KR100904987B1 - Incremental launching method(i.l.m) for arch bridge structure using atemporary segment-supporter installed to substructureof bridge - Google Patents

Incremental launching method(i.l.m) for arch bridge structure using atemporary segment-supporter installed to substructureof bridge Download PDF

Info

Publication number
KR100904987B1
KR100904987B1 KR1020080107936A KR20080107936A KR100904987B1 KR 100904987 B1 KR100904987 B1 KR 100904987B1 KR 1020080107936 A KR1020080107936 A KR 1020080107936A KR 20080107936 A KR20080107936 A KR 20080107936A KR 100904987 B1 KR100904987 B1 KR 100904987B1
Authority
KR
South Korea
Prior art keywords
bridge
arch
cross
construction
extrusion
Prior art date
Application number
KR1020080107936A
Other languages
Korean (ko)
Inventor
김상복
조원섭
Original Assignee
현대스틸산업주식회사
경남기업 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 현대스틸산업주식회사, 경남기업 주식회사 filed Critical 현대스틸산업주식회사
Priority to KR1020080107936A priority Critical patent/KR100904987B1/en
Application granted granted Critical
Publication of KR100904987B1 publication Critical patent/KR100904987B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/06Methods or apparatus specially adapted for erecting or assembling bridges by translational movement of the bridge or bridge sections
    • E01D21/065Incremental launching
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D4/00Arch-type bridges

Abstract

An arch bridge construction method using an incremental launching method is provided to carry out construction of an arch bridge in case traffic control is difficult and bypasses are limited in carrying out temporary construction at the area in which national roads, freeways, train rails intersect. An arch bridge construction method using an incremental launching method comprises: a process of forming a propulsion yard having propulsion facility and a field assembly yard with a crossbeam; a process of extruding temporary bridge structure prefabricated in the field assembly yard through an extruding machine at the position for constructing the bridge(20) and constructing an arch-shaped structure(50); a process of extruding the arch-shaped structure manufactured in the field assembly yard on a span bridge of the bridge structure which is temporarily constructed and extruding the bridge structure to the field assembly yard and setting the arch-shaped structure to be fixed; and a process of dismantling facilities surrounding the arch bridge.

Description

연속압출공법을 이용한 아치교시공방법{incremental launching method(I.L.M) for Arch bridge structure using atemporary segment-supporter installed to substructureof bridge}Incremental launching method (I.L.M) for Arch bridge structure using atemporary segment-supporter installed to substructureof bridge}

본 발명은 연속압출공법(ILM:Increment Launching Method)을 이용한 아치교 시공방법에 관한 것으로 특히, 교량 시공할 교대 또는 교각의 연장선상에 교량 길이에 상응하는 추진시설과 추진장을 갖는 지조립장를 조성하여 상기 지조립장에서 완성된 가교구조물을 아치교 교량 시공 위치로 압출시키는 방법으로 경간가교를 가설하고, 지조립장에서 조립된 또 다른 아치구조물을 기시공된 가교구조물의 경간가교 위에 위치하도록 압출시킨 후 가교구조물 위로 압출된 아치구조물을 인양장치를 이용하여 상측으로 들어올린 상태에서 가교구조물을 지조립장쪽으로 피드백(feedback) 시켜 해체함과 동시에 인양장치에 의해 인상된 아치구조물을 양쪽 교대에 최종 세팅하는 방법으로 아치 교량을 건설함으로써 형하공간의 제약이 있고 보강토 및 인접공사의 중복으로 인해 우회도로확보 또한 제한적인 곳에서 적합하도록 된 아치교를 제공함에 있는 것이다.The present invention relates to an arch bridge construction method using a continuous extrusion method (ILM), and in particular, by forming a ground assembly site having a propulsion facility and a propulsion field corresponding to the bridge length on the bridge or extension of the bridge to be constructed Span bridge is constructed by extruding the completed cross-linked structure from the subassembly to the arch bridge construction site, and another arch structure assembled from the sub-assembly is extruded to be placed on the span bridge of the constructed cross-linked structure Arch bridges are formed by lifting the extruded arch structure upwards by lifting device and dismantling by feeding back the cross-linked structure to the paper assembly field and finally setting the arch structure raised by lifting device on both sides. Construction of the structure has limitations in the space of the geometry, Bypassing will also ensure that in providing the arch to fit in a limited area.

도로나 철도, 수로 또는 하천, 계곡, 농경지, 바다 등을 횡단하여 건설되는 도로교의 지간장은 짧게는 8~10m로부터 길게는 2000m의 해상 현수교에 이르기까지 그 분포가 다양하다.Road bridges constructed across roads, railways, waterways or rivers, valleys, farmland, and the sea can vary in length from 8 to 10m to 2000m long suspension bridges.

일반적으로 교량은 MSS공법, ILM공법(Incremental Launching Method), FCM공법, PSM공법(Prestressed Concrete Beam Bridge), FSM공법(Full Staging Method;동바리 공법)등이 있다.In general, bridges include MSS method, ILM method (Incremental Launching Method), FCM method, PSM method (Prestressed Concrete Beam Bridge), FSM method (Full Staging Method).

그 중에서 연속압출공법(ILM)은, 교대 배면에 위치한 제작장(지조립장)에서 교량상부구조물(콘크리트 또는 강재 등으로 제작된 각종 형상의 교량 바닥판 등)을 세그먼트(segment) 단위로 연속 제작(조립)하고 그 전면에 노즈(nose)를 연결한 상태에서 수직, 수평잭 등과 같은 압출용 교좌장치 및 압출유도장치에 의해 교량이 설치되어야 할 방향 즉, 교량 경간을 통과할 수 있는 수평압축력을 포스트텐션 방식에 의하여 상기 세그먼트구조물에 도입시킨 상태에서 교대방향으로 1개의 세그먼트씩 전진시키는 공정과 또 다른 세그먼트 단위의 다른 상판을 압출된 상판을 연결하는 작업을 반복적으로 수행하는 런칭을 통해 교량을 완성시키는 공법이다.Among them, the continuous extrusion method (ILM) continuously manufactures the upper structure of the bridge (bridge bottom plate of various shapes made of concrete or steel, etc.) in the unit of segment at the manufacturing site (paper assembly site) located on the rear side of the shift ( And the horizontal compression force that can pass through the span of the bridge by the extrusion bridge and extrusion guide device such as vertical and horizontal jacks, with the nose connected to the front of the bridge. Completion of the bridge by launching a step of advancing one by one segment in the alternating direction in the state introduced into the segment structure by the tension method and repeatedly connecting the extruded top plate to another top of the segment unit It is a construction method.

초기의 연속압출공법은 교량 연장만큼의 길이를 가진 제작장에서 전연장의 상부거더세그먼트(upper girder segment)를 제작하여 압출하였으나 제작장이 과다 소요되고 제작된 상부거더세그먼트를 소정의 위치로 이동시키기 위한 비용도 과다소모되어 경제성이 없는 것으로 평가 되었다.The initial continuous extrusion method produced and extruded the upper girder segment of the entire length in the workshop with the length as long as the extension of the bridge. However, it took too much workshop and moved the upper girder segment to the predetermined position. The cost was excessively consumed and evaluated as not economical.

그 후 마찰계수가 매우 작은 테프론판(teflon plate : sliding pad)이 개발되고 콘크리트 상부거더세그먼트에 프리스트레싱(prestressing)이 도입되는 등 연속적으로 압출할 수 있는 공법이 개발되어 현재까지 교량 시공에 적용되어 왔다.Since then, a teflon plate (sliding pad) with a very low coefficient of friction has been developed, and a pre-stressing method has been developed such as the introduction of prestressing to concrete upper girder segments, which has been applied to bridge construction until now. .

이러한 연속압출공법(ILM)은 비계작업 없이 시공할 수 있으므로 장애물(도 로, 철도, 강, 건물 보호지역, 깊은 계곡) 지역에 적용하기 적합하며, 공사 규모에 따라 거푸집에 대한 공사비가 절감되는 효과가 있다. 또한, 증기양생과 덮개 설치를 이용하여 기후에 관계없이 전천후 시공이 가능하며 교량연장이 긴 경우에는 공사기간이 단축되는 장점을 가지고 있다.Since the continuous extrusion method (ILM) can be constructed without scaffolding, it is suitable for obstacles (roads, railroads, rivers, building protected areas, deep valleys), and construction cost for formwork is reduced according to the construction scale. There is. In addition, all-weather construction is possible regardless of climate by using steam curing and cover installation, and in case of long bridge extension, construction period is shortened.

그리고 세그먼트 제작 및 시공 장소가 일정하여 공사 지연없이 반복 진행할 수 있어 공정관리가 용이하고, 세그먼트 제작과 전체 교량시공작업이 사이클화되어 소수의 인원으로 숙련된 작업을 할 수 있고, 세그먼트 거푸집이 기계화되어 조립 및 해체가 신속하고, 단면치수의 정도가 높은 주형을 용이하게 제작할 수 있고, 모든 공정이 일정한 장소에서 이루어지므로 자재의 운송이 편리하여 작업의 능률화를 꾀할 수 있다는 장점이 있다.In addition, the segment production and construction site is constant so that it can be repeated without construction delay, so it is easy to manage the process, and the segment production and the entire bridge construction work are cycled, so that the skilled work can be done with a few people, and the segment formwork is Fast assembly and disassembly, easy to manufacture molds with high degree of cross-sectional dimension, and all the processes are made in a certain place, there is an advantage that it is convenient to transport the material to streamline the work.

또한, 동바리 가설을 필요로 하지 않으므로 동바리 가설이 용이하지 않은 깊은 계곡이나 하천 등을 횡단할 경우에는 특히 경제적이며, 교량 상부공정을 하부구조 공정과 병행하여 실시하므로 공기가 단축되는 장점이 있다.In addition, it is particularly economical when traversing deep valleys or streams, which are not easy to install, since it does not require the Dongbari hypothesis, and the bridge upper process is performed in parallel with the substructure process.

반면에, 세그먼트 제작시 엄격한 시공관리가 필요하며, 교대 후방 또는 제1교대의 후방에 세그먼트를 제작을 위한 작업장 용지를 확보해야 하므로 작업장 설치의 제한을 받는다는 단점이 있지만 24시간 차량 통행이 줄지 않는 매우 혼잡한 고속도로 주변지역을 횡단하는 작업장의 경우 차량통제의 어려움과 더불어 보강토 및 인접공사의 중복으로 인한 우회도로 확보 또한 제한적이고, 기존 교량시공 방법으로 인한 각종 민원, 안전사고 등이 예상되는 작업장에서도 형하공간에 자유롭고 우회도로 확보 등의 추가 공정이 불필요한 합리적인 대안공법이 절실히 요구되고 있다.On the other hand, strict construction management is required when manufacturing a segment, and it is disadvantageous that it is restricted in the installation of the workshop because it is necessary to secure a workshop paper for manufacturing the segment at the rear of the shift or the rear of the first shift. In the case of workplaces crossing the congested highway area, it is not only difficult to control the vehicle, but it is also possible to secure a detour road due to overlapping reinforcement soils and adjacent constructions. There is an urgent need for a rational alternative method that is free of space and requires no additional steps such as securing a bypass.

이에 본 발명의 연속압출공법(ILM)을 이용한 아치교시공방법이 해결하고자 하는 과제는, 통행이 빈번한 기존 국도나 고속도로, 고속전철 등이 교차하는 지역에서의 가설공사 진행시 차량통제에 어려움이 있고, 보강토 및 인접공사의 중복으로 우회로 확보 또한 제한적인 경우에도 합리적인 방법으로 아치교를 시공하고자 하는데 그 목적이 있는 것이다.Therefore, the problem to be solved by the arch bridge construction method using the continuous extrusion method (ILM) of the present invention, there is a difficulty in controlling the vehicle during the construction of the temporary construction in the intersection of the existing national road, highway, high-speed train, etc. The purpose of this is to construct the arch bridge in a reasonable way even if the detours are limited by overlapping reinforcement soil and adjacent construction.

본 발명의 또 다른 목적은 기존 공법들의 문제점과 제약사항들을 극복 또는 개선하여 경제성이 우수하며, 단순공정에 의한 교량시공이 가능하도록 개선된 아치교시공방법을 제공함에 있는 것이다.Still another object of the present invention is to provide an improved arch bridge construction method which is excellent in economic efficiency and enables bridge construction by a simple process by overcoming or improving problems and limitations of existing construction methods.

본 발명의 또 다른 목적은 종래보다 형고(Beam높이)가 월등히 낮아 형하공간 확보에 유리한 아치교를 제공함에 있는 것이다.Another object of the present invention is to provide an arch bridge that is much lower than the conventional height (Beam height), which is advantageous for securing the space.

본 발명의 연속압출공법을 이용한 아치교시공방법이 해결하고자 하는 과제 해결수단은, 교량을 시공할 교대의 한쪽 연장선상에 가교구조물(20)과 아치구조물(50)을 각각 조립할 수 있도록 교량 길이에 상응하는 추진시설을 갖는 추진장(12)과 크로스빔(14)이 구비되는 지조립장(10)을 조성하여 상기 지조립장(10)에서 먼저 조립된 가교구조물(20)은 압출장치를 매개로 교량을 시공할 위치로 압출시켜 아치구조물(50) 시공을 위한 경간가교를 가설하고, 상기 지조립장(10)에서 조립되는 아치구조물(50)은 가설된 가교구조물(20)의 상부측으로 압출 이동시킨 후, 인양장치(70)를 이용하여 가교구조물(20) 위의 상기 아치구조물(50)을 상부측으로 들어올린 상태에서 압출장치를 매개로 가설된 가교구조물(20)을 지조립장(10)쪽으로 피드백(feedback) 시켜 가교구조물(20) 제거 및 해체함과 동시에 인양장치(70)에 의해 인상된 아치구조물(50)을 양쪽 교대에 하강 및 세팅하는 방법으로 아치 교량을 건설하는 것을 특징으로 하는 연속압출공법을 이용한 아치교시공방법이 제공된다.The problem solving means to be solved by the arch bridge construction method using the continuous extrusion method of the present invention, corresponding to the bridge length to assemble the bridge structure 20 and the arch structure 50 on one extension line of the alternating bridge construction The cross-linked structure 20, which is first assembled in the ground assembly 10 by forming a ground assembly 10 having a propulsion plant 12 having a propulsion facility and a cross beam 14, is used to form a bridge through an extrusion device. Extruded to the construction site to install the bridge construction for the construction of the arch structure 50, the arch structure 50 assembled in the support assembly 10 is extruded and moved to the upper side of the cross-linked structure 20, In the state in which the arch structure 50 on the cross-linked structure 20 is lifted to the upper side by using the lifting device 70, the cross-linked structure 20 installed through the extrusion device is fed back toward the paper assembly 10. To remove the cross-linked structure (20) And the arch bridge construction method using a continuous extrusion method is characterized in that the construction of the arch bridge by the method of lowering and setting the arch structure 50, which is lifted by the lifting device 70 at both shifts and at the same time.

상기한 연속압출공법을 이용한 아치교시공방법은, 교량이 시공될 교대 또는 교각(P:P1 또는 P2)의 한쪽 연장선상에 추진시설을 갖는 추진장(12)과 크로스빔(14)이 구비되는 지조립장(10)을 조성하는 지조립장 조성공정과;According to the arch bridge construction method using the continuous extrusion method, the propulsion site 12 having a propulsion facility and a cross beam 14 having a propulsion facility on one extension line of a bridge or a bridge P: P1 or P2 on which a bridge is to be constructed is provided. A paper granulation field forming step of forming the lip length 10;

교량이 시공될 기존 도로상에 다수의 가설벤트(15:15a,15b,15c)를 순차적으로 시공하는 단계(S2)와, 지조립장(10)의 추진장(12)에 가교(20a,20b,20c,…)들이 순차적으로 조립되는 가교구조물(20)을 제작하여 그 선단부에 런칭노즈(17)를 조립하는 단계(S3)와, 런칭노즈(17)가 조립된 가교구조물(20)을 압출장치를 매개로 교량 시공위치로 압출(Launching)시키는 단계(S4)와, 압출이 완료된 가교구조물(20)에서 런칭노즈(17)를 해체하는 단계(S5), 런칭노즈(17)가 해체된 가교구조물(20)을 횡이동시스템(30;Pulling)을 이용하여 정위치로 이동 및 세팅(Setting)하는 단계(S6)와, 정위치에 세팅된 가교구조물(20)에 안전시설(40)을 설치하는 단계(S7)로 시공되는 경간가교 가설공정과;Constructing a plurality of temporary vents (15: 15a, 15b, 15c) sequentially on the existing road to be built bridge (S2), bridge (20a, 20b, to the propulsion site 12 of the subassembly 10) 20c, ... to fabricate the cross-linked structure 20 is sequentially assembled to the step (S3) of assembling the launching nose 17 at its distal end, and the cross-linked structure 20 is assembled to the launching nose (17) extrusion device Extruding (Launching) to the bridge construction site via the step (S4), the step of dismantling the launch nose 17 in the cross-linked structure 20, the extrusion is completed (S5), the cross-linked structure in which the launch nose 17 is dismantled Step (S6) of moving and setting to the right position by using the lateral movement system 30 (Pulling) (S6), and to install the safety facility 40 in the cross-linked structure 20 is set in place Span bridge construction step constructed in step (S7);

지조립장(10)의 추진장(12)에서 아치구조물(50)을 조립하는 단계(S8)와, 조립된 아치구조물(50)에 압출장치를 조립하는 단계(S9)와, 압출장치를 매개로 아치구조물(50)을 기시공된 가교구조물(20) 위쪽으로 압출시키는 단계(S10)와, 압출된 아치구조물(50)에서 압출장치를 해체하고 인양장치(70)를 설치하는 단계(S11)와, 인양장치를 이용하여 아치구조물(50)을 인상하는 단계(S12)와, 인양장치에 의해 인상된 아치구조물(50)의 하부측에 위치한 가교구조물(20)을 횡이동시스템을 이용하여 횡이동시킨 다음 런칭노즈(17)를 조립하는 단계(S13)와, 런칭노즈(17)가 조립된 가교구조물(20)을 압출장치를 이용하여 지조립장(10) 후방으로 압출하여 피드백된 가교구조물(20)을 해체하는 단계(S14)와, 인양장치(70)에 의해 인상된 아치구조물(50)을 양쪽 교각(P2) 위로 인하시킨 후 세팅하는 단계(S15)로 시공되는 아치교 세팅공정과;Assembling the arch structure 50 in the propulsion site 12 of the paper assembly (10) (S8), Assembling the extrusion device to the assembled arch structure (S9), and through the extrusion device Extruding the arch structure 50 onto the construction of the cross-linked structure 20 (S10), disassembling the extrusion apparatus from the extruded arch structure 50 and installing the lifting device 70 (S11) and , Step (S12) of raising the arch structure 50 by using the lifting device, and the cross-linked structure 20 located on the lower side of the arch structure 50 lifted by the lifting device by the horizontal movement system. And then assembling the launching nose 17 (S13), and the crosslinked structure 20 to which the launching nose 17 is assembled is extruded to the rear of the paper assembly 10 by using an extrusion apparatus and fed back to the crosslinked structure 20 Step (S14) and the arch structure 50 lifted by the lifting device 70 is lowered on both piers (P2) and then set And the arch is set to be applied by the process step (S15);

인양장치(70)를 포함하는 아치교 주변의 시설물을 모두 해체하는 마무리단계(S17); 를 포함하는 연속압출공법을 이용한 아치교시공방법이 제공된다.A finishing step of dismantling all the facilities around the arch bridge including the lifting device 70 (S17); Provided is an arch bridge construction method using a continuous extrusion method comprising a.

또한 교량을 시공할 교대의 양쪽 연장선상에 가교구조물(20)과 아치구조물(50)을 각각 조립할 수 있도록 교량 길이에 상응하는 추진시설을 갖는 추진장(12)과 크로스빔(14)이 구비되는 지조립장(10)(10')이 서로 마주하도록 나란히 조성하여 한쪽 지조립장(10)에서 조립된 가교구조물(20)은 압출장치를 매개로 교량을 시공할 위치로 압출시켜 아치구조물(50) 시공을 위한 경간가교를 가설하고, 다른 한쪽 지조립장(10')에서 조립되는 아치구조물(50)은 압출장치를 매개로 가설된 가교구조물(20)의 상부측으로 압출 이동시킨 후, 인양장치(70)를 이용하여 가교구조물(20) 위로 이송된 아치구조물(50)을 상부측으로 들어올린 상태에서 압출장치를 매개로 가설된 가교구조물(20)을 지조립장(10)쪽으로 피드백(feedback) 시켜 가교구조물(20) 제거 및 해체함과 동시에 인양장치(70)에 의해 인상된 아치구조물(50)을 양쪽 교대에 거치되도록 하강 및 세팅하는 방법으로 아치 교량을 건설하는 것을 특징으로 하는 연속압출공법을 이용한 아치교시공방법이 제공된다.In addition, the propulsion site 12 and the cross beam 14 having a propulsion facility corresponding to the bridge length are provided so that the bridge structure 20 and the arch structure 50 can be assembled on both extension lines of the bridge to be constructed. The cross-sectional structure 20 assembled side by side so that the support sheet 10 (10 ') facing each other is assembled in one of the support sheet (10) is extruded to the position where the bridge construction via the extrusion device construction of the arch structure (50) After installing the span bridge for the arch structure 50 is assembled in the other support assembly (10 ') is extruded and moved to the upper side of the cross-linked structure 20 is installed through the extrusion device, the lifting device 70 In the state in which the arch structure 50 transferred to the cross-linked structure 20 is lifted to the upper side by using the extruder, the cross-linked structure 20 is fed back to the support assembly 10 to the cross-linked structure ( 20) Lifting device at the same time as removal and dismantling There is provided an arch bridge construction method using a continuous extrusion method, characterized in that the arch bridge is constructed by descending and setting the arch structure 50, which is lifted by) to be mounted on both shifts.

상기한 연속압출공법을 이용한 아치교시공방법은, 교량이 시공될 교대 또는 교각(P:P1 또는 P2)의 양쪽 연장선상에 교량 길이에 상응하는 추진시설을 갖는 추진장(12)과 크로스빔(14)이 구비되는 가교구조물(20)과 아치구조물(50) 가설을 위한 지조립장(10)(10')이 서로 마주하도록 나란히 조성하는 단계(S1);According to the arch bridge construction method using the continuous extrusion method, the propulsion field 12 and the cross beam 14 having a propulsion facility corresponding to the bridge length on both extension lines of the bridges or bridges P: P1 or P2 on which the bridge is to be constructed. (S1) forming side by side so that the cross-linking structure 20 and the arch assembly 50 for the construction of the arch structure 50 are provided to face each other;

교량이 시공될 기존 도로상에 다수의 가설벤트(15:15a,15b,15c)를 순차적으로 시공하는 단계(S2)와, 지조립장(10)의 추진장(12)에 가교(20a,20b,20c,…)들이 순차적으로 조립되는 가교구조물(20)을 제작하여 그 선단부에 런칭노즈(17)를 조립하는 단계(S3)와, 런칭노즈(17)가 조립된 가교구조물(20)을 압출장치를 매개로 교량 시공위치로 압출(Launching)시키는 단계(S4)와, 압출이 완료된 가교구조물(20)에서 런칭노즈(17)를 해체하는 단계(S5), 런칭노즈(17)가 해체된 가교구조물(20)을 횡이동시스템(30;Pulling)을 이용하여 정위치로 이동 및 세팅(Setting)하는 단계(S6)와, 정위치에 세팅된 가교구조물(20)에 안전시설(40)을 설치하는 단계(S7)로 시공되는 경간가교 가설공정과;,Constructing a plurality of temporary vents (15: 15a, 15b, 15c) sequentially on the existing road to be built bridge (S2), bridge (20a, 20b, to the propulsion site 12 of the subassembly 10) 20c, ... to fabricate the cross-linked structure 20 is sequentially assembled to the step (S3) of assembling the launching nose 17 at its distal end, and the cross-linked structure 20 is assembled to the launching nose (17) extrusion device Extruding (Launching) to the bridge construction site via the step (S4), the step of dismantling the launch nose 17 in the cross-linked structure 20, the extrusion is completed (S5), the cross-linked structure in which the launch nose 17 is dismantled Step (S6) of moving and setting to the right position by using the lateral movement system 30 (Pulling) (S6), and to install the safety facility 40 in the cross-linked structure 20 is set in place Span bridge construction step constructed in step (S7) ;,

지조립장(10')의 추진장(12)에서 아치구조물(50)을 조립하는 단계(S8)와, 조립된 아치구조물(50)에 압출장치를 조립하는 단계(S9)와, 압출장치를 매개로 아치구조물(50)을 기시공된 가교구조물(20) 위쪽으로 압출시키는 단계(S10)와, 압출된 아치구조물(50)에서 압출장치를 해체하고 인양장치(70)를 설치하는 단계(S11)와, 인양장치를 이용하여 아치구조물(50)을 인상하는 단계(S12)와, 인양장치에 의해 인상된 아치구조물(50)의 하부측에 위치한 가교구조물(20)을 횡이동시스템을 이용하여 횡이동시킨 다음 런칭노즈(17)를 조립하는 단계(S13), 런칭노즈(17)가 조립된 가교구조물(20)을 압출장치를 이용하여 지조립장(10) 후방으로 압출하여 피드백된 가교구조물(20)을 해체하는 단계(S14), 인양장치(70)에 의해 인상된 아치구조 물(50)을 양쪽 교각(P2) 위로 인하시킨 후 세팅하는 단계(S15)로 시공되는 아치교 세팅공정과;,Assembling the arch structure 50 in the propulsion site 12 of the paper assembly (10 ') (S8), Assembling the extrusion device to the assembled arch structure (S9), and through the extrusion device Extruding the furnace arch structure 50 to the construction of the crosslinked structure 20 (S10), and disassembling the extrusion apparatus from the extruded arch structure 50 and installing the lifting device 70 (S11). And, the step (S12) for raising the arch structure 50 by using the lifting device, and the cross-linked structure 20 located on the lower side of the arch structure 50 is lifted by the lifting device by the horizontal movement system Moving and then assembling the launching nose (17) (S13), the crosslinked structure 20 is assembled by the launching nose 17 is extruded to the rear of the paper assembly (10) by using an extrusion apparatus fed back cross-linked structure (20) ) Step (S14), the arch structure 50 is lifted by the lifting device 70 is lowered on both piers (P2) and then set An arch bridge setting process constructed in step S15;

인양장치(70)를 포함하는 아치교 주변의 시설물을 모두 해체하는 마무리단계(S17)를 포함하는 연속압출공법을 이용한 아치교시공방법이 제공된다.Provided is an arch bridge construction method using a continuous extrusion method including a finishing step (S17) of dismantling all the facilities around the arch bridge including the lifting device 70.

본 발명의 연속압출식 아치교시공방법은 교대의 한쪽 연장선을 공유하는 지조립장을 조성하여 상기 지조립장에서 가교구조물을 조립하여 교량 시공 위치로 런칭되는 경간가교를 시공하고, 지조립장에서 제작된 아치구조물은 상기 가교구조물 위쪽으로 런칭(pushing or pulling) 및 세팅하여 교량을 시공하고, 기시공된 가교구조물은 압출장치를 이용하여 지조립장쪽으로 피드백시킨 다음 해체하는 방법으로 아치교를 건설함으로써 형하공간의 제약이 있거나, 보강토 및 인접공사의 중복으로 우회도로확보에 어려움이 있는 작업장에서 신속하게 교량을 가설할 수 있다는 이점이 있는 것이다.Continuous extrusion type arch bridge construction method of the present invention forms a bridge assembly to share one extension line of the shift to assemble a cross-linked structure in the bridge assembly to construct a bridge bridge that is launched to the bridge construction site, the arch structure manufactured in the ground assembly site The construction of the bridge by launching (pushing or pulling) and setting the bridge over the cross-linked structure, and the construction of the arch bridge by constructing the arch bridge by feeding back to the paper assembly site using an extrusion device and then dismantling the restriction of the geometry space Or, there is an advantage that the bridge can be constructed quickly in the workplace where it is difficult to secure the bypass road due to the overlap of reinforcement soil and adjacent construction.

또한, 본 발명은 교량구조물이 일정한 장소에서 작업이 가능하여 정밀시공 및 우수한 품질확보, 공정관리에 유리하고, 압출시 압출장치 이외의 기중기나 비계설비 등이 불필요하고, 하부공간에 지장을 주지 않고 교각이 높은 경우에 효율적으로 안정적인 교량을 제공할 수 있는 이점이 있다.In addition, the present invention is advantageous in precision construction, excellent quality, process control, the bridge structure is possible to work in a certain place, it is unnecessary for the extruder crane or scaffolding equipment, etc., without disturbing the lower space In the case of high pier, there is an advantage that can provide an efficient and stable bridge.

이하, 본 발명의 구체적인 실시 예를 첨부도면을 참고하여 보다 상세하게 설명하면 다음과 같다.Hereinafter, specific embodiments of the present invention will be described in detail with reference to the accompanying drawings.

첨부도면 도 1은 본 발명에 따른 연속압출공법(ILM)을 이용한 아치교시공방법을 설명하기 위한 블록도이다.1 is a block diagram illustrating an arch bridge construction method using a continuous extrusion method (ILM) according to the present invention.

<제1 실시예><First Embodiment>

본 발명은 교대의 한쪽 연장선상에 교량 길이에 상응하는 추진시설을 갖는 추진장(12)과 크로스빔(14)을 공유하는 지조립장(10)을 조성하여 상기 지조립장(10)에서 조립되는 가교구조물(20)은 압출장치를 매개로 교량을 시공할 위치로 압출되는 경간가교를 가설하고, 상대쪽 지조립장(10)에서 조립되는 아치구조물(50)은 압출장치를 매개로 가교구조물(20)의 상부측으로 압출하여 세팅하되, 가교구조물(20)은 인양장치(70)를 이용한 아치구조물(50) 인상시 압출장치를 이용하여 지조립장(10)쪽으로 피드백 시킨 후 해체하는 것을 특징으로 하고 있다.The present invention is to form a cross-sectional assembly (10) sharing the propulsion field 12 and the cross beam 14 having a propulsion facility corresponding to the bridge length on one extension line of the bridge bridge to be assembled in the sheet assembly (10) Structure 20 is the construction of the bridge bridge is extruded to the construction site via the extrusion device, the arch structure 50 is assembled in the mating support 10, the cross-linked structure 20 via the extrusion device Extruded and set to the upper side of the cross-linked structure 20 is characterized in that the dismantled after feeding back to the support assembly 10 using the extrusion device when the arch structure 50 is lifted using the lifting device 70.

이에 따라 본 발명은 교량이 시공될 교대 또는 교각(P:P1 또는 P2)의 한쪽 연장선상에 교량의 길이에 상응하는 크기의 지조립장(10)을 조성하는 지조립장 조성공정과;, 지조립장(10)에서 조립된 가교구조물(20)을 교량 시공위치로 압출시킨 후 정위치에 세팅(Setting)하는 경간가교 가설공정과;, 지조립장(10)에서 제작된 아치(Arch)교구조물(50)을 가설된 가교구조물(20)의 경간가교 위로 압출시킨 후 가교구조물(20)을 지조립장으로 압출 및 해체한 후 아치구조물을 고정되게 세팅하는 아치교 세팅공정과;, 아치교 주변의 시설물을 모두 해체하는 마무리공정을 포함하고 있는 것이다.Accordingly, the present invention is a paper assembly field forming process for forming a paper sheet 10 of the size corresponding to the length of the bridge on one extension of the bridge or bridge (P: P1 or P2) to be constructed; 10) span bridge construction process of extruded cross-linked structure 20 assembled in the bridge construction position and then set in place; Arch structure (50) fabricated in the support assembly (10) After the extruded over the span bridge of the hypothesized cross-linked structure 20, the cross-linked structure 20 is extruded and dismantled into a paper assembly, and the arch bridge setting step of setting the arch structure fixed; and, all the facilities around the arch bridge It includes the finishing process.

상기 구성에 있어서, 지조립장 조성공정은 교량이 시공될 교대 또는 교 각(P:P1 또는 P2)의 한쪽 연장선상에 교량의 길이에 상응하는 크기의 추진시설을 갖는 추진장(12)과 크로스빔(14)이 설치하는 단계(S1)로 구성된다.In the above configuration, the subassembly forming process is performed by the propulsion field 12 and the cross beam having a propulsion facility having a size corresponding to the length of the bridge on one extension of the alternating or pier P: P1 or P2 on which the bridge is to be constructed. 14 comprises a step S1 of installation.

아치구조물(50)을 시공하기 위한 경간가교 가설공정은 교량이 시공될 기존 도로상에 다수의 가설벤트(15:15a,15b,15c)를 순차적으로 시공하는 단계(S2)와, 지조립장(10)의 추진장(12)에 단위 가교(20a,20b,20c,…)들이 순차적으로 조립되는 가교구조물(20)을 제작하여 그 선단부에 런칭노즈(17)를 조립하는 단계(S3)와, 런칭노즈(17)가 조립된 가교구조물(20)을 압출장치를 매개로 교량 시공위치의 상대쪽 교각까지 압출(Launching)시키는 단계(S4)와, 압출이 완료된 가교구조물(20)에서 런칭노즈(17)를 분리 해체하는 단계(S5), 런칭노즈(17)가 해체된 가교구조물(20)을 횡이동시스템(30;Pulling)을 이용하여 정위치로 이동 및 세팅(Setting)하는 단계(S6)와, 정위치에 세팅된 가교구조물(20)에 안전시설(40)을 설치하는 단계(S7)를 포함하고 있다.Span bridge construction process for the construction of the arch structure (50) is a step (S2) to sequentially install a plurality of construction vents (15: 15a, 15b, 15c) on the existing road to be bridge construction, and the ground assembly (10) In step (S3) and assembling the launching nose (17) at the distal end of the bridge structure (20a, 20b, 20c, ...) to form a cross-linked structure 20 is sequentially assembled in the propulsion field 12) The step (Launching) of the cross-linked structure 20 assembled with the nose 17 to the opposite piers of the bridge construction position via the extrusion device (S4), and the launching nose (17) in the cross-linked structure 20 is completed extrusion Step (S6) of separating and dismantling (S5), and moving and setting the crosslinked structure 20 in which the launching nose 17 is dismantled, using a lateral movement system 30 (Pulling) and setting (S6). It includes a step (S7) for installing the safety facility 40 in the cross-linked structure 20 is set in place.

또한, 아치구조물(50) 세팅공정은 지조립장(10)의 추진장(12)에 아치(Arch)교 구조물(50)을 조립하는 단계(S8)와, 조립된 아치구조물(50)에 압출장치를 조립하는 단계(S9)와, 압출장치를 매개로 아치구조물(50)을 가설된 가교구조물(20) 위로 압출시키는 단계(S10)와, 압출 이동된 아치구조물(50)에서 압출장치를 해체하고 인양장치를 설치하는 단계(S11)와, 인양장치를 이용하여 아치구조물(50)을 인상하는 단계(S12)와, 인양장치에 의해 인상된 아치구조물(50)의 하부측에 위치한 가교구조물(20)을 횡이동시스템을 이용하여 횡이동시킨 다음 런칭노즈(17)를 조립하는 단계(S13), 런칭노즈(17)가 조립된 가교구조물(20)을 압출장치를 이용하여 지조립장(10) 후방으로 압출하여 피드백된 가교구조물(20)을 해체하는 단계(S14), 인양장치(70)에 의해 인상된 아치구조물(50)을 양쪽 교각(P2) 위로 인하시킨 후 세팅하는 단계(S15)를 포함하고 있다.In addition, the arch structure 50 setting process is a step (S8) of assembling the arch (Arch) bridge structure 50 to the propulsion site 12 of the support assembly 10, and the extrusion device to the assembled arch structure 50 Assembling the step (S9), the step of extruding the arch structure 50 over the hypothesized cross-linked structure 20 via the extrusion device (S10), and dismantled the extrusion apparatus in the extrusion moved arch structure 50 Installing the lifting device (S11), the step of raising the arch structure 50 using the lifting device (S12), and the cross-linked structure 20 located on the lower side of the arch structure 50 lifted by the lifting device ) And laterally assembling the launching nose 17 (S13), the cross-linked structure 20 assembled with the launching nose 17 by using an extrusion device to the rear of the paper assembly (10) Step (S14) of dismantling the fed back cross-linked structure 20 by extruded, both cross the arch structure 50 is lifted by the lifting device 70 After the cut the top (P2) includes a step (S15) of setting.

본 발명에 따른 연속압출공법(ILM)을 이용한 아치교시공방법에 의한 아치교가 시공되는 것을 설명하면 다음과 같다.Referring to the construction of the arch bridge by the arch bridge construction method using the continuous extrusion method (ILM) according to the present invention.

도 2a 내지 도 2c는 교대의 한쪽 연장선상에 지조립장이 조성되는 것을 나타내고 있는 것으로, 교량이 시공될 교대 또는 교각(P:P1 또는 P2)의 한쪽 연장선상에 교량의 길이에 상응하는 크기의 추진시설을 갖는 추진장(12)과 크로스빔(14)(COROSS BEAM)이 설치되는 지조립장(10)이 조성된다.(S1)2A to 2C show that the subassembly is formed on one extension line of the shift, the propulsion having a size corresponding to the length of the bridge on one extension line of the shift or the bridge P: P1 or P2 to be constructed. A paper assembly field 10 on which a propulsion field 12 having a facility and a cross beam 14 (COROSS BEAM) is installed is formed. (S1)

지조립장(10)의 추진장(12)은 시공하고자 하는 교량 길이에 상응하는 길이이상으로 평탄하게 조성되는 지반위에 타설되는 하부 기초콘크리트(11)에 가교(20)(HV-BOX) 조립 및 추진장 설치를 위한 반력대(12a)와 런칭롤러(12b)가 구비되는 한쌍의 레일(Rail)로 구성되고, 가교구조물(20)을 압출시키기 위한 압출장치를 더 포함하고 있다.Assembling and pushing the bridge (20) (HV-BOX) to the lower foundation concrete 11 is placed on the ground that is formed flat above the length corresponding to the bridge length to be constructed It consists of a pair of rails (Rail) provided with a reaction table (12a) and the launching roller (12b) for installing the field, and further comprises an extrusion device for extruding the cross-linked structure (20).

상기 레일(12)의 양쪽에는 소정 간격으로 이격되는 다수의 크로스빔(COROSS BEAM)(14)들이 양쪽 가장자리면을 따라 길이방향으로 길게 배치되고 있다.On both sides of the rail 12, a plurality of cross beams (COROSS BEAM) 14 spaced at predetermined intervals are arranged in the longitudinal direction along both edge surfaces.

도 3은 교량이 시공될 기존 도로상에 다수의 가설벤트가 설치되는 것을 나타내고 있는 것으로, 가설벤트(15)는 기중기(16)를 이용하여 1~3개소에 가설벤트(15a,15b,15c)가 순차적으로 시공되어 교량 시공 위치로 압출되는 가교구조물(20)의 하부측을 지지하도록 되어 있다(S2). 가설벤트(15)는 교량 시공을 위한 임시구조물로 교량 시공후에는 모두 해체한다.FIG. 3 shows that a plurality of temporary vents are installed on an existing road on which a bridge is to be constructed. The temporary vents 15 may be installed at one or three locations by using a crane 16 (15a, 15b, and 15c). Is sequentially constructed to support the lower side of the cross-linked structure 20 which is extruded to the bridge construction position (S2). Temporary vent (15) is a temporary structure for the construction of the bridge after the bridge construction all dismantled.

가교구조물(20)은 지조립장(10)의 추진장(12)에서 다수의 가교(20a,20b,20c,…)들이 순차적으로 연결되도록 조립되어 추후 아치구조물을 압출을 유도하는 가교 역활을 하도록 수행한다.The crosslinked structure 20 is assembled so that a plurality of bridges (20a, 20b, 20c, ...) are sequentially connected in the propulsion field 12 of the support assembly 10 to perform a crosslinking role to induce extrusion of the arch structure later. do.

가교구조물(20)의 선단에는 도 4a에 나타낸 바와 같이 기중기(16)를 이용하여 런칭노즈(17)(Launching Nose)를 고정되도록 조립된다(S3).At the front end of the cross-linked structure 20, as shown in FIG. 4A, the launching nozzle 17 is assembled using a crane 16 (S3).

런칭노즈(17)는 첫번째 가설벤트(15a)의 상부측에 런칭노즈(17)의 일측단을 거치시킨 상태에서 타측단이 가교구조물(20)의 선단에 조립하여 압출장치와 추진장치를 매개로 가교구조물(20)이 교량시공 위치로 압출(Launching)시키도록 되어 있다.The launching nose 17 has one end of the launching nose 17 mounted on the upper side of the first temporary vent 15a, and the other end is assembled to the front end of the cross-linked structure 20 by means of an extrusion device and a propulsion device. The crosslinked structure 20 is adapted to extrude to a bridge construction position.

런칭노즈(17)가 조립된 가교구조물(20)을 압출장치를 매개로 교량 시공위치의 상대쪽 교각(P2)까지 압출(Launching)시킨다(S4).The crosslinked structure 20 having the launching nose 17 assembled therein is extruded (Launching) to the opposite piers P2 at the bridge construction position through an extrusion apparatus (S4).

압출장치에 의해 양쪽 교각(P1)(P2)사이로 압출되는 가교구조물(20)의 하부면은 도 4b에서와 같이 기존 도로상에 설치한 가설벤트(15a,15b,15c)들에 거치시켜 런칭시 정(+), 부(-)모멘트 구간을 통과하는 구조계 변화에 따른 구조물의 강성확보할 수 있게 한다.The lower surface of the cross-linked structure 20, which is extruded between both piers P1 and P2 by an extrusion device, is mounted on temporary constructions 15a, 15b, and 15c installed on an existing road as shown in FIG. 4b. It is possible to secure the rigidity of the structure according to the structural change through the positive and negative moment sections.

가교구조물(20)를 런칭하기 위한 압출장치는 슬라이딩 패드(Sliding Pad)와 같은 스키드 타입(Skid Type)으로 구성되고, 압출이 용이하게 이루어질 수 있도록 런칭롤러(Launching Roller) 및 가이드롤러(Guide Roller)도 함께 구비하고 있다. 상기 압출장치는 압출되는 가교구조물(20)의 한쪽 선단이 상대쪽 교각(P2)에 일부 가 거치되는 위치까지 압출시킨다.Extrusion apparatus for launching the cross-linked structure 20 is composed of a skid type (Skid Type), such as a sliding pad, the launching roller (Launching Roller) and a guide roller (Guide Roller) to facilitate the extrusion Also equipped with. The extruder is extruded to a position where one end of the cross-linked structure 20 to be extruded is partially mounted on the opposite piers (P2).

이처럼 교량 시공위치로 가교구조물(20)를 런칭시킨 후에는 그 선단에 조립된 런칭노즈(17)는 기중기(16)를 이용하여 해체한다.(S5)After launching the cross-linked structure 20 to the bridge construction position as described above, the launching nose 17 assembled at its tip is dismantled using the crane 16 (S5).

한편, 런칭노즈(17)가 해체된 가교구조물(20)은 도 5a에 도시된 바와 같이 가설벤트(15a,15b,15c)에 부설되는 횡이동시스템(30;Pulling)을 이용하여 정위치로 이동(화살표 방향) 및 세팅(Setting)한다(S6).Meanwhile, the crosslinked structure 20 in which the launching nose 17 is dismantled is moved to a proper position by using a lateral moving system 30 installed in the temporary fittings 15a, 15b, and 15c as shown in FIG. 5a. (Arrow direction) and setting (S6).

정위치에 세팅되는 가교구조물(20)에는 안전시설(40)을 설치한다.(S7) 상기 안전시설(40)은 도 5b에 나타낸 바와 같이 정위치에 세팅된 가교구조물(20)의 상부측으로 아치구조물(50)을 압출시킬 때 전도 및 비틀림에 대처하는 구조적 안정성을 확보할 수 있게 한다.The safety facility 40 is installed in the bridge structure 20 which is set in place. (S7) The safety facility 40 is arched to the upper side of the bridge structure 20 set in place as shown in FIG. 5B. When extruding the structure 50 it is possible to ensure the structural stability to cope with the fall and twist.

또한, 가교구조물(20)의 하부측을 지지하는 각각의 가설벤트(15a,15b,15c)에 부설되는 별도의 교좌장치를 이용하여 가교구조물(20)을 견고하게 고정하여 가교구조물(20)에 의한 경간가설을 모두 완료한다(S7).In addition, the crosslinked structure 20 is firmly fixed to the crosslinked structure 20 by using a separate crossover device attached to each of the temporary vents 15a, 15b, and 15c supporting the lower side of the crosslinked structure 20. Complete all of the span hypothesis (S7).

이와 같이 지조립장에서 제작되어 교량 시공위치로 가교구조물(20)을 압출 및 정위치에 세팅이 완료되면 본 구조물 즉, 아치교를 제작한다.As such, when the assembly is completed and the setting of the cross-linked structure 20 to the bridge construction position is completed, the construction of the arch bridge is completed.

아치교는 도 6a, 6b에 나타낸 바와 같이 지조립장(10)에 설치되는 조립정반(H-250x250x 9x14(SS400))에 보강형 및 단부(51)를 조립한 다음 아치조립장비(52)(250Tonf Crwaller Crane)를 이용하여 아치교를 조립을 위한 아치벤트(Arch Bent)와 아치리브(Arch Rib)와 함께 1, 2, 3단 아치(53a,53b,53c) 기둥(Strut), 버팀대(Brach) 및 최종 상부구조물(Key Seg Arch Rib)등을 순차적으로 조립하여 도 6c와 같이 아치구조물(50)을 완성한다(S8).6A and 6B, the arch bridge is assembled with the reinforcing type and the end 51 to the assembly plate (H-250x250x 9x14 (SS400)) installed in the support assembly 10, and then the arch assembly equipment 52 (250 Tonf Crwaller) 1, 2, 3 stage arches (53a, 53b, 53c) with arch vents and arch ribs for assembling arch bridges using cranes, struts, braces and final The upper structure (Key Seg Arch Rib), etc. are sequentially assembled to complete the arch structure 50 as shown in Figure 6c (S8).

이와 같이 지조립장(10)에서 조립된 아치구조물(50)은 런칭 준비를 위해 하부측에 이동대차(62)를 설치함과 동시에 조립정반(51) 및 아치벤트를 해체하고 아치구조물(50) 압출을 위한 압출장치를 조립한다.(S9)The arch structure 50 assembled in the support assembly 10 as described above dismantles the assembly plate 51 and the arch vent and extrudes the arch structure 50 at the same time as the mobile cart 62 is installed on the lower side to prepare for launching. Assemble the extrusion device for (S9).

상기 압출장치는 Pushing Hydraulic Jack (Grip Type) 2개와 유사시를 대비한 Winch System 4개를 함께 이용된다.The extrusion device is used with two Pushing Hydraulic Jack (Grip Type) and four Winch System in case of emergency.

아치구조물(50)은 도 7a, 7b에 나타낸 바와 같이 압출장치를 매개로 아치구조물(50)을 교량을 시공할 위치 즉, 기시공된 가교구조물(20) 위쪽으로 압출시키고, 가교구조물(20)의 상부측으로 압출된 아치구조물(50)은 아치벤트를 제거함과 동시에 케이블을 조립하여 아치구조물(50)을 보강한다.(S10)7A and 7B, the arch structure 50 is extruded through the extrusion apparatus via the extrusion device to the bridge construction position, that is, over the pre-installed cross-linked structure 20, the cross-linked structure 20 Arch structure 50 extruded to the upper side of the reinforcement of the arch structure 50 by assembling the cable at the same time to remove the arch vent (S10).

압출장치에 의해 아치구조물(50)이 가교구조물(20) 위쪽으로 압출이 완료되면 아치구조물(50)에서 압출장치를 모두 해체하고, 아치구조물(50)을 인상하기 위한 별도의 인양장치(70)를 조립한다(S11).When extrusion of the arch structure 50 is completed by the extrusion device to the cross-linked structure 20 is completed, all the lifting device is dismantled from the arch structure 50, the separate lifting device 70 for raising the arch structure 50 Assemble (S11).

인양장치(70)는 인용용량 900tonf 리프트(HEAVY LIFTING JACK)와 잭(JACK DOWN SYSTEM)으로 구성되어 아치구조물(50)의 지점부 4개소에 부설되는 리프팅용 가설지지벤트(72)에 고정되어 상기 인양장치(70)를 매개로 아치구조물(50)을 소정의 높이로 인상시켜 하부측에 조립된 이동대차(55)를 분리하여 하부측 가교구조물(20)과 결합상태를 모두 해지한다(S12).The lifting device 70 is composed of a citation capacity 900tonf lift (HEAVY LIFTING JACK) and a jack (JACK DOWN SYSTEM) is fixed to the lifting temporary support vent 72 to be installed at four points of the arch structure 50 is The arch structure 50 is lifted to a predetermined height by the lifting device 70 to separate the moving trolley 55 assembled at the lower side to terminate all of the coupling state with the lower side crosslinked structure 20 (S12). .

인양장치(70)에 의해 아치구조물(50)이 인상됨에 따라 그 하부측에 위치한 가교구조물(20)은 가설벤트(15)에 부설되는 횡이동시스템(30)을 이용하여 횡방향 (화살표방향)으로 이동시키고, 횡이동된 양쪽 가교구조물(20)에는 압출을 위한 런칭노즈(17)가 다시 조립된다(S13).As the arch structure 50 is lifted by the lifting device 70, the cross-linked structure 20 located on the lower side thereof is moved in the horizontal direction (arrow direction) by using the horizontal movement system 30 installed in the temporary vent 15. In the cross-linked structure 20, which is moved to the horizontal direction, the launching nose 17 for extrusion is assembled again (S13).

런칭노즈(17)가 조립된 가교구조물(20)은 압출장치를 이용하여 지조립장(10) 후방으로 압출되도록 피드백 시키고, 지조립장(10)으로 압출된 가교구조물(20)은 런칭노즈(17)를 분리한 후 모두 해체한다(S14). 이때 도로상에 시공된 가설벤트(15)도 모두 해체한다.The crosslinked structure 20 into which the launching nose 17 is assembled is fed back so as to be extruded to the rear of the subassembly 10 using an extrusion device, and the crosslinked structure 20 extruded into the subassembly 10 is the launching nose 17. After dismantling and dismantle all (S14). At this time, all of the temporary constructions 15 constructed on the road are dismantled.

한편, 인양장치(70)에 의해 인상된 아치구조물(50)은 도 10에서와 같이 양쪽 교각(P1,P2) 위로 인하시킨 다음 아치교가 견고하게 고정되도록 세팅하여 작업을 모두 완료한다(S15).On the other hand, the arch structure 50 is lifted by the lifting device 70 is lowered over both piers (P1, P2) as shown in Figure 10 and then set to securely secure the arch bridge (S15).

도 11에 나타낸 바와 같이 아치교가 시공된 후에는 인양장치(70)를 포함하는 아치교 주변의 시설물을 모두 해체하게 되면 아치교 시공 작업을 모두 종료되게 된다.(S17)After the arch bridge is constructed as shown in FIG. 11, if all the facilities around the arch bridge including the lifting device 70 are dismantled, the construction of the arch bridge is completed.

이상에서와 같이 본 발명의 연속압출공법을 이용한 아치교시공방법은 교량의 연장선상에 교량 길이에 상응하는 가교 추진장과 아치(Arch)교 추진장 가설을 위한 지조립장(10)에서 조립된 가교구조물(20) 및 아치구조물(50)을 압출장치를 매개로 교량을 시공할 위치로 런칭시키되, 아치구조물(50)은 압출장치를 매개로 가교구조물(20)의 상부측으로 런칭하고, 가교구조물(20)는 아치구조물(50) 시공후 지조립장(10)쪽으로 다시 피드 백(back)하여 제거 및 해체함으로써 통행량이 많은 기존 국도나 고속도로 및 보강토 및 인접공사의 중복으로 우회로 확보 또한 제한적인 경우에도 합리적인 방법으로 아치교를 건설할 수 있는 것이다.As described above, the arch bridge construction method using the continuous extrusion method of the present invention is a cross-linked structure assembled at the ground assembly 10 for the construction of a bridge propulsion bridge and arch bridge propulsion site corresponding to the bridge length on the extension line of the bridge. (20) and the arch structure 50 is launched to the position where the bridge construction via the extrusion device, the arch structure 50 is launched to the upper side of the cross-linked structure 20 via the extrusion device, the cross-linked structure (20) ) Is removed and dismantled by feeding back to the subassembly (10) after construction of the arch structure (50) to remove and dismantle. It is possible to build an arch bridge.

<제2 실시예>Second Embodiment

도 12a와 도 12b는 본 발명의 또 다른 실시예로 교대의 양쪽 연장선상에 교량 길이에 상응하는 지조립장이 각각 조성되는 것을 나타낸 평면도와 정면도이고, 도 13은 본 발명의 제 2 실시예를 설명하기 위한 블록도를 나타내고 있는 것이다.12A and 12B are a plan view and a front view of a paper assembly field corresponding to a bridge length respectively formed on both extension lines of a shift as another embodiment of the present invention, and FIG. 13 illustrates a second embodiment of the present invention. The block diagram for this is shown.

첨부도면 도 12a, 12b에 나타낸 바와 같이 교대의 양쪽 연장선상에 교량 길이에 상응하는 추진시설을 갖는 추진장(12)과 크로스빔(14)이 구비되는 지조립장(10)(10')을 서로 마주하도록 나란히 조성하여 상기 지조립장(10)에서 조립되는 가교구조물(20)은 압출장치를 매개로 교량 시공할 위치로 압출되는 경간가교를 가설하고, 상대쪽 지조립장(10')에서 조립되는 아치구조물(50)은 압출장치를 매개로 가교구조물(20)의 상부측으로 압출시키고, 가설된 가교구조물(20)은 인양장치(70)를 이용한 아치구조물(50) 인상시 압출장치를 이용하여 지조립장(10)쪽으로 피드백 시킨 후 해체하는 것을 특징으로 하는 연속압출공법을 이용한 아치교시공방법이 제공된다.As shown in Figs. 12A and 12B, the propulsion plant 12 having the propulsion facilities corresponding to the bridge length and the subassembly 10 and 10 'provided with the cross beams 14 on both extension lines of the shift are mutually supported. The cross-linked structure 20 assembled side by side so as to face each other and assembled in the support assembly 10 is hypothesized to span the bridge to be extruded to the position of the bridge construction via the extrusion device, the arch assembled in the opposite support assembly (10 ') The structure 50 is extruded to the upper side of the cross-linked structure 20 via an extrusion device, and the hypothesized cross-linked structure 20 is a paper assembly using the extrusion device when lifting the arch structure 50 using the lifting device 70 Provided is an arch bridge construction method using a continuous extrusion method characterized in that the dismantling after feedback to (10).

이에 따라 본 발명은 교량이 시공될 교대 또는 교각(P:P1 또는 P2)의 양쪽 연장선상에 교량의 길이에 상응하는 크기의 지조립장(10)(10')을 서로 마주하도록 나란히 조성하는 지조립장 조성공정과;, 지조립장(10)에서 조립된 가교구조물(20)을 교량 시공위치로 압출시킨 후 정위치에 세팅(Setting)하는 경간가교 가설공정과;, 지조립장(10')에서 제작된 아치(Arch)교구조물(50)을 기시공된 가교구조물(20)의 경간가교 위로 압출시킨 후 가교구조물(20)을 지조립장으로 압출 및 해체한 후 아치구조물을 고정되게 세팅하는 아치교 세팅공정과;, 아치교 주변의 시설물을 모두 해체하는 마무리공정을 포함한다.Accordingly, the present invention is to support the construction of the ground assembly side by side so as to face each other in the assembly (10, 10 ') of the size corresponding to the length of the bridge on both extension lines of the bridge or piers (P: P1 or P2) to be constructed Composition process; Span cross-linking construction step of setting the set point after extrusion of the cross-linked structure 20 assembled in the paper assembly (10) to the bridge construction position ;, Made in the paper assembly (10 ') The arch bridge setting process of extruding the arch bridge structure 50 over the span bridge of the constructed crosslinked structure 20, extruding and dismantling the crosslinked structure 20 into a paper assembly, and then setting the arch structure to be fixed. ; Finishing process of dismantling all facilities around arch bridge.

도 13에서와 같이 상기한 제2 실시예의 연속압출공법을 이용한 아치교시공방법은, 교량이 시공될 교대 또는 교각(P:P1 또는 P2)의 양쪽 연장선상에 교량 길이에 상응하는 추진시설을 갖는 추진장(12)과 크로스빔(14)이 구비되는 가교구조물(20)과 아치구조물(50) 가설을 위한 지조립장(10)(10')를 조성하는 단계(S1);,As shown in FIG. 13, the arch bridge construction method using the continuous extrusion method of the second embodiment has a propulsion facility having a propulsion facility corresponding to the bridge length on both extension lines of bridges or bridges P: P1 or P2 to be constructed. Step (S1) to form a cross-sectional structure (10) (10) (10 ') for the construction of the cross-linked structure 20 and the arch structure 50 is provided with the chapter 12 and the cross beam (14);

교량이 시공될 기존 도로상에 다수의 가설벤트(15:15a,15b,15c)를 순차적으로 시공하는 단계(S2)와, 지조립장(10)의 추진장(12)에 가교(20a,20b,20c,…)들이 순차적으로 조립되는 가교구조물(20)을 제작하여 그 선단부에 런칭노즈(17)를 조립하는 단계(S3)와, 런칭노즈(17)가 조립된 가교구조물(20)을 압출장치를 매개로 교량 시공위치로 압출(Launching)시키는 단계(S4)와, 압출이 완료된 가교구조물(20)에서 런칭노즈(17)를 해체하는 단계(S5), 런칭노즈(17)가 해체된 가교구조물(20)을 횡이동시스템(30;Pulling)을 이용하여 정위치로 이동 및 세팅(Setting)하는 단계(S6)와, 정위치에 세팅된 가교구조물(20)에 안전시설(40)을 설치하는 단계(S7)로 시공되는 경간가교 가설공정과;, Constructing a plurality of temporary vents (15: 15a, 15b, 15c) sequentially on the existing road to be built bridge (S2), bridge (20a, 20b, to the propulsion site 12 of the subassembly 10) 20c, ... to fabricate the cross-linked structure 20 is sequentially assembled to the step (S3) of assembling the launching nose 17 at its distal end, and the cross-linked structure 20 is assembled to the launching nose (17) extrusion device Extruding (Launching) to the bridge construction site via the step (S4), the step of dismantling the launch nose 17 in the cross-linked structure 20, the extrusion is completed (S5), the cross-linked structure in which the launch nose 17 is dismantled Step (S6) of moving and setting to the right position by using the lateral movement system 30 (Pulling) (S6), and to install the safety facility 40 in the cross-linked structure 20 is set in place Span bridge construction step constructed in step (S7) ;,

지조립장(10')의 추진장(12)에서 아치구조물(50)을 조립하는 단계(S8)와, 조립된 아치구조물(50)에 압출장치를 조립하는 단계(S9)와, 압출장치를 매개로 아치구조물(50)을 기시공된 가교구조물(20) 위쪽으로 압출시키는 단계(S10)와, 압출된 아치구조물(50)에서 압출장치를 해체하고 인양장치(70)를 설치하는 단계(S11)와, 인양장치를 이용하여 아치구조물(50)을 인상하는 단계(S12)와, 인양장치에 의해 인상된 아치구조물(50)의 하부측에 위치한 가교구조물(20)을 횡이동시스템을 이용하여 횡이동시킨 다음 런칭노즈(17)를 조립하는 단계(S13), 런칭노즈(17)가 조립된 가교구조물(20)을 압출장치를 이용하여 지조립장(10) 후방으로 압출하여 피드백된 가교구조물(20)을 해체하는 단계(S14), 인양장치(70)에 의해 인상된 아치구조물(50)을 양쪽 교각(P2) 위로 인하시킨 후 세팅하는 단계(S15)로 시공되는 아치교 세팅공정과;,Assembling the arch structure 50 in the propulsion site 12 of the paper assembly (10 ') (S8), Assembling the extrusion device to the assembled arch structure (S9), and through the extrusion device Extruding the furnace arch structure 50 to the construction of the crosslinked structure 20 (S10), and disassembling the extrusion apparatus from the extruded arch structure 50 and installing the lifting device 70 (S11). And, the step (S12) for raising the arch structure 50 by using the lifting device, and the cross-linked structure 20 located on the lower side of the arch structure 50 is lifted by the lifting device by the horizontal movement system Moving and then assembling the launching nose (17) (S13), the crosslinked structure 20 is assembled by the launching nose 17 is extruded to the rear of the paper assembly (10) by using an extrusion apparatus fed back cross-linked structure (20) Dismantling step (S14), the arch structure 50 is lifted by the lifting device 70 is lowered on both piers (P2) and then set An arch bridge setting process constructed in step S15;

인양장치(70)를 포함하는 아치교 주변의 시설물을 모두 해체하는 마무리단계(S17)를 포함하는 연속압출공법을 이용한 아치교시공방법이 제공된다.Provided is an arch bridge construction method using a continuous extrusion method including a finishing step (S17) of dismantling all the facilities around the arch bridge including the lifting device 70.

참고로 본 발명은 상기한 실시 예외에도 다양하게 변형 실시될 수 있고, 여러 가지의 형태를 취할 수 있으나 상기 발명의 상세한 설명에서는 그에 따른 특별한 실시 예에 대해서만 기술하였다.For reference, the present invention may be variously modified and may take various forms in spite of the above-described embodiment. However, in the detailed description of the present invention, only specific embodiments thereof have been described.

그러므로, 본 발명은 상세한 설명에서 언급되는 특별한 형태로 한정되는 것이 아닌 것으로 인정되어야 하며, 오히려 첨부된 청구범위에 의해 정의되는 본 발명의 사상과 범위내에 있는 모든 변형물과 균등물 및 대체물을 포함하는 것으로 이해되어야 한다.Therefore, it is to be understood that the invention is not limited to the specific forms referred to in the description, but rather includes all modifications, equivalents and substitutions that fall within the spirit and scope of the invention as defined by the appended claims. It should be understood that.

도 1은 본 발명에 따른 연속압출공법(ILM)을 이용한 아치교시공방법을 설명하기 위한 블록도,1 is a block diagram for explaining the arch bridge construction method using a continuous extrusion method (ILM) according to the present invention,

도 2a, 2b, 2c는 교대의 한쪽 연장선상에 조성되는 지조립장의 평면도와 정면도 및 일측면도,2A, 2B and 2C are plan and front views and one side view of a paper assembly field formed on one extension line of the shift;

도 3은 교량이 시공될 기존 도로상에 가설벤트가 시공되는 것을 나타낸 정면도,Figure 3 is a front view showing the construction of the temporary vent on the existing road to be bridge construction,

도 4a, 4b는 런칭노즈가 가교구조물의 선단부으로 조립 및 해제되는 것을 나타낸 평면도,Figure 4a, 4b is a plan view showing that the launching nose is assembled and released to the front end of the cross-linked structure,

도 5a는 런칭노즈가 해체된 가교구조물이 횡방향으로 이동되는 것을 나타낸 평면도,5a is a plan view showing that the crosslinked structure in which the launch nose is dismantled is moved laterally;

도 5b는 정위치에 세팅된 가교구조물에 안전시설이 설치되는 것을 나타내고 평면도,Figure 5b shows that the safety facility is installed on the bridge structure set in place, plan view,

도 6a, 6b는 지조립장에서 아치구조물이 조립되는 것을 나타낸 평면도와 정면도,6a and 6b are a plan view and a front view showing that the arch structure is assembled in the paper assembly;

도 6c는 완성된 아치구조물에 이동대차가 조립되는 것을 나타낸 정면도,Figure 6c is a front view showing the mobile cart is assembled to the completed arch structure,

도 7a, 7b는 완성된 아치구조물이 가교구조물에 압출되는 것을 나타낸 정면도,7a, 7b is a front view showing that the completed arch structure is extruded to the cross-linked structure,

도 8a는 아치구조물이 인양장치에 의해 인상된 상태를 나타낸 정면도,8A is a front view showing a state in which the arch structure is lifted by the lifting device;

도 8b는 하부측 가교구조물에 런칭노즈가 조립되는 것을 나타낸 평면도,8B is a plan view illustrating the launching nose assembled to the lower crosslinked structure;

도 8c는 가교구조물이 지조립장으로 압출되는 것을 나타낸 평면도,8c is a plan view showing that the cross-linked structure is extruded into a paper assembly,

도 9a는 가교구조물이 지조립장에서 해체되는 것을 나타낸 정면도,Figure 9a is a front view showing that the cross-linked structure is dismantled in the paper assembly,

도 9b는 도로상에 시공한 가설벤트를 해체한 상태의 정면도,9B is a front view of a state in which a temporary vent constructed on a road is dismantled;

도 10은 인양장치에 의해 인상된 아치구조물을 세팅하는 것을 나타낸 정면도,10 is a front view showing setting the arch structure lifted by the lifting device;

도 11는 아치교 시공을 완료하여 작업장 주변벤트가 모두 해체된 상태의 정면도.11 is a front view of the state completed the arch bridge construction all the vents around the workshop dismantled.

도 12a와 도 12b는 본 발명의 또 다른 실시예로 교대의 양쪽 연장선상에 교량 길이에 상응하는 지조립장이 각각 조성되는 것을 나타낸 평면도와 정면도,12A and 12B are a plan view and a front view of a paper assembly field corresponding to a bridge length respectively formed on both extension lines of a shift as another embodiment of the present invention;

도 13은 본 발명의 제 2 실시예의 블록도,13 is a block diagram of a second embodiment of the present invention;

<도면의 주요부분에 대한 부호 설명><Description of Signs of Major Parts of Drawings>

10, 10': 지조립장10, 10 ': assembly paper

11: 기초콘크리트11: foundation concrete

12: 레일12: rail

12a: 반력대12a: reaction table

12b: 런칭롤러12b: Launch Roller

14: 크로스빔(COROSS BEAM)14: COROSS BEAM

15,15a,15b,15c: 가설벤트15,15a, 15b, 15c: hypothetical vent

16: 기중기16: crane

17: 런칭노즈(Launching Nose)17: Launching Nose

20: 가교20: crosslinking

30: 횡이동시스템30: lateral movement system

40: 안전시설40: safety facilities

50: 아치구조물50: arch structure

62; 이동대차62; Trolley

70: 인양장치70: lifting device

Claims (4)

교량을 시공할 교대의 한쪽 연장선상에 가교구조물(20)과 아치구조물(50)을 각각 조립할 수 있도록 교량 길이에 상응하는 추진시설을 갖는 추진장(12)과 크로스빔(14)이 구비되는 지조립장(10)을 조성하여 상기 지조립장(10)에서 먼저 조립된 가교구조물(20)은 압출장치를 매개로 교량을 시공할 위치로 압출시켜 아치구조물(50) 시공을 위한 경간가교를 가설하고, 상기 지조립장(10)에서 조립되는 아치구조물(50)은 가설된 가교구조물(20)의 상부측으로 압출 이동시킨 후, 인양장치(70)를 이용하여 가교구조물(20) 위의 상기 아치구조물(50)을 상부측으로 들어올린 상태에서 압출장치를 매개로 가설된 가교구조물(20)을 지조립장(10)쪽으로 피드백(feedback) 시켜 가교구조물(20) 제거 및 해체함과 동시에 인양장치(70)에 의해 인상된 아치구조물(50)을 양쪽 교대에 하강 및 세팅하는 방법으로 아치 교량을 건설하는 것을 특징으로 하는 연속압출공법을 이용한 아치교시공방법.A prop provided with a propulsion site 12 and a cross beam 14 having a propulsion facility corresponding to the bridge length so that the bridge structure 20 and the arch structure 50 can be assembled on one extension line of the bridge to be constructed. By constructing the lip length 10, the cross-linked structure 20, which is first assembled in the support assembly 10, is extruded to a position where the bridge is to be constructed by means of an extrusion device, and then, the construction of the span bridge for the construction of the arch structure 50, The arch structure 50 assembled in the supporting assembly 10 is extruded and moved to the upper side of the temporary cross-linked structure 20, and then the arch structure 50 on the cross-linked structure 20 using the lifting device 70. ) To the upper side to feed back the cross-linked structure 20 constructed through the extrusion device toward the paper assembly (10) to remove and disassemble the cross-linked structure (20) and at the same time by the lifting device 70 Lower the raised arch structure 50 on both sides of the shift and Arch bridge construction method using a continuous extrusion process, characterized in that the construction of arch bridges as a way of marketing. 교량이 시공될 교대 또는 교각(P:P1 또는 P2)의 한쪽 연장선상에 추진시설을 갖는 추진장(12)과 크로스빔(14)이 설치되는 지조립장(10)을 조성하는 지조립장 조성공정과,A process for forming a ground assembly site for creating a ground assembly site 10 in which a propulsion plant 12 having a propulsion facility and a cross beam 14 are installed on one extension line of a bridge or piers P: P1 or P2 to be constructed; , 교량이 시공될 기존 도로상에 다수의 가설벤트(15:15a,15b,15c)를 순차적으로 시공하는 단계(S2)와, 지조립장(10)의 추진장(12)에 가교(20a,20b,20c,…)들이 순차적으로 조립되는 가교구조물(20)을 제작하여 그 선단부에 런칭노즈(17)를 조립하는 단계(S3)와, 런칭노즈(17)가 조립된 가교구조물(20)을 압출장치를 매개로 교량의 시공위치로 압출(Launching)시키는 단계(S4)와, 압출이 완료된 가교구조물(20)에서 런칭노즈(17)를 해체하는 단계(S5), 런칭노즈(17)가 해체된 가교구조물(20)을 횡이동시스템(30;Pulling)을 이용하여 정위치로 이동 및 세팅(Setting)하는 단계(S6)와, 정위치에 세팅된 가교구조물(20)에 안전시설(40)을 설치하는 단계(S7)로 시공되는 경간가교 가설공정과;, Constructing a plurality of temporary vents (15: 15a, 15b, 15c) sequentially on the existing road to be built bridge (S2), bridge (20a, 20b, to the propulsion site 12 of the subassembly 10) 20c, ... to fabricate the cross-linked structure 20 is sequentially assembled to the step (S3) of assembling the launching nose 17 at its distal end, and the cross-linked structure 20 is assembled to the launching nose (17) extrusion device Extruding (Launching) to the construction site of the bridge via the step (S4), the step of dismantling the launching nose 17 in the cross-linked structure 20, the extrusion is completed (S5), the crosslinking the launching nose 17 dismantled Step (S6) of moving and setting the structure 20 to the right position by using the lateral movement system (Pulling) (S6), and install the safety facility 40 to the cross-linked structure 20 is set in place Span bridge construction step construction is performed in step (S7); 지조립장(10)의 추진장(12)에서 아치구조물(50)을 조립하는 단계(S8)와, 조립된 아치구조물(50)에 압출장치를 조립하는 단계(S9)와, 압출장치를 매개로 아치구조물(50)을 가설된 가교구조물(20) 위쪽으로 압출시키는 단계(S10)와, 압출된 아치구조물(50)에서 압출장치를 해체하고 인양장치(70)를 설치하는 단계(S11)와, 인양장치를 이용하여 아치구조물(50)을 인상하는 단계(S12)와, 인양장치에 의해 인상된 아치구조물(50)의 하부측에 위치한 가교구조물(20)을 횡이동시스템을 이용하여 횡이동시킨 다음 런칭노즈(17)를 조립하는 단계(S13), 런칭노즈(17)가 조립된 가교구조물(20)을 압출장치를 이용하여 지조립장(10) 후방으로 피드백하여 가교구조물(20)을 제거 및 해체하는 단계(S14), 인양장치(70)에 의해 인상된 아치구조물(50)을 양쪽 교각(P2) 위로 인하시킨 후 세팅하는 단계(S15)로 시공되는 아치교 세팅공정과;,Assembling the arch structure 50 in the propulsion site 12 of the paper assembly (10) (S8), Assembling the extrusion device to the assembled arch structure (S9), and through the extrusion device Extruding the arch structure 50 onto the hypothesized crosslinked structure 20 (S10), disassembling the extrusion apparatus from the extruded arch structure 50, and installing the lifting device 70 (S11); Lifting the arch structure 50 by using the lifting device (S12), and the cross-linked structure 20 located on the lower side of the arch structure 50 is lifted by the lifting device by the horizontal movement system Next, assembling the launching nose 17 (S13), the crosslinked structure 20, to which the launching nose 17 is assembled, is fed back to the support assembly 10 using an extrusion apparatus to remove the crosslinked structure 20, and Step of dismantling (S14), the arch structure 50 is lifted by the lifting device 70 is lowered on both piers (P2) and then set (S15) Arch setting step and the construction in which;, 인양장치(70)를 포함하는 아치교 주변의 시설물을 모두 해체하는 마무리단계(S16)를 포함하는 연속압출공법을 이용한 아치교시공방법.Arch bridge construction method using the continuous extrusion method comprising a finishing step (S16) of dismantling all the facilities around the arch bridge including the lifting device (70). 교량을 시공할 교대의 양쪽 연장선상에 가교구조물(20)과 아치구조물(50)을 각각 조립할 수 있도록 교량 길이에 상응하는 추진시설을 갖는 추진장(12)과 크로스빔(14)이 구비되는 지조립장(10)(10')이 서로 마주하도록 나란히 조성하여 한쪽 지조립장(10)에서 조립된 가교구조물(20)은 압출장치를 매개로 교량을 시공할 위치로 압출시켜 아치구조물(50) 시공을 위한 경간가교를 가설하고, 다른 한쪽 지조립장(10')에서 조립되는 아치구조물(50)은 압출장치를 매개로 가설된 가교구조물(20)의 상부측으로 압출 이동시킨 후, 인양장치(70)를 이용하여 가교구조물(20) 위로 이송된 아치구조물(50)을 상부측으로 들어올린 상태에서 압출장치를 매개로 가설된 가교구조물(20)을 지조립장(10)쪽으로 피드백(feedback) 시켜 가교구조물(20) 제거 및 해체함과 동시에 인양장치(70)에 의해 인상된 아치구조물(50)을 양쪽 교대에 거치되도록 하강 및 세팅하는 방법으로 아치 교량을 건설하는 것을 특징으로 하는 연속압출공법을 이용한 아치교시공방법.A prop provided with a propulsion plant 12 and a cross beam 14 having a propulsion facility corresponding to the bridge length for assembling the bridged structure 20 and the arch structure 50 on both extension lines of the bridge to be constructed. The cross-linked structure 20 assembled in one side of the support assembly 10 by forming the rib lengths 10 and 10 'side by side to face each other is extruded to the position where the bridges are to be constructed by means of an extrusion device to construct the arch structure 50. After installing the span bridge for the arch structure 50 is assembled in the other support assembly (10 ') is extruded and moved to the upper side of the cross-linked structure 20 is installed through the extrusion device, lifting device 70 In the state of lifting the arch structure 50 transferred to the upper cross-linked structure 20 to the upper side by using the extrusion device through the construction of the cross-linked structure 20 is fed back (feedback) toward the support sheet (10) the cross-linked structure (20) ) To the lifting device 70 at the same time as removing and dismantling To arch bridge construction method using a continuous extrusion process for the impression of the arch structure (50) characterized in that the arch bridge constructed in a manner that lowering and setting such that mounting on both sides alternately. 교량이 시공될 교대 또는 교각(P:P1 또는 P2)의 양쪽 연장선상에 가교구조물(20)과 아치구조물(50)을 각각 조립할 수 있도록 교량 길이에 상응하는 추진시설을 갖는 추진장(12)과 크로스빔(14)이 구비되는 지조립장(10)(10')이 서로 마주하도록 나란히 조성하는 단계(S1);,A propulsion plant 12 having propulsion facilities corresponding to the length of the bridge so that the bridge structures 20 and the arch structures 50 can be assembled on both extension lines of the bridges or bridges P: P1 or P2 to be constructed; Step (S1) to form side by side so that the cross-sectional field (10, 10 ') is provided with a cross beam (14); 교량이 시공될 기존 도로상에 다수의 가설벤트(15:15a,15b,15c)를 순차적으로 시공하는 단계(S2)와, 한쪽 지조립장(10)의 추진장(12)에 가교(20a,20b,20c,…)들이 순차적으로 조립되는 가교구조물(20)을 제작하여 그 선단부에 런칭노즈(17)를 조립하는 단계(S3)와, 런칭노즈(17)가 조립된 가교구조물(20)을 압출장치를 매개로 교량의 시공위치로 압출(Launching)시키는 단계(S4)와, 압출이 완료된 가교구조물(20)에서 런칭노즈(17)를 해체하는 단계(S5), 런칭노즈(17)가 해체된 가교구조물(20)을 횡이동시스템(30;Pulling)을 이용하여 정위치로 이동 및 세팅(Setting)하는 단계(S6)와, 정위치에 세팅된 가교구조물(20)에 안전시설(40)을 설치하는 단계(S7)로 시공되는 경간가교 가설공정과;, Constructing a plurality of temporary vents (15: 15a, 15b, 15c) sequentially on the existing road to be built bridge (S2), and bridges (20a, 20b) to the propulsion site 12 of one support assembly (10) And (20c, ...) to assemble the cross-linked structure 20 is sequentially assembled to the step of assembling the launching nose 17 to the front end (S3), the extrusion of the cross-linked structure 20, the launching nose 17 is assembled Extruding (Launching) to the construction site of the bridge via the device (S4), the step of dismantling the launching nose 17 in the cross-linked structure 20, the extrusion is completed (S5), the launching nose 17 is dismantled Moving and setting the cross-linked structure 20 to the right position by using the lateral movement system 30 (Pulling) (S6), and the safety facility 40 to the cross-linked structure 20 set in place Span bridge construction and construction step is installed in step (S7); 다른 한쪽 지조립장(10')의 추진장(12)에서 아치구조물(50)을 조립하는 단계(S8)와, 조립된 아치구조물(50)에 압출장치를 조립하는 단계(S9)와, 압출장치를 매개로 아치구조물(50)을 가설된 가교구조물(20)의 위쪽으로 압출시키는 단계(S10)와, 압출된 아치구조물(50)에서 압출장치를 해체하고 인양장치(70)를 설치하는 단계(S11)와, 인양장치를 이용하여 아치구조물(50)을 인상하는 단계(S12)와, 인양장치에 의해 인상된 아치구조물(50)의 하부측에 위치한 가교구조물(20)을 횡이동시스템을 이용하여 횡이동시킨 다음 런칭노즈(17)를 조립하는 단계(S13), 압출장치를 이용하여 런칭노즈(17)가 조립된 가교구조물(20)을 지조립장(10) 후방으로 피드백하여 제거 및 해체하는 단계(S14), 인양장치(70)에 의해 인상된 아치구조물(50)을 양쪽 교각(P2) 위로 인하시킨 후 세팅하는 단계(S15)로 시공되는 아치교 세팅공정과;,Assembling the arch structure 50 in the propulsion station 12 of the other support assembly (10 ') (S8), Assembling the extrusion device to the assembled arch structure (S9) and the extrusion device Extruding the arch structure 50 upward through the hypothesized cross-linked structure 20 through the step (S10), and disassembling the extrusion apparatus from the extruded arch structure 50 and installing the lifting device 70 ( S11), the step of raising the arch structure 50 by using the lifting device (S12), and the cross-linked structure 20 located on the lower side of the arch structure 50 raised by the lifting device using the lateral movement system After lateral movement by assembling the launching nose 17 (S13), by using the extrusion apparatus to feed back the cross-linked structure 20 assembled with the launching nose 17 to the rear assembly 10 to remove and dismantle Step S14, lowering the arch structure 50 lifted by the lifting device 70 over both piers P2 and setting it (S1) 5) Arch bridge setting process constructed with; 인양장치(70)를 포함하는 아치교 주변의 시설물을 모두 해체하는 마무리단계(S16)를 포함하는 연속압출공법을 이용한 아치교시공방법.Arch bridge construction method using the continuous extrusion method comprising a finishing step (S16) of dismantling all the facilities around the arch bridge including the lifting device (70).
KR1020080107936A 2008-10-31 2008-10-31 Incremental launching method(i.l.m) for arch bridge structure using atemporary segment-supporter installed to substructureof bridge KR100904987B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020080107936A KR100904987B1 (en) 2008-10-31 2008-10-31 Incremental launching method(i.l.m) for arch bridge structure using atemporary segment-supporter installed to substructureof bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020080107936A KR100904987B1 (en) 2008-10-31 2008-10-31 Incremental launching method(i.l.m) for arch bridge structure using atemporary segment-supporter installed to substructureof bridge

Publications (1)

Publication Number Publication Date
KR100904987B1 true KR100904987B1 (en) 2009-06-26

Family

ID=40983238

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020080107936A KR100904987B1 (en) 2008-10-31 2008-10-31 Incremental launching method(i.l.m) for arch bridge structure using atemporary segment-supporter installed to substructureof bridge

Country Status (1)

Country Link
KR (1) KR100904987B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110468734A (en) * 2019-06-03 2019-11-19 中铁二院工程集团有限责任公司 Steel lagging jack pushing tow system and steel lagging jack push construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030039259A (en) * 2001-11-12 2003-05-17 심찬구 incremental launching method(I.L.M) for bridge construction and I.L.M bridge structure using a temporary segment-supporter installed to substructure of bridge
KR100580819B1 (en) 2005-07-20 2006-05-16 주식회사 삼보기술단 Incremental launching method of discontinuous bridge using a temporary connection
KR100669445B1 (en) 2006-03-21 2007-01-16 현대건설주식회사 Pulling up structure for inclined climbing up and method pulling up using the same
KR100706052B1 (en) 1999-08-28 2007-04-13 삼성중공업 주식회사 A erection method of bridge

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100706052B1 (en) 1999-08-28 2007-04-13 삼성중공업 주식회사 A erection method of bridge
KR20030039259A (en) * 2001-11-12 2003-05-17 심찬구 incremental launching method(I.L.M) for bridge construction and I.L.M bridge structure using a temporary segment-supporter installed to substructure of bridge
KR100580819B1 (en) 2005-07-20 2006-05-16 주식회사 삼보기술단 Incremental launching method of discontinuous bridge using a temporary connection
KR100669445B1 (en) 2006-03-21 2007-01-16 현대건설주식회사 Pulling up structure for inclined climbing up and method pulling up using the same

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110468734A (en) * 2019-06-03 2019-11-19 中铁二院工程集团有限责任公司 Steel lagging jack pushing tow system and steel lagging jack push construction method

Similar Documents

Publication Publication Date Title
CN105952482B (en) Self-propelled tunnel inverted arch lining trolley
CN101781878B (en) Integral lifting template of main pylon of single-pylon cable-stayed bridge without dorsal cables and lifting construction method thereof
CN104594918A (en) Split integrated underground passage steel mold plate trolley and construction method thereof
JP3954869B2 (en) Bridge girder replacement method
KR101632922B1 (en) Bridge construction method using non-self launching beam launcher
CN111593665A (en) Bridge construction method integrating dismantling and construction
CN113481874B (en) Construction method for pushing steel box girder by automatic roller type steel buttress wheel set structure
CN109629439B (en) Construction method of single-tower cable-stayed bridge
KR100904987B1 (en) Incremental launching method(i.l.m) for arch bridge structure using atemporary segment-supporter installed to substructureof bridge
CN109778700B (en) Cast-in-place trough beam three-point sliding pushing construction method for crossing existing road
CN204552760U (en) Traveling type hydraulic formwork jumbo
CN111705682A (en) Construction method and equipment for removing and rebuilding superstructure of widened bridge across electrified railway
CN110939071A (en) Non-buttress construction method for assembled steel-concrete I-shaped composite beam bridge
JP5613294B1 (en) Bridge repair method
KR20040100083A (en) Bridge construction method is by means of Incremental launching method using lateral launching apparatus
CN112610244B (en) Prefabricated part for expanding existing elevated operation subway station platform and installation method thereof
CN109797657B (en) Cast-in-situ bridge template support system device and bridge cast-in-situ construction method
KR100468500B1 (en) Method for construction of curvature steel bridge
CN203411914U (en) Segment supporting and locating system structure
JP2005090109A (en) Erection method of bridge, and upper work unit for bridge
CN219240333U (en) Trolley for construction of cover culvert
JP6063795B2 (en) Bridge girder replacement method
KR102247200B1 (en) Method for carrying out replacement of an upperstructure of a bridge
JP2004308225A (en) Work method and overhead bypass road
KR200325428Y1 (en) Bridge construction system is by means of Incremental launching method using lateral launching apparatus

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
N231 Notification of change of applicant
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130425

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20140429

Year of fee payment: 6

LAPS Lapse due to unpaid annual fee