.

【0009】図1乃至図7は本発明の一実施例であり、
図1は土留壁1の構築状態を示す。土留壁1は地下構築
物2を両側から挟んだ状態で、その隣接位置に構築され
る。かかる土留壁1の構築は、地中にH型鋼等の鋼杭3
を所定間隔で打設或いは圧入した後、鋼杭3間に横矢板
4を掛け渡すことにより行なわれる。この横矢板4は鋼
杭3間に、順次積層されることにより土留壁として作用
するものであり、図示例においては、下側の土留壁群5
と、上側の土留壁群6とを備えている。図3は鋼杭3間
に横矢板4を掛け渡した状態を示し、横矢板4は鋼杭3
のフランジ部3aに沿って掛け渡され、その両端部と鋼
杭3のウェブ部3bとは一定の間隔を有している。本発
明はかかる間隔を利用して横矢板4を鋼杭3から取り外
すものである。
1 to 7 show an embodiment of the present invention.
FIG. 1 shows a construction state of the retaining wall 1. The retaining wall 1 is constructed at a position adjacent to the underground structure 2 with the underground structure 2 sandwiched from both sides. Construction of such retaining wall 1 is carried out by steel piles 3 such as H-section steel in the ground.
After placing or press-fitting at a predetermined interval, the cross sheet pile 4 is bridged between the steel piles 3. The horizontal sheet pile 4 acts as a soil retaining wall by being sequentially laminated between the steel piles 3. In the illustrated example, the lower soil retaining wall group 5 is used.
And the earth retaining wall group 6 on the upper side. FIG. 3 shows a state in which a horizontal sheet pile 4 is bridged between the steel piles 3, and the horizontal sheet pile 4 is a steel pile 3
Of the steel pile 3 and the web portion 3b of the steel pile 3 have a constant distance. The present invention utilizes this interval to remove the horizontal sheet pile 4 from the steel pile 3.

【0010】図1において、7は上下の土留壁群5、6
の離間部分に設けられた裏矢板であり、複数の横矢板4
を鋼杭3の外側のフランジ部3aに沿って積層されるこ
とにより構成される。8はこの裏矢板7と上部の土留壁
群6との間に設けられた角材である。
In FIG. 1, 7 is a group of upper and lower earth retaining walls 5, 6.
Is a back sheet pile provided in a separated portion of the
Are laminated along the outer flange portion 3a of the steel pile 3. Reference numeral 8 is a square bar provided between the back sheet pile 7 and the upper earth retaining wall group 6.

【0011】本実施例において、下側の土留壁群5の構
築に際し、最下段の横矢板4aにフック部材9を予め取
り付けるものである。このフック部材9は最下段の横矢
板4aに引っ掛ける等することで係合状態となる。かか
るフック部材9は図1及び図2に示すように、ワイヤ等
の長尺な吊上げ部材10が連結されている。そして、上
段に対して横矢板4を積層する際には、各横矢板4と吊
上げ部材10とを結合させる。この結合は横矢板が木材
の場合には、当部材の打ち込みや接着、鋼材の場合に
は、当部材の溶接等の適宜の手段で行なわれる。図1及
び図2において、符号11で示す部位はこの吊上げ部材
10と各横矢板4との結合部分である。尚、図示例にお
いては、一列の横矢板4に対して、夫々2本の吊上げ部
材10が設けられているが、この本数は特に限定される
ものではない。又、吊上げ部材10の上端部分は連結プ
レート12により連結されている。
In this embodiment, when the lower retaining wall group 5 is constructed, the hook member 9 is previously attached to the lowermost horizontal sheet pile 4a. The hook member 9 is brought into an engaged state by being hooked on the lowermost horizontal sheet pile 4a. As shown in FIGS. 1 and 2, the hook member 9 is connected to a long lifting member 10 such as a wire. Then, when laminating the horizontal sheet piles 4 on the upper stage, the respective horizontal sheet piles 4 and the lifting members 10 are coupled. When the horizontal sheet pile is made of wood, this connection is performed by appropriate means such as driving or bonding the member, and when it is steel, welding the member. In FIGS. 1 and 2, a portion indicated by reference numeral 11 is a connecting portion between the hoisting member 10 and each lateral sheet pile 4. In the illustrated example, two lifting members 10 are provided for each row of horizontal sheet piles 4, but the number is not particularly limited. Further, the upper end portion of the lifting member 10 is connected by a connecting plate 12.

【0012】以上のようにして土留壁1を構築した後の
横矢板4の撤去工法を図4乃至図7により、説明する。
これらの図において、13は対向した鋼杭3間に架設さ
れた梁部材であり、土圧によって鋼杭3が内方に倒れる
ことを防止している。先ず、図4に示すように、吊上げ
部材10の上端部分を連結している連結プレート12に
フックアーム14を掛合する。フックアーム14にはチ
ェーン15が連結されており、このチェーン15がクレ
ーン等の駆動手段(図示省略)に連結されている。そし
て、駆動手段を駆動して吊上げ部材10を引き上げる。
これにより、最下段の横矢板4aがフック部材9により
引き上げられるため、下側の土留壁群5は鋼杭3に沿っ
て上昇する。この時、格横矢板4は吊上げ部材10に結
合しているため、積層状態が崩れることなく円滑に引き
上げられる。そして、最上段の横矢板4が裏矢板7にま
で達したとき、その横矢板4と吊上げ部材10との結合
を解除した後、横矢板4と鋼杭3のウェブ部3bとの間
隔(図3参照)を利用して、図5に示すように、横矢板
4を鋼杭3から取り外す。以下、図6及び図7に示すよ
うに、土留壁群5を上昇させながら横矢板4を1枚づつ
鋼杭3から取り外し、下側の土留壁群5の撤去を完了す
る。以上の後、上側の土留壁群6及び裏矢板7について
は、埋め戻しながら横矢板4を1枚づつ鋼杭3から撤去
する。
A method of removing the horizontal sheet pile 4 after the soil retaining wall 1 is constructed as described above will be described with reference to FIGS. 4 to 7.
In these figures, 13 is a beam member installed between the steel piles 3 facing each other, and prevents the steel piles 3 from falling inward by earth pressure. First, as shown in FIG. 4, the hook arm 14 is engaged with the connecting plate 12 connecting the upper end portion of the lifting member 10. A chain 15 is connected to the hook arm 14, and the chain 15 is connected to driving means (not shown) such as a crane. Then, the driving means is driven to pull up the lifting member 10.
As a result, the lowermost horizontal sheet pile 4a is pulled up by the hook member 9, so that the lower earth retaining wall group 5 rises along the steel pile 3. At this time, since the case side sheet pile 4 is connected to the hoisting member 10, the stacked state can be smoothly pulled up without breaking the stacked state. Then, when the uppermost horizontal sheet pile 4 reaches the back sheet pile 7, after the connection between the horizontal sheet pile 4 and the lifting member 10 is released, the distance between the horizontal sheet pile 4 and the web portion 3b of the steel pile 3 (Fig. 3), the transverse sheet pile 4 is removed from the steel pile 3 as shown in FIG. Hereinafter, as shown in FIGS. 6 and 7, while removing the earth retaining wall group 5, the horizontal sheet piles 4 are removed from the steel pile 3 one by one, and the removal of the lower earth retaining wall group 5 is completed. After the above, with respect to the earth retaining wall group 6 and the back sheet pile 7 on the upper side, the horizontal sheet piles 4 are removed one by one from the steel pile 3 while backfilling.

【0013】このような構成では、土留壁群5、6から
全ての横矢板4を撤去出来るため、横矢板4の埋め殺し
に起因した道路陥没、地盤沈下等の発生を防止出来ると
共に、新規構築物の障害になることがなくなる。
With such a structure, since all the lateral sheet piles 4 can be removed from the retaining wall groups 5 and 6, road collapse, ground subsidence, etc. due to the burying of the lateral sheet piles 4 can be prevented, and a new structure can be constructed. It will not become an obstacle to.

【0014】図8及び図9は本発明の第2実施例を示
し、この実施例では所定の積層ブロック毎(図示例では
3枚毎の横矢板)の横矢板4に対してフック部材9が取
り付けられている。従って、引き上げは積層されたブロ
ック毎に行なわれるが、複数に分割されているため、引
き上げ力が小さくなり、引き上げを更に円滑に行なうこ
とが出来る利点がある。
FIG. 8 and FIG. 9 show a second embodiment of the present invention. In this embodiment, the hook member 9 is attached to the horizontal sheet pile 4 for each predetermined laminated block (every three sheet piles in the illustrated example). It is installed. Therefore, the pulling-up is performed for each of the stacked blocks, but since it is divided into a plurality of blocks, the pulling-up force becomes small, and the pulling-up can be performed more smoothly.

【0015】図10及び図11は本発明の第3実施例を
示す。この実施例では、吊上げ部材10が横矢板4の両
側に設けられている。このような吊上げ部材10の配設
は、横矢板4の裏側に吊上げ部材10を引き込みながら
積層した後、吊上げ部材10を横矢板4の表側に引き込
み、この横矢板4と表側と吊上げ部材10とを当部材に
より結合することにより、行なうことが出来る。本実施
例では、吊上げ部材10が横矢板4を両側から引き上げ
るため、均等で確実にして円滑な引き上げと横矢板4の
撤去を行なうことが出来る利点がある。
10 and 11 show a third embodiment of the present invention. In this embodiment, the lifting members 10 are provided on both sides of the horizontal sheet pile 4. To arrange such a lifting member 10, after stacking the lifting member 10 on the back side of the horizontal sheet pile 4 while pulling it in, the lifting member 10 is drawn to the front side of the horizontal sheet pile 4, and the horizontal sheet pile 4 and the front side and the lifting member 10 are arranged. Can be performed by connecting the above with the member. In this embodiment, since the lifting member 10 pulls up the horizontal sheet pile 4 from both sides, there is an advantage that the horizontal sheet pile 4 can be pulled up evenly and surely and smoothly.

【0016】[0016]

【発明の効果】以上説明したように、本発明は横矢板に
フック部材を取り付けて積層し、フック部材に連結され
た吊上げ部材を引き上げながら鋼杭から横矢板を取り外
すため、簡単な操作で横矢板の撤去を確実に行なうこと
が可能となり、このため、横矢板の埋め殺しに起因した
道路陥没、地盤沈下等の環境悪化を防止出来る利点があ
る。
As described above, according to the present invention, the hook members are attached to the horizontal sheet piles and stacked, and the horizontal sheet piles are removed from the steel pile while pulling up the lifting members connected to the hook members. Since the sheet piles can be reliably removed, there is an advantage that it is possible to prevent environmental deterioration such as road sinking and ground subsidence due to the burying of the horizontal sheet piles.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の第1実施例における土留壁を示す斜視
図である。
FIG. 1 is a perspective view showing a retaining wall in a first embodiment of the present invention.

【図2】第1実施例の横矢板の積層状態を示す斜視図で
ある。
FIG. 2 is a perspective view showing a stacked state of the horizontal sheet piles according to the first embodiment.

【図3】鋼杭への横矢板の掛け渡し状態を示す平面図で
ある。
FIG. 3 is a plan view showing a state in which a horizontal sheet pile is laid on a steel pile.

【図4】第1実施例の横矢板の撤去工程を示す断面図で
ある。
FIG. 4 is a cross-sectional view showing a step of removing the horizontal sheet pile according to the first embodiment.

【図5】第1実施例の横矢板の撤去工程を示す断面図で
ある。
FIG. 5 is a cross-sectional view showing a step of removing the horizontal sheet pile according to the first embodiment.

【図6】第1実施例の横矢板の撤去工程を示す断面図で
ある。
FIG. 6 is a cross-sectional view showing a step of removing the horizontal sheet pile according to the first embodiment.

【図7】第1実施例の横矢板の撤去工程を示す断面図で
ある。
FIG. 7 is a cross-sectional view showing a step of removing the horizontal sheet pile according to the first embodiment.

【図8】本発明の第2実施例の土留壁を示す斜視図であ
る。
FIG. 8 is a perspective view showing a retaining wall of a second embodiment of the present invention.

【図9】第2実施例の横矢板の積層状態を示す斜視図で
ある。
FIG. 9 is a perspective view showing a laminated state of the transverse sheet piles according to the second embodiment.

【図10】本発明の第3実施例の土留壁を示す斜視図で
ある。
FIG. 10 is a perspective view showing a retaining wall of a third embodiment of the present invention.

【図11】第3実施例の横矢板の積層状態を示す斜視図
である。
FIG. 11 is a perspective view showing a stacked state of the transverse sheet piles according to the third embodiment.

【符号の説明】[Explanation of symbols]

3 鋼杭 4 横矢板 9 フック部材 10 吊上げ部材 3 Steel pile 4 Horizontal sheet pile 9 Hook member 10 Lifting member

───────────────────────────────────────────────────── フロントページの続き (72)発明者 神山 鉄男 埼玉県大宮市堀の内町1−606 グランド シティ S−910 (72)発明者 若林 克郎 東京都練馬区石神井台8−20−8 ─────────────────────────────────────────────────── --- Continuation of the front page (72) Inventor Tetsuo Kamiyama 1-606 Horinouchi-cho, Omiya-shi, Saitama Grand City S-910 (72) Inventor Katsuro Wakabayashi 8-20-8 Shakujidai, Nerima-ku, Tokyo

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 地中に打設された鋼杭に掛け渡される横
矢板の内、少なくとも最下段の横矢板に吊上げ部材が連
結されているフック部材を取り付けて横矢板を順次積層
すると共に、前記吊上げ部材と上段部分の横矢板を結合
し、この状態で前記吊上げ部材を引き上げながら横矢板
を鋼杭間から取り外すことを特徴とする横矢板撤去工
法。
1. A horizontal sheet pile to be laid on a steel pile placed in the ground, at least the horizontal sheet pile at the bottom of the horizontal sheet pile is attached with a hook member connected to a lifting member, and the horizontal sheet piles are sequentially laminated, A horizontal sheet pile removing method, characterized in that the horizontal sheet piles of the upper part are connected to each other and the horizontal sheet piles are removed from between the steel piles while pulling up the suspension members in this state.
JP12824392A 1992-04-21 1992-04-21 Horizontal sheet pile removal method Expired - Fee Related JP2911016B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP12824392A JP2911016B2 (en) 1992-04-21 1992-04-21 Horizontal sheet pile removal method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP12824392A JP2911016B2 (en) 1992-04-21 1992-04-21 Horizontal sheet pile removal method

Publications (2)

Publication Number Publication Date
JPH05295732A true JPH05295732A (en) 1993-11-09
JP2911016B2 JP2911016B2 (en) 1999-06-23

Family

ID=14980041

Family Applications (1)

Application Number Title Priority Date Filing Date
JP12824392A Expired - Fee Related JP2911016B2 (en) 1992-04-21 1992-04-21 Horizontal sheet pile removal method

Country Status (1)

Country Link
JP (1) JP2911016B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100913945B1 (en) * 2009-04-22 2009-08-25 주식회사 지에이엔지니어링건축사사무소 Retaining of shutter type for construction and engineering work
KR102300590B1 (en) * 2020-12-16 2021-09-09 이성희 Reinforce method of cutting Ground
KR102301605B1 (en) * 2021-01-22 2021-09-10 차상호 A Method of Bottom-up Removal of Underground Structures

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100913945B1 (en) * 2009-04-22 2009-08-25 주식회사 지에이엔지니어링건축사사무소 Retaining of shutter type for construction and engineering work
KR102300590B1 (en) * 2020-12-16 2021-09-09 이성희 Reinforce method of cutting Ground
KR102301605B1 (en) * 2021-01-22 2021-09-10 차상호 A Method of Bottom-up Removal of Underground Structures

Also Published As

Publication number Publication date
JP2911016B2 (en) 1999-06-23

Similar Documents

Publication Publication Date Title
CN207144538U (en) A kind of underground structure top board reserving hole temporary plugging structure
KR102082333B1 (en) Prestressed pile and Self reliance retaining wall construction method using the same
JPH05295732A (en) Crosswise sheet pile removing method
JPH07268885A (en) Method of drive construction used for construction of subsurface structure
JPH07145625A (en) Method of constructing earth retaining wall
CN115977111A (en) Environment-friendly foundation pit supporting structure with double rows of steel sheet piles of inclined front and straight back and construction method
JP2001248135A (en) Jacket structure
JP3353200B2 (en) Earth retaining method
JP3010536B2 (en) Steel sheet pile wall
JP2860780B2 (en) Large concrete block
JP2001003331A (en) Breakwater
CN110374191B (en) Basement exterior wall component with supporting function and construction method thereof
JP3319494B2 (en) Simple underground structure
JP3045907B2 (en) Construction method of continuous wall support pile
JP3445753B2 (en) Method of forming a support for a structure
JP7084668B1 (en) Construction processing method of steel sheet pile
JPH07305319A (en) Installating method for caison for breakwater
JPH0571115A (en) Piling block engineering method
AU2002231658B2 (en) Offshore platform
JP2583830B2 (en) Construction method of concrete deep foundation pile
JPS63181804A (en) Breakwater and its construction and concrete caisson therefor
JPS6310250B2 (en)
JPH0743172Y2 (en) Slope retaining wall
JPH0673727A (en) Method of constructing soil pile column row earth retaining wall and special h-shaped steel bar
JP2592902B2 (en) How to put a long pipe into the groove in sheet pile construction

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees