JPH11217823A - Earth retaining method in cut and cover tunneling work of ground and steel sheet pile used therefor - Google Patents

Earth retaining method in cut and cover tunneling work of ground and steel sheet pile used therefor

Info

Publication number
JPH11217823A
JPH11217823A JP3380698A JP3380698A JPH11217823A JP H11217823 A JPH11217823 A JP H11217823A JP 3380698 A JP3380698 A JP 3380698A JP 3380698 A JP3380698 A JP 3380698A JP H11217823 A JPH11217823 A JP H11217823A
Authority
JP
Japan
Prior art keywords
sheet pile
steel sheet
earth retaining
cut
groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP3380698A
Other languages
Japanese (ja)
Inventor
Masakuni Taguchi
雅邦 田口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
AZUMA KIGYO KK
Original Assignee
AZUMA KIGYO KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by AZUMA KIGYO KK filed Critical AZUMA KIGYO KK
Priority to JP3380698A priority Critical patent/JPH11217823A/en
Publication of JPH11217823A publication Critical patent/JPH11217823A/en
Pending legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To enable the promotion of working efficiency for an earth retaining method in a cut and cover tunneling site and the prevention of a ground collapse accident. SOLUTION: Steel sheet piles B used for earth retaining in a ground cut and cover tunneling site are so formed that two sheet pile members 1a and 1b are connected to the front and rear to combine them with each other in a slidable manner in the vertical direction (up and down directions). The steel sheet piles are erected at a stage excavating shallowly a cut and cover tunneling groove A to carry out the initial earth retaining work, and then, the sheet pile member 1b on the rear side is pushed forward with the excavtion of the cut and cover tunneling groove A.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、道路等の開削工事にお
いて行う土止工法及びこれに使用する軽量鋼矢板に関す
るものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an earth retaining method for digging a road or the like and a lightweight steel sheet pile used for the method.

【0002】[0002]

【従来の技術】一般に、ガスや上下水道、地下ケーブル
の埋設、或はそれら既設物の修複や取り替え等の工事で
は、地盤を開削して行われるが、その際、開削した溝の
側壁に沿って、地山の崩壊を防止するための軽量鋼矢板
による土止めを行うようにしている。
2. Description of the Related Art In general, when laying gas, water and sewage, burying underground cables, or repairing or replacing existing ones, the ground is cut open, and at that time, along the side walls of the cut grooves. In order to prevent the collapse of the ground, the earth is stopped by lightweight steel sheet piles.

【0003】この種の工事では、開削溝の深さは通常2
−3m程度であることから、従来は、図11に示すよう
に、まず、所定の深さの開削溝A全体を掘削、形成し、
その後溝壁に沿って軽量鋼矢板B,Bを並べて建て込
み、腹起し材を取り付け、切梁を架設するようにしてい
る。
[0003] In this type of construction, the depth of the cut groove is usually two.
Conventionally, as shown in FIG. 11, first, the entire excavation groove A having a predetermined depth is excavated and formed, as shown in FIG.
Thereafter, light steel sheet piles B, B are laid side by side along the groove wall, a flared material is attached, and a cutting beam is erected.

【0004】[0004]

【発明が解決しようとする課題】この種工事における従
来の土止工法では、上記のように、開削溝を所定の深さ
まで掘削してから土止めを行うため、工事としては簡便
であるが、ある程度掘削して鋼矢板を建て込む前に地山
が崩壊してしまうという危険性を回避できないという難
点がある。また、軟弱な地盤での工事では、鋼矢板を打
設した後で開削工事を行うようにしなければならず、工
事が大規模化し多大な経費を要することになる。
According to the conventional earth retaining method in this kind of construction, as described above, since the earth retaining work is performed after excavating the open cut groove to a predetermined depth, the construction is simple, but the construction is simple. There is a drawback that the danger that the ground collapses before excavating to some extent and building steel sheet piles cannot be avoided. Moreover, in the construction on soft ground, the excavation work must be performed after the steel sheet pile has been driven, and the construction becomes large-scale and requires a great deal of cost.

【0005】本発明は、上記従来の問題点を解決するた
めになされたもので、土止材として使用する軽量鋼矢板
を、複数の矢板部材を上下にスライド可能に組み合せた
ものとすることにより、開削溝掘削の進行にともなって
鋼矢板を伸長させて行くことにより、地山の崩壊を防止
するとともに、作業員の安全確保と作業能率の向上を図
ろうとするものである。
SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned conventional problems. A lightweight steel sheet pile used as an earth retaining material is obtained by combining a plurality of sheet pile members so as to be slidable up and down. By extending the steel sheet pile as the excavation digging progresses, the collapse of the ground is prevented, and the safety of workers and the improvement of work efficiency are aimed at.

【0006】[0006]

【課題を解決するための手段】上記の目的を達成するた
めの本発明の構成について、実施例に対応する図面を参
照して説明すると、請求項1の土止工法は、複数の矢板
部材1a,1bをその長手方向にスライド可能に重ね合
せて形成した鋼矢板Bを使用し、開削溝Aが浅く形成さ
れた掘削初期の段階で、上記鋼矢板Bを溝壁に沿って建
て込み、腹起し材12及び切梁13を架設して土止めを行
い、その後、開削溝Aの掘削進行にともない、鋼矢板B
における矢板部材の一方1bを下方に押し下げて行くこ
とを特徴とするものである。
The construction of the present invention for attaining the above object will be described with reference to the drawings corresponding to the embodiments. , 1b are slidably overlapped in the longitudinal direction of the steel sheet pile B, and the steel sheet pile B is erected along the groove wall at an early stage of excavation where the cut groove A is formed shallowly. The erection material 12 and the cutting beam 13 are erected and earth retaining is performed. Then, as the excavation groove A is excavated, the steel sheet pile B
, One of the sheet pile members 1b is pushed down.

【0007】また、請求項2の鋼矢板は、鋼板により縦
長の帯状をなし、両外側部の裏面側に縦に走る係合溝4
を設けた一方の矢板部材1aと、鋼板により上記矢板部
材1aと相似の形状をなし、その両側部には係合条7が
設けられ、また下端部に打ち下げ用のフック部材8を突
設してなる他方の矢板部材1bとよりなり、一方の矢板
部材1aの裏面に他方の矢板部材1bが接合して、互い
に係合溝4と係合条7とが係合し、それら矢板部材1
a,1bが互いに分離しないで縦方向にスライド可能に
組み合されていることを特徴とするものである。
Further, the steel sheet pile according to the second aspect is formed in a vertically long band shape by a steel plate, and the engaging grooves 4 run vertically on the back sides of both outer portions.
One sheet pile member 1a provided with a sheet metal and a steel sheet have a shape similar to the above sheet pile member 1a, engaging strips 7 are provided on both sides thereof, and a hook member 8 for depressing is provided at the lower end part. And the other sheet pile member 1b is joined to the back surface of one sheet pile member 1a, and the engaging groove 4 and the engaging strip 7 are engaged with each other.
a and 1b are combined so as to be slidable in the vertical direction without being separated from each other.

【0008】[0008]

【発明の実施の形態】以下、本発明の実施の形態につい
て図面を参照して説明する。図1〜図3は本発明工法の
実施態様の一例を示したものであり、図4〜図10は本発
明工法において使用する軽量鋼矢板(以下鋼矢板とい
う)の実施例を示したものである。
Embodiments of the present invention will be described below with reference to the drawings. 1 to 3 show an embodiment of the method of the present invention, and FIGS. 4 to 10 show examples of a lightweight steel sheet pile (hereinafter referred to as a steel sheet pile) used in the method of the present invention. is there.

【0009】まず、本発明工法において使用する鋼矢板
の一実施例について説明する。図4〜図7において、B
は鋼矢板で、2枚の矢板部材1a,1bとにより形成さ
れている。一方の矢板部材1aは、縦長の鋼板を幅方向
に屈曲して帯状に形成されており、例えば図示のよう
に、幅方向中央部には表面側(一面側)に突出する断面
山形の突条2が縦走し、その両側には裏面側(地面側)
方向に台形状をなす窪み部3,3が形成され、窪み部に
続く両外側部には、裏側から内方に向けて弧状に屈曲し
縦に走る係合溝4,4が設けられたものとなっている。
First, an embodiment of a steel sheet pile used in the method of the present invention will be described. 4 to FIG.
Is a steel sheet pile, which is formed by two sheet pile members 1a and 1b. One sheet pile member 1a is formed in a strip shape by bending a vertically long steel plate in the width direction, and for example, as shown in the drawing, a ridge having a mountain-shaped cross section protruding toward the front side (one surface side) at the center in the width direction. 2 runs vertically, and on both sides the back side (ground side)
The recesses 3 and 3 having a trapezoidal shape are formed in the direction, and the engagement grooves 4 and 4 which are bent in an arc shape inward from the back side and run vertically are provided on both outer sides following the recess. It has become.

【0010】また、他方の矢板部材1bは、上記一方の
矢板部材1aと同等またはそれ以上に長く、そして、一
方の矢板部材1aの裏面に接し得るように、矢板部材1
aと相似の、突条5の両側に窪み部6,6を有し、両外
側部に、上記係合溝4内係合する湾曲した係合条7,7
が設けられたものとなっているとともに、矢板部材1b
の下端部には、その表面側のほぼ全幅にわたって突出す
る打ち下げ用のフック部材8が設けられている。
Further, the other sheet pile member 1b is longer than or equal to the one sheet pile member 1a, and is made to be in contact with the back surface of the one sheet pile member 1a.
a, which has concave portions 6 and 6 on both sides of the ridge 5 and curved engagement ridges 7 and 7 which engage in the engagement groove 4 on both outer portions.
And the sheet pile member 1b
At the lower end portion, a hook member 8 for depressing, which protrudes over almost the entire width of the front surface side, is provided.

【0011】この他方の矢板部材1bは、一方の矢板部
材1aの裏面に接合され、その両外側にある係合条7,
7を係合溝4,4内に係合させて、一方の矢板部材1a
と互いに上下(縦方向)にスライド可能に組み合せ(重
合)される。それによって、本発明工法において使用さ
れる鋼矢板Bとなる。この鋼矢板Bは、他方の矢板部材
1bのフック部材8が一方の矢板部材1aの下端と接す
る程度にして両矢板部材1a,1bが重なり合った縮少
状態から、一方の矢板部材1aの下端部に他方の矢板部
材1bの上端部が重なり合った伸長状態までの間自在に
伸縮されて使用に応じることができる。
The other sheet pile member 1b is joined to the back surface of one sheet pile member 1a, and engagement strips 7,
7 into the engagement grooves 4 and 4, and the one sheet pile member 1a
Are combined (polymerized) so that they can slide up and down (vertically) with each other. Thereby, the steel sheet pile B used in the method of the present invention is obtained. In this steel sheet pile B, the hook member 8 of the other sheet pile member 1b is brought into contact with the lower end of one sheet pile member 1a so that the two sheet pile members 1a and 1b overlap each other in a reduced state. Thus, the upper end of the other sheet pile member 1b can be freely expanded and contracted until it is in an extended state in which the sheet pile member 1b is overlapped, so that it can be used.

【0012】図8〜図10は鋼矢板の他の実施例を示した
ものである。この実施例のものは、さきの実施例のもの
に対し、一方の矢板部材1aでは、その窪み部3,3
に、その長手方向に沿って上端から下端近くまで至るス
リット10が設けられ、また、他方の矢板部1bの方に
は、その窪み部6,6の上部に、上記スリット部10と係
合する、断面T形の離脱防止フック11が突設されてい
る。その他の構成についてはさきの実施例におけると同
様であるから、その説明は省略する。
8 to 10 show another embodiment of the steel sheet pile. This embodiment is different from the previous embodiment in that one of the sheet pile members 1a has recesses 3, 3 thereof.
Is provided with a slit 10 extending from the upper end to the vicinity of the lower end along the longitudinal direction, and the other sheet pile portion 1b is engaged with the slit portion 10 in the upper portion of the depressions 6, 6. A hook 11 having a T-shaped cross section is provided to protrude. Other configurations are the same as those in the previous embodiment, and the description thereof will be omitted.

【0013】なお、上記各実施例は2枚の矢板部材1
a,1bを重ね合わせて係合したものとなっているが、
矢板部材の重ね数は3枚以上であってもよい。また、矢
板部材の断面形状は各実施例のものに限定されることは
なく、各種の形状を採用することが可能である。
In each of the above embodiments, two sheet pile members 1 are used.
a and 1b are overlapped and engaged,
The number of piles of the sheet pile members may be three or more. Further, the cross-sectional shape of the sheet pile member is not limited to that of each embodiment, and various shapes can be adopted.

【0014】本発明の土止工法は、上記のような鋼矢板
Bを使用して行われる。地盤には、当初、所要幅を有す
る開削溝Aが、地盤の崩壊しない深さに掘削される。特
に軟弱でない地盤では、縮少形態とした鋼矢板Bの長さ
に相応する1m程度の深さとするのがよい。そして、図
1、図2に示すように、この初期に開設の開削溝A内
に、その両溝壁a,aと接して縮少形態とした鋼矢板B
の多数を並列して建て込むとともに、それらの各一方の
矢板部材1a,1aどうしを腹起し材12により連結し、
両側の腹起し材12,12間に切梁13を架設して、早期土止
めを行う。
The earth retaining method of the present invention is performed using the steel sheet pile B as described above. In the ground, an open groove A having a required width is initially excavated to a depth at which the ground does not collapse. In particular, in the case of a non-soft ground, the depth is preferably about 1 m corresponding to the length of the reduced steel sheet pile B. As shown in FIG. 1 and FIG. 2, a steel sheet pile B in a reduced form in contact with the two groove walls a, a in the cut groove A formed at the initial stage.
Of the sheet pile members 1a, 1a of the sheet pile members 1a, 1a are connected to each other by the protruding material 12,
A bridge 13 is erected between the flared uprights 12 on both sides to provide an early stop.

【0015】その後は、図3に示すように、開削溝A下
底の地盤を掘り下げて行き、またその掘削にともない、
裏側にある他方の矢板部材1bを、その打下げ用フック
8を打撃するなどして一方の矢板部材1aに対しスライ
ドさせ、開削溝Aの深さに追随させて行くのである。そ
れにより、開削溝Aの溝壁a,aは、一方の矢板部材1
a及びスライドして下方に伸びた他方の矢板部材1bに
よって土止めが施されることになる。したがって、開削
工のほぼ全工程にわたって地山崩壊が防止でき、開削溝
内で働く作業員の安全が確保されることになる。
Thereafter, as shown in FIG. 3, the ground below the bottom of the cut groove A is dug down, and with the excavation,
The other sheet pile member 1b on the back side is slid with respect to the one sheet pile member 1a by hitting the down hook 8 or the like to follow the depth of the cut groove A. Thereby, the groove walls a, a of the cut groove A are connected to one of the sheet pile members 1.
a and the other sheet pile member 1b extending downward by sliding, the earth retaining is performed. Therefore, the collapse of the ground can be prevented in almost all the steps of the excavation work, and the safety of the worker working in the excavation groove is secured.

【0016】[0016]

【発明の効果】以上説明したように、本発明の土止工法
によれば、上下に伸長することのできる鋼矢板を用い
て、開削溝の浅い開削初期の段階での早期土止めを行
い、その後は開削溝の掘り下げ進行にともない鋼矢板を
伸長させるようにしたので、開削溝の工事において、そ
の掘削開始から工事終了までの全工程にわたって開削溝
壁の崩壊を防止することができ、作業員の安全確保が図
られるばかりでなく、地山崩壊防止にともなう作業の効
率アップができ、工事期間の短縮ができる。
As described above, according to the earth retaining method of the present invention, a steel sheet pile that can be extended up and down is used to perform an early earth embankment in the initial stage of the shallow excavation, After that, the steel sheet pile was extended as the trench was dug down, so that in the construction of the trench, the collapse of the trench wall was prevented throughout the entire process from the start of the excavation to the end of the construction. In addition to ensuring the safety of construction, the efficiency of work associated with preventing the collapse of the ground can be improved, and the construction period can be shortened.

【0017】また、本発明土止工法に使用される鋼矢板
は、両矢板部材が表裏に重なり合って離れることなくス
ライドするので、取り扱いが容易であり、また、縮少時
の長さが短くできるので、運搬にも便利である。
Further, the steel sheet pile used in the earth retaining method of the present invention slides without overlapping because both sheet pile members are overlapped on the front and back, so that the sheet pile is easy to handle and the length when the sheet pile is reduced can be shortened. Therefore, it is convenient for transportation.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明工法の実施態様における初期土止の状態
を示す側断面図である。
FIG. 1 is a side sectional view showing a state of an initial embankment in an embodiment of the method of the present invention.

【図2】同一部の平断面図である。FIG. 2 is a plan sectional view of the same part.

【図3】同鋼矢板を伸長した状態を示す側断面図であ
る。
FIG. 3 is a side sectional view showing a state where the steel sheet pile is extended.

【図4】鋼矢板の一実施例を示す平面図である。FIG. 4 is a plan view showing one embodiment of a steel sheet pile.

【図5】同側断面図である。FIG. 5 is a sectional side view of the same.

【図6】同一部の斜視図である。FIG. 6 is a perspective view of the same part.

【図7】同矢板部材どうしを分離して示した平面図であ
る。
FIG. 7 is a plan view showing the sheet pile members separated from each other.

【図8】鋼矢板の他の実施例を示す平面図である。FIG. 8 is a plan view showing another embodiment of the steel sheet pile.

【図9】同側断面図である。FIG. 9 is a sectional side view of the same.

【図10】同矢板部材どうしを分離して示した平断面図で
ある。
FIG. 10 is a plan sectional view showing the sheet pile members separated from each other.

【図11】従来工法の態様を示す側断面図である。FIG. 11 is a side sectional view showing an embodiment of a conventional method.

【符号の説明】[Explanation of symbols]

A 開削溝 B 鋼矢板 1a,1b 矢板部材 2,5 突条 3,6 窪み部 4 係合溝 7 係合条 8 打下げ用フック部材 10 スリット 11 離脱防止フック 12 腹起し材 13 切梁 DESCRIPTION OF SYMBOLS A Opening groove B Steel sheet pile 1a, 1b Sheet pile member 2, 5 Ridge 3, 6 Depression 4 Engagement groove 7 Engagement line 8 Depression hook member 10 Slit 11 Detachment prevention hook 12 Belly raised material 13 Cut beam

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 複数の矢板部材をその長手方向にスライ
ド可能に重ね合わせて形成した鋼矢板を使用し、開削溝
が浅く形成された掘削初期の段階で、上記鋼矢板を溝壁
に沿って建て込み、腹起し材及び切梁を架設して土止め
を行い、その後、開削溝の掘削進行にともない、鋼矢板
における矢板部材の一方を下方に押し下げて行くことを
特徴とする、地盤の開削工事における土止工法。
1. A steel sheet pile formed by stacking a plurality of sheet pile members so as to be slidable in the longitudinal direction of the sheet pile member, and in an initial stage of excavation in which an open groove is formed shallowly, the steel sheet pile is moved along a groove wall. Erecting, erection material and cutting beams are installed and earth retaining is performed, and then, as the excavation groove is excavated, one of the sheet pile members of the steel sheet pile is pushed down, and Earth retaining method in digging work.
【請求項2】 鋼板により縦長の帯状をなし、両外側部
の裏面側に縦に走る係合溝を設けた一方の矢板部材と、
鋼板により上記矢板部材と相似の形状をなし、その両側
部には係合条が設けられ、また下端部に打ち下げ用のフ
ック部材を突設してなる他方の矢板部材とよりなり、一
方の矢板部材の裏面に他方の矢板部材が接合して、互い
に係合溝と係合条とが係合し、それら矢板部材が互いに
分離しないで縦方向にスライド可能に組み合されている
ことを特徴とする、地盤の開削工事における土止工法で
使用する鋼矢板。
2. A sheet pile member having a vertically elongated band shape made of a steel plate and having engagement grooves running vertically on the back surfaces of both outer portions,
The sheet pile has a shape similar to that of the sheet pile member, engagement strips are provided on both sides thereof, and the other sheet pile member is provided with a hook member for depressing at a lower end portion. The other sheet pile member is joined to the back surface of the sheet pile member, the engagement groove and the engagement strip are engaged with each other, and the sheet pile members are combined so as to be slidable in the vertical direction without being separated from each other. Steel sheet pile used in earth retaining method in ground excavation work.
JP3380698A 1998-01-30 1998-01-30 Earth retaining method in cut and cover tunneling work of ground and steel sheet pile used therefor Pending JPH11217823A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3380698A JPH11217823A (en) 1998-01-30 1998-01-30 Earth retaining method in cut and cover tunneling work of ground and steel sheet pile used therefor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3380698A JPH11217823A (en) 1998-01-30 1998-01-30 Earth retaining method in cut and cover tunneling work of ground and steel sheet pile used therefor

Publications (1)

Publication Number Publication Date
JPH11217823A true JPH11217823A (en) 1999-08-10

Family

ID=12396734

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3380698A Pending JPH11217823A (en) 1998-01-30 1998-01-30 Earth retaining method in cut and cover tunneling work of ground and steel sheet pile used therefor

Country Status (1)

Country Link
JP (1) JPH11217823A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100808109B1 (en) 2006-09-06 2008-03-04 고려개발 주식회사 Supporting structure for being used to excavated ground
KR100913945B1 (en) 2009-04-22 2009-08-25 주식회사 지에이엔지니어링건축사사무소 Retaining of shutter type for construction and engineering work
KR101005572B1 (en) 2008-12-10 2011-01-05 엘에스씨산업기술 주식회사 Temporary retaining wall structure
CN108343071A (en) * 2018-03-19 2018-07-31 南京市测绘勘察研究院股份有限公司 A kind of foundation pit supporting construction and construction method of steel sheet pile combined deposited pile
CN115354668A (en) * 2022-09-15 2022-11-18 曾春凤 Landscaping engineering support construction method
CN115467336A (en) * 2022-10-08 2022-12-13 北京市政建设集团有限责任公司 Reinforced cushion layer supporting system for reinforcing local deep pit

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100808109B1 (en) 2006-09-06 2008-03-04 고려개발 주식회사 Supporting structure for being used to excavated ground
KR101005572B1 (en) 2008-12-10 2011-01-05 엘에스씨산업기술 주식회사 Temporary retaining wall structure
KR100913945B1 (en) 2009-04-22 2009-08-25 주식회사 지에이엔지니어링건축사사무소 Retaining of shutter type for construction and engineering work
CN108343071A (en) * 2018-03-19 2018-07-31 南京市测绘勘察研究院股份有限公司 A kind of foundation pit supporting construction and construction method of steel sheet pile combined deposited pile
CN115354668A (en) * 2022-09-15 2022-11-18 曾春凤 Landscaping engineering support construction method
CN115467336A (en) * 2022-10-08 2022-12-13 北京市政建设集团有限责任公司 Reinforced cushion layer supporting system for reinforcing local deep pit
CN115467336B (en) * 2022-10-08 2023-06-16 北京市政建设集团有限责任公司 Reinforcing cushion layer supporting system for reinforcing local pit

Similar Documents

Publication Publication Date Title
JP4309219B2 (en) Tunnel construction method
JPS6145014B2 (en)
JPH11217823A (en) Earth retaining method in cut and cover tunneling work of ground and steel sheet pile used therefor
KR101069702B1 (en) Method for installing waterproofing steel plate and soil-drop preventing plate in construction of undergound tunnel
JP2011042992A (en) Earth retaining method and earth retaining self-supporting frame
JP4303512B2 (en) Construction method of large section tunnel
JP6804034B2 (en) How to build a retaining wall structure
JP2933476B2 (en) Underground pipe laying method
JPH02252892A (en) Method for constructing underground structure
JPH11193685A (en) Segment piece
JP4705467B2 (en) Construction method of underground structure
JP2005106201A (en) Pipe support
JP2020125661A (en) Joint structure of underground continuous wall, and construction method of underground continuous wall
JPH05256098A (en) Construction method of underground structure having large section and split block used for said structure and excavator
KR102108936B1 (en) Construction method for slab of undergroud structure
JP4548949B2 (en) Undercover structure lining element and underground structure construction method
JP4272228B2 (en) Construction method of underground structure
JPH02272192A (en) Execution of underground construction
JP2000034894A (en) Tunnel timbering unit
JP6353431B2 (en) Friction cut plate joining method
JP6476450B2 (en) Method of retaining the ceiling part of the widened part and method of widening the underground part
KR200339369Y1 (en) Form system for retaining concrete wall
JPH0593422A (en) Continuous underground steel wall and construction method thereof
JP2001073685A (en) Work execution method of underground structure
CN112900525A (en) Groove excavation depth limiting device and groove excavation method