JP3353200B2 - Earth retaining method - Google Patents

Earth retaining method

Info

Publication number
JP3353200B2
JP3353200B2 JP24348997A JP24348997A JP3353200B2 JP 3353200 B2 JP3353200 B2 JP 3353200B2 JP 24348997 A JP24348997 A JP 24348997A JP 24348997 A JP24348997 A JP 24348997A JP 3353200 B2 JP3353200 B2 JP 3353200B2
Authority
JP
Japan
Prior art keywords
earth retaining
pair
tension
retaining
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP24348997A
Other languages
Japanese (ja)
Other versions
JPH1161821A (en
Inventor
正男 三村
知史 結城
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Penta Ocean Construction Co Ltd
Original Assignee
Penta Ocean Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Penta Ocean Construction Co Ltd filed Critical Penta Ocean Construction Co Ltd
Priority to JP24348997A priority Critical patent/JP3353200B2/en
Publication of JPH1161821A publication Critical patent/JPH1161821A/en
Application granted granted Critical
Publication of JP3353200B2 publication Critical patent/JP3353200B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、土留め方法、特に
水平方向に剛性の高い土留壁、例えば連続地中壁に土水
圧に対抗する予圧を与えるために適用される土留め方法
に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an earth retaining method, and more particularly to an earth retaining method applied to give a prestress against a soil water pressure to a horizontally rigid earth retaining wall, for example, a continuous underground wall. is there.

【0002】[0002]

【従来の技術】従来の土留め方法では、図10Aに示す
ように一対の土留壁1の築造完了後、土留壁1,1間に
延びる地山2を全面的に掘削し、図10Bに示すように
水平面内で縦及び横方向に延びる腹起こし3及び切梁4
よりなる土留支保工を架設し土留壁1を押さえ、次いで
図10Cに示すように地山2を更に掘削する。その後の
土留支保工の架設は後追いで施工されていた。
2. Description of the Related Art In a conventional earth retaining method, as shown in FIG. 10A, after the construction of a pair of earth retaining walls 1 is completed, a ground 2 extending between the earth retaining walls 1 and 1 is entirely excavated, as shown in FIG. 10B. 3 and cutting beam 4 extending in the vertical and horizontal directions in the horizontal plane
A soil retaining support is constructed to hold the retaining wall 1, and then the ground 2 is further excavated as shown in FIG. 10C. Subsequent erection of the earth retaining structure was being carried out afterwards.

【0003】[0003]

【発明が解決しようとする課題】然しながら、上記従来
の方法においては、地山2を所定深さ掘削した都度土留
支保工を設置することになるため、土留壁は掘削に伴っ
て深くなるにつれて側圧が大きくなり、応力や変形の発
生を許し、図11のように土留壁が内側方向に変位し、
この変形した空間を埋めるべき地山の側方の土が変形部
分に向かって動き地表面に地盤沈下をもたらしてしまう
原因となっていた。
However, in the above-mentioned conventional method, a soil retaining structure is installed every time the ground 2 is excavated to a predetermined depth. Increases, allowing the occurrence of stress and deformation, and the retaining wall is displaced inward as shown in FIG.
The soil on the side of the ground, which should fill the deformed space, moved toward the deformed part, causing land subsidence on the ground surface.

【0004】このため上記土留壁を大きな剛性のものと
する必要があったが、壁厚が大きくなり経済的に高価と
なり、また土地占有面積も大きくなる欠点があった。
[0004] For this reason, it was necessary to make the retaining wall large in rigidity. However, there were disadvantages that the wall thickness became large, it became economically expensive, and the land occupied area became large.

【0005】また、特に地盤が軟弱な場合には、薬液注
入などの地盤改良を行なう方法があるが、地盤改良は非
常に高価であるため掘削地盤全体を改良することができ
ず、図12に示すように一部分だけに先行地中梁5を施
工せざるをえず、先行地中梁5のない部分において土留
壁1に大きな応力と変形を生じていた。
[0005] In addition, when the ground is particularly soft, there is a method of performing ground improvement such as injection of a chemical solution. However, since the ground improvement is extremely expensive, the entire excavated ground cannot be improved. As shown in the drawing, the preceding underground beam 5 had to be constructed only in a part, and large stress and deformation occurred in the retaining wall 1 in the portion without the preceding underground beam 5.

【0006】本発明の目的は、上記の欠点を除くように
したものである。
An object of the present invention is to eliminate the above-mentioned disadvantages.

【0007】[0007]

【課題を解決するための手段】本発明の土留め方法は、
一対の土留壁を築造し、上記一対の土留壁間に存在する
地山に鉛直方向に延びる幅狭の溝を掘削し、上記溝内
に、上記一対の土留壁間に所定の張力を与え、一対の腹
起こしと、上記一対の腹起こし間に油圧ジャッキを介し
て挿入した切梁と、上記切梁の張力検知器と、張力コン
トロールシステムとよりなる土留架構装置を挿入し、上
記張力検知器よりの出力に対応して上記油圧ジャッキに
より上記切梁を介して上記一対の腹起こし間に所定の張
力を与え、上記所定の力を維持しながら上記一対の土
留壁間を本掘削することを特徴とする。
The earth retaining method of the present invention comprises:
Construct a pair of retaining walls, excavate a narrow groove extending vertically in the ground existing between the pair of retaining walls, in the groove, apply a predetermined tension between the pair of retaining walls, A pair of upsets, a girder inserted between the pair of upsets via a hydraulic jack, a tension detector for the girder, and a soil retaining structure device including a tension control system, and the tension detector giving a predetermined tension between a raised the pair of belly through the Setsuhari by the hydraulic jack in response to more outputs, to the excavating the pair of earth retaining walls while maintaining the predetermined tension force It is characterized by.

【0008】[0008]

【発明の実施の形態】以下図面によって本発明の実施例
を説明する。
Embodiments of the present invention will be described below with reference to the drawings.

【0009】本発明においては、図1及び図2に示すよ
うに、築造された例えば連続地中壁(連壁)などの剛性
の高い左右の土留壁1,1に沿って夫々鉛直(深さ方
向)に建込まれる杭状の腹起こし6,6と、この左右の
腹起こし6,6間に鉛直方向に一定の間隔をおいて夫々
油圧ジャッキ7を介して水平に配置した複数の切梁8
と、上記切梁8の張力を検知する張力検知器(図示せ
ず)と、切梁8の張力を所定値ならしめるため、上記油
圧ジャッキ7を作動せしめる張力コントロールシステム
9とにより土留架構装置10を構成する。
In the present invention, as shown in FIG. 1 and FIG. 2, each of the vertical (depth) along the left and right retaining walls 1, 1 having high rigidity, such as a continuous underground wall (continuous wall). Direction)), and a plurality of cutting beams horizontally arranged via hydraulic jacks 7 with a certain vertical interval between the left and right side uplifts 6,6. 8
And a tension detector (not shown) for detecting the tension of the girder 8 and a tension control system 9 for operating the hydraulic jack 7 to equalize the tension of the girder 8 to a predetermined value. Is configured.

【0010】なお、11は上記油圧ジャッキ7と上記張
力コントロールシステム9を接続する油圧ホースであ
る。
Reference numeral 11 denotes a hydraulic hose connecting the hydraulic jack 7 and the tension control system 9.

【0011】本発明の土留め方法においては図3に示す
ように、土留壁1,1の築造完了後に、土留壁1,1間
の地山2の本掘削に先だって、連壁用の溝掘機械により
地山2に土留壁1,1間に延びる幅の狭い溝12を所定
の深さまで掘削し、地山2上より上記溝12中に上記土
留架構装置10を挿入する。
In the earth retaining method of the present invention, as shown in FIG. 3, after the construction of the earth retaining walls 1 and 1 is completed, prior to the main excavation of the ground 2 between the earth retaining walls 1 and 1, the trench for the continuous wall is excavated. A narrow groove 12 extending between the retaining walls 1 and 1 is excavated to a predetermined depth in the ground 2 by a machine, and the soil retaining structure device 10 is inserted into the groove 12 from above the ground 2.

【0012】上記土留架構装置10を挿入した後、上記
張力コントロールシステム9により油圧ジャッキ7を作
動せしめて、掘削完了時に作用されると予想される切梁
張力を各切梁8を介して上記一対の土留壁1,1間に加
え、その後上記溝12を砂等で埋めもしくは固化せしめ
る。
After the earth retaining frame device 10 is inserted, the hydraulic jack 7 is operated by the tension control system 9 so that the shear beam tension expected to be applied when the excavation is completed is applied to the pair of shear beams via the respective shear beams 8. After that, the groove 12 is filled or solidified with sand or the like.

【0013】上記溝12は必要に応じて地山2の他の部
分に一定の間隔を介して設け、同様に土留架構装置10
を挿入せしめ、切梁8を介して土留壁1,1間に張力を
加え、砂等で埋める。
The above-mentioned groove 12 is provided at other portions of the ground 2 at a predetermined interval as necessary, and similarly,
Is inserted, tension is applied between the retaining walls 1 and 1 via the cutting beams 8, and the soil is filled with sand or the like.

【0014】全ての溝12を砂等で埋めた後、上記土留
架構装置10を埋めたままの状態で、切梁8の一段毎に
本掘削を行い、各段毎に各段の切梁8の張力を上記張力
検知器により逐次監視しながら、地山の側面の張力に適
合する大きさの張力となるように上記張力コントロール
システム9で調整し、理想的な土留架構状態を維持す
る。
After all the trenches 12 are filled with sand or the like, main excavation is performed for each step of the cutting beam 8 while the earth retaining structure device 10 is filled, and the cutting beam 8 of each step is provided for each step. The tension control system 9 adjusts the tension of the ground by the tension detector so that the tension is adjusted to the magnitude of the tension on the side surface of the ground while maintaining the ideal soil retaining state.

【0015】最終掘削が終った時点で、従来工法に準じ
て施工を行う。
When the final excavation is completed, construction is performed according to the conventional method.

【0016】なお、上記腹起こし6には必要に応じて傾
斜計を設置し、土留壁1の変形を測定し、土留壁の応力
状態を把握しながら上記張力コントロールシステム9に
より切梁張力を調整して、土留壁1に作用する土圧分布
を均一化させ土留壁1の必要剛性を小さくし(二低廉
化)、壁の撓み量を極力小さくせしめことが可能とな
る。
In addition, an inclinometer is installed on the belly 6 as needed, and the deformation of the retaining wall 1 is measured, and the tension control system 9 adjusts the cutting beam tension while grasping the stress state of the retaining wall. Thus, the distribution of the earth pressure acting on the retaining wall 1 can be made uniform, the required rigidity of the retaining wall 1 can be reduced (two inexpensive), and the amount of deflection of the wall can be minimized.

【0017】また、地盤条件によっては最終床付面より
深い位置迄溝12を形成し、これに土留架構装置10を
挿入しても良い。
Further, depending on the ground conditions, the groove 12 may be formed to a position deeper than the surface with the final floor, and the earth retaining structure device 10 may be inserted into this.

【0018】図4及び図5は本発明の土留架構装置の他
の実施例を示し、この実施例においては、上記切梁8に
鉛直方向に延びる中間杭13を複数個固定せしめる。
FIGS. 4 and 5 show another embodiment of the earth retaining structure apparatus according to the present invention. In this embodiment, a plurality of intermediate piles 13 extending in the vertical direction are fixed to the cutting beam 8.

【0019】この実施例によれば切梁8の長さが長くな
る場合でも必要な土留架構装置10の強度を確保するこ
とができる。
According to this embodiment, the required strength of the earth retaining frame device 10 can be ensured even when the length of the cutting beam 8 becomes long.

【0020】単に溝12の長さが大きくなっただけに対
処するためには、図6に示すように非掘削部分の地山に
H形鋼など崩壊抑止杭14を打設して地山の安定を図る
こともできる。なお、この杭は部分的には中間杭13と
しても利用できる。
In order to cope with only the increase in the length of the groove 12, as shown in FIG. Stability can also be achieved. In addition, this pile can also be partially used as the intermediate pile 13.

【0021】なお、図7に示すように本掘削時に上記土
留架構装置10の他に従来のように土留壁1に水平方向
に延びる腹起こし3を更に架設せしめながら施工を進め
てもよい。
As shown in FIG. 7, during the main excavation, in addition to the above-mentioned earth retaining structure device 10, the construction may be carried out while additionally erectionally extending a belly 3 extending horizontally in the earth retaining wall 1 as in the prior art.

【0022】また、切梁8の鉛直方向の位置を自由に変
更できるため、図8に示すように、例えばブルトーザー
15等を掘削に都合のよい配置にすることができたり、
図9に示すように電車の入る空間や地下道となる空間1
6などを構造物築造に都合のよい配置となし得る。
Further, since the vertical position of the cutting beam 8 can be freely changed, as shown in FIG. 8, for example, the bulltozer 15 or the like can be arranged in a convenient manner for excavation.
As shown in FIG. 9, the space 1 where the train enters and the underground passage 1
6 and the like can be arranged conveniently for building structures.

【0023】[0023]

【発明の効果】本発明の土留架構装置及び土留め方法に
よれば、下記のような種々の利益がある。
According to the earth retaining structure apparatus and the earth retaining method of the present invention, there are various advantages as described below.

【0024】(1)土留壁の変位を超微量に抑えること
ができる。
(1) The displacement of the retaining wall can be suppressed to an extremely small amount.

【0025】(2)従来工法の場合、切梁を設置する直
前の状態(超短期間に発生する多大な応力状態)で土留
工の各部材の断面性能を決定する必要があるが本発明に
よれば、各段の切梁を事前に計画よく設置できるので、
切梁を設置する直前の短期間の異常状態を対象としなく
て済み従って、これにより、土留壁の壁厚を従来工法よ
り薄くしたり、壁の根入れを短くすることができ、工費
縮減ができる。
(2) In the case of the conventional construction method, it is necessary to determine the cross-sectional performance of each member of the earth retaining work in a state immediately before installing the cutting beam (a large stress state generated in a very short time). According to this, the cutting beams for each step can be set in advance in a well planned manner.
It is not necessary to cover the short-term abnormal condition immediately before the installation of the girder.Therefore, the wall thickness of the retaining wall can be made thinner than the conventional method, and the embedding of the wall can be shortened. it can.

【0026】(3)土留工の応力、変位状況を把握でき
る計測器の使用により本掘削に先行して切梁の張力を調
整しながら与えることができることによって、土留壁に
作用する土水圧を均等化し、土留壁の剛性を従来の方法
よりも小さく(壁厚を薄く)することができ、土留壁を
経済的な断面とすることができる。
(3) The use of a measuring device capable of grasping the stress and displacement state of the earth retaining work can be applied while adjusting the tension of the girder prior to the main excavation, so that the soil water pressure acting on the earth retaining wall can be equalized. Therefore, the rigidity of the retaining wall can be made smaller (the wall thickness is smaller) than in the conventional method, and the retaining wall can have an economical cross section.

【0027】(4)土留支保工の設置作業(とび、鍛冶
作業)が路上でできる。従って、
(4) The installation work (jumping and forging work) of earth retaining supports can be performed on the road. Therefore,

【0028】各掘削段階毎に行われる、断続的な工程
の作業でなく、とび、鍛冶工の作業が一回にまとめて実
施でき、作業員の動員もし易く、作業能率もよい。
The work of skipping and blacksmithing, which is performed at each excavation stage, can be carried out at once, and the work of the blacksmith can be carried out at one time.

【0029】また、従来工法のような、暗く、狭く、
足場の悪い杭内作業とならない路上作業なので、作業効
率もよく、かつ作業の安全性は高い。
Also, as in the conventional method, it is dark, narrow,
Since work is not performed on a pile with poor scaffolding, work efficiency is high and work safety is high.

【0030】また、掘削作業も、従来のような土留支
保工設置作業によって断続することはないため、作業が
連続し、作業能率が向上する。
Further, the excavation work is not interrupted by the conventional earth retaining support installation work, so that the work is continued and the work efficiency is improved.

【0031】また、作業スペースは開削工事が実施さ
れる前なので、本掘削をするスペース全体の広いスペー
スが使用でき、作業効率が向上する。
Further, since the work space is before the digging work is performed, a wide space for the entire excavation space can be used, and the work efficiency is improved.

【0032】従って、これらのことにより掘削・土留
支保工設置の工程が短縮できる。また、局部的にも作業
が可能となる。
[0032] Therefore, the steps of excavation and earth retaining support installation can be shortened by these things. In addition, work can be performed locally.

【0033】(5)また、腹起こしを鉛直方向に設置し
たので、土留支保工の設置が、本掘削前に施工できる。
(5) Further, since the belly is installed in the vertical direction, the earth retaining support can be installed before the main excavation.

【0034】(6)切梁の水平方向及び鉛直方向の位置
を自由に変更できるため、各作業を能率よく施工でき
る。
(6) Since the horizontal and vertical positions of the cutting beams can be freely changed, each work can be performed efficiently.

【0035】(7)構造物築造時の切梁撤去する時、腹
起こしが鉛直方向で兼用できるので切梁盛替え作業が容
易となる。
(7) When removing the girder at the time of constructing the structure, the uprighting can also be used in the vertical direction, so that the girder reshuffling work becomes easy.

【0036】(8)腹起こしは最後に、まとめて杭のよ
うに引抜き撤去することが可能で、腹起こし撤去作業が
簡単で能率よく施工できる。
(8) Lastly, it is possible to collectively pull out and remove like a pile, and the work for removing and raising the belly is simple and efficient.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明を適用する土留架構装置の説明用正面図
である。
FIG. 1 is an explanatory front view of an earth retaining frame apparatus to which the present invention is applied .

【図2】図1に示す土留架構装置の一部の拡大正面図で
ある。
2 is an enlarged front view of a portion of the earth retaining Frames apparatus shown in FIG.

【図3】図1に示す土留架構装置の説明用平面図であ
る。
FIG. 3 is an explanatory plan view of the earth retaining structure device shown in FIG . 1 ;

【図4】図1に示す土留架構装置の他の実施例を示す一
部の拡大正面図である。
FIG. 4 is a partially enlarged front view showing another embodiment of the earth retaining structure apparatus shown in FIG . 1 ;

【図5】図1に示す土留架構装置の他の実施例を示す説
明用側面図である。
FIG. 5 is an explanatory side view showing another embodiment of the earth retaining structure apparatus shown in FIG . 1 ;

【図6】図1に示す土留架構装置の更に他の実施例を示
す説明用平面図である。
FIG. 6 is an explanatory plan view showing still another embodiment of the earth retaining frame apparatus shown in FIG . 1 .

【図7】図1に示す土留架構装置の更に他の実施例を示
す説明用平面図である。
FIG. 7 is an explanatory plan view showing still another embodiment of the earth retaining frame apparatus shown in FIG . 1 .

【図8】本発明の説明用正面図である。FIG. 8 is an explanatory front view of the present invention.

【図9】本発明の他の例を示す説明用正面図である。FIG. 9 is an explanatory front view showing another example of the present invention.

【図10A】従来の土留め方法の説明用正面図である。FIG. 10A is a front view for explaining a conventional earth retaining method.

【図10B】従来の土留め方法の説明用正面図である。FIG. 10B is a front view for explaining a conventional earth retaining method.

【図10C】従来の土留め方法の説明用正面図である。FIG. 10C is a front view for explaining a conventional earth retaining method.

【図11】従来の土留架構装置の説明用正面図である。FIG. 11 is an explanatory front view of a conventional earth retaining structure device.

【図12】従来の土留架構装置の説明用正面図である。FIG. 12 is an explanatory front view of a conventional earth retaining structure device.

【符号の説明】[Explanation of symbols]

1 土留壁 2 地山 3 腹起こし 4 切梁 5 地中梁 6 杭状の腹起こし 7 油圧ジャッキ 8 切梁 9 コントロールシステム 10 土留架構装置 11 油圧ホース 12 溝 13 中間杭 14 崩壊抑止杭 15 ブルドーザー 16 空間 DESCRIPTION OF SYMBOLS 1 Soil retaining wall 2 Ground pile 3 Uplift 4 Cut beam 5 Underground beam 6 Piled uplift 7 Hydraulic jack 8 Cut beam 9 Control system 10 Soil retaining structure device 11 Hydraulic hose 12 Groove 13 Middle pile 14 Collapse prevention pile 15 Bulldozer 16 space

フロントページの続き (58)調査した分野(Int.Cl.7,DB名) E02D 17/04 E02D 17/08 Continuation of the front page (58) Field surveyed (Int.Cl. 7 , DB name) E02D 17/04 E02D 17/08

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 一対の土留壁を築造し、 上記一対の土留壁間に存在する地山に鉛直方向に延びる
幅狭の溝を掘削し、 上記溝内に、上記一対の土留壁間に所定の張力を与え、 一対の腹起こしと、上記一対の腹起こし間に油圧ジャッ
キを介して挿入した切梁と、上記切梁の張力検知器と、
張力コントロールシステムとよりなる土留架構装置を挿
入し、 上記張力検知器よりの出力に対応して上記油圧ジャッキ
により上記切梁を介して上記一対の腹起こし間に所定の
張力を与え、 上記所定の力を維持しながら上記一対の土留壁間を本
掘削することを特徴とする土留め方法。
1. A pair of retaining walls are constructed, and a narrow groove extending vertically is excavated in a ground existing between the pair of retaining walls, and a predetermined groove is formed between the pair of retaining walls in the groove. A pair of belly upsets, a girder inserted through a hydraulic jack between the pair of uprights, and a tension detector for the girder,
Inserting a soil retaining structure device comprising a tension control system, applying a predetermined tension between the pair of belly uprights via the cutting beam by the hydraulic jack in response to the output from the tension detector, retaining method characterized by the excavating the pair of earth retaining walls while maintaining the tension force.
JP24348997A 1997-08-26 1997-08-26 Earth retaining method Expired - Fee Related JP3353200B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP24348997A JP3353200B2 (en) 1997-08-26 1997-08-26 Earth retaining method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP24348997A JP3353200B2 (en) 1997-08-26 1997-08-26 Earth retaining method

Publications (2)

Publication Number Publication Date
JPH1161821A JPH1161821A (en) 1999-03-05
JP3353200B2 true JP3353200B2 (en) 2002-12-03

Family

ID=17104660

Family Applications (1)

Application Number Title Priority Date Filing Date
JP24348997A Expired - Fee Related JP3353200B2 (en) 1997-08-26 1997-08-26 Earth retaining method

Country Status (1)

Country Link
JP (1) JP3353200B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103603361A (en) * 2013-12-06 2014-02-26 黄河水利职业技术学院 Compressible device of deep foundation pit horizontal inner support
KR101750701B1 (en) 2016-07-11 2017-06-27 안성근 Droop prevention structure module of steel pipe strut and maingirder

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103243722B (en) * 2012-02-13 2015-10-28 郑鸿彰 The construction method of novel inner support of foundation trench
JP6905387B2 (en) * 2017-05-08 2021-07-21 清水建設株式会社 Construction method of earth retaining structure
CN107906085B (en) * 2017-12-21 2023-08-04 浙江同禾传感技术有限公司 Intelligent control pump station and control method
JP7257881B2 (en) * 2018-05-25 2023-04-14 丸藤シートパイル株式会社 Wireless earth pressure measurement system and wireless earth pressure measurement method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103603361A (en) * 2013-12-06 2014-02-26 黄河水利职业技术学院 Compressible device of deep foundation pit horizontal inner support
KR101750701B1 (en) 2016-07-11 2017-06-27 안성근 Droop prevention structure module of steel pipe strut and maingirder

Also Published As

Publication number Publication date
JPH1161821A (en) 1999-03-05

Similar Documents

Publication Publication Date Title
JP2002227204A (en) Earth retaining method of excavation section
JP3353200B2 (en) Earth retaining method
KR100584701B1 (en) A method of construction for temporary retaining wall
JP4558145B2 (en) Seismic isolation method for existing buildings
JPH07268885A (en) Method of drive construction used for construction of subsurface structure
JP3850785B2 (en) Caisson laying method using main foundation pile
JP3516391B2 (en) Ground excavation method
JP2868651B2 (en) Earth retaining method above existing underground structure
JP2899670B2 (en) Excavation for underground structures
JP2964295B2 (en) Basement floor construction method
JP2654719B2 (en) Simple underground continuous wall method
JPH11247195A (en) Temporary earth retaining wall structure and temporary earth retaining wall execution method
KR101025399B1 (en) Underground Structure and Method for Constructing thereof
JP3782180B2 (en) Support structure using sheet piles for earth retaining bells
JPH10317374A (en) Method for constructing underground column made of reinforced concrete
KR102149709B1 (en) Deformation prevention method of files for retaining wall of underground
KR102638676B1 (en) Construction method of earth retaining wall without wale
KR100669530B1 (en) Construction method of a rataining well
JPH07259080A (en) Self-supported sheath wall structure
JP2000257069A (en) Earth retaining and earth retaining construction method
KR102302599B1 (en) Construction method for soil guard and concrete deck plate
JP3969090B2 (en) Cutting beam
KR20040035449A (en) Straight retaining wall having a shelf using H-shaped piles and constructing method thereof
JP3032455B2 (en) Method of pressing structure upward
JPH10159094A (en) Timbering structure of earth retaining wall

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080927

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090927

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100927

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100927

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110927

Year of fee payment: 9

LAPS Cancellation because of no payment of annual fees